CN203159149U - Large-span prestress double-arching-frame hoisting structure - Google Patents
Large-span prestress double-arching-frame hoisting structure Download PDFInfo
- Publication number
- CN203159149U CN203159149U CN201320192653.5U CN201320192653U CN203159149U CN 203159149 U CN203159149 U CN 203159149U CN 201320192653 U CN201320192653 U CN 201320192653U CN 203159149 U CN203159149 U CN 203159149U
- Authority
- CN
- China
- Prior art keywords
- steel beam
- arch
- arching
- screws
- hoisting structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 36
- 239000010959 steel Substances 0.000 claims abstract description 36
- 238000000034 method Methods 0.000 abstract description 7
- 238000010276 construction Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A40/00—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
- Y02A40/10—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
- Y02A40/25—Greenhouse technology, e.g. cooling systems therefor
Landscapes
- Types And Forms Of Lifts (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及大跨度预应力双拱架吊装结构。The utility model relates to a large-span prestressed double arch hoisting structure.
背景技术Background technique
大跨度双拱架吊装重量重,吊装高度高,施工难度大。The hoisting weight of the large-span double-arch frame is heavy, the hoisting height is high, and the construction is difficult.
实用新型内容Utility model content
本实用新型所要解决的技术问题就是提供一种大跨度预应力双拱架吊装结构,保证在拱架吊装过程中施工人员安全健康,保证结构不发生因吊装工艺造成结构质量破坏,同时缩短吊装时间。The technical problem to be solved by the utility model is to provide a large-span prestressed double arch hoisting structure, which can ensure the safety and health of construction personnel during the arch hoisting process, ensure that the structure does not suffer from structural quality damage caused by the hoisting process, and shorten the hoisting time at the same time. .
为解决上述技术问题,本实用新型采用如下技术方案:大跨度预应力双拱架吊装结构,包括设于两根并排的承重柱间的操作平台,其特征在于:所述操作平台上设有下钢横梁,在下钢横梁上方设有上钢横梁,所述下钢横梁与上钢横梁之间设有千斤顶,拱架端部位于两根承重柱之间操作平台下方,所述拱架端部与上钢横梁之间由螺杆连接,所述螺杆顶端穿出上钢横梁并由螺帽紧固,所述螺杆底端穿出拱架端部并由螺帽紧固。In order to solve the above-mentioned technical problems, the utility model adopts the following technical scheme: the large-span prestressed double-arch hoisting structure includes an operating platform arranged between two side-by-side load-bearing columns. A steel crossbeam, an upper steel crossbeam is arranged above the lower steel crossbeam, a jack is provided between the lower steel crossbeam and the upper steel crossbeam, the end of the arch is located under the operating platform between two load-bearing columns, and the end of the arch is connected to the The upper steel beams are connected by screws, the top ends of the screws pass through the upper steel beams and are fastened by nuts, the bottom ends of the screws pass through the ends of the arch frame and are fastened by nuts.
优选的,所述螺杆设有四根并呈矩形分布。Preferably, there are four screws arranged in a rectangular distribution.
优选的,所述螺杆为精扎螺纹钢,所述螺杆的直径为40mm。Preferably, the screw is precision rolled rebar, and the diameter of the screw is 40mm.
优选的,所述承重柱上设有休息孔。Preferably, rest holes are provided on the load-bearing column.
优选的,所述拱架端部设有供螺杆穿过的提升预留孔,所述提升预留孔内预埋有钢管作套管,钢管套管与拱架内钢筋焊接固定。Preferably, the end of the arch is provided with a lifting reserved hole for the screw to pass through, and a steel pipe is pre-embedded in the lifting reserved hole as a casing, and the steel pipe casing is welded and fixed to the steel bar in the arch.
本实用新型利用螺杆作为提升工具,利用千斤顶作为动力源提升螺杆,由螺杆牵引拱架至设计标高,保证在拱架吊装过程中施工人员安全健康,保证结构不发生因吊装工艺造成结构质量破坏,同时缩短了吊装时间。The utility model uses the screw as the lifting tool, and the jack as the power source to lift the screw, and the screw pulls the arch frame to the design elevation, so as to ensure the safety and health of the construction personnel during the hoisting process of the arch frame, and to ensure that the structure will not be damaged due to the hoisting process. At the same time, the hoisting time is shortened.
附图说明Description of drawings
下面结合附图和具体实施方式对本实用新型作进一步描述:Below in conjunction with accompanying drawing and specific embodiment the utility model is further described:
图1为大跨度预应力双拱架吊装结构示意图。Figure 1 is a schematic diagram of the large-span prestressed double arch hoisting structure.
具体实施方式Detailed ways
下面结合图1具体说明大跨度预应力双拱架吊装结构,两根并排的承重柱1间设有操作平台10,所述操作平台10上设有下钢横梁20,在下钢横梁上方设有上钢横梁21,所述下钢横梁20与上钢横梁21之间设有千斤顶22,拱架端部3位于两根承重柱1之间操作平台10下方,所述拱架端部与上钢横梁之间由螺杆2连接,所述螺杆顶端穿出上钢横梁并由螺帽紧固,所述螺杆底端穿出拱架端部并由螺帽紧固。The hoisting structure of the large-span prestressed double arch will be described in detail below in conjunction with Fig. 1. An
所述螺杆设有四根并呈矩形分布。所述螺杆为精扎螺纹钢,所述螺杆的直径为40mm。所述承重柱上设有休息孔。所述拱架端部设有供螺杆穿过的提升预留孔,所述提升预留孔内预埋有钢管作套管,钢管套管与拱架内钢筋焊接固定。The screw rods are provided with four and distributed in a rectangular shape. The screw rod is precision-rolled rebar, and the diameter of the screw rod is 40mm. A rest hole is provided on the load-bearing column. The end of the arch is provided with a lifting reserved hole for the screw to pass through, and a steel pipe is pre-embedded in the lifting reserved hole as a casing, and the steel pipe casing is welded and fixed to the steel bar in the arch.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201320192653.5U CN203159149U (en) | 2013-04-16 | 2013-04-16 | Large-span prestress double-arching-frame hoisting structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201320192653.5U CN203159149U (en) | 2013-04-16 | 2013-04-16 | Large-span prestress double-arching-frame hoisting structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203159149U true CN203159149U (en) | 2013-08-28 |
Family
ID=49020352
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201320192653.5U Expired - Fee Related CN203159149U (en) | 2013-04-16 | 2013-04-16 | Large-span prestress double-arching-frame hoisting structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203159149U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103264977A (en) * | 2013-04-16 | 2013-08-28 | 中天建设集团有限公司 | Large-span prestress double-arch-frame hoisting structure |
-
2013
- 2013-04-16 CN CN201320192653.5U patent/CN203159149U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103264977A (en) * | 2013-04-16 | 2013-08-28 | 中天建设集团有限公司 | Large-span prestress double-arch-frame hoisting structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202509404U (en) | High-pier single-column capping beam framework construction support system | |
| CN204510005U (en) | A kind of Coping Construction operating platform | |
| CN201895984U (en) | Hydraulic pay-off stand | |
| CN105369745A (en) | Bridge support exchanging and lifting reaction frame | |
| CN203247031U (en) | Hoisting device for curtain board transporting | |
| CN203159149U (en) | Large-span prestress double-arching-frame hoisting structure | |
| CN203312666U (en) | Lift truck for replacing or overhauling disconnecting switch | |
| CN203830937U (en) | Auxiliary device for butt welding of sectional materials | |
| CN206467579U (en) | A kind of support meanss of bridge coping | |
| CN203160116U (en) | Overturning prevention bridge pier mechanism | |
| CN103056649B (en) | Super-large-scale multi-functional pressing machine frame installing method | |
| CN203132908U (en) | Loading device of template support system | |
| CN203479511U (en) | Railway T beam static load test pedestal | |
| CN202214680U (en) | Device is changed to tied in a bow member bridge jib | |
| CN104695717A (en) | Upwarp degree precontrol adjusting equipment of revolving platform | |
| CN101774516B (en) | Lifting device and construction method for replacing rake crane bridge | |
| CN204162235U (en) | Lift crosshead safety overhauling device | |
| CN103274324B (en) | A kind of disconnector changes overhaul lift car | |
| CN204038986U (en) | For removing the fork truck of inner support steel pipe | |
| CN204643728U (en) | A kind of driftage clamp lift car | |
| CN103063510A (en) | Loading device for template supporting systems | |
| CN203361596U (en) | Auxiliary support of integrated lifting operation platform | |
| CN206667255U (en) | Base for reaction frame | |
| CN206245702U (en) | A kind of hanging construction of beam protection carrier | |
| CN205134533U (en) | Complicated special -shaped steel mesh frame and steel skeleton construction and installation structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130828 Termination date: 20140416 |