CN116201118A - Anchor cable dismantling construction method for foundation pit anchor pile - Google Patents
Anchor cable dismantling construction method for foundation pit anchor pile Download PDFInfo
- Publication number
- CN116201118A CN116201118A CN202310109998.8A CN202310109998A CN116201118A CN 116201118 A CN116201118 A CN 116201118A CN 202310109998 A CN202310109998 A CN 202310109998A CN 116201118 A CN116201118 A CN 116201118A
- Authority
- CN
- China
- Prior art keywords
- anchor
- pile
- stress
- pile body
- foundation pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 30
- 238000005520 cutting process Methods 0.000 claims abstract description 29
- 238000012544 monitoring process Methods 0.000 claims abstract description 19
- 238000000034 method Methods 0.000 claims abstract description 15
- 239000002689 soil Substances 0.000 claims description 11
- 230000008569 process Effects 0.000 claims description 10
- 238000006073 displacement reaction Methods 0.000 claims description 9
- 239000003337 fertilizer Substances 0.000 claims description 7
- 230000009467 reduction Effects 0.000 claims description 4
- 230000008859 change Effects 0.000 claims description 3
- 239000011435 rock Substances 0.000 claims description 2
- 238000010586 diagram Methods 0.000 description 5
- 238000004873 anchoring Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000007423 decrease Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005489 elastic deformation Effects 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
发明提供一种用于基坑锚拉桩的锚索拆除施工方法。该方法包括对锚索位置进行定位编号、确定应力释放度进度表、确定锚拉桩截面刚度释放区、对锚拉桩桩身截面进行切割及同步监测并动态化调整等步骤。该方法可解决在特定建筑功能要求的前提下,对常规锚拉桩的锚索进行安全快速拆除,从而满足后期的建筑功能需要。本发明施工较为简捷,仅需确定桩身刚度释放区对锚拉桩桩身做一定切割,待应力释放后直接拆除支护桩及锚索,具有操作简单,工期短、安全性较高等优点。
The invention provides an anchor cable removal construction method for foundation pit anchor piles. The method includes the steps of locating and numbering the position of the anchor cable, determining the schedule of the stress release degree, determining the rigidity release area of the cross-section of the anchor-stayed pile, cutting and synchronously monitoring and dynamically adjusting the cross-section of the anchor-stay pile. This method can solve the problem of safely and quickly removing the anchor cables of conventional anchor piles under the premise of specific building function requirements, so as to meet the later building function needs. The construction of the present invention is relatively simple, and only needs to determine the rigidity release area of the pile body to cut the anchor pile body to a certain extent, and directly remove the supporting pile and the anchor cable after the stress is released, which has the advantages of simple operation, short construction period and high safety.
Description
技术领域technical field
本发明涉及基坑工程领域,特别涉及一种用于基坑锚拉桩的锚索拆除施工方法。The invention relates to the field of foundation pit engineering, in particular to an anchor cable removal construction method for foundation pit anchor piles.
背景技术Background technique
目前基坑围护工程根据地质情况可采用土钉墙、锚杆支护、排桩、锚拉桩以及排桩加内支撑等工程方案。随着城市的大规模建设,基坑工程周边的建筑环境日趋复杂,如电力管沟、给水管线,通讯管线等,这对基坑围护结构的变形控制指标提出了更高的要求。At present, according to the geological conditions, the foundation pit enclosure project can adopt engineering schemes such as soil nailing wall, anchor support, row of piles, anchor piles, and row of piles plus internal support. With the large-scale construction of the city, the surrounding building environment of the foundation pit project is becoming more and more complex, such as power pipe trenches, water supply pipelines, communication pipelines, etc., which put forward higher requirements for the deformation control indicators of the foundation pit enclosure structure.
锚拉桩作为控制变形较好的一种结构形式,在基坑工程中应用较为广泛。基坑开挖过程中按照逆作法施工锚拉桩围护结构,基坑回填过程中,锚索体系直接回填在建筑主体结构与围护结构之间不再拆除。Anchor-stayed piles, as a structural form with better deformation control, are widely used in foundation pit engineering. During the excavation of the foundation pit, the anchor pile enclosure structure is constructed according to the reverse method. During the backfilling process of the foundation pit, the anchor cable system is directly backfilled between the main structure of the building and the enclosure structure without dismantling.
随着人民对城市建筑功能的需求呈现多样化,建筑功能布局正在发生更多的变化,锚索有时会与建筑的附属结构之间存在冲突,需要在建筑的附属结构施工前对锚索进行拆除。With the diversification of people's demands on the functions of urban buildings, more changes are taking place in the layout of building functions. Sometimes there are conflicts between the anchor cables and the auxiliary structures of the buildings, and the anchor cables need to be removed before the construction of the auxiliary structures of the buildings. .
常规的基坑支护中锚拉桩结构拆除方法为先搭设支架平台,再由工人手持风镐对锚头的钢筋混凝土结构进行凿打,待锚头上锚索的锚固结构失效后,锚索应力急剧释放,再进行锚拉桩结构拆除。然而,锚索为预应力结构,受力较大,应力高。这种传统的拆除方法会导致锚索的高应力突然释放,锚索的高应力瞬时回弹会对施工作业人员造成伤害,施工风险极大。The conventional method of demolishing the anchor pile structure in foundation pit support is to first set up the support platform, and then the workers hold the jackhammer to chisel the reinforced concrete structure of the anchor head. After the anchoring structure of the anchor cable on the anchor head fails, the anchor cable The stress is released rapidly, and then the anchor pile structure is demolished. However, the anchor cable is a prestressed structure, which is subjected to a large force and high stress. This traditional demolition method will lead to the sudden release of the high stress of the anchor cable, and the instantaneous rebound of the high stress of the anchor cable will cause injury to the construction workers, and the construction risk is extremely high.
综述,亟需对锚拉桩的常规锚索体系拆除工艺提出一种新的普遍适用的拆除施工方法。In summary, it is urgent to propose a new universally applicable demolition construction method for the conventional anchor cable system demolition process of anchor-stayed piles.
发明内容Contents of the invention
本发明的目的是提供一种用于基坑锚拉桩的锚索拆除施工方法,以解决现有技术中存在的问题。The purpose of the present invention is to provide a kind of anchor cable removal construction method for foundation pit anchor pile, to solve the problems existing in the prior art.
为实现本发明目的而采用的技术方案是这样的,一种用于基坑锚拉桩的锚索拆除施工方法,基坑围护结构采用排桩+锚索支护体系。支护桩下部嵌入岩土层中。相邻支护桩的桩顶设置有连系梁。所述支护桩沿着桩身长度方向开设有多个锚索孔。锚索的一端穿过锚索孔植入基坑周侧土体内,另一端通过锚头与支护桩固定。附属建筑附着在主楼结构旁侧。The technical solution adopted to realize the purpose of the present invention is as follows, a construction method for removing anchor cables for foundation pit anchor piles, and the foundation pit enclosure structure adopts a row of piles + anchor cable support system. The lower part of the support pile is embedded in the rock-soil layer. The pile tops of adjacent support piles are provided with connecting beams. The support pile is provided with a plurality of anchor cable holes along the length direction of the pile body. One end of the anchor cable is implanted into the soil around the foundation pit through the anchor cable hole, and the other end is fixed with the support pile through the anchor head. The outbuildings are attached to the side of the main building structure.
用于基坑锚拉桩的锚索拆除施工方法包括以下步骤:The anchor cable removal construction method for foundation pit anchor piles comprises the following steps:
1)确定需要拆除的锚索的位置,并进行编号。1) Determine the position of the anchor cable that needs to be removed and number it.
2)初步确定支护桩的桩身应力释放度进度表。其中,桩身应力释放度进度表为初定的锚索拉力释放进度表。2) Preliminary determination of the pile body stress release schedule of the supporting piles. Among them, the pile body stress release schedule is the initially determined anchor cable tension release schedule.
3)根据初步确定的应力释放度进度表拟定好各个分步的桩身切割深度后,逐步分序释放桩身刚度,从而得到支护桩截面刚度释放区。3) According to the initially determined schedule of stress release degree, after each step-by-step cutting depth of the pile body is prepared, the stiffness of the pile body is released step by step, so as to obtain the section stiffness release area of the supporting pile.
4)安装应力测定计,对支护桩桩身截面进行第一次切割至初定的切割深度。其中,切割深度按照刚度释放区确定。4) Install the stress gauge, and cut the section of the support pile body for the first time to the predetermined cutting depth. Wherein, the cutting depth is determined according to the stiffness release area.
5)等待支护桩变形。在此过程中进行桩身应力监测记录。支护桩缓慢释放刚度,锚索应力逐渐松弛。5) Wait for the deformation of the support pile. During this process, pile body stress monitoring records are carried out. The stiffness of the supporting pile is slowly released, and the stress of the anchor cable is gradually relaxed.
6)待支护桩应力值降低并趋于稳定值。若实际支护桩应力降低值与初定的应力释放进度表不吻合,则根据实际的监测记录进行动态化调整。6) The stress value of the pile to be supported decreases and tends to a stable value. If the actual stress reduction value of the support piles does not match the initial stress release schedule, dynamic adjustments will be made based on the actual monitoring records.
7)重复步骤3)~步骤6),多次释放支护桩应力,直至锚索应力全部松弛,而后完全拆除锚索。7) Repeat steps 3) to 6) to release the stress of the support pile several times until the stress of the anchor cable is completely relaxed, and then completely remove the anchor cable.
进一步,步骤3)中,锚索拉力释放进度表按照单次释放15%的锚索拉力为标准,逐次分步切割桩身,减小桩身截面,减少桩身刚度,降低桩身应力的进度表。Further, in step 3), the anchor cable tension release schedule is based on a single release of 15% of the anchor cable tension as the standard, and the pile body is cut step by step to reduce the section of the pile body, reduce the stiffness of the pile body, and reduce the progress of the pile body stress surface.
进一步,步骤5)中,通过应力测定计监测支护桩的应力变化情况。所述应力测定计布置在锚头周边。Further, in step 5), the stress change of the support pile is monitored by a stress gauge. The stress gauge is arranged around the anchor head.
进一步,在基坑肥槽底面以及地表设置有位移监测点。锚索拆除过程中,位移监测点对基坑顶部及主体结构之间的相关位移进行监测。Further, displacement monitoring points are set on the bottom of the fertilizer tank of the foundation pit and the ground surface. During the removal of the anchor cable, the displacement monitoring point monitors the relative displacement between the top of the foundation pit and the main structure.
进一步,锚索拆除过程中,逐步回填基坑肥槽。Further, during the removal of the anchor cables, the fertilizer groove of the foundation pit is gradually backfilled.
进一步,步骤6)中,若实测应力释放值较大,则在下一次桩身切割时减小切割深度。Further, in step 6), if the measured stress release value is larger, the cutting depth will be reduced in the next pile cutting.
本发明的技术效果是毋庸置疑的:Technical effect of the present invention is beyond doubt:
A.施工较为简捷,仅需确定桩身应力释放进度表及桩身刚度释放区即切割深度,对锚拉桩桩身做一定切割后,待桩身应力完全释放后直接拆除锚索,具有操作简单,工期短、安全性较高等优点;A. The construction is relatively simple. It is only necessary to determine the stress release schedule of the pile body and the cutting depth of the pile body stiffness release area. After a certain cut is made on the anchor pile body, the anchor cable is removed directly after the pile body stress is completely released. Simple, short construction period, high safety and other advantages;
B.可解决在特定建筑功能要求的前提下,对常规锚拉桩的锚索进行安全快速拆除,从而满足后期的建筑功能需要。B. Under the premise of specific architectural functional requirements, the anchor cables of conventional anchor piles can be safely and quickly removed, so as to meet the later architectural functional needs.
附图说明Description of drawings
图1为施工方法流程图;Fig. 1 is the flow chart of construction method;
图2为锚索平面位置示意图;Figure 2 is a schematic diagram of the plane position of the anchor cable;
图3为锚索竖向位置示意图;Fig. 3 is a schematic diagram of the vertical position of the anchor cable;
图4为锚拉桩桩身截面切割位置示意图;Fig. 4 is the schematic diagram of the cutting position of the pile body section of the anchor pile;
图5为基坑肥槽回填示意图;Fig. 5 is a schematic diagram of backfilling the foundation pit fertilizer tank;
图6为锚索拆除后修建的附属建筑结构图。Figure 6 is a structural diagram of the ancillary buildings built after the anchor cables were removed.
具体实施方式Detailed ways
下面结合实施例对本发明作进一步说明,但不应该理解为本发明上述主题范围仅限于下述实施例。在不脱离本发明上述技术思想的情况下,根据本领域普通技术知识和惯用手段,做出各种替换和变更,均应包括在本发明的保护范围内。The present invention will be further described below in conjunction with the examples, but it should not be understood that the scope of the subject of the present invention is limited to the following examples. Without departing from the above-mentioned technical ideas of the present invention, various replacements and changes made according to common technical knowledge and conventional means in this field shall be included in the protection scope of the present invention.
实施例1:Example 1:
本实施例提供一种用于基坑锚拉桩的锚索拆除施工方法,基坑围护结构采用排桩+锚索支护体系。支护桩1下部嵌入岩土层中。相邻支护桩1的桩顶设置有连系梁。所述支护桩1沿着桩身长度方向开设有多个锚索孔。锚索2的一端穿过锚索孔植入基坑周侧土体内,另一端通过锚头3与支护桩1固定。附属建筑9附着在主楼结构8旁侧。This embodiment provides a construction method for removing anchor cables for anchor piles in foundation pits. The enclosure structure of the foundation pit adopts a pile row + anchor cable support system. The lower part of the
用于基坑锚拉桩的锚索拆除施工方法包括以下步骤:The anchor cable removal construction method for foundation pit anchor piles comprises the following steps:
1)确定需要拆除的锚索2的位置,并进行编号。1) Determine the position of the
2)初步确定支护桩1的桩身应力释放度进度表。其中,桩身应力释放度进度表为逐次分步切割桩身,减小桩身截面,释放桩身刚度,降低桩身应力的进度表。2) Preliminary determination of the pile body stress release schedule of the
3)根据初步确定的应力释放度进度表拟定好各个分步的桩身切割深度后,逐步分序释放桩身刚度,从而得到支护桩1截面刚度释放区。在本实施例中,桩身应力释放度进度表为锚索拉力释放进度表,按照单次释放15%的锚索拉力为标准,逐次分步切割桩身,减小桩身截面,减少桩身刚度,降低桩身应力的进度表。3) According to the initially determined stress release schedule, after each step-by-step cutting depth of the pile body is prepared, the stiffness of the pile body is released step by step, so as to obtain the section stiffness release area of the
4)安装应力测定计5,对支护桩1桩身截面进行第一次切割至初定的切割深度。其中,切割深度按照刚度释放区确定。所述应力测定计5布置在锚头3周边。4) Install the
5)等待支护桩1变形。在此过程中通过应力测定计5监测支护桩1的应力变化情况。支护桩1缓慢释放刚度,锚索2应力逐渐松弛。5) Wait for the
6)待支护桩1应力值降低并趋于稳定值。若实际支护桩1应力降低值与初定的应力释放进度表不吻合,则根据实际的监测记录进行动态化调整。若实测应力释放值较大,则在下一次桩身切割时减小切割深度。6) The stress value of
7)重复步骤3)~步骤6),多次释放支护桩1应力,直至锚索2应力全部松弛,而后完全拆除锚索2。7) Repeat steps 3) to 6) to release the stress of the
本实施例可解决在特定建筑功能要求的前提下,对常规锚拉桩的锚索进行安全快速拆除,从而满足后期的建筑功能需要。本实施例施工较为简捷,仅需确定桩身刚度释放区对锚拉桩桩身做一定切割,待应力释放后直接拆除支护桩及锚索,具有操作简单,工期短、安全性较高等优点。This embodiment can solve the problem of safely and quickly removing the anchor cables of conventional anchor piles under the premise of specific architectural functional requirements, so as to meet the later architectural functional requirements. The construction of this embodiment is relatively simple. It only needs to determine the rigidity release area of the pile body and cut the anchor pile body to a certain extent. After the stress is released, the supporting pile and anchor cable are directly removed. It has the advantages of simple operation, short construction period and high safety. .
实施例2:Example 2:
参见图1~图6,本实施例提供一种用于基坑锚拉桩的锚索拆除施工方法,基坑围护结构采用排桩+锚索支护体系。支护桩1下部嵌入岩土层中。相邻支护桩1的桩顶设置有连系梁。所述支护桩1沿着桩身长度方向开设有多个锚索孔。锚索2的一端穿过锚索孔植入基坑外侧岩土体内,另一端通过锚头3与支护桩1固定。通过锚头3对锚索2施加预应力,并将锚固力传递给支护桩1。所述锚索2的自由段连接锚头3和锚固段,利用自由段的弹性变形特性把预加应力传递给锚固段。锚固段通过与胶结体之间的粘结力、胶结体自身的承载力以及胶结体与周围土体之间的粘结力,最终将排桩后土压力通过锚索2传递到土体。Referring to FIGS. 1 to 6 , this embodiment provides a construction method for removing anchor cables for anchor piles in foundation pits. The enclosure structure of the foundation pit adopts a pile row + anchor cable support system. The lower part of the
附属建筑9附着在主楼结构8旁侧。附属建筑9在主楼结构8之后施工,附属建筑9在空间上与主楼结构8的桩锚支护体系在空间上存在重叠,故施工附属建筑9前,需要对与其有空间重叠的桩锚支护体系部分进行拆除。An
参见图1,用于基坑锚拉桩的锚索拆除施工方法包括以下步骤:Referring to Fig. 1, the anchor cable removal construction method for foundation pit anchor pile comprises the following steps:
1)确定需要拆除的锚索2的位置并进行编号。1) Determine the position of the
2)初步确定支护桩1应力释放度进度表,桩身应力释放度进度表特指逐次分步切割桩身,减小桩身截面,释放桩身刚度,降低桩身应力的进度表。支护桩1第一次切割桩身深度采用15cm。2) Preliminarily determine the schedule of stress release degree of supporting
3)对支护桩1桩身截面采用风钻及钢筋剪刀或常见的手推式切桩机等工具进行切割,切割深度及进度按照上述应力释放进度表分步分序实施。切割桩身前需要在桩身切割线上方50cm范围内安装应力测定计5,在对桩身切割的过程中做好对桩身应力监测。3) The section of the
4)完成第一次切割后,做好桩基应力监测并做好监测记录,等待支护桩1变形稳定。在此过程中,支护桩1缓慢释放刚度,锚索2应力逐渐松弛。4) After the first cutting, do a good job of monitoring the pile foundation stress and making monitoring records, and wait for the deformation and stability of the supporting
5)按照上述应力释放进度表分步分序采用风钻及钢筋剪刀或常见的手推式切桩机等工具对桩身进行切割,同时做好桩身应力监测,直至桩身应力趋于0并通过监测显示处于稳定状态。支护桩1的应力释放度进度表应根据上述切割过程中的应力实测值实时动态修正,整个过程采用动态化调整,加强监测。若支护桩(1)应力实际降低值与初定的应力释放进度表不吻合,则根据实际的监测记录做动态化调整,如实测应力释放值较大,则在下一次桩身切割时减小切割深度,缓慢降低桩身刚度,防止应力骤降,引发不利工况。5) According to the above stress release schedule, use tools such as pneumatic drills, steel scissors or common hand-push pile cutters to cut the pile body step by step, and do a good job of monitoring the stress of the pile body until the stress of the pile body tends to 0 and The monitoring shows that it is in a stable state. The stress release schedule of the
6)重复步骤3)~步骤5),多次释放支护桩1应力,直至锚索2应力全部松弛,而后完全拆除锚索2。6) Repeat steps 3) to 5) to release the stress of the
实施例3:Example 3:
本实施例主要步骤同实施例1,其中,步骤4)中,通过应力测定计5监测支护桩1的应力变化情况。所述应力测定计5布置在锚头3周边。The main steps of this embodiment are the same as those of
实施例4:Example 4:
本实施例主要步骤同实施例1,其中,在基坑肥槽底面以及地表设置有位移监测点4。锚索拆除过程中,位移监测点4对基坑顶部及主体结构之间的相关位移进行监测。The main steps of this embodiment are the same as those of
实施例5:Example 5:
本实施例主要步骤同实施例1,其中,锚索拆除过程中,逐步回填基坑肥槽。The main steps of this embodiment are the same as those of
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310109998.8A CN116201118B (en) | 2023-02-14 | 2023-02-14 | Anchor cable dismantling construction method for foundation pit anchor pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310109998.8A CN116201118B (en) | 2023-02-14 | 2023-02-14 | Anchor cable dismantling construction method for foundation pit anchor pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116201118A true CN116201118A (en) | 2023-06-02 |
| CN116201118B CN116201118B (en) | 2024-08-02 |
Family
ID=86510734
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310109998.8A Active CN116201118B (en) | 2023-02-14 | 2023-02-14 | Anchor cable dismantling construction method for foundation pit anchor pile |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116201118B (en) |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1393880A1 (en) * | 1986-09-29 | 1988-05-07 | Бюро внедрения новых видов оснований и фундаментов Научно-исследовательского института оснований и подземных сооружений им.Н.М.Герсеванова | Apparatus for driving trench pits |
| DE4411643A1 (en) * | 1994-04-02 | 1995-10-05 | Dyckerhoff & Widmann Ag | Method of dismantling free part of tensioned member of prestressed anchor on bore-hole end of loaded anchoring body |
| JP2000073374A (en) * | 1998-09-02 | 2000-03-07 | Sakata Construction Co Ltd | Slope stabilizing method and independent slope bearing device |
| US20150211205A1 (en) * | 2014-01-29 | 2015-07-30 | Guangzhou Jishi Construction Group Co., Ltd. | Construction system for subway station |
| CN205591268U (en) * | 2015-12-10 | 2016-09-21 | 中铁二院工程集团有限责任公司 | Anchor rope stress relaxation restores reinforcing structure |
| CN110396916A (en) * | 2019-07-11 | 2019-11-01 | 重庆大学 | Joint structure and construction technology of U-shaped thin-walled steel-prestressed concrete composite cover beam and thin-walled concrete-filled steel tube pier |
| CN111287225A (en) * | 2020-02-20 | 2020-06-16 | 中南大学 | Anchor rod stress monitoring and reconstruction slope stability evaluation method for anchoring type slope |
| CN111456023A (en) * | 2020-03-31 | 2020-07-28 | 江苏东合南岩土科技股份有限公司 | A kind of construction method of underground prestressed support structure |
| CN212926102U (en) * | 2020-08-20 | 2021-04-09 | 机械工业勘察设计研究院有限公司 | Recoverable ground tackle and waist rail supporting device based on foundation ditch slope protection pile |
-
2023
- 2023-02-14 CN CN202310109998.8A patent/CN116201118B/en active Active
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1393880A1 (en) * | 1986-09-29 | 1988-05-07 | Бюро внедрения новых видов оснований и фундаментов Научно-исследовательского института оснований и подземных сооружений им.Н.М.Герсеванова | Apparatus for driving trench pits |
| DE4411643A1 (en) * | 1994-04-02 | 1995-10-05 | Dyckerhoff & Widmann Ag | Method of dismantling free part of tensioned member of prestressed anchor on bore-hole end of loaded anchoring body |
| JP2000073374A (en) * | 1998-09-02 | 2000-03-07 | Sakata Construction Co Ltd | Slope stabilizing method and independent slope bearing device |
| US20150211205A1 (en) * | 2014-01-29 | 2015-07-30 | Guangzhou Jishi Construction Group Co., Ltd. | Construction system for subway station |
| CN205591268U (en) * | 2015-12-10 | 2016-09-21 | 中铁二院工程集团有限责任公司 | Anchor rope stress relaxation restores reinforcing structure |
| CN110396916A (en) * | 2019-07-11 | 2019-11-01 | 重庆大学 | Joint structure and construction technology of U-shaped thin-walled steel-prestressed concrete composite cover beam and thin-walled concrete-filled steel tube pier |
| CN111287225A (en) * | 2020-02-20 | 2020-06-16 | 中南大学 | Anchor rod stress monitoring and reconstruction slope stability evaluation method for anchoring type slope |
| CN111456023A (en) * | 2020-03-31 | 2020-07-28 | 江苏东合南岩土科技股份有限公司 | A kind of construction method of underground prestressed support structure |
| CN212926102U (en) * | 2020-08-20 | 2021-04-09 | 机械工业勘察设计研究院有限公司 | Recoverable ground tackle and waist rail supporting device based on foundation ditch slope protection pile |
Non-Patent Citations (2)
| Title |
|---|
| 周莉莉;曹小兵;: "预应力锚索在边坡工程中的应用", 西部探矿工程, no. 1, 25 June 2006 (2006-06-25), pages 525 - 526 * |
| 毕平均;刘全林;: "旋喷搅拌加劲锚桩对软土基坑变形控制效果的分析", 建筑结构, vol. 2, no. 2, 15 October 2013 (2013-10-15), pages 635 - 639 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116201118B (en) | 2024-08-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109610881A (en) | A construction method for replacing broken columns with prestressed beams in the renovation of existing multi-storey buildings | |
| CN106978807A (en) | Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area | |
| CN113356219A (en) | Synchronous excavation construction method for foundation pits at different depths on two sides of operation subway | |
| CN111622268A (en) | Protection construction method based on large rigid box culvert passing under power pipe gallery | |
| CN105421474B (en) | For the plant pile cofferdam platform integral construction method of lithostratigraphy low pile cap | |
| CN106988754A (en) | Narrow space shield tunneling machine starting method | |
| CN113356198A (en) | Single-spliced channel steel anchor rod waist beam structure and using method thereof | |
| CN206570811U (en) | Existing bridge pile pulling device is passed through in weak soil shield driving area | |
| CN119121967A (en) | A tunnel portal side slope micro steel pipe pile-anchor support construction method | |
| CN114687345A (en) | Method for repairing surface subsidence or deformation of underground pipe outside foundation pit enclosure wall | |
| CN112443335B (en) | Supporting system for automatically controlling deformation of tunnel underpass pipeline and construction method thereof | |
| CN109854266B (en) | Non-excavation type pipe jacking prestressed beam construction method | |
| CN106760851A (en) | The construction method of the newly-increased Seismic Isolation of Isolation Layer of existing brick mix structure | |
| CN106948347B (en) | Pile pulling method and pile pulling system | |
| CN212358029U (en) | Tunnel type anchorage structure for cable crane | |
| CN116201118A (en) | Anchor cable dismantling construction method for foundation pit anchor pile | |
| CN108797323A (en) | Steel trestle suitable for hard stratum | |
| CN109706848B (en) | Construction method for jacking bridge and culvert by using through jack | |
| CN119801545A (en) | Construction method of inclined shaft section of hydraulic tunnel | |
| CN218932918U (en) | Abutment Correction and Reinforcement Structure | |
| CN115717368B (en) | Bridge abutment correction reinforcing structure and construction method thereof | |
| CN111827307A (en) | A combined construction method pile supporting structure and its construction method | |
| CN118128107A (en) | Construction method for reinforcing and synchronously rectifying existing building foundation | |
| CN117905943A (en) | A construction method to ensure the safety of pipeline under shield tunnel | |
| CN116025005B (en) | Subway station main body structure construction method influenced by double rows of lattice columns |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |