CN1990371B - The method of elevator installation and the lifting system used in it - Google Patents
The method of elevator installation and the lifting system used in it Download PDFInfo
- Publication number
- CN1990371B CN1990371B CN2005101120374A CN200510112037A CN1990371B CN 1990371 B CN1990371 B CN 1990371B CN 2005101120374 A CN2005101120374 A CN 2005101120374A CN 200510112037 A CN200510112037 A CN 200510112037A CN 1990371 B CN1990371 B CN 1990371B
- Authority
- CN
- China
- Prior art keywords
- elevator
- car frame
- frame
- counterweight
- hoistway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
本发明公开了一种电梯安装的方法,首先安装能使轿厢进行升降的必要部件,包括曳引机、对重、曳引钢丝绳、轿厢导轨和轿厢架等,然后以轿厢架为基础构造一个升降平台,利用该升降平台对电梯的其它部件进行安装作业。本发明还公开了一种电梯安装的升降系统,包括电梯的曳引装置、对重架和轿厢架,在所述轿厢架的四周安装有防护栏,在上部平台的防护栏的顶部设有防护顶板,所述防护顶板与轿厢架之间设有一纵向的保护筒,电梯的曳引钢丝绳穿过保护筒与轿厢架相连接,轿厢架上设置有用来控制电梯升降的控制盘。本发明减少了大量的设备运输及维护的工作,成本低,容易管理和控制,大大提高了工作效率,而且保证部件安装的准确性。
The invention discloses a method for installing an elevator. Firstly, the necessary components capable of raising and lowering the car are installed, including a traction machine, a counterweight, a traction wire rope, a car guide rail and a car frame, etc., and then the car frame is used as the The basic structure is a lifting platform, and other parts of the elevator are installed by using the lifting platform. The invention also discloses a lifting system installed with an elevator, which includes a traction device of the elevator, a counterweight frame and a car frame, guardrails are installed around the car frame, and a protective fence is installed on the top of the guardrail of the upper platform. There is a protective top plate, a longitudinal protective tube is set between the protective top plate and the car frame, the traction wire rope of the elevator passes through the protective tube and is connected with the car frame, and the car frame is provided with a control panel for controlling the lifting of the elevator . The invention reduces a lot of equipment transportation and maintenance work, has low cost, is easy to manage and control, greatly improves work efficiency, and ensures the accuracy of component installation.
Description
技术领域technical field
本发明涉及一种电梯安装的方法。本发明还涉及一种安装电梯时所用的电梯安装的升降系统。The invention relates to a method for elevator installation. The invention also relates to an elevator-mounted hoisting system for use in the installation of elevators.
背景技术Background technique
目前传统的电梯安装方法是使用脚手架的安装工艺,即在所要安装的电梯井道内每1.8米左右一层搭设固定式脚手架工作平台,并且贯通整个井道。然后根据电梯各个部件的安装位置的不同,选择不同位置的脚手架工作平台作为施工平台进行作业。直至井道内的电梯部件基本安装完毕后,拆除脚手架进行电梯调整、调试。传统的安装工艺使各工作平台的一致性较差,井道内的每个施工区域难以提供足够的照明,在不同施工平台作业时的移动主要依靠安装人员攀爬或走楼梯,从而浪费了大量的时间和安装人员体力。为减少搬运,电梯部件也无法集中堆放,井道内立体施工的安全防护很难得到严密的控制,部件也无法一次安装到位。另外,脚手架拆除后将有大量的调整工作以及其它的一系列问题。The current traditional elevator installation method is to use the installation process of scaffolding, that is, a fixed scaffolding work platform is set up every 1.8 meters or so in the elevator shaft to be installed, and runs through the entire shaft. Then, according to the different installation positions of the various parts of the elevator, the scaffolding working platform in different positions is selected as the construction platform for operation. After the elevator components in the hoistway are basically installed, remove the scaffolding to adjust and debug the elevator. The traditional installation process makes the consistency of each working platform poor, and it is difficult to provide sufficient lighting for each construction area in the hoistway. The movement when working on different construction platforms mainly depends on the installation personnel to climb or take the stairs, thus wasting a lot of time. time and physical strength of the installer. In order to reduce handling, elevator components cannot be stacked together. It is difficult to strictly control the safety protection of the three-dimensional construction in the hoistway, and the components cannot be installed in place at one time. In addition, there will be a lot of adjustment work and a series of other problems after the scaffolding is removed.
发明内容Contents of the invention
本发明所要解决的技术问题是提供一种电梯安装的方法,能够摒弃原有繁琐的脚手架搭建及拆除工序,并且节省工时和人力,提高工作效率。The technical problem to be solved by the present invention is to provide an elevator installation method, which can abandon the original cumbersome scaffolding construction and dismantling procedures, save working hours and manpower, and improve work efficiency.
为解决上述技术问题,本发明电梯安装的方法的技术方案是,包括如下步骤:In order to solve the problems of the technologies described above, the technical solution of the method for elevator installation of the present invention is to include the following steps:
(1)根据对应井道所需安装的电梯营业设计图,在机房地坪上进行样板架的设定,确定该电梯的所有相关部件确切的安装位置,根据样板架的要求对机房内的部件进行定位安装,对机房楼板的预留孔进行确认、修正;(1) According to the business design drawing of the elevator that needs to be installed in the corresponding well, set the sample frame on the floor of the machine room, determine the exact installation position of all relevant components of the elevator, and carry out the parts in the machine room according to the requirements of the sample frame Positioning and installation, confirming and correcting the reserved holes on the floor of the machine room;
(2)通过起吊设备将两列进行依次连接后的轿厢导轨整列吊起,并固定在机房楼板上,使整列导轨的两端得到可靠的临时固定;在对重侧固定两根平行于对重运行方向的对重架导向钢丝绳,然后在井道底部安装缓冲器和张紧轮;(2) Lift the car guide rails after the two rows are connected sequentially by lifting equipment, and fix them on the floor of the machine room, so that the two ends of the guide rails in the whole row can be temporarily fixed reliably; The counterweight frame guides the steel wire rope in the heavy running direction, and then installs a buffer and a tensioning wheel at the bottom of the hoistway;
(3)在井道底层位置拼装轿厢架,组成移动平台,同时在底层的后侧进行对重架和对重铁的拼装,并使拼装好的对重架通过对重架导向钢丝绳的导向用起吊设备将其提升到井道的顶层;(3) Assemble the car frame at the bottom of the hoistway to form a mobile platform. At the same time, assemble the counterweight frame and counterweight iron on the rear side of the bottom layer, and make the assembled counterweight frame pass through the guiding wire rope of the counterweight frame. Hoisting equipment to lift it to the top floor of the hoistway;
(4)安装曳引机钢丝绳,使曳引机钢丝绳通过曳引机的过渡,将拼装好的工作平台与对重架连接,构成曳引驱动的平衡系统,随后将限速器钢丝绳安装到位,使限速器与安全钳联动的安全保护生效,将报警灯、电缆卷筒、运转电缆和手动控制盘安装就位,实现在升降平台上就可以对平台的上下移动进行操作;将超层限位开关安装到位,避免平台运行时的沉底及冲顶;(4) Install the traction machine wire rope, make the traction machine wire rope pass through the transition of the traction machine, connect the assembled working platform with the counterweight frame to form a traction-driven balance system, and then install the speed limiter wire rope in place, Make the safety protection of the linkage between the speed limiter and the safety gear take effect, install the alarm lamp, cable reel, running cable and manual control panel in place, and realize that the platform can be moved up and down on the lifting platform; The position switch is installed in place to avoid the bottom and top of the platform during operation;
(5)对临时移动平台进行检修运行的接线、调试,检查所有安全保护是否有效,将保护筒安装就位,然后通过平台的上下运行对井道内的固定部件进行安装。(5) Carry out wiring and debugging for the maintenance operation of the temporary mobile platform, check whether all safety protections are effective, install the protection tube in place, and then install the fixed parts in the hoistway through the up and down operation of the platform.
本发明所要解决的另一技术问题是,提供一种电梯安装的升降系统,能够替代安装电梯时所需要的脚手架,而且结构简单,便于使用。Another technical problem to be solved by the present invention is to provide a lifting system for elevator installation, which can replace the scaffolding required for elevator installation, and has a simple structure and is easy to use.
为解决上述技术问题,本发明电梯安装的升降系统的技术方案是,所述升降系统包括电梯的曳引装置、所述对重架和所述轿厢架,所述轿厢架包括上部平台和下部平台,在所述轿厢架的上部平台的四周和下部平台的四周都安装有防护栏,在所述上部平台的防护栏的顶部设有防护顶板,所述防护顶板与轿厢架之间设有一个纵向的保护筒,所述电梯的曳引装置的曳引钢丝绳穿过保护筒与轿厢架相连接,轿厢架上设置有用来控制电梯升降的控制盘。In order to solve the above-mentioned technical problems, the technical scheme of the hoisting system installed in the elevator of the present invention is that the hoisting system includes the traction device of the elevator, the counterweight frame and the car frame, and the car frame includes an upper platform and For the lower platform, guardrails are installed around the upper platform of the car frame and around the lower platform, and a protective roof is provided on the top of the guardrail of the upper platform, between the protective roof and the car frame A longitudinal protection cylinder is provided, and the traction wire rope of the traction device of the elevator passes through the protection cylinder and is connected with the car frame, and the car frame is provided with a control panel for controlling the elevator up and down.
本发明在原电梯平台上增加一些护栏,在安装结束后将护栏拆除即可直接进行轿厢拼装,并且减少了大量的设备运输及维护的工作,成本低,容易管理和控制,大大提高了工作效率,而且保证部件安装的准确性。The present invention adds some guardrails to the original elevator platform. After the installation, the guardrails can be removed and the car can be assembled directly, and a large amount of equipment transportation and maintenance work is reduced. The cost is low, easy to manage and control, and the work efficiency is greatly improved. , and ensure the accuracy of component installation.
附图说明Description of drawings
下面结合附图和实施例对本发明作进一步描述:The present invention will be further described below in conjunction with accompanying drawing and embodiment:
图1为本发明电梯安装的升降系统的结构示意图。Fig. 1 is a structural schematic diagram of the lifting system installed in the elevator of the present invention.
图中附图标记为:1.曳引机;2.曳引机钢丝绳;3.导向轮;4.曳引机座梁;5.对重架;6.对重铁;7.对重架导向钢丝绳;8.防护顶板;9.保护筒;10.上部工作平台;11.防护栏;12.下部工作平台;13.张紧轮;14.缓冲器;15.报警灯;16.电缆卷筒;17.控制屏;18.限速器;19.超层限位开关;20.轿厢导轨;21.层站;22.轿厢架;23.手动控制盘;24.超层限位开关;25.运转电缆。The reference marks in the figure are: 1. traction machine; 2. traction machine wire rope; 3. guide wheel; 4. traction frame beam; 5. counterweight frame; 6. counterweight iron; 7. counterweight frame Guide wire rope; 8. Protective top plate; 9. Protective tube; 10. Upper working platform; 11. Guardrail; 12. Lower working platform; 13. Tensioning wheel; 14. Buffer; 15. Alarm light; Tube; 17. Control panel; 18. Speed limiter; 19. Super-layer limit switch; 20. Car guide rail; 21. Floor station; 22. Car frame; 23. Manual control panel; 24. Super-layer limit switch; 25. run the cable.
具体实施方式Detailed ways
本发明通过巧妙的对现有的安装工艺进行改进,同时充分利用电梯原有部件的基本组合,提供一种结构简单、安全可靠、推广性强、成本较低、拆装方便、省时省力、高效保质的用于升降电梯的专用移动操作平台,实现电梯安装工艺中的无脚手架安装的变革。The present invention cleverly improves the existing installation process, and at the same time makes full use of the basic combination of the original parts of the elevator to provide a simple structure, safe and reliable, strong popularization, low cost, convenient disassembly and assembly, saving time and effort, The high-efficiency and quality-guaranteed special mobile operating platform for lifting elevators realizes the transformation of scaffold-free installation in the elevator installation process.
本发明电梯安装的方法,具体包括如下步骤:The method for elevator installation of the present invention specifically comprises the steps:
(1)根据对应井道所需安装的电梯营业设计图,在机房地坪上进行样板架的设定,确定该电梯的所有相关部件确切的安装位置,根据样板架的要求对机房内的部件进行定位安装,所述机房内的部件包括曳引机1、导向轮3、曳引机座梁4、控制屏17和限速器18,并且对机房楼板的预留孔进行确认、修正;(1) According to the business design drawing of the elevator that needs to be installed in the corresponding well, set the sample frame on the floor of the machine room, determine the exact installation position of all relevant components of the elevator, and carry out the parts in the machine room according to the requirements of the sample frame Positioning and installation, the components in the machine room include the traction machine 1, the guide wheel 3, the traction base beam 4, the control panel 17 and the speed limiter 18, and confirm and correct the reserved holes on the floor of the machine room;
(2)通过起吊设备将两列进行依次连接后的轿厢导轨20整列吊起,并固定在机房楼板上,使整列导轨的两端得到可靠的临时固定;在对重侧固定两根平行于对重运行方向的对重架导向钢丝绳7,然后在井道底部安装缓冲器14和张紧轮13;(2) The car guide rails 20 after the two rows are connected in sequence are hoisted by the hoisting equipment and fixed on the floor of the machine room, so that the two ends of the guide rails in the whole row are reliably temporarily fixed; The counterweight frame guide wire rope 7 in the counterweight running direction, and then a buffer 14 and a tensioning pulley 13 are installed at the bottom of the hoistway;
(3)在井道底层位置拼装轿厢架22,组成移动平台,同时在底层的后侧进行对重架5和对重铁6的拼装,并使拼装好的对重架5通过对重架导向钢丝绳7的导向用起吊设备将其提升到井道的顶层;(3) Assemble the car frame 22 at the bottom of the hoistway to form a mobile platform. At the same time, the counterweight frame 5 and the counterweight iron 6 are assembled on the rear side of the bottom layer, and the assembled counterweight frame 5 is guided by the counterweight frame The guiding of steel wire rope 7 is promoted to the top floor of hoistway with hoisting equipment;
(4)安装曳引机钢丝绳2,使曳引机钢丝绳2通过曳引机1的过渡,将拼装好的工作平台与对重架5连接,构成曳引驱动的平衡系统,随后将限速器钢丝绳安装到位,使限速器18与安全钳联动的安全保护生效,将报警灯15、电缆卷筒16、运转电缆25和手动控制盘23安装就位,实现在升降平台上就可以对平台的上下移动进行操作;将超层限位开关19安装到位,避免平台运行时的沉底及冲顶;(4) Install the traction machine wire rope 2, make the traction machine wire rope 2 pass through the transition of the traction machine 1, and connect the assembled working platform with the counterweight frame 5 to form a traction-driven balance system, and then the overspeed governor The steel wire rope is installed in place to make the safety protection of the overspeed governor 18 and the safety gear linkage take effect, and the warning light 15, the cable reel 16, the running cable 25 and the manual control panel 23 are installed in place, so that the platform can be controlled on the lifting platform. Move up and down for operation; install the super-level limit switch 19 in place to avoid sinking and topping when the platform is running;
(5)对临时移动平台进行检修运行的接线、调试,检查所有安全保护是否有效,将保护筒9安装就位,然后通过平台的上下运行对井道内的固定部件进行安装。(5) Carry out the wiring and debugging of the maintenance operation of the temporary mobile platform, check whether all safety protections are effective, install the protective tube 9 in place, and then install the fixed parts in the shaft through the up and down operation of the platform.
本发明还包括一种电梯安装的升降系统,其包括电梯的曳引装置、所述对重架和所述轿厢架,所述轿厢架22包括上部平台10和下部平台12,在所述轿厢架22的上部平台10的四周和下部平台12的四周都安装有防护栏11,在所述上部平台10的防护栏11的顶部设有防护顶板8,所述防护顶板8与轿厢架22之间设有一个纵向的保护筒9,所述电梯曳引装置的曳引钢丝绳2穿过保护筒9与轿厢架22相连接,轿厢架22上设置有用来控制电梯升降的控制盘23,所述轿厢架22上还设置有电源箱,供施工时使用。另外,所述井道下端设有张紧轮13,张紧钢丝绳绕在所述张紧轮外侧且纵向贯穿整个井道,所述轿厢架通过该张紧钢丝绳进行导向。The present invention also includes a hoisting system installed with an elevator, which includes the traction device of the elevator, the counterweight frame and the car frame, the car frame 22 includes an upper platform 10 and a lower platform 12, in the Around the upper platform 10 of the car frame 22 and around the lower platform 12, guardrails 11 are installed, and the top of the guardrail 11 of the upper platform 10 is provided with a protective top plate 8, and the protective top plate 8 is connected to the car frame. 22 is provided with a longitudinal protection tube 9, the traction steel wire rope 2 of the elevator traction device passes through the protection tube 9 and is connected with the car frame 22, and the car frame 22 is provided with a control panel for controlling the lift 23. The car frame 22 is also provided with a power supply box for use during construction. In addition, the lower end of the hoistway is provided with a tensioning wheel 13, and the tensioning wire rope is wound around the outer side of the tensioning wheel and longitudinally runs through the entire hoistway, and the car frame is guided by the tensioning wire rope.
与传统的安装工艺相比,本发明的主要区别在于,原安装工艺通过安装人员在贯通井道的脚手架临时平台的反复攀爬作业,将井道内的所有电梯部件基本安装到位后,拆除脚手架进行调试、调整。而本发明利用底层和机房两个固有的工作平台,即土建地坪;将电梯的运行、移动的相关部件进行安装设定,使其先期实现能够在电梯井道内临时垂直移动的一套升降平台,利用该平台对井道、层站的所有固定部件进行安装。其完全能够克服有脚手架安装工艺存在的一致性较差、照明困难、浪费大量的时间和人力、电梯部件无法集中堆放、井道内立体施工的安全防护很难严密控制、部件无法一次安装到位,脚手架拆除后将有大量的调整工作等问题。本发明提供了一个双层的稳定平台,能够确保该作业平台有足够的施工照明,井道内的人员垂直移动及部件的搬运工作靠平台的运送即可实现,部件不需事先分层,可以集中堆放并且便于管理,移动平台上可以设定许多部件安装的基准或参照尺寸,部件一次安装到位率大大提高,并且在安装完成之后,不需要对升降系统进行完全拆卸,因为升降系统就是利用电梯的部分部件组成的,使用完成之后只要把升降平台上的防护栏和防护顶板拆除,然后可直接对轿厢架进行组装而构成电梯的轿厢。Compared with the traditional installation process, the main difference of the present invention is that in the original installation process, the installer repeatedly climbs on the temporary platform of the scaffold that runs through the shaft, and after basically installing all the elevator components in the shaft, the scaffold is removed for debugging. ,Adjustment. However, the present invention utilizes the two inherent working platforms of the ground floor and the machine room, i.e. the civil construction floor; the relevant components for the operation and movement of the elevator are installed and set, so that a set of lifting platforms that can temporarily move vertically in the elevator shaft can be realized in advance. , use this platform to install all the fixed parts of the hoistway and landing. It can completely overcome the poor consistency of the scaffolding installation process, lighting difficulties, wasting a lot of time and manpower, the elevator components cannot be stacked together, the safety protection of the three-dimensional construction in the shaft is difficult to strictly control, and the components cannot be installed in place at one time. After dismantling, there will be a lot of adjustment work and other issues. The invention provides a double-layer stable platform, which can ensure that the working platform has sufficient construction lighting. The vertical movement of personnel in the shaft and the handling of parts can be realized by the transportation of the platform. The parts do not need to be layered in advance and can be concentrated It is stacked and easy to manage. The benchmark or reference size for the installation of many components can be set on the mobile platform. The rate of components being installed at one time is greatly improved, and after the installation is completed, the lifting system does not need to be completely disassembled, because the lifting system uses the elevator. It is composed of some parts. After the use is completed, only the protective fence and the protective roof on the lifting platform are removed, and then the car frame can be directly assembled to form the elevator car.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2005101120374A CN1990371B (en) | 2005-12-27 | 2005-12-27 | The method of elevator installation and the lifting system used in it |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2005101120374A CN1990371B (en) | 2005-12-27 | 2005-12-27 | The method of elevator installation and the lifting system used in it |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN1990371A CN1990371A (en) | 2007-07-04 |
| CN1990371B true CN1990371B (en) | 2010-07-21 |
Family
ID=38212957
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2005101120374A Expired - Lifetime CN1990371B (en) | 2005-12-27 | 2005-12-27 | The method of elevator installation and the lifting system used in it |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN1990371B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102398854A (en) * | 2010-09-08 | 2012-04-04 | 东芝电梯株式会社 | Method And Device For Installing Elevator Winch |
Families Citing this family (20)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5029188B2 (en) * | 2007-07-20 | 2012-09-19 | 三菱電機ビルテクノサービス株式会社 | Elevator installation method and elevator installation cam device |
| CN103287946B (en) * | 2009-12-28 | 2016-03-16 | 日立电梯(中国)有限公司 | counterweight guide system |
| CN101830388B (en) * | 2010-05-21 | 2012-05-30 | 日立电梯(中国)有限公司 | Installation method of counter-weight frame of elevator |
| CN101863406A (en) * | 2010-06-21 | 2010-10-20 | 马海英 | Installation method of elevator |
| CN101920893A (en) * | 2010-08-27 | 2010-12-22 | 康力电梯股份有限公司 | Cage top overhauling platform |
| EP2746211A1 (en) * | 2012-12-19 | 2014-06-25 | Inventio AG | Maintenance method for a lift |
| EP2746210A1 (en) | 2012-12-19 | 2014-06-25 | Inventio AG | Installation method for a lift |
| CN103350940A (en) * | 2013-07-04 | 2013-10-16 | 大连佳林设备制造有限公司 | Elevator structure vertical conveying system |
| CN103991827B (en) * | 2014-06-09 | 2016-06-08 | 黄文龙 | Device installed by elevator |
| CN104528500B (en) * | 2014-12-29 | 2019-05-14 | 中国建筑股份有限公司 | Double tabletop is without scaffold elevator installing method |
| KR102106837B1 (en) * | 2016-05-25 | 2020-05-07 | 미쓰비시덴키 가부시키가이샤 | Elevator hoisting machine installation method |
| CN109689558B (en) * | 2016-09-29 | 2021-04-02 | 因温特奥股份公司 | Car safety supervision unit and physical safety supervision unit for elevator |
| CN106553951B (en) * | 2017-01-23 | 2018-07-13 | 荆门创佳机械科技有限公司 | It is a kind of using elevator shaft and the material elevator of guide rail |
| CN107215748B (en) * | 2017-07-04 | 2020-06-23 | 东莞市鑫峰建筑机械有限公司 | Special construction hoist for hoistway and installation method thereof |
| CN107522062A (en) * | 2017-10-17 | 2017-12-29 | 上海市浦东新区建设(集团)有限公司 | A kind of installation construction method for elevator |
| CN108584589A (en) * | 2018-01-30 | 2018-09-28 | 上海盛蒂斯自动化设备股份有限公司 | A kind of elevator floor stops floor hole fills up system and method |
| US11014783B2 (en) * | 2018-02-08 | 2021-05-25 | Otis Elevator Company | Protective sleeve for elevator belt |
| JP7230175B2 (en) * | 2019-03-05 | 2023-02-28 | 株式会社日立製作所 | Elevator system for construction work and method for extending governor rope of elevator system for construction work |
| CN111071877B (en) * | 2019-12-19 | 2022-04-08 | 快奥电梯有限公司 | Safe elevator car |
| CN116810702B (en) * | 2023-06-12 | 2025-08-19 | 海宁市红狮电梯装饰有限公司 | Elevator safety tongs assembly platform frock with cylinder drags structure |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1519190A (en) * | 2003-02-06 | 2004-08-11 | 三菱电机株式会社 | How to install the elevator |
-
2005
- 2005-12-27 CN CN2005101120374A patent/CN1990371B/en not_active Expired - Lifetime
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1519190A (en) * | 2003-02-06 | 2004-08-11 | 三菱电机株式会社 | How to install the elevator |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102398854A (en) * | 2010-09-08 | 2012-04-04 | 东芝电梯株式会社 | Method And Device For Installing Elevator Winch |
Also Published As
| Publication number | Publication date |
|---|---|
| CN1990371A (en) | 2007-07-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN1990371B (en) | The method of elevator installation and the lifting system used in it | |
| FI120089B (en) | A method of installing a lift | |
| CN104477736A (en) | Shaft elevator installation method | |
| CN107043060A (en) | A kind of installation method of inverse formula installation lift | |
| CN206753012U (en) | A kind of attachment type raise scaffold just hangs hanging apparatus | |
| CN109653481A (en) | A kind of hanging rail formula high-altitude operation platform and production method | |
| CN108286332A (en) | A kind of concrete of crossing soars aloft beam from climbing monoblock type bylinder system and construction method | |
| CN208934715U (en) | A kind of anchor bar of waterproof plate in tunnels construction platform vehicle | |
| CN202379620U (en) | Lifting and operating platform comprehensive equipment | |
| WO2019015243A1 (en) | Shaft module splicing system and splicing method therefor | |
| CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
| CN208648493U (en) | A kind of no scaffold installation elevator operation platform device | |
| CN110761813A (en) | Waterproof board trolley capable of automatically feeding | |
| CN108425348B (en) | Hydraulic overhaul platform for flood discharge flow channel of hydropower station and operation method | |
| CN205369033U (en) | Gallows formula bridge tool car | |
| CN208899841U (en) | A kind of steel structural roof ceiling board installation Mobile operating platform | |
| CN2923635Y (en) | Single-column towing type elevator | |
| CN1990372A (en) | Elevator temporary up-down system and installation method thereof | |
| CN113753716B (en) | Method for installing guide rail of elevator arraying crane with machine room | |
| CN210561720U (en) | Pier stud maintenance repair operation platform | |
| CN210919088U (en) | Waterproof board trolley capable of automatically feeding | |
| CN116262586B (en) | Jump elevator and jump method thereof | |
| CN203269287U (en) | Underneath type elevator without machine room | |
| CN209603469U (en) | A kind of hanging rail formula high-altitude operation platform | |
| CN215666814U (en) | Light reactor hoisting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20100721 |