KR100951097B1 - Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket - Google Patents
Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket Download PDFInfo
- Publication number
- KR100951097B1 KR100951097B1 KR1020090062871A KR20090062871A KR100951097B1 KR 100951097 B1 KR100951097 B1 KR 100951097B1 KR 1020090062871 A KR1020090062871 A KR 1020090062871A KR 20090062871 A KR20090062871 A KR 20090062871A KR 100951097 B1 KR100951097 B1 KR 100951097B1
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- reinforcement
- wall
- construction
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
- E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/61—Connections for building structures in general of slab-shaped building elements with each other
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/04—Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/388—Separate connecting elements
- E04B2001/389—Brackets
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- Geology (AREA)
- Geochemistry & Mineralogy (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본 발명은 지하구조물의 각 층 슬래브를 시공한 뒤 흙막이벽에 접하는 지하외벽을 구축하여 합벽으로 시공하는 과정에서, 상기 지하외벽 내에 매립되는 슬래브 부분, 즉 매입슬래브 영역에 상하로 관통하는 개구부를 형성하기 위한 거푸집 역할을 하면서 하중 지지를 위한 영구 구조체의 역할을 동시에 수행할 수 있는 스틸 웨일(wale) 구조체를 설치하여 슬래브를 시공하고, 전 층의 슬래브를 시공한 상태에서 상기 스틸 웨일 구조체에 의해 형성된 개구부를 지하외벽의 수직철근 층간 배근과 콘크리트 타설용 통로로 사용하여 합벽을 층간 연속적으로 순타 시공하는 지하구조물의 슬래브 및 합벽 시공 방법과 이 시공 방법으로 구축한 슬래브 및 합벽 구조물, 그리고 슬래브 및 합벽 시공용 브라켓에 관한 것이다.According to the present invention, after constructing each layer slab of the underground structure, the outer outer wall contacting the earthquake wall is constructed to construct a plywood wall, and the opening portion penetrates up and down in the slab portion embedded in the underground outer wall, that is, the buried slab area. The slab is constructed by installing a steel wale structure that can simultaneously serve as a formwork for supporting loads and a permanent structure for supporting a load, and is formed by the steel wale structure in a state in which slabs of all layers are constructed. Construction method of slab and plywood of underground structures for continuous plying of plywood walls using openings as vertical reinforcement for floor reinforcement and concrete placing passage, slab and plywood structures constructed by this construction method, and slab and plywood construction It is about a dragon bracket.
이러한 본 발명에 의하면, 기존 테두리보가 삭제되면서 테두리보 설치에 따른 문제점이 해소될 수 있으며, 특히 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있으면서도 상기 스틸 웨일 구조체가 하중을 지지하게 되면서 매입슬래브를 포함한 슬래브 전체의 강성이 극대화되는 장점이 있는 한편, 지하외벽에 의해 매립되는 슬래브 부분인 매입슬래브의 내부에 영구구조물로서 매입되는 매입형 RC보 철근틀을 마련하여 양생 후 매입형 RC보 철근틀이 데크슬래브를 지지할 수 있도록 함으로써, 수평방향 및 수직방향의 원활한 하중 전달 시스템을 구현할 수 있고, 따라서 슬래브 및 합벽의 구조적인 안전성을 확보할 수 있는 장점이 있다. According to the present invention, the problem of the installation of the edge beam can be solved by eliminating the existing edge beam, in particular, the continuous reinforcement between the vertical reinforcement of the vertical reinforcement of the basement outer wall and the interlayer continuous casting of concrete can be smoothly performed using the steel As the wale structure supports the load, the stiffness of the entire slab including the buried slab is maximized, while the embedded RC beam reinforcement frame which is embedded as a permanent structure inside the buried slab, which is the slab part embedded by the basement outer wall, is used. After the curing, the embedded RC beam rebar supports the deck slab, so that a smooth load transmission system in the horizontal and vertical directions can be realized, thus securing the structural safety of the slab and the plywood wall. have.
Description
본 발명은 지하구조물의 슬래브 및 합벽 구조물과 시공 방법에 관한 것으로서, 더욱 상세하게는 지하구조물의 층간 슬래브를 시공한 후 흙막이벽에 접하는 지하 외벽을 구축하여 합벽으로 시공하는 방법과 이 시공 방법에 의해 구축되는 슬래브 및 합벽 구조물과 받침브라켓에 관한 것이다.The present invention relates to a slab, a plywood structure and a construction method of an underground structure, and more particularly, after constructing an interlayer slab of an underground structure, constructing an underground outer wall in contact with an earthquake wall and constructing it as a plywood wall and by this construction method. The present invention relates to a slab and plywood structure and a supporting bracket to be constructed.
일반적으로 지하구조물을 구축하는 방법에는 두 가지가 있다.In general, there are two ways to build underground structures.
지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고 토사를 전부 반출한 뒤 맨 아래층부터 구조물을 축조해 올라가는 순타설공법과, 흙막이를 시공하고 1층 구조물을 축조한 다음 그 구조물을 흙막이용 버팀부재로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 역타설 공법이 그것이다.After constructing the earthquake on the ground where the underground structure is constructed, install the temporary facility to support the earthquake while excavating the ground, take out all the earth and sand, and build the structure from the bottom floor, After the construction of the first-floor structure, using the structure as a retaining member for the earthquake, the reverse casting method is to construct the structure while drilling the ground from the top to the bottom.
최근 토지 이용의 극대화 차원에서 지하공사가 점차 고심도화되고 있고, 특히 순타설공법에 의한 시공시에는 흙막이 붕괴의 위험이나 주변 건물들 침하 등으로 인한 균열 발생은 물론, 시각적으로도 불안할 뿐만 아니라 공사기간이 길어지는 등 여러 문제가 있어서, 근래에는 역타설 공법이 널리 적용되고 있다.In recent years, underground construction has been increasingly intensified in order to maximize land use. In particular, when the construction is carried out by the net pouring method, not only the construction of cracks due to the risk of earthquake collapse or the settlement of nearby buildings, but also visually unstable construction Due to various problems such as long periods of time, the reverse casting method has been widely applied in recent years.
상기 역타설 공법은 지하구조물 축조시에 지상 1층부터 단계적으로 시공해 내려가는 방식이므로, 지하구조물과 지상구조물의 시공을 동시에 진행할 수 있고, 지상 1층의 바닥을 작업장으로 활용할 수 있어 별도의 복공판이 필요하지 않은 장점이 있다.The reverse casting method is a method of constructing the ground structure from the ground floor step by step when constructing the underground structure, so that the construction of the underground structure and the ground structure can be carried out at the same time, and the floor of the ground floor can be used as a workshop so that a separate perforated plate is provided. There is an advantage that is not necessary.
이러한 역타설 공법으로는 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(Concrete on grade)과, 지반을 어느 정도 굴착하고 지반을 고른 뒤 동바리를 세우고 거푸집을 설치하여 콘크리트를 타설하는 방법(Form on supporting)과, 거푸집 지지를 위한 동바리를 세우지 않는 대신에 선(先) 시공한 상층의 콘크리트 슬래브에 거푸집 지지를 위한 거푸집 지지거더를 현수시켜 콘크리트를 타설하는 방법(무지보 역타설 현수 거푸집 공법) 등이 있다.Such a reverse casting method involves placing concrete slabs and beams on the ground while the ground is stopped (concrete on grade), and excavating the ground to some extent, picking the ground, placing the clubs and installing the formwork, and placing the concrete. (Form on supporting) and the method of placing concrete by suspending form support girder for form support on the upper concrete slab which is pre-constructed instead of erecting a circle for supporting form (unsupported reversal suspension form Construction method).
또한, 최근 널리 사용되고 있는 방법으로, 거푸집 지지거더(이는 H-형강 철골보로서 영구 구조체로 사용되거나, 가설 구조체로서 시공 후에 해체함)를 골조용 기둥에 해체 가능한 이동식 조립 브라켓을 이용하여 지지시키고, 상기 지지거더를 이용하여 층간 슬래브 및 보 시공을 위한 거푸집을 지지시켜 설치한 뒤 슬래브 및 보 콘크리트를 타설하는 방식이 있다.In addition, as a method widely used in recent years, formwork girders (which are used as permanent structures as H-beam steel beams or dismantled after construction as construction structures) are supported by using a movable assembly bracket which can be disassembled to a frame pillar, and There is a method of placing slab and beam concrete after supporting and installing formwork for interlayer slab and beam construction by using support girder.
한편, 역타설 시공시에는 통상적으로 흙막이벽과 각 층 슬래브가 만나는 외 곽 경계부분에 띠장 또는 접합거더 역할을 하는 철근 콘크리트 테두리보(perimeter beam)가 설치되고, 모든 지하층의 슬래브 시공이 끝난 뒤에는 맨 아래층부터 위층으로 올라가면서 흙막이벽 안쪽에 지하외벽을 순타 시공하여 지하합벽을 완성하게 된다.On the other hand, reinforcement construction is usually provided with a reinforced concrete perimeter beam that acts as a strip or a joining girder at the outer boundary where the earth wall and the slab meet each other. Going upstairs from the lower floor, the underground outer wall is smoothly constructed inside the retaining wall to complete the underground plywood.
여기서, 종래기술에 따른 지하층의 슬래브 및 테두리보 시공을 위한 거푸집 구성 및 작업에 대하여 첨부한 도면을 참조하여 설명하면 다음과 같다.Here, with reference to the accompanying drawings for the formwork and work for the slab and rim beam construction of the basement layer according to the prior art as follows.
첨부한 도 1은 종래 슬래브 및 테두리보의 시공을 위한 거푸집 구조체의 설치상태를 보여주는 단면도로서, 거푸집 설치상태에서 콘크리트의 양생 중 상태를 나타내고, 도 2는 종래 슬래브 및 테두리보의 시공이 완료된 상태를 보여주는 단면도로서, 콘크리트의 양생 후에 거푸집을 해체한 상태를 나타낸다. 1 is a cross-sectional view showing the installation state of the formwork for the construction of the conventional slab and rim beam, showing the state of curing of the concrete in the formwork installation state, Figure 2 shows the state of the construction of the conventional slab and rim beam is completed The cross-sectional view shows a state in which the formwork is dismantled after curing of concrete.
이들 도면은 데크 플레이트(deck plate) 지지를 위한 지지거더 설치된 위치에서의 단면도이다.These figures are sectional views in the position where the support girders are installed for supporting the deck plate.
도 1에서 도면부호 2는 흙막이벽 내에 수직 시공된 엄지말뚝, 즉 수직 강재빔인 H-파일(pile)을 나타낸다.In FIG. 1,
보통 흙막이벽(1)의 형식으로는 주열식 벽으로서 SCW(Soil Cement Wall)와 CIP(Cast In-Place Pile)가 있고, 이들은 엄지말뚝으로서 통상 H-파일(2)을 사용하고 있으며, 이 H-파일(2)이 배면의 토압 및 수압을 직접 지지하는 수직 휨부재로서의 역할을 하게 된다.Usually, there are two types of soil walls (Soil Cement Wall) and CIP (Cast In-Place Pile) as main heating walls, and they usually use H-pile (2) as thumb pile. The
테두리보(17)의 시공을 위하여 종래에는 흙막이벽(1)을 시공한 뒤 굴토작업을 먼저 하고, 버림 콘크리트(3)를 타설한 뒤 동바리(4)를 설치하여 거푸집을 지지 시키게 된다.For the construction of the
여기서, 시공하고자 하는 테두리보(17)의 길이방향에 대하여 그 횡방향으로 길게 배치되는 각재(5)를 복수개의 동바리(4)로 지지시키고, 이 각재(5) 위에는 테두리보 하면 성형을 위한 합판 거푸집(6)을 수평으로 배치하여 지지시키며, 이 수평의 합판 거푸집, 즉 거푸집 하판(6) 위로는 테두리보 측면 성형을 위한 합판 거푸집(미도시)을 수직으로 고정 배치하여 지지시킨다.Here, the lumber 5 which is arranged long in the transverse direction with respect to the longitudinal direction of the
또한, 슬래브 구축용 구조체로서 도면부호 7은 철골보 구조물인 지지거더를 나타내고, 도면부호 15는 지지거더(7)에 의해 지지되는 데크 플레이트를 나타낸다.In addition, as the slab construction structure,
상기 지지거더(7)로는 통상 H-형강이 사용되고, 그 일단부가 동바리(4) 및 거푸집 하판(6) 등에 의해 지지되며, 일단부 끝단에는 임베디드 플레이트(embedded plate)(8)가 용접 및/또는 고정 브라켓(9a)과 체결부재(9b)에 의해 수직으로 결합된다.As the
그리고, 도 1은 지지거더(7)가 설치되는 위치에서의 종방향 단면도이기 때문에 테두리보 측면 성형을 위한 합판 거푸집, 즉 거푸집 옆판이 미도시되었으나, 이 거푸집 옆판은 시공하고자 하는 테두리보(17)의 길이방향을 따라서 임베디드 플레이트(8)의 양 측방으로 길게 설치되며, 이는 각 지지거더(7) 끝단의 임베디드 플레이트(8)와 함께 테두리보 성형공간의 측면을 이루게 된다.And, Figure 1 is a longitudinal cross-sectional view at the position where the support girder (7) is installed, plywood formwork for forming the side beams, that is, the formwork side plate is not shown, this formwork side plate is the
또한, 테두리보용 콘크리트가 타설되는 성형공간, 즉 H-파일(2)을 포함한 흙막이벽(1), 거푸집 하판(6), 임베디드 플레이트(8) 및 미도시된 거푸집 옆판이 형성하는 사각 단면형상의 테두리보 성형공간 내에는 길이방향의 철근(11) 및 스터럽 철근(12)을 설치함과 더불어 지하합벽 공간 내 매립되는 수직철근(19)을 상하로 연결하여 설치하는 배근작업을 하고, 테두리보 성형공간 내에서 흙막이벽(1)에 내장된 H-파일(2)의 플랜지면에는 벽의 일부를 제거한 후 전단연결부재인 스터드(13)가 용접 시공된다.In addition, the square space of the cross-section formed by the molding space in which the frame for the concrete is poured, that is, the retaining wall (1), the formwork lower plate (6), the embedded plate (8) and the formwork side plate not shown In the frame beam forming space, the reinforcing
또한, 테두리보 성형공간 내에서 상기 임베디드 플레이드(8)에도 전단연결부재인 스터드(14)가 용접 시공되는데, 이와 같이 설치되는 스터드(13,14)는 테두리보 콘크리트 속에 매립되는 바, 이들은 H-파일(2)과 테두리보(17) 간, 그리고 테두리보(17)와 임베디드 플레이트(8) 간 상호 결착력을 증대시키기 위하여 시공되는 것들이다.In addition, the
이와 같이, 슬래브(16) 및 테두리보(17) 시공을 위한 거푸집 등 구조체를 모두 설치하고 나면, 슬래브 및 보 콘크리트 타설시에 상기 테두리보 성형공간 내에 콘크리트를 함께 타설하여 테두리보(17)를 성형한다.As such, after installing all the structures such as the formwork for the construction of the slab (16) and the rim beam (17), when the slab and beam concrete is poured, the concrete is poured together in the rim beam forming space to form the rim beam (17) do.
그리고, 콘크리트가 양생되고 나면, 동바리(4) 및 각재(5), 합판 거푸집(거푸집 하판 및 옆판)(6) 등은 해체하고, 철골보인 지지거더(7) 및 임베디드 플레이트(8) 등은 영구 구조체로 사용하게 된다.Then, after the concrete is cured, the copper bar (4) and the lumber (5), plywood formwork (form lower plate and side plate) (6), etc. are dismantled, the steel girders support girder (7) and embedded plate (8) is permanent It will be used as a structure.
이후 하층으로 내려가면서 각 층에 대해 상기와 같은 작업을 반복하여 층간 슬래브 및 각 층 슬래브와 흙막이벽을 접합시켜주는 테두리보를 단계적으로 시공하게 되며, 모든 지하층에 대하여 층간 슬래브 및 테두리보의 역타 시공이 완료되면, 지하외벽 거푸집 설치 및 콘크리트 시공을 하여 테두리보가 드러나지 않도록 합벽(옹벽) 순타 시공을 하게 된다. After going down to the lower floor, the above operation is repeated for each floor, and the girder beam connecting the interlayer slab and each layer slab and the earthen wall is constructed step by step, and the reverse construction of the interlayer slab and the rim beam is performed for all basement floors. Upon completion, the base wall wall formwork is installed and concrete construction, and the plywood (retaining wall) netting construction is performed so that the rim beam is not exposed.
이때의 순타 시공은 아래층부터 위층의 순으로 시공을 하게 된다.The net construction at this time is to be constructed in the order of the lower floor to the upper floor.
통상적으로 지하합벽은 층간 슬래브와 테두리보가 시공되고 나면 이후 흙막이벽 내측면에 외벽 시공용 거푸집을 설치한 뒤 이 거푸집 내부에 콘크리트를 타설하여, 테두리보가 매립되도록 흙막이벽과 외벽을 합벽 시공하여 완성되는데, 이러한 지하합벽의 시공은 층간 슬래브 및 테두리보의 시공 후 아래층으로부터 위층으로 올라가면서 외벽을 시공하는 순타 시공의 방식으로 작업이 이루어진다.Normally, the basement cladding is completed after the interlayer slab and the rim beam are installed, and then install the formwork for exterior wall construction on the inner side of the retaining wall, and then cast concrete inside the formwork to finish the construction of the cladding wall and the outer wall so that the rim beam is embedded. In addition, the construction of the underground plywood is carried out in the manner of the netting construction of the outer wall while going up from the lower floor to the upper floor after the construction of the interlayer slab and the rim beam.
첨부한 도 3은 지하합벽의 순타 시공이 이루어지는 상태의 예를 도시한 단면도로서, 이는 지지거더가 설치되지 않은 위치, 즉 지지거더와 지지거더 사이의 중간위치에서 취한 단면도이다.FIG. 3 is a cross-sectional view showing an example of a smooth construction of the underground plywood, which is a cross-sectional view taken at a position where the support girder is not installed, that is, an intermediate position between the support girder and the support girder.
슬래브(16)와 테두리보(17)의 시공이 완료된 후 흙막이벽(1) 내측으로 외벽 시공용 거푸집(미도시)을 설치하고, 이 거푸집 공간에 콘크리트를 타설하여 외벽(18)을 시공하는 방식으로 지하합벽의 시공작업이 이루어진다.After the construction of the
한편, 지하구조물의 슬래브 및 합벽을 시공하는 과정에 있어서, 도 1 및 도 2, 그리고 도 3에 도시한 종래기술에 따르면 다음과 같은 문제점이 있다.On the other hand, in the process of constructing the slab and plywood of the underground structure, according to the prior art shown in Figures 1 and 2, and 3 has the following problems.
테두리보 시공에 따른 문제점으로서, 위에서 설명한 바와 같이 일반 합판 거푸집(6)과 동바리(4)를 이용함으로써, 동바리 설치에 따른 토공작업 지연과 콘크리트 타설시 가끔 거푸집 파괴 등에 의해 작업 차질이 많이 발생하고, 거푸집 설치가 복잡하여 시공성 저하 및 원가 증대의 문제가 발생한다. As a problem due to the construction of the rim beam, as described above, by using the general plywood formwork (6) and the copper barrier (4), a lot of work disruptions occur due to delayed earthwork work due to the installation of the copper bar and occasional formwork destruction during concrete pouring, The formwork is complicated to install, which leads to problems of poor workability and cost increase.
특히, 동바리(4)의 이용시에는 연약 지반상에서의 지지가 불안정하고, 또한 콘크리트의 강도가 일정 이상으로 보양되지 않으면 해체가 불가하기 때문에 콘크리 트 양생 중 동바리의 존치로 인해 아래층의 굴토공사가 진행되지 못하여 공기가 지연될 수 밖에 없는 문제가 있다.In particular, when the
더구나, 동바리 등 가설자재는 역타설 시공시 굴토작업장 외부로 반출한 뒤 굴토 후 다시 아래층으로 이동하여 설치해야 하고, 이를 각 층의 시공시마다 반복해야 하는 바, 이러한 작업을 반복 수행하는데 있어서 번잡한 문제점이 있다.In addition, temporary materials such as dongbari should be moved to the lower floor after the excavation after installation to the outside of the gulto workshop during the construction of reverse casting, and this should be repeated for the construction of each floor. There is this.
또한, 동바리의 소운반 및 재조립에 소요되는 비용과 시간이 과다하여 비경제적일 뿐만 아니라, 모든 작업이 인력에 의존하는 노동집약적이기 때문에 기능공의 인력 부족이 점차 심화되는 현실에서 동바리의 사용은 원가 절감을 어렵게 한다.In addition, the cost and time required for transporting and reassembling the club are not only economically unfavorable, but also the labor-intensive labor shortage of all workers makes the use of copper club cost-effective. Makes it difficult.
그리고, 테두리보 시공으로 거푸집 작업을 위한 목공작업이 중간 중간에 실시되어야 하는 문제점도 있다.In addition, there is a problem that the woodworking work for the formwork by the rim beam construction should be carried out in the middle.
특히, 슬래브 시공을 위해 데크 플레이트(15)를 설치하여 데크 슬래브(deck slab)(16)를 시공하고 있는데 반하여, 테두리보 시공시에는 거푸집 작업을 위해 목재로 된 합판 거푸집의 작업이 필요하므로 목공작업 인원이 단속적으로 투입되어야 한다.In particular, the deck slab (16) is installed by installing the deck plate (15) for the slab construction, while the rim beam construction requires the work of wood plywood formwork for formwork work, so woodworking work Personnel should be intermittent.
이와 같이, 철공공 외에 목공작업공의 이질공종 인력이 투입됨으로써 공사원가가 상승함은 물론 인력 투입의 효율성이 크게 떨어지는 문제점을 가진다.As such, the work cost increases as well as the labor cost of the woodworker in addition to the ironworker, as well as the efficiency of manpower input has a problem that is greatly reduced.
또한, 테두리보 시공에 따른 스터럽 및 보강 철근량의 과다 소요, 연결철근의 사용량 과다로 인한 재료 낭비의 문제점이 있고, 테두리보 철근 배근을 위한 철근 가공 및 조립이 복잡할 뿐만 아니라, 배근 설치를 위한 조립시간이 필요하여 공 기 지연 및 공사비 증대의 요인이 되고 있다.In addition, there is a problem of excessive waste of stirrups and reinforcing bars according to the construction of the rim beams, waste of materials due to excessive use of connecting bars, and complicated reinforcing and assembly of reinforcing bars for rim reinforcement. Time is required, causing air delays and increasing construction costs.
또한, 슬래브(16)가 선 시공되고 외벽(18)이 후 시공됨에 따라서 테두리보(17)의 상,하면과 외벽(18) 간에는 접합면이 발생하는 바, 이 접합면에서의 누수가 문제점으로 지적되고 있으며, 이러한 누수문제를 해결하기 위해서는 시공 후 접합면 간에 에폭시를 주입해야 하는 보수작업이 필요하다. In addition, as the
상기한 종래 테두리보 시공의 문제점을 해결하기 위하여, 테두리보를 최소화하거나 아예 생략하는 다양한 시공 기술들이 본 발명자에 의해 고안 또는 발명된 바 있다(실용신안등록 제370107호, 실용신안등록 제370135호, 실용신안등록 제381303호, 실용신안등록 제385376호, 특허등록 제634726호).In order to solve the problems of the conventional rim beam construction, various construction techniques that minimize or omit the rim beam has been devised or invented by the present inventors (Utility Model Registration No. 370107, Utility Model Registration No. 370135, Utility Registered Model No. 381303, Registered Utility Model No. 385376, Registered Patent No. 634726).
상기의 기술에서는 테두리보를 최소화하여 테두리보 시공에 소요되는 철근 및 거푸집 물량을 최소화하고 공기를 단축하는 한편 기존 테두리보 시공에 따른 문제점을 해결하였다. The above technique minimizes the edge beams, minimizes the amount of rebar and formwork required for the construction of the edge beams, shortens the air, and solves the problems caused by the existing edge beam constructions.
또는 층간 슬래브를 흙막이벽에 바로 연결 시공하여 테두리보를 아예 삭제함으로써 종래 테두리보 시공에 따른 문제점을 해결하였다.Or by connecting the interlayer slab directly to the wall of the barrier to solve the problem of the conventional rim beam construction by eliminating the rim beam at all.
한편, 테두리보를 시공하거나 테두리보가 생략된 지하구조물의 역타 시공 과정에서는 테두리보나 슬래브(테두리보가 생략된 경우) 사이의 나머지 상하부 합벽 부분을 나중에 시공한다.On the other hand, in the construction of the reverse beam construction of the rim beam or the underground structure without the rim beam, the remaining upper and lower plywood parts between the rim beam or the slab (when the rim beam is omitted) are later constructed.
즉, 흙막이벽을 지지하도록 각 층의 층간 수평구조체인 슬래브 및 테두리보(생략될 수 있음)를 우선 시공한 뒤 흙막이벽과 일체로 외벽을 구축하여 합벽으로 시공하게 되는 것이다.That is, the slab and the rim beam (which may be omitted), which are the interlayer horizontal structures of each layer, are first constructed to support the wall, and then the outer wall is integrally formed with the wall to construct the plywood wall.
이때, 슬래브 또는 테두리보를 흙막이벽에 직접 정착되도록 선 시공하여 토압 등 외력을 지지케 하고, 외벽을 후 시공하여 슬래브 또는 테두리보를 외벽에 매립시키는 방법으로 합벽 시공이 이루어지는 바, 외벽의 후 시공을 위해서는 선 시공된 슬래브나 테두리보에 콘크리트 타설용 슬리브(sleeve)가 반드시 설치되어야 하며, 나아가 외벽 주철근의 층간 연속 배근의 어려움이 있으므로 상하층의 외벽을 일체화하기 위한 별도의 다월 철근(dowel bar)를 설치해야 한다.At this time, the slab or rim beam is pre-installed to be settled directly to the retaining wall to support external force such as earth pressure, and after the outer wall is installed, the plywood is constructed by embedding the slab or rim beam on the outer wall. A concrete sleeve must be installed on the pre-installed slab or rim beam, and additional dowel bars are installed to integrate the outer walls of the upper and lower layers because of the difficulty of continuous reinforcement between the layers of the outer reinforcing bars. Should be.
상기 슬리브는 외벽에 매립되는 슬래브 부분(이하, '매입슬래브'라 함) 또는 테두리보를 상하로 관통하는 통로가 되는 것으로서, 슬래브, 테두리보의 시공시 매입슬래브 또는 테두리보 영역에 슬리브 형성을 위한 충전 파이프를 미리 수직으로 내설하고 이후 그 외측으로만 콘크리트를 타설하여, 콘크리트가 타설되지 않은 충전 파이프의 내부공간에 의해 상하로 관통하는 슬리브가 형성되도록 한다.The sleeve is a passage for vertically penetrating the slab portion (hereinafter referred to as 'buried slab') or the rim beam embedded in the outer wall, the filling for forming the sleeve in the embedded slab or rim beam area during the construction of the slab, rim beam The pipe is pre-verted vertically and then concrete is poured outward so that the sleeve penetrates up and down by the inner space of the filling pipe where the concrete is not poured.
그러나, 합벽 시공시 슬리브를 통한 콘크리트의 타설은 그 시공 자체가 어려울 뿐만 아니라 콘크리트가 밀실하게 채워지는 것을 어렵게 하여 매입슬래브나 테두리보 저면에 콘크리트의 건조 수축에 의한 역타조인트(지하외벽의 층간 틈)를 발생시키며, 이러한 역타조인트는 건축물의 누수에 의한 구조적인 성능을 저하시키는 원인으로 작용하게 된다. However, in the construction of plywood walls, the casting of concrete through the sleeve is not only difficult for the construction itself but also makes it difficult for the concrete to be filled tightly. This reverse oscillation joint acts as a cause of deteriorating structural performance due to leakage of the building.
역타조인트를 통하여 지하수의 유입이 이루어지면, 유입된 지하수는 철근의 부식, 콘크리트 열화현상을 일으키고, 그 결과로 구조물의 내구성이 떨어지게 된다. When the groundwater is introduced through the inverted joint, the inflowed groundwater causes corrosion of the reinforcing steel and deterioration of the concrete, resulting in poor durability of the structure.
따라서, 테두리보가 시공되든 시공되지 않든 간에 기존 슬리브와 같은 지하 합벽 콘크리트 타설용 구조는 좀더 개선될 필요가 있는 것이다.Therefore, whether the rim beam is constructed or not, the underground plywood concrete placing structure such as the existing sleeve needs to be further improved.
이에 본 발명자는, 앞에서 설명한 모든 문제점이 해소될 수 있는 기술로서, 동바리의 사용이 불필요하고 또한 테두리보가 삭제될 수 있으며 지하외벽 콘크리트 타설을 위한 별도 슬리브 시공이 필요 없는 기술을 특허등록 제634726호를 통해 제시한 바 있다.Therefore, the present inventors, as a technology that can solve all the problems described above, the use of the copper bar and the edge beam can be eliminated, and the technology that does not need a separate sleeve construction for concrete laying underground walls outside the patent registration No. 634726 It was suggested through.
여기서는 테두리보의 삭제 및 슬리브 시공의 생략을 위해서 흙막이벽과 슬래브 공간 사이에 복수개의 그레이팅 지지틀을 연속되게 설치하는 기술이 제시되어 있다. In this case, a technique for continuously installing a plurality of grating support frames between the retaining wall and the slab space is proposed for eliminating the rim beam and eliminating the sleeve construction.
그러나, 상기와 같이 그레이팅 지지틀을 설치하는 방법에서는 다음과 같은 문제점이 있었다.However, the method of installing the grating support frame as described above had the following problems.
우선, 공장 가공된 그레이팅 지지틀을 현장에서 흙막이벽과 슬래브 공간 사이, 즉 매입슬래브 영역에 설치하도록 되어 있으나, 그레이팅 지지틀을 실제 설치함에 있어서 그 크기와 부피가 매우 크므로 설치에 많은 어려움이 있다.First of all, the factory-worked grating support frame is installed in the field between the earthquake wall and the slab space, that is, the buried slab area. However, the size and volume of the grating support frame is very large, so the installation is difficult. .
실제 설치하는 과정에서 두 사람이 그레이팅 지지틀을 손으로 잡고 정 위치에 설치하게 되는데, 그 부피와 무게가 두 사람이 작업하기에 어려움이 있으므로 실제 시공시 더욱 많은 인력이 소요될 수 있고, 인건비 및 작업시간의 과다 소요, 작업능률 저하 등 여전히 개선해야 할 몇 가지 문제가 있는 것이 사실이다. In the actual installation process, two people hold the grating support frame by hand and install it in the right position. Since the volume and weight are difficult for two people to work, it may require more manpower during actual construction, labor costs and work. It is true that there are still some problems that need to be improved, such as excessive time and poor work efficiency.
또한, 그레이팅 지지틀을 매입슬래브 영역을 따라 연속되게 설치하므로 많은 철재 물량(그레이팅 지지틀 제작에 소요되는 물량 및 그레이팅 지지틀의 사용 개수에 따른 물량)이 소요되고, 이는 곧 공사비 과다의 원인이 되어 왔다.In addition, since the grating support frame is continuously installed along the buried slab area, a large amount of steel (amount required for manufacturing the grating support frame and the number of grating support frames used) is required, which causes excessive construction cost. come.
아울러, 그레이팅 지지틀이 지하외벽 두께, 즉 외벽 폭의 전체 구간에 걸쳐 설치되기 때문에 중량 과다, 경제성 저하의 문제를 가중시킨다. In addition, since the grating support frame is installed over the entire section of the outer wall thickness, that is, the outer wall width, the grating support frame adds to the problem of overweight and deterioration of economic efficiency.
또한, 규격화하여 공장 제작한 크기의 큰 그레이팅 지지틀을 현장에서 전 구간을 따라 서로 연속되게 붙여서 설치하는 것이기 때문에, 건축물의 모서리 부분에서는 설치가 불가능하다. In addition, it is impossible to install in the corner portion of the building because it is installed by attaching a large grating support frame of the size standardized and factory manufactured in succession along the entire section in the field.
따라서, 모서리 부분에서는 별도 방법을 고려해야 하며, 필요에 따라서는 공장 제작된 그레이팅 지지틀을 현장에서 절단 가공하여 사용하는 것이 필요하다.Therefore, a separate method should be considered in the corner portion, and if necessary, it is necessary to cut and use the factory-made grating support frame in the field.
이로 인한 작업의 어려움, 작업능률의 저하, 자재 손실 등이 문제점으로 지적될 수 있다.This can be pointed out as a problem due to the difficulty of work, deterioration of work efficiency, material loss.
또한, 그레이팅 지지틀을 구성하는 플레이트가 평판 형태이므로 단면 효율 저하 및 경제성 저하의 문제가 있다. In addition, since the plate constituting the grating support frame is in the form of a flat plate, there is a problem of lowering cross-sectional efficiency and lowering economic efficiency.
다음으로, 동바리의 사용이 불필요하고 또한 테두리보가 삭제될 수 있으며 지하외벽 콘크리트 타설을 위한 별도 슬리브 시공이 필요없는 또 다른 방식의 기술이 특허등록 제722198호에 개시되어 있다.Next, another type of technology is disclosed in Patent No.722198, which does not require the use of a copper bar and can remove the rim beam, and does not require a separate sleeve construction for placing an underground outer wall concrete.
이는 건축물 지하의 층간 슬래브가 흙막이벽을 지지하도록 시공되는 지하 흙막이벽의 지지구조에서 흙막이벽에 접하면서 지하외벽에 매립되는 매입슬래브에 개구부가 형성되도록 매입거푸집을 설치한 뒤 지하외벽 밖으로 노출되는 노출슬래브 두께 이상으로 콘크리트를 타설하여 개구부를 형성시키는 방식이다.This is because the exposed formwork is formed so that openings are formed in the embedded slab buried in the basement outer wall while the interlayer slab in the building is constructed to support the retaining wall. It is a method of forming the opening by pouring concrete more than the slab thickness.
이러한 시공 방식에서는 슬래브 콘크리트 타설 후 매입거푸집에 의해 매입슬래브에 상하로 관통하는 개구부가 성형되므로, 이 개구부에 의해 지하외벽의 시공 을 연속적으로 용이하게 진행할 수 있는 장점이 있다.In this construction method, since the openings penetrating up and down the embedded slab are formed by embedding dies after slab concrete is poured, there is an advantage that the construction of the basement outer wall can be easily proceeded by the openings.
그러나, 이 방식에서는 다음과 같은 치명적인 단점이 있다.However, this method has the following fatal disadvantages.
첨부한 도 4 및 도 5는 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 4는 개방형 판재 구조의 매입거푸집을 사용하여 시공한 평면도이고, 도 5는 도 4의 선 'A-A'를 따라 취한 단면도이다. 4 and 5 are views for explaining the problems according to the prior art, Figure 4 is a plan view using a built-in formwork of the open plate structure, Figure 5 is a line 'A-A' of Figure 4 It is a cross section taken along.
도 3에 도시한 바와 같이, 시공된 철근 콘크리트 슬래브(S)는 흙막이벽(100)에 접하면서 지하외벽(111)에 매립되는 부분인 매입슬래브(S1)와 지하외벽 밖으로 노출되는 부분인 노출슬래브(S2)로 구분되고, 매입거푸집(121)이 매입슬래브 영역에서 소정 간격으로 배치되어 슬래브 콘크리트 타설 후에는 개구부(OP)를 형성하게 된다. As shown in FIG. 3, the constructed reinforced concrete slab S is a buried slab S1 which is a portion embedded in the basement
또한, 슬래브(S)의 시공이 완료되면 매입슬래브(S1)에 형성된 개구부(OP)를 이용하여 합벽 시공이 진행된다. In addition, when the construction of the slab (S) is completed, the construction of the plywood wall proceeds using the opening OP formed in the embedded slab S1.
일단, 테두리보가 생략되므로 테두리보 시공에 따른 문제점이 해결되고 동바리를 사용하지 않으므로 동바리 사용에 따른 문제점이 해결되나, 매입거푸집(121)에 의해 형성된 개구부(OP)가 매입슬래브를 상하로 관통하는 종래의 슬리브와 비교할 때 그 형상을 원형에서 그 외 다양한 각형(나비형 개구부를 예로 개시하고 있음)으로 변경한 점에 불과하다. Once, the edge beam is omitted, so the problem caused by the construction of the edge beam is solved and the problem of the use of the copper bar is solved since the copper bar is not used, but the opening OP formed by the embedding
즉, 매입거푸집(121)을 사용하여 기존 슬리브의 단면적을 원형에서 개시된 바의 각형으로 변경 및 확대하고, 각형의 매입거푸집에 의해 형성되는 확대된 개구부(OP)를 통하여, 지하외벽(111) 내 안팎으로 매립되는 수직철근(112,113)의 층간 연속 배근과 콘크리트 층간 연속 타설을 기존 원형의 슬리브 사용시에 비해 좀더 원활히 시행할 수 있도록 한 것에 지나지 않는다.That is, using the embedding
이러한 구조는 지하외벽(111)의 콘크리트 연속 타설 및 콘크리트의 밀실 충전이 가능하다는 점에서 소기의 효과는 있다 할 수 있으나, 무엇보다 매입슬래브(S1)에 개구부(OP)라는 빈공간, 즉 종래에 비해 보다 확대된 상하 관통 통로가 형성됨으로 인하여, 매입슬래브(S1)의 구조 내력 측면에서는 매우 취약해지는 치명적인 단점이 있게 된다.Such a structure may have a desired effect in that concrete continuous pouring of the basement
특히, 상기 매입거푸집(121)은 평판으로 제작되는 비구조재(개방형 판재 구조의 단순 거푸집)이며, 단순히 개구부(OP)를 성형하기 위한 거푸집에 지나지 않으므로 흙막이벽(100)으로부터 슬래브(S)로의 토압 전달, 토압 지지, 측압 지지, 축력 지지 등의 하중 지지 역할을 모두 수행하지 못한다. In particular, the embedding
역타 시공시에는 층간 슬래브(S)가 구조적으로 흙막이벽(100)의 지지 역할을 수행한다는 관점에서 볼 때, 흙막이벽(100)과 접합된 매입슬래브(S1)에서 확대된 단면적의 개구부(OP)가 존재하는 경우 외벽(111) 시공 전 구조물의 안정성 측면에서 매우 취약해지는 치명적인 단점이 있다(매입슬래브에 구멍이 크게 뚫린 형태가 되므로 편토압 작용시 구조적으로 매우 취약하다). The opening OP of the cross-sectional area enlarged in the embedded slab S1 joined to the
상기 특허에서 안팎의 수직철근(112,113) 배치를 원활히 하기 위해 나비형 개구부를 바람직한 형상의 예로 제시하고는 있으나, 개구부가 종래의 슬리브 단면적을 크게 확대한 단순 변형 이상의 효과(매입거푸집이 토압 등 하중에 저항하는 구조적인 효과)를 기대하기 어렵고, 매입거푸집이 구조적으로 어떠한 하중 지지 역 할을 하지 못하므로, 실제 시공 중 구조적인 안정성 측면의 치명적인 문제 발생 및 사고 발생 가능성이 지적되고 있다. Although the patent suggests a butterfly-shaped opening as an example of a preferred shape to facilitate the arrangement of the inner and outer vertical reinforcing
추가적으로, 도 4에서 알 수 있는 바와 같이, 매입거푸집(121)이 매입슬래브 영역에서 일정 간격으로 배치되고, 이때 각 매입거푸집의 크기는 안팎에서 2겹으로 배근되는 지하외벽(111)의 수직철근(112,113)을 동시에 관통시켜 배근할 수 있는 개구부(OP)의 크기를 성형할 수 있는 크기로 결정되어야 한다.In addition, as can be seen in Figure 4, buried dies 121 are disposed at a predetermined interval in the buried slab area, wherein the size of each buried die is a vertical reinforcing bar of the basement outer wall (111) that is arranged in two layers in and out ( The size of the opening OP that can penetrate through 112 and 113 at the same time should be determined as a size that can be molded.
안팎의 수직철근(112,113)을 모두 개구부(OP)에 통과시켜야 할 경우, 실제 시공시 매입거푸집(121)은 외벽(111)의 폭방향(두께방향) 및 매입슬래브(S1)의 폭방향으로 거의 전체 구간에 걸쳐 설치되어야 하며, 이에 개구부(OP)의 길이는 도 5에 나타낸 바와 같이 외벽의 폭방향으로 길어질 수밖에 없다. When both the inner and outer vertical reinforcing
이러한 구조에서 개구부(OP)와 개구부 사이에서는 토압이 크게 작용함에 따라 상당한 구조 보강이 있어야 한다. In such a structure, there must be considerable structural reinforcement as the earth pressure acts largely between the opening OP and the opening.
즉, 실제 시공시에, 좌우 양쪽으로 상당한 길이의 빈공간이 존재하는 상황에서, 개구부(OP)와 개구부 사이의 구간에서는 구조적인 취약함을 보완하기 위해 후프(hoop) 배근(114) 등 기둥 시공시의 배근 수준 및 배근 형태에 준하는 상당량의 철근 보강이 이루어져야 한다.That is, in actual construction, in a situation where a considerable length of left and right spaces exist in the construction, the pillar construction such as the hoop back 114 to compensate for the structural weakness in the section between the opening OP and the opening A significant amount of rebar reinforcement should be made in accordance with the city's reinforcement levels and reinforcement shapes.
비구조재인 개방형 판재 구조의 단순 거푸집을 사용하여, 외벽의 대략 폭방향 전체 구간에 걸쳐 개구부를 형성하기 때문에, 개구부와 개구부 사이 구간에서 좌굴에 불리해지고(개구부 사이 구간의 좌굴 길이가 길어 취약), 축하중 내력이 저하되어 기둥 보강을 요하는 것이다.By using the simple formwork of the open plate structure, which is a non-structural material, an opening is formed over the entire widthwise section of the outer wall, which is disadvantageous to buckling in the section between the opening and the opening (the buckling length of the section between the openings is fragile), During the celebration, the strength is reduced and the column needs to be reinforced.
특히, 개구부 사이의 구간이 편토압 작용시 장주 기둥 거동을 함에 따라 구조적으로 매우 취약한 구조가 되고, 시공 중 전단 균열 발생 등의 문제가 있는 바, 안전성에서 많은 문제를 노출하고 있다.In particular, as the sections between the openings act as pole pillars during the action of the earth pressure, the structure becomes very fragile, and there are problems such as shear cracking during construction, thereby exposing many problems in safety.
이를 도면을 참조하여 좀더 상세히 설명하기로 한다.This will be described in more detail with reference to the drawings.
첨부한 도 6과 도 7은 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 6은 평면도이고, 도 7은 도 6의 선 'B-B'를 따라 취한 단면도이다. 6 and 7 are views for explaining the problem according to the prior art, Figure 6 is a plan view, Figure 7 is a cross-sectional view taken along the line 'B-B' of FIG.
도 6은 슬래브 폐합 후 상태, 즉 (I) 영역과 (Ⅱ) 영역의 슬래브(S) 시공이 모두 완료된 상태를, 도 7은 슬래브 폐합 전 상태, 즉 (I) 영역에 대해서만 슬래브 시공이 이루어진 상태를 나타낸 것이다.FIG. 6 shows a state after slab closing, that is, a state in which both the slab (S) constructions of the regions (I) and (II) are completed, and FIG. 7 shows a state before the slab closing, that is, the slab construction is performed only for the region (I). It is shown.
도 6에 도시한 바와 같이, 사각 면적의 지하구조물을 시공한다고 할 때, 주지된 바와 같이 각 층에서 실제 슬래브 콘크리트 시공은 (I) 영역과 (Ⅱ) 영역이 나누어져 순차 시공되는 것이 통상적이다.As shown in FIG. 6, when constructing a square structure underground structure, as is well known, actual slab concrete construction in each layer is generally performed by sequentially dividing (I) and (II) regions.
즉, 슬래브(S) 시공시에 (I) 영역에서 콘크리트를 선타설한 뒤 동층의 (Ⅱ) 영역에서 슬래브 거푸집 구조체(141)를 설치하고, 이어 (I) 영역에서 선 시공된 슬래브 하측의 굴토작업이 실시된 다음, (Ⅱ) 영역에서 슬래브 콘크리트를 후 타설하는 것이다(슬래브 폐합).That is, when the slab (S) is constructed, concrete is cast in the area (I), and then the
이는 각 층의 슬래브 시공시 실제 적용되는 통상의 작업 순서로서, 굴토작업을 (Ⅱ) 영역의 슬래브 콘크리트 시공보다 앞서 실시함으로써 공기 단축이 가능해진다.This is a general work order that is actually applied in the construction of slabs of each layer, and the air shortening can be performed by performing the excavation work before the construction of the slab concrete in the area (II).
그러나, (Ⅱ) 영역의 슬래브 콘크리트가 타설되고 나면 구조적 문제는 발생 하지 않지만, 도 6과 및 도 7에서와 같이 슬래브 폐합 전, 즉 (Ⅱ) 영역의 슬래브 콘크리트가 타설되기 전까지는 (I) 영역의 선 시공된 슬래브가 토압을 전적으로 지지해야 한다. However, structural problems do not occur after slab concrete is poured in the area (II), but before slab closing, that is, until the slab concrete in the area (II) is poured, as shown in FIGS. 6 and 7, The pre-installed slab must support the earth pressure completely.
결국, (Ⅱ) 영역의 슬래브 콘크리트가 타설되기 전, 특히 (I) 영역의 굴토작업시에 편토압이 크게 발생하게 되고, 이로 인해 개구부(OP)와 개구부 사이 구간에서 전단 균열이 발생할 수 있다. As a result, before the slab concrete in the region (II) is poured, in particular during the excavation work in the region (I), the excavation pressure is greatly generated, which may cause shear cracking in the section between the opening OP and the opening.
도 4 및 도 5에서와 같이 개방형 판재 구조의 단순 거푸집(121)을 사용하고 매입슬래브(S1)에서 외벽 폭방향으로 개구부(OP)의 길이가 길어지게 되면(각 개구부가 외벽 폭의 대부분을 개방), 슬래브 폐합이 안된 상태에서 슬래브 선타설 영역((I) 영역))의 추가 굴토작업시 상당한 크기의 편토압에 의해 전단 균열 발생시 붕괴의 위험이 매우 커지게 된다.4 and 5, when the
따라서, 본 발명은 이와 같은 점을 감안하여 안출한 것으로서, 기존 동바리의 사용이 불필요함은 물론 테두리보가 삭제될 수 있으며, 특히 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있으면서도 매입슬래브를 포함한 슬래브 전체의 강성을 극대화할 수 있는 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 슬래브 및 합벽 시공용 받침브라켓을 제공하는데 그 목적이 있다.Therefore, the present invention has been devised in view of the above points, and the use of the existing clubs is not necessary, as well as the rim beam can be eliminated. The purpose is to provide slab and plywood structures and construction methods of underground structures that can maximize the stiffness of the entire slab including embedded slabs, and to support the brackets for the slab and plywood construction.
또한, 본 발명은 외벽에 의해 매립되는 슬래브 부분인 매입슬래브의 내부에 영구구조물로서 매입되는 매입형 RC보 철근틀을 마련하여 양생 후 매입형 RC보 철근틀이 데크슬래브를 지지할 수 있도록 함으로써, 데크슬래브→매입형 RC보 철근틀→받침 브라켓→엄지말뚝(H-파일)으로 이어지는 수직방향 하중 전달체계를 확보할 수 있고, 또 횡토압→합벽→매입형 RC보 철근틀을 포함하는 매입 슬래브→테크 슬래브로 이어지는 수평방향 하중 전달체계를 확보할 수 있는 등 하중전달을 원활하게 할 수 있는 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 슬래브 및 합벽 시공용 받침브라켓을 제공하는데 다른 목적이 있다.In addition, the present invention by providing an embedded RC beam reinforcement frame to be embedded as a permanent structure in the interior of the embedded slab which is part of the slab buried by the outer wall to enable the embedded RC beam reinforcement frame to support the deck slab after curing, Deck slab → embedded RC beam rebar frame → Secure vertical load transfer system from supporting bracket to thumb pile (H-pile); transverse pressure → plywood → embedded slab including embedded RC beam rebar frame → There are other objectives to provide slab and plywood structures and construction methods for underground structures that can facilitate load transfer, such as securing horizontal load transfer system leading to tech slabs, and supporting brackets for slab and ply wall construction. .
상기 목적을 달성하기 위하여 본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 시공 방법은 각 층의 슬래브 시공시 매입슬래브의 거푸집 역할 및 하기 스틸 웨일 구조체의 지지 역할을 수행하는 받침브라켓을 흙막이벽에 설치하는 단계와, 매입슬래브의 개구부 형성을 위한 거푸집 역할과 동시에 흙막이벽으로부터 전달되는 하중 지지, 분산 및 전달 역할을 수행하는 스틸 웨일 구조체를 상기 받침브라켓 위 매입슬래브 영역을 따라 이격 배치하는 단계와, 수평철근과 외곽철근을 포함하는 형태로 이루어져 하중의 원활한 전달을 위한 역할을 수행하는 매입형 RC보 철근틀을 상기 받침브라켓 위 매입슬래브 영역을 따라 배근하는 단계와, 상기 받침브라켓에 연결되도록 슬래브 구축용 거푸집 구조체를 설치한 뒤에 상기 스틸 웨일 구조체의 내부공간을 제외한 전 슬래브 영역에 콘크리트를 타설하여 슬래브를 시공하는 단계와, 전 층의 슬래브 시공이 완료되면 상기 스틸 웨일 구조체의 내부공간에 의해 형성된 개구부를 지하외벽의 수직철근 층간 배근 및 지하외벽의 콘크리트 타설을 위한 통로로 사용하여 지하합벽을 층간 연속적으로 순타 시공하는 단계로 이루어진 것을 특징으로 한다. The slab and plywood construction method of the underground structure provided by the present invention in order to achieve the above object is to install a support bracket to form the formwork of the embedded slab and the supporting role of the following steel wale structure in the slab construction when the slab construction of each layer And disposing a steel wale structure spaced apart along the buried slab area on the support bracket to serve as a formwork for forming an opening of the buried slab, and at the same time serving as a load supporting, distributing, and transferring material from the retaining wall; And reinforcing the embedded RC beam reinforcing frame along the buried slab area on the support bracket, which is formed in a shape including the external reinforcement and serves to smoothly transfer the load, and forms a slab to be connected to the support bracket. After installing the structure, the inner space of the steel wale structure Constructing the slab by placing concrete in the entire slab area except the slab construction, and when the slab construction of the entire layer is completed, the opening formed by the inner space of the steel wale structure is divided into the vertical reinforcing bars of the basement wall and the concrete casting of the basement outer wall. It is characterized by consisting of a step for the continuous construction of the subterranean plywood wall using the passageway for.
또한, 상기 목적을 달성하기 위하여 본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 구조물은 매입슬래브의 거푸집 역할 및 스틸 웨일 구조체의 지지 역할을 수행하기 위하여 흙막이벽에 설치되는 받침브라켓과, 상기 받침브라켓 위 매입슬래브 영역을 따라 배치되는 장선철근 및 이 장선철근 위에 설치되는 철망형 거푸집과, 매입슬래브 영역과 이어지는 슬래브 영역을 구축하기 위한 슬래브 구축용 거푸집 구조체와, 매입슬래브의 개구부 형성을 위한 거푸집 역할과 동시에 흙막이벽으로부터 전달되는 하중 지지, 분산 및 전달 역할을 수행하며 상기 받침브라켓 위 매입슬래브 영역을 따라 이격 배치되는 스틸 웨일 구조체와, 수평철근과 외곽철근을 포함하는 형태로 이루어져 하중의 원활한 전달을 위한 역할을 수행하며 상기 받침브라켓 위 매입슬래브 영역을 따라 배근되는 매입형 RC보 철근틀을 포함하며, 상기 스틸 웨일 구조체의 내부공간을 제외한 전 슬래브 영역에 콘크리트가 타설되어 슬래브 시공이 완료되고, 상기 스틸 웨일 구조체의 내부공간에 의해 형성된 개구부가 지하외벽용 수직철근 층간 배근 및 콘크리트 타설을 위한 통로로 사용되어 지하외벽 시공이 완료되어, 지하합벽과 슬래브가 구축된 구조로 이루어진 것을 특징으로 한다. In addition, the slab and plywood structure of the underground structure provided by the present invention in order to achieve the above object is a support bracket which is installed on the earth wall to serve as the formwork of the embedded slab and the supporting role of the steel wale structure, and on the support bracket Jang reinforcing bars arranged along the buried slab area, wire mesh formwork installed on the reinforcing bar slab, slab construction formwork for constructing the slab area connected with the buried slab area, and the formwork for forming the opening of the buried slab. It serves to support the load, distribute and transfer the load from the retaining wall, and is composed of a steel wale structure spaced apart along the buried slab area on the support bracket, and a horizontal reinforcement and an outer reinforcement. Perform the purchase on the support bracket An embedded RC beam reinforcement frame is disposed along the slab area, and concrete is poured into the entire slab area except the inner space of the steel wale structure to complete the slab construction, and the opening formed by the inner space of the steel wale structure. It is used as a passage for vertical reinforcing bar reinforcement and concrete placing for the basement outer wall.
그리고, 상기 목적을 달성하기 위하여 본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 시공용 받침브라켓은 지하구조물의 슬래브 및 합벽 시공시 사용되는 것으로서, 매입슬래브의 거푸집 역할 및 스틸 웨일 구조체의 지지 역할을 수행하며, 흙막이벽에 설치되는 받침브라켓 본체와, 이 받침브라켓 본체의 선단부분에 착탈가능하게 결합되는 보조브라켓으로 구성되어, 슬래브 양생 후 지하외벽 타설 전에 보조브라켓을 받침브라켓 본체로부터 떼어낼 수 있는 구조로 이루어진 것을 특징으로 한다. In addition, the slab and plywood construction support bracket of the underground structure provided by the present invention in order to achieve the above object is used in the construction of the slab and plywood construction of the underground structure, and performs the role of formwork of the embedded slab and the support role of the steel wale structure. It consists of a supporting bracket body installed on the earthen wall, and an auxiliary bracket detachably coupled to the front end of the supporting bracket body, so that the auxiliary bracket can be detached from the supporting bracket body before slaying the slab after curing the slab. Characterized in that consisting of.
본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 슬래브 및 합벽 시공용 받침브라켓은 다음과 같은 장점이 있다. The slab and plywood structure and construction method of the underground structure provided by the present invention, and the support bracket for the slab and plywood construction has the following advantages.
첫째, 기존 테두리보가 삭제되면서 테두리보 설치에 따른 문제점이 해소될 수 있으며, 특히 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있으면서도 상기 스틸 웨일 구조체가 하중을 지지하게 되면서 매입슬래브를 포함한 슬래브의 강성이 극대화될 수 있다. First, as the existing edge beams are deleted, the problems caused by the edge beam installation can be solved. In particular, the steel wale structure is loaded while the continuous reinforcement of the vertical reinforcement between floors and the interlayer continuous casting of concrete can be smoothly carried out using an opening. By supporting the stiffness of the slab including the embedded slab can be maximized.
둘째, 스틸 웨일 구조체의 경우 개구부를 형성하기 위한 성형틀(거푸집) 역할을 하면서도 매입슬래브 내 개구부 주변의 하중 지지 및 분산 지지를 위한 구조체 역할을 동시에 수행하게 되며, 이에 흙막이벽의 역타 지지구조인 슬래브의 강성이 극대화될 수 있다. Secondly, in the case of the steel wale structure, while serving as a forming mold (form) for forming the openings, the steel wale structure simultaneously serves as a structure for supporting loads and distributed support around the openings in the embedded slab, and thus a slab which is a reverse support structure of the retaining wall. The rigidity of can be maximized.
셋째, 스틸 웨일 구조체의 경우 간단한 구조를 가지면서 소형, 경량으로 제작될 수 있고, 옹벽 두께에 따라 웨일 스틸 구조체 크기가 변하지 않고 일정함에 따라 공장에서 가공하여 용접 조립하는 방식으로 모듈화하여 하나의 단품으로 대량 생산할 수 있다.Third, the steel wale structure can be manufactured in a small size and light weight while having a simple structure. As the size of the wale steel structure does not change according to the retaining wall thickness, the steel wale structure is modularized by processing in the factory and welding assembly. Can mass produce.
따라서, 구조가 복잡하고 철재 물량이 많이 소요되는 종래의 그레이팅 지지틀을 사용할 때보다 비용 측면에서 매우 유리해지며, 작업성 향상, 작업시간 단축, 인건비 절감 등의 많은 장점이 있다. Therefore, it is very advantageous in terms of cost than when using a conventional grating support frame, which is complicated in structure and takes a lot of steel, and has many advantages such as improved workability, reduced work time, and reduced labor costs.
특히, 상기 스틸 웨일 구조체는 종래의 그레이팅 지지틀에 비해 제작시 철재 사용량이 적고, 제작원가가 상대적으로 낮으며, 그레이팅 지지틀과 달리 연속되게 설치하지 않고 서로 간격을 두어 설치하므로 현장에서 사용 개수 또한 적기 때문에 전체적인 공사 비용의 절감이 가능하다.In particular, the steel wale structure is less steel used in the production compared to the conventional grating support frame, manufacturing cost is relatively low, unlike the grating support frame is installed at intervals apart from each other without continuous installation, so the number of use in the field Because of this, the overall construction cost can be reduced.
넷째, 상기 스틸 웨일 구조체는 건축물의 모서리 부분 사용 제약 등과 같은 시공 위치의 제약이 없고, 이와 관련한 종래의 제반 문제점들을 해결할 수 있다. Fourth, the steel wale structure is not limited in the construction position, such as constraints on the use of the corner portion of the building, it can solve all the conventional problems associated with this.
다섯째, 지하 외벽에 의해 매립되는 매입슬래브 내에 영구구조물인 매입형 RC보 철근틀을 설치하여, 양생 후 매입형 RC보 철근틀이 데크슬래브를 지지할 수 있도록 함으로써, 수직방향 하중 전달체계(데크슬래브→매입형 RC보 철근틀→받침 브라켓→엄지말뚝)와 수평방향 하중 전달체계(횡토압→합벽→매입형 RC보 철근틀을 포함하는 매입 슬래브→테크 슬래브)을 구축할 수 있으며, 따라서 구조물에 대한 원활한 하중 전달 시스템을 통해 구조적 안전성을 향상시킬 수 있다. Fifth, by installing embedded RC beam reinforcement frame, which is a permanent structure, in the embedded slab buried by the outer wall of the basement, and allowing the embedded RC beam reinforcement frame to support the deck slab, the vertical load transfer system (deck slab) → embedded RC beam reinforcing frame → support bracket → thumb pile) and horizontal load transfer system (lateral soil pressure → plywood → embedded slab → tech slab including embedded RC beam reinforcement frame). Seamless load transfer systems can improve structural safety.
이하, 첨부한 도면을 참조하여 본 발명의 바람직한 실시예에 대해 더욱 상세히 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
본 발명에서 제공하는 지하구조물의 슬래브 및 합벽 시공 방법은 지하구조물의 각 층 슬래브를 시공한 뒤 흙막이벽에 접하는 지하외벽을 구축하여 합벽으로 시공하는 과정에서, 상기 지하외벽 내에 매립되는 슬래브 부분, 즉 매입슬래브 영역에 상하로 관통하는 개구부를 형성하기 위한 거푸집 역할을 하면서 하중 지지를 위한 영구 구조체의 역할을 동시에 수행할 수 있는 스틸 웨일(wale) 구조체를 설치하여 슬래브를 시공하고, 전 층의 슬래브를 시공한 상태에서 상기 스틸 웨일 구조체에 의해 형성된 개구부를 지하외벽의 수직철근 층간 배근과 콘크리트 타설용 통로로 사용하여 합벽을 층간 연속적으로 시공하는 방법이다. In the slab and plywood construction method of the underground structure provided by the present invention, after constructing each layer slab of the underground structure and constructing the basement outer wall contacting the earth wall, the construction of the slab portion, that is, the slab portion embedded in the basement outer wall The slab is constructed by installing a steel wale structure that can serve as a formwork for forming openings penetrating up and down in the buried slab area, and can simultaneously serve as a permanent structure for supporting loads. In the construction state, the opening formed by the steel wale structure is used as a vertical reinforcing layer reinforcement of the basement outer wall and concrete casting passageway to continuously install the plywood wall.
이러한 본 발명에서는 기존 테두리보가 삭제되면서 테두리보 설치에 따른 문제점이 해소될 수 있고, 개구부를 이용하여 지하외벽의 수직철근 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 시행할 수 있음은 물론, 상기 스틸 웨일 구조체가 매입슬래브 내에서 흙막이벽으로부터 슬래브로의 토압 전달, 토압 지지, 측압 지지, 축력 지지 등의 하중 지지 역할을 수행하고, 또 매입슬래브 내에 마련되는 매입형 RC에 의해 수직방향 및 수직방향의 원활한 하중 전달을 유도함으로써, 매입슬래브를 포함한 슬래브 전체의 강성을 극대화시킬 수 있다. In the present invention, as the existing edge beams are deleted, the problems caused by the edge beam installation can be solved, and the continuous reinforcement of the vertical reinforcement interlayers of the basement outer walls and the interlayer continuous casting of concrete can be smoothly performed using the openings, as well as the steel. Whale structure performs load supporting role such as earth pressure transfer, earth pressure support, lateral pressure support, axial force support, etc. from the retaining wall to the slab in the embedded slab, and the vertical and vertical directions are made by the embedded RC provided in the embedded slab. By inducing smooth load transfer, the stiffness of the entire slab including the embedded slab can be maximized.
이러한 본 발명의 시공 방법을 첨부한 도면을 참조하여 좀더 구체적으로 살펴보면 다음과 같다. The construction method of the present invention will be described in more detail with reference to the accompanying drawings.
첨부한 도 8은 본 발명에 따른 시공 과정의 공정도이고, 도 9는 본 발명에 따른 매입슬래브(S1) 영역에서 스틸 웨일 구조체(130), 메입형 RC보(150)가 설치된 상태를 보여주는 사시도이고, 도 10은 흙막이벽(100)의 H-파일(101)에 받침브라켓(122)을 설치한 뒤 받침브라켓 위에 장선철근(123), 철망형 거푸집(124), 스틸 웨일 구조체(130), 메입형 RC보(150), 받침각관(125)을 설치한 상태를 도시한 평면도이다. 8 is a process diagram of the construction process according to the present invention, Figure 9 is a perspective view showing a state in which the
그리고, 첨부한 도 11은 단면도로서, 흙막이벽(100)의 H-파일(101)이 설치된 위치에서 취한 단면도이며, 슬래브(S)의 시공이 완료된 상태를 도시한 것이다.11 is a sectional view taken in a position where the H-
여기서, 도면부호 111은 콘크리트가 타설된 상태에서 외벽을 나타낸다.Here,
또한, 첨부한 도 12는 본 발명에 따른 시공 과정에서 슬래브(S) 시공 후 합벽 시공 과정에서 수직철근(112,113)의 배근상태를 도시한 도면이고, 도 13은 도 12에서 'C' 방향에서 본 수직철근(112,113)의 배근상태를 나타낸 도면이다.In addition, Figure 12 is a view showing the reinforcement state of the vertical reinforcing bars (112, 113) in the plywood construction process after the slab (S) construction in the construction process according to the present invention, Figure 13 is viewed from the 'C' direction in FIG. Figure showing the reinforcement state of the vertical reinforcing bars (112, 113).
여기서, 도면부호 100은 흙막이벽을 나타내며, 본 발명은 흙막이벽으로서 H-파일(101)이 사용되는 CIP나 SCW에 모두 적용될 수 있는 것이므로, 이하 본 명세서에서는 이들을 따로 구분하지 않고 "흙막이벽"으로 통칭하기로 한다.Here, the
첨부한 도 8을 참조하여 전체 시공 과정에 대해 개략적으로 설명하면 다음과 같다. Referring to FIG. 8, the overall construction process is briefly described as follows.
시공되는 건물의 경계선을 따라 흙막이벽을 시공하고, 그 안쪽 지중에 골조용 기둥(미도시)을 시공한 뒤(S110), 1차로 소정 깊이의 터파기를 진행하여 흙막이벽과 골조용 기둥의 상부 일부가 노출되도록 한다(S120).Construct the retaining wall along the boundary of the building to be constructed, construct the framed pillar (not shown) in the inner ground (S110), and then proceed with the dig of the predetermined depth by the first part of the upper part of the retaining wall and the framed pillar. To be exposed (S120).
이어 1층 바닥 슬래브를 시공하고(S130), 1층 바닥 슬래브의 시공이 모두 완료되면 2차 굴토(S140) 후에 그 하층의 슬래브를 동일하게 작업하여 시공한다(S150). Subsequently, the construction of the first floor slab (S130), and when the construction of the first floor slab is completed, the secondary slab (S140) after the slab of the lower floor to work the same (S150).
이후 계속해서 하층으로 내려가면서 단계적으로 상기와 같은 굴토 및 슬래브 시공 작업을 반복하여 전 층의 슬래브를 모두 시공하고(S160), 모든 지하층의 슬래브 시공 작업이 완료된 뒤에는 맨 아래층부터 위층으로 올라가면서 흙막이벽 안쪽에 지하외벽을 순타 시공하여 지하합벽(옹벽)을 완성하게 된다(S170).After continuing to go down to the lower floors by repeating the construction of the above-mentioned pit and slab step by step construction all the slabs of all floors (S160), after the completion of the slab construction work of all basement floors, the bottom wall from the bottom floor going up to the top floor The basement outer wall is smoothly constructed inside to complete the basement wall (retaining wall) (S170).
이러한 합벽 순타 시공시에는 콘크리트의 밀실 충전이 가능하고, 순타조인트의 경우 콘크리트의 밀실 충전으로 역타조인트에 비해 틈새 발생이 최소화될 수 있다. When the plywood nets are constructed, it is possible to fill the closed room of the concrete, and in the case of the netta joint, the gap can be minimized compared to the reverse oscillating joint by filling the closed room of the concrete.
물론, 각 층의 슬래브 시공시에 도 6 및 도 7에 나타낸 바와 같이 동층의 전체 슬래브 면적을 분할하여, 분할된 영역에 따라 동층의 슬래브를 순차 시공하는 것이 가능하며, 이때 선 시공된 슬래브 영역의 하측 굴토작업을 슬래브 폐합, 즉 동층 다른 영역의 슬래브 시공 전에 우선 실시할 수 있다.Of course, it is possible to divide the entire slab area of the copper layer and sequentially construct the slab of the copper layer according to the divided area, as shown in Figs. 6 and 7 at the time of slab construction of each layer. Lower excavation may be carried out prior to slab consolidation, ie slab construction in other areas of the same layer.
위와 같이 각 층 시공에 있어서, 층간 수평구조체인 슬래브(S)가 흙막이벽(100)을 직접 지지하도록 슬래브를 선 시공한 뒤 이어 굴토하고, 이러한 과정을 지하 최하층까지 반복적으로 수행한 다음, 흙막이벽(100)과 일체로 지하외벽(111)을 구축하여 흙막이벽(100)과 지하외벽(111)으로 이루어진 지하합벽을 시공하게 된다(도 11 참조).In the construction of each floor as above, the slab (S), which is a horizontal interlayer structure, the slab is pre-constructed after the construction so as to directly support the
여기서, 각 층 슬래브(S)를 시공할 때, 지하외벽(111)에 매립되는 슬래브 부분(이하, '매입슬래브'라 함)(S1)에는 도 9 내지 도 11에 나타낸 바와 같이 스틸 웨일 구조체(130)와 매입형 RC보 철근틀(150)을 설치한 뒤 시공하게 된다.Here, when constructing each layer slab (S), the slab portion (hereinafter referred to as "buried slab") (S1) buried in the basement
이때, 스틸 웨일 구조체(130)는 기본적으로 매입슬래브(S1)의 개구부(OP)를 성형하기 위한 거푸집 역할을 하게 된다.At this time, the
매입슬래브(S1)에서 상기 스틸 웨일 구조체(130)에 의해 성형된 각 층 슬래브(S)의 개구부(OP)는 지하외벽 수직철근(113)의 층간 연속 배근과 지하외벽(111) 콘크리트의 층간 연속 타설을 위한 상하 관통 통로가 된다. The opening OP of each layer slab S formed by the
즉, 상기 개구부(OP)를 통해 지하외벽(111)의 연속적인 순타 시공이 가능해지는 것이다.That is, the continuous smooth construction of the basement
또한, 본 발명에서 스틸 웨일 구조체(130)는 현장 시공 후 매입슬래브(S1) 내에 매립되는 영구 구조체로서, 개구부(OP)를 성형하기 위한 거푸집 역할과 함께, 슬래브(S)의 시공 후 매입슬래브(S1) 내부에서 흙막이벽(100)으로부터 전달되는 토압 지지, 측압 지지, 축력 지지, 슬래브로의 토압 전달 등 하중 지지 구조체의 역할을 동시에 수행한다. In addition, in the present invention, the
즉, 상기 스틸 웨일 구조체(130)는 단순 거푸집 역할은 물론이고, 하중 지지 구조체의 역할을 수행할 수 있도록 구조 및 자체 강성을 보완하여 제작 및 설치된 다.That is, the
상기 스틸 웨일 구조체는 공장 제작되어 현장에 제공되는 것으로, 각 층의 슬래브 시공시에 공장 제작된 스틸 웨일 구조체를 현장의 소정 위치에 설치한 뒤 이후의 시공 작업을 진행하게 된다. The steel wale structure is to be manufactured in the factory and provided to the site, and the installation of the steel wale structure produced at the time of the slab construction of each layer at a predetermined position of the site and then proceed with the subsequent construction work.
상기 스틸 웨일 구조체는 후술하는 바와 같이 스틸 평판 또는 앵글부재(L-형강), 채널부재(ㄷ-형강) 등을 사용하여 제작되는데, 이들을 혼용하여 제작될 수도 있으며, 전체적으로 사각형의 틀 구조로 제작될 수 있다.The steel wale structure is manufactured by using a steel plate or angle member (L-shaped steel), a channel member (c-shaped steel), etc., as will be described later, and may be produced by mixing them, or a rectangular frame structure as a whole. Can be.
이때, 슬래브 시공 후, 특히 합벽 시공 전에 흙막이벽으로부터 콘크리트를 통해 가해지는 하중에 충분히 견딜 수 있는 강성을 가지도록 구조적으로 설계되어 제작된다.At this time, after the slab construction, especially before the construction of the plywood is structurally designed and manufactured so as to have a rigid enough to withstand the load applied through the concrete from the earth wall.
종래의 그레이팅 지지틀의 경우 대형이면서 연속적으로 설치돼야 하기 때문에 제작시 철재 물량이 과다해지고 따라서 사용시 비용이 커지는 단점, 및 건축물의 모서리 부분 사용시 제약이 발생하는 단점이 있는 것을 고려하여, 본 발명의 스틸 웨일 구조체는, 상대적으로 소형이면서도 그 자체가 토압 하중을 충분이 지지할 수 있는 강성을 가지도록 제작되는 것과 함께, 현장 설치시 매입슬래브 영역을 따라 연속적으로 설치되는 것이 아닌 소정 간격을 두고 이격 설치된다.In the case of the conventional grating support frame, the steel of the present invention in consideration of the disadvantage that the steel volume is excessive during manufacturing, and thus the cost is increased when using it, and that the limitation occurs when using the corner portion of the building. The wale structure is relatively small and in itself manufactured to be rigid enough to support the earth pressure load, and is spaced apart at predetermined intervals rather than being continuously installed along the buried slab area during field installation. .
즉, 스틸 웨일 구조체(130)가 매입슬래브(S1) 영역을 따라 연속 배치되는 것이 아닌 소정 간격으로 이격 배치되어 매입슬래브 전체 구간에 대해 부분적으로만 설치되는 것이다.That is, the
특히, 상기 스틸 웨일 구조체(130)의 폭, 슬래브쪽으로 연장되는 방향으로의 폭은 지하외벽의 두께에 상응하는 폭으로 이루어지는 매입슬래브(S1)의 폭에 비해 상대적으로 매우 적은 폭을 갖게 된다. In particular, the width of the
이는 매입슬래브(S1)의 내부에 매입형 RC보 철근틀(150)의 설치를 위한 자리를 확보 및 적정크기로 하여 편토압 저항에 유리하게 하기 위함이다. This is to secure the seat for the installation of the embedded RC
이에 따라, 기존 매입거푸집의 경우와 같이 2열의 수직철근을 관통시키기 위하여 지하외벽의 폭과 거의 근접한, 다시 말해 매입슬래브(S1)의 폭과 거의 근접한 폭을 갖는 것과는 달리, 상기 스틸 웨일 구조체(130)는 매입 슬래브(S1)의 폭에 비해 상대적으로 작은 폭을 갖게 되고, 이로 인해 확보되는 매입슬래브(S1) 내의 영역에 매입형 RC보 철근틀(150)을 설치할 수 있다. Accordingly, unlike the case of the existing formwork, the
이때, 지하외벽의 골조용으로 사용되는 2개의 수직철근, 즉 인장철근의 역할을 하는 바깥쪽 수직철근(113)은 스틸 웨일 구조체(130)의 공간을 통해 관통 배근되고, 압축철근의 역할을 하는 안쪽 수직철근(112)은 매입슬래브(S1) 내의 매입형 RC보 철근틀(150)을 관통하여 설치되어 있는 다월 철근(115)을 이용하여 연결 배근된다. At this time, the two vertical reinforcing bars used for framing the basement outer wall, that is, the outer vertical reinforcing
여기서, 상기 매입형 RC보 철근틀(150)은 슬래브 부분의 전반적인 구조적 강성을 강화하기 위한 용도로 사용되며, 토압이 작용하는 쪽 및 슬래브쪽으로의 하중 전달을 원활히 해줄 수 있다. Here, the embedded RC
이러한 매입형 RC보 철근틀(150)은 매입슬래브(S1) 내의 확보된 영역(스틸 웨일 구조체의 폭 감소로 인해 확보된 영역)에서 길이방향을 따라, 즉 지하외벽을 따라 나란하게 연장되는 형태로 배치되는 다수의 수평철근(151)과 이 수평철근(151)의 둘레를 적정간격으로 군데군데 묶어주는 외곽철근(152)으로 이루어진다. The embedded RC
이에 따라, 상기 매입형 RC보 철근틀(150)은 데크슬래브→매입형 RC보 철근틀→받침 브라켓→엄지말뚝(H-파일)으로 이어지는 수직방향 하중 전달이 원활히 이루어질 수 있도록 해주는 역할과, 또 횡토압→합벽→매입형 RC보 철근틀을 포함하는 매입 슬래브→테크 슬래브로 이어지는 수평방향 하중 전달이 원활히 이루어질 수 있도록 해주는 역할을 수행할 수 있다. Accordingly, the embedded RC
그리고, 상기 매입형 RC보 철근틀(150)의 경우 하중 전달이 원활히 이루어질 수 있도록 해주는 역할을 함으로써 시공을 보다 경제적이고 효율적으로 할 수 있는 이점도 제공한다. In addition, in the case of the embedded RC
예를 들면, 슬래브 구축을 위해 콘크리트를 타설한 후, 양생 전이나 양생 직 후 일정기간 동안에는 받침각관(125)이 슬래브를 지지하게 되는데, 만약 매입형 RC보 철근틀(150)이 없는 경우라면 슬래브가 완전히 양생되어 구조적 강성을 발휘할 때까지 받침각관(125)을 그대로 남겨놓은 상태에서 지하층을 계속해서 시공해야 하고, 결국 받침각관(125)의 재사용하지 못하고 새로운 받침각관(125)을 사용하면서 아래층을 계속 시공해나가야 하므로 경제성 측면에서 불리한 점이 있다. For example, after pouring concrete to build a slab, the
본 발명에서는 이러한 받침각관(125)의 역할을 매입형 RC보 철근틀(150)이 대신할 수 있으므로, 받침각관(125)이 없어도 양생 중이나 어느 정도 양생 후 일정기간 동안 매입형 RC보 철근틀(150)이 슬래브를 지지할 수 있으므로, 1개층 시공 후 사용되었던 받침각관(125)을 다음 아래층 시공시 재사용할 수 있고, 결국 경제적인 측면에서 유리한 이점이 있다. In the present invention, since the role of the
도 12에서는 시공이 끝난 윗층에서 사용되었던 받침각관(125)을 현재 시공중 인 아래층에서 사용하고 있는 예를 볼 수 있다. In Figure 12 you can see an example of using the
이러한 스틸 웨일 구조체 및 매입형 RC보 철근틀의 구성 및 사용에 대해서 좀더 상세히 설명하면 다음과 같다. The construction and use of the steel whale structure and the embedded RC beam rebar are described in more detail below.
우선, 지하구조물의 1층 바닥 슬래브를 포함한 각 지하층 슬래브(S)의 시공시에, 매입슬래브(S1) 영역에서 매입슬래브의 거푸집 역할 및 스틸 웨일 구조체(130)의 지지 역할을 하게 되는 지지수단을 흙막이벽(100)에 설치하고, 상기 지지수단에 연결되도록 슬래브 구축용 거푸집 구조체(141)를 설치한다. First, at the time of construction of each basement slab S including the ground floor slab of the underground structure, the supporting means serving as the formwork of the embedded slab and the supporting role of the
보다 상세하게는, 도 9 내지 도 11에 나타낸 바와 같이, 흙막이벽(100)이 갖는 각 H-파일(101)의 플랜지면이 외부로 노출되도록 H-파일(101)이 설치된 위치에서 흙막이벽의 일부를 면갈이하고, 노출된 각 H-파일(101)의 플랜지면에 받침브라켓(122)을 각각 용접하여 설치한다. More specifically, as shown in Figs. 9 to 11, the wall of the retaining wall at the position where the H-
이때, H-파일(101)들에 역삼각 구조의 받침브라켓(122)을 고정 설치할 수 있으며, 일 예로서, 각 H-파일(101)에 앵글부재(L-형강)를 역삼각 구조가 되도록 고정 설치하여 상기 받침브라켓(122)을 구성할 수 있다. At this time, the
여기서, 상기 받침브라켓(122)의 경우, 지하외벽(111)의 폭보다도 더욱 안쪽으로 연장된 길이를 갖게 되는데, 즉 매입슬래브(S1)의 면적을 받쳐주면서 또 슬래브 양생 전이나 양생 중에 거푸집 구조체(141)를 지지하는 임시거치용 받침각관(125)을 받쳐주는 충분한 길이를 갖게 된다. Here, in the case of the
이 경우 지하외벽(111)을 완전히 구축한 상태에 받침브라켓(122)의 끝부분 일부(받침각관을 받치고 있던 부분)가 외벽 밖으로 노출되므로, 이를 용접 등의 작 업을 통해 제거하는 별도의 후작업이 필요하고, 결국 작업성이나 시공성 측면에서 효율이 떨어질 수 있다. In this case, since a part of the end of the base bracket 122 (the part supporting the base angle tube) is exposed outside the outer wall in the state where the basement
이를 해소하기 위하여, 본 발명에서는 상기 받침브라켓(122)으로부터 착탈가능한 보조브라켓(153)를 마련하여, 슬래브 및 매입슬래브(S1) 양생 후 받침브라켓(122) 본체만 남겨놓고 보조브라켓(153)을 제거할 수 있도록 함으로써, 번거롭던 후작업을 배제할 수 있는 이점을 얻을 수 있다. In order to solve this problem, in the present invention, the
즉, 상기 받침브라켓(122)은 앵글부재로 짠 역삼각 구조의 받침브라켓 본체와, 이 받침브라켓 본체의 선단부분에 볼트 등의 체결구조로 결합되는 보조브라켓(153)으로 구성하여, 슬래브 및 매입슬래브(S1) 양생 후 보조브라켓(153)을 받침브라켓 본체로부터 용이하게 떼어낼 수 있도록 함으로써, 종전과 같은 받침브라켓 노출문제를 해소할 수 있다. That is, the
이어 매입슬래브(S1) 영역에서 상기 받침브라켓(122) 위로 장선철근(123), 철망형 거푸집(124), 받침각관(또는 받침각재)(125), 스틸 웨일 구조체(130), 매입형 RC보 철근틀(150)을 설치한다. Subsequently, the reinforcing
즉, 매입슬래브(S1) 영역을 따라 이웃한 받침브라켓(122)들 위에 동시에 걸쳐지도록 장선철근(123)을 복수열로 받침브라켓 위에 횡으로 길게 지지시킨 뒤, 상기 장선철근(123) 위로 철망형 거푸집(124)을 설치하고, 상기 받침브라켓(122)의 선단부 위로는 데크 플레이트 등과 같은 슬래브(노출슬래브) 구축용 거푸집 구조체(141)의 가장자리부를 지지시키기 위한 받침각관(125) 또는 받침각재를 지지시킨다. That is, after supporting the
이때, 상기 받침각관(125) 또는 받침각재는 이웃한 받침브라켓(122)들 위에 동시에 걸쳐지도록 횡으로 길게 설치되어 지지된다. At this time, the
그리고, 슬래브 양생 후에 원활한 하중 전달이 이루어질 수 있도록 하기 위하여, 철망형 거푸집(124) 위로 매입형 RC보 철근틀(150)을 설치한다. Then, in order to enable a smooth load transfer after the slab curing, the embedded RC
여기서, 상기 매입형 RC보 철근틀(150)은 매입형 RC보를 형성하기 위한 철근틀로서, 이때의 매입형 RC보 철근틀(150)은 매입슬래브(S1) 영역을 따라 이웃한 받침브라켓(122)들 위에 동시에 걸쳐지도록 하는 구조로 설치한다.
예를 들면, 매입슬래브(S1) 내의 확보된 영역에서 지하외벽을 따라 나란하게 연장되는 형태로 다수의 수평철근(150)이 배치되고, 이 수평철근(150)의 둘레가 외곽철근(152)에 의해 적정간격 묶여지면 매입형 RC보 철근틀(150)이 완성되며, 후술하는 바와 같이, 스틸 웨일 구조체(130) 내부 공간을 제외한 주변의 철망 거푸집 영역과 데크 플레이트 위 슬래브 영역에 콘크리트가 타설되면, 이때의 매입형 RC보 철근틀(150)에도 콘크리트가 타설되게 된다. Here, the embedded RC
For example, a plurality of horizontal reinforcing
상기 철망형 거푸집(124)은 통상 메탈 리브 라스(metal rib lath)라고 불리는 거푸집으로, 철망 라스(lath)에 리브(rib)를 두어 제작된 거푸집이며, 현재 네트 거푸집 공법에서 사용되는 거푸집이다.The
시공시 상기 철망형 거푸집(124)은 장선철근(123) 등에 적절히 용접하여 고정하거나 철선 등으로 고정하게 된다.During construction, the
그리고, 상기 받침각관(125) 또는 받침각재 위로 거푸집 구조체(141)의 가장자리부를 지지시킨 뒤, 매입슬래브(S1) 영역에서는 사각형 틀 구조로 공장 제작된 스틸 웨일 구조체(130)를 매입슬래브 영역을 따라 상기 철망형 거푸집(124) 위에 일정 간격으로 지지시켜 설치하게 된다.Then, after supporting the edge of the
이후 매입슬래브(S1) 영역 내에서 스틸 웨일 구조체(130) 주변으로 적절히 보강 철근을 배근하는 작업을 실시한다. Thereafter, a work of appropriately reinforcing the reinforcing bar is performed around the
또한, 지하외벽 내측으로 상,하 층간을 연결하게 되는 철근으로서 다월 철근(dowel bar)(115)을 매입슬래브(S1) 영역을 수직 관통시키는 형태로 배근한다.In addition, as a reinforcing bar connecting the upper and lower floors to the inside of the basement outer wall, the
이는 바깥쪽에 관통 형식으로 배근되는 인장철근인 수직철근(113)과 달리 내 측의 다월 철근(115)과 연결되는 수직철근(112)은 압축측에 위치하기 때문에 배근간격을 보통 수직철근의 배근간격보다 3∼5배 간격으로 넓게 배근하여 시공성 및 경제성을 향상시킬 수 있다.This is because the vertical reinforcing
안쪽 수직철근의 배근시에 안쪽 수직철근의 일부는 다월 철근 및 수평철근, 그리고 매입형 RC보 철근틀에 함께 결속하고, 다월 철근이 배근되지 않은 구간의 나머지 일부는 수평철근에만 결속한다. At the time of reinforcement of the inner vertical reinforcing bars, some of the inner vertical reinforcing bars bind together to the dowel and horizontal reinforcement bars and the embedded RC beam reinforcement frame, and the rest of the sections in which the dorsal reinforcing bars are not reinforced are bound only to the horizontal reinforcing bars.
상기 다월 철근(115)은 합벽 내 배근 과정에서 압축철근인 안쪽 수직철근(112) 및 수평철근(116)과 함께 결속(와이어 결속)되어지는 철근이며, 다만 지상 1층 바닥 슬래브의 매입슬래브 영역에서는 다월 철근(115)을 수직철근(112)과 동일 간격으로 설치하는데, 이는 인장측 철근이 되기 때문이다(도 13 참조). The
이와 같이 하여, 받침브라켓(122) 및 장선철근(123), 철망형 거푸집(124), 스틸 웨일 구조체(130), 받침각관(125), 매입형 RC보 철근틀(150), 거푸집 구조체(141) 등을 모두 설치하고, 매입슬래브(S1) 내 보강 철근 및 다월 철근(115)을 모두 배근하며, 데크 플레이트 위 노출슬래브 영역에서도 상, 하부 철근을 배근하는 슬래브 철근 배근작업 등 통상의 슬래브 작업을 모두 완료하게 되면, 스틸 웨일 구조체(130) 내부공간을 제외한 주변의 철망형 거푸집 영역(매입슬래브 영역)과 데크 플레이트 위 슬래브 영역(데크 슬래브 영역)에 콘크리트를 타설하여 슬래브 시공을 완료한다.Thus, the
이와 같이 한 층의 슬래브(S)를 시공한 후에는 전술한 바와 같이 하층으로 내려가면서 동일한 방식으로 각 층의 슬래브를 시공하게 된다.As described above, after the slab S of one layer is constructed, the slab of each layer is constructed in the same manner while descending to the lower layer as described above.
각 층 슬래브(S)의 시공이 완료된 상태에서는 스틸 웨일 구조체(130)의 내부공간을 제외한 나머지 부분이 콘크리트로 채워져 슬래브를 형성하며, 이 슬래브는 합벽 시공 후 지하외벽(111) 속에 매립되는 매입슬래브(S1) 부분과 지하외벽 밖으로 노출되는 노출슬래브(S2) 부분(데크 플레이트로 시공되는 데크 슬래브 부분)으로 구분되게 된다.When the construction of each layer slab (S) is completed, the remaining portion of the
각 층의 매입슬래브(S1)에서 스틸 웨일 구조체(130)의 내부공간은 콘크리트가 타설되지 않기 때문에 개구부(OP)를 형성하게 되는데, 이 개구부(OP)는 이후 합벽 시공 과정에서 지하외벽(111)용 콘크리트를 타설하기 위한 콘크리트 타설 및 충전 통로로 활용되고, 또한 층간 수직철근(113)이 설치되는 통로로 활용될 수 있는 바, 결국 개구부(OP)를 통한 지하외벽(111)의 수직철근(113) 층간 연속 배근과 콘크리트의 층간 연속 타설을 원활히 수행할 수 있게 된다.In the buried slab S1 of each layer, the inner space of the
슬래브(S)의 시공 후 매입슬래브(S1)의 개구부(OP)가 충분히 확보되기 때문에 개구부를 통해 지하외벽(111)의 수직철근(113) 층간 연속 배근과 콘크리트 층간 연속 타설이 가능해지며, 이로써 지하외벽(111)은 층간 일체성이 강화되면서 흙막이벽(100)에 접하여 하나의 지하합벽으로 구축되게 된다. Since the opening OP of the embedded slab S1 is sufficiently secured after the construction of the slab S, continuous reinforcement between the vertical reinforcing
지하외벽(111)의 시공은, 인장철근이 되는 바깥쪽 수직철근(113)을 매입슬래브(S1)의 개구부(OP)를 통과하도록 층간 연속 배근하고, 지하외벽 내 공간의 상하층 다월 철근(115)에 연결되는 안쪽 수직철근(112), 수평철근(116), 이 수평철근(116)에 결속되어 지지되는 또 다른 안쪽 수직철근들을 배근하며, 지하외벽 거푸집을 설치한 뒤 콘크리트를 타설하여, 상기 수직철근(112,113), 다월 철근(115), 수평철근(116), 매입슬래브(S1)를 지하외벽(111)에 모두 매립시키는 방식으로 이루어진다.In the construction of the basement
물론, 콘크리트 타설시에 스틸 웨일 구조체(130)의 내부공간, 즉 개구부(OP)를 통해 콘크리트를 타설해야 하므로 스틸 웨일 구조체의 내부공간에 위치된 철망형 거푸집은 절단하여 제거한다.Of course, since concrete must be poured through the inner space of the
지하외벽 철근 배근시에는 지상 1층 바닥 슬래브의 매입슬래브(S1)에 설치된 각 다월 철근(115)에 압축철근인 안쪽 수직철근(112)을 결속하여 연결하고, 그 이하 지하층에서는 안쪽 수직철근(112)의 일부만을 다월 철근(115)에, 나머지 일부는 수평철근(116)에 각각 결속하여 연결한다.In case of reinforcement of the basement outer wall, the inner vertical reinforcing
토압 작용시 모멘트 특성상 바깥쪽 수직철근(113)에는 인장력이, 안쪽 수직철근(112)에는 압축력이 작용하므로, 인장철근이 되는 상기 바깥쪽 수직철근(113)은 인장력에 저항할 수 있게 개구부(OP)를 관통시켜 층간 연속 배근하고(바깥쪽 수직철근 = 관통철근), 압축철근이 되는 상기 안쪽 수직철근(112)은 매입슬래브(S1)에 상하 관통 매립된 다월 철근(115)과 수평철근(116)에 간단히 결속시켜 배근한다.Due to the characteristic of the moment during earth action, the tensile force acts on the outer
그리고, 상기 매입슬래브(S1)의 내부에 설치되는 매입형 RC보 철근틀(150)로 인해 슬래브 양생 후, 하중 전달이 원활히 이루어질 수 있게 되므로, 토압 작용시 또는 슬래브측 하중 작용시 견고한 구조적인 강성이 확보될 수 있다. And, because the buried RC
본 발명에서 상기 다월 철근(115)은 상하층을 구조적으로 연결하는 연결용 철근이 아니라 안쪽 수직철근(112)을 고정시키는 고정용 철근으로 사용되며, 수직 철근(112)의 고정이 용이한 간격을 고려하여 매입슬래브(S1)에 매립된다.In the present invention, the
상기 다월 철근(115)의 간격이 지상 1층의 경우를 제외하고는 안쪽 수직철근(112)의 간격과 다르므로 다월 철근이 설치되지 않은 나머지 구간에서는 안쪽 수직철근(112)을 수평철근(116)에 결속시켜 지지시킨다. Since the interval of the
한편, 첨부한 도 14는 본 발명에 따른 스틸 웨일 구조체의 다양한 실시예를 도시한 도면이다. Meanwhile, FIG. 14 is a view showing various embodiments of the steel wale structure according to the present invention.
도시된 바와 같이, 스틸 웨일 구조체(130)는 전면부재(131), 후면부재(132), 양 측면부재(133a,133b)를 사각형 형태로 배치하여 상호 용접 고정함으로써 이루어진 사각형 틀 구조로 제작된다.As shown, the
이때, 전면부재(131)와 후면부재(132) 사이에 중간부재(134)를 설치하여 1개의 공간, 2개의 공간, 3개의 공간, ..., n개의 공간으로 구획된 구조가 될 수 있으며, 전체적인 외각 형상에 있어서 좌우 길이에 비해 폭을 짧게 구성하여 짧은 좌굴길이를 갖도록 한다. 이와 같이 폭을 상대적으로 짧게 구성하는 경우 좌굴길이가 짧아지므로 좌굴 허용 축하중이 커져 토압 저항에 유리해진다. In this case, the
또한, 스틸 웨일 구조체(130)를 설치함에 있어서, 사용되는 스틸 웨일 구조체의 폭은 매입슬래브(S1)의 폭(=지하외벽의 폭)에 대해 50% 이하가 되도록 하며, 더욱 바람직하게는 25∼50%의 범위가 되도록 하는 것이 바람직하다.In the installation of the
여기서, 스틸 웨일 구조체(130)의 폭이 매입슬래브(S1)의 폭에 비해 25% 미만이 되면, 충분한 개구부(OP)의 면적을 확보하지 못하게 되어, 지하외벽(111)의 관통철근, 즉 바깥쪽 수직철근(113)의 층간 배근이 어렵고, 콘크리트 타설용 통로 로 사용하는데 어려움이 있다.Here, when the width of the
또한, 스틸 웨일 구조체(130)의 폭이 매입슬래브(S1)의 폭에 비해 50%를 초과하게 되면, 개구부(OP)의 면적은 크게 확보될 수 있으나, 개구부의 지나친 면적 증가로 인해 매입슬래브(S1)가 구조적으로 취약해지고, 개구부(OP) 사이 구간의 영역에서 편토압 작용으로 인한 전단 균열이 발생할 우려가 있으므로 바람직하지 않다.In addition, when the width of the
또한, 본 발명의 스틸 웨일 구조체(130)를 제작함에 있어서, 각 부재는 평판의 사용이 가능하나, 충분한 강성 확보 및 내력 증가를 위해 측면부재(133a,133b)와 중간부재(134)의 경우 첨부한 도 15에 나타낸 바와 같이 평판 외에 앵글부재(L-형강), 채널부재(ㄷ-형강), 절곡단면판을 사용하는 것이 바람직하다.In addition, in manufacturing the
또한, 상기 스텔 웨일 구조체(130)에서 사각 틀의 내부공간(구획된 각 내부공간)에는 대각선 방향의 보강부재(135)가 고정 설치될 수 있다.In addition, a
첨부한 도 16은 본 발명에서 상기의 스틸 웨일 구조체를 사용하여 시공함에 따른 개구부의 시공 상태를 보여주는 도면으로, 사각 면적의 지하구조물을 시공한다고 할 때, 슬래브 콘크리트 시공이 (I) 영역과 (Ⅱ) 영역으로 나누어져 순차 시공되는 경우, 슬래브(S) 폐합 전, 즉 (Ⅱ) 영역의 슬래브 콘크리트가 타설되기 전에 (I) 영역의 추가적인 굴토작업이 실시되어 상당한 크기의 편토압이 매입슬래브(S1)에 작용하더라도, 스틸 웨일 구조체(130)가 내력 구조재로서 하중을 충분히 분산 지지하므로 효과적으로 편토압 저항 및 토압을 전달할 수 있고, 또한 개구부(OP) 사이의 구간이 편토압에 대해 충분한 내력을 가지므로 종래와 같은 전단 균 열의 발생이 방지될 수 있다.FIG. 16 is a view showing a construction state of openings according to the construction using the steel wale structure in the present invention. Slab concrete construction includes (I) and (II) In case of sequential construction and dividing into (S) area, additional excavation work in (I) area is performed before slab (S) closing, that is, before slab concrete in (II) area is placed, so that a large amount of excavation pressure is applied to embedded slab (S1). Even if it acts on), the
더불어, 본 발명에서는 개구부(OP)의 폭이 외벽(111)의 전체 폭(두께)에 대해 50% 이내로서 개구부가 외벽의 전체 폭에서 부분적으로 짧게 형성되므로, 개구부(OP) 사이의 구간(장주가 아닌 단주 거동)의 구조 성능이 증대되고(축하중 내력이 크고 편토압에 유리), 개구부 사이의 구간에서 종래와 같은 상당량의 철근이 보강될 필요가 없는 바, 철근 물량 축소, 비용 절감의 장점이 있게 된다. 개구부 사이의 구간에서 후프 배근 등이 불필요하고 일반 배근으로 시공이 가능하다.In addition, in the present invention, since the width of the opening OP is 50% or less with respect to the total width (thickness) of the
아울러, 본 발명에서 사용되는 스틸 웨일 구조체(130) 자체가 폭이 짧고 측면부재(133a,133b) 및 중간부재(134)의 길이가 짧으므로 구조적인 성능 및 효율이 우수한 장점이 있으며, 특히 스틸 웨일 구조체 내 좌굴길이가 짧아 저항 축력 및 강성이 우수하여(축하중 내력이 크고 편토압에 유리) 매입슬래브(S1)를 포함한 슬래브 전체의 강성을 극대화할 수 있게 된다. In addition, since the
또한, 본 발명에서 사용되는 스틸 웨일 구조체(130)는 그 크기가 작고 경량이므로 시공성이 향상되고, 아울러 스틸 웨일 구조체의 설치가 연속 설치가 아닌 이격 배치되는 부분 설치이므로 종래의 그레이팅 지지틀에 비해 물량 축소(사용 개수 축소) 및 물량 비용 절감, 작업시간 단축, 인건비 절감 등의 장점이 있게 된다.In addition, since the
도 1은 종래기술에 따른 슬래브 및 테두리보의 시공을 위한 거푸집 구조체의 설치상태를 보여주는 단면도 1 is a cross-sectional view showing the installation state of the formwork for the construction of the slab and the rim beam according to the prior art
도 2는 종래기술에 따른 슬래브 및 테두리보의 시공이 완료된 상태를 보여주는 단면도2 is a cross-sectional view showing a state in which the construction of the slab and the rim beam according to the prior art is completed
도 3은 지하합벽의 역타 시공이 이루어지는 상태의 예를 도시한 단면도3 is a sectional view showing an example of a state in which the reverse construction of the underground plywood is made;
도 4 및 도 5는 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 4은 개방형 판재 구조의 매입거푸집을 사용하여 시공한 평면도이고, 도 5는 도 4의 선 'A-A'를 따라 취한 단면도4 and 5 is a view for explaining the problem according to the prior art, Figure 4 is a plan view using a built-in formwork of open plate structure, Figure 5 is taken along the line 'A-A' of Figure 4 Cross-section
도 6과 도 7은 종래기술에 따른 문제점을 설명하기 위한 도면으로서, 도 6은 평면도이고, 도 7은 도 6의 선 'B-B'를 따라 취한 단면도6 and 7 are diagrams for explaining a problem according to the prior art, Figure 6 is a plan view, Figure 7 is a cross-sectional view taken along the line 'B-B' of FIG.
도 8은 본 발명에 따른 시공 과정의 공정도8 is a process chart of the construction process according to the present invention
도 9는 본 발명에 따른 매입슬래브 영역에서 스틸 웨일 구조체와 매입형 RC보 철근틀이 설치된 상태를 보여주는 사시도9 is a perspective view showing a state in which the steel wale structure and the embedded RC beam reinforcement frame is installed in the buried slab area according to the present invention;
도 10은 본 발명에서 흙막이벽의 H-파일에 받침브라켓을 설치한 뒤 받침브라켓 위에 장선철근, 철망형 거푸집, 스틸 웨일 구조체, 매입형 RC보 철근틀, 받침각관을 설치한 상태의 평면도Figure 10 is a plan view of the state installed the reinforcement bracket, wire mesh formwork, steel wale structure, embedded RC beam reinforcement frame, support angle tube on the support bracket after installing the support bracket on the H- pile of the earth wall in the present invention
도 11은 본 발명에서 흙막이벽의 H-파일이 설치된 위치의 단면도11 is a cross-sectional view of the installation position of the H-pile of the retaining wall in the present invention
도 12는 본 발명에 따른 시공 과정에서 슬래브 시공 후 합벽 시공 과정에서 수직철근의 배근상태를 도시한 도면12 is a view showing the reinforcement state of the vertical rebar in the plywood construction process after the slab construction in the construction process according to the present invention
도 13은 도 12에서 'C' 방향에서 본 수직철근의 배근상태를 나타낸 도면FIG. 13 is a view illustrating a reinforcement state of vertical rebars viewed from a direction 'C' in FIG. 12.
도 14는 본 발명에 따른 스틸 웨일 구조체의 다양한 실시예를 도시한 도면14 illustrates various embodiments of a steel wale structure in accordance with the present invention.
도 15는 본 발명에 따른 스틸 웨일 구조체에서 측면부재와 중간부재로 사용되는 판재의 여러 예를 도시한 단면도15 is a cross-sectional view showing several examples of the plate used as the side member and the intermediate member in the steel wale structure according to the present invention
도 16은 본 발명에서 개구부의 시공 상태를 보여주는 도면16 is a view showing a construction state of the opening in the present invention
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
100 : 흙막이벽 101 : H-파일100: retaining wall 101: H- pile
110 : 지하합벽 111 : 지하외벽110: underground plywood 111: underground outer wall
112 : 안쪽 수직철근 113 : 바깥쪽 수직철근112: inside vertical bar 113: outside vertical bar
115 : 다월 철근 116 : 수평철근115: Dowel rebar 116: horizontal rebar
121 : 매입거푸집 122 : 받침브라켓121: purchase die 122: support bracket
123 : 장선철근 124 : 철망형 거푸집123: Jangbar rebar 124: wire mesh formwork
125 : 받침각관 130 : 스틸 웨일 구조체125: support angle tube 130: steel wale structure
131 : 전면부재 132 : 후면부재131: front member 132: rear member
133a, 133b : 측면부재 134 : 중간부재133a, 133b: side member 134: intermediate member
135 : 보강부재 135: reinforcing member
141 : 슬래브 구축용 거푸집 구조체(데크 플레이트)141: formwork for the slab construction (deck plate)
150 : 매입형 RC보 철근틀 151 : 수평철근150: embedded RC beam rebar frame 151: horizontal rebar
152 : 외곽철근 153 : 보조브라켓152: outer reinforcement 153: auxiliary bracket
OP : 개구부 S : 슬래브 OP: opening S: slab
S1 : 매입슬래브 S2 : 노출슬래브S1: embedded slab S2: exposed slab
Claims (11)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020090021841 | 2009-03-13 | ||
| KR20090021841 | 2009-03-13 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| KR100951097B1 true KR100951097B1 (en) | 2010-04-07 |
Family
ID=42219536
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| KR1020090062871A Active KR100951097B1 (en) | 2009-03-13 | 2009-07-10 | Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket |
Country Status (1)
| Country | Link |
|---|---|
| KR (1) | KR100951097B1 (en) |
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101852016A (en) * | 2010-06-11 | 2010-10-06 | 中国二十二冶集团有限公司 | One-time installation of scaffolding construction method for super-long vertical reinforcement of underground wall |
| KR101034853B1 (en) | 2010-06-22 | 2011-05-17 | (주)씨엠파트너스건축사사무소 | Reversal Construction Method of Underground Structures through Front Support of Retaining Walls and Uneven Surface Corresponding Forms |
| KR101046941B1 (en) | 2011-03-14 | 2011-07-07 | 주식회사 하이드로코리아 | Ramen Bridge Construction Method Excluding Hunts |
| KR101215764B1 (en) | 2011-05-13 | 2013-01-09 | 삼성중공업 주식회사 | A burial slab structure of an outer wall of an underground construction |
| KR101473218B1 (en) | 2013-04-24 | 2014-12-16 | 황기수 | A construction method of an underground structure |
| WO2015105230A1 (en) * | 2014-01-13 | 2015-07-16 | 윤동현 | Underground structure construction method using sump |
| KR101627708B1 (en) | 2015-06-25 | 2016-06-07 | 주식회사 거원에코텍 | Apparatus and method for closing an opening of building slab formed by the interference with the temporary structure |
| KR101665909B1 (en) * | 2016-02-19 | 2016-10-17 | 주식회사 세진이엔시 | Composite wall structure of underground outer wall with cip retaining wall |
| CN106168035A (en) * | 2016-08-17 | 2016-11-30 | 广州地铁设计研究院有限公司 | The subassembly formula construction method of subassembly formula underground structure and underground structure |
| KR20170012017A (en) | 2015-07-24 | 2017-02-02 | (주)씨지스플랜 | Edge girder for slurry wall |
| CN106522261A (en) * | 2016-10-26 | 2017-03-22 | 国家电网公司 | Reinforcing structure and method of double-cement tower in coal gob area |
| JP2017119968A (en) * | 2015-12-28 | 2017-07-06 | 株式会社大林組 | Evaluation method of piles made of soil cement column walls |
| CN109025260A (en) * | 2018-07-26 | 2018-12-18 | 中民筑友科技投资有限公司 | A kind of prefabricated floor slab back casting band joint structure and its construction method |
| KR20190091397A (en) | 2018-01-27 | 2019-08-06 | 양병진 | Grouting method for joint portion of concrete structure in construction and top-down joint grouting method for underground structure using the same |
| KR102156793B1 (en) | 2019-12-24 | 2020-09-16 | (주)동아엔지니어링 | Top-down method for underground structure to prevent sinkhole |
| KR20200114553A (en) * | 2019-03-29 | 2020-10-07 | 유병훈 | Underground structure with top-down construction method using underground column wall and construction method therefor |
| KR20210013888A (en) * | 2019-07-29 | 2021-02-08 | 유병훈 | Top-down construction method with underground utility |
| CN115387502A (en) * | 2022-09-20 | 2022-11-25 | 中建三局集团有限公司 | Same-layer construction system and construction method for assembled partition wall and main body structure |
| KR102579169B1 (en) * | 2023-06-02 | 2023-09-14 | 홍승대 | Top-down method using suspended rebar |
| KR102579166B1 (en) * | 2023-06-02 | 2023-09-14 | 홍승대 | Top-down Structures Using Suspended rebar |
| CN117905108A (en) * | 2024-03-19 | 2024-04-19 | 福建一建集团有限公司 | Construction method for building engineering reverse construction method of civil air defense in heavy-layer water-bearing sand layer |
| KR20240085473A (en) | 2022-12-08 | 2024-06-17 | 송성민 | Underground structure with top-down construction method using underground column wall and roof pipe structure, and construction method therefor |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR200370135Y1 (en) | 2004-09-09 | 2004-12-13 | 박무용 | Forms for edge girder construction |
| KR20060107638A (en) * | 2005-04-11 | 2006-10-16 | (주)에스피에스 | Supporting Structure of Underground Retaining Wall and Construction Method of Building Underground Wall Using the Same |
| KR100722198B1 (en) | 2006-04-17 | 2007-05-29 | (주) 씨엠파트너스 | Reverse support structure of earth wall for continuous construction of underground plywood and continuous construction method of underground plywood applying the same |
-
2009
- 2009-07-10 KR KR1020090062871A patent/KR100951097B1/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR200370135Y1 (en) | 2004-09-09 | 2004-12-13 | 박무용 | Forms for edge girder construction |
| KR20060107638A (en) * | 2005-04-11 | 2006-10-16 | (주)에스피에스 | Supporting Structure of Underground Retaining Wall and Construction Method of Building Underground Wall Using the Same |
| KR100722198B1 (en) | 2006-04-17 | 2007-05-29 | (주) 씨엠파트너스 | Reverse support structure of earth wall for continuous construction of underground plywood and continuous construction method of underground plywood applying the same |
Cited By (26)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101852016A (en) * | 2010-06-11 | 2010-10-06 | 中国二十二冶集团有限公司 | One-time installation of scaffolding construction method for super-long vertical reinforcement of underground wall |
| KR101034853B1 (en) | 2010-06-22 | 2011-05-17 | (주)씨엠파트너스건축사사무소 | Reversal Construction Method of Underground Structures through Front Support of Retaining Walls and Uneven Surface Corresponding Forms |
| KR101046941B1 (en) | 2011-03-14 | 2011-07-07 | 주식회사 하이드로코리아 | Ramen Bridge Construction Method Excluding Hunts |
| KR101215764B1 (en) | 2011-05-13 | 2013-01-09 | 삼성중공업 주식회사 | A burial slab structure of an outer wall of an underground construction |
| KR101473218B1 (en) | 2013-04-24 | 2014-12-16 | 황기수 | A construction method of an underground structure |
| WO2015105230A1 (en) * | 2014-01-13 | 2015-07-16 | 윤동현 | Underground structure construction method using sump |
| KR101627708B1 (en) | 2015-06-25 | 2016-06-07 | 주식회사 거원에코텍 | Apparatus and method for closing an opening of building slab formed by the interference with the temporary structure |
| KR20170012017A (en) | 2015-07-24 | 2017-02-02 | (주)씨지스플랜 | Edge girder for slurry wall |
| JP2017119968A (en) * | 2015-12-28 | 2017-07-06 | 株式会社大林組 | Evaluation method of piles made of soil cement column walls |
| KR101665909B1 (en) * | 2016-02-19 | 2016-10-17 | 주식회사 세진이엔시 | Composite wall structure of underground outer wall with cip retaining wall |
| CN106168035A (en) * | 2016-08-17 | 2016-11-30 | 广州地铁设计研究院有限公司 | The subassembly formula construction method of subassembly formula underground structure and underground structure |
| CN106522261A (en) * | 2016-10-26 | 2017-03-22 | 国家电网公司 | Reinforcing structure and method of double-cement tower in coal gob area |
| KR20190091397A (en) | 2018-01-27 | 2019-08-06 | 양병진 | Grouting method for joint portion of concrete structure in construction and top-down joint grouting method for underground structure using the same |
| CN109025260A (en) * | 2018-07-26 | 2018-12-18 | 中民筑友科技投资有限公司 | A kind of prefabricated floor slab back casting band joint structure and its construction method |
| KR20200114553A (en) * | 2019-03-29 | 2020-10-07 | 유병훈 | Underground structure with top-down construction method using underground column wall and construction method therefor |
| KR102210345B1 (en) * | 2019-03-29 | 2021-02-01 | 유병훈 | Underground structure with top-down construction method using underground column wall and construction method therefor |
| KR20210013888A (en) * | 2019-07-29 | 2021-02-08 | 유병훈 | Top-down construction method with underground utility |
| KR102292152B1 (en) | 2019-07-29 | 2021-08-24 | 유병훈 | Top-down construction method with underground utility |
| KR102156793B1 (en) | 2019-12-24 | 2020-09-16 | (주)동아엔지니어링 | Top-down method for underground structure to prevent sinkhole |
| CN115387502A (en) * | 2022-09-20 | 2022-11-25 | 中建三局集团有限公司 | Same-layer construction system and construction method for assembled partition wall and main body structure |
| CN115387502B (en) * | 2022-09-20 | 2023-12-22 | 中建三局集团有限公司 | Same-layer construction system and construction method for assembled partition wall and main body structure |
| KR20240085473A (en) | 2022-12-08 | 2024-06-17 | 송성민 | Underground structure with top-down construction method using underground column wall and roof pipe structure, and construction method therefor |
| KR102579169B1 (en) * | 2023-06-02 | 2023-09-14 | 홍승대 | Top-down method using suspended rebar |
| KR102579166B1 (en) * | 2023-06-02 | 2023-09-14 | 홍승대 | Top-down Structures Using Suspended rebar |
| CN117905108A (en) * | 2024-03-19 | 2024-04-19 | 福建一建集团有限公司 | Construction method for building engineering reverse construction method of civil air defense in heavy-layer water-bearing sand layer |
| CN117905108B (en) * | 2024-03-19 | 2024-05-28 | 福建一建集团有限公司 | Construction method for building engineering reverse construction method of civil air defense in heavy-layer water-bearing sand layer |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100951097B1 (en) | Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket | |
| KR100927344B1 (en) | Construction method for connecting underground structure and underground structure using connection structure for underground construction | |
| KR101148272B1 (en) | Downward Construction Method of Basement applying SCFSliding Channel Form | |
| KR101344063B1 (en) | The construction method of steel-concrete underpass | |
| JP6855296B2 (en) | Building foundation structure and its construction method | |
| KR100531385B1 (en) | Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab | |
| KR20090094971A (en) | Under ground top-down method | |
| TWM428973U (en) | Building structure with stay-in-place mould | |
| KR100938395B1 (en) | Construction method of underground roadway using steel composite wall pile | |
| KR101167511B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
| KR100634726B1 (en) | Slab construction structure of underground structure and slab and underground retaining wall construction method without frame rib | |
| KR101230986B1 (en) | Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow | |
| KR102286225B1 (en) | Method for constructing underground structure busing PC integrating method without support | |
| KR100640244B1 (en) | Construction Method of Slab-Outer Wall Simultaneous Placement Using Basement File Without Edge Beam | |
| JP4083334B2 (en) | Underground structure having arch roof and method for constructing the same | |
| KR20100118482A (en) | To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method | |
| JP7344721B2 (en) | Roof structures and their construction methods | |
| CN113294175A (en) | Construction method of tunnel secondary lining structure and tunnel secondary lining structure | |
| KR101483865B1 (en) | Construction Method of Underground Structure using Composite Wale | |
| KR200370135Y1 (en) | Forms for edge girder construction | |
| KR101908943B1 (en) | RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa | |
| KR100351135B1 (en) | Method of constructing arch ring of steel framed reinforced concrete arch bridge | |
| KR100620366B1 (en) | Construction method of underground structures including composite reinforced concrete beams | |
| KR200385376Y1 (en) | Form system for construction of underground slab | |
| KR101028695B1 (en) | PC beam connection structure combined with steel frame or steel pipe column in underground reverse drilling method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A201 | Request for examination | ||
| PA0109 | Patent application |
Patent event code: PA01091R01D Comment text: Patent Application Patent event date: 20090710 |
|
| PA0201 | Request for examination | ||
| A302 | Request for accelerated examination | ||
| PA0302 | Request for accelerated examination |
Patent event date: 20090717 Patent event code: PA03022R01D Comment text: Request for Accelerated Examination Patent event date: 20090710 Patent event code: PA03021R01I Comment text: Patent Application |
|
| E902 | Notification of reason for refusal | ||
| PE0902 | Notice of grounds for rejection |
Comment text: Notification of reason for refusal Patent event date: 20091006 Patent event code: PE09021S01D |
|
| E701 | Decision to grant or registration of patent right | ||
| PE0701 | Decision of registration |
Patent event code: PE07011S01D Comment text: Decision to Grant Registration Patent event date: 20100114 |
|
| GRNT | Written decision to grant | ||
| PR0701 | Registration of establishment |
Comment text: Registration of Establishment Patent event date: 20100329 Patent event code: PR07011E01D |
|
| PR1002 | Payment of registration fee |
Payment date: 20100330 End annual number: 3 Start annual number: 1 |
|
| PG1601 | Publication of registration | ||
| FPAY | Annual fee payment |
Payment date: 20130326 Year of fee payment: 4 |
|
| PR1001 | Payment of annual fee |
Payment date: 20130326 Start annual number: 4 End annual number: 4 |
|
| FPAY | Annual fee payment |
Payment date: 20140326 Year of fee payment: 5 |
|
| PR1001 | Payment of annual fee |
Payment date: 20140326 Start annual number: 5 End annual number: 5 |
|
| FPAY | Annual fee payment |
Payment date: 20170321 Year of fee payment: 8 |
|
| PR1001 | Payment of annual fee |
Payment date: 20170321 Start annual number: 8 End annual number: 8 |
|
| FPAY | Annual fee payment |
Payment date: 20190328 Year of fee payment: 10 |
|
| PR1001 | Payment of annual fee |
Payment date: 20190328 Start annual number: 10 End annual number: 10 |
|
| FPAY | Annual fee payment |
Payment date: 20200305 Year of fee payment: 11 |
|
| PR1001 | Payment of annual fee |
Payment date: 20200305 Start annual number: 11 End annual number: 11 |
|
| PR1001 | Payment of annual fee |
Payment date: 20210329 Start annual number: 12 End annual number: 12 |
|
| PR1001 | Payment of annual fee |
Payment date: 20220329 Start annual number: 13 End annual number: 13 |
|
| PR1001 | Payment of annual fee |
Payment date: 20230329 Start annual number: 14 End annual number: 14 |
|
| PR1001 | Payment of annual fee |
Payment date: 20240328 Start annual number: 15 End annual number: 15 |
|
| PR1001 | Payment of annual fee |
Payment date: 20250331 Start annual number: 16 End annual number: 16 |