DE1224801B - Overhead line mast with more than two high-voltage overhead line systems using plastic trusses - Google Patents
Overhead line mast with more than two high-voltage overhead line systems using plastic trussesInfo
- Publication number
- DE1224801B DE1224801B DEL45145A DEL0045145A DE1224801B DE 1224801 B DE1224801 B DE 1224801B DE L45145 A DEL45145 A DE L45145A DE L0045145 A DEL0045145 A DE L0045145A DE 1224801 B DE1224801 B DE 1224801B
- Authority
- DE
- Germany
- Prior art keywords
- mast
- overhead line
- line systems
- systems
- plastic
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004020 conductor Substances 0.000 description 8
- 239000012212 insulator Substances 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/20—Spatial arrangements or dispositions of lines or cables on poles, posts or towers
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Description
Freileitungsmast mit mehr als zwei Hochspannungsfreileitungssystemen unter Verwendung von Kunststofftraversen Die Erfindung bezieht sich auf einen Freileitungsmast, bei dem mehr als zwei Hochspannungsfreileitungssysteme unter Verwendung von Kunststofftraversen angebracht sind.Overhead line mast with more than two high-voltage overhead line systems using plastic trusses The invention relates to an overhead line mast, in which more than two high-voltage overhead line systems using plastic trusses are appropriate.
Infolge der zunehmenden Elektrifizierung und im Zusammenhang mit einer starken Vergrößerung der Städte und Industrieanlagen ist in manchen Ländern eine erhebliche Schwierigkeit entstanden, die darin besteht, daß die zur Verlegung von Hochspannungsfreileitungen erforderlichen Trassen nicht mehr zur Verfügung stehen. An vielen Stellen ist schon heute eine so starke Massierung von Freileitungen vorhanden, daß keine weiteren Freileitungen mehr verlegt werden können. Gleichzeitig tritt mit Rücksicht auf die Flugsicherheit die Forderung auf, daß die Maste von- Hochspannungsfreileitungen möglichst niedrig sein sollen. Dies gilt insbesondere für das Einfluggelände in der Nähe von Flugplätzen, deren Zahl ständig zunimmt.As a result of increasing electrification and in connection with a large expansion of cities and industrial plants is one in some countries considerable difficulty arose in that the laying of High-voltage overhead lines are no longer available. In many places there is already such a strong massing of overhead lines that that no more overhead lines can be laid. At the same time occurs with regard to flight safety, the requirement that the masts of high-voltage overhead lines should be as low as possible. This applies in particular to the approach area in near airfields, the number of which is constantly increasing.
Aufgabe der Erfindung ist es nun, diesen Mängeln abzuhelfen und einen raumsparenden Freileitungsmast zu schaffen, an dem mehrere Freileitungssysteme befestigt werden können.The object of the invention is now to remedy these deficiencies and a To create space-saving overhead line mast to which several overhead line systems are attached can be.
Erfindungsgemäß ist der Freileitungsmast in bekannter Weise als Portalmast in H-Form ausgebildet, und die in horizontalen Ebenen verlegten Freileitungssysteme sind im Innern des H-Mastes und die in senkrechten Ebenen verlegten Freileitungssysteme an den äußeren, nahezu senkrechten Streben des H-Mastes angeordnet.According to the invention, the overhead line mast is known as a portal mast designed in an H-shape, and the overhead line systems laid in horizontal planes are inside the H-mast and the overhead line systems laid in vertical planes arranged on the outer, almost vertical struts of the H-mast.
Vorteilhafterweise sind nach einem weiteren Merkmal der Erfindung die Freileitungssysteme höherer Betriebsspannung an den äußeren Streben des H-Mastes in senkrechten Ebenen, die niedrigerer Spannung im Innern des H-Mastes in horizontalen Ebenen angebracht.Advantageously, according to a further feature of the invention the overhead line systems with higher operating voltage on the outer struts of the H-mast in vertical planes, the lower tension inside the H-mast in horizontal planes Levels attached.
Wird es erforderlich, ein innerhalb des Mastes angeordnetes Freileitungssystein von der Trasse abzuzweigen, so sind nach einem weiteren Erfindungsgedanken die an den äußeren Streben der H-Maste verlegten Freileitungssysteme an den Stellen, an denen die im Innern der H-Maste gelegenen Freileitungssysteme von der Trasse abzweigen, in die nächste, nach oben folgende Abspannhöhe des H-Mastes verlegt.If it is necessary, an overhead line system arranged within the mast to branch off from the route, according to a further inventive idea, the on the outer struts of the H-masts laid overhead line systems at the points where the overhead line systems located inside the H-mast branch off from the route, Relocated to the next guy height of the H-mast following upwards.
Unter Berücksichtigung des Umstandes, daß zur Befestigung der Leiterseile Kunststofftraversen an Stelle von Hängeisolatoren dienen, ist die Gesamthöhe der Freileitungsmaste trotz der Verlegung von drei oder sogar vier Drehstrom-Freileitungssystemen gering. Eine noch weitergehende Verringerung der Masthöhe kann erreicht werden, wenn die Leiterseile selbst teilisoliert ausgebildet sind, da dann die Leitungsabstände erheblich verringert werden können.Taking into account the fact that for fastening the conductor cables Plastic trusses are used in place of suspension insulators, the total height is the Overhead line masts despite the laying of three or even four three-phase overhead line systems small amount. A further reduction in the mast height can be achieved, if the conductors themselves are designed to be partially insulated, then the line spacing can be reduced significantly.
Auf diese Weise ist es, wie an Hand der Ausführungsbeispiele erläutert wird, möglich, auf einem Mast drei oder sogar vier Drehstrom-Freileitungssysteme unterzubringen. Voraussetzung dabei ist, daß die Leiterseile nicht in der bisher üblichen Weise an Isolatorhängeketten befestigt sind, weil diese unter dem Einfluß von Wind ins Schwingen geraten können und deshalb recht beträchtliche Abstände gegenübei geerdeten Mastteilen eingehalten werden müssen. Vielmehr sind die Leiterseile an Kunststofftraversen befestigt, so daß Seilschwingungen der erwähnten Art überhaupt nicht mehr auftreten können.In this way it is as explained with reference to the exemplary embodiments it becomes possible to have three or even four three-phase overhead line systems on one mast accommodate. The prerequisite for this is that the conductors are not in the previously are usually attached to isolator suspension chains because they are under the influence can swing from the wind and therefore quite considerable distances opposite earthed mast sections must be observed. Rather, the conductors are on Plastic traverses attached, so that rope vibrations of the type mentioned at all can no longer occur.
Die Zeichnung F i g. 1 bis 4 zeigt Ausführungsbeispiele der Erfindung, und zwar in F i g. 1 einen Portalmast in H-Form mit drei Freileitungssystemen, in F i g. 2 einen Portalmast in H-Form mit vier Freileitungssystemen. Dabei sind Freileitungssysteme im Innern des Mastes geführt. An Hand der F i g. 3 und 4 wird erläutert, wie solche im Innern des Mastes angeordneten Freileitungssysteme seitlich herausgeführt werden können.The drawing F i g. 1 to 4 show exemplary embodiments of the invention, specifically in FIG. 1 shows an H-shaped portal mast with three overhead line systems, in FIG. 2 an H-shaped portal mast with four overhead line systems. Overhead line systems are routed inside the mast. On the basis of FIG. 3 and 4 it is explained how such overhead line systems arranged inside the mast can be led out laterally.
Die F i g. 1 zeigt einen Portalmäst in H-Form, an dem drei Drehstromsysteme befestigt sind. Der Mast besteht aus dem rechten Eckstiel 1, dem linken Eckstiel l' und dem horizontalen Querbalken l". An Kunststofftraversen 2, die der Einfachheit halber als Stützisolatoren dargestellt sind, ist ein Leitungssystem 20 befestigt. Durch die zeichnerische Darstellung ist angedeutet, wie weit die Leiterseile im freien Spannfeld durchhängen. Die Leiterseile liegen nicht genau in einer lotrechten Ebene, sondern sind mit Absicht etwas gegeneinander versetzt. An dem linken Masteckstiel l' ist unter Verwendung von Kunststofftraversen 3 ein weiteres Leitungssystem 30 befestigt. Schließlich ist noch ein drittes Leitungssystem 40 vorhanden, das an Kunststofftraversen 4 befestigt ist. Diese Kunststofftraversen befinden sich auf dem honzontalen Querbalken der H-Foim. Man wird zweckmäßigerweise die Leitungssysteme mit der höchsten Betriebsspannung, z. B. 220 kV, rechts und links außerhalb des Mastes, das Leitungssystein mit niedrigerer Spannung dagegen auf dem Querbalken anbringen.The F i g. 1 shows an H-shaped portal mast to which three three-phase systems are attached. The mast consists of the right corner post 1, the left corner post l ' and the horizontal crossbeam l ". A line system 20 is attached to plastic traverses 2, which are shown as post insulators for the sake of simplicity conductors sag in the free span. The conductors are not exactly in a vertical plane, but are slightly offset to one another on purpose. at the left Masteckstiel l 'is attached using plastic trusses 3, a further conduit system 30. Finally, a third conduit system 40 is provided , which is attached to plastic crossbars 4. These plastic crossbars are located on the horizontal crossbeam of the H-Foim. The line systems with the highest operating voltage, e.g. 220 kV, to the right and left outside the mast, the line system with the lower voltage are expediently used however, attach it to the crossbeam.
Die F i g. 2 zeigt sinngemäß eine Abwandlung dieser Anordnung mit einem H-Mast ' der aber zwei horizontale Querbalken besitzt. An diesen Querbalken sind unter Verwendung von Kunststofftraversen die Leitungssysteine 40 und 50 aufgehängt. Auch hier sind mit Absicht die außerhalb des Mastes angeordneten Teilleiter der Systeme 20 bzw. 30 nicht genau lotrecht übereinander angeordnet, und zwar mit Rücksicht auf -das soaenannte Tanzen der Leiterseile.The F i g. 2 shows a modification of this arrangement with an H-mast ' which, however, has two horizontal crossbeams. The line systems 40 and 50 are suspended from these crossbeams using plastic traverses. Here, too, the sub-conductors of the systems 20 and 30, which are arranged outside the mast, are intentionally not arranged exactly perpendicularly one above the other, with a view to the so-called dancing of the conductor ropes.
Bei den beschriebenen Bauformen kommt es vor, daß ein oder sogar zwei Leitungssysteme innerhalb des Mastes, also zwischen den beiden Masteckstielen, befestigt sind. Es tritt nun die Frage auf, wie die Anordnung weitergebildet werden muß, um ein solches innerhalb des Mastes angeordnetes Leitungssystem nach der Seite, beispielsweise nach rechts, als Ab- zweig herauszuführen. Es sei in diesem Zusammeii hang auf die F i g. 3 und 4 verwiesen. Die F i g. 4 zeigt die im Zug ,e der Leitung hintereinander angeordneten Maste 8, 9, 10, 11. Der Mast 8 soll so ausgebildet sein, wie es beispielsweise die F i g. 1 zeigt. Bei dem nächstfolgenden Mast 9 werden die zu beiden Seiten der Masteckstiele befindlichen Leitungssysteine in eine höhere Ebene geführL Es ergibt sich dabei eine Mastform, wie sie etwa in F i g. 3 dargestellt ist. An dem Mast 9 befinden sich also die Leitungssysteme 20 bzw. 30 in einer höheren Ebene, z. B. in der Lage 20', 30' oder, falls notwendig, sogar in einer Lage 20" bzw. 30". Nunmehr kann im Spannfeld zwischen den aufeinanderfolgenden Masten 9 und 10 ein Zwischenmast 12 als Abzweigmast angebracht werden, der ein Winkelabspannmast ist und an dem das Leitungssystem 40 bzw. 50 abgespannt und seitlich in Richtung des Pfeiles x als Abzweig herausgeführt wird. Dieselbe Anordnung kann sinngemäß auch verwendet werden, wenn nicht nur eines,. sondern beide im: Innern des H-Mastes angeordneten Leitungssysteme nach der Seite als Abzweige herausgeführt werden sollen.With the designs described, it happens that one or even two line systems are attached within the mast, that is, between the two mast corner posts. It now takes the question of how the arrangement must be made to such within the mast arranged pipe system to the side, for example, to the right, as a waste branch out perform. In this connection it is to the Fig . 3 and 4 referenced. The F i g. 4 shows the masts 8, 9, 10, 11 arranged one behind the other in the train, e of the line. The mast 8 should be designed as shown, for example, in FIG. 1 shows. In the case of the next mast 9 , the line systems located on both sides of the corner posts are led into a higher level. This results in a mast shape such as that shown in FIG . 3 is shown. On the mast 9 are the line systems 20 and 30 in a higher level, for. B. in position 20 ', 30' or, if necessary, even in a position 20 "or 30". An intermediate mast 12 can now be attached as a branch mast in the span between the successive masts 9 and 10 , which is an angled guy mast and on which the line system 40 or 50 is braced and led out laterally in the direction of the arrow x as a branch. The same arrangement can be used accordingly, if not just one. but both pipe systems arranged in the interior of the H-mast are to be led out to the side as branches.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DEL45145A DE1224801B (en) | 1963-06-19 | 1963-06-19 | Overhead line mast with more than two high-voltage overhead line systems using plastic trusses |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DEL45145A DE1224801B (en) | 1963-06-19 | 1963-06-19 | Overhead line mast with more than two high-voltage overhead line systems using plastic trusses |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE1224801B true DE1224801B (en) | 1966-09-15 |
Family
ID=7271005
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DEL45145A Pending DE1224801B (en) | 1963-06-19 | 1963-06-19 | Overhead line mast with more than two high-voltage overhead line systems using plastic trusses |
Country Status (1)
| Country | Link |
|---|---|
| DE (1) | DE1224801B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE202015101022U1 (en) | 2015-03-04 | 2015-04-27 | Ltb Leitungsbau Gmbh | Modular linkage for picking up ladder cables above the tie bar of overhead power pylons |
-
1963
- 1963-06-19 DE DEL45145A patent/DE1224801B/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE202015101022U1 (en) | 2015-03-04 | 2015-04-27 | Ltb Leitungsbau Gmbh | Modular linkage for picking up ladder cables above the tie bar of overhead power pylons |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP0140014B1 (en) | Framework for a weak current installation, especially for distribution frames | |
| DE4241952C2 (en) | Switchgear containers | |
| DE1224801B (en) | Overhead line mast with more than two high-voltage overhead line systems using plastic trusses | |
| DE19637047A1 (en) | HV voltage transformer sub-station with HV switchgear | |
| DE10144028A1 (en) | Modular machine frame | |
| EP3581737A1 (en) | Device for holding and lowering conductors of an overhead line | |
| EP2501005B1 (en) | Overhead line device, in particular for high voltage overhead lines | |
| DE4430761C2 (en) | Method and device for replacing a mast head of a mast of a high-voltage overhead line | |
| DE2424214A1 (en) | Overhead transmission line insulator suspension system - single and double insulator strings carry three phase circuit | |
| DE4238675C1 (en) | Work platform for attachment to HV overhead cable pylon - has two=part bolted construction and box section for enclosing corner pillar of pylon to afford access to horizontal tread-plate surface | |
| DE551934C (en) | Frame for fastening a large number of auxiliary electrical lines in a switchgear | |
| DE2754558C2 (en) | LF distribution frame for communication technology equipment | |
| DE2309935A1 (en) | INSTALLATION CHANNEL FOR ELECTRICAL AND / OR GAS TECHNICAL EQUIPMENT | |
| DE2549547A1 (en) | Prefabricated cable shaft of reinforced concrete - has shaft trough split in longitudinal direction and both halves form seam | |
| DE6913685U (en) | BASE PLATE FOR CABLE DISTRIBUTION CABINET. | |
| DE739180C (en) | Outdoor switchgear | |
| DE3706797A1 (en) | Rack system for light-current installation construction, especially for distribution installations | |
| DE2750517C3 (en) | Flat cable carrier for use especially in telephone exchanges and booster stations (TZV) | |
| DE2016434A1 (en) | Transport and assembly equipment | |
| DE2538711A1 (en) | Guide rig for HV multiple line overhead transmission lines - has masts spaced alternately along right of way with insulation arms on both sides and one side respectively | |
| DE3539110C2 (en) | ||
| DE2638578A1 (en) | HV overhead power lines cable pull-out appts. - uses cable run-out pulley suspended on side of multi-pulley box (NL 1.3.78) | |
| DE2227474B2 (en) | Layout for overhead cables on electric railways - has horizontal support line below main suspension cable, support line has rigid sections | |
| DE918455C (en) | Outdoor switchgear | |
| DE2706057A1 (en) | BUILDING CONSTRUCTION FOR SWITCHGEAR |