Process for the manufacture of buildings

Info

Publication number
CH431912A
CH431912A CH291665A CH291665A CH431912A CH 431912 A CH431912 A CH 431912A CH 291665 A CH291665 A CH 291665A CH 291665 A CH291665 A CH 291665A CH 431912 A CH431912 A CH 431912A
Authority
CH
Switzerland
Prior art keywords
buildings
prefabricated
building
components
production
Prior art date
Application number
CH291665A
Other languages
German (de)
Inventor
Schmid Felix
Stuessi Rudolf
Original Assignee
Schmid Felix
Stuessi Rudolf
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Schmid Felix, Stuessi Rudolf filed Critical Schmid Felix
Priority to CH291665A priority Critical patent/CH431912A/en
Publication of CH431912A publication Critical patent/CH431912A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/348Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Description

  

  Verfahren     zur    Herstellung von Gebäuden    Bei der Herstellung von Gebäuden wird zur Be  schleunigung der Herstellung und zur Herabsetzung der  Kosten weitgehend von der Verwendung vorfabrizierter  Teile Gebrauch gemacht. Als solche     vorfabrizierte    Teile  werden Wände, Böden oder Decken hergestellt und auf  dem Bauplatz zu einem Gebäude     zusammengesetzt.    Es  ist auch schon vorgeschlagen worden, ganze Zimmer     in     Form eines     Hohl-Kubus    in     Vorfabrikation    herzustellen  und durch Zusammenfügen mehrerer solcher Gebilde       ein    Gebäude zu     errichten.     



  Die     erstgenannte    Art bedeutet nur einen Schritt in  der Herstellung der Gebäude und verlangt noch weit  gehende Bauarbeiten auf dem Bauplatz selbst.  



  Das zweitgenannte Verfahren lässt sich praktisch  nur verwenden, wenn Gebäude gebaut werden sollen,  welche alle genau gleich grosse Wohnräume aufweisen.  Ausserdem ergibt sich     beim        Zusammenfügen    der Hohl  kuben     immer    eine doppelte     Wand    oder     ein    doppelter  Boden bzw. Decke.  



  Die     vorliegende    Erfindung betrifft ein     Verfahren,     welches die     Vorfabrikation        weitertreibt    als die erstge  nannte Art, aber die Möglichkeit schafft, Wohnräume  verschiedener Grösse bilden zu können.  



  Das Verfahren zeichnet sich dadurch aus, dass man  U-förmige Bauelemente vorfabriziert, welche Seiten  wände und Boden oder Decke eines     Gebäudeteiles    zu  bilden bestimmt sind, wobei man in diese Bauelemente  mindestens einen Teil der vorgesehenen Installationen  einbaut, und dass man diese Bauelemente zu einem Ge  bäude zusammensetzt und sie     miteinander        verbindet.    In  den beiliegenden Zeichnungen ist ein Ausführungsbei  spiel dargestellt, anhand welchem das Verfahren er  läutert werden soll.  



  Es zeigen:       Fig.    1 ein Bauelement mit einer Zwischenwand in       perspektivischer        Ansicht,          Fig.    2 mehrere     aufeinander    und nebeneinander ge  stellte Bauelemente,       Fig.3    mehrere nebeneinander gestellte Bauele  mente, die zusammen eine Wohnung     bilden.       Das Bauelement 1 besitzt     U-Form,    welche im vor  liegenden Fall nach oben offen ist; es besteht aus einem  Boden 2 und zwei Seitenteilen 3, welche Teile der  Aussenwand des zu erstellenden Gebäudes bilden.  



  Das Bauelement 1 ist     zweckmässigerweise    so di  mensioniert, dass seine beiden     Seitenteile    3 Teile der  Aussenwand des Gebäudes bilden, in welchem     Falle     die Seitenteile 3 eine entsprechende Dicke aufweisen.  



  Zur Bildung von Räumen ist das Bauelement in       seiner    Querrichtung durch Einbau von     einer    oder meh  reren Zwischenwänden 4 unterteilt, wobei diese Zwi  schenwände Türöffnungen oder Öffnungen für eine  Durchreiche usw. aufweisen     können.     



  In der Längsrichtung können die Bauelemente eben  falls Zwischenwände 5 aufweisen, welche die freien  Öffnungen     abschliessen,    wobei auch diese Zwischen  wände 5 Türöffnungen besitzen oder Installationen auf  weisen können.  



  Wenn ein Bauelement     bestimmt    ist, Ecke     eines    Ge  bäudes zu bilden, kann es auf der Aussenseite mit einer  Aussenwand 6     (Fig.    3) versehen sein, welche entweder  aus einem oder mehreren Teilen besteht. Diese Aussen  wände 6 dienen zur Befestigung der Zwischenwände 4.  



  In die Bauelemente 1 sind Installationen eingebaut,  welche in den betreffenden Räumen vorhanden     sein     sollen. Vor allem werden die in den Wänden unterzu  bringenden Leitungen für Wasser, Strom bei der Vor  fabrikation eingebaut, derart, dass nach Zusammen  setzung des Gebäudes lediglich     benachbarte    Leitungen  verschiedener Elemente     zusammengeschlossen    werden  müssen.  



  Daneben werden     zweckmässigerweise,    wie dies       Fig.    3 zeigt, noch weitere Installationen 7 in das Bau  element eingebaut,     nämlich    z. B. Badewanne, WC,  Kochherd, Schüttstein, Abwaschbecken,     Tropfbrett,          Kasten,    Treppen, Elektroinstallationen und     Heizungsin-          stallationen,    Steigleitungen usw.

   Es ist     ohne    weiteres  klar, dass der     Einbau    der Installationen während und  nach der Erstellung des Bauelementes     im    Werk eine be-      deutende Zeit- und     Kostenersparnis    gegenüber dem Ein=  bau auf dem Bauplatz bedeutet.  



  Der     Zusammenbau    erfolgt so, dass die     einzelnen     Bauelemente in vorbestimmter Reihenfolge etagenweise       nebeneinandergestellt    und     miteinander    verbunden wer  den. Die Verbindung kann erfolgen,     indem    die benach  barten Bauelemente durch besondere Befestigungsor  gane     miteinander    verbunden werden oder indem, bei  spezieller     Ausgestaltung    der gegenseitigen     Berührungs-          flächen    der Bauelemente, diese     ineinandergefügt    und  ausgegossen werden.  



  Nach Verlegen einer Etage werden     die    Bauelemente  der nächsten Etage darauf gestellt, so dass der Boden  des oberen Stockwerkes die Decke des darunterliegen  den Stockwerkes     bildet.    Die beiden Stockwerke werden  miteinander     in    irgendeiner Weise verbunden.  



  Das oberste Stockwerk wird durch Deckenteile,  welche in     ihrem    Ausmass zweckmässig einem Bauele  ment entsprechen, gedeckt und verbunden.



  Process for the manufacture of buildings In the manufacture of buildings, extensive use is made of the use of prefabricated parts in order to accelerate the manufacture and to reduce costs. Walls, floors or ceilings are manufactured as such prefabricated parts and put together to form a building on the construction site. It has also been proposed to manufacture whole rooms in the form of a hollow cube in prefabrication and to erect a building by joining several such structures.



  The first type means only one step in the construction of the building and requires extensive construction work on the site itself.



  The second-mentioned method can only be used in practice if buildings are to be built which all have living spaces of exactly the same size. In addition, when the hollow cubes are joined, there is always a double wall or a double floor or ceiling.



  The present invention relates to a method which advances prefabrication than the first mentioned type, but creates the possibility of being able to form living spaces of different sizes.



  The process is characterized in that U-shaped components are prefabricated, which side walls and floor or ceiling of a building section are intended to be formed, with at least part of the planned installations being built into these components, and these components being made into a Ge building and connecting them together. In the accompanying drawings, a Ausführungsbei is shown game on the basis of which the method he is to be explained.



  1 shows a component with a partition in a perspective view, FIG. 2 shows several components placed one on top of the other and side by side, FIG. 3 shows several components placed next to one another, which together form an apartment. The component 1 has a U-shape, which is open at the top in the case before; it consists of a floor 2 and two side parts 3, which form parts of the outer wall of the building to be constructed.



  The component 1 is expediently dimensioned so that its two side parts 3 form parts of the outer wall of the building, in which case the side parts 3 have a corresponding thickness.



  To form spaces, the component is divided in its transverse direction by installing one or more intermediate walls 4, which intermediate walls can have door openings or openings for a hatch, etc.



  In the longitudinal direction, the components can also have intermediate walls 5 which close the free openings, and these intermediate walls 5 have door openings or can have installations.



  If a component is intended to form the corner of a building, it can be provided on the outside with an outer wall 6 (FIG. 3), which consists of either one or more parts. These outer walls 6 are used to fasten the partition walls 4.



  In the components 1 installations are built in, which should be present in the rooms concerned. Above all, the lines for water and electricity to be accommodated in the walls are installed in the prefabrication in such a way that only adjacent lines of different elements have to be connected after the building has been put together.



  In addition, as shown in FIG. 3, further installations 7 are expediently built into the construction element, namely z. B. bath tub, toilet, stove, pouring stone, sink, drip board, box, stairs, electrical and heating installations, risers, etc.

   It is immediately clear that the installation of the installations during and after the construction of the component in the factory means significant time and cost savings compared to installation on the construction site.



  The assembly is carried out in such a way that the individual components are placed next to one another in a predetermined sequence and connected to one another. The connection can be made in that the neighboring components are connected to one another by special fastening elements or, in the case of a special configuration of the mutual contact surfaces of the components, they are inserted into one another and poured out.



  After laying one floor, the structural elements of the next floor are placed on it so that the floor of the upper floor forms the ceiling of the floor below. The two floors are connected to each other in some way.



  The top floor is covered and connected by ceiling parts, which suitably correspond to a component in their dimensions.

 

Claims (1)

PATENTANSPRUCH Verfahren zur Herstellung von Gebäuden mittels vorfabrizierten Bauelementen, dadurch gekennzeichnet, dass man U-förmige Bauelemente vorfabriziert, welche Seitenwände und Boden oder Decke eines Gebäude teiles zu bilden bestimmt sind, wobei man in diese Bau elemente mindestens einen Teil der vorgesehenen In stallationen einbaut, und dass man diese Bauelemente zu einem Gebäude zusammensetzt und sie miteinander verbindet. UNTERANSPRÜCHE 1. PATENT CLAIM Process for the production of buildings by means of prefabricated construction elements, characterized in that U-shaped construction elements are prefabricated, which side walls and floor or ceiling of a building part are intended to be formed, with at least a part of the intended installations being built into these construction elements and that you put these components together to form a building and connect them to one another. SUBCLAIMS 1. Verfahren zur Herstellung von Gebäuden mittels vorfabrizierten Bauelementen nach Patentanspruch, da- durch gekennzeichnet, dass man sämtliche Installationen in die Bauelemente einbaut. 2. Process for the production of buildings by means of prefabricated structural elements according to patent claim, characterized in that all installations are built into the structural elements. 2. Verfahren zur Herstellung von Gebäuden mittels vorfabrizierten Bauelementen nach Patentanspruch, da durch gekennzeichnet, dass man die Bauelemente derart ausbildet, dass die Seitenteile Aussenwände des Gebäu des bilden, und dass man den vom Bauelement um schlossenen Raum durch Einfügen von Zwischenwänden unterteilt. 3. Verfahren zur Herstellung von Gebäuden mittels vorfabrizierten Bauelementen nach Patentanspruch und Unteranspruch 2, dadurch gekennzeichnet, dass man die Bauelemente an mindestens einer freien Aussenseite mit einer Zwischenwand versieht. Process for the production of buildings by means of prefabricated components according to claim, characterized in that the components are designed in such a way that the side parts form the outer walls of the building, and that the space enclosed by the component is divided by inserting partitions. 3. A method for the production of buildings by means of prefabricated structural elements according to claim and dependent claim 2, characterized in that the structural elements are provided with an intermediate wall on at least one free outer side. 4. Verfahren zur Herstellung von Gebäuden mittels vorfabrizierten Bauelementen nach Patentanspruch, da durch gekennzeichnet, dass man die Bauelemente, die bestimmt sind, Ecken des Gebäudes zu bilden, in der Vorfabrikation an :der freien Aussenseite mit einer Aus senwand versieht. 4. A method for the production of buildings by means of prefabricated components according to claim, characterized in that the components that are intended to form corners of the building in the prefabrication: the free outside with an out senwand provides.
CH291665A 1965-03-03 1965-03-03 Process for the manufacture of buildings CH431912A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH291665A CH431912A (en) 1965-03-03 1965-03-03 Process for the manufacture of buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH291665A CH431912A (en) 1965-03-03 1965-03-03 Process for the manufacture of buildings

Publications (1)

Publication Number Publication Date
CH431912A true CH431912A (en) 1967-03-15

Family

ID=4244499

Family Applications (1)

Application Number Title Priority Date Filing Date
CH291665A CH431912A (en) 1965-03-03 1965-03-03 Process for the manufacture of buildings

Country Status (1)

Country Link
CH (1) CH431912A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3952465A (en) * 1971-03-19 1976-04-27 Dominic Joseph Masiello Building structure formed of modular units with cantilevered portions for forming a corridor floor
US4050215A (en) 1972-04-13 1977-09-27 John Sergio Fisher Premanufactured modular housing building construction
US4115962A (en) * 1975-11-11 1978-09-26 Ronald Caisley Prefabricated building structure
US4759158A (en) * 1984-04-24 1988-07-26 Andre Aubry Set of prefabricated construction elements

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3952465A (en) * 1971-03-19 1976-04-27 Dominic Joseph Masiello Building structure formed of modular units with cantilevered portions for forming a corridor floor
US4050215A (en) 1972-04-13 1977-09-27 John Sergio Fisher Premanufactured modular housing building construction
US4115962A (en) * 1975-11-11 1978-09-26 Ronald Caisley Prefabricated building structure
US4759158A (en) * 1984-04-24 1988-07-26 Andre Aubry Set of prefabricated construction elements

Similar Documents

Publication Publication Date Title
DE1434760A1 (en) Space box for buildings
DE3003446A1 (en) Prefabricated concrete load bearing wall or ceiling construction - involves casting concrete in row of hollow boxes with linked cavities
DE69913288T2 (en) Prefabricated living space for a ship and installation method for such living space in a ship
DE2425335B2 (en) Prefabricated, transportable room element
DE2231943A1 (en) MODULAR UNIT AND PROCESS FOR MANUFACTURING A BUILDING ACCORDING TO A MODULAR SYSTEM
CH431912A (en) Process for the manufacture of buildings
CH662849A5 (en) METHOD FOR PRODUCING A BUILDING AND A BUILDING PRODUCED BY THIS METHOD.
DE19820438C1 (en) Frame body system for prefabricated buildings
AT402417B (en) THERMALLY INSULATED BUILDING
DE2810317A1 (en) PROCESS FOR CREATING BUILDINGS FOR RESIDENTIAL, SOCIAL OR COMMERCIAL PURPOSES AND BUILDING ACHIEVED WITH THIS PROCESS
DE2322920C3 (en) Prefabricated component for the manufacture of buildings
DE1459901C3 (en) Building that has a front with loggias
DE2065437A1 (en) RESIDENTIAL BUILDING WITH SEVERAL SINGLE BUILDINGS CONSISTING OF PRE-FABRICATED ROOMS
CH659280A5 (en) PREFABRICATED COMPONENT.
DE1684822A1 (en) Residential building and process for its manufacture
DE2900172A1 (en) Prefabricated unit assembled building - has roof supported on four corner load bearing room modules
DE2318121A1 (en) APARTMENT CONSTRUCTED FROM PREFABRICATED ELEMENTS OR THE LIKE
DE819968C (en) Building game for assembling building models etc.
DE2013044A1 (en) building
DE3039626A1 (en) METHOD FOR BUILDING PREFabricated Building and Prefabricated Building
AT142442B (en) Procedure for laying pipes in new buildings.
DE903505C (en) Panel-shaped component
DE2618228A1 (en) Variable plan multiple purpose prefabricated building elements - comprise external wall elements, internal columns and concrete ceiling and floor slabs covering defined spaces
DE817808C (en) Panel construction for barracks and similar buildings
EP4177412A1 (en) Multi-storey multiparty building