US20160108618A1 - Prefabricated modular rebar modules and methods of using the same - Google Patents

Prefabricated modular rebar modules and methods of using the same Download PDF

Info

Publication number
US20160108618A1
US20160108618A1 US14/874,545 US201514874545A US2016108618A1 US 20160108618 A1 US20160108618 A1 US 20160108618A1 US 201514874545 A US201514874545 A US 201514874545A US 2016108618 A1 US2016108618 A1 US 2016108618A1
Authority
US
United States
Prior art keywords
welded
cages
steel structure
prefabricated
bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US14/874,545
Inventor
Emin Buzimkic
Keith Baugaard
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from US14/517,113 external-priority patent/US20170321421A9/en
Application filed by Individual filed Critical Individual
Priority to US14/874,545 priority Critical patent/US20160108618A1/en
Publication of US20160108618A1 publication Critical patent/US20160108618A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
    • E04C5/0609Closed cages composed of two or more coacting cage parts, e.g. transversally hinged or nested parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/04Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
    • E04C2/06Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres reinforced
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements

Definitions

  • This invention relates generally to the broad field of reinforced concrete and more particularly to the steel, or rebar used to reinforce the concrete. More particularly, this invention relates to methods and apparatus for constructing and installing rebar used in concrete construction.
  • Reinforced concrete is a well known and widely used building material which is used in building, bridges, roads, tunnels and other structural construction projects. Essentially the concrete, which is strong in compression but has no strength in tension, is reinforced with steel rods which pass through the zones of tension in the structural element. Engineers design the structural components; calculate the forces which will be generated by the structure, which may be carrying dynamic or static loads or both; and then develop a rebar plan to provide enough rebar reinforcement in the regions of the concrete structure where tension forces may be created. The rebar plan often requires complex cages with rebar elements bent from, for example, a top surface to a bottom surface and then back to the top surface to accommodate the load pattern created in a beam supported by a column for example.
  • rebar rods are transported individually to a work site and then assembled on site. In some cases they may be bent on site and in other cases they may be bent at the factory and merely assembled on site. Assembly means placing the rebar rods into a form which will then hold the liquid concrete which is poured into the form around the rebar. Once the concrete cures and hardens the forms can be removed and the structural element is ready for use.
  • the rebar is typically provided with a textured outer surface to enable the concrete to better grip the steel bars.
  • the assembly of the rebar into the forms is done with great care—the correct positioning of the rebar is required to ensure the structural element has the strength that it has been designed for.
  • Each rebar element must be precisely located in the three dimensional space within the form to ensure appropriate load bearing capacity of the finished structural element.
  • the engineers provide the fabricators with exact rebar cage plans and designs and every rod is checked for correct positioning before any concrete is poured.
  • the fabrication of the re-bar cage according to the detailed design specifications can be slow and tedious work.
  • the rebar components are connected on site by workers using ties with wires.
  • the rods themselves can be long and unwieldy.
  • the position of the components each have to carefully measured to ensure that they are properly spaced and located and that they will be located at an appropriate depth within the concrete once the concrete is poured into the form.
  • the entire process of installing the components on site can be time consuming, which in turns increases the costs of the projects. Delays in the construction of rebar cages can cause significant delays in the entire construction project since the installation of reinforced concrete will often be one of the first steps in a major building project.
  • rebar structures for raft and transfer slabs onsite is also awkward in that incomplete cage assemblies may lead to partially built cage structures that are shaky and hard to walk on, causing safety issues. Installation may also be more challenging where confined spaces exist during the construction of the slab layers. It may also be challenging to place rebar on slabs that are deeper than 1800 mm or approximately 6′ in depth. Slabs are typically 2′ to 12′ deep.
  • the structure may comprise one or more prefabricated, welded modular cages having vertical reinforcing bars.
  • the cages may be prefabricated in an offsite factory where there are the space, tools and workers to quickly and easily create the modular cages.
  • There may be a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars.
  • Each prefabricated welded cage may be sized and shaped for shipping and said structure may be quickly and easily formed onsite from a plurality of said modular cages lapped together.
  • a method of constructing a reinforcing steel structure for use in a concrete building wall A plurality of prefabricated, welded cages having vertical reinforcing bars are provided at a worksite. Each of the plurality of prefabricated, welded cages may have a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars.
  • the plurality of prefabricated, welded cages may be installed at a worksite.
  • Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a continuous reinforcing steel structure. Concrete is added to the reinforcing steel structure to form a concrete building wall.
  • the structure comprises one or more prefabricated, welded beams.
  • the prefabricated, welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer.
  • Each welded beam may be sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together.
  • a method of constructing a reinforcing steel structure for use in a concrete building slab A plurality of prefabricated, welded beams may be provided at a worksite.
  • the welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer.
  • a bottom slab layer comprising a plurality of horizontal reinforcing bars may be installed.
  • the plurality of prefabricated, welded beams may be installed adjacent to one another on the bottom slab layer.
  • a top slab layer comprising a plurality of horizontal reinforcing bars is installed on the plurality of welded beams to form a reinforcing steel structure. Concrete is poured around the reinforcing steel structure and permitted to cure to form a concrete building slab.
  • FIG. 1 is a top view of an embodiment of a prefabricated, welded cage for a heavy wall
  • FIG. 2 is a top view of an embodiment of a continuous tie for use in a pre-fabricated, welded cage
  • FIG. 3 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure;
  • FIG. 4 is a top view of an embodiment having two prefabricated, welded cages for a heavy wall
  • FIG. 5 is a top view showing a pair of lap bars connecting two continuous ties
  • FIG. 6 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure
  • FIG. 7 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages;
  • FIG. 8 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in walls with zones;
  • FIG. 9 is a top view of a section of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in a wall with zones;
  • FIG. 10 is a top view of an embodiment of a steel structure having a plurality of prefabricated, welded cages.
  • FIG. 11 is a side view of an embodiment having a pair of prefabricated welded beam for use in a transfer slab or raft slab;
  • FIG. 12 is a perspective view of an embodiment of a bottom slab layer of FIG. 11 for a transfer slab or raft slab;
  • FIG. 13 is a perspective view of an embodiment of a prefabricated, welded beam of FIG. 11 for installation in a transfer slab or raft slab;
  • FIG. 14 is a perspective view of an embodiment of FIG. 11 having a pair of prefabricated, welded beams installed on a bottom slab layer;
  • FIG. 15 is a perspective view of an embodiment of FIG. 11 of a top slab layer installed on top of a pair of prefabricated, welded beams;
  • FIG. 16 is a side view of an embodiment having a pair of prefabricated, welded beams having shear ties
  • FIG. 17 is a perspective view of an embodiment of a bottom slab layer of FIG. 16 ;
  • FIG. 18 is a perspective view of an embodiment of a prefabricated, welded beam of FIG. 16 for a transfer slab or raft slab;
  • FIG. 19 is a perspective view of an embodiment of a steel structure having a pair of prefabricated, welded beams of FIG. 16 installed on a bottom slab layer;
  • FIG. 20 is a perspective view of an embodiment of a steel structure of FIG. 16 having a top slab layer installed on a pair of prefabricated, welded beams.
  • a prefabricated welded cage 104 is shown in FIG. 1 .
  • the prefabricated welded cage 104 includes a number of vertical reinforcing bars 106 .
  • a continuous tie 108 extends around the vertical reinforcing bars 106 .
  • the welded cage 104 includes a plurality of continuous ties 108 which are placed at vertical intervals around the vertical reinforcing bars 106 .
  • the plurality of continuous ties 108 are spaced at even intervals along the height of the vertical reinforcing bars 106 .
  • a plurality of shear ties 110 extend generally horizontally between the vertical reinforcing bars 106 .
  • the welded cage 104 is sized and shaped for shipping.
  • the structure of one of the plurality of continuous ties 108 is shown in FIG. 2 .
  • the continuous tie 108 shown in FIG. 2 is a single piece of reinforcing steel that forms a closed loop with, for example, ends that overlap.
  • FIG. 3 a prior art design for rebar components in a wall structure is shown.
  • a pair of horizontal bars 120 is connected to a pair of u-caps 118 at each end.
  • This structure would need to be constructed using individual horizontal bars and u-caps on site and then carefully connected to each of the vertical reinforcing bars 106 . Installation of this prior art system would likely be expensive and time consuming.
  • FIGS. 4 and 5 show how two prefabricated welded cages 104 B and 104 C may be installed at a work site.
  • the two cages 104 B and 104 C are placed side-by-side as shown in FIG. 4 .
  • a pair of lap bars 116 are connected between each of the adjacent continuous ties 108 B and 108 C.
  • pairs of lap bars 116 are connected between them. Multiple cages may be connected in this manner.
  • the pair of welded cages 104 B and 104 C are placed adjacent and parallel to each other for use in a single length of a concrete building wall.
  • the plurality of lap bars 116 extend generally horizontally between overlapping adjacent ends of the pair of welded cages.
  • each of the plurality of shear ties 110 have a hook end 112 and a flat end 114 .
  • the plurality of shear ties 110 are arranged between the vertical reinforcing bars 106 in an alternating parallel pattern with the hook ends 112 of each adjacent shear tie facing in an opposite direction.
  • FIG. 6 shows a prior art method of installing a section of wall, which requires a long horizontal bar 120 and u-caps 118 connecting the horizontal bars 120 at the ends of the components. This installation method has similar drawbacks to the prior art method shown in FIG. 3 .
  • FIG. 7 shows a reinforcing steel structure 100 including a plurality of the one or more prefabricated, welded cages 104 .
  • the reinforcing steel structure 100 has a corner pair of welded cages 104 A and 104 B which are placed adjacent and perpendicular to each other for use in two adjoining walls forming a corner of a concrete building wall.
  • a plurality of u-caps 118 extend generally horizontally around adjacent ends of the pair of welded cages.
  • the welded cages 104 A and 104 B meet at a corner generally denoted by 126 .
  • welded cages 104 C and 104 D are adjacent corner pieces connected by a plurality of u-caps 118 .
  • Welded cages 104 B and 104 C form a parallel pair of welded cages placed adjacent and parallel to each other to together form a structure for a single length of a concrete building wall.
  • a plurality of lap bars 116 extend generally horizontally within the vertically reinforcing bars 106 and between overlapping adjacent ends of the parallel pair of welded cages 1048 and 104 C.
  • various different combinations and configurations of welded cages 104 may be connected to form steel structures for concrete walls of various different configurations and sizes.
  • FIG. 8 shows an embodiment of the steel structure 100 having walls with zones having a different configuration of shear ties 110 .
  • shear ties 110 are placed with the hook ends 112 oriented in the same direction as each other and the shear bars 110 are placed at each end of the welded cages 104 A to 104 D.
  • add bars 122 are used exclusively as the vertical reinforcing bars 106
  • add bars 122 are used only at each end of the respective welded cages 104 A to 1048 .
  • the shear ties 110 are placed between the add bars 122 .
  • the thicker vertical bars 122 are zone concentrated reinforcing bars and the thinner of the vertical bars 106 represent stress distributed reinforcing bars.
  • FIG. 9 shows an embodiment of a portion of a steel structure having welded cages 104 C and 104 D.
  • Hooked horizontal bars 124 are placed at the corner 126 where welded cages 104 C and 104 D are adjacent.
  • Horizontal j-bars 116 are located inside the vertical reinforcing bars 106 and match the continuous ties 108 .
  • the horizontal bars 124 are also closed ties.
  • the j-bars 116 are embedded between the modular welded cages 104 C and 104 D and which may assist in preventing failure when concrete spalls under stress.
  • FIG. 10 shows a steel structure 400 having a plurality of prefabricated welded cages 404 A to 404 D.
  • Vertical reinforcing bars 406 all in the form of add bars 422 , lie between continuous ties 408 in each of the welded cages 404 A to 404 D.
  • Shear ties 410 connect between the vertical reinforce bars 406 and are placed with the hooked ends 412 of adjacent shear ties 410 facing in opposite directions. Opposite the hooked ends 412 of each shear tie is a flat end 414 .
  • U-caps 418 provide a connection between corners 426 of adjacent welded cages 404 A and 404 B, as well as adjacent welded cages 404 C and 404 D. The embodiment shown in FIG.
  • FIG. 10 is similar to the embodiment of reinforcing steel structure of FIG. 7 , except with the addition of a plurality of lap bars 416 extending generally horizontally within the vertical reinforcing bars 406 and between the corner pairs of welded cages 404 A and 404 B as well as welded cages 404 C and 404 D.
  • the addition of the plurality of lap bars 416 may be preferred in cases where a seismic resistant design is required.
  • the reinforcing steel structure 100 of FIGS. 1, 4, and 7 to 9 may be installed for use in a concrete building wall by the following method.
  • the method of constructing the steel structure 400 in the embodiment shown in FIG. 10 is similar to the method of installing the steel structure 100 shown in FIG. 7 .
  • a plurality prefabricated, welded cages 104 are provided on site at a worksite.
  • the plurality of prefabricated, welded cages are installed at a worksite where a concrete wall is to be made.
  • Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a reinforcing steel structure. As shown in FIGS.
  • the reinforcing bars installed between the welded cages 104 may include u-bars, lap bars or other rebar structures that allow for the communication of tension stress between the cages.
  • concrete (not shown) is poured into the reinforcing steel structure 100 to form a concrete building wall.
  • FIGS. 1 to 10 have certain dimensions, it will be understood that various difference dimensions of walls may be constructed, using different sizes of cages depending on the application.
  • the size of the cages should be chosen to fall within transportation limits, which may be, for example, 12 feet by 12 feet by 60 feet. In this sense transportation limits means the size of module that can be readily accommodated within the existing size of conventional transport vehicle (truck, or train car) that may be used for shipping rebar. While at present the size as outlined above is suitable in some jurisdictions, it will be understood that the present invention comprehends adapting the size of the modular cages to meet whatever the local transportation limits might be.
  • the present invention comprehends a modular approach and therefore in some cases depending upon the structural design, the equipment available on site to assemble multiple modules into compound cage assemblies the modules may be made smaller than the maximum size and yet dimensioned to be efficiently fit within the typical transportable volume.
  • FIG. 11 shows a side view of two prefabricated welded beams 204 A and 204 B.
  • the welded beams together form a reinforcing steel structure 200 ( FIG. 15 ) for use in a concrete building transfer or raft slab.
  • a plurality of continuous ties 212 extend generally vertically around a top beam layer 206 having horizontal reinforcing bars and a bottom beam layer 208 having horizontal reinforcing bars.
  • Each welded beam 204 A and 204 B is sized and shaped for shipping.
  • the prefabricated welded beams 204 A and 204 B are installed between a top slab layer 214 and a bottom slab later 218 .
  • the continuous ties 212 shown in FIG. 11 are a single piece of reinforcing steel that forms a closed loop.
  • the components of the reinforcing steel structure 200 are shown in FIGS. 12-15 .
  • the bottom slab layer 218 is shown in FIG. 12 .
  • a plurality of bottom horizontal reinforcing bars 220 are installed parallel to one another.
  • a prefabricated welded beam 204 is shown in FIG. 13 .
  • the welded beam 204 has a plurality of vertical continuous ties 212 that extend around top and bottom beam layers 206 and 208 .
  • the top beam layer 206 has a plurality of top horizontal reinforcing bars 210 .
  • the bottom beam layer 208 has a plurality of bottom horizontal reinforcing bars 211 .
  • the top and bottom horizontal reinforcing bars 210 and 211 are oriented lengthways along the welded beam 204 and are parallel with one another. Different orientations of the horizontal reinforcing bars may be used.
  • FIG. 14 shows one of the steps in installing the welded beams 204 A and 204 B in a steel structure.
  • the welded beams are placed side-by-side on top of the bottom slab layer 218 .
  • the top slab layer 214 is then installed on top of the welded beams to form the steel structure 200 .
  • the top horizontal reinforcing bars 210 of the top beam layer 206 lie adjacent to and in the same plane as the top horizontal reinforcing bars 216 of the top slab layer 214 , with the two layers oriented so that the plurality of horizontal reinforcing bars 216 of the top slab layer 214 are oriented generally perpendicularly to the horizontal reinforcing bars 210 of the top beam layer 206 .
  • the bottom horizontal reinforcing bars 211 of the bottom beam layer 208 lie adjacent to and in the same plane as the top horizontal reinforcing bars 220 of the bottom slab layer 218 , with the two layers oriented so that plurality of horizontal reinforcing bars 220 of the bottom slab layer 218 are oriented generally perpendicularly to the horizontal reinforcing bars 211 of the bottom beam layer 208 . It will be understood that different orientations of each of the various horizontal reinforcing bars may be used.
  • FIGS. 16 to 20 show a steel structure 300 ( FIG. 20 ) comprising a plurality of prefabricated welded beams 304 installed side-by-side between a bottom slab layer 318 ( FIG. 17 ) having horizontal reinforcing bars 320 and a top slab layer 314 ( FIG. 20 ) having horizontal reinforcing bars 316 .
  • the prefabricated welded beams 304 are shown in more detail in FIG. 16 where the welded beams 304 each include a plurality of vertical continuous ties 312 which extend around a top beam layer 306 and a bottom beam layer 308 .
  • the top beam layer 306 formed from a plurality of top horizontal reinforcing bars 310 and the bottom beam layer 308 being formed from a plurality of bottom horizontal reinforcing bars 311 .
  • the embodiment of the steel structure 300 shown in FIGS. 16 to 20 is similar to the steel structure 200 shown in FIGS. 11 to 15 , except that the embodiment of the steel structure 300 includes a plurality of shear ties 322 extending generally vertically between the horizontal reinforcing bars 310 of the top beam layer 306 and the horizontal reinforcing bars 311 of the bottom beam layer 308 .
  • the shear ties 322 include a hook end 324 and a flat end 326 .
  • Each of the one or more prefabricated, welded beams 304 A, 304 B include shear ties 322 that are oriented with the hook ends 324 connected to the horizontal reinforcing bars 310 of the top beam layer 306 .
  • the plurality of shear ties 322 form two parallel rows of shear ties 322 extending along a length of the one or more prefabricated, welded beams 304 A and 304 B.
  • FIGS. 12 to 15 and 17 to 20 generally set out the steps in constructing a reinforcing steel structure 200 or 300 for use in a concrete building slab.
  • the beams are assembled as units using a combination of welds and ties at intersections. The ratio between the number of ties and welds is adjusted as required due to loading and flexibility requirements.
  • the process described herein has two layers of rebar in the top and bottom formed from the top and bottom beam layers and the top and bottom slab layers, a similar procedure may be used when there are more than two layers of rebar for the top and bottom mats. All welding may be done in accordance with local welding standards. Different numbers, orientations and sizes of welded beams may be used in a steel structure depending on the application desired.
  • a plurality of prefabricated, welded beams 204 are provided at a worksite.
  • the beams preferably have dimensions equal to or less than 12 feet by 12 feet by 60 feet, in order to conform with transportation limits. The size of the beams may depend on the transportation limits in different jurisdictions.
  • the plurality of prefabricated welded beams 204 may be assembled and welded at a separate facility from the worksite.
  • the beams 204 may be delivered on site when the concrete slab structure is being constructed. By providing the beams 204 in a prefabricated form, the installation process on site may be simplified.
  • the bottom slab layer 218 is installed as shown in FIG. 12 at a work site.
  • each of the prefabricated, welded beams 204 are placed adjacent to one another on the bottom slab layer 218 .
  • the bottom slab layer 218 and the beams 204 may be connected by a suitable combination of welding or wire ties.
  • the top slab layer 214 is installed on the plurality of welded beams to form the reinforcing steel structure 200 .
  • the top slab layer 214 and the beams are connected using welding or wire ties.
  • concrete (not shown) is added to the reinforcing steel structure to form a concrete building transfer or raft slab.
  • the beams are generally sturdy for transportation and installation.
  • the rigidity of the beams 204 may allow them to be walked on and can provide a surface to stand on during installation.
  • By providing the beams 204 in a completed form it may lessen the need for workers to install rebar components in confined spaces. Testing has shown that installation using modulated welded cages may reduce installation time by as much as half of the time compared to traditional methods.
  • each of the connections allows each of the connections to be provided entirely by welding.
  • the reinforcing steel in each of the welded cages and welded beams are joined using 100% welding, which may increase the strength of the prefabricated components compared to using wire ties.
  • each of the one or more prefabricated, welded cages or beams have dimensions equal to or less than 12 feet by 12 feet by 60 feet or other suitable dimensions that may be required by transportation limits. Different sizes of welded beams may be constructed.
  • the welded beams are sized and shaped to suit the profile of the transfer or raft slab. Variations of the size and shape may also be required since slabs may have steps or slopes on the top or bottom.
  • the welded beams and welded cages are generally arranged on the transportation vehicles to fit as many as possible onto a single load.
  • the amount loaded onto each vehicle also depends on the sequence of delivery, which should follow a logical order based on the order each component is installed.
  • a load of welded beams or cages may also be combined with additional loads, such as loose bars to fully load a transport vehicle.
  • the sequence of transportation may be of heightened important since there are frequently issues with the amount of free space on site.
  • Welded cages generally are no wider than 12′ in width to meet certain transportation requirements and the length may be dependent on the length of wall.
  • the welded cages may be sized and shaped to fit the least number of cages as possible in each wall in order to reduce the number of laps required when installing the cages. It may be beneficial to ensure that the wall cages are each the same size and there are a number of factors which may have an effect on the size and shape of a cage, and there may be variation from cage to cage. Factors which may dictate width of a welded cage may include the thickness of the walls, any additional openings in the walls and the intersections with other walls, etc.
  • the welded cages and beams may be limited to being no more than 12′ wide in one direction, since the trailers are 8′ wide and the limit for the overhang is 2′ on each side. Trailers also come in different sizes, and in some jurisdictions, the maximum length may be 60′. Longer or wider assemblies than the maximums in a particular jurisdiction are possible with special permits and may require heavy duty cranes for positioning and offloading. Another factor for the size of welded cages and beams is crane lifting capacity onsite, since cages cannot be designed heavier than allowed by the crane lifting capacity, which may vary from site to site.
  • the welded cages 104 and 404 are preferably made using vertical reinforcing bars which are welded inside a plurality of parallel horizontal continuous ties.
  • the welded beams 204 and 304 are preferably made using top and bottom beam layers which are welded inside a plurality of vertical continuous ties.
  • the prefabricated beams and cages described herein may be mass produced, since each component may be fabricated following a specific design.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

There is provided a reinforcing steel structure for use in a concrete building wall. The structure includes one or more prefabricated, welded cages having vertical reinforcing bars. A plurality of continuous ties extends around the vertical reinforcing bars and a plurality of shear ties extends generally horizontally between the vertical reinforcing bars. Each welded cage is sized and shaped for shipping and said structure can be formed onsite from a plurality of said cages lapped together. Concrete is added to the reinforcing steel structure to form a concrete building wall.
There is also provided a reinforcing steel structure for use in a concrete building transfer or raft slab. The structure includes one or more prefabricated, welded beams. The prefabricated, welded beams have a top beam layer and a bottom beam layer, each having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top and bottom beam layers. Each welded beam is sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together. Concrete is added to the reinforcing steel structure to form a concrete building slab.

Description

    CROSS REFERENCE TO RELATED APPLICATION
  • This application is a divisional application of and claims priority to co-pending non-provisional U.S. patent application Ser. No. 14/517,113 filed on Oct. 17, 2014, which is hereby incorporated by reference in its entirety.
  • FIELD OF THE INVENTION
  • This invention relates generally to the broad field of reinforced concrete and more particularly to the steel, or rebar used to reinforce the concrete. More particularly, this invention relates to methods and apparatus for constructing and installing rebar used in concrete construction.
  • BACKGROUND OF THE INVENTION
  • Reinforced concrete is a well known and widely used building material which is used in building, bridges, roads, tunnels and other structural construction projects. Essentially the concrete, which is strong in compression but has no strength in tension, is reinforced with steel rods which pass through the zones of tension in the structural element. Engineers design the structural components; calculate the forces which will be generated by the structure, which may be carrying dynamic or static loads or both; and then develop a rebar plan to provide enough rebar reinforcement in the regions of the concrete structure where tension forces may be created. The rebar plan often requires complex cages with rebar elements bent from, for example, a top surface to a bottom surface and then back to the top surface to accommodate the load pattern created in a beam supported by a column for example.
  • Conventionally, rebar rods are transported individually to a work site and then assembled on site. In some cases they may be bent on site and in other cases they may be bent at the factory and merely assembled on site. Assembly means placing the rebar rods into a form which will then hold the liquid concrete which is poured into the form around the rebar. Once the concrete cures and hardens the forms can be removed and the structural element is ready for use.
  • The rebar is typically provided with a textured outer surface to enable the concrete to better grip the steel bars. The assembly of the rebar into the forms is done with great care—the correct positioning of the rebar is required to ensure the structural element has the strength that it has been designed for. Each rebar element must be precisely located in the three dimensional space within the form to ensure appropriate load bearing capacity of the finished structural element. Thus the engineers provide the fabricators with exact rebar cage plans and designs and every rod is checked for correct positioning before any concrete is poured.
  • The fabrication of the re-bar cage according to the detailed design specifications can be slow and tedious work. The rebar components are connected on site by workers using ties with wires. The rods themselves can be long and unwieldy. The position of the components each have to carefully measured to ensure that they are properly spaced and located and that they will be located at an appropriate depth within the concrete once the concrete is poured into the form. The entire process of installing the components on site can be time consuming, which in turns increases the costs of the projects. Delays in the construction of rebar cages can cause significant delays in the entire construction project since the installation of reinforced concrete will often be one of the first steps in a major building project. For example, in a building the concrete frame of the building must be in place before the windows and interior finishing can be attempted within the frame. Since the installation of the rebar components requires rodworkers and other workers to be present on site, any staffing issues may also cause delays in the overall project. Construction of rebar structures onsite also requires each structure to be custom made.
  • Constructing rebar structures for raft and transfer slabs onsite is also awkward in that incomplete cage assemblies may lead to partially built cage structures that are shaky and hard to walk on, causing safety issues. Installation may also be more challenging where confined spaces exist during the construction of the slab layers. It may also be challenging to place rebar on slabs that are deeper than 1800 mm or approximately 6′ in depth. Slabs are typically 2′ to 12′ deep.
  • Patent applications of general interest in the field of rebar include:
  • U.S. Pat. No. 5,392,580 patented on Feb. 28, 1995;
  • U.S. Pat. No. 8,381,479 patented on Feb. 26, 2013; and
  • U.S. Appl. No. 2009/0014419 published on Jan. 15, 2009.
  • SUMMARY OF THE INVENTION
  • What is desired is a simpler and more efficient way of constructing reinforced concrete structures.
  • In an embodiment there is a modular reinforcing steel structure for use in a concrete building wall. The structure may comprise one or more prefabricated, welded modular cages having vertical reinforcing bars. The cages may be prefabricated in an offsite factory where there are the space, tools and workers to quickly and easily create the modular cages. There may be a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars. Each prefabricated welded cage may be sized and shaped for shipping and said structure may be quickly and easily formed onsite from a plurality of said modular cages lapped together.
  • In another embodiment there is provided a method of constructing a reinforcing steel structure for use in a concrete building wall. A plurality of prefabricated, welded cages having vertical reinforcing bars are provided at a worksite. Each of the plurality of prefabricated, welded cages may have a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars. The plurality of prefabricated, welded cages may be installed at a worksite. Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a continuous reinforcing steel structure. Concrete is added to the reinforcing steel structure to form a concrete building wall.
  • In another embodiment there is a reinforcing steel structure for use in a concrete building transfer or raft slab. The structure comprises one or more prefabricated, welded beams. The prefabricated, welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer. Each welded beam may be sized and shaped for shipping and said structure can be formed onsite from a plurality of said beams lapped together.
  • In another embodiment there is a method of constructing a reinforcing steel structure for use in a concrete building slab. A plurality of prefabricated, welded beams may be provided at a worksite. The welded beams may comprise a top beam layer having horizontal reinforcing bars, a bottom beam layer having horizontal reinforcing bars, and a plurality of continuous ties extending generally vertically around the top beam layer and the bottom beam layer. A bottom slab layer comprising a plurality of horizontal reinforcing bars may be installed. The plurality of prefabricated, welded beams may be installed adjacent to one another on the bottom slab layer. A top slab layer comprising a plurality of horizontal reinforcing bars is installed on the plurality of welded beams to form a reinforcing steel structure. Concrete is poured around the reinforcing steel structure and permitted to cure to form a concrete building slab.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • Reference will now be made by way of example only to preferred embodiments of the invention by reference to the following drawings in which:
  • FIG. 1 is a top view of an embodiment of a prefabricated, welded cage for a heavy wall;
  • FIG. 2 is a top view of an embodiment of a continuous tie for use in a pre-fabricated, welded cage;
  • FIG. 3 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure;
  • FIG. 4 is a top view of an embodiment having two prefabricated, welded cages for a heavy wall;
  • FIG. 5 is a top view showing a pair of lap bars connecting two continuous ties;
  • FIG. 6 is a top view of a PRIOR ART configuration of u-caps and horizontal bars for use in a concrete wall structure;
  • FIG. 7 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages;
  • FIG. 8 is a top view of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in walls with zones;
  • FIG. 9 is a top view of a section of an embodiment of a steel structure made from a plurality of pre-fabricated, welded cages for use in a wall with zones;
  • FIG. 10 is a top view of an embodiment of a steel structure having a plurality of prefabricated, welded cages.
  • FIG. 11 is a side view of an embodiment having a pair of prefabricated welded beam for use in a transfer slab or raft slab;
  • FIG. 12 is a perspective view of an embodiment of a bottom slab layer of FIG. 11 for a transfer slab or raft slab;
  • FIG. 13 is a perspective view of an embodiment of a prefabricated, welded beam of FIG. 11 for installation in a transfer slab or raft slab;
  • FIG. 14 is a perspective view of an embodiment of FIG. 11 having a pair of prefabricated, welded beams installed on a bottom slab layer;
  • FIG. 15 is a perspective view of an embodiment of FIG. 11 of a top slab layer installed on top of a pair of prefabricated, welded beams;
  • FIG. 16 is a side view of an embodiment having a pair of prefabricated, welded beams having shear ties;
  • FIG. 17 is a perspective view of an embodiment of a bottom slab layer of FIG. 16;
  • FIG. 18 is a perspective view of an embodiment of a prefabricated, welded beam of FIG. 16 for a transfer slab or raft slab;
  • FIG. 19 is a perspective view of an embodiment of a steel structure having a pair of prefabricated, welded beams of FIG. 16 installed on a bottom slab layer; and
  • FIG. 20 is a perspective view of an embodiment of a steel structure of FIG. 16 having a top slab layer installed on a pair of prefabricated, welded beams.
  • DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
  • A prefabricated welded cage 104 is shown in FIG. 1. The prefabricated welded cage 104 includes a number of vertical reinforcing bars 106. A continuous tie 108 extends around the vertical reinforcing bars 106. Although only one continuous tie is shown in FIG. 1, it will be understood that the welded cage 104 includes a plurality of continuous ties 108 which are placed at vertical intervals around the vertical reinforcing bars 106. Preferably, the plurality of continuous ties 108 are spaced at even intervals along the height of the vertical reinforcing bars 106. A plurality of shear ties 110 extend generally horizontally between the vertical reinforcing bars 106. The welded cage 104 is sized and shaped for shipping.
  • The structure of one of the plurality of continuous ties 108 is shown in FIG. 2. The continuous tie 108 shown in FIG. 2 is a single piece of reinforcing steel that forms a closed loop with, for example, ends that overlap.
  • In FIG. 3, a prior art design for rebar components in a wall structure is shown. A pair of horizontal bars 120 is connected to a pair of u-caps 118 at each end. This structure would need to be constructed using individual horizontal bars and u-caps on site and then carefully connected to each of the vertical reinforcing bars 106. Installation of this prior art system would likely be expensive and time consuming.
  • FIGS. 4 and 5 show how two prefabricated welded cages 104B and 104C may be installed at a work site. The two cages 104B and 104C are placed side-by-side as shown in FIG. 4. As shown in FIG. 5, a pair of lap bars 116 are connected between each of the adjacent continuous ties 108B and 108C. For each of the plurality of continuous ties 108B and 108C in each of the cages 104B and 104C, pairs of lap bars 116 are connected between them. Multiple cages may be connected in this manner. The pair of welded cages 104B and 104C are placed adjacent and parallel to each other for use in a single length of a concrete building wall. The plurality of lap bars 116 extend generally horizontally between overlapping adjacent ends of the pair of welded cages.
  • As shown in FIG. 4, each of the plurality of shear ties 110 have a hook end 112 and a flat end 114. In the embodiment shown in FIG. 4, the plurality of shear ties 110 are arranged between the vertical reinforcing bars 106 in an alternating parallel pattern with the hook ends 112 of each adjacent shear tie facing in an opposite direction.
  • FIG. 6 shows a prior art method of installing a section of wall, which requires a long horizontal bar 120 and u-caps 118 connecting the horizontal bars 120 at the ends of the components. This installation method has similar drawbacks to the prior art method shown in FIG. 3.
  • FIG. 7 shows a reinforcing steel structure 100 including a plurality of the one or more prefabricated, welded cages 104. In this case there are shown four welded cages 104A, 104B, 104C, and 104D. The reinforcing steel structure 100 has a corner pair of welded cages 104A and 104B which are placed adjacent and perpendicular to each other for use in two adjoining walls forming a corner of a concrete building wall. A plurality of u-caps 118 extend generally horizontally around adjacent ends of the pair of welded cages. The welded cages 104A and 104B meet at a corner generally denoted by 126. Similarly, welded cages 104C and 104D are adjacent corner pieces connected by a plurality of u-caps 118. Welded cages 104B and 104C form a parallel pair of welded cages placed adjacent and parallel to each other to together form a structure for a single length of a concrete building wall. A plurality of lap bars 116 extend generally horizontally within the vertically reinforcing bars 106 and between overlapping adjacent ends of the parallel pair of welded cages 1048 and 104C. As will be understood, various different combinations and configurations of welded cages 104 may be connected to form steel structures for concrete walls of various different configurations and sizes.
  • FIG. 8 shows an embodiment of the steel structure 100 having walls with zones having a different configuration of shear ties 110. In the embodiment shown in FIG. 8, shear ties 110 are placed with the hook ends 112 oriented in the same direction as each other and the shear bars 110 are placed at each end of the welded cages 104A to 104D. Also, although in the embodiment shown in FIG. 7, add bars 122 are used exclusively as the vertical reinforcing bars 106, in the embodiment shown in FIG. 8, add bars 122 are used only at each end of the respective welded cages 104A to 1048. The shear ties 110 are placed between the add bars 122. The thicker vertical bars 122 are zone concentrated reinforcing bars and the thinner of the vertical bars 106 represent stress distributed reinforcing bars.
  • FIG. 9 shows an embodiment of a portion of a steel structure having welded cages 104C and 104D. Hooked horizontal bars 124 are placed at the corner 126 where welded cages 104C and 104D are adjacent. Horizontal j-bars 116 are located inside the vertical reinforcing bars 106 and match the continuous ties 108. The horizontal bars 124 are also closed ties. The j-bars 116 are embedded between the modular welded cages 104C and 104D and which may assist in preventing failure when concrete spalls under stress.
  • FIG. 10 shows a steel structure 400 having a plurality of prefabricated welded cages 404A to 404D. Vertical reinforcing bars 406, all in the form of add bars 422, lie between continuous ties 408 in each of the welded cages 404A to 404D. Shear ties 410 connect between the vertical reinforce bars 406 and are placed with the hooked ends 412 of adjacent shear ties 410 facing in opposite directions. Opposite the hooked ends 412 of each shear tie is a flat end 414. U-caps 418 provide a connection between corners 426 of adjacent welded cages 404A and 404B, as well as adjacent welded cages 404C and 404D. The embodiment shown in FIG. 10 is similar to the embodiment of reinforcing steel structure of FIG. 7, except with the addition of a plurality of lap bars 416 extending generally horizontally within the vertical reinforcing bars 406 and between the corner pairs of welded cages 404A and 404B as well as welded cages 404C and 404D. The addition of the plurality of lap bars 416 may be preferred in cases where a seismic resistant design is required.
  • The reinforcing steel structure 100 of FIGS. 1, 4, and 7 to 9, may be installed for use in a concrete building wall by the following method. The method of constructing the steel structure 400 in the embodiment shown in FIG. 10 is similar to the method of installing the steel structure 100 shown in FIG. 7. A plurality prefabricated, welded cages 104 are provided on site at a worksite. The plurality of prefabricated, welded cages are installed at a worksite where a concrete wall is to be made. Reinforcing steel bars are installed between the plurality of prefabricated, welded cages to form a reinforcing steel structure. As shown in FIGS. 1, 4 and 7 to 9, the reinforcing bars installed between the welded cages 104 may include u-bars, lap bars or other rebar structures that allow for the communication of tension stress between the cages. As a final step, concrete (not shown) is poured into the reinforcing steel structure 100 to form a concrete building wall.
  • Although the walls shown in FIGS. 1 to 10 have certain dimensions, it will be understood that various difference dimensions of walls may be constructed, using different sizes of cages depending on the application. The size of the cages should be chosen to fall within transportation limits, which may be, for example, 12 feet by 12 feet by 60 feet. In this sense transportation limits means the size of module that can be readily accommodated within the existing size of conventional transport vehicle (truck, or train car) that may be used for shipping rebar. While at present the size as outlined above is suitable in some jurisdictions, it will be understood that the present invention comprehends adapting the size of the modular cages to meet whatever the local transportation limits might be. Further, while the above noted size limit is the maximum size, the present invention comprehends a modular approach and therefore in some cases depending upon the structural design, the equipment available on site to assemble multiple modules into compound cage assemblies the modules may be made smaller than the maximum size and yet dimensioned to be efficiently fit within the typical transportable volume.
  • FIG. 11 shows a side view of two prefabricated welded beams 204A and 204B. The welded beams together form a reinforcing steel structure 200 (FIG. 15) for use in a concrete building transfer or raft slab. A plurality of continuous ties 212 extend generally vertically around a top beam layer 206 having horizontal reinforcing bars and a bottom beam layer 208 having horizontal reinforcing bars. Each welded beam 204A and 204B is sized and shaped for shipping. As shown in FIG. 11, the prefabricated welded beams 204A and 204B are installed between a top slab layer 214 and a bottom slab later 218. The continuous ties 212 shown in FIG. 11 are a single piece of reinforcing steel that forms a closed loop.
  • The components of the reinforcing steel structure 200 are shown in FIGS. 12-15. The bottom slab layer 218 is shown in FIG. 12. A plurality of bottom horizontal reinforcing bars 220 are installed parallel to one another.
  • A prefabricated welded beam 204 is shown in FIG. 13. The welded beam 204 has a plurality of vertical continuous ties 212 that extend around top and bottom beam layers 206 and 208. The top beam layer 206 has a plurality of top horizontal reinforcing bars 210. The bottom beam layer 208 has a plurality of bottom horizontal reinforcing bars 211. The top and bottom horizontal reinforcing bars 210 and 211 are oriented lengthways along the welded beam 204 and are parallel with one another. Different orientations of the horizontal reinforcing bars may be used.
  • FIG. 14 shows one of the steps in installing the welded beams 204A and 204B in a steel structure. The welded beams are placed side-by-side on top of the bottom slab layer 218. As shown in FIG. 15, the top slab layer 214 is then installed on top of the welded beams to form the steel structure 200. As shown in FIG. 15, the top horizontal reinforcing bars 210 of the top beam layer 206 lie adjacent to and in the same plane as the top horizontal reinforcing bars 216 of the top slab layer 214, with the two layers oriented so that the plurality of horizontal reinforcing bars 216 of the top slab layer 214 are oriented generally perpendicularly to the horizontal reinforcing bars 210 of the top beam layer 206. Similarly, the bottom horizontal reinforcing bars 211 of the bottom beam layer 208 lie adjacent to and in the same plane as the top horizontal reinforcing bars 220 of the bottom slab layer 218, with the two layers oriented so that plurality of horizontal reinforcing bars 220 of the bottom slab layer 218 are oriented generally perpendicularly to the horizontal reinforcing bars 211 of the bottom beam layer 208. It will be understood that different orientations of each of the various horizontal reinforcing bars may be used.
  • FIGS. 16 to 20 show a steel structure 300 (FIG. 20) comprising a plurality of prefabricated welded beams 304 installed side-by-side between a bottom slab layer 318 (FIG. 17) having horizontal reinforcing bars 320 and a top slab layer 314 (FIG. 20) having horizontal reinforcing bars 316. The prefabricated welded beams 304 are shown in more detail in FIG. 16 where the welded beams 304 each include a plurality of vertical continuous ties 312 which extend around a top beam layer 306 and a bottom beam layer 308. The top beam layer 306 formed from a plurality of top horizontal reinforcing bars 310 and the bottom beam layer 308 being formed from a plurality of bottom horizontal reinforcing bars 311.
  • The embodiment of the steel structure 300 shown in FIGS. 16 to 20 is similar to the steel structure 200 shown in FIGS. 11 to 15, except that the embodiment of the steel structure 300 includes a plurality of shear ties 322 extending generally vertically between the horizontal reinforcing bars 310 of the top beam layer 306 and the horizontal reinforcing bars 311 of the bottom beam layer 308. The shear ties 322 include a hook end 324 and a flat end 326. Each of the one or more prefabricated, welded beams 304A, 304B include shear ties 322 that are oriented with the hook ends 324 connected to the horizontal reinforcing bars 310 of the top beam layer 306. As shown in FIG. 16, the plurality of shear ties 322 form two parallel rows of shear ties 322 extending along a length of the one or more prefabricated, welded beams 304A and 304B.
  • FIGS. 12 to 15 and 17 to 20 generally set out the steps in constructing a reinforcing steel structure 200 or 300 for use in a concrete building slab. Reference will be made hereafter to the embodiment of the steel structure 200 shown in FIGS. 12 to 15, but the same method installation applies to the steel structure 300 in FIGS. 17 to 20. Generally, the beams are assembled as units using a combination of welds and ties at intersections. The ratio between the number of ties and welds is adjusted as required due to loading and flexibility requirements. Although the process described herein has two layers of rebar in the top and bottom formed from the top and bottom beam layers and the top and bottom slab layers, a similar procedure may be used when there are more than two layers of rebar for the top and bottom mats. All welding may be done in accordance with local welding standards. Different numbers, orientations and sizes of welded beams may be used in a steel structure depending on the application desired.
  • Initially, a plurality of prefabricated, welded beams 204 are provided at a worksite. The beams preferably have dimensions equal to or less than 12 feet by 12 feet by 60 feet, in order to conform with transportation limits. The size of the beams may depend on the transportation limits in different jurisdictions. The plurality of prefabricated welded beams 204 may be assembled and welded at a separate facility from the worksite. The beams 204 may be delivered on site when the concrete slab structure is being constructed. By providing the beams 204 in a prefabricated form, the installation process on site may be simplified. The bottom slab layer 218 is installed as shown in FIG. 12 at a work site.
  • Next, each of the prefabricated, welded beams 204 are placed adjacent to one another on the bottom slab layer 218. The bottom slab layer 218 and the beams 204 may be connected by a suitable combination of welding or wire ties. After the welded beams are installed, the top slab layer 214 is installed on the plurality of welded beams to form the reinforcing steel structure 200. The top slab layer 214 and the beams are connected using welding or wire ties. Finally, concrete (not shown) is added to the reinforcing steel structure to form a concrete building transfer or raft slab.
  • By installing the steel structure 200 using modular components in the form of prefabricated welded beams 204, the beams are generally sturdy for transportation and installation. The rigidity of the beams 204 may allow them to be walked on and can provide a surface to stand on during installation. By providing the beams 204 in a completed form, it may lessen the need for workers to install rebar components in confined spaces. Testing has shown that installation using modulated welded cages may reduce installation time by as much as half of the time compared to traditional methods.
  • The prefabrication of welded cages and beams allows each of the connections to be provided entirely by welding. Preferably, the reinforcing steel in each of the welded cages and welded beams are joined using 100% welding, which may increase the strength of the prefabricated components compared to using wire ties. Preferably, each of the one or more prefabricated, welded cages or beams have dimensions equal to or less than 12 feet by 12 feet by 60 feet or other suitable dimensions that may be required by transportation limits. Different sizes of welded beams may be constructed. The welded beams are sized and shaped to suit the profile of the transfer or raft slab. Variations of the size and shape may also be required since slabs may have steps or slopes on the top or bottom. The welded beams and welded cages are generally arranged on the transportation vehicles to fit as many as possible onto a single load. The amount loaded onto each vehicle also depends on the sequence of delivery, which should follow a logical order based on the order each component is installed. A load of welded beams or cages may also be combined with additional loads, such as loose bars to fully load a transport vehicle. The sequence of transportation may be of heightened important since there are frequently issues with the amount of free space on site.
  • Welded cages generally are no wider than 12′ in width to meet certain transportation requirements and the length may be dependent on the length of wall. The welded cages may be sized and shaped to fit the least number of cages as possible in each wall in order to reduce the number of laps required when installing the cages. It may be beneficial to ensure that the wall cages are each the same size and there are a number of factors which may have an effect on the size and shape of a cage, and there may be variation from cage to cage. Factors which may dictate width of a welded cage may include the thickness of the walls, any additional openings in the walls and the intersections with other walls, etc.
  • From a delivery point of view, in some jurisdictions, the welded cages and beams may be limited to being no more than 12′ wide in one direction, since the trailers are 8′ wide and the limit for the overhang is 2′ on each side. Trailers also come in different sizes, and in some jurisdictions, the maximum length may be 60′. Longer or wider assemblies than the maximums in a particular jurisdiction are possible with special permits and may require heavy duty cranes for positioning and offloading. Another factor for the size of welded cages and beams is crane lifting capacity onsite, since cages cannot be designed heavier than allowed by the crane lifting capacity, which may vary from site to site.
  • Although the prefabricated welded cages 104 and 404, and the prefabricated welded beams 204 and 304 are shown with particular arrangements of reinforcing steel, it will be understood that various modifications may be made which allow for the construction of prefabricated welded components offsite which may be transported in a completed form. The welded cages 104 and 404 are preferably made using vertical reinforcing bars which are welded inside a plurality of parallel horizontal continuous ties. The welded beams 204 and 304 are preferably made using top and bottom beam layers which are welded inside a plurality of vertical continuous ties.
  • The prefabricated beams and cages described herein may be mass produced, since each component may be fabricated following a specific design.
  • Although the foregoing description has been made with respect to preferred embodiments of the present invention it will be understood by those skilled in the art that many variations and alterations are possible. Some of these variations have been discussed above and others will be apparent to those skilled in the art.
  • In the claims, the word “comprising” is used in its inclusive sense and does not exclude the possibility of other elements being present. The indefinite article “a/an” before a claim feature does not exclude more than one of the feature being present unless it is clear from the context that only a single element is intended.

Claims (8)

What is claimed is:
1. A reinforcing steel structure for use in a concrete building wall, the structure comprising:
one or more prefabricated, welded cages having vertical reinforcing bars;
a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars; and
wherein each welded cage is sized and shaped for shipping and said structure can be formed onsite from a plurality of said cages lapped together.
2. The reinforcing steel structure of claim 1 wherein each of the plurality of shear ties have a hook end and a flat end, and the plurality of shear ties are arranged between the vertical reinforcing bars in an alternating parallel pattern with the hook ends of each adjacent shear tie facing in an opposite direction.
3. The reinforcing steel structure of claim 1 further comprising a plurality of the one or more prefabricated, welded cages and the reinforcing steel structure further comprising a pair of welded cages placed adjacent and parallel to each other for use in a single length of a concrete building wall and having a plurality of lap bars extending generally horizontally between overlapping adjacent ends of the pair of welded cages.
4. The reinforcing steel structure of claim 1 further comprising a plurality of the one or more prefabricated, welded cages and the reinforcing steel structure further comprising a corner pair of welded cages placed adjacent and perpendicular to each other for use in two adjoining walls forming a corner of a concrete building wall and having a plurality of u-caps extending generally horizontally around adjacent ends of the pair of welded cages.
5. The reinforcing steel structure of claim 4 further comprising a parallel pair of welded cages placed adjacent and parallel to each other for use in a single length of a concrete building wall and having a plurality of lap bars extending generally horizontally within the vertically reinforcing bars and between overlapping adjacent ends of the parallel pair of welded cages.
6. The reinforcing steel structure of claim 5 further comprising a plurality of lap bars extending generally horizontally within the vertical reinforcing bars and between the corner pair of welded cages.
7. The reinforcing steel structure of any of claims 1 to 6, wherein each of the one or more prefabricated, welded cages have dimensions equal to or less than 12 feet by 12 feet by 60 feet.
8. A method of constructing a reinforcing steel structure for use in a concrete building wall, the method comprising:
providing a plurality prefabricated, welded cages having vertical reinforcing bars at a worksite, each of the plurality of prefabricated, welded cages having a plurality of continuous ties extending around the vertical reinforcing bars and a plurality of shear ties extending generally horizontally between the vertical reinforcing bars; and
installing the plurality of prefabricated, welded cages at a worksite;
installing reinforcing steel bars between the plurality of prefabricated, welded cages to form a reinforcing steel structure; and
adding concrete to the reinforcing steel structure to form a concrete building wall.
US14/874,545 2014-10-17 2015-10-05 Prefabricated modular rebar modules and methods of using the same Abandoned US20160108618A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US14/874,545 US20160108618A1 (en) 2014-10-17 2015-10-05 Prefabricated modular rebar modules and methods of using the same

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US14/517,113 US20170321421A9 (en) 2014-10-16 2014-10-17 Prefabricated modular rebar modules and methods of using the same
US14/874,545 US20160108618A1 (en) 2014-10-17 2015-10-05 Prefabricated modular rebar modules and methods of using the same

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US14/517,113 Division US20170321421A9 (en) 2014-10-16 2014-10-17 Prefabricated modular rebar modules and methods of using the same

Publications (1)

Publication Number Publication Date
US20160108618A1 true US20160108618A1 (en) 2016-04-21

Family

ID=55748609

Family Applications (1)

Application Number Title Priority Date Filing Date
US14/874,545 Abandoned US20160108618A1 (en) 2014-10-17 2015-10-05 Prefabricated modular rebar modules and methods of using the same

Country Status (1)

Country Link
US (1) US20160108618A1 (en)

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760055A (en) * 2017-03-29 2017-05-31 河北建筑工程学院 A kind of vertical connecting structure of fabricated shear wall and its construction method
CN107165313A (en) * 2017-06-28 2017-09-15 姜雯雯 Overlaid plate type concrete shear wall reinforcing bar is fastened and connected node and construction method
CN107916749A (en) * 2017-11-10 2018-04-17 宁乡远大住宅工业有限公司 The enhanced prefabricated outer wall panel of outer impeller and its production method
CN108374504A (en) * 2018-04-27 2018-08-07 中铁建工集团有限公司 Prefabricated assembling type reinforced concrete shear wall structure and its construction method
CN108468402A (en) * 2018-04-03 2018-08-31 中国航天建设集团有限公司 Shear Behavior of R. c. Laminated Slabs precast construction and method
CN108625524A (en) * 2018-06-30 2018-10-09 湖北神州建材有限责任公司 A kind of novel steam-aerated concrete plate
CN108708480A (en) * 2018-08-30 2018-10-26 河北建筑工程学院 A kind of the frame wall filled with masonry structural system and its construction method of sliding slot limit connection
CN108838589A (en) * 2018-07-11 2018-11-20 广州鑫桥建筑工程有限公司 Automatic welding method for reinforcement cage of underground continuous wall
CN109296138A (en) * 2018-11-02 2019-02-01 广西建工集团第三建筑工程有限责任公司 A positioning device and construction method for post-planting steel bars in a structural column
CN109695293A (en) * 2019-02-02 2019-04-30 河北工业大学 A kind of assembled steel tube bank concrete wall formula frame structure system
CN109914617A (en) * 2019-04-19 2019-06-21 中民筑友房屋科技集团有限公司 A kind of assembling frame structural building building
CN109968523A (en) * 2019-04-22 2019-07-05 中建三局基础设施建设投资有限公司 A kind of prefabricated box girder prestress advance positioning device and its implementation method
CN110118011A (en) * 2019-05-28 2019-08-13 天元建设集团有限公司 A kind of automation seat slurry tool and its construction method based on assembled architecture
CN110397069A (en) * 2019-06-28 2019-11-01 天津大学 A single-tube multi-chamber combined foundation structure with supporting structure and its construction method
CN111062075A (en) * 2019-12-11 2020-04-24 三一筑工科技有限公司 Beam-column one-to-one hoop model generation method and device and computing equipment
CN111139934A (en) * 2020-01-16 2020-05-12 清华大学 Structure and method for improving crack resistance of precast reinforced concrete beam-slab joint area
CN111749362A (en) * 2020-08-06 2020-10-09 赵东昕 A prefabricated semi-rigid composite slab
CN112761373A (en) * 2019-11-04 2021-05-07 泰州职业技术学院 Reinforced concrete frame beam structure reinforced by prefabricated checkered plate steel truss
CN114263116A (en) * 2021-12-23 2022-04-01 中交第二航务工程局有限公司 Industrial construction method for concrete bridge tower reinforcing steel bar part
US11346100B1 (en) 2019-08-06 2022-05-31 Kim D. Blackburn Tilt-up and precast construction panels
CN114799742A (en) * 2022-03-30 2022-07-29 中钢集团西安重机有限公司 Nozzle beam and manufacturing method and machining tool thereof
CN114875967A (en) * 2022-06-15 2022-08-09 中建八局第三建设有限公司 Novel pre-buried construction method of two-wall-in-one ground connection wall steel bar connector
CN114961274A (en) * 2022-06-08 2022-08-30 中交第二航务工程局有限公司 Method for assembling block-type box girder steel reinforcement framework
CN115262751A (en) * 2022-08-31 2022-11-01 陕西建筑产业投资集团有限公司 Construction method of low-rise fabricated concrete structure system
US20220356706A1 (en) * 2019-09-23 2022-11-10 Midland Steel Reinforcement Supplies Limited Reinforcing Steel Skeletal Framework
CN115434353A (en) * 2022-09-30 2022-12-06 上海核工程研究设计院有限公司 Design and construction method of fabricated nuclear island raft foundation reinforcement truss structure
US20230111206A1 (en) * 2021-10-13 2023-04-13 Ruentex Engineering & Construction Co., Ltd. Tie bar for shear wall, shear wall, and method for constructing the same
USD984243S1 (en) * 2019-05-23 2023-04-25 Dan Warren Brazed rebar gabion façade
US20240109224A1 (en) * 2022-09-30 2024-04-04 Ruentex Engineering & Construction Co., Ltd. Waffle slab and structures and method of manufacturing the same
US20240254769A1 (en) * 2022-03-25 2024-08-01 Shahn Christian Andersen Modular Prefabricated Rebar Component
CN118564059A (en) * 2024-06-26 2024-08-30 中国核工业第二二建设有限公司 Complex steel bar full-module construction method for reactor
US12378743B2 (en) * 2022-02-24 2025-08-05 Jyu Sin Steel Co., Ltd Multi-piece pre-assembled raft foundation and construction method thereof
WO2026007867A1 (en) * 2024-07-05 2026-01-08 广东铝遊家科技有限公司 Beam-column rebar connection structure for prefabricated concrete building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5038541A (en) * 1988-04-01 1991-08-13 Gibbar Jr James H Polymer building wall form construction
US5216860A (en) * 1991-07-16 1993-06-08 Maploca Of Illinois, Inc. Building system for reinforced concrete construction
US5218809A (en) * 1990-04-14 1993-06-15 Baumann Hanns U Earthquake resistant structure utilizing a confinement reinforcing framework
US7562613B2 (en) * 2003-12-19 2009-07-21 The Cooper Union For The Advancement Of Science And Art Protective structure and protective system
US20100272509A1 (en) * 2009-04-27 2010-10-28 Tri-State Construction, Inc. Traffic barrier section
US20110247291A1 (en) * 2010-04-07 2011-10-13 Adrian Hammon Reinforcement Bar Support Device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5038541A (en) * 1988-04-01 1991-08-13 Gibbar Jr James H Polymer building wall form construction
US5218809A (en) * 1990-04-14 1993-06-15 Baumann Hanns U Earthquake resistant structure utilizing a confinement reinforcing framework
US5216860A (en) * 1991-07-16 1993-06-08 Maploca Of Illinois, Inc. Building system for reinforced concrete construction
US7562613B2 (en) * 2003-12-19 2009-07-21 The Cooper Union For The Advancement Of Science And Art Protective structure and protective system
US20100272509A1 (en) * 2009-04-27 2010-10-28 Tri-State Construction, Inc. Traffic barrier section
US20110247291A1 (en) * 2010-04-07 2011-10-13 Adrian Hammon Reinforcement Bar Support Device

Cited By (36)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760055A (en) * 2017-03-29 2017-05-31 河北建筑工程学院 A kind of vertical connecting structure of fabricated shear wall and its construction method
CN107165313A (en) * 2017-06-28 2017-09-15 姜雯雯 Overlaid plate type concrete shear wall reinforcing bar is fastened and connected node and construction method
CN107916749A (en) * 2017-11-10 2018-04-17 宁乡远大住宅工业有限公司 The enhanced prefabricated outer wall panel of outer impeller and its production method
CN108468402A (en) * 2018-04-03 2018-08-31 中国航天建设集团有限公司 Shear Behavior of R. c. Laminated Slabs precast construction and method
CN108374504A (en) * 2018-04-27 2018-08-07 中铁建工集团有限公司 Prefabricated assembling type reinforced concrete shear wall structure and its construction method
CN108625524A (en) * 2018-06-30 2018-10-09 湖北神州建材有限责任公司 A kind of novel steam-aerated concrete plate
CN108838589A (en) * 2018-07-11 2018-11-20 广州鑫桥建筑工程有限公司 Automatic welding method for reinforcement cage of underground continuous wall
CN108708480A (en) * 2018-08-30 2018-10-26 河北建筑工程学院 A kind of the frame wall filled with masonry structural system and its construction method of sliding slot limit connection
CN109296138A (en) * 2018-11-02 2019-02-01 广西建工集团第三建筑工程有限责任公司 A positioning device and construction method for post-planting steel bars in a structural column
CN109695293A (en) * 2019-02-02 2019-04-30 河北工业大学 A kind of assembled steel tube bank concrete wall formula frame structure system
CN109914617A (en) * 2019-04-19 2019-06-21 中民筑友房屋科技集团有限公司 A kind of assembling frame structural building building
CN109968523A (en) * 2019-04-22 2019-07-05 中建三局基础设施建设投资有限公司 A kind of prefabricated box girder prestress advance positioning device and its implementation method
USD984243S1 (en) * 2019-05-23 2023-04-25 Dan Warren Brazed rebar gabion façade
CN110118011A (en) * 2019-05-28 2019-08-13 天元建设集团有限公司 A kind of automation seat slurry tool and its construction method based on assembled architecture
CN110397069A (en) * 2019-06-28 2019-11-01 天津大学 A single-tube multi-chamber combined foundation structure with supporting structure and its construction method
US11346100B1 (en) 2019-08-06 2022-05-31 Kim D. Blackburn Tilt-up and precast construction panels
US11834825B2 (en) 2019-08-06 2023-12-05 Kim D Blackburn Tilt-up and precast construction panels
US20220356706A1 (en) * 2019-09-23 2022-11-10 Midland Steel Reinforcement Supplies Limited Reinforcing Steel Skeletal Framework
CN112761373A (en) * 2019-11-04 2021-05-07 泰州职业技术学院 Reinforced concrete frame beam structure reinforced by prefabricated checkered plate steel truss
CN111062075A (en) * 2019-12-11 2020-04-24 三一筑工科技有限公司 Beam-column one-to-one hoop model generation method and device and computing equipment
CN111139934A (en) * 2020-01-16 2020-05-12 清华大学 Structure and method for improving crack resistance of precast reinforced concrete beam-slab joint area
CN111749362A (en) * 2020-08-06 2020-10-09 赵东昕 A prefabricated semi-rigid composite slab
US12404672B2 (en) * 2021-10-13 2025-09-02 Ruentex Engineering & Construction Co., Ltd Tie bar for shear wall, shear wall, and method for constructing the same
US20230111206A1 (en) * 2021-10-13 2023-04-13 Ruentex Engineering & Construction Co., Ltd. Tie bar for shear wall, shear wall, and method for constructing the same
CN114263116A (en) * 2021-12-23 2022-04-01 中交第二航务工程局有限公司 Industrial construction method for concrete bridge tower reinforcing steel bar part
US12378743B2 (en) * 2022-02-24 2025-08-05 Jyu Sin Steel Co., Ltd Multi-piece pre-assembled raft foundation and construction method thereof
US20240254769A1 (en) * 2022-03-25 2024-08-01 Shahn Christian Andersen Modular Prefabricated Rebar Component
CN114799742A (en) * 2022-03-30 2022-07-29 中钢集团西安重机有限公司 Nozzle beam and manufacturing method and machining tool thereof
CN114961274A (en) * 2022-06-08 2022-08-30 中交第二航务工程局有限公司 Method for assembling block-type box girder steel reinforcement framework
CN114875967A (en) * 2022-06-15 2022-08-09 中建八局第三建设有限公司 Novel pre-buried construction method of two-wall-in-one ground connection wall steel bar connector
CN115262751A (en) * 2022-08-31 2022-11-01 陕西建筑产业投资集团有限公司 Construction method of low-rise fabricated concrete structure system
CN115434353A (en) * 2022-09-30 2022-12-06 上海核工程研究设计院有限公司 Design and construction method of fabricated nuclear island raft foundation reinforcement truss structure
US20240109224A1 (en) * 2022-09-30 2024-04-04 Ruentex Engineering & Construction Co., Ltd. Waffle slab and structures and method of manufacturing the same
US12416151B2 (en) * 2022-09-30 2025-09-16 Ruentex Engineering & Construction Co., Ltd. Waffle slab and structures and method of manufacturing the same
CN118564059A (en) * 2024-06-26 2024-08-30 中国核工业第二二建设有限公司 Complex steel bar full-module construction method for reactor
WO2026007867A1 (en) * 2024-07-05 2026-01-08 广东铝遊家科技有限公司 Beam-column rebar connection structure for prefabricated concrete building

Similar Documents

Publication Publication Date Title
CA2867964C (en) Prefabricated modular rebar modules and methods of using the same
US20160108618A1 (en) Prefabricated modular rebar modules and methods of using the same
US11598056B2 (en) Module for a structure
US7596909B1 (en) Prefabricated building having a pre-cast concrete chain wall foundation
CN103140639A (en) A building structure
JP7082522B2 (en) Precast synthetic deck joint structure
KR101614842B1 (en) frame system of buildings using the pc-column with overhanging beam applicable various span without increase of story-height
JP5261296B2 (en) Building construction method
KR101324884B1 (en) Hybrid building construction method combining dry type and wet type
EP3535460A1 (en) Reinforcing framework and slab design
KR20130081850A (en) Caisson having assembly-type or single block-type base slab, and manufacturing system and method thereof
JP2017223055A (en) Formwork / rebar integrated structure, reinforced concrete, and formwork / rebar integrated construction method
JP6902760B2 (en) How to build a concrete structure
JPH05222766A (en) Building method
JP2008190232A (en) Exterior foundation unit, exterior foundation structure, and construction method of exterior foundation
NO342534B1 (en) A connecting means of a building structure and a method of using same
JP6539914B2 (en) Steel girder joint structure and steel girder joint method
Bywaters et al. Modern methods of construction
JPS63272847A (en) Reinforced concrete construction method using plate reinforcement
HK40036836A (en) Composite structural wall and method of construction thereof
BR112017024905B1 (en) MODULE FOR A STRUCTURE, STRUCTURE, ASSEMBLY OF A FORM MEMBER, REINFORCED MODULAR BRIDGE, REINFORCED BRIDGE, CONSTRUCTION METHOD, MODULES FOR A STRUCTURE, PACKAGING METHOD, AND, SELF-SUFFICIENT MODULE FOR A STRUCTURE
CN109736834A (en) Installation process method and apparatus, processor and the memory of inverted arch prefabricated film
OA18683A (en) A Module for a structure
KR20170135242A (en) How to build parking
HK1250527A1 (en) A module for a structure

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION