GB1110410A - A method of erecting subterranean structures - Google Patents
A method of erecting subterranean structuresInfo
- Publication number
- GB1110410A GB1110410A GB20082/65A GB2008265A GB1110410A GB 1110410 A GB1110410 A GB 1110410A GB 20082/65 A GB20082/65 A GB 20082/65A GB 2008265 A GB2008265 A GB 2008265A GB 1110410 A GB1110410 A GB 1110410A
- Authority
- GB
- United Kingdom
- Prior art keywords
- apertures
- supplied
- soil
- subterranean
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000000034 method Methods 0.000 title abstract 2
- 239000000463 material Substances 0.000 abstract 4
- 239000002689 soil Substances 0.000 abstract 3
- 239000004568 cement Substances 0.000 abstract 2
- 230000015572 biosynthetic process Effects 0.000 abstract 1
- 238000007599 discharging Methods 0.000 abstract 1
- 238000005553 drilling Methods 0.000 abstract 1
- 239000012530 fluid Substances 0.000 abstract 1
- 238000011065 in-situ storage Methods 0.000 abstract 1
- 230000003014 reinforcing effect Effects 0.000 abstract 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B17/00—Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
- E21B17/18—Pipes provided with plural fluid passages
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D1/00—Investigation of foundation soil in situ
- E02D1/02—Investigation of foundation soil in situ before construction work
- E02D1/04—Sampling of soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/24—Placing by using fluid jets
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B10/00—Drill bits
- E21B10/46—Drill bits characterised by wear resisting parts, e.g. diamond inserts
- E21B10/50—Drill bits characterised by wear resisting parts, e.g. diamond inserts the bit being of roller type
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B25/00—Apparatus for obtaining or removing undisturbed cores, e.g. core barrels or core extractors
- E21B25/08—Coating, freezing, consolidating cores; Recovering uncontaminated cores or cores at formation pressure
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Physics & Mathematics (AREA)
- Fluid Mechanics (AREA)
- Geochemistry & Mineralogy (AREA)
- Mechanical Engineering (AREA)
- Soil Sciences (AREA)
- Analytical Chemistry (AREA)
- Chemical & Material Sciences (AREA)
- Piles And Underground Anchors (AREA)
Abstract
1,110,410. Wells etc.; cast in situ piles. I. FAILLA. 12 May, 1965 [13 May, 1965], No. 20082/65. Headings E1F and E1H. A subterranean structure is formed by sinking a tubular member 3 into the ground, and by discharging material forming part of the structure from apertures 2 in the lower end of the member as it is withdrawn from the ground. During the formation of a pile the soil within the member, or material (including reinforcing) replacing this soil, is impregnated with cement mix supplied through the apertures. The cement mix may be supplied so that it does not impregnate the central part of the soil within the member, and this part is removed so that a lined shaft is formed. The member may have an annular bit 12 and drilling fluid may be supplied through the apertures. A number of piles formed by the process may overlap one another to form a subterranean wall. The member may have a rectangular cross section. The material discharged from the apertures may be heated, and material may be supplied from the apertures during sinking the member.
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| IT1036864 | 1964-05-13 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| GB1110410A true GB1110410A (en) | 1968-04-18 |
Family
ID=11134066
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| GB20082/65A Expired GB1110410A (en) | 1964-05-13 | 1965-05-12 | A method of erecting subterranean structures |
Country Status (4)
| Country | Link |
|---|---|
| BE (1) | BE663872A (en) |
| CH (1) | CH466997A (en) |
| GB (1) | GB1110410A (en) |
| NL (1) | NL6506137A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2000040808A1 (en) * | 1999-01-07 | 2000-07-13 | Menard Soltraitement | Method and device for forming a foundation pipe pile in the ground |
| EP1342851A1 (en) * | 2002-03-08 | 2003-09-10 | BVV Spezialtiefbautechnik Vertriebs GmbH | Method and apparatus for forming a soil-concrete trench wall |
| CN102677658A (en) * | 2012-04-25 | 2012-09-19 | 北京市三一重机有限公司 | Pile construction method and pile casings |
| CN115899442A (en) * | 2022-12-08 | 2023-04-04 | 中交第四航务工程局有限公司 | Newly-built river channel strides across oil gas pipeline and encapsulates protection device |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4621950A (en) * | 1983-01-18 | 1986-11-11 | Electric Power Research Institute | Techniques for establishing inground support footings and for strengthening and stabilizing the soil at inground locations |
| NL8403277A (en) * | 1984-10-29 | 1986-05-16 | Verstraeten Funderingstech Bv | METHOD FOR FORMING A HOLE IN THE GROUND; ALSO CAVE, OPEN AND BOTTOM OPEN BODY, DESIGNED FOR APPLICATION IN THIS METHOD. |
| NL191893C (en) * | 1984-12-06 | 1996-10-04 | Verstraeten Funderingstech Bv | Method and device for forming a sealing wall in the ground. |
| NL8700246A (en) * | 1987-02-02 | 1988-09-01 | Stichting Waterbouwkundig Lab | METHOD AND APPARATUS FOR INSULATING, TREATING AND / OR REMOVING IN CELLS HIGHLY CONTAMINATED MATERIAL IN OR ON THE SOIL. |
| FR2610652B1 (en) * | 1987-02-09 | 1991-09-06 | Soletanche | METHOD FOR REINFORCING A TUBULAR BATTERY PILE, PIE OBTAINED BY THIS PROCESS, DEVICE FOR IMPLEMENTING THE PROCESS |
| WO1990011412A1 (en) * | 1989-03-22 | 1990-10-04 | Iniectojet S.P.A. | A procedure for the forming of consolidation and foundation piles with embedded reinforcements |
-
1965
- 1965-05-06 CH CH631765A patent/CH466997A/en unknown
- 1965-05-12 GB GB20082/65A patent/GB1110410A/en not_active Expired
- 1965-05-13 BE BE663872D patent/BE663872A/xx unknown
- 1965-05-13 NL NL6506137A patent/NL6506137A/xx unknown
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2000040808A1 (en) * | 1999-01-07 | 2000-07-13 | Menard Soltraitement | Method and device for forming a foundation pipe pile in the ground |
| EP1342851A1 (en) * | 2002-03-08 | 2003-09-10 | BVV Spezialtiefbautechnik Vertriebs GmbH | Method and apparatus for forming a soil-concrete trench wall |
| CN102677658A (en) * | 2012-04-25 | 2012-09-19 | 北京市三一重机有限公司 | Pile construction method and pile casings |
| CN102677658B (en) * | 2012-04-25 | 2015-10-28 | 北京市三一重机有限公司 | hole pile construction method |
| CN115899442A (en) * | 2022-12-08 | 2023-04-04 | 中交第四航务工程局有限公司 | Newly-built river channel strides across oil gas pipeline and encapsulates protection device |
| CN115899442B (en) * | 2022-12-08 | 2023-09-15 | 中交第四航务工程局有限公司 | Protection device is sealed to new construction river course span oil gas pipeline |
Also Published As
| Publication number | Publication date |
|---|---|
| BE663872A (en) | 1965-09-01 |
| CH466997A (en) | 1968-12-31 |
| NL6506137A (en) | 1965-11-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA1050291A (en) | Process for providing a foundation pile for alternating compressive and tractive stresses and a pile thus provided | |
| GB1429107A (en) | Method for installing concrete anchor piles in situ | |
| IT8223387A1 (en) | EQUIPMENT FOR MAKING CAST-IN-SITE TUBULAR POLES, AND PROCEDURE FOR CONSTRUCTING SUCH POLES USING SUCH EQUIPMENT | |
| US3852966A (en) | Method for consolidating impermeable soils and pile provided thereby as fitted with spaced apart enlargements | |
| GB1110410A (en) | A method of erecting subterranean structures | |
| DE2011823A1 (en) | Method of creating watertight barriers | |
| US3191390A (en) | Method of preparing subsurface and forming concrete column therein | |
| RU93057042A (en) | METHOD OF MANUFACTURING PUNCHED PILED | |
| US3097492A (en) | Method of forming concrete piles in situ | |
| RU2087617C1 (en) | Method for construction of cast-in-place pile | |
| SU1162900A1 (en) | Method of reinforcing pile foundation | |
| GB1026094A (en) | Method and apparatus for forming piles and buried continuous walls | |
| US3064438A (en) | Pile and method of installing the same | |
| GB1030619A (en) | A process for the production of piles | |
| SU1677180A1 (en) | Method of manufacturing reinforced cast-in-place pile | |
| CN207987928U (en) | A kind of foundation pit supporting construction | |
| JPS58189414A (en) | Construction of sheathing wall | |
| SU903473A1 (en) | Method of constructing cast-in-place piles | |
| GB1500835A (en) | Concrete pile construction | |
| SU958595A1 (en) | Method of producing cast-in-place pile | |
| DE936561C (en) | Procedure for sinking sheep | |
| DE767144C (en) | Manufacture of foundation bodies in the underwater concreting process | |
| NL7510980A (en) | Prodn. of precast concrete pile foundations - using auger to predrill hole for hollow pile passing flushing fluid and filled in situ | |
| SU97752A1 (en) | The method of manufacture of concrete piles | |
| SU1033752A1 (en) | Method of hydraulic fracturing of rock |