DE19802654A1 - Modular octagonal industrial unit as prefabricated unit with central supply systems and completed by optional extensions on one or more sides - Google Patents
Modular octagonal industrial unit as prefabricated unit with central supply systems and completed by optional extensions on one or more sidesInfo
- Publication number
- DE19802654A1 DE19802654A1 DE1998102654 DE19802654A DE19802654A1 DE 19802654 A1 DE19802654 A1 DE 19802654A1 DE 1998102654 DE1998102654 DE 1998102654 DE 19802654 A DE19802654 A DE 19802654A DE 19802654 A1 DE19802654 A1 DE 19802654A1
- Authority
- DE
- Germany
- Prior art keywords
- unit
- module
- industrial
- sides
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 7
- 239000010959 steel Substances 0.000 claims abstract description 7
- 239000011150 reinforced concrete Substances 0.000 claims description 3
- 239000011178 precast concrete Substances 0.000 claims 1
- 239000004567 concrete Substances 0.000 abstract description 4
- 238000010276 construction Methods 0.000 description 22
- 230000008901 benefit Effects 0.000 description 5
- 238000000034 method Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 3
- 238000005253 cladding Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000003860 storage Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H5/00—Buildings or groups of buildings for industrial or agricultural purposes
- E04H5/02—Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H1/00—Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
- E04H1/005—Modulation co-ordination
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B2001/0053—Buildings characterised by their shape or layout grid
- E04B2001/0084—Buildings with non right-angled horizontal layout grid, e.g. triangular or hexagonal
- E04B2001/0092—Small buildings with hexagonal or similar horizontal cross-section
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
Gegenstand der Erfindung ist eine neue Konzeption für Industrieanlagen, die aus Modulen in Achteckform konzipiert sind.The invention relates to a new concept for industrial plants, which are designed from modules in octagon shape.
Diese Baukonzeption ermöglicht es Industrieanlagen zu errichten, die je nach Produktivitäts- oder Verfahrenserfordernissen, aus einem oder mehreren Modulen bestehen.This construction concept enables industrial plants to be erected according to productivity or process requirements, from one or consist of several modules.
Diese Möglichkeiten bringen besonders chemischen Industrieanlagen große Vorteile.These possibilities bring great opportunities especially for chemical industrial plants Benefits.
Die Größe (Außen∅) der achteckigen Module beträgt ca. 24 m. Diese Größenordnung ergibt sich durch Erfahrungswerte bisher erstellter konventioneller Industrieanlagen unter Beachtung von Menge, Größe und Art des Equipments.The size (outside∅) of the octagonal modules is approx. 24 m. This order of magnitude results from past experience conventional industrial plants considering quantity, size and Equipment type.
Es sind im Industrieanlagenbau bereits verschiedene Bauausführungen bekannt.There are already different types of construction in industrial plant construction known.
Die bisher am meisten verwirklichten Anlagenprojekte gruppieren sich in der sogenannten Raffineriebauweise in langgestreckter Rechteckform längsseits einer Versorgungseinheit (Rohrbrücke, Rohrtrasse) oder der sogenannten Fabrikbauweise in rechteckiger oder viereckiger Form. The most implemented plant projects are grouped into the so-called refinery construction in an elongated rectangular shape alongside a supply unit (pipe bridge, pipe route) or the so-called factory construction in rectangular or square shape.
Für die Errichtung dieser konventionellen Industrieanlagen ist das Vorhandensein optimaler, also geradliniger und großflächiger Grundflächen notwendig.That is for the construction of these conventional industrial plants Presence of optimal, that is straightforward and large-area base areas necessary.
Zum anderen werden noch immer die verschiedenen Gewerke wie Bau, Stahlbau, Equipment, Rohrleitungen, Armaturen usw. in aufwendiger Weise Teil für Teil montiert.On the other hand, the various trades such as construction, Steel construction, equipment, pipes, fittings, etc. in a complex manner Assembled part by part.
Die Verteuerung und Verknappung von idealen Bauarealen und der Zwang zur Kostenminimierung aufgrund des scharfen Wettbewerbes im Anlagenbaugeschäft macht es unmöglich, an den bisherigen Konzepten festzuhalten.The increase in price and shortage of ideal building areas and the constraint to minimize costs due to the fierce competition in the Plant construction business makes it impossible to stick to the previous concepts to hold on.
Ziel der Erfindung ist es technische und ökonomische Vorteile gegenüber den bisherig bekannten Bauweisen zu erzielen.The aim of the invention is to offer technical and economic advantages to achieve the previously known designs.
Durch die Modulbauweise wird erheblich weniger Grundfläche benötigt (Fig. 8, 9), das bedeutet Kosteneinsparung bei den Grundstückskosten.Due to the modular design, considerably less floor space is required ( Fig. 8, 9), which means cost savings in property costs.
Durch die Modulbauweise ergibt sich eine kostengünstigere Bauausführung (30-40%). Zum einen durch weniger Grundfläche, zum anderen durch die nur einmal anfallenden Engineeringaktivitäten sowie durch Serieneffekt bei Herstellung mehrerer Module.The modular design results in a more cost-effective construction (30-40%). On the one hand by less floor space, on the other hand by the one-off engineering activities as well as through series effects when producing several modules.
Aufgrund der kompakten kreisförmigen Bauweise ergeben sich auch im Bereich der technischen Ausrüstung durch kürzere Wege zwischen den jeweiligen Apparaten im Rohrleitungs-, Elektro-, Meßtechnik-, Isolier- und Anstrichbereich Kosteneinsparungen (15-20%). Due to the compact circular design, the Area of technical equipment due to shorter distances between the respective apparatus in piping, electrical, measuring technology, insulation and Painting area cost savings (15-20%).
Die Modulbauweise bietet ausgezeichnete Möglichkeiten der Nutzung unsymmetrischer Geländevorgaben. Konkret bedeutet dies Kundenwünsche bezüglich vorhandener Baulücken im bestehenden Werksgelände oder Umgehung von nicht zu beseitigten Hindernissen (Fig. 9, 11) zu verwirklichen.The modular design offers excellent opportunities for using asymmetrical terrain specifications. Specifically, this means realizing customer requests with regard to vacant lots in the existing factory premises or avoiding obstacles that cannot be removed ( Fig. 9, 11).
Eine Erweiterung einer Industrieanlage in Modulbauweise ist nach fast jeder Seite des Modules möglich. Falls eine Industrieanlage bereits nach Verfahrensstufen in mehreren Modulen (Fig. 8, 9, 11) konzipiert ist, kann eine Erweiterung einzelner Verfahrensstufen unproblematisch verwirklicht werden.An industrial plant in modular design can be extended on almost every side of the module. If an industrial plant is already designed according to process stages in several modules ( Fig. 8, 9, 11), an extension of individual process stages can be implemented without problems.
Je nach Bedarf können Industrieanlagen in Modulbauweise in Freiluft- oder geschlossener Bauweise ausgeführt werden (Fig. 1, 2, 3).Depending on requirements, industrial plants can be designed in modular construction in open-air or closed construction ( Fig. 1, 2, 3).
Diese Modulbauweise ist gleichermaßen günstig in Stahlbau-, Stahlbeton- oder in Betonfertigbauweise zu verwirklichen.This modular design is equally cheap in steel construction, reinforced concrete or to be realized in prefabricated concrete.
Industrieanlagen in Modulbauweise ermöglichen schnellere und günstigere Montagen, da die Module bereits vor Fertigstellung von Bodenplatte und Fundamenten separat gefertigt werden können und dann als Komplettbauwerk montiert werden.Industrial plants in modular design enable faster and cheaper Assembly, since the modules are already in place before the base plate and Foundations can be made separately and then as Complete structure can be assembled.
Dieser schnellere Montagefortschritt erspart Baukosten und ermöglicht einen früheren Produktionsbeginn. This faster assembly progress saves construction costs and enables an earlier start of production.
Durch die Modulform erhält der Anlagenbetreiber Vorteile für Wartung und Reparatur, da sich von fast allen Seiten immer die kürzesten Wege (für Kräne, Gerüste usw.) zu den jeweiligen Maschinen- oder Apparatekomponenten ergeben.The modular form gives the plant operator advantages for maintenance and Repairs, since the shortest paths (for Cranes, scaffolding etc.) to the respective machine or Apparatus components result.
Fig. 1 zeigt Ebene + 6,0 m einer chem. Industrieanlage, konzipiert in Modulbauweise, Fig. 1 shows level + 6.0 m of a chem. Industrial plant, designed in modular design,
Fig. 2 zeigt Ebene ±0 (Bodenplatte u. Fundamente) einer chem. Industrieanlage in Modulbauweise, Fig. 2 shows level ± 0 (base plate and foundations) of a chem. Industrial plant in modular design,
Fig. 3 zeigt die Ansicht von II vorgenannter Ebenen, Fig. 3 shows the view of the abovementioned levels II,
Fig. 4 zeigt das Modul mit seinen konstruktiven Einzelteilen, Fig. 4 shows the module with its structural parts,
Fig. 5 zeigt das Modul als Einheit, Fig. 5 shows the module as a unit,
Fig. 6 zeigt Schnitt I-I durch das Modul, Fig. 6 shows section II through the module,
Fig. 7 zeigt das Detail III als Modulausschnitt von Fig. 1, Fig. 7 shows the detail III as a module portion of FIG. 1,
Fig. 8 zeigt Draufsicht bzw. Grundriß der Industrieanlagen 18 und 19, Fig. 8 shows plan view and plan view of industrial equipment 18 and 19,
Fig. 9 zeigt Draufsicht bzw. Grundriß der Industrieanlagen 20 und 21, Fig. 9 plan view and plan view showing the industrial plant 20 and 21,
Fig. 10, 11 zeigen ebenso wie Fig. 9 Industrieanlagenkonzeptionen mit Modulen. Fig. 10, 11 also as shown in FIGS. 9 industrial plant designs with modules.
Basis für die Konzipierung einer Industrieanlage in Modulbauweise ist das Modul 1.Module 1 is the basis for the design of an industrial plant in modular design.
Die Bestimmung der Größe des Moduls 1 ergibt sich zum einen aus dem vorhandenen Platzbedarf, im wesentlichen jedoch aus Art und Größe der zu planenden Industrieanlage. Daher ist es sinnvoll, bei der Berücksichtigung der Anzahl der Module 1 die Verfahrensschritte einer Industrieanlage zu beachten, um spätere Erweiterungen oder Ersatz von Equipment unproblematisch zu bewerkstelligen.The determination of the size of module 1 results on the one hand from the available space, but essentially from the type and size of the industrial plant to be planned. It is therefore advisable to take the process steps of an industrial plant into account when considering the number of modules 1 in order to be able to carry out subsequent extensions or replacement of equipment without problems.
Das Modul 1, das in den Fig. 1, 2, 8, 9, 10, 11 relativ schematisch dargestellt ist, wird in den Fig. 4, 5 klarer detailliert um den konstruktiven Aufbau besser zu verdeutlichen. Aufgrund der Größenordnung eines Moduls 1 mit ca. 24 m Außendurchmesser in Achteckform und der konstruktiven Gestaltung einer solchen Konstruktion ergeben sich zwangsläufig acht Stahlkonstruktionselemente in Trapezform.The module 1 , which is shown relatively schematically in FIGS. 1, 2, 8, 9, 10, 11, is clarified in more detail in FIGS. 4, 5 in order to better illustrate the construction. Due to the size of a module 1 with an outer diameter of approximately 24 m in octagon shape and the constructive design of such a construction, there are inevitably eight steel construction elements in a trapezoidal shape.
Um ein klareres Bild zu vermitteln wurde Modul 1 mit seinen Konstruktionselementen in Fig. 4 herausgerückt dargestellt.In order to convey a clearer picture, module 1 with its construction elements was shown in Fig. 4.
Als komplette Einheit wird Modul 1 in Fig. 5 gezeigt.Module 1 is shown as a complete unit in FIG. 5.
Das Modul wird in der Regel von den Stützen 3 (Stahl oder Fertigbeton) getragen. Bei Benötigung einer weiteren Ebene werden die Stützen 3, entsprechend bemessen, verlängert oder auf das Modul 1 aufgesetzt. The module is usually supported by supports 3 (steel or ready-mixed concrete). If a further level is required, the supports 3 are dimensioned accordingly, extended or placed on the module 1 .
Die konstruktive Anordnung der Apparate oder anderer Ausrüstungsteile auf dem Modul 1 wird in Detail III in Fig. 7 dargestellt.The structural arrangement of the apparatus or other equipment on the module 1 is shown in detail III in FIG. 7.
Fig. 1, 2, 3, 8, 9 zeigen die in Modulbauweise konzipierten Industrieanlagen 18 und 20. Das wesentliche hierbei ist, daß diesen Entwürfen bereits errichtete, in konventioneller Bauweise konzipierte Industrieanlagen 19 bzw. 21 zugrunde liegen. Fig. 1, 2, 3, 8, 9 show the designed in modular construction industry systems 18 and 20. The essential thing here is that these designs are based on industrial systems 19 and 21 which have already been constructed and designed in a conventional manner.
Anhand Fig. 8, 9 ist ersichtlich, wie im Bezug auf kompakte Bauweise und des erheblich geringeren Platzbedarfes, die Modulbauweise im Vorteil ist.With reference to Fig. 8, 9 can be seen, as is with respect to the compact design and considerably lower space requirements, the modular design advantage.
Bei der in Fig. 9 konzipierten Industrieanlage 20 wurden die Module einer U-förmigen Anordnung erstellt.In the industrial system 20 designed in FIG. 9, the modules of a U-shaped arrangement were created.
Es ergeben sich entsprechend der Verfahrensschritte fünf Module 1 als Industrieanlageneinheit und ein Modul 1 als Kopfgebäude 17. Wegen der Größe der Industrieanlage 20 wurde das Kopfgebäude 17 als volles Modul 1 konzipiert um den erhöhten Bedarf an Räumlichkeiten für Personal, Labor, Meß- und Steuerzentrale, Schalträume und Lagerflächen zu ermöglichen. Diese in Modulbauweise errichtete Industrieanlage erfüllt in dieser Version alle Voraussetzungen wie z. B. kürzeste Wege zum Energieversorger (Rohrbrücke 18), kompakte Bauweise, weniger Grundfläche, gute Erweiterungsmöglichkeiten nach vielen Seiten, gute De- und Montagemöglichkeiten usw.According to the method steps, five modules 1 result as an industrial plant unit and one module 1 as a head building 17 . Because of the size of the industrial plant 20 , the head building 17 was designed as a full module 1 in order to enable the increased need for rooms for staff, laboratory, measuring and control center, switch rooms and storage areas. In this version, this industrial plant, built in modular construction, fulfills all requirements such as: B. shortest routes to the energy supplier (pipe bridge 18 ), compact design, less floor space, good expansion options on many sides, good disassembly and assembly options, etc.
Einen kleinen Überblick von vielen Planungsmöglichkeiten zeigen die Fig. 8, 9, 10, 11.8, 9, 10, 11 show a small overview of many planning options .
Diese Möglichkeiten sind vor allem von Vorteil, wenn neue Produktionsstätten in Baulücken vorhandener Fabrikgelände oder in unsymmetrische Bauareale eingebunden werden sollen. These opportunities are especially beneficial when new Production sites in vacant lots of existing factory premises or in asymmetrical construction areas are to be integrated.
Nützliche Nebeneffekte des Moduls 1 ergeben sich durch die Öffnung 13, die in mannigfaltiger Weise genutzt werden kann.Useful side effects of module 1 result from opening 13 , which can be used in a variety of ways.
Das Kopfgebäude 17 wird sinnvollerweise in Stahlbetonkonstruktion konzipiert und kann entsprechend der klimatischen Voraussetzungen mit der Gebäudeverkleidung 12 versehen werden. The head building 17 is expediently designed in a reinforced concrete construction and can be provided with the building cladding 12 in accordance with the climatic conditions.
11
Modul - Achteckform
Module - octagon shape
22nd
Stützen
Support
33rd
Luftkühler
Air cooler
44th
Abscheider
Separator
55
Wärmetauscher
Heat exchanger
66
Reaktor
reactor
77
Behälter
container
88th
Verdampfer
Evaporator
99
Kompressoren
Compressors
1010th
Kolonnen
Columns
1111
Pumpen
pump
1212th
Gebäudeverkleidung
Building cladding
1313
Möglichkeiten für Fluchtwege, Materialversorgung, Montage
usw.
Options for escape routes, material supply, assembly, etc.
1414
Möglichkeiten für Labor, E-Schaltraum
Possibilities for laboratory, electrical control room
1515
Möglichkeiten für Personalbüros, Meß- und Steuerzentrale
Possibilities for personnel offices, measuring and control center
1616
Möglichkeiten für Lagerraum
Possibilities for storage space
1717th
Kopfgebäude
Head building
1818th
Modulkonzeption I
Module conception I
1919th
konservative Anlagenkonzeption I
conservative plant design I
2020th
Modulkonzeption II
Module concept II
2121
konservative Anlagenkonzeption II
conservative plant design II
2222
Träger (Wechsel)
Carrier (change)
2323
Tragsattel für Verdampfer
Carrier saddle for evaporators
2424th
Rohrbrücke oder Rohrtrasse
Pipe bridge or pipe route
2525th
Auffangtasse
Collecting cup
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE1998102654 DE19802654A1 (en) | 1998-01-24 | 1998-01-24 | Modular octagonal industrial unit as prefabricated unit with central supply systems and completed by optional extensions on one or more sides |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE1998102654 DE19802654A1 (en) | 1998-01-24 | 1998-01-24 | Modular octagonal industrial unit as prefabricated unit with central supply systems and completed by optional extensions on one or more sides |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE19802654A1 true DE19802654A1 (en) | 2000-01-20 |
Family
ID=7855552
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DE1998102654 Ceased DE19802654A1 (en) | 1998-01-24 | 1998-01-24 | Modular octagonal industrial unit as prefabricated unit with central supply systems and completed by optional extensions on one or more sides |
Country Status (1)
| Country | Link |
|---|---|
| DE (1) | DE19802654A1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE20211284U1 (en) | 2002-07-26 | 2002-11-14 | Graeff Container- und Hallenbau GmbH, 68199 Mannheim | Portable pavilion |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2456620A1 (en) * | 1974-11-29 | 1976-08-12 | Iii Emile Joseph Lacoste | Prefabricated component octagonal unit building - with common wall slabs and rectangular connecting spaces between adjacent room units |
| DE2943961A1 (en) * | 1979-10-31 | 1981-05-07 | Aka Aufbereitung Konstruktion | Large scale coal dressing plant - is laid out on single level in building with regular symmetrical floor area |
| WO1990008871A1 (en) * | 1989-01-27 | 1990-08-09 | Tsentralny Nauchno-Issledovatelsky I Proektno-Experimentalny Institut Promyshlennykh Zdany I Sooruzheny (Tsniipromzdany) | Single-storey multispan module industrial building |
| WO1992018725A1 (en) * | 1991-04-18 | 1992-10-29 | L-O Grudeborn Teknisk Utveckling Hb | Building assembly |
-
1998
- 1998-01-24 DE DE1998102654 patent/DE19802654A1/en not_active Ceased
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2456620A1 (en) * | 1974-11-29 | 1976-08-12 | Iii Emile Joseph Lacoste | Prefabricated component octagonal unit building - with common wall slabs and rectangular connecting spaces between adjacent room units |
| DE2943961A1 (en) * | 1979-10-31 | 1981-05-07 | Aka Aufbereitung Konstruktion | Large scale coal dressing plant - is laid out on single level in building with regular symmetrical floor area |
| WO1990008871A1 (en) * | 1989-01-27 | 1990-08-09 | Tsentralny Nauchno-Issledovatelsky I Proektno-Experimentalny Institut Promyshlennykh Zdany I Sooruzheny (Tsniipromzdany) | Single-storey multispan module industrial building |
| WO1992018725A1 (en) * | 1991-04-18 | 1992-10-29 | L-O Grudeborn Teknisk Utveckling Hb | Building assembly |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE20211284U1 (en) | 2002-07-26 | 2002-11-14 | Graeff Container- und Hallenbau GmbH, 68199 Mannheim | Portable pavilion |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DE1684724C3 (en) | Procedure for the erection of spiral structures. Eliminated from: 1431057 | |
| DE19802654A1 (en) | Modular octagonal industrial unit as prefabricated unit with central supply systems and completed by optional extensions on one or more sides | |
| DE102010010868A1 (en) | Multi-story building has closed outer facade, which is attached to supporting frame with ring-shaped ceilings, where supporting frame is made of multiple peripheral cores and multiple ceilings | |
| DE2206171A1 (en) | METHOD OF MANUFACTURING ROOM BOXES FOR FABRIC HOUSES | |
| DE2617504C2 (en) | Set of components for the construction of switchgear houses for electrical switchgear | |
| DE2061544A1 (en) | Method of erecting tall buildings made up of modular units | |
| DE1230993B (en) | Building with a supporting structure consisting of support plates and struts | |
| DE2049687B1 (en) | skyscraper | |
| DE2807553C2 (en) | Jacket for cooling towers or large chimneys and method for making the jacket | |
| DE10138813B4 (en) | Baumodulsatz | |
| AT411609B (en) | BUILDING OR Prefabricated house in modular steel skeleton construction | |
| AT332062B (en) | TRANSPORTABLE BUILDING | |
| DE2013044A1 (en) | building | |
| DE102009008697A1 (en) | Treatment tank with candle filter bottom construction | |
| AT265593B (en) | Multi-storey building | |
| DE2203761A1 (en) | COMPONENTS COMPATIBLE TO HOUSING UNITS OR THE SAME BY USING SUITABLE CONNECTING PARTS | |
| DD274250A1 (en) | MULTI-STOREY INDUSTRIAL PLANT FOR VARIABLE USE | |
| DE3423352A1 (en) | A service-engineering structure and an urban-development structure | |
| AT257893B (en) | Lightweight carrier | |
| DE19803149A1 (en) | House conversion | |
| DE1551407B2 (en) | REAR INSTALLATION FOR COOLING TOWERS OR REPLACEMENT DEVICES FOR THE TREATMENT OF LIQUIDS OR GASES | |
| AT352954B (en) | STEEL WATER TOWER | |
| DE19928479A1 (en) | Prefabricated block of flats for long and wide piece of ground | |
| EP1870528A2 (en) | Dismountable building | |
| DE541456C (en) | Outdoor switchgear |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| ON | Later submitted papers | ||
| OP8 | Request for examination as to paragraph 44 patent law | ||
| 8122 | Nonbinding interest in granting licenses declared | ||
| 8131 | Rejection |