JP4016591B2 - Process management method, process management apparatus, and computer-readable recording medium recording process management program - Google Patents

Process management method, process management apparatus, and computer-readable recording medium recording process management program Download PDF

Info

Publication number
JP4016591B2
JP4016591B2 JP2000352621A JP2000352621A JP4016591B2 JP 4016591 B2 JP4016591 B2 JP 4016591B2 JP 2000352621 A JP2000352621 A JP 2000352621A JP 2000352621 A JP2000352621 A JP 2000352621A JP 4016591 B2 JP4016591 B2 JP 4016591B2
Authority
JP
Japan
Prior art keywords
department
information
work
request
specialized
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000352621A
Other languages
Japanese (ja)
Other versions
JP2002157389A (en
Inventor
茂男 白鳥
浩樹 下川
清司 今井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu Ltd
Original Assignee
Fujitsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu Ltd filed Critical Fujitsu Ltd
Priority to JP2000352621A priority Critical patent/JP4016591B2/en
Publication of JP2002157389A publication Critical patent/JP2002157389A/en
Application granted granted Critical
Publication of JP4016591B2 publication Critical patent/JP4016591B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務の作業工程を管理する技術に関する。
【0002】
【従来の技術】
従来から工場の製造ラインや生産業務などの定型業務では、ガントチャート法やパート図法などの工程管理手法が公知である。また、業務フローは定型的に定義できるが、各作業部門の前後関係は不定である、といった半定型業務ではワークフローの手法も公知である。
【0003】
しかし、一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務においては、これら公知の手法を適用することが甚だ困難である。なぜなら、従来のワークフロー法ではある作業結果から想定される次の専門担当部門を複数事前に設定することはできるが、あくまでも狭い範囲に限らなければならなかった。ある作業が次の作業要求を発生する、という作業の入れ子構造を許すならば、その入れ子がどこまで深くいくか、どこまで広く広がるかに事前制限を設けないならばフロー定義は無限に発散してしまうからである。
【0004】
このような問題解決型業務としては、新規商品の開発業務、病院における患者の診療業務などあるが、典型的な問題解決型業務としてはユーザ稼働情報処理システムの障害通知を受けるヘルプデスク部門をサポートする障害調査業務が挙げられる。このような業務ではある専門担当部門が障害現象を通知され調査中に、更なる資料採取が必要であるとか、他の専門分野で調査してもらわなければ先へ進めない、といった理由で、他の専門担当部門に作業を依頼して自らは一旦作業を中断する、といった事態がしばしば出現する。一方、ヘルプデスクの扱う多種の製品システムは多くの専門担当部門の担当するハードソフト部品の複雑な構成からなっており、これら関与する専門担当部門の作業が次にどの専門担当部門へ作業依頼を発生するのかは、実際のケースバイケースであり、とうてい事前に制限することができないと思われる。また、他社製品を組み込んだケースでは、他社の専門担当部門に調査を依頼することも多い。
【0005】
その結果、従来の工程管理では最初に窓口となった専門担当部門のみが作業者として管理され、その内部における他の専門担当部門への調査依頼や結果回答は工程管理側からは見えなかった。しかし、各専門担当部門の作業状況やそれに基づく他の専門担当部門の作業などの真の作業状況を正確に把握しなければ、このような問題解決型業務の工程管理を効率的に行うことはできない。
【0006】
また、一つの障害調査を通常インシデントと称するが、これを一つの業務と数えると、年間数万インシデントを扱う大規模なヘルプデスクの実態では、後方の数十の専門担当部門や提携他社ベンダーに毎日100件以上の業務が降り注いでいることになる。このような環境では各専門担当部門が現在真に担当しているインシデントはいくつあるのか、繁忙度はどうなのか、あるインシデントはどの専門担当部門が受けて、現在真に担当している専門担当部門はどこなのか、どこの専門担当部門で調査が滞っているのか、などを把握する必要がある。
【0007】
さらに、このような各専門担当部門の真に作業をおこなった部門消費時間の実績はインシデント内容と合わせてデータベース化することにより、今後のこれら専門担当部門の作業の目標管理や提携調査契約内容を検討するための基礎データとなるのであるが、従来はこのような真の部門消費時間を計測する工程管理手法がなかったために、これら基礎データを積み重ねることができなかった。
【0008】
【発明が解決しようとする課題】
このように従来の工程管理方法では、各専門担当部門の作業状況やそれに基づく他の専門担当部門の作業などの真の作業状況を正確に把握せず、あるインシデントはどの専門担当部門が受けて、現在真に担当している専門担当部門はどこなのか、どこの専門担当部門で調査が滞っているのかがわからず、各専門担当部門の真の部門消費時間を計測することができない、という課題があった。
【0009】
【課題を解決するための手段】
一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務では、ある専門担当部門の作業過程で予期せぬ他部門の別の作業が必要となるなど、従来の工程管理ツールでは実態把握が困難である、という上記の課題は、各専門担当部門の操作するクライアント装置と通信するサーバ装置において、図2に示す如く、(A) 課題管理部門から入力された課題識別子を含む課題登録情報を検出して部門消費時間データベース上に当該課題にかかわる部門消費時間データ領域を作成する段階と、(B) 前記課題管理部門から受けた課題登録情報に基づき、依頼先専門担当部門を特定して作業依頼情報を送出するとともに当該依頼先専門担当部門に関連づけた部門消費時間計測を開始する段階と、(C) 各専門担当部門から入力された作業結果情報を解析して、作業結果が完結していれば当該作業の依頼元部門を特定して前記作業結果情報を送出し、作業結果が次の依頼先専門担当部門の作業を要求する場合は次依頼先部門を特定して前記作業結果情報とともに次作業依頼情報を送出する段階と、(D) 前記段階(C) にて特定された送出先の専門担当部門に関連づけた部門消費時間計測を開始する段階と、(E) 前記段階(C) にて入力された作業結果情報を解析して、当該入力元の専門担当部門に関連づけた部門消費時間計測を停止する段階と、(F) 前記部門消費時間計測の開始、停止に基づいて、専門担当部門毎の部門消費時間を算出し、部門消費時間データベースに記録する段階と、を有する工程管理方法よって解決される。
【0010】
また、本発明の工程管理装置は図1に示す如く、各専門担当部門の操作する工程管理クライアント装置1と、これと通信して工程管理する工程管理サーバ装置2とからなる。図1ではその実施の一例として、工程管理クライアント装置1では通常の公知のウェブブラウザによって工程管理サーバ装置2に情報送信を行い、また、工程管理サーバ装置2からの情報受信は通常の公知の電子メールサーバを介して、通常の公知のウェブメーラによって行う例を掲げた。
【0011】
すなわち、段階(A)では課題管理部門の工程管理クライアント装置からウェブ画面上で工程管理サーバ装置2を呼び出し、ウェブページ入出力制御手段21に課題登録情報Kを入力する。段階(B)ではこの課題登録情報Kを課題登録手段23によって解析し、データベース更新手段24を用いて必要な部門消費時間データ領域rを部門消費時間データベース26上に生成する。また、入力解析手段27を通じて課題登録情報Kから作業依頼情報Iを抽出し、メール作成手段28はこれを次作業依頼情報I’としてウェブメーラ22にわたす。また、これと同時に入力解析手段27は部門消費時間計測手段25を通じて部門消費時間計測を開始する。
【0012】
段階(C)では工程管理クライアント装置1からウェブページ入出力制御手段21を通じて得られた作業結果情報res を入力解析手段27が解析し、必要な送出先を決定する。メール作成手段28はこの送出先に従って作業結果情報res と必要あれば次作業依頼情報I’を組み立ててウェブメーラ22を通じて指定の工程管理クライアント装置1にメールとしてわたす。段階(D)はこれと同時に入力解析手段27は部門消費時間計測手段25を起動し、必要な部門消費時間計測を開始する。また、これと同時に、段階(E)で部門消費時間計測手段25は入力解析手段27から規定された作業結果情報res 送出元の部門消費時間の計測を停止する。
【0013】
段階(F)では部門消費時間計測手段25は停止した計測の部門消費時間を算出してデータベース更新手段24を起動してこれを部門消費時間データベース26に記録する。
【0014】
【発明の実施の形態】
本発明の工程管理方法の実施例を図1〜図7により説明する。なお、本発明におけるコンピュータ処理は、コンピュータプログラムにより当該コンピュータの主記憶装置上で実行されるが、このコンピュータプログラムの提供形態は、当該コンピュータに接続された補助記憶装置をはじめ、フロッピーディスクやCD−ROM等の可搬型記憶装置やネットワーク接続された他のコンピュータの主記憶装置及び補助記憶装置等の各記録媒体に格納されて提供されるもので、このコンピュータプログラムの実行に際しては、当該コンピュータの主記憶装置上にローディングされ実行されるものである。
【0015】
図1に本発明の工程管理装置の一つの構成例を示す。本実施例では工程管理クライアント装置1と工程管理サーバ装置2との通信の手段として通常の公知のウェブブラウザ、およびウェブメーラを使用した。従って本例の実施には通常の公知の電子メールサーバの介在が必要であるが、この構成によって、工程管理クライアント装置1、工程管理サーバ装置2ともインプリメンテーションが大幅に簡略化できる。もちろん、ウェブブラウザまたはウェブメーラに代えて、固有の情報送受信手段を作成することも可能であり、本発明はこれをも含むものであることは言うまでもない。また、本実施例ではウェブページ入出力制御手段21によって工程管理クライアント装置1のウェブブラウザからの情報受信を行う構成としたが、ウェブページ入出力制御手段21をも通常の公知のウェブメーラとし、すべての情報送受信を電子メールによって行うことも可能であり、この場合、工程管理サーバ装置2は電子メールサーバから見たらメールクライアントの位置づけとなるが、本発明はこれをも含むものであることは言うまでもない。
【0016】
本出願明細書では、『業務』は一つの課題解決のための『作業』の総和であり、『作業』は一つの専門担当部門の一区切りの時間消費に対応する単位と定義する。従って、一つの『業務』は複数の『作業』からなり、一つの『作業』には一つの専門担当部門と一つの部門消費時間が対応する。ある専門担当部門Aが調査中に別の専門担当部門Bの調査を依頼し、Bの調査結果を得てAの作業が続行する場合、本明細書ではこれを『Aのはじめの作業』『Bの作業』『Aのあとの作業』の3つの作業として、それぞれの専門担当部門に関連づけて管理するものとする。
【0017】
図2に従って、本発明の工程管理装置の部門消費時間管理動作を説明する。なお、本実施例では前記問題解決型業務としてはヘルプデスクをサポートする障害調査業務を想定し、前記課題管理部門はユーザ稼働情報処理システムの障害通知を受けるヘルプデスク部門である場合を想定して以下の説明を行う。
【0018】
課題管理部門であるヘルプデスク部門から工程管理サーバ装置2に対し課題登録情報Kが入力されることによってシステム動作が開始する。この入力方法は種々考えられるが、本例では、課題管理部門も工程管理クライアント装置1を持っており、ウェブページ入出力制御手段21の画面を通じて課題登録情報Kを入力するものとした。
【0019】
さて、図2のステップS201で、上記課題登録情報Kの入力が得られ、ステップS202でウェブページ入出力制御手段21は課題登録情報Kであることを認識して図3(a) の課題登録情報Kの処理へと進む。ステップS301はステップS202の分岐を再掲したものである。次いでステップS302によって、課題登録手段23が起動され、データベース更新手段24は部門消費時間データベース26上に部門消費時間データ領域rを作成する。その詳細を以下に示す。
【0020】
課題登録情報Kは図3(b) に示すような要素構成をもつ。課題識別子idはヘルプデスクの場合インシデント番号として発行されるものである。依頼元部門名はxxx(課題管理部門名) である。緊急度は障害内容や障害システムの構成、業務状況などによって決まるもので、数字が小さいほど緊急に復旧が必要である。依頼内容(zzzzzz..)は本インシデントの内容を示すもので、障害の状況や採取したログデータなどを依頼先専門担当部門に伝えるものである。
【0021】
ステップS302でデータベース更新手段24はこれらの情報を図6に示す如き部門消費時間データ領域rに記入する。ここに部門消費時間データ領域rは部門消費時間データベース26上に課題識別子id=rに対応する領域であり、この時点ではまず図6の課題データベースDKの課題識別子id=r 対応レコードが作られる。ただし、作業履歴フィールドは作業id=001 の要素のみが作られる。そして、データベース更新手段24はこれに対応して作業データベースDW上に課題識別子id=r 、作業id=001( 作業開始) 対応レコード( 図6において※で示すレコード) を生成する。
【0022】
作成された課題データベースDKの課題識別子id=r 対応レコードの各フィールドには課題登録情報Kの対応する内容が記入される。課題登録情報K中の緊急度によって復旧までに許容される許容時間が決まっており、図示しないテーブルで与えられるので、データベース更新手段24はこのテーブルを参照して図6の課題データベースDK( 課題識別子id=r 対応レコード) 上の許容時間フィールドに該当値を書き込む。
【0023】
ステップS302では作業データベースDW上の作業id=001レコードには課題識別子idフィールド=r 、作業idフィールド=001の他、依頼元部門名フィールドのみを記入する。ここに依頼元部門名は図3(b) の課題登録情報Kの依頼元部門名すなわちxxx(課題管理部門名) を転記する。
【0024】
次いでステップS303において課題登録手段23は課題登録情報Kの依頼コード(例えばOD237)によって依頼先専門担当部門ij001 を特定する。依頼コードは障害の製品構成、ユーザを区別するが、通常、障害システムの製品構成によって、最初に調査を依頼する専門担当部門は定まっているので、本実施例では依頼コードと専門担当部門とを対応づける図示しないテーブルがあるものとし、課題登録手段23はこれを参照して最初の依頼先専門担当部門ij001 を決定し担当部門名hbフィールドに記入するとともに入力解析手段27にこれを伝える。
【0025】
次いでステップS304で、メール作成手段28は課題登録情報Kの依頼内容フィールドを取り出し、これを作業依頼情報Iとする。そして依頼先専門担当部門ij001 のアドレスを送信先とし作業依頼情報Iを本文とするメールを作成しウェブメーラ22を通じて発信する。
【0026】
このとき、ステップS305で部門消費時間計測手段25を起動し、依頼先専門担当部門ij001 に関連づけた部門消費時間計測を開始する。
【0027】
ここで部門消費時間計測動作および表記について説明する。図6の部門消費時間データベース26の構造から明らかな如く、個々の作業は作業データベースDW上の作業idレコードに対応づけられ、これは課題識別子idと作業idの組で一意に指定される。そして作業データベースDW上の作業idレコードにはON時刻フィールド、OFF 時刻フィールドおよび担当部門名フィールドが配置されているので、これらを使って依頼先専門担当部門ij001 に関連づけた部門消費時間計測が可能である。すなわち、ステップS302において生成された作業データベースDW上の作業id=001レコードは課題識別子idフィールド=r、担当部門名ij001 を有しており、そのON時刻フィールドを図3のフロー上ではON(r,ij001) と表記する。また 、工程管理サーバ装置2のもつ時計を参照する関数 now()によって現在年月日時分が得られるので、これをON時刻フィールドに記入する動作をON(r,ij001)=now() と表記する。図6※レコードに示す如く、このようにしてON時刻フィールドに現在年月日時分が設定される。
【0028】
また、課題データベースDKの課題識別子id=rレコードの現在状態コードには、部門消費時間計測手段25がON時刻フィールドを更新する都度、現在作業中の状態を示すコード値である作業中担当部門名が格納される。従って、課題データベースDKのr レコード( 課題識別子id=rのレコード) の現在状態コードフィールドの値を見れば、当該課題r についての現在の担当部門がわかる。なお、このフィールドは最後に課題管理部門に最終の作業結果情報res が帰されたときに課題解決状態を示す値"CLOSE" が記入される。
【0029】
このようにステップS305で部門消費時間計測手段25は課題データベースDK上の現在状態コードフィールドに担当部門名ij001 を記入するが、このフィールドを図3のフロー上でS(r)と表記し、S(r)=ij001 によって現在依頼先専門担当部門ij001 が当該課題の作業を担当していることを課題データベースDK上に記録することを意味する。
【0030】
以上によって、図2のステップS202で課題登録情報Kを検出した場合の動作を説明した。次いで、ステップS203に移る。一般に作業を依頼された専門担当部門では当該作業を行い、やがてその結果を工程管理クライアント装置1から工程管理サーバ装置2に入力する。図7にはその入力情報である作業結果情報res および作業依頼情報Iのデータ構造を示し、その入力ウィンドウの一端である状況報告ウィンドウ等の例を示す。
【0031】
ステップS203でウェブページ入出力制御手段21は工程管理クライアント装置1からの作業結果情報res 入力を受け、データベース更新手段24はこれを作業データベースDW上の現作業idレコードの該当フィールドに記入する。作業結果情報res の発信日時、発信元アドレスのほかの入力については、本実施例では入力画面は図7に示すように結果入力ウィンドウ、状況報告ウィンドウ、依頼入力ウィンドウの3つのサブウィンドウから入力する。結果本文は添付ファイルを伴ってもよく、ウィンドウに記入された内容が作業結果情報res の該当フィールドに格納される。作業依頼情報Iは次作業依頼が伴う時のみ生成され、依頼入力ウィンドウの内容が作業依頼情報Iの依頼本文フィールドに転記される。
【0032】
状況報告ウィンドウは作業結果情報res の性格を示す情報を入力するウィンドウである。本実施例では図7に示すように、1〜4の4つの選択肢を用意した。1は当該作業が完了したことを示す。2は中間報告であり、なお当該専門担当部門が作業中であることを示す。3は次作業の依頼を示し、その結果受領によって当該専門担当部門が作業を再開することを示す。4は作業を他の専門担当部門に移転することを希望している。上記3、4では次依頼先部門ijを画面で指定して入力する。
【0033】
ステップS203〜207については図8を併せて参照しつつ説明する。ステップS203でウェブページ入出力制御手段21はこれら記入された作業結果情報res を受け、入力解析手段27は次作業依頼フラグが3または4である場合にステップS204へ、次作業依頼フラグが1である場合にステップS205へ制御を移す。次作業依頼フラグが2の場合は同一部門で作業を続けるので本工程管理サーバ装置2では無視する。また、4の場合も3の場合と同じ制御を行い、作業間のリンクを保つものとする。
【0034】
次にステップS204の段階(C1)においては、データベース更新手段24は現作業id=nn を参照して次作業id=nn+1 を発行し、課題データベースDKの作業履歴および現作業id=nn レコードとリンクする次作業id=nn+1 のレコードを作業データベースDW上に生成する。このとき図8中に矢印で示すように依頼元部門名、担当部門名のフィールド値も書き込まれる。
【0035】
ステップS204および205の段階(C1)では入力解析手段27は課題データベースDKの作業履歴最終の作業id=nn 要素からリンクする当該発信元専門担当部門hbの作業に対応する作業id=nn レコードを調べ、その次作業依頼フラグに従って、ステップS204のときは次依頼先部門フィールド値を、ステップS205のときは依頼元部門名フィールド値を次送出先と設定してメール作成手段28に伝える。この様子を図8では太破線のかこみで示した。そしてステップS204および205の段階(C2)では、上記次送出先に対しメール作成手段28は現作業id=nn レコードの作業結果情報res および次作業依頼情報I’(ステップS204のみ)を本文としてウェブメーラ22に発信を指示する。
【0036】
段階(D)は図8に示す如く、データベース更新手段24は各送出先に対応する作業idレコード中のON時刻フィールドに現在年月日時分を設定する。また対応する値を課題データベースDKのr レコード( 課題識別子id=rのレコード) の現在状態コードフィールドに設定する。(図8に(D)と記した部分である。)これらの動作はすでに述べたステップS305の説明と同一であるので省略する。
【0037】
次にステップS206に移り、作業結果情報res の受信に対応して部門消費時間計測手段25は発信元専門担当部門hbに対応する作業id=nn レコードのOFF 時刻フィールドに現在年月日時分を設定する。これは図8に段階(E)における記入として示すとおりである。ステップS207は段階(F)に対応し、部門消費時間計測手段25はOFF 時刻フィールド書込時にその同一レコード中のON時刻フィールド値を参照して、部門消費時間=OFF 時刻フィールド値−ON時刻フィールド値を部門消費時間フィールドに書き込む。なお、図示していないが、部門消費時間計測手段25はリアルタイムクロック割り込みによって常時、課題データベースDK上の作業履歴最終作業idをたどり現作業idレコードをとらえ、その部門消費時間フィールドにnow() −ON時刻フィールド値を記入する。この動作により、作業データベースDW上のすべての作業idレコードが常に部門消費時間フィールドに正しい部門消費時間を格納していることになり、常時の検索に対処できる。
【0038】
最後に、本発明の工程管理装置の部門消費時間管理画面表示例について図4〜5により説明する。工程管理クライアント装置1画面上にはウェブページ入出力制御手段21により常時ホームページが表示されている。その一部またはリンクする別ウィンドウで種々の部門消費時間管理画面を検索することができる。その動作は図4の如くであり、ステップS401で検索メニューを表示してクリック選択を待ち、ステップS402〜404で選択された画面表示を行う。
【0039】
本実施例では、作業(または作業遂行責任)を現在担っている状態をボールを保持している、と例えることとしている。従って、あるインシデント発行に伴って課題管理部門から最初の専門担当部門にボールが打ち込まれ、それを課題管理部門に返したり他の専門担当部門に打ち返す等のシーケンスとしてとらえる。
【0040】
あるインシデントの現在のボールの行方を調べたい管理者は、メニューから『ボール保持部門一覧』を選択する。ステップS402では表示画面作成手段29は図4(b) の如き画面を作成して表示する。すなわち、部門消費時間データベース26の課題データベースDKから全課題識別子id(『インシデント番号』欄に対応)分のレコードについて、その現在状態フィールド値を『ボール保持』欄に示す。その値が"CLOSE" は『終了』で表示される。また、『累積時間』欄は課題データベースDKの課題識別子id=rレコードにリンクする作業データベースDW上の全作業idレコードの部門消費時間フィールド値の和で求められ、例えば05日23時間40分と表示する。また現在状態フィールド値が"CLOSE" の場合は最終作業idにリンクする作業データベースDW上の作業idレコードのOFF 時刻フィールド値を画面の『終了日付』欄に表示する。図4(b) では終了でない『ボール保持』欄を太枠で、また累積時間が許容時間を越えた欄を囲み印で強調表示する例を示したが、色や文字フォントによって強調表示してもよい。
【0041】
図5(a) はステップS401で『課題別部門消費時間一覧』が選択された場合にステップS403で表示画面作成手段29が生成した画面例である。この例では表示画面作成手段29は部門消費時間データベース26上の課題データベースDKから全課題識別子id(『インシデント番号』欄に対応)分のレコードについて、個々の課題識別子idレコードにリンクする作業データベースDW上の全作業idレコードを順にたどり、担当部門名hbフィールドごとにその部門消費時間を累積して部門別に表示したものである。図の例では課題識別子id=1008-397 、担当部門名hb=pppでは累積部門消費時間=05日23時間40分、担当部門名hb=qqq では累積部門消費時間=01日13時間20分、等々である。
【0042】
図5(b) はステップS401で『部門別全課題消費時間一覧』が選択された場合にステップS404で表示画面作成手段29が生成した画面例である。この例では表示画面作成手段29は部門消費時間データベース26上の課題データベースDKから、検索指定された期間(00/01/01 〜00/10/15) を依頼日時フィールド値にもつ課題識別子id(『インシデント番号』欄に対応)分のレコードににリンクする作業データベースDW上の全作業idレコードから特定の検索指定を受けた担当部門名hb=pppを持つ作業データベースDW上の作業idレコードの部門消費時間フィールド値をすべて累積するものである。
【0043】
このような場合、検索指定を受けてから上記検索を行ってもよいが、検索時間を縮めるために、図6に示すような専門担当部門データベースDSを常時作成しておくと、この専門担当部門データベースDSをサーチすることにより高速に図5(b) の画面を提供できる。このような専門担当部門データベースDSの更新はステップS206の個々の作業データベースDW上の作業idレコードのOFF 時刻フィールド記入時に併せて行うほか、前記リアルタイムクロック割り込みによって常時、課題データベースDK上の作業履歴最終作業idをたどり現作業idレコードをとらえ、その部門消費時間フィールドにnow() −ON時刻フィールド値を記入する時点でも併せ行えば常時更新されていることになる。
(付記1) 課題発生を管理する課題管理部門から与えられた一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務の作業工程を管理する工程管理方法であって、
各専門担当部門の操作するクライアント装置と通信するサーバ装置において、
(A) 課題管理部門から入力された課題識別子を含む課題登録情報を検出して部門消費時間データベース上に当該課題にかかわる部門消費時間データ領域を作成する段階と、
(B) 前記課題管理部門から受けた課題登録情報に基づき、依頼先専門担当部門を特定して作業依頼情報を送出するとともに当該依頼先専門担当部門に関連づけた部門消費時間計測を開始する段階と、
(C) 各専門担当部門から入力された作業結果情報を解析して、作業結果が完結していれば当該作業の依頼元部門を特定して前記作業結果情報を送出し、作業結果が次の依頼先専門担当部門の作業を要求する場合は次依頼先部門を特定して前記作業結果情報とともに次作業依頼情報を送出する段階と、
(D) 前記段階(C) にて特定された送出先の専門担当部門に関連づけた部門消費時間計測を開始する段階と、
(E) 前記段階(C) にて入力された作業結果情報を解析して、当該入力元の専門担当部門に関連づけた部門消費時間計測を停止する段階と、
(F) 前記部門消費時間計測の開始、停止に基づいて、専門担当部門毎の部門消費時間を算出し、部門消費時間データベースに記録する段階と、
を有することを特徴とする工程管理方法。
(付記2) 前記部門消費時間データベースを参照して課題別や専門担当部門別に累積した部門消費時間に関する各種統計データを作成表示する段階を有する付記1記載の工程管理方法。
(付記3) 前記課題登録情報の内容から解決に要する時間の許容限界値である許容時間を設定し、前記許容時間と前記部門消費時間との差である残り時間を算出し、前記許容時間や残り時間との対比を交えて、課題別や専門担当部門別に累積した部門消費時間に関する各種統計データを作成表示する段階、を有する付記1記載の工程管理方法。
(付記4) 前記課題管理部門はユーザ稼働情報処理システムの障害通知を受けるヘルプデスク部門であり、前記問題解決型業務はヘルプデスクをサポートする障害調査業務であることを特徴とする付記1記載の工程管理方法。
(付記5) 付記1記載の工程管理方法であって、さらに、前記部門消費時間データベースを参照して各課題毎に現在部門消費時間計測中の専門担当部門を強調表示する段階を有することを特徴とする工程管理方法。
(付記6) 課題発生を管理する課題管理部門から与えられた一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務の作業工程を管理する工程管理方法であって、
サーバ装置と通信する各専門担当部門のクライアント装置は、
依頼元部門名を含む作業結果情報とともに、次の作業を依頼する送出先専門担当部門を指定した作業依頼情報を送出する段階、を有することを特徴とする工程管理方法。
(付記7) 課題発生を管理する課題管理部門から与えられた一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務の作業工程を管理する工程管理に関する情報処理をコンピュータに行わせるプログラムを記録した記録媒体であって、
(A) 課題管理部門から入力された課題識別子を含む課題登録情報を検出して部門消費時間データベース上に当該課題にかかわる部門消費時間データ領域を作成する段階と、
(B) 前記課題管理部門から受けた課題登録情報に基づき、依頼先専門担当部門を特定して作業依頼情報を送出するとともに当該依頼先専門担当部門に関連づけた部門消費時間計測を開始する段階と、
(C) 各専門担当部門から入力された作業結果情報を解析して、作業結果が完結していれば当該作業の依頼元部門を特定して前記作業結果情報を送出し、作業結果が次の依頼先専門担当部門の作業を要求する場合は次依頼先部門を特定して前記作業結果情報とともに次作業依頼情報を送出する段階と、
(D) 前記段階(C) にて特定された送出先の専門担当部門に関連づけた部門消費時間計測を開始する段階と、
(E) 前記段階(C) にて入力された作業結果情報を解析して、当該入力元の専門担当部門に関連づけた部門消費時間計測を停止する段階と、
(F) 前記部門消費時間計測の開始、停止に基づいて、専門担当部門毎の部門消費時間を算出し、部門消費時間データベースに記録する段階と、
を実現させるプログラムを記録したコンピュータ読み取り可能な記録媒体。
(付記8) 課題発生を管理する課題管理部門から与えられた一つの課題を解決するために、複数の専門担当部門が各自の専門分野の作業を行う問題解決型業務の作業工程を管理する工程管理装置であって、
各専門担当部門の操作するクライアント装置と通信するサーバ装置において、
(A) 課題管理部門から入力された課題識別子を含む課題登録情報を検出して部門消費時間データベース上に当該課題にかかわる部門消費時間データ領域を作成する手段と、
(B) 前記課題管理部門から受けた課題登録情報に基づき、依頼先専門担当部門を特定して作業依頼情報を送出するとともに当該依頼先専門担当部門に関連づけた部門消費時間計測を開始する手段と、
(C) 各専門担当部門から入力された作業結果情報を解析して、作業結果が完結していれば当該作業の依頼元部門を特定して前記作業結果情報を送出し、作業結果が次の依頼先専門担当部門の作業を要求する場合は次依頼先部門を特定して前記作業結果情報とともに次作業依頼情報を送出する手段と、
(D) 前記手段(C) にて特定された送出先の専門担当部門に関連づけた部門消費時間計測を開始する手段と、
(E) 前記手段(C) にて入力された作業結果情報を解析して、当該入力元の専門担当部門に関連づけた部門消費時間計測を停止する手段と、
(F) 前記部門消費時間計測の開始、停止に基づいて、専門担当部門毎の部門消費時間を算出し、部門消費時間データベースに記録する手段と、
を有することを特徴とする工程管理装置。
(付記9) 付記4記載の記録媒体であって、さらに、前記部門消費時間データベースを参照して各課題毎に現在部門消費時間計測中の専門担当部門を強調表示する段階を実現させるプログラムを記録したコンピュータ読み取り可能な記録媒体。
(付記10) 付記5記載の工程管理装置であって、さらに、前記部門消費時間データベースを参照して各課題毎に現在部門消費時間計測中の専門担当部門を強調表示する手段を有することを特徴とする工程管理装置。
【0044】
【発明の効果】
以上の説明から明らかなように、本発明によれば、作業を担当した専門担当部門から入力された作業結果情報を解析して、作業結果が完結していれば当該作業の依頼元部門に前記作業結果情報を送出し、作業結果が次の依頼先専門担当部門の作業を要求する場合は次依頼先部門を特定して前記作業結果情報とともに次作業依頼情報を送出し、これらに関連づけた部門消費時間計測を行い、その結果を種々の管理用画面に表示する段階を備えた工程管理方法により、業務(課題)ごとに各専門担当部門が消費する時間を実測でき、繁忙度の把握や作業目標管理の基礎データを得ることができる、という効果がある。
【図面の簡単な説明】
【図1】本発明の工程管理装置の実施例
【図2】本発明の工程管理装置の部門消費時間管理動作フロー例
【図3】課題登録情報Kの処理例
【図4】本発明の工程管理装置の画面表示動作例
【図5】本発明の工程管理装置の部門消費時間管理画面例
【図6】部門消費時間データベース26の構成例
【図7】作業結果情報res と作業依頼情報Iのデータ構造例
【図8】ステップS203〜207の動作説明
【符号の説明】
1 工程管理クライアント装置
2 工程管理サーバ装置
21 ウェブページ入出力制御手段
22 ウェブメーラ
23 課題登録手段
24 データベース更新手段
25 部門消費時間計測手段
26 部門消費時間データベース
27 入力解析手段
28 メール作成手段
29 表示画面作成手段
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a technique for managing a work process of a problem-solving business in which a plurality of specialized departments perform work in their own specialized field in order to solve one problem.
[0002]
[Prior art]
Conventionally, in routine operations such as factory production lines and production operations, process management techniques such as Gantt chart method and part diagram method are well known. In addition, workflow methods are well known for semi-fixed tasks where the business flow can be defined in a fixed manner but the context of each work department is undefined.
[0003]
However, in order to solve one problem, it is extremely difficult to apply these known methods in problem-solving work in which a plurality of specialized departments work in their own specialized fields. This is because, in the conventional workflow method, it is possible to set in advance a plurality of next specialized departments assumed from a certain work result, but it must be limited to a narrow range. If a work nesting structure that allows a work to generate the next work request is allowed, the flow definition will diverge indefinitely if there is no prior restriction on how deep the nesting will be and how far it will spread. Because.
[0004]
Such problem-solving operations include new product development operations and patient medical treatment operations in hospitals, but typical problem-solving operations support the help desk department that receives failure notifications for user-operated information processing systems. Failure investigation work to be performed. In such a business, a specialized department is informed of the failure phenomenon, and during the investigation, it is necessary to collect further data, or because it cannot proceed unless it is investigated in other specialized fields. There are often situations in which a specialist department in charge of work is suspended and the work is temporarily suspended. On the other hand, the various product systems handled by the help desk consist of complex configurations of hardware and software parts that are handled by many specialized departments. It does occur on an actual case-by-case basis and is unlikely to be limited in advance. Also, in cases where products of other companies are incorporated, surveys are often requested from the specialized departments of other companies.
[0005]
As a result, in the conventional process management, only the department in charge of specialist who became the first contact point is managed as an operator, and the investigation request and the result answer to other departments in charge of the inside are not visible from the process management side. However, if we do not accurately grasp the work status of each specialized department and the work status of other specialized departments based on it, it is not possible to efficiently manage the process of such problem-solving work. Can not.
[0006]
In addition, one trouble investigation is usually called an incident. If this is counted as one work, in the actual situation of a large-scale help desk that deals with tens of thousands of incidents per year, dozens of specialized departments and partner vendors are behind. More than 100 jobs are pouring every day. In such an environment, how many incidents each specialist department is currently in charge of, how busy it is, what specialized department has received an incident, and the specialist department that is currently in charge It is necessary to ascertain where the survey is, and in which specialized department the survey is delayed.
[0007]
Furthermore, the results of the department consumption time that each department in charge of such specialized work actually performed are compiled into a database together with the contents of incidents, so that the future objective management and alliance survey contract contents of these departments in charge of specialized work Although this is basic data for examination, there has been no process management method for measuring such true department consumption time, so it was impossible to accumulate these basic data.
[0008]
[Problems to be solved by the invention]
In this way, the conventional process management method does not accurately grasp the work status of each specialized department and the work status of other specialized departments based on it, and which specialized department receives an incident. , It is impossible to measure the true department consumption time of each department in charge, because it is not known where the department in charge is really in charge and where the department in charge is behind the survey. There was a problem.
[0009]
[Means for Solving the Problems]
In order to solve a single problem, a problem-solving work in which multiple specialized departments work in their own specialized field requires an unexpected work in another department in the course of the work of one specialized department. The above-mentioned problem that it is difficult to grasp the actual situation with the conventional process management tool, such as the server device that communicates with the client device operated by each specialized department, as shown in FIG. Detecting task registration information including the input task identifier and creating a section consumption time data area related to the task on the section consumption time database; and (B) based on the task registration information received from the task management department. , Specify the department in charge of the request destination, send work request information and start measuring the department consumption time associated with the department in charge of the request destination, and (C) from each department in charge Analyzing the received work result information, if the work result is completed, specify the department that requested the work and send the work result information. When requesting, the stage of specifying the next request destination department and sending the next work request information together with the work result information, and (D) the department associated with the department in charge of the destination specified in the stage (C) Starting consumption time measurement, (E) analyzing the work result information input in the step (C), and stopping the department consumption time measurement associated with the specialized department in charge of the input source, (F) Based on the start and stop of the department consumption time measurement, the department management time for each department in charge of the department is calculated and recorded in the department consumption time database.
[0010]
Further, as shown in FIG. 1, the process management apparatus of the present invention comprises a process management client apparatus 1 operated by each specialized department, and a process management server apparatus 2 for performing process management in communication therewith. In FIG. 1, as an example of the implementation, the process management client device 1 transmits information to the process management server device 2 by an ordinary known web browser, and information reception from the process management server device 2 is performed by an ordinary known electronic device. An example is shown in which an ordinary known web mailer is used via a mail server.
[0011]
That is, in step (A), the process management server apparatus 2 is called on the web screen from the process management client apparatus of the problem management department, and the problem registration information K is input to the web page input / output control means 21. In step (B), the task registration information K is analyzed by the task registration means 23, and the necessary department consumption time data area r is generated on the department consumption time database 26 using the database update means 24. Further, the work request information I is extracted from the task registration information K through the input analysis means 27, and the mail creation means 28 passes this to the web mailer 22 as the next work request information I '. At the same time, the input analysis means 27 starts the department consumption time measurement through the department consumption time measurement means 25.
[0012]
In step (C), the input analysis means 27 analyzes the work result information res obtained from the process management client device 1 through the web page input / output control means 21, and determines a necessary destination. The mail creation means 28 assembles the work result information res and, if necessary, the next work request information I ′ in accordance with this destination, and passes it as a mail to the designated process management client device 1 through the web mailer 22. At the same time as step (D), the input analysis means 27 activates the department consumption time measurement means 25 and starts the necessary department consumption time measurement. At the same time, in step (E), the department consumption time measuring means 25 stops measuring the department consumption time of the work result information res sending source defined by the input analysis means 27.
[0013]
In step (F), the department consumption time measuring means 25 calculates the department consumption time of the stopped measurement, starts the database update means 24 and records this in the department consumption time database 26.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
An embodiment of the process management method of the present invention will be described with reference to FIGS. The computer processing in the present invention is executed on the main storage device of the computer by a computer program. The computer program is provided in an auxiliary storage device connected to the computer, a floppy disk, a CD- Provided by being stored in a recording medium such as a portable storage device such as a ROM or a main storage device or an auxiliary storage device of another computer connected to a network. It is loaded and executed on a storage device.
[0015]
FIG. 1 shows one configuration example of the process management apparatus of the present invention. In the present embodiment, an ordinary known web browser and web mailer are used as means for communication between the process management client apparatus 1 and the process management server apparatus 2. Therefore, the implementation of this example requires the intervention of an ordinary known e-mail server. With this configuration, the implementation of both the process management client device 1 and the process management server device 2 can be greatly simplified. Of course, it is possible to create a unique information transmission / reception means instead of the web browser or the web mailer, and it goes without saying that the present invention includes this. Further, in this embodiment, the web page input / output control means 21 is configured to receive information from the web browser of the process management client device 1, but the web page input / output control means 21 is also a normal known web mailer, It is also possible to perform all information transmission / reception by e-mail. In this case, the process management server apparatus 2 is positioned as a mail client when viewed from the e-mail server, but it goes without saying that the present invention includes this. .
[0016]
In the specification of this application, “business” is the sum of “work” for solving one problem, and “work” is defined as a unit corresponding to one segment of time consumption in one specialized department. Accordingly, one “operation” is composed of a plurality of “work”, and one “work” corresponds to one specialized department and one department consumption time. When a specialized department A requests an investigation of another specialized department B during the investigation, and the work of A is continued after obtaining the investigation result of B, this is referred to as “A's first work” “ Assume that the three tasks of “work of B” and “work after A” are managed in association with each specialized department.
[0017]
The department consumption time management operation of the process management apparatus of the present invention will be described with reference to FIG. In this embodiment, it is assumed that the problem-solving work is a trouble investigation work that supports a help desk, and that the problem management department is a help desk department that receives a trouble notification of a user operation information processing system. The following description will be given.
[0018]
The system operation starts when the problem registration information K is input to the process management server apparatus 2 from the help desk department which is the problem management department. In this example, the problem management department also has the process management client device 1 and inputs the problem registration information K through the screen of the web page input / output control means 21.
[0019]
In step S201 in FIG. 2, the input of the task registration information K is obtained. In step S202, the web page input / output control means 21 recognizes that the task registration information K is present, and the task registration in FIG. Proceed to processing information K. Step S301 shows the branch of step S202 again. Next, in step S302, the task registration means 23 is activated, and the database update means 24 creates a department consumption time data area r on the department consumption time database 26. Details are shown below.
[0020]
The assignment registration information K has an element configuration as shown in FIG. The issue identifier id is issued as an incident number in the case of a help desk. The requesting department name is xxx (issue management department name). The degree of urgency is determined by the content of the failure, the configuration of the failure system, the business situation, and the like. The request content (zzzzzz...) Indicates the content of this incident, and conveys the failure status, collected log data, and the like to the department in charge of the request destination.
[0021]
In step S302, the database updating means 24 enters these information in the department consumption time data area r as shown in FIG. Here, the department consumption time data area r is an area corresponding to the assignment identifier id = r on the department consumption time database 26. At this time, a record corresponding to the assignment identifier id = r of the assignment database DK in FIG. 6 is first created. However, only the element of work id = 001 is created in the work history field. Corresponding to this, the database update means 24 generates a task identifier id = r, work id = 001 (work start) corresponding record (record indicated by * in FIG. 6) on the work database DW.
[0022]
The corresponding contents of the task registration information K are entered in each field of the task identifier id = r corresponding record of the created task database DK. The allowable time allowed for recovery is determined by the degree of urgency in the assignment registration information K, and is given by a table (not shown). Therefore, the database update means 24 refers to this table, and the assignment database DK (issue identifier in FIG. Write the corresponding value in the allowable time field above (id = r record).
[0023]
In step S302, in the work id = 001 record on the work database DW, only the requesting department name field is entered in addition to the task identifier id field = r and the work id field = 001. As the request source department name, the request source department name, that is, xxx (the assignment management department name) of the assignment registration information K in FIG.
[0024]
Next, in step S303, the task registration means 23 specifies the requested department in charge ij001 by the request code (for example, OD237) of the task registration information K. The request code distinguishes between the product configuration of the fault and the user. Usually, the department in charge of the request for the investigation is determined initially depending on the product configuration of the fault system. Assume that there is a table (not shown) to be associated, and the task registration unit 23 refers to this to determine the first department ij001 to be specialized for the request destination, fill in the department name hb field, and inform the input analysis unit 27 of this.
[0025]
Next, in step S304, the mail creating means 28 takes out the request content field of the assignment registration information K and uses it as work request information I. Then, an e-mail is created with the address of the request-destination specialist department ij001 as the transmission destination and the work request information I as the text, and is transmitted through the web mailer 22.
[0026]
At this time, the department consumption time measuring means 25 is activated in step S305, and the department consumption time measurement associated with the department ij001 in charge of the requested specialist is started.
[0027]
Here, the department consumption time measurement operation and notation will be described. As is clear from the structure of the department consumption time database 26 in FIG. 6, each work is associated with a work id record on the work database DW, and this is uniquely specified by a set of a task identifier id and a work id. The work id record in the work database DW has an ON time field, an OFF time field, and a department name field in charge, so it is possible to measure the department consumption time associated with the requested department ij001. is there. That is, the work id = 001 record in the work database DW generated in step S302 has an assignment identifier id field = r and a department name ij001 in charge, and the ON time field is ON (r , ij001). In addition, since the current year / month / day / hour / minute is obtained by the function now () that refers to the clock of the process management server device 2, the operation of entering this in the ON time field is expressed as ON (r, ij001) = now () To do. As shown in FIG. 6 * record, the current year / month / day / hour / minute is set in the ON time field in this way.
[0028]
In addition, the current status code of the task identifier id = r record of the task database DK includes the name of the department in charge, which is a code value indicating the current work status, every time the department consumption time measuring means 25 updates the ON time field. Is stored. Therefore, by looking at the value of the current state code field of the r record of the assignment database DK (the record with the assignment identifier id = r), the current department in charge for the assignment r can be known. This field is filled with a value “CLOSE” indicating the problem solving state when the final work result information “res” is finally returned to the problem management department.
[0029]
Thus, in step S305, the department consumption time measuring means 25 enters the department name ij001 in charge in the current status code field on the assignment database DK. This field is represented as S (r) in the flow of FIG. This means that (r) = ij001 records on the assignment database DK that the specialist department in charge of the client ij001 is currently in charge of the assignment.
[0030]
The operation when the task registration information K is detected in step S202 of FIG. 2 has been described above. Next, the process proceeds to step S203. Generally, the department in charge of the work requested to perform the work performs the work, and eventually inputs the result from the process management client device 1 to the process management server device 2. FIG. 7 shows the data structure of the work result information res and work request information I which are the input information, and shows an example of a status report window which is one end of the input window.
[0031]
In step S203, the web page input / output control means 21 receives the work result information res input from the process management client apparatus 1, and the database update means 24 enters this in the corresponding field of the current work id record on the work database DW. In the present embodiment, the input screen is input from three sub-windows of a result input window, a status report window, and a request input window as shown in FIG. The result body may be accompanied by an attached file, and the contents entered in the window are stored in the corresponding field of the work result information res. The work request information I is generated only when the next work request is accompanied, and the contents of the request input window are transferred to the request text field of the work request information I.
[0032]
The status report window is a window for inputting information indicating the nature of the work result information res. In this embodiment, four options 1 to 4 were prepared as shown in FIG. 1 indicates that the work has been completed. 2 is an interim report indicating that the department in charge is working. Reference numeral 3 indicates a request for the next work, and the receipt of the result indicates that the relevant department in charge will resume the work. 4 wishes to transfer the work to other specialized departments. In the above 3 and 4, the next request destination department ij is designated and entered on the screen.
[0033]
Steps S203 to S207 will be described with reference to FIG. In step S203, the web page input / output control means 21 receives the entered work result information res, and the input analysis means 27 advances to step S204 when the next work request flag is 3 or 4, and the next work request flag is 1. If there is, control is passed to step S205. When the next work request flag is 2, the work is continued in the same department and is ignored by the process management server device 2. In the case of 4, the same control as in the case of 3 is performed, and the link between operations is maintained.
[0034]
Next, in the step (C1) of step S204, the database updating means 24 refers to the current work id = nn and issues the next work id = nn + 1, and the work history of the issue database DK and the current work id = nn record. The record of the next work id = nn + 1 linked with the is generated on the work database DW. At this time, field values of the requesting department name and the department name in charge are also written as indicated by arrows in FIG.
[0035]
In the stage (C1) of steps S204 and 205, the input analysis means 27 examines the work id = nn record corresponding to the work of the sender department in charge hb linked from the final work id = nn element of the work database DK. According to the next work request flag, the next request destination department field value is set as the next transmission destination at step S204, and the request source department name field value is set as the next transmission destination at step S205, and is transmitted to the mail creating means 28. This state is shown by a bold broken line in FIG. At the stage (C2) of steps S204 and 205, the mail creation means 28 sends the work result information res and the next work request information I ′ (only step S204) of the current work id = nn record to the next destination. Instruct mailer 22 to make a call.
[0036]
In step (D), as shown in FIG. 8, the database update means 24 sets the current year, month, day and time in the ON time field in the work id record corresponding to each destination. Also, the corresponding value is set in the current status code field of the r record of the issue database DK (record of issue identifier id = r). (This is the part indicated by (D) in FIG. 8.) Since these operations are the same as those already described in step S305, description thereof is omitted.
[0037]
Next, in step S206, the department consumption time measuring means 25 sets the current year / month / day / hour / minute in the OFF time field of the work id = nn record corresponding to the sending department specialized department hb in response to the reception of the work result information res. To do. This is as shown in FIG. 8 as an entry in step (E). Step S207 corresponds to stage (F), and the department consumption time measuring means 25 refers to the ON time field value in the same record when writing the OFF time field, and the department consumption time = OFF time field value−ON time field. Write the value into the department consumption time field. Although not shown, the department consumption time measuring means 25 always traces the work history final work id on the assignment database DK by the real-time clock interrupt, captures the current work id record, and now () − Enter the ON time field value. With this operation, all the work id records on the work database DW always store the correct department consumption time in the department consumption time field, and can deal with a constant search.
[0038]
Finally, an example of the department consumption time management screen display of the process management apparatus of the present invention will be described with reference to FIGS. A home page is always displayed on the screen of the process management client device 1 by the web page input / output control means 21. Various department consumption time management screens can be searched in a part or another window linked therewith. The operation is as shown in FIG. 4. In step S401, a search menu is displayed, a click selection is awaited, and the screen selected in steps S402 to 404 is displayed.
[0039]
In the present embodiment, a state in which work (or work execution responsibility) is currently being carried out is assumed to be holding a ball. Accordingly, a ball is shot from the problem management department to the first specialized department in accordance with the issuance of an incident, and this is regarded as a sequence such as returning it to the assignment management department or returning it to another specialized department.
[0040]
The administrator who wants to check the current ball whereabouts of an incident selects “ball holding department list” from the menu. In step S402, the display screen creation means 29 creates and displays a screen as shown in FIG. That is, the current state field values of the records for all the problem identifiers id (corresponding to the “incident number” field) from the problem database DK of the department consumption time database 26 are shown in the “ball holding” field. The value "CLOSE" is displayed as "End". In addition, the “cumulative time” column is obtained as the sum of the department consumption time field values of all work id records on the work database DW linked to the task identifier id = r record of the task database DK. For example, 05 days 23 hours 40 minutes indicate. If the current state field value is "CLOSE", the OFF time field value of the work id record on the work database DW linked to the final work id is displayed in the "End date" column of the screen. Fig. 4 (b) shows an example in which the "Ball holding" field that is not finished is highlighted with a thick frame and the field where the accumulated time exceeds the allowable time is highlighted with a surrounding mark. Also good.
[0041]
FIG. 5A shows an example of a screen generated by the display screen creation means 29 in step S403 when “issue-specific department consumption time list” is selected in step S401. In this example, the display screen creation means 29 is a work database DW that links all issue identifier ids (corresponding to the “incident number” field) from the issue database DK on the department consumption time database 26 to the individual issue identifier id records. All the work id records above are traced in order, and the department consumption time is accumulated for each department name hb field and displayed by department. In the example in the figure, with the issue identifier id = 1008-397, the department name hb = ppp, the cumulative department consumption time = 05 days 23 hours 40 minutes, and the department name hb = qqq, the cumulative department consumption time = 01 days 13 hours 20 minutes, And so on.
[0042]
FIG. 5B shows an example of a screen generated by the display screen creation means 29 in step S404 when “List of all task consumption times by department” is selected in step S401. In this example, the display screen creating means 29 searches the task database DK in the department consumption time database 26 for a task identifier id (in the requested date and time field value) that has a search specified period (00/01/01 to 00/10/15). Corresponding to the “incident number” field) The department of the work id record on the work database DW with the department name hb = ppp that has received a specific search designation from all work id records on the work database DW linked to the corresponding records Accumulate all time field values.
[0043]
In such a case, the above search may be performed after receiving the search designation. However, in order to shorten the search time, if the specialist department database DS as shown in FIG. By searching the database DS, the screen shown in FIG. 5 (b) can be provided at high speed. The update of the specialized department database DS is performed at the time of filling in the OFF time field of the work id record on each work database DW in step S206, and the work history on the problem database DK is always updated by the real-time clock interrupt. If the current work id record is traced, the current work id record is captured, and the now ()-ON time field value is entered in the department consumption time field, it is always updated.
(Supplementary note 1) Process to manage the work process of problem-solving work where multiple specialized departments work in their own specialized field in order to solve one problem given by the problem management department that manages problem occurrence A management method,
In the server device that communicates with the client device operated by each specialized department,
(A) detecting task registration information including a task identifier input from a task management department and creating a department consumption time data area related to the task on the department consumption time database;
(B) Based on the problem registration information received from the problem management department, identifying the department in charge of the request destination and sending out work request information, and starting the department consumption time measurement associated with the department in charge of the request destination ,
(C) Analyze the work result information input from each department in charge of the specialist.If the work result is complete, specify the requesting department of the work and send the work result information. When requesting the work of the department specializing in the request destination, identifying the next request destination department and sending the next work request information together with the work result information;
(D) starting the department consumption time measurement associated with the specialized department of the destination specified in step (C);
(E) analyzing the work result information input in the step (C), and stopping the department consumption time measurement associated with the department in charge of the input source,
(F) calculating the department consumption time for each department in charge based on the start / stop of the department consumption time measurement and recording it in the department consumption time database;
A process management method characterized by comprising:
(Additional remark 2) The process management method of Additional remark 1 which has a step which produces and displays the various statistical data regarding the division | segmentation consumption time accumulate | stored according to the subject and the department in charge with reference with reference to the said division | segmentation consumption time database.
(Supplementary note 3) An allowable time that is an allowable limit value of the time required for the solution is set from the content of the task registration information, a remaining time that is a difference between the allowable time and the department consumption time is calculated, and the allowable time or The process management method according to appendix 1, further comprising the step of creating and displaying various statistical data related to department consumption time accumulated for each problem and for each specialized department in comparison with the remaining time.
(Additional remark 4) The said problem management department is a help desk department which receives the failure notification of a user operation information processing system, and the said problem-solving type | formula is a failure investigation work which supports a help desk, The additional description 1 characterized by the above-mentioned Process control method.
(Additional remark 5) It is the process management method of Additional remark 1, Comprising: It further has the step which highlights and displays the department in charge of specialization currently measuring department consumption time for every subject with reference to the said department consumption time database Process management method.
(Appendix 6) A process for managing work processes of problem-solving work in which a plurality of departments in charge of specialization work in their own specialized fields in order to solve one problem given by the problem management department that manages the occurrence of problems A management method,
Each specialized department client device that communicates with the server device
A process management method comprising: a step of transmitting work request information specifying a destination department in charge of requesting a next work together with work result information including a request source department name.
(Supplementary note 7) Process to manage the work process of problem-solving work where multiple specialized departments work in their own specialized field in order to solve one problem given by the problem management department that manages problem occurrence A recording medium storing a program for causing a computer to perform information processing related to management,
(A) detecting task registration information including a task identifier input from a task management department and creating a department consumption time data area related to the task on the department consumption time database;
(B) Based on the problem registration information received from the problem management department, identifying the department in charge of the request destination and sending out work request information, and starting the department consumption time measurement associated with the department in charge of the request destination ,
(C) Analyze the work result information input from each department in charge of the specialist.If the work result is complete, specify the requesting department of the work and send the work result information. When requesting the work of the department specializing in the request destination, identifying the next request destination department and sending the next work request information together with the work result information;
(D) starting the department consumption time measurement associated with the specialized department of the destination specified in step (C);
(E) analyzing the work result information input in the step (C), and stopping the department consumption time measurement associated with the department in charge of the input source,
(F) calculating the department consumption time for each department in charge based on the start / stop of the department consumption time measurement and recording it in the department consumption time database;
The computer-readable recording medium which recorded the program which implement | achieves.
(Appendix 8) A process for managing work processes of problem-solving work in which a plurality of departments in charge of specialization work in their own specialized fields in order to solve one problem given by the problem management department that manages the occurrence of problems A management device,
In the server device that communicates with the client device operated by each specialized department,
(A) means for detecting issue registration information including an issue identifier input from the issue management department and creating a department consumption time data area related to the issue on the department consumption time database;
(B) Based on the problem registration information received from the problem management department, means for specifying the department in charge of the request destination and sending out work request information, and starting the department consumption time measurement associated with the department in charge of the request destination ,
(C) Analyze the work result information input from each department in charge of the specialist.If the work result is complete, specify the requesting department of the work and send the work result information. When requesting the work of the department specializing in the request destination, a means for specifying the next request destination department and sending the next work request information together with the work result information;
(D) means for starting department consumption time measurement associated with the department in charge of the destination specified in the means (C);
(E) means for analyzing the work result information inputted in the means (C) and stopping the department consumption time measurement associated with the department in charge of the input source;
(F) Based on the start and stop of the department consumption time measurement, a means for calculating a department consumption time for each department in charge of specialization and recording it in the department consumption time database;
A process management apparatus comprising:
(Additional remark 9) It is a recording medium of Additional remark 4, Furthermore, the program which implement | achieves the stage which highlights the department in charge of specialization currently measuring department consumption time for every subject with reference to the said department consumption time database is recorded Computer-readable recording medium.
(Supplementary note 10) The process management apparatus according to supplementary note 5, further comprising means for highlighting a department in charge of the current department consumption time measurement for each subject with reference to the department consumption time database. A process management device.
[0044]
【The invention's effect】
As is clear from the above description, according to the present invention, the work result information input from the specialized department in charge of the work is analyzed, and if the work result is completed, the work request source department receives the work result information. When the work result information is sent and the work result requests the work of the department in charge of the next request destination, the next request destination department is specified, the next work request information is sent together with the work result information, and the department associated with these By measuring the time consumed and displaying the results on various management screens, the time spent by each department in charge can be measured for each task (issue), and the degree of busyness and work can be measured. There is an effect that basic data of goal management can be obtained.
[Brief description of the drawings]
FIG. 1 shows an embodiment of a process management apparatus according to the present invention.
FIG. 2 shows an example of a department consumption time management operation flow of the process management apparatus of the present invention.
FIG. 3 is a processing example of assignment registration information K
FIG. 4 is a screen display operation example of the process management apparatus of the present invention.
FIG. 5 shows an example of a department consumption time management screen of the process management apparatus of the present invention.
FIG. 6 shows a configuration example of the department consumption time database 26.
FIG. 7: Data structure example of work result information res and work request information I
FIG. 8 is a diagram illustrating operations in steps S203 to S207.
[Explanation of symbols]
1 Process management client device
2 Process management server device
21 Web page input / output control means
22 Webmailer
23 Assignment registration means
24 Database update method
25 Department consumption time measurement means
26 Department consumption time database
27 Input analysis means
28 Email creation means
29 Display screen creation means

Claims (5)

複数の専門担当部門のクライアント装置にネットワークを介して接続した工程管理サーバ装置の工程管理方法であって、A process management method of a process management server device connected to a client device of a plurality of specialized departments via a network,
該工程管理サーバ装置は、作業を依頼する部門の依頼元部門情報、作業を識別する依頼識別番号情報、作業の内容を示す依頼内容情報、および作業を行う部門である依頼先の専門担当部門情報を有する課題登録情報が入力されると、該依頼識別番号情報、該依頼先の専門担当部門情報、および該依頼先の専門担当部門情報が作業に要した時間情報を記憶する部門消費時間データ領域を部門消費時間データベース上に作成して、該課題登録情報の依頼先の専門担当部門情報に対応するクライアント装置に該依頼内容情報を送信するとともに該依頼先の専門担当部門が作業に要する時間の計測を開始し、The process management server device includes: request source department information of a department requesting work; request identification number information identifying work; request content information indicating work content; and specialized department information of a request destination that is a department performing work When the task registration information including the request is input, the request identification number information, the department information in charge of the request destination, and the department consumption time data area for storing the time information required for the work by the department information in charge of the request destination Is created in the department consumption time database, and the request contents information is transmitted to the client device corresponding to the department department in charge of the request for the assignment registration information. Start measuring,
該工程管理サーバ装置は、該課題登録情報の依頼先の専門担当部門情報のクライアント装置から作業の結果情報、次の依頼内容情報、および次の依頼先の専門担当部門情報を受信すると、該依頼先の専門担当部門情報が作業に要した時間を該部門消費時間データ領域に格納し、該依頼識別番号情報、該次の依頼先の専門担当部門情報、および該次の依頼先の専門担当部門が作業に要した時間情報を記憶する部門消費時間データ領域を部門消費時間データベース上に作成し、該次の依頼先の専門担当部門情報に対応するクライアント装置に該作業の結果情報および該次の依頼内容情報を送信するとともに該次の依頼先の専門担当部門が作業に要する時間の計測を開始し、When the process management server device receives the work result information, the next request content information, and the specialized department information of the next request destination from the client device of the specialized department information that is the request destination of the assignment registration information, The time taken by the previous specialized department information is stored in the department consumption time data area, the request identification number information, the specialized department information of the next request destination, and the specialized department of the next request destination The department consumption time data area for storing the time information required for the work is created on the department consumption time database, and the result information of the work and the next information are sent to the client device corresponding to the department department in charge of the next request destination. Send the request content information and start measuring the time required for the work by the specialized department in charge of the next request,
該工程管理サーバ装置は、該課題登録情報の依頼先の専門担当部門情報のクライアント装置から作業の結果情報および作業が完了した旨の情報を受信すると、該依頼先の専門担当部門情報が作業に要した時間を部門消費時間データ領域に格納して、作業の結果情報を依頼元部門情報に出力するWhen the process management server device receives the work result information and the information indicating that the work is completed from the client device of the specialized department information of the request destination of the assignment registration information, the specialized department information of the requested destination is changed to the work. Stores the time required in the department consumption time data area and outputs the work result information to the requesting department information
ことを特徴とする工程管理方法。A process management method characterized by that.
該部門消費時間データベース内の部門消費時間データ領域から作業に要した時間の累積値を専門担当部門毎に算出することを特徴とする請求項1に記載の工程管理方法。2. The process management method according to claim 1, wherein a cumulative value of time required for work is calculated for each department in charge from a department consumption time data area in the department consumption time database. 部門消費時間データベースは更に、The department consumption time database
依頼内容情報を送信しかつ作業結果情報を実受信である該専門担当部門のクライアント装置を識別する情報を更に有し、依頼内容情報を送信しかつ作業結果情報を実受信である該専門担当部門を出力することを特徴とする請求項1に記載の工程管理方法。The specialized department in which request content information is transmitted and the client device of the specialized department that is actually receiving the work result information is further identified, and the requested department information is transmitted and the operational result information is actually received. The process management method according to claim 1, wherein:
複数の専門担当部門のクライアント装置にネットワークを介して接続した工程管理サーバ装置による該複数の専門担当部門の作業工程を管理する工程管理サーバ装置であって、A process management server device for managing the work processes of a plurality of specialized departments by a process management server device connected to a client device of a plurality of specialized departments via a network,
作業を依頼する部門の依頼元部門情報、作業を識別する依頼識別番号情報、作業の内容を示す依頼内容情報、および作業を行う部門である依頼先の専門担当部門情報を有する課題登録情報が入力されると、該依頼識別番号情報、該依頼先の専門担当部門情報、および該依頼先の専門担当部門情報が作業に要した時間情報を記憶する部門消費時間データ領域を部門消費時間データベース上に作成して、該課題登録情報の依頼先の専門担当部門情報に対応するクライアント装置に該依頼内容情報を送信するとともに該依頼先の専門担当部門が作業に要する時間の計測を開始し、Input of task registration information including request source department information of department requesting work, request identification number information for identifying work, request contents information indicating work contents, and department information in charge of request destination which is the department performing the work When this is done, the department consumption time data area for storing the request identification number information, the department information in charge of the request destination, and the time information required by the department information in charge of the request destination is stored on the department consumption time database. Create and send the request content information to the client device corresponding to the specialized department information of the request destination of the assignment registration information and start measuring the time required for the specialized department of the request destination,
該課題登録情報の依頼先の専門担当部門情報のクライアント装置から作業の結果情報、次の依頼内容情報、および次の依頼先の専門担当部門情報を受信すると、該依頼先の専門担当部門情報が作業に要した時間を該部門消費時間データ領域に格納し、該依頼識別番号情報、該次の依頼先の専門担当部門情報、および該次の依頼先の専門担当部門が作業に要した時間情報を記憶する部門消費時間データ領域を部門消費時間データベース上に作成し、該次の依頼先の専門担当部門情報に対応するクライアント装置に該作業の結果情報および該次の依頼内容情報を送信するとともに該次の依頼先の専門担当部門が作業に要する時間の計測を開始し、When work result information, next request content information, and specialized department information of the next request destination are received from the client apparatus of the specialized department information of the request destination of the assignment registration information, the specialized department information of the requested destination is obtained. The time required for work is stored in the department consumption time data area, the request identification number information, the department information in charge of the next request destination, and the time information required by the department in charge of the next request destination Is created on the department consumption time database, and the work result information and the next request content information are transmitted to the client device corresponding to the department information in charge of the next request destination. The specialized department in charge of the next request starts measuring the time required for work,
該課題登録情報の依頼先の専門担当部門情報のクライアント装置から作業の結果情報および作業が完了した旨の情報を受信すると、該依頼先の専門担当部門情報が作業に要した時間を部門消費時間データ領域に格納して、作業の結果情報を依頼元部門情報に出力することを特徴とする工程管理装置。When the work result information and the information indicating that the work is completed are received from the client device of the department department information requesting the assignment registration information, the time required for the work by the department department information of the request destination is calculated. A process management apparatus which stores data in a data area and outputs work result information to requesting department information.
複数の専門担当部門のクライアント装置にネットワークを介して接続した工程管理サーバ装置に該複数の専門担当部門の作業工程を管理させる工程管理プログラムを記憶したコンピュータ読み取り可能な記録媒体であって、A computer-readable recording medium storing a process management program for managing a work process of a plurality of specialized departments in a process management server device connected to a client apparatus of a plurality of specialized departments via a network,
該工程管理サーバ装置に、In the process management server device,
作業を依頼する部門の依頼元部門情報、作業を識別する依頼識別番号情報、作業の内容を示す依頼内容情報、および作業を行う部門である依頼先の専門担当部門情報を有する課題登録情報が入力されると、該依頼識別番号情報、該依頼先の専門担当部門情報、および該依頼先の専門担当部門情報が作業に要した時間情報を記憶する部門消費時間データ領域を部門消費時間データベース上に作成して、該課題登録情報の依頼先の専門担当部門情報に対応するクライアント装置に該依頼内容情報を送信するとともに該依頼先の専門担当部門が作業に要する時間の計測を開始するステップ、Input of task registration information including request source department information of department requesting work, request identification number information for identifying work, request contents information indicating work contents, and department information in charge of request destination which is the department performing the work When this is done, the department consumption time data area for storing the request identification number information, the department information in charge of the request destination, and the time information required by the department information in charge of the request destination is stored on the department consumption time database. Creating and transmitting the request content information to the client device corresponding to the specialized department information of the request destination of the assignment registration information and starting measuring the time required for the specialized department of the request destination;
該課題登録情報の依頼先の専門担当部門情報のクライアント装置から作業の結果情報、次の依頼内容情報、および次の依頼先の専門担当部門情報を受信すると、該依頼先の専門担当部門情報が作業に要した時間を該部門消費時間データ領域に格納し、該依頼識別番号情報、該次の依頼先の専門担当部門情報、および該次の依頼先の専門担当部門が作業に要した時間情報を記憶する部門消費時間データ領域を部門消費時間データベース上に作成し、該次の依頼先の専門担当部門情報に対応するクライアント装置に該作業の結果情報および該次の依頼内容情報を送信するとともに該次の依頼先の専門担当部門が作業に要する時間の計測を開始するステップ、When work result information, next request content information, and specialized department information of the next request destination are received from the client apparatus of the specialized department information of the request destination of the assignment registration information, the specialized department information of the requested destination is obtained. The time required for work is stored in the department consumption time data area, the request identification number information, the department information in charge of the next request destination, and the time information required by the department in charge of the next request destination Is created on the department consumption time database, and the work result information and the next request content information are transmitted to the client device corresponding to the department information in charge of the next request destination. A step in which the specialized department in charge of the next request starts measuring the time required for work;
該課題登録情報の依頼先の専門担当部門情報のクライアント装置から作業の結果情報および作業が完了した旨の情報を受信すると、該依頼先の専門担当部門情報が作業に要した時間を部門消費時間データ領域に格納して、作業の結果情報を依頼元部門情報に出力するステップWhen the work result information and the information indicating that the work is completed are received from the client device of the department department information requesting the assignment registration information, the time required for the work by the department department information of the request destination is calculated. Step to store work result information to requesting department information by storing in data area
とを実行させることを特徴とする工程管理プログラムを記憶したコンピュータ読み取り可能な記録媒体。And a computer-readable recording medium storing a process management program.
JP2000352621A 2000-11-20 2000-11-20 Process management method, process management apparatus, and computer-readable recording medium recording process management program Expired - Fee Related JP4016591B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000352621A JP4016591B2 (en) 2000-11-20 2000-11-20 Process management method, process management apparatus, and computer-readable recording medium recording process management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000352621A JP4016591B2 (en) 2000-11-20 2000-11-20 Process management method, process management apparatus, and computer-readable recording medium recording process management program

Publications (2)

Publication Number Publication Date
JP2002157389A JP2002157389A (en) 2002-05-31
JP4016591B2 true JP4016591B2 (en) 2007-12-05

Family

ID=18825490

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000352621A Expired - Fee Related JP4016591B2 (en) 2000-11-20 2000-11-20 Process management method, process management apparatus, and computer-readable recording medium recording process management program

Country Status (1)

Country Link
JP (1) JP4016591B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004078708A (en) * 2002-08-21 2004-03-11 Nec Corp Service operation management device, service operation system, service operation method used for same, and program
JP2006146830A (en) * 2004-11-24 2006-06-08 Glory Ltd System, method, and program for processing form

Also Published As

Publication number Publication date
JP2002157389A (en) 2002-05-31

Similar Documents

Publication Publication Date Title
US9928480B2 (en) Method and system for network connectivity migration management
US8799796B2 (en) System and method for generating graphical dashboards with drill down navigation
US8495571B2 (en) Computer method and apparatus for engineered product management including simultaneous indication of working copy status and repository status
US20120245954A1 (en) Medical Record Collection System
CN103329150A (en) Construction trade building information management system, software and method
CN113010208B (en) Version information generation method, device, equipment and storage medium
KR20150033453A (en) Method of big data processing, apparatus performing the same and storage media storing the same
JP2021189780A (en) Scenario retrieval device, scenario retrieval system, scenario retrieval method, and program
CN115841310A (en) Construction method of plan flow model, event processing method and device
CN114303134A (en) Method, apparatus and computer readable medium for maintaining visual consistency
US20100274601A1 (en) Supply chain perameter optimization and anomaly identification in product offerings
JP2007316905A (en) Computer system and method for monitoring application program
US20100299272A1 (en) Workflow status tracking and reporting
JP4016591B2 (en) Process management method, process management apparatus, and computer-readable recording medium recording process management program
US7793259B2 (en) System and method for managing user interaction data in a networked environment
JP2013037478A (en) Work man-hour calculation device, work man-hour calculation method, and program
JP2016518646A (en) System, apparatus, and method for generating contextual objects mapped to data measurements by dimensional data
US20080004925A1 (en) Multi-site project management
US20100146002A1 (en) Capturing enterprise architectures
CN112686743A (en) Resource transfer tracking method, device and system and electronic equipment
US20030125815A1 (en) E-installation system and method for use in installation of power-plant equipment
US11620322B1 (en) System and method for managing regulatory information
US10810640B1 (en) Automated time tracking of events in a calendar and use of the same to generate invoices
JP2017102870A (en) System operation automation device, system operation automation program, and system operation automation method
JP2001134681A (en) Method for processing and defining electronic document, storage medium with stored processing program for electronic document, storage medium with stored definition program for electronic document and electronic document system

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070220

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070403

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070828

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070910

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100928

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100928

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110928

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120928

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120928

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130928

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees