DE102004057459A1 - Railway crossing safety system - Google Patents
Railway crossing safety system Download PDFInfo
- Publication number
- DE102004057459A1 DE102004057459A1 DE200410057459 DE102004057459A DE102004057459A1 DE 102004057459 A1 DE102004057459 A1 DE 102004057459A1 DE 200410057459 DE200410057459 DE 200410057459 DE 102004057459 A DE102004057459 A DE 102004057459A DE 102004057459 A1 DE102004057459 A1 DE 102004057459A1
- Authority
- DE
- Germany
- Prior art keywords
- level crossing
- controller
- frequency
- track circuit
- track
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B61—RAILWAYS
- B61L—GUIDING RAILWAY TRAFFIC; ENSURING THE SAFETY OF RAILWAY TRAFFIC
- B61L29/00—Safety means for rail/road crossing traffic
- B61L29/08—Operation of gates; Combined operation of gates and signals
- B61L29/18—Operation by approaching rail vehicle or train
- B61L29/22—Operation by approaching rail vehicle or train electrically
- B61L29/226—Operation by approaching rail vehicle or train electrically using track-circuits, closed or short-circuited by train or using isolated rail-sections
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Train Traffic Observation, Control, And Security (AREA)
Abstract
Die Erfindung betrifft ein Bahnübertragungssicherungssystem mit einem Bahnübergangssicherungscontroller zur Steuerung von Sicherungseinrichtungen, insbesondere Lichtsignalanlagen, sowie ein Verfahren zur Überwachung und Ansteuerung eines Bahnübergangssicherungssystems. Um auf Kabelverbindungen weitgehend verzichten zu können, ist vorgesehen, dass der Bahnübergangscontroller von einem frequenzgesteuerten Gleisstromkreis für Fernbereich (LFTC - Long Frequency-operated Track Circuit) aktivierbar und von einem frequenzgesteuerten Gleisstromkreis für Nahbereich (SFTC - Short Frequency-operated Track Circuit) deaktivierbar ist.The invention relates to a railway transfer security system with a level crossing protection controller for controlling safety devices, in particular traffic signal systems, as well as a method for monitoring and controlling a level crossing safety system. In order to be able to largely dispense with cable connections, it is provided that the level crossing controller can be activated by a frequency-controlled track circuit for long-range-operated track circuit (LFTC) and deactivated by a frequency-controlled track circuit for short-range (SFTC - short frequency-operated track circuit) ,
Description
Die Erfindung betrifft ein Bahnübergangssystem gemäß dem Oberbegriff des Patentanspruchs 1.The The invention relates to a level crossing system according to the generic term of claim 1
Mehr als 60 % aller unbeschrankten Bahnübergänge weltweit sind einfache Anwendungen. Dabei handelt es sich überwiegend um eingleisige Bahnstrecken mit bidirektionaler Verkehrsführung. Entlang der Strecke ist kein Kabelnetz vorhanden und es gibt keine Elektro- oder Gerätehäuser an den Einschaltpunkten.More As 60% of all unrestricted level crossings worldwide are simple Applications. These are predominantly single-track rail lines with bidirectional traffic guidance. Along there is no cable network on the route and there are no electrical or sheds the switch-on points.
Der Erfindung liegt die Aufgabe zugrunde, ein Bahnübergangssicherungssystem der gattungsgemäßen Art anzugeben, dessen Bahnübergangscontroller weitgehend kabellos ansteuerbar ist.Of the Invention is based on the object, a level crossing protection system of generic type specify whose level crossing controller is largely wirelessly controlled.
Die Aufgabe wird mit den kennzeichnenden Merkmalen des Anspruchs 1 gelöst.The The object is achieved with the characterizing features of claim 1.
Die beanspruchte Anlage zur Sicherung und Steuerung von Bahnübergängen ist ein computergestütztes System, das speziell für einfache Anwendungen vorgesehen ist. Das System ist, verglichen mit anderen computergestützten und konventionellen relaisgestützten Bahnübergangssystemen, in Bezug auf Sicherheit und Preis höchst konkurrenzfähig.The claimed system for securing and controlling level crossings is a computer aided System specifically for simple applications is provided. The system is compared to other computer aided and conventional relay-based Level crossing systems, highly competitive in terms of safety and price.
Das System, nachfolgend LX7 genannt, verfügt über die Funktionalität eines automatisierten Bahnübergangssicherungssystems für eine eingleisige Bahnstrecke mit bidirektionaler Verkehrsführung.The System, hereafter called LX7, has the functionality of a automated level crossing system for one single-track railway with bidirectional traffic management.
Die fahrzeuggesteuerten Gleisstromkreise, nachfolgend FTC – Frequency-operated Track Circuit – genannt, dienen zur Erkennung von Zügen oder anderen Schienenfahrzeugen auf überwachten Streckenabschnitten. Ein FTC ist ein elektronischer Gleisstromkreis ohne isolierte Schienenstöße. Die Funktionalität des FTC beruht auf dem variablen Übertragungsbereich der Signale mit unterschiedlichen Frequenzen, die auf die Abweichungen der induktiven Komponente der Gleisimpedanz zurückzuführen sind. Somit bestimmt der mit dem Gleis verbundene Sender den Übergangsbereich in Abhängigkeit von seiner Arbeitsfrequenz. Der Empfänger, der in unmittelbarer Nähe des Senders an das Gleis angeschlossen sein kann, erkennt die Änderung der Gleisimpedanz. Wenn ein Zug oder ein anderes Schienenfahrzeug den kontrollierten Gleisabschnitt belegt, d. h. befährt und sich dem Anschlusspunkt des FTC annähert, verringert sich die Gleisimpedanz. Diese Änderung der Gleisimpedanz wird vom Empfänger des FTC registriert, der auf den Übertragungsbereich eingestellt und auf die Betriebsfrequenz des Senders abgestimmt ist.The vehicle-controlled track circuits, hereinafter FTC - Frequency-operated Track Circuit - called, serve to detect trains or other rolling stock on supervised sections. An FTC is an electronic track circuit without insulated rail joints. The functionality The FTC relies on the variable transmission range of the signals with different frequencies due to the deviations of the inductive component attributable to the track impedance. Thus, the transmitter connected to the track determines the transition region dependent on from his working frequency. The receiver, in the immediate Near the Transmitter can be connected to the track, recognizes the change the track impedance. If a train or another rail vehicle the track section checked, d. H. travels and As the FTC approaches the connection point, the track impedance decreases. This change the track impedance is from the receiver registered by the FTC, which is set to the transmission range and tuned to the operating frequency of the transmitter.
Nachfolgend wird die Erfindung anhand figürlicher Darstellungen näher erläutert. Es zeigenfollowing The invention is based figurlicher Representations closer explained. Show it
Die
schematische Anordnung der Komponenten für ein typisches Anwendungsbeispiel
ist in
In einer Grundversion sind als Sicherungseinrichtungen des LX7 rot/weiß blinkende Road Signals-Straßensignale-RS1 und RS2 sowie Warning Bells-Läutewerke-WB1 und WB2 vorgesehen. Aufgrund der modularen und erweiterbaren Struktur des LX7 kann das System zur Steuerung weiterer optionaler externer Sicherungseinrichtungen aufgerüstet werden, beispielsweise Boom Barriers-Schranken-BB1 und BB2 oder durchgehend gelb leuchtende und weiß blinkende Signallampen-Train Control Signals-TCS1 und TCS2.In A basic version are flashing red / white as safety devices of the LX7 Road Signals Road Signals RS1 and RS2 as well as Warning Bells Ringtone WB1 and WB2 provided. Due to the modular and expandable structure The LX7 allows the system to control additional optional external Safety devices are upgraded, for example, boom barrier barriers BB1 and BB2 or continuous yellow glowing and white flashing Signal Lamp Train Control Signals-TCS1 and TCS2.
Die PLC-Plattform ermöglicht einen einfachen Zugriff auf die Software, weit verbreitete Designtools sowie eine einfache Anpassung der Software an verschiedene Anwendungsbedürfnisse. Die Software des Systems wird aus unabhängigen funktionalen Modulen erstellt. Jedes Modul enthält eine spezielle Funktion oder Funktionsgruppe. Die Software wird nach dem Ladder-Logic-Prinzip entwickelt. Somit können Ingenieure, die mit der Konstruktion der Relaiskontakte vertraut sind, die Funktionalität des Systems problemlos verfolgen. Die wichtigsten Softwaremodule sind:
- • Modul für Steuerungs- und Überwachungsfunktion,
- • Modul für Anwendungsdaten,
- • Modul für Service, Diagnose und Ereignisprotokollierung,
- • Modul für Service-, Diagnose- und Ereignisprotokollierungsdaten,
- • Modul für SMS-Unterstützung.
- • module for control and monitoring function,
- • module for application data,
- • module for service, diagnostics and event logging,
- • module for service, diagnostic and event logging data,
- • Module for SMS support.
Das LX7 ist vorzugsweise für universelle Anwendbarkeit konzipiert. Landesspezifische Unterschiede, die durch die jeweili ge Eisenbahnbehörde vorgeschrieben sind, werden größtenteils innerhalb des Moduls für Anwendungsdaten definiert. Für die meisten Anwendungen beziehen sich die entsprechenden Änderungen jeweils auf unterschiedliche Einstellungen von Timern. Änderungen der Hardware und der landesspezifischen Software werden nur in sehr geringem Umfang erforderlich sein und sich vorwiegend auf die Schaltkreise der Relaisschnittstellen beschränken.The LX7 is preferably for Universal applicability designed. Country-specific differences, which are prescribed by the respective railway authority Mostly within the module for Application data defined. For most applications refer to the corresponding changes each on different settings of timers. amendments The hardware and the country specific software are only in great be required to a small extent and mainly on the circuits restrict the relay interfaces.
Das LX7 ist für einfache Anwendungen bestimmt und für alle Einsatzzwecke auf eingleisigen Strecken mit Gegenverkehr geeignet. In diesem Fall ist nur eine geringe Anzahl von Eingängen und Ausgängen erforderlich. Daher wird eine kostengünstige, für den Einsatzzweck adäquate Architektur verwendet. Bei diesem System ist jedoch die Möglichkeit einer Erweiterung durch Einbau zusätzlicher Ein-/Ausgänge und weiterer funktionaler Module nicht ausgeschlossen, so dass auch komplexere Anwendungen, z. B. zweigleisige Konfigurationen mit Implementierung der Down-Holding-Funktion, möglich sind. In solchen Fällen müssen jedoch Software- und Hardwareerweiterungen für das jeweilige Land vorgenommen werden.The LX7 is for simple applications and intended for all applications on single-track routes suitable for oncoming traffic. In this case, only a small number of entrances and outputs required. Therefore, a cost-effective, adequate for the purpose of architecture used. With this system, however, there is the possibility of an extension by installing additional Input / Output and further functional modules are not excluded, so too more complex applications, eg. B. two-track configurations with implementation the down holding function, possible are. In such cases have to however, software and hardware enhancements have been made for each country become.
Der Sicherheit des Systems LX7 basiert auf PLC-Komponenten, die in einer Basisversion und einer ausfallsicheren F-Version- Failsafe-erhältlich sind. Die F-Versionen sind bis zu SIL3 entsprechend den CENELEC-Normen zertifiziert. Die Sicherheit des Systems ist skalierbar, so dass die verschiedenen SIL-Anforderungen erfüllt werden können. Die Basisversion des LX7 ist auf die Einhaltung der Anforderungen gemäß SIL1/SIL2 ausgelegt. Mit der F-Version der PLCs kann das LX7 auf SIL3 und SIL4 aufgerüstet werden.Of the Security of the system LX7 is based on PLC components that are in one Basic version and a failsafe F-version failsafe available. The F versions are certified up to SIL3 according to the CENELEC standards. The Security of the system is scalable, so the different ones SIL requirements met can be. The basic version of the LX7 is based on meeting the requirements according to SIL1 / SIL2 designed. With the F version of the PLCs, the LX7 can run on SIL3 and Upgraded SIL4 become.
Die Ausgänge sind ausfallsicher konstruiert, d. h. diese befinden sich normalerweise in aktiviertem Zustand. Der Zustand der Ausgangsrelais wird durch den PLC auf der entsprechenden Verarbeitungsstufe abgerufen. Daher wird ein regelwidriger Zustand jedes einzelnen Relais erkannt und angezeigt, so dass Sicherheitsvorkehrungen über die Funktionalität des LX7 ausgeführt werden können.The outputs are designed fail-safe, d. H. These are usually in activated state. The state of the output relay is determined by the PLC retrieved at the appropriate processing level. Therefore, will a faulty state of each individual relay is detected and displayed so that safety arrangements over the functionality of the LX7 can be.
Die Software kann in Anlehnung an die Relaisschaltkreise, die sich seit vielen Jahren in Sicherheitsanwendungen bewährt haben, entwickelt werden. Bei der Definition einer gemeinsamen Funktionalität und der Entwicklung möglichst flexibel anwendbarer Software können verschiedene länderspezifische Praktiken berücksichtigt werden. Prüfschaltkreise dienen zur Lampenüberprüfung und zur Kontrolle der Blinkfunktionen, um die entsprechenden Ausfälle möglichst rechtzeitig zu erkennen und somit die SIL-Stufe des Systems zu erhöhen.The Software can be modeled on the relay circuits that have been around many years in security applications have proven to be developed. When defining a common functionality and the Development as possible flexible software can different country-specific Considered practices become. checking circuits serve for lamp checking and to control the flashing functions to minimize the corresponding failures detect in time and thus increase the SIL level of the system.
Durch Verwendung der optionalen Zugkontrollsignale TCS ((Anspruch 3) lässt sich bei Bedarf ebenfalls die SIL-Stufe des Systems erhöhen. Das TCS kann das Streckensignal nur dann auf Weiterfahrt stellen, wenn die entsprechenden Freigabebedingungen erfüllt sind, nämlich Bahnübergang eingeschaltet, Streckensignalleuchten funktionsfähig und LX7 fehlerfrei. Für die Funktionsüberwachung des LX7 wird ein Arbeitskontakt Fehlererkennungsrelais FDR (Fault Detection Relay) bereitgestellt (Anspruch 4). Das FDR führt die Überwachungsfunktionen für den PLC aus. Die Funktionsfähigkeit des FDR wird unmittelbar nach jeder Aktivierung des LX7 überprüft. Das Zeitfenster, in dem ein potenzieller Ausfall des PLC unerkannt bleiben könnte, wird somit erheblich eingeschränkt. Das FDR muss aktiviert und betriebsbereit sein, damit die Zugkontrollsignale TCS auf Freigabe geschaltet werden können.By using the optional train control signals TCS (claim 3), the SIL level of the system can also be increased if necessary.The TCS can only continue the route signal if the appropriate release conditions are met, namely, railroad crossing turned on, beacon lights functional, and LX7 The FDR performs the monitoring functions for the PLC The FDR functionality is checked immediately after each activation of the LX7 Thus, a potential failure of the PLC could go undetected, thus severely limited.The FDR must be activated and ready for operation so that the train control signals TCS on Release can be switched.
Das beschriebene skalierbare Sicherheitskonzept des LX7 in Verbindung mit seiner relativ einfachen Architektur, der ge ringen Komponentenzahl sowie seiner hohen Zuverlässigkeit erfüllt ein breites Spektrum der von Eisenbahnbehörden gestellten Anforderungen in Bezug auf die Ausfallsicherheit von Systemen.The described scalable security concept of the LX7 in connection with its relatively simple architecture, the number of components and the number of rings its high reliability Fulfills a wide range of requirements imposed by railway authorities in terms of system resilience.
Das LX7 überwacht ständig einen Annäherungsabschnitt, um einen ggf. herannahenden Zug zu erkennen. Dabei ist das LX7 in der Lage, die erforderliche Anzahl von Annäherungsgleisabschnitten, den Freigabegleisabschnitt und einen zusätzlichen Overlay-Freigabedetektor mit geeigneter Schnittstellenkonstruktion zu überwachen, ohne dass die Software des Controllers geändert werden muss. Der Annäherungsgleisabschnitt – vorsignalabstand – wird beispielsweise in einem Intervall von 25 bis 90 Sekunden – bis max. 2 km definiert, je nachdem, welche Höchstgeschwindigkeit im Annäherungsgleisabschnitt erreicht werden kann.The LX7 monitors constantly a rapprochement section, to detect a possibly approaching train. The LX7 is in capable of the required number of approach track sections, the Release track section and an additional overlay enable detector monitor with appropriate interface design without the software changed the controller must become. The approaching track section - pre-signal spacing - becomes, for example in an interval of 25 to 90 seconds - up to max. 2 km defined, depending on which maximum speed in the approach track section can be achieved.
Das LX7 verfügt vorzugsweise über eine integrierte direktionale Selbsthaltungsfunktion, so dass eine Reaktivierung des LX7 durch einem abfahrenden Zug verhindert wird.The LX7 features preferably over an integrated directional self-holding function, so that one Reactivation of the LX7 is prevented by a departing train.
Die Abfolge der Belegung und die Freigabe der Einschalt- und Ausschaltkomponenten werden durch den Controller überprüft und registriert. Wenn ein Fehler festgestellt wird, schaltet das LX7 die Streckensignallampen aus – dunkle Signale. Bei einem Fehler des Controllers wird der Blinkausgang deaktiviert und die Stromversorgung für die Streckensignallampen wird unterbrochen – dunkle Signale.The Sequence of the assignment and the release of the switch-on and switch-off components are checked and registered by the controller. If an error is detected, the LX7 switches the track signal lamps out - dark Signals. If the controller fails, the flashing output will turn on disabled and the power supply for the track signal lamps is interrupted - dark Signals.
Wenn die erste Achse des ankommenden Zuges den Annäherungsgleisabschnitt erreicht hat, aktiviert sich das LX7 und schaltet die weißen Lampen der Straßensignale aus. Zugleich werden die roten Lampen der Straßensignale eingeschaltet. Nachdem die letzte Achse des abfahrenden Zuges den Freigabe gleisabschnitt verlassen hat, deaktiviert sich das LX7 und schaltet die roten Straßensignallampen aus und die weißen Straßensignallampen wieder ein. Bei einer normalen Zugfreigabemeldung des LX7 muss das rote Blinklicht der Straßensignale spätestens 5 Sekunden nach dem Verlassen des Freigabegleisabschnitts auf das weiße Blinklicht umschalten. Das Blinken des Signals wird durch die Software generiert und überwacht, so dass die verschiedenen Blinkfrequenzen und Einschaltzyklen unterstützt werden. Für die Schnittstellen werden Halbleiterrelais verwendet.If the first axis of the incoming train reaches the approach track section has activated the LX7 and turns off the white lights of the road signals out. At the same time, the red lights of the road signals are switched on. After this the last axis of the departing train the release track section has left, the LX7 deactivates and turns off the red road signal lamps and the white ones Road signal lamps again. In a normal train release message the LX7 must red flashing light of the road signals no later than 5 seconds after leaving the release track section on the white Switch flashing light. The flashing of the signal is through the software generated and monitored, so that the different flashing frequencies and switch-on cycles are supported. For the Interfaces are used semiconductor relay.
Normalerweise erkennt das LX7 mit dem LFTC und dem SFTC einen Zug auf dem Zufahrtsgleis. Voraussetzung ist, dass die Schienengleise im Annäherungsabschnitt durchgängig geschweißt oder auf eine andere geeignete Weise verbunden sind, wobei der Annäherungsabschnitt mindestens über einen Ballastwiderstand von 1,5 Ohm/km verfügen muss. Die beidseitige Überwachung der Annäherungsabschnitte erfolgt mit der LFTC – bidirektionalen Anwendung. Wahlweise ist auch eine einseitige Anwendung möglich. In diesem Fall sind isolierte oder elektrische Schienenlaschen am LX7-Standort zu montieren. Außerdem werden zwei Einheiten des LFTC benötigt – jeweils eine Einheit pro Annäherungsgleisabschnitt. Die Vorteile in diesem Fall bestehen in der Möglichkeit der Erkennung des herannahenden Zuges sowie in den längeren Annäherungsgleisabschnitten.Usually recognizes the LX7 with the LFTC and the SFTC a train on the access track. The condition is that the rail tracks in the approach section continuously welded or in any other suitable manner, the approaching section at least one Ballast resistance of 1.5 ohms / km must have. The bilateral surveillance the approach sections is done with the LFTC bidirectional application. Optionally, a one-sided application is possible. In this case are Install insulated or electrical rail straps at the LX7 location. Furthermore Two units of the LFTC are required - one unit each Approach track section. The advantages in this case consist in the possibility of detecting the approaching train as well as in the longer approach track sections.
Das LFTC kann im LX7-Gehäuse eingebaut werden. Ein Einbau in einem Gehäuse entlang der Strecke ist jedoch ebenfalls möglich, beispielsweise als Remote-Einschaltmodul mit hoher Reichweite. Auch das SFTC kann im LX7-Gehäuse eingebaut werden.The LFTC can be in the LX7 case to be built in. An installation in a housing along the track is but also possible for example, as a remote power-on module with a long range. Also the SFTC can be in the LX7 case to be built in.
Falls der vorhandene Gleisabschnitt zu lang für die Freigabe ist, kann das SFTC zusätzlich als Overlay-Schaltkreis verwen det werden, um die erforderliche Länge des Freigabegleisabschnitts zu erreichen. Falls das vorhandene Gleis zu lang für die Annäherungssignalisierung ist, kann auch das LFTC zusätzlich als Overlay-Schaltkreis verwendet werden, um die erforderliche Länge des Annäherungsgleisabschnitts zu erreichen – kabellose Anwendung vom Ende des vorhandenen Gleises. Das FTC, das zur Ferneinschaltung dient, benötigt lediglich zwei Leiter des Signalkabels pro Empfänger zur Übertragung der Informationen "Belegt/Frei" an das LX7. Bei doppeltem Empfänger werden vier Leiter benötigt, um zwei Impulsrelais am LX7-Standort anzusteuern.If the existing track section is too long for the release, that can SFTC additionally verwen be used as an overlay circuit to the required length of the Reach clearance section. If the existing track too long for the proximity signaling is, the LFTC can also used as an overlay circuit to the required length of the Approach track section to reach - wireless Application from the end of the existing track. The FTC, the remote power on serves, needs only two wires of the signal cable per receiver for transmitting the information "busy / free" to the LX7. at double receiver four conductors are needed by two pulse relays at the LX7 site head for.
Falls der Annäherungsgleisabschnitt für eine festgelegte maximale Zeitspanne belegt war und der Freigabebereich nicht ausgelöst wurde, wird ein Fehler des Annäherungsdetektors festgestellt sowie gemeldet, und die Streckensignalleuchten werden abgeschaltet. Auch andere Fehler und Störungen des Annäherungsdetektors und des Freigabedetektors können erkannt und gemeldet werden.If the approach track section for a fixed maximum time was used and the release area was not triggered, becomes an error of the proximity detector be detected and reported, and the signal lights will be off. Also other errors and disturbances of the proximity detector and the release detector be detected and reported.
Wenn keine externe Stromversorgung – 230 V/50 Hz – vorhanden ist, die Batterie jedoch betriebsbereit ist, wird eine Unterbrechung erkannt und gemeldet. Die normale Funktionsweise wird davon jedoch nicht beeinträchtigt. Bei einer zu geringen Akkuspannung kann ein Fehler der Batterie erkannt und gemeldet werden. Die Streckensignalleuchten werden dann ausgeschaltet.If no external power supply - 230 V / 50 Hz - available is, but the battery is ready, is an interruption detected and reported. The normal functioning of it is however not impaired. If the battery voltage is too low, the battery may fail be detected and reported. The signal lights then become switched off.
Beim Ausfall einer Glühlampe eines Streckensignals wird die Ersatzglühlampe automatisch eingeschaltet, und die Unterbrechung der Lampenfunktion wird erkannt bzw. gemeldet. Das gilt auch für den Ausfall eines Straßensignals.In the event of failure of a light bulb of a track signal, the replacement bulb is automatically turned on, and the interruption of the lamps Function is recognized or reported. This also applies to the failure of a road signal.
Falls die Blinkfrequenz oder der Einschaltzyklus außerhalb des voreingestellten Bereiches liegen, wird ein Fehler des Blinkmoduls festgestellt und gemeldet.If the flashing frequency or the duty cycle outside the preset one Range are located, an error of the flashing module is detected and reported.
Nachdem das System die erste reguläre fehlerfreie Zugdurchfahrt registriert hat und keine weiteren Gründe für einen Systemfehlerzustand vorliegen, schaltet das System in den Normalzustand zurück und schaltet die weißen Blinkleuchten der Streckensignale ein.After this the system is the first regular faultless train passage has registered and no further reasons for one System error state, the system switches to the normal state back and turns off the white ones Flashing lights of the route signals on.
Das LX7 kann auch in Bahnhofsbereichen eingesetzt werden, in denen Signale innerhalb der Annäherungsgleisabschnitte – Sicherungssignale für den Bahnübergang – vorhanden sind. Die Aktivierung des LX7 durch die Belegung des Annäherungsgleisabschnitts wird hier deaktiviert, solange das Haltesignal gesetzt ist. In Abhängigkeit von der Stellung des Signals und der Zuggeschwindigkeit ist es unter Umständen erforderlich, die Freigabestellung des Sicherungssignals durch Blockierung im Bahnhof zu verzögern, um einen ausreichenden Warnzeitraum für das LX7 zu gewährleisten.The LX7 can also be used in station areas where signals within the approach track sections - safety signals for the Railroad crossing - available are. Activation of the LX7 by occupying the approach track section is deactivated here, as long as the hold signal is set. Dependent on the position of the signal and the train speed may require the release position of the backup signal by blocking in To delay station, to ensure a sufficient warning period for the LX7.
Das
Stromversorgungssystem des LX7 (
Bei Sytemen mit direkter Energieerzeugung vor Ort, die über eine Alarmanlage mit Sirenen verfügen, kann ein Eingang des Controllers speziell für das Senden von SMS-Meldungen an einen zuentralen Dispatcher reserviert werden (Anspruch 5). Die Spannung der Akkus wird überwacht. Falls diese Spannung unter den zulässigen Mindestwert fällt, kann eine entsprechende SMS-Meldung an das zuständige Wartungspersonal gesendet werden. Das LX7 ist vorzugsweise in der Lage, SMS-Meldungen zu senden und zu empfangen. Als optionale Ausstattungsvariante kann das LX7 per SMS-Meldung neu gestartet werden, wenn das System fehlerfrei funktioniert. Wenn das LX7 einen Fehler, eine Störung oder ein anderes meldepflichtiges Ereignis feststellt, wird eine SMS-Meldung an das Wartungs- oder Wachpersonal oder den Zugdispatcher gesendet. Diese GSM-Meldung ent hält die ID-Nummer des Bahnübergangs, den Code bzw. die Beschreibung des Vorfalls und den Zeitpunkt des Vorfalls. Das LX7 ist vorzugsweise in der Lage, SMS-Meldungen als Empfangsbestätigung vom Dispatcher, Wach- oder Wartungspersonal zu empfangen.at Systems with direct on-site generation of energy via a Alarm system with sirens, can be an input of the controller specifically for sending SMS messages be reserved to a zuentraler Dispatcher (claim 5). The voltage the battery is being monitored. If this voltage falls below the allowed minimum value, can sent a corresponding SMS message to the responsible maintenance personnel become. The LX7 is preferably capable of sending SMS messages and to receive. As an optional equipment variant, the LX7 be restarted via SMS message if the system is error free works. If the LX7 has an error, an error or another reportable Event identifies an SMS message to the maintenance or security personnel or the train dispatcher. This GSM message contains the ID number the railroad crossing, the code or description of the incident and the time of the event Incident. The LX7 is preferably capable of receiving SMS messages as acknowledgment from the Dispatcher, security or maintenance personnel to receive.
Das LX7 verfügt über eine integrierte Diagnosedatenbank, durch die festgelegte reguläre Ereignisse sowie Fehler und Störungen in Echtzeit aufgezeichnet werden. Die Datenbank funktioniert vorzugsweise zyklisch, d. h. bei einer erschöpften Speicherkapazität werden jeweils die ältesten Ereignisse durch neue Ereignisse überschrieben. Zum Abrufen der Datenbank dient spezielle Software, die unter Windows auf PCs oder Laptop-Computern ausgeführt sein kann. Ein lokaler oder Remote-Zugriff auf die Datenbank ist somit problemlos möglich.The LX7 has one integrated diagnostics database, through the set regular events as well as errors and faults be recorded in real time. The database works best cyclically, d. H. in an exhausted storage capacity each become the oldest Events overwritten by new events. To retrieve the Database serves special software that runs on Windows or PCs Laptop computers running can be. There is a local or remote access to the database thus easily possible.
Ein
Blockschaltbild des FTC mit Gleisanschlüssen ist in
Für asymmetrische Annäherungen werden elektrische oder mechanische Schienenstöße benötigt. Schienenstöße können unmittelbar neben dem Anschlusspunkt des Senders eingebaut werden. In diesem Fall ist der Erkennungsbereich nur auf eine Seite des Gleises gerichtet – unidirektionale Anwendung. Der einseitig gerichtete Erkennungsbereich ist bei unidirektionaler Anwendung ca. 33 % länger als bei bidirektionaler Anwendung.For asymmetrical approaches electrical or mechanical rail joints are needed. Rail joints can be installed directly next to the connection point of the transmitter. In In this case, the detection area is directed to only one side of the track - unidirectional application. The unidirectional detection area is approximately 33% longer in unidirectional applications than in bidirectional applications.
Da die Gleisimpedanz von den Witterungsbedingungen abhängig ist, ergeben sich bezüglich des Erkennungsbereiches, insbesondere bei LFTCs, leichte Schwankungen. Wenn für die entsprechende Anwendung ein sehr genauer Erkennungsbereich erforderlich ist, sind Schienenstöße zu verwenden.There the track impedance depends on the weather conditions, arise with respect to the Detection range, especially in LFTCs, slight fluctuations. If for the appropriate application requires a very accurate detection area is to use rail joints.
Die Arbeitsfrequenzen von FTCs werden so ausgewählt, dass der Einfluss der Bahnstromversorgung (25 kV/50 Hz) und der entsprechenden Oberschwingungen möglichst minimiert wird. Durch die Arbeitsfrequenzen wird ebenfalls die maximale Erkennungsreichweite definiert. Eine Trennung zwischen den verschiedenen Arbeitsfrequenzen wird gewählt, um die Verwendung von zwei oder mehr FTCs mit unterschiedlichen Betriebsfrequenzen auf einem kontrollierten Gleisabschnitt zu ermöglichen.The Operating frequencies of FTCs are selected so that the influence of the Traction power supply (25 kV / 50 Hz) and the corresponding harmonics preferably is minimized. Due to the working frequencies is also the maximum Detection range defined. A separation between the different ones Working frequencies are chosen to use two or more FTCs with different ones Operating frequencies on a controlled track section.
Durch den Einbau sowohl des Empfängers als auch des Senders in einem gemeinsamen Gerätegehäuse wird erreicht, dass der Empfänger ein starkes Signal in unmittelbarer Nähe des Senders empfängt und nicht lediglich ein schwaches Signal am Ende des kontrollierten Gleisabschnitts registriert. Dies ermöglicht es, die Leistung des Senders und Empfängers zu reduzieren und führt außerdem zu Kosteneinsparungen hinsichtlich des Kabelnetzes zwischen Sender und Empfänger. Die Kosten für ein zusätzliches Gerätegehäuse können hierbei ebenfalls eingespart werden. Insgesamt ergeben sich, insbesondere bei den LFTCs, Einsparungen in beträchtlicher Höhe.By the installation of both the receiver and Even the transmitter in a common device housing is achieved that the receiver receives a strong signal in the immediate vicinity of the transmitter and not just a weak signal at the end of the controlled Track section registered. This allows the performance of the Transmitter and receiver to reduce and leads as well Cost savings regarding the cable network between transmitters and receiver. The price for an additional Device housing can hereby also be saved. Overall, arise, in particular at the LFTCs, significant savings.
Die Erkennungsreichweite des FTC kann über einen Regelwiderstand eingestellt werden. Zwei FTCs mit nebeneinander liegenden Arbeitsfrequenzen können daher über dieselbe Erkennungsreichweite verfügen. Daraus ergibt sich, dass die Zugerkennungsfunktion innerhalb des überwachten Streckenabschnitts dupliziert werden kann – Redundanz. Dies ist für manche Signalanwendungen von großer Bedeutung, insbesondere für die Steuerung von Bahnübergängen, bei denen durch die Eisenbahnbehörden in vielen Ländern eine duplizierte Zugmeldung vorgeschrieben ist. FTCs ermöglichen die Implementierung der duplizierten Annäherungsgleisabschnitte für die Bahnübergangscontroller, ohne dass teure Kabelnetze neben den Gleisen verlegt werden müssen. Zwei Empfänger R1 und R2 sind mit den FTCs verbunden und beaufschlagen serielle Kontakte Cont.1 und Cont.2 der zugeordneten Relais Re1 und Re2.The Recognition range of the FTC can be set via a variable resistor become. Two FTCs with adjacent working frequencies can therefore about have the same recognition range. It follows that the train detection function within the monitored section can be duplicated - redundancy. This is for some signal applications of great importance, in particular for the controller of level crossings, at those by the railway authorities in many countries a duplicate train notification is required. Enable FTCs the implementation of the duplicated approach track sections for the level crossing controllers, without having to lay expensive cable networks next to the tracks. Two receiver R1 and R2 are connected to the FTCs and apply serial Contacts Cont.1 and Cont.2 of the assigned relays Re1 and Re2.
Welche Einsparungen dadurch erzielt werden können, dass kein Kabelnetz neben der Strecke – Kabel, Grabenaushub, Verlegung und Prüfung – benötigt wird, ist von der maximalen Zuggeschwindigkeit abhängig. Demzufolge können bei höheren Zuggeschwindigkeiten wegen der längeren Annäherungsgleisabschnitte auch höhere Einsparungen erzielt werden. Diese Einsparungen sind außerdem von dem jeweils vor Ort gültigen Preis der Kabel und vor allem auch von den Arbeitskosten abhängig. Überwiegend könnten Kosten für mehr als 2.600 m Kabel eingespart werden.Which Savings can be made by not having a cable network next to it the route - cable, Trenching, laying and testing - needed, depends on the maximum train speed. Consequently, at higher train speeds because of the longer Approach track sections also higher Savings are achieved. These savings are also from the locally valid Price of cables and, above all, on labor costs. Mostly could costs for more than 2,600 m of cable can be saved.
Eine
typische Anordnung einer stoßlosen und
kabellosen Bahnübergangsanwendung
ist in
Die Erfindung beschränkt sich nicht auf das vorstehend genannte Ausführungsbeispiel. Vielmehr ist eine Anzahl von Varianten denkbar, welche auch bei grundsätzlich anders gearteter Ausführung von den Merkmalen der Erfindung Gebrauch machen. Insbesondere ist die Fernprogrammierung gemäß Anspruch 7 nicht auf Systeme mit LFTCs und SFTCs beschränkt, sondern kann bei jeglichen Bahnübergangssicherungssystemen verwendet werden, sofern diese einen programmierbaren Bahnübergangscontroller aufweisen.The Restricted invention not on the above embodiment. Rather, it is a number of variants conceivable, which is also fundamentally different of the type make use of the features of the invention. In particular the remote programming according to claim 7 not limited to systems with LFTCs and SFTCs, but can be used at any Crossing protection systems provided they have a programmable grade crossing controller exhibit.
Claims (7)
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE200410057459 DE102004057459A1 (en) | 2004-11-25 | 2004-11-25 | Railway crossing safety system |
| PCT/EP2005/056197 WO2006056587A2 (en) | 2004-11-25 | 2005-11-24 | Level crossing safety system |
| EP05813522A EP1814768A2 (en) | 2004-11-25 | 2005-11-24 | Level crossing safety system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE200410057459 DE102004057459A1 (en) | 2004-11-25 | 2004-11-25 | Railway crossing safety system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE102004057459A1 true DE102004057459A1 (en) | 2006-06-01 |
Family
ID=35686533
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DE200410057459 Withdrawn DE102004057459A1 (en) | 2004-11-25 | 2004-11-25 | Railway crossing safety system |
Country Status (3)
| Country | Link |
|---|---|
| EP (1) | EP1814768A2 (en) |
| DE (1) | DE102004057459A1 (en) |
| WO (1) | WO2006056587A2 (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2048055A1 (en) * | 2007-10-09 | 2009-04-15 | Siemens Schweiz AG | Autonomous level crossing and method for its operation |
| EP2371666A3 (en) * | 2010-03-17 | 2012-04-11 | Invensys Rail Corporation | Crossing predictor with authorized track speed input |
| US8500071B2 (en) | 2009-10-27 | 2013-08-06 | Invensys Rail Corporation | Method and apparatus for bi-directional downstream adjacent crossing signaling |
| US8590844B2 (en) | 2009-07-17 | 2013-11-26 | Siemens Rail Auotmation Corporation | Track circuit communications |
| US8660215B2 (en) | 2010-03-16 | 2014-02-25 | Siemens Rail Automation Corporation | Decoding algorithm for frequency shift key communications |
| WO2014179026A3 (en) * | 2013-04-30 | 2015-02-19 | Siemens Industry, Inc. | Dual frequency train detection |
| WO2015071169A1 (en) * | 2013-11-13 | 2015-05-21 | Siemens Aktiengesellschaft | Level crossing safety system |
| DE102015211141A1 (en) | 2015-06-17 | 2016-12-22 | Siemens Aktiengesellschaft | Level crossing protection system and method for controlling a level crossing protection system |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| NL2004899C2 (en) * | 2010-06-16 | 2011-12-19 | Id4Tech B V | BATTLE TREE INSTALLATION, BATTLE TREE AND METHOD FOR THIS. |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2896068A (en) * | 1955-10-05 | 1959-07-21 | Gen Railway Signal Co | Electronic track circuit for railroads |
| US3359416A (en) * | 1965-03-29 | 1967-12-19 | Gen Signal Corp | Continuous rail track circuits |
| US6641091B1 (en) * | 2000-06-01 | 2003-11-04 | General Electric Company | Highway railroad crossing vehicle detection methods and systems |
-
2004
- 2004-11-25 DE DE200410057459 patent/DE102004057459A1/en not_active Withdrawn
-
2005
- 2005-11-24 WO PCT/EP2005/056197 patent/WO2006056587A2/en not_active Ceased
- 2005-11-24 EP EP05813522A patent/EP1814768A2/en not_active Withdrawn
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2048055A1 (en) * | 2007-10-09 | 2009-04-15 | Siemens Schweiz AG | Autonomous level crossing and method for its operation |
| US8590844B2 (en) | 2009-07-17 | 2013-11-26 | Siemens Rail Auotmation Corporation | Track circuit communications |
| US8500071B2 (en) | 2009-10-27 | 2013-08-06 | Invensys Rail Corporation | Method and apparatus for bi-directional downstream adjacent crossing signaling |
| US9248849B2 (en) | 2009-10-27 | 2016-02-02 | Siemens Industry, Inc. | Apparatus for bi-directional downstream adjacent crossing signaling |
| US8660215B2 (en) | 2010-03-16 | 2014-02-25 | Siemens Rail Automation Corporation | Decoding algorithm for frequency shift key communications |
| EP2371666A3 (en) * | 2010-03-17 | 2012-04-11 | Invensys Rail Corporation | Crossing predictor with authorized track speed input |
| WO2014179026A3 (en) * | 2013-04-30 | 2015-02-19 | Siemens Industry, Inc. | Dual frequency train detection |
| WO2015071169A1 (en) * | 2013-11-13 | 2015-05-21 | Siemens Aktiengesellschaft | Level crossing safety system |
| DE102015211141A1 (en) | 2015-06-17 | 2016-12-22 | Siemens Aktiengesellschaft | Level crossing protection system and method for controlling a level crossing protection system |
| WO2016202575A1 (en) | 2015-06-17 | 2016-12-22 | Siemens Aktiengesellschaft | Level crossing safety system and method for controlling a level crossing safety system |
Also Published As
| Publication number | Publication date |
|---|---|
| WO2006056587A3 (en) | 2006-08-03 |
| WO2006056587A2 (en) | 2006-06-01 |
| EP1814768A2 (en) | 2007-08-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US8469319B2 (en) | Railway sensor communication system and method | |
| EP2403746B1 (en) | Remote monitoring of operating parameters of a contact line system | |
| DE69022193T2 (en) | Highway crossing control system for rail road using a transmission link between the train locomotive and the crossing protection device. | |
| WO2010133541A1 (en) | Method for controlling an obstruction light | |
| EP2057056B1 (en) | Method and device for a modular adaptive system for controlling and monitoring railway safety installations | |
| EP3016830A1 (en) | Device and method for operating functional units arranged in a decentralized manner | |
| EP1999001B1 (en) | Device for switching on and monitoring a traffic light installation for rail traffic | |
| DE102004057459A1 (en) | Railway crossing safety system | |
| EP2162339B1 (en) | Device and transfer of data between an immovably installed data transmission unit and a movable object | |
| EP2307256B1 (en) | Method and device for operating a railroad security system | |
| DE102016114322B4 (en) | Network device and system with a variety of network devices | |
| EP2790994A2 (en) | System for controlling, securing and/or monitoring travel paths of track-bound vehicles and method for operating such a system | |
| EP1187750B1 (en) | Safeguarding plant for level crossing | |
| DE10336022B4 (en) | Procedure for the flexible allocation of responsibilities of line centers | |
| EP2236389B1 (en) | Method for settling error messages of a decentralised function unit in a securing system for rail-bound traffic | |
| EP0720539B1 (en) | Process and arrangement for detecting and reporting the electrical condition of voltage flashover fuses | |
| EP1172274B1 (en) | Device for transmitting the signal aspect of a traffic control device to a vehicle | |
| DE3223779A1 (en) | Error-protected light-signal control device with fewer wires | |
| GB2542649A (en) | Integrated lamp assembly and method | |
| EP2978654A2 (en) | Method for replacing a first signal box with a second signal box | |
| EP2878510B1 (en) | Balise for an automatic train control system, and train safety system with such a balise | |
| EP3305622A1 (en) | Method for diagnosis of spatially distributed technical components | |
| DE102017215853A1 (en) | Device for detecting vibrations | |
| EP0698543A1 (en) | Method and device for warning persons in the track area | |
| WO2017092911A1 (en) | Device and method for controlling and/or monitoring decentralized intelligent functional units arranged in a rail network |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| ON | Later submitted papers | ||
| 8139 | Disposal/non-payment of the annual fee |