DE1658747C - Method for producing a tunnel body - Google Patents
Method for producing a tunnel bodyInfo
- Publication number
- DE1658747C DE1658747C DE1658747C DE 1658747 C DE1658747 C DE 1658747C DE 1658747 C DE1658747 C DE 1658747C
- Authority
- DE
- Germany
- Prior art keywords
- tunnel
- walls
- ceiling
- support
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000004519 manufacturing process Methods 0.000 title claims description 6
- 238000000034 method Methods 0.000 claims description 10
- 239000007788 liquid Substances 0.000 claims description 9
- 230000009974 thixotropic effect Effects 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 5
- 238000005065 mining Methods 0.000 claims description 3
- 239000004567 concrete Substances 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 5
- 238000010276 construction Methods 0.000 description 3
- 239000011150 reinforced concrete Substances 0.000 description 3
- 230000000903 blocking effect Effects 0.000 description 2
- 238000011065 in-situ storage Methods 0.000 description 2
- 206010052428 Wound Diseases 0.000 description 1
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
Description
ι 2ι 2
Die Erfindung betrifft ein Verfahren zum Her- der seitlichen TragwHnde ouej Tragglieder ausgenutztThe invention relates to a method for making use of lateral support walls or support members
stellen eines Tunnelkörpers, bei dem im Erdreich werden kann. Schädliche Setzungen sind daher nichtprovide a tunnel body that can be buried in the ground. There are therefore no harmful subsidence
vor dem Herstellen der Tunneldecke von der Erd- zu ,befürchten. Wenn die Tragglieder als Schlitzwand-before making the tunnel ceiling from the earth to fear. If the support members are used as diaphragm wall
oberflüche aus bis unter die spätere Tunnelsohle abschnitte in der Flucht jeder Seitenwand im AbstandSurfaces from to below the later tunnel sole sections in line with each side wall at a distance
reichende seitliche Tragwünde oder mit Abstand von- 5 voneinander erstellt werden, so kann dieser AbstandReaching lateral support wounds or with a distance of 5 from each other are created, this distance can
einander in der Flucht jeder Seitenwand angeordnete etwa zwei bis drei Meter betragen. Die Länge derbe about two to three meters in alignment with each other in the alignment of each side wall. The length of the
Tragglieder bis mindestens zur Unterkante der Decke Schlitzabschnitte kann in der gleichen GrößenordnungSupport members to at least the lower edge of the ceiling slot sections can be of the same order of magnitude
reichend hergestellt werden und der zwischen den liegen, kann aber je nach den Verhältnissen auchcan be produced sufficiently and that lies between them, but can also, depending on the circumstances
seitlichen Tragwänden bzw. Traggliedern bestehende größer sein. Bei allen Ausführungsformen dt-τ Erfin-side walls or support members existing larger. In all embodiments dt-τ invent
Erdkern nach dem Einbau der Tunneldecke wegge- io dung besteht der Vorteil, daß Kanäle und Leitungen,The earth core after the installation of the tunnel ceiling has the advantage that channels and lines,
nommen wird. die quer zur Tunnelachse über den zu errichtendenis taken. the one across the tunnel axis over the one to be built
Es sind Verfahren dieser Art bekannt, bei denen Tunnelkörper hinweg verlaufen, erhalten bleiben die Tunneldecke unter Auflagerung auf den seitlichen können, da z. B. durchgehende Schlitzwände im Be-Tragwänden oder auf den in der Flucht jeder Seiten- re'ch von querverlaufenden Kanälen oder Leitungen wand angeordneten Traggliedern in offener Bauweise 15 nur unterhalb derselben mit Beton oder Stahlbeton hergestellt wird. Hierbei läßt sich, wenn der Tunnel- ausgefüllt zu werden brauchen oder im Abstand körper im Zuge städtischer Verkehrsstraßen herge- voneinander angeordnete Tragpfähle oder Schlitzstellt wird, nicht vermeiden, daß die Straße für die wandabschnitte an solchen Stellen von Übertage aus Herstellung der Tuiineldecke weggenommen und ge- eingebracht werden können, an denen sie mit diesen sperrt oder über der offenen Baugrube eine den ao Kanälen und Leitungen nicht in Berührung kommen. Straßenverkehr aufnehmende Abdeckung hergestellt Nachstehend ist die Erfindung an Hand der in der werden muß. Zeichnung als Beispiel dargestellten AusführungsformMethods of this type are known in which tunnel bodies run away and are retained the tunnel ceiling can be superimposed on the side, as z. B. continuous slotted walls in the loading bearing walls or on the alignment of each side right of transverse channels or lines wall arranged support members in open construction 15 only below the same with concrete or reinforced concrete will be produced. This can be done when the tunnel needs to be filled in or at a distance body in the course of urban traffic roads arranged support piles or slots will not avoid that the road for the wall sections in such places from above ground Production of the Tuiinel blanket can be removed and brought in, where they can be used with them blocks or over the open excavation one of the ao channels and lines do not come into contact. Road traffic receiving cover produced The invention is based on the in the must become. Drawing shown as an example embodiment
Der Erfindung liegt demgegenüber die Aufgabe beschrieben. Die Zeichnung zeigt den herzustellendenIn contrast, the object of the invention is described. The drawing shows the one to be produced
zugrunde, die Tunneldecke unter Beibehaltung der Tunnelkörper im Querschnitt.based on the tunnel ceiling while maintaining the tunnel body in cross section.
Straße und ohne Sperrung derselber; in solcher Weise as Die Herstellung des in der Zeichnung dargestelltenStreet and without blocking it; in such a way as The manufacture of what is shown in the drawing
herzustellen, daß die Decke zugleich zur wirksamen Tunnelkörpers erfolgt in an sich bekannter Weiseproduce that the ceiling at the same time to the effective tunnel body takes place in a manner known per se
gegenseitigen Aussteifung der seitlichen Tragwände derart, daß zunächst die seitlichen Tragwände 4 odermutual reinforcement of the side support walls such that initially the side support walls 4 or
oder Tragglieder dient und Setzungen außerhalb der an deren Stelle mit Abstand voneinander in deror support members is used and settlements outside the instead of at a distance from each other in the
Tragwände vermied, ι werden. Flucht jeder Seitenwand 3 angeordnete TraggliederSupport walls avoided, ι. Align each side wall 3 arranged support members
Die Lösung der Aufgabe besteht gemäß der Erfin- 30 von der Straßen- bzw. Erdoberfläche aus eingebrachtAccording to the invention, the object is achieved by introducing it from the road surface or the surface of the earth
dung darin, daß die Tunneldecke in bergmännischer werden, dann die Tunneldecke 1 eingebaut undtion in the fact that the tunnel ceiling in mining, then installed the tunnel ceiling 1 and
Bauweise als Gewölbedecke eingubau' wird. schließlich der zwischen den seitlichen TragwändenConstruction as a vaulted ceiling is built. finally the one between the side walls
Die seitlichen Tragwände können hierbei als zu- bzw. Traggliedern bestehende Erdkern unterirdischThe side load-bearing walls can be used as connecting or supporting elements underground
sammenhängende Schlitzwände mit Hilfe von thixo- weggenommen wird.contiguous diaphragm walls are removed with the help of thixo-.
troper Flüssigkeit hergestellt werden. Die seitlichen 35 Die seitlichen Tragwände 4 können als zuspmmen-tropical liquid can be produced. The lateral 35 The lateral supporting walls 4 can be used as a zuspmmen-
Tragwände können aber auch aus dicht an dicht hängende Schlitzwände unter Verwendung von thixo-Support walls can also be made from tightly hanging diaphragm walls using thixo-
eingebrachten Tragpfählen hergestellt werden. troper Flüssigkeit hergestellt werui,i und im Bereichinstalled support piles are made. troper liquid manufactured werui, i and in the area
Das Verfahren gemäß der Erfindung kann auch so der Seitenwände 3 des Tunnelkörpers diese gegebedurchgeführt werden, daß die Tragglieder als Schlitz- nenfalls selbst bilden. Die seitlichen Tragwände wandabschnitte mit Hilfe von thixotroper Flüssigkeit 40 können jedoch auch aus dicht an dicht eingebrachten im Abstand voneinander hergestellt werden, und daß Tragpfählen, vorzugsweise in Form von Ortbetondie Zwischenräume zwischen je zwei in Flucht liegen- pfählen, von Übertage aus im Boden hergestellt den, ausbetonierten Schlitzwandabschnitten nach dem werden. Weiterhin können an Stelle von geschlossenen Einbau der Tunneldecke durch Betonieren von ent- seitlichen Tragwänden auch seitliche Tragglieder im sprechenden Abschnitten der Seitenwände vom 45 Abstand voneinander in der Flucht jeder Seitenwand Tunnelinnem aus geschlossen werden. gebildet werden. Derartige Tragglieder können alsThe method according to the invention can also be carried out against the side walls 3 of the tunnel body that the support members form themselves as slots. The side load-bearing walls However, wall sections with the aid of thixotropic liquid 40 can also be introduced from close together are made at a distance from each other, and that support piles, preferably in the form of in-situ concrete Gaps between each two in alignment piles, made from above ground in the ground the, concreted diaphragm wall sections after being. Furthermore, instead of closed Installation of the tunnel ceiling by concreting lateral load-bearing walls and lateral load-bearing members in the speaking portions of the side walls spaced 45 apart from each other in line with each side wall Inside the tunnel are closed. are formed. Such support members can be used as
Weiterhin ist es möglich, daß die Tragglieder aus Schlitzwandabschnitte unter Verwendung von thixo-Furthermore, it is possible that the support members from diaphragm wall sections using thixo-
mit Abstand voneinander eingebrachten, vorzugsweise troper Flüssigkeit oder als Tragpfähle hergestelltpreferably tropical liquid introduced at a distance from one another or made as support piles
mit Hilfe von thixotroper Flüssigkeit hergesteliten werden. Bei Anwendung von Tragpfählen könnenbe produced with the help of thixotropic liquid. When using support piles, you can
Tragpfählen gebildet werden, und daß die Zwischen- 50 diese z. B. einen Durchmesser von 80 cm und eineSupport piles are formed, and that the intermediate 50 these z. B. a diameter of 80 cm and one
räume zwischen je zwei in Flucht liegenden Trag- Lange von 20 bis 25 m haben. Die OrtbetonpfähleHave spaces between each two in alignment bearing lengths of 20 to 25 m. The in-situ concrete piles
pfählen nach dem Einbau der Tunneldecke durch können ebenfalls unter Zuhilfenahme von thixotroperpiles after the installation of the tunnel ceiling can also be done with the help of thixotropic
Betonieren von entsprechenden Abschnitten der Flüssigkeit hergestellt, und, wie bereits erwähnt,Concreting made of appropriate sections of the liquid, and, as already mentioned,
Scitcnwändc vom Tunnelinnem aus geschlossen gegebenenfalls auch dicht an dicht in Form vonScitcnwändc closed from the inside of the tunnel, possibly also close together in the form of
werden. 55 Pfahlwänden erstellt werden. Bei seitlichen Trag-will. 55 pile walls are to be built. With side carrying
Bei allen Ausfuhrungsformen des Verfahrens nach gliedern in Form von Schlitzwandabschnittcn in der der Erfindung braucht eine Straße, in derem Zuge Flucht jeder Seitenwand 3 kann der Abstand zwischen ein Tunnelkörper herzustellen ist, nur in geringer zwei Schlitzabschnitten etwa zwei bis drei Meter be-Breite für die anfängliche Herstellung der seitlichen tragen. In jedem Fall werden die seitlichen Trag· Tragwände oder der in der Flucht der Seitenwände βο wände oder die seitlichen Tragglieder mit einer Bezu bildenden Traggllcder nur kurzzeitig in schmalen wehrung versehen, die mindestens bis zur Unterkante Streifen in Anspruch genommen werden, so daß in der noch herzustellenden Tunneldecke reicht. Hier* den meisten Füllen eine Sperrung der Straß* nicht durch werden nach Erhärten des Betons Stahlbetonerforderlich ist. Weiterhin wird bei der bergmännl- auflager für die Tunneldecke 1 gebildet, sehen Herstellung der Tunneldecke als Gewölbedecke 65 Gemäß der Erfindung wird die Tunneldecke 1 in ermöglicht, daß diese so mit den seitlichen Trag- bergmännischer Bauweise als Gewölbedecke einge* wänden oder Traggliedern verbunden werden kann, baut. Die Art und Weise des bergmännischen Vordaß der Gewölbeschub zur gegenseitigen Aussteifung triebe» ist für die Erfindung ohne Bedeutung. Bei* In all embodiments of the method according to subdivide in the form of Schlitzwandabschnittcn in the invention, a road in which the alignment of each side wall 3, the distance between a tunnel body is to be established, only in less than two slot sections about two to three meters wide for the initial manufacture of the side wear. In any case, the side load-bearing walls or those in alignment with the side walls or the side load-bearing members with a cover are only briefly provided in narrow reinforcement, which are used at least up to the lower edge of the strip, so that in the still tunnel ceiling to be produced is sufficient. Here * most of the filling a blocking of the road * is not necessary after hardening of the concrete reinforced concrete. Furthermore, the tunnel ceiling 1 is formed in the mining industry, see production of the tunnel ceiling as a vaulted ceiling 65. According to the invention, the tunnel ceiling 1 is made possible so that it can be walled in with the lateral support miner's construction as a vaulted ceiling or connected with support members , builds. The manner in which the miners did so that the vault thrust drove for mutual reinforcement »is of no importance for the invention. At*
1 8581 858
spielsweisa könnte ein Messervortrieb angewendet werden, In jedem Falle werden aber vor dem Betonieren der Decke an den seitlichen Tragwa"nden4 oder an den seitlichen Traggliedern in Höhe der Kämpfer 2 Auflager gebildet, die den Gewölbeschub der fertig betonierten Tunneldecke 1 auf die seitlichen Tragwände oder Traggüeder übertragen, so daß für diese eine wirksame gegenseitige Aussteifung gebildet wird.For example, a knife advance could be used In any case, before the ceiling is concreted on the side walls4 or on the lateral support members at the level of the fighters 2 supports are formed, which push the arch the finished concreted tunnel ceiling 1 transferred to the side bearing walls or Traggüeder, so that for this forms an effective mutual reinforcement.
Bei der dargestellten Ausführungsform sind die seitlichen Tragwände 4 bzw. die seitlichen Tragglieder von der Kämpferhöhe bis zur Scheitelhöhe der Tunneldecke betoniert, enthalten jedoch in diesem Bereich keine Bewehrung. Oberhalb dieser Höhe kann eine Kiesfüllung angeordnet sein. Die Tragwände 4 bzw. Tragglieder reichen mit ihren unteren Enden jeweils etwa zwei Meter unter die Sohlenunterkante des herzustellenden Tunnelkörpers. Bei im Abstand voneinander angeordneten Schlitzwandabschnitten oder Tragpfählen können die Seitenwände 3 des Tunnelkörpers in den jeweiligen Zwischenräumen zwischen den in Flucht liegenden Traggliedern in an sich bekannter Weise aus Beton oder Stahlbeton vom Tunnelinnern aus hergestellt werden. asIn the embodiment shown, the side support walls 4 or the side support members concreted from the transom height to the apex height of the tunnel ceiling, but included in this Area no reinforcement. A gravel filling can be arranged above this height. The supporting walls 4 or support members extend with their lower ends about two meters below the lower edge of the sole of the tunnel body to be produced. In the case of diaphragm wall sections arranged at a distance from one another or support piles can be the side walls 3 of the tunnel body in the respective intermediate spaces between the aligned Support members made in a known manner from concrete or reinforced concrete from the inside of the tunnel will. as
Claims (6)
Family
ID=
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3042942A1 (en) * | 1980-11-14 | 1982-06-03 | Bilfinger + Berger Bauaktiengesellschaft, 6800 Mannheim | Tunnel construction under undisturbed earth surface - involves excavating tunnel core while prefab. roof sections are inserted on initially sunk side walls |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3042942A1 (en) * | 1980-11-14 | 1982-06-03 | Bilfinger + Berger Bauaktiengesellschaft, 6800 Mannheim | Tunnel construction under undisturbed earth surface - involves excavating tunnel core while prefab. roof sections are inserted on initially sunk side walls |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DE3401629A1 (en) | Block, and wall formed from blocks of this type | |
| DE2142894C3 (en) | Process for the production of a continuous diaphragm wall | |
| DE68904949T2 (en) | Methods and components for the construction of underground garages. | |
| DE1947249C3 (en) | Method for producing a diaphragm wall in the ground and prefabricated part for carrying out the method | |
| DE1658747C (en) | Method for producing a tunnel body | |
| DE2724680A1 (en) | Multi-span bridge with ground level traffic route - has posts in drilled holes and superstructure formed on ground later excavated | |
| DE69403971T2 (en) | Method for executing a sheet pile wall and wall segment used for this | |
| DE1658747B1 (en) | Method for producing a tunnel body | |
| DE2747774C3 (en) | Holding device for support cheeks to support slope material on an embankment | |
| DE3218516C2 (en) | ||
| DE1153048B (en) | Prefabricated concrete slab for making or repairing concrete roads | |
| DE1910556B2 (en) | Process for the production of in-situ concrete piles with extensions of the pile shaft and the pile base | |
| DE2510912C3 (en) | Method for building the lining of a bunker, in particular in underground mining and device for carrying out the method | |
| AT357328B (en) | LOST FORMWORK FOR A FOUNDATION OF A SUPPORTING COMPONENT | |
| DE3630053A1 (en) | Slope sheeting | |
| DE3320772A1 (en) | Method of producing wall-shaped structures in the earth and displacement body for carrying out the method | |
| DE3623178C2 (en) | ||
| AT271552B (en) | Tunnel body for underground railways and process for its manufacture | |
| DE3514333A1 (en) | Method of producing a concrete structure, preferably a tunnel tube | |
| DE2217459A1 (en) | PROCEDURES AND EQUIPMENT FOR UNDER CONSTRUCTION OF STRUCTURES AND TRAFFIC ROUTES | |
| AT390290B (en) | Method of producing a slope protective structure, and slope protective structure produced according to this method | |
| CH505943A (en) | Method for producing a tunnel body | |
| DE1634445A1 (en) | Method for sealing the vertical construction joints of a concrete or reinforced concrete wall to be built underground | |
| AT384640B (en) | Sound-absorbing cladding for a wall, supporting cultivated greenery | |
| DE392341C (en) | Process for the construction of tunnels with built-in invert, especially under urban roads |