US20170321421A9 - Prefabricated modular rebar modules and methods of using the same - Google Patents
Prefabricated modular rebar modules and methods of using the same Download PDFInfo
- Publication number
- US20170321421A9 US20170321421A9 US14/517,113 US201414517113A US2017321421A9 US 20170321421 A9 US20170321421 A9 US 20170321421A9 US 201414517113 A US201414517113 A US 201414517113A US 2017321421 A9 US2017321421 A9 US 2017321421A9
- Authority
- US
- United States
- Prior art keywords
- welded
- reinforcing bars
- prefabricated
- layer
- steel structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims description 16
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 68
- 239000004567 concrete Substances 0.000 claims abstract description 47
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 39
- 238000012546 transfer Methods 0.000 claims abstract description 12
- 229910000831 Steel Inorganic materials 0.000 description 25
- 239000010959 steel Substances 0.000 description 25
- 238000009434 installation Methods 0.000 description 11
- 238000010276 construction Methods 0.000 description 7
- 238000013461 design Methods 0.000 description 7
- 238000003466 welding Methods 0.000 description 6
- 239000011150 reinforced concrete Substances 0.000 description 4
- 230000000712 assembly Effects 0.000 description 3
- 238000000429 assembly Methods 0.000 description 3
- 230000001934 delay Effects 0.000 description 3
- 230000004075 alteration Effects 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
- E04C5/0604—Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
- E04C5/0609—Closed cages composed of two or more coacting cage parts, e.g. transversally hinged or nested parts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C2/00—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
- E04C2/02—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
- E04C2/04—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
- E04C2/06—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres reinforced
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
- E04C5/0604—Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
Definitions
- This invention relates generally to the broad field of reinforced concrete and more particularly to the steel, or rebar used to reinforce the concrete. More particularly, this invention relates to methods and apparatus for constructing and installing rebar used in concrete construction.
- Reinforced concrete is a well known and widely used building material which is used in building, bridges, roads, tunnels and other structural construction projects. Essentially the concrete, which is strong in compression but has no strength in tension, is reinforced with steel rods which pass through the zones of tension in the structural element. Engineers design the structural components; calculate the forces which will be generated by the structure, which may be carrying dynamic or static loads or both; and then develop a rebar plan to provide enough rebar reinforcement in the regions of the concrete structure where tension forces may be created. The rebar plan often requires complex cages with rebar elements bent from, for example, a top surface to a bottom surface and then back to the top surface to accommodate the load pattern created in a beam supported by a column for example.
- rebar rods are transported individually to a work site and then assembled on site. In some cases they may be bent on site and in other cases they may be bent at the factory and merely assembled on site. Assembly means placing the rebar rods into a form which will then hold the liquid concrete which is poured into the form around the rebar. Once the concrete cures and hardens the forms can be removed and the structural element is ready for use.
- the rebar is typically provided with a textured outer surface to enable the concrete to better grip the steel bars.
- the assembly of the rebar into the forms is done with great care—the correct positioning of the rebar is required to ensure the structural element has the strength that it has been designed for.
- Each rebar element must be precisely located in the three dimensional space within the form to ensure appropriate load bearing capacity of the finished structural element.
- the engineers provide the fabricators with exact rebar cage plans and designs and every rod is checked for correct positioning before any concrete is poured.
- the fabrication of the re-bar cage according to the detailed design specifications can be slow and tedious work.
- the rebar components are connected on site by workers using ties with wires.
- the rods themselves can be long and unwieldy.
- the position of the components each have to carefully measured to ensure that they are properly spaced and located and that they will be located at an appropriate depth within the concrete once the concrete is poured into the form.
- the entire process of installing the components on site can be time consuming, which in turns increases the costs of the projects. Delays in the construction of rebar cages can cause significant delays in the entire construction project since the installation of reinforced concrete will often be one of the first steps in a major building project.
- rebar structures for raft and transfer slabs onsite is also awkward in that incomplete cage assemblies may lead to partially built cage structures that are shaky and hard to walk on, causing safety issues. Installation may also be more challenging where confined spaces exist during the construction of the slab layers. It may also be challenging to place rebar on slabs that are deeper than 1800 mm or approximately 6′ in depth. Slabs are typically 2′ to 12′ deep.
- the structure may comprise one or more prefabricated, welded modular cages having vertical reinforcing bars.
- the cages may be prefabricated in an offsite factory where there are the space, tools and workers to quickly and easily create the modular cages.
- There may be a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars.
- Each prefabricated welded cage may be sized and shaped for shipping and said structure may be quickly and easily formed onsite from a plurality of said modular cages lapped together.
- a method of constructing a reinforcing steel structure for use in a concrete building wall A plurality of prefabricated, welded cages having vertical reinforcing bars are provided at a worksite. Each of the plurality of prefabricated, welded cages may have a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars.
- the plurality of prefabricated, welded cages may be installed at a worksite.
- Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a continuous reinforcing steel structure. Concrete is added to the reinforcing steel structure to form a concrete building wall.
- the structure comprises one or more prefabricated, welded beams.
- the prefabricated, welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer.
- Each welded beam may be sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together.
- a method of constructing a reinforcing steel structure for use in a concrete building slab A plurality of prefabricated, welded beams may be provided at a worksite.
- the welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer.
- a bottom slab layer comprising a plurality of horizontal reinforcing bars may be installed.
- the plurality of prefabricated, welded beams may be installed adjacent to one another on the bottom slab layer.
- a top slab layer comprising a plurality of horizontal reinforcing bars is installed on the plurality of welded beams to form a reinforcing steel structure. Concrete is poured around the reinforcing steel structure and permitted to cure to form a concrete building slab.
- FIG. 1 is a top view of an embodiment of a prefabricated, welded cage for a heavy wall
- FIG. 2 is a top view of an embodiment of a continuous tie for use in a pre-fabricated, welded cage
- FIG. 3 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure;
- FIG. 4 is a top view of an embodiment having two prefabricated, welded cages for a heavy wall
- FIG. 5 is a top view showing a pair of lap bars connecting two continuous ties
- FIG. 6 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure
- FIG. 7 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages;
- FIG. 8 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in walls with zones;
- FIG. 9 is a top view of a section of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in a wall with zones;
- FIG. 10 is a top view of an embodiment of a steel structure having a plurality of prefabricated, welded cages.
- FIG. 11 is a side view of an embodiment having a pair of prefabricated welded beam for use in a transfer slab or raft slab;
- FIG. 12 is a perspective view of an embodiment of a bottom slab layer of FIG. 11 for a transfer slab or raft slab;
- FIG. 13 is a perspective view of an embodiment of a prefabricated, welded beam of FIG. 11 for installation in a transfer slab or raft slab;
- FIG. 14 is a perspective view of an embodiment of FIG. 11 having a pair of prefabricated, welded beams installed on a bottom slab layer;
- FIG. 15 is a perspective view of an embodiment of FIG. 11 of a top slab layer installed on top of a pair of prefabricated, welded beams;
- FIG. 16 is a side view of an embodiment having a pair of prefabricated, welded beams having shear ties
- FIG. 17 is a perspective view of an embodiment of a bottom slab layer of FIG. 16 ;
- FIG. 18 is a perspective view of an embodiment of a prefabricated, welded beam of FIG. 16 for a transfer slab or raft slab;
- FIG. 19 is a perspective view of an embodiment of a steel structure having a pair of prefabricated, welded beams of FIG. 16 installed on a bottom slab layer;
- FIG. 20 is a perspective view of an embodiment of a steel structure of FIG. 16 having a top slab layer installed on a pair of prefabricated, welded beams.
- a prefabricated welded cage 104 is shown in FIG. 1 .
- the prefabricated welded cage 104 includes a number of vertical reinforcing bars 106 .
- a continuous tie 108 extends around the vertical reinforcing bars 106 .
- the welded cage 104 includes a plurality of continuous ties 108 which are placed at vertical intervals around the vertical reinforcing bars 106 .
- the plurality of continuous ties 108 are spaced at even intervals along the height of the vertical reinforcing bars 106 .
- A. plurality of shear ties 110 extend generally horizontally between the vertical reinforcing bars 106 .
- the welded cage 104 is sized and shaped for shipping.
- the structure of one of the plurality of continuous ties 108 is shown in FIG. 2 .
- the continuous tie 108 shown in FIG. 2 is a single piece of reinforcing steel that forms a closed loop with, for example, ends that overlap.
- FIG. 3 a prior art design for rebar components in a wall structure is shown.
- a pair of horizontal bars 120 is connected to a pair of u-caps 118 at each end.
- This structure would need to be constructed using individual horizontal bars and u-caps on site and then carefully connected to each of the vertical reinforcing bars 106 . Installation of this prior art system would likely be expensive and time consuming.
- FIGS. 4 and 5 show how two prefabricated welded cages 104 B and 104 C may he installed at a work site.
- the two cages 104 B and 104 C are placed side-by-side as shown in FIG. 4 .
- a pair of lap bars 116 are connected between each of the adjacent continuous ties 108 B and 108 C.
- pairs of lap bars 116 are connected between them. Multiple cages may be connected in this manner.
- the pair of welded cages 104 B and 104 C are placed adjacent and parallel to each other for use in a single length of a concrete building wall.
- the plurality of lap bars 116 extend generally horizontally between overlapping adjacent ends of the pair of welded cages.
- each of the plurality of shear ties 110 have a hook end 112 and a flat end 114 .
- the plurality of shear ties 110 are arranged between the vertical reinforcing bars 106 in an alternating parallel pattern with the hook ends 112 of each adjacent shear tie facing in an opposite direction.
- FIG. 6 shows a prior art method of installing a section of wall, which requires a long horizontal bar 120 and u-caps 118 connecting the horizontal bars 120 at the ends of the components. This installation method has similar drawbacks to the prior art method shown in FIG. 3 .
- FIG. 7 shows a reinforcing steel structure 100 including a plurality of the one or more prefabricated, welded cages 104 .
- the reinforcing steel structure 100 has a corner pair of welded cages 104 A and 104 B which are placed adjacent and perpendicular to each other for use in two adjoining walls forming a corner of a concrete building wall.
- a plurality of u-caps 118 extend generally horizontally around adjacent ends of the pair of welded cages.
- the welded cages 104 A and 104 B meet at a corner generally denoted by 126 .
- welded cages 104 C and 104 D are adjacent corner pieces connected by a plurality of u-caps 118 .
- Welded cages 1048 and 104 C form a parallel pair of welded cages placed adjacent and parallel to each other to together form a structure for a single length of a concrete building wall.
- a plurality of lap bars 116 extend generally horizontally within the vertically reinforcing bars 106 and between overlapping adjacent ends of the parallel pair of welded cages 104 B and 1040 .
- various different combinations and configurations of welded cages 104 may be connected to form steel structures for concrete walls of various different configurations and sizes.
- FIG. 8 shows an embodiment of the steel structure 100 having walls with zones having a different configuration of shear ties 110 .
- shear ties 110 are placed with the hook ends 112 oriented in the same direction as each other and the shear bars 110 are placed at each end of the welded cages 104 A to 104 D.
- add bars 122 are used exclusively as the vertical reinforcing bars 106
- add bars 122 are used only at each end of the respective welded cages 104 A to 1048 .
- the shear ties 110 are placed between the add bars 122 .
- the darker vertical bars 122 are zone concentrated reinforcing bars and the lighter of the vertical bars 106 represent stress distributed reinforcing bars.
- FIG. 9 shows an embodiment of a portion of a steel structure having welded cages 104 C and 104 D.
- Hooked horizontal bars 124 are placed at the corner 126 where welded cages 1040 and 104 D are adjacent.
- Horizontal j-bars 116 are located inside the vertical reinforcing bars 106 and match the continuous ties 108 .
- the horizontal bars 124 are also closed ties.
- the j-bars 116 are embedded between the modular welded cages 104 C and 104 D and which may assist in preventing failure when concrete spalls under stress.
- FIG. 10 shows a steel structure 400 having a plurality of prefabricated welded cages 404 A to 404 D.
- Vertical reinforcing bars 406 all in the form of add bars 422 , lie between continuous ties 408 in each of the welded cages 404 A to 404 D.
- Shear ties 410 connect between the vertical reinforce bars 406 and are placed with the hooked ends 412 of adjacent shear ties 410 facing in opposite directions. Opposite the hooked ends 412 of each shear tie is a fiat end 414 .
- U-caps 418 provide a connection between corners 426 of adjacent welded cages 404 A and 404 B, as well as adjacent welded cages 404 C and 404 D. The embodiment shown in FIG.
- FIG. 10 is similar to the embodiment of reinforcing steel structure of FIG. 7 , except with the addition of a plurality of lap bars 416 extending generally horizontally within the vertical reinforcing bars 406 and between the corner pairs of welded cages 404 A and 4048 as well as welded cages 404 C and 404 D.
- the addition of the plurality of lap bars 416 may be preferred in cases where a seismic resistant design is required.
- the reinforcing steel structure 100 of FIGS. 1 4 , and 7 to 9 may be installed for use in a concrete building wall by the following method.
- the method of constructing the steel structure 400 in the embodiment shown in FIG. 10 is similar to the method of installing the steel structure 100 shown in FIG. 7 ,
- a plurality prefabricated, welded cages 104 are provided on site at a worksite.
- the plurality of prefabricated, welded cages are installed at a worksite where a concrete wall is to be made.
- Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a reinforcing steel structure. As shown in FIGS.
- the reinforcing bars installed between the welded cages 104 may include u-bars, lap bars or other rebar structures that allow for the communication of tension stress between the cages.
- concrete (not shown) is poured into the reinforcing steel structure 100 to form a concrete building wall.
- FIGS. 1 to 10 have certain dimensions, it will be understood that various difference dimensions of walls may be constructed, using different sizes of cages depending on the application.
- the size of the cages should be chosen to fall within transportation limits, which may be, for example, 12 feet by 12 feet by 60 feet. In this sense transportation limits means the size of module that can be readily accommodated within the existing size of conventional transport vehicle (truck, or train car) that may be used for shipping rebar. While at present the size as outlined above is suitable in some jurisdictions, it will be understood that the present invention comprehends adapting the size of the modular cages to meet whatever the local transportation limits might be.
- the present invention comprehends a modular approach and therefore in some cases depending upon the structural design, the equipment available on site to assemble multiple modules into compound cage assemblies the modules may be made smaller than the maximum size and yet dimensioned to be efficiently fit within the typical transportable volume.
- FIG. 11 shows a side view of two prefabricated welded beams 204 A and 204 B.
- the welded beams together form a reinforcing steel structure 200 ( FIG. 15 ) for use in a concrete building transfer or raft slab.
- a plurality of continuous ties 212 extend generally vertically around a top beam layer 206 having horizontal reinforcing bars and a bottom beam layer 208 having horizontal reinforcing bars.
- Each welded beam 204 A and 204 B is sized and shaped for shipping.
- the prefabricated welded beams 204 A and 204 B are installed between a top slab layer 214 and a bottom slab later 218 .
- the continuous ties 212 shown in FIG. 11 are a single piece of reinforcing steel that forms a closed loop.
- the components of the reinforcing steel structure 200 are shown in FIGS. 12-15 .
- the bottom slab layer 218 is shown in FIG. 12 .
- a plurality of bottom horizontal reinforcing bars 220 are installed parallel to one another.
- a prefabricated welded beam 204 is shown in FIG. 13 .
- the welded beam 204 has a plurality of vertical continuous ties 212 that extend around top and bottom beam layers 206 and 208 .
- the top beam layer 206 has a plurality of top horizontal reinforcing bars 210 .
- the bottom beam layer 208 has a plurality of bottom horizontal reinforcing bars 211 .
- the top and bottom horizontal reinforcing bars 210 and 211 are oriented lengthways along the welded beam 204 and are parallel with one another. Different orientations of the horizontal reinforcing bars may be used.
- FIG. 14 shows one of the steps in installing the welded beams 204 A and 204 B in a steel structure.
- the welded beams are placed side-by-side on top of the bottom slab layer 218 .
- the top slab layer 214 is then installed on top of the welded beams to form the steel structure 200 .
- the top horizontal reinforcing bars 210 of the top beam layer 206 lie adjacent to and in the same plane as the top horizontal reinforcing bars 216 of the top slab layer 214 , with the two layers oriented so that the plurality of horizontal reinforcing bars 216 of the top slab layer 214 are oriented generally perpendicularly to the horizontal reinforcing bars 210 of the top beam layer 206 .
- the bottom horizontal reinforcing bars 211 of the bottom beam layer 208 lie adjacent to and in the same plane as the top horizontal reinforcing bars 220 of the bottom slab layer 218 , with the two layers oriented so that plurality of horizontal reinforcing bars 220 of the bottom slab layer 218 are oriented generally perpendicularly to the horizontal reinforcing bars 211 of the bottom beam layer 208 . It will be understood that different orientations of each of the various horizontal reinforcing bars may be used.
- FIGS. 16 to 20 show a steel structure 300 ( FIG. 20 ) comprising a plurality of prefabricated welded beams 304 installed side-by-side between a bottom slab layer 318 ( FIG. 17 ) having horizontal reinforcing bars 320 and a top slab layer 314 ( FIG. 20 ) having horizontal reinforcing bars 316 .
- the prefabricated welded beams 304 are shown in more detail in FIG. 16 where the welded beams 304 each include a plurality of vertical continuous ties 312 which extend around a top beam layer 306 and a bottom beam layer 308 .
- the top beam layer 306 formed from a plurality of top horizontal reinforcing bars 310 and the bottom beam layer 308 being formed from a plurality of bottom horizontal reinforcing bars 311 .
- the embodiment of the steel structure 300 shown in FIGS. 16 to 20 is similar to the steel structure 200 shown in FIGS. 11 to 15 , except that the embodiment of the steel structure 300 includes a plurality of shear ties 322 extending generally vertically between the horizontal reinforcing bars 310 of the top beam layer 306 and the horizontal reinforcing bars 311 of the bottom beam layer 308 .
- the shear ties 322 include a hook end 324 and a flat end 326 .
- Each of the one or more prefabricated, welded beams 304 A. 304 B include shear ties 322 that are oriented with the hook ends 324 connected to the horizontal reinforcing bars 310 of the top beam layer 306 .
- the plurality of shear ties 322 form two parallel rows of shear ties 322 extending along a length of the one or more prefabricated, welded beams 304 A and 304 B.
- FIGS. 12 to 15 and 17 to 20 generally set out the steps in constructing a reinforcing steel structure 200 or 300 for use in a concrete building slab.
- the beams are assembled as units using a combination of welds and ties at intersections. The ratio between the number of ties and welds is adjusted as required due to loading and flexibility requirements.
- the process described herein has two layers of rebar in the top and bottom formed from the top and bottom beam layers and the top and bottom slab layers, a similar procedure may be used when there are more than two layers of rebar for the top and bottom mats.
- welded beams 204 are provided at a worksite.
- the beams preferably have dimensions equal to or less than 12 feet by 12 feet by 60 feet, in order to conform with transportation limits. The size of the beams may depend on the transportation limits in different jurisdictions.
- the plurality of prefabricated welded beams 204 may be assembled and welded at a separate facility from the worksite.
- the beams 204 may be delivered on site when the concrete slab structure is being constructed. By providing the beams 204 in a prefabricated form, the installation process on site may be simplified.
- the bottom slab layer 218 is installed as shown in FIG. 12 at a work site.
- each of the prefabricated, welded beams 204 are placed adjacent to one another on the bottom slab layer 218 .
- the bottom slab layer 218 and the beams 204 may be connected by a suitable combination of welding or wire ties.
- the top slab layer 214 is installed on the plurality of welded beams to form the reinforcing steel structure 200 .
- the top slab layer 214 and the beams are connected using welding or wire ties.
- concrete (not shown) is added to the reinforcing steel structure to form a concrete building transfer or raft slab.
- the beams are generally sturdy for transportation and installation.
- the rigidity of the beams 204 may allow them to be walked on and can provide a surface to stand on during installation.
- By providing the beams 204 in a completed form it may lessen the need for workers to install rebar components in confined spaces. Testing has shown that installation using modulated welded cages may reduce installation time by as much as half of the time compared to traditional methods.
- each of the connections allows each of the connections to be provided entirely by welding.
- the reinforcing steel in each of the welded cages and welded beams are joined using 100% welding, which may increase the strength of the prefabricated components compared to using wire ties.
- each of the one or more prefabricated, welded cages or beams have dimensions equal to or less than 12 feet by 12 feet by 60 feet or other suitable dimensions that may be required by transportation limits. Different sizes of welded beams may be constructed.
- the welded beams are sized and shaped to suit the profile of the transfer or raft slab. Variations of the size and shape may also be required since slabs may have steps or slopes on the top or bottom.
- the welded beams and welded cages are generally arranged on the transportation vehicles to fit as many as possible onto a single load.
- the amount loaded onto each vehicle also depends on the sequence of delivery, which should follow a logical order based on the order each component is installed.
- a load of welded beams or cages may also be combined with additional loads, such as loose bars to fully load a transport vehicle.
- the sequence of transportation may be of heightened important since there are frequently issues with the amount of free space on site.
- Welded cages generally are no wider than 12′ in width to meet certain transportation requirements and the length may be dependent on the length of wall.
- the welded cages may be sized and shaped to fit the least number of cages as possible in each wall in order to reduce the number of laps required when installing the cages. It may be beneficial to ensure that the wall cages are each the same size and there are a number of factors which may have an effect on the size and shape of a cage, and there may be variation from cage to cage. Factors which may dictate width of a welded cage may include the thickness of the walls, any additional openings in the walls and the intersections with other walls, etc.
- the welded cages and beams may be limited to being no more than 12′ wide in one direction, since the trailers are 8′ wide and the limit for the overhang is 2′ on each side. Trailers also come in different sizes, and in some jurisdictions, the maximum length may be 60′. Longer or wider assemblies than the maximums in a particular jurisdiction are possible with special permits and may require heavy duty cranes for positioning and offloading. Another factor for the size of welded cages and beams is crane lifting capacity onsite, since cages cannot be designed heavier than allowed by the crane lifting capacity, which may vary from site to site.
- the welded cages 104 and 404 are preferably made using vertical reinforcing bars which are welded inside a plurality of parallel horizontal continuous ties.
- the welded beams 204 and 304 are preferably made using top and bottom beam layers which are welded inside a plurality of vertical continuous ties.
- the prefabricated beams and cages described herein may be mass produced, since each component may be fabricated following a specific design.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
There is provided a reinforcing steel structure for use in a concrete building wall. The structure includes one or more prefabricated, welded cages having vertical reinforcing bars. A plurality of continuous ties extends around the vertical reinforcing bars and a plurality of shear ties extends generally horizontally between the vertical reinforcing bars. Each welded cage is sized and shaped for shipping and said structure can be formed onsite from a plurality of said cages lapped together. Concrete is added to the reinforcing steel structure to form a concrete building wall.
There is also provided a reinforcing steel structure for use in a concrete building transfer or raft slab. The structure includes one or more prefabricated, welded beams. The prefabricated, welded beams have a top beam layer and a bottom beam layer, each having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top and bottom beam layers. Each welded beam is sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together. Concrete is added to the reinforcing steel structure to form a concrete building slab.
Description
- This invention relates generally to the broad field of reinforced concrete and more particularly to the steel, or rebar used to reinforce the concrete. More particularly, this invention relates to methods and apparatus for constructing and installing rebar used in concrete construction.
- Reinforced concrete is a well known and widely used building material which is used in building, bridges, roads, tunnels and other structural construction projects. Essentially the concrete, which is strong in compression but has no strength in tension, is reinforced with steel rods which pass through the zones of tension in the structural element. Engineers design the structural components; calculate the forces which will be generated by the structure, which may be carrying dynamic or static loads or both; and then develop a rebar plan to provide enough rebar reinforcement in the regions of the concrete structure where tension forces may be created. The rebar plan often requires complex cages with rebar elements bent from, for example, a top surface to a bottom surface and then back to the top surface to accommodate the load pattern created in a beam supported by a column for example.
- Conventionally, rebar rods are transported individually to a work site and then assembled on site. In some cases they may be bent on site and in other cases they may be bent at the factory and merely assembled on site. Assembly means placing the rebar rods into a form which will then hold the liquid concrete which is poured into the form around the rebar. Once the concrete cures and hardens the forms can be removed and the structural element is ready for use.
- The rebar is typically provided with a textured outer surface to enable the concrete to better grip the steel bars. The assembly of the rebar into the forms is done with great care—the correct positioning of the rebar is required to ensure the structural element has the strength that it has been designed for. Each rebar element must be precisely located in the three dimensional space within the form to ensure appropriate load bearing capacity of the finished structural element. Thus the engineers provide the fabricators with exact rebar cage plans and designs and every rod is checked for correct positioning before any concrete is poured.
- The fabrication of the re-bar cage according to the detailed design specifications can be slow and tedious work. The rebar components are connected on site by workers using ties with wires. The rods themselves can be long and unwieldy. The position of the components each have to carefully measured to ensure that they are properly spaced and located and that they will be located at an appropriate depth within the concrete once the concrete is poured into the form. The entire process of installing the components on site can be time consuming, which in turns increases the costs of the projects. Delays in the construction of rebar cages can cause significant delays in the entire construction project since the installation of reinforced concrete will often be one of the first steps in a major building project. For example, in a building the concrete frame of the building must be in place before the windows and interior finishing can be attempted within the frame. Since the installation of the rebar components requires rodworkers and other workers to be present on site, any staffing issues may also cause delays in the overall project. Construction of rebar structures onsite also requires each structure to be custom made.
- Constructing rebar structures for raft and transfer slabs onsite is also awkward in that incomplete cage assemblies may lead to partially built cage structures that are shaky and hard to walk on, causing safety issues. Installation may also be more challenging where confined spaces exist during the construction of the slab layers. It may also be challenging to place rebar on slabs that are deeper than 1800 mm or approximately 6′ in depth. Slabs are typically 2′ to 12′ deep.
- Patent applications of general interest in the field of rebar include:
- U.S. Pat. No. 5,392,580 patented on Feb. 28, 1995;
- U.S. Pat. No. 8,381,479 patented on Feb. 26, 2013; and
- U.S. Appl. No. 2009;0014419 published on Jan. 15, 2009.
- What is desired is a simpler and more efficient way of constructing reinforced concrete structures.
- In an embodiment there is a modular reinforcing steel structure for use in a concrete building wall. The structure may comprise one or more prefabricated, welded modular cages having vertical reinforcing bars. The cages may be prefabricated in an offsite factory where there are the space, tools and workers to quickly and easily create the modular cages. There may be a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars. Each prefabricated welded cage may be sized and shaped for shipping and said structure may be quickly and easily formed onsite from a plurality of said modular cages lapped together.
- In another embodiment there is provided a method of constructing a reinforcing steel structure for use in a concrete building wall. A plurality of prefabricated, welded cages having vertical reinforcing bars are provided at a worksite. Each of the plurality of prefabricated, welded cages may have a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars. The plurality of prefabricated, welded cages may be installed at a worksite. Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a continuous reinforcing steel structure. Concrete is added to the reinforcing steel structure to form a concrete building wall.
- In another embodiment there is a reinforcing steel structure for use in a concrete building transfer or raft, slab. The structure comprises one or more prefabricated, welded beams. The prefabricated, welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer. Each welded beam may be sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together.
- In another embodiment there is a method of constructing a reinforcing steel structure for use in a concrete building slab. A plurality of prefabricated, welded beams may be provided at a worksite. The welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer. A bottom slab layer comprising a plurality of horizontal reinforcing bars may be installed. The plurality of prefabricated, welded beams may be installed adjacent to one another on the bottom slab layer. A top slab layer comprising a plurality of horizontal reinforcing bars is installed on the plurality of welded beams to form a reinforcing steel structure. Concrete is poured around the reinforcing steel structure and permitted to cure to form a concrete building slab.
- Reference will now be made by way of example only to preferred embodiments of the invention by reference to the following drawings in which:
-
FIG. 1 is a top view of an embodiment of a prefabricated, welded cage for a heavy wall; -
FIG. 2 is a top view of an embodiment of a continuous tie for use in a pre-fabricated, welded cage; -
FIG. 3 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure; -
FIG. 4 is a top view of an embodiment having two prefabricated, welded cages for a heavy wall; -
FIG. 5 is a top view showing a pair of lap bars connecting two continuous ties; -
FIG. 6 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure; -
FIG. 7 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages; -
FIG. 8 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in walls with zones; -
FIG. 9 is a top view of a section of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in a wall with zones; -
FIG. 10 is a top view of an embodiment of a steel structure having a plurality of prefabricated, welded cages. -
FIG. 11 is a side view of an embodiment having a pair of prefabricated welded beam for use in a transfer slab or raft slab; -
FIG. 12 is a perspective view of an embodiment of a bottom slab layer ofFIG. 11 for a transfer slab or raft slab; -
FIG. 13 is a perspective view of an embodiment of a prefabricated, welded beam ofFIG. 11 for installation in a transfer slab or raft slab; -
FIG. 14 is a perspective view of an embodiment ofFIG. 11 having a pair of prefabricated, welded beams installed on a bottom slab layer; -
FIG. 15 is a perspective view of an embodiment ofFIG. 11 of a top slab layer installed on top of a pair of prefabricated, welded beams; -
FIG. 16 is a side view of an embodiment having a pair of prefabricated, welded beams having shear ties; -
FIG. 17 is a perspective view of an embodiment of a bottom slab layer ofFIG. 16 ; -
FIG. 18 is a perspective view of an embodiment of a prefabricated, welded beam ofFIG. 16 for a transfer slab or raft slab; -
FIG. 19 is a perspective view of an embodiment of a steel structure having a pair of prefabricated, welded beams ofFIG. 16 installed on a bottom slab layer; and -
FIG. 20 is a perspective view of an embodiment of a steel structure ofFIG. 16 having a top slab layer installed on a pair of prefabricated, welded beams. - A prefabricated welded
cage 104 is shown inFIG. 1 . The prefabricated weldedcage 104 includes a number of vertical reinforcing bars 106. Acontinuous tie 108 extends around the vertical reinforcing bars 106. Although only one continuous tie is shown inFIG. 1 , it will be understood that the weldedcage 104 includes a plurality ofcontinuous ties 108 which are placed at vertical intervals around the vertical reinforcing bars 106. Preferably, the plurality ofcontinuous ties 108 are spaced at even intervals along the height of the vertical reinforcing bars 106. A. plurality ofshear ties 110 extend generally horizontally between the vertical reinforcing bars 106. The weldedcage 104 is sized and shaped for shipping. - The structure of one of the plurality of
continuous ties 108 is shown inFIG. 2 . Thecontinuous tie 108 shown inFIG. 2 is a single piece of reinforcing steel that forms a closed loop with, for example, ends that overlap. - In
FIG. 3 , a prior art design for rebar components in a wall structure is shown. A pair ofhorizontal bars 120 is connected to a pair ofu-caps 118 at each end. This structure would need to be constructed using individual horizontal bars and u-caps on site and then carefully connected to each of the vertical reinforcing bars 106. Installation of this prior art system would likely be expensive and time consuming. -
FIGS. 4 and 5 show how two prefabricated welded 104B and 104C may he installed at a work site. The twocages 104B and 104C are placed side-by-side as shown incages FIG. 4 . As shown inFIG. 5 , a pair of lap bars 116 are connected between each of the adjacent 108B and 108C. For each of the plurality ofcontinuous ties 108B and 108C in each of thecontinuous ties 104B and 104C, pairs of lap bars 116 are connected between them. Multiple cages may be connected in this manner. The pair of weldedcages 104B and 104C are placed adjacent and parallel to each other for use in a single length of a concrete building wall. The plurality of lap bars 116 extend generally horizontally between overlapping adjacent ends of the pair of welded cages.cages - As shown in
FIG. 4 , each of the plurality ofshear ties 110 have ahook end 112 and aflat end 114. In the embodiment shown inFIG. 4 , the plurality ofshear ties 110 are arranged between the vertical reinforcingbars 106 in an alternating parallel pattern with the hook ends 112 of each adjacent shear tie facing in an opposite direction. -
FIG. 6 shows a prior art method of installing a section of wall, which requires a longhorizontal bar 120 and u-caps 118 connecting thehorizontal bars 120 at the ends of the components. This installation method has similar drawbacks to the prior art method shown inFIG. 3 . -
FIG. 7 shows a reinforcingsteel structure 100 including a plurality of the one or more prefabricated, weldedcages 104. In this case there are shown four welded 104A, 104B, 104C, and 104D. The reinforcingcages steel structure 100 has a corner pair of welded 104A and 104B which are placed adjacent and perpendicular to each other for use in two adjoining walls forming a corner of a concrete building wall. A plurality ofcages u-caps 118 extend generally horizontally around adjacent ends of the pair of welded cages. The welded 104A and 104B meet at a corner generally denoted by 126. Similarly, weldedcages 104C and 104D are adjacent corner pieces connected by a plurality ofcages u-caps 118. Weldedcages 1048 and 104C form a parallel pair of welded cages placed adjacent and parallel to each other to together form a structure for a single length of a concrete building wall. A plurality of lap bars 116 extend generally horizontally within the vertically reinforcingbars 106 and between overlapping adjacent ends of the parallel pair of weldedcages 104B and 1040. As will be understood, various different combinations and configurations of weldedcages 104 may be connected to form steel structures for concrete walls of various different configurations and sizes. -
FIG. 8 shows an embodiment of thesteel structure 100 having walls with zones having a different configuration of shear ties 110. In the embodiment shown inFIG. 8 ,shear ties 110 are placed with the hook ends 112 oriented in the same direction as each other and the shear bars 110 are placed at each end of the weldedcages 104A to 104D. Also, although in the embodiment shown inFIG. 7 , addbars 122 are used exclusively as the vertical reinforcingbars 106, in the embodiment shown inFIG. 8 , addbars 122 are used only at each end of the respective weldedcages 104A to 1048. The shear ties 110 are placed between the add bars 122. The darkervertical bars 122 are zone concentrated reinforcing bars and the lighter of thevertical bars 106 represent stress distributed reinforcing bars. -
FIG. 9 shows an embodiment of a portion of a steel structure having welded 104C and 104D. Hookedcages horizontal bars 124 are placed at thecorner 126 where weldedcages 1040 and 104D are adjacent. Horizontal j-bars 116 are located inside the vertical reinforcingbars 106 and match thecontinuous ties 108. Thehorizontal bars 124 are also closed ties. The j-bars 116 are embedded between the modular welded 104C and 104D and which may assist in preventing failure when concrete spalls under stress.cages -
FIG. 10 shows asteel structure 400 having a plurality of prefabricated weldedcages 404A to 404D. Vertical reinforcingbars 406, all in the form of addbars 422, lie betweencontinuous ties 408 in each of the weldedcages 404A to 404D. Shear ties 410 connect between the vertical reinforcebars 406 and are placed with the hooked ends 412 ofadjacent shear ties 410 facing in opposite directions. Opposite the hooked ends 412 of each shear tie is afiat end 414.U-caps 418 provide a connection betweencorners 426 of adjacent welded 404A and 404B, as well as adjacent weldedcages 404C and 404D. The embodiment shown incages FIG. 10 is similar to the embodiment of reinforcing steel structure ofFIG. 7 , except with the addition of a plurality of lap bars 416 extending generally horizontally within the vertical reinforcingbars 406 and between the corner pairs of weldedcages 404A and 4048 as well as welded 404C and 404D. The addition of the plurality of lap bars 416 may be preferred in cases where a seismic resistant design is required.cages - The reinforcing
steel structure 100 ofFIGS. 1 4, and 7 to 9, may be installed for use in a concrete building wall by the following method. The method of constructing thesteel structure 400 in the embodiment shown inFIG. 10 is similar to the method of installing thesteel structure 100 shown inFIG. 7 , A plurality prefabricated, weldedcages 104 are provided on site at a worksite. The plurality of prefabricated, welded cages are installed at a worksite where a concrete wall is to be made. Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a reinforcing steel structure. As shown inFIGS. 1, 4 and 7 to 9 , the reinforcing bars installed between the weldedcages 104 may include u-bars, lap bars or other rebar structures that allow for the communication of tension stress between the cages. As a final step, concrete (not shown) is poured into the reinforcingsteel structure 100 to form a concrete building wall. - Although the walls shown in
FIGS. 1 to 10 have certain dimensions, it will be understood that various difference dimensions of walls may be constructed, using different sizes of cages depending on the application. The size of the cages should be chosen to fall within transportation limits, which may be, for example, 12 feet by 12 feet by 60 feet. In this sense transportation limits means the size of module that can be readily accommodated within the existing size of conventional transport vehicle (truck, or train car) that may be used for shipping rebar. While at present the size as outlined above is suitable in some jurisdictions, it will be understood that the present invention comprehends adapting the size of the modular cages to meet whatever the local transportation limits might be. Further, while the above noted size limit is the maximum size, the present invention comprehends a modular approach and therefore in some cases depending upon the structural design, the equipment available on site to assemble multiple modules into compound cage assemblies the modules may be made smaller than the maximum size and yet dimensioned to be efficiently fit within the typical transportable volume. -
FIG. 11 shows a side view of two prefabricated welded 204A and 204B. The welded beams together form a reinforcing steel structure 200 (beams FIG. 15 ) for use in a concrete building transfer or raft slab. A plurality ofcontinuous ties 212 extend generally vertically around atop beam layer 206 having horizontal reinforcing bars and abottom beam layer 208 having horizontal reinforcing bars. Each welded 204A and 204B is sized and shaped for shipping. As shown inbeam FIG. 11 , the prefabricated welded 204A and 204B are installed between abeams top slab layer 214 and a bottom slab later 218. Thecontinuous ties 212 shown inFIG. 11 are a single piece of reinforcing steel that forms a closed loop. - The components of the reinforcing steel structure 200 are shown in
FIGS. 12-15 . Thebottom slab layer 218 is shown inFIG. 12 . A plurality of bottom horizontal reinforcingbars 220 are installed parallel to one another. - A prefabricated welded
beam 204 is shown inFIG. 13 . The weldedbeam 204 has a plurality of verticalcontinuous ties 212 that extend around top and bottom beam layers 206 and 208. Thetop beam layer 206 has a plurality of top horizontal reinforcingbars 210. Thebottom beam layer 208 has a plurality of bottom horizontal reinforcingbars 211. The top and bottom horizontal reinforcing 210 and 211 are oriented lengthways along the weldedbars beam 204 and are parallel with one another. Different orientations of the horizontal reinforcing bars may be used. -
FIG. 14 shows one of the steps in installing the welded 204A and 204B in a steel structure. The welded beams are placed side-by-side on top of thebeams bottom slab layer 218. As shown inFIG. 15 , thetop slab layer 214 is then installed on top of the welded beams to form the steel structure 200. As shown inFIG. 15 , the top horizontal reinforcingbars 210 of thetop beam layer 206 lie adjacent to and in the same plane as the top horizontal reinforcing bars 216 of thetop slab layer 214, with the two layers oriented so that the plurality of horizontal reinforcing bars 216 of thetop slab layer 214 are oriented generally perpendicularly to the horizontal reinforcingbars 210 of thetop beam layer 206. Similarly, the bottom horizontal reinforcingbars 211 of thebottom beam layer 208 lie adjacent to and in the same plane as the top horizontal reinforcingbars 220 of thebottom slab layer 218, with the two layers oriented so that plurality of horizontal reinforcingbars 220 of thebottom slab layer 218 are oriented generally perpendicularly to the horizontal reinforcingbars 211 of thebottom beam layer 208. It will be understood that different orientations of each of the various horizontal reinforcing bars may be used. -
FIGS. 16 to 20 show a steel structure 300 (FIG. 20 ) comprising a plurality of prefabricated weldedbeams 304 installed side-by-side between a bottom slab layer 318 (FIG. 17 ) having horizontal reinforcingbars 320 and a top slab layer 314 (FIG. 20 ) having horizontal reinforcingbars 316. The prefabricated weldedbeams 304 are shown in more detail inFIG. 16 where the weldedbeams 304 each include a plurality of verticalcontinuous ties 312 which extend around atop beam layer 306 and abottom beam layer 308. Thetop beam layer 306 formed from a plurality of top horizontal reinforcingbars 310 and thebottom beam layer 308 being formed from a plurality of bottom horizontal reinforcingbars 311. - The embodiment of the
steel structure 300 shown inFIGS. 16 to 20 is similar to the steel structure 200 shown inFIGS. 11 to 15 , except that the embodiment of thesteel structure 300 includes a plurality ofshear ties 322 extending generally vertically between the horizontal reinforcingbars 310 of thetop beam layer 306 and the horizontal reinforcingbars 311 of thebottom beam layer 308. The shear ties 322 include ahook end 324 and aflat end 326. Each of the one or more prefabricated, welded beams 304A. 304B includeshear ties 322 that are oriented with the hook ends 324 connected to the horizontal reinforcingbars 310 of thetop beam layer 306. As shown inFIG. 16 , the plurality ofshear ties 322 form two parallel rows ofshear ties 322 extending along a length of the one or more prefabricated, welded beams 304A and 304B. -
FIGS. 12 to 15 and 17 to 20 generally set out the steps in constructing a reinforcingsteel structure 200 or 300 for use in a concrete building slab. Reference will be made hereafter to the embodiment of the steel structure 200 shown inFIGS. 12 to 15 , but the same method installation applies to thesteel structure 300 inFIGS. 17 to 20 . Generally, the beams are assembled as units using a combination of welds and ties at intersections. The ratio between the number of ties and welds is adjusted as required due to loading and flexibility requirements. Although the process described herein has two layers of rebar in the top and bottom formed from the top and bottom beam layers and the top and bottom slab layers, a similar procedure may be used when there are more than two layers of rebar for the top and bottom mats. All welding may be done in accordance with local welding standards. Different numbers, orientations and sizes of welded beams may be used in a steel structure depending on the application desired. Initially, a plurality of prefabricated, weldedbeams 204 are provided at a worksite. The beams preferably have dimensions equal to or less than 12 feet by 12 feet by 60 feet, in order to conform with transportation limits. The size of the beams may depend on the transportation limits in different jurisdictions. The plurality of prefabricated weldedbeams 204 may be assembled and welded at a separate facility from the worksite. Thebeams 204 may be delivered on site when the concrete slab structure is being constructed. By providing thebeams 204 in a prefabricated form, the installation process on site may be simplified. Thebottom slab layer 218 is installed as shown inFIG. 12 at a work site. Next, each of the prefabricated, weldedbeams 204 are placed adjacent to one another on thebottom slab layer 218. Thebottom slab layer 218 and thebeams 204 may be connected by a suitable combination of welding or wire ties. After the welded beams are installed, thetop slab layer 214 is installed on the plurality of welded beams to form the reinforcing steel structure 200. Thetop slab layer 214 and the beams are connected using welding or wire ties. Finally, concrete (not shown) is added to the reinforcing steel structure to form a concrete building transfer or raft slab. - By installing the steel structure 200 using modular components in the form of prefabricated welded
beams 204, the beams are generally sturdy for transportation and installation. The rigidity of thebeams 204 may allow them to be walked on and can provide a surface to stand on during installation. By providing thebeams 204 in a completed form, it may lessen the need for workers to install rebar components in confined spaces. Testing has shown that installation using modulated welded cages may reduce installation time by as much as half of the time compared to traditional methods. - The prefabrication of welded cages and beams allows each of the connections to be provided entirely by welding. Preferably, the reinforcing steel in each of the welded cages and welded beams are joined using 100% welding, which may increase the strength of the prefabricated components compared to using wire ties. Preferably, each of the one or more prefabricated, welded cages or beams have dimensions equal to or less than 12 feet by 12 feet by 60 feet or other suitable dimensions that may be required by transportation limits. Different sizes of welded beams may be constructed. The welded beams are sized and shaped to suit the profile of the transfer or raft slab. Variations of the size and shape may also be required since slabs may have steps or slopes on the top or bottom. The welded beams and welded cages are generally arranged on the transportation vehicles to fit as many as possible onto a single load. The amount loaded onto each vehicle also depends on the sequence of delivery, which should follow a logical order based on the order each component is installed. A load of welded beams or cages may also be combined with additional loads, such as loose bars to fully load a transport vehicle. The sequence of transportation may be of heightened important since there are frequently issues with the amount of free space on site.
- Welded cages generally are no wider than 12′ in width to meet certain transportation requirements and the length may be dependent on the length of wall. The welded cages may be sized and shaped to fit the least number of cages as possible in each wall in order to reduce the number of laps required when installing the cages. It may be beneficial to ensure that the wall cages are each the same size and there are a number of factors which may have an effect on the size and shape of a cage, and there may be variation from cage to cage. Factors which may dictate width of a welded cage may include the thickness of the walls, any additional openings in the walls and the intersections with other walls, etc.
- From a delivery point of view, in some jurisdictions, the welded cages and beams may be limited to being no more than 12′ wide in one direction, since the trailers are 8′ wide and the limit for the overhang is 2′ on each side. Trailers also come in different sizes, and in some jurisdictions, the maximum length may be 60′. Longer or wider assemblies than the maximums in a particular jurisdiction are possible with special permits and may require heavy duty cranes for positioning and offloading. Another factor for the size of welded cages and beams is crane lifting capacity onsite, since cages cannot be designed heavier than allowed by the crane lifting capacity, which may vary from site to site.
- Although the prefabricated welded
cages 104 and 404, and the prefabricated welded 204 and 304 are shown with particular arrangements of reinforcing steel, it will be understood that various modifications may be made which allow for the construction of prefabricated welded components offsite which may be transported in a completed form. The weldedbeams cages 104 and 404 are preferably made using vertical reinforcing bars which are welded inside a plurality of parallel horizontal continuous ties. The welded beams 204 and 304 are preferably made using top and bottom beam layers which are welded inside a plurality of vertical continuous ties. - The prefabricated beams and cages described herein may be mass produced, since each component may be fabricated following a specific design.
- Although the foregoing description has been made with respect to preferred embodiments of the present invention it will be understood by those skilled in the art that many variations and alterations are possible. Some of these variations have been discussed above and others will be apparent to those skilled in the art.
- in the claims, the word “comprising” is used in its inclusive sense and does not exclude the possibility of other elements being present. The indefinite article “a/an” before a claim feature does not exclude more than one of the feature being present unless it is clear from the context that only a single element is intended.
Claims (9)
1-8. (canceled)
9. A reinforcing steel structure for use in a concrete building transfer or raft slab, the structure comprising:
one or more prefabricated, welded beams comprising:
a top beam layer having horizontal reinforcing bars,
a bottom beam layer having horizontal reinforcing bars, and
a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer; and
wherein each welded beam is sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together.
10. The reinforcing steel structure of claim 9 , wherein the structure further comprises:
a plurality of prefabricated, welded beams lapped together;
a top slab layer comprising a plurality of horizontal reinforcing bars oriented generally perpendicularly to the horizontal reinforcing bars of the top beam layer;
a bottom slab layer comprising a plurality of horizontal reinforcing bars oriented generally perpendicularly to the horizontal reinforcing bars of the bottom beam layer;
wherein the structure can be formed onsite by installing the bottom slab layer, installing the plurality of welded beams on the bottom slab layer and installing the top slab layer on the plurality of welded beams.
11. The reinforcing steel structure of claim 9 , wherein each of the one or more prefabricated, welded beams further comprises a plurality of shear ties extending generally vertically between the horizontal reinforcing bars of the top beam layer and the horizontal reinforcing bars of the bottom beam layer.
12. The reinforcing steel structure of claim 11 , wherein each of the one or more prefabricated, welded beams further comprises the plurality of shear ties being oriented with the hook ends connected to the horizontal reinforcing bars of the top layer slab.
13. The reinforcing steel structure of claim 12 , wherein the plurality of shear ties further comprise two or more parallel rows of shear ties extending along a length of the one or more prefabricated, welded beams.
14. The reinforcing steel structure of claim 9 , wherein each of the one or more prefabricated, welded beams have dimensions equal to or less than 12 feet by 12 feet by 60 feet.
15. The reinforcing steel structure of claim 9 for use in a concrete transfer slab or a concrete raft slab.
16. A method of constructing a reinforcing steel structure for use in a concrete building slab, comprising:
providing a plurality of prefabricated, welded beams at a worksite, the welded beams comprising:
a top beam layer having horizontal reinforcing bars,
a bottom beam layer having horizontal reinforcing bars, and
a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer;
installing a bottom slab layer comprising a plurality of horizontal reinforcing bars;
installing the plurality of prefabricated, welded beams adjacent to one another on the bottom slab layer; and
installing a top slab layer comprising a plurality of horizontal reinforcing bars on the plurality of welded beams to form a reinforcing steel structure; and
adding concrete to the reinforcing steel structure to form a concrete building slab.
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US14/517,113 US20170321421A9 (en) | 2014-10-16 | 2014-10-17 | Prefabricated modular rebar modules and methods of using the same |
| US14/874,545 US20160108618A1 (en) | 2014-10-17 | 2015-10-05 | Prefabricated modular rebar modules and methods of using the same |
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CA2867964 | 2014-10-16 | ||
| CA2867964A CA2867964C (en) | 2014-10-16 | 2014-10-16 | Prefabricated modular rebar modules and methods of using the same |
| US14/517,113 US20170321421A9 (en) | 2014-10-16 | 2014-10-17 | Prefabricated modular rebar modules and methods of using the same |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US14/874,545 Division US20160108618A1 (en) | 2014-10-17 | 2015-10-05 | Prefabricated modular rebar modules and methods of using the same |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| US20160108619A1 US20160108619A1 (en) | 2016-04-21 |
| US20170321421A9 true US20170321421A9 (en) | 2017-11-09 |
Family
ID=52471934
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US14/517,113 Abandoned US20170321421A9 (en) | 2014-10-16 | 2014-10-17 | Prefabricated modular rebar modules and methods of using the same |
Country Status (2)
| Country | Link |
|---|---|
| US (1) | US20170321421A9 (en) |
| CA (2) | CA2892837C (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20190040977A1 (en) * | 2015-02-26 | 2019-02-07 | Engineered Wire Products, Inc. | Concrete Reinforcement Elements and Structures |
| CN115478553A (en) * | 2022-09-23 | 2022-12-16 | 中国五冶集团有限公司 | Support frame for raft casting |
Families Citing this family (55)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2539709A (en) * | 2015-06-25 | 2016-12-28 | Render Stephen | Device for splicing reinforcement cages |
| PL3535460T3 (en) * | 2016-11-03 | 2024-03-18 | Midland Steel Reinforcement Supplies Limited | Reinforcing framework and slab design |
| CN106996161A (en) * | 2017-05-31 | 2017-08-01 | 桑大勇 | A kind of steel bar girder sandwich precast floor slab |
| CN107558631A (en) * | 2017-08-30 | 2018-01-09 | 中建七局安装工程有限公司 | One kind wears muscle anchoring concrete-filled steel tube shear wall fabricated construction |
| CN107542185B (en) * | 2017-09-30 | 2023-12-01 | 新疆玉龙河建设工程有限公司 | Bending shear type combined key slot connecting structure of assembly frame shear structure and assembly method |
| CN108252420A (en) * | 2017-12-19 | 2018-07-06 | 浙江绿筑集成科技有限公司 | A kind of connection method of no support type laminated floor slab and PEC shear walls |
| CN108005265B (en) * | 2017-12-20 | 2023-06-09 | 中冶建筑研究总院有限公司 | Multilayer prefabricated steel reinforced concrete shear wall structure and preparation and construction methods thereof |
| CN108179826B (en) * | 2018-02-05 | 2023-10-13 | 哈密康建工程施工有限责任公司 | Pin bolt type shear wall horizontal connection structure and manufacturing method and construction method thereof |
| CN108265850A (en) * | 2018-02-26 | 2018-07-10 | 广东省建筑科学研究院集团股份有限公司 | A kind of box compound shear wall of double L-shaped rectangle steel |
| CN108265867A (en) * | 2018-03-16 | 2018-07-10 | 浙江大学建筑设计研究院有限公司 | A kind of plate end and plate side do not go out the bidirectional laminated slab bottom plate and its construction method of muscle |
| CN108487542B (en) * | 2018-03-16 | 2020-07-28 | 杭萧钢构股份有限公司 | Method for calculating stable bearing capacity of steel tube concrete bundle combined member |
| CN108442534B (en) * | 2018-05-09 | 2024-03-19 | 李藏柱 | A connection node between steel columns/beams and prefabricated panels and its construction method |
| CN114214961B (en) * | 2018-05-18 | 2024-10-15 | 中交路桥华南工程有限公司 | Integral-lowering underwater bearing platform mounting structure |
| CN108755946B (en) * | 2018-07-10 | 2023-08-11 | 福州大学 | Partially prefabricated bolt connection assembly type beam column node structure and construction method thereof |
| CN109972656B (en) * | 2018-08-09 | 2024-08-02 | 中铁二十二局集团第三工程有限公司 | Overlapped assembly type construction comprehensive pipe gallery and construction method thereof |
| CN109296140B (en) * | 2018-11-27 | 2024-12-31 | 中建海龙科技有限公司 | Multi-directional steel bar connection device |
| EP3670775B1 (en) * | 2018-12-17 | 2022-01-26 | Ed. Züblin Aktiengesellschaft | Method for producing a wall of a structure made of concrete and a wall of a concrete structure |
| CN109898691B (en) * | 2019-02-27 | 2024-04-12 | 苏州科技大学 | A damping grounding type assembled reinforced concrete tuned mass damping wall |
| CN109881790B (en) * | 2019-03-09 | 2024-04-16 | 中铁建设集团有限公司 | Connection structure and installation method of additional movable steel bars for steel bar formwork integrated wall |
| CN109944358B (en) * | 2019-04-04 | 2024-05-03 | 河南绿建建筑科技有限公司 | L-shaped node of stirrup bent anchor type steel concrete combined pipe |
| CN109944335B (en) * | 2019-04-04 | 2024-05-03 | 河南绿建建筑科技有限公司 | Frame and shear wall core tube combined assembly type structure system |
| CN110080394B (en) * | 2019-04-23 | 2024-05-28 | 中铁第四勘察设计院集团有限公司 | Connecting structure and connecting method of assembled prefabricated components |
| CN110029739B (en) * | 2019-05-07 | 2024-11-22 | 河南绿建建筑科技有限公司 | Transverse reinforcement and studs combined with embedded wall beam connection nodes |
| CN110258773A (en) * | 2019-06-13 | 2019-09-20 | 刘全义 | Thin-wall shear wall prefabricated building and special mold for prefabricated wall panels and construction method |
| CN110424603A (en) * | 2019-07-18 | 2019-11-08 | 南京长江都市建筑设计股份有限公司 | A kind of two-way prefabricated superimposed sheet structure of close spelling formula |
| CN110258302B (en) * | 2019-07-31 | 2024-02-09 | 福州大学 | Semi-prefabricated UHPC shell superposed capping beam and prefabricated pier stud connection structure and construction method thereof |
| US11352786B2 (en) * | 2019-08-19 | 2022-06-07 | WSP USA, Inc. | Constructing buildings with modular wall structure |
| CN110499849A (en) * | 2019-08-28 | 2019-11-26 | 浙江精工钢结构集团有限公司 | A kind of multi-cavity steel reinforced concrete compound shear wall of square steel tube composition |
| CN110847354A (en) * | 2019-10-30 | 2020-02-28 | 上海市政工程设计研究总院(集团)有限公司 | Reinforced concrete prefabricated bracket node and mounting method |
| CN110924292B (en) * | 2019-11-26 | 2024-06-07 | 福州大学 | Reinforced dumbbell type composite column of stainless steel reinforced concrete plate and construction method thereof |
| CN111186017B (en) * | 2020-02-19 | 2024-11-12 | 中交路桥建设有限公司 | Modular formwork for openwork bridge panels |
| CN111501833A (en) * | 2020-03-30 | 2020-08-07 | 中国建筑第八工程局有限公司 | Reinforced structure of thick raft and its inverse construction method |
| CN111485645B (en) * | 2020-05-14 | 2025-03-14 | 中恒建设集团有限公司 | A local prestressed connection structure of assembled concrete shear wall |
| CN111691574B (en) * | 2020-06-24 | 2022-03-29 | 江苏中营仝建装配建筑科技有限公司 | Prefabricated assembly type shear wall vertical joint connecting structure and construction method thereof |
| CN112854028A (en) * | 2021-03-09 | 2021-05-28 | 上海市城市建设设计研究总院(集团)有限公司 | Hollow slab beam-changing hinge joint connecting structure and construction method thereof |
| CN113026434A (en) * | 2021-03-12 | 2021-06-25 | 中铁二十三局集团轨道交通工程有限公司 | Steel plate and wire mesh structure concrete track slab |
| CN113047426B (en) * | 2021-05-18 | 2022-08-09 | 中国十九冶集团有限公司 | Steel bar setting method for large concrete funnel opening |
| CN113445534B (en) * | 2021-08-03 | 2024-07-19 | 山西建筑工程集团有限公司 | Multilayer steel bar construction structure and construction method for different elevations of super-thick raft foundation |
| CN113737993A (en) * | 2021-09-16 | 2021-12-03 | 陕西建工第五建设集团有限公司 | Shear wall structure with interlayer beams and aluminum-wood formwork construction method thereof |
| TWI777811B (en) * | 2021-10-13 | 2022-09-11 | 潤弘精密工程事業股份有限公司 | Tie bar for shear wall, shear wall and method for constructing the same |
| CN114673374A (en) * | 2021-12-02 | 2022-06-28 | 东莞市彩丽建筑维护技术有限公司 | Structure and method for prevention and control of building disasters by reinforcing external walls with section steel |
| CN114046157B (en) * | 2022-01-12 | 2022-03-29 | 北京科技大学 | A kind of downward horizontal approach filling method large-span false roof structure and construction method |
| CN114250793B (en) * | 2022-01-19 | 2025-09-26 | 中铁上海设计院集团有限公司 | A connection structure for the first precast concrete support system of a foundation pit |
| TWI848271B (en) * | 2022-02-24 | 2024-07-11 | 承錡鋼鐵股份有限公司 | Pre-assembled raft foundation and construction method thereof |
| CN114622478B (en) * | 2022-03-31 | 2023-09-12 | 山西省交通规划勘察设计院有限公司 | Reinforced steel structure bridge prefabrication assembly |
| CN114776064B (en) * | 2022-04-12 | 2023-09-26 | 中原城建集团有限公司 | Reinforcing component for assembled wall |
| CN114753315B (en) * | 2022-04-19 | 2024-04-26 | 中国葛洲坝集团第二工程有限公司 | Construction method for replacing reinforcing steel bars with glass fiber reinforced plastic bars for dam panels |
| CN114718123B (en) * | 2022-04-28 | 2023-10-24 | 中国一冶集团有限公司 | Butt joint construction method for prefabricated top pipe gallery and cast-in-situ pipe gallery |
| CN115012534B (en) * | 2022-06-01 | 2024-04-05 | 中冶(上海)钢结构科技有限公司 | Method for installing complex embedded part in steel rib column |
| CN114919063B (en) * | 2022-06-08 | 2023-05-26 | 中交第二航务工程局有限公司 | Method for assembling steel reinforcement framework of core box type box girder |
| CN115434353A (en) * | 2022-09-30 | 2022-12-06 | 上海核工程研究设计院有限公司 | Design and construction method of fabricated nuclear island raft foundation reinforcement truss structure |
| CN115434363B (en) * | 2022-09-30 | 2023-06-02 | 武汉誉城千里建工有限公司 | Retaining wall construction method suitable for repeated excavation backfill working condition |
| CN115680711B (en) * | 2022-10-26 | 2025-10-21 | 中交第三公路工程局有限公司 | Modular purlin structure for tunnel construction |
| CN115897906B (en) * | 2022-12-07 | 2025-03-04 | 江苏博森建筑设计有限公司 | Prefabricated wall reinforcement positioning auxiliary device and prefabricated shear wall construction method |
| CN119122293B (en) * | 2024-11-07 | 2025-10-31 | 中铁建工集团有限公司 | Narrow and small space reinforcing bar binding apparatus |
-
2014
- 2014-10-16 CA CA2892837A patent/CA2892837C/en active Active
- 2014-10-16 CA CA2867964A patent/CA2867964C/en active Active
- 2014-10-17 US US14/517,113 patent/US20170321421A9/en not_active Abandoned
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20190040977A1 (en) * | 2015-02-26 | 2019-02-07 | Engineered Wire Products, Inc. | Concrete Reinforcement Elements and Structures |
| US20200200297A1 (en) * | 2015-02-26 | 2020-06-25 | Engineered Wire Products, Inc. | Concrete Reinforcement Elements and Structures |
| CN115478553A (en) * | 2022-09-23 | 2022-12-16 | 中国五冶集团有限公司 | Support frame for raft casting |
Also Published As
| Publication number | Publication date |
|---|---|
| US20160108619A1 (en) | 2016-04-21 |
| CA2892837C (en) | 2016-07-12 |
| CA2892837A1 (en) | 2015-02-06 |
| CA2867964A1 (en) | 2015-02-06 |
| CA2867964C (en) | 2016-04-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA2867964C (en) | Prefabricated modular rebar modules and methods of using the same | |
| US20160108618A1 (en) | Prefabricated modular rebar modules and methods of using the same | |
| US11598056B2 (en) | Module for a structure | |
| US7596909B1 (en) | Prefabricated building having a pre-cast concrete chain wall foundation | |
| JP7082522B2 (en) | Precast synthetic deck joint structure | |
| CN103140639A (en) | A building structure | |
| KR101614842B1 (en) | frame system of buildings using the pc-column with overhanging beam applicable various span without increase of story-height | |
| AU2021103539A4 (en) | A flooring panel, system and method for constructing a fire-rated suspended floor | |
| US20190277031A1 (en) | Reinforcing framework and slab design | |
| KR101324884B1 (en) | Hybrid building construction method combining dry type and wet type | |
| KR20130081850A (en) | Caisson having assembly-type or single block-type base slab, and manufacturing system and method thereof | |
| CN101809240B (en) | Temporary post joint, temporary structure, and slab constructing method for multiple floors | |
| JP6902760B2 (en) | How to build a concrete structure | |
| JPH05222766A (en) | Building method | |
| JP6539914B2 (en) | Steel girder joint structure and steel girder joint method | |
| Bywaters et al. | Modern methods of construction | |
| NO342534B1 (en) | A connecting means of a building structure and a method of using same | |
| JPS63272847A (en) | Reinforced concrete construction method using plate reinforcement | |
| BR112017024905B1 (en) | MODULE FOR A STRUCTURE, STRUCTURE, ASSEMBLY OF A FORM MEMBER, REINFORCED MODULAR BRIDGE, REINFORCED BRIDGE, CONSTRUCTION METHOD, MODULES FOR A STRUCTURE, PACKAGING METHOD, AND, SELF-SUFFICIENT MODULE FOR A STRUCTURE | |
| CN109736834A (en) | Installation process method and apparatus, processor and the memory of inverted arch prefabricated film | |
| OA18683A (en) | A Module for a structure | |
| KR20170135242A (en) | How to build parking | |
| HK1250527A1 (en) | A module for a structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |