WO2017111070A1 - 定期調査スケジュールの自動割り振り方法およびシステム - Google Patents
定期調査スケジュールの自動割り振り方法およびシステム Download PDFInfo
- Publication number
- WO2017111070A1 WO2017111070A1 PCT/JP2016/088466 JP2016088466W WO2017111070A1 WO 2017111070 A1 WO2017111070 A1 WO 2017111070A1 JP 2016088466 W JP2016088466 W JP 2016088466W WO 2017111070 A1 WO2017111070 A1 WO 2017111070A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- survey
- data
- customer
- date
- investigator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Definitions
- the difference between the concentrated gas supply and the simple gas supply is the scale of the supplier (customer).
- the case where the number of customers is less than 70 is distinguished from the concentrated gas supply, and the case where the number is 70 or more is distinguished from the simple gas supply.
- the part from the gas cylinder or gas bulk to the outlet of the gas meter is called supply equipment.
- the name of the supply facility is originally used in the case of LP gas.
- the gas facility in the city gas may be referred to as a supply facility.
- the gas holder, the gas cylinder, and the gas bulk may be collectively referred to as a “gas container”.
- FIG. 1 is a diagram showing a system configuration according to an embodiment of the present invention.
- an automatic allocation server 100 installed in a data center or the like has a plurality of mobile terminals 102a, 102b,..., 102n (hereinafter referred to as “mobile terminals 102”) and a plurality of mobile terminals 102a, 102b,. , 103n (hereinafter, referred to as “administrator terminal 103”) is configured to communicate with the administrator terminals 103a, 103b,.
- the automatic allocation server 100 allocates survey target customers to the investigators in charge for each security survey area, and creates survey schedule data.
- the automatic allocation server 100 creates postcard data (such as a PDF file) for notifying consumers based on the survey schedule data.
- the automatic allocation server 100 transmits the created postcard data to a printing company server (not shown). This requests the printing company to print and ship the postcard.
- the automatic allocation server 100 receives postcard data created from the printing company server. Thereafter, the automatic allocation server 100 prints a postcard based on the postcard data, and the printed postcard is sent to each customer.
- the automatic allocation server 100 receives an adjustment request for the scheduled survey date from the mobile terminal 102 or the administrator terminal 103.
- the automatic allocation server 100 determines whether or not the adjustment can be performed according to the received request. If the adjustment as requested is possible, the automatic allocation server 100 updates the survey schedule data.
- the automatic allocation server 100 includes a CPU (processor) 110, a RAM (memory) 111, an input device 112, an output device 113, a communication control device 114, and a nonvolatile storage medium (ROM, HDD, etc.) via a system bus 115.
- a storage device 116 to be configured is connected.
- the storage device 116 includes a program storage area for storing software programs related to the automatic allocation process, and a data storage area for storing related data and the like. Each means in the program storage area described below is actually an independent software program, its routine, component, and the like. These are called from the storage device 116 by the CPU 110, expanded in the work area of the RAM 111, and sequentially executed, thereby performing each function.
- the survey schedule data creation means 123 creates survey schedule data based on the automatic allocation result and stores it in the survey schedule data storage unit 136. Further, the survey schedule data creating means 123 updates the survey schedule data based on the reallocation result.
- the postal code mapping data storage unit 133 stores data for mapping the security investigation area and the postal code.
- FIG. 6 is a diagram illustrating data stored in the postal code mapping data storage unit 133 according to an embodiment of the present invention.
- the zip code mapping data in FIG. 6 includes a “zip code” indicating the customer's zip code and a “survey area code” mapped to the zip code.
- one survey area includes a plurality of postal code areas.
- the customer data extraction unit 120 extracts customer data (FIG. 4) relating to a customer to be surveyed that matches a predetermined condition from the customer data storage unit 131.
- the predetermined condition is a customer in a specific area, within the upper limit of maturity, and being opened (that is, a customer who needs a survey and has a high survey priority).
- the term “within maturity upper limit” means that the “survey maturity date” or “re-survey maturity date” in the customer data (FIG. 4) is within a predetermined period (for example, within three months from the following month).
- a customer who is being opened is a customer whose “opening type” in the customer data (FIG.
- the investigator assigns the customer type of the customer to be allocated (0: liquid stone method, 1: gas law method, 2 : If you do not have qualifications regarding the High Pressure Gas Safety Act), exclude it from the allocation (in this case, the next highest priority “Practice Jiro” will be judged).
- step 304 if there is no investigator with the next highest priority in step 304, the process proceeds to No route, and the process of FIG. Strictly speaking, in order to perform the allocation process for the next scheduled survey date, the process from step 301 to FIG. 3 is repeated again. At this time, in order to maintain the fairness of the investigator, the priority of the investigator (“priority” in the investigator data in FIG. 7) can be changed for each scheduled work day.
- the process of FIG. 3 is repeatedly executed and the allocation for the scheduled survey date (for example, one month for the next month) is completed, the process returns to FIG. 2 and step 204 is executed.
- Step 204 is executed after the assignment of the consumers to be surveyed is completed in Step 203 (FIG. 3).
- the survey schedule data creating means 123 creates survey schedule data (FIG. 9) based on the allocation result and stores it in the survey schedule data storage unit 136. Specifically, data is created by assigning the scheduled date of survey based on the allocation result, the investigator in charge, etc. to the customer to be surveyed.
- the automatic allocation server 100 searches the survey date notification data ( Or postcard data) transmission timing can be adjusted.
- the automatic allocation server 100 can have the printing company's holiday data in advance, and can adjust the transmission timing so that the postcard reaches the customer at least one week before the scheduled survey date. After step 206, the process ends.
- the automatic allocation server 100 Upon receiving the plugging notification, the automatic allocation server 100 searches the customer data (FIG. 4) using the customer code of the customer to be plugged as a search key, and sets the “opening type” of the target customer to “capped state”. (“1” is set) (step 1102).
- the automatic allocation server 100 searches whether there is survey plan data of the target customer (step 1103). Similarly to step 1102, the survey schedule data (FIG. 9) is searched using the customer code of the customer to be plugged as a search key. If there is no survey plan data for the target customer, the process proceeds to No route in step 1103 and the process ends. Note that the processing order of step 1102 and steps 1103 and 1104 may be reversed, but it is desirable to perform processing in the same transaction.
- the automatic allocation server 100 Upon receiving the opening notification, the automatic allocation server 100 searches the customer data (FIG. 4) using the customer code of the customer to be opened as a search key, and sets the “opening type” of the target customer to “open”.
- the plug state is set (“0” is set) (step 1202).
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- General Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Public Health (AREA)
- Primary Health Care (AREA)
- General Health & Medical Sciences (AREA)
- Water Supply & Treatment (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
前記需要家に係る、調査対象設備の法定調査期限を示す調査満期日、前記調査対象設備の再調査が必要な場合の法定調査期限を示す再調査満期日、および郵便番号を少なくとも含む、前記メモリに格納された需要家データから、前記調査満期日または前記再調査満期日が所定期間内であり、かつ特定エリアの需要家データを抽出する手段であって、前記特定エリアは、複数の前記郵便番号が示す複数のエリアを含む、手段と、
割り振りの優先順位を少なくとも含む、前記メモリに格納された調査員データから、前記特定エリアの調査員データを抽出する手段と、
前記抽出した需要家データを、少なくとも前記郵便番号順にソートする手段と、
前記ソートした需要家データを、前記優先順位の高い調査員から順に割り振る手段と
を備えたことを特徴とする。
前記ソートした需要家データの割り振り結果に基づいて、前記需要家、調査予定日、および担当調査員を少なくとも含む調査予定データを作成する手段と、
前記調査予定データに基づいて、前記需要家の住所および氏名、調査予定日、調査時間帯、ならびに調査を担当する会社の名称および連絡先を少なくとも含む調査予定通知データを作成する手段と、
前記需要家への葉書の発送を印刷会社に依頼する場合は、前記印刷会社のコンピュータに前記調査予定通知データ、または前記調査予定通知データに基づいて作成した葉書印刷用データを送信する手段と、
前記需要家への葉書の発送を印刷会社に依頼しない場合は、前記調査予定通知データに基づいて、前記葉書を印刷する手段と
をさらに備えたことを特徴とする。
前記ソートすることは、前記調査満期日または前記再調査満期日が翌月以前のデータを最優先にソートすることを含む
ことを特徴とする。
前記需要家が閉栓状態となる旨を示す閉栓通知を受信する手段と、
前記閉栓通知を受信したことに応答して、前記作成した調査予定データに閉栓状態となる需要家のデータが含まれるか否かを判定する手段と、
前記作成した調査予定データに閉栓状態となる需要家のデータが含まれる場合、そのデータを削除状態とする手段と
をさらに備えたことを特徴とする。
前記需要家が開栓状態となる旨を示す開栓通知を受信する手段と、
前記開栓通知を受信したことに応答して、前記調査予定データのうち開栓状態となる需要家のデータの削除状態をリセットする手段と
をさらに備えたことを特徴とする。
前記需要家に係る、調査対象設備の法定調査期限を示す調査満期日、前記調査対象設備の再調査が必要な場合の法定調査期限を示す再調査満期日、および郵便番号を少なくとも含む、前記メモリに格納された需要家データから、前記調査満期日または前記再調査満期日が所定期間内であり、かつ特定エリアの需要家データを、前記プロセッサが抽出するステップであって、前記特定エリアは、複数の前記郵便番号が示す複数のエリアを含む、ステップと、
割り振りの優先順位を少なくとも含む、前記メモリに格納された調査員データから、前記特定エリアの調査員データを、前記プロセッサが抽出するステップと、
前記抽出した需要家データを、少なくとも前記郵便番号順に、前記プロセッサがソートするステップと、
前記ソートした需要家データを、前記優先順位の高い調査員から順に、前記プロセッサが割り振るステップと
を備えたことを特徴とする。
前記需要家に係る、調査対象設備の法定調査期限を示す調査満期日、前記調査対象設備の再調査が必要な場合の法定調査期限を示す再調査満期日、および郵便番号を少なくとも含む、前記メモリに格納された需要家データから、前記調査満期日または前記再調査満期日が所定期間内であり、かつ特定エリアの需要家データを抽出するステップであって、前記特定エリアは、複数の前記郵便番号が示す複数のエリアを含む、ステップと、
割り振りの優先順位を少なくとも含む、前記メモリに格納された調査員データから、前記特定エリアの調査員データを抽出するステップと、
前記抽出した需要家データを、少なくとも前記郵便番号順にソートするステップと、
前記ソートした需要家データを、前記優先順位の高い調査員から順に割り振るステップと
を備えたことを特徴とする。
Claims (8)
- 保安調査作業における需要家を調査員に割り振るコンピュータであって、前記コンピュータはプロセッサおよびメモリを備え、前記プロセッサは、
前記需要家に係る、調査対象設備の法定調査期限を示す調査満期日、前記調査対象設備の再調査が必要な場合の法定調査期限を示す再調査満期日、および郵便番号を少なくとも含む、前記メモリに格納された需要家データから、前記調査満期日または前記再調査満期日が所定期間内であり、かつ特定エリアの需要家データを抽出する手段であって、前記特定エリアは、複数の前記郵便番号が示す複数のエリアを含む、手段と、
割り振りの優先順位を少なくとも含む、前記メモリに格納された調査員データから、前記特定エリアの調査員データを抽出する手段と、
前記抽出した需要家データを、少なくとも前記郵便番号順にソートする手段と、
前記ソートした需要家データを、前記優先順位の高い調査員から順に割り振る手段と
を備えたことを特徴とするコンピュータ。 - 前記プロセッサは、
前記ソートした需要家データの割り振り結果に基づいて、前記需要家、調査予定日、および担当調査員を少なくとも含む調査予定データを作成する手段と、
前記調査予定データに基づいて、前記需要家の住所および氏名、調査予定日、調査時間帯、ならびに調査を担当する会社の名称および連絡先を少なくとも含む調査予定通知データを作成する手段と、
前記需要家への葉書の発送を印刷会社に依頼する場合は、前記印刷会社のコンピュータに前記調査予定通知データ、または前記調査予定通知データに基づいて作成した葉書印刷用データを送信する手段と、
前記需要家への葉書の発送を印刷会社に依頼しない場合は、前記調査予定通知データに基づいて、前記葉書を印刷する手段と
をさらに備えたことを特徴とする請求項1に記載のコンピュータ。 - 前記調査予定データは、翌月以降の調査予定日に係るデータであり、
前記ソートすることは、前記調査満期日または前記再調査満期日が翌月以前のデータを最優先にソートすることを含む
ことを特徴とする請求項2に記載のコンピュータ。 - 前記需要家データは、さらにガスの開栓および閉栓状態を示す開栓種別を含み、前記需要家データの抽出は、さらに前記開栓種別が開栓状態を示すデータのみ抽出され、前記プロセッサは、
前記需要家が閉栓状態となる旨を示す閉栓通知を受信する手段と、
前記閉栓通知を受信したことに応答して、前記作成した調査予定データに閉栓状態となる需要家のデータが含まれるか否かを判定する手段と、
前記作成した調査予定データに閉栓状態となる需要家のデータが含まれる場合、そのデータを削除状態とする手段と
をさらに備えたことを特徴とする請求項2または3に記載のコンピュータ。 - 前記割り振ることは、予め設定された、作業時間帯、調査の所要時間、割り振りの余裕率、ならびに前記調査員の休日および有資格のうちの少なくとも1つに基づいて、前記ソートした需要家データを、前記優先順位の高い調査員から順に割り振ることを含むことを特徴とする請求項1ないし4のいずれかに記載のコンピュータ。
- 前記プロセッサは、
前記需要家が開栓状態となる旨を示す開栓通知を受信する手段と、
前記開栓通知を受信したことに応答して、前記調査予定データのうち開栓状態となる需要家のデータの削除状態をリセットする手段と
をさらに備えたことを特徴とする請求項4に記載のコンピュータ。 - 保安調査作業における需要家を調査員に割り振るコンピュータによって実行される方法であって、前記コンピュータはプロセッサおよびメモリを備え、前記方法は、
前記需要家に係る、調査対象設備の法定調査期限を示す調査満期日、前記調査対象設備の再調査が必要な場合の法定調査期限を示す再調査満期日、および郵便番号を少なくとも含む、前記メモリに格納された需要家データから、前記調査満期日または前記再調査満期日が所定期間内であり、かつ特定エリアの需要家データを、前記プロセッサが抽出するステップであって、前記特定エリアは、複数の前記郵便番号が示す複数のエリアを含む、ステップと、
割り振りの優先順位を少なくとも含む、前記メモリに格納された調査員データから、前記特定エリアの調査員データを、前記プロセッサが抽出するステップと、
前記抽出した需要家データを、少なくとも前記郵便番号順に、前記プロセッサがソートするステップと、
前記ソートした需要家データを、前記優先順位の高い調査員から順に、前記プロセッサが割り振るステップと
を備えたことを特徴とする方法。 - 保安調査作業における需要家を調査員に割り振る方法をコンピュータに実行させるコンピュータ実行可能命令を記憶したコンピュータ可読記憶媒体であって、前記コンピュータはプロセッサおよびメモリを備え、前記方法は、
前記需要家に係る、調査対象設備の法定調査期限を示す調査満期日、前記調査対象設備の再調査が必要な場合の法定調査期限を示す再調査満期日、および郵便番号を少なくとも含む、前記メモリに格納された需要家データから、前記調査満期日または前記再調査満期日が所定期間内であり、かつ特定エリアの需要家データを前記プロセッサが抽出するステップであって、前記特定エリアは、複数の前記郵便番号が示す複数のエリアを含む、ステップと、
割り振りの優先順位を少なくとも含む、前記メモリに格納された調査員データから、前記特定エリアの調査員データを前記プロセッサが抽出するステップと、
前記抽出した需要家データを、少なくとも前記郵便番号順に前記プロセッサがソートするステップと、
前記ソートした需要家データを、前記優先順位の高い調査員から順に前記プロセッサが割り振るステップと
を備えたことを特徴とするコンピュータ可読記憶媒体。
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| AU2016379286A AU2016379286A1 (en) | 2015-12-25 | 2016-12-22 | Automatic assigning method and system of periodic inspection schedule |
| US15/744,001 US20180286001A1 (en) | 2015-12-25 | 2016-12-22 | Automatic assigning method and system of periodic inspection schedule |
| CA2992415A CA2992415A1 (en) | 2015-12-25 | 2016-12-22 | Automatic assigning method and system of periodic inspection schedule |
Applications Claiming Priority (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2015-253940 | 2015-12-25 | ||
| JP2015253940 | 2015-12-25 | ||
| JP2016218940A JP6243994B2 (ja) | 2015-12-25 | 2016-11-09 | 保安調査作業における需要家を調査員に割り振るコンピュータ、方法およびコンピュータプログラム |
| JP2016-218940 | 2016-11-09 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2017111070A1 true WO2017111070A1 (ja) | 2017-06-29 |
Family
ID=59090530
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP2016/088466 Ceased WO2017111070A1 (ja) | 2015-12-25 | 2016-12-22 | 定期調査スケジュールの自動割り振り方法およびシステム |
Country Status (1)
| Country | Link |
|---|---|
| WO (1) | WO2017111070A1 (ja) |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006318311A (ja) * | 2005-05-13 | 2006-11-24 | Sap Ag | 担当割当装置及び方法ならびにコンピュータプログラム |
| JP2012238205A (ja) * | 2011-05-12 | 2012-12-06 | Nippon Gas Co Ltd | 携帯保安システム |
| JP2014021631A (ja) * | 2012-07-13 | 2014-02-03 | Nippon Gas Co Ltd | 保安員の定期調査スケジューリング方法およびシステム |
-
2016
- 2016-12-22 WO PCT/JP2016/088466 patent/WO2017111070A1/ja not_active Ceased
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006318311A (ja) * | 2005-05-13 | 2006-11-24 | Sap Ag | 担当割当装置及び方法ならびにコンピュータプログラム |
| JP2012238205A (ja) * | 2011-05-12 | 2012-12-06 | Nippon Gas Co Ltd | 携帯保安システム |
| JP2014021631A (ja) * | 2012-07-13 | 2014-02-03 | Nippon Gas Co Ltd | 保安員の定期調査スケジューリング方法およびシステム |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5181041B2 (ja) | 携帯保安システム | |
| US9990600B2 (en) | Delivery prediction system and method accelerated by α days | |
| JP5457502B2 (ja) | 配送エリア管理方法 | |
| JP6243994B2 (ja) | 保安調査作業における需要家を調査員に割り振るコンピュータ、方法およびコンピュータプログラム | |
| CA2877070C (en) | Periodic survey scheduling method and system for safety inspector | |
| JP5814956B2 (ja) | ガス管理システム | |
| US20180357593A9 (en) | Method for leveling delivery counts | |
| JP5331157B2 (ja) | 携帯配送システム | |
| CA2877069C (en) | Download for safety inspection item | |
| WO2015113109A1 (en) | Method and system for managing geospatial deployment | |
| JP5782467B2 (ja) | 二次元コード読み込みによるlpガス業務の作業詳細データ配信システムおよび方法 | |
| KR101664830B1 (ko) | 규정 관리 시스템 및 방법 | |
| JP5469753B2 (ja) | 携帯保安システムを構成するサーバコンピュータ | |
| WO2017111070A1 (ja) | 定期調査スケジュールの自動割り振り方法およびシステム | |
| JP6757437B1 (ja) | 配送員がメーター交換作業を行うことによる年間作業の平準化方法 | |
| JP2020166595A (ja) | 保安不適合時の対応方法 | |
| AU2013284832B2 (en) | Customer management system and customer management method | |
| JP2020166594A (ja) | 配送員が保安業務を行うことによる年間作業の平準化方法 | |
| Yun et al. | Preliminary Study of the Systematic Management of Project Claim | |
| JP2010055536A (ja) | 被災補償管理システム、被災補償管理プログラム、及び被災補償管理方法 | |
| McVey | Hot sample archiving. Revision 3 | |
| AU2017245317A1 (en) | Method for leveling delivery counts |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 16878956 Country of ref document: EP Kind code of ref document: A1 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 15744001 Country of ref document: US |
|
| ENP | Entry into the national phase |
Ref document number: 2992415 Country of ref document: CA |
|
| ENP | Entry into the national phase |
Ref document number: 2016379286 Country of ref document: AU Date of ref document: 20161222 Kind code of ref document: A |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 16878956 Country of ref document: EP Kind code of ref document: A1 |