[go: up one dir, main page]

KR100951097B1 - Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket - Google Patents

Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket Download PDF

Info

Publication number
KR100951097B1
KR100951097B1 KR1020090062871A KR20090062871A KR100951097B1 KR 100951097 B1 KR100951097 B1 KR 100951097B1 KR 1020090062871 A KR1020090062871 A KR 1020090062871A KR 20090062871 A KR20090062871 A KR 20090062871A KR 100951097 B1 KR100951097 B1 KR 100951097B1
Authority
KR
South Korea
Prior art keywords
slab
reinforcement
wall
construction
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020090062871A
Other languages
Korean (ko)
Inventor
황기수
정영기
박무용
Original Assignee
(주)한국건설공법
황기수
정영기
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한국건설공법, 황기수, 정영기 filed Critical (주)한국건설공법
Application granted granted Critical
Publication of KR100951097B1 publication Critical patent/KR100951097B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/61Connections for building structures in general of slab-shaped building elements with each other
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • E04B2001/389Brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 발명은 지하구조물의 각 층 슬래브를 시공한 뒤 흙막이벽에 접하는 지하외벽을 구축하여 합벽으로 시공하는 과정에서, 상기 지하외벽 내에 매립되는 슬래브 부분, 즉 매입슬래브 영역에 상하로 관통하는 개구부를 형성하기 위한 거푸집 역할을 하면서 하중 지지를 위한 영구 구조체의 역할을 동시에 수행할 수 있는 스틸 웨일(wale) 구조체를 설치하여 슬래브를 시공하고, 전 층의 슬래브를 시공한 상태에서 상기 스틸 웨일 구조체에 의해 형성된 개구부를 지하외벽의 수직철근 층간 배근과 콘크리트 타설용 통로로 사용하여 합벽을 층간 연속적으로 순타 시공하는 지하구조물의 슬래브 및 합벽 시공 방법과 이 시공 방법으로 구축한 슬래브 및 합벽 구조물, 그리고 슬래브 및 합벽 시공용 브라켓에 관한 것이다.According to the present invention, after constructing each layer slab of the underground structure, the outer outer wall contacting the earthquake wall is constructed to construct a plywood wall, and the opening portion penetrates up and down in the slab portion embedded in the underground outer wall, that is, the buried slab area. The slab is constructed by installing a steel wale structure that can simultaneously serve as a formwork for supporting loads and a permanent structure for supporting a load, and is formed by the steel wale structure in a state in which slabs of all layers are constructed. Construction method of slab and plywood of underground structures for continuous plying of plywood walls using openings as vertical reinforcement for floor reinforcement and concrete placing passage, slab and plywood structures constructed by this construction method, and slab and plywood construction It is about a dragon bracket.

이러한 본 발명에 의하면, 기존 테두리보가 삭제되면서 테두리보 설치에 따른 문제점이 해소될 수 있으며, 특히 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있으면서도 상기 스틸 웨일 구조체가 하중을 지지하게 되면서 매입슬래브를 포함한 슬래브 전체의 강성이 극대화되는 장점이 있는 한편, 지하외벽에 의해 매립되는 슬래브 부분인 매입슬래브의 내부에 영구구조물로서 매입되는 매입형 RC보 철근틀을 마련하여 양생 후 매입형 RC보 철근틀이 데크슬래브를 지지할 수 있도록 함으로써, 수평방향 및 수직방향의 원활한 하중 전달 시스템을 구현할 수 있고, 따라서 슬래브 및 합벽의 구조적인 안전성을 확보할 수 있는 장점이 있다. According to the present invention, the problem of the installation of the edge beam can be solved by eliminating the existing edge beam, in particular, the continuous reinforcement between the vertical reinforcement of the vertical reinforcement of the basement outer wall and the interlayer continuous casting of concrete can be smoothly performed using the steel As the wale structure supports the load, the stiffness of the entire slab including the buried slab is maximized, while the embedded RC beam reinforcement frame which is embedded as a permanent structure inside the buried slab, which is the slab part embedded by the basement outer wall, is used. After the curing, the embedded RC beam rebar supports the deck slab, so that a smooth load transmission system in the horizontal and vertical directions can be realized, thus securing the structural safety of the slab and the plywood wall. have.

Description

지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 받침브라켓{slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket}Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket}

본 발명은 지하구조물의 슬래브 및 합벽 구조물과 시공 방법에 관한 것으로서, 더욱 상세하게는 지하구조물의 층간 슬래브를 시공한 후 흙막이벽에 접하는 지하 외벽을 구축하여 합벽으로 시공하는 방법과 이 시공 방법에 의해 구축되는 슬래브 및 합벽 구조물과 받침브라켓에 관한 것이다.The present invention relates to a slab, a plywood structure and a construction method of an underground structure, and more particularly, after constructing an interlayer slab of an underground structure, constructing an underground outer wall in contact with an earthquake wall and constructing it as a plywood wall and by this construction method. The present invention relates to a slab and plywood structure and a supporting bracket to be constructed.

일반적으로 지하구조물을 구축하는 방법에는 두 가지가 있다.In general, there are two ways to build underground structures.

지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고 토사를 전부 반출한 뒤 맨 아래층부터 구조물을 축조해 올라가는 순타설공법과, 흙막이를 시공하고 1층 구조물을 축조한 다음 그 구조물을 흙막이용 버팀부재로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 역타설 공법이 그것이다.After constructing the earthquake on the ground where the underground structure is constructed, install the temporary facility to support the earthquake while excavating the ground, take out all the earth and sand, and build the structure from the bottom floor, After the construction of the first-floor structure, using the structure as a retaining member for the earthquake, the reverse casting method is to construct the structure while drilling the ground from the top to the bottom.

최근 토지 이용의 극대화 차원에서 지하공사가 점차 고심도화되고 있고, 특히 순타설공법에 의한 시공시에는 흙막이 붕괴의 위험이나 주변 건물들 침하 등으로 인한 균열 발생은 물론, 시각적으로도 불안할 뿐만 아니라 공사기간이 길어지는 등 여러 문제가 있어서, 근래에는 역타설 공법이 널리 적용되고 있다.In recent years, underground construction has been increasingly intensified in order to maximize land use. In particular, when the construction is carried out by the net pouring method, not only the construction of cracks due to the risk of earthquake collapse or the settlement of nearby buildings, but also visually unstable construction Due to various problems such as long periods of time, the reverse casting method has been widely applied in recent years.

상기 역타설 공법은 지하구조물 축조시에 지상 1층부터 단계적으로 시공해 내려가는 방식이므로, 지하구조물과 지상구조물의 시공을 동시에 진행할 수 있고, 지상 1층의 바닥을 작업장으로 활용할 수 있어 별도의 복공판이 필요하지 않은 장점이 있다.The reverse casting method is a method of constructing the ground structure from the ground floor step by step when constructing the underground structure, so that the construction of the underground structure and the ground structure can be carried out at the same time, and the floor of the ground floor can be used as a workshop so that a separate perforated plate is provided. There is an advantage that is not necessary.

이러한 역타설 공법으로는 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(Concrete on grade)과, 지반을 어느 정도 굴착하고 지반을 고른 뒤 동바리를 세우고 거푸집을 설치하여 콘크리트를 타설하는 방법(Form on supporting)과, 거푸집 지지를 위한 동바리를 세우지 않는 대신에 선(先) 시공한 상층의 콘크리트 슬래브에 거푸집 지지를 위한 거푸집 지지거더를 현수시켜 콘크리트를 타설하는 방법(무지보 역타설 현수 거푸집 공법) 등이 있다.Such a reverse casting method involves placing concrete slabs and beams on the ground while the ground is stopped (concrete on grade), and excavating the ground to some extent, picking the ground, placing the clubs and installing the formwork, and placing the concrete. (Form on supporting) and the method of placing concrete by suspending form support girder for form support on the upper concrete slab which is pre-constructed instead of erecting a circle for supporting form (unsupported reversal suspension form Construction method).

또한, 최근 널리 사용되고 있는 방법으로, 거푸집 지지거더(이는 H-형강 철골보로서 영구 구조체로 사용되거나, 가설 구조체로서 시공 후에 해체함)를 골조용 기둥에 해체 가능한 이동식 조립 브라켓을 이용하여 지지시키고, 상기 지지거더를 이용하여 층간 슬래브 및 보 시공을 위한 거푸집을 지지시켜 설치한 뒤 슬래브 및 보 콘크리트를 타설하는 방식이 있다.In addition, as a method widely used in recent years, formwork girders (which are used as permanent structures as H-beam steel beams or dismantled after construction as construction structures) are supported by using a movable assembly bracket which can be disassembled to a frame pillar, and There is a method of placing slab and beam concrete after supporting and installing formwork for interlayer slab and beam construction by using support girder.

한편, 역타설 시공시에는 통상적으로 흙막이벽과 각 층 슬래브가 만나는 외 곽 경계부분에 띠장 또는 접합거더 역할을 하는 철근 콘크리트 테두리보(perimeter beam)가 설치되고, 모든 지하층의 슬래브 시공이 끝난 뒤에는 맨 아래층부터 위층으로 올라가면서 흙막이벽 안쪽에 지하외벽을 순타 시공하여 지하합벽을 완성하게 된다.On the other hand, reinforcement construction is usually provided with a reinforced concrete perimeter beam that acts as a strip or a joining girder at the outer boundary where the earth wall and the slab meet each other. Going upstairs from the lower floor, the underground outer wall is smoothly constructed inside the retaining wall to complete the underground plywood.

여기서, 종래기술에 따른 지하층의 슬래브 및 테두리보 시공을 위한 거푸집 구성 및 작업에 대하여 첨부한 도면을 참조하여 설명하면 다음과 같다.Here, with reference to the accompanying drawings for the formwork and work for the slab and rim beam construction of the basement layer according to the prior art as follows.

첨부한 도 1은 종래 슬래브 및 테두리보의 시공을 위한 거푸집 구조체의 설치상태를 보여주는 단면도로서, 거푸집 설치상태에서 콘크리트의 양생 중 상태를 나타내고, 도 2는 종래 슬래브 및 테두리보의 시공이 완료된 상태를 보여주는 단면도로서, 콘크리트의 양생 후에 거푸집을 해체한 상태를 나타낸다. 1 is a cross-sectional view showing the installation state of the formwork for the construction of the conventional slab and rim beam, showing the state of curing of the concrete in the formwork installation state, Figure 2 shows the state of the construction of the conventional slab and rim beam is completed The cross-sectional view shows a state in which the formwork is dismantled after curing of concrete.

이들 도면은 데크 플레이트(deck plate) 지지를 위한 지지거더 설치된 위치에서의 단면도이다.These figures are sectional views in the position where the support girders are installed for supporting the deck plate.

도 1에서 도면부호 2는 흙막이벽 내에 수직 시공된 엄지말뚝, 즉 수직 강재빔인 H-파일(pile)을 나타낸다.In FIG. 1, reference numeral 2 denotes an H-pile that is a thumb pile vertically constructed in the retaining wall, that is, a vertical steel beam.

보통 흙막이벽(1)의 형식으로는 주열식 벽으로서 SCW(Soil Cement Wall)와 CIP(Cast In-Place Pile)가 있고, 이들은 엄지말뚝으로서 통상 H-파일(2)을 사용하고 있으며, 이 H-파일(2)이 배면의 토압 및 수압을 직접 지지하는 수직 휨부재로서의 역할을 하게 된다.Usually, there are two types of soil walls (Soil Cement Wall) and CIP (Cast In-Place Pile) as main heating walls, and they usually use H-pile (2) as thumb pile. The pile 2 serves as a vertical bending member that directly supports the earth pressure and the hydraulic pressure of the rear surface.

테두리보(17)의 시공을 위하여 종래에는 흙막이벽(1)을 시공한 뒤 굴토작업을 먼저 하고, 버림 콘크리트(3)를 타설한 뒤 동바리(4)를 설치하여 거푸집을 지지 시키게 된다.For the construction of the rim beam 17 in the prior art after the construction of the retaining wall (1) to the gulting work first, after casting the discarded concrete (3) to support the formwork by installing the copper club (4).

여기서, 시공하고자 하는 테두리보(17)의 길이방향에 대하여 그 횡방향으로 길게 배치되는 각재(5)를 복수개의 동바리(4)로 지지시키고, 이 각재(5) 위에는 테두리보 하면 성형을 위한 합판 거푸집(6)을 수평으로 배치하여 지지시키며, 이 수평의 합판 거푸집, 즉 거푸집 하판(6) 위로는 테두리보 측면 성형을 위한 합판 거푸집(미도시)을 수직으로 고정 배치하여 지지시킨다.Here, the lumber 5 which is arranged long in the transverse direction with respect to the longitudinal direction of the rim beam 17 to be constructed is supported by a plurality of copper wheels 4, on the rim beam 5, plywood for molding The formwork 6 is horizontally arranged and supported, and the horizontal plywood formwork, ie, the formwork lower plate 6, is fixed and vertically supported by a plywood formwork (not shown) for forming the side beams.

또한, 슬래브 구축용 구조체로서 도면부호 7은 철골보 구조물인 지지거더를 나타내고, 도면부호 15는 지지거더(7)에 의해 지지되는 데크 플레이트를 나타낸다.In addition, as the slab construction structure, reference numeral 7 denotes a support girder which is a steel golbo structure, and reference numeral 15 denotes a deck plate supported by the support girder 7.

상기 지지거더(7)로는 통상 H-형강이 사용되고, 그 일단부가 동바리(4) 및 거푸집 하판(6) 등에 의해 지지되며, 일단부 끝단에는 임베디드 플레이트(embedded plate)(8)가 용접 및/또는 고정 브라켓(9a)과 체결부재(9b)에 의해 수직으로 결합된다.As the support girder 7, H-shaped steel is generally used, one end of which is supported by a copper wheel 4, a form lower plate 6, and the like, and an embedded plate 8 is welded and / or at one end of the support girder 7. It is vertically coupled by the fixing bracket 9a and the fastening member 9b.

그리고, 도 1은 지지거더(7)가 설치되는 위치에서의 종방향 단면도이기 때문에 테두리보 측면 성형을 위한 합판 거푸집, 즉 거푸집 옆판이 미도시되었으나, 이 거푸집 옆판은 시공하고자 하는 테두리보(17)의 길이방향을 따라서 임베디드 플레이트(8)의 양 측방으로 길게 설치되며, 이는 각 지지거더(7) 끝단의 임베디드 플레이트(8)와 함께 테두리보 성형공간의 측면을 이루게 된다.And, Figure 1 is a longitudinal cross-sectional view at the position where the support girder (7) is installed, plywood formwork for forming the side beams, that is, the formwork side plate is not shown, this formwork side plate is the edge beam 17 to be constructed It is installed along both longitudinal sides of the embedded plate 8 in a long direction, which forms a side of the rim beam forming space with the embedded plate 8 at the end of each support girder 7.

또한, 테두리보용 콘크리트가 타설되는 성형공간, 즉 H-파일(2)을 포함한 흙막이벽(1), 거푸집 하판(6), 임베디드 플레이트(8) 및 미도시된 거푸집 옆판이 형성하는 사각 단면형상의 테두리보 성형공간 내에는 길이방향의 철근(11) 및 스터럽 철근(12)을 설치함과 더불어 지하합벽 공간 내 매립되는 수직철근(19)을 상하로 연결하여 설치하는 배근작업을 하고, 테두리보 성형공간 내에서 흙막이벽(1)에 내장된 H-파일(2)의 플랜지면에는 벽의 일부를 제거한 후 전단연결부재인 스터드(13)가 용접 시공된다.In addition, the square space of the cross-section formed by the molding space in which the frame for the concrete is poured, that is, the retaining wall (1), the formwork lower plate (6), the embedded plate (8) and the formwork side plate not shown In the frame beam forming space, the reinforcing bar 11 and the stub reinforcing bar 12 are installed in the longitudinal direction, and the vertical reinforcing bar 19 embedded in the underground plywood space is connected up and down to install the reinforcement. After removing a part of the wall, the stud 13, which is a shear connection member, is welded to the flange surface of the H-pile 2 embedded in the retaining wall 1 in the space.

또한, 테두리보 성형공간 내에서 상기 임베디드 플레이드(8)에도 전단연결부재인 스터드(14)가 용접 시공되는데, 이와 같이 설치되는 스터드(13,14)는 테두리보 콘크리트 속에 매립되는 바, 이들은 H-파일(2)과 테두리보(17) 간, 그리고 테두리보(17)와 임베디드 플레이트(8) 간 상호 결착력을 증대시키기 위하여 시공되는 것들이다.In addition, the stud 14, which is a shear connection member, is welded to the embedded plate 8 in the edge beam forming space, and the studs 13 and 14 installed as described above are embedded in the edge beam concrete, and these are H -They are constructed to increase the mutual binding force between the pile (2) and the rim beam 17, and the rim beam 17 and the embedded plate (8).

이와 같이, 슬래브(16) 및 테두리보(17) 시공을 위한 거푸집 등 구조체를 모두 설치하고 나면, 슬래브 및 보 콘크리트 타설시에 상기 테두리보 성형공간 내에 콘크리트를 함께 타설하여 테두리보(17)를 성형한다.As such, after installing all the structures such as the formwork for the construction of the slab (16) and the rim beam (17), when the slab and beam concrete is poured, the concrete is poured together in the rim beam forming space to form the rim beam (17) do.

그리고, 콘크리트가 양생되고 나면, 동바리(4) 및 각재(5), 합판 거푸집(거푸집 하판 및 옆판)(6) 등은 해체하고, 철골보인 지지거더(7) 및 임베디드 플레이트(8) 등은 영구 구조체로 사용하게 된다.Then, after the concrete is cured, the copper bar (4) and the lumber (5), plywood formwork (form lower plate and side plate) (6), etc. are dismantled, the steel girders support girder (7) and embedded plate (8) is permanent It will be used as a structure.

이후 하층으로 내려가면서 각 층에 대해 상기와 같은 작업을 반복하여 층간 슬래브 및 각 층 슬래브와 흙막이벽을 접합시켜주는 테두리보를 단계적으로 시공하게 되며, 모든 지하층에 대하여 층간 슬래브 및 테두리보의 역타 시공이 완료되면, 지하외벽 거푸집 설치 및 콘크리트 시공을 하여 테두리보가 드러나지 않도록 합벽(옹벽) 순타 시공을 하게 된다. After going down to the lower floor, the above operation is repeated for each floor, and the girder beam connecting the interlayer slab and each layer slab and the earthen wall is constructed step by step, and the reverse construction of the interlayer slab and the rim beam is performed for all basement floors. Upon completion, the base wall wall formwork is installed and concrete construction, and the plywood (retaining wall) netting construction is performed so that the rim beam is not exposed.

이때의 순타 시공은 아래층부터 위층의 순으로 시공을 하게 된다.The net construction at this time is to be constructed in the order of the lower floor to the upper floor.

통상적으로 지하합벽은 층간 슬래브와 테두리보가 시공되고 나면 이후 흙막이벽 내측면에 외벽 시공용 거푸집을 설치한 뒤 이 거푸집 내부에 콘크리트를 타설하여, 테두리보가 매립되도록 흙막이벽과 외벽을 합벽 시공하여 완성되는데, 이러한 지하합벽의 시공은 층간 슬래브 및 테두리보의 시공 후 아래층으로부터 위층으로 올라가면서 외벽을 시공하는 순타 시공의 방식으로 작업이 이루어진다.Normally, the basement cladding is completed after the interlayer slab and the rim beam are installed, and then install the formwork for exterior wall construction on the inner side of the retaining wall, and then cast concrete inside the formwork to finish the construction of the cladding wall and the outer wall so that the rim beam is embedded. In addition, the construction of the underground plywood is carried out in the manner of the netting construction of the outer wall while going up from the lower floor to the upper floor after the construction of the interlayer slab and the rim beam.

첨부한 도 3은 지하합벽의 순타 시공이 이루어지는 상태의 예를 도시한 단면도로서, 이는 지지거더가 설치되지 않은 위치, 즉 지지거더와 지지거더 사이의 중간위치에서 취한 단면도이다.FIG. 3 is a cross-sectional view showing an example of a smooth construction of the underground plywood, which is a cross-sectional view taken at a position where the support girder is not installed, that is, an intermediate position between the support girder and the support girder.

슬래브(16)와 테두리보(17)의 시공이 완료된 후 흙막이벽(1) 내측으로 외벽 시공용 거푸집(미도시)을 설치하고, 이 거푸집 공간에 콘크리트를 타설하여 외벽(18)을 시공하는 방식으로 지하합벽의 시공작업이 이루어진다.After the construction of the slab 16 and the rim beam 17 is completed, a formwork for exterior wall construction (not shown) is installed inside the retaining wall 1, and concrete is poured into the form space to construct the outer wall 18. The construction of the underground plywood is done.

한편, 지하구조물의 슬래브 및 합벽을 시공하는 과정에 있어서, 도 1 및 도 2, 그리고 도 3에 도시한 종래기술에 따르면 다음과 같은 문제점이 있다.On the other hand, in the process of constructing the slab and plywood of the underground structure, according to the prior art shown in Figures 1 and 2, and 3 has the following problems.

테두리보 시공에 따른 문제점으로서, 위에서 설명한 바와 같이 일반 합판 거푸집(6)과 동바리(4)를 이용함으로써, 동바리 설치에 따른 토공작업 지연과 콘크리트 타설시 가끔 거푸집 파괴 등에 의해 작업 차질이 많이 발생하고, 거푸집 설치가 복잡하여 시공성 저하 및 원가 증대의 문제가 발생한다. As a problem due to the construction of the rim beam, as described above, by using the general plywood formwork (6) and the copper barrier (4), a lot of work disruptions occur due to delayed earthwork work due to the installation of the copper bar and occasional formwork destruction during concrete pouring, The formwork is complicated to install, which leads to problems of poor workability and cost increase.

특히, 동바리(4)의 이용시에는 연약 지반상에서의 지지가 불안정하고, 또한 콘크리트의 강도가 일정 이상으로 보양되지 않으면 해체가 불가하기 때문에 콘크리 트 양생 중 동바리의 존치로 인해 아래층의 굴토공사가 진행되지 못하여 공기가 지연될 수 밖에 없는 문제가 있다.In particular, when the copper barrier 4 is used, support on the soft ground is unstable and dismantlement is impossible unless the strength of concrete is maintained above a certain level. There is a problem that can not but delay the air.

더구나, 동바리 등 가설자재는 역타설 시공시 굴토작업장 외부로 반출한 뒤 굴토 후 다시 아래층으로 이동하여 설치해야 하고, 이를 각 층의 시공시마다 반복해야 하는 바, 이러한 작업을 반복 수행하는데 있어서 번잡한 문제점이 있다.In addition, temporary materials such as dongbari should be moved to the lower floor after the excavation after installation to the outside of the gulto workshop during the construction of reverse casting, and this should be repeated for the construction of each floor. There is this.

또한, 동바리의 소운반 및 재조립에 소요되는 비용과 시간이 과다하여 비경제적일 뿐만 아니라, 모든 작업이 인력에 의존하는 노동집약적이기 때문에 기능공의 인력 부족이 점차 심화되는 현실에서 동바리의 사용은 원가 절감을 어렵게 한다.In addition, the cost and time required for transporting and reassembling the club are not only economically unfavorable, but also the labor-intensive labor shortage of all workers makes the use of copper club cost-effective. Makes it difficult.

그리고, 테두리보 시공으로 거푸집 작업을 위한 목공작업이 중간 중간에 실시되어야 하는 문제점도 있다.In addition, there is a problem that the woodworking work for the formwork by the rim beam construction should be carried out in the middle.

특히, 슬래브 시공을 위해 데크 플레이트(15)를 설치하여 데크 슬래브(deck slab)(16)를 시공하고 있는데 반하여, 테두리보 시공시에는 거푸집 작업을 위해 목재로 된 합판 거푸집의 작업이 필요하므로 목공작업 인원이 단속적으로 투입되어야 한다.In particular, the deck slab (16) is installed by installing the deck plate (15) for the slab construction, while the rim beam construction requires the work of wood plywood formwork for formwork work, so woodworking work Personnel should be intermittent.

이와 같이, 철공공 외에 목공작업공의 이질공종 인력이 투입됨으로써 공사원가가 상승함은 물론 인력 투입의 효율성이 크게 떨어지는 문제점을 가진다.As such, the work cost increases as well as the labor cost of the woodworker in addition to the ironworker, as well as the efficiency of manpower input has a problem that is greatly reduced.

또한, 테두리보 시공에 따른 스터럽 및 보강 철근량의 과다 소요, 연결철근의 사용량 과다로 인한 재료 낭비의 문제점이 있고, 테두리보 철근 배근을 위한 철근 가공 및 조립이 복잡할 뿐만 아니라, 배근 설치를 위한 조립시간이 필요하여 공 기 지연 및 공사비 증대의 요인이 되고 있다.In addition, there is a problem of excessive waste of stirrups and reinforcing bars according to the construction of the rim beams, waste of materials due to excessive use of connecting bars, and complicated reinforcing and assembly of reinforcing bars for rim reinforcement. Time is required, causing air delays and increasing construction costs.

또한, 슬래브(16)가 선 시공되고 외벽(18)이 후 시공됨에 따라서 테두리보(17)의 상,하면과 외벽(18) 간에는 접합면이 발생하는 바, 이 접합면에서의 누수가 문제점으로 지적되고 있으며, 이러한 누수문제를 해결하기 위해서는 시공 후 접합면 간에 에폭시를 주입해야 하는 보수작업이 필요하다. In addition, as the slab 16 is pre-constructed and the outer wall 18 is post-constructed, a joint surface is generated between the upper and lower surfaces of the rim beam 17 and the outer wall 18. It is pointed out that, in order to solve this leak problem, repair work that requires the injection of epoxy between the joint surface after construction is required.

상기한 종래 테두리보 시공의 문제점을 해결하기 위하여, 테두리보를 최소화하거나 아예 생략하는 다양한 시공 기술들이 본 발명자에 의해 고안 또는 발명된 바 있다(실용신안등록 제370107호, 실용신안등록 제370135호, 실용신안등록 제381303호, 실용신안등록 제385376호, 특허등록 제634726호).In order to solve the problems of the conventional rim beam construction, various construction techniques that minimize or omit the rim beam has been devised or invented by the present inventors (Utility Model Registration No. 370107, Utility Model Registration No. 370135, Utility Registered Model No. 381303, Registered Utility Model No. 385376, Registered Patent No. 634726).

상기의 기술에서는 테두리보를 최소화하여 테두리보 시공에 소요되는 철근 및 거푸집 물량을 최소화하고 공기를 단축하는 한편 기존 테두리보 시공에 따른 문제점을 해결하였다. The above technique minimizes the edge beams, minimizes the amount of rebar and formwork required for the construction of the edge beams, shortens the air, and solves the problems caused by the existing edge beam constructions.

또는 층간 슬래브를 흙막이벽에 바로 연결 시공하여 테두리보를 아예 삭제함으로써 종래 테두리보 시공에 따른 문제점을 해결하였다.Or by connecting the interlayer slab directly to the wall of the barrier to solve the problem of the conventional rim beam construction by eliminating the rim beam at all.

한편, 테두리보를 시공하거나 테두리보가 생략된 지하구조물의 역타 시공 과정에서는 테두리보나 슬래브(테두리보가 생략된 경우) 사이의 나머지 상하부 합벽 부분을 나중에 시공한다.On the other hand, in the construction of the reverse beam construction of the rim beam or the underground structure without the rim beam, the remaining upper and lower plywood parts between the rim beam or the slab (when the rim beam is omitted) are later constructed.

즉, 흙막이벽을 지지하도록 각 층의 층간 수평구조체인 슬래브 및 테두리보(생략될 수 있음)를 우선 시공한 뒤 흙막이벽과 일체로 외벽을 구축하여 합벽으로 시공하게 되는 것이다.That is, the slab and the rim beam (which may be omitted), which are the interlayer horizontal structures of each layer, are first constructed to support the wall, and then the outer wall is integrally formed with the wall to construct the plywood wall.

이때, 슬래브 또는 테두리보를 흙막이벽에 직접 정착되도록 선 시공하여 토압 등 외력을 지지케 하고, 외벽을 후 시공하여 슬래브 또는 테두리보를 외벽에 매립시키는 방법으로 합벽 시공이 이루어지는 바, 외벽의 후 시공을 위해서는 선 시공된 슬래브나 테두리보에 콘크리트 타설용 슬리브(sleeve)가 반드시 설치되어야 하며, 나아가 외벽 주철근의 층간 연속 배근의 어려움이 있으므로 상하층의 외벽을 일체화하기 위한 별도의 다월 철근(dowel bar)를 설치해야 한다.At this time, the slab or rim beam is pre-installed to be settled directly to the retaining wall to support external force such as earth pressure, and after the outer wall is installed, the plywood is constructed by embedding the slab or rim beam on the outer wall. A concrete sleeve must be installed on the pre-installed slab or rim beam, and additional dowel bars are installed to integrate the outer walls of the upper and lower layers because of the difficulty of continuous reinforcement between the layers of the outer reinforcing bars. Should be.

상기 슬리브는 외벽에 매립되는 슬래브 부분(이하, '매입슬래브'라 함) 또는 테두리보를 상하로 관통하는 통로가 되는 것으로서, 슬래브, 테두리보의 시공시 매입슬래브 또는 테두리보 영역에 슬리브 형성을 위한 충전 파이프를 미리 수직으로 내설하고 이후 그 외측으로만 콘크리트를 타설하여, 콘크리트가 타설되지 않은 충전 파이프의 내부공간에 의해 상하로 관통하는 슬리브가 형성되도록 한다.The sleeve is a passage for vertically penetrating the slab portion (hereinafter referred to as 'buried slab') or the rim beam embedded in the outer wall, the filling for forming the sleeve in the embedded slab or rim beam area during the construction of the slab, rim beam The pipe is pre-verted vertically and then concrete is poured outward so that the sleeve penetrates up and down by the inner space of the filling pipe where the concrete is not poured.

그러나, 합벽 시공시 슬리브를 통한 콘크리트의 타설은 그 시공 자체가 어려울 뿐만 아니라 콘크리트가 밀실하게 채워지는 것을 어렵게 하여 매입슬래브나 테두리보 저면에 콘크리트의 건조 수축에 의한 역타조인트(지하외벽의 층간 틈)를 발생시키며, 이러한 역타조인트는 건축물의 누수에 의한 구조적인 성능을 저하시키는 원인으로 작용하게 된다. However, in the construction of plywood walls, the casting of concrete through the sleeve is not only difficult for the construction itself but also makes it difficult for the concrete to be filled tightly. This reverse oscillation joint acts as a cause of deteriorating structural performance due to leakage of the building.

역타조인트를 통하여 지하수의 유입이 이루어지면, 유입된 지하수는 철근의 부식, 콘크리트 열화현상을 일으키고, 그 결과로 구조물의 내구성이 떨어지게 된다. When the groundwater is introduced through the inverted joint, the inflowed groundwater causes corrosion of the reinforcing steel and deterioration of the concrete, resulting in poor durability of the structure.

따라서, 테두리보가 시공되든 시공되지 않든 간에 기존 슬리브와 같은 지하 합벽 콘크리트 타설용 구조는 좀더 개선될 필요가 있는 것이다.Therefore, whether the rim beam is constructed or not, the underground plywood concrete placing structure such as the existing sleeve needs to be further improved.

이에 본 발명자는, 앞에서 설명한 모든 문제점이 해소될 수 있는 기술로서, 동바리의 사용이 불필요하고 또한 테두리보가 삭제될 수 있으며 지하외벽 콘크리트 타설을 위한 별도 슬리브 시공이 필요 없는 기술을 특허등록 제634726호를 통해 제시한 바 있다.Therefore, the present inventors, as a technology that can solve all the problems described above, the use of the copper bar and the edge beam can be eliminated, and the technology that does not need a separate sleeve construction for concrete laying underground walls outside the patent registration No. 634726 It was suggested through.

여기서는 테두리보의 삭제 및 슬리브 시공의 생략을 위해서 흙막이벽과 슬래브 공간 사이에 복수개의 그레이팅 지지틀을 연속되게 설치하는 기술이 제시되어 있다. In this case, a technique for continuously installing a plurality of grating support frames between the retaining wall and the slab space is proposed for eliminating the rim beam and eliminating the sleeve construction.

그러나, 상기와 같이 그레이팅 지지틀을 설치하는 방법에서는 다음과 같은 문제점이 있었다.However, the method of installing the grating support frame as described above had the following problems.

우선, 공장 가공된 그레이팅 지지틀을 현장에서 흙막이벽과 슬래브 공간 사이, 즉 매입슬래브 영역에 설치하도록 되어 있으나, 그레이팅 지지틀을 실제 설치함에 있어서 그 크기와 부피가 매우 크므로 설치에 많은 어려움이 있다.First of all, the factory-worked grating support frame is installed in the field between the earthquake wall and the slab space, that is, the buried slab area. However, the size and volume of the grating support frame is very large, so the installation is difficult. .

실제 설치하는 과정에서 두 사람이 그레이팅 지지틀을 손으로 잡고 정 위치에 설치하게 되는데, 그 부피와 무게가 두 사람이 작업하기에 어려움이 있으므로 실제 시공시 더욱 많은 인력이 소요될 수 있고, 인건비 및 작업시간의 과다 소요, 작업능률 저하 등 여전히 개선해야 할 몇 가지 문제가 있는 것이 사실이다. In the actual installation process, two people hold the grating support frame by hand and install it in the right position. Since the volume and weight are difficult for two people to work, it may require more manpower during actual construction, labor costs and work. It is true that there are still some problems that need to be improved, such as excessive time and poor work efficiency.

또한, 그레이팅 지지틀을 매입슬래브 영역을 따라 연속되게 설치하므로 많은 철재 물량(그레이팅 지지틀 제작에 소요되는 물량 및 그레이팅 지지틀의 사용 개수에 따른 물량)이 소요되고, 이는 곧 공사비 과다의 원인이 되어 왔다.In addition, since the grating support frame is continuously installed along the buried slab area, a large amount of steel (amount required for manufacturing the grating support frame and the number of grating support frames used) is required, which causes excessive construction cost. come.

아울러, 그레이팅 지지틀이 지하외벽 두께, 즉 외벽 폭의 전체 구간에 걸쳐 설치되기 때문에 중량 과다, 경제성 저하의 문제를 가중시킨다. In addition, since the grating support frame is installed over the entire section of the outer wall thickness, that is, the outer wall width, the grating support frame adds to the problem of overweight and deterioration of economic efficiency.

또한, 규격화하여 공장 제작한 크기의 큰 그레이팅 지지틀을 현장에서 전 구간을 따라 서로 연속되게 붙여서 설치하는 것이기 때문에, 건축물의 모서리 부분에서는 설치가 불가능하다. In addition, it is impossible to install in the corner portion of the building because it is installed by attaching a large grating support frame of the size standardized and factory manufactured in succession along the entire section in the field.

따라서, 모서리 부분에서는 별도 방법을 고려해야 하며, 필요에 따라서는 공장 제작된 그레이팅 지지틀을 현장에서 절단 가공하여 사용하는 것이 필요하다.Therefore, a separate method should be considered in the corner portion, and if necessary, it is necessary to cut and use the factory-made grating support frame in the field.

이로 인한 작업의 어려움, 작업능률의 저하, 자재 손실 등이 문제점으로 지적될 수 있다.This can be pointed out as a problem due to the difficulty of work, deterioration of work efficiency, material loss.

또한, 그레이팅 지지틀을 구성하는 플레이트가 평판 형태이므로 단면 효율 저하 및 경제성 저하의 문제가 있다. In addition, since the plate constituting the grating support frame is in the form of a flat plate, there is a problem of lowering cross-sectional efficiency and lowering economic efficiency.

다음으로, 동바리의 사용이 불필요하고 또한 테두리보가 삭제될 수 있으며 지하외벽 콘크리트 타설을 위한 별도 슬리브 시공이 필요없는 또 다른 방식의 기술이 특허등록 제722198호에 개시되어 있다.Next, another type of technology is disclosed in Patent No.722198, which does not require the use of a copper bar and can remove the rim beam, and does not require a separate sleeve construction for placing an underground outer wall concrete.

이는 건축물 지하의 층간 슬래브가 흙막이벽을 지지하도록 시공되는 지하 흙막이벽의 지지구조에서 흙막이벽에 접하면서 지하외벽에 매립되는 매입슬래브에 개구부가 형성되도록 매입거푸집을 설치한 뒤 지하외벽 밖으로 노출되는 노출슬래브 두께 이상으로 콘크리트를 타설하여 개구부를 형성시키는 방식이다.This is because the exposed formwork is formed so that openings are formed in the embedded slab buried in the basement outer wall while the interlayer slab in the building is constructed to support the retaining wall. It is a method of forming the opening by pouring concrete more than the slab thickness.

이러한 시공 방식에서는 슬래브 콘크리트 타설 후 매입거푸집에 의해 매입슬래브에 상하로 관통하는 개구부가 성형되므로, 이 개구부에 의해 지하외벽의 시공 을 연속적으로 용이하게 진행할 수 있는 장점이 있다.In this construction method, since the openings penetrating up and down the embedded slab are formed by embedding dies after slab concrete is poured, there is an advantage that the construction of the basement outer wall can be easily proceeded by the openings.

그러나, 이 방식에서는 다음과 같은 치명적인 단점이 있다.However, this method has the following fatal disadvantages.

첨부한 도 4 및 도 5는 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 4는 개방형 판재 구조의 매입거푸집을 사용하여 시공한 평면도이고, 도 5는 도 4의 선 'A-A'를 따라 취한 단면도이다. 4 and 5 are views for explaining the problems according to the prior art, Figure 4 is a plan view using a built-in formwork of the open plate structure, Figure 5 is a line 'A-A' of Figure 4 It is a cross section taken along.

도 3에 도시한 바와 같이, 시공된 철근 콘크리트 슬래브(S)는 흙막이벽(100)에 접하면서 지하외벽(111)에 매립되는 부분인 매입슬래브(S1)와 지하외벽 밖으로 노출되는 부분인 노출슬래브(S2)로 구분되고, 매입거푸집(121)이 매입슬래브 영역에서 소정 간격으로 배치되어 슬래브 콘크리트 타설 후에는 개구부(OP)를 형성하게 된다. As shown in FIG. 3, the constructed reinforced concrete slab S is a buried slab S1 which is a portion embedded in the basement outer wall 111 while exposed to the earth wall 100 and an exposed slab that is exposed outside the basement outer wall. It is divided into (S2), the embedding die 121 is disposed at predetermined intervals in the embedded slab area to form the opening OP after slab concrete pouring.

또한, 슬래브(S)의 시공이 완료되면 매입슬래브(S1)에 형성된 개구부(OP)를 이용하여 합벽 시공이 진행된다. In addition, when the construction of the slab (S) is completed, the construction of the plywood wall proceeds using the opening OP formed in the embedded slab S1.

일단, 테두리보가 생략되므로 테두리보 시공에 따른 문제점이 해결되고 동바리를 사용하지 않으므로 동바리 사용에 따른 문제점이 해결되나, 매입거푸집(121)에 의해 형성된 개구부(OP)가 매입슬래브를 상하로 관통하는 종래의 슬리브와 비교할 때 그 형상을 원형에서 그 외 다양한 각형(나비형 개구부를 예로 개시하고 있음)으로 변경한 점에 불과하다. Once, the edge beam is omitted, so the problem caused by the construction of the edge beam is solved and the problem of the use of the copper bar is solved since the copper bar is not used, but the opening OP formed by the embedding die 121 penetrates the embedded slab vertically. Compared to its sleeve, the shape has only been changed from circular to various other squares (butterfly openings are shown as examples).

즉, 매입거푸집(121)을 사용하여 기존 슬리브의 단면적을 원형에서 개시된 바의 각형으로 변경 및 확대하고, 각형의 매입거푸집에 의해 형성되는 확대된 개구부(OP)를 통하여, 지하외벽(111) 내 안팎으로 매립되는 수직철근(112,113)의 층간 연속 배근과 콘크리트 층간 연속 타설을 기존 원형의 슬리브 사용시에 비해 좀더 원활히 시행할 수 있도록 한 것에 지나지 않는다.That is, using the embedding die 121, the cross-sectional area of the existing sleeve is changed and enlarged into a square as disclosed in the circle, and through the enlarged opening OP formed by the rectangular embedding die, in the basement outer wall 111 Interlayer continuous reinforcement of the vertical reinforcing bars (112, 113) embedded in and out of the concrete interlayer continuous casting is only to enable more smoothly than when using a conventional circular sleeve.

이러한 구조는 지하외벽(111)의 콘크리트 연속 타설 및 콘크리트의 밀실 충전이 가능하다는 점에서 소기의 효과는 있다 할 수 있으나, 무엇보다 매입슬래브(S1)에 개구부(OP)라는 빈공간, 즉 종래에 비해 보다 확대된 상하 관통 통로가 형성됨으로 인하여, 매입슬래브(S1)의 구조 내력 측면에서는 매우 취약해지는 치명적인 단점이 있게 된다.Such a structure may have a desired effect in that concrete continuous pouring of the basement outer wall 111 and the filling of a closed room of the concrete may be performed, but above all, an empty space called an opening OP in the buried slab S1, namely, Due to the enlarged upper and lower through passages are formed, there is a fatal disadvantage that becomes very weak in terms of the structural strength of the buried slab (S1).

특히, 상기 매입거푸집(121)은 평판으로 제작되는 비구조재(개방형 판재 구조의 단순 거푸집)이며, 단순히 개구부(OP)를 성형하기 위한 거푸집에 지나지 않으므로 흙막이벽(100)으로부터 슬래브(S)로의 토압 전달, 토압 지지, 측압 지지, 축력 지지 등의 하중 지지 역할을 모두 수행하지 못한다. In particular, the embedding die 121 is a non-structural material (simple formwork of an open plate structure) made of a flat plate, and is merely a formwork for forming the opening OP, so the earth pressure from the retaining wall 100 to the slab (S). It does not perform all the load supporting roles such as transmission, earth pressure support, lateral pressure support and axial force support.

역타 시공시에는 층간 슬래브(S)가 구조적으로 흙막이벽(100)의 지지 역할을 수행한다는 관점에서 볼 때, 흙막이벽(100)과 접합된 매입슬래브(S1)에서 확대된 단면적의 개구부(OP)가 존재하는 경우 외벽(111) 시공 전 구조물의 안정성 측면에서 매우 취약해지는 치명적인 단점이 있다(매입슬래브에 구멍이 크게 뚫린 형태가 되므로 편토압 작용시 구조적으로 매우 취약하다). The opening OP of the cross-sectional area enlarged in the embedded slab S1 joined to the barrier wall 100 in view of the interlayer slab S structurally supporting the barrier wall 100 during the reverse construction. There is a fatal disadvantage that the outer wall 111 is very vulnerable in terms of stability of the structure before construction (because it becomes a form of a large hole in the buried slab structurally very weak during the action of the pneumatic pressure).

상기 특허에서 안팎의 수직철근(112,113) 배치를 원활히 하기 위해 나비형 개구부를 바람직한 형상의 예로 제시하고는 있으나, 개구부가 종래의 슬리브 단면적을 크게 확대한 단순 변형 이상의 효과(매입거푸집이 토압 등 하중에 저항하는 구조적인 효과)를 기대하기 어렵고, 매입거푸집이 구조적으로 어떠한 하중 지지 역 할을 하지 못하므로, 실제 시공 중 구조적인 안정성 측면의 치명적인 문제 발생 및 사고 발생 가능성이 지적되고 있다. Although the patent suggests a butterfly-shaped opening as an example of a preferred shape to facilitate the arrangement of the inner and outer vertical reinforcing bars 112 and 113, the opening is more than a simple deformation that greatly enlarges the conventional sleeve cross-sectional area (buy die to load such as earth pressure). It is difficult to expect a structural effect, and since the formwork does not play any load structurally, it is pointed out that fatal problems and accidents may occur in terms of structural stability during construction.

추가적으로, 도 4에서 알 수 있는 바와 같이, 매입거푸집(121)이 매입슬래브 영역에서 일정 간격으로 배치되고, 이때 각 매입거푸집의 크기는 안팎에서 2겹으로 배근되는 지하외벽(111)의 수직철근(112,113)을 동시에 관통시켜 배근할 수 있는 개구부(OP)의 크기를 성형할 수 있는 크기로 결정되어야 한다.In addition, as can be seen in Figure 4, buried dies 121 are disposed at a predetermined interval in the buried slab area, wherein the size of each buried die is a vertical reinforcing bar of the basement outer wall (111) that is arranged in two layers in and out ( The size of the opening OP that can penetrate through 112 and 113 at the same time should be determined as a size that can be molded.

안팎의 수직철근(112,113)을 모두 개구부(OP)에 통과시켜야 할 경우, 실제 시공시 매입거푸집(121)은 외벽(111)의 폭방향(두께방향) 및 매입슬래브(S1)의 폭방향으로 거의 전체 구간에 걸쳐 설치되어야 하며, 이에 개구부(OP)의 길이는 도 5에 나타낸 바와 같이 외벽의 폭방향으로 길어질 수밖에 없다. When both the inner and outer vertical reinforcing bars 112 and 113 have to pass through the opening OP, the embedding die 121 is substantially in the width direction (thickness direction) of the outer wall 111 and the width direction of the embedding slab S1 during actual construction. It must be installed over the entire section, and thus the length of the opening OP can be long in the width direction of the outer wall, as shown in FIG. 5.

이러한 구조에서 개구부(OP)와 개구부 사이에서는 토압이 크게 작용함에 따라 상당한 구조 보강이 있어야 한다. In such a structure, there must be considerable structural reinforcement as the earth pressure acts largely between the opening OP and the opening.

즉, 실제 시공시에, 좌우 양쪽으로 상당한 길이의 빈공간이 존재하는 상황에서, 개구부(OP)와 개구부 사이의 구간에서는 구조적인 취약함을 보완하기 위해 후프(hoop) 배근(114) 등 기둥 시공시의 배근 수준 및 배근 형태에 준하는 상당량의 철근 보강이 이루어져야 한다.That is, in actual construction, in a situation where a considerable length of left and right spaces exist in the construction, the pillar construction such as the hoop back 114 to compensate for the structural weakness in the section between the opening OP and the opening A significant amount of rebar reinforcement should be made in accordance with the city's reinforcement levels and reinforcement shapes.

비구조재인 개방형 판재 구조의 단순 거푸집을 사용하여, 외벽의 대략 폭방향 전체 구간에 걸쳐 개구부를 형성하기 때문에, 개구부와 개구부 사이 구간에서 좌굴에 불리해지고(개구부 사이 구간의 좌굴 길이가 길어 취약), 축하중 내력이 저하되어 기둥 보강을 요하는 것이다.By using the simple formwork of the open plate structure, which is a non-structural material, an opening is formed over the entire widthwise section of the outer wall, which is disadvantageous to buckling in the section between the opening and the opening (the buckling length of the section between the openings is fragile), During the celebration, the strength is reduced and the column needs to be reinforced.

특히, 개구부 사이의 구간이 편토압 작용시 장주 기둥 거동을 함에 따라 구조적으로 매우 취약한 구조가 되고, 시공 중 전단 균열 발생 등의 문제가 있는 바, 안전성에서 많은 문제를 노출하고 있다.In particular, as the sections between the openings act as pole pillars during the action of the earth pressure, the structure becomes very fragile, and there are problems such as shear cracking during construction, thereby exposing many problems in safety.

이를 도면을 참조하여 좀더 상세히 설명하기로 한다.This will be described in more detail with reference to the drawings.

첨부한 도 6과 도 7은 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 6은 평면도이고, 도 7은 도 6의 선 'B-B'를 따라 취한 단면도이다. 6 and 7 are views for explaining the problem according to the prior art, Figure 6 is a plan view, Figure 7 is a cross-sectional view taken along the line 'B-B' of FIG.

도 6은 슬래브 폐합 후 상태, 즉 (I) 영역과 (Ⅱ) 영역의 슬래브(S) 시공이 모두 완료된 상태를, 도 7은 슬래브 폐합 전 상태, 즉 (I) 영역에 대해서만 슬래브 시공이 이루어진 상태를 나타낸 것이다.FIG. 6 shows a state after slab closing, that is, a state in which both the slab (S) constructions of the regions (I) and (II) are completed, and FIG. 7 shows a state before the slab closing, that is, the slab construction is performed only for the region (I). It is shown.

도 6에 도시한 바와 같이, 사각 면적의 지하구조물을 시공한다고 할 때, 주지된 바와 같이 각 층에서 실제 슬래브 콘크리트 시공은 (I) 영역과 (Ⅱ) 영역이 나누어져 순차 시공되는 것이 통상적이다.As shown in FIG. 6, when constructing a square structure underground structure, as is well known, actual slab concrete construction in each layer is generally performed by sequentially dividing (I) and (II) regions.

즉, 슬래브(S) 시공시에 (I) 영역에서 콘크리트를 선타설한 뒤 동층의 (Ⅱ) 영역에서 슬래브 거푸집 구조체(141)를 설치하고, 이어 (I) 영역에서 선 시공된 슬래브 하측의 굴토작업이 실시된 다음, (Ⅱ) 영역에서 슬래브 콘크리트를 후 타설하는 것이다(슬래브 폐합).That is, when the slab (S) is constructed, concrete is cast in the area (I), and then the slab formwork structure 141 is installed in the area (II) of the same layer. After the work is carried out, the slab concrete is post-cast in the area (II) (slab closure).

이는 각 층의 슬래브 시공시 실제 적용되는 통상의 작업 순서로서, 굴토작업을 (Ⅱ) 영역의 슬래브 콘크리트 시공보다 앞서 실시함으로써 공기 단축이 가능해진다.This is a general work order that is actually applied in the construction of slabs of each layer, and the air shortening can be performed by performing the excavation work before the construction of the slab concrete in the area (II).

그러나, (Ⅱ) 영역의 슬래브 콘크리트가 타설되고 나면 구조적 문제는 발생 하지 않지만, 도 6과 및 도 7에서와 같이 슬래브 폐합 전, 즉 (Ⅱ) 영역의 슬래브 콘크리트가 타설되기 전까지는 (I) 영역의 선 시공된 슬래브가 토압을 전적으로 지지해야 한다. However, structural problems do not occur after slab concrete is poured in the area (II), but before slab closing, that is, until the slab concrete in the area (II) is poured, as shown in FIGS. 6 and 7, The pre-installed slab must support the earth pressure completely.

결국, (Ⅱ) 영역의 슬래브 콘크리트가 타설되기 전, 특히 (I) 영역의 굴토작업시에 편토압이 크게 발생하게 되고, 이로 인해 개구부(OP)와 개구부 사이 구간에서 전단 균열이 발생할 수 있다. As a result, before the slab concrete in the region (II) is poured, in particular during the excavation work in the region (I), the excavation pressure is greatly generated, which may cause shear cracking in the section between the opening OP and the opening.

도 4 및 도 5에서와 같이 개방형 판재 구조의 단순 거푸집(121)을 사용하고 매입슬래브(S1)에서 외벽 폭방향으로 개구부(OP)의 길이가 길어지게 되면(각 개구부가 외벽 폭의 대부분을 개방), 슬래브 폐합이 안된 상태에서 슬래브 선타설 영역((I) 영역))의 추가 굴토작업시 상당한 크기의 편토압에 의해 전단 균열 발생시 붕괴의 위험이 매우 커지게 된다.4 and 5, when the simple formwork 121 of the open plate structure is used and the length of the opening OP becomes longer in the width direction of the outer wall in the embedded slab S1 (each opening opens most of the outer wall width). ), The additional risk of collapse during shear cracking is due to the large amount of excavation pressure during the additional excavation of the slab precasting region ((I) region) without the slab closing.

따라서, 본 발명은 이와 같은 점을 감안하여 안출한 것으로서, 기존 동바리의 사용이 불필요함은 물론 테두리보가 삭제될 수 있으며, 특히 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있으면서도 매입슬래브를 포함한 슬래브 전체의 강성을 극대화할 수 있는 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 슬래브 및 합벽 시공용 받침브라켓을 제공하는데 그 목적이 있다.Therefore, the present invention has been devised in view of the above points, and the use of the existing clubs is not necessary, as well as the rim beam can be eliminated. The purpose is to provide slab and plywood structures and construction methods of underground structures that can maximize the stiffness of the entire slab including embedded slabs, and to support the brackets for the slab and plywood construction.

또한, 본 발명은 외벽에 의해 매립되는 슬래브 부분인 매입슬래브의 내부에 영구구조물로서 매입되는 매입형 RC보 철근틀을 마련하여 양생 후 매입형 RC보 철근틀이 데크슬래브를 지지할 수 있도록 함으로써, 데크슬래브→매입형 RC보 철근틀→받침 브라켓→엄지말뚝(H-파일)으로 이어지는 수직방향 하중 전달체계를 확보할 수 있고, 또 횡토압→합벽→매입형 RC보 철근틀을 포함하는 매입 슬래브→테크 슬래브로 이어지는 수평방향 하중 전달체계를 확보할 수 있는 등 하중전달을 원활하게 할 수 있는 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 슬래브 및 합벽 시공용 받침브라켓을 제공하는데 다른 목적이 있다.In addition, the present invention by providing an embedded RC beam reinforcement frame to be embedded as a permanent structure in the interior of the embedded slab which is part of the slab buried by the outer wall to enable the embedded RC beam reinforcement frame to support the deck slab after curing, Deck slab → embedded RC beam rebar frame → Secure vertical load transfer system from supporting bracket to thumb pile (H-pile); transverse pressure → plywood → embedded slab including embedded RC beam rebar frame → There are other objectives to provide slab and plywood structures and construction methods for underground structures that can facilitate load transfer, such as securing horizontal load transfer system leading to tech slabs, and supporting brackets for slab and ply wall construction. .

상기 목적을 달성하기 위하여 본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 시공 방법은 각 층의 슬래브 시공시 매입슬래브의 거푸집 역할 및 하기 스틸 웨일 구조체의 지지 역할을 수행하는 받침브라켓을 흙막이벽에 설치하는 단계와, 매입슬래브의 개구부 형성을 위한 거푸집 역할과 동시에 흙막이벽으로부터 전달되는 하중 지지, 분산 및 전달 역할을 수행하는 스틸 웨일 구조체를 상기 받침브라켓 위 매입슬래브 영역을 따라 이격 배치하는 단계와, 수평철근과 외곽철근을 포함하는 형태로 이루어져 하중의 원활한 전달을 위한 역할을 수행하는 매입형 RC보 철근틀을 상기 받침브라켓 위 매입슬래브 영역을 따라 배근하는 단계와, 상기 받침브라켓에 연결되도록 슬래브 구축용 거푸집 구조체를 설치한 뒤에 상기 스틸 웨일 구조체의 내부공간을 제외한 전 슬래브 영역에 콘크리트를 타설하여 슬래브를 시공하는 단계와, 전 층의 슬래브 시공이 완료되면 상기 스틸 웨일 구조체의 내부공간에 의해 형성된 개구부를 지하외벽의 수직철근 층간 배근 및 지하외벽의 콘크리트 타설을 위한 통로로 사용하여 지하합벽을 층간 연속적으로 순타 시공하는 단계로 이루어진 것을 특징으로 한다. The slab and plywood construction method of the underground structure provided by the present invention in order to achieve the above object is to install a support bracket to form the formwork of the embedded slab and the supporting role of the following steel wale structure in the slab construction when the slab construction of each layer And disposing a steel wale structure spaced apart along the buried slab area on the support bracket to serve as a formwork for forming an opening of the buried slab, and at the same time serving as a load supporting, distributing, and transferring material from the retaining wall; And reinforcing the embedded RC beam reinforcing frame along the buried slab area on the support bracket, which is formed in a shape including the external reinforcement and serves to smoothly transfer the load, and forms a slab to be connected to the support bracket. After installing the structure, the inner space of the steel wale structure Constructing the slab by placing concrete in the entire slab area except the slab construction, and when the slab construction of the entire layer is completed, the opening formed by the inner space of the steel wale structure is divided into the vertical reinforcing bars of the basement wall and the concrete casting of the basement outer wall. It is characterized by consisting of a step for the continuous construction of the subterranean plywood wall using the passageway for.

또한, 상기 목적을 달성하기 위하여 본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 구조물은 매입슬래브의 거푸집 역할 및 스틸 웨일 구조체의 지지 역할을 수행하기 위하여 흙막이벽에 설치되는 받침브라켓과, 상기 받침브라켓 위 매입슬래브 영역을 따라 배치되는 장선철근 및 이 장선철근 위에 설치되는 철망형 거푸집과, 매입슬래브 영역과 이어지는 슬래브 영역을 구축하기 위한 슬래브 구축용 거푸집 구조체와, 매입슬래브의 개구부 형성을 위한 거푸집 역할과 동시에 흙막이벽으로부터 전달되는 하중 지지, 분산 및 전달 역할을 수행하며 상기 받침브라켓 위 매입슬래브 영역을 따라 이격 배치되는 스틸 웨일 구조체와, 수평철근과 외곽철근을 포함하는 형태로 이루어져 하중의 원활한 전달을 위한 역할을 수행하며 상기 받침브라켓 위 매입슬래브 영역을 따라 배근되는 매입형 RC보 철근틀을 포함하며, 상기 스틸 웨일 구조체의 내부공간을 제외한 전 슬래브 영역에 콘크리트가 타설되어 슬래브 시공이 완료되고, 상기 스틸 웨일 구조체의 내부공간에 의해 형성된 개구부가 지하외벽용 수직철근 층간 배근 및 콘크리트 타설을 위한 통로로 사용되어 지하외벽 시공이 완료되어, 지하합벽과 슬래브가 구축된 구조로 이루어진 것을 특징으로 한다. In addition, the slab and plywood structure of the underground structure provided by the present invention in order to achieve the above object is a support bracket which is installed on the earth wall to serve as the formwork of the embedded slab and the supporting role of the steel wale structure, and on the support bracket Jang reinforcing bars arranged along the buried slab area, wire mesh formwork installed on the reinforcing bar slab, slab construction formwork for constructing the slab area connected with the buried slab area, and the formwork for forming the opening of the buried slab. It serves to support the load, distribute and transfer the load from the retaining wall, and is composed of a steel wale structure spaced apart along the buried slab area on the support bracket, and a horizontal reinforcement and an outer reinforcement. Perform the purchase on the support bracket An embedded RC beam reinforcement frame is disposed along the slab area, and concrete is poured into the entire slab area except the inner space of the steel wale structure to complete the slab construction, and the opening formed by the inner space of the steel wale structure. It is used as a passage for vertical reinforcing bar reinforcement and concrete placing for the basement outer wall.

그리고, 상기 목적을 달성하기 위하여 본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 시공용 받침브라켓은 지하구조물의 슬래브 및 합벽 시공시 사용되는 것으로서, 매입슬래브의 거푸집 역할 및 스틸 웨일 구조체의 지지 역할을 수행하며, 흙막이벽에 설치되는 받침브라켓 본체와, 이 받침브라켓 본체의 선단부분에 착탈가능하게 결합되는 보조브라켓으로 구성되어, 슬래브 양생 후 지하외벽 타설 전에 보조브라켓을 받침브라켓 본체로부터 떼어낼 수 있는 구조로 이루어진 것을 특징으로 한다. In addition, the slab and plywood construction support bracket of the underground structure provided by the present invention in order to achieve the above object is used in the construction of the slab and plywood construction of the underground structure, and performs the role of formwork of the embedded slab and the support role of the steel wale structure. It consists of a supporting bracket body installed on the earthen wall, and an auxiliary bracket detachably coupled to the front end of the supporting bracket body, so that the auxiliary bracket can be detached from the supporting bracket body before slaying the slab after curing the slab. Characterized in that consisting of.

본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 슬래브 및 합벽 시공용 받침브라켓은 다음과 같은 장점이 있다. The slab and plywood structure and construction method of the underground structure provided by the present invention, and the support bracket for the slab and plywood construction has the following advantages.

첫째, 기존 테두리보가 삭제되면서 테두리보 설치에 따른 문제점이 해소될 수 있으며, 특히 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있으면서도 상기 스틸 웨일 구조체가 하중을 지지하게 되면서 매입슬래브를 포함한 슬래브의 강성이 극대화될 수 있다. First, as the existing edge beams are deleted, the problems caused by the edge beam installation can be solved. In particular, the steel wale structure is loaded while the continuous reinforcement of the vertical reinforcement between floors and the interlayer continuous casting of concrete can be smoothly carried out using an opening. By supporting the stiffness of the slab including the embedded slab can be maximized.

둘째, 스틸 웨일 구조체의 경우 개구부를 형성하기 위한 성형틀(거푸집) 역할을 하면서도 매입슬래브 내 개구부 주변의 하중 지지 및 분산 지지를 위한 구조체 역할을 동시에 수행하게 되며, 이에 흙막이벽의 역타 지지구조인 슬래브의 강성이 극대화될 수 있다. Secondly, in the case of the steel wale structure, while serving as a forming mold (form) for forming the openings, the steel wale structure simultaneously serves as a structure for supporting loads and distributed support around the openings in the embedded slab, and thus a slab which is a reverse support structure of the retaining wall. The rigidity of can be maximized.

셋째, 스틸 웨일 구조체의 경우 간단한 구조를 가지면서 소형, 경량으로 제작될 수 있고, 옹벽 두께에 따라 웨일 스틸 구조체 크기가 변하지 않고 일정함에 따라 공장에서 가공하여 용접 조립하는 방식으로 모듈화하여 하나의 단품으로 대량 생산할 수 있다.Third, the steel wale structure can be manufactured in a small size and light weight while having a simple structure. As the size of the wale steel structure does not change according to the retaining wall thickness, the steel wale structure is modularized by processing in the factory and welding assembly. Can mass produce.

따라서, 구조가 복잡하고 철재 물량이 많이 소요되는 종래의 그레이팅 지지틀을 사용할 때보다 비용 측면에서 매우 유리해지며, 작업성 향상, 작업시간 단축, 인건비 절감 등의 많은 장점이 있다. Therefore, it is very advantageous in terms of cost than when using a conventional grating support frame, which is complicated in structure and takes a lot of steel, and has many advantages such as improved workability, reduced work time, and reduced labor costs.

특히, 상기 스틸 웨일 구조체는 종래의 그레이팅 지지틀에 비해 제작시 철재 사용량이 적고, 제작원가가 상대적으로 낮으며, 그레이팅 지지틀과 달리 연속되게 설치하지 않고 서로 간격을 두어 설치하므로 현장에서 사용 개수 또한 적기 때문에 전체적인 공사 비용의 절감이 가능하다.In particular, the steel wale structure is less steel used in the production compared to the conventional grating support frame, manufacturing cost is relatively low, unlike the grating support frame is installed at intervals apart from each other without continuous installation, so the number of use in the field Because of this, the overall construction cost can be reduced.

넷째, 상기 스틸 웨일 구조체는 건축물의 모서리 부분 사용 제약 등과 같은 시공 위치의 제약이 없고, 이와 관련한 종래의 제반 문제점들을 해결할 수 있다. Fourth, the steel wale structure is not limited in the construction position, such as constraints on the use of the corner portion of the building, it can solve all the conventional problems associated with this.

다섯째, 지하 외벽에 의해 매립되는 매입슬래브 내에 영구구조물인 매입형 RC보 철근틀을 설치하여, 양생 후 매입형 RC보 철근틀이 데크슬래브를 지지할 수 있도록 함으로써, 수직방향 하중 전달체계(데크슬래브→매입형 RC보 철근틀→받침 브라켓→엄지말뚝)와 수평방향 하중 전달체계(횡토압→합벽→매입형 RC보 철근틀을 포함하는 매입 슬래브→테크 슬래브)을 구축할 수 있으며, 따라서 구조물에 대한 원활한 하중 전달 시스템을 통해 구조적 안전성을 향상시킬 수 있다. Fifth, by installing embedded RC beam reinforcement frame, which is a permanent structure, in the embedded slab buried by the outer wall of the basement, and allowing the embedded RC beam reinforcement frame to support the deck slab, the vertical load transfer system (deck slab) → embedded RC beam reinforcing frame → support bracket → thumb pile) and horizontal load transfer system (lateral soil pressure → plywood → embedded slab → tech slab including embedded RC beam reinforcement frame). Seamless load transfer systems can improve structural safety.

이하, 첨부한 도면을 참조하여 본 발명의 바람직한 실시예에 대해 더욱 상세히 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 시공 방법은 지하구조물의 각 층 슬래브를 시공한 뒤 흙막이벽에 접하는 지하외벽을 구축하여 합벽으로 시공하는 과정에서, 상기 지하외벽 내에 매립되는 슬래브 부분, 즉 매입슬래브 영역에 상하로 관통하는 개구부를 형성하기 위한 거푸집 역할을 하면서 하중 지지를 위한 영구 구조체의 역할을 동시에 수행할 수 있는 스틸 웨일(wale) 구조체를 설치하여 슬래브를 시공하고, 전 층의 슬래브를 시공한 상태에서 상기 스틸 웨일 구조체에 의해 형성된 개구부를 지하외벽의 수직철근 층간 배근과 콘크리트 타설용 통로로 사용하여 합벽을 층간 연속적으로 시공하는 방법이다. In the slab and plywood construction method of the underground structure provided by the present invention, after constructing each layer slab of the underground structure and constructing the basement outer wall contacting the earth wall, the construction of the slab portion, that is, the slab portion embedded in the basement outer wall The slab is constructed by installing a steel wale structure that can serve as a formwork for forming openings penetrating up and down in the buried slab area, and can simultaneously serve as a permanent structure for supporting loads. In the construction state, the opening formed by the steel wale structure is used as a vertical reinforcing layer reinforcement of the basement outer wall and concrete casting passageway to continuously install the plywood wall.

이러한 본 발명에서는 기존 테두리보가 삭제되면서 테두리보 설치에 따른 문제점이 해소될 수 있고, 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있음은 물론, 상기 스틸 웨일 구조체가 매입슬래브 내에서 흙막이벽으로부터 슬래브로의 토압 전달, 토압 지지, 측압 지지, 축력 지지 등의 하중 지지 역할을 수행하고, 또 매입슬래브 내에 마련되는 매입형 RC에 의해 수직방향 및 수직방향의 원활한 하중 전달을 유도함으로써, 매입슬래브를 포함한 슬래브 전체의 강성을 극대화시킬 수 있다. In the present invention, as the existing edge beams are deleted, the problems caused by the edge beam installation can be solved, and the continuous reinforcement of the vertical reinforcement interlayers of the basement outer walls and the interlayer continuous casting of concrete can be smoothly performed using the openings, as well as the steel. Whale structure performs load supporting role such as earth pressure transfer, earth pressure support, lateral pressure support, axial force support, etc. from the retaining wall to the slab in the embedded slab, and the vertical and vertical directions are made by the embedded RC provided in the embedded slab. By inducing smooth load transfer, the stiffness of the entire slab including the embedded slab can be maximized.

이러한 본 발명의 시공 방법을 첨부한 도면을 참조하여 좀더 구체적으로 살펴보면 다음과 같다. The construction method of the present invention will be described in more detail with reference to the accompanying drawings.

첨부한 도 8은 본 발명에 따른 시공 과정의 공정도이고, 도 9는 본 발명에 따른 매입슬래브(S1) 영역에서 스틸 웨일 구조체(130), 메입형 RC보(150)가 설치된 상태를 보여주는 사시도이고, 도 10은 흙막이벽(100)의 H-파일(101)에 받침브라켓(122)을 설치한 뒤 받침브라켓 위에 장선철근(123), 철망형 거푸집(124), 스틸 웨일 구조체(130), 메입형 RC보(150), 받침각관(125)을 설치한 상태를 도시한 평면도이다. 8 is a process diagram of the construction process according to the present invention, Figure 9 is a perspective view showing a state in which the steel wale structure 130, the embedded RC beam 150 is installed in the buried slab (S1) region according to the present invention , FIG. 10 shows that the support bracket 122 is installed on the H-pile 101 of the retaining wall 100, and the reinforcing bar 123, the wire mesh formwork 124, the steel wale structure 130, and the mes on the support bracket. It is a top view which shows the state which installed the standing RC beam 150 and the support angle tube 125.

그리고, 첨부한 도 11은 단면도로서, 흙막이벽(100)의 H-파일(101)이 설치된 위치에서 취한 단면도이며, 슬래브(S)의 시공이 완료된 상태를 도시한 것이다.11 is a sectional view taken in a position where the H-pile 101 of the earthen wall 100 is installed, showing a state in which the construction of the slab S is completed.

여기서, 도면부호 111은 콘크리트가 타설된 상태에서 외벽을 나타낸다.Here, reference numeral 111 denotes an outer wall in the state where concrete is poured.

또한, 첨부한 도 12는 본 발명에 따른 시공 과정에서 슬래브(S) 시공 후 합벽 시공 과정에서 수직철근(112,113)의 배근상태를 도시한 도면이고, 도 13은 도 12에서 'C' 방향에서 본 수직철근(112,113)의 배근상태를 나타낸 도면이다.In addition, Figure 12 is a view showing the reinforcement state of the vertical reinforcing bars (112, 113) in the plywood construction process after the slab (S) construction in the construction process according to the present invention, Figure 13 is viewed from the 'C' direction in FIG. Figure showing the reinforcement state of the vertical reinforcing bars (112, 113).

여기서, 도면부호 100은 흙막이벽을 나타내며, 본 발명은 흙막이벽으로서 H-파일(101)이 사용되는 CIP나 SCW에 모두 적용될 수 있는 것이므로, 이하 본 명세서에서는 이들을 따로 구분하지 않고 "흙막이벽"으로 통칭하기로 한다.Here, the reference numeral 100 denotes a barrier wall, and the present invention is applicable to both the CIP or SCW in which the H-pile 101 is used as the barrier wall. Hereinafter, in the present specification, these are referred to as "soil walls" without being separated. Collectively.

첨부한 도 8을 참조하여 전체 시공 과정에 대해 개략적으로 설명하면 다음과 같다. Referring to FIG. 8, the overall construction process is briefly described as follows.

시공되는 건물의 경계선을 따라 흙막이벽을 시공하고, 그 안쪽 지중에 골조용 기둥(미도시)을 시공한 뒤(S110), 1차로 소정 깊이의 터파기를 진행하여 흙막이벽과 골조용 기둥의 상부 일부가 노출되도록 한다(S120).Construct the retaining wall along the boundary of the building to be constructed, construct the framed pillar (not shown) in the inner ground (S110), and then proceed with the dig of the predetermined depth by the first part of the upper part of the retaining wall and the framed pillar. To be exposed (S120).

이어 1층 바닥 슬래브를 시공하고(S130), 1층 바닥 슬래브의 시공이 모두 완료되면 2차 굴토(S140) 후에 그 하층의 슬래브를 동일하게 작업하여 시공한다(S150). Subsequently, the construction of the first floor slab (S130), and when the construction of the first floor slab is completed, the secondary slab (S140) after the slab of the lower floor to work the same (S150).

이후 계속해서 하층으로 내려가면서 단계적으로 상기와 같은 굴토 및 슬래브 시공 작업을 반복하여 전 층의 슬래브를 모두 시공하고(S160), 모든 지하층의 슬래브 시공 작업이 완료된 뒤에는 맨 아래층부터 위층으로 올라가면서 흙막이벽 안쪽에 지하외벽을 순타 시공하여 지하합벽(옹벽)을 완성하게 된다(S170).After continuing to go down to the lower floors by repeating the construction of the above-mentioned pit and slab step by step construction all the slabs of all floors (S160), after the completion of the slab construction work of all basement floors, the bottom wall from the bottom floor going up to the top floor The basement outer wall is smoothly constructed inside to complete the basement wall (retaining wall) (S170).

이러한 합벽 순타 시공시에는 콘크리트의 밀실 충전이 가능하고, 순타조인트의 경우 콘크리트의 밀실 충전으로 역타조인트에 비해 틈새 발생이 최소화될 수 있다. When the plywood nets are constructed, it is possible to fill the closed room of the concrete, and in the case of the netta joint, the gap can be minimized compared to the reverse oscillating joint by filling the closed room of the concrete.

물론, 각 층의 슬래브 시공시에 도 6 및 도 7에 나타낸 바와 같이 동층의 전체 슬래브 면적을 분할하여, 분할된 영역에 따라 동층의 슬래브를 순차 시공하는 것이 가능하며, 이때 선 시공된 슬래브 영역의 하측 굴토작업을 슬래브 폐합, 즉 동층 다른 영역의 슬래브 시공 전에 우선 실시할 수 있다.Of course, it is possible to divide the entire slab area of the copper layer and sequentially construct the slab of the copper layer according to the divided area, as shown in Figs. 6 and 7 at the time of slab construction of each layer. Lower excavation may be carried out prior to slab consolidation, ie slab construction in other areas of the same layer.

위와 같이 각 층 시공에 있어서, 층간 수평구조체인 슬래브(S)가 흙막이벽(100)을 직접 지지하도록 슬래브를 선 시공한 뒤 이어 굴토하고, 이러한 과정을 지하 최하층까지 반복적으로 수행한 다음, 흙막이벽(100)과 일체로 지하외벽(111)을 구축하여 흙막이벽(100)과 지하외벽(111)으로 이루어진 지하합벽을 시공하게 된다(도 11 참조).In the construction of each floor as above, the slab (S), which is a horizontal interlayer structure, the slab is pre-constructed after the construction so as to directly support the earth wall 100, and this process is repeatedly carried out to the basement floor, and then the earth wall The basement outer wall 111 is integrally formed with the 100 to construct an underground sump wall consisting of the earth barrier wall 100 and the basement outer wall 111 (see FIG. 11).

여기서, 각 층 슬래브(S)를 시공할 때, 지하외벽(111)에 매립되는 슬래브 부분(이하, '매입슬래브'라 함)(S1)에는 도 9 내지 도 11에 나타낸 바와 같이 스틸 웨일 구조체(130)와 매입형 RC보 철근틀(150)을 설치한 뒤 시공하게 된다.Here, when constructing each layer slab (S), the slab portion (hereinafter referred to as "buried slab") (S1) buried in the basement outer wall 111, as shown in Figure 9 to Figure 11 to the steel wale structure ( 130) and after installing the embedded RC beam reinforcement frame 150 will be installed.

이때, 스틸 웨일 구조체(130)는 기본적으로 매입슬래브(S1)의 개구부(OP)를 성형하기 위한 거푸집 역할을 하게 된다.At this time, the steel wale structure 130 basically serves as a form for forming the opening (OP) of the buried slab (S1).

매입슬래브(S1)에서 상기 스틸 웨일 구조체(130)에 의해 성형된 각 층 슬래브(S)의 개구부(OP)는 지하외벽 수직철근(113)의 층간 연속 배근과 지하외벽(111) 콘크리트의 층간 연속 타설을 위한 상하 관통 통로가 된다. The opening OP of each layer slab S formed by the steel wale structure 130 in the buried slab S1 is the interlayer continuous reinforcement of the basement outer wall vertical reinforcement 113 and the interlayer continuous of the basement outer wall 111 concrete. It is a top and bottom passage for pouring.

즉, 상기 개구부(OP)를 통해 지하외벽(111)의 연속적인 순타 시공이 가능해지는 것이다.That is, the continuous smooth construction of the basement outer wall 111 is possible through the opening OP.

또한, 본 발명에서 스틸 웨일 구조체(130)는 현장 시공 후 매입슬래브(S1) 내에 매립되는 영구 구조체로서, 개구부(OP)를 성형하기 위한 거푸집 역할과 함께, 슬래브(S)의 시공 후 매입슬래브(S1) 내부에서 흙막이벽(100)으로부터 전달되는 토압 지지, 측압 지지, 축력 지지, 슬래브로의 토압 전달 등 하중 지지 구조체의 역할을 동시에 수행한다. In addition, in the present invention, the steel wale structure 130 is a permanent structure that is embedded in the embedded slab S1 after field construction, and serves as a formwork for forming the opening OP, and the embedded slab after construction of the slab S ( S1) simultaneously serves as a load supporting structure such as earth pressure support, side pressure support, axial force support, and earth pressure transfer to the slab transmitted from the retaining wall 100.

즉, 상기 스틸 웨일 구조체(130)는 단순 거푸집 역할은 물론이고, 하중 지지 구조체의 역할을 수행할 수 있도록 구조 및 자체 강성을 보완하여 제작 및 설치된 다.That is, the steel wale structure 130 is manufactured and installed to complement the structure and its rigidity so as to serve as a simple formwork, as well as the load supporting structure.

상기 스틸 웨일 구조체는 공장 제작되어 현장에 제공되는 것으로, 각 층의 슬래브 시공시에 공장 제작된 스틸 웨일 구조체를 현장의 소정 위치에 설치한 뒤 이후의 시공 작업을 진행하게 된다. The steel wale structure is to be manufactured in the factory and provided to the site, and the installation of the steel wale structure produced at the time of the slab construction of each layer at a predetermined position of the site and then proceed with the subsequent construction work.

상기 스틸 웨일 구조체는 후술하는 바와 같이 스틸 평판 또는 앵글부재(L-형강), 채널부재(ㄷ-형강) 등을 사용하여 제작되는데, 이들을 혼용하여 제작될 수도 있으며, 전체적으로 사각형의 틀 구조로 제작될 수 있다.The steel wale structure is manufactured by using a steel plate or angle member (L-shaped steel), a channel member (c-shaped steel), etc., as will be described later, and may be produced by mixing them, or a rectangular frame structure as a whole. Can be.

이때, 슬래브 시공 후, 특히 합벽 시공 전에 흙막이벽으로부터 콘크리트를 통해 가해지는 하중에 충분히 견딜 수 있는 강성을 가지도록 구조적으로 설계되어 제작된다.At this time, after the slab construction, especially before the construction of the plywood is structurally designed and manufactured so as to have a rigid enough to withstand the load applied through the concrete from the earth wall.

종래의 그레이팅 지지틀의 경우 대형이면서 연속적으로 설치돼야 하기 때문에 제작시 철재 물량이 과다해지고 따라서 사용시 비용이 커지는 단점, 및 건축물의 모서리 부분 사용시 제약이 발생하는 단점이 있는 것을 고려하여, 본 발명의 스틸 웨일 구조체는, 상대적으로 소형이면서도 그 자체가 토압 하중을 충분이 지지할 수 있는 강성을 가지도록 제작되는 것과 함께, 현장 설치시 매입슬래브 영역을 따라 연속적으로 설치되는 것이 아닌 소정 간격을 두고 이격 설치된다.In the case of the conventional grating support frame, the steel of the present invention in consideration of the disadvantage that the steel volume is excessive during manufacturing, and thus the cost is increased when using it, and that the limitation occurs when using the corner portion of the building. The wale structure is relatively small and in itself manufactured to be rigid enough to support the earth pressure load, and is spaced apart at predetermined intervals rather than being continuously installed along the buried slab area during field installation. .

즉, 스틸 웨일 구조체(130)가 매입슬래브(S1) 영역을 따라 연속 배치되는 것이 아닌 소정 간격으로 이격 배치되어 매입슬래브 전체 구간에 대해 부분적으로만 설치되는 것이다.That is, the steel wale structure 130 is not disposed continuously along the buried slab S1 area, but is spaced at a predetermined interval so that only part of the steel wale structure 130 is provided for the entire buried slab section.

특히, 상기 스틸 웨일 구조체(130)의 폭, 슬래브쪽으로 연장되는 방향으로의 폭은 지하외벽의 두께에 상응하는 폭으로 이루어지는 매입슬래브(S1)의 폭에 비해 상대적으로 매우 적은 폭을 갖게 된다. In particular, the width of the steel wale structure 130, the width in the direction extending toward the slab has a relatively small width compared to the width of the buried slab (S1) made of a width corresponding to the thickness of the basement outer wall.

이는 매입슬래브(S1)의 내부에 매입형 RC보 철근틀(150)의 설치를 위한 자리를 확보 및 적정크기로 하여 편토압 저항에 유리하게 하기 위함이다. This is to secure the seat for the installation of the embedded RC beam reinforcement frame 150 in the interior of the embedded slab (S1) and to have an appropriate size to favor the earth pressure resistance.

이에 따라, 기존 매입거푸집의 경우와 같이 2열의 수직철근을 관통시키기 위하여 지하외벽의 폭과 거의 근접한, 다시 말해 매입슬래브(S1)의 폭과 거의 근접한 폭을 갖는 것과는 달리, 상기 스틸 웨일 구조체(130)는 매입 슬래브(S1)의 폭에 비해 상대적으로 작은 폭을 갖게 되고, 이로 인해 확보되는 매입슬래브(S1) 내의 영역에 매입형 RC보 철근틀(150)을 설치할 수 있다. Accordingly, unlike the case of the existing formwork, the steel wale structure 130, unlike having a width almost close to the width of the basement outer wall, that is, almost close to the width of the buried slab S1 in order to penetrate two rows of vertical rebars. ) Has a relatively small width compared to the width of the embedded slab (S1), it is possible to install the embedded RC beam reinforcement frame 150 in the area within the embedded slab (S1) secured thereby.

이때, 지하외벽의 골조용으로 사용되는 2개의 수직철근, 즉 인장철근의 역할을 하는 바깥쪽 수직철근(113)은 스틸 웨일 구조체(130)의 공간을 통해 관통 배근되고, 압축철근의 역할을 하는 안쪽 수직철근(112)은 매입슬래브(S1) 내의 매입형 RC보 철근틀(150)을 관통하여 설치되어 있는 다월 철근(115)을 이용하여 연결 배근된다. At this time, the two vertical reinforcing bars used for framing the basement outer wall, that is, the outer vertical reinforcing bars 113 serving as the tensile reinforcing bars are penetrated through the space of the steel wale structure 130 and serve as compressed reinforcing bars. The inner vertical reinforcement 112 is connected and reinforced using a dowel reinforcement 115 installed through the embedded RC beam reinforcing frame 150 in the buried slab S1.

여기서, 상기 매입형 RC보 철근틀(150)은 슬래브 부분의 전반적인 구조적 강성을 강화하기 위한 용도로 사용되며, 토압이 작용하는 쪽 및 슬래브쪽으로의 하중 전달을 원활히 해줄 수 있다. Here, the embedded RC beam reinforcement frame 150 is used to reinforce the overall structural rigidity of the slab portion, it can facilitate the load transfer to the side and the slab to which the earth pressure acts.

이러한 매입형 RC보 철근틀(150)은 매입슬래브(S1) 내의 확보된 영역(스틸 웨일 구조체의 폭 감소로 인해 확보된 영역)에서 길이방향을 따라, 즉 지하외벽을 따라 나란하게 연장되는 형태로 배치되는 다수의 수평철근(151)과 이 수평철근(151)의 둘레를 적정간격으로 군데군데 묶어주는 외곽철근(152)으로 이루어진다. The embedded RC beam reinforcement frame 150 extends along the longitudinal direction, that is, along the basement outer wall in the secured area in the embedded slab S1 (area secured due to the reduced width of the steel wale structure). It consists of a plurality of horizontal reinforcing bars 151 disposed and the outer reinforcing bars 152 tying the circumferences of the horizontal reinforcing bars 151 at appropriate intervals.

이에 따라, 상기 매입형 RC보 철근틀(150)은 데크슬래브→매입형 RC보 철근틀→받침 브라켓→엄지말뚝(H-파일)으로 이어지는 수직방향 하중 전달이 원활히 이루어질 수 있도록 해주는 역할과, 또 횡토압→합벽→매입형 RC보 철근틀을 포함하는 매입 슬래브→테크 슬래브로 이어지는 수평방향 하중 전달이 원활히 이루어질 수 있도록 해주는 역할을 수행할 수 있다. Accordingly, the embedded RC beam reinforcement frame 150 serves to facilitate the vertical load transfer to the deck slab → embedded RC beam reinforcement frame → support bracket → thumb pile (H-pile), and It can play a role of smoothing the horizontal load transfer from lateral earth pressure to plywood to embedded slab including embedded RC beams.

그리고, 상기 매입형 RC보 철근틀(150)의 경우 하중 전달이 원활히 이루어질 수 있도록 해주는 역할을 함으로써 시공을 보다 경제적이고 효율적으로 할 수 있는 이점도 제공한다. In addition, in the case of the embedded RC beam reinforcement frame 150 serves to facilitate the load transfer to provide a more economic and efficient construction.

예를 들면, 슬래브 구축을 위해 콘크리트를 타설한 후, 양생 전이나 양생 직 후 일정기간 동안에는 받침각관(125)이 슬래브를 지지하게 되는데, 만약 매입형 RC보 철근틀(150)이 없는 경우라면 슬래브가 완전히 양생되어 구조적 강성을 발휘할 때까지 받침각관(125)을 그대로 남겨놓은 상태에서 지하층을 계속해서 시공해야 하고, 결국 받침각관(125)의 재사용하지 못하고 새로운 받침각관(125)을 사용하면서 아래층을 계속 시공해나가야 하므로 경제성 측면에서 불리한 점이 있다. For example, after pouring concrete to build a slab, the support angle tube 125 supports the slab for a period of time before or after curing, if there is no embedded RC beam rebar 150, the slab The construction of the basement floor should be continued while leaving the support angle tube 125 intact until it is fully cured and exhibits structural rigidity. Finally, the base layer 125 cannot be reused and the lower level is used while using the new support angle tube 125. There is a disadvantage in terms of economic feasibility because construction has to be continued.

본 발명에서는 이러한 받침각관(125)의 역할을 매입형 RC보 철근틀(150)이 대신할 수 있으므로, 받침각관(125)이 없어도 양생 중이나 어느 정도 양생 후 일정기간 동안 매입형 RC보 철근틀(150)이 슬래브를 지지할 수 있으므로, 1개층 시공 후 사용되었던 받침각관(125)을 다음 아래층 시공시 재사용할 수 있고, 결국 경제적인 측면에서 유리한 이점이 있다. In the present invention, since the role of the support angle tube 125 can be replaced by the embedded RC beam reinforcement frame 150, embedded RC beam reinforcement frame for a certain period of time after curing or curing some degree even without the support angle tube 125 ( Since 150) can support the slab, the support angle tube 125, which was used after the construction of one floor, can be reused during the construction of the next downstairs, which is advantageous in terms of economy.

도 12에서는 시공이 끝난 윗층에서 사용되었던 받침각관(125)을 현재 시공중 인 아래층에서 사용하고 있는 예를 볼 수 있다. In Figure 12 you can see an example of using the support angle tube 125, which was used in the upper floor after construction is currently used in the lower floor under construction.

이러한 스틸 웨일 구조체 및 매입형 RC보 철근틀의 구성 및 사용에 대해서 좀더 상세히 설명하면 다음과 같다. The construction and use of the steel whale structure and the embedded RC beam rebar are described in more detail below.

우선, 지하구조물의 1층 바닥 슬래브를 포함한 각 지하층 슬래브(S)의 시공시에, 매입슬래브(S1) 영역에서 매입슬래브의 거푸집 역할 및 스틸 웨일 구조체(130)의 지지 역할을 하게 되는 지지수단을 흙막이벽(100)에 설치하고, 상기 지지수단에 연결되도록 슬래브 구축용 거푸집 구조체(141)를 설치한다. First, at the time of construction of each basement slab S including the ground floor slab of the underground structure, the supporting means serving as the formwork of the embedded slab and the supporting role of the steel wale structure 130 in the embedded slab S1 area. It is installed on the retaining wall 100, and installs the formwork structure 141 for slab construction to be connected to the support means.

보다 상세하게는, 도 9 내지 도 11에 나타낸 바와 같이, 흙막이벽(100)이 갖는 각 H-파일(101)의 플랜지면이 외부로 노출되도록 H-파일(101)이 설치된 위치에서 흙막이벽의 일부를 면갈이하고, 노출된 각 H-파일(101)의 플랜지면에 받침브라켓(122)을 각각 용접하여 설치한다. More specifically, as shown in Figs. 9 to 11, the wall of the retaining wall at the position where the H-pile 101 is installed so that the flange surface of each H-pile 101 of the retaining wall 100 is exposed to the outside. The surface is partly replaced, and the support brackets 122 are welded to the flange surfaces of the exposed H-piles 101, respectively.

이때, H-파일(101)들에 역삼각 구조의 받침브라켓(122)을 고정 설치할 수 있으며, 일 예로서, 각 H-파일(101)에 앵글부재(L-형강)를 역삼각 구조가 되도록 고정 설치하여 상기 받침브라켓(122)을 구성할 수 있다. At this time, the support bracket 122 having an inverted triangular structure may be fixedly installed on the H-files 101. For example, an angle member (L-shaped steel) may be inverted triangular structure on each of the H-files 101. It can be fixed to configure the support bracket (122).

여기서, 상기 받침브라켓(122)의 경우, 지하외벽(111)의 폭보다도 더욱 안쪽으로 연장된 길이를 갖게 되는데, 즉 매입슬래브(S1)의 면적을 받쳐주면서 또 슬래브 양생 전이나 양생 중에 거푸집 구조체(141)를 지지하는 임시거치용 받침각관(125)을 받쳐주는 충분한 길이를 갖게 된다. Here, in the case of the support bracket 122, it has a length extending further inward than the width of the basement outer wall 111, that is, while supporting the area of the buried slab (S1) and before the slab curing or curing the formwork ( 141 has a sufficient length to support the temporary support base angle tube 125 for supporting.

이 경우 지하외벽(111)을 완전히 구축한 상태에 받침브라켓(122)의 끝부분 일부(받침각관을 받치고 있던 부분)가 외벽 밖으로 노출되므로, 이를 용접 등의 작 업을 통해 제거하는 별도의 후작업이 필요하고, 결국 작업성이나 시공성 측면에서 효율이 떨어질 수 있다. In this case, since a part of the end of the base bracket 122 (the part supporting the base angle tube) is exposed outside the outer wall in the state where the basement outer wall 111 is completely constructed, a separate post work to remove it through a work such as welding. This is necessary and, in the end, efficiency may be reduced in terms of workability and workability.

이를 해소하기 위하여, 본 발명에서는 상기 받침브라켓(122)으로부터 착탈가능한 보조브라켓(153)를 마련하여, 슬래브 및 매입슬래브(S1) 양생 후 받침브라켓(122) 본체만 남겨놓고 보조브라켓(153)을 제거할 수 있도록 함으로써, 번거롭던 후작업을 배제할 수 있는 이점을 얻을 수 있다. In order to solve this problem, in the present invention, the auxiliary bracket 153 detachable from the support bracket 122 is provided to remove the auxiliary bracket 153 leaving only the support bracket 122 main body after curing the slab and the embedded slab S1. By doing so, it is possible to eliminate the cumbersome post-work.

즉, 상기 받침브라켓(122)은 앵글부재로 짠 역삼각 구조의 받침브라켓 본체와, 이 받침브라켓 본체의 선단부분에 볼트 등의 체결구조로 결합되는 보조브라켓(153)으로 구성하여, 슬래브 및 매입슬래브(S1) 양생 후 보조브라켓(153)을 받침브라켓 본체로부터 용이하게 떼어낼 수 있도록 함으로써, 종전과 같은 받침브라켓 노출문제를 해소할 수 있다. That is, the support bracket 122 is composed of a support bracket body having an inverted triangular structure woven from an angle member, and an auxiliary bracket 153 coupled to the front end portion of the support bracket body by a fastening structure such as a bolt, and a slab and a buried body. After curing the slab (S1) by the auxiliary bracket 153 can be easily removed from the base bracket body, it is possible to solve the problem of exposure to the base bracket as before.

이어 매입슬래브(S1) 영역에서 상기 받침브라켓(122) 위로 장선철근(123), 철망형 거푸집(124), 받침각관(또는 받침각재)(125), 스틸 웨일 구조체(130), 매입형 RC보 철근틀(150)을 설치한다. Subsequently, the reinforcing bar 123, the wire mesh formwork 124, the support angle tube (or the support angle material) 125, the steel wale structure 130, and the embedded RC beam in the buried slab (S1) area above the support bracket 122. Install the reinforcing frame 150.

즉, 매입슬래브(S1) 영역을 따라 이웃한 받침브라켓(122)들 위에 동시에 걸쳐지도록 장선철근(123)을 복수열로 받침브라켓 위에 횡으로 길게 지지시킨 뒤, 상기 장선철근(123) 위로 철망형 거푸집(124)을 설치하고, 상기 받침브라켓(122)의 선단부 위로는 데크 플레이트 등과 같은 슬래브(노출슬래브) 구축용 거푸집 구조체(141)의 가장자리부를 지지시키기 위한 받침각관(125) 또는 받침각재를 지지시킨다. That is, after supporting the joist reinforcement 123 in a plurality of rows laterally on the support bracket in a plurality of rows so as to be spread simultaneously on the adjacent support brackets 122 along the buried slab S1 area, the wire mesh type above the joist reinforcement 123. The formwork 124 is installed, and the support angle tube 125 or the support angle material for supporting the edge portion of the formwork structure 141 for building a slab (exposure slab), such as a deck plate, is installed on the tip end of the support bracket 122. Let's do it.

이때, 상기 받침각관(125) 또는 받침각재는 이웃한 받침브라켓(122)들 위에 동시에 걸쳐지도록 횡으로 길게 설치되어 지지된다. At this time, the support angle tube 125 or the support angle material is installed long and supported horizontally so as to be covered on the adjacent support brackets 122 at the same time.

그리고, 슬래브 양생 후에 원활한 하중 전달이 이루어질 수 있도록 하기 위하여, 철망형 거푸집(124) 위로 매입형 RC보 철근틀(150)을 설치한다. Then, in order to enable a smooth load transfer after the slab curing, the embedded RC beam reinforcing frame 150 is installed on the wire mesh formwork 124.

여기서, 상기 매입형 RC보 철근틀(150)은 매입형 RC보를 형성하기 위한 철근틀로서, 이때의 매입형 RC보 철근틀(150)은 매입슬래브(S1) 영역을 따라 이웃한 받침브라켓(122)들 위에 동시에 걸쳐지도록 하는 구조로 설치한다.
예를 들면, 매입슬래브(S1) 내의 확보된 영역에서 지하외벽을 따라 나란하게 연장되는 형태로 다수의 수평철근(150)이 배치되고, 이 수평철근(150)의 둘레가 외곽철근(152)에 의해 적정간격 묶여지면 매입형 RC보 철근틀(150)이 완성되며, 후술하는 바와 같이, 스틸 웨일 구조체(130) 내부 공간을 제외한 주변의 철망 거푸집 영역과 데크 플레이트 위 슬래브 영역에 콘크리트가 타설되면, 이때의 매입형 RC보 철근틀(150)에도 콘크리트가 타설되게 된다.
Here, the embedded RC beam reinforcement frame 150 is a reinforcing frame for forming the embedded RC beam, the embedded RC beam reinforcement frame 150 is the adjacent support bracket 122 along the buried slab (S1) region Install in a structure that spans at the same time.
For example, a plurality of horizontal reinforcing bars 150 are arranged in a form extending side by side along the underground outer wall in the area secured in the buried slab S1, and the periphery of the horizontal reinforcing bars 150 is disposed on the outer reinforcing bars 152. When the appropriate intervals are tied to the embedded RC beam reinforcement frame 150 is completed, as will be described later, when the concrete is poured into the slab area on the deck plate and the wire mesh formwork region, except the inner space of the steel wale structure 130, At this time, concrete is poured into the embedded RC beam reinforcement frame 150.

상기 철망형 거푸집(124)은 통상 메탈 리브 라스(metal rib lath)라고 불리는 거푸집으로, 철망 라스(lath)에 리브(rib)를 두어 제작된 거푸집이며, 현재 네트 거푸집 공법에서 사용되는 거푸집이다.The wire mesh formwork 124 is a formwork commonly referred to as metal rib lath, and is a formwork made by placing ribs on a wire mesh lath, and is a formwork currently used in a net formwork method.

시공시 상기 철망형 거푸집(124)은 장선철근(123) 등에 적절히 용접하여 고정하거나 철선 등으로 고정하게 된다.During construction, the wire mesh formwork 124 is fixed by welding the reinforcing bar 123 or the like or fixed with an iron wire or the like.

그리고, 상기 받침각관(125) 또는 받침각재 위로 거푸집 구조체(141)의 가장자리부를 지지시킨 뒤, 매입슬래브(S1) 영역에서는 사각형 틀 구조로 공장 제작된 스틸 웨일 구조체(130)를 매입슬래브 영역을 따라 상기 철망형 거푸집(124) 위에 일정 간격으로 지지시켜 설치하게 된다.Then, after supporting the edge of the formwork structure 141 over the support angle tube 125 or the support angle material, in the embedded slab (S1) region of the steel wale structure 130 manufactured in a rectangular frame structure along the embedded slab region The wire mesh formwork 124 is installed to be supported at a predetermined interval.

이후 매입슬래브(S1) 영역 내에서 스틸 웨일 구조체(130) 주변으로 적절히 보강 철근을 배근하는 작업을 실시한다. Thereafter, a work of appropriately reinforcing the reinforcing bar is performed around the steel wale structure 130 in the buried slab S1 region.

또한, 지하외벽 내측으로 상,하 층간을 연결하게 되는 철근으로서 다월 철근(dowel bar)(115)을 매입슬래브(S1) 영역을 수직 관통시키는 형태로 배근한다.In addition, as a reinforcing bar connecting the upper and lower floors to the inside of the basement outer wall, the dowel bar 115 is disposed in the form of vertically penetrating the buried slab S1 region.

이는 바깥쪽에 관통 형식으로 배근되는 인장철근인 수직철근(113)과 달리 내 측의 다월 철근(115)과 연결되는 수직철근(112)은 압축측에 위치하기 때문에 배근간격을 보통 수직철근의 배근간격보다 3∼5배 간격으로 넓게 배근하여 시공성 및 경제성을 향상시킬 수 있다.This is because the vertical reinforcing bars 113, which are connected to the dowel reinforcing bars 115 on the inner side, are located on the compression side, unlike the vertical reinforcing bars reinforcing bars in the form of penetrating outwards. It is possible to improve workability and economic efficiency by broadening the spacing at intervals of 3 to 5 times.

안쪽 수직철근의 배근시에 안쪽 수직철근의 일부는 다월 철근 및 수평철근, 그리고 매입형 RC보 철근틀에 함께 결속하고, 다월 철근이 배근되지 않은 구간의 나머지 일부는 수평철근에만 결속한다. At the time of reinforcement of the inner vertical reinforcing bars, some of the inner vertical reinforcing bars bind together to the dowel and horizontal reinforcement bars and the embedded RC beam reinforcement frame, and the rest of the sections in which the dorsal reinforcing bars are not reinforced are bound only to the horizontal reinforcing bars.

상기 다월 철근(115)은 합벽 내 배근 과정에서 압축철근인 안쪽 수직철근(112) 및 수평철근(116)과 함께 결속(와이어 결속)되어지는 철근이며, 다만 지상 1층 바닥 슬래브의 매입슬래브 영역에서는 다월 철근(115)을 수직철근(112)과 동일 간격으로 설치하는데, 이는 인장측 철근이 되기 때문이다(도 13 참조). The dowel reinforcement 115 is a reinforcing bar (wire binding) together with the inner vertical reinforcing bars 112 and the horizontal reinforcing bars 116, which are compressed reinforcing bar in the reinforcement process in the plywood, but in the buried slab area of the ground floor slab Dowel reinforcement 115 is installed at the same interval as the vertical reinforcement 112, because it becomes the tension-side reinforcement (see Fig. 13).

이와 같이 하여, 받침브라켓(122) 및 장선철근(123), 철망형 거푸집(124), 스틸 웨일 구조체(130), 받침각관(125), 매입형 RC보 철근틀(150), 거푸집 구조체(141) 등을 모두 설치하고, 매입슬래브(S1) 내 보강 철근 및 다월 철근(115)을 모두 배근하며, 데크 플레이트 위 노출슬래브 영역에서도 상, 하부 철근을 배근하는 슬래브 철근 배근작업 등 통상의 슬래브 작업을 모두 완료하게 되면, 스틸 웨일 구조체(130) 내부공간을 제외한 주변의 철망형 거푸집 영역(매입슬래브 영역)과 데크 플레이트 위 슬래브 영역(데크 슬래브 영역)에 콘크리트를 타설하여 슬래브 시공을 완료한다.Thus, the base bracket 122 and the long wire reinforcement 123, the wire mesh formwork 124, steel wale structure 130, the support angle pipe 125, embedded RC beam reinforcement frame 150, formwork structure 141 And all the reinforcing bars and dowel reinforcing bars 115 in the embedded slab (S1), and slab reinforcement work for reinforcing the upper and lower bars in the exposed slab area on the deck plate. When all is completed, the slab construction is completed by pouring concrete into the surrounding wire mesh formwork area (buying slab area) and the deck plate slab area (deck slab area) except for the inner space of the steel wale structure 130.

이와 같이 한 층의 슬래브(S)를 시공한 후에는 전술한 바와 같이 하층으로 내려가면서 동일한 방식으로 각 층의 슬래브를 시공하게 된다.As described above, after the slab S of one layer is constructed, the slab of each layer is constructed in the same manner while descending to the lower layer as described above.

각 층 슬래브(S)의 시공이 완료된 상태에서는 스틸 웨일 구조체(130)의 내부공간을 제외한 나머지 부분이 콘크리트로 채워져 슬래브를 형성하며, 이 슬래브는 합벽 시공 후 지하외벽(111) 속에 매립되는 매입슬래브(S1) 부분과 지하외벽 밖으로 노출되는 노출슬래브(S2) 부분(데크 플레이트로 시공되는 데크 슬래브 부분)으로 구분되게 된다.When the construction of each layer slab (S) is completed, the remaining portion of the steel wale structure 130, except the inner space is filled with concrete to form a slab, the slab is embedded buried in the underground outer wall 111 after construction of the plywood wall Part S1 and the exposed slab S2 exposed outside the basement outer wall (deck slab part constructed with deck plates) are divided.

각 층의 매입슬래브(S1)에서 스틸 웨일 구조체(130)의 내부공간은 콘크리트가 타설되지 않기 때문에 개구부(OP)를 형성하게 되는데, 이 개구부(OP)는 이후 합벽 시공 과정에서 지하외벽(111)용 콘크리트를 타설하기 위한 콘크리트 타설 및 충전 통로로 활용되고, 또한 층간 수직철근(113)이 설치되는 통로로 활용될 수 있는 바, 결국 개구부(OP)를 통한 지하외벽(111)의 수직철근(113) 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 수행할 수 있게 된다.In the buried slab S1 of each layer, the inner space of the steel wale structure 130 forms an opening OP because concrete is not poured, and the opening OP is formed in the basement outer wall 111 during the plywood construction. It can be used as a concrete pouring and filling passage for placing concrete for the concrete, and also can be used as a passage where the interlayer vertical reinforcing bars 113 are installed, and thus, vertical reinforcing bars 113 of the basement outer wall 111 through the opening OP. ) It is possible to perform the continuous continuous placement of interlayer continuous reinforcement and concrete.

슬래브(S)의 시공 후 매입슬래브(S1)의 개구부(OP)가 충분히 확보되기 때문에 개구부를 통해 지하외벽(111)의 수직철근(113) 층간 연속 배근과 콘크리트 층간 연속 타설이 가능해지며, 이로써 지하외벽(111)은 층간 일체성이 강화되면서 흙막이벽(100)에 접하여 하나의 지하합벽으로 구축되게 된다. Since the opening OP of the embedded slab S1 is sufficiently secured after the construction of the slab S, continuous reinforcement between the vertical reinforcing bars 113 of the basement outer wall 111 and the continuous inter-concrete flooring are possible through the opening. The outer wall 111 is constructed as one underground plywood in contact with the earth barrier wall 100 while increasing the interlayer integrity.

지하외벽(111)의 시공은, 인장철근이 되는 바깥쪽 수직철근(113)을 매입슬래브(S1)의 개구부(OP)를 통과하도록 층간 연속 배근하고, 지하외벽 내 공간의 상하층 다월 철근(115)에 연결되는 안쪽 수직철근(112), 수평철근(116), 이 수평철근(116)에 결속되어 지지되는 또 다른 안쪽 수직철근들을 배근하며, 지하외벽 거푸집을 설치한 뒤 콘크리트를 타설하여, 상기 수직철근(112,113), 다월 철근(115), 수평철근(116), 매입슬래브(S1)를 지하외벽(111)에 모두 매립시키는 방식으로 이루어진다.In the construction of the basement outer wall 111, the outer vertical reinforcing bars 113, which are tensile reinforcing bars, are continuously intercalated between layers so as to pass through the opening OP of the buried slab S1, and the upper and lower layer dowel reinforcing bars in the space in the basement outer wall (115). Inner vertical reinforcing bars 112, horizontal reinforcing bars 116 connected to the) and other inner vertical reinforcing bars bound to and supported by the horizontal reinforcing bars 116, and after installing the basement wall formwork, the concrete is poured, Vertical reinforcing bars (112, 113), dowel reinforcement (115), horizontal reinforcing bars (116), buried slab (S1) is made in such a way that all buried in the basement outer wall (111).

물론, 콘크리트 타설시에 스틸 웨일 구조체(130)의 내부공간, 즉 개구부(OP)를 통해 콘크리트를 타설해야 하므로 스틸 웨일 구조체의 내부공간에 위치된 철망형 거푸집은 절단하여 제거한다.Of course, since concrete must be poured through the inner space of the steel wale structure 130, that is, the opening OP, when the concrete is placed, the wire mesh formwork located in the inner space of the steel wale structure is cut and removed.

지하외벽 철근 배근시에는 지상 1층 바닥 슬래브의 매입슬래브(S1)에 설치된 각 다월 철근(115)에 압축철근인 안쪽 수직철근(112)을 결속하여 연결하고, 그 이하 지하층에서는 안쪽 수직철근(112)의 일부만을 다월 철근(115)에, 나머지 일부는 수평철근(116)에 각각 결속하여 연결한다.In case of reinforcement of the basement outer wall, the inner vertical reinforcing bars 112, which are compressed reinforcing bars, are connected to each dowel reinforcing bars 115 installed in the buried slab S1 of the ground slab of the ground floor. Only a part of the) to the dowel reinforcement 115, the remaining part is connected to the horizontal reinforcing bars 116, respectively.

토압 작용시 모멘트 특성상 바깥쪽 수직철근(113)에는 인장력이, 안쪽 수직철근(112)에는 압축력이 작용하므로, 인장철근이 되는 상기 바깥쪽 수직철근(113)은 인장력에 저항할 수 있게 개구부(OP)를 관통시켜 층간 연속 배근하고(바깥쪽 수직철근 = 관통철근), 압축철근이 되는 상기 안쪽 수직철근(112)은 매입슬래브(S1)에 상하 관통 매립된 다월 철근(115)과 수평철근(116)에 간단히 결속시켜 배근한다.Due to the characteristic of the moment during earth action, the tensile force acts on the outer vertical reinforcement 113 and the compressive force acts on the inner vertical reinforcement 112, so that the outer vertical reinforcement 113, which becomes the tensile reinforcement, can resist the tensile force. ) Through the interlayer continuous reinforcement (outer vertical reinforcement = through reinforcing bar), and the inner vertical reinforcing bar 112, which becomes a compressed reinforcing bar, the dowel reinforcing bars 115 and horizontal reinforcing bars (118) vertically buried in the buried slab (S1) Binding simply to) to work.

그리고, 상기 매입슬래브(S1)의 내부에 설치되는 매입형 RC보 철근틀(150)로 인해 슬래브 양생 후, 하중 전달이 원활히 이루어질 수 있게 되므로, 토압 작용시 또는 슬래브측 하중 작용시 견고한 구조적인 강성이 확보될 수 있다. And, because the buried RC beam reinforcement frame 150 is installed inside the embedded slab (S1), after the slab curing, it is possible to smoothly transfer the load, so that the structural rigidity during the earth pressure action or the slab side load action This can be secured.

본 발명에서 상기 다월 철근(115)은 상하층을 구조적으로 연결하는 연결용 철근이 아니라 안쪽 수직철근(112)을 고정시키는 고정용 철근으로 사용되며, 수직 철근(112)의 고정이 용이한 간격을 고려하여 매입슬래브(S1)에 매립된다.In the present invention, the dowel reinforcement 115 is used as a fixing reinforcing bar for fixing the inner vertical reinforcing bar 112, not the connecting reinforcing bar structurally connecting the upper and lower layers, the interval between which easy to fix the vertical reinforcing bar 112 It is buried in the embedded slab S1 in consideration.

상기 다월 철근(115)의 간격이 지상 1층의 경우를 제외하고는 안쪽 수직철근(112)의 간격과 다르므로 다월 철근이 설치되지 않은 나머지 구간에서는 안쪽 수직철근(112)을 수평철근(116)에 결속시켜 지지시킨다. Since the interval of the dowel reinforcement 115 is different from the interval of the inner vertical reinforcement 112 except in the case of the first floor above the ground, the inner vertical reinforcement 112 is replaced with the horizontal reinforcement 112 in the remaining section where the dowel reinforcement is not installed. Bind to and support

한편, 첨부한 도 14는 본 발명에 따른 스틸 웨일 구조체의 다양한 실시예를 도시한 도면이다. Meanwhile, FIG. 14 is a view showing various embodiments of the steel wale structure according to the present invention.

도시된 바와 같이, 스틸 웨일 구조체(130)는 전면부재(131), 후면부재(132), 양 측면부재(133a,133b)를 사각형 형태로 배치하여 상호 용접 고정함으로써 이루어진 사각형 틀 구조로 제작된다.As shown, the steel wale structure 130 is manufactured in a rectangular frame structure made by welding the front member 131, the rear member 132, both side members (133a, 133b) in a rectangular shape by mutual welding.

이때, 전면부재(131)와 후면부재(132) 사이에 중간부재(134)를 설치하여 1개의 공간, 2개의 공간, 3개의 공간, ..., n개의 공간으로 구획된 구조가 될 수 있으며, 전체적인 외각 형상에 있어서 좌우 길이에 비해 폭을 짧게 구성하여 짧은 좌굴길이를 갖도록 한다. 이와 같이 폭을 상대적으로 짧게 구성하는 경우 좌굴길이가 짧아지므로 좌굴 허용 축하중이 커져 토압 저항에 유리해진다. In this case, the intermediate member 134 is installed between the front member 131 and the rear member 132 to have a structure partitioned into one space, two spaces, three spaces, ..., n spaces. In the overall outer shape, the width is shorter than the left and right lengths so as to have a short buckling length. In this case, when the width is relatively short, the buckling length is shortened, so that the buckling allowable axial load becomes large, which is advantageous for earth pressure resistance.

또한, 스틸 웨일 구조체(130)를 설치함에 있어서, 사용되는 스틸 웨일 구조체의 폭은 매입슬래브(S1)의 폭(=지하외벽의 폭)에 대해 50% 이하가 되도록 하며, 더욱 바람직하게는 25∼50%의 범위가 되도록 하는 것이 바람직하다.In the installation of the steel wale structure 130, the width of the steel wale structure to be used is 50% or less with respect to the width of the embedded slab S (= width of the basement outer wall), more preferably 25 to It is preferable to make it into 50% of range.

여기서, 스틸 웨일 구조체(130)의 폭이 매입슬래브(S1)의 폭에 비해 25% 미만이 되면, 충분한 개구부(OP)의 면적을 확보하지 못하게 되어, 지하외벽(111)의 관통철근, 즉 바깥쪽 수직철근(113)의 층간 배근이 어렵고, 콘크리트 타설용 통로 로 사용하는데 어려움이 있다.Here, when the width of the steel wale structure 130 is less than 25% of the width of the buried slab S1, it is impossible to secure a sufficient area of the opening OP, so that the reinforcing bars of the basement outer wall 111, that is, the outside Interlayer reinforcement of the side vertical reinforcement 113 is difficult, there is a difficulty in using as a concrete pouring passage.

또한, 스틸 웨일 구조체(130)의 폭이 매입슬래브(S1)의 폭에 비해 50%를 초과하게 되면, 개구부(OP)의 면적은 크게 확보될 수 있으나, 개구부의 지나친 면적 증가로 인해 매입슬래브(S1)가 구조적으로 취약해지고, 개구부(OP) 사이 구간의 영역에서 편토압 작용으로 인한 전단 균열이 발생할 우려가 있으므로 바람직하지 않다.In addition, when the width of the steel wale structure 130 exceeds 50% of the width of the buried slab S1, the area of the opening OP may be largely secured, but the buried slab ( It is not preferable because S1) is structurally weak and there is a possibility that shear cracking may occur due to the excavation pressure action in the region between the openings OP.

또한, 본 발명의 스틸 웨일 구조체(130)를 제작함에 있어서, 각 부재는 평판의 사용이 가능하나, 충분한 강성 확보 및 내력 증가를 위해 측면부재(133a,133b)와 중간부재(134)의 경우 첨부한 도 15에 나타낸 바와 같이 평판 외에 앵글부재(L-형강), 채널부재(ㄷ-형강), 절곡단면판을 사용하는 것이 바람직하다.In addition, in manufacturing the steel wale structure 130 of the present invention, each member is possible to use a flat plate, but in the case of the side member (133a, 133b) and the intermediate member 134 to secure sufficient rigidity and increase the strength As shown in FIG. 15, it is preferable to use an angle member (L-shaped steel), a channel member (c-shaped steel), and a bent section plate in addition to the flat plate.

또한, 상기 스텔 웨일 구조체(130)에서 사각 틀의 내부공간(구획된 각 내부공간)에는 대각선 방향의 보강부재(135)가 고정 설치될 수 있다.In addition, a diagonal reinforcement member 135 may be fixedly installed in the inner space (each inner space) of the rectangular frame in the stealth wale structure 130.

첨부한 도 16은 본 발명에서 상기의 스틸 웨일 구조체를 사용하여 시공함에 따른 개구부의 시공 상태를 보여주는 도면으로, 사각 면적의 지하구조물을 시공한다고 할 때, 슬래브 콘크리트 시공이 (I) 영역과 (Ⅱ) 영역으로 나누어져 순차 시공되는 경우, 슬래브(S) 폐합 전, 즉 (Ⅱ) 영역의 슬래브 콘크리트가 타설되기 전에 (I) 영역의 추가적인 굴토작업이 실시되어 상당한 크기의 편토압이 매입슬래브(S1)에 작용하더라도, 스틸 웨일 구조체(130)가 내력 구조재로서 하중을 충분히 분산 지지하므로 효과적으로 편토압 저항 및 토압을 전달할 수 있고, 또한 개구부(OP) 사이의 구간이 편토압에 대해 충분한 내력을 가지므로 종래와 같은 전단 균 열의 발생이 방지될 수 있다.FIG. 16 is a view showing a construction state of openings according to the construction using the steel wale structure in the present invention. Slab concrete construction includes (I) and (II) In case of sequential construction and dividing into (S) area, additional excavation work in (I) area is performed before slab (S) closing, that is, before slab concrete in (II) area is placed, so that a large amount of excavation pressure is applied to embedded slab (S1). Even if it acts on), the steel wale structure 130 can sufficiently support the load resistance and earth pressure as the load bearing structure is sufficiently distributed, and the section between the openings OP has sufficient strength against the earth pressure. The occurrence of shear cracks as in the prior art can be prevented.

더불어, 본 발명에서는 개구부(OP)의 폭이 외벽(111)의 전체 폭(두께)에 대해 50% 이내로서 개구부가 외벽의 전체 폭에서 부분적으로 짧게 형성되므로, 개구부(OP) 사이의 구간(장주가 아닌 단주 거동)의 구조 성능이 증대되고(축하중 내력이 크고 편토압에 유리), 개구부 사이의 구간에서 종래와 같은 상당량의 철근이 보강될 필요가 없는 바, 철근 물량 축소, 비용 절감의 장점이 있게 된다. 개구부 사이의 구간에서 후프 배근 등이 불필요하고 일반 배근으로 시공이 가능하다.In addition, in the present invention, since the width of the opening OP is 50% or less with respect to the total width (thickness) of the outer wall 111, the opening is partially formed at the entire width of the outer wall. Structure performance of steel castings is not increased, and the load capacity is large and favorable for flat soil pressure, and it is not necessary to reinforce the same amount of reinforcing bar in the section between openings. This will be. In the section between the openings, hoop back muscles are unnecessary and can be installed as general back muscles.

아울러, 본 발명에서 사용되는 스틸 웨일 구조체(130) 자체가 폭이 짧고 측면부재(133a,133b) 및 중간부재(134)의 길이가 짧으므로 구조적인 성능 및 효율이 우수한 장점이 있으며, 특히 스틸 웨일 구조체 내 좌굴길이가 짧아 저항 축력 및 강성이 우수하여(축하중 내력이 크고 편토압에 유리) 매입슬래브(S1)를 포함한 슬래브 전체의 강성을 극대화할 수 있게 된다. In addition, since the steel wale structure 130 itself used in the present invention has a short width and the length of the side members 133a, 133b and the intermediate member 134 is short, there is an advantage in excellent structural performance and efficiency, in particular steel wale The short buckling length in the structure makes it possible to maximize the stiffness of the entire slab including the embedded slab S1 due to its excellent resistance axial force and rigidity (large axial load capacity and favorable to earth pressure).

또한, 본 발명에서 사용되는 스틸 웨일 구조체(130)는 그 크기가 작고 경량이므로 시공성이 향상되고, 아울러 스틸 웨일 구조체의 설치가 연속 설치가 아닌 이격 배치되는 부분 설치이므로 종래의 그레이팅 지지틀에 비해 물량 축소(사용 개수 축소) 및 물량 비용 절감, 작업시간 단축, 인건비 절감 등의 장점이 있게 된다.In addition, since the steel wale structure 130 used in the present invention is small in size and light in weight, the workability is improved, and the installation of the steel wale structure is a partial installation spaced apart from the continuous installation. There are advantages such as reduction (reduced number of uses) and volume cost reduction, work time reduction and labor cost reduction.

도 1은 종래기술에 따른 슬래브 및 테두리보의 시공을 위한 거푸집 구조체의 설치상태를 보여주는 단면도 1 is a cross-sectional view showing the installation state of the formwork for the construction of the slab and the rim beam according to the prior art

도 2는 종래기술에 따른 슬래브 및 테두리보의 시공이 완료된 상태를 보여주는 단면도2 is a cross-sectional view showing a state in which the construction of the slab and the rim beam according to the prior art is completed

도 3은 지하합벽의 역타 시공이 이루어지는 상태의 예를 도시한 단면도3 is a sectional view showing an example of a state in which the reverse construction of the underground plywood is made;

도 4 및 도 5는 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 4은 개방형 판재 구조의 매입거푸집을 사용하여 시공한 평면도이고, 도 5는 도 4의 선 'A-A'를 따라 취한 단면도4 and 5 is a view for explaining the problem according to the prior art, Figure 4 is a plan view using a built-in formwork of open plate structure, Figure 5 is taken along the line 'A-A' of Figure 4 Cross-section

도 6과 도 7은 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 6은 평면도이고, 도 7은 도 6의 선 'B-B'를 따라 취한 단면도6 and 7 are diagrams for explaining a problem according to the prior art, Figure 6 is a plan view, Figure 7 is a cross-sectional view taken along the line 'B-B' of FIG.

도 8은 본 발명에 따른 시공 과정의 공정도8 is a process chart of the construction process according to the present invention

도 9는 본 발명에 따른 매입슬래브 영역에서 스틸 웨일 구조체와 매입형 RC보 철근틀이 설치된 상태를 보여주는 사시도9 is a perspective view showing a state in which the steel wale structure and the embedded RC beam reinforcement frame is installed in the buried slab area according to the present invention;

도 10은 본 발명에서 흙막이벽의 H-파일에 받침브라켓을 설치한 뒤 받침브라켓 위에 장선철근, 철망형 거푸집, 스틸 웨일 구조체, 매입형 RC보 철근틀, 받침각관을 설치한 상태의 평면도Figure 10 is a plan view of the state installed the reinforcement bracket, wire mesh formwork, steel wale structure, embedded RC beam reinforcement frame, support angle tube on the support bracket after installing the support bracket on the H- pile of the earth wall in the present invention

도 11은 본 발명에서 흙막이벽의 H-파일이 설치된 위치의 단면도11 is a cross-sectional view of the installation position of the H-pile of the retaining wall in the present invention

도 12는 본 발명에 따른 시공 과정에서 슬래브 시공 후 합벽 시공 과정에서 수직철근의 배근상태를 도시한 도면12 is a view showing the reinforcement state of the vertical rebar in the plywood construction process after the slab construction in the construction process according to the present invention

도 13은 도 12에서 'C' 방향에서 본 수직철근의 배근상태를 나타낸 도면FIG. 13 is a view illustrating a reinforcement state of vertical rebars viewed from a direction 'C' in FIG. 12.

도 14는 본 발명에 따른 스틸 웨일 구조체의 다양한 실시예를 도시한 도면14 illustrates various embodiments of a steel wale structure in accordance with the present invention.

도 15는 본 발명에 따른 스틸 웨일 구조체에서 측면부재와 중간부재로 사용되는 판재의 여러 예를 도시한 단면도15 is a cross-sectional view showing several examples of the plate used as the side member and the intermediate member in the steel wale structure according to the present invention

도 16은 본 발명에서 개구부의 시공 상태를 보여주는 도면16 is a view showing a construction state of the opening in the present invention

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100 : 흙막이벽 101 : H-파일100: retaining wall 101: H- pile

110 : 지하합벽 111 : 지하외벽110: underground plywood 111: underground outer wall

112 : 안쪽 수직철근 113 : 바깥쪽 수직철근112: inside vertical bar 113: outside vertical bar

115 : 다월 철근 116 : 수평철근115: Dowel rebar 116: horizontal rebar

121 : 매입거푸집 122 : 받침브라켓121: purchase die 122: support bracket

123 : 장선철근 124 : 철망형 거푸집123: Jangbar rebar 124: wire mesh formwork

125 : 받침각관 130 : 스틸 웨일 구조체125: support angle tube 130: steel wale structure

131 : 전면부재 132 : 후면부재131: front member 132: rear member

133a, 133b : 측면부재 134 : 중간부재133a, 133b: side member 134: intermediate member

135 : 보강부재 135: reinforcing member

141 : 슬래브 구축용 거푸집 구조체(데크 플레이트)141: formwork for the slab construction (deck plate)

150 : 매입형 RC보 철근틀 151 : 수평철근150: embedded RC beam rebar frame 151: horizontal rebar

152 : 외곽철근 153 : 보조브라켓152: outer reinforcement 153: auxiliary bracket

OP : 개구부 S : 슬래브 OP: opening S: slab

S1 : 매입슬래브 S2 : 노출슬래브S1: embedded slab S2: exposed slab

Claims (11)

각 층의 슬래브(S) 시공시 매입슬래브의 거푸집 역할 및 하기 스틸 웨일 구조체(130)의 지지 역할을 수행하는 받침브라켓(122)을 흙막이벽(100)에 설치하는 단계;Installing a support bracket 122 to the earth wall 100 to serve as a formwork of the embedded slab and a support role of the steel whale structure 130 as a slab (S) for each layer construction; 매입슬래브(S1)의 개구부 형성을 위한 거푸집 역할과 동시에 흙막이벽(100)으로부터 전달되는 하중 지지, 분산 및 전달 역할을 수행하는 스틸 웨일 구조체(130)를 상기 받침브라켓(122) 위 매입슬래브(S1) 영역을 따라 이격 배치하는 단계;At the same time as the formwork for forming the opening of the buried slab S1 and the steel whale structure 130, which performs the load supporting, dispersing, and transferring roles from the retaining wall 100, the buried slab S1 on the support bracket 122. ) Spaced apart along the area; 수평철근(151)과 외곽철근(152)을 포함하는 형태로 이루어져 하중의 원활한 전달을 위한 역할을 수행하는 매입형 RC보 철근틀(150)을 상기 받침브라켓(122) 위 매입슬래브(S1) 영역을 따라 배근하는 단계;Recessed slab (S1) area on the support bracket 122 has a buried RC beam reinforcement frame 150, which consists of a horizontal reinforcement 151 and the outer reinforcement 152, which serves to smoothly transfer loads Step along the back; 상기 받침브라켓(122)에 연결되도록 슬래브 구축용 거푸집 구조체(141)를 설치한 뒤, 상기 스틸 웨일 구조체(130)의 내부공간을 제외한 전 슬래브(S) 영역에 콘크리트를 타설하여 슬래브(S)를 시공하는 단계; After installing the slab construction formwork 141 to be connected to the support bracket 122, the slab (S) by placing concrete in the entire slab (S) area excluding the internal space of the steel wale structure 130 Construction step; 전 층의 슬래브(S) 시공이 완료되면, 상기 스틸 웨일 구조체(130)의 내부공간에 의해 형성된 개구부를 지하외벽(111)의 수직철근 층간 배근 및 지하외벽(111)의 콘크리트 타설을 위한 통로로 사용하여 지하합벽을 층간 연속적으로 순타 시공하는 단계;When the construction of the slab (S) of the entire layer is completed, the opening formed by the inner space of the steel wale structure 130 as a passageway for the concrete reinforcement of the vertical reinforcement interlayer reinforcement of the basement outer wall 111 and the basement outer wall 111 Using a step of successive construction of the subterranean wall using the interlayer; 를 포함하는 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법.Slab and plywood construction method of the underground structure comprising a. 청구항 1에 있어서, 상기 받침브라켓(122)을 설치하는 단계에서는 받침브라켓(122) 위에 매입슬래브(S1) 영역을 따라 장선철근(123)을 복수열로 설치하고, 상기 장선철근(123) 위에 철망형 거푸집(124)을 설치한 다음, 상기 받침브라켓(122)의 선단부 위로는 상기 슬래브 구축용 거푸집 구조체(141)의 가장자리부를 지지시키기 위한 받침각관(125) 또는 받침각재를 설치하는 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법.The method according to claim 1, wherein in the step of installing the support bracket 122, a plurality of columns of reinforcing bar 123 along the buried slab (S1) on the support bracket 122, the wire mesh on the reinforcing bar 123 After installing the formwork 124, above the tip of the support bracket 122, characterized in that the support angle tube 125 or a support angle member for supporting the edge of the slab construction formwork structure 141, characterized in that for installing Slab and plywood construction method of underground structure. 청구항 1에 있어서, 상기 매입슬래브(S1) 영역에 상기 스틸 웨일 구조체(130)를 설치함에 있어서 스틸 웨일 구조체(130)의 폭이 매입슬래브(S1)의 폭에 대해 25∼50%의 범위가 되도록 부분 설치하는 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법.The method of claim 1, wherein the width of the steel wale structure 130 is 25 to 50% of the width of the buried slab S1 in installing the steel wale structure 130 in the buried slab S1 region. Slab and plywood construction method of the underground structure characterized in that part installation. 청구항 1 내지 청구항 3 중 어느 한 항에 있어서, 상기 스틸 웨일 구조체(130)는 전면부재(131)와 후면부재(132), 양 측면부재(133a,133b)가 사각형의 틀 구조로 고정되어 내부공간을 가지도록 제작된 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법.According to any one of claims 1 to 3, The steel wale structure 130 is the front member 131, the rear member 132, both side members (133a, 133b) is fixed in a rectangular frame structure internal space Slab and plywood construction method of the underground structure, characterized in that it is made to have. 청구항 4에 있어서, 상기 스틸 웨일 구조체(130)는 상기 전면부재(131)와 후면부재(132) 사이에 내부공간을 구획하는 중간부재(134)가 추가로 고정되어 상기 중간부재(134)에 의해 스틸 웨일 구조체(130)의 내부공간이 n개로 구획된 구조로 제작된 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법. The method of claim 4, wherein the steel wale structure 130 is an intermediate member 134 for partitioning the inner space between the front member 131 and the rear member 132 is further fixed by the intermediate member 134 Slab and plywood construction method of the underground structure, characterized in that the inner space of the steel wale structure 130 is made of a structure divided into n. 청구항 1에 있어서, 상기 지하합벽 내에서 인장철근이 되는 바깥쪽 수직철근(113)근은 상기 스틸 웨일 구조체(130)에 의해 형성된 개구부를 관통하도록 하여 층간 연속 배근하고, 상기 지하합벽 내에서 압축철근이 되는 안쪽 수직철근(112)은 매입슬래브(S1)에 상하 관통 매립된 다월 철근(115) 및 수평철근(116)에 함께 결속하거나 수평철근(116)에만 결속하여 배근하는 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법.The method of claim 1, wherein the outer vertical reinforcing bar 113, which is a tensile reinforcing bar in the underground junction wall to pass through the opening formed by the steel wale structure 130, continuous reinforcement between the layers, the compression reinforcement in the underground junction wall The inner vertical reinforcement 112 is an underground structure, characterized in that it is bound to the dowel reinforcement 115 and the horizontal reinforcement 116 embedded in the upper and lower through the embedded slab (S1) or to bind only to the horizontal reinforcement (116) Method of slab and plywood construction 청구항 6에 있어서, 상기 다월 철근(115)을 안쪽 수직철근(112) 배근간격의 3∼5배 간격으로 배근하여, 상기 안쪽 수직철근(112)의 일부는 상기 다월 철근(115) 및 수평철근(116)에 함께 결속하고, 다월 철근(115)이 배근되지 않은 구간의 나머지 일부는 수평철근(116)에만 결속하는 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법. The method of claim 6, wherein the dowel reinforcement 115 is arranged at an interval of 3 to 5 times the spacing interval of the inner vertical reinforcement 112, a part of the inner vertical reinforcement 112 is the dowel reinforcement 115 and the horizontal reinforcement ( 116) and the remaining portion of the section where the dowel reinforcement (115) is not reinforcement is bound only to the horizontal rebar (116) slab and plywood construction method of the underground structure. 청구항 1에 있어서, 상기 매입형 RC보 철근틀(150)을 배치하는 단계에서는 매입슬래브(S1) 내의 확보된 영역에서 지하외벽(111)을 따라 나란하게 연장 배치되는 다수의 수평철근(151)과, 이 수평철근(151)의 둘레를 군데군데 묶어주는 외곽철근(152)을 포함하는 형태로 이루어진 매입형 RC보 철근틀(150)을 사용하는 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공 방법. 2. The method of claim 1, wherein in the arranging the embedded RC beam reinforcing frame 150, a plurality of horizontal rebars 151 extending side by side along the basement outer wall 111 in an area secured in the embedded slab S1 and , Slab and plywood construction method of the underground structure, characterized in that using the embedded RC beam reinforcement frame 150 made of a shape including the outer reinforcing bars 152 to tie the circumference of the horizontal reinforcing bars (151). 매입슬래브(S1)의 거푸집 역할 및 스틸 웨일 구조체(130)의 지지 역할을 수행하기 위하여 흙막이벽(100)에 설치되는 받침브라켓(122);A support bracket 122 installed on the retaining wall 100 to serve as a formwork of the embedded slab S1 and a supporting role of the steel wale structure 130; 상기 받침브라켓(122) 위 매입슬래브(S1) 영역을 따라 배치되는 장선철근(123) 및 이 장선철근(123) 위에 설치되는 철망형 거푸집(124);Jang wire reinforcement (123) disposed along the buried slab (S1) area on the support bracket 122 and the wire mesh formwork 124 is installed on the Jang wire reinforcement (123); 매입슬래브(S1) 영역과 이어지는 슬래브(S) 영역을 구축하기 위한 슬래브 구축용 거푸집 구조체(141);A slab construction formwork structure 141 for constructing an embedded slab S1 region and a subsequent slab S region; 매입슬래브(S1)의 개구부 형성을 위한 거푸집 역할과 동시에 흙막이벽(100)으로부터 전달되는 하중 지지, 분산 및 전달 역할을 수행하며, 상기 받침브라켓(122) 위 매입슬래브(S1) 영역을 따라 이격 배치되는 스틸 웨일 구조체(130);Simultaneously with the formwork for forming the opening of the buried slab (S1) serves to support, distribute and transfer the load transmitted from the retaining wall (100), spaced apart along the buried slab (S1) area on the support bracket 122 A steel wale structure 130; 수평철근(151)과 외곽철근(152)을 포함하는 형태로 이루어져 하중의 원활한 전달을 위한 역할을 수행하며, 상기 받침브라켓(122) 위 매입슬래브(S1) 영역을 따라 배근되는 매입형 RC보 철근틀(150);Consists of a shape including the horizontal reinforcing bar 151 and the outer reinforcing bar 152 to smoothly transfer the load, and embedded RC beam reinforcement is reinforced along the buried slab (S1) area on the support bracket 122 Frame 150; 을 포함하며, Including; 상기 스틸 웨일 구조체의 내부공간을 제외한 전 슬래브 영역에 콘크리트가 타설되어 슬래브 시공이 완료되고, 상기 스틸 웨일 구조체의 내부공간에 의해 형성된 개구부가 지하외벽용 수직철근 층간 배근 및 콘크리트 타설을 위한 통로로 사용되어 지하외벽 시공이 완료되어, 지하합벽과 슬래브가 구축된 구조로 이루어진 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 구조물.Concrete is laid in all slab areas except the inner space of the steel wale structure, and the slab construction is completed, and the opening formed by the inner space of the steel wale structure is used as a passage for placing the vertical reinforcing bars and concrete for the underground outer wall. Underground construction of the outer wall is completed, the slab and plywood structure of the underground structure, characterized in that the structure consisting of a basement wall and the slab structure. 청구항 9에 있어서, 상기 매입형 RC보 철근틀(150)은 매입슬래브(S1) 내의 확보된 영역에서 지하외벽(111)을 따라 나란하게 연장 배치되는 다수의 수평철근(151)과, 이 수평철근(151)의 둘레를 군데군데 묶어주는 외곽철근(152)을 포함하는 형태로 이루어진 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 구조물. 10. The method of claim 9, wherein the embedded RC beam reinforcement frame 150 is a plurality of horizontal reinforcing bars 151 arranged side by side along the outer outer wall 111 in the area secured in the buried slab (S1) and the horizontal reinforcement Slab and plywood structure of the underground structure, characterized in that formed in the form including the outer reinforcing bars (152) tying around the periphery of (151). 지하구조물의 슬래브(S) 및 합벽 시공시 사용되는 것으로서, 매입슬래브(S1)의 거푸집 역할 및 스틸 웨일 구조체(130)의 지지 역할을 수행하며, 흙막이벽(100)에 설치되는 받침브라켓 본체와, 이 받침브라켓 본체의 선단부분에 착탈가능하게 결합되는 보조브라켓(153)으로 구성되어, 슬래브(S) 양생 후 보조브라켓을 받침브라켓 본체로부터 떼어낼 수 있도록 된 것을 특징으로 하는 지하구조물의 슬래브 및 합벽 시공용 받침브라켓. As used during the construction of the slab (S) and plywood of the underground structure, and serves as the formwork of the embedded slab (S1) and the supporting role of the steel wale structure 130, and the support bracket body is installed on the earth wall (100), Slab and plywood of the underground structure, characterized in that it consists of an auxiliary bracket 153 detachably coupled to the front end of the support bracket body, so that the auxiliary bracket can be detached from the support bracket body after curing the slab (S). Supporting bracket for construction.
KR1020090062871A 2009-03-13 2009-07-10 Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket Active KR100951097B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020090021841 2009-03-13
KR20090021841 2009-03-13

Publications (1)

Publication Number Publication Date
KR100951097B1 true KR100951097B1 (en) 2010-04-07

Family

ID=42219536

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090062871A Active KR100951097B1 (en) 2009-03-13 2009-07-10 Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket

Country Status (1)

Country Link
KR (1) KR100951097B1 (en)

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101852016A (en) * 2010-06-11 2010-10-06 中国二十二冶集团有限公司 One-time installation of scaffolding construction method for super-long vertical reinforcement of underground wall
KR101034853B1 (en) 2010-06-22 2011-05-17 (주)씨엠파트너스건축사사무소 Reversal Construction Method of Underground Structures through Front Support of Retaining Walls and Uneven Surface Corresponding Forms
KR101046941B1 (en) 2011-03-14 2011-07-07 주식회사 하이드로코리아 Ramen Bridge Construction Method Excluding Hunts
KR101215764B1 (en) 2011-05-13 2013-01-09 삼성중공업 주식회사 A burial slab structure of an outer wall of an underground construction
KR101473218B1 (en) 2013-04-24 2014-12-16 황기수 A construction method of an underground structure
WO2015105230A1 (en) * 2014-01-13 2015-07-16 윤동현 Underground structure construction method using sump
KR101627708B1 (en) 2015-06-25 2016-06-07 주식회사 거원에코텍 Apparatus and method for closing an opening of building slab formed by the interference with the temporary structure
KR101665909B1 (en) * 2016-02-19 2016-10-17 주식회사 세진이엔시 Composite wall structure of underground outer wall with cip retaining wall
CN106168035A (en) * 2016-08-17 2016-11-30 广州地铁设计研究院有限公司 The subassembly formula construction method of subassembly formula underground structure and underground structure
KR20170012017A (en) 2015-07-24 2017-02-02 (주)씨지스플랜 Edge girder for slurry wall
CN106522261A (en) * 2016-10-26 2017-03-22 国家电网公司 Reinforcing structure and method of double-cement tower in coal gob area
JP2017119968A (en) * 2015-12-28 2017-07-06 株式会社大林組 Evaluation method of piles made of soil cement column walls
CN109025260A (en) * 2018-07-26 2018-12-18 中民筑友科技投资有限公司 A kind of prefabricated floor slab back casting band joint structure and its construction method
KR20190091397A (en) 2018-01-27 2019-08-06 양병진 Grouting method for joint portion of concrete structure in construction and top-down joint grouting method for underground structure using the same
KR102156793B1 (en) 2019-12-24 2020-09-16 (주)동아엔지니어링 Top-down method for underground structure to prevent sinkhole
KR20200114553A (en) * 2019-03-29 2020-10-07 유병훈 Underground structure with top-down construction method using underground column wall and construction method therefor
KR20210013888A (en) * 2019-07-29 2021-02-08 유병훈 Top-down construction method with underground utility
CN115387502A (en) * 2022-09-20 2022-11-25 中建三局集团有限公司 Same-layer construction system and construction method for assembled partition wall and main body structure
KR102579169B1 (en) * 2023-06-02 2023-09-14 홍승대 Top-down method using suspended rebar
KR102579166B1 (en) * 2023-06-02 2023-09-14 홍승대 Top-down Structures Using Suspended rebar
CN117905108A (en) * 2024-03-19 2024-04-19 福建一建集团有限公司 Construction method for building engineering reverse construction method of civil air defense in heavy-layer water-bearing sand layer
KR20240085473A (en) 2022-12-08 2024-06-17 송성민 Underground structure with top-down construction method using underground column wall and roof pipe structure, and construction method therefor

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200370135Y1 (en) 2004-09-09 2004-12-13 박무용 Forms for edge girder construction
KR20060107638A (en) * 2005-04-11 2006-10-16 (주)에스피에스 Supporting Structure of Underground Retaining Wall and Construction Method of Building Underground Wall Using the Same
KR100722198B1 (en) 2006-04-17 2007-05-29 (주) 씨엠파트너스 Reverse support structure of earth wall for continuous construction of underground plywood and continuous construction method of underground plywood applying the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200370135Y1 (en) 2004-09-09 2004-12-13 박무용 Forms for edge girder construction
KR20060107638A (en) * 2005-04-11 2006-10-16 (주)에스피에스 Supporting Structure of Underground Retaining Wall and Construction Method of Building Underground Wall Using the Same
KR100722198B1 (en) 2006-04-17 2007-05-29 (주) 씨엠파트너스 Reverse support structure of earth wall for continuous construction of underground plywood and continuous construction method of underground plywood applying the same

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101852016A (en) * 2010-06-11 2010-10-06 中国二十二冶集团有限公司 One-time installation of scaffolding construction method for super-long vertical reinforcement of underground wall
KR101034853B1 (en) 2010-06-22 2011-05-17 (주)씨엠파트너스건축사사무소 Reversal Construction Method of Underground Structures through Front Support of Retaining Walls and Uneven Surface Corresponding Forms
KR101046941B1 (en) 2011-03-14 2011-07-07 주식회사 하이드로코리아 Ramen Bridge Construction Method Excluding Hunts
KR101215764B1 (en) 2011-05-13 2013-01-09 삼성중공업 주식회사 A burial slab structure of an outer wall of an underground construction
KR101473218B1 (en) 2013-04-24 2014-12-16 황기수 A construction method of an underground structure
WO2015105230A1 (en) * 2014-01-13 2015-07-16 윤동현 Underground structure construction method using sump
KR101627708B1 (en) 2015-06-25 2016-06-07 주식회사 거원에코텍 Apparatus and method for closing an opening of building slab formed by the interference with the temporary structure
KR20170012017A (en) 2015-07-24 2017-02-02 (주)씨지스플랜 Edge girder for slurry wall
JP2017119968A (en) * 2015-12-28 2017-07-06 株式会社大林組 Evaluation method of piles made of soil cement column walls
KR101665909B1 (en) * 2016-02-19 2016-10-17 주식회사 세진이엔시 Composite wall structure of underground outer wall with cip retaining wall
CN106168035A (en) * 2016-08-17 2016-11-30 广州地铁设计研究院有限公司 The subassembly formula construction method of subassembly formula underground structure and underground structure
CN106522261A (en) * 2016-10-26 2017-03-22 国家电网公司 Reinforcing structure and method of double-cement tower in coal gob area
KR20190091397A (en) 2018-01-27 2019-08-06 양병진 Grouting method for joint portion of concrete structure in construction and top-down joint grouting method for underground structure using the same
CN109025260A (en) * 2018-07-26 2018-12-18 中民筑友科技投资有限公司 A kind of prefabricated floor slab back casting band joint structure and its construction method
KR20200114553A (en) * 2019-03-29 2020-10-07 유병훈 Underground structure with top-down construction method using underground column wall and construction method therefor
KR102210345B1 (en) * 2019-03-29 2021-02-01 유병훈 Underground structure with top-down construction method using underground column wall and construction method therefor
KR20210013888A (en) * 2019-07-29 2021-02-08 유병훈 Top-down construction method with underground utility
KR102292152B1 (en) 2019-07-29 2021-08-24 유병훈 Top-down construction method with underground utility
KR102156793B1 (en) 2019-12-24 2020-09-16 (주)동아엔지니어링 Top-down method for underground structure to prevent sinkhole
CN115387502A (en) * 2022-09-20 2022-11-25 中建三局集团有限公司 Same-layer construction system and construction method for assembled partition wall and main body structure
CN115387502B (en) * 2022-09-20 2023-12-22 中建三局集团有限公司 Same-layer construction system and construction method for assembled partition wall and main body structure
KR20240085473A (en) 2022-12-08 2024-06-17 송성민 Underground structure with top-down construction method using underground column wall and roof pipe structure, and construction method therefor
KR102579169B1 (en) * 2023-06-02 2023-09-14 홍승대 Top-down method using suspended rebar
KR102579166B1 (en) * 2023-06-02 2023-09-14 홍승대 Top-down Structures Using Suspended rebar
CN117905108A (en) * 2024-03-19 2024-04-19 福建一建集团有限公司 Construction method for building engineering reverse construction method of civil air defense in heavy-layer water-bearing sand layer
CN117905108B (en) * 2024-03-19 2024-05-28 福建一建集团有限公司 Construction method for building engineering reverse construction method of civil air defense in heavy-layer water-bearing sand layer

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR100927344B1 (en) Construction method for connecting underground structure and underground structure using connection structure for underground construction
KR101148272B1 (en) Downward Construction Method of Basement applying SCFSliding Channel Form
KR101344063B1 (en) The construction method of steel-concrete underpass
JP6855296B2 (en) Building foundation structure and its construction method
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR20090094971A (en) Under ground top-down method
TWM428973U (en) Building structure with stay-in-place mould
KR100938395B1 (en) Construction method of underground roadway using steel composite wall pile
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR100634726B1 (en) Slab construction structure of underground structure and slab and underground retaining wall construction method without frame rib
KR101230986B1 (en) Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR100640244B1 (en) Construction Method of Slab-Outer Wall Simultaneous Placement Using Basement File Without Edge Beam
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
JP7344721B2 (en) Roof structures and their construction methods
CN113294175A (en) Construction method of tunnel secondary lining structure and tunnel secondary lining structure
KR101483865B1 (en) Construction Method of Underground Structure using Composite Wale
KR200370135Y1 (en) Forms for edge girder construction
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
KR100351135B1 (en) Method of constructing arch ring of steel framed reinforced concrete arch bridge
KR100620366B1 (en) Construction method of underground structures including composite reinforced concrete beams
KR200385376Y1 (en) Form system for construction of underground slab
KR101028695B1 (en) PC beam connection structure combined with steel frame or steel pipe column in underground reverse drilling method

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20090710

PA0201 Request for examination
A302 Request for accelerated examination
PA0302 Request for accelerated examination

Patent event date: 20090717

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

Patent event date: 20090710

Patent event code: PA03021R01I

Comment text: Patent Application

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20091006

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20100114

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20100329

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20100330

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
FPAY Annual fee payment

Payment date: 20130326

Year of fee payment: 4

PR1001 Payment of annual fee

Payment date: 20130326

Start annual number: 4

End annual number: 4

FPAY Annual fee payment

Payment date: 20140326

Year of fee payment: 5

PR1001 Payment of annual fee

Payment date: 20140326

Start annual number: 5

End annual number: 5

FPAY Annual fee payment

Payment date: 20170321

Year of fee payment: 8

PR1001 Payment of annual fee

Payment date: 20170321

Start annual number: 8

End annual number: 8

FPAY Annual fee payment

Payment date: 20190328

Year of fee payment: 10

PR1001 Payment of annual fee

Payment date: 20190328

Start annual number: 10

End annual number: 10

FPAY Annual fee payment

Payment date: 20200305

Year of fee payment: 11

PR1001 Payment of annual fee

Payment date: 20200305

Start annual number: 11

End annual number: 11

PR1001 Payment of annual fee

Payment date: 20210329

Start annual number: 12

End annual number: 12

PR1001 Payment of annual fee

Payment date: 20220329

Start annual number: 13

End annual number: 13

PR1001 Payment of annual fee

Payment date: 20230329

Start annual number: 14

End annual number: 14

PR1001 Payment of annual fee

Payment date: 20240328

Start annual number: 15

End annual number: 15

PR1001 Payment of annual fee

Payment date: 20250331

Start annual number: 16

End annual number: 16