DE10229088A1 - Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect - Google Patents

Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect

Info

Publication number
DE10229088A1
DE10229088A1 DE10229088A DE10229088A DE10229088A1 DE 10229088 A1 DE10229088 A1 DE 10229088A1 DE 10229088 A DE10229088 A DE 10229088A DE 10229088 A DE10229088 A DE 10229088A DE 10229088 A1 DE10229088 A1 DE 10229088A1
Authority
DE
Germany
Prior art keywords
infrastructure channel
infrastructure
channel according
segments
base plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE10229088A
Other languages
German (de)
Inventor
Michael Zuern
Hermann Laistner
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE10229088A priority Critical patent/DE10229088A1/en
Publication of DE10229088A1 publication Critical patent/DE10229088A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F5/022Partitioned to allow more than one medium to flow through
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Rigid Pipes And Flexible Pipes (AREA)
  • Sewage (AREA)

Abstract

The infrastructure channel (1) for supply and drainage conduit is assembled in a sealed manner from individual, monolithic, read-made segments (2), each having a baseplate (6), to which two lateral walls (7,8) connect. The walls are connected to each other in a one-piece structure to form an arch (9,10). The ready-made segments can be made of fiber-reinforced, special concrete, particularly polymer concrete, or plastic. On the lateral walls, consoles are provided (21). In the baseplate, a waste water channel (22) is integrated. The cross-section of the infrastructure channel (1) is so dimensioned that it is accessible on foot. The ready-made segments are produced without reinforcement, or simply with a transport protection reinforcement.

Description

Die Erfindung bezieht sich auf einen Infrastruktur-Kanal nach der Gattung des Hauptanspruches. Ein derartiger Infrastruktur-Kanal ist bekannt. The invention relates to an infrastructure channel according to the genus of Main claim. Such an infrastructure channel is known.

Solche bekannten Infrastruktur-Kanäle werden verwendet, um vorzugsweise in Neubaugebieten alle Versorgungs- und Entwässerungs-Leitungen in einem einzigen Kanalelement zusammenzufassen. Damit sind Überwachungs-, Reparatur- und/oder Ergänzungs- und Ausbauarbeiten wesentlich vereinfacht und verbilligt. Such known infrastructure channels are used to preferably in New areas all supply and drainage pipes in one Summarize channel element. This means monitoring, repair and / or Complementary and expansion work significantly simplified and cheaper.

Als Kanalelemente werden meist armierte Betonrohre verwendet, die fabrikmäßig hergestellt werden und die dann auf der Baustelle zu einem Rohrleitungs-Kanal unter Verwendung von Stirndichtungen zusammengesetzt werden. Reinforced concrete pipes are usually used as duct elements and are manufactured in the factory and then using a pipe duct at the construction site Face seals are assembled.

Nachteilig an einer solchen. Bauweise ist, dass die im Querschnitt runden Betonrohre nach ihrer Verlegung unterfüttert werden müssen, weil der den Aufnahmegraben aushebende Bagger mit seiner Schaufel nur weitgehend ebene Auflage-Bodenflächen erstellen kann. Eine solche Unterfütterung ist aber zeitraubend und teuer. Außerdem sind Rohre mit rundem Querschnitt nicht auftriebssicher gegenüber dem Grundwasser. A disadvantage of such. The construction method is based on the round concrete pipes their relocation must be relined, because the digging of the trench With its bucket, excavators can only create largely flat support floor areas. A such relining is time-consuming and expensive. Besides, tubes are round Cross section not buoyancy-proof against groundwater.

Der Erfindung liegt die Aufgabe zugrunde, die aufgezeigten Nachteile zu vermeiden und einen Infrastruktur-Kanal zu schaffen, der eine der Baggerschaufel angepasste, zumindest weitgehend ebene Grundplatte hat, der weiterhin keine Unterfütterung benötigt, der auftriebssicher ist und der, abgesehen von einem Transportschutz, ohne Armierung auskommt. The invention has for its object to avoid the disadvantages and to create an infrastructure channel that at least adapted to the excavator bucket largely flat base plate, which still needs no relining, the is buoyancy-proof and, apart from transport protection, without reinforcement gets along.

Diese Aufgabe wird gemäß der Erfindung gelöst durch die kennzeichnenden Merkmale des Hauptanspruches. Vorteilhafte Weiterbildungen des Gegenstandes des Anspruches 1 ergeben sich aus den Merkmalen der Unteransprüche. So ist es gemäß den Merkmalen des Anspruches 8 von Vorteil, dass die Fertig-Segmente wegen ihrer Gewölbe-Bauweise ohne statische Drücke aufnehmende Armierungen hergestellt werden können, denn herkömmliche Eisenbetonrohre sind aufgrund ihrer notwendigen Armierung verhältnismäßig teuer. This object is achieved according to the invention by the characterizing features of Main claim. Advantageous further developments of the subject matter of claim 1 result derive from the features of the subclaims. So it is according to the features of claim 8 advantageous that the prefabricated segments because of their vaulted construction without static Pressure-absorbing reinforcements can be produced, because conventional ones Reinforced concrete pipes are relatively expensive due to their necessary reinforcement.

Desweiteren besteht in manchen Fällen das Problem, dass mit dem Infrastruktur-Kanal Steigungen oder Gefälle zu überwinden sind, z. B. bei einer Unterquerung von Autobahnen oder Eisenbahnanlagen oder Gewässern oder Kanälen (Düker). Gemäß den Merkmalen der Ansprüche 9-11 ist dieses Problem vorteilhaft gelöst. Furthermore, in some cases there is a problem with the infrastructure channel Uphill or downhill to be overcome, e.g. B. when crossing under motorways or railway facilities or bodies of water or canals (culverts). According to the characteristics of the Claims 9-11 solved this problem advantageously.

Zeichnungdrawing

Mehrere Ausführungsbeispiele der Erfindung sind in der Zeichnung perspektivisch dargestellt und in der nachfolgenden Beschreibung näher erläutert. Several embodiments of the invention are shown in perspective in the drawing and explained in more detail in the following description.

Beschreibung der AusführungsbeispieleDescription of the embodiments

Die Fig. 1 zeigt einen Infrastruktur-Kanal 1, der aus einzelnen monolithisch hergestellten Fertig-Segmenten 2 zusammengestellt ist. Die Fertig-Segmente 2 sind aus Beton fabrikmäßig hergestellt und werden als Fertigteile an die Baustelle angeliefert. An mindestens einer ihrer beiden Stirnseiten 3 und 4 sind sie mit umlaufenden Dichtungen 5 versehen, so dass die auf der Baustelle zusammengesetzten Fertig-Segmente 2 einen durchgehenden, dichten Infrastruktur-Kanal 1 bilden. Fig. 1 shows an infrastructure channel 1, the monolithically fabricated from individual prefabricated segments 2 is assembled. The prefabricated segments 2 are factory-made of concrete and are delivered to the construction site as prefabricated parts. They are provided with circumferential seals 5 on at least one of their two end faces 3 and 4 , so that the prefabricated segments 2 assembled on the construction site form a continuous, tight infrastructure channel 1 .

Wie aus der Zeichnung zu erkennen, ist der Querschnitt des Infrastruktur-Kanals 1 insgesamt gewölbeartig gestaltet mit einer Grundplatte 6, an die sich zwei seitliche Wände 7 und 8 anschließen, und oben werden die Wände 7 und 8 über eine Wölbung 9 miteinander verbunden. Auf diese Weise ist ein in sich geschlossenes, einstückiges und druckbelastbares Gewölbe 10 geschaffen, das durchgehenden Leitungen einen druckfesten Schutz bietet. As can be seen from the drawing, the cross section of the infrastructure channel 1 is designed in a vault-like manner with a base plate 6 , to which two side walls 7 and 8 are connected, and at the top the walls 7 and 8 are connected to one another via a curvature 9 . In this way, a self-contained, one-piece and pressure-resistant vault 10 is created, which offers continuous lines a pressure-resistant protection.

Als solche Leitungen kommen in Frage und sind dargestellt: Zwei Leitungen 11 und 12 (Vor- und Rücklauf) für Fernwärme, ein Kommunikations-Kabel-Kanal 13, zwei Leitungen 14 und 15 für Trinkwasser und Brauchwasser, eine Vakuum-Leitung 16 für Schwarzwasser und Grünabfall und eine Regenwasser-Sammel-Leitung 19, die zu einer Zisterne 20 führt. Natürlich ließe sich die Anzahl der Leitungen bei Bedarf noch vergrößern. As such lines come into question and are shown: Two lines 11 and 12 (supply and return) for district heating, a communication cable channel 13 , two lines 14 and 15 for drinking water and process water, a vacuum line 16 for black water and Green waste and a rainwater collection line 19 , which leads to a cistern 20 . Of course, the number of lines could be increased if necessary.

Außenanschlüsse der genannten Leitungen werden durch Durchbrüche 17 und 18 in den Wänden 7 und 8 installiert. Innen sind an den Wänden 7 und 8 Konsole 21 zum Abstützen der Leitungen vorgesehen. Diese Konsole 21 sind vorzugsweise unmittelbar an die Wände 7 und 8 angeformt, d. h. angegossen. Im Gewölbe 10 links oben sind außerdem 20 kW-, 360 V- und Solarleitungen an die Wand 7 anmontiert. Die Grundplatte 6 ist des weiteren mit einem eingegossenen bzw. eingeformten Abwasser-Kanal 22 ausgestattet, der vorzugsweise mit einem Bodenblech 23 abgedeckt wird, insbesondere auch deshalb, weil der Infrastruktur- Kanal 1 so bemessen ist, dass er begehbar ist. Ein Verteilerkasten schließlich trägt die Bezugszahl 24. External connections of the lines mentioned are installed through openings 17 and 18 in the walls 7 and 8 . Inside, brackets 21 are provided on the walls 7 and 8 for supporting the lines. These brackets 21 are preferably molded directly onto the walls 7 and 8 , ie cast on. In the vault 10 on the top left, 20 kW, 360 V and solar lines are also mounted on the wall 7 . The base plate 6 is further equipped with a cast-in or molded-in sewer channel 22 , which is preferably covered with a floor panel 23 , in particular also because the infrastructure channel 1 is dimensioned such that it can be walked on. Finally, a distribution box bears the reference number 24 .

Die Fig. 2 zeigt einen Infrastruktur-Kanal 25, der zur Überwindung einer Steigung bestimmt ist und der deshalb innen mit Stufen 26 versehen ist, die entsprechend dem Steigungswinkel innen in seine Grundplatte 27 eingeformt sind. Natürlich ist ebenfalls möglich, auf diese Weise auch ein Gefälle zu überwinden; die Stufen 26 müssen dann jedoch abwärts führen. Der Steigung oder dem Gefälle des Infrastruktur-Kanals ist dann auch die Konfiguration der Fertig-Segmente 28 angepasst. FIG. 2 shows an infrastructure channel 25 which is intended to overcome an incline and which is therefore provided on the inside with steps 26 which are molded into its base plate 27 on the inside in accordance with the angle of inclination. Of course, it is also possible to overcome a gradient in this way; however, stages 26 must then lead downwards. The configuration of the prefabricated segments 28 is then also adapted to the incline or descent of the infrastructure channel.

Bei dem Ausführungsbeispiel nach Fig. 2 erstrecken sich die Stufen 26 über die gesamte Breite der Grundplatte 27. Die Fig. 3 zeigt, dass Stufen 29 auch so angeordnet werden können, dass sich ihre Breite lediglich auf den meist begangenen Teil einer Grundplatte 30 beschränkt. In the embodiment according to FIG. 2, the stages 26 of the base plate 27 extend over the entire width. FIG. 3 shows that steps 29 can also be arranged in such a way that their width is limited only to the part of a base plate 30 that is mostly used.

Wirkungsweiseoperation

Die fabrikmäßig monolithisch hergestellten Fertig-Segmente 2 werden per Lastwagen oder per Bahn an die Baustelle angeliefert. Dort hat ein Bagger einen Graben ausgehoben mit durchgehender, ebener Sohle und glatten Seitenwänden, die in ihren Abmessungen auf die Fertig-Segmente 2 abgestimmt sind. In diesen derart vorbereiteten Graben werden die Fertig- Segmente 2 mittels Greifer eingebracht, wobei ihr äußerer Querschnitt den Graben satt ausfüllt. Ein Unterfüttern und ein seitliches Auffüllen kann damit entfallen. Übliche Bodensetzungen sind damit vermieden. Auch Verdichtungsarbeiten sind nicht notwendig. Damit werden Zeit und Geld und Ärger erspart. The factory-made monolithic finished segments 2 are delivered to the construction site by truck or by train. There, an excavator has dug a trench with a continuous, level sole and smooth side walls, the dimensions of which are matched to the prefabricated segments 2 . The prefabricated segments 2 are introduced into this trench prepared in this way by means of a gripper, their outer cross section filling the trench. A relining and a side filling can be omitted. This avoids the usual subsidence. Compaction work is also not necessary. This saves time and money and trouble.

Die gewölbeartige Form der Einzel-Segmente 2 gewährleistet eine hervorragende Festigkeit und Drucksicherheit des Struktur-Kanals 2, so dass das Bauwerk eine lange Lebensdauer aufweist. Die ebene Grundplatte 6 garantiert des weiteren eine weitgehende Auftriebssicherheit gegenüber steigendem Grundwasserspiegel. The arch-like shape of the individual segments 2 ensures excellent strength and pressure resistance of the structural channel 2 , so that the structure has a long service life. The flat base plate 6 also guarantees a high level of buoyancy protection against rising groundwater levels.

Bei der Erstellung des Infrastruktur-Kanals 1 ist es vorteilhaft, in gewissen Abständen T- Stücke als Fertig-Segmente 2 einzubauen, bei denen der T-Abzweig mit einer Tür verschließbar, das Fertig-Segment 2 also zugänglich ist. Auf diese Weise hat dann Montage- oder Wartungspersonal einen Zugang zum Kanal-Inneren. Auch ist es möglich, ein Fertig- Segment 2 mit einem Mannloch zu versehen, das durch einen Deckel verschließbar ist. Dann wäre ein Zugang von oben geschaffen. Des weiteren sind Einrichtungen für Belüftung und Beleuchtung im Inneren des Gewölbes 10 zu installieren. When creating the infrastructure channel 1 , it is advantageous to install T-pieces as finished segments 2 at certain intervals, in which the T-branch can be closed with a door, so that the finished segment 2 is accessible. In this way, assembly or maintenance personnel have access to the inside of the duct. It is also possible to provide a finished segment 2 with a manhole which can be closed by a cover. Then access from above would be created. Furthermore, facilities for ventilation and lighting are to be installed inside the vault 10 .

Schließlich ist noch zu bemerken, dass die Fertig-Segmente 2 nicht nur aus reinem Beton, sondern auch aus einem faserverstärkten Sonderbeton, insbesondere aus einem Polymer- Beton hergestellt sein können. Auch eine Ausführung der Fertig-Segmente 2 aus Kunststoff ist denkbar. Finally, it should be noted that the prefabricated segments 2 can be made not only from pure concrete, but also from a fiber-reinforced special concrete, in particular from a polymer concrete. A design of the finished segments 2 made of plastic is also conceivable.

Die Ausführungen nach den Fig. 2 und 3 werden verwendet, wenn der Infrastruktur-Kanal 25 Steigungen oder Gefälle überwinden bzw. durchdringen soll. Eine solche Aufgabe liegt z. B. vor bei einer Unter- oder Überquerung von Autobahnen oder von Bahnanlagen. Auch ist es möglich, mit einem solchen ansteigenden und/oder abfallenden Infrastruktur-Kanal 25 nach Art eines Dükers Gewässer oder Kanäle zu unterqueren. Für die waagrechten Teile des Bauwerkes wird dann wieder der stufenlose Infrastruktur-Kanal 1 nach der Fig. 1 Anwendung finden. Bezugszeichenliste 1 Infrastruktur-Kanal
2 Fertig-Segment
3 Stirnseite
4 Stirnseite
5 Dichtung
6 Grundplatte
7 Wand
8 Wand
9 Wölbung
10 Gewölbe
11 Leitung
12 Leitung
13 Kabelkanal
14 Leitung
15 Leitung
16 Vakuum-Leitung
17 Durchbruch
18 Durchbruch
19 Regenwasser-Sammel-Leitung
20 Zisterne
21 Konsole
22 Abwasserkanal
23 Bodenblech
24 Elektr. Verteilerkasten
25 Infrastruktur-Kanal
26 Stufen
27 Grundplatte
28 Fertig-Segment
29 Stufen
30 Grundplatte
The embodiments according to FIGS. 2 and 3 are used when the infrastructure channel is to overcome or penetrate 25 gradients. Such a task lies e.g. B. in front of when crossing or crossing motorways or railway systems. It is also possible to cross under water or channels with such a rising and / or falling infrastructure channel 25 in the manner of a culvert. The stepless infrastructure channel 1 according to FIG. 1 will then be used again for the horizontal parts of the building. LIST OF REFERENCE NUMERALS 1 channel infrastructure
2 finished segment
3 end face
4 end face
5 seal
6 base plate
7 wall
8 wall
9 curvature
10 vaults
11 line
12 line
13 cable duct
14 line
15 line
16 vacuum line
17 breakthrough
18 breakthrough
19 Rainwater collecting pipe
20 cistern
21 console
22 sewer
23 floor panel
24 electrical distribution box
25 infrastructure channel
26 levels
27 base plate
28 finished segment
29 levels
30 base plate

Claims (11)

1. Infrastruktur-Kanal, der aus einzelnen, monolithisch hergestellten, zu einem durchgehenden Kanal dichtend zusammensetzbaren Fertig-Segmenten besteht, dadurch gekennzeichnet, dass jedes Fertig-Segment (2, 28) eine Grundplatte (6,27 u. 30) aufweist, an die zwei seitliche Wände (7 u. 8) anschließen, die über eine Wölbung (9) miteinander einstückig zu einem Gewölbe (10) verbunden sind. 1. Infrastructure channel, which consists of individual, monolithically manufactured prefabricated segments that can be assembled to form a continuous channel, characterized in that each prefabricated segment ( 2 , 28 ) has a base plate ( 6 , 27 and 30 ) connect the two side walls ( 7 and 8 ), which are connected to each other in one piece via a curvature ( 9 ) to form a vault ( 10 ). 2. Infrastruktur-Kanal nach Anspruch 1 dadurch gekennzeichnet, dass die Fertigsegmente (2) aus Beton erstellt sind 2. Infrastructure channel according to claim 1, characterized in that the finished segments ( 2 ) are made of concrete 3. Infrastruktur-Kanal nach Anspruch 2 dadurch gekennzeichnet, dass der Beton ein faserverstärkter Sonder-Beton, insbesondere in Polymer-Beton ist. 3. Infrastructure channel according to claim 2, characterized in that the concrete fiber reinforced special concrete, especially in polymer concrete. 4. Infrastruktur-Kanal nach Anspruch 1, dadurch gekennzeichnet, dass die Fertig-Segmente (2) aus Kunststoff hergestellt sind. 4. Infrastructure channel according to claim 1, characterized in that the finished segments ( 2 ) are made of plastic. 5. Infrastruktur-Kanal nach einem der Ansprüche 1-4, dadurch gekennzeichnet, dass an den seitlichen Wänden (7 und 8) Konsole (21) vorgesehen sind. 5. Infrastructure channel according to one of claims 1-4, characterized in that on the side walls ( 7 and 8 ) console ( 21 ) are provided. 6. Infrastruktur-Kanal nach einem der Ansprüche 1-5, dadurch gekennzeichnet, dass in die Grundplatte (6) des Gewölbes (10) ein Abwasserkanal (22) integriert ist. 6. Infrastructure channel according to one of claims 1-5, characterized in that in the base plate ( 6 ) of the vault ( 10 ), a sewer ( 22 ) is integrated. 7. Infrastruktur-Kanal nach einem der Ansprüche 1-6, dadurch gekennzeichnet, dass ein Querschnitt des Infrastruktur-Kanals (1) derart bemessen ist, dass der Kanal begehbar ist. 7. Infrastructure channel according to one of claims 1-6, characterized in that a cross section of the infrastructure channel ( 1 ) is dimensioned such that the channel is accessible. 8. Infrastruktur-Kanal nach einem der Ansprüche 1-7, dadurch gekennzeichnet, dass die Fertig-Segmente (2) ohne Armierung, gegebenenfalls lediglich mit einer Transportschutz- Armierung, erstellt sind. 8. Infrastructure channel according to one of claims 1-7, characterized in that the finished segments ( 2 ) without reinforcement, possibly only with a transport protection reinforcement, are created. 9. Infrastruktur-Kanal nach einem der Ansprüche 1-8, dadurch gekennzeichnet, dass die Grundplatte (27 u. 30) mit einer normalen Treppenanlage entsprechenden Stufen (26, 29) versehen ist mit einem Steigungswinkel, dem auch die seitlichen Wände (7 u. 8) und die obenliegende Wölbung (9) angepasst sind. 9. Infrastructure channel according to one of claims 1-8, characterized in that the base plate ( 27 and 30 ) with a normal staircase corresponding steps ( 26 , 29 ) is provided with a pitch angle, which also the side walls ( 7 u . 8 ) and the upper curvature ( 9 ) are adapted. 10. Infrastruktur-Kanal nach Anspruch 9, dadurch gekennzeichnet, dass die Stufen (26) sich zumindest weitgehend über die ganze innere Breite der Grundplatte (27) erstrecken. 10. Infrastructure channel according to claim 9, characterized in that the steps ( 26 ) extend at least largely over the entire inner width of the base plate ( 27 ). 11. Infrastruktur-Kanal nach Anspruch 9, dadurch gekennzeichnet, dass die Stufen (29) in ihrer Breite auf den begehbaren Teil der Grundplatte (30) beschränkt sind. 11. Infrastructure channel according to claim 9, characterized in that the width of the steps ( 29 ) is limited to the accessible part of the base plate ( 30 ).
DE10229088A 2001-08-22 2002-06-28 Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect Withdrawn DE10229088A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE10229088A DE10229088A1 (en) 2001-08-22 2002-06-28 Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE20113897U DE20113897U1 (en) 2001-08-22 2001-08-22 Infrastructure channel
DE10229088A DE10229088A1 (en) 2001-08-22 2002-06-28 Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect

Publications (1)

Publication Number Publication Date
DE10229088A1 true DE10229088A1 (en) 2003-03-06

Family

ID=7960809

Family Applications (2)

Application Number Title Priority Date Filing Date
DE20113897U Expired - Lifetime DE20113897U1 (en) 2001-08-22 2001-08-22 Infrastructure channel
DE10229088A Withdrawn DE10229088A1 (en) 2001-08-22 2002-06-28 Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect

Family Applications Before (1)

Application Number Title Priority Date Filing Date
DE20113897U Expired - Lifetime DE20113897U1 (en) 2001-08-22 2001-08-22 Infrastructure channel

Country Status (1)

Country Link
DE (2) DE20113897U1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007061802B3 (en) * 2007-12-19 2009-03-05 Frank Dupre Channel system for receiving power cables

Also Published As

Publication number Publication date
DE20113897U1 (en) 2001-11-22

Similar Documents

Publication Publication Date Title
DE69623414T2 (en) Waterproofing system for hydraulic structures made of rigid plastic material
CN206538789U (en) A kind of pipe gallery
DE20206800U1 (en) Infrastructure Channel
DE60317611T2 (en) Wide drainage channel
EP2049739A1 (en) Arrangement for the construction of a structure having prefabricated construction components
DE10229088A1 (en) Infrastructure channel for supply and drainage conduits is assembled in sealed manner from individual, monolithic, ready-made segments, each having baseplate to which two lateral walls connect
EP0736636B1 (en) Manhole shaft with at least one shaft ring
DE20319998U1 (en) Connection between main sewer, domestic drain and road gully, comprises pre=fabricated part acting as common inspection shaft
DE10023399A1 (en) Connection and distribution shaft for household supply lines, e.g. water, electricity and gas, comprises connection plate with cover having access opening
EP1662051B1 (en) Method of connecting municipal manhole with supply mains to buildung supply
DE10315559A1 (en) Method for reconstruction of sewage shaft system uses sewer constructed through it, and plastic shaft lining aligned through and connected to, sewer
DE10018432A1 (en) Multiple sewer pipe system for parcels of land built on and not built on
DE20210039U1 (en) Infrastructure Channel
DE102005006240B4 (en) Infrastructure empty pipe system
DE1515669C3 (en) Cable duct for power supply and / or telephone lines
EP0600319B1 (en) Method of constructing a water conduit through a barrier, in particular from concrete, under water pressure
DE19503345C1 (en) Appts. for ventilation dewatering stored, esp. compostable, material
DE4011736A1 (en) Shaft construction system
CN208415292U (en) For the novel foundation structure of charging pile
DE29923337U1 (en) Shaft structure
DE2715127A1 (en) Prefabricated reinforced concrete tunnel - is for district heating has sections with side and base plates covered with ridge plates
DE19959250B4 (en) shaft structure
DE102020126966A1 (en) light incidence device
DE29906068U1 (en) Sewage system for area drainage after the separation process
DE202008013441U1 (en) Prefabricated device for collectors of engineering networks

Legal Events

Date Code Title Description