CN116856565A - Construction method for top plug of post-built filling wall - Google Patents
Construction method for top plug of post-built filling wall Download PDFInfo
- Publication number
- CN116856565A CN116856565A CN202310773756.9A CN202310773756A CN116856565A CN 116856565 A CN116856565 A CN 116856565A CN 202310773756 A CN202310773756 A CN 202310773756A CN 116856565 A CN116856565 A CN 116856565A
- Authority
- CN
- China
- Prior art keywords
- wall
- sphene
- construction
- post
- wooden
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6801—Fillings therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6806—Waterstops
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
Description
技术领域Technical field
本发明属于房屋建筑与安装工程技术领域,具体地说,是一种后砌填充墙顶塞砌的施工方法。The invention belongs to the technical field of house construction and installation engineering. Specifically, it is a construction method of back-filling wall and top-filling construction.
背景技术Background technique
随着建筑砌筑材料的不断发展,越来越多的砌筑材料被应用于建筑工程中,而墙体裂缝也都有不同程度的出现在各个工程中,尤其是墙、梁交界处较为突出,后砌填充墙与主体结构连接处裂缝问题一直以来是现场的难题,往往被称为质量通病。传统做法填充墙砌至梁、板底时,应留有一定空隙(180-200mm),待填充墙砌筑完并至少间隔14d后,再将其斜砌挤紧。图1为已知的顶部斜砌剖面示意图,其顶端塞砌了斜砌砖。但斜砌顶部不能够与梁底进行紧密结合,对于墙体的防水、保温隔热产生不利影响,斜砌施工繁琐,施工进度慢,对工人技术水平要求高,成型外观一般。With the continuous development of building masonry materials, more and more masonry materials are used in construction projects, and wall cracks also appear to varying degrees in various projects, especially at the junctions of walls and beams. , the crack problem at the connection between the back-filled infill wall and the main structure has always been a difficult problem on site, and is often called a common quality problem. According to the traditional method, when the infill wall is built to the bottom of the beams and slabs, a certain gap (180-200mm) should be left. After the infill wall is completed and the interval is at least 14 days, the infill wall should be built diagonally and tightly. Figure 1 is a schematic cross-sectional view of a known top sloping brick, the top of which is filled with sloping bricks. However, the top of the inclined masonry cannot be closely integrated with the bottom of the beam, which has a negative impact on the waterproofing and thermal insulation of the wall. The construction of the inclined masonry is cumbersome, the construction progress is slow, the technical level of the workers is high, and the molding appearance is average.
因此已知的后砌填充墙顶塞砌方式存在着上述种种不便和问题。Therefore, the known back-laying filling wall top plugging method has the above-mentioned various inconveniences and problems.
发明内容Contents of the invention
本发明的目的,在于提出一种安全可靠的后砌填充墙顶塞砌的施工方法。The object of the present invention is to provide a safe and reliable construction method for back-laying infill walls and top plugging.
为实现上述目的,本发明的技术解决方案是:In order to achieve the above objects, the technical solution of the present invention is:
一种后砌填充墙顶塞砌的施工方法,其特征在于包括以下步骤:A construction method for back-filling wall top plugging, which is characterized by including the following steps:
a、制作、安装木榍:将木榍加工成楔形木榍,楔形木榍长度为100-150mm,采用防腐沥青浸泡、晒干楔形木榍;安装时以整块砌块长度为间距或其他砌筑材料成模数,将楔形木榍塞紧砌块缝隙,楔形木榍间距不大于600mm,墙体两侧的木榍交错布置;a. Make and install wooden dowels: process the wooden dowels into wedge-shaped dowels with a length of 100-150mm. Use anti-corrosion asphalt to soak and dry the wedge-shaped dowels; when installing, use the length of the entire block as the spacing or other masonry blocks. The building materials are made into modules, and wedge-shaped wooden dowels are plugged into the gaps between the blocks. The spacing between the wedge-shaped dowels is no more than 600mm, and the wooden dowels on both sides of the wall are staggered;
b、安装钢丝网:砌块缝隙与抹灰层的交界面设置长度不小于300mm的镀锌钢丝网,加强在抹灰层的底部,抹灰层的面层压入一层玻璃纤维网格布(300g/m2);所述交界面包括混凝土梁及砌块与抹灰层的交界面;b. Install steel wire mesh: A galvanized steel wire mesh with a length of not less than 300mm is installed at the interface between the block gap and the plastering layer. It is reinforced at the bottom of the plastering layer and a layer of fiberglass mesh is pressed into the surface of the plastering layer. (300g/m 2 ); the interface includes the interface between concrete beams and blocks and the plaster layer;
c、甩浆湿润:在塞缝前用水湿润墙体顶面及混凝土梁板底,然后在砌块缝隙处甩浆;c. Dump grout to moisten: Wet the top surface of the wall and the bottom of the concrete beam slab with water before plugging the joints, and then dump grout at the gaps between the blocks;
d、发泡胶或细石混凝土塞缝:塞缝时先从墙体一侧进行,待凝固后再行填塞另一侧;塞缝时保证密实,以干硬性为宜,塞缝后表面与墙体一平。d. Fill the joints with foam glue or fine stone concrete: When filling the joints, start from one side of the wall first, and then fill the other side after solidification; when filling the joints, ensure that they are dense and dry and hard. The wall is flat.
本发明的后砌填充墙顶塞砌的施工方法还可以采用以下的技术措施来进一步实现。The construction method of back-laying infill wall top plugging according to the present invention can also be further implemented by adopting the following technical measures.
前述的方法,其中所述发泡胶用于填充空隙高度为<20mm。The aforementioned method, wherein the foam rubber is used to fill the gap with a height of <20 mm.
前述的方法,其中所述细石混凝土用于填充空隙高度为30-50mm。The aforementioned method, wherein the fine stone concrete is used to fill gaps with a height of 30-50mm.
前述的方法,其中所述楔形木榍厚度为20-50mm。The aforementioned method, wherein the thickness of the wedge-shaped wood is 20-50mm.
前述的方法,其中所述镀锌钢丝网的孔距为<12.7×12.7mm,镀锌钢丝网的丝径0.9mm。The aforementioned method, wherein the hole spacing of the galvanized steel wire mesh is <12.7×12.7mm, and the wire diameter of the galvanized steel wire mesh is 0.9mm.
前述的方法,其中所述木榍固定时不破坏砌块棱角,木榍露出墙面的部分用锯割除。According to the aforementioned method, the edges and corners of the building blocks are not damaged when the wooden dowels are fixed, and the exposed portion of the wooden dowels on the wall is cut off with a saw.
采用上述技术方案后,本发明的后砌填充墙顶塞砌的施工方法具有以下优点:After adopting the above technical solution, the construction method of back-laying infill wall and top plugging of the present invention has the following advantages:
1、通过防腐木榍塞紧施加预应力,后塞砌发泡剂或细石混凝土(微膨胀)等方法能够很好的代替斜砖工艺抵消梁、板的挠度变形,且与墙砖自身的收缩变形相协调,能有效减少墙体表面裂缝;1. Methods such as tightly applying prestress through anti-corrosion wooden dowels and then plugging with foaming agent or fine stone concrete (micro-expansion) can effectively replace the inclined brick process to offset the deflection deformation of beams and plates, and are in harmony with the wall bricks themselves. Coordinated shrinkage and deformation can effectively reduce cracks on the wall surface;
2、发泡胶或细石混凝土固化快,技术间歇时间短,减少斜砌施工二次结构脚手架重复搭设,节约了成本,具有良好的适用性和适用效果。2. Foam rubber or fine stone concrete solidifies quickly, and the technical interval is short, which reduces the repeated erection of secondary structural scaffolding in inclined masonry construction, saves costs, and has good applicability and application effects.
附图说明Description of the drawings
图1为已知的顶部斜砌剖面示意图;Figure 1 is a schematic diagram of a known top inclined masonry section;
图2为本发明实施例的后砌填充墙顶塞砌的结构示意图。Figure 2 is a schematic structural diagram of a back-built infill wall and top plug construction according to an embodiment of the present invention.
图中:1混凝土梁,2缝隙,3钢丝网,4抹灰层。In the picture: 1 concrete beam, 2 gaps, 3 steel mesh, 4 plaster layer.
具体实施方式Detailed ways
以下结合实施例及其附图对本发明作更进一步说明。The present invention will be further described below with reference to the embodiments and the accompanying drawings.
实施例1Example 1
本发明的后砌填充墙顶塞砌的施工方法的施工流程:测量放线→排砖撂底(竖立皮数杆)→砌筑梁(板)底50mm以内空隙→养护14d→安装木榍、塞紧→甩浆湿润→在墙体一侧先填塞缝宽一半→在墙体另一侧填塞缝宽的另一半→固定镀锌钢丝网→墙面拍浆、养护→抹灰。The construction process of the construction method of back-filling wall top plugging according to the present invention: measuring and laying out → arranging bricks and laying down the bottom (erecting the skin rod) → building a gap within 50mm of the bottom of the beam (board) → curing for 14 days → installing wooden dowels, Plug tightly → Moisten the grout → Fill half of the gap width on one side of the wall → Fill the other half of the gap width on the other side of the wall → Fix galvanized steel wire mesh → Plaster and maintain the wall → Plaster.
现请参阅图2,图2为本发明实施例的后砌填充墙顶塞砌的结构示意图。本发明的后砌填充墙顶塞砌的施工方法,包括以下步骤:Please refer to Figure 2. Figure 2 is a schematic structural diagram of a back-built infill wall and top plug-in construction according to an embodiment of the present invention. The construction method of back-laying infill wall top plugging according to the present invention includes the following steps:
(1)缝隙处理:后砌填充墙构造中填充墙砌筑至梁1(板)底留有一定的空隙,使砌体充分沉实后,进行墙体顶部缝隙2处理。当空隙厚度在20mm以内时,采用发泡胶进行填充;当空隙厚度在30-50mm时,采用C20细石混凝土(微膨胀)填充。交界处采用长度不小于300mm的镀锌钢丝网3(孔距12.7×12.7mm,丝径0.9mm)加强在抹灰层4的底部,抹灰层的面层压入一层玻璃纤维网格布(300g/m2)。(1) Gap treatment: In the back-laying infill wall structure, the infill wall is built until there is a certain gap at the bottom of the beam 1 (slab). After the masonry is fully settled, the gap 2 treatment at the top of the wall is carried out. When the gap thickness is within 20mm, use foam rubber to fill it; when the gap thickness is between 30-50mm, use C20 fine stone concrete (micro-expansion) to fill it. The junction is reinforced with galvanized steel wire mesh 3 with a length of not less than 300mm (hole spacing 12.7×12.7mm, wire diameter 0.9mm) at the bottom of the plastering layer 4, and a layer of fiberglass mesh is pressed into the surface of the plastering layer. (300g/m 2 ).
(2)安装木榍:木榍加工成契型,契型木榍厚度20-50mm不等,长度100-150mm,采用防腐沥青浸泡、晒干。安装时要求木榍塞紧,间距不大于600mm(以整块砌块长度为间距或其他砌筑材料成模数),墙体两侧的木榍交错布置。(2) Install the wooden dowel: The wooden dowel is processed into a wedge shape. The wedge-shaped wooden dowel has a thickness ranging from 20-50mm and a length of 100-150mm. It is soaked in anti-corrosion asphalt and dried in the sun. During installation, the wooden dowels are required to be tightly packed, with a spacing of no more than 600mm (use the length of the entire block as the spacing or other masonry materials as the module), and the wooden dowels on both sides of the wall are arranged in a staggered manner.
(3)甩浆湿润:在塞缝前用水湿润墙体顶面及混凝土梁板底,然后在缝隙处甩浆。(3) Slurry wetting: wet the top surface of the wall and the bottom of the concrete beam slab with water before plugging the joints, and then slurry the gaps.
(4)发泡胶或细石混凝土塞缝:塞缝时先从墙体一侧进行,待凝固后再行填塞另一侧。塞缝时保证密实,以干硬性为宜,塞缝后表面与墙体一平。(4) Seams with foam glue or fine stone concrete: When filling seams, start from one side of the wall first, and then fill the other side after solidification. When plugging the joints, make sure they are dense and dry and hard. The surface after plugging the joints should be flush with the wall.
本发明的后砌填充墙构造原理:填充墙砌筑至梁(板)底留有一定的空隙,使砌体充分沉实后,进行墙体顶部塞缝处理。当空隙厚度在20mm以内时,采用发泡胶进行填充;当空隙厚度在30-50mm时,采用C20细石混凝土(微膨胀)填充。交界处采用长度不小于300mm的镀锌钢丝网(孔距12.7×12.7mm,丝径0.9mm)加强在抹灰层的底部,抹灰层的面层压入一层玻璃纤维网格布(300g/m2)。The construction principle of the back-laying infill wall of the present invention is as follows: the infill wall is built until there is a certain gap at the bottom of the beam (slab), and after the masonry is fully compacted, the top of the wall is caulked. When the gap thickness is within 20mm, use foam rubber to fill it; when the gap thickness is between 30-50mm, use C20 fine stone concrete (micro-expansion) to fill it. The junction is reinforced with galvanized steel wire mesh with a length of not less than 300mm (hole spacing 12.7×12.7mm, wire diameter 0.9mm) at the bottom of the plastering layer, and a layer of fiberglass mesh (300g) is pressed into the surface of the plastering layer. / m2 ).
本发明具有实质性特点和显著的技术进步,本发明的后砌填充墙顶塞砌的施工方法,与传统做法相比,施工简便,易于操作,能加快工程进度,缩短工程工期,该塞砌做法能够很好的代替斜砖工艺抵消梁、板的挠度变形,且与墙砖自身的收缩变形相协调,能有效减少墙体表面裂缝。同时发泡胶或细石混凝土固化快,技术间歇时间短,减少斜砌施工二次结构脚手架重复搭设,受到了操作工人及管理、使用单位的欢迎。The present invention has substantive features and significant technological progress. Compared with the traditional method, the construction method of back-fill wall top plugging is simple to construct and easy to operate. It can speed up the project progress and shorten the construction period. The plugging method This method can effectively replace the inclined brick process to offset the deflection deformation of beams and slabs, and is coordinated with the shrinkage deformation of the wall bricks themselves, which can effectively reduce cracks on the wall surface. At the same time, foam rubber or fine stone concrete solidifies quickly, and the technical interval is short, which reduces the repeated erection of secondary structural scaffolding in inclined masonry construction. It is welcomed by operators, management and user units.
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。The above embodiments are only for illustrating the present invention, rather than limiting the present invention. Those skilled in the relevant technical fields can also make various transformations or changes without departing from the spirit and scope of the present invention. Therefore, all equivalent technical solutions should also fall within the scope of the present invention and should be defined by each claim.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310773756.9A CN116856565A (en) | 2023-06-28 | 2023-06-28 | Construction method for top plug of post-built filling wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310773756.9A CN116856565A (en) | 2023-06-28 | 2023-06-28 | Construction method for top plug of post-built filling wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116856565A true CN116856565A (en) | 2023-10-10 |
Family
ID=88220880
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310773756.9A Pending CN116856565A (en) | 2023-06-28 | 2023-06-28 | Construction method for top plug of post-built filling wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116856565A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN119801282A (en) * | 2025-01-14 | 2025-04-11 | 中建八局第二建设有限公司 | A kind of brick wall brick joint processing technology |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106812219A (en) * | 2017-03-14 | 2017-06-09 | 中国十七冶集团有限公司 | Filling wall top stuff up a crack construction method |
| KR101899039B1 (en) * | 2018-04-12 | 2018-09-17 | 한국건설기술연구원 | Brick wall construction method of masonry structure using boundary reinforcement technology |
| CN110905219A (en) * | 2019-12-02 | 2020-03-24 | 淙创(上海)企业管理咨询中心 | Frame structure and filler wall interface combined anti-crack structure and construction method |
| CN219175539U (en) * | 2022-12-01 | 2023-06-13 | 华北冶建工程建设有限公司 | Thermal insulation structure of self-thermal insulation air-adding block wall top and bearing main body structure |
-
2023
- 2023-06-28 CN CN202310773756.9A patent/CN116856565A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106812219A (en) * | 2017-03-14 | 2017-06-09 | 中国十七冶集团有限公司 | Filling wall top stuff up a crack construction method |
| KR101899039B1 (en) * | 2018-04-12 | 2018-09-17 | 한국건설기술연구원 | Brick wall construction method of masonry structure using boundary reinforcement technology |
| CN110905219A (en) * | 2019-12-02 | 2020-03-24 | 淙创(上海)企业管理咨询中心 | Frame structure and filler wall interface combined anti-crack structure and construction method |
| CN219175539U (en) * | 2022-12-01 | 2023-06-13 | 华北冶建工程建设有限公司 | Thermal insulation structure of self-thermal insulation air-adding block wall top and bearing main body structure |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN119801282A (en) * | 2025-01-14 | 2025-04-11 | 中建八局第二建设有限公司 | A kind of brick wall brick joint processing technology |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110747899B (en) | Basement waterproof construction method | |
| CN105484391A (en) | Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks | |
| CN206737417U (en) | A kind of PC prefabricated outer wall panels grouting typified form | |
| CN101761155A (en) | Construction method for ceramsite concrete light-weight wall boards | |
| CN106812219A (en) | Filling wall top stuff up a crack construction method | |
| CN111877596A (en) | Miscellaneous-masonry antique wall structure and construction method thereof | |
| CN102287053A (en) | Construction method for resisting cracks at junctions of plastered filler wall and dry concrete wall | |
| CN116856565A (en) | Construction method for top plug of post-built filling wall | |
| CN219158515U (en) | Masonry wall crack reinforcing structure | |
| CN108894242A (en) | Prefabricated board and its cushion cap foundation fetal membrane construction method for cushion cap foundation fetal membrane | |
| CN117661844A (en) | A kind of lightweight energy-saving wall partition installation and construction method | |
| CN116241007A (en) | Prefabricated floor unidirectional plate close-spliced node structure | |
| CN108486978A (en) | The wing square stone material of the good severe cold area large area of effect is mated formation prevention and cure of crack method | |
| CN211735536U (en) | Off-wall ditch structure and station hall structure layer | |
| CN209585343U (en) | A wall and blocks for filling the top of the wall | |
| CN119392836A (en) | A low energy consumption exterior wall enclosure system and construction method | |
| CN116220244B (en) | Construction method of thermal insulation exterior wall structure with window sill opening | |
| CN106337511A (en) | Wall structure of house and construction method of wall structure | |
| CN102182323A (en) | Process for dry laying of autoclaved aerated concrete blocks in low-latitude plateaus | |
| CN102535847A (en) | Method for constructing gypsum self-insulation outer wall block masonry | |
| CN114908993A (en) | A brick wall reinforcement method based on cyclic polyolefin resin and prefabricated high ductility cementitious composite board | |
| CN221001655U (en) | Retaining member for masonry and pouring of filled wall constructional column | |
| CN105297950A (en) | Infilled wall and horizontal load-bearing structure gap wall surface crack-controlling construction method | |
| CN117926859B (en) | Basement waterproof protection structure and construction method | |
| CN204225307U (en) | A kind of fire hydrant box back side body of wall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |