[go: up one dir, main page]

WO2015118614A1 - 水圧試験方法及び装置 - Google Patents

水圧試験方法及び装置 Download PDF

Info

Publication number
WO2015118614A1
WO2015118614A1 PCT/JP2014/052575 JP2014052575W WO2015118614A1 WO 2015118614 A1 WO2015118614 A1 WO 2015118614A1 JP 2014052575 W JP2014052575 W JP 2014052575W WO 2015118614 A1 WO2015118614 A1 WO 2015118614A1
Authority
WO
WIPO (PCT)
Prior art keywords
pressure
water
test
servo motor
cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/JP2014/052575
Other languages
English (en)
French (fr)
Inventor
諭 鶴田
勝彦 森崎
充 中田
勝己 石垣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nakata Manufacturing Co Ltd
Original Assignee
Nakata Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nakata Manufacturing Co Ltd filed Critical Nakata Manufacturing Co Ltd
Priority to RU2016135535A priority Critical patent/RU2649619C1/ru
Priority to CN201480074786.XA priority patent/CN105980830B/zh
Priority to JP2015504809A priority patent/JP5783656B1/ja
Priority to EP14881914.7A priority patent/EP3104158B1/en
Priority to US15/115,729 priority patent/US10234367B2/en
Priority to KR1020167024020A priority patent/KR20160117538A/ko
Priority to PCT/JP2014/052575 priority patent/WO2015118614A1/ja
Publication of WO2015118614A1 publication Critical patent/WO2015118614A1/ja
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M3/00Investigating fluid-tightness of structures
    • G01M3/02Investigating fluid-tightness of structures by using fluid or vacuum
    • G01M3/26Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors
    • G01M3/28Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors for pipes, cables or tubes; for pipe joints or seals; for valves ; for welds
    • G01M3/2846Investigating fluid-tightness of structures by using fluid or vacuum by measuring rate of loss or gain of fluid, e.g. by pressure-responsive devices, by flow detectors for pipes, cables or tubes; for pipe joints or seals; for valves ; for welds for tubes
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M5/00Investigating the elasticity of structures, e.g. deflection of bridges or air-craft wings
    • G01M5/0041Investigating the elasticity of structures, e.g. deflection of bridges or air-craft wings by determining deflection or stress
    • G01M5/005Investigating the elasticity of structures, e.g. deflection of bridges or air-craft wings by determining deflection or stress by means of external apparatus, e.g. test benches or portable test systems
    • G01M5/0058Investigating the elasticity of structures, e.g. deflection of bridges or air-craft wings by determining deflection or stress by means of external apparatus, e.g. test benches or portable test systems of elongated objects, e.g. pipes, masts, towers or railways
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/08Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces
    • G01N3/10Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces generated by pneumatic or hydraulic pressure
    • G01N3/12Pressure testing
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/0001Type of application of the stress
    • G01N2203/0003Steady
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/003Generation of the force
    • G01N2203/0042Pneumatic or hydraulic means
    • G01N2203/0048Hydraulic means
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/02Details not specific for a particular testing method
    • G01N2203/0202Control of the test
    • G01N2203/0208Specific programs of loading, e.g. incremental loading or pre-loading
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N2203/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N2203/02Details not specific for a particular testing method
    • G01N2203/026Specifications of the specimen
    • G01N2203/0262Shape of the specimen
    • G01N2203/0274Tubular or ring-shaped specimens

Definitions

  • the present invention relates to a water pressure test method for quality inspection of welded pipes such as ERW pipes and spiral pipes, and seamless pipes. More specifically, the present invention relates to an increase in hydraulic drive after the test pipes are full.
  • the present invention relates to a water pressure test method and apparatus for injecting high-pressure water into a test tube using a pressure cylinder to pressurize and hold the inside of the tube at a predetermined pressure.
  • a water pressure test is conducted to investigate the quality of the produced ERW pipe, particularly the quality of the welded part called the seam.
  • the manufactured ERW pipe of a predetermined length is sandwiched between the head stock and tail stock arranged before and after the test line, and the front and rear ends are sealed, and in this state, the head stock is passed through the head stock. This is done by injecting high-pressure water into the ERW pipe.
  • the pressure of the high-pressure water reaches about 90% of the guaranteed strength, and a product that can withstand this pressure for a predetermined time and does not cause breakage of the welded portion and tube burst due to this is determined as a good product in terms of mechanical strength.
  • the outline of the water pressure test procedure is as follows. Fix the test tube between the headstock and tailstock and seal both tube ends. Water is injected from the tank into the test tube through the headstock at low pressure (including its own weight). The air in the test tube is discharged out of the tube through the tailstock. When the test tube is substantially full, high-pressure water is forcibly supplied to the test tube to pressurize the test tube to the required test pressure, and the test pressure is maintained for a predetermined time to perform a pressurization test. Complete.
  • the pressure reducing valves provided on the tail side, head side or both side stocks are opened, the inside of the pipe is decompressed, the test pipe is removed from between both stocks, and the water in the pipe is discharged into the pit for testing. Is all completed.
  • a pressure increasing mechanism using hydraulic pressure is used as described in Patent Document 1. That is, high pressure water is supplied into the test tube by a pressure increasing cylinder driven by hydraulic pressure. Specifically, by sucking water into the output side of a pressure-increasing cylinder driven by hydraulic pressure, the pressure on the input side of the cylinder is increased by supplying pressure oil, and the piston in the cylinder is driven forward. The high pressure water is supplied from the output side of the pressure increasing cylinder into the headstock and further into the test tube.
  • a plurality of hydraulic pumps 1 arranged in parallel are used simultaneously as a drive system for the pressure increasing cylinder, that is, a hydraulic power source for supplying pressure oil to the input side of the pressure increasing cylinder.
  • the reason for this is that the pressure of the pressurized oil supplied to the input side of the pressure-increasing cylinder 5 varies because the water pressure, water volume, and supply pattern of the high-pressure water supplied to the test tube vary depending on the size of the test tube. This is because the oil pressure and oil amount need to cover a wide range.
  • the hydraulic control is performed by a proportional control valve 4 interposed as a check valve in a sub-line 3 branched from the main line 2 extending from the plurality of hydraulic pumps 1 to the input side of the pressure increasing cylinder 5.
  • the hydraulic control valve is not installed in the main line 2 but is installed in the sub-line 3 branched from the main line 2 as in the case where a plurality of hydraulic pumps 1 arranged in parallel are used simultaneously. This is because the pressure oil supplied to the pressure cylinder 5 needs to cover a wide range from low pressure / small flow rate to high pressure / large flow rate.
  • the pressure oil continues to be discharged at a constant rotation, and the discharge pressure of the pressure oil passes through the sub line as a check valve. Controlled by the mounted proportional control valve. That is, when the pressure oil pressure in the main line 2 is higher than the set pressure in the proportional control valve 4 interposed in the sub-line 3, the pressure oil passes through the proportional control valve 4 so that the set pressure is maintained. By being released, the pressure oil pressure in the main line 2 is maintained at the set pressure. As shown in FIG. 5, the hydraulic pressure and the oil amount of the hydraulic pump 1 are in an inversely proportional relationship. The relationship between the hydraulic pressure and the high pressure water pressure and the relationship between the oil amount and the high pressure water amount are proportional.
  • the set oil pressure in the proportional control valve 4 is increased stepwise such as 10 MPa, 20 MPa, and 30 MPa, and finally the set holding pressure is transferred.
  • the pressure of the high-pressure water is increased stepwise and finally reaches the holding pressure.
  • the flow rate of the high-pressure water decreases as the pressure increases, and the flow rate is almost zero while the holding pressure is maintained.
  • a plurality of hydraulic pumps 1 are used. Most of the discharged pressure oil is released out of the line via the proportional control valve 4 in the sub line 3.
  • the pressure of the high-pressure water supplied into the test tube is increased stepwise to reduce the flow rate when the set pressure in the proportional control valve 4 is set to the highest pressure corresponding to the holding pressure from the beginning.
  • the pressure on the input side of the pressure increasing cylinder 5 is increased while maintaining a large flow rate.
  • the pressure of the high pressure water causes an overshoot due to the inertia force of the pressure increasing cylinder itself (inertial force of the piston). This is because the upper limit is exceeded.
  • the holding pressure of the high pressure water is set between the pressure required for the test and the upper limit pressure, and in order to prevent the overpressure from occurring in the pressure of the high pressure water, the high pressure water supplied into the test tube is set. While increasing the pressure stepwise to decrease the flow rate, and immediately before the pressure of the high-pressure water reaches the holding pressure, the set pressure in the proportional control valve is adjusted to the final pressure corresponding to the holding pressure, Fully absorb the inertial force.
  • high-pressure water having a required pressure can be held in the test tube for a required time.
  • cycle time becomes long, the number of treatments per unit time increases, and the efficiency is poor.
  • the hydraulic pump continues to operate at a constant rotation both when the pressure increasing cylinder is raised and when it is not, so there is a problem that the power loss of the pump is essentially large.
  • the size of the test tube covers a wide range, it is necessary to adjust the hydraulic pump to the maximum size when performing a water pressure test with one test device. Since the hydraulic pump continues to discharge the pressure oil at a constant rotation as described above, the release amount of the pressure oil increases when the size of the test tube is reduced, and the hydraulic pump is used not only during the test period but also during the test period. A large power loss occurs. Thirdly, when the hydraulic pump is adjusted to the maximum size, the control accuracy of the hydraulic pressure and the oil amount is reduced in a small size. These problems also make it difficult to perform the water pressure test with a single test device.
  • An object of the present invention is to provide a water pressure test method and apparatus capable of accurately, efficiently and economically performing a water pressure test on each test tube even when the size of the test tube covers a wide range.
  • a servo motor drive pump that can be operated at a rotational speed corresponding to the required pressure condition and flow rate condition, thereby preventing generation of useless power loss.
  • the use of is effective.
  • hydraulic pumps generally have a lower flow rate as the pressure increases.
  • Servo motor-driven pumps have a wider adjustment range for this pressure and flow rate. You can cover the work with just one machine.
  • Third, in the final stage of pressure increase it is effective to increase the pressure to the holding pressure by selectively using one of a plurality of servo motor driven hydraulic pumps.
  • the hydraulic drive source of the booster cylinder is a servo motor drive pump
  • the size and thickness of the test tube vary widely by feedback control of the drive source based on the pressure on the output side of the booster cylinder
  • the necessary pressure increase can be performed by setting only the holding pressure and holding time required for each test tube. For this reason, the troublesomeness of setting the pressure increase speed and the change point of the pressure increase speed for each difference in the size of the test tube and the holding pressure is eliminated.
  • the pump is operated only at the time of boosting and the release of the pressure oil is not required even at the time of boosting, there is substantially no power loss.
  • the pressure increasing ratio (pressure receiving area ratio) of the pressure increasing cylinder is 2
  • the holding pressure is 30 MPa
  • the holding time is 10 seconds
  • the pressure is increased.
  • the servo motor drive pump continues until the water pressure on the output side of the pressure increasing cylinder reaches 30 MPa (the oil pressure on the input side of the pressure increasing cylinder becomes 15 MPa).
  • the input side of the pressure-increasing cylinder is automatically increased, and then the pressure is maintained for a set retention time (10 seconds).
  • the servo motor-driven pump supplies a relatively low pressure oil to the input side of the pressure increasing cylinder at a stroke during the low pressure period at the initial stage of pressure increase, thereby minimizing the effect of pressure absorption due to residual air in the test tube.
  • a relatively high pressure oil is continuously supplied to the input side of the pressure-increasing cylinder to increase the pressure on the input side, thereby enabling boosting in a short time.
  • the servo motor drive pump is of the two-capacity type, it has two modes of a low pressure and a high flow rate and a high pressure and a small flow rate, and switching between these two modes enables boosting at a higher speed.
  • the servo motor drive pump can increase the flow rate by simultaneously operating a plurality of pressure boosting cylinders connected in parallel, thereby further shortening the pressurization time.
  • multiple servo motor-driven pumps are operated simultaneously until the holding pressure is reached, complete synchronous operation is not possible, so an operation failure due to a synchronization failure occurs at the end of boosting (immediately before the holding pressure is reached). Pressure control becomes difficult. For this reason, at the end of boosting (immediately before reaching the holding pressure), it is necessary to stop the operation with the exception of one of the plurality of servo motor drive pumps and perform boosting with the remaining one servo motor drive pump. It is effective from the point of view.
  • the pressure increasing cylinder when the holding pressure is low, the pressure can be increased with one cylinder.
  • the pressure increase ratio of the cylinder inevitably increases.
  • the pressure booster cylinder operates at a low pressure and a large flow rate, but when the pressure increase ratio is large, the pressure increase cylinder becomes a high pressure and a small flow rate, and not only the cylinder scale increases due to the increase of the piston stroke but also the pressure increase speed decreases. Extending cycle time becomes a problem. For this reason, it is effective to connect a plurality of pressure increasing cylinders having different pressure increasing ratios in parallel to the test tube and use them in stages from a low pressure increasing ratio to a high pressure increasing cylinder.
  • a pressure increase ratio of 3.75 or more is required.
  • the pressure increasing ratio of the pressure increasing cylinder is required to be 3.75 or more.
  • the pressure increasing cylinder with such a high pressure increasing ratio has a pressure limit of the hydraulic pressure source. Under such circumstances, the flow rate is inevitably small due to the high pressure increase ratio, and thus the pressure increase rate cannot be avoided.
  • the pressure increasing cylinder is divided into a plurality of pressure increasing ratios in stages. For example, a 20 MPa pressure increasing cylinder and a 75 MPa pressure increasing cylinder are used. Since the maximum pressure of the hydraulic pressure source is 20 MPa in the 20 MPa pressure increasing cylinder, the pressure increasing ratio is 1, and the pressure increasing ratio of the 75 MPa pressure increasing cylinder is 3.75 or more as originally. Then, high pressure can be increased by the pressure increasing cylinder having a low pressure increasing ratio until the output side of the pressure increasing cylinder reaches 20 MPa, and pressure increase at the initial pressure increasing speed is performed above 20 MPa. As a result, the pressurization time in the low pressure period up to 20 MPa is shortened, and as a result, the overall pressurization time is shortened.
  • the booster cylinder with a low boost ratio used in the initial stage of boosting is driven mainly at a low pressure and a large flow rate, and the booster cylinder with a high boost ratio used thereafter is also used. Since the pressure on the input side (pressure of the hydraulic pressure source) required at the start of pressure increase is reduced to about 5 (20 / 3.75) MPa, at least the initial pressure increase is driven with a low pressure and a large flow rate. For this reason, the boosting time is further shortened.
  • a servo motor drive pump with a wide adjustment range of pressure and flow is very effective as a hydraulic pressure source when the pressure increasing cylinder is divided into a plurality of cylinders. A servo motor driven pump of the type becomes more effective.
  • the pressure increasing ratio in the pressure increasing cylinder of 40 MPa is 2.
  • the pressurization time in the medium pressure period from 20 MPa to 40 MPa is shortened, and the overall pressurization time is further shortened.
  • the size of the test tube ranges from 8 inch diameter to 24 inch diameter or more. Even in the case of, it is possible to increase the pressure in each test tube up to the holding pressure by simply setting the holding pressure and setting the holding time, and increase the pressure accurately and economically in a short time. It is.
  • the water pressure test method of the present invention has been completed on the basis of such knowledge, and in order to perform a water pressure test on the manufactured metal pipe, high pressure water is forcibly supplied from the hydraulically driven pressure increasing cylinder into the test pipe.
  • a plurality of servo motor drive pumps connected in parallel are used as the hydraulic drive source of the booster cylinder, and the output side of the booster cylinder is set in advance.
  • the plurality of servo motor drive pumps are operated simultaneously, and thereafter, the operation is stopped except for one of the plurality of servo motor drive pumps, and the remaining one By operating the servo motor drive pump, the output side of the pressure increasing cylinder is made to reach the holding pressure.
  • the pressure increase time is shortened by adopting a multi-servo pump system in which the hydraulic drive source of the pressure-increasing cylinder is a combination of a plurality of servo motor drive pumps in parallel. Specifically, until the output side of the pressure increasing cylinder reaches the vicinity of the preset holding pressure, the plurality of servo motor-driven pumps are initially at a low pressure and a high flow rate, and thereafter, are shifted to a high pressure and a low flow rate. , Simultaneously run at as much power as possible.
  • a switching point pressure lower than the holding pressure by a predetermined pressure for example, 1 MPa
  • a predetermined pressure for example, 1 MPa
  • Multiple servo motor drive pumps are operated simultaneously until the measured water pressure is reached, and when the measured water pressure reaches the switching point pressure, operation is stopped except for one of the multiple servo motor driven pumps.
  • the pressure reaches the holding pressure it is preferable to stop the operation of one servo motor drive pump that is being operated. Since only the holding pressure and holding time are set as the setting operation, the setting operation is greatly simplified.
  • the hydraulic pressure and oil amount can be adjusted over a wide range, and when low pressure is used, the hydraulic oil can be supplied to the low pressure side of the booster cylinder with a large flow rate and at a high pressure with a small flow rate. it can.
  • the two-capacity servo motor driven pump with a particularly wide adjustment range since the water pressure in the test tube is low at the initial stage of boosting, multiple servo motor driven pumps are operated in the high pressure and large flow rate mode. High pressure water can be supplied into the test tube.
  • the amount of high-pressure water supplied and the holding pressure will be small, so multiple servo motor drive pumps will continue to operate in the low-pressure and large-flow mode, and the pressure will increase to near the holding pressure. From the vicinity of the holding pressure, there is one servo motor drive pump, and the inside of the pipe is raised to the holding pressure with high accuracy in the high pressure and small flow rate mode.
  • multiple servo motor drive pumps continue to operate in the low pressure and large flow rate mode and continue to supply a large amount of high pressure water after the initial pressure increase, and continue to supply high pressure in the high pressure and small flow rate mode.
  • Supply water From the vicinity of the holding pressure, there is one servo motor drive pump, and the pressure in the pipe is increased to the holding pressure in the high pressure and small flow rate mode.
  • the switching timing from the low pressure large flow rate mode to the high pressure small flow rate mode after the initial boost is variously changed.
  • the reason for setting one operation pump at the end of the pressure increase near the holding pressure is that it is difficult to drive a plurality of servo motor drive pumps in complete synchronization. This is because the simultaneous drive of the bases causes a malfunction due to the extremely low flow rate, and secondary adverse effects such as hunting occur, making it difficult to raise the pressure smoothly and accurately at the final stage. Even if there is only one drive pump, the inside of the pipe is quickly boosted by a high pressure and a small flow rate. A small flow rate is more advantageous from the viewpoint of precision control.
  • One cylinder may be used for the pressure increasing cylinder, but a plurality of cylinders are preferable in consideration of a case where the holding pressure setting range is wide and the maximum value of the holding pressure is considerably higher than the pressure of the hydraulic pressure source. More specifically, it is preferable that a plurality of pressure increasing cylinders whose pressure increasing ratios are increased stepwise are arranged in parallel with the test tube and used in order from the smallest pressure increasing ratio to the largest.
  • Boosting speed is increased and the boosting time is shortened.
  • the water pressure test apparatus further reduces the pressure increase time by combining a multi-servo pump system using a plurality of servo motor-driven pumps and a multi-cylinder system using a plurality of pressure-increasing cylinders.
  • a plurality of servo motor drive pumps are connected in parallel to the pressure increasing cylinder as a hydraulic pressure driving source of the pressure increasing cylinder, and the pressure increasing ratio is defined as the pressure increasing cylinder.
  • the pressure increasing ratio is defined as the pressure increasing cylinder.
  • a switching mechanism for alternatively supplying.
  • a water pressure sensor for measuring the water pressure of high pressure water is provided on the output side line of the pressure increasing cylinder so that the pressure increasing cylinder with a small pressure increasing ratio is operated in order from the pressure increasing cylinder with a small pressure increasing ratio. It is desirable to provide a cylinder control system in which the switching mechanism is controlled based on a measured water pressure by a water pressure sensor.
  • a water pressure sensor that measures the water pressure of high-pressure water is provided on the output side line of the pressure increasing cylinder, and a plurality of servo motors are used until the measured water pressure reaches a switching point pressure that is lower than the holding pressure by a predetermined pressure (for example, 1 MPa).
  • a pump control system may be provided in which a plurality of servo motor drive pumps are controlled so that one servo motor drive pump operates until the measured water pressure reaches the holding pressure after the drive pumps are operated simultaneously. desired.
  • the pressure oil from a plurality of servo motor drive pumps is supplied to the pressure increasing cylinder with the smallest pressure increasing ratio, and when the measured water pressure reaches near the maximum water pressure of the pressure increasing cylinder, the pressure increases.
  • Pressure oil is supplied to the pressure-increasing cylinder having the next largest pressure ratio, and the pressure in the test tube is increased by a plurality of servo motor drive pumps up to the vicinity of the holding water pressure by continuing this. Thereafter, the pressure in the test tube is increased by one servo motor drive pump.
  • the hydraulic pressure test method of the present invention uses a plurality of servo motor-driven pumps arranged in parallel as hydraulic sources when hydraulically driving a pressure-increasing cylinder that supplies high-pressure water into a test tube.
  • Boost Boosts well.
  • the cycle time is shortened, the number of tests per unit time increases, and the rationalization effect by this increases.
  • production of motive power loss is suppressed effectively, the reduction effect of the motive power cost by this is also large, and the water pressure test method of this invention exhibits a great effect for reduction of the cost which a water pressure test requires.
  • the water pressure test apparatus includes a multi-cylinder method that sequentially operates a plurality of pressure-increasing cylinders whose pressure increase ratio increases stepwise from a small pressure increase ratio to a large pressure increase ratio.
  • Embodiments of the present invention will be described below.
  • the water pressure test method and apparatus of this embodiment are used for a water pressure test of an electric resistance welded tube manufactured in an electric resistance welded tube production line.
  • the water pressure test apparatus includes an electric sewing tube 10 (hereinafter referred to as a test tube 10) subjected to a water pressure test, a head stock unit 20A that is a fixed head, and a tail stock that is a movable head. Water is poured into the pipe between the unit 20B and high-pressure water is supplied after the water is full, thereby checking the quality and the like of the welded portion (seam portion) of the test tube 10, and into the test tube 10.
  • a test tube 10 an electric sewing tube 10 (hereinafter referred to as a test tube 10) subjected to a water pressure test
  • a head stock unit 20A that is a fixed head
  • a tail stock that is a movable head. Water is poured into the pipe between the unit 20B and high-pressure water is supplied after the water is full, thereby checking the quality and the like of the welded portion (seam portion) of the test tube 10, and into the test tube 10.
  • Low-pressure water supply system 30 that performs a large amount of water injection at non-pressurized (normal pressure) or low pressure, and forcibly pressurizing high-pressure water into the test tube 10 after the inside of the test tube 10 is filled with non-pressurized water or low-pressure water And a high-pressure water supply system 40 to be injected.
  • the low-pressure water supply system 30 allows water in the water tank 31 installed at a position higher than the set position of the test tube 10 to flow into the test tube 10 at a stretch by its own weight or a low pressure of 1 MPa or less (for example, about 0.8 MPa). is there.
  • the water discharged from the test tube 10 after the test is temporarily stored in the lower pool 32 and transferred to a sedimentation tank (not shown), and then the supernatant is stored in the water sump 33.
  • the water in the water sump 33 is pumped by the pump 34 to the tank 31 at a high position via the filter, and is poured into the test tube 10 via the headstock 20A.
  • the air in the test tube 10 is discharged from an air vent valve 21 provided in the tailstock 20B.
  • a cylinder type opening / closing valve 35 is interposed in the line E from the water tank 31 to the headstock 20A.
  • the high-pressure water supply system 40 forcibly supplies high-pressure water such as a maximum of 75 MPa into the test tube 10 that has become full of water by hydraulic pressure-increasing cylinders 41A and 41B.
  • the hydraulic pressure increasing cylinders 41 ⁇ / b> A and 41 ⁇ / b> B are arranged in parallel to the test tube 10 and are selectively driven by the drive system 42.
  • a switching mechanism 43 including electromagnetic valves 43A and 43B is interposed between the pressure-increasing cylinders 41A and 41B and the drive system 42.
  • the first pressure-increasing cylinder 41A is for low pressure with a maximum pressure of 21 MPa
  • the second pressure-increasing cylinder 41B is for high pressure with a maximum pressure of 75 MPa.
  • the piston is reciprocated by the pressure oil supplied from the drive system 42, and water is sucked from the tank 31 through the line A to the output side during retraction driving, and is sucked during advance driving.
  • pressurized water to the headstock 20A via the line B, high-pressure water is forcibly supplied into the test tube 10 in a full state.
  • the drive system 42 of the pressure-increasing cylinders 41A and 41B includes a plurality of servo motor drive pumps 44 arranged in parallel as main components. Of the plurality of servo motor drive pumps 44, one servo motor drive pump is a main pump, and the remaining is a sub pump. Each of these servo motor drive pumps 44 is of a two-capacity type, and the water pressure on the output side of the pressure-increasing cylinders 41A and 41B is reduced to the target value by simultaneous driving of these servo motors and subsequent single drive of the main pump. Automatic boosting.
  • the water pressure on the output side (line B) of the pressure-increasing cylinders 41A and 41B is measured by the water pressure sensor 47 and sent to the controller 48 that serves as both the cylinder control system and the pump control system. Switching control of the switching mechanism 43 and output control and switching control of the servo motor drive pump 44 are performed.
  • the switching control of the switching mechanism 43 includes on / off switching control of the pressure increasing cylinders 41A and 41B and forward / reverse switching control of the cylinders in the on state.
  • the on / off switching control of the pressure-increasing cylinders 41A and 41B is performed by setting one of the electromagnetic valves 43A and 43B constituting the switching mechanism 43 to an open state and closing the other to close the pressure oil from the drive system 42.
  • the pressure increasing cylinders 41A and 41B are supplied to one of them, and only one of them is operated in the forward and reverse directions.
  • the forward / reverse switching control is to switch the forward operation and the reverse operation of the cylinder in the operating state among the pressure increasing cylinders 41A and 41B, and is as follows.
  • the oil in the oil sump 45 is pressurized and discharged by driving the servo motor drive pump 44.
  • the discharged pressure oil is supplied from the line C to the input side (inlet) of one of the pressure-increasing cylinders 41A and 41B via one of the solenoid valves 43A and 43B in the open state (positive direction).
  • one of the pistons of the pressure-increasing cylinders 41A and 41B is driven to advance, and high-pressure water is discharged from the output side.
  • the high-pressure water is sent to the headstock 20A.
  • the oil discharged from the input side (exit) with the advance drive of the piston returns to the oil sump 45 via the line D from one of the electromagnetic valves 43A and 43B.
  • the water pressure test method of this embodiment is carried out using such a water pressure test apparatus.
  • the function of the water pressure test apparatus of this embodiment is demonstrated below, and the water pressure test method of this embodiment is demonstrated collectively.
  • the servo motor drive pump 44 which forms the main body of the drive system 42, there are a one-capacity model and a two-capacity model, and a two-capacity type is used here.
  • a two-capacity model as shown in FIG. 2, switching from the low-pressure large flow mode M1 to the high-pressure small-flow mode M2 and switching from the high-pressure small-flow mode M2 to the low-pressure large-flow mode M1 by switching the capacity of the variable displacement pump. Can be switched.
  • the servo motor drive pump 44 can adjust the relationship between the pressure and the flow rate over a wide range from a low pressure and a large flow rate to a high pressure and a small flow rate as compared with a normal hydraulic pump (FIG. 5) driven by an AC motor. It becomes possible.
  • the test tube 10 is set on the test line as a first step with respect to the test tube 10, and between the head stock 20 ⁇ / b> A and the tail stock 20 ⁇ / b> B. Between. As a second stage, the cylinder type on-off valve 35 in the line E is switched from the closed state to the open state while the water tank 31 in the low-pressure water supply system 30 is filled with water. As a result, the water in the tank 30 flows into the test tube 10 through the line E by its own weight or a low pressure of 1 MPa or less.
  • the pressure increasing cylinder 41A for low pressure has a maximum pressure of 21 MPa and a pressure increasing ratio (pressure receiving area ratio) of 1.
  • the high pressure boosting cylinder 41B has a maximum pressure of 75 MPa and a pressure increase ratio (pressure receiving area ratio) of 3.57.
  • the pressure increasing cylinder 41A for low pressure performs the retreat operation as the first stage.
  • the drive system 42 is operated. Specifically, the three servo motors in the drive system 42 are driven with the electromagnetic valve 43A corresponding to the pressure increasing cylinder 41A opened in the reverse direction and the electromagnetic valve 43B corresponding to the pressure increasing cylinder 41B closed.
  • the pumps 44 are operated simultaneously at the maximum output or an output close to this.
  • the solenoid valve 43A is switched from the reverse direction to the forward direction, and the pressure increasing cylinder 41A starts to advance.
  • the two-capacity servo motor drive pump 44 operates in the low pressure and large flow rate mode, and forcibly supplies a large amount of pressure oil to the input side of the pressure increasing cylinder 41A in a short time.
  • a large amount of pressurized water is forcibly supplied from the output side of the pressure increasing cylinder 41A into the fully filled test tube 10 through the line B and further through the headstock 20A.
  • the pressure in the test tube 10 increases with the supply.
  • the internal pressure of the test tube 10 is monitored by a water pressure sensor 47 provided on the output side (line B) of the pressure increasing cylinders 41A and 41B.
  • ⁇ P fixed value, here 1 MPa
  • the slave pumps of the three servo motor drive pumps 44 are stopped.
  • the main pump continues to operate in the high pressure and small flow rate mode M2 (see FIG. 2), and increases the internal pressure of the test tube 10 to the set holding pressure.
  • the pressure reducing valves provided in the head stock 20A, the tail stock 20B, or both of them are opened to decompress the inside of the pipe.
  • the tailstock 20B is separated from the test tube 10, and then the test tube 10 is separated from the fixed tailstock 20A and tilted to discharge all the water in the tube to the lower pool 32. As described above, a part of the water is reused in the next test.
  • the test pressure (holding pressure) is more than 21 MPa and not more than 75 MPa
  • the test pressure (holding pressure) and holding time are set in the controller 48.
  • the low pressure boosting cylinder 41A and the high pressure boosting pressure are set.
  • the drive system 42 is operated so that the pressure cylinder 41B performs the retreat operation.
  • the solenoid valves 43A and 43B corresponding to the pressure increasing cylinders 41A and 41B opened in the reverse direction the three servo motor drive pumps 44 in the drive system 42 have the maximum output or an output close to this. Drive at the same time.
  • the two-capacity servo motor drive pump 44 operates in the low pressure and large flow rate mode, and forcibly supplies a large amount of pressure oil to the input side of the pressure increasing cylinder 41A in a short time.
  • a large amount of pressurized water is forcibly supplied from the output side of the pressure increasing cylinder 41A into the fully filled test tube 10 through the line B and the headstock 20A.
  • the pressure in the test tube 10 increases.
  • the pressure in the test tube 10 is monitored by a water pressure sensor 47 provided on the output side (line B) of the pressure increasing cylinders 41A and 41B.
  • the electromagnetic valve 43A is switched from the open state in the positive direction to the closed state, and the electromagnetic valve 43B is switched from the closed state to the open state in the positive direction.
  • the pressure increasing cylinder 41A for low pressure stops the advance operation, and instead, the pressure increasing cylinder 41B for high pressure starts the advance operation.
  • the pressure increasing ratio of the pressure increasing cylinder 41B for high pressure is 3.57. For this reason, even if the maximum pressure of the servo motor drive pump 44 is 21 MPa, the water pressure on the output side can be increased to 75 MPa. When switching to the high pressure boosting cylinder 41B, the water pressure on the output side is increased to 21 MPa, so the substantial burden on the servo motor drive pump 44 is from 5.9 (21 / 3.57) MPa, Become. At such a low pressure, the servo motor drive pump 44 operates again in the low pressure large capacity mode M1. For this reason, a large amount of pressure oil starts to be supplied again to the input side of the pressure increasing cylinder 41B.
  • the pressure increasing ratio of the pressure increasing cylinder 41B is as high as 3.57, and accordingly, the output side has a low flow rate.
  • the input side is a large flow rate
  • the flow rate on the high pressure side is compensated
  • the output side of the pressure increasing cylinder 41A is compensated.
  • the difference is small. Therefore, a large amount of pressurized water is forcibly supplied from the output side of the pressure increasing cylinder 41B into the test tube 10 through the line B and the headstock 20A, and the pressure in the test tube 10 is further increased.
  • the pressure increasing cylinder 41A If the water pressure on the output side of the pressure increasing cylinder 41A further increases due to the forced supply of pressure oil to the input side of the pressure increasing cylinder 41B and the further supply of pressurized water into the test tube 10 associated therewith, the pressure increasing cylinder 41A The oil pressure on the input side also increases. As a result, the two-capacity servo motor drive pump 44 shifts from the low pressure large flow rate mode to the high pressure small flow rate mode, and continues to supply pressure oil to the input side of the pressure increasing cylinder 41B while further increasing the hydraulic pressure. As a result, pressurized water is supplied from the output side of the pressure increasing cylinder 41B into the test tube 10 while further increasing the pressure, and the water pressure in the test tube 10 is further increased.
  • the slave pumps of the three servo motor drive pumps 44 are stopped. And continue to operate only the main pump.
  • the main pump continues to operate in the high pressure and small flow rate mode M2, and increases the internal pressure of the test tube 10 to the set holding pressure.
  • the pressure reducing valves provided in the head stock 20A, the tail stock 20B, or both of them are opened to decompress the inside of the pipe.
  • the tailstock 20B is separated from the test tube 10, and then the test tube 10 is separated from the fixed tailstock 20A and tilted to discharge all the water in the tube to the lower pool 32. As described above, a part of the water is reused in the next test.
  • the controller 48 thereafter sets the water pressure on the output side of the pressure increasing cylinders 41 ⁇ / b> A and 21 ⁇ / b> B. Therefore, since the automatic control is performed, the setting operation is simple. For this reason, even when the size and thickness of the test tube 10 are various, it is possible to test the test tubes 10 of all sizes with one test apparatus.
  • the test tube 10 When testing various types of test tubes 10 with one apparatus, it is necessary to shorten the time (cycle time) required for the test of one test tube 10, but in the water pressure test method of this embodiment, this is the case. Is also possible. That is, in the water pressure test method of the present embodiment, the pressure in the test tube 10 is increased by a plurality of hydraulic units up to the vicinity of the set holding pressure, so a large amount of high-pressure water is supplied into the test tube 10 in a short time. Can do. In addition, since these hydraulic units are two-capacity servo motor drive pumps 44 having both the low pressure large flow rate mode M1 and the high pressure small flow rate mode M2, the test tube 10 has various sizes and thicknesses.
  • the set holding pressure is compensated for by absorbing the pressurization due to the compression of residual air in the initial stage of pressurization in any test tube 10.
  • the voltage can be boosted to the vicinity in as short a time as possible.
  • the test can be performed with one water pressure test apparatus from the small diameter test tube 10 to the large diameter test tube 10. Moreover, in each test, the time required for the test is shortened, the number of tests per unit time is increased, and generation of power loss in the hydraulic unit is suppressed. These greatly reduce the cost of testing.
  • ERW steel pipe is API-X80 standard. There are two types of wall thickness of 5.0 mm and 12.7 mm for each outer diameter except for a tube with an outer diameter of 203 mm, and one type of 12.7 mm for a tube with an outer diameter of 203 mm. The length is 1372 cm (13.72 m) for all tubes.
  • the yield stress YS was set to 562 MPa between the minimum value of 555 MPa and the maximum value of 705 MPa, and the test pressure P was determined from this and the steel pipe specifications.
  • the formula for calculating the test pressure P is as in Formula 1.
  • Table 1 shows the specifications of each test tube, the test pressure P, and the required water amount calculated from these.
  • the required water amount shows two types, a low-pressure water supply amount and a high-pressure water supply amount.
  • the high-pressure water supply amount the water amount necessary to absorb the compression of the residual air, the water amount necessary to absorb the expansion of the steel pipe, and 21 MPa pressure increase The amount of water required to increase the pressure from 21 MPa to the test pressure, and the total amount of these waters, among the total amount of water, the amount of water borne by the low pressure booster cylinder, Indicates the amount of water to be borne.
  • the amount of water required for increasing the pressure to 21 MPa is the amount of water required for increasing the pressure to the test pressure, and the amount of water required for increasing the pressure from 21 MPa to the test pressure is zero.
  • the maximum capacity of the booster cylinder for low pressure is 95L, and the maximum capacity of the booster cylinder for high pressure is 40L.
  • Three servo motor drive pumps of 15 kW were used.
  • the amount of residual air in the test tube is 1.5% here, but as described above, it is unavoidable that the air actually varies greatly. Therefore, the required amount of water calculated here is a guideline, and as described above, the influence of this variation can be avoided by monitoring the water pressure on the output side of the pressure increasing cylinder in the actual test.
  • the cycle time required for one test is as follows. Test tube loading / unloading 6.0 seconds, test tube centering 1.0 seconds, tail head advance 4.0 seconds, non-pressurized water 6.0-9.5 seconds, air vent valve 0.5 seconds for the operation, 3.5 to 10 seconds for forced pressurized water supply up to the test pressure, 10 seconds for the holding time, 0.5 seconds for the pressure release time, 3.0 seconds for the tail head retraction, test tube
  • the discharge was 1.0 seconds
  • the time lag was 1.5 to 3.0 seconds
  • the cycle time was between 37.0 and 47.5 seconds.
  • the forced pressurized water supply time varies because the test pressure is different, and in the water pressure test method of the present embodiment, the shortening of the forced pressurized water supply time is significant.
  • the number of servo motor drive pumps 44 that constitute the main body of the drive system 42 may be two or more, and is appropriately determined depending on the capability of the individual pumps 44 and required characteristics.
  • the test tube that has passed the above-mentioned water pressure test is threaded at the end of the tube for connection to the pipe joint in the next step.
  • the test tube that has been threaded is subjected to the same water pressure test with one or both ends fitted with pipe joints.
  • a water pressure test is performed with a pipe joint attached to only one end, high pressure water is supplied into a special plug that integrates a plug that seals the end of the test tube and a plug that seals the open side of the pipe joint. Then test for water leakage at the thread. For this reason, the test is performed with a small amount of high-pressure water as compared with the case where the entire pipe is full.
  • the test since the test is performed at a high pressure as in the embodiment, it takes time to increase the pressure. Therefore, the water pressure test method and apparatus of the embodiment are very effective in the water pressure test at the pipe end, and the effect of shortening the test time is remarkable.
  • the test object is an electric resistance welded tube, but the present invention can also be applied to a water pressure test of a seamless tube.
  • the test pressure is, for example, 160 MPa, which is higher than that of an electric resistance welded pipe.
  • Test tube 20A Headstock unit 20B Tailstock 21 Air vent valve 30 Low pressure water supply system 31 Water tank 32 Pool 33 Water sump 34 Pump 35 On-off valve 40 High pressure water supply system 41 Pressure increase cylinder 42 Drive system 43 of pressure increase cylinder 41 Switching mechanism ( solenoid valve) 44 Servo motor drive pump 45 Oil sump 47 Water pressure sensor 48 Control system

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Engineering & Computer Science (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
  • Control Of Positive-Displacement Pumps (AREA)

Abstract

 試験管のサイズが広範囲に及ぶ場合も、それぞれの試験管の水圧試験を精度よく、しかも効率的かつ経済的に実施する。 これを実現するために、試験管に対して並列接続され且つ増圧比が段階的に高くなった複数本の増圧シリンダ41を使用する。複数本の増圧シリンダ41の駆動源として、並列配置された複数台のサーボモータ駆動ポンプ51を使用する。増圧シリンダ41の出力側の水圧が試験圧力の近傍に到達するまでは、複数台のサーボモータ駆動ポンプ51を同時運転する。その後は、複数のサーボモータ駆動ポンプ51のうちの1台を除いて駆動を停止して、残り1台のサーボモータ駆動ポンプ51により試験圧力まで昇圧する。昇圧の際には、複数本の増圧シリンダ41を増圧比の低いものから高いものへ順番に使用する。

Description

水圧試験方法及び装置
 本発明は、電縫管やスパイラル管などの溶接管、更にはシームレス管の品質調査のために実施される水圧試験方法に関し、より具体的には、試験管内を満水とした後に油圧駆動の増圧シリンダを使用してその試験管内に高圧水を注入して管内を所定圧に加圧し保持する水圧試験方法及び装置に関する。
 電縫管の製造ラインでは、製造された電縫管の品質、特にシーム部と呼ばれる溶接部の品質を調査するために水圧試験が施される。ここにおける水圧試験は、製造された所定長の電縫管を、試験ラインの前後に配置されたヘッドストックとテールストックとの間に挟んで前後両端を密閉し、この状態でヘッドストックを介して電縫管内へ高圧水を注入することにより行われる。高圧水の圧力は保証強度の90%程度に達し、この圧力に所定の時間耐えて溶接部の破壊、これによる管バーストを生じなかったものが、機械的強度上の良品と判定される。
 水圧試験手順の概要は次のとおりである。試験管をヘッドストックとテールストックとの間に固定し、両方の管端を密閉する。ヘッドストックを介して試験管内にタンクから低圧(自重を含む)で注水を行う。試験管内の空気は、テールストックを介して管外へ排出される。試験管内が実質的に満水状態となると、その試験管内に高圧水を強制的に供給して管内を要求される試験圧力まで加圧し、更に、その試験圧力に所定時間保持して加圧試験を完了する。加圧試験が完了すると、テール側又はヘッド側若しくは両側のストックに設けられた減圧弁を開き、管内を減圧した後、両ストック間から試験管を取り外し、管内の水をピットに排出して試験が全て完了する。
 試験管内へ高圧水を強制的に供給する高圧給水系としては、特許文献1に記載されているように、油圧を用いた増圧機構が用いられる。すなわち、油圧で駆動される増圧シリンダにより高圧水が試験管内へ供給される。具体的に説明すると、油圧で駆動される増圧シリンダの出力側に水を吸込んだ後、そのシリンダの入力側を、圧油の供給により昇圧して、シリンダ内のピストンを進出駆動することにより、増圧シリンダの出力側からヘッドストック、更には試験管内へ高圧水を供給する。
 増圧シリンダの駆動系、すなわち増圧シリンダの入力側へ圧油を供給する油圧源としては、図4に示すように、並列配置された複数台の油圧ポンプ1が同時使用される。その理由は、試験管へ供給する高圧水の水圧、水量、更には供給パターンなどが試験管のサイズなどに応じて多岐に及ぶために、増圧シリンダ5の入力側へ供給される圧油の油圧、油量も広範囲をカバーする必要があることによる。
 油圧の制御は、複数台の油圧ポンプ1から増圧シリンダ5の入力側へ至る主ライン2から分岐した副ライン3にチェック弁として介装された比例制御弁4により行われる。油圧制御弁が主ライン2に介装されず、主ライン2から分岐した副ライン3に介装されるのは、並列配置された複数台の油圧ポンプ1が同時使用されるのと同じく、増圧シリンダ5へ供給される圧油も、低圧・小流量から高圧・大流量まで、広い範囲をカバーする必要があるからである。
 そして、複数台の油圧ポンプ1は、ACモータにて駆動される一般の油圧ユニットであるため、一定回転で圧油を吐出し続け、その圧油の吐出圧力が、副ラインにチェック弁として介装された比例制御弁により制御される。すなわち、主ライン2における圧油の圧力が、副ライン3に介装された比例制御弁4での設定圧力より高いと、設定圧力が維持されるように圧油が比例制御弁4を介してリリースされることにより、主ライン2における圧油の圧力が設定圧力に維持される。油圧ポンプ1の油圧と油量とは、図5に示すように、逆比例の関係にある。油圧と高圧水圧との関係、及び油量と高圧水量との関係は比例関係である。
 実際の水圧試験では、比例制御弁4での設定油圧が10MPa、20MPa、30MPaというように段階的に高められて最後に設定保持圧に移行する。これにより、高圧水の圧力は、図6に示すように、段階的に高められて最終的に保持圧力に到達する。高圧水の流量は、圧力が高くなるにつれて減少し、保持圧力が維持されている間の流量は殆ど0であり、このとき、増圧シリンダ5の油圧駆動系においては、複数の油圧ポンプ1から吐出される圧油の殆どが副ライン3内の比例制御弁4を介してライン外へリリースされる。
 試験管内へ供給される高圧水の圧力を段階的に高めて流量を減らしていくのは、比例制御弁4での設定圧力を、当初から、保持圧力に対応する最高圧にしておくと、図7に示すように、増圧シリンダ5の入力側が大流量のまま昇圧され、その結果、増圧シリンダ自身の慣性力(ピストンの慣性力)などにより、高圧水の圧力がオーバーシュートを起こして圧力上限を超えてしまうからである。
 ちなみに、高圧水の保持圧力は試験に必要な圧力と上限圧力との間に設定されており、高圧水の圧力にオーバーシュートが生じるのを防止するために、試験管内へ供給される高圧水の圧力を段階的に高めて流量を減らしていくと共に、高圧水の圧力がその保持圧力に到達する直前に、比例制御弁での設定圧力を、保持圧力に対応する最終圧に調整して、前記慣性力の完全吸収を図る。
 このような増圧シリンダによる高圧給水系、及び増圧シリンダの駆動系によると、試験管内に、要求される圧力の高圧水を、要求される時間だけ保持することができる。しかしながら、試験管内の圧力を、要求される圧力まで段階的に上昇させるために、いわゆるサイクルタイムが長くなり、単位時間あたりの処理本数が増加し、効率が悪いという本質的な問題がある。また、油圧ポンプは増圧シリンダを昇圧するときも、そうでないときも、一定回転で動作し続けるので、ポンプの動力損失が本質的に大きいという問題もある。
 加えて、電縫管の製造では、近年、整形ロールの画期的な共用化技術(特許文献2)が提案されたことに伴い、1ラインで製造できる電縫管のサイズ(管径、肉厚、長さ)を、8インチ径から24インチ径、あるいはそれ以上までというように、非常に広くできることが一つの傾向となっているが、製造された電縫管の水圧試験では、この傾向のために、試験管内に注入する高圧水の水圧は数倍、水量は20倍もの差異を生じ、このことが逆に様々な問題の要因となる。
 第1に、試験管のサイズ、保持圧力の違いごとに昇圧速度、昇圧速度の変更点の設定を行うため、膨大なデータを保持する必要があり、設定にかかる操作が非常に煩わしくなる。このため、1ラインで製造されるサイズの種類が増加した近時にあっては、水圧試験を1つの試験装置で行うことは現実的でないと考えられている。その結果、1ラインに多くの水圧試験装置が必要になるという不合理が生じていた。
 第2に、試験管のサイズが広範囲に及ぶため、一つの試験装置で水圧試験を行おうとすると、油圧ポンプを最大サイズに合わせる必要がある。油圧ポンプは前述したとおり常時一定回転で圧油を吐出し続けるので、試験管のサイズが小さくなったときに圧油のリリース量が増え、試験期間以外だけでなく、試験期間中も油圧ポンプに大きな動力損失が発生する。第3に、油圧ポンプを最大サイズに合わせると、小さいサイズにおいて油圧、油量の制御精度が低下する。これらの問題も、水圧試験を1つの試験装置で行うことを困難にしている。
 また、試験管内への高圧水供給に先立つ低圧水供給では、試験管内への空気の残留が避けられない。低圧水供給において試験管内に空気が残留すると、試験管内へ高圧給水が始まっても、その加圧が空気の圧縮に吸収されるので、給水初期の圧力上昇が非常に遅くなる。このことは、試験に要する時間(サイクルタイム)の一層の延長を招く。それのみならず、空気の残留量は平均的には1.5%程度であるが、そのばらつきが大きいため、大きな不確定要素となる。このため、空気の残留は、設定操作を一層複雑にする原因にもなっている。
日本特許第4738783号公報 米国特許第4770019号公報
 本発明の目的は、試験管のサイズが広範囲に及ぶ場合も、それぞれの試験管の水圧試験を精度よく、しかも効率的かつ経済的に実施できる水圧試験方法及び装置を提供することにある。
 増圧シリンダに対して精密な油圧制御を行うためには、油圧ポンプなどの油圧源から増圧シリンダの低圧側へ至る主ラインに油圧制御弁を直接的に介装するのが有効であるが、本発明が対象とする水圧試験装置においては、主ラインを高圧の圧油が多量に流通するため、これが困難である。このため、従来はその主ラインから分岐した副ラインに比例制御弁が介装されていたが、動力損失の大きさを始めとして、様々な問題のあることは前述したとおりである。
 本発明者らは、主ラインから油圧制御弁を排除するという基本原則を維持しつつ、従来の様々な問題を解決するために、油圧源である圧油ユニット自体の変更に着目し、従来の油圧ポンプに代わる様々な圧油ユニットについて比較検討した。その結果、次のことが判明した。
 第1に、増圧シリンダの油圧駆動源としては、要求される圧力条件・流量条件に応じた回転数で運転が可能であり、これにより無駄な動力損失の発生が阻止されるサーボモータ駆動ポンプの使用が効果的である。第2に、油圧ポンプは一般に圧力が高くなるほど流量が少なくなるところ、サーボモータ駆動ポンプはこの圧力・流量の調整範囲が広く、2容量形では低圧大流量・高圧小流量という2台のポンプの働きを1台で賄うことができる。このようなサーボモータ駆動ポンプの使用、特に複数台のサーボモータ駆動ポンプを並列的に使用して、特に昇圧初期に、増圧シリンダに大量の圧油を送り込んでシリンダを昇圧することが効果的である。第3に、昇圧の最終段階では複数台のサーボモータ駆動油圧ポンプのうちの一つを選択的に使用して保持圧力まで昇圧することが効果的である。
 すなわち、増圧シリンダの油圧駆動源がサーボモータ駆動ポンプであると、駆動源を増圧シリンダの出力側の圧力に基づいてフィードバック制御することにより、試験管のサイズ、肉厚等が多岐にわたる場合にも、個々の試験管に要求される保持圧力及び保持時間のみを設定するだけで必要な昇圧を行うことができる。このため、試験管のサイズ、保持圧力の違いごとに昇圧速度、昇圧速度の変更点の設定を行うという煩わしさがなくなる。また、昇圧時にのみポンプが作動する上に、その昇圧時も圧油のリリースが不要となるため、実質的に動力損失が発生しない。
 具体的に説明すると、サーボモータ駆動ポンプの能力が20MPaであり、増圧シリンダの増圧比(受圧面積比)が2であり、保持圧力が30MPa、保持時間が10秒であるとすると、増圧シリンダの出力側の水圧に基づいてサーボモータ駆動ポンプをフィードバック制御すると、サーボモータ駆動ポンプは、増圧シリンダの出力側の水圧が30MPaになるまで(増圧シリンダの入力側の油圧が15MPaになるまで)、増圧シリンダの入力側を自動昇圧し、そのあと更に、設定された保持時間(10秒間)だけその圧力を保持するのである。
 このとき、サーボモータ駆動ポンプは、昇圧初期の低圧期間においては、比較的低圧の圧油を増圧シリンダの入力側へ一気に供給して、試験管内への空気の残留による圧力吸収の影響を軽微に抑制し、その後の昇圧期間においては、比較的高圧の圧油を増圧シリンダの入力側へ連続的に供給して入力側の圧力を高めていくことにより、短時間での昇圧が可能になる。特にサーボモータ駆動ポンプが2容量形である場合は、低圧大流量と高圧小流量という2つのモードをもち、これら2つのモードの切り替えにより、より高速での昇圧が可能になる。
 また、サーボモータ駆動ポンプは、増圧シリンダに対して複数台を並列的に接続して同時に運転することにより、流量を増加させることができ、昇圧時間の一層の短縮を図ることができる。但し、複数台のサーボモータ駆動ポンプを保持圧力到達まで同時運転すると、完全な同期運転が不可能であるため、昇圧末期(保持圧力到達直前)において同期不良に起因する動作不良が発生し、精密な圧力コントロールが困難になる。このため、昇圧末期(保持圧力到達直前)においては、複数のサーボモータ駆動ポンプのうちの1台を除いて運転を停止して残り1台のサーボモータ駆動ポンプで昇圧を行うのが制御精度の点から有効である。
 一方、増圧シリンダについては、保持圧力が低い場合は1本のシリンダで増圧を行うことができる。しかし、保持圧力が高い場合に1本のシリンダで増圧を行うと、必然的にシリンダの増圧比が大きくなる。増圧シリンダは増圧比が小さい場合は低圧大流量で高速動作を行うが、増圧比が大きくなると高圧小流量となり、ピストンストロークの増大によるシリンダ規模の増大だけでなく、昇圧速度が低下することによるサイクルタイムの延長が問題になる。このため、試験管に対して、増圧比が異なる複数本の増圧シリンダを並列的に接続して、増圧比の低いものから高いものへ段階的に使用していくのが有効である。
 具体的に説明すると、油圧源の圧力が最大20MPaで、保持圧力が最大で75MPaの場合、3.75以上の増圧比が必要となる。1本の増圧シリンダで増圧を行う場合は、その増圧シリンダの増圧比として3.75以上が必要となるが、このような高増圧比の増圧シリンダは、油圧源の圧力が限られている状況下では、高増圧比ゆえに必然的に小流量となるので、昇圧速度が低下するのを避けられないのである。
 そこで、この増圧シリンダを複数本に分割し、増圧比を段階的に大きくする。例えば20MPaの増圧シリンダと75MPaの増圧シリンダを使うわけである。そして、20MPaの増圧シリンダは油圧源の最大圧力が20MPaであることから増圧比を1とし、75MPaの増圧シリンダの増圧比は当初のとおり3.75以上とする。そうすると、増圧シリンダの出力側が20MPaに到達するまでは低増圧比の増圧シリンダにより高速昇圧が可能となり、20MPaより上は当初のとおりの昇圧速度による昇圧が行われる。これにより20MPaまでの低圧期間における昇圧時間が短縮され、その結果として全体の昇圧時間が短縮される。
 特に、駆動源がサーボモータ駆動ポンプである場合は、昇圧初期に使用される低増圧比の増圧シリンダは主に低圧大流量で駆動され、その後に使用される高増圧比の増圧シリンダも、昇圧開始時に必要な入力側の圧力(油圧源の圧力)が約5(20/3.75)MPaまで低下するので、少なくとも昇圧当初は低圧大流量で駆動される。このため、昇圧時間が更に短縮される。この点において、増圧シリンダを複数本に分割した場合の油圧源として、圧力と流量の調整範囲が広いサーボモータ駆動ポンプは非常に効果的であり、圧力と流量の調整範囲が特に広い2容量形のサーボモータ駆動ポンプがより効果的となる。
 20MPa、40MPa及び75MPaという3本の増圧シリンダを使用した場合は、40MPaの増圧シリンダにおける増圧比は2となる。その結果、20MPaまでの低圧期間に加えて、20MPaから40MPaまでの中圧期間における昇圧時間も短縮され、全体の昇圧時間が更に短縮される。
 そして、このような複数台のサーボモータ駆動ポンプの運転モードの切替えと運転台数の切替えとの組み合わせによれば、試験管のサイズが8インチ径から24インチ径、あるいはそれ以上までというように広範囲に及ぶ場合も、それぞれの試験管内を保持圧力まで、保持圧力の設定と保持時間の設定のみという簡単な設定操作で、しかも短時間で正確かつ経済的に昇圧して保持することが可能となるのである。
 本発明の水圧試験方法は、かかる知見を基礎として完成されたものであり、製造された金属管を水圧試験するために油圧駆動式の増圧シリンダから試験管内へ高圧水を強制的に供給して管内を所定の保持圧力に昇圧する水圧試験方法において、前記増圧シリンダの油圧駆動源として、並列接続された複数台のサーボモータ駆動ポンプを使用し、前記増圧シリンダの出力側が、予め設定した保持圧力の近傍に到達するまでは、複数台のサーボモータ駆動ポンプを同時運転し、その後は、複数台のサーボモータ駆動ポンプのうちの1台を除いて運転を停止して残り1台のサーボモータ駆動ポンプの運転により、前記増圧シリンダの出力側を保持圧力まで到達させるものである。
 本発明の水圧試験方法においては、増圧シリンダの油圧駆動源が、複数台のサーボモータ駆動ポンプを並列に組み合わせたマルチサーボポンプ方式とされることにより、昇圧時間が短縮される。具体的には、増圧シリンダの出力側が、予め設定した保持圧力の近傍に到達するまでは、複数台のサーボモータ駆動ポンプが、当初は低圧大流量で、その後は高圧小流量に移行しながら、時々に可能な限りの大出力で同時運転する。これにより、試験管内へ高圧水が大量に供給され、試験管内への残留の空気の影響を抑制しつつ、試験管内が高速で昇圧する。その後は、増圧シリンダの出力側が保持圧力に到達するまでの僅かの最終期間のみ、1台のサーボモータ駆動ポンプのみが運転する。これにより、マルチサーボポンプ方式で問題となる同期不良に起因する動作不良の発生が防止される。このため、試験管内を保持圧力まで高速で正確かつ安定に昇圧することができる。サーボモータ駆動ポンプでは、圧油のリリースが生じないので、昇圧期間、非昇圧期間を問わず動力損失は発生しない。
 実際の水圧試験方法では、保持圧力より所定圧(例えば1MPa)低い切り替え点圧力を設定しておき、昇圧中は増圧シリンダの出力側で高圧水の水圧を測定し、測定水圧が切り替え点圧力に到達するまでは複数台のサーボモータ駆動ポンプを同時運転し、測定水圧が切り替え点圧力に到達した時点で、複数のサーボモータ駆動ポンプのうちの1台を除いて運転を停止し、測定水圧が保持圧力に到達した時点で運転中の1台のサーボモータ駆動ポンプの運転を停止するのがよい。設定操作としては、保持圧力及び保持時間を設定するだけとなるので、設定操作がすこぶる簡素化される。
 サーボモータ駆動ポンプは動作範囲が広いために油圧、油量を広範囲に調整でき、低圧のときは大流量で、高圧のときは小流量で圧油を増圧シリンダの低圧側へ供給することができる。調整範囲が特に広い2容量形のサーボモータ駆動ポンプによると、昇圧初期は試験管内の水圧が低いために、複数台のサーボモータ駆動ポンプが高圧大流量モードで運転されることにより、短時間で試験管内へ高圧水を供給することができる。試験管のサイズ、肉厚が小さいときは、高圧水の供給量も保持圧力も小さくなるため、複数台のサーボモータ駆動ポンプが低圧大流量モードのまま運転され続けて、保持圧力の近傍まで昇圧が行われ、保持圧力の近傍からはサーボモータ駆動ポンプが1台になって、最終的には高圧小流量モードで保持圧力まで管内が高精度に昇圧される。
 試験管のサイズ、肉厚が大きいときは、昇圧初期の後も、複数台のサーボモータ駆動ポンプが低圧大流量モードで運転され続けて高圧水の大量供給を続け、引き続き高圧小流量モードで高圧水の供給を行う。保持圧力の近傍からはサーボモータ駆動ポンプが1台になって、高圧小流量モードで保持圧力まで管内を昇圧する。中間サイズの場合は、昇圧初期の後の低圧大流量モードから高圧小流量モードへの切替えタイミングが様々に変更される。
 保持圧力近傍の昇圧末期に運転ポンプを1台とするのは、複数台のサーボモータ駆動ポンプを完全に同期させて駆動するのが困難なために、最終段階の高圧小流量での昇圧を複数台の同時駆動で行うと、流量が極端に少ないために同期不調が顕在化し、ハンチングなどの二次的弊害が発生して、最終段階でのスムーズかつ正確な昇圧が困難になるからである。駆動ポンプが1台であっても、高圧小流量により管内が迅速に昇圧される。精密制御の観点からは、小流量の方が有利である。
 増圧シリンダについては、1本でも良いが、保持圧力の設定範囲が広く、保持圧力の最大値が油圧源の圧力に比して相当に高くなる場合などを考慮すると、複数本の方が望ましく、より具体的には、段階的に増圧比を高くした複数本の増圧シリンダを試験管に対して並列的に配置して、増圧比が小さいものから大きいものへ順次使用するのが好ましい。増圧比が小さい増圧シリンダから、増圧比が大きい増圧シリンダへ順次、段階的に使用すると、増圧比が大きい増圧シリンダのみを使用する場合に比べて低圧側、或いは低圧側及び中圧側での昇圧速度が上がり、昇圧時間が短縮される。
 また、本発明の水圧試験装置は、複数台のサーボモータ駆動ポンプを使用するマルチサーボポンプ方式と、複数本の増圧シリンダを使用するマルチシリンダ方式とを組み合わせることにより昇圧時間の更なる短縮を図るものであり、具体的には、増圧シリンダの油圧駆動源として、複数台のサーボモータ駆動ポンプが、前記増圧シリンダに対して並列に接続されると共に、前記増圧シリンダとして、増圧比が段階的に大きくなった複数本が、試験管に対して並列に接続されており、油圧源と複数本の増圧シリンダとの間に、油圧源からの圧油を複数本の増圧シリンダへ択一的に供給する切り替え機構が設けられているものである。
 実際の水圧試験装置では、増圧シリンダの出力側ラインに高圧水の水圧を測定する水圧センサが設けられ、増圧比の小さい増圧シリンダから増圧比の大きい増圧シリンダへ順番に動作するように前記切り替え機構が水圧センサによる測定水圧に基づいて制御されるシリンダ制御系が設けられることが望まれる。
 また、増圧シリンダの出力側ラインに高圧水の水圧を測定する水圧センサが設けられ、測定水圧が、保持圧力より所定圧(例えば1MPa)低い切り替え点圧力に到達するまでは複数台のサーボモータ駆動ポンプが同時運転し、その後、測定水圧が保持圧力に到達するまでは1台のサーボモータ駆動ポンプが運転するように複数台のサーボモータ駆動ポンプが制御されるポンプ制御系が設けられることが望まれる。
 このような制御系によると、最初は複数台のサーボモータ駆動ポンプからの圧油が増圧比の最も小さい増圧シリンダに供給され、測定水圧がその増圧シリンダの最大水圧近傍に到達すると、増圧比が次に大きい増圧シリンダに圧油が供給され、これを順次続けることにより、保持水圧の近傍までは複数台のサーボモータ駆動ポンプにより試験管内が昇圧される。その後は1台のサーボモータ駆動ポンプにより試験管内が昇圧される。
 本発明の水圧試験方法は、試験管内へ高圧水を供給する増圧シリンダを油圧駆動する際に、油圧源として、並列配置された複数台のサーボモータ駆動ポンプを使用して、駆動ポンプの運転台数を昇圧時期に応じて適切に切り替えるマルチポンプ方式を用いることにより、試験管のサイズが広範囲に及び試験圧力及びその保持時間が多岐にわたる場合も、簡単な設定操作で試験管内を試験圧力まで精度よく昇圧することができる。これにより、1つの試験装置で多種類の水圧試験を行うことか可能となり、これによる試験装置の合理化による効果は多大である。またサイクルタイムが短縮されることにより単位時間あたりの試験本数が多くなり、これによる合理化効果も大きい。また、動力損失の発生が効果的に抑制されるので、これによる動力コストの低減効果も大きく、水圧試験に要するコストの低減に、本発明の水圧試験方法は多大の効果を発揮する。
 また、本発明の水圧試験装置は、前記マルチポンプ方式に加えて、増圧比が段階的に大きくなる複数本の増圧シリンダを、増圧比の小さいものから大きいものへ順次運転するマルチシリンダ方式を採用することにより、試験時間の一層の短縮を図り、水圧試験に要するコストの低減に更に大きな効果を発揮する。
本発明の水圧試験方法を実施するのに適した水圧試験装置の構成図で、流体系統図である。 同水圧試験装置の増圧シリンダ駆動源に使用されるサーボモータ駆動ポンプの使用可能範囲を示すグラフで、吐出圧力と吐出流量との関係を示す。 同水圧試験における管内水圧の経時変化を示すグラフである。 従来の水圧試験方法に使用される水圧試験装置の増圧シリンダ駆動源を示す油圧回路図である。 同増圧シリンダ駆動源に使用されている油圧ポンプの使用可能範囲を示すグラフで、吐出圧力と吐出流量との関係を示す。 従来の水圧試験における管内水圧の経時変化を示すグラフである。 従来の水圧試験における管内水圧の経時変化を示すグラフである。
 以下に本発明の実施形態を説明する。本実施形態の水圧試験方法及び装置は、電縫管製造ラインにおいて製造される電縫管の水圧試験に使用される。
 本実施形態の水圧試験装置は、図1に示すように、水圧試験を受ける電縫管10(以下、試験管10という)を、固定ヘッドであるヘッドストックユニット20Aと、可動ヘッドであるテールストックユニット20Bとの間に挟んで管内へ注水を行い、満水の後に高圧水を供給することにより、試験管10の溶接部(シーム部)の品質等をチェックするものであり、試験管10内へ非加圧(常圧)又は低圧で大量の注水を行う低圧給水系30と、試験管10内が非加圧水又は低圧水で満水となった後に試験管10内へ高圧水を強制的に加圧注入する高圧給水系40とを備えている。
 低圧給水系30は、試験管10のセット位置より高い位置に設置された水タンク31内の水を自重、又は1MPa以下(例えば0.8MPa程度)の低圧により試験管10内へ一気に流し込むものである。具体的には、試験の後に試験管10から排出される水を下側のプール32に一旦溜め、図示されない沈殿槽に移送した後、その上澄みを水サンプ33に溜める。そして、水サンプ33内の水をポンプ34によりフィルタ経由で高位置のタンク31に汲み上げ、これを試験管10内へヘッドストック20A経由で流し込む。このとき、試験管10内の空気は、テールストック20Bに設けられた空気抜き弁21から排出される。水タンク31からヘッドストック20Aへ至るラインEにはシリンダ式の開閉弁35が介装されている。
 高圧給水系40は、満水状態となった試験管10内へ、油圧式の増圧シリンダ41A,41Bにより、最大75MPaというような高圧水を強制的に供給するものである。油圧式の増圧シリンダ41A,41Bは、試験管10に対して並列的に配置されており、駆動系42により選択的に駆動される。増圧シリンダ41A,41Bの選択的な駆動のために、増圧シリンダ41A,41Bと駆動系42との間には、電磁弁43A,43Bからなる切り替え機構43が介装されている。
 第1の増圧シリンダ41Aは最大圧力が21MPaである低圧用であり、第2の増圧シリンダ41Bは最大圧力が75MPaである高圧用である。いずれも、駆動系42から供給される圧油によりピストンを往復駆動され、退入駆動のときに出力側に前記タンク31内からラインAを経由して水を吸い込み、進出駆動のときに、吸い込んだ水を加圧してラインB経由でヘッドストック20Aへ供給することにより、満水状態の試験管10内に高圧水を強制的に供給する。
 増圧シリンダ41A,41Bの駆動系42は、並列的に配置された複数台のサーボモータ駆動ポンプ44を主要構成要素としている。複数台のサーボモータ駆動ポンプ44のうち、1台のサーボモータ駆動ポンプが主ポンプ、残りが従ポンプである。これらのサーボモータ駆動ポンプ44は、いずれも2容量形であり、これらの同時駆動と、これに続く主ポンプの単独駆動とにより、増圧シリンダ41A,41Bの出力側の水圧が、目標値まで自動昇圧される。この自動昇圧のために、増圧シリンダ41A,41Bの出力側(ラインB)の水圧が水圧センサ47により測定されて、シリンダ制御系とポンプ制御系とを兼ねる制御器48に送られることにより、切り替え機構43の切り替え制御、並びにサーボモータ駆動ポンプ44の出力制御及び切り替え制御が行われる。
 切り替え機構43の切り替え制御は、増圧シリンダ41A,41Bのオンオフ切り替え制御と、オン状態にあるシリンダの正逆切り替え制御とからなる。増圧シリンダ41A,41Bのオンオフ切り替え制御は、切り替え機構43を構成する電磁弁43A,43Bのうちの何れか一方を開放状態、他方を閉止状態とすることにより、駆動系42からの圧油を増圧シリンダ41A,41Bの何れか一方に供給して、その一方のみを正逆動作させるものである。また、正逆切り替え制御は、増圧シリンダ41A,41Bのうちの動作状態にあるシリンダの正動作と逆動作とを切り替えるものであり、以下のとおりである。
 サーボモータ駆動ポンプ44の駆動により、油サンプ45内の油が加圧されて吐出される。吐出される圧油は、電磁弁43A,43Bのうちの開放状態(正方向)にある一方を経由してラインCから増圧シリンダ41A,41Bの何れか一方の入力側(入口)に供給される。これにより、増圧シリンダ41A,41Bの何れか一方のピストンが進出駆動され、出力側から高圧水が吐出される。その高圧水がヘッドストック20Aへ送られることは前述したとおりである。ピストンの進出駆動に伴って入力側(出口)から排出される油は、電磁弁43A,43Bの一方からラインDを経由して油サンプ45に戻る。
 電磁弁43A,43Bのうちの開放状態にある一方が正方向から逆方向へ操作されることにより、油サンプ45内の油がラインCを経由して増圧シリンダ41A,41Bの何れか一方の入力側(出口)へ供給され、ピストンが退入駆動される。ピストンの退入駆動に伴って入力側(入口)から排出される油は、電磁弁43A,43Bの一方からラインDを経由して油サンプ45に戻る。
 本実施形態の水圧試験方法は、このような水圧試験装置を使用して実施される。以下に本実施形態の水圧試験装置の機能を説明し、合わせて、本実施形態の水圧試験方法を説明する。
 駆動系42の主体をなすサーボモータ駆動ポンプ44としては、1容量形モデルと2容量形モデルとがあり、ここでは2容量形が使用されている。2容量形モデルでは、図2に示すように、可変容量形ポンプの容量切替えにより、低圧大流量モードM1から高圧小流量モードM2への切替え、及び高圧小流量モードM2から低圧大流量モードM1への切替えが可能である。これにより、サーボモータ駆動ポンプ44は、ACモータにより駆動される通常の油圧ポンプ(図5)と比べて、低圧大流量から高圧小流量まで、格段に広範囲に圧力と流量との関係の調整が可能となる。
 製造された電縫管である試験管10の水圧試験では、同試験管10に対して、第1段階として、その試験管10を試験ラインにセットし、ヘッドストック20Aとテールストック20Bとの間に挟む。第2段階として、低圧給水系30内の水タンク31内に水を満たした状態で、ラインE内のシリンダ式開閉弁35を閉状態から開状態に切り替える。これにより、タンク30内の水が自重又は1MPa以下の低圧によりラインEを通して試験管10内へ一気に流れ込む。水タンク31から試験管10内への注水により管内が満水状態になると、第3段階として、高圧給水系40から試験管10内へ最大圧力が75MPaとういような高圧水を供給して、試験管10内を水圧試験に要求される試験水圧まで昇圧し、更に、その試験水圧を、水圧試験に要求される保持時間、保持する。この操作は、試験管10に要求される試験圧力により相違する。試験圧力は保持圧力であるので、両者は同じ意味である。
 以下に、高圧給水系40による高圧水の供給操作、これによる試験管10内の昇圧操作を、試験圧力ごとに説明する。サーボモータ駆動ポンプ44は3台使用し、1台は主ポンプ、2台は従ポンプであり、いずれの最大加圧力も21MPa以上である。低圧用の増圧シリンダ41Aは、最大加圧力が21MPaであり、増圧比(受圧面積比)は1である。高圧用の増圧シリンダ41Bは、最大加圧力が75MPaであり、増圧比(受圧面積比)は3.57である。
 試験圧力(保持圧力)が21MPa以下の場合は、試験圧力(保持圧力)及び保持時間を制御器48に設定すると、第1段階として、低圧用の増圧シリンダ41Aが退入動作を行うように、駆動系42が操作される。具体的には、増圧シリンダ41Aに対応する電磁弁43Aを逆方向に開とし、増圧シリンダ41Bに対応する電磁弁43Bを閉とした状態で、駆動系42内の3台のサーボモータ駆動ポンプ44が最大出力もしくはこれに近い出力で同時運転する。増圧シリンダ41Aの退入動作により、そのシリンダ41Aの出力側に水タンク31内から水が吸い込まれる。そうすると、第2段階として、電磁弁43Aが逆方向から正方向へ切り替わり、増圧シリンダ41Aが進出動作を開始する。
 増圧シリンダ41Aの進出動作開始当初は、入力側の油圧が低い。このため、2容量形のサーボモータ駆動ポンプ44は、低圧大流量モードで運転し、増圧シリンダ41Aの入力側に大量の圧油を短時間で強制的に供給する。これにより、増圧シリンダ41Aの出力側からラインB、更にはヘッドストック20Aを通じて満水状態の試験管10内へ、加圧水が大量に強制供給される。増圧シリンダ41Aの入力側への圧油の強制供給、これに伴う試験管10内への加圧水の供給に伴い、増圧シリンダ41Aの出力側の水圧が上がり、増圧シリンダ41Aの入力側の油圧も上がる。これにより、2容量形のサーボモータ駆動ポンプ44は、低圧大流量モードから高圧小流量モードへ移行し、油圧を高めながら増圧シリンダ41Aの入力側への圧油の供給を続ける。その結果、増圧シリンダ41Aの出力側から試験管10内へ加圧水が圧力を高めながら供給される。
 試験管10内へ加圧水が供給されると、図3に示すように、その供給に伴って試験管10内の圧力が上昇する。試験管10の内圧は、増圧シリンダ41A,41Bの出力側(ラインB)に設けられた水圧センサ47によりモニターされている。その内圧が保持開始圧力よりも低く且つ設定保持圧力よりもΔP(固定値で、ここでは1MPa)だけ低い切り替え点圧力に到達すると、3台のサーボモータ駆動ポンプ44のうちの従ポンプを停止し、主ポンプのみを運転し続ける。その主ポンプは高圧小流量モードM2(図2参照)で運転を続け、試験管10の内圧を設定保持圧力まで高める。
 試験管10内が設定保持圧力に到達すると、その圧力を所定時間保持して試験を終える。その後は、ヘッドストック20A又はテールストック20B、若しくはこれらの両方に設けられた減圧弁を開いて、管内を減圧する。減圧が終わると、試験管10からテールストック20Bを分離した後、その試験管10を固定のテールストック20Aから分離し、傾斜させて、管内の水を全量下側のプール32に排出する。その水の一部が次の試験に再使用されることは前述したとおりである。
 試験圧力(保持圧力)が21MPaを超え75MPa以下の場合は、試験圧力(保持圧力)及び保持時間を制御器48に設定すると、第1段階として、低圧用の増圧シリンダ41A及び高圧用の増圧シリンダ41Bが退入動作を行うように、駆動系42が操作される。具体的には、増圧シリンダ41A,41Bに対応する電磁弁43A,43Bを逆方向に開とした状態で、駆動系42内の3台のサーボモータ駆動ポンプ44が最大出力もしくはこれに近い出力で同時運転する。増圧シリンダ41A,41Bの退入動作により、それらのシリンダ41A,41Bの出力側に水タンク31内から水が吸い込まれる。そうすると、第2段階として、電磁弁43Aが逆方向から正方向へ切り替わり、電磁弁43Bが逆方向の開状態から閉状態へ切り替わる。これにより、増圧シリンダ41Aのみが進出動作を開始する。
 増圧シリンダ41Aの進出動作開始当初は、入力側の油圧が低い。このため、2容量形のサーボモータ駆動ポンプ44は、低圧大流量モードで運転し、増圧シリンダ41Aの入力側に大量の圧油を短時間で強制的に供給する。これにより、増圧シリンダ41Aの出力側からラインB及びヘッドストック20Aを通じて満水状態の試験管10内へ、加圧水が大量に強制供給される。増圧シリンダ41Aの入力側への圧油の強制供給、これに伴う試験管10内への加圧水の供給に伴い、増圧シリンダ41Aの出力側の水圧が上がり、増圧シリンダ41Aの入力側の油圧も上がる。その結果、2容量形のサーボモータ駆動ポンプ44は、低圧大流量モードから高圧小流量モードへ移行し、油圧を高めながら増圧シリンダ41Aの入力側への圧油の供給を続ける。これにより、増圧シリンダ41Aの出力側から試験管10内へ加圧水が圧力を高めながら供給される。
 試験管10内へ加圧水が供給されると、試験管10内の圧力が上昇する。試験管10内の圧力は、増圧シリンダ41A,41Bの出力側(ラインB)に設けられた水圧センサ47によりモニターされている。その内圧が21MPaに達すると、第3段階として、電磁弁43Aが正方向の開状態から閉状態へ切り替わり、電磁弁43Bが閉状態から正方向の開状態へ切り替わる。これにより、低圧用の増圧シリンダ41Aが進出動作を停止し、代わって高圧用の増圧シリンダ41Bが進出動作を開始する。
 高圧用の増圧シリンダ41Bの増圧比は3.57である。このため、サーボモータ駆動ポンプ44の最大圧力が21MPaであっても、出力側の水圧を75MPaまで高めることができる。高圧用の増圧シリンダ41Bに切り替わったとき、出力側の水圧は21MPaまで昇圧されているので、サーボモータ駆動ポンプ44の実質的な負担は5.9(21/3.57)MPaから、となる。このような低圧だと、サーボモータ駆動ポンプ44は再び低圧大容量モードM1で運転する。このため、増圧シリンダ41Bの入力側に再び大量の圧油が供給され始める。増圧シリンダ41Bの増圧比は3.57と高く、その分、出力側は低流量となるが、入力側が大流量であるので、高圧側の流量が補われ、増圧シリンダ41Aの出力側の流量より少なくなるものの、その差は小さい。したがって、増圧シリンダ41Bの出力側からラインB及びヘッドストック20Aを通じて試験管10内へ、加圧水が大量に強制供給され、試験管10内が更に昇圧される。
 増圧シリンダ41Bの入力側への圧油の強制供給、これに伴う試験管10内への加圧水の更なる供給に伴い、増圧シリンダ41Aの出力側の水圧が更に上がると、増圧シリンダ41Aの入力側の油圧も上がる。これにより、2容量形のサーボモータ駆動ポンプ44は、低圧大流量モードから高圧小流量モードへ移行し、油圧を更に高めながら増圧シリンダ41Bの入力側への圧油の供給を続ける。その結果、増圧シリンダ41Bの出力側から試験管10内へ加圧水が圧力を更に高めながら供給され、試験管10内の水圧が更に高くなる。
 試験管10内の水圧が、保持開始圧力よりも低く且つ設定保持圧力よりもΔP(ここでは1MPa)だけ低い切り替え点圧力に到達すると、3台のサーボモータ駆動ポンプ44のうちの従ポンプを停止し、主ポンプのみを運転し続ける。その主ポンプは高圧小流量モードM2で運転を続け、試験管10の内圧を設定保持圧力まで高める。
 試験管10内が設定保持圧力に到達すると、その圧力を所定時間保持して試験を終える。その後は、ヘッドストック20A又はテールストック20B、若しくはこれらの両方に設けられた減圧弁を開いて、管内を減圧する。減圧が終わると、試験管10からテールストック20Bを分離した後、その試験管10を固定のテールストック20Aから分離し、傾斜させて、管内の水を全量下側のプール32に排出する。その水の一部が次の試験に再使用されることは前述したとおりである。
 このような水圧試験方法、特に試験管10内の昇圧方法によると、制御器48に保持圧力と保持時間を設定すれば、後は制御器48が増圧シリンダ41A、21Bの出力側の水圧にしたがって自動制御を行うので、設定操作が簡単である。このため、試験管10のサイズ、肉厚が多岐に及ぶ場合も一つの試験装置で全てのサイズの試験管10を試験することが可能となる。
 多種類の試験管10を一つの装置で試験する場合は、1本の試験管10の試験に要する時間(サイクルタイム)を短くする必要があるが、本実施形態の水圧試験方法においては、これも可能である。すなわち、本実施形態の水圧試験方法においては、設定保持圧力の近傍まで複数台の油圧ユニットにより試験管10内の昇圧を行うので、試験管10内に大量の高圧水を短時間で供給することができる。しかも、それらの油圧ユニットが、低圧大流量モードM1と高圧小流量モードM2とを併有する2容量形のサーボモータ駆動ポンプ44であるため、試験管10のサイズ、肉厚が多岐に及び、24インチ径を超えるような極端に大径で厚肉の試験管10を含む場合も、何れの試験管10内をも、昇圧初期の残留空気の圧縮による加圧の吸収を補って、設定保持圧力近傍まで可及的に短い時間で昇圧することができる。
 加えて、設定保持圧力近傍から設定保持圧力までは、複数台のサーボモータ駆動ポンプ44のうちの1台のみが高圧小流量モードM2で単独運転し、小流量により設定保持圧に収束させるので、オーバーシュートを発生させる危険がない。また、同期不良によるハンチングの問題も生じない。したがって、設定保持圧に収束させる精度が高い。
 また、試験の全期間、及び試験外の全期間をとおして、必要量の圧油のみが増圧シリンダ41の低圧側に供給され、リリースされる圧油が実質的に存在しないために、事実上、油圧ユニットにおける動力損失が発生しない。
 かくして、本実施形態の水圧試験方法によると、小径の試験管10から大径の試験管10まで一つの水圧試験装置で試験を行うことができる。しかも、各試験では試験の所要時間が短縮され、単位時間あたりの試験本数が増加すると共に、油圧ユニットでの動力損失の発生が抑制される。これらのために試験に要するコストが大幅に低減する。
 なお、高圧給水において複数台のサーボモータ駆動ポンプ44が低圧大流量モードのままで出力側の水圧が切り替え点圧力に到達した場合は、高圧小流量モードへの切り替えは起こらない。また、その後の保持圧力までの単独運転でも、サーボモータ駆動ポンプ44は低圧大流量モードのまま運転を続ける。
 このような水圧試験方法により、外径が203mmから21インチまでの電縫鋼管を実際に試験した結果を説明する。電縫鋼管はAPI-X80規格である。肉厚は、外径が203mmの管を除き、各外径について5.0mm、12.7mmの2種類であり、外径が203mmの管では12.7mmの1種類である。長さは、全ての管について1372cm(13.72m)である。降伏応力YSは、最小値である555MPaと最大値である705MPaとの間の562MPaに設定し、これと鋼管仕様とから試験圧力Pを求めた。試験圧力Pの算出式は数式1のとおりである。
Figure JPOXMLDOC01-appb-M000001
 各試験管の仕様、試験圧力P及びこれらから算出した必要水量を表1に示す。必要水量は、低圧給水水量と高圧給水水量の2種類を示し、高圧給水水量については、残留空気の圧縮を吸収するのに必要な水量、鋼管の膨張を吸収するのに必要な水量、21MPa昇圧に必要な水量、21MPaから試験圧力へ昇圧するのに必要な水量、及びこれらの合計水量を示すと共に、合計水量のうち、低圧用の増圧シリンダが負担する水量、高圧用の増圧シリンダが負担する水量を示す。試験圧力が21MPa以下のときは、21MPa昇圧に必要な水量は試験圧力への昇圧に必要な水量であり、21MPaから試験圧力へ昇圧するのに必要な水量は0である。
 低圧用の増圧シリンダの最大容量は95L、高圧用の増圧シリンダの最大容量は40Lである。サーボモータ駆動ポンプとしては15kWのものを3台使用した。試験管内の残留空気量は、ここでは1.5%としているが、実際は大きくばらつくのを避け得ないことは前述したとおりである。したがって、ここで算出した必要水量は目安であり、実際の試験では増圧シリンダの出力側の水圧をモニターすることにより、このばらつきの影響を回避できることも前述したとおりである。
Figure JPOXMLDOC01-appb-T000002

 1本の試験に要するサイクルタイムは例えば次のとおりである。試験管のローディング、アンローディングに6.0秒、試験管のセンタリングに1.0秒、テールヘッドの前進に4.0秒、非加圧給水に6.0~9.5秒、エア抜きバルブの操作に0.5秒、試験圧力までの強制加圧給水に3.5~10秒、保持時間が10秒、圧抜き時間に0.5秒、テールヘッド後退に3.0秒、試験管の排出に1.0秒、タイムラグが1.5~3.0秒であり、サイクルタイムは37.0~47.5秒の間に納まった。強制加圧給水時間がばらついているのは、試験圧力が異なるためであり、本実施形態の水圧試験方法では、この強制加圧給水時間の短縮が顕著である。また、従来の水圧試験方法では、そもそも、このような多種類の試験管を一つの装置で試験すること自体が不可能であった。
 なお、駆動系42の主体をなすサーボモータ駆動ポンプ44の台数は、2台以上であればよく、個々のポンプ44の能力と要求される特性とにより適宜決められる。
 上述の水圧試験に合格した試験管は、次工程で管継手との接続のために管端にねじ切りが行われる。ねじ切りが完了した試験管は、一方又は両端に管継手を装着した状態で同様の水圧試験に供される。一方端のみに管継手を装着して水圧試験される場合は、試験管の端部内を密封するプラグと管継手の開放側を密封するプラグとが一体になった特殊プラグ内に高圧水を供給してねじ部の水漏れを試験する。そのため、管内全体を満水とする場合に比較して少量の高圧水で試験されるが、実施例と同様に高圧で試験されるため、やはり昇圧には時間を要する。従って、かかる管端の水圧試験においても実施例の水圧試験方法及び装置が極めて有効であり、試験時間の短縮効果が顕著である。
 上述の説明では、試験対象は電縫管であったが、本発明はシームレス管の水圧試験にも適用可能である。シームレス管の水圧試験の場合は試験圧力が例えば160MPaと、電縫管に比べて高い。このため、増圧シリンダは3本、或いはそれ以上使用するのが望ましい。サーボモータ駆動ポンプは、15kWのものであれば8~9台必要である。同様に、電縫管の水圧試験でも、増圧シリンダを3本以上使用することが可能である。
 10 試験管
 20A ヘッドストックユニット
 20B テールストック
 21 空気抜き弁
 30 低圧給水系
 31 水タンク
 32 プール
 33 水サンプ
 34 ポンプ
 35 開閉弁
 40 高圧給水系
 41 増圧シリンダ
 42 増圧シリンダ41の駆動系
 43 切り替え機構(電磁弁)
 44 サーボモータ駆動ポンプ
 45 油サンプ
 47 水圧センサ
 48 制御系

Claims (8)

  1.  製造された金属管を水圧試験するために油圧駆動式の増圧シリンダから試験管内へ高圧水を供給して管内を所定の試験圧力に昇圧して所定時間保持する水圧試験方法において、前記増圧シリンダの油圧式駆動源として、並列接続された複数台のサーボモータ駆動ポンプを使用し、前記増圧シリンダの出力側が、予め設定した試験圧力の近傍に到達するまでは、複数台のサーボモータ駆動ポンプを同時運転し、その後は、複数台のサーボモータ駆動ポンプのうちの1台を除いて運転を停止して残り1台のサーボモータ駆動ポンプの運転により、前記増圧シリンダの出力側を試験圧力まで到達させて保持する水圧試験方法。
  2.  請求項1に記載の水圧試験方法において、サーボモータ駆動ポンプが2容量形である水圧試験方法。
  3.  請求項1又は2に記載の水圧試験方法において、試験圧力より所定圧小さい切り替え点圧力を設定しておき、昇圧中は増圧シリンダの出力側で高圧水の水圧Pを測定し、測定水圧が前記切り替え点圧力に到達するまでは複数台のサーボモータ駆動ポンプを同時運転し、測定水圧が前記切り替え点圧力に到達した時点で、複数のサーボモータ駆動ポンプのうちの1台を除いて運転を停止し、測定水圧が試験圧力に到達した時点で運転中の1台のサーボモータ駆動ポンプの運転を停止する水圧試験方法。
  4.  請求項1又は2に記載の水圧試験方法において、増圧比を段階的に高くした複数本の増圧シリンダを試験管に対して並列的に配置して、増圧比が小さいものから大きいものへ順番に使用する水圧試験方法。
  5.  製造された金属管を水圧試験するために油圧駆動式の増圧シリンダから試験管内へ高圧水を供給して管内を所定の試験圧力に昇圧して所定時間保持する水圧試験装置において、増圧シリンダの油圧駆動源として、複数台のサーボモータ駆動ポンプが、前記増圧シリンダに対して並列に接続されると共に、前記増圧シリンダとして、増圧比が段階的に大きくなった複数本が、試験管に対して並列に接続されており、油圧源と複数本の増圧シリンダとの間に、油圧源からの圧油を複数本の増圧シリンダへ択一的に供給する切り替え機構が設けられている水圧試験装置。
  6.  請求項5に記載の水圧試験装置において、サーボモータ駆動ポンプが2容量形である水圧試験装置。
  7.  請求項5又は6に記載の水圧試験装置において、増圧シリンダの出力側ラインに高圧水の水圧を測定する水圧センサが設けられ、増圧比の小さい増圧シリンダから増圧比の大きい増圧シリンダへ順番に動作するように前記切り替え機構が水圧センサによる測定水圧に基づいて制御されるシリンダ制御系が構成されている水圧試験装置。
  8.  請求項5又は6に記載の水圧試験装置において、試験圧力より所定圧小さい切り替え点圧力が設定されており、測定水圧が切り替え点圧力に到達するまでは複数台のサーボモータ駆動ポンプが同時運転し、その後、測定水圧Pが試験圧力に到達するまでは1台のサーボモータ駆動ポンプが運転するように複数台のサーボモータ駆動ポンプが制御されるポンプ制御系が構成されている水圧試験装置。
PCT/JP2014/052575 2014-02-04 2014-02-04 水圧試験方法及び装置 Ceased WO2015118614A1 (ja)

Priority Applications (7)

Application Number Priority Date Filing Date Title
RU2016135535A RU2649619C1 (ru) 2014-02-04 2014-02-04 Способ гидравлического испытания и устройство для гидравлического испытания
CN201480074786.XA CN105980830B (zh) 2014-02-04 2014-02-04 水压试验方法及装置
JP2015504809A JP5783656B1 (ja) 2014-02-04 2014-02-04 水圧試験方法及び装置
EP14881914.7A EP3104158B1 (en) 2014-02-04 2014-02-04 Hydraulic testing method and device
US15/115,729 US10234367B2 (en) 2014-02-04 2014-02-04 Hydraulic test method and hydraulic test device
KR1020167024020A KR20160117538A (ko) 2014-02-04 2014-02-04 수압 시험 방법 및 장치
PCT/JP2014/052575 WO2015118614A1 (ja) 2014-02-04 2014-02-04 水圧試験方法及び装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2014/052575 WO2015118614A1 (ja) 2014-02-04 2014-02-04 水圧試験方法及び装置

Publications (1)

Publication Number Publication Date
WO2015118614A1 true WO2015118614A1 (ja) 2015-08-13

Family

ID=53777451

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2014/052575 Ceased WO2015118614A1 (ja) 2014-02-04 2014-02-04 水圧試験方法及び装置

Country Status (7)

Country Link
US (1) US10234367B2 (ja)
EP (1) EP3104158B1 (ja)
JP (1) JP5783656B1 (ja)
KR (1) KR20160117538A (ja)
CN (1) CN105980830B (ja)
RU (1) RU2649619C1 (ja)
WO (1) WO2015118614A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106224332A (zh) * 2016-08-31 2016-12-14 南京大地水刀股份有限公司 一种电伺服超高压系统及其操作原理
KR101998395B1 (ko) * 2018-12-28 2019-07-09 한국가스안전공사 초고압용기 반복 가압 시험용 고속 대용량 유량 측정장치

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015118614A1 (ja) 2014-02-04 2015-08-13 株式会社中田製作所 水圧試験方法及び装置
ES2683089B1 (es) * 2017-03-23 2019-07-05 Univ Burgos Dispositivo para ensayo de componentes sometidos a alta presion en una maquina de traccion-compresion
KR102012949B1 (ko) * 2017-06-16 2019-08-21 한국기계연구원 대유량 밸브 충격압력 시험장치
KR101941704B1 (ko) * 2017-12-28 2019-01-23 한국가스안전공사 가스용기 수압시험용 동시 주입장치
CN109060547B (zh) * 2018-09-05 2020-03-31 江苏科技大学 复杂压力环境试验装置
CN109556964B (zh) * 2018-11-06 2021-12-14 宁波大学 一种基于三维模型的隧道模型试验平台的监测控制系统
CN111413205B (zh) * 2020-02-25 2021-03-02 蓝箭航天空间科技股份有限公司 一种双介质压力试验系统和方法
CN111238919B (zh) * 2020-02-25 2021-02-19 蓝箭航天空间科技股份有限公司 一种双介质压力试验装置
KR102500817B1 (ko) * 2020-07-01 2023-02-17 주식회사 맥시스 밸브용 누설 시험 장치 및 방법
RU206134U1 (ru) * 2021-06-07 2021-08-24 Общество с ограниченной ответственностью Управляющая компания "Алтайский завод прецизионных изделий" Установка для гидравлического нагружения компонентов систем common rail
CN113280896B (zh) * 2021-06-22 2022-11-25 宁波东海集团有限公司 一种水表密封性检测装置及方法
CN114061863B (zh) * 2021-10-11 2025-01-21 岭澳核电有限公司 核电站指套管完整备件水压试验系统
KR102520823B1 (ko) * 2022-11-15 2023-04-11 (재)한국건설생활환경시험연구원 해수압 환경 시험장치를 이용한 부력 시험방법
CN115855674A (zh) * 2023-01-04 2023-03-28 一重集团大连工程技术有限公司 一种管件压力实验系统
CN116861589B (zh) * 2023-07-07 2024-03-12 上海贺力液压机电有限公司 一种冶金液压站伺服电机驱动系统可靠性设计方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007509329A (ja) * 2003-10-25 2007-04-12 アイゼン ウント メタルヴェルケ フェルンドルフ ゲーエムベーハー 管の品質特性および品質特異性を圧力検査により調整するための方法
CN102042935A (zh) * 2010-10-29 2011-05-04 马利芳 一种端面密封薄壁钢管静水压检测方法
JP4738783B2 (ja) * 2004-09-24 2011-08-03 Jfeスチール株式会社 溶接鋼管の水圧試験装置
WO2013005283A1 (ja) * 2011-07-01 2013-01-10 株式会社中田製作所 管クランプ装置及び水圧試験機

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1238701B (de) * 1964-03-26 1967-04-13 Kieserling & Albrecht Druckverhaeltnisregler
JPS5575634A (en) 1978-12-04 1980-06-07 Hitachi Ltd Running control unit for vibration test machine
US4416147A (en) * 1981-07-15 1983-11-22 Hasha Brian B Apparatus and method for hydrostatically testing pipe
US4770019A (en) 1985-12-28 1988-09-13 Nakata Manufacture Company Limited Forming roll, forming process and its apparatus in the pipe mill
JPH0792061B2 (ja) 1986-10-30 1995-10-09 日精樹脂工業株式会社 射出成形機の制御装置
JPH0687040B2 (ja) 1989-04-10 1994-11-02 株式会社巴技研 引張クリープ破断試験機の伸び追従装置
US5152167A (en) * 1991-02-08 1992-10-06 Colman Manufacturing Company Method and apparatus for measuring leakage in a fluid system
JPH04362285A (ja) 1991-06-11 1992-12-15 Kawasaki Heavy Ind Ltd 油圧源制御装置
JP3137530B2 (ja) 1994-04-15 2001-02-26 三菱重工業株式会社 歪み速度コントロール装置
JPH08187155A (ja) 1995-01-09 1996-07-23 Yoshio Shimizu 回転寿司における湯呑み茶わん載せ台
JPH08187755A (ja) 1995-01-10 1996-07-23 Mitsubishi Heavy Ind Ltd 射出成形機の保圧制御方法
JP4770019B2 (ja) 2000-12-22 2011-09-07 三菱瓦斯化学株式会社 プリプレグ及び金属箔張り積層板
CN101709725B (zh) 2009-11-17 2011-07-27 华东交通大学 一种采用多泵组合技术的井下防爆提升机液压控制系统
WO2015118614A1 (ja) 2014-02-04 2015-08-13 株式会社中田製作所 水圧試験方法及び装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007509329A (ja) * 2003-10-25 2007-04-12 アイゼン ウント メタルヴェルケ フェルンドルフ ゲーエムベーハー 管の品質特性および品質特異性を圧力検査により調整するための方法
JP4738783B2 (ja) * 2004-09-24 2011-08-03 Jfeスチール株式会社 溶接鋼管の水圧試験装置
CN102042935A (zh) * 2010-10-29 2011-05-04 马利芳 一种端面密封薄壁钢管静水压检测方法
WO2013005283A1 (ja) * 2011-07-01 2013-01-10 株式会社中田製作所 管クランプ装置及び水圧試験機

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106224332A (zh) * 2016-08-31 2016-12-14 南京大地水刀股份有限公司 一种电伺服超高压系统及其操作原理
KR101998395B1 (ko) * 2018-12-28 2019-07-09 한국가스안전공사 초고압용기 반복 가압 시험용 고속 대용량 유량 측정장치

Also Published As

Publication number Publication date
EP3104158A1 (en) 2016-12-14
KR20160117538A (ko) 2016-10-10
JP5783656B1 (ja) 2015-09-24
CN105980830A (zh) 2016-09-28
RU2649619C1 (ru) 2018-04-04
CN105980830B (zh) 2019-08-16
US10234367B2 (en) 2019-03-19
EP3104158A4 (en) 2017-10-25
US20170167961A1 (en) 2017-06-15
EP3104158B1 (en) 2019-10-30
JPWO2015118614A1 (ja) 2017-03-23

Similar Documents

Publication Publication Date Title
JP5783656B1 (ja) 水圧試験方法及び装置
CN106734493B (zh) 一种胀形压力脉动加载的中小型内高压成形机
CN106996403B (zh) 一种可精确控制压力的流体动力装置和加压方法
CN105181475A (zh) 一种伺服电动缸增压的脉冲试验系统
CN113295538B (zh) 一种水压试验机调压方法
CN107035739B (zh) 一种可精确控制压力的气体动力装置和加压方法
CN113309745B (zh) 一种双缸增压结构及控制方法
JP2017003502A (ja) 圧力試験装置及び圧力試験方法
CN106094913B (zh) 一种超高压试压系统及其控制方法
RU2644443C1 (ru) Гидросистема для нагружения конструкций при прочностных испытаниях
CN104865132A (zh) 内拉式超高压大直径钢管水压试验机及其液压系统
KR101355117B1 (ko) 유압제어압력에 의한 임펄스 발생장치
CN108708889A (zh) 一种节能型低振快响应混合控制伺服液压机液压系统
US10336027B2 (en) Hydraulic feeder system having compression stage with multi-cylinder hydraulic circuit
JP3181356U (ja) 液圧拡管成形装置
JP5701678B2 (ja) 加圧装置および加圧装置の制御方法
US11603868B2 (en) Pressurizing device
US11015622B2 (en) Hydraulic intensifiers, boosters and/or controllers
CN209265286U (zh) 一种高精度流体自动控压装置
US20160075068A1 (en) Injection molding device
JP2017202496A (ja) 押出プレスのコンテナ・メインクロスヘッドの後退動作方法
RU2449861C2 (ru) Способ управления зажимными гидроцилиндрами и стенд для свинчивания и развинчивания резьбовых соединений гидравлических забойных двигателей
CN106930987B (zh) 用于对成型机的元件加载力的液压系统和成型机
CN109139586B (zh) 一种变压型水下切粒机刀盘移动液压系统及其工作方法
CN119053438A (zh) 压力增强器单元的系统、控制该系统的方法和相关的计算机程序、以及包括所述系统的压制设备

Legal Events

Date Code Title Description
ENP Entry into the national phase

Ref document number: 2015504809

Country of ref document: JP

Kind code of ref document: A

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 14881914

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 15115729

Country of ref document: US

NENP Non-entry into the national phase

Ref country code: DE

REEP Request for entry into the european phase

Ref document number: 2014881914

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2014881914

Country of ref document: EP

ENP Entry into the national phase

Ref document number: 20167024020

Country of ref document: KR

Kind code of ref document: A

ENP Entry into the national phase

Ref document number: 2016135535

Country of ref document: RU

Kind code of ref document: A