[go: up one dir, main page]

JP2019148108A - Bridge pier construction method - Google Patents

Bridge pier construction method Download PDF

Info

Publication number
JP2019148108A
JP2019148108A JP2018033240A JP2018033240A JP2019148108A JP 2019148108 A JP2019148108 A JP 2019148108A JP 2018033240 A JP2018033240 A JP 2018033240A JP 2018033240 A JP2018033240 A JP 2018033240A JP 2019148108 A JP2019148108 A JP 2019148108A
Authority
JP
Japan
Prior art keywords
gap
column
pier
main body
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2018033240A
Other languages
Japanese (ja)
Other versions
JP6960870B2 (en
Inventor
光則 村尾
Mitsunori Murao
光則 村尾
臨 関
Mozomu Seki
臨 関
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2018033240A priority Critical patent/JP6960870B2/en
Publication of JP2019148108A publication Critical patent/JP2019148108A/en
Application granted granted Critical
Publication of JP6960870B2 publication Critical patent/JP6960870B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

【課題】橋梁工事の工期を短縮できる橋脚の構築方法を提供する。【解決手段】外側パネル34、内側パネル35及び連結パネル36を有し、鉄筋篭38が一体化されたプレキャストコンクリートからなる複数のパネル部材30を用意し(ステップST1)、柱本体部8の輪郭に沿って且つ少なくとも周方向の1箇所に隙間41を空けて、複数のパネル部材30を並べ(ステップST12)、隙間41が設けられた部分以外の閉空間37にコンクリートを打設し(ステップST14)、これを繰り返して、隙間41が上方へ延長された、柱本体部8の未完成状態である柱本体中間体48を構築し(ステップST2)、柱本体中間体48の上に柱頭部9を構築し(ステップST3)、柱本体中間体48の隙間41を間詰めして柱本体部8を完成させる(ステップST4、ST7)。【選択図】図9[Problem] To provide a method for constructing bridge piers that can shorten the construction period of bridge construction. [Solution] A plurality of panel members 30 made of precast concrete having an outer panel 34, an inner panel 35, and a connecting panel 36 and with an integrated reinforcing bar cage 38 are prepared (step ST1), and the outline of a column main body 8 is prepared. A plurality of panel members 30 are arranged along with a gap 41 at at least one location in the circumferential direction (step ST12), and concrete is poured into the closed space 37 other than the part where the gap 41 is provided (step ST14). ), this is repeated to construct the column body intermediate body 48 which is an unfinished state of the column body part 8 in which the gap 41 is extended upward (step ST2), and the column head 9 is placed on the column body intermediate body 48. is constructed (step ST3), and the gap 41 of the column body intermediate body 48 is closed to complete the column body portion 8 (steps ST4, ST7). [Selection diagram] Figure 9

Description

本開示は、柱本体部と柱頭部とを有する橋脚の構築方法に関する。   The present disclosure relates to a method for constructing a pier having a column main body and a column head.

山間部の谷あい等では、高さの大きな鉄筋コンクリート造の橋脚が建設されることがある。そのような橋脚は、基礎上に所定の高さのコンクリート構造物の構築をリフト毎に繰り返して鉛直方向に高さを増してゆく必要があるため、構築に時間がかかる上、断面寸法も大きくなる。そのため、近年では、橋脚の外周面の部分にプレキャストコンクリートを用い、これを型枠として利用するハーフプレキャスト工法が増えている。   Large reinforced concrete piers may be constructed in valleys in mountainous areas. Such piers need to be constructed in a vertical direction by repeatedly building a concrete structure of a predetermined height on the foundation for each lift, so that construction takes time and the cross-sectional dimensions are large. Become. Therefore, in recent years, a half precast method using precast concrete for the outer peripheral surface portion of the pier and using this as a formwork is increasing.

また、リフト毎に橋脚を構築してゆく場合には、上下方向に延びる主鉄筋を接続する必要がある上、帯鉄筋及び中間帯鉄筋の組立にも時間がかかる。そこで、橋脚表面を形成するプレキャストコンクリート製のパネル部材に予め帯鉄筋及び中間帯鉄筋を埋め込んでおき、このパネル部材を、複数リフト分の長さを有する主鉄筋が建て込まれた構築中の橋脚上に建て込む作業と、パネル部材の内部にコンクリートを打設する作業とを繰り返し行うSPER工法を本出願人は開発している(非特許文献1参照)。SPER工法は、現場での鉄筋組立作業を省力化できるため、工期を大幅に短縮することができる。   In addition, when building a pier for each lift, it is necessary to connect the main reinforcing bars extending in the vertical direction, and it takes time to assemble the band reinforcing bars and the intermediate band reinforcing bars. Therefore, a precast concrete panel member that forms the surface of the pier surface is pre-embedded with a strip reinforcement and intermediate strip reinforcement, and the panel pier under construction in which main reinforcement with a length equivalent to multiple lifts is built. The present applicant has developed a SPER method that repeatedly performs the work of building up and the work of placing concrete inside the panel member (see Non-Patent Document 1). The SPER method can save labor for rebar assembling work on site, so the construction period can be greatly shortened.

[online]、平成28年12月1日検索、インターネット(URL: http://www.smcon.co.jp/service/sper/)[Online], search on December 1, 2016, Internet (URL: http://www.smcon.co.jp/service/sper/)

ところで、川や湖、海等に橋脚が設けられる場合、鋼管矢板井筒基礎の上に橋脚が構築されることがある。更に、橋脚を構築する部分に鋼管矢板井筒の支保工の切梁が必要になることがある。このような場合、切梁よりも低い高さまで橋脚の下部を構築し、鋼管矢板井筒内に土砂を埋め戻したり注水したりして鋼管矢板井筒の側圧を低下させ、切梁を撤去した後に橋脚の構築を再開することで、橋脚を完成させることができる。しかしながら、このような手順をとると、橋脚が完成した後にしか橋の上部工を着手することができないため、非特許文献1記載のSPER工法を用いたとしても、橋梁工事の工期の長期化は避けられない。   By the way, when a pier is provided in a river, a lake, the sea, etc., a pier may be built on a steel pipe sheet pile well foundation. In addition, there is a case where a beam for supporting a steel pipe sheet pile well is required in the part where the pier is constructed. In such a case, the lower part of the pier is built to a height lower than that of the cut beam, and the side pressure of the steel pipe sheet pile cannula is reduced by backfilling or pouring water into the steel pipe sheet pile well, and then the pier is removed after removing the cut beam. You can complete the pier by restarting the construction. However, if such a procedure is taken, since the superstructure of the bridge can be started only after the pier is completed, even if the SPER method described in Non-Patent Document 1 is used, the construction period of the bridge work is prolonged. Unavoidable.

本発明は、このような背景に鑑み、このような背景に鑑み、橋梁工事の工期を短縮できる橋脚の構築方法を提供することを課題とする。   In view of such a background, it is an object of the present invention to provide a method for constructing a pier that can shorten the construction period of bridge work.

このような課題を解決するために、本発明のある態様は、柱本体部(8)と前記柱本体部の上に配置される柱頭部(9)とを有する橋脚(2)を構築するための橋脚構築方法であって、外側パネル(34)、内側パネル(35)、及び前記外側パネルと前記内側パネルとを連結する連結部(36)を有し、複数の帯鉄筋(32)及び複数の中間帯鉄筋(33)を含む鉄筋篭(38)が一体化されたプレキャストコンクリートからなる複数のパネル部材(30)を用意するステップ(ST1)と、前記柱本体部の輪郭に沿って且つ少なくとも周方向の1箇所に隙間(41)を空けて、複数の前記パネル部材を並べるステップ(ST12)と、前記外側パネル、前記内側パネル及び少なくとも2つの前記連結部によって閉じられた、前記隙間が設けられた部分以外の閉空間(37)にコンクリートを打設するステップ(ST14)と、前記パネル部材を並べるステップ及び前記閉空間にコンクリートを打設するステップを、前記柱本体部の高さになるまで繰り返し、前記隙間が上方へ延長された、前記柱本体部の未完成状態である柱本体中間体(48)を構築するステップ(ST2(ST11−ST16))と、前記柱本体中間体の上に前記柱頭部を構築するステップ(ST3)と、前記柱頭部の下方にて前記柱本体中間体の前記隙間を間詰めして前記柱本体部を完成させるステップ(ST4、ST7)とを含むことを特徴とする。   In order to solve such a problem, an aspect of the present invention is to construct a pier (2) having a column main body (8) and a column head (9) disposed on the column main body. A pier construction method comprising an outer panel (34), an inner panel (35), and a connecting portion (36) for connecting the outer panel and the inner panel, and a plurality of strip reinforcing bars (32) and a plurality Preparing a plurality of panel members (30) made of precast concrete integrated with reinforcing bar rods (38) including intermediate band reinforcing bars (33) (ST1), at least along the contour of the column main body and A step (ST12) of arranging a plurality of the panel members with a gap (41) in one circumferential direction, and the gap closed by the outer panel, the inner panel and at least two of the connecting portions are provided. The step of placing concrete in the closed space (37) other than the formed portion (ST14), the step of arranging the panel members, and the step of placing concrete in the closed space become the height of the column main body. Step (ST2 (ST11-ST16)) of constructing the column body intermediate body (48) which is the unfinished state of the column body portion with the gap extended upward, and the top of the column body intermediate body The step of building the column head (ST3), and the step of completing the column main body by filling the gap of the column main body intermediate below the column head (ST4, ST7). It is characterized by.

この構成によれば、隙間が上方へ延長された柱本体中間体を構築した後に、柱本体中間体の上に柱頭部を構築するため、柱頭部の上で行われる或いは柱頭部から張り出すように行われる橋梁の上部工を橋脚工事が完了する前に着工できる。このように、柱本体部を完成させる工事は、クリティカルではなく、上部工と並行して行えばよいため、橋梁工事の工期を短縮することができる。   According to this configuration, after the pillar main body intermediate with the gap extended upward is constructed, the pillar head is constructed on the pillar main body intermediate, so that it is performed on or protrudes from the column head The superstructure of the bridge can be started before the pier work is completed. As described above, the construction for completing the column main body is not critical and may be performed in parallel with the superstructure, so that the construction period of the bridge construction can be shortened.

また、上記構成において、前記柱本体部(8)を完成させるステップ(ST4、ST7)は、前記隙間(41)の両側に配置された前記パネル部材(30)の帯鉄筋(32)を、機械継手ユニット(43)を介して互いに連結するステップ(ST31、ST43)と、前記隙間の両側に配置された前記パネル部材の前記内側パネル(35)間及び前記外側パネル(34)間を塞ぐように、型枠(50)又は前記柱本体部の周縁部をなすプレキャストコンクリート製の継手パネルを組み立てるステップ(ST32、ST44)と、前記型枠又は前記継手パネルによって閉じられた前記隙間にコンクリートを打設するステップ(ST33、ST45)とを含むとよい。   In the above configuration, the step (ST4, ST7) of completing the column main body (8) is performed by using the reinforcing bars (32) of the panel member (30) disposed on both sides of the gap (41). Steps (ST31, ST43) connected to each other via a joint unit (43), and the inner panel (35) and the outer panel (34) of the panel member arranged on both sides of the gap are closed. , A step of assembling a precast concrete joint panel (ST32, ST44) which forms the periphery of the formwork (50) or the column main body, and placing concrete in the gap closed by the formwork or the joint panel (ST33, ST45).

この構成によれば、柱本体部を完成させる前に柱頭部を構築しても、帯鉄筋を周方向に連続させた上で柱本体部を完成させることができる。   According to this configuration, even if the column head is constructed before the column main body is completed, the column main body can be completed after the belt reinforcing bars are continuous in the circumferential direction.

また、上記構成において、前記柱頭部(9)を構築するステップ(ST3)は、前記柱頭部から下方に延出して前記隙間(41)に配置される接続用主鉄筋(31D)を組み立てるステップ(ST25)を含み、前記柱本体部(8)を完成させるステップ(ST7)は、主鉄筋(31)を延長して前記接続用主鉄筋に接続するステップ(ST42)を更に含むとよい。   Moreover, in the said structure, the step (ST3) which builds the said column head (9) assembles the connection main rebar (31D) extended below from the said column head and arrange | positioned in the said clearance gap (41) ( The step (ST7) of completing the column main body portion (8) including ST25) may further include a step (ST42) of extending the main reinforcing bar (31) and connecting to the connecting main reinforcing bar.

この構成によれば、柱本体部を完成させる前に柱頭部を構築しても、主鉄筋を縦方向に連続させた上で柱本体部を完成させることができる。   According to this configuration, even if the column head is constructed before the column main body is completed, the column main body can be completed after the main reinforcing bars are continued in the vertical direction.

また、上記構成において、前記柱本体部(8)が構築される部分に少なくとも1本の切梁(22)が設けられ、且つ、前記隙間(41)が各切梁に対して平面視において前記柱本体部(8)を通過する周方向の2箇所に設けられており、前記柱頭部(9)を構築するステップ(ST3)の後に、前記少なくとも1本の切梁を撤去するステップ(ST6)を更に含み、前記柱本体部を完成させるステップ(ST4、ST7)は、前記少なくとも1本の切梁よりも低い空間において、前記型枠(50)又は前記継手パネルを組み立てるステップ(ST32)及び前記隙間にコンクリートを打設するステップ(ST33)を行って前記隙間の下部を間詰めするステップ(ST4)と、前記少なくとも1本の切梁が撤去された空間において、前記型枠又は前記継手パネルを組み立てるステップ(ST44)及び前記隙間にコンクリートを打設するステップ(ST45)を行って前記隙間の上部を間詰めするステップ(ST7)とを含むとよい。   In the above configuration, at least one beam (22) is provided in a portion where the column main body (8) is constructed, and the gap (41) is in plan view with respect to each beam. Steps (ST6) for removing the at least one beam after the step (ST3) for constructing the column head (9), provided at two locations in the circumferential direction passing through the column main body (8). The step (ST4, ST7) of completing the column main body portion includes the step of assembling the formwork (50) or the joint panel (ST32) in a space lower than the at least one beam. In the space where the step of placing concrete in the gap (ST33) and filling the lower part of the gap (ST4), and the space where the at least one beam is removed, the formwork May includes a step (ST7) for filled between the upper portion of the gap by performing a step (ST45) for concrete is in the step (ST44) and the gap of assembling the joint panel.

この構成によれば、切梁が残っている状態で構築した柱本体中間体の上に柱頭部を構築することができる。即ち、切梁の撤去作業がクリティカルでなくなり、橋梁工事の工期短縮が可能である。また、切梁を撤去しながら、隙間を段階的に間詰めして柱本体部を完成させることができる。   According to this configuration, the column head can be constructed on the column main body constructed in a state where the cutting beam remains. That is, the removal work of the cut beam is not critical, and the construction period of the bridge work can be shortened. Further, the pillar main body portion can be completed by gradually filling the gap while removing the beam.

また、上記構成において、前記隙間の下部を間詰めするステップ(ST4)が、前記柱頭部を構築するステップ(ST3)の後に行われるとよい。   Moreover, in the said structure, the step (ST4) which fills the lower part of the said gap | interval is good to be performed after the step (ST3) which builds the said column head.

隙間の下部を間詰めするステップは、切梁が干渉しないことから、柱頭部を構築するステップの前に、例えば柱本体中間体を構築する際に一緒に構築することもできるが、この構成によれば、柱本体中間体を早急に構築してより早期に柱頭部を構築することができる。   The step of filling the lower part of the gap can be constructed together with, for example, the construction of the column body intermediate before the step of constructing the column head, since the beams do not interfere with each other. According to this, the column main body intermediate can be constructed quickly and the column head can be constructed earlier.

また、上記構成において、前記橋脚(2)が鋼管矢板井筒基礎(10)の上に構築され、前記切梁(22)を撤去するステップ(ST6)の前に、前記切梁の下方にて前記橋脚の周囲に土砂を埋め戻す又は注水する第1埋め戻しステップ(ST5)と、前記隙間の下部を間詰めするステップ(ST4)の後に、前記橋脚の周囲に土砂を埋め戻す又は注水する第2埋め戻しステップ(ST8)とを更に含むとよい。   Moreover, in the said structure, the said pier (2) is constructed | assembled on the steel pipe sheet pile well foundation (10), and before the step (ST6) which removes the said cut beam (22), the said lower part of the said cut beam After the first backfilling step (ST5) of backfilling or pouring the earth and sand around the pier and the step of filling the lower part of the gap (ST4), the second backfilling or pouring the earth and sand around the pier A backfilling step (ST8) may be further included.

この構成によれば、橋脚が鋼管矢板井筒基礎の上に構築されるものであっても、埋め戻しを段階的に行いながら、切梁を安全に撤去できる。   According to this configuration, even if the pier is constructed on a steel pipe sheet pile well foundation, it is possible to safely remove the beam while performing backfilling step by step.

このように本発明によれば、橋梁工事の工期を短縮できる橋脚の構築方法を提供することができる。   Thus, according to this invention, the construction method of the pier which can shorten the construction period of bridge construction can be provided.

実施形態に係る方法を適用して構築する橋梁の側面図Side view of a bridge constructed by applying the method according to the embodiment 実施形態に係る方法を適用して構築する橋梁の正面図Front view of the bridge constructed by applying the method according to the embodiment 図1に示される基礎の橋脚構築前の状態を示す横断面図1 is a cross-sectional view showing a state before the foundation pier construction shown in FIG. 図1に示される基礎の橋脚構築前の状態を示す平面図The top view which shows the state before construction of the pier of the foundation shown in FIG. 図1に示される橋脚の施工割付を示す正面図Front view showing the construction allocation of the pier shown in FIG. 図1に示される橋脚の施工割付を示す平面図Plan view showing the construction assignment of the pier shown in FIG. 図6に示される橋脚端部の詳細平面図Detailed plan view of the pier end shown in FIG. 図6に示される橋脚中間部の詳細平面図Detailed plan view of the middle part of the pier shown in FIG. 実施形態に係る橋脚構築方法の手順を示すフロー図The flowchart which shows the procedure of the pier construction method which concerns on embodiment 図9に示される柱本体中間体構築工の手順を示すフロー図Flow chart showing the procedure of the pillar body intermediate construction work shown in FIG. 柱本体中間体構築工が完了した状態の橋脚の正面図Front view of the pier with the pillar body intermediate construction completed 図9に示される柱頭部構築工の手順を示すフロー図Flow chart showing the procedure of the pillar head construction work shown in FIG. 柱頭部構築工が完了した状態の橋脚の正面図Front view of the pier after the construction of the column head has been completed 図9に示される隙間下部間詰め工の手順を示すフロー図FIG. 9 is a flowchart showing the procedure of the gap lowering process shown in FIG. 隙間下部間詰め工が完了した状態の橋脚の正面図Front view of the pier after the gap clearance is complete 図9に示される隙間上部間詰め工の手順を示すフロー図FIG. 9 is a flowchart showing the procedure of the upper gap filling process shown in FIG. 隙間上部間詰め工が完了した状態の橋脚の正面図Front view of the pier in the state where the gap gap filling work has been completed

以下、図面を参照して、本発明の実施形態について詳細に説明する。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

図1は実施形態に係る方法を適用して構築する橋梁1の側面図であり、図2はその正面図である。図1及び図2に示されるように、橋梁1は、橋軸方向に離間するように配置された3つ以上の橋台や橋脚2等の支持台間の多径間にわたって橋桁3が連続するように設けられた連続桁形式の多径間連続橋である。   FIG. 1 is a side view of a bridge 1 constructed by applying the method according to the embodiment, and FIG. 2 is a front view thereof. As shown in FIG. 1 and FIG. 2, the bridge 1 is constructed so that the bridge girder 3 is continuous over a plurality of spans between three or more abutments arranged so as to be separated from each other in the direction of the bridge axis, and support stands such as the pier 2. Is a multi-girder continuous bridge of continuous girder type.

橋桁3は、支承4を介して橋脚2に支持されており、上床版5と下床版6とを複数のウェブ7により連結したコンクリートからなる連続箱桁である。図示例では、橋桁3は、橋軸直角方向に離間する4つのウェブ7を有する多重箱桁とされている。両端に配置された2つのウェブ7は、上方に向けて拡開するように傾斜しており、中央に配置された2つのウェブ7は、それぞれ鉛直方向に延在している。両端に配置された2つのウェブ7は、下端が下床版6の橋軸直角方向の端部に、上端が上床版5の橋軸直角方向の中間部に結合している。上床版5は、下床版6よりも幅広に形成され、ウェブ7から側方に張り出している。下床版6及び1対のウェブ7の幅は橋脚2の幅よりも小さく、上床版5の幅は橋脚2の幅よりも大きくされている。   The bridge girder 3 is supported by the pier 2 via a support 4 and is a continuous box girder made of concrete in which an upper floor slab 5 and a lower floor slab 6 are connected by a plurality of webs 7. In the illustrated example, the bridge girder 3 is a multi-box girder having four webs 7 spaced in the direction perpendicular to the bridge axis. The two webs 7 arranged at both ends are inclined so as to expand upward, and the two webs 7 arranged at the center respectively extend in the vertical direction. The two webs 7 arranged at both ends have a lower end connected to an end portion of the lower floor slab 6 in the direction perpendicular to the bridge axis and an upper end joined to an intermediate portion of the upper floor slab 5 in the direction perpendicular to the bridge axis. The upper floor slab 5 is formed wider than the lower floor slab 6 and protrudes laterally from the web 7. The width of the lower floor slab 6 and the pair of webs 7 is smaller than the width of the pier 2, and the width of the upper floor slab 5 is larger than the width of the pier 2.

他の実施形態では、橋桁3が、橋脚2の左側のスパンに対応する部分と右側のスパンに対応する部分とで分離していてもよく、支承4を介さずに橋脚2に剛結合されていてもよい。また、橋桁3が2つのウェブ7を有する単一箱桁とされていてもよい。   In another embodiment, the bridge girder 3 may be separated into a portion corresponding to the left span of the pier 2 and a portion corresponding to the right span, and is rigidly coupled to the pier 2 without the support 4. May be. The bridge girder 3 may be a single box girder having two webs 7.

橋脚2は、橋軸直角方向に長い長円形の概ね一定の断面形状を有しており、実質的に中空構造の柱本体部8と、柱本体部8の上に配置された中実構造の柱頭部9とを有している。橋脚2は、地盤G中に構築された基礎10の上に鉄筋コンクリートにより構築される。   The pier 2 has an oblong, generally constant cross-sectional shape that is long in a direction perpendicular to the bridge axis, and has a substantially hollow column main body 8 and a solid structure disposed on the column main body 8. It has a column head 9. The pier 2 is constructed of reinforced concrete on the foundation 10 constructed in the ground G.

本明細書において、鉄筋コンクリートにより構築されるとは、鉄筋によりコンクリートが補強された一般的な意味の鉄筋コンクリート造だけでなく、PC鋼線やPCケーブル、鋼材、鋼繊維、炭素繊維、アラミド繊維、アラミド筋等が含まれたものも含む。また、コンクリートからなるとは、コンクリートのみからなることを意味するのではなく、構造体としてコンクリートを含むことを意味し、鉄筋コンクリート造や、PC鋼線やPCケーブルにより補強されたプレストレストコンクリート構造、鋼繊維や炭素繊維、アラミド繊維、アラミド筋等により補強された構造であってよい。   In this specification, the term "constructed by reinforced concrete" means not only reinforced concrete structures in which concrete is reinforced by reinforcing bars, but also PC steel wires, PC cables, steel materials, steel fibers, carbon fibers, aramid fibers, and aramids. Including those containing muscles. The term “consisting of concrete” does not mean that it is composed of concrete alone, but includes concrete as a structural body. It is a reinforced concrete structure, a prestressed concrete structure reinforced with PC steel wire or PC cable, or steel fiber. Or a structure reinforced with carbon fiber, aramid fiber, aramid muscle, or the like.

実質的に中空構造とは、柱本体部8が、中実構造の柱脚部8Aと柱脚部8Aの上に構築された中空構造の柱部8Bとにより構成されていることを意味する。本実施形態では、互いに分離して橋軸直角方向に1列に配置された4つの中空空間が柱部8Bに形成されている。言い換えれば、橋脚2の柱本体部8は、柱部8Bにおいて、外形輪郭をなす外周壁8Cと、外周壁8Cの内側に橋軸方向に延在するように一体に形成された3つの中間壁8Dとを有している。   The substantially hollow structure means that the column main body 8 is composed of a solid column base 8A and a hollow column 8B constructed on the column base 8A. In the present embodiment, four hollow spaces that are separated from each other and arranged in a row in a direction perpendicular to the bridge axis are formed in the column portion 8B. In other words, the pillar body portion 8 of the pier 2 includes an outer peripheral wall 8C having an outer contour at the pillar portion 8B and three intermediate walls integrally formed so as to extend in the bridge axis direction inside the outer peripheral wall 8C. 8D.

他の実施形態では、柱本体部8の全体が中実構造とされてもよい。この場合、柱頭部9は、支承4を介して橋桁3を支持する橋脚2の上端部分を指す。また、他の実施形態では、柱頭部9が柱本体部8よりも大きな断面形状を有していてもよい。上記のように橋桁3が橋脚2に剛結合されている場合、橋桁3が張り出す橋脚2の上端部分(連続する橋桁3のうち、橋脚2上に配置された部分とも言える)が柱頭部9をなし、橋脚2の柱頭部9以下の部分が柱本体部8をなす。この場合にも、柱本体部8は実質的に中空構造であってもよく、中実構造であってもよい。   In other embodiments, the entire column main body 8 may have a solid structure. In this case, the column head 9 indicates the upper end portion of the pier 2 that supports the bridge girder 3 via the support 4. In other embodiments, the column head 9 may have a larger cross-sectional shape than the column main body 8. When the bridge girder 3 is rigidly connected to the pier 2 as described above, the upper end portion of the pier 2 overhanging from the bridge girder 3 (which can be said to be a portion of the continuous bridge girder 3 disposed on the pier 2) is the column head 9. The part below the column head 9 of the pier 2 forms the column main body 8. Also in this case, the column main body 8 may have a substantially hollow structure or a solid structure.

図3は、図1に示される基礎10の橋脚構築前の状態を示す横断面図であり、図4はその平面図である。なお、橋脚2は想像線で示されている。図3及び図4に示されるように、基礎10は、河川の中に構築される鋼管矢板井筒基礎であり、外周縁に環状に井筒状に配置された複数の鋼管矢板11と、複数の鋼管矢板11の内側に下から順に構築された敷砂12、底盤コンクリート13及び頂版コンクリート14とを備えている。互いに隣接する鋼管矢板11同士は、止水処理された継手15(図4に一部のみを示す)によって互いに連結されており、複数の鋼管矢板11によって閉環状の鋼管矢板井筒16が形成されている。本実施形態では、鋼管矢板井筒16は平面視において橋軸直角方向に長い長円形に形成されている。各鋼管矢板11の内部における、頂版コンクリート14や底盤コンクリート13、敷砂12に対応する部分には中詰コンクリート17(図3)が構築されている。頂版コンクリート14は、底面及び上面が、水面18下の現況地盤線19よりも低くなる位置に設けられる。   FIG. 3 is a cross-sectional view showing a state before the pier of the foundation 10 shown in FIG. 1 is constructed, and FIG. 4 is a plan view thereof. The pier 2 is indicated by an imaginary line. As shown in FIG. 3 and FIG. 4, the foundation 10 is a steel pipe sheet pile well foundation constructed in a river, and a plurality of steel pipe sheet piles 11 arranged in a ring shape on the outer peripheral edge, and a plurality of steel pipes. Inside the sheet pile 11, there is provided a spread sand 12, a bottom concrete 13 and a top concrete 14 constructed in order from the bottom. The steel pipe sheet piles 11 adjacent to each other are connected to each other by a joint 15 (only a part of which is shown in FIG. 4) subjected to a water stop treatment, and a plurality of steel pipe sheet piles 11 form a closed annular steel pipe sheet pile well 16. Yes. In this embodiment, the steel pipe sheet pile well 16 is formed in an oval shape that is long in the direction perpendicular to the bridge axis in plan view. Filled concrete 17 (FIG. 3) is constructed in portions corresponding to the top slab concrete 14, the bottom base concrete 13, and the laying sand 12 in each steel pipe sheet pile 11. The top slab concrete 14 is provided at a position where the bottom surface and the top surface are lower than the existing ground line 19 below the water surface 18.

鋼管矢板井筒16は、その内側にて頂版コンクリート14上に橋脚2を構築する際の土留め壁として機能する。橋脚2の構築後、鋼管矢板井筒16は、頂版コンクリート14の上面近傍の高さで切断され、上部が撤去され、残された下部が図1及び図2に示される基礎10の一部となる。鋼管矢板井筒16が土留め壁として機能する間、鋼管矢板井筒16には外側から土圧及び水圧が作用する。そのため、鋼管矢板井筒16の内側には、H形鋼からなる支保工20が設けられている。本実施形態では、高さの異なる位置に2段の支保工20が設けられた状態で橋脚2が構築される。   The steel pipe sheet pile well 16 functions as a retaining wall when the pier 2 is constructed on the top concrete 14 inside thereof. After the construction of the pier 2, the steel pipe sheet pile well 16 is cut at a height near the upper surface of the top slab concrete 14, the upper part is removed, and the remaining lower part is a part of the foundation 10 shown in FIGS. Become. While the steel pipe sheet pile well 16 functions as a retaining wall, earth pressure and water pressure act on the steel pipe sheet pile well 16 from the outside. Therefore, a support 20 made of H-section steel is provided inside the steel pipe sheet pile well 16. In the present embodiment, the pier 2 is constructed in a state where the two-stage support works 20 are provided at positions having different heights.

支保工20は、頂版コンクリート14の構築のために鋼管矢板井筒16の内側の掘削及び水抜きを行う際には、3段以上(例えば、5段)の段数をもって設けられる。頂版コンクリート14の構築後、不要になった下側の段の支保工20は撤去されており、橋脚2の構築時には、鋼管矢板井筒16の内側に注水するまで撤去できない上側の2段の支保工20が残されている。   The support 20 is provided with three or more stages (for example, five stages) when excavating and draining the inside of the steel pipe sheet pile 16 for the construction of the top concrete 14. After the construction of the top slab concrete 14, the lower stage support 20 which has become unnecessary has been removed, and when the pier 2 is constructed, the upper two stages of support that cannot be removed until water is poured inside the steel pipe sheet pile 16 The work 20 is left.

各支保工20は、鋼管矢板井筒16の内側に設けられた環状長円形の腹起し21と、腹起し21の内側に架け渡され、橋軸方向に延在する複数(本実施形態では4本)の切梁22と、複数の火打ち23を有している。腹起し21は、1対のフランジを内側及び外側に向けて配置され、各鋼管矢板11との間に間詰め材が充填されることによって各鋼管矢板11を内側から支持する。切梁22は、1対のフランジを上下に向けて配置され、腹起し21の変形を防止するべく腹起し21の内周面に接合される。火打ち23は、切梁22の両端部の左右両側に、切梁22及び腹起し21に対して斜めに接合されている。切梁22は、各段に4本設けられ、合計8本の切梁22が橋脚2を構築する空間を通過している。   Each supporter 20 includes an annular oval flank 21 provided inside the steel pipe sheet pile cannula 16, and a plurality of (in this embodiment) extending in the flank 21 and extending in the bridge axis direction. 4) and a plurality of fires 23. The flank 21 is arranged with the pair of flanges facing inward and outward, and supports the steel pipe sheet piles 11 from the inside by filling the space between the steel pipe sheet piles 11. The cut beam 22 is arranged with a pair of flanges facing up and down, and is joined to the inner peripheral surface of the flank 21 to prevent deformation of the flank 21. The fire struck 23 is obliquely joined to the cut beam 22 and the protuberance 21 on both the left and right sides of both ends of the cut beam 22. Four cutting beams 22 are provided in each stage, and a total of eight cutting beams 22 pass through the space for constructing the pier 2.

次に、橋脚2の構築方法について説明する。   Next, the construction method of the pier 2 will be described.

本実施形態では、工期の短縮を図るため、予め帯鉄筋32を埋め込むように形成したプレキャストコンクリート製の複数のパネル部材30(30A、30B)によって橋脚表面を形成する上記SPER工法によって橋脚2を構築する。図5は、図1に示される橋脚2の施工割付を示す正面図であり、図6は、その平面図である。図5に示されるように、橋脚2は、パネル部材30の内部へのコンクリートの打設を6回に分けて行う(6リフトに分けて行う)ように計画される。1リフトのコンクリートの打設高さは概ね5m程度(例えば、5.4m)に計画され、パネル部材30の高さは、パネル部材30を複数段積み重ねて1リフトの高さとなるように計画される。本実施形態では、3段のパネル部材30の高さが1リフトの高さに相当する。   In the present embodiment, in order to shorten the construction period, the pier 2 is constructed by the above SPER method in which the pier surface is formed by a plurality of precast concrete panel members 30 (30A, 30B) formed so as to embed the band rebar 32 in advance. To do. FIG. 5 is a front view showing construction assignment of the pier 2 shown in FIG. 1, and FIG. 6 is a plan view thereof. As shown in FIG. 5, the pier 2 is planned to perform concrete placement into the inside of the panel member 30 in six times (divided into six lifts). The height of concrete for one lift is planned to be approximately 5 m (for example, 5.4 m), and the height of the panel member 30 is planned to be one lift by stacking the panel members 30 in a plurality of stages. The In the present embodiment, the height of the three-stage panel member 30 corresponds to the height of one lift.

図6に示されるように、各段のパネル部材30は、橋軸直角方向について、中空空間に対応する4箇所で5つに分割されるように計画される。両端に設けられる2つの橋脚端部は中間壁8Dを含んでおらず、中間部に設けられる3つの橋脚中間部は中間壁8Dを含んでいる。これらの分割位置は、平面視において切梁22に整合している。言い換えれば、仮設である切梁22の位置が、パネル部材30の分割位置(中空空間の位置)に整合するように計画されている。本実施形態では、3つの橋脚中間部は互いに同一形状、同一寸法を有し、2つの橋脚端部は互いに同一形状、同一寸法を有している。   As shown in FIG. 6, the panel member 30 at each stage is planned to be divided into five at four locations corresponding to the hollow space in the direction perpendicular to the bridge axis. The two pier end portions provided at both ends do not include the intermediate wall 8D, and the three pier intermediate portions provided in the intermediate portion include the intermediate wall 8D. These division positions are aligned with the beam 22 in plan view. In other words, it is planned that the position of the temporary cutting beam 22 matches the division position of the panel member 30 (the position of the hollow space). In the present embodiment, the three pier intermediate portions have the same shape and the same size, and the two pier end portions have the same shape and the same size.

更に、トレーラーによる運搬可能な大きさの制限や、揚重設備の吊り上げ荷重の制限等により、各段のパネル部材30は、橋軸方向について2つに分割されるように計画される。橋軸方向に分割された2つのパネル部材30は回転対称をなしており、実質的に同一である。即ち、橋脚2の各段は、概ね1/4円の円弧形状をなす4つのコーナーパネル部材30Aと、T字形状をなす6つの中間パネル部材30Bとの合計10個のパネル部材30によって構成される。   Furthermore, the panel member 30 at each stage is planned to be divided into two in the bridge axis direction due to the limitation of the size that can be transported by the trailer and the limitation of the lifting load of the lifting equipment. The two panel members 30 divided in the bridge axis direction have rotational symmetry and are substantially the same. That is, each step of the pier 2 is configured by a total of ten panel members 30 including four corner panel members 30A having an arc shape of approximately ¼ circle and six intermediate panel members 30B having a T shape. The

図7は、図6に示される橋脚端部の詳細平面図であり、図8は、図6に示される橋脚中間の詳細平面図である。図7及び図8に示されるように、橋脚2の内部(コンクリート内)には、鉛直に延在する複数の主鉄筋31(31A、31B、31C)と、水平に環状に配置される複数の帯鉄筋32(32A、32B、32C)と、橋脚2の周方向に沿って所定の間隔をもって配置され、水平に延在する複数の中間帯鉄筋33(33A、33B、33C)とが配置されている。   7 is a detailed plan view of the pier end shown in FIG. 6, and FIG. 8 is a detailed plan view of the middle part of the pier shown in FIG. As shown in FIGS. 7 and 8, in the pier 2 (in the concrete), there are a plurality of main reinforcing bars 31 (31A, 31B, 31C) extending vertically and a plurality of horizontally arranged annular members. A belt reinforcing bar 32 (32A, 32B, 32C) and a plurality of intermediate belt reinforcing bars 33 (33A, 33B, 33C) that are arranged at predetermined intervals along the circumferential direction of the pier 2 and extend horizontally are arranged. Yes.

具体的には、橋脚2の外周面に沿って複数の第1主鉄筋31Aが配置され、第1主鉄筋31Aの内側に複数の第2主鉄筋31Bが配置され、橋脚2の内周面及び中間壁8D(図8)の外面に沿って複数の第3主鉄筋31Cが配置されている。第1主鉄筋31Aの外周側には、鉛直方向に所定の間隔をもって配置された複数の第1帯鉄筋32Aが第1主鉄筋31Aを取り囲むように配置されている。第2主鉄筋31Bの外周側には、鉛直方向に所定の間隔をもって配置された複数の第2帯鉄筋32Bが第2主鉄筋31Bを取り囲むように配置されている。第3主鉄筋31Cの内周側には、鉛直方向に所定の間隔をもって配置された複数の第3帯鉄筋32Cが第3主鉄筋31Cにより取り囲まれるように配置されている。   Specifically, a plurality of first main reinforcing bars 31A are arranged along the outer peripheral surface of the pier 2 and a plurality of second main reinforcing bars 31B are arranged inside the first main reinforcing bar 31A, and the inner peripheral surface of the pier 2 and A plurality of third main reinforcing bars 31C are arranged along the outer surface of the intermediate wall 8D (FIG. 8). On the outer peripheral side of the first main reinforcing bar 31A, a plurality of first strip reinforcing bars 32A arranged at predetermined intervals in the vertical direction are arranged so as to surround the first main reinforcing bar 31A. On the outer peripheral side of the second main reinforcing bar 31B, a plurality of second band reinforcing bars 32B arranged at predetermined intervals in the vertical direction are arranged so as to surround the second main reinforcing bar 31B. On the inner peripheral side of the third main reinforcing bar 31C, a plurality of third strip reinforcing bars 32C arranged at predetermined intervals in the vertical direction are arranged so as to be surrounded by the third main reinforcing bar 31C.

橋脚2の中間壁8D(図8)が設けられた位置には、鉛直方向に所定の間隔をもって配置されて橋軸方向に延在する複数の第1中間帯鉄筋33Aが、前後の第1主鉄筋31Aに端部を係止させてこれらに架け渡されるように配置されている。橋脚2の中間壁8Dが設けられていない位置には、鉛直方向に所定の間隔をもって配置された複数の第2中間帯鉄筋33Bが、橋脚2の周方向の所定の位置にて第1帯鉄筋32Aと第3帯鉄筋32Cとに端部を係止させてこれらに架け渡されている。中間壁8D(図8)の内部には、鉛直方向に所定の間隔をもって配置されて橋軸直角方向に延在する複数の第3中間帯鉄筋33Cが、橋軸方向の所定の位置にて左右の第1中間帯鉄筋33Aに端部を係止させてこれらに架け渡されている。   At the position where the intermediate wall 8D (FIG. 8) of the bridge pier 2 is provided, a plurality of first intermediate strip reinforcing bars 33A that are arranged in the vertical direction with a predetermined interval and extend in the bridge axis direction are the first main front and rear. The reinforcing bars 31A are arranged so that the ends thereof are locked and bridged between them. At a position where the intermediate wall 8D of the pier 2 is not provided, a plurality of second intermediate band reinforcing bars 33B arranged at predetermined intervals in the vertical direction are arranged at predetermined positions in the circumferential direction of the pier 2 at the first band reinforcing bar. 32A and the 3rd belt | strand reinforcement 32C are made to latch over an edge part, and it is spanned over them. Inside the intermediate wall 8D (FIG. 8), a plurality of third intermediate strip rebars 33C that are arranged at a predetermined interval in the vertical direction and extend in the direction perpendicular to the bridge axis are left and right at a predetermined position in the bridge axis direction. The first intermediate band reinforcing bar 33A is engaged with the end portion of the reinforcing bar 33A.

図7に示されるように、コーナーパネル部材30Aは、それぞれコンクリートからなる外側パネル34、内側パネル35、及び複数の連結パネル36を有している。外側パネル34は橋脚2の外周面を形成し、内側パネル35は橋脚2の内周面を形成する。連結パネル36は、外側パネル34と内側パネル35とを連結しており、外側パネル34及び内側パネル35と協働して、コーナーパネル部材30Aの内部に平面視において閉じられた閉空間37を形成している。また、コーナーパネル部材30Aは、複数の帯鉄筋32及び複数の中間帯鉄筋33を組み立ててなる鉄筋篭38が、一体に設けられたプレキャスト製品として製造されている。帯鉄筋32は、機械継手39を設けることができるように、近接する外側パネル34又は内側パネル35の周方向の端縁から周方向に突出している。   As shown in FIG. 7, the corner panel member 30 </ b> A includes an outer panel 34, an inner panel 35, and a plurality of connection panels 36 each made of concrete. The outer panel 34 forms the outer peripheral surface of the pier 2, and the inner panel 35 forms the inner peripheral surface of the pier 2. The connection panel 36 connects the outer panel 34 and the inner panel 35, and cooperates with the outer panel 34 and the inner panel 35 to form a closed space 37 that is closed in a plan view inside the corner panel member 30 </ b> A. doing. Further, the corner panel member 30A is manufactured as a precast product in which a reinforcing bar 38 formed by assembling a plurality of band reinforcing bars 32 and a plurality of intermediate band reinforcing bars 33 is integrally provided. The band reinforcement 32 protrudes in the circumferential direction from the circumferential edge of the adjacent outer panel 34 or inner panel 35 so that the mechanical joint 39 can be provided.

図8に示されるように、中間パネル部材30Bは、それぞれコンクリートからなる外側パネル34、2つの内側パネル35、及び複数の連結パネル36を有している。外側パネル34は橋脚2の外周面を形成し、内側パネル35は橋脚2の内周面及び中間壁8Dの外面を形成する。連結パネル36は、外側パネル34と内側パネル35とを連結する、或いは2つの内側パネル35を連結しており、外側パネル34及び内側パネル35と協働して、中間パネル部材30Bの内部に平面視において閉じられた閉空間37を形成している。また、中間パネル部材30Bは、複数の帯鉄筋32及び複数の中間帯鉄筋33を組み立ててなる鉄筋篭38が、一体に設けられたプレキャスト製品として製造されている。帯鉄筋32及び第1中間帯鉄筋33Aは、機械継手39を設けることができるように、近接する外側パネル34又は内側パネル35の周方向の端縁から周方向に突出している。   As shown in FIG. 8, the intermediate panel member 30 </ b> B includes an outer panel 34 made of concrete, two inner panels 35, and a plurality of connection panels 36. The outer panel 34 forms the outer peripheral surface of the pier 2 and the inner panel 35 forms the inner peripheral surface of the pier 2 and the outer surface of the intermediate wall 8D. The connection panel 36 connects the outer panel 34 and the inner panel 35, or connects the two inner panels 35, and cooperates with the outer panel 34 and the inner panel 35 to form a flat surface inside the intermediate panel member 30B. A closed space 37 that is closed in view is formed. Further, the intermediate panel member 30B is manufactured as a precast product in which a reinforcing bar bar 38 formed by assembling a plurality of band reinforcing bars 32 and a plurality of intermediate band reinforcing bars 33 is integrally provided. The band reinforcing bar 32 and the first intermediate band reinforcing bar 33A protrude in the circumferential direction from the circumferential edge of the adjacent outer panel 34 or inner panel 35 so that the mechanical joint 39 can be provided.

なお、主鉄筋31は、頂版コンクリート14から上方へ延出するように設けられており、適宜な位置にて継ぎ足されて上方へ延長されるものであり、鉄筋篭38には含まれていない。主鉄筋31は、パネル部材30を吊り下ろして適切な位置に配置する前に所定の位置に予め配置されており、上記の配置となるようにパネル部材30に下方から挿入される。本実施形態では、主鉄筋31は、頂版コンクリート14から1リフトの高さよりも若干長く突出しており、2リフトの高さに相当する長さの主鉄筋31が順次継ぎ足され、柱頭部9に柱頭部9の下端から下方に突出するように設けられる接続用主鉄筋31D(図13参照)に接続される。   The main reinforcing bar 31 is provided so as to extend upward from the top slab concrete 14, is added at an appropriate position and extended upward, and is not included in the reinforcing bar 38. . The main reinforcing bar 31 is arranged in advance at a predetermined position before the panel member 30 is suspended and arranged at an appropriate position, and is inserted into the panel member 30 from below so as to have the above arrangement. In the present embodiment, the main reinforcing bar 31 protrudes from the top concrete 14 slightly longer than the height of one lift, and the main reinforcing bars 31 having a length corresponding to the height of two lifts are sequentially added to the column head 9. It is connected to a connecting main reinforcing bar 31D (see FIG. 13) provided so as to protrude downward from the lower end of the column head 9.

橋軸方向に互いに隣接するパネル部材30の帯鉄筋32同士は、機械継手39によって互いに連結される。また、第1中間帯鉄筋33A同士は、短い中間帯鉄筋33の両端に2つの機械継手39を設けた中間帯鉄筋継手ユニット42によって互いに連結される。機械継手39及び中間帯鉄筋継手ユニット42が配置される位置には、コンクリートパネル(34、35)は設けられておらず、本実施形態では、橋脚2の周縁部をなすコンクリートからなる継手パネル40がコンクリートパネル間を塞ぐように設けられる。これにより、橋軸方向に互いに隣接するパネル部材30間にも閉空間37が形成される。他の実施形態では、継手パネル40を設ける代わりに、型枠を組み付けてコンクリートパネル間を塞いでもよい。   The band reinforcing bars 32 of the panel members 30 adjacent to each other in the bridge axis direction are connected to each other by a mechanical joint 39. Further, the first intermediate band reinforcing bars 33 </ b> A are connected to each other by an intermediate band reinforcing bar joint unit 42 in which two mechanical joints 39 are provided at both ends of the short intermediate band reinforcing bar 33. A concrete panel (34, 35) is not provided at a position where the mechanical joint 39 and the intermediate band reinforcing bar joint unit 42 are arranged. In this embodiment, the joint panel 40 made of concrete that forms the periphery of the pier 2 is used. Is provided to block between the concrete panels. Thereby, the closed space 37 is also formed between the panel members 30 adjacent to each other in the bridge axis direction. In another embodiment, instead of providing the joint panel 40, a formwork may be assembled to close between the concrete panels.

図3及び図4に示されるように、4本×2段、合計8本の切梁22は、橋脚2を構築する空間を通過するように設けられている。そこで、図6に示されるように、平面視において切梁22が設けられた位置に隙間41が形成されるようにパネル部材30が配置される。ここで、隙間41が形成されるように配置されるとは、互いに隣接するパネル部材30の帯鉄筋32同士が切梁22の幅よりも大きな寸法をもって互いに離間することを意味する。図7及び図8に示されるように、橋軸直角方向に互いに隣接するパネル部材30の帯鉄筋32同士は、隙間41に配置された、短い帯鉄筋32の両端に2つの機械継手39を設けた帯鉄筋継手ユニット43を介して互いに連結される。   As shown in FIG. 3 and FIG. 4, the four cut beams 22 in total of 4 × 2 stages are provided so as to pass through the space for constructing the pier 2. Therefore, as shown in FIG. 6, the panel member 30 is arranged so that the gap 41 is formed at the position where the cut beam 22 is provided in plan view. Here, the arrangement so that the gap 41 is formed means that the strip reinforcing bars 32 of the panel members 30 adjacent to each other are separated from each other with a dimension larger than the width of the cut beam 22. As shown in FIG. 7 and FIG. 8, the band reinforcing bars 32 of the panel members 30 adjacent to each other in the direction perpendicular to the bridge axis are provided with two mechanical joints 39 at both ends of the short band reinforcing bar 32 arranged in the gap 41. They are connected to each other through the band reinforcing bar joint unit 43.

図9は、実施形態に係る橋脚構築方法の手順を示すフロー図である。図9に示されるように、橋脚2の構築は、次のようにして行われる。即ち、工場やヤードにおいて、上記構成を有するパネル部材30を必要な数だけ製造、用意する(ステップST1)。その後、柱本体中間体48(図11参照)を構築する柱本体中間体構築工を行う(ステップST2)。   FIG. 9 is a flowchart showing a procedure of the pier construction method according to the embodiment. As shown in FIG. 9, the construction of the pier 2 is performed as follows. That is, a necessary number of panel members 30 having the above-described configuration are manufactured and prepared in a factory or a yard (step ST1). Thereafter, a pillar body intermediate construction work for constructing the pillar body intermediate 48 (see FIG. 11) is performed (step ST2).

図10は、図9に示される柱本体中間体構築工の手順を示すフロー図である。図10に示されるように、柱本体中間体構築工では、積み上げるパネル部材30の段数が、主鉄筋31の組立が必要な所定リフト目(本実施形態では、第2、第4、第6リフト目)でなければ(ステップST11:No)、1段分のパネル部材30を、橋軸直角方向に隣接するもの同士の間に隙間41が形成されるように所定の位置に並べる(ステップST12)。1リフトの段数(本実施形態では、3段)になっていなければ(ステップST13:No)、ステップST12の作業を繰り返し、1リフトの段数である3段までパネル部材30を積み重ねる。この際、橋軸方向に互いに隣接するパネル部材30については、機械継手39(図7)又は中間帯鉄筋継手ユニット42(図8)によって鉄筋同士を連結した後、継手パネル40を配置して鉄筋連結部を閉じて閉空間37とする。   FIG. 10 is a flowchart showing a procedure of the pillar body intermediate construction work shown in FIG. 9. As shown in FIG. 10, in the pillar body intermediate construction work, the number of steps of the panel members 30 to be stacked is a predetermined lift level that requires assembly of the main reinforcing bars 31 (in this embodiment, the second, fourth, and sixth lifts). If not (step ST11: No), the one-stage panel members 30 are arranged at predetermined positions so that a gap 41 is formed between those adjacent in the direction perpendicular to the bridge axis (step ST12). . If the number of steps of one lift (three steps in this embodiment) is not reached (step ST13: No), the operation of step ST12 is repeated, and the panel members 30 are stacked up to three steps that are the number of steps of one lift. At this time, for the panel members 30 adjacent to each other in the bridge axis direction, the reinforcing bars are connected to each other by the mechanical joint 39 (FIG. 7) or the intermediate strip reinforcing bar joint unit 42 (FIG. 8), and then the joint panel 40 is arranged to reinforce the reinforcing bars. The connecting portion is closed to form a closed space 37.

パネル部材30が3段になった後に(ステップST13:Yes)、パネル部材30の内部の閉空間37にコンクリートを打設する(ステップST14)。柱本体部8の構築に必要な5リフトが完了していなければ(ステップST15:No)、ステップST11に戻る。ステップST11で主鉄筋31の組立が必要な所定リフト目である場合には(Yes)、主鉄筋31を組み立て(ステップST16)、ステップST12以降の作業を続ける。ステップST15で柱本体部8の構築に必要な5リフトが完了すると(Yes)、図11に示されるように、隙間41が上方へ延長された、柱本体部8の未完成状態である柱本体中間体48が構築され、本工程が終了する。   After the panel member 30 has three stages (step ST13: Yes), concrete is placed in the closed space 37 inside the panel member 30 (step ST14). If the five lifts necessary for the construction of the column main body 8 have not been completed (step ST15: No), the process returns to step ST11. If it is a predetermined lift that requires assembly of the main reinforcing bar 31 in step ST11 (Yes), the main reinforcing bar 31 is assembled (step ST16), and the operations after step ST12 are continued. When 5 lifts necessary for the construction of the column main body 8 are completed in step ST15 (Yes), the column main body in an unfinished state of the column main body 8 with the gap 41 extended upward as shown in FIG. Intermediate 48 is constructed and the process is completed.

図9に戻り、ステップST2の柱本体中間体構築工の後、柱頭部構築工を行う(ステップST3)。図12は、図9に示される柱頭部構築工の手順を示すフロー図である。図12に示されるように、柱頭部構築工では、1段分のパネル部材30を柱本体中間体48上の所定の位置に並べる(ステップST21)。1リフトの段数(本実施形態では、3段)になっていなければ(ステップST22:No)、ステップST21の作業を繰り返し、1リフトの段数になった後に(ステップST22:Yes)、中空空間を塞ぐ柱頭部9の底型枠を組み立てる(ステップST23)。その後、互いに隣接するパネル部材30の帯鉄筋32同士を互いに連結し(ステップST24)、接続用主鉄筋31Dを含む各種鉄筋を組み立てる(ステップST25)。更に、隙間41を塞ぐように側型枠50(図13参照)を組み立て(ステップST26)、コンクリートを打設して(ステップST27)、図13に示されるように柱頭部9を構築する。コンクリートの硬化後、柱頭部9の上に支承4(図2)を取り付け(ステップST28)、本工程が終了する。   Returning to FIG. 9, after the pillar body intermediate construction work in step ST2, a pillar head construction work is performed (step ST3). FIG. 12 is a flowchart showing the procedure of the pillar head construction work shown in FIG. 9. As shown in FIG. 12, in the pillar head construction work, the panel members 30 for one step are arranged at predetermined positions on the pillar main body intermediate 48 (step ST21). If the number of steps of one lift (in this embodiment, three steps) is not reached (step ST22: No), the work of step ST21 is repeated, and after the number of steps of one lift is reached (step ST22: Yes), the hollow space is removed. The bottom formwork of the column head 9 to be closed is assembled (step ST23). Thereafter, the band reinforcing bars 32 of the panel members 30 adjacent to each other are coupled to each other (step ST24), and various reinforcing bars including the connecting main reinforcing bars 31D are assembled (step ST25). Further, the side mold 50 (see FIG. 13) is assembled so as to close the gap 41 (step ST26), concrete is placed (step ST27), and the column head 9 is constructed as shown in FIG. After the concrete is hardened, the support 4 (FIG. 2) is attached on the column head 9 (step ST28), and this process ends.

柱本体中間体構築工が完了すると、柱頭部9の上で橋桁3を架設する橋梁1の上部工を開始することができる。以降の工事は、上部工と並行して行われてよい。   When the pillar body intermediate construction work is completed, the superstructure of the bridge 1 for erection of the bridge girder 3 on the pillar head 9 can be started. Subsequent construction may be performed in parallel with the superstructure.

図9に戻り、説明を続ける。ステップST3の柱頭部構築工の後、隙間下部間詰め工を行う(ステップST4)。図14は、図9に示される隙間下部間詰め工の手順を示すフロー図である。図14に示されるように、隙間下部間詰め工では、下段の切梁22よりも低い空間において、互いに隣接するパネル部材30の帯鉄筋32同士を、帯鉄筋継手ユニット43により互いに連結し(ステップST31)、隙間41の両側に配置されたパネル部材30の内側パネル35間及び外側パネル34間を塞ぐように側型枠50(図15参照)を組み立てる(ステップST32)。その後、側型枠50によって閉じられた隙間41にコンクリートを打設して隙間41の下部を間詰めし(ステップST33)、本工程が終了する。隙間下部間詰め工のコンクリートは、隙間41における第1リフト目に相当する。   Returning to FIG. 9, the description will be continued. After the column head construction work in step ST3, a gap lower space filling work is performed (step ST4). FIG. 14 is a flowchart showing a procedure of the gap lowering work shown in FIG. As shown in FIG. 14, in the gap lower space filling work, the band reinforcing bars 32 of the panel members 30 adjacent to each other are connected to each other by the band reinforcing bar joint unit 43 in a space lower than the lower cut beam 22 (step ST31), the side mold frame 50 (see FIG. 15) is assembled so as to close the space between the inner panels 35 and the outer panels 34 of the panel member 30 disposed on both sides of the gap 41 (step ST32). Thereafter, concrete is placed in the gap 41 closed by the side mold 50 to fill the lower portion of the gap 41 (step ST33), and this process is completed. The concrete of the gap lower stuffing work corresponds to the first lift in the gap 41.

図15は、隙間下部間詰め工が完了した状態の橋脚2の正面図である。図9に戻り、説明を続ける。ステップST4の隙間下部間詰め工の後、図15に示されるように間詰めした隙間41の下部の上端よりも低い高さまで鋼管矢板井筒16内に注水し(ステップST5)、支保工20を撤去する(ステップST6)。その後、隙間上部間詰め工を行う(ステップST7)。   FIG. 15 is a front view of the pier 2 in a state in which the gap lowering work has been completed. Returning to FIG. 9, the description will be continued. After step ST4, the gap lower portion is filled, and water is poured into the steel sheet pile well 16 to a height lower than the upper end of the lower portion of the gap 41 as shown in FIG. 15 (step ST5), and the support work 20 is removed. (Step ST6). Thereafter, the gap upper portion is stuffed (step ST7).

図16は、図9に示される隙間上部間詰め工の手順を示すフロー図である。図16に示されるように、隙間上部間詰め工では、次のリフトが、主鉄筋31の組立が必要な所定リフト目(本実施形態では、第2、第4リフト目)であるため(ステップST41:Yes)、隙間41における切梁22が撤去された空間において、第2、第3リフト用の主鉄筋31を組み立てる(ステップST42)。次いで、互いに隣接するパネル部材30の帯鉄筋32同士を、帯鉄筋継手ユニット43により互いに連結し(ステップST43)、第2リフトの側型枠50を組み立て(ステップST44)、側型枠50によって閉じられた隙間41にコンクリートを打設する(ステップST45)。第2〜第5の4リフトが完了していないので(ステップST46:No)、上記ステップST41以降を繰り返す。ステップST41において、第4リフト目である場合(Yes)、ステップST42にて主鉄筋31を組み立てる際には、主鉄筋31を上方に配置されている接続用主鉄筋31Dの下端にも接続する。第5リフトのコンクリートを逆巻きで打設し(ステップST45)、4リフトが完了すると(ステップST46:Yes)、本工程が終了する。   FIG. 16 is a flowchart showing the procedure of the gap upper space shown in FIG. As shown in FIG. 16, in the gap upper stuffing process, the next lift is a predetermined lift that requires assembly of the main reinforcing bars 31 (in this embodiment, the second and fourth lifts) (steps). (ST41: Yes), the main rebar 31 for the second and third lifts is assembled in the space where the cut beam 22 in the gap 41 is removed (step ST42). Next, the band reinforcing bars 32 of the panel members 30 adjacent to each other are connected to each other by the band reinforcing bar joint unit 43 (step ST43), the side mold frame 50 of the second lift is assembled (step ST44), and is closed by the side mold frame 50. Concrete is placed in the formed gap 41 (step ST45). Since the second to fifth 4 lifts are not completed (step ST46: No), the steps after step ST41 are repeated. In step ST41, when it is the fourth lift (Yes), when assembling the main reinforcing bar 31 in step ST42, the main reinforcing bar 31 is also connected to the lower end of the connecting main reinforcing bar 31D disposed above. The fifth lift of concrete is placed by reverse winding (step ST45), and when the four lifts are completed (step ST46: Yes), this process ends.

図17は、隙間上部間詰め工が完了した状態の橋脚2の正面図である。図9に戻り、更に説明を続ける。ステップST7の隙間上部間詰め工の後、鋼管矢板井筒16内に土砂などの埋め戻し材を埋め戻し(ステップST8)、鋼管矢板11を切断して上部を撤去する(ステップST9)。これにより、図1及び図2に示される橋脚2が完成する。   FIG. 17 is a front view of the pier 2 in a state in which the gap upper stuffing work has been completed. Returning to FIG. 9, the description will be continued. After the gap upper portion filling work in step ST7, a backfill material such as earth and sand is backfilled in the steel pipe sheet pile well 16 (step ST8), the steel pipe sheet pile 11 is cut, and the upper part is removed (step ST9). Thereby, the pier 2 shown in FIG.1 and FIG.2 is completed.

次に、このような手順で橋脚2を構築する本実施形態の橋脚構築方法の特徴点と、その効果を説明する。   Next, the feature point of the bridge pier construction method of this embodiment which builds the bridge pier 2 in such a procedure, and the effect are demonstrated.

図10及び図11に示されるように、本橋脚構築方法では、柱本体部8の輪郭に沿って且つ少なくとも周方向の1箇所に隙間41を空けて、複数のパネル部材30を並べるステップST12と、外側パネル34、内側パネル35及び少なくとも2つの連結パネル36によって閉じられた、隙間41が設けられた部分以外の閉空間37にコンクリートを打設するステップST14とを、柱本体部8の高さになる(ステップST15がYesとなる)まで繰り返し、隙間41が上方へ延長された、柱本体部8の未完成状態である柱本体中間体48を構築する(ステップST2)。続いて、図9及び図13に示されるように、柱本体中間体48の上に柱頭部9を構築する柱頭部構築工を行い(ステップST3)、その後、図15及び図17に示されるように、柱頭部9の下方にて柱本体中間体48の隙間41を間詰めして柱本体部8を完成させる(ステップST4及びステップST7)。   As shown in FIGS. 10 and 11, in the present pier construction method, step ST12 in which a plurality of panel members 30 are arranged along the outline of the column main body portion 8 with a gap 41 at least in one circumferential direction. Step ST14 in which concrete is placed in a closed space 37 other than the portion provided with the gap 41, which is closed by the outer panel 34, the inner panel 35, and the at least two connecting panels 36, and the height of the column body 8 (Step ST15 becomes Yes), and the column main body intermediate 48 which is the unfinished state of the column main body 8 with the gap 41 extended upward is constructed (Step ST2). Subsequently, as shown in FIGS. 9 and 13, a pillar head construction work for constructing the pillar head 9 is performed on the pillar main body intermediate 48 (step ST3), and thereafter, as shown in FIGS. 15 and 17. Further, the column main body portion 8 is completed by filling the gap 41 of the column main body intermediate body 48 below the column head 9 (step ST4 and step ST7).

そのため、柱頭部9の上で行われる橋梁1の上部工を、ステップST3の柱頭部構築工の後、橋脚工事が完了する前に着工できる。より詳しく説明すると、4本、2段、合計8本の切梁22は、図3及び図4に示されるように、橋脚2を構築する空間を通過するように設けられている。従って、従来は、下側の切梁22よりも低い高さまで橋脚2の下部を構築し、構築した橋脚2の上端よりも低い高さまで鋼管矢板井筒16内に注水し、或いは鋼管矢板井筒16内の埋め戻しを行って支保工20を撤去した後、橋脚2の構築を再開する手順で橋脚2を構築していた。そのため、柱頭部9が完成して橋脚工事が完了した後にしか、上部工を開始することができなかった。これに対し、本実施形態の橋脚構築方法では、柱本体部8を完成させる前に柱頭部9を構築する柱頭部構築工を行い(ステップST3)、柱本体部8を完成させるステップST4以降の工事がクリティカルではなくなり、上部工と並行して行えるため、橋梁工事の工期を短縮することができる。   Therefore, the superstructure of the bridge 1 performed on the pillar head 9 can be started after the pillar head construction work in step ST3 and before the pier construction is completed. More specifically, four, two stages, a total of eight cut beams 22 are provided so as to pass through the space for constructing the pier 2 as shown in FIGS. 3 and 4. Therefore, conventionally, the lower part of the pier 2 is constructed to a height lower than the lower beam 22 and water is poured into the steel pipe sheet pile well 16 to a height lower than the upper end of the constructed bridge pier 2, or After removing the supporting work 20 by backfilling, the pier 2 was constructed by the procedure of resuming the construction of the pier 2. Therefore, the superstructure could only be started after the column head 9 was completed and the pier construction was completed. On the other hand, in the pier construction method of the present embodiment, a pillar head construction work for constructing the pillar head 9 is performed before the pillar body portion 8 is completed (step ST3), and the steps after step ST4 for completing the pillar body portion 8 are performed. Since the construction is not critical and can be performed in parallel with the superstructure, the bridge construction period can be shortened.

柱本体部8を完成させる隙間下部間詰め工(ステップST4)及び隙間上部間詰め工(ステップST7)では、図6〜図8、図14及び図16に示されるように、隙間41の両側に配置されたパネル部材30の帯鉄筋32同士を、帯鉄筋継手ユニット43を介して互いに連結し(ステップST31、ステップST43)、隙間41の両側に配置されたパネル部材30の内側パネル35間及び外側パネル34間を塞ぐように、側型枠50を組み立て(ステップST32、ステップST44)、側型枠50によって閉じられた隙間41にコンクリートを打設する(ステップST33、ステップST45)。そのため、柱本体部8を完成させるステップST7の前のステップST3にて柱頭部9を構築しても、帯鉄筋32を周方向に連続させた上で柱本体部8を完成させることができる。   In the gap lower gap filling step (step ST4) and the gap upper gap filling step (step ST7) for completing the column main body portion 8, as shown in FIGS. The band reinforcing bars 32 of the arranged panel member 30 are connected to each other via the band reinforcing bar joint unit 43 (step ST31, step ST43), and between the inner panel 35 and the outer side of the panel member 30 arranged on both sides of the gap 41. The side molds 50 are assembled so as to close the space between the panels 34 (step ST32, step ST44), and concrete is placed in the gap 41 closed by the side molds 50 (step ST33, step ST45). Therefore, even if the column head portion 9 is constructed in step ST3 before step ST7 for completing the column main body portion 8, the column main body portion 8 can be completed after the belt reinforcing bars 32 are continued in the circumferential direction.

柱頭部9を構築する柱頭部構築工事(ステップST3)では、図12及び図13に示されるように、柱頭部9から下方に延出して隙間41に配置される接続用主鉄筋31Dを組み立てる(ステップST25)。また、柱本体部8を完成させる隙間上部間詰め工(ステップST7)では、図16に示されるように、主鉄筋31を延長して接続用主鉄筋31Dに接続する(ステップST42)。そのため、柱本体部8を完成させるステップST7の前のステップST3にて柱頭部9を構築しても、主鉄筋31を縦方向に連続させた上で柱本体部8を完成させることができる。   In the pillar head construction work (step ST3) for constructing the pillar head 9, as shown in FIGS. 12 and 13, the connecting main reinforcing bars 31D extending downward from the pillar head 9 and arranged in the gap 41 are assembled ( Step ST25). Further, in the gap upper gap work (step ST7) for completing the column main body 8, the main reinforcing bar 31 is extended and connected to the connecting main reinforcing bar 31D as shown in FIG. 16 (step ST42). Therefore, even if the column head portion 9 is constructed in step ST3 before step ST7 for completing the column main body portion 8, the column main body portion 8 can be completed after the main reinforcing bars 31 are continued in the vertical direction.

隙間下部間詰め工(ステップST4)では、図14に示されるように、切梁22よりも低い空間において、側型枠50を組み立て(ステップST32)、隙間41にコンクリートを打設する(ステップST33)。また、図9に示されるように、柱頭部9を構築する柱頭部構築工(ステップST3)よりも後に、切梁22を撤去し(ステップST6)、隙間上部間詰め工(ステップST7)では、図16に示されるように、切梁22が撤去された空間において、側型枠50を組み立て(ステップST44)、隙間41にコンクリートを打設して(ステップST45)、柱本体部8を完成させる。このような手順を採ることにより、切梁22が残っている状態で構築した柱本体中間体48の上に柱頭部9を構築することが可能になり、切梁22を撤去するステップST6がクリティカルでなくなる。これにより、橋梁工事の工期短縮が可能である。また、切梁22を撤去しながら、隙間41を段階的に間詰めして柱本体部8を完成させることができる。   In the gap lower gap filling step (step ST4), as shown in FIG. 14, the side formwork 50 is assembled in a space lower than the cut beam 22 (step ST32), and concrete is placed in the gap 41 (step ST33). ). In addition, as shown in FIG. 9, after the pillar head construction work (step ST3) for constructing the pillar head 9, the cutting beam 22 is removed (step ST6), and the gap upper spacing work (step ST7), As shown in FIG. 16, in the space from which the cut beam 22 has been removed, the side formwork 50 is assembled (step ST44), and concrete is placed in the gap 41 (step ST45) to complete the column main body portion 8. . By adopting such a procedure, it becomes possible to construct the column head 9 on the column main body intermediate 48 constructed with the beam 22 remaining, and step ST6 for removing the beam 22 is critical. Not. This makes it possible to shorten the construction period for bridge construction. Moreover, the pillar main body 8 can be completed by removing the gaps 22 in stages while removing the beam 22.

図9に示されるように、隙間41の下部を間詰めする隙間下部間詰め工(ステップST4)は、切梁22が干渉しないことから、柱頭部9を構築する柱頭部構築工(ステップST3)の前に、例えば柱本体中間体48を構築する柱本体中間体構築工(ステップST2)の際に一緒に行うこともできる。但し、そのようにすると、柱本体中間体48を構築するのにより多くの時間がかかる。本実施形態では、隙間下部間詰め工(ステップST4)が、柱頭部構築工(ステップST3)の後に行われる。そのため、柱本体中間体48を早急に構築してより早期に柱頭部構築工(ステップST3)を行うことができる。   As shown in FIG. 9, the gap lower portion filling step (step ST4) for filling the lower portion of the gap 41 does not interfere with the beam 22, so that the column head constructing step (step ST3) for constructing the column head 9. For example, the column main body intermediate construction work (step ST2) for constructing the column main body intermediate 48 may be performed together. However, in doing so, it takes more time to build the column body intermediate 48. In the present embodiment, the gap lowering work (step ST4) is performed after the column head construction work (step ST3). Therefore, it is possible to quickly construct the column main body intermediate 48 and perform the column head construction work (step ST3) earlier.

また、ステップST6にて下側の切梁22を撤去する前に、下側の切梁22の下方にて橋脚2の周囲に注水し(ステップST5)、隙間下部間詰め工(ステップST4)の後に、橋脚2の周囲に土砂を埋め戻す(ステップST8)。このように、橋脚2周囲の鋼管矢板井筒16内への注水や埋め戻しが、段階的に行われることから、ステップST6にて切梁22を安全に撤去することができる。   In addition, before removing the lower beam 22 in step ST6, water is injected around the pier 2 below the lower beam 22 (step ST5), and the gap lower space is filled (step ST4). Later, earth and sand are backfilled around the pier 2 (step ST8). Thus, since the water injection and backfilling into the steel pipe sheet pile canteen 16 around the pier 2 are performed in stages, the cut beam 22 can be safely removed in step ST6.

以上で具体的実施形態の説明を終えるが、本発明は上記実施形態に限定されることなく幅広く変形実施することができる。例えば、上記実施形態では、ステップST32、ステップST44において隙間41を塞ぐために側型枠50を組み立てているが、橋脚2の周縁部をなすコンクリートからなる継手パネル40を組み立ててもよい。また、ステップST3の隙間下部間詰め工は、ステップST3の柱頭部構築工の前に行ってもよい。或いは、切梁22よりも下方においては、パネル部材30の周方向長さを長くして隙間41を形成せず、橋軸方向に互いに隣接するパネル部材30間と同様に継手パネル40によってコンクリートパネル間を塞ぐようにしてもよい。更に、上記実施形態では、柱頭部構築工において、パネル部材30を並べている(ステップST21)が、パネル部材30を用いずに型枠を組み立ててもよい。上記実施形態では、橋脚2の断面形状が長円形の概ね一定の形状とされているが、矩形や円形でもよく、上下方向の位置に応じて変化してもよい。この他、各部材や部位の具体的構成や配置、数量、手順など、本発明の趣旨を逸脱しない範囲であれば適宜変更可能である。一方、上記実施形態に示した各構成要素は必ずしも全てが必須ではなく、適宜選択することができる。   Although the description of the specific embodiment is finished as described above, the present invention is not limited to the above embodiment and can be widely modified. For example, in the above-described embodiment, the side mold frame 50 is assembled in order to close the gap 41 in step ST32 and step ST44, but the joint panel 40 made of concrete forming the periphery of the pier 2 may be assembled. In addition, the gap lower gap filling process in step ST3 may be performed before the column head construction work in step ST3. Alternatively, below the beam 22, the circumferential length of the panel member 30 is increased so as not to form the gap 41, and the concrete panel is formed by the joint panel 40 in the same manner as between the panel members 30 adjacent to each other in the bridge axis direction. You may make it close | close. Furthermore, in the said embodiment, in the pillar head construction work, although the panel member 30 is arranged (step ST21), you may assemble a formwork without using the panel member 30. FIG. In the above-described embodiment, the cross-sectional shape of the pier 2 is an oval substantially constant shape, but it may be a rectangle or a circle, and may vary depending on the position in the vertical direction. In addition, the specific configuration, arrangement, quantity, and procedure of each member and part can be changed as long as they do not depart from the spirit of the present invention. On the other hand, not all the constituent elements shown in the above embodiment are necessarily essential, and can be appropriately selected.

1 橋梁
2 橋脚
3 橋桁
8 柱本体部
9 柱頭部
10 基礎(鋼管矢板井筒基礎)
20 支保工
22 切梁
30 パネル部材
30A コーナーパネル部材
30B 中間パネル部材
31 主鉄筋
31D 接続用主鉄筋
32 帯鉄筋
33 中間帯鉄筋
34 外側パネル
35 内側パネル
36 連結パネル
37 閉空間
38 鉄筋篭
41 隙間
43 帯鉄筋継手ユニット(機械継手ユニット)
48 柱本体中間体
50 側型枠
1 Bridge 2 Pier 3 Bridge Girder 8 Column body 9 Column head 10 Foundation (Steel pipe sheet pile well)
DESCRIPTION OF SYMBOLS 20 Supporting work 22 Cutting beam 30 Panel member 30A Corner panel member 30B Intermediate panel member 31 Main reinforcing bar 31D Main reinforcing bar for connection 32 Reinforcing bar 33 Intermediate reinforcing bar 34 Outer panel 35 Inner panel 36 Connection panel 37 Closed space 38 Reinforcing bar 41 Clearance 43 Band rebar joint unit (mechanical joint unit)
48 Column body intermediate 50 Side formwork

Claims (6)

柱本体部と前記柱本体部の上に配置される柱頭部とを有する橋脚の構築方法であって、
外側パネル、内側パネル、及び前記外側パネルと前記内側パネルとを連結する連結部を有し、複数の帯鉄筋及び複数の中間帯鉄筋を含む鉄筋篭が一体化されたプレキャストコンクリートからなる複数のパネル部材を用意するステップと、
前記柱本体部の輪郭に沿って且つ少なくとも周方向の1箇所に隙間を空けて、複数の前記パネル部材を並べるステップと、
前記外側パネル、前記内側パネル及び少なくとも2つの前記連結部によって閉じられた、前記隙間が設けられた部分以外の閉空間にコンクリートを打設するステップと、
前記パネル部材を並べるステップ及び前記閉空間にコンクリートを打設するステップを、前記柱本体部の高さになるまで繰り返し、前記隙間が上方へ延長された、前記柱本体部の未完成状態である柱本体中間体を構築するステップと、
前記柱本体中間体の上に前記柱頭部を構築するステップと、
前記柱頭部の下方にて前記柱本体中間体の前記隙間を間詰めして前記柱本体部を完成させるステップと
を含むことを特徴とする橋脚構築方法。
A construction method of an pier having a column main body and a column head arranged on the column main body,
A plurality of panels made of precast concrete having an outer panel, an inner panel, and a connecting portion that connects the outer panel and the inner panel, and a plurality of reinforcing bars including a plurality of reinforcing bars and intermediate reinforcing bars Preparing a member;
Arranging the plurality of panel members along the outline of the column main body part and at least at one circumferential position;
Placing concrete in a closed space other than the portion provided with the gap, which is closed by the outer panel, the inner panel and at least two of the connecting portions;
The step of arranging the panel members and the step of placing concrete in the closed space are repeated until the height of the column main body is reached, and the gap is extended upward, and the column main body is in an incomplete state. Building a pillar body intermediate;
Building the column head on the column body intermediate;
Filling the gap of the column main body intermediate below the column head to complete the column main body portion.
前記柱本体部を完成させるステップは、
前記隙間の両側に配置された前記パネル部材の帯鉄筋を、機械継手ユニットを介して互いに連結するステップと、
前記隙間の両側に配置された前記パネル部材の前記内側パネル間及び前記外側パネル間を塞ぐように、型枠又は前記柱本体部の周縁部をなすプレキャストコンクリート製の継手パネルを組み立てるステップと、
前記型枠又は前記継手パネルによって閉じられた前記隙間にコンクリートを打設するステップと
を含むことを特徴とする請求項1に記載の橋脚構築方法。
The step of completing the pillar main body is as follows:
Connecting the reinforcing bars of the panel members arranged on both sides of the gap to each other via a mechanical joint unit;
Assembling a joint panel made of precast concrete that forms the periphery of the formwork or the column main body so as to close the space between the inner panels and the outer panels of the panel members disposed on both sides of the gap;
2. The pier construction method according to claim 1, further comprising: placing concrete in the gap closed by the formwork or the joint panel.
前記柱頭部を構築するステップは、前記柱頭部から下方に延出して前記隙間に配置される接続用主鉄筋を組み立てるステップを含み、
前記柱本体部を完成させるステップは、主鉄筋を延長して前記接続用主鉄筋に接続するステップを更に含むことを特徴とする請求項2に記載の橋脚構築方法。
The step of constructing the column head includes a step of assembling a connecting main rebar extending downward from the column head and arranged in the gap,
The pier construction method according to claim 2, wherein the step of completing the column main body further includes a step of extending a main reinforcing bar and connecting the main reinforcing bar to the connecting main reinforcing bar.
前記柱本体部が構築される部分に少なくとも1本の切梁が設けられ、且つ、前記隙間が各切梁に対して平面視において前記柱本体部を通過する周方向の2箇所に設けられており、
前記柱頭部を構築するステップの後に、前記少なくとも1本の切梁を撤去するステップを更に含み、
前記柱本体部を完成させるステップは、
前記少なくとも1本の切梁よりも低い空間において、前記型枠又は前記継手パネルを組み立てるステップ及び前記隙間にコンクリートを打設するステップを行って前記隙間の下部を間詰めするステップと、
前記少なくとも1本の切梁が撤去された空間において、前記型枠又は前記継手パネルを組み立てるステップ及び前記隙間にコンクリートを打設するステップを行って前記隙間の上部を間詰めするステップとを含むことを特徴とする請求項2又は請求項3に記載の橋脚構築方法。
At least one cutting beam is provided in a portion where the column main body portion is constructed, and the gap is provided in two circumferential directions passing through the column main body portion in plan view with respect to each cutting beam. And
After the step of constructing the column head, further comprising the step of removing the at least one beam;
The step of completing the pillar main body is as follows:
In the space lower than the at least one beam, the step of assembling the formwork or the joint panel and the step of placing concrete in the gap to fill the lower portion of the gap;
Including a step of assembling the formwork or the joint panel and a step of placing concrete in the gap in the space where the at least one beam is removed, and filling the upper portion of the gap. The pier construction method according to claim 2 or claim 3, wherein
前記隙間の下部を間詰めするステップが、前記柱頭部を構築するステップの後に行われることを特徴とする請求項4に記載の橋脚構築方法。   The pier construction method according to claim 4, wherein the step of filling the lower portion of the gap is performed after the step of constructing the column head. 前記橋脚が鋼管矢板井筒基礎の上に構築され、
前記切梁を撤去するステップの前に、前記切梁の下方にて前記橋脚の周囲に土砂を埋め戻す又は注水する第1埋め戻しステップと、
前記隙間の下部を間詰めするステップの後に、前記橋脚の周囲に土砂を埋め戻す又は注水する第2埋め戻しステップとを更に含むことを特徴とする請求項4又は請求項5に記載の橋脚構築方法。
The pier is built on a steel pipe sheet pile well foundation,
Before the step of removing the beam, a first backfilling step of backfilling or pouring water around the pier below the beam;
6. The pier construction according to claim 4, further comprising a second backfilling step of backfilling or pouring water around the pier after the step of filling the lower portion of the gap. Method.
JP2018033240A 2018-02-27 2018-02-27 How to build a pier Active JP6960870B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018033240A JP6960870B2 (en) 2018-02-27 2018-02-27 How to build a pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018033240A JP6960870B2 (en) 2018-02-27 2018-02-27 How to build a pier

Publications (2)

Publication Number Publication Date
JP2019148108A true JP2019148108A (en) 2019-09-05
JP6960870B2 JP6960870B2 (en) 2021-11-05

Family

ID=67850332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018033240A Active JP6960870B2 (en) 2018-02-27 2018-02-27 How to build a pier

Country Status (1)

Country Link
JP (1) JP6960870B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114108666A (en) * 2021-11-24 2022-03-01 中铁上海工程局集团有限公司 Construction method of cemented pebble geological cofferdam and cofferdam structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0835210A (en) * 1994-07-22 1996-02-06 Shimizu Corp Tower structure and its construction method
JP2002188159A (en) * 2000-12-19 2002-07-05 Kajima Corp Construction method for underwater structures
JP2008101363A (en) * 2006-10-18 2008-05-01 Oriental Shiraishi Corp Columnar structure, its construction method, and concrete panel
US20080196341A1 (en) * 2007-02-15 2008-08-21 Korea University Industry and Academy Cooperation Foundation Modular Column System Using Internally Confined Hollow Column Unit and Method of Constructing the Same
JP2013002238A (en) * 2011-06-21 2013-01-07 Sumitomo Mitsui Construction Co Ltd Method of constructing bridge pier

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0835210A (en) * 1994-07-22 1996-02-06 Shimizu Corp Tower structure and its construction method
JP2002188159A (en) * 2000-12-19 2002-07-05 Kajima Corp Construction method for underwater structures
JP2008101363A (en) * 2006-10-18 2008-05-01 Oriental Shiraishi Corp Columnar structure, its construction method, and concrete panel
US20080196341A1 (en) * 2007-02-15 2008-08-21 Korea University Industry and Academy Cooperation Foundation Modular Column System Using Internally Confined Hollow Column Unit and Method of Constructing the Same
JP2013002238A (en) * 2011-06-21 2013-01-07 Sumitomo Mitsui Construction Co Ltd Method of constructing bridge pier

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114108666A (en) * 2021-11-24 2022-03-01 中铁上海工程局集团有限公司 Construction method of cemented pebble geological cofferdam and cofferdam structure
CN114108666B (en) * 2021-11-24 2023-01-24 中铁上海工程局集团有限公司 Construction method of cemented pebble geological cofferdam and cofferdam structure

Also Published As

Publication number Publication date
JP6960870B2 (en) 2021-11-05

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
US20160340855A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
JP6855296B2 (en) Building foundation structure and its construction method
KR101187170B1 (en) Application of under pinning method in remodeling
KR100634726B1 (en) Slab construction structure of underground structure and slab and underground retaining wall construction method without frame rib
KR20060092552A (en) Construction method of unsupported downward frame using cast-in-place pile
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR100640244B1 (en) Construction Method of Slab-Outer Wall Simultaneous Placement Using Basement File Without Edge Beam
JP3728653B2 (en) Bonding structure between flat slab and concrete-filled steel pipe column and flat slab construction method
JP2004027609A (en) Construction method of underground structure and underground structure
JP7386095B2 (en) Underground structure construction method
CN111764578B (en) Reverse construction pile column structure and construction method thereof
JP2019148108A (en) Bridge pier construction method
KR100620366B1 (en) Construction method of underground structures including composite reinforced concrete beams
KR20060096706A (en) Deck suspension type underground structure reverse casting method
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP5201719B2 (en) Column construction method and column structure
KR100593203B1 (en) Construction method of underground structure using deck support frame for side pressure support formation and deck support frame for side pressure support formation
JP6514739B2 (en) Construction method for forming underground structure and underground structure completed thereby
CN113136946A (en) Self-supporting assembly type seawater sea sand concrete frame structure and construction method
KR960016755B1 (en) Apparatus and construction method for constructing temporary wall for permanent wall (building base wall)
KR100694762B1 (en) Simultaneous construction of slab-outer wall of basement level without edge beam
KR100757710B1 (en) Dowel rebar construction method of underground structure
KR200390421Y1 (en) Top-down substructure by deck suspension

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201013

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210909

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211005

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211012

R150 Certificate of patent or registration of utility model

Ref document number: 6960870

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250