WO2015151734A1 - 鉱山の管理システム - Google Patents
鉱山の管理システム Download PDFInfo
- Publication number
- WO2015151734A1 WO2015151734A1 PCT/JP2015/056872 JP2015056872W WO2015151734A1 WO 2015151734 A1 WO2015151734 A1 WO 2015151734A1 JP 2015056872 W JP2015056872 W JP 2015056872W WO 2015151734 A1 WO2015151734 A1 WO 2015151734A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- ore
- machine
- loading
- mine
- transporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/02—Agriculture; Fishing; Forestry; Mining
Definitions
- the present invention relates to a mine management system used for underground mining.
- Patent Document 1 describes a working machine that moves a tunnel while holding a drilled ore in a bucket after a vehicle that excavates ore with a bucket enters the tunnel and excavates the ore.
- the durability of the transporting machine may be reduced. The same applies to underground mining.
- This invention aims at suppressing the fall of the durability of the conveyance machine which conveys an ore in underground mining.
- the present invention provides a mining place installed inside or below the ore body, a soil removal place installed inside or below the ore body, and a plurality of first tunnels installed inside or below the ore body.
- a second mine shaft connecting the mining site and the first mine shaft, and a third mine shaft connected to the plurality of first mine shafts, and a peripheral circuit is formed by the third mine shaft and the first mine shaft.
- the machine and the loading machine that excavates the ore at the mining site and loads the excavated ore into the transporting machine and the loading machine is determined to move to a different mining site, the machine operates in the peripheral circuit.
- the sum of the first distances that move from the loaded position to the earthing location and the sum of the second distances that move from the earthing location to the position where the ore is loaded are obtained, and the sum of the first distances and the A management system for a mine, including a management device that reverses the traveling direction of the transporting machine when the difference from the total sum of the second distances is equal to or greater than a predetermined value.
- the management device transmits a command to reverse the traveling direction to the plurality of transport machines after the loading machine arrives at the different mining site.
- the plurality of transport machines execute a process determined according to the current state after receiving the instruction to reverse the travel direction, and after all the transport machines execute the process, It is preferable to reverse the direction and start running.
- the plurality of transport machines start traveling by reversing each traveling direction after receiving a command to reverse the traveling direction.
- the mine is provided with a plurality of the earthing sites.
- the plurality of first mine shafts extend in one direction and are arranged side by side, and the loading machine is one for each of the first mine shafts, and a plurality of the first mine shafts, It is preferable that the second mine shaft and the third mine shaft are installed so as to be point-symmetric with respect to a central portion when viewed from above.
- One of the loading machines installed so as to be point-symmetric moves from a mining place on one end side of the first tunnel toward a mining place on the other end side, and the other product It is preferable that the embedded machine moves from the mining site on the other end side of the first mine tunnel toward the mining site on the one end side.
- a pair of the soil removal places are provided on both end sides of the plurality of first tunnels, and the loading machines are disposed on the first tunnels on both sides with respect to a straight line connecting the pair of soil removal places.
- the moving directions of the loading machines are opposite on one side and the other side based on the straight line.
- the present invention includes a mining place installed inside or below the ore body, a plurality of earthing places installed inside or below the ore body, and a plurality of first places installed inside or below the ore body.
- a first mine shaft, a second mine shaft that connects the mining site and the first mine shaft, and a third mine shaft that is connected to the plurality of first mine shafts, and a circumferential circuit between the third mine shaft and the first mine shaft When ore is mined from the ore body in a mine where the ore is formed, it travels in one direction on the peripheral circuit, and the ore mined at the mining site is loaded and transported to the earthing site before being discharged.
- the total sum of the first distances that move from the position where the ore was loaded to the earthing location and the position where the ore is loaded from the earthing location for all the transporting machines operating in the peripheral circuit The sum of the second distances to be moved to and if the difference between the sum of the first distances and the sum of the second distances is equal to or greater than a predetermined value, the loading machine
- a management device that transmits a command for reversing the traveling direction to the plurality of transporting machines after the time of arrival at the place, and the plurality of transporting machines received the command for reversing the traveling direction. Thereafter, the mine management system starts traveling by reversing each traveling direction.
- the present invention can suppress a decrease in durability of a transporting machine that transports ore during underground mining.
- FIG. 1 is a mimetic diagram showing an example of the field where the conveyance machine and loading machine concerning this embodiment operate.
- FIG. 2 is a schematic diagram showing an example of a mine and a mining system.
- FIG. 3 is an enlarged view of a part of FIG.
- FIG. 4 is a diagram showing excavation of ore from the natural ground by the loading machine and loading of the ore into the transporting machine.
- FIG. 5 is a diagram illustrating excavation of ore from the natural ground by the loading machine and loading of the ore into the transporting machine.
- FIG. 6 is an example of a functional block diagram of a management device provided in the mine management system.
- FIG. 7 is a perspective view of the transport machine according to the present embodiment.
- FIG. 8 is a side view of the transport machine according to the present embodiment.
- FIG. 9 is a diagram illustrating a support structure of a vessel provided in the transport machine according to the present embodiment.
- FIG. 10 is a top view of the transport machine according to the present embodiment.
- FIG. 11 is a diagram illustrating a state where the transport machine according to the present embodiment tilts the vessel.
- FIG. 12 is an example of a block diagram illustrating a control device included in the transport machine.
- FIG. 13 is a side view of the loading machine according to the present embodiment.
- FIG. 14 is a top view of the loading machine according to the present embodiment.
- FIG. 15 is a front view of the loading machine according to the present embodiment.
- FIG. 16 is a diagram illustrating a posture when the loading machine according to the present embodiment travels.
- FIG. 17 is an example of a block diagram illustrating a control device included in the loading machine according to the present embodiment.
- FIG. 18 is a diagram illustrating an example of the capacitor handling device EX included in the mining system according to the present embodiment.
- FIG. 19 is a diagram illustrating a direction in which the transport machine advances drift in the mine in the mining system according to the present embodiment.
- FIG. 20 is a diagram for explaining a process of reversing the traveling direction of the transport machine in the mine management system according to the present embodiment.
- FIG. 21 is a conceptual diagram showing a peripheral circuit.
- FIG. 22 is a flowchart illustrating a process of reversing the traveling direction of the transport machine in the mine management system according to the present embodiment.
- the mine productivity can be based on the quotient of both as shown in the equation (1).
- $ / t is an index representing productivity
- t is a mining amount
- h time
- $ is cost.
- FIG. 1 is a schematic diagram illustrating an example of a site where the transport machine 10 and the loading machine 30 according to the present embodiment operate.
- the transporting machine 10 and the loading machine 30 are used for underground mining for mining ore from underground.
- the transport machine 10 is a type of work machine that transports a load in the mine shaft R
- the load machine 30 is a type of work machine that loads a load on the transport machine 10.
- ore is mined by the block caving method.
- the block caving method is the installation of an ore MR mining place (hereinafter referred to as a draw point) DP on the ore body (or vein) MG of the mine M and a mine channel R for transporting the mined ore. It is a method of mining the ore MR from the draw point DP by undercutting the upper part of the point DP and blasting to naturally collapse the ore MR.
- the draw point DP is installed inside the ore body MG or below the ore body MG.
- the block caving method is a method that uses the property that a fragile rock starts to naturally collapse when the lower part of the bedrock or ore body is undercut.
- the ore MR When the ore MR is mined from inside or below D of the ore body MG, the collapse propagates to the upper part. For this reason, when the block caving method is used, the ore MR of the ore body MG can be mined efficiently.
- a plurality of draw points DP are usually provided.
- the management device 3 is arranged on the ground.
- the management device 3 is installed in a management facility on the ground. In principle, the management device 3 does not consider movement.
- the management device 3 manages the mining site.
- the management device 3 can communicate with work machines in the mine including the transporting machine 10 and the loading machine 30 via a communication system including the wireless communication device 4 and the antenna 4A.
- the transporting machine 10 and the loading machine 30 are unmanned work machines, but may be manned work machines that are operated by an operator's operation.
- FIG. 2 is a schematic diagram illustrating an example of a mine MI and a mine management system.
- FIG. 3 is an enlarged view of a part of FIG.
- the mine shaft R installed below the ore body MG includes a first mine shaft DR and a second mine shaft CR.
- the mine shaft R is installed, for example, inside the ore body MG or below the ore body MG.
- the second tunnel CR connects each draw point DP and the first tunnel DR.
- the loading machine 30 can approach the draw point DP through the second mine tunnel CR.
- the mine shaft R includes a third mine shaft TR.
- a plurality (two in this example) of third tunnels TR are connected to a plurality of first tunnels DR.
- the first mine tunnel DR is appropriately referred to as a drift DR
- the second mine tunnel CR is appropriately referred to as a cross-cut CR
- the third mine tunnel TR is appropriately referred to as an outer circumferential path TR.
- each outer peripheral path TR is not divided by the draw point DP like the cross cut CR.
- One outer peripheral path TR connects one end of each of the plurality of drifts DR, and the other outer peripheral path TR connects the other end of each of the plurality of drifts DR.
- all the drifts DR are connected to the two outer peripheral paths TR.
- the transport machine 10 and the loading machine 30 can enter from one outer circumferential path TR regardless of which drift DR. In the example illustrated in FIG. 3, the transport machine 10 and the loading machine 30 travel in the direction of the arrow FC in the drift DR.
- the loading position LP where the loading operation by the loading machine 30 to the transporting machine 10 is performed is determined at the crosscut CR or in the vicinity thereof.
- An area including the draw point DP and the loading position LP may be referred to as a loading place LA.
- the underground mine MI is provided with a soil removal place (or pass) OP from which ore MR as a load transported by the transporting machine 10 is discharged.
- a soil removal place (or pass) OP from which ore MR as a load transported by the transporting machine 10 is discharged.
- the transporting machine 10 shown in FIGS. 2 and 3 includes an electric motor for traveling and a capacitor that supplies electric power to the electric motor.
- a space SP is connected to the outer circumferential path TR.
- a storage battery handling device EX for replacing a storage battery mounted on the transporting machine 10 is installed.
- the road surface of the mine shaft R on which the transporting machine 10 travels and the XY plane are substantially parallel.
- the road surface of the mine shaft R is often uneven or has an uphill and a downhill.
- the mine management system 1 shown in FIG. 2 includes a management device 3 and a radio communication antenna 4A.
- the management device 3 manages the operation of the transporting machine 10 and the loading machine 30 that operate in the underground mine MI, for example.
- the management of operation includes allocation of the transporting machine 10 and the loading machine 30, collection of information on the operating states of the transporting machine 10 and the loading machine 30 (hereinafter, referred to as operation information as appropriate), management thereof, and the like.
- the operation information includes, for example, the operation time of the transporting machine 10 and the loading machine 30, the traveling distance, the traveling speed, the remaining amount of the battery, the presence / absence of abnormality, the location of the abnormality, the loading amount, and the like.
- the operation information is mainly used for operation evaluation, preventive maintenance, abnormality diagnosis, and the like of the transporting machine 10 and the loading machine 30. Therefore, the operation information is useful to meet the needs for improving the productivity of the mine M or improving the operation of the mine M.
- the management device 3 includes a communication device as will be described later.
- the wireless communication device 4 provided with the antenna 4A is connected to this communication device.
- the management device 3 exchanges information with the transport machine 10 and the loading machine 30 operating in the underground mine MI, for example, via the communication device, the wireless communication device 4 and the antenna 4A.
- the management device 3 provided in the mine management system 1 manages the operation of the transporting machine 10 and the loading machine 30 as described above.
- the loading machine 30 travels with a traveling motor, and drives the stirrer with the motor to excavate the ore MR.
- a feeding cable 5 that supplies electric power to these electric motors from the outside of the loading machine 30 is provided in the mine channel R of the mine MI.
- the loading machine 30 is supplied with power from the power feeding cable 5 via, for example, a power feeding connector 6 as a power supply device provided in the loading place LA and a power cable 7 from the loading machine 30.
- the electric power supply apparatus mentioned above should just be provided in any one of drift DR or crosscut CR.
- the loading machine 30 may perform at least one of traveling and excavation with electric power supplied from the outside.
- the loading machine 30 may be equipped with a capacitor, and may receive at least one of traveling and excavation by receiving power supply from the capacitor. Further, the loading machine 30 may be equipped with a capacitor, and may receive at least one of traveling and excavation by receiving power supply from the capacitor. That is, the loading machine 30 performs at least one of traveling and excavation with at least one of electric power supplied from the outside and electric power supplied from the battery. For example, the loading machine 30 can perform excavation with electric power supplied from the outside and can travel with electric power supplied from the storage battery. Further, when traveling in the crosscut CR, the loading machine 30 may travel with electric power supplied from the outside.
- the loading machine 30 may excavate the ore MR by driving a hydraulic pump with an electric motor to generate hydraulic pressure and driving the hydraulic motor with this hydraulic pressure.
- the loading machine 30 may be provided with an electric storage device, run by electric power supplied from the electric storage device, and excavate.
- the connection between the power supply cable 5 and the power cable 7 from the loading machine 30 is not limited to the connector 6.
- an electrode provided on the tunnel R side and connected to the power supply cable 5 and an electrode connected to the power cable 7 from the loading machine 30 side are used as a power supply device, and both electrodes are brought into contact with each other.
- power may be supplied from the feeding cable 5 to the loading machine 30. If it does in this way, even if the positioning accuracy of both electrodes is low, both can be contacted and electric power can be supplied to loading machine 30.
- the loading machine 30 shall operate
- the loading machine 30 may be, for example, one that travels by an internal combustion engine or excavates the ore MR. In this case, the loading machine 30 drives a hydraulic pump by an internal combustion engine, and travels by driving a hydraulic motor, a hydraulic cylinder, or the like with hydraulic oil discharged from the hydraulic pump, or excavates the ore MR. Or you may.
- ⁇ Ore MR drilling and transportation> 4 and 5 are diagrams showing excavation of the ore MR of the natural ground RM by the loading machine 30 and loading of the ore MR into the transporting machine 10.
- a natural ground RM of the ore MR is formed at the draw point DP.
- the loading machine 30 is installed in the crosscut CR at the loading place LA, and the tip portion penetrates into the natural ground RM of the ore MR to excavate it.
- the loading machine 30 loads the excavated ore MR on the transporting machine 10 that is on the opposite side of the natural ground RM and is waiting in the drift DR.
- a power supply cable 5 for supplying power to the loading machine 30 is provided.
- the loading machine 30 includes a vehicle body 30 ⁇ / b> B, a feeder 31 as a conveying device, a rotating roller 33 as an excavating device, a support mechanism 32 that supports the rotating roller 33, and a traveling device. 34.
- the rotating roller 33 and the support mechanism 32 function as a scraping device that excavates the ore MR and sends it to the feeder 31.
- the support mechanism 32 includes a boom 32a as a first member attached to the vehicle body 30B, and an arm 32b as a second member that is connected to the boom 32a and swings and rotatably supports the rotating roller 33.
- the vehicle body 30 ⁇ / b> B of the loading machine 30 includes a penetrating member 35 that penetrates into the natural ground RM of the ore MR, a rotating body 36, and a rock guard 37.
- the penetration member 35 penetrates the natural ground RM when excavating the ore MR.
- the rotating body 36 rotates when the penetrating member 35 of the loading machine 30 penetrates the natural ground RM, and assists the penetrating.
- the transporting machine 10 includes a vehicle body 10 ⁇ / b> B and a vessel 11.
- the vessel 11 is mounted on the vehicle body 10B.
- the vessel 11 loads the ore MR as a load.
- the vessel 11 moves in the width direction W of the vehicle body 10B, that is, in a direction parallel to the axle, as shown in FIGS.
- the vessel 11 is installed at the center in the width direction of the vehicle body 10B when the transporting machine 10 travels. Further, the vessel 11 moves outward in the width direction of the vehicle body 10B when the ore MR is loaded.
- the transporting machine 10 can bring the vessel 11 closer to the lower part D of the feeder 31 of the loading machine 30, the possibility that the ore MR transported by the feeder 31 falls outside the vessel 11, The ore MR can be reliably dropped into the vessel 11.
- the loading machine 30 excavates the ore MR and transports the excavated ore MR to the transporting machine 10 and loads it on the transporting machine 10.
- the transporting machine 10 transports the loaded ore MR to the ore pass OP shown in FIG. 2 and discharges it here.
- the loading machine 30 stays in the crosscut CR while leaving the space in which the transporting machine 10 travels in the drift DR, and excavates the ore MR at the draw point DP. Then, the loading machine 30 conveys the excavated ore MR in a direction away from the draw point DP and loads it on the transporting machine 10.
- the loading machine 30 does not move in a state where the excavated ore MR is loaded.
- the transport machine 10 loads the ore MR mined at the draw point DP, travels on the drift DR, and transports it to the ore pass OP shown in FIG.
- the mine management system 1 causes the loading machine 30 to perform only excavation and loading of the ore MR and causes the transport machine 10 to transport only the ore MR.
- the functions of both are separated.
- the loading machine 30 can concentrate on excavation work and conveyance work, and the conveyance machine 10 can concentrate on conveyance work. That is, the loading machine 30 may not have the function of transporting the ore MR, and the transporting machine 10 may not have the function of excavating and transporting the ore MR.
- the loading machine 30 can specialize in the function of excavation and conveyance, and the conveyance machine 10 can be specialized in the function of conveyance of the ore MR, each function can be exhibited to the maximum. As a result, the mine management system 1 can improve the productivity of the mine M.
- FIG. 6 is an example of a functional block diagram of the management device 3 included in the mine management system 1.
- the management device 3 includes a processing device 3C, a storage device 3M, and an input / output unit (I / O) 3IO. Further, in the management device 3, a display device 8, an input device 9, and a communication device 3R as an output device are connected to the input / output unit 3IO.
- the management device 3 is a computer, for example.
- the processing device 3C is, for example, a CPU (Central Processing Unit).
- the storage device 3M is, for example, a RAM (Random Access Memory), a ROM (Read Only Memory), a flash memory, a hard disk drive, or the like, or a combination thereof.
- the input / output unit 3IO is used for input / output (interface) of information between the processing device 3C and the display device 8, the input device 9, and the communication device 3R connected to the outside of the processing device 3C.
- the processing device 3C executes processing of the management device 3 such as allocation of the transporting machine 10 and the loading machine 30 and collection of operation information thereof. Processing such as vehicle allocation and collection of operation information is realized by the processing device 3C reading the corresponding computer program from the storage device 3M and executing it.
- the storage device 3M stores various computer programs for causing the processing device 3C to execute various processes.
- the computer program stored in the storage device 3M collects, for example, a computer program for dispatching the transporting machine 10 and the loading machine 30, and operation information of the transporting machine 10 and the loading machine 30.
- the display device 8 is, for example, a liquid crystal display or the like, and displays information necessary for dispatching the transporting machine 10 and the loading machine 30 and collecting operation information.
- the input device 9 is, for example, a keyboard, a touch panel, a mouse, or the like, and inputs information necessary for dispatching the transporting machine 10 and the loading machine 30 and collecting their operation information.
- the communication device 3R is connected to the wireless communication device 4 including the antenna 4A. As described above, the wireless communication device 4 and the antenna 4A are installed in the underground mine MI. The communication device 3R and the wireless communication device 4 are connected by wire.
- the communication device 3R and the transport machine 10 and the loading machine 30 in the underground mine MI can communicate with each other by, for example, a wireless LAN (Local Aria Network). Next, the transporting machine 10 will be described in more detail.
- FIG. 7 is a perspective view of the transport machine 10 according to the present embodiment.
- FIG. 8 is a side view of the transport machine 10 according to the present embodiment.
- the transporting machine 10 includes a vehicle body 10B, a vessel 11, and wheels 12A and 12B. Further, the transporting machine 10 includes a power storage device 14 as a power storage device, an antenna 15, imaging devices 16A and 16B, and non-contact sensors 17A and 17B.
- the wheels 12A and 12B are attached to the front and rear of the vehicle body 10B, respectively. In the present embodiment, the wheels 12A and 12B are driven by electric motors 13A and 13B mounted in the vehicle body 10B shown in FIG. Thus, in the transporting machine 10, all the wheels 12A and 12B are driving wheels.
- the wheels 12A and 12B are respectively steered wheels.
- the wheels 12A and 12B are, for example, solid tires. By doing in this way, since wheel 12A, 12B becomes a small diameter, the height of the materials handling machine 10 is suppressed.
- the transporting machine 10 can travel in any of the direction from the wheel 12A to the wheel 12B and the direction from the wheel 12B to the wheel 12A.
- the wheels 12A and 12B are not limited to solid tires, and may be pneumatic tires, for example. Further, only one of the wheels 12A and 12B may be a drive wheel.
- both the wheel 12A and the wheel 12B can function as steering wheels
- the transport machine 10 advances so that the wheel 12A is the front wheel and the wheel 12B is the rear wheel
- only the wheel 12A (front wheel) is steered.
- the wheel 12B (rear wheel) may not be steered, only the wheel 12B (rear wheel) may be steered and the wheel 12A (front wheel) may not be steered, the wheel 12A (front wheel) and the wheel 12B (rear wheel) ) May be steered.
- the wheel 12A and the wheel 12B may be steered in the same phase direction, or the wheel 12A and the wheel 12B may be steered in the opposite phase direction.
- the vehicle By steering the wheels 12A and 12B in the same phase direction, for example, the vehicle can stably travel during high-speed turning.
- the turning radius can be reduced by steering the wheel 12A and the wheel 12B in the opposite phase direction.
- the transport machine 10 advances so that the wheel 12B is the front wheel and the wheel 12A is the rear wheel.
- the vessel 11 is mounted above the vehicle body 10B and supported by the vehicle body 10B.
- a battery 14 for supplying electric power to the electric motors 13A and 13B is mounted on the vehicle body 10B.
- the external shape of the battery 14 is a rectangular parallelepiped shape.
- One battery 14 is mounted before and after the vehicle body 10B. By doing in this way, since the balance of the mass of front and back becomes close
- the battery 14 is detachably mounted on the vehicle body 10B.
- the electric motors 13 ⁇ / b> A and 13 ⁇ / b> B and the electronic device included in the transport machine 10 are operated by the electric power supplied from the battery 14.
- the transport machine 10 is electrically driven, but the internal combustion engine may be a power source.
- An antenna 15, imaging devices 16A and 16B, and non-contact sensors 17A and 17B are attached to the vehicle body 10B.
- the antenna 15 wirelessly communicates with the management device 3 via the antenna 4A and the communication device 3R illustrated in FIG.
- the imaging devices 16A and 16B photograph the load loaded on the vessel 11, that is, the state (packing state) of the ore MR shown in FIGS. 3 and 4 in this embodiment.
- the imaging devices 16A and 16B may be, for example, cameras that capture visible light or infrared cameras that capture infrared light.
- the imaging devices 16A and 16B are attached to the tips of support columns 16AS and 16BS attached to the upper surface of the vehicle body 10B, respectively. With such a structure, each of the imaging devices 16 ⁇ / b> A and 16 ⁇ / b> B can image the entire vessel 11 from above, so that the state of the ore MR loaded on the vessel 11 can be reliably imaged.
- Non-contact sensors 17A and 17B are attached to the front and rear of the vehicle body 10B, respectively.
- the non-contact sensors 17A and 17B detect an object existing around the transport machine 10, particularly on the traveling direction side, in a non-contact manner.
- radar devices are used as the non-contact sensors 17A and 17B.
- the non-contact sensors 17A and 17B can emit a radio wave or an ultrasonic wave, receive a radio wave reflected by the object, and detect a relative distance and direction from the object.
- the non-contact sensors 17A and 17B are not limited to radar devices.
- the non-contact sensors 17A and 17B may include at least one of a laser scanner and a three-dimensional distance sensor, for example.
- the transporting machine 10 includes peripheral monitoring cameras 17CA and 17CB as imaging devices before and after the vehicle body 10B.
- the peripheral monitoring cameras 17CA and 17CB image the periphery of the vehicle body 10B, particularly the front, and detect the shape of an object existing around the vehicle body 10B.
- the vehicle body 10B has a recess 10BU between the front and rear.
- Recess 10BU is arranged between wheel 12A and wheel 12B.
- the vessel 11 is a member on which ore MR as a load is loaded by the loading machine 30. At least a part of the vessel 11 is disposed in the recess 10BU.
- a part of the vehicle body 10B disposed on one side of the center portion AX of the vehicle body 10B and a part of the vehicle body 10B disposed on the other side in the front-rear direction of the vehicle body 10B are symmetric (front-back symmetry). Further, in the front-rear direction of the vehicle body 10B, a part of the vessel 11 arranged on one side of the center part AX of the vehicle body 10B and a part of the vessel 11 arranged on the other side are symmetrical (front-rear object). Further, the vehicle body 10B and the vessel 11 are symmetric (laterally symmetric) with respect to the central axis in the front-rear direction of the vehicle body 10B in plan view.
- the vessel 11 includes a bottom surface 11B and four side surfaces 11SF, 11SR, 11SA, and 11SB connected to the bottom surface 11B.
- the side surfaces 11SA and 11SB stand up vertically from the bottom surface 11B.
- the side surfaces 11SF and 11SR are inclined toward the wheels 12A and 12B, respectively, with respect to the bottom surface 11B.
- a recess 11U is formed by the bottom surface 11B and the four side surfaces 11SF, 11SR, 11SA, and 11SB. Ore MR as a load is loaded in the recess 11U.
- the recess 10BU of the vehicle body 10B has a shape along the outer shape of the vessel 11. Next, the support structure of the vessel 11 will be described.
- FIG. 9 is a diagram illustrating a support structure of the vessel 11 provided in the transport machine 10 according to the present embodiment.
- FIG. 10 is a top view of the transport machine 10 according to the present embodiment.
- FIG. 11 is a diagram illustrating a state in which the transport machine 10 according to the present embodiment tilts the vessel 11.
- the vessel 11 is placed on the upper surface of the table 11T via a hydraulic cylinder (hoist cylinder) 11Cb as an actuator for moving the vessel 11 up and down.
- a hydraulic cylinder (hoist cylinder) 11Cb as an actuator for moving the vessel 11 up and down.
- the table 11T is supported by the vehicle body 10B via a pair of support bodies 11R and 11R provided on the upper surface of the recess 10BU of the vehicle body 10B.
- the support 11R is a rod-like member extending in the width direction of the vehicle body 10B.
- Each support 11R, 11R is fitted in a pair of grooves 11TU, 11TU provided in a portion of the table 11T facing the vehicle body 10B.
- the grooves 11TU and 11TU are provided in the direction in which the support 11R extends, that is, in the width direction of the vehicle body 10B.
- the table 11T moves along the supports 11R and 11R. That is, the table 11T can move in the width direction of the vehicle body 10B of the transporting machine 10.
- a hydraulic cylinder (slide cylinder) 11Ca is attached between the table 11T and the vehicle body 10B as an actuator for moving the table 11T in the width direction of the vehicle body 10B.
- the hydraulic cylinder 11Ca expands and contracts, the table 11T moves to both sides in the width direction of the vehicle body 10B. Since the vessel 11 is attached to the table 11T, as shown in FIG. 10, the vessel 11 can also move to both sides in the width direction W of the vehicle body 10B together with the table 11T.
- the vessel 11 moves to the loading machine 30 side as shown in FIG. By doing in this way, the conveyance machine 10 can load the ore MR on the vessel 11 reliably. Further, when the ore MR is loaded on one side of the vessel 11, the transporting machine 10 reciprocates the vessel 11 in the width direction of the vehicle body 10 ⁇ / b> B to disperse the ore MR over the entire vessel 11, and the ore MR. Can be suppressed.
- FIG. 11 shows a state where the hydraulic cylinder 11Cb is extended and the vessel 11 is tilted. As shown in FIG. 11, the vessel 11 swings about an axis Zb on one side in the width direction W of the vehicle body 10B.
- the axis Zb is included in the table 11T and is parallel to the front-rear direction of the vehicle body 10B.
- the hydraulic cylinder 11Cb extends, the vessel 11 becomes higher on the side opposite to the axis Zb and protrudes from the recess 10BU of the vehicle body 10B.
- the vessel 11 is inclined, the lid 11CV on the axis Zb side is opened, and the ore MR is discharged from the axis Zb side.
- the hydraulic cylinder 11Cb contracts, the vessel 11 is received in the recess 10BU of the vehicle body 10B.
- the lid 11CV is interlocked with the operation in which the vessel 11 moves up and down by a link mechanism (not shown).
- the vessel 11 swings about only the axis Zb existing on one side in the width direction W of the vehicle body 10B, but is not limited to this.
- the vessel 11 may swing about another axis that is present on the other side and parallel to the longitudinal direction of the vehicle body 10B in addition to the axis Zb on one side of the vehicle body 10B. In this way, the transporting machine 10 can discharge the ore MR from both sides in the width direction W of the vehicle body 10B.
- FIG. 12 is an example of a block diagram illustrating the control device 70 provided in the transport machine 10.
- the control device 70 included in the transport machine 10 controls the travel of the transport machine 10 and the movement and elevation of the vessel 11 in the width direction W.
- the control device 70 includes a processing device 71 and a storage device 72.
- the processing device 71 includes imaging devices 16A and 16B, non-contact sensors 17A and 17B, peripheral monitoring cameras 17CA and 17CB, a mass sensor 18, a reading device 19, a range sensor 20, a gyro sensor 21, a speed sensor 22, and an acceleration sensor 23.
- the drive control device 24, the communication device 25, the storage device 72, and the like are connected.
- the imaging devices 16A and 16B and the peripheral monitoring cameras 17CA and 17CB include an image sensor such as a CCD or a CMOS, and can acquire an optical image of an object and detect the outer shape of the object.
- at least one of the imaging devices 16A and 16B and the peripheral monitoring cameras 17CA and 17CB includes a stereo camera, and can acquire three-dimensional outline data of an object.
- the imaging devices 16A and 16B and the surrounding monitoring cameras 17CA and 17CB output the captured results to the processing device 71.
- the processing device 71 acquires the detection results of the imaging devices 16A and 16B, and acquires information related to the state of the ore MR in the vessel 11 based on the detection results.
- the outer shape of the ore MR loaded on the vessel 11 may be detected using at least one of a laser scanner and a three-dimensional distance sensor.
- the non-contact sensors 17A and 17B are connected to the processing device 71 and output the detection result to the processing device 71.
- the non-contact sensors 17A and 17B output the acquired results to the processing device 71.
- the mass sensor 18 detects the mass of the vessel 11 and the ore MR loaded on the vessel 11. Since the mass of the vessel 11 is known in advance, the mass of the ore MR loaded on the vessel 11 can be obtained by subtracting the mass of the vessel 11 from the detection result of the mass sensor 18.
- the mass sensor 18 is connected to the processing device 71 and outputs a detection result to the processing device 71.
- the processing device 71 Based on the detection result of the mass sensor 18, the processing device 71 obtains information on the mass of the ore MR loaded on the vessel 11 and whether or not the ore MR is loaded on the vessel 11.
- the mass sensor 18 may be, for example, a strain gauge type load cell provided between the vessel 11 and the table 11T, or may be a pressure sensor that detects the hydraulic pressure of the hydraulic cylinder 11Cb.
- the reading device 19 detects the identification information (unique information) of the mark provided in the drift DR.
- a plurality of marks are arranged along the drift DR.
- the mark may be an identifier (code) such as a barcode and a two-dimensional code, or may be an identifier (tag) such as an IC tag or RFID.
- the reading device 19 is connected to the processing device 71 and outputs a detection result to the processing device 71.
- the range sensor 20 is attached to the outside of the vehicle body 10B of the transporting machine 10, for example, forward and rearward, and acquires and outputs physical shape data of the space around the transporting machine 10.
- the gyro sensor 21 detects the direction (direction change amount) of the transport machine 10 and outputs the detection result to the processing device 71.
- the speed sensor 22 detects the traveling speed of the transport machine 10 and outputs the detection result to the processing device 71.
- the acceleration sensor 23 detects the acceleration of the transport machine 10 and outputs the detection result to the processing device 71.
- the drive control device 24 is, for example, a microcomputer.
- the drive control device 24 controls the operation of the electric motors 13A and 13B, the braking system 13BS, the steering system 13SS, and the electric motor 13C that drives the hydraulic pump 13P based on a command from the processing device 71.
- the hydraulic pump 13P is a device that supplies hydraulic oil to the hydraulic cylinders 11Ca and 11Cb.
- the transporting machine 10 travels using the traveling electric motors 13A and 13B, but is not limited thereto.
- the transporting machine 10 may travel by a hydraulic motor that is driven by hydraulic fluid discharged from the hydraulic pump 13P.
- the braking system 13BS and the steering system 13SS may also be electric, or may operate using hydraulic pressure.
- the information regarding the position (absolute position) where the mark is arranged in the drift DR is known information measured in advance.
- Information regarding the absolute position of the mark is stored in the storage device 72.
- the processing device 71 determines the absolute value of the transport machine 10 in the drift DR based on the mark detection result (mark identification information) detected by the reading device 19 provided in the transport machine 10 and the storage information in the storage device 72. The position can be determined.
- the range sensor 20 includes a scanning lightwave distance meter that can output physical shape data of a space.
- the range sensor 20 includes, for example, at least one of a laser scanner and a three-dimensional distance sensor, and can acquire and output two-dimensional or three-dimensional spatial data.
- the range sensor 20 detects at least one of the loading machine 30 and the wall surface of the drift DR.
- the range sensor 20 can acquire at least one of the shape data of the loading machine 30, the shape data of the wall surface of the drift DR, and the shape data of the load of the vessel 11.
- the range sensor 20 can detect at least one of a relative position (relative distance and direction) with the loading machine 30 and a relative position with the wall surface of the drift DR.
- the range sensor 20 outputs the detected information to the processing device 71.
- information regarding the wall surface of the drift DR is obtained in advance and stored in the storage device 72. That is, the information regarding the wall surface of the drift DR is known information measured in advance.
- the information regarding the wall surface of the drift DR includes information regarding each shape of the plurality of portions of the wall surface and information regarding the absolute position of each of the wall surface portions.
- the storage device 72 stores the relationship between the shapes of the plurality of wall portions and the absolute positions of the wall portions having the shapes.
- the processing device 71 transports in the drift DR based on the detection result (wall shape data) of the drift DR detected by the range sensor 20 provided in the transporting machine 10 and the storage information in the storage device 72. The absolute position and orientation of the machine 10 can be determined.
- the processing device 71 Based on the current position (absolute position) of the transporting machine 10 derived using at least one of the reading device 19 and the range sensor 20, the processing device 71 transports according to a determined route (target route) of the underground mine MI.
- the transporting machine 10 that travels the drift DR is controlled so that the machine 10 travels.
- the processing device 71 is, for example, a microcomputer including a CPU. Based on the detection results of the non-contact sensors 17A, 17B, the reading device 19, the range sensor 20, and the like, the processing device 71 is configured to use the electric motors 13A, 13B, the braking system 13BS, the wheels 12A, The steering system 13SS of 12B is controlled. Then, the processing device 71 causes the transport machine 10 to travel according to the target route described above at a predetermined traveling speed and acceleration.
- the storage device 72 includes at least one of a RAM, a ROM, a flash memory, and a hard disk drive, and is connected to the processing device 71.
- the storage device 72 stores a computer program and various information necessary for the processing device 71 to autonomously run the transporting machine 10.
- the communication device 25 is connected to the processing device 71 and performs data communication with at least one of the communication device mounted on the loading machine 30 and the management device 3.
- the transport machine 10 is an unmanned vehicle and can autonomously travel.
- the communication device 25 can receive information (including a command signal) transmitted from at least one of the management device 3 and the loading machine 30. Further, the communication device 25 can transmit information detected by the imaging devices 16A and 16B, the peripheral monitoring cameras 17CA and 17CB, the speed sensor 22, the acceleration sensor 23, and the like to at least one of the management device 3 and the loading machine 30.
- the transporting machine 10 transmits information about the periphery of the transporting machine 10 acquired by at least one of the peripheral monitoring cameras 17CA and 17CB and the non-contact sensors 17A and 17B to the management device 3, and the operator transports based on the peripheral information.
- the machine 10 can also be remotely controlled. Thus, the transport machine 10 can travel not only autonomously but also by an operator's operation, and can slide and lift the vessel 11.
- the management device 3 that has acquired the information detected by the speed sensor 22, the acceleration sensor 23, and the like accumulates this information in the storage device 3M, for example, as operation information of the transporting machine 10.
- the management device 3 acquires information captured by the peripheral monitoring cameras 17CA and 17CB
- the operator operates the transporting machine 10 while visually recognizing an image around the transporting machine 10 captured by the peripheral monitoring cameras 17CA and 17CB.
- the loading machine 30 which acquired the information regarding the mass of the ore MR of the vessel 11 detected by the mass sensor 18 can also control the loading amount of the ore MR on the vessel 11 based on this information. Next, the loading machine 30 will be described.
- FIG. 13 is a side view of the loading machine 30 according to the present embodiment.
- FIG. 14 is a top view of the loading machine 30 according to the present embodiment.
- FIG. 15 is a front view of the loading machine 30 according to the present embodiment.
- FIG. 13 shows a state where the loading machine 30 excavates the ore MR of the natural ground RM and conveys the excavated ore MR.
- the loading machine 30 excavates the natural ground RM of the ore MR in the crosscut CR, and loads the excavated ore MR on the vessel 11 of the transporting machine 10 shown in FIGS.
- a feeder 31, a support mechanism 32, a traveling device 34, a penetrating member 35, a rotating body 36, and a rock guard 37 are attached to the vehicle body 30 ⁇ / b> B of the loading machine 30.
- the side on which the penetrating member 35 is attached is the front side of the loading machine 30, and the side opposite to the side on which the penetrating member 35 is attached is the rear side of the loading machine 30. Note that the loading machine 30 may not include the rotating body 36 and the rock guard 37.
- the feeder 31 loads the ore MR from the natural ground RM, transports it in a direction away from the natural ground RM at the draw point DP, and then discharges it. That is, the feeder 31 conveys the ore MR loaded in front of the loading machine 30 toward the rear, and discharges it from the rear.
- the feeder 31 uses a transport belt as an endless transport body and rotates the belt around a pair of rollers to transport the ore MR from the loading side 31F to the discharge side 31E.
- the loading side 31F is the natural ground RM side
- the discharge side 31E is the opposite side to the loading side 31F. As shown in FIG.
- the feeder 31 is provided with a pair of guides 31 ⁇ / b> G and 31 ⁇ / b> G on both sides in the width direction W.
- the pair of guides 31 ⁇ / b> G and 31 ⁇ / b> G suppress the ore MR that is being transported from the feeder 31 from dropping off.
- the width direction W is a direction orthogonal to the direction F in which the feeder 31 transports the ore MR, and is a direction parallel to the rotation center axis of the pair of rollers provided in the feeder 31.
- the width direction W of the feeder 31 is also the width direction of the vehicle body 30B.
- the feeder 31 includes a guide 39 for guiding the ore MR into the vessel 11 of the transporting machine 10 on the discharge side 31E.
- the feeder 31 swings about the axis of the loading side 31F of the feeder 31 in front of the vehicle body 30B.
- the feeder 31 can change the angle ⁇ with respect to the ground G.
- the angle ⁇ is an angle formed between the straight line LC connecting the rotation center axes of the pair of rollers included in the feeder 31 and the ground G.
- Rotating roller 33 loads ore MR into feeder 31.
- the rotating roller 33 feeds the ore MR into the feeder 31 while rotating on the loading side 31F of the feeder 31, that is, in front of the feeder 31.
- the rotating roller 33 is installed on the loading side 31F of the feeder 31 by the support mechanism 32 including the boom 32a and the arm 32b.
- the rotating roller 33 includes a rotating member 33D that rotates around a predetermined axis Zr and a contact member 33B that is provided on the outer periphery of the rotating member 33D and that excavates in contact with the ore MR.
- the contact member 33B is a plurality of plate-like members that protrude outward in the radial direction from the rotating member 33D and that are provided at predetermined intervals along the circumferential direction of the rotating member 33D.
- a plane parallel to the plate surface of the contact member 33B is not orthogonal to the axis Zr.
- a plane parallel to the plate surface of the contact member 33B is parallel to the axis Zr.
- the contact member 33B may be bent so that the tip, that is, the end opposite to the rotating member 33D side, bites into the natural ground RM to be excavated.
- the contact member 33B moves away from the feeder 31 when positioned at the upper U, and approaches the feeder 31 when positioned at the lower D.
- the plurality of contact members 33B excavate the ore MR from the natural ground RM and send it to the feeder 31. Since the plurality of contact members 33B rotate together with the rotation member 33D, the ore MR can be continuously excavated and fed into the feeder 31.
- the support mechanism 32 that rotatably supports the rotating roller 33 includes a boom 32a attached to the vehicle body 30B and an arm 32b connected to the boom 32a.
- the boom 32a is attached to the vehicle body 30B of the loading machine 30 via the shaft 38A, and swings with respect to the vehicle body 30B about the shaft 38A.
- the arm 32b is connected to, for example, the end of the boom 32a opposite to the vehicle body 30B via the shaft 38B, and swings about the shaft 38B with respect to the boom 32a.
- the arm 32b is an end opposite to the end connected to the boom 32a, and rotatably supports the rotating roller 33.
- the boom 32a and the arm 32b may be driven to swing by a hydraulic cylinder as an actuator, or may be driven to swing by an electric motor or a hydraulic motor.
- the boom 32a swings around the first axis line Za with respect to the vehicle body 30B
- the arm 32b swings around an axis line Za 'parallel to the first axis line Za.
- the first axis Za is the central axis of the shaft 38A that connects the boom 32a and the vehicle body 30B
- the axis Za ′ that is parallel to the first axis Za is the center of the shaft 38B that connects the boom 32a and the arm 32b. Is the axis.
- the arm 32b may further swing around an axis parallel to the second axis perpendicular to the first axis Za. If it does in this way, since the range which can rotate rotation roller 33 becomes large, the freedom degree of excavation work improves.
- the boom 32a is a pair of rod-shaped members (first rod-shaped members) provided on both sides in the width direction W of the vehicle body 30B, in this embodiment, on both sides in the width direction W of the feeder 31.
- the arms 32b are a pair of rod-shaped members (second rod-shaped members) connected to the respective booms 32a. As shown in FIG. 14, the pair of arms 32b supports the rotating roller 33 between them.
- the pair of booms 32a are connected by beams 32J. Since the rigidity of the support mechanism 32 is improved by such a structure, the excavation efficiency of the ore MR is reduced since the support mechanism 32 can reliably press the rotating roller 33 against the natural ground RM when excavating the ore MR. It is suppressed. Moreover, you may connect a pair of arm 32b with a rod-shaped or plate-shaped member. This is more preferable because the rigidity of the support mechanism 32 is further improved.
- the rotating roller 33 moves when the boom 32a swings with respect to the vehicle body 30B and the arm 32b swings with respect to the boom 32a.
- the support mechanism 32 can change the relative positional relationship between the rotation roller 33, the feeder 31, and the vehicle body 30B by moving the rotation roller 33.
- the support mechanism 32 excavates different positions of the natural ground RM by moving the rotating roller 33, or moves the rotating roller 33 from the natural ground RM toward the feeder 31 to ore MR from the natural ground RM. Can be scraped into the feeder 31 side.
- the support mechanism 32 uses the rotating roller 33 to scrape the object toward the feeder 31. , The object ahead of the loading machine 30 in the traveling direction can be removed.
- the rotating roller 33 is rotated by an electric motor 33M attached to the tip of the arm 32b as shown in FIG.
- the device for driving the rotating roller 33 is not limited to the electric motor 33M, and may be, for example, a hydraulic motor. Further, the location where the electric motor 33M is attached is not limited to the tip of the arm 32b.
- a traveling device 34 for traveling the vehicle body 30B is attached.
- the traveling device 34 includes a pair of crawler belts 34C provided on both sides in the width direction of the vehicle body 30B, a pair of drive wheels 34D provided on both sides in the width direction of the vehicle body 30B, and a pair of wheels provided on both sides in the width direction of the vehicle body 30B.
- a driven wheel 34S a crawler belt 34C is wound around the drive wheel 34D and the driven wheel 34S.
- Each drive wheel 34D is driven separately and independently.
- the loading machine 30 includes a traveling electric motor for each drive wheel 34D. With such a structure, the pair of crawler belts 34C and 34C are driven independently.
- the penetration member 35 is attached to the vehicle body 30B.
- the penetration member 35 is disposed on the loading side 31F of the feeder 31 of the vehicle body 30B.
- the penetrating member 35 is a member having a cone shape, and in the present embodiment, has a quadrangular pyramid shape.
- the shape of the penetrating member 35 is not limited to a quadrangular pyramid shape, and may be a triangular pyramid shape, for example.
- the penetrating member 35 is attached to the vehicle body 30B so that the top of the cone is in front of the vehicle body 30B. By doing in this way, when the loading machine 30 penetrates into the natural ground RM, the penetration member 35 penetrates into the natural ground RM from the top.
- the penetrating member 35 penetrates the natural mountain RM from the top of the cone and breaks the natural mountain RM.
- the traveling device 34 causes the feeder 31 and the vehicle body 30B to which the penetrating member 35 is attached to travel forward, and the feeder 31 is moved to the natural ground RM while operating the feeder 31. Intrude.
- the upper conveyor belt moves from the loading side 31F toward the discharging side 31E.
- the loading machine 30 can penetrate deeper into the natural ground RM because the driving force of the feeder 31 can be used for penetration by operating the feeder 31 in this way during penetration.
- a pair of rotating bodies 36 are provided on both sides in the width direction of the vehicle body 30B, that is, on both sides in the direction orthogonal to the conveying direction of the feeder 31.
- the pair of rotating bodies 36 is disposed in front of the traveling device 34 and on the loading side 31 ⁇ / b> F of the feeder 31.
- the rotating body 36 is a structure in which a plurality of blades 36B are provided at predetermined intervals around a drum 36D that rotates around a predetermined axis.
- the rotating body 36 is driven by, for example, an electric motor.
- the rotating body 36 may be driven by an electric motor that drives the feeder 31.
- the driving of the feeder 31 and the driving of the rotating body 36 may be switched by a clutch or the like. For example, when the clutch is engaged, the feeder 31 and the rotator 36 rotate at the same time, and when the clutch is released, only the feeder 31 can rotate.
- the rotating body 36 rotates in a direction in which the vehicle body 30B of the loading machine 30 is pressed against the ground G when the penetrating member 35 penetrates into the natural ground RM. Specifically, the rotating body 36 rotates so that the blade 36B on the natural mountain RM side is directed upward U from the lower side D, and the blade 36B on the traveling device 34 side is directed downward D from the upper side U. By doing in this way, when the blade 36B on the natural ground RM side contacts the natural ground RM, the rotating body 36 pushes the front of the vehicle body 30B downward D, so that the crawler belt 34C of the traveling device 34 touches the ground G. It is more strongly pressed against.
- the frictional force between the crawler belt 34C and the ground G increases, so that the traveling device 34 can easily allow the penetration member 35 to penetrate the natural ground RM.
- a rock guard 37 is provided between the rotating body 36 and the crawler belt 34 ⁇ / b> C of the traveling device 34.
- the rock guard 37 is attached to the vehicle body 30B.
- the rock guard 37 protects the traveling device 34 from the ore MR flying from the rotating roller 33 during excavation, or protects the traveling device 34 from rocks or the like existing in the tunnel when the loading machine 30 travels. To do.
- the rock guard 37 suppresses a decrease in durability of the traveling device 34.
- the vehicle body 30B includes a fixing device 30F that extends toward the outer side in the width direction of the vehicle body 30B and is pressed against the wall surface CRW of the crosscut CR connected to the draw point DP.
- a fixing device 30F is provided on each side of the vehicle body 30B in the width direction so as to face each other, but the number and installation locations of the fixing devices 30F are not limited thereto.
- the fixing device 30F may be provided above the vehicle body 30B.
- the fixing device 30F includes, for example, a hydraulic cylinder 30FC and a pressing member 30FP provided at the tip of the piston of the hydraulic cylinder 30FC.
- the fixing device 30F fixes the loading machine 30 in the cross cut CR when the loading machine 30 is excavated and when the ore MR is conveyed. Specifically, the fixing device 30F extends the hydraulic cylinder 30FC and presses the pressing member 30FP against the wall surface CRW, thereby fixing the vehicle body 30B of the loading machine 30 in the crosscut CR via these members. By doing in this way, the reaction force generated when the loading machine 30 excavates the natural ground RM can be received by the cross cut CR via the fixing device 30F. As a result, since the posture of the loading machine 30 is stable, the natural ground RM can be excavated stably.
- the hydraulic cylinder 30FC may be provided between the fixing device 30F and the vehicle body 30B, and after fixing the fixing device 30F to the wall surface CRW of the crosscut CR, the vehicle body may be penetrated using the driving force of the hydraulic cylinder 30FC.
- the fixing device 30F When the fixing device 30F is provided on both sides or above the width direction of the vehicle body 30B, the fixing by the fixing device 30F is released when the loading machine 30 penetrates.
- the hydraulic cylinder 30FC is contracted, and the pressing member 30FP does not press the wall surface CRW.
- the fixing device 30F operates to fix the loading machine 30 in the cross cut CR.
- the traveling device 34 moves the loading machine 30 after the fixing by the fixing device 30F is released. Move.
- a fixing device 30F is provided behind the vehicle body 30B, that is, on the discharge side 31E of the feeder 31, and is fixed between the reaction force receiver TG protruding from the ground G in the crosscut CR and the vehicle body 30B. You may receive the reaction force mentioned above through the apparatus 30F. At the time of excavation, the reaction force in the front-rear direction of the loading machine 30 is large, but by using such a structure, the reaction force at the time of excavation can be more effectively received. Moreover, the loading machine 30 can also adjust the position of the loading machine 30 at the time of excavation by extending the fixing device 30F. Note that the loading machine 30 may not include the fixing device 30F.
- the loading machine 30 includes the ore MR between a portion where the ore MR is loaded on the feeder 31 (loading side 31F) and a portion where the ore MR is discharged from the feeder 31 (discharge side 31E).
- a switching mechanism 80 for switching between discharging and stopping discharging is provided.
- the switching mechanism 80 includes a support body 81, a lid 82, and a hydraulic cylinder 83 as an actuator that opens and closes the lid 82. As shown in FIG.
- the support 81 has two leg portions 81 ⁇ / b> R attached at one end to both sides in the width direction of the vehicle body 30 ⁇ / b> B, specifically, both sides in the width direction of the feeder 31, and the two leg portions 81 ⁇ / b> R. It is a gate-shaped member including a connecting portion 81C that connects them at the other end. The ore MR passes through a portion surrounded by the two leg portions 81R and the connecting portion 81C.
- the lid 82 is a plate-like member, and is provided at a portion surrounded by the two leg portions 81R and the connecting portion 81C.
- the lid 82 rotates around a predetermined axis Zg existing on the connecting portion 81C side of the support 81.
- a hydraulic cylinder 83 is provided between the lid 82 and the connecting portion 81 ⁇ / b> C of the support body 81. As the hydraulic cylinder 83 expands and contracts, the lid 82 opens and closes a portion surrounded by the two leg portions 81R and the connecting portion 81C. When the lid 82 is opened, the ore MR passes through a portion surrounded by the two leg portions 81R and the connecting portion 81C.
- the loading machine 30 includes an information collection device 40.
- the information collecting device 40 is attached to the loading side 31F of the vehicle body 30B, that is, the front side. More specifically, the part where the information collecting device 40 collects information is attached to the loading side 31F of the vehicle body 30B, that is, facing forward.
- the information collection device 40 is a device that acquires and outputs three-dimensional spatial data.
- the information collection device 40 acquires ore information as information relating to the state of the ore MR of the natural ground RM.
- the ore information is three-dimensional spatial data of the natural ground RM.
- the information collection device 40 is, for example, a camera, a stereo camera, a laser scanner, a three-dimensional distance sensor, or the like.
- the part where the information collecting device 40 collects information is a lens in the case of a camera or a stereo camera, and a light receiving part in the case of a laser scanner and a three-dimensional distance sensor.
- a stereo camera is used as the information collection device 40.
- the loading machine 30 has three information collection devices 40 attached to the beam 32J of the support mechanism 32. That is, the plurality of information collection devices 40 are installed at a plurality of locations in the width direction of the vehicle body 30B. By doing in this way, even when the imaging target of one information collection device 40 is hidden in the arm 32b, the loading machine 30 can obtain the ore information of the imaging target by the other information collection device 40.
- the control device included in the loading machine 30 controls the operation of the loading machine 30 using the ore information collected by the information collecting device 40.
- the control device described above controls at least one of the feeder 31, the rotating roller 33, the support mechanism 32, and the traveling device 34 based on the ore information acquired by the information collecting device 40.
- the loading machine 30 includes an information collecting device 41 on the discharge side 31E of the vehicle body 30B, that is, on the rear side. More specifically, the part where the information collecting device 41 collects information is attached facing the discharge side 31E of the vehicle body 30B, that is, the rear side.
- the information collection device 41 is a device that acquires and outputs three-dimensional spatial data, like the information collection device 40 described above.
- the information collection device 41 acquires load information as information regarding the state of the ore MR loaded on the vessel 11 of the transporting machine 10 illustrated in FIGS. 4 and 5.
- the cargo information is three-dimensional spatial data of the ore MR.
- the information collection device 41 is, for example, a camera, a stereo camera, a laser scanner, a three-dimensional distance sensor, or the like, similar to the information collection device 40 described above.
- the part where the information collecting device 41 collects information is a lens in the case of a camera or a stereo camera, and a light receiving part in the case of a laser scanner and a three-dimensional distance sensor.
- a stereo camera is used as the information collection device 41.
- the loading machine 30 has two information collection devices 41 attached to both sides of the feeder 31 in the width direction. That is, the plurality of information collection devices 41 are installed at a plurality of locations in the width direction W of the vehicle body 30B. By doing in this way, the loading machine 30 can obtain the ore information of the imaging target by the other information collecting device 41 even when the imaging target of one information collecting device 41 is hidden in the shadow of the mine shaft.
- the control device provided in the loading machine 30 controls at least one of the loading machine 30 and the transporting machine 10 using the load information collected by the information collecting device 41.
- the control device described above controls the operation of the rotating roller 33, the feeder 31, the switching mechanism 80, or the like based on the load information acquired by the information collecting device 41, or the position or vessel of the vessel 11 provided in the transport machine 10. 11 movements are controlled.
- the loading machine 30 changes the conveyance amount of the ore MR or adjusts the position of the vessel 11 according to the state of the ore MR loaded on the vessel 11 of the transporting machine 10. Therefore, for example, the production efficiency of the mine M is improved.
- FIG. 16 is a view showing a posture when the loading machine 30 according to the present embodiment travels.
- the angle ⁇ of the feeder 31 with respect to the ground G is smaller than when the loading machine 30 excavates and conveys the ore MR (see FIG. 13). That is, the straight line LC connecting the rotation center axes of the pair of rollers provided in the feeder 31 is closer to the ground G. If it does in this way, since the loading side 31F of the feeder 31 arrange
- the support mechanism 32 when the loading machine 30 travels, the support mechanism 32 is folded. Then, the rotating roller 33 moves to a position closer to the feeder 31 as compared with the case where the loading machine 30 excavates and conveys the ore MR (see FIG. 13). For this reason, in the loading machine 30, the rotation roller 33 that exists at a position away from the center of gravity in the front-rear direction of the vehicle body 30B moves to a position closer to the center of gravity. To do. As a result, the loading machine 30 can travel stably.
- FIG. 17 is an example of a block diagram illustrating a control device 75 provided in the loading machine 30 according to the present embodiment.
- the control device 75 included in the loading machine 30 controls the feeder 31, the support mechanism 32, the rotating roller 33, the traveling device 34, the rotating body 36, and the switching mechanism 80.
- the control device 70 includes a processing device 76 and a storage device 77.
- the processing device 76 includes a front imaging device 40C corresponding to the information collecting device 40, a rear imaging device 41C corresponding to the information collecting device 41, a non-contact sensor 42, a reading device 43, a range sensor 44, a gyro sensor 45, a speed sensor.
- the non-contact sensor 42, the reading device 43, and the range sensor 44 are attached to the outside of the vehicle body 30B of the loading machine 30.
- the front imaging device 40C and the rear imaging device 41C include an image sensor such as a CCD or a CMOS, and can acquire an optical image of an object and detect the outer shape of the object.
- the front imaging device 40C and the rear imaging device 41C include a stereo camera and can acquire three-dimensional outline data of an object.
- the front imaging device 40C and the rear imaging device 41C output the captured result to the processing device 76.
- the processing device 76 acquires the detection result of the front imaging device 40C, and obtains the ore information described above based on the detection result. Further, the processing device 76 acquires the detection result of the rear imaging device 41C, and obtains the load information described above based on the detection result.
- the outer shape of the ore MR of the natural ground RM and the outer shape of the ore MR loaded on the vessel 11 may be detected using at least one of a laser scanner and a three-dimensional distance sensor.
- the non-contact sensor 42 detects an object existing around the loading machine 30.
- the non-contact sensor 42 is connected to the processing device 76 and outputs a detection result to the processing device 76.
- the non-contact sensor 42 outputs the acquired result to the processing device 76.
- the reading device 43 detects identification information (unique information) of marks provided on the drift DR or the cross cut CR. A plurality of marks are arranged along the drift DR or the crosscut CR.
- the reading device 43 is connected to the processing device 76 and outputs a detection result to the processing device 76.
- the mark may be an identifier (code) such as a barcode and a two-dimensional code, or may be an identifier (tag) such as an IC tag or RFID.
- the information regarding the position (absolute position) where the mark is arranged in the drift DR or the crosscut CR is known information measured in advance.
- Information regarding the absolute position of the mark is stored in the storage device 77.
- the processing device 76 Based on the mark detection result (mark identification information) detected by the reading device 43 provided in the loading machine 30 and the storage information of the storage device 77, the processing device 76 uses the drift DR or the crosscut CR. The absolute position of the loading machine 30 can be determined.
- the range sensor 44 acquires and outputs the physical shape data of the space.
- the gyro sensor 45 detects the direction (direction change amount) of the loading machine 30 and outputs the detection result to the processing device 76.
- the speed sensor 46 detects the traveling speed of the loading machine 30 and outputs the detection result to the processing device 76.
- the acceleration sensor 47 detects the acceleration of the loading machine 30 and outputs the detection result to the processing device 76.
- the drive control device 48 is, for example, a microcomputer.
- the drive control device 48 is based on a command from the processing device 76, and includes an electric motor 33M that drives the rotating roller 33 shown in FIG.
- the operation of the electric motor 50 that swings the arm 32b, the electric motor 51F that drives the feeder 31, the electric motor 51R that rotates the rotating body 36, and the electric motor 86 that drives the hydraulic pump 85 is controlled.
- the hydraulic pump 85 is a device that supplies hydraulic oil to the hydraulic cylinder 83 provided in the switching mechanism 80, the hydraulic cylinder 87 as an actuator that changes the posture of the feeder 31, and the hydraulic cylinder 30FC of the fixing device 30F.
- the boom 32a and the arm 32b may be swung by the hydraulic cylinder 30FC. In this case, hydraulic oil is supplied from the hydraulic pump 85 to the boom cylinder that swings the boom 32a and the arm cylinder that swings the arm 32b.
- the electric motor 48L drives one crawler belt 34C shown in FIG. 14, and the electric motor 48R drives the other crawler belt 34C.
- the electric motor 48L drives one crawler belt 34C shown in FIG. 14, and the electric motor 48R drives the other crawler belt 34C.
- the loading machine 30 travels by the electric motors 48L and 48R included in the travel device 34, but is not limited thereto.
- the loading machine 30 may travel by a hydraulic motor that is driven by hydraulic oil discharged from the hydraulic pump 85.
- the boom 32 a and the arm 32 b of the support mechanism 32, the rotating roller 33 and the rotating body 36, and the feeder 31 may also be driven by a hydraulic cylinder or a hydraulic motor that is driven by hydraulic oil discharged from the hydraulic pump 85.
- the range sensor 44 includes a scanning lightwave distance meter that can output physical shape data of a space.
- the range sensor 44 includes, for example, at least one of a laser range finder, a laser scanner, and a three-dimensional scanner, and can acquire and output three-dimensional spatial data.
- the range sensor 44 detects at least one of the wall surfaces of the transport machine 10, the drift DR, and the crosscut CR.
- the range sensor 44 can acquire at least one of the shape data of the transporting machine 10, the shape data of the wall surface of the drift DR or the crosscut CR, and the shape data of the load of the vessel 11 included in the transporting machine 10. is there.
- the range sensor 44 can detect at least one of a relative position (relative distance and direction) with the transporting machine 10 and a relative position with the wall surface of the drift DR or the crosscut CR. The range sensor 44 outputs the detected information to the processing device 76.
- information regarding the wall surfaces of the drift DR and the crosscut CR is obtained in advance and stored in the storage device 77. That is, the information regarding the wall surface of the drift DR is known information measured in advance.
- the information regarding the wall surface of the drift DR includes information regarding each shape of the plurality of portions of the wall surface and information regarding the absolute position of each of the wall surface portions.
- the storage device 77 stores the relationship between the shapes of the plurality of wall portions and the absolute positions of the wall portions having the shapes.
- the processing device 76 uses the drift DR wall surface detection result (wall surface shape data) detected by the range sensor 44 provided in the loading machine 30 and the storage information of the storage device 77 to determine whether the drift DR The absolute position and orientation of the loading machine 30 can be determined.
- the processing device 76 Based on the current position (absolute position) of the loading machine 30 derived using at least one of the reading device 43 and the range sensor 44, the processing device 76 follows a determined route (target route) of the underground mine MI. The loading machine 30 that travels in the drift DR or the cross-cut CR is controlled so that the loading machine 30 travels. At this time, the processing device 76 controls the loading machine 30 so as to be arranged at the designated draw point DP.
- the processing device 76 is a microcomputer including a CPU, for example.
- the processing device 76 controls the electric motors 48L and 48R included in the traveling device 34 via the drive control device 48 based on the detection results of the front imaging device 40C, the rear imaging device 41C, the non-contact sensor 42, the reading device 43, and the like. . Then, the processing device 76 causes the loading machine 30 to travel at a predetermined traveling speed and acceleration according to the above-described target route.
- the storage device 77 includes at least one of a RAM, a ROM, a flash memory, and a hard disk drive, and is connected to the processing device 76.
- the storage device 77 stores a computer program and various information necessary for the processing device 76 to autonomously run the loading machine 30.
- the communication device 52 is connected to the processing device 76 and performs data communication with at least one of the communication device mounted on the transporting machine 10 and the management device 3.
- the loading machine 30 is an unmanned vehicle and can autonomously travel.
- the communication device 52 can receive information (including a command signal) transmitted from at least one of the management device 3 and the transporting machine 10 via the antenna 53. Further, the communication device 52 manages information detected by the front imaging device 40C, the rear imaging device 41C, the non-contact sensor 42, the reading device 43, the range sensor 44, the gyro sensor 45, the speed sensor 46, the acceleration sensor 47, and the like. 3 and at least one of the transporting machines 10 can be transmitted via the antenna 53.
- the loading machine 30 is not limited to an unmanned vehicle capable of autonomous traveling.
- the management device 3 acquires an image captured by the front imaging device 40C and displays it on the display device 8 shown in FIG.
- the management device 3 acquires an image captured by the rear imaging device 41C and displays it on the display device 8 shown in FIG. 6, and the operator excavates and loads the loading machine 30 while visually checking the displayed image.
- the operation of the vessel 11 of the transporting machine 10 may be controlled by remote control.
- the management device 3 that has acquired information detected by the speed sensor 46, the acceleration sensor 47, and the like accumulates this information as operation information of the loading machine 30, for example, in the storage device 3M.
- the management device 3 acquires information captured by the front imaging device 40C or the rear imaging device 41C
- the operator visually recognizes an image around the loading machine 30 captured by the front imaging device 40C or the rear imaging device 41C.
- the loading machine 30 can also be operated.
- the transporting machine 10 that has acquired information on the state of the ore MR of the vessel 11 detected by the rear imaging device 41C controls the loading amount of the ore MR on the vessel 11 or the position of the vessel 11 based on this information. You can also.
- the loading machine 30 is electric, but the internal combustion engine may be a power source.
- the battery handling device EX installed in the space SP shown in FIG. 2 will be described.
- FIG. 18 is a diagram illustrating an example of the capacitor handling device EX included in the mine management system 1 according to the present embodiment.
- the capacitor handling device EX is installed in the space SP.
- a maintenance space MS for maintaining the transporting machine 10 and the loading machine 30 is provided in the space SP.
- the storage battery handling device EX includes a storage battery holding device 90, a pair of guides 91a and 91b installed on both sides thereof, and replacement carts 92a and 92b guided by the guides 91a and 91b.
- the capacitor storage device 90 holds a plurality of replacement capacitors 14.
- the battery holder 90 has a function as a charger that charges the discharged battery 14.
- the guide 91a is provided on one side of the battery holding device 90, and the guide 91b is provided on the other side of the battery holding device 90.
- the guide 91a is two rails that extend from the battery holder 90 toward the entrance / exit SPG of the space SP.
- the guide 91b is the same as the guide 91a.
- the carriage 92a is attached to the guide 91a and moves along the guide 91a, and the carriage 92b is attached to the guide 91b and moves along the guide 91b.
- the transport machine 10 that has entered the space SP in order to replace the storage battery 14 stops between the guide 91a and the guide 91b. At this time, the transporting machine 10 stops with one capacitor 14 facing the guide 91a and the other capacitor 14 facing the guide 91b.
- the carriage 92 a and the carriage 92 b receive the charged battery 14 from the battery holder 90 and move toward the transport machine 10.
- the discharged storage battery 14 mounted on the transporting machine 10 is moved from the transporting machine 10 to the upper part thereof.
- the carriage 92a and the carriage 92b move to a position where the charged storage battery 14 loaded on each of the carriages 92a and 92b faces the transporting machine 10.
- the carriage 92 a and the carriage 92 b load the charged battery 14 into the transporting machine 10.
- the carriage 92 a and the carriage 92 b return to the position of the storage battery holding device 90 and move the storage battery 14 collected from the transport machine 10 to the storage battery holding device 90.
- the capacitor holding device 90 charges the capacitor. In this way, the battery 14 of the transport machine 10 is replaced.
- the storage battery 14 included in the transporting machine 10 may not be detachable.
- the battery storage device EX may charge the battery 14 included in the transport machine 10.
- the loading machine 30 since the transporting machine 10 travels by the capacitor 14, the discharged capacitor 14 is replaced with the charged capacitor 14 using the capacitor handling device EX in the space SP.
- the loading machine 30 is supplied with electric power from the power supply cable 5 shown in FIG. 3 and the like, and the rotating roller 33, the feeder 31 and the like operate. Since the loading machine 30 moves in the mine, for example, it travels to move to a different draw point DP. In this case, the loading machine 30 is disconnected from the feeding cable 5. For this reason, the loading machine 30 includes a capacitor for driving the electric motors 48L and 48R for traveling shown in FIG.
- This accumulator is charged by the electric power supplied from the power supply cable 5 when the loading machine 30 is excavating and transporting the ore MR at the draw point DP.
- the storage battery 30 is replaced with, for example, the maintenance space MS in the space SP.
- FIG. 19 is a diagram illustrating a direction in which the transporting machine 10 travels the drift DR of the mine MI in the mine management system 1 according to the present embodiment.
- a plurality of drifts DR a plurality of outer peripheral paths TR, a plurality of draw points DP, or a plurality of OR paths OP provided in the underground mine MI
- a code DR a code TR, a code DP, or a code OP
- the symbols a and b are not attached.
- a peripheral circuit CD is formed by the drift DR and the outer peripheral path TR.
- a plurality of drifts DR and a plurality of outer peripheral paths TR are connected to form one peripheral circuit CD.
- a peripheral circuit CDa is formed by two drifts DRb and DRd and two outer peripheral paths TRa and TRb.
- a peripheral circuit CDb is formed by the two drifts DRc and DRe and the two outer peripheral paths TRa and TRb.
- one peripheral circuit CD is formed by the two drifts DR and the two outer peripheral paths TR.
- one peripheral circuit CD is formed by two drift DRs and two outer peripheral paths TR.
- the two drift DRs included in one peripheral circuit CD have mutually travelable directions. Is different.
- At least one loading machine 30 is arranged in one drift DR. This is because even if two or more loading machines 30 are arranged in the same drift, waste occurs.
- the circumferential circuit CD on which the transport machine 10 travels is formed to include at least one of the ore pass OPa and the ore pass OPb. It is preferable.
- the peripheral circuit CD on which the transporting machine 10 traveling toward the storage battery handling apparatus EX installed in the space SP travels is provided with an ore path OPa and an ore path OPb. It does not have to be included.
- the management device 3 can arbitrarily generate a peripheral circuit CD for each transport machine 10.
- the management device 3 may generate the circuit CD according to the state of the transport machine 10. As an example, when the capacity of the battery 14 included in the transporting machine 10 falls below a predetermined threshold value and the transporting machine 10 does not load the ore MR on the vessel 11, the management apparatus 3 includes the power handling apparatus EX. Thus, the shortest circuit CD from the current position to the space SP can be generated as a replacement of the battery 14.
- the transporting machine 10 traveling on the drift DR travels on the circuit CD in the same direction.
- the vehicle travels clockwise around the circuit CD.
- the transporting machine 10 is loaded with the ore MR from the loading machine 30 at the draw point DP.
- the transporting machine 10 discharges the loaded ore MR with the ore pass OPa or the ore pass OPb.
- the transporting machine 10 traveling on the circumferential circuit CDa receives the loading of the ore MR from the loading machine 30 at the draw point DPb connected to the drift DRb.
- the transporting machine 10 travels along the drift DRb and the outer circumferential path TRa, and discharges the ore MR to the ore pass OPa provided adjacent to the outer circumferential path TRa.
- the transporting machine 10 that has discharged the ore MR travels on the drift DRd and receives the loading of the ore MR from the loading machine 30 at the draw point DPd connected to the drift DRd.
- the transporting machine 10 travels along the drift DRd and the outer circumferential path TRb, and discharges the ore MR to the ore pass OPb provided adjacent to the outer circumferential path TRb.
- the transporting machine 10 traveling on the peripheral circuit CDb receives the loading of the ore MR from the loading machine 30 at the draw point DPc connected to the drift DRc. Thereafter, the transporting machine 10 travels along the drift DRc and the outer circumferential path TRa, and discharges the ore MR to the ore pass OPa provided adjacent to the outer circumferential path TRa.
- the transporting machine 10 that has discharged the ore MR travels on the drift DRe and receives the loading of the ore MR from the loading machine 30 at the draw point DPe connected to the drift DRe. Thereafter, the transporting machine 10 travels along the drift DRe and the outer circumferential path TRb, and discharges the ore MR to the ore pass OPb provided adjacent to the outer circumferential path TRb.
- the passing of the transporting machine 10 can be minimized as compared with the case of reciprocating between the draw point DP and the ore pass OP.
- the circuit CD includes both the OR path OPa and the OR path OPb, the loading and discharging of the ore MR can be performed twice while the transporting machine 10 makes one circuit of the circuit CD.
- the conveyance amount of the ore MR can be increased.
- the mine management system 1 can improve the cycle time and improve the productivity of the mine M.
- the passing of the transport machine 10 can be suppressed.
- each drift DR the direction in which the transporting machine 10 or the like travels is determined in one direction (one-way) for each drift DR. That is, each drift DR can travel only in one direction.
- the traveling direction of the drift DRb included in the circuit CDa is a direction from the ore path OPb toward the ore path OPa. In this case, the transport machine 10 cannot travel on the drift DRb so as to go from the ore pass OPa to the ore pass OPb.
- the management device 3 prevents the transporting machine 10 from passing another transporting machine or the loading machine 30 in each drift DR. Is generated.
- the peripheral circuit CD that reversely travels the drift DR in which the traveling direction is determined as one direction as a result of being included in the already generated peripheral circuit CD. Cannot be generated.
- the management device 3 generates a new peripheral circuit CD using the drift DR included in the already generated peripheral circuit CD, the traveling direction of the new peripheral circuit CD is the already generated peripheral circuit CD. So as to coincide with the traveling direction of the drift DR included in. By doing in this way, the passing of the transport machine 10 in the peripheral circuit CD is reduced or avoided.
- drift DRs are connected to the outer track TRa provided with the ore pass OPa, and six drift DRs are also connected to the outer route TRb provided with the ore pass OPb. ing. In the direction in which the outer circumferential path TRa extends, the same number (three in this embodiment) of drift DRs are connected to the outer circumferential path TRa in any direction with respect to the ore path OPa. Similarly, in the direction in which the outer peripheral path TRb extends, the same number (three in this embodiment) of drift DRs are connected to the outer peripheral path TRb in any direction with respect to the OR path OPb.
- the peripheral circuit CD that includes both the ore pass OPa and the ore pass OPb has the following nine patterns.
- Pattern 1 Drift DRa, outer periphery TRa, drift DRf, outer periphery TRb
- Pattern 2 Drift DRa, outer periphery TRa, drift DRe, outer periphery TRb
- Pattern 3 Drift DRa, outer periphery TRa, drift DRd, outer periphery TRb
- Pattern 4 Drift DRb, outer periphery TRa, drift DRf, outer periphery TRb
- Pattern 5 Drift DRb, outer periphery TRa, drift DRe, outer periphery TRb
- Pattern 6 Drift DRb, outer periphery TRa, drift DRd, outer periphery TRb
- Pattern 7 Drift DRc, outer periphery TRa, drift DRf, outer
- the transporting machine 10 travels in one direction (for example, clockwise) through the peripheral circuit CD so that the passing of the transporting machine 10 can be minimized and the transporting machine 10
- the ore MR can be loaded and discharged twice during one round of the circuit CD.
- the position and the number of OR paths OP provided in the respective outer circumferential paths TR are not limited.
- the same number of drift DRs in the extending direction of the outer circumferential path TR with respect to the ore path OP. are preferably connected because the number of patterns of the peripheral circuit CD can be increased.
- the mine management system 1 separates the functions of the loading machine 30 and the transporting machine 10. For this reason, since the loading machine 30 can specialize in excavation and conveyance, and the conveyance machine 10 can specialize in conveyance of the ore MR, each capability can be exhibited to the maximum. As a result, the mine management system 1 can improve the productivity of the mine M. Next, processing for reversing the traveling direction of the transport machine 10 in the mine management system 1 will be described.
- FIG. 20 is a diagram for explaining a process of reversing the traveling direction of the transport machine 10 in the mine management system 1 according to the present embodiment.
- FIG. 21 is a conceptual diagram showing a peripheral circuit.
- the first distance of the transporting machine 10 operating in the underground MI when at least one of the loading machines 30 operating in the underground MI moves from the current draw point DP to another draw point DP, the first distance of the transporting machine 10 operating in the underground MI.
- the traveling direction of the transporting machine 10 is reversed.
- the first distance is a distance traveled by the transporting machine 10 operating in the mine MI with the ore MR loaded thereon.
- the second distance is a distance traveled in a state where the transporting machine 10 operating in the mine MI does not load the ore MR, that is, in an empty state.
- the first distance is appropriately referred to as a loading distance
- the second distance is appropriately referred to as an empty distance.
- the transporting machine 10 is excavated at the draw point DP, loads the loaded ore MR, transports it to the ore pass OP, and discharges it.
- the transporting machine 10 that has discharged the ore MR with the ore pass OP moves again to the draw point DP through the outer circumference TR and the drift DR, and receives the loading of the ore MR here. Therefore, the loading distance corresponds to the distance that the transporting machine 10 moves from the draw point DP to the ore pass OP, and the empty load distance corresponds to the distance that the transporting machine 10 moves from the ore pass OP to the draw point DP.
- the loading distance is a distance from the draw point DP to the ore pass OP along the drift DR and the outer circumference TR, and the empty distance is a distance from the ore pass OP to the draw point DP.
- the traveling device, the suspension device, and the vessel 11 of the transporting machine 10 are supported in order to support a larger load than when traveling without loading the load.
- the load received by the supporting mechanism or the like increases. As a result, the durability of these devices and mechanisms may be reduced.
- the transporting machine 10 operating in the underground mine MI travels in one direction on a circumferential circuit formed by the drift DR and the outer circumferential path TR. That is, the peripheral circuit is one-way, but the one-way direction can be changed.
- the traveling direction of the transporting machine 10 operating in the underground mine MI is reversed. Then, before the inversion, the distance from the draw point DP to the OR path OP was longer than the distance from the OR path OP to the draw point DP, but after the inversion, the former becomes shorter than the latter.
- the loading distance of the transporting machine 10 operating in the underground mine MI can be made shorter than the unloading distance. Therefore, the durability of the traveling device, the suspension device, the mechanism for supporting the vessel 11, etc. The decline in sex is suppressed. Moreover, since the distance which the conveyance machine 10 drive
- the process for reversing the traveling direction of the transporting machine 10 will be described in more detail.
- the underground mine MI includes a plurality (six in this example) of drifts DRa, DRb, DRc, DRd, DRe, and DRf, and a plurality (two in this example) of outer circumferential paths TRa and TRb. And have.
- the peripheral circuit CDI illustrated in FIG. 21 is formed by the two drifts DRc and DRd and the two outer peripheral paths TRa and TRb.
- the peripheral circuit CDI is appropriately referred to as a first peripheral circuit CDI.
- the peripheral circuit CDE shown in FIG. 21 is formed by the two drifts DRb and DRe and the two outer peripheral paths TRa and TRb.
- the peripheral circuit CDE is appropriately referred to as a second peripheral circuit CDE.
- a second peripheral circuit CDE In this embodiment, for the sake of convenience, an example in which the mine M has two of the first peripheral circuit CDI and the second peripheral circuit CDE will be described. However, the number of peripheral circuits CD that the mine M has is not limited to two. Absent.
- the pattern of the peripheral circuit CD may be, for example, the peripheral circuits CDa and CDb shown in FIG.
- the transporting machine 10 travels in one direction on the first circuit CDI and the second circuit CDE.
- the vehicle travels counterclockwise around a central portion (hereinafter, appropriately referred to as a pit central portion) CP when the drift DR, the cross cut CR, and the outer circumferential path TR are viewed from above.
- a pit central portion a central portion (hereinafter, appropriately referred to as a pit central portion) CP when the drift DR, the cross cut CR, and the outer circumferential path TR are viewed from above.
- the pit center portion CP is the center of gravity of the portion surrounded by the outermost drifts DRa and DRf and the outer periphery TRs and TRb connecting them.
- the centroid is the centroid.
- an ore pass OP is provided in the mine MI of the mine M.
- a plurality (two) of ore passes OPa and OPb are provided in the underground mine MI, but the number thereof is not limited and may be one.
- the transporting machine 10D that has reached the positions of the ore passes OPa and OPb discharges the loaded ore MR.
- the first peripheral circuit CDI and the second peripheral circuit CDE each have a common OR path OP on the way.
- the OR path OPa is provided in the outer circumferential path TRa that connects the drift DRc and the drift DRd of the first circuit CDI
- the OR path OPb is another outer circuit that connects the drift DRc and the drift DRd of the first circuit CDI.
- TRb The outer peripheral paths TRa and TRb connect the drift DRb and the drift DRe included in the second peripheral circuit CDE.
- the OR paths OPa and OPb are arranged between the drift DRc and the drift DRd of the first circuit CDI and between the drift DRb and the drift DRe of the second circuit CDE. With such an arrangement, the transporting machine 10 traveling on the first circuit CDI or the second circuit CDE can always reach the ore path OP. Even when the traveling direction of the transporting machine 10 is reversed, the transporting machine 10 traveling on the first circuit CDI or the second circuit CDE can always reach the ore path OP.
- the outermost drifts DRa and DRf do not form the peripheral circuit CD, but a peripheral circuit CD including these may be formed.
- the peripheral circuit CD is formed so as to include the OR path OP in the middle, and the OR path OP is provided between the two drifts DR as described above.
- one loading machine 30 is disposed in one drift DR.
- a loading machine 30b is disposed in the drift DRb
- a loading machine 30c is disposed in the drift DRc
- a loading machine 30d is disposed in the drift DRd
- a loading machine 30e is disposed in the drift DRe.
- the loading machine 30b is disposed in the cross cut CRb connected to the drift DRb.
- the loading machine 30c is disposed in a cross cut CRc connected to the drift DRc.
- the loading machine 30d is disposed in a cross cut CRd connected to the drift DRd.
- the loading machine 30e is disposed in a crosscut CRe connected to the drift DRe.
- the transporting machine 10 loads the ore MR from the loading machine 30b in the drift DRb, from the loading machine 30c in the drift DRc, from the loading machine 30d in the drift DRd, and from the loading machine 30e in the drift DRe.
- the transporting machine 10 travels the first circuit CDI and the second circuit CDE in one direction in either the first traveling direction RD1 or the second traveling direction RD2 shown in FIG.
- the first traveling direction RD1 is a direction that travels counterclockwise in the pit center portion CP when the first circumferential circuit CDI and the second circumferential circuit CDE are viewed from above.
- the second traveling direction RD2 is a direction in which the underground center portion CP travels clockwise when the first circumferential circuit CDI and the second circumferential circuit CDE are viewed from above.
- FIG. 22 is a flowchart illustrating a process of reversing the traveling direction of the transport machine 10 in the mine management system 1 according to the present embodiment.
- the management device 3 illustrated in FIG. 20 determines whether or not the loading machine 30 has moved.
- the loading machine 30 is dispatched to one of a plurality of draw points DP provided in the underground mine MI, for example, by a dispatching process described below.
- the management device 3 executes a dispatch process for the loading machine 30.
- the mine M shown in FIG. 1 where the ore MR is mined by the block caving method has a plurality of draw points DP in the mine MI.
- the ore MR is mined from the plurality of draw points DP in a well-balanced manner.
- the production plan of the mine M is planned so that the ore MR is mined in a well-balanced manner from the plurality of draw points DP of the mine M so that the ore MR is not mined from a specific draw point DP.
- the management device 3 moves the loading machine 30 to a plurality of draw points DP according to the production plan of the mine M, and mine the ore MR.
- ore clogging may occur at the draw point DP, or a large block of ore MR that cannot be excavated or conveyed by the loading machine 30 may appear at the draw point DP.
- the management apparatus 3 moves the loading machine 30 to the draw point DP where the ore clogging or the large block of the ore MR does not appear. For this reason, the management device 3 executes a vehicle allocation process for the loading machine 30.
- This dispatching process includes a first dispatching process and a second dispatching process.
- the draw point DP where the loading machine 30 is arranged is determined based on the difference between the production plan of the mine M and the actual production amount (mining amount).
- the management device 3 determines the draw point DP at which the loading machine 30 is disposed by executing either the first vehicle allocation process or the second vehicle allocation process.
- the management device 3 determines the priority of the draw point DP where the loading machine 30 is arranged, and the draw point DP in which the actual production amount of the draw point DP is determined by the production plan of the mine M.
- the draw point DP is smaller in order, and the difference between the production amount of the production plan of the mine M and the actual production amount is relatively large.
- the management apparatus 3 determines the draw point DP where the loading machine 30 is arrange
- the management device 3 determines the draw point DP where the loading machine 30 is arranged from the draw point DP connected to the same drift DR, and determines the production amount at the determined draw point DP, Adjustment is made based on the difference between the production amount determined by the production plan of the mine M, that is, the target production amount, and the actual production amount, that is, the actual production amount.
- the management device 3 sets the other draw point DP adjacent to the predetermined draw point DP, and the loading machine 30 is arranged next. Determined as the draw point DP. According to the second dispatching process, the moving amount of the loading machine 30 can be reduced.
- a plurality of loading machines 30 are operating in the underground mine MI.
- the management device 3 determines in step S101 the loading machine 30. It is determined that there is movement.
- the loading machine 30 is moved by the first dispatching process or the second dispatching process (step S101, Yes)
- the management device 3 advances the process to step S102.
- step S101, No the management device 3 ends the process.
- step S102 the management device 3 obtains the sum ⁇ Le of the unloading distance Le and the sum ⁇ Lf of the loading distance Lf for all the transporting machines 10 operating in the mine MI.
- the unloading distance Le and the loading distance Lf are obtained from, for example, the position of the draw point DP, the position of the ore pass OP, and the traveling direction of the transport machine 10.
- the unloading distance Le and the loading distance Lf for one transporting machine 10 are values when the transporting machine 10 makes one round of the circumferential circuit CD.
- the second circuit CDE shown in FIG. 21, specifically the outer periphery TRb, the drift DRe, and the outer periphery TRa. And through the drift DRb.
- the second circuit CDE there are two draw points DP where the loading machine 30 is arranged, specifically, a draw point DPb where the loading machine 30b is arranged and a draw point DPe where the loading machine 30e is arranged.
- the former is provided in the drift DRb, and the latter is provided in the drift DRe.
- the transporting machine 10S and the transporting machine 10F of the drift DRb and the drift DRc travel to the ore pass OPb through the drift DRb and the outer peripheral path TRb after the ore MR is loaded at the draw point DPb.
- the transport machine 10S and the transport machine 10F discharge the ore MR with the ore pass OPb, and then reach the next draw point DPe through the outer circumference TRb and the drift DRe in an empty state.
- the transporting machine 10S and the transporting machine 10F reach the ore pass OPa through the drift DRe and the outer circumferential path TRa.
- the loading distance Lf of the transport machine 10S and the transport machine 10F is the distance from the draw point DPb to the ore path OPb through the drift DRb and the outer path TRb, and the ore path OPa from the draw point DPe to the ore path OPa. It is the sum with the distance to reach.
- the unloading distance Le of the transport machine 10S and the transport machine 10F is the distance from the ore pass OPb to the draw point DPe through the outer periphery TRb and the drift DRe, and the ore pass OPa through the outer periphery TRa and the drift DRb. This is the sum of the distance to the draw point DPb.
- the empty distance Le is longer than the loading distance Lf.
- step S103 the management device 3 calculates the total ⁇ Lf of the loading distance Lf. And a sum ⁇ Le of the unloading distance Le is obtained, and the difference ⁇ L is compared with a predetermined specified value ⁇ Lc. As a result of the comparison, when the difference ⁇ L is greater than or equal to the predetermined specified value ⁇ Lc (step S103, Yes), the management device 3 advances the process to step S104. When the difference ⁇ L is less than the predetermined specified value ⁇ Lc (No at Step S103), the management device 3 ends the process.
- the specified value ⁇ Lc includes zero. In this case, if the sum ⁇ Lf of the loading distance Lf is equal to or greater than the sum ⁇ Le of the unloading distance Le, the process proceeds to step S104. If the sum ⁇ Lf of the loading distance Lf is less than the sum ⁇ Le of the unloading distance Le, Ends.
- the specified value ⁇ Lc may be set to 0, but in this case, when the loading distance Lf becomes larger than the unloading distance Le, the traveling direction of the transporting machine 10 is immediately reversed, and immediately after that, the loading distance Lf is unloaded. It may be larger than the distance Le. In this case, since the traveling direction is reversed again, if the specified value ⁇ Lc is set to 0, a phenomenon such as hunting in which the reversal of the traveling direction is repeated in a short cycle may occur. In order to avoid this, by providing the specified value ⁇ Lc, it is possible to avoid the phenomenon that the reversal of the traveling direction is repeated in a short cycle.
- step S104 the management device 3 determines whether or not the movement of the loading machine 30 is completed.
- the management device 3 waits until the movement of the loading machine 30 is completed at Step S105.
- the management device 3 instructs the reverse of the traveling direction of the transporting machine 10 to all the transporting machines 10 operating in the underground mine MI at Step S106. As a reverse command. That is, after the time when the loading machine 30 arrives at a different draw point DP, the management device 3 transmits a reversal command to the plurality of transporting machines 10 operating in the underground mine MI.
- the inversion command is transmitted from the wireless communication device 4 to the transport machine 10 via the antenna 4A.
- the transmitted inversion command is input to the processing device 71 via the antenna 15 and the communication device 25 of the transport machine 10 shown in FIG.
- the reversal command is also transmitted to the loading machine 30 operating in the underground mine MI.
- the inversion command transmitted from the wireless communication device 4 to the loading machine 30 via the antenna 4A is input to the processing device 76 via the antenna 53 and the communication device 52 of the loading machine 30 shown in FIG. May be.
- step S107 the management device 3 determines whether all the transporting machines 10 are in a standby state. For example, at the timing when the reversal command is transmitted from the management device 3, there is a transporting machine 10 that has been loaded with ore MR from the loading machine 30, or there is a transporting machine 10 that is discharging the ore MR with ore pass OP. Or exist. Even if such a transporting machine 10 receives the reversal command, it cannot immediately travel with the traveling direction reversed. Further, when the traveling direction is reversed, the transport machine 10 needs to reset the destination.
- the management device 3 sets the traveling direction of each transporting machine 10 to the reversal command after all the transporting machines 10 operating in the underground mine MI are ready to travel by reversing the traveling direction. Invert the vehicle before it is transmitted.
- the transporting machine 10 that has received the reversal command executes processing determined according to the current state after receiving the reversal command. This process will be described.
- the transporting machine 10 heading for the target loading machine 30 has no other transporting machine 10 at the position of the target loading machine 30 to which the transporting machine 10 is headed, or the other transporting machine 10 heading for the target loading machine 30 If not, the vehicle travels to the position of the target loading machine 30 and waits. If it does in this way, the conveyance machine 10 can start from loading of the ore MR, when a running direction is reversed.
- the transport machine 10E traveling on the drifts DRc and DRd has another transport machine 10 or the transport machine 10 toward the target load machines 30c and 30d at the position of the target load machines 30c and 30d. do not do.
- the transporting machine 10E that travels in the drifts DRc and DRd stops at the position of the loading machines 30c and 30d and waits until a command to start reverse traveling is issued from the management device 3.
- the transporting machine 10 transmits a signal indicating that it is in the standby state to the management device 3 (the same applies hereinafter).
- the loading machine 30 (Processing of the loading machine 30 after the transport machine 10 receives the reverse command) After the transporting machine 10 receives the reversal command, the loading machine 30 that loads the ore MR onto the transporting machine 10 continues until the work is completed. The loading machine 30 that has not loaded the ore MR into the transporting machine 10 stands by in a state as it is. When the transporting machine 10 arrives, the ore MR is loaded on the transporting machine 10.
- step S107 when all the transporting machines 10 are not in the standby state (No in step S107), in step S108, the management device 3 waits until the transporting machine 10 enters the standby state.
- the case where all the transporting machines 10 are not in the standby state is a state where at least one of the above-described processing 1 to processing 4 has not been completed.
- the case where all the transporting machines 10 enter the standby state is a state where all the executions of the processing 1 to the processing 4 described above are completed.
- step S109 the management device 3 transmits a command to start the reverse traveling to the transporting machine 10 on standby.
- the traveling direction of the transport machine 10 is reversed, the destination of the transport machine 10 is also different.
- the management device 3 generates a new destination for each transport machine 10 according to the current position of the transport machine 10, the travel direction after reversal, and the loaded state of the load, and commands to start reversal travel. At the same time, it is transmitted to each transporting machine 10.
- step S110 the transporting machine 10 that has received the instruction to start the reverse traveling and the new destination reverses the traveling direction before receiving the reverse instruction and starts traveling toward the new destination.
- all the transport machines 10 operating in the underground mine MI start the traveling by reversing the traveling directions after all of the processing 1 to the processing 4 determined according to the current state are executed.
- All the transporting machines 10 operating in the underground mine MI reverse the traveling direction before receiving the reversal command, so that the loading distance Lf before the reversal becomes the empty load distance Le after the reversal.
- the load distance Lf of all the transporting machines 10 is shorter than the empty load distance Le, so that a decrease in durability is suppressed.
- all the transporting machines 10 operating in the underground mine MI have their respective traveling directions regardless of whether or not the processing 1 to the processing 4 determined according to the current state is performed after receiving the reverse command. You may start traveling with the reverse. In this way, it is not necessary to wait until all of the processing 1 to the processing 4 are executed, so that the operation stoppage period of the transporting machine 10 can be shortened to prevent the productivity of the mine M from being lowered.
- the management device 3 transmits a new destination together with the reversal command after reversing the traveling direction. By doing in this way, the materials handling machine 10 can move toward a new destination immediately after receiving the reverse command.
- the transporting machine 10 When the traveling direction of the transporting machine 10 is reversed immediately after receiving the reversal command, the transporting machine 10 that is loading the ore MR and discharging the ore MR at the time of receiving the reversal command finishes the respective work. Then start reverse running. By doing in this way, it can avoid that the materials handling machine 10 starts moving during loading operation or discharge operation.
- the plurality of drifts DR extend in one direction and are arranged side by side, and each of the pair of outer circumferential paths TRa and TRb connecting the plurality of drifts DR at both ends has an OR path OPa. , OPb are provided.
- the same peripheral circuit CD is provided with two OR paths OPa and OPb.
- the plurality of loading machines 30 that operate in such a mine MI and are installed in the same peripheral circuit CD are installed in a region that is point-symmetric with respect to the mine center portion CP.
- a pair of OR paths OPa and OPb are connected, a straight line LL parallel to the drift DR and passing through the pit center portion CP, and intersecting the straight line LL.
- a straight line LR parallel to the path TR.
- the first quadrant ER1 and the third quadrant ER3 are areas that are point-symmetric.
- the second quadrant ER2 and the fourth quadrant ER4 are areas that are point-symmetric. is there.
- a loading machine 30b and a loading machine 30e are installed in a cross cut CRb of the drift DRb and a cross cut CRe of the drift DRe that is point-symmetric with this part.
- the loading machine 30b and the loading machine 30e are installed in the second circuit CDE shown in FIG.
- a loading machine 30c and a loading machine 30d are respectively installed in the cross cut CRc of the drift DRc and the cross cut CRd of the drift DRd that is point-symmetric with this portion.
- the loading machine 30c and the loading machine 30d are installed in the first circuit CDI shown in FIG.
- the distance between the loading machine 30b and the ore pass OPb is the same.
- the distance between the loading machine 30b and the ore path OPa is the same as the distance between the loading machine 30e and the ore path OPb.
- these loading machines 30b and 30e load the ore MR, and all the transporting machines 10 traveling on the second circuit CDE have the same loading distance Lf and the same unloading distance Le. Become.
- the transporting machine 10 that travels on the circumferential circuit CD that is installed in a region in which the plurality of loading machines 30 are point-symmetric with respect to the pit center portion CP has substantially the same loading distance Lf and an empty loading distance Le. Are almost the same.
- the loads on all the transporting machines 10 traveling on the above-described peripheral circuit CD are substantially equal.
- the load on the transporting machine 10 can be more effectively reduced by reversing the traveling direction of the loading machine 10.
- the direction in which one loading machine 30 moves to a different draw point DP, and the other The direction in which the loading machine 30 moves to a different draw point DP is preferably the opposite of that.
- one loading machine 30b installed in the second circumferential circuit CDE moves from the other outer circumferential path TRb toward one outer circumferential path TRa to a different draw point DP. That is, one loading machine 30b moves from the draw point DP provided on the other end side of the drift DR toward the draw point DP provided on the one end side.
- the other loading machine 30e installed at the position of the second circumferential circuit CDE that is point-symmetric with the loading machine 30b with respect to the pit center portion CP is changed from one outer circumferential path TRa to the other outer circumferential path TRb. Move to a different draw point DP. That is, the other loading machine 30e moves from the draw point DP on one end side of the drift DR toward the draw point DP on the other end side. By doing in this way, the loading machine 30b and the loading machine 30e installed in the area
- the distance between the two loading machines 30 is fixed so that the direction in which one loading machine 30 moves to a different draw point DP is opposite to the direction in which the other loading machine 30 moves to a different draw point DP. To be kept. For this reason, all the transporting machines 10 traveling on the circumferential circuit CD in which these loading machines 30 are installed have almost the same loading distance Lf and empty loading distance Le when the draw point DP of the loading machine 30 moves. It changes as well.
- the drift DRe on the left side of the pit center portion CP with respect to the direction from one outer circumferential path TRa to the other outer circumferential path TRb is one-way traveling from the other outer circumferential path TRb to one outer circumferential path TRa.
- the drift DRb on the right side is a one-way road from one outer circumferential path TRa to the other outer circumferential path TRb.
- the loading machine 30e sequentially moves toward the cross cut CR on the other outer circumferential path TRb, and the loading machine 30b moves toward the cross cut CR on the one outer circumferential path TRa. Move sequentially. Then, the load distance Lf is gradually increased, and the empty load distance Le is gradually decreased. The difference ⁇ L between the two gradually increases.
- ⁇ L becomes equal to or greater than the specified value ⁇ Lc
- the traveling direction of the transport machine 10 is reversed.
- the initial positions of the loading machines 30b and 30e are set on the front side in the traveling direction after the reversal.
- the difference ⁇ L between the loading distance Lf and the unloading distance Le of the transporting machine 10 traveling on the drifts DRb and DRe provided on both sides of the center portion CP of the mine due to the movement of the excavating machine accompanying the progress of the mining of the ore MR is the same. It becomes small by the tendency.
- the load distance Lf increases even after the load distance Lf and the empty load distance Le are reversed, the travel direction of the transporting machine 10 is reversed when the difference ⁇ L becomes equal to or greater than the specified value ⁇ Lc. In this way, the management device 3 suppresses the load distance Lf.
- the mine management system 1 arranges the loading machines 30e and 30b at target positions with respect to the center portion CP of the mine, and moves the former from one draw point DPa side to the other draw point DPb side. The latter is moved from the other draw point DPb side toward the one draw point DPa side.
- the loading machines 30b and 30e are disposed in the drift DR on both sides with respect to the straight line LL connecting the pair of OR paths OPa and OPb provided on both end sides of the plurality of drifts DR, and the straight line LL is used as a reference.
- the moving directions of the loading machines 30b and 30e are opposite on the one side and the other side.
- the straight line LL is parallel to the drift DR.
- the timing or frequency of moving the loading machines 30b, 30e, for example, to the adjacent draw point DP is adjusted by adjusting the state of dispatch of the transporting machine 10 and the speed of the feeders or rotating rollers of the loading machines 30b, 30e. Some adjustment is possible.
- the management device 3 executes the above-described adjustment to align the timings of moving the loading machines 30b and 30e to the adjacent draw point DP, and loads the loading machine at a target position with respect to the underground center portion CP.
- the loading machines 30b and 30e in which 30e and 30b are arranged are moved so that a pair of weights hung on both sides of the pulley move.
- the loading machine 30 may perform excavation using a bucket having a cutting edge, or may perform loading.
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Mining & Mineral Resources (AREA)
- Economics (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Remote Sensing (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Agronomy & Crop Science (AREA)
- Animal Husbandry (AREA)
- Marine Sciences & Fisheries (AREA)
- Quality & Reliability (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Educational Administration (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
鉱山の採掘システムは、鉱体の内部又は下方の周回路を一方向に走行し、かつ採掘場所で採掘された鉱石を積載して前記鉱体の内部に設置された排土場所まで運搬してから排出する運搬機械と、前記採掘場所で前記鉱石を掘削し、掘削した前記鉱石を搬送して、前記運搬機械に積み込む積込機械と、前記積込機械が異なる採掘場所へ移動することが決定した場合、前記周回路で稼働しているすべての前記運搬機械について、前記鉱石を積載して前記鉱石を積み込まれた位置から前記排土場所まで移動する第1距離の総和と、前記排土場所から前記鉱石が積み込まれる位置まで移動する第2距離の総和とを求め、前記第1距離の総和が前記第2距離の総和よりも大きい場合には、前記運搬機械の走行方向を反転させる管理装置と、を含む。
Description
本発明は、坑内採掘に用いられる鉱山の管理システムに関する。
鉱山における採掘方法として、地表から採掘する露天採掘と、地下から採掘する坑内採掘とが知られている。環境に対する負荷の低減及び鉱石の存在部位の深部化等により、近年においては、坑内採掘が採用されるケースが増えている。例えば、特許文献1には、鉱石をバケットで掘削する車両が坑道内に進入して鉱石を掘削した後、掘削した鉱石をバケットに保持した状態で坑道を移動する作業機械が記載されている。
鉱石を運搬する運搬機械が鉱石を積載した状態で走行する距離が長いと、運搬機械の耐久性の低下を招く可能性がある。これは、坑内採掘においても同様である。
本発明は、坑内採掘において、鉱石を運搬する運搬機械の耐久性の低下を抑制することを目的とする。
本発明は、鉱体の内部又は下方に設置された採掘場所と、前記鉱体の内部又は下方に設置された排土場所と、前記鉱体の内部又は下方に設置された複数の第1坑道、前記採掘場所と前記第1坑道とを接続する第2坑道及び複数の前記第1坑道と接続される第3坑道と、を含み、前記第3坑道と前記第1坑道とで周回路が形成される鉱山で前記鉱体から鉱石を採掘するにあたり、前記周回路を一方向に走行し、かつ前記採掘場所で採掘された前記鉱石を積載して前記排土場所まで運搬してから排出する運搬機械と、前記採掘場所で前記鉱石を掘削し、掘削した前記鉱石を前記運搬機械に積み込む積込機械と、前記積込機械が異なる採掘場所へ移動することが決定した場合、前記周回路で稼働しているすべての前記運搬機械について、前記鉱石を積み込まれた位置から前記排土場所まで移動する第1距離の総和と、前記排土場所から前記鉱石が積み込まれる位置まで移動する第2距離の総和とを求め、前記第1距離の総和と前記第2距離の総和との差分が予め定められた規定値以上である場合には、前記運搬機械の走行方向を反転させる管理装置と、を含む、鉱山の管理システムである。
前記管理装置は、前記積込機械が前記異なる採掘場所に到着した時点以降に、複数の前記運搬機械に対して、走行方向を反転させる指令を送信することが好ましい。
複数の前記運搬機械は、前記走行方向を反転させる指令を受信した後に、現在の状態に応じて定められた処理を実行し、すべての前記運搬機械が前記処理を実行した後に、それぞれの走行方向を反転して走行を開始することが好ましい。
複数の前記運搬機械は、前記走行方向を反転させる指令を受信した後に、それぞれの走行方向を反転して走行を開始することが好ましい。
前記鉱山は、前記排土場所を複数備えることが好ましい。
複数の前記第1坑道は、一方向に向かって延在し、かつ並んで配列され、前記積込機械は、それぞれの前記第1坑道に対して1台ずつ、かつ複数の前記第1坑道、前記第2坑道及び前記第3坑道を上方から見たときの中心部に対して点対称となるように設置されることが好ましい。
点対称となるように設置された一方の前記積込機械は、前記第1坑道の一方の端部側の採掘場所から他方側の端部側の採掘場所に向かって移動し、他方の前記積込機械は、前記第1坑道の他方の端部側の採掘場所から一方の端部側の採掘場所に向かって移動することが好ましい。
一対の前記排土場所が、複数の前記第1坑道の両方の端部側に設けられ、一対の前記排土場所を結ぶ直線に対して両側の前記第1坑道にそれぞれ前記積込機械が配置され、かつ前記直線を基準とした一方側と他方側とでそれぞれの前記積込機械の移動方向が反対になることが好ましい。
本発明は、鉱体の内部又は下方に設置された採掘場所と、前記鉱体の内部又は下方に設置された複数の排土場所と、前記鉱体の内部又は下方に設置された複数の第1坑道、前記採掘場所と前記第1坑道とを接続する第2坑道及び複数の前記第1坑道と接続される第3坑道と、を含み、前記第3坑道と前記第1坑道とで周回路が形成される鉱山で前記鉱体から鉱石を採掘するにあたり、前記周回路を一方向に走行し、かつ前記採掘場所で採掘された前記鉱石を積載して前記排土場所まで運搬してから排出する運搬機械と、前記第2坑道に留まって、前記採掘場所で前記鉱石を掘削し、掘削した前記鉱石を前記採掘場所から離れる方向に搬送して、前記運搬機械に積み込む積込機械と、前記積込機械が異なる採掘場所へ移動することが決定した場合、前記周回路で稼働しているすべての前記運搬機械について、前記鉱石を積み込まれた位置から前記排土場所まで移動する第1距離の総和と、前記排土場所から前記鉱石が積み込まれる位置まで移動する第2距離の総和とを求め、前記第1距離の総和と前記第2距離の総和との差分が予め定められた規定値以上である場合には、前記積込機械が前記異なる採掘場所に到着した時点以降に、複数の前記運搬機械に対して、走行方向を反転させる指令を送信する管理装置と、を含み、複数の前記運搬機械は、前記走行方向を反転させる指令を受信した以降に、それぞれの走行方向を反転して走行を開始する、鉱山の管理システムである。
本発明は、坑内採掘において、鉱石を運搬する運搬機械の耐久性の低下を抑制することができる。
本発明を実施するための形態(実施形態)について、図面を参照しつつ詳細に説明する。以下においては、所定面内の一方向をX軸方向、所定面内においてX軸方向と直交する方向をY軸方向、X軸方向及びY軸方向のそれぞれと直交する方向をZ軸方向として、各部の位置関係を説明する。また、重力の作用方向を下方、重力の作用方向とは反対方向を上方という。鉱山の生産性は、単位時間あたりの採掘量(t/h)と単位時間量あたりのコスト($/h)との両方を含む。鉱山の生産性は、式(1)に示すように、両者の商を指標とすることができる。式(1)中の$/tは生産性を表す指標、tは採掘量、hは時間、$はコストである。式(1)で表される指標$/tが小さいほど、鉱山の生産性は高いことになる。
$/t=($/h)/(t/h)・・(1)
$/t=($/h)/(t/h)・・(1)
<採掘現場の概要>
図1は、本実施形態に係る運搬機械10及び積込機械30が稼働する現場の一例を示す模式図である。運搬機械10及び積込機械30は、地下から鉱石を採掘する坑内採掘に使用される。運搬機械10は、坑道Rにおいて積荷を運搬する作業機械の一種であり、積込機械30は、運搬機械10に積荷を積み込む作業機械の一種である。本実施形態においては、ブロックケービング工法により鉱石が採掘される。
図1は、本実施形態に係る運搬機械10及び積込機械30が稼働する現場の一例を示す模式図である。運搬機械10及び積込機械30は、地下から鉱石を採掘する坑内採掘に使用される。運搬機械10は、坑道Rにおいて積荷を運搬する作業機械の一種であり、積込機械30は、運搬機械10に積荷を積み込む作業機械の一種である。本実施形態においては、ブロックケービング工法により鉱石が採掘される。
ブロックケービング工法とは、鉱山Mの鉱体(鉱脈)MGに鉱石MRの採掘場所(以下、適宜ドローポイントという)DPと、採掘された鉱石を搬送するための坑道Rとを設置し、そのドローポイントDPの上部をアンダーカットして発破し、鉱石MRを自然崩落させることによって、そのドローポイントDPから鉱石MRを採掘する工法をいう。ドローポイントDPは、鉱体MGの内部又は鉱体MGの下方Dに設置される。ブロックケービング工法は、岩盤又は鉱体の下部をアンダーカットすると、脆弱な岩が自然崩壊を始める性質を利用した工法である。鉱体MGの内部又は下方Dから鉱石MRが採掘されると、崩落が上部まで伝播する。このため、ブロックケービング工法を用いると、鉱体MGの鉱石MRを効率よく採掘することができる。ブロックケービング工法において、通常、ドローポイントDPは複数設けられる。
本実施形態においては、地上に管理装置3が配置される。管理装置3は、地上の管理施設内に設置される。管理装置3は、原則として移動を考慮していないものである。管理装置3は、採掘現場を管理する。管理装置3は、無線通信装置4及びアンテナ4Aを備える通信システムを介して、運搬機械10及び積込機械30を含む坑内の作業機械と通信可能である。本実施形態において、運搬機械10及び積込機械30は、無人で稼働する作業機械であるが、オペレーターの操作により稼働する有人の作業機械であってもよい。
<坑内MIについて>
図2は、坑内MIの一例及び鉱山の管理システムを示す模式図である。図3は、図2の一部を拡大した図である。これらの図に示すように、鉱体MGの下方Dに設置された坑道Rは、第1坑道DRと、第2坑道CRとを含む。坑道Rは、例えば、鉱体MGの内部又は鉱体MGの下方Dに設置される。本実施形態において、坑内MIには、第1坑道DR及び第2坑道CRは、それぞれ複数存在する。第2坑道CRは、それぞれのドローポイントDPと第1坑道DRとを接続する。積込機械30は、第2坑道CRを通ってドローポイントDPに接近することができる。本実施形態において、坑道Rは第3坑道TRを含む。本実施形態において、複数(この例では2本)の第3坑道TRが、複数の第1坑道DRと接続されている。以下において、第1坑道DRを適宜ドリフトDRといい、第2坑道CRを適宜クロスカットCRといい、第3坑道TRを適宜外周路TRという。
図2は、坑内MIの一例及び鉱山の管理システムを示す模式図である。図3は、図2の一部を拡大した図である。これらの図に示すように、鉱体MGの下方Dに設置された坑道Rは、第1坑道DRと、第2坑道CRとを含む。坑道Rは、例えば、鉱体MGの内部又は鉱体MGの下方Dに設置される。本実施形態において、坑内MIには、第1坑道DR及び第2坑道CRは、それぞれ複数存在する。第2坑道CRは、それぞれのドローポイントDPと第1坑道DRとを接続する。積込機械30は、第2坑道CRを通ってドローポイントDPに接近することができる。本実施形態において、坑道Rは第3坑道TRを含む。本実施形態において、複数(この例では2本)の第3坑道TRが、複数の第1坑道DRと接続されている。以下において、第1坑道DRを適宜ドリフトDRといい、第2坑道CRを適宜クロスカットCRといい、第3坑道TRを適宜外周路TRという。
図2に示すように、坑内MIには、2本の外周路TRが設置されている。それぞれの外周路TRは、クロスカットCRのようにはドローポイントDPによって分断されていない。1本の外周路TRは、複数のドリフトDRのそれぞれの一端部を接続し、もう1本の外周路TRは、複数のドリフトDRのそれぞれの他端部を接続する。このように、すべてのドリフトDRは、2本の外周路TRと接続されている。本実施形態においては、運搬機械10及び積込機械30は、いずれのドリフトDRであっても一方の外周路TRから進入することができる。図3に示す例において、運搬機械10及び積込機械30は、ドリフトDR内を矢印FCの方向に進行する。
図2及び図3に示すように、運搬機械10に対する積込機械30による積込作業が行われる積込位置LPは、クロスカットCR又はその近傍に定められる。ドローポイントDP及び積込位置LPを含む領域を、積込場所LA、と称してもよい。
図2に示すように、坑内MIには、運搬機械10によって運搬された積荷としての鉱石MRが排出される排土場所(オアパス)OPが設けられる。運搬機械10は、ドローポイントDP近傍の積込場所LAにおいて積込機械30により積荷としての鉱石MRを積み込まれた後、ドリフトDRを走行して、オアパスOPまで移動する。運搬機械10は、到着したオアパスOPに積荷としての鉱石MRを排出する。
本実施形態において、図2及び図3に示す運搬機械10は、走行用の電動機と、この電動機に電力を供給する蓄電器とを有する。外周路TRには、空間SPが接続されている。外周路TRと接続する空間SPには、運搬機械10に搭載された蓄電器を交換する蓄電器取扱装置EXが設置される。
以下の説明においては、便宜上、運搬機械10が走行する坑道Rの路面とXY平面とが実質的に平行であることとする。なお、実際には、坑道Rの路面は、凹凸を有していたり、上り坂及び下り坂を有していたりする場合が多い。
図2に示す鉱山の管理システム1は、管理装置3と、無線通信用のアンテナ4Aとを含む。管理装置3は、例えば、坑内MIで稼働する運搬機械10及び積込機械30の運行を管理する。運行の管理には、運搬機械10及び積込機械30の配車、運搬機械10及び積込機械30の稼働状態に関する情報(以下、適宜稼働情報という)の収集及びその管理等が含まれる。稼働情報は、例えば、運搬機械10及び積込機械30の稼働時間、走行距離、走行速度、蓄電器の残量、異常の有無、異常の箇所、積載量等が含まれる。稼働情報は、主として運搬機械10及び積込機械30の運転評価、予防保全及び異常診断等に用いられる。したがって、稼働情報は、鉱山Mの生産性向上又は鉱山Mのオペレーションの改善といったニーズに応えるために有用である。
管理装置3は、後述するように通信装置を備えている。アンテナ4Aを備えた無線通信装置4は、この通信装置と接続されている。管理装置3は、例えば、通信装置、無線通信装置4及びアンテナ4Aを介して、坑内MIで稼働する運搬機械10及び積込機械30との間で情報をやり取りする。鉱山の管理システム1が備える管理装置3は、前述したように運搬機械10及び積込機械30の運行を管理する。
本実施形態において、積込機械30は、走行用の電動機によって走行し、電動機によって掻き込み装置を駆動して鉱石MRを掘削する。図3に示すように、これらの電動機に積込機械30の外部から電力を供給する給電ケーブル5が坑内MIの坑道Rに設けられている。積込機械30は、例えば、積込場所LAに設けられた電力供給装置としての給電用のコネクタ6及び積込機械30からの電力ケーブル7を介して、給電ケーブル5からの電力の供給を受ける。前述した電力供給装置は、ドリフトDR又はクロスカットCRのいずれか一方に設けられていればよい。本実施形態において、積込機械30は、外部から供給される電力によって走行及び掘削の少なくとも一方を行ってもよい。また、積込機械30は、蓄電器を搭載し、この蓄電器から電力の供給を受けて走行及び掘削の少なくとも一方を行ってもよい。また、積込機械30は、蓄電器を搭載し、この蓄電器から電力の供給を受けて走行及び掘削の少なくとも一方を行ってもよい。すなわち、積込機械30は、外部から供給される電力及び蓄電器から供給される電力の少なくとも一方によって、走行及び掘削の少なくとも一方を行う。例えば、積込機械30は、外部から供給される電力によって掘削を行い、蓄電器から供給される電力によって走行することができる。また、積込機械30は、クロスカットCR内を走行する場合は、外部から供給される電力により走行してもよい。本実施形態において、積込機械30は、電動機によって油圧ポンプを駆動して油圧を発生させ、この油圧によって油圧モータを駆動することにより、鉱石MRを掘削してもよい。また、積込機械30は、蓄電器を備え、この蓄電器から供給される電力により走行し、掘削してもよい。
給電ケーブル5と積込機械30からの電力ケーブル7との接続は、コネクタ6に限定されるものではない。例えば、坑道R側に設けられ、かつ給電ケーブル5と接続された電極と、積込機械30側からの電力ケーブル7に接続された電極とを電力供給装置として用い、両方の電極を接触させて、給電ケーブル5から積込機械30に電力を供給してもよい。このようにすると、両方の電極の位置決め精度が低くても両者を接触させて電力を積込機械30に供給することができる。本実施形態では、積込機械30は電力で動作するものとしたが、このようなものには限定されない。積込機械30は、例えば、内燃機関によって走行したり鉱石MRを掘削したりするものであってもよい。この場合、積込機械30は、内燃機関によって油圧ポンプを駆動し、油圧ポンプから吐出される作動油によって、例えば、油圧モータ又は油圧シリンダ等を駆動することにより走行したり、鉱石MRを掘削したりしてもよい。
<鉱石MRの掘削及び運搬>
図4及び図5は、積込機械30による地山RMの鉱石MRの掘削及び運搬機械10への鉱石MRの積込を示す図である。積込場所LAは、ドローポイントDPに鉱石MRの地山RMが形成される。図4及び図5に示すように、積込機械30は、積込場所LAのクロスカットCR内に設置されて、先端部が鉱石MRの地山RMに貫入してこれを掘削する。積込機械30は、掘削した鉱石MRを、地山RMとは反対側であって、ドリフトDR内に待機している運搬機械10に積載する。ドリフトDR内には、積込機械30に電力を供給する給電ケーブル5が設けられている。
図4及び図5は、積込機械30による地山RMの鉱石MRの掘削及び運搬機械10への鉱石MRの積込を示す図である。積込場所LAは、ドローポイントDPに鉱石MRの地山RMが形成される。図4及び図5に示すように、積込機械30は、積込場所LAのクロスカットCR内に設置されて、先端部が鉱石MRの地山RMに貫入してこれを掘削する。積込機械30は、掘削した鉱石MRを、地山RMとは反対側であって、ドリフトDR内に待機している運搬機械10に積載する。ドリフトDR内には、積込機械30に電力を供給する給電ケーブル5が設けられている。
図4及び図5に示すように、積込機械30は、車体30Bと、搬送装置としてのフィーダー31と、掘削装置としての回転ローラー33と、回転ローラー33を支持する支持機構32と、走行装置34とを含む。回転ローラー33と支持機構32とは、鉱石MRを掘削してフィーダー31に送り込む掻き込み装置として機能する。
支持機構32は、車体30Bに取り付けられる第1部材としてのブーム32aと、これに連結されて揺動し、かつ回転ローラー33を回転可能に支持する第2部材としてのアーム32bとを有する。積込機械30の車体30Bは、鉱石MRの地山RMに貫入する貫入部材35と、回転体36と、岩石ガード37とを備える。貫入部材35は、鉱石MRの掘削時に地山RMに貫入する。回転体36は、積込機械30の貫入部材35が地山RMに貫入するときに回転して、貫入を補助する。
運搬機械10は、車体10Bと、ベッセル11とを含む。ベッセル11は、車体10Bに搭載される。ベッセル11は、鉱石MRを積荷として積載する。本実施形態において、ベッセル11は、図4及び図5に示すように、車体10Bの幅方向W、すなわち車軸と平行な方向に移動する。ベッセル11は、運搬機械10の走行時には車体10Bの幅方向中央に設置される。また、ベッセル11は、鉱石MRの積載時において、車体10Bの幅方向外側に移動する。その結果、運搬機械10は、ベッセル11を積込機械30のフィーダー31の下方Dに接近させることができるので、フィーダー31によって搬送された鉱石MRがベッセル11外に落下する可能性を低減し、鉱石MRをベッセル11内に確実に落下させることができる。
本実施形態では、図4及び図5に示すように、積込機械30は鉱石MRの掘削及び掘削した鉱石MRを運搬機械10に搬送しこれに積載する。運搬機械10は、積載された鉱石MRを、図2に示すオアパスOPまで運搬し、ここに排出する。このとき、積込機械30は、運搬機械10が走行する空間をドリフトDR内に残した状態でクロスカットCRに留まって、ドローポイントDPで鉱石MRを掘削する。そして、積込機械30は、掘削した鉱石MRをドローポイントDPから離れる方向に搬送して、運搬機械10に積み込む。積込機械30は、掘削した鉱石MRを積載した状態では移動しない。運搬機械10は、ドローポイントDPで採掘された鉱石MRを積載し、ドリフトDRを走行して図2に示すオアパスOPまで運搬する。
このように、本実施形態において、鉱山の管理システム1は、積込機械30には鉱石MRの掘削及び積込のみを行わせ、運搬機械10には鉱石MRの運搬のみを行わせるようにして、両者の機能を分離している。このため、積込機械30は掘削作業及び搬送作業に専念でき、運搬機械10は運搬作業に専念できる。すなわち、積込機械30は鉱石MRを運搬する機能を有していなくてもよく、運搬機械10は鉱石MRの掘削及び搬送する機能を有していなくてもよい。積込機械30は、掘削及び搬送の機能に特化でき、運搬機械10は鉱石MRの運搬の機能に特化できるので、それぞれの機能を最大限発揮させることができる。結果として、鉱山の管理システム1は、鉱山Mの生産性を向上させることができる。
<鉱山の管理システム1の管理装置3>
図6は、鉱山の管理システム1が備える管理装置3の機能ブロック図の一例である。管理装置3は、処理装置3Cと、記憶装置3Mと、入出力部(I/O)3IOとを含む。さらに、管理装置3は、入出力部3IOに、出力装置としての表示装置8と、入力装置9と、通信装置3Rとが接続されている。管理装置3は、例えば、コンピュータである。処理装置3Cは、例えば、CPU(Central Processing Unit)である。記憶装置3Mは、例えば、RAM(Random Access Memory)、ROM(Read Only Memory)、フラッシュメモリ若しくはハードディスクドライブ等又はこれらを組み合わせたものである。入出力部3IOは、処理装置3Cと、処理装置3Cの外部に接続する表示装置8、入力装置9及び通信装置3Rとの情報の入出力(インターフェース)に用いられる。
図6は、鉱山の管理システム1が備える管理装置3の機能ブロック図の一例である。管理装置3は、処理装置3Cと、記憶装置3Mと、入出力部(I/O)3IOとを含む。さらに、管理装置3は、入出力部3IOに、出力装置としての表示装置8と、入力装置9と、通信装置3Rとが接続されている。管理装置3は、例えば、コンピュータである。処理装置3Cは、例えば、CPU(Central Processing Unit)である。記憶装置3Mは、例えば、RAM(Random Access Memory)、ROM(Read Only Memory)、フラッシュメモリ若しくはハードディスクドライブ等又はこれらを組み合わせたものである。入出力部3IOは、処理装置3Cと、処理装置3Cの外部に接続する表示装置8、入力装置9及び通信装置3Rとの情報の入出力(インターフェース)に用いられる。
処理装置3Cは、運搬機械10及び積込機械30の配車並びにこれらの稼働情報の収集等といった管理装置3の処理を実行する。配車及び稼働情報の収集等の処理は、処理装置3Cがそれぞれに対応するコンピュータプログラムを記憶装置3Mから読み込んで実行することにより実現される。
記憶装置3Mは、処理装置3Cに各種の処理を実行させるための各種のコンピュータプログラムを記憶している。本実施形態において、記憶装置3Mが記憶しているコンピュータプログラムは、例えば、運搬機械10及び積込機械30の配車をするためのコンピュータプログラム、運搬機械10及び積込機械30の稼働情報を収集するためのコンピュータプログラム、稼働情報等に基づいて各種解析を実現するコンピュータプログラム等である。
表示装置8は、例えば、液晶ディスプレイ等であり、運搬機械10及び積込機械30の配車をしたり、稼働情報を収集したりする際に必要な情報を表示する。入力装置9は、例えば、キーボード、タッチパネル又はマウス等であり、運搬機械10及び積込機械30の配車をしたり、これらの稼働情報を収集したりする際に必要な情報を入力する。通信装置3Rは、アンテナ4Aを備えた無線通信装置4と接続されている。前述したように、無線通信装置4及びアンテナ4Aは坑内MIに設置される。通信装置3Rと無線通信装置4とは有線で接続される。通信装置3Rと坑内MIの運搬機械10及び積込機械30とは、例えば、無線LAN(Local Aria Network)によって通信することができる。次に、運搬機械10について、より詳細に説明する。
<運搬機械10>
図7は、本実施形態に係る運搬機械10の斜視図である。図8は、本実施形態に係る運搬機械10の側面図である。運搬機械10は、車体10Bと、ベッセル11と、車輪12A、12Bとを含む。さらに、運搬機械10は、蓄電器としての蓄電器14と、アンテナ15と、撮像装置16A、16Bと、非接触センサ17A、17Bとを有している。車輪12A、12Bは、車体10Bの前後にそれぞれ取り付けられる。本実施形態において、車輪12A、12Bは、図8に示す、車体10B内に搭載された電動機13A、13Bによって駆動される。このように、運搬機械10は、すべての車輪12A、12Bが駆動輪となる。また、本実施形態において、車輪12A、12Bは、それぞれ操舵輪となる。本実施形態において、車輪12A、12Bは、例えば、ソリッドタイヤである。このようにすることで、車輪12A、12Bが小径となるので、運搬機械10の高さが抑制される。運搬機械10は、車輪12Aから車輪12Bの方向及び車輪12Bから車輪12Aの方向のいずれにも走行することができる。車輪12A、12Bは、ソリッドタイヤに限定されるものではなく、例えば、空気入りタイヤ等であってもよい。また、車輪12A、12Bのうち、一方のみが駆動輪であってもよい。
図7は、本実施形態に係る運搬機械10の斜視図である。図8は、本実施形態に係る運搬機械10の側面図である。運搬機械10は、車体10Bと、ベッセル11と、車輪12A、12Bとを含む。さらに、運搬機械10は、蓄電器としての蓄電器14と、アンテナ15と、撮像装置16A、16Bと、非接触センサ17A、17Bとを有している。車輪12A、12Bは、車体10Bの前後にそれぞれ取り付けられる。本実施形態において、車輪12A、12Bは、図8に示す、車体10B内に搭載された電動機13A、13Bによって駆動される。このように、運搬機械10は、すべての車輪12A、12Bが駆動輪となる。また、本実施形態において、車輪12A、12Bは、それぞれ操舵輪となる。本実施形態において、車輪12A、12Bは、例えば、ソリッドタイヤである。このようにすることで、車輪12A、12Bが小径となるので、運搬機械10の高さが抑制される。運搬機械10は、車輪12Aから車輪12Bの方向及び車輪12Bから車輪12Aの方向のいずれにも走行することができる。車輪12A、12Bは、ソリッドタイヤに限定されるものではなく、例えば、空気入りタイヤ等であってもよい。また、車輪12A、12Bのうち、一方のみが駆動輪であってもよい。
なお、車輪12A及び車輪12Bの両方が操舵輪として機能可能な場合において、車輪12Aが前輪で車輪12Bが後輪となるように運搬機械10が進行する場合、車輪12A(前輪)だけが操舵され車輪12B(後輪)は操舵されなくてもよいし、車輪12B(後輪)だけが操舵され車輪12A(前輪)は操舵されなくてもよいし、車輪12A(前輪)及び車輪12B(後輪)の両方が操舵されてもよい。車輪12A及び車輪12Bの両方が操舵される場合、車輪12Aと車輪12Bとが同位相方向に操舵されてもよいし、車輪12Aと車輪12Bとが逆位相方向に操舵されてもよい。車輪12Aと車輪12Bとが同位相方向に操舵されることにより、例えば高速旋回時において安定して走行することができる。車輪12Aと車輪12Bとが逆位相方向に操舵されることにより、旋回半径を小さくすることができる。車輪12Bが前輪で車輪12Aが後輪となるように運搬機械10が進行する場合も同様である。
ベッセル11は、車体10Bの上方に搭載されて、車体10Bに支持される。車体10Bには、電動機13A、13Bに電力を供給するための蓄電器14が搭載される。本実施形態において、蓄電器14の外形は、直方体状である。蓄電器14は、車体10Bの前後にそれぞれ1個ずつ搭載される。このようにすることで、運搬機械10は、前後の質量のバランスが均等に近くなるので、安定して走行することができる。蓄電器14は、車体10Bに対して着脱可能に搭載される。蓄電器14から供給される電力によって、運搬機械10が有する電動機13A、13B及び電子機器が作動する。本実施形態においては、運搬機械10は電動としているが、内燃機関が動力源であってもよい。
車体10Bには、アンテナ15と、撮像装置16A、16Bと、非接触センサ17A、17Bとが取り付けられる。アンテナ15は、図6に示すアンテナ4A及び通信装置3Rを介して、管理装置3と無線通信する。撮像装置16A、16Bは、ベッセル11に積載された積荷、本実施形態では図3及び図4等に示す鉱石MRの状態(荷姿)を撮影する。撮像装置16A、16Bは、例えば、可視光を撮像するカメラであってもよいし、赤外線を撮像する赤外線カメラであってもよい。撮像装置16A、16Bは、それぞれ車体10Bの上面に取り付けられた支持柱16AS、16BSの先端に取り付けられる。このような構造により、それぞれの撮像装置16A、16Bは、ベッセル11の全体を上方から撮像することができるので、ベッセル11に積載された鉱石MRの状態を確実に撮像することができる。
非接触センサ17A、17Bは、車体10Bの前後にそれぞれ取り付けられる。非接触センサ17A、17Bは、運搬機械10の周囲、特に進行方向側に存在する物体を非接触で検出する。非接触センサ17A、17Bは、例えば、レーダー装置が用いられる。非接触センサ17A、17Bは、電波又は超音波等を発射して、物体で反射した電波を受信して、物体との相対的な距離及び方位を検出可能である。非接触センサ17A、17Bは、レーダー装置に限定されるものではない。非接触センサ17A、17Bは、例えば、レーザスキャナー、及び3次元距離センサの少なくとも1つを含んでもよい。
運搬機械10は、車体10Bの前後に、それぞれ撮像装置としての周辺監視カメラ17CA、17CBを備えている。周辺監視カメラ17CA、17CBは、車体10Bの周囲、特に前方を撮像して、車体10Bの周囲に存在する物体の形状を検出する。
車体10Bは、前後の間に凹部10BUを有している。凹部10BUは、車輪12Aと車輪12Bとの間に配置される。ベッセル11は、積込機械30によって積荷としての鉱石MRが積み込まれる部材である。ベッセル11の少なくとも一部は、凹部10BUに配置される。
本実施形態において、車体10Bの前後方向において車体10Bの中心部AXの一方側に配置される車体10Bの一部分と他方側に配置される車体10Bの一部分とは対称(前後対称)である。また、車体10Bの前後方向において車体10Bの中心部AXの一方側に配置されるベッセル11の一部分と他方側に配置されるベッセル11の一部分とは対称(前後対象)である。また、車体10B及びベッセル11は、平面視において、車体10Bの前後方向の中心軸に対して対称(左右対称)である。
ベッセル11は、底面11Bと、底面11Bと接続する4個の側面11SF、11SR、11SA、11SBとを含む。側面11SA、11SBは、底面11Bから垂直に立ち上がっている。側面11SF、11SRは、底面11Bに対してそれぞれ車輪12A、12B側に傾斜している。底面11Bと、4個の側面11SF、11SR、11SA、11SBとによって凹部11Uが形成される。凹部11Uには、積荷としての鉱石MRが積載される。車体10Bの凹部10BUは、ベッセル11の外形に沿った形状を有する。次に、ベッセル11の支持構造について説明する。
図9は、本実施形態に係る運搬機械10が備えるベッセル11の支持構造を示す図である。図10は、本実施形態に係る運搬機械10の上面図である。図11は、本実施形態に係る運搬機械10がベッセル11を傾斜させた状態を示す図である。ベッセル11は、テーブル11Tの上面に、ベッセル11を昇降させるアクチュエータとしての油圧シリンダ(ホイストシリンダ)11Cbを介して載置されている。
テーブル11Tは、車体10Bの凹部10BUの上面に設けられた一対の支持体11R、11Rを介して車体10Bに支持されている。支持体11Rは、車体10Bの幅方向に延在する棒状の部材である。それぞれの支持体11R、11Rは、テーブル11Tの車体10Bと対向する部分に設けられた一対の溝11TU、11TUに嵌め合わされている。溝11TU、11TUは、支持体11Rが延在する方向、すなわち、車体10Bの幅方向に向かって設けられている。このような構造により、テーブル11Tは、支持体11R、11Rに沿って移動する。すなわち、テーブル11Tは、運搬機械10の車体10Bの幅方向に向かって移動することができる。
テーブル11Tと車体10Bとの間には、テーブル11Tを車体10Bの幅方向に移動させるためのアクチュエータとして、油圧シリンダ(スライド用シリンダ)11Caが取り付けられている。油圧シリンダ11Caが伸縮することにより、テーブル11Tは、車体10Bの幅方向の両側に移動する。テーブル11Tにはベッセル11が取り付けられているので、図10に示すように、ベッセル11も、テーブル11Tとともに車体10Bの幅方向Wの両側に移動することができる。
積込機械30から鉱石MRがベッセル11に積載されるときには、図5に示すように、ベッセル11が積込機械30側に移動する。このようにすることで、運搬機械10は、鉱石MRを確実にベッセル11に積載することができる。また、ベッセル11の一方に鉱石MRが偏って積載された場合、運搬機械10は、ベッセル11を車体10Bの幅方向に往復運動させることにより、鉱石MRをベッセル11の全体に分散させ、鉱石MRの偏りを抑制することができる。
ベッセル11は、油圧シリンダ11Cbが伸縮することにより昇降する。図11は、油圧シリンダ11Cbが伸びてベッセル11が傾いた状態を示している。ベッセル11は、図11に示すように、車体10Bの幅方向Wの一方側の軸線Zbを中心として揺動する。軸線Zbは、テーブル11Tに含まれており、かつ車体10Bの前後方向と平行である。油圧シリンダ11Cbが伸びると、ベッセル11は、軸線Zbとは反対側が高くなり、車体10Bの凹部10BUから突出する。その結果、ベッセル11が傾斜し、軸線Zb側の蓋11CVが開いて、軸線Zb側から鉱石MRが排出される。油圧シリンダ11Cbが縮むと、ベッセル11は車体10Bの凹部10BUに収まる。蓋11CVは、図示しないリンク機構により、ベッセル11が昇降する動作に連動する。
本実施形態では、ベッセル11は車体10Bの幅方向Wの一方側に存在する軸線Zbのみを中心として揺動するが、これに限定されない。例えば、ベッセル11は、車体10Bの一方側の軸線Zbに加え、他方側に存在し、かつ車体10Bの前後方向と平行なもう1つの軸線を中心として揺動してもよい。このようにすれば、運搬機械10は、車体10Bの幅方向Wの両側から鉱石MRを排出することができる。
図12は、運搬機械10が備える制御装置70を示すブロック図の一例である。運搬機械10が備える制御装置70は、運搬機械10の走行及びベッセル11の幅方向Wにおける移動及び昇降を制御する。制御装置70は、処理装置71と記憶装置72とを備える。処理装置71には、撮像装置16A、16B、非接触センサ17A、17B、周辺監視カメラ17CA、17CB、質量センサ18、読取装置19、測域センサ20、ジャイロセンサ21、速度センサ22、加速度センサ23、駆動制御装置24、通信装置25及び記憶装置72等が接続されている。
撮像装置16A、16B及び周辺監視カメラ17CA、17CBは、CCD又はCMOSのような撮像素子を含み、物体の光学像を取得して、その物体の外形を検出可能である。本実施形態において、撮像装置16A、16B及び周辺監視カメラ17CA、17CBの少なくとも一方は、ステレオカメラを含み、物体の3次元の外形データを取得可能である。撮像装置16A、16B及び周辺監視カメラ17CA、17CBは、撮像した結果を処理装置71に出力する。処理装置71は、撮像装置16A、16Bの検出結果を取得し、これに基づいて、ベッセル11における鉱石MRの状態に関する情報を取得する。本実施形態において、ベッセル11に積載された鉱石MRの外形は、レーザスキャナー及び3次元距離センサの少なくとも1つを用いて検出されてもよい。
非接触センサ17A、17Bは、処理装置71と接続され、検出結果を処理装置71に出力する。非接触センサ17A、17Bは、取得した結果を処理装置71に出力する。質量センサ18は、ベッセル11及びベッセル11に積載された鉱石MRの質量を検出する。ベッセル11の質量は予め分かっているので、質量センサ18の検出結果からベッセル11の質量を減算すれば、ベッセル11に積載された鉱石MRの質量が得られる。質量センサ18は、処理装置71と接続されており、検出結果を処理装置71に出力する。処理装置71は、質量センサ18の検出結果に基づいて、ベッセル11に積み込まれた鉱石MRの質量及びベッセル11に鉱石MRが積載されているか否かに関する情報を求める。質量センサ18は、例えば、ベッセル11とテーブル11Tとの間に設けられるひずみゲージ式ロードセルでもよいし、油圧シリンダ11Cbの油圧を検出する圧力センサであってもよい。
読取装置19は、ドリフトDRに設けられたマークの識別情報(固有情報)を検出する。マークは、ドリフトDRに沿って複数配置されている。マークは、バーコード及び2次元コードのような識別子(コード)でもよいし、ICタグ又はRFIDのような識別子(タグ)でもよい。読取装置19は、処理装置71と接続され、検出結果を処理装置71に出力する。
測域センサ20は、運搬機械10の車体10Bの外側、例えば、前方及び後方に取り付けられて、運搬機械10の周囲における空間の物理的な形状データを取得して出力する。ジャイロセンサ21は、運搬機械10の方位(方位変化量)を検出し、検出結果を処理装置71に出力する。速度センサ22は、運搬機械10の走行速度を検出し、検出結果を処理装置71に出力する。加速度センサ23は、運搬機械10の加速度を検出し、検出結果を処理装置71に出力する。駆動制御装置24は、例えば、マイクロコンピュータである。駆動制御装置24は、処理装置71からの指令に基づき、走行用の電動機13A、13B、制動システム13BS、操舵システム13SS及び油圧ポンプ13Pを駆動する電動機13Cの動作を制御する。油圧ポンプ13Pは、油圧シリンダ11Ca、11Cbに作動油を供給する装置である。本実施形態において、運搬機械10は、走行用の電動機13A、13Bによって走行するが、これに限定されない。例えば、運搬機械10は、油圧ポンプ13Pから吐出される作動油によって駆動する油圧モータによって走行してもよい。制動システム13BS及び操舵システム13SSも、電動であってもよいし、油圧を利用して動作するものであってもよい。
本実施形態において、ドリフトDRにおいてマークが配置されている位置(絶対位置)に関する情報は、事前に測定された既知な情報である。マークの絶対位置に関する情報は、記憶装置72に記憶されている。処理装置71は、運搬機械10に設けられている読取装置19で検出したマークの検出結果(マークの識別情報)と、記憶装置72の記憶情報とに基づいて、ドリフトDRにおける運搬機械10の絶対位置を求めることができる。
測域センサ20は、空間の物理的な形状データを出力可能な走査型の光波距離計を含む。測域センサ20は、例えば、レーザスキャナー及び3次元距離センサの少なくとも1つを含み、2次元又は3次元の空間データを取得し、出力することができる。測域センサ20は、積込機械30及びドリフトDRの壁面の少なくとも一方を検出する。本実施形態において、測域センサ20は、積込機械30の形状データ、ドリフトDRの壁面の形状データ及びベッセル11の積荷の形状データの少なくとも1つを取得可能である。また、測域センサ20は、積込機械30との相対位置(相対的な距離及び方位)及びドリフトDRの壁面との相対位置の少なくとも一方を検出可能である。測域センサ20は、検出した情報を処理装置71に出力する。
本実施形態において、ドリフトDRの壁面に関する情報が予め求められており、記憶装置72に記憶されている。すなわち、ドリフトDRの壁面に関する情報は、事前に測定された既知の情報である。ドリフトDRの壁面に関する情報は、壁面の複数の部分におけるそれぞれの形状に関する情報及びそれら壁面の部分それぞれの絶対位置に関する情報を含む。記憶装置72には、壁面の複数の部分の形状と、その形状を有する壁面の部分におけるそれぞれの絶対位置との関係が記憶されている。処理装置71は、運搬機械10に設けられている測域センサ20が検出したドリフトDRの壁面の検出結果(壁面の形状データ)と、記憶装置72の記憶情報とに基づいて、ドリフトDRにおける運搬機械10の絶対位置及び方位を求めることができる。
処理装置71は、読取装置19及び測域センサ20の少なくとも一方を用いて導出された運搬機械10の現在位置(絶対位置)に基づいて、坑内MIの決められた経路(目標経路)にしたがって運搬機械10が走行するように、ドリフトDRを走行する運搬機械10を制御する。
処理装置71は、例えば、CPUを含むマイクロコンピュータである。処理装置71は、非接触センサ17A、17B、読取装置19及び測域センサ20等の検出結果に基づいて、駆動制御装置24を介して走行用の電動機13A、13B、制動システム13BS及び車輪12A、12Bの操舵システム13SSを制御する。そして、処理装置71は、所定の走行速度及び加速度で、前述した目標経路にしたがって運搬機械10を走行させる。
記憶装置72は、RAM、ROM、フラッシュメモリ及びハードディスクドライブの少なくとも1つを含み、処理装置71と接続される。記憶装置72は、処理装置71が運搬機械10を自律走行させるために必要なコンピュータプログラム及び各種の情報を記憶している。通信装置25は、処理装置71と接続され、積込機械30に搭載された通信装置及び管理装置3の少なくとも一方との間でデータ通信する。
本実施形態において、運搬機械10は、無人車両であり、自律走行が可能である。通信装置25は、管理装置3及び積込機械30の少なくとも一方から送信された情報(指令信号を含む)を受信可能である。また、通信装置25は、撮像装置16A、16B、周辺監視カメラ17CA、17CB、速度センサ22及び加速度センサ23等が検出した情報を管理装置3及び積込機械30の少なくとも一方に送信可能である。運搬機械10は、周辺監視カメラ17CA、17CB及び非接触センサ17A、17Bの少なくとも一方が取得した運搬機械10の周辺の情報を管理装置3に送信し、この周辺の情報を基に、オペレーターが運搬機械10を遠隔操作することもできる。このように、運搬機械10は、自律走行のみならず、オペレーターの操作によっても走行し、ベッセル11をスライド及び昇降させることができる。
例えば、速度センサ22及び加速度センサ23等が検出した情報を取得した管理装置3は、この情報を運搬機械10の稼働情報として、例えば、記憶装置3Mに蓄積する。また、周辺監視カメラ17CA、17CBが撮像した情報を管理装置3が取得した場合、オペレーターは、周辺監視カメラ17CA、17CBが撮像した運搬機械10の周辺の画像を視認しながら、運搬機械10を操作することもできる。さらに、質量センサ18が検出したベッセル11の鉱石MRの質量に関する情報を取得した積込機械30は、この情報に基づいて、ベッセル11への鉱石MRの積載量を制御することもできる。次に、積込機械30について説明する。
<積込機械30>
図13は、本実施形態に係る積込機械30の側面図である。図14は、本実施形態に係る積込機械30の上面図である。図15は、本実施形態に係る積込機械30の正面図である。図13は、積込機械30が地山RMの鉱石MRを掘削し、掘削した鉱石MRを搬送する状態を示している。積込機械30は、クロスカットCR内で鉱石MRの地山RMを掘削し、掘削した鉱石MRを図7及び図8等に示す運搬機械10のベッセル11に積載する。積込機械30の車体30Bには、フィーダー31と、支持機構32と、走行装置34と、貫入部材35と、回転体36と、岩石ガード37とが取り付けられる。貫入部材35が取り付けられている側が積込機械30の前方であり、貫入部材35が取り付けられている側とは反対側が積込機械30の後方である。なお、積込機械30は、回転体36及び岩石ガード37を備えていなくてもよい。
図13は、本実施形態に係る積込機械30の側面図である。図14は、本実施形態に係る積込機械30の上面図である。図15は、本実施形態に係る積込機械30の正面図である。図13は、積込機械30が地山RMの鉱石MRを掘削し、掘削した鉱石MRを搬送する状態を示している。積込機械30は、クロスカットCR内で鉱石MRの地山RMを掘削し、掘削した鉱石MRを図7及び図8等に示す運搬機械10のベッセル11に積載する。積込機械30の車体30Bには、フィーダー31と、支持機構32と、走行装置34と、貫入部材35と、回転体36と、岩石ガード37とが取り付けられる。貫入部材35が取り付けられている側が積込機械30の前方であり、貫入部材35が取り付けられている側とは反対側が積込機械30の後方である。なお、積込機械30は、回転体36及び岩石ガード37を備えていなくてもよい。
フィーダー31は、地山RMから鉱石MRを積み込んで、ドローポイントDPの地山RMから離れる方向に搬送した後、排出する。すなわち、フィーダー31は、積込機械30の前方で積み込まれた鉱石MRを後方に向かって搬送し、後方から排出する。フィーダー31は、例えば、無端の搬送体として搬送ベルトを用い、これを一対のローラーに掛け回して回転させることにより、積込側31Fから排出側31Eに鉱石MRを搬送する。積込側31Fは、地山RM側であり、排出側31Eは積込側31Fとは反対側である。図14に示すように、フィーダー31は、幅方向Wの両側に、一対のガイド31G、31Gが設けられている。一対のガイド31G、31Gは、フィーダー31から搬送途中の鉱石MRが脱落することを抑制する。幅方向Wは、フィーダー31が鉱石MRを搬送する方向Fと直交する方向であり、フィーダー31が備える一対のローラーの回転中心軸と平行な方向である。フィーダー31の幅方向Wは、車体30Bの幅方向でもある。フィーダー31は、排出側31Eに、鉱石MRを運搬機械10のベッセル11内に導くためのガイド39を備えている。フィーダー31は、車体30Bの前方、すなわちフィーダー31の積込側31Fの軸線を中心として揺動する。フィーダー31は、地面Gに対する角度αを変更することができる。角度αは、フィーダー31が備える一対のローラーの回転中心軸を結ぶ直線LCと、地面Gとのなす角度である。
フィーダー31に鉱石MRを積み込むのは、回転ローラー33である。回転ローラー33は、フィーダー31の積込側31F、すなわちフィーダー31の前方で回転しながら鉱石MRをフィーダー31に送り込む。このため、鉱石MRの掘削時において、回転ローラー33は、ブーム32aとアーム32bとを備える支持機構32によってフィーダー31の積込側31Fに設置される。回転ローラー33は、所定の軸線Zrの周りを回転する回転部材33D及び回転部材33Dの外周部に設けられて鉱石MRと接触して掘削する接触部材33Bとを有する。本実施形態において、接触部材33Bは、回転部材33Dからその径方向外側に突出し、かつ回転部材33Dの周方向に沿って所定の間隔で設けられた複数の板状部材である。接触部材33Bの板面と平行な平面は、軸線Zrとは直交しない。本実施形態において、接触部材33Bの板面と平行な平面は、軸線Zrと平行になっている。接触部材33Bは、先端部、すなわち回転部材33D側とは反対側の端部が、掘削対象である地山RMに食い込むように曲げられていてもよい。
回転ローラー33が回転することにより、接触部材33Bは、上方Uに位置する場合にフィーダー31から遠ざかり、下方Dに位置する場合にフィーダー31に近づく。この動きによって、複数の接触部材33Bは、地山RMから鉱石MRを掘削してフィーダー31に送り込む。複数の接触部材33Bは、回転部材33Dとともに回転しているので、連続して鉱石MRを掘削して、フィーダー31に送り込むことができる。
回転ローラー33を回転可能に支持する支持機構32は、車体30Bに取り付けられるブーム32aと、ブーム32aに連結されるアーム32bとを有する。ブーム32aは、例えば、シャフト38Aを介して積込機械30の車体30Bに取り付けられて、シャフト38Aを中心として車体30Bに対して揺動する。アーム32bは、例えば、シャフト38Bを介してブーム32aの車体30Bとは反対側の端部と連結されて、ブーム32aに対してシャフト38Bを中心として揺動する。アーム32bは、ブーム32aと連結されている端部とは反対側の端部で、回転ローラー33を回転可能に支持する。ブーム32a及びアーム32bは、例えば、アクチュエータとしての油圧シリンダによって駆動されて揺動してもよいし、電動機又は油圧モータによって駆動されて揺動してもよい。
ブーム32aは、車体30Bに対して第1の軸線Zaの周りを揺動し、アーム32bは、第1の軸線Zaと平行な軸線Za’の周りを揺動する。第1の軸線Zaは、ブーム32aと車体30Bとを連結するシャフト38Aの中心軸であり、第1の軸線Zaと平行な軸線Za’は、ブーム32aとアーム32bとを連結するシャフト38Bの中心軸である。本実施形態において、アーム32bは、さらに、第1の軸線Zaと直交する第2の軸線と平行な軸線の周りを揺動してもよい。このようにすると、回転ローラー33が移動できる範囲が大きくなるので、掘削作業の自由度が向上する。
ブーム32aは、車体30Bの幅方向Wの両側、本実施形態においてはフィーダー31の幅方向Wの両側に設けられた一対の棒状部材(第1棒状部材)である。アーム32bは、それぞれのブーム32aに連結された一対の棒状部材(第2棒状部材)である。図14に示すように、一対のアーム32bは、両者の間に回転ローラー33を支持している。本実施形態において、一対のブーム32aは、梁32Jによって連結されている。このような構造により、支持機構32の剛性が向上するので、鉱石MRの掘削時には、支持機構32が回転ローラー33を確実に地山RMに押し付けることができるので、鉱石MRの掘削効率の低下が抑制される。また、一対のアーム32bを棒状又は板状の部材で連結してもよい。このようにすれば、支持機構32の剛性がさらに向上するのでより好ましい。
支持機構32は、ブーム32aが車体30Bに対して揺動し、アーム32bがブーム32aに対して揺動することにより、回転ローラー33が移動する。支持機構32は、回転ローラー33を移動させることにより、回転ローラー33とフィーダー31及び車体30Bとの相対的な位置関係を変更することができる。また、支持機構32は、回転ローラー33を移動させることによって、地山RMの異なる位置を掘削したり、回転ローラー33を地山RMからフィーダー31に向かって移動させることにより地山RMから鉱石MRをフィーダー31側に掻き込んだりすることができる。また、例えば、積込機械30の走行中、前方に物体が存在して走行の妨げとなっている場合において、支持機構32は、回転ローラー33を用いて物体をフィーダー31に向かって掻き込んでからフィーダー31に送り込むことにより、積込機械30の進行方向前方の物体を取り除くこともできる。
本実施形態において、回転ローラー33は、図14に示すように、アーム32bの先端部に取り付けられた電動機33Mによって回転する。回転ローラー33を駆動させる装置は電動機33Mに限定されるものではなく、例えば、油圧モータであってもよい。また、電動機33Mが取り付けられる箇所はアーム32bの先端部に限定されるものではない。
車体30Bには、これを走行させる走行装置34が取り付けられている。走行装置34は、車体30Bの幅方向両側に設けられた一対の履帯34Cと、車体30Bの幅方向両側に設けられた一対の駆動輪34Dと、車体30Bの幅方向両側に設けられた一対の従動輪34Sとを含む。駆動輪34Dと従動輪34Sとに履帯34Cが掛け回されている。それぞれの駆動輪34Dは、別個に独立して駆動される。本実施形態において、積込機械30は、それぞれの駆動輪34Dに走行用の電動機を備えている。このような構造により、一対の履帯34C、34Cは、別個独立に駆動される。
車体30Bには、貫入部材35が取り付けられる。貫入部材35は、車体30Bのフィーダー31の積込側31Fに配置される。貫入部材35は、錐体の形状をした部材であり、本実施形態では四角錐の形状である。貫入部材35の形状は、四角錐の形状に限定されるものではなく、例えば、三角錐の形状であってもよい。貫入部材35は、錐体の頂部が車体30Bの前方になるように、車体30Bに取り付けられる。このようにすることで、積込機械30が地山RMに貫入するときには、貫入部材35が頂部から地山RMに貫入する。
貫入部材35は、積込機械30の掘削時において、錐体の頂部から地山RMに貫入して、地山RMを突き崩す。貫入部材35が地山RMに貫入する場合、走行装置34は、フィーダー31及び貫入部材35が取り付けられた車体30Bを前方に走行させ、かつフィーダー31を動作させながら貫入部材35を地山RMに貫入させる。このとき、フィーダー31は、上方の搬送ベルトが積込側31Fから排出側31Eに向かって移動する。積込機械30は、貫入時において、このようにフィーダー31を動作させることで、フィーダー31の駆動力を貫入に利用できるので、地山RMにより深く貫入することができる。
車体30Bの幅方向両側、すなわち、フィーダー31の搬送方向と直交する方向における両側には、一対の回転体36が設けられる。一対の回転体36は、走行装置34の前方であってフィーダー31の積込側31Fに配置される。回転体36は、所定の軸線周りを回転するドラム36Dの周囲に複数の羽根36Bが所定の間隔で設けられた構造体である。回転体36は、例えば、電動機によって駆動される。回転体36は、フィーダー31を駆動する電動機によって駆動されてもよい。この場合、フィーダー31の駆動と回転体36の駆動とをクラッチ等で切り替えられるようにしてもよい。例えば、クラッチを係合させた場合にはフィーダー31と回転体36とが同時に回転し、クラッチを開放するとフィーダー31のみが回転するようにすることができる。
回転体36は、貫入部材35が地山RMに貫入するときには、積込機械30の車体30Bを地面Gに押し付ける方向に回転する。具体的には、回転体36は、地山RM側の羽根36Bが下方Dから上方Uに向かうように、また、走行装置34側の羽根36Bが上方Uから下方Dに向かうように回転する。このようにすることで、回転体36は、地山RM側の羽根36Bが地山RMに接触すると、車体30Bの前方を下方Dに向かって押し下げるので、走行装置34の履帯34Cが地面Gに対してより強く押し付けられる。その結果、履帯34Cと地面Gとの間の摩擦力が増加するので、走行装置34は、貫入部材35を地山RMに貫入させやすくなる。積込機械30の地山RMへの貫入が終了し、回転ローラー33による掘削及びフィーダー31による積み込みが開始されるときには、回転体36の回転は停止する。
回転体36と走行装置34の履帯34Cとの間には、岩石ガード37が設けられる。本実施形態において、岩石ガード37は、車体30Bに取り付けられている。岩石ガード37は、例えば、掘削中に回転ローラー33から飛来する鉱石MRから走行装置34を保護したり、積込機械30の走行時において坑道内に存在する岩石等から走行装置34を保護したりする。岩石ガード37によって、走行装置34の耐久性低下が抑制される。
本実施形態において、車体30Bは、車体30Bの幅方向外側に向かって伸びて、ドローポイントDPにつながるクロスカットCRの壁面CRWに押し付けられる固定装置30Fを有する。本実施形態では、固定装置30Fを車体30Bの幅方向両側にそれぞれ1個ずつ、対向するように設けてあるが、固定装置30Fの数及び設置箇所はこれに限定されるものではない。例えば、固定装置30Fは、車体30Bの上方に設けられていてもよい。本実施形態において、固定装置30Fは、例えば、油圧シリンダ30FCと、油圧シリンダ30FCのピストンの先端に設けられた押付部材30FPとを有する。積込機械30の掘削時及び鉱石MRの搬送時において、固定装置30Fは、積込機械30をクロスカットCR内に固定する。具体的には、固定装置30Fは、油圧シリンダ30FCを伸ばして押付部材30FPを壁面CRWに押し付けることにより、これらを介してクロスカットCR内に積込機械30の車体30Bを固定する。このようにすることで、積込機械30が地山RMを掘削するときに発生する反力は、固定装置30Fを介してクロスカットCRが受けることができる。その結果、積込機械30は、姿勢が安定するので、安定して地山RMを掘削することができる。固定装置30Fと車体30Bとの間に油圧シリンダ30FCを設け、固定装置30FをクロスカットCRの壁面CRWに固定した後に、油圧シリンダ30FCの駆動力を利用して車体を貫入させてもよい。
車体30Bの幅方向両側又は上方に固定装置30Fを設ける場合、積込機械30の貫入時には、固定装置30Fによる固定は解除される。本実施形態では、油圧シリンダ30FCが縮んだ状態となり、押付部材30FPが壁面CRWを押さないようになる。積込機械30の掘削時において、固定装置30Fが動作して、積込機械30をクロスカットCR内に固定する。掘削中、積込機械30が地山RMに対してさらに貫入したり、地山RMから遠ざかったりする場合には、固定装置30Fによる固定が解除された後に、走行装置34が積込機械30を移動させる。
図13に示すように、固定装置30Fを車体30Bの後方、すなわち、フィーダー31の排出側31Eに設け、クロスカットCR内の地面Gから突出させた反力受けTGと車体30Bとの間に固定装置30Fを介在させて、前述した反力を受けてもよい。掘削時においては、積込機械30の前後方向の反力が大きいが、このような構造にすることにより、より効果的に掘削時の反力を受けることができる。また、積込機械30は、固定装置30Fを伸ばすことにより、掘削時における積込機械30の位置の調整をすることもできる。なお、積込機械30は、固定装置30Fを備えていなくてもよい。
本実施形態において、積込機械30は、フィーダー31に鉱石MRが積み込まれる部分(積込側31F)と、フィーダー31から鉱石MRが排出される部分(排出側31E)との間に、鉱石MRの排出と排出の停止とを切り替える切替機構80が設けられる。切替機構80は、支持体81と、蓋82と、蓋82を開閉するアクチュエータとしての油圧シリンダ83とを含む。支持体81は、図15に示すように、一端部が車体30Bの幅方向両側、具体的にはフィーダー31の幅方向両側に取り付けられる2本の脚部81Rと、2本の脚部81Rの他端部でこれらを連結する連結部81Cとを含む、門型の部材である。2本の脚部81Rと連結部81Cとで囲まれる部分を、鉱石MRが通過する。
蓋82は、板状の部材であり、2本の脚部81Rと連結部81Cとで囲まれる部分に設けられる。蓋82は、支持体81の連結部81C側に存在する所定の軸線Zg周りを回動する。蓋82と支持体81の連結部81Cとの間には、油圧シリンダ83が設けられる。油圧シリンダ83が伸縮することにより、蓋82は、2本の脚部81Rと連結部81Cとで囲まれる部分を開閉する。蓋82が開くことによって、2本の脚部81Rと連結部81Cとで囲まれる部分を鉱石MRが通過する。蓋82が閉じることによって、鉱石MRは、2本の脚部81Rと連結部81Cとで囲まれる部分を通過しない。このようにすることで、積込機械30は、フィーダー31からの鉱石MRの排出量を調整することができる。
本実施形態において、積込機械30は、情報収集装置40を備える。情報収集装置40は、車体30Bの積込側31F、すなわち前方に取り付けられる。より具体的には、情報収集装置40が情報を収集する部分が、車体30Bの積込側31F、すなわち前方を向いて取り付けられる。情報収集装置40は、3次元の空間データを取得し、出力する装置である。情報収集装置40は、地山RMの鉱石MRの状態に関する情報としての鉱石情報を取得する。鉱石情報は、地山RMの3次元の空間データである。
情報収集装置40は、例えばカメラ、ステレオカメラ、レーザスキャナー又は3次元距離センサ等である。情報収集装置40が情報を収集する部分は、カメラ又はステレオカメラの場合はレンズ、レーザスキャナー及び3次元距離センサの場合は受光部である。本実施形態において、情報収集装置40としては、ステレオカメラが用いられる。本実施形態において、積込機械30は、3個の情報収集装置40を支持機構32の梁32Jに取り付けている。すなわち、複数の情報収集装置40は、車体30Bの幅方向において複数箇所に設置される。このようにすることで、積込機械30は、1つの情報収集装置40の撮像対象がアーム32bに隠れる場合でも、他の情報収集装置40によって撮像対象の鉱石情報を得ることができる。
本実施形態において、積込機械30が備える制御装置は、情報収集装置40が収集した鉱石情報を用いて積込機械30の動作を制御する。例えば、前述した制御装置は、情報収集装置40が取得した鉱石情報に基づいて、フィーダー31、回転ローラー33、支持機構32及び走行装置34の少なくとも1つを制御する。このようにすることで、積込機械30は、地山RM及び鉱石MRの状態に応じて柔軟に動作することができるので、例えば、鉱山Mの生産効率が向上する。
本実施形態において、積込機械30は、車体30Bの排出側31E、すなわち後方に情報収集装置41を備える。より具体的には情報収集装置41が情報を収集する部分が、車体30Bの排出側31E、すなわち後方を向いて取り付けられる。情報収集装置41は、前述した情報収集装置40と同様に、3次元の空間データを取得し、出力する装置である。情報収集装置41は、図4及び図5に示す運搬機械10のベッセル11に積載された鉱石MRの状態に関する情報としての積荷情報を取得する。積荷情報は、鉱石MRの3次元の空間データである。
情報収集装置41は、前述した情報収集装置40と同様に、例えばカメラ、ステレオカメラ、レーザスキャナー又は3次元距離センサ等である。情報収集装置41が情報を収集する部分は、カメラ又はステレオカメラの場合はレンズ、レーザスキャナー及び3次元距離センサの場合は受光部である。本実施形態において、情報収集装置41としては、ステレオカメラが用いられる。本実施形態において、積込機械30は、2個の情報収集装置41をフィーダー31の幅方向両側に取り付けている。すなわち、複数の情報収集装置41は、車体30Bの幅方向Wにおいて複数箇所に設置される。このようにすることで、積込機械30は、1つの情報収集装置41の撮像対象が坑道の影等に隠れる場合でも、他の情報収集装置41によって撮像対象の鉱石情報を得ることができる。
本実施形態において、積込機械30が備える制御装置は、情報収集装置41が収集した積荷情報を用いて積込機械30及び運搬機械10の少なくとも一方を制御する。例えば、前述した制御装置は、情報収集装置41が取得した積荷情報に基づいて、回転ローラー33、フィーダー31又は切替機構80等の動作を制御したり、運搬機械10が備えるベッセル11の位置又はベッセル11の運動を制御したりする。このようにすることで、積込機械30は、運搬機械10のベッセル11に積載された鉱石MRの状態に応じて、鉱石MRの搬送量を変更したり、ベッセル11の位置を調整したりすることができるので、例えば、鉱山Mの生産効率が向上する。
図16は、本実施形態に係る積込機械30が走行するときの姿勢を示す図である。積込機械30が走行する場合、フィーダー31の地面Gに対する角度αは、積込機械30が鉱石MRを掘削及び搬送する場合(図13参照)と比較して小さくなる。すなわち、フィーダー31が備える一対のローラーの回転中心軸を結ぶ直線LCは、地面Gに対してより平行に近くなる。このようにすると、積込機械30の前方、すなわち進行方向側に配置されるフィーダー31の積込側31Fが地面Gと離れるので、積込機械30の走行時にフィーダー31と地面Gとが干渉する可能性を低減できる。
図16に示すように、積込機械30が走行する場合、支持機構32は折り畳まれる。そして、回転ローラー33は、積込機械30が鉱石MRを掘削及び搬送する場合(図13参照)と比較して、よりフィーダー31に近い位置に移動する。このため、積込機械30は、重心から車体30Bの前後方向に離れた位置に存在していた回転ローラー33が、より重心に近い位置に移動することになるので、前後の質量のバランスが向上する。その結果、積込機械30は、安定して走行することができる。
図17は、本実施形態に係る積込機械30が備える制御装置75を示すブロック図の一例である。積込機械30が備える制御装置75は、フィーダー31、支持機構32、回転ローラー33、走行装置34、回転体36及び切替機構80を制御する。制御装置70は、処理装置76と記憶装置77とを備える。処理装置76には、情報収集装置40に対応する前方撮像装置40C、情報収集装置41に対応する後方撮像装置41C、非接触センサ42、読取装置43、測域センサ44、ジャイロセンサ45、速度センサ46、加速度センサ47、駆動制御装置48、通信装置52及び記憶装置77等が接続されている。非接触センサ42、読取装置43、測域センサ44は、積込機械30の車体30Bの外部に取り付けられる。
前方撮像装置40C及び後方撮像装置41Cは、CCD又はCMOSのような撮像素子を含み、物体の光学像を取得して、その物体の外形を検出可能である。本実施形態において、前方撮像装置40C及び後方撮像装置41Cは、ステレオカメラを含み、物体の3次元の外形データを取得可能である。前方撮像装置40C及び後方撮像装置41Cは、撮像した結果を処理装置76に出力する。処理装置76は、前方撮像装置40Cの検出結果を取得し、これに基づいて前述した鉱石情報を得る。また、処理装置76は、後方撮像装置41Cの検出結果を取得し、これに基づいて前述した積荷情報を得る。本実施形態において、地山RMの鉱石MRの外形及びベッセル11に積載された鉱石MRの外形は、レーザスキャナー及び3次元距離センサの少なくとも1つを用いて検出されてもよい。
非接触センサ42は、積込機械30の周囲に存在する物体を検出する。非接触センサ42は、処理装置76と接続され、検出結果を処理装置76に出力する。非接触センサ42は、取得した結果を処理装置76に出力する。読取装置43は、ドリフトDR又はクロスカットCRに設けられたマークの識別情報(固有情報)を検出する。マークは、ドリフトDR又はクロスカットCRに沿って複数配置されている。読取装置43は、処理装置76と接続され、検出結果を処理装置76に出力する。マークは、バーコード及び2次元コードのような識別子(コード)でもよいし、ICタグ又はRFIDのような識別子(タグ)でもよい。
本実施形態において、ドリフトDR又はクロスカットCRにおいてマークが配置されている位置(絶対位置)に関する情報は、事前に測定された既知な情報である。マークの絶対位置に関する情報は、記憶装置77に記憶されている。処理装置76は、積込機械30に設けられている読取装置43で検出したマークの検出結果(マークの識別情報)と、記憶装置77の記憶情報とに基づいて、ドリフトDR又はクロスカットCRにおける積込機械30の絶対位置を求めることができる。
測域センサ44は、空間の物理的な形状データを取得して出力する。ジャイロセンサ45は、積込機械30の方位(方位変化量)を検出し、検出結果を処理装置76に出力する。速度センサ46は、積込機械30の走行速度を検出し、検出結果を処理装置76に出力する。加速度センサ47は、積込機械30の加速度を検出し、検出結果を処理装置76に出力する。駆動制御装置48は、例えば、マイクロコンピュータである。駆動制御装置48は、処理装置76からの指令に基づき、図13に示す回転ローラー33を駆動する電動機33M、走行装置34が備える電動機48L、48R、支持機構32のブーム32aを揺動させる電動機49、アーム32bを揺動させる電動機50、フィーダー31を駆動する電動機51F、回転体36を回転させる電動機51R、油圧ポンプ85を駆動する電動機86の動作を制御する。油圧ポンプ85は、切替機構80が備える油圧シリンダ83、フィーダー31の姿勢を変更するアクチュエータとしての油圧シリンダ87及び固定装置30Fの油圧シリンダ30FCに作動油を供給する装置である。ブーム32a及びアーム32bは、油圧シリンダ30FCによって揺動させられてもよい。この場合、ブーム32aを揺動させるブームシリンダ及びアーム32bを揺動させるアームシリンダには、油圧ポンプ85から作動油が供給される。電動機48Lは、図14に示す一方の履帯34Cを駆動し、電動機48Rは、他方の履帯34Cを駆動する。電動機48Lは、図14に示す一方の履帯34Cを駆動し、電動機48Rは、他方の履帯34Cを駆動する。
本実施形態において、積込機械30は、走行装置34が備える電動機48L、48Rによって走行するが、これに限定されない。例えば、積込機械30は、油圧ポンプ85から吐出される作動油によって駆動する油圧モータによって走行してもよい。また、支持機構32のブーム32a及びアーム32b、回転ローラー33及び回転体36並びにフィーダー31も、油圧ポンプ85から吐出される作動油によって駆動する油圧シリンダ又は油圧モータによって駆動されてもよい。
測域センサ44は、空間の物理的な形状データを出力可能な走査型の光波距離計を含む。測域センサ44は、例えば、レーザレンジファインダ、レーザスキャナー及び3次元スキャナの少なくとも1つを含み、3次元の空間データを取得し、出力することができる。測域センサ44は、運搬機械10、ドリフトDR及びクロスカットCRの壁面の少なくとも1つを検出する。本実施形態において、測域センサ44は、運搬機械10の形状データ、ドリフトDR又はクロスカットCRの壁面の形状データ及び運搬機械10が備えるベッセル11の積荷の形状データの少なくとも1つを取得可能である。また、測域センサ44は、運搬機械10との相対位置(相対的な距離及び方位)及びドリフトDR又はクロスカットCRの壁面との相対位置の少なくとも一方を検出可能である。測域センサ44は、検出した情報を処理装置76に出力する。
本実施形態において、ドリフトDR及びクロスカットCRの壁面に関する情報が予め求められており、記憶装置77に記憶されている。すなわち、ドリフトDRの壁面に関する情報は、事前に測定された既知の情報である。ドリフトDRの壁面に関する情報は、壁面の複数の部分におけるそれぞれの形状に関する情報及びそれら壁面の部分それぞれの絶対位置に関する情報を含む。記憶装置77には、壁面の複数の部分の形状と、その形状を有する壁面の部分におけるそれぞれの絶対位置との関係が記憶されている。処理装置76は、積込機械30に設けられている測域センサ44が検出したドリフトDRの壁面の検出結果(壁面の形状データ)と、記憶装置77の記憶情報とに基づいて、ドリフトDRにおける積込機械30の絶対位置及び方位を求めることができる。
処理装置76は、読取装置43及び測域センサ44の少なくとも一方を用いて導出された積込機械30の現在位置(絶対位置)に基づいて、坑内MIの決められた経路(目標経路)にしたがって積込機械30が走行するように、ドリフトDR又はクロスカットCRを走行する積込機械30を制御する。このとき、処理装置76は、積込機械30が指定されたドローポイントDPに配置されるように、これを制御する。
処理装置76は、例えば、CPUを含むマイクロコンピュータである。処理装置76は、前方撮像装置40C、後方撮像装置41C、非接触センサ42、読取装置43等の検出結果に基づいて、駆動制御装置48を介して走行装置34が備える電動機48L、48Rを制御する。そして、処理装置76は、所定の走行速度及び加速度で、前述した目標経路にしたがって積込機械30を走行させる。
記憶装置77は、RAM、ROM、フラッシュメモリ及びハードディスクドライブの少なくとも1つを含み、処理装置76と接続される。記憶装置77は、処理装置76が積込機械30を自律走行させるために必要なコンピュータプログラム及び各種の情報を記憶している。通信装置52は、処理装置76と接続され、運搬機械10に搭載された通信装置及び管理装置3の少なくとも一方との間でデータ通信する。
本実施形態において、積込機械30は、無人車両であり、自律走行が可能である。通信装置52は、管理装置3及び運搬機械10の少なくとも一方から送信された情報(指令信号を含む)を、アンテナ53を介して受信可能である。また、通信装置52は、前方撮像装置40C、後方撮像装置41C、非接触センサ42、読取装置43、測域センサ44、ジャイロセンサ45、速度センサ46及び加速度センサ47等が検出した情報を管理装置3及び運搬機械10の少なくとも一方に、アンテナ53を介して送信可能である。積込機械30は、自律走行が可能な無人車両に限定されない。例えば、管理装置3が、前方撮像装置40Cが撮像した画像を取得して図6に示す表示装置8に表示し、オペレーターは、表示された画像を視認しながら積込機械30の掘削、積込及び走行を遠隔操作により制御してもよい。また、管理装置3が、後方撮像装置41Cが撮像した画像を取得して図6に示す表示装置8に表示し、オペレーターは、表示された画像を視認しながら積込機械30の掘削及び積込並びに運搬機械10のベッセル11の動作を遠隔操作により制御してもよい。
例えば、速度センサ46及び加速度センサ47等が検出した情報を取得した管理装置3は、この情報を積込機械30の稼働情報として、例えば、記憶装置3Mに蓄積する。また、前方撮像装置40C又は後方撮像装置41Cが撮像した情報を管理装置3が取得した場合、オペレーターは、前方撮像装置40C又は後方撮像装置41Cが撮像した積込機械30の周辺の画像を視認しながら、積込機械30を操作することもできる。さらに、後方撮像装置41Cが検出したベッセル11の鉱石MRの状態に関する情報を取得した運搬機械10は、この情報に基づいて、ベッセル11への鉱石MRの積載量又はベッセル11の位置を制御することもできる。本実施形態において、積込機械30は、電動であるが、内燃機関が動力源であってもよい。次に、図2に示す空間SPに設置されている蓄電器取扱装置EXについて説明する。
図18は、本実施形態に係る鉱山の管理システム1が備える蓄電器取扱装置EXの一例を示す図である。蓄電器取扱装置EXは、空間SP内に設置されている。本実施形態において、空間SPには、運搬機械10及び積込機械30を整備するための整備スペースMSが設けられている。蓄電器取扱装置EXは、蓄電器保持装置90と、この両側に設置された一対のガイド91a、91bと、それぞれのガイド91a、91bに案内される交換用の台車92a、92bとを備える。蓄電器保持装置90は、交換用の蓄電器14を複数保持している。蓄電器保持装置90は、放電された蓄電器14を充電する充電器としての機能を有している。ガイド91aは蓄電器保持装置90の一方に設けられ、ガイド91bは蓄電器保持装置90の他方に設けられる。ガイド91aは、蓄電器保持装置90から空間SPの出入口SPGに向かって延在した2本のレールである。ガイド91bもガイド91aと同様である。台車92aは、ガイド91aに取り付けられて、ガイド91aに沿って移動し、台車92bは、ガイド91bに取り付けられて、ガイド91bに沿って移動する。
蓄電器14を交換するために空間SPに進入した運搬機械10は、ガイド91aとガイド91bとの間に停車する。このとき、運搬機械10は、一方の蓄電器14をガイド91aに向けて、他方の蓄電器14をガイド91bに向けて停車する。台車92a及び台車92bは、充電済みの蓄電器14を蓄電器保持装置90から受け取り、運搬機械10に向かって移動する。台車92a及び台車92bは、運搬機械10と対向する位置に移動したら、運搬機械10に搭載されている放電された蓄電器14を運搬機械10から自身の上部に移動させる。次に、台車92a及び台車92bは、それぞれに積載されている充電済みの蓄電器14が運搬機械10と対向する位置まで移動する。その後、台車92a及び台車92bは、充電済みの蓄電器14を運搬機械10に積み込む。台車92a及び台車92bは、蓄電器保持装置90の位置まで戻り、運搬機械10から回収した蓄電器14を蓄電器保持装置90に移動させる。蓄電器保持装置90は、この蓄電器を充電する。このようにして、運搬機械10の蓄電器14が交換される。
運搬機械10が備える蓄電器14は、着脱可能でなくてもよい。この場合、蓄電器取扱装置EXは、運搬機械10が備える蓄電器14を充電するものであってもよい。
本実施形態において、運搬機械10は蓄電器14によって走行するため、空間SP内の蓄電器取扱装置EXを用いて放電された蓄電器14が充電済みの蓄電器14と交換される。積込機械30は、前述したように、図3等に示す給電ケーブル5から電力を供給されて回転ローラー33及びフィーダー31等が動作する。積込機械30は、自身が坑内を移動するため、例えば、異なるドローポイントDPに移動するために走行するが、この場合、給電ケーブル5から切り離される。このため、積込機械30は、図17に示す走行用の電動機48L、48Rを駆動するための蓄電器を備えている。この蓄電器は、積込機械30がドローポイントDPで掘削及び鉱石MRを搬送しているときに、給電ケーブル5から供給される電力によって充電される。積込機械30の蓄電器は、例えば、使用により性能が許容値よりも低下したような場合に、例えば、空間SP内の整備スペースMSで交換される。
<運搬機械10が走行する経路>
図19は、本実施形態に係る鉱山の管理システム1において、運搬機械10が坑内MIのドリフトDRを進行する方向を示す図である。以下の説明において、坑内MIに設けられた複数のドリフトDR、複数の外周路TR、複数のドローポイントDP又は複数のオアパスOPを区別する場合には、符号DR、符号TR、符号DP又は符号OPに符号a、b等を付す。複数のドリフトDR、複数の外周路TR、複数のドローポイントDP及び複数のオアパスOPを区別しない場合、符号a、b等は付さない。
図19は、本実施形態に係る鉱山の管理システム1において、運搬機械10が坑内MIのドリフトDRを進行する方向を示す図である。以下の説明において、坑内MIに設けられた複数のドリフトDR、複数の外周路TR、複数のドローポイントDP又は複数のオアパスOPを区別する場合には、符号DR、符号TR、符号DP又は符号OPに符号a、b等を付す。複数のドリフトDR、複数の外周路TR、複数のドローポイントDP及び複数のオアパスOPを区別しない場合、符号a、b等は付さない。
図19に示す鉱山の採掘システム1では、坑内MIに、6本のドリフトDRa、DRb、DRc、DRd、DRe、DRfと2本の外周路TRa、TRbとが形成されている。本実施形態において、ドリフトDRと、外周路TRとで周回路CDが形成される。具体的には、複数本のドリフトDRと、複数本の外周路TRとが接続されて、1つの周回路CDが形成される。例えば、2本のドリフトDRb、DRdと2本の外周路TRa、TRbとで周回路CDaが形成される。また、2本のドリフトDRc、DReと2本の外周路TRa、TRbとで周回路CDbが形成される。このように、本実施形態では、2本のドリフトDRと、2本の外周路TRとで、1つの周回路CDが形成される。この場合、1つの周回路CDは、2本のドリフトDRと、2本の外周路TRとによって形成されるが、1つの周回路CDが有する2本のドリフトDRは、走行可能な方向が互いに異なっている。
1本のドリフトDRには最大1台の積込機械30が配置されることが好ましい。同一のドリフトに2台以上の積込機械30が配置されていても、無駄が生じるためである。
運搬機械10がドローポイントDPで採掘された鉱石MRを積載し、オアパスOPで排出する場合、この運搬機械10が走行する周回路CDは、オアパスOPa及びオアパスOPbの少なくとも一方を含むように形成されることが好ましい。鉱石MRを積載せず、図7及び図8に示す蓄電器14を交換するため、空間SPに設置された蓄電器取扱装置EXに向かう運搬機械10が走行する周回路CDは、オアパスOPa及びオアパスOPbを含まなくてもよい。管理装置3は、運搬機械10毎に、周回路CDを任意に生成することができる。例えば、管理装置3は、運搬機械10の状態に応じて周回路CDを生成してもよい。一例として、管理装置3は、運搬機械10が備える蓄電器14の容量が所定の閾値を下回り、かつ運搬機械10がベッセル11に鉱石MRを積載していない場合は、運搬機械10が蓄電器取扱装置EXで蓄電器14を交換するものとして、現在位置から空間SPまでの最短の周回路CDを生成することができる。
ドリフトDRを走行する運搬機械10は、周回路CDを同一方向に走行する。本実施形態では、周回路CDを右回りに走行する。その過程で、運搬機械10は、ドローポイントDPで積込機械30から鉱石MRを積載される。そして、運搬機械10は、積載された鉱石MRをオアパスOPa又はオアパスOPbで排出する。例えば、周回路CDaを走行する運搬機械10は、ドリフトDRbにつながっているドローポイントDPbで、積込機械30から鉱石MRの積載を受ける。その後、運搬機械10は、ドリフトDRb及び外周路TRaを走行し、外周路TRaに隣接して設けられたオアパスOPaに鉱石MRを排出する。鉱石MRを排出した運搬機械10は、ドリフトDRdを走行して、ドリフトDRdにつながっているドローポイントDPdで、積込機械30から鉱石MRの積載を受ける。その後、運搬機械10は、ドリフトDRd及び外周路TRbを走行し、外周路TRbに隣接して設けられたオアパスOPbに鉱石MRを排出する。
周回路CDbを走行する運搬機械10は、ドリフトDRcにつながっているドローポイントDPcで、積込機械30から鉱石MRの積載を受ける。その後、運搬機械10は、ドリフトDRc及び外周路TRaを走行し、外周路TRaに隣接して設けられたオアパスOPaに鉱石MRを排出する。鉱石MRを排出した運搬機械10は、ドリフトDReを走行して、ドリフトDReにつながっているドローポイントDPeで、積込機械30から鉱石MRの積載を受ける。その後、運搬機械10は、ドリフトDRe及び外周路TRbを走行し、外周路TRbに隣接して設けられたオアパスOPbに鉱石MRを排出する。
このように、運搬機械10が周回路CDを一方向に走行することにより、ドローポイントDPからオアパスOPの間を往復する場合と比較して、運搬機械10のすれ違いを最小限に抑制できる。また、周回路CDがオアパスOPaとオアパスOPbとの両方を含むようにすると、運搬機械10が周回路CDを1周する間に鉱石MRの積込と排出とを2回行うことができるので、鉱石MRの搬送量を大きくすることができる。その結果、鉱山の管理システム1は、サイクルタイムを改善し、鉱山Mの生産性を向上させることができる。また、運搬機械10が周回路CDを一方向に走行することにより、運搬機械10のすれ違いを抑制できるので、すれ違いに要する箇所を少なくすることができ、また、すれ違いが不要であればすれ違いに要する箇所を設けなくてもよい。その結果、坑道の幅を無闇に大きくする必要がなくなるので、坑道を掘削する手間、時間及び費用を抑制できる。
本実施形態において、それぞれのドリフトDRにおいて、運搬機械10等が走行する方向は、ドリフトDR毎に一方の方向(一方通行)に決められている。すなわち、それぞれのドリフトDRは、一方向のみ走行可能である。運搬機械10等が周回路CDを右回りに走行する場合、例えば、周回路CDaに含まれるドリフトDRbの走行方向は、オアパスOPbからオアパスOPaに向かう方向である。この場合、運搬機械10は、オアパスOPaからオアパスOPbに向かうようにドリフトDRbを走行することはできない。
運搬機械10等が周回路CDを一方向に走行する場合、管理装置3は、それぞれのドリフトDRにおいて、運搬機械10が他の運搬機械又は積込機械30とすれ違わないように、周回路CDを生成する。例えば、管理装置3は、周回路CDを生成する場合、既に生成されている周回路CDに含まれる結果、走行する方向が一方向に定められているドリフトDRを逆走するような周回路CDは生成することができない。管理装置3は、既に生成されている周回路CDに含まれるドリフトDRを用いて、新たな周回路CDを生成する場合、新たな周回路CDの走行方向が、既に生成されている周回路CDに含まれるドリフトDRの走行方向と一致するようにする。このようにすることで、周回路CDでの運搬機械10のすれ違いが低減又は回避される。
鉱山の管理システム1において、オアパスOPaが設けられている外周路TRaには6本のドリフトDRが接続されており、オアパスOPbが設けられている外周路TRbにも6本のドリフトDRが接続されている。外周路TRaが延びる方向において、オアパスOPaを基準としていずれの方向においても同数(本実施形態では3本)のドリフトDRが外周路TRaに接続されている。同様に、外周路TRbが延びる方向において、オアパスOPbを基準としていずれの方向においても同数(本実施形態では3本)のドリフトDRが外周路TRbに接続されている。このようなドリフトDR及び外周路TRを有する鉱山の管理システム1において、オアパスOPaとオアパスOPbとの両方を含むようにする周回路CDは、次の9パターンがある。
(1)パターン1:ドリフトDRa、外周路TRa、ドリフトDRf、外周路TRb
(2)パターン2:ドリフトDRa、外周路TRa、ドリフトDRe、外周路TRb
(3)パターン3:ドリフトDRa、外周路TRa、ドリフトDRd、外周路TRb
(4)パターン4:ドリフトDRb、外周路TRa、ドリフトDRf、外周路TRb
(5)パターン5:ドリフトDRb、外周路TRa、ドリフトDRe、外周路TRb
(6)パターン6:ドリフトDRb、外周路TRa、ドリフトDRd、外周路TRb
(7)パターン7:ドリフトDRc、外周路TRa、ドリフトDRf、外周路TRb
(8)パターン8:ドリフトDRc、外周路TRa、ドリフトDRe、外周路TRb
(9)パターン9:ドリフトDRc、外周路TRa、ドリフトDRd、外周路TRb
(1)パターン1:ドリフトDRa、外周路TRa、ドリフトDRf、外周路TRb
(2)パターン2:ドリフトDRa、外周路TRa、ドリフトDRe、外周路TRb
(3)パターン3:ドリフトDRa、外周路TRa、ドリフトDRd、外周路TRb
(4)パターン4:ドリフトDRb、外周路TRa、ドリフトDRf、外周路TRb
(5)パターン5:ドリフトDRb、外周路TRa、ドリフトDRe、外周路TRb
(6)パターン6:ドリフトDRb、外周路TRa、ドリフトDRd、外周路TRb
(7)パターン7:ドリフトDRc、外周路TRa、ドリフトDRf、外周路TRb
(8)パターン8:ドリフトDRc、外周路TRa、ドリフトDRe、外周路TRb
(9)パターン9:ドリフトDRc、外周路TRa、ドリフトDRd、外周路TRb
鉱山の管理システム1において、運搬機械10が、これらの周回路CDをいずれも一方向(例えば右回り)に走行することにより、運搬機械10のすれ違いを最小限に抑制でき、かつ運搬機械10が周回路CDを1周する間に鉱石MRの積込と排出とを2回行うことができるようになる。本実施形態において、それぞれの外周路TRに設けられるオアパスOPの位置及び数は限定されるものではない。一対の外周路TRに複数のドリフトDRが接続され、かつそれぞれの外周路TRに1個ずつオアパスOPが設けられている場合、オアパスOPを基準として外周路TRが延びる方向にそれぞれ同数のドリフトDRが接続されるようにすると、周回路CDのパターンを多くできるので好ましい。
鉱山の管理システム1は、積込機械30と運搬機械10との機能を分離している。このため、積込機械30は、掘削及び搬送に特化でき、運搬機械10は鉱石MRの運搬に特化できるので、それぞれの能力を最大限発揮させることができる。結果として、鉱山の管理システム1は、鉱山Mの生産性を向上させることができる。次に、鉱山の管理システム1における運搬機械10の走行方向を反転させる処理について説明する。
(運搬機械10の走行方向を反転させる処理)
図20は、本実施形態に係る鉱山の管理システム1において、運搬機械10の走行方向を反転させる処理を説明するための図である。図21は、周回路を示す概念図である。本実施形態においては、坑内MIで稼働する積込機械30のうち少なくとも1台が現在のドローポイントDPから他のドローポイントDPへ移動する際に、坑内MIで稼働する運搬機械10の第1距離の総和と第2距離の総和との差分が予め定められた規定値以上である場合には、運搬機械10の走行方向を反転させる。第1距離とは、坑内MIで稼働する運搬機械10が鉱石MRを積載して走行する距離である。第2距離とは、坑内MIで稼働する運搬機械10が鉱石MRを積載しない状態、すなわち空荷の状態で走行する距離である。以下において、第1距離を適宜積載距離と称し、第2距離を適宜空荷距離と称する。
図20は、本実施形態に係る鉱山の管理システム1において、運搬機械10の走行方向を反転させる処理を説明するための図である。図21は、周回路を示す概念図である。本実施形態においては、坑内MIで稼働する積込機械30のうち少なくとも1台が現在のドローポイントDPから他のドローポイントDPへ移動する際に、坑内MIで稼働する運搬機械10の第1距離の総和と第2距離の総和との差分が予め定められた規定値以上である場合には、運搬機械10の走行方向を反転させる。第1距離とは、坑内MIで稼働する運搬機械10が鉱石MRを積載して走行する距離である。第2距離とは、坑内MIで稼働する運搬機械10が鉱石MRを積載しない状態、すなわち空荷の状態で走行する距離である。以下において、第1距離を適宜積載距離と称し、第2距離を適宜空荷距離と称する。
運搬機械10は、ドローポイントDPで掘削され、積載された鉱石MRを積載してオアパスOPまで運搬して排出する。オアパスOPで鉱石MRを排出した運搬機械10は、外周路TR及びドリフトDRを通って、再びドローポイントDPに移動し、ここで鉱石MRの積載を受ける。したがって、積載距離は、運搬機械10がドローポイントDPからオアパスOPまで移動する距離に相当し、空荷距離は、運搬機械10がオアパスOPからドローポイントDPまで移動する距離に相当する。実質的には、積載距離はドローポイントDPからオアパスOPまでの、ドリフトDR及び外周路TRに沿った距離であり、空荷距離はオアパスOPからドローポイントDPまでの距離である。
運搬機械10が鉱石MR又は排土等の積荷を積載して走行すると、積荷を積載しないで走行する場合と比較して大きな荷重を支えるため、運搬機械10の走行装置、懸架装置及びベッセル11を支持する機構等の受ける負荷が大きくなる。その結果、これらの装置及び機構の耐久性が低下する可能性がある。
本実施形態において、坑内MIで稼働する運搬機械10は、ドリフトDRと外周路TRとで形成される周回路を一方向に走行する。すなわち、周回路は一方通行であるが、一方通行の方向は変更することができる。本実施形態では、積載距離の総和と空荷距離の総和との差分が所定の規定値以上である場合、坑内MIで稼働する運搬機械10の走行方向を反転させる。すると、反転前はドローポイントDPからオアパスOPまでの距離の方がオアパスOPからドローポイントDPまでの距離よりも長かったのが、反転後は、前者が後者よりも短くなる。その結果、反転後においては坑内MIで稼働する運搬機械10の積載距離を空荷距離よりも短くすることができるので、運搬機械10の走行装置、懸架装置及びベッセル11を支持する機構等の耐久性の低下が抑制される。また、運搬機械10が高い負荷で走行する距離を短くすることができるので、運搬機械10の燃費を改善することができる。次に、運搬機械10の走行方向を反転させる処理についてより詳細に説明する。
図20に示すように、坑内MIは、複数本(この例では6本)のドリフトDRa、DRb、DRc、DRd、DRe、DRfと、複数本(この例では2本)の外周路TRa、TRbとを有する。図20に示す例においては、2本のドリフトDRc、DRdと2本の外周路TRa、TRbとで、図21に示す周回路CDIが形成される。周回路CDIを、適宜第1周回路CDIと称する。また、2本のドリフトDRb、DReと2本の外周路TRa、TRbとで、図21に示す周回路CDEが形成される。周回路CDEを、適宜第2周回路CDEと称する。本実施形態では、便宜上、鉱山Mが第1周回路CDI及び第2周回路CDEの2つを有する例を説明するが、鉱山Mが有する周回路CDの数は2つに限定されるものではない。周回路CDのパターンは、例えば図19で示した周回路CDa、CDbのようなものでもよい。
運搬機械10は、第1周回路CDI及び第2周回路CDEを一方向に走行する。図20に示す例では、ドリフトDR、クロスカットCR及び外周路TRを上方から見た場合の中心部(以下、適宜坑内中心部と称する)CPの周りを半時計回りに走行する。坑内中心部CPは、ドリフトDR、クロスカットCR及び外周路TRを上方から見た場合において、最も外側のドリフトDRa、DRfと、これらを接続する外周路TRa、TRbとで囲まれる部分の重心又は図心である。
鉱山Mの坑内MIには、オアパスOPが設けられる。本実施形態では、複数(2個)のオアパスOPa、OPbが坑内MIに設けられるが、その数は限定されず1個でもよい。オアパスOPa、OPbの位置に到達した運搬機械10Dは、積載している鉱石MRを排出する。第1周回路CDI及び第2周回路CDEは、それぞれ途中に共通のオアパスOPを有している。オアパスOPaは、第1周回路CDIのドリフトDRcとドリフトDRdとを接続する外周路TRaに設けられ、オアパスOPbは、第1周回路CDIのドリフトDRcとドリフトDRdとを接続するもう一つの外周路TRbに設けられる。外周路TRa、TRbは、第2周回路CDEが有するドリフトDRbとドリフトDReとを接続している。
オアパスOPa、OPbは、第1周回路CDIのドリフトDRcとドリフトDRdとの間、かつ第2周回路CDEのドリフトDRbとドリフトDReとの間に配置される。このような配置により、第1周回路CDI又は第2周回路CDEを走行する運搬機械10は、必ずオアパスOPに到達できる。また、運搬機械10の走行方向が反転した場合であっても、第1周回路CDI又は第2周回路CDEを走行する運搬機械10は、必ずオアパスOPに到達できる。
本実施形態において、最も外側のドリフトDRa、DRfは周回路CDを形成しないが、これらを含む周回路CDが形成されてもよい。この場合、周回路CDは、オアパスOPを途中に含むように形成される点及び2本のドリフトDRの間にオアパスOPが設けられる点は前述した通りである。
本実施形態において、前述したように、1本のドリフトDRには1台の積込機械30が配置される。ドリフトDRbには積込機械30bが、ドリフトDRcには積込機械30cが、ドリフトDRdには積込機械30dが、ドリフトDReには積込機械30eが配置される。積込機械30bは、ドリフトDRbと接続するクロスカットCRbに配置される。積込機械30cは、ドリフトDRcと接続するクロスカットCRcに配置される。積込機械30dは、ドリフトDRdと接続するクロスカットCRdに配置される。積込機械30eは、ドリフトDReと接続するクロスカットCReに配置される。運搬機械10は、ドリフトDRbにおいては積込機械30bから、ドリフトDRcにおいては積込機械30cから、ドリフトDRdにおいては積込機械30dから、ドリフトDReにおいては積込機械30eから鉱石MRが積み込まれる。
運搬機械10は、第1周回路CDI及び第2周回路CDEを、図21に示す第1走行方向RD1又は第2走行方向RD2のいずれか一方の方向に一方通行で走行する。第1走行方向RD1は、第1周回路CDI及び第2周回路CDEを上方から見た場合に、坑内中心部CPを反時計回りに走行する方向である。第2走行方向RD2は、第1周回路CDI及び第2周回路CDEを上方から見た場合に、坑内中心部CPを時計回りに走行する方向である。次に、運搬機械10の走行方向を反転させる処理の手順を説明する。
(運搬機械10の走行方向を判定させる処理の手順)
図22は、本実施形態に係る鉱山の管理システム1において、運搬機械10の走行方向を反転させる処理を示すフローチャートである。ステップS101において、図20に示す管理装置3は、積込機械30の移動があるか否かを判定する。積込機械30は、例えば、次に説明する配車処理によって、坑内MIに設けられた複数のドローポイントDPのうち1つに配車される。
図22は、本実施形態に係る鉱山の管理システム1において、運搬機械10の走行方向を反転させる処理を示すフローチャートである。ステップS101において、図20に示す管理装置3は、積込機械30の移動があるか否かを判定する。積込機械30は、例えば、次に説明する配車処理によって、坑内MIに設けられた複数のドローポイントDPのうち1つに配車される。
<積込機械30の配車処理>
本実施形態において、管理装置3は、積込機械30の配車処理を実行する。図1に示す、ブロックケービング工法により鉱石MRを採掘する鉱山Mは、図20に示すように、坑内MIに複数のドローポイントDPを有する。このため、複数のドローポイントDPからバランスよく鉱石MRが採掘されることが好ましい。鉱山Mの生産計画は、特定のドローポイントDPから偏って鉱石MRが採掘されないように、鉱山Mが有する複数のドローポイントDPからバランスよく鉱石MRが採掘されるように立案される。
本実施形態において、管理装置3は、積込機械30の配車処理を実行する。図1に示す、ブロックケービング工法により鉱石MRを採掘する鉱山Mは、図20に示すように、坑内MIに複数のドローポイントDPを有する。このため、複数のドローポイントDPからバランスよく鉱石MRが採掘されることが好ましい。鉱山Mの生産計画は、特定のドローポイントDPから偏って鉱石MRが採掘されないように、鉱山Mが有する複数のドローポイントDPからバランスよく鉱石MRが採掘されるように立案される。
管理装置3は、鉱山Mの生産計画にしたがって、積込機械30を複数のドローポイントDPに移動させて、鉱石MRを採掘させる。また、前述したように、ドローポイントDPに鉱石詰まりが発生したり、ドローポイントDPに積込機械30が掘削又は搬送できない鉱石MRの大塊が現れたりすることがある。このような場合も、管理装置3は、鉱石詰まり又は鉱石MRの大塊が現れていないドローポイントDPに積込機械30を移動させる。このため、管理装置3は、積込機械30の配車処理を実行する。この配車処理には、第1の配車処理及び第2の配車処理がある。いずれも、鉱山Mの生産計画と実際の生産量(採掘量)との差に基づいて、積込機械30が配置されるドローポイントDPが決定される。管理装置3は、第1の配車処理又は第2の配車処理のいずれか一方を実行することにより、積込機械30が配置されるドローポイントDPを決定する。
<第1の配車処理>
第1の配車処理において、管理装置3は、積込機械30が配置されるドローポイントDPの優先順位を、ドローポイントDPの実際の生産量が鉱山Mの生産計画により定められたそのドローポイントDPの生産量よりも小さく、かつ鉱山Mの生産計画による生産量と実際の生産量との差が相対的に大きいドローポイントDPの順とする。そして、管理装置3は、この優先順位にしたがって積込機械30が配置されるドローポイントDPを決定する。この場合、1本のドリフトDRには、最大1台の積込機械30が配置されるものとする。このようにすることで、積込機械30が配置されるドローポイントDPを決定する際の処理が比較的簡単になる。
第1の配車処理において、管理装置3は、積込機械30が配置されるドローポイントDPの優先順位を、ドローポイントDPの実際の生産量が鉱山Mの生産計画により定められたそのドローポイントDPの生産量よりも小さく、かつ鉱山Mの生産計画による生産量と実際の生産量との差が相対的に大きいドローポイントDPの順とする。そして、管理装置3は、この優先順位にしたがって積込機械30が配置されるドローポイントDPを決定する。この場合、1本のドリフトDRには、最大1台の積込機械30が配置されるものとする。このようにすることで、積込機械30が配置されるドローポイントDPを決定する際の処理が比較的簡単になる。
<第2の配車処理>
第2の配車処理において、管理装置3は、積込機械30が配置されるドローポイントDPを、同一のドリフトDRにつながるドローポイントDPから決定し、決定されたドローポイントDPでの生産量を、鉱山Mの生産計画により定められた生産量、すなわち目標生産量と、実際の生産量、すなわち実生産量との差に基づいて調整する。このとき、管理装置3は、積込機械30が既に所定のドローポイントDPに配置されている場合、所定のドローポイントDPに隣接する他のドローポイントDPを、積込機械30が次に配置されるドローポイントDPとして決定する。第2の配車処理によれば、積込機械30の移動量を少なくすることができる。
第2の配車処理において、管理装置3は、積込機械30が配置されるドローポイントDPを、同一のドリフトDRにつながるドローポイントDPから決定し、決定されたドローポイントDPでの生産量を、鉱山Mの生産計画により定められた生産量、すなわち目標生産量と、実際の生産量、すなわち実生産量との差に基づいて調整する。このとき、管理装置3は、積込機械30が既に所定のドローポイントDPに配置されている場合、所定のドローポイントDPに隣接する他のドローポイントDPを、積込機械30が次に配置されるドローポイントDPとして決定する。第2の配車処理によれば、積込機械30の移動量を少なくすることができる。
坑内MIでは複数の積込機械30が稼働しているが、これらのうち少なくとも1台が現時点のドローポイントDPから移動することが決定された場合、管理装置3は、ステップS101において積込機械30の移動があると判定する。第1の配車処理又は第2の配車処理によって、積込機械30が移動することになったら(ステップS101、Yes)、管理装置3は、処理をステップS102に進める。坑内MIのすべての積込機械30が移動しない場合(ステップS101、No)、管理装置3は、処理を終了させる。
ステップS102において、管理装置3は、坑内MIで稼働しているすべての運搬機械10について、空荷距離Leの総和ΣLeと、積載距離Lfの総和ΣLfとを求める。空荷距離Le及び積載距離Lfは、例えば、ドローポイントDPの位置と、オアパスOPの位置と、運搬機械10の走行方向とによって求められる。1台の運搬機械10についての空荷距離Le及び積載距離Lfは、運搬機械10が周回路CDを1周するときの値である。
図20に示す、ドリフトDRb及びドリフトDReの運搬機械10S及び運搬機械10Fを例とすると、これらは、図21に示す第2周回路CDE、具体的には外周路TRb、ドリフトDRe、外周路TRa及びドリフトDRbを通る。第2周回路CDEには、積込機械30が配置された2つのドローポイントDP、具体的には積込機械30bが配置されたドローポイントDPb及び積込機械30eが配置されたドローポイントDPeが存在する。前者はドリフトDRbに設けられ、後者はドリフトDReに設けられる。
ドリフトDRb及びドリフトDRcの運搬機械10S及び運搬機械10Fは、ドローポイントDPbで鉱石MRが積載された後、ドリフトDRb及び外周路TRbを通ってオアパスOPbに向かう。運搬機械10S及び運搬機械10Fは、オアパスOPbで鉱石MRを排出した後、空荷の状態で外周路TRb及びドリフトDReを通って次のドローポイントDPeに到達する。運搬機械10S及び運搬機械10Fは、ドローポイントDPeの積込機械30eから鉱石MRが積み込まれた後、ドリフトDRe及び外周路TRaを通ってオアパスOPaに到達する。オアパスOPaに到達した運搬機械10S及び運搬機械10Fは、鉱石MRを排出した後、外周路TRa及びドリフトDRbを通ってドローポイントDPbに到達し、積込機械30bから鉱石MRが積み込まれる。
運搬機械10S及び運搬機械10Fの積載距離Lfは、ドローポイントDPbからドリフトDRb及び外周路TRbを通ってオアパスOPbに至るまでの距離と、ドローポイントDPeからドリフトDRe及び外周路TRaを通ってオアパスOPaに至るまでの距離との和である。また、運搬機械10S及び運搬機械10Fの空荷距離Leは、オアパスOPbから外周路TRb及びドリフトDReを通ってドローポイントDPeに至るまでの距離と、オアパスOPaから外周路TRa及びドリフトDRbを通ってドローポイントDPbに至るまでの距離との和である。運搬機械10S及び運搬機械10Fについて、図20に示す例では、積載距離Lfよりも空荷距離Leの方が長くなっている。
坑内MIで稼働しているすべての運搬機械10について、空荷距離Leの総和ΣLeと、積載距離Lfの総和ΣLfとが求められたら、ステップS103において、管理装置3は、積載距離Lfの総和ΣLfと空荷距離Leの総和ΣLeとの差分ΔLを求め、差分ΔLと予め定められた規定値ΔLcとを比較する。比較の結果、差分ΔLが所定の規定値ΔLc以上である場合には(ステップS103、Yes)、管理装置3は、処理をステップS104に進める。差分ΔLが所定の規定値ΔLc未満である場合には(ステップS103、No)、管理装置3は、処理を終了させる。規定値ΔLcは、0も含む。この場合、積載距離Lfの総和ΣLfが空荷距離Leの総和ΣLe以上であれば、処理がステップS104に進められ、積載距離Lfの総和ΣLfが空荷距離Leの総和ΣLe未満であれば、処理が終了する。
規定値ΔLcを0にしてもよいが、この場合、空荷距離Leよりも積荷距離Lfが大きくなったら、直ちに運搬機械10の走行方向が反転し、その直後に積荷距離Lfの方が空荷距離Leよりも大きくなることがある。この場合、再び走行方向が反転するので、規定値ΔLcを0にすると、走行方向の反転が短い周期で繰り返されるハンチングのような現象が発生する可能性がある。これを回避するために、規定値ΔLcを設けることにより、走行方向の反転が短い周期で繰り返される現象を回避できる。鉱山Mの規模にもよるが、規定値ΔLcを、例えば50m程度とする程積荷距離が長くなってから反転させれば、運搬機械10の配車の管理によらず、走行方向の反転が短い周期で繰り返される現象を回避できる。
ステップS104において、管理装置3は、積込機械30の移動が完了したか否かを判定する。積込機械30の移動が完了していない場合(ステップS104、No)、管理装置3は、ステップS105において、積込機械30の移動が完了するまで待機する。積込機械30の移動が完了した場合(ステップS104、Yes)、管理装置3は、ステップS106において、坑内MIで稼働するすべての運搬機械10に対して、運搬機械10の走行方向を反転させる指令としての反転指令を送信する。すなわち、管理装置3は、積込機械30が異なるドローポイントDPに到着した時点以降に、坑内MIで稼働する複数の運搬機械10に対して反転指令を送信する。
反転指令は、無線通信装置4からアンテナ4Aを介して運搬機械10に送信される。送信された反転指令は、図12に示す、運搬機械10のアンテナ15及び通信装置25を介して、処理装置71に入力される。本実施形態において、反転指令は、坑内MIで稼働する積込機械30にも送信される。この場合、無線通信装置4からアンテナ4Aを介して積込機械30に送信された反転指令は、図17に示す、積込機械30のアンテナ53及び通信装置52を介して、処理装置76に入力されてもよい。
ステップS107に進み、管理装置3は、すべての運搬機械10が待機状態にあるか否かを判定する。例えば、管理装置3から反転指令が送信されたタイミングにおいて、積込機械30から鉱石MRの積み込みを受けている運搬機械10が存在したり、オアパスOPで鉱石MRを排出している運搬機械10が存在したりする。このような運搬機械10は、反転指令を受信してもすぐには走行方向を反転させて走行することができない。また、走行方向を反転させると、運搬機械10は目的地が設定し直される必要がある。このため、本実施形態において、管理装置3は、坑内MIで稼働するすべての運搬機械10について、走行方向を反転させて走行できる準備が整ってから、各運搬機械10の走行方向を、反転指令が送信される前に対して反転させて走行させる。
反転指令を受信した運搬機械10は、反転指令を受信した後に、現在の状態に応じて定められた処理を実行する。この処理について説明する。
(処理1)
運搬機械10は、現在の状態が、積込機械30に向かっている場合、これから鉱石MRの積み込みを受けようとする積込機械(以下、適宜目標積込機械と称する)30の位置に、既に他の運搬機械10が存在するときには、現在の位置で待機する。図20に示す例において、ドリフトDRb、DReを走行する運搬機械10Eは、目標積込機械30の位置に既に他の運搬機械10Sが存在して、目標積込機械30から鉱石MRの積み込みを受けている。したがって、運搬機械10Eは、現在の位置で停止して、管理装置3から反転走行開始の指令があるまで待機する。
運搬機械10は、現在の状態が、積込機械30に向かっている場合、これから鉱石MRの積み込みを受けようとする積込機械(以下、適宜目標積込機械と称する)30の位置に、既に他の運搬機械10が存在するときには、現在の位置で待機する。図20に示す例において、ドリフトDRb、DReを走行する運搬機械10Eは、目標積込機械30の位置に既に他の運搬機械10Sが存在して、目標積込機械30から鉱石MRの積み込みを受けている。したがって、運搬機械10Eは、現在の位置で停止して、管理装置3から反転走行開始の指令があるまで待機する。
目標積込機械30に向かっている運搬機械10は、自身が向かう目標積込機械30の位置に他の運搬機械10が存在しない場合又は目標積込機械30に向かっている他の運搬機械10が存在しない場合、そのまま目標積込機械30の位置まで走行して待機する。このようにすれば、運搬機械10は、走行方向を反転させた場合に、鉱石MRの積み込みから開始することができる。図20に示す例において、ドリフトDRc、DRdを走行する運搬機械10Eは、目標積込機械30c、30dの位置に、他の運搬機械10又は目標積込機械30c、30dに向かう運搬機械10が存在しない。この場合、ドリフトDRc、DRdを走行する運搬機械10Eは、積込機械30c、30dの位置で停止して、管理装置3から反転走行開始の指令があるまで待機する。運搬機械10は、待機状態に入ったら、待機状態であることを示す信号を管理装置3に送信する(以下同様)。
(処理2)
運搬機械10は、現在の状態が、積込機械30から鉱石MRの積み込みを受けている場合、鉱石MRの積み込みが継続される。鉱石MRの積み込みが終了したら、運搬機械10はその位置で停止した状態で待機する。図20に示す例では、ドリフトDRbのクロスカットCRbの運搬機械10S及びドリフトDReのクロスカットCReの運搬機械10Sが、積込機械30b及び積込機械30eから鉱石MRの積み込みを受けている。これらの運搬機械10Sは、鉱石MRの積み込みが終了した場合、その場所で停止し、管理装置3から反転走行開始の指令があるまで待機する。
運搬機械10は、現在の状態が、積込機械30から鉱石MRの積み込みを受けている場合、鉱石MRの積み込みが継続される。鉱石MRの積み込みが終了したら、運搬機械10はその位置で停止した状態で待機する。図20に示す例では、ドリフトDRbのクロスカットCRbの運搬機械10S及びドリフトDReのクロスカットCReの運搬機械10Sが、積込機械30b及び積込機械30eから鉱石MRの積み込みを受けている。これらの運搬機械10Sは、鉱石MRの積み込みが終了した場合、その場所で停止し、管理装置3から反転走行開始の指令があるまで待機する。
(処理3)
運搬機械10は、現在の状態がオアパスOPに向かっている場合、目標とするオアパスOPまで走行して、そこで鉱石MRを排出する。鉱石MRを排出した後、他の運搬機械10の通行又は鉱石MRの排出の妨げとなる場合、運搬機械10は邪魔にならない位置に移動して停止し、管理装置3から反転走行開始の指令があるまで待機する。運搬機械10が邪魔にならない位置に移動する場合、オアパスOPよりも、現時点における周回路CDの走行方向の前方まで移動して待機することが好ましい(以下同様)。このようにすれば、一方通行の周回路CD内であっても、他の運搬機械10のスペースを確実に確保することができる。
運搬機械10は、現在の状態がオアパスOPに向かっている場合、目標とするオアパスOPまで走行して、そこで鉱石MRを排出する。鉱石MRを排出した後、他の運搬機械10の通行又は鉱石MRの排出の妨げとなる場合、運搬機械10は邪魔にならない位置に移動して停止し、管理装置3から反転走行開始の指令があるまで待機する。運搬機械10が邪魔にならない位置に移動する場合、オアパスOPよりも、現時点における周回路CDの走行方向の前方まで移動して待機することが好ましい(以下同様)。このようにすれば、一方通行の周回路CD内であっても、他の運搬機械10のスペースを確実に確保することができる。
(処理4)
運搬機械10は、現在の状態がオアパスOPで鉱石MRを排出している場合、鉱石MRの排出を継続する。鉱石MRの積載が終了した後、運搬機械10が他の運搬機械10の通行又は鉱石MRの排出の妨げとなる場合、運搬機械10は邪魔にならない位置に移動して停止し、管理装置3から反転走行開始の指令があるまで待機する。
運搬機械10は、現在の状態がオアパスOPで鉱石MRを排出している場合、鉱石MRの排出を継続する。鉱石MRの積載が終了した後、運搬機械10が他の運搬機械10の通行又は鉱石MRの排出の妨げとなる場合、運搬機械10は邪魔にならない位置に移動して停止し、管理装置3から反転走行開始の指令があるまで待機する。
(搬機械10が反転指令を受信した後における積込機械30の処理)
搬機械10が反転指令を受信した後において、鉱石MRを運搬機械10に積み込んでいる積込機械30は、その作業が終了するまで継続する。鉱石MRを運搬機械10に積み込んでいない積込機械30は、そのままの状態で待機する。運搬機械10が到着した場合、この運搬機械10に鉱石MRを積み込む。
搬機械10が反転指令を受信した後において、鉱石MRを運搬機械10に積み込んでいる積込機械30は、その作業が終了するまで継続する。鉱石MRを運搬機械10に積み込んでいない積込機械30は、そのままの状態で待機する。運搬機械10が到着した場合、この運搬機械10に鉱石MRを積み込む。
ステップS107において、すべての運搬機械10が待機状態に入っていない場合(ステップS107、No)、ステップS108において、管理装置3は、運搬機械10が待機状態に入るまで待機する。すべての運搬機械10が待機状態に入っていない場合とは、前述した処理1から処理4の少なくとも1つの実行が完了していない状態である。これに対して、すべての運搬機械10が待機状態に入った場合とは、前述した処理1から処理4のすべての実行が完了した状態である。
すべての運搬機械10が待機状態に入った場合(ステップS107、Yes)、ステップS109において、管理装置3は、待機中の運搬機械10に対して反転走行を開始させる指令を送信する。運搬機械10の走行方向が反転すると、運搬機械10の向かう目的地も異なる。このため、管理装置3は、運搬機械10の現在位置、反転後の走行方向及び積荷の積載状態に応じて、それぞれの運搬機械10の新たな目的地を生成して、反転走行を開始させる指令とともにそれぞれの運搬機械10に送信する。
反転走行を開始させる指令及び新たな目的地を受信した運搬機械10は、ステップS110において、反転指令を受信する前の走行方向を反転させ、新たな目的地に向かって走行を開始する。このように、坑内MIで稼働するすべての運搬機械10は、現在の状態に応じて定められた処理1から処理4がすべて実行された後に、それぞれの走行方向を反転して走行を開始する。
坑内MIで稼働するすべての運搬機械10は、反転指令を受信する前と走行方向が反転することにより、反転前における積載距離Lfが反転後における空荷距離Leになる。その結果、走行方向が反転した後において、すべての運搬機械10は、積載距離Lfが空荷距離Leよりも短くなるので、耐久性低下が抑制される。
本実施形態において、坑内MIで稼働するすべての運搬機械10は、反転指令を受信した後、現在の状態に応じて定められた処理1から処理4の実行の有無に関わらず、それぞれの走行方向を反転した走行を開始してもよい。このようにすると、処理1から処理4がすべて実行されるまで待機する必要はなくなるので、運搬機械10の稼働の停止期間を短縮して鉱山Mの生産性の低下を抑制することができる。
反転指令を受信した直後に運搬機械10の走行方向を反転させて走行させる場合、管理装置3は、走行方向を反転させた後の新たな目的地を反転指令とともに送信する。このようにすることで、運搬機械10は、反転指令を受信した直後に、新たな目的地に向かって移動することができる。
反転指令を受信した直後に運搬機械10の走行方向を反転させて走行させる場合、反転指令を受信した時点で鉱石MRの積み込み中及び鉱石MRの排出中の運搬機械10は、それぞれの作業が終了してから反転走行を開始する。このようにすることで、積み込み作業又は排出作業中に運搬機械10が動き出すことを回避することができる。
(積込機械30の設置例)
本実施形態において、複数のドリフトDRは一方向に向かって延在し、かつ並んで配列されており、複数のドリフトDRをそれぞれの両端で接続する一対の外周路TRa、TRbにはそれぞれオアパスOPa、OPbが設けられる。そして、同一の周回路CDには、2つのオアパスOPa、OPbが設けられる。このような坑内MIで稼働し、かつ同一の周回路CDに設置される複数の積込機械30は、坑内中心部CPに対して点対称となる領域に設置される。
本実施形態において、複数のドリフトDRは一方向に向かって延在し、かつ並んで配列されており、複数のドリフトDRをそれぞれの両端で接続する一対の外周路TRa、TRbにはそれぞれオアパスOPa、OPbが設けられる。そして、同一の周回路CDには、2つのオアパスOPa、OPbが設けられる。このような坑内MIで稼働し、かつ同一の周回路CDに設置される複数の積込機械30は、坑内中心部CPに対して点対称となる領域に設置される。
ドリフトDR、クロスカットCR及び外周路TRを上方から見た場合、一対のオアパスOPa、OPbを結び、ドリフトDRに平行かつ坑内中心部CPを通る直線LLと、この直線LLに交差し、かつ外周路TRと平行な直線LRとで形成される二次元座標系を考える。二次元座標系において、第1象限ER1と第3象限ER3とが点対称となる領域である同様に、二次元座標系において、第2象限ER2と第4象限ER4とが点対称となる領域である。
図20に示す例では、ドリフトDRbのクロスカットCRbと、この部分と点対称となるドリフトDReのクロスカットCReとに、それぞれ積込機械30bと積込機械30eとが設置されている。積込機械30bと積込機械30eは、図21に示す第2周回路CDEに設置されている。また、ドリフトDRcのクロスカットCRcと、この部分と点対称となるドリフトDRdのクロスカットCRdとに、それぞれ積込機械30cと積込機械30dとが設置されている。積込機械30cと積込機械30dとは、図21に示す第1周回路CDIに設置されている。
同一の周回路CDに設置される複数の積込機械30が、坑内中心部CPに対して点対称となるように設置されると、これらが設置される周回路CDに沿った積込機械30同士の距離が周回路CDの長さの1/2になる。さらに、同一の周回路CDに設置される複数の積込機械30同士の間に、オアパスOPが設けられる。
例えば、第2周回路CDEに設置される積込機械30b、30eが、坑内中心部CPに対して点対称となるように設置されることにより、積込機械30bとオアパスOPbまでの距離と、積込機械30eとオアパスOPaまでの距離とは同一になる。また、積込機械30bとオアパスOPaまでの距離と、積込機械30eとオアパスOPbまでの距離とは同一になる。このため、これらの積込機械30b、30eが鉱石MRを積み込み、かつ第2周回路CDEを走行するすべての運搬機械10は、積載距離Lfがほぼ同一になり、空荷距離Leもほぼ同一になる。第1周回路CDIに設けられた積込機械30c、30dについても同様である(以下同様)。
このように、複数の積込機械30が坑内中心部CPに対して点対称となる領域に設置された周回路CDを走行する運搬機械10は、積載距離Lfがほぼ同一、かつ空荷距離Leもほぼ同一になる。その結果、前述した周回路CDを走行するすべての運搬機械10に対する負荷がほぼ同等になる。また、積載距離Lfの総和が低減されるので、積込機械10の走行方向を反転させることにより、運搬機械10に対する負荷をより効果的に低減できる。
同一の周回路CDに、坑内中心部CPに対して点対称となる領域に複数の積込機械30が設置される場合、一方の積込機械30が異なるドローポイントDPに移動する方向と、他方の積込機械30が異なるドローポイントDPに移動する方向とは正反対になることが好ましい。図20に示す例において、第2周回路CDEに設置される一方の積込機械30bが他方の外周路TRbから一方の外周路TRaに向かって異なるドローポイントDPに移動するとする。すなわち、一方の積込機械30bは、ドリフトDRの他方の端部側に設けられたドローポイントDPから一方の端部側に設けられたドローポイントDPに向かって移動するとする。
この場合、坑内中心部CPに対して、積込機械30bと点対称になる第2周回路CDEの位置に設置された他方の積込機械30eは、一方の外周路TRaから他方の外周路TRbに向かって異なるドローポイントDPに移動する。すなわち、他方の積込機械30eは、ドリフトDRの一方の端部側におけるドローポイントDPから他方の端部側のドローポイントDPに向かって移動する。このようにすることで、点対称となる領域に設置された積込機械30bと積込機械30eとは、両者の距離を一定に保った状態で異なるドローポイントDP間を移動することができる。
また、一方の積込機械30が異なるドローポイントDPに移動する方向と、他方の積込機械30が異なるドローポイントDPに移動する方向とが正反対となるようにすることで、両者の距離は一定に保たれる。このため、これらの積込機械30が設置された周回路CDを走行するすべての運搬機械10は、積込機械30のドローポイントDPが移動するとき、積載距離Lfと空荷距離Leとがほぼ同様に変化する。
このため、周回路CDを走行するすべての運搬機械10において、それぞれの積載距離Lf及び空荷距離Leのばらつきが小さくなるので、すべての運搬機械10が積載状態で走行する距離を同程度にすることができる。その結果、前述した周回路CDを走行するすべての運搬機械10に対する負荷がほぼ同等になる。
第2周回路CDEにおいて、一方の外周路TRaから他方の外周路TRbに向かう方向を基準として坑内中心部CPよりも左側のドリフトDReは他方の外周路TRbから一方の外周路TRaへ向かう一方通行であり、右側のドリフトDRbは一方の外周路TRaから他方の外周路TRbへ向かう一方通行である。初期において、積込機械30eは、一方の外周路TRaに最も近いクロスカットCRに配置され、積込機械30bは、他方の外周路TRbに最も近いクロスカットCRに配置されるとする。この状態では、積荷距離Lfは最小であり、空荷距離Leよりも小さい状態である。
鉱石MRの採掘が進むにしたがって、積込機械30eは、他方の外周路TRb側のクロスカットCRに向かって順次移動し、積込機械30bは、一方の外周路TRa側のクロスカットCRに向かって順次移動する。すると、積荷距離Lfが徐々に長くなり、空荷距離Leは徐々に短くなる。両者の差分ΔLは、徐々に大きくなる。ΔLが規定値ΔLc以上になったら、運搬機械10の走行方向は反転する。運搬機械10の走行方向が反転する場合、反転後における走行方向の前方側に積込機械30b、30eの初期位置が設定される。
鉱石MRの採掘の進行に伴う掘削機械の移動により、坑内中心部CPの両側に設けられているドリフトDRb、DReを走行する運搬機械10の積荷距離Lfと空荷距離Leとの差分ΔLは同じ傾向で小さくなる。積荷距離Lfと空荷距離Leとの大小が逆転してからも同様に、積荷距離Lfは増加するので、差分ΔLが規定値ΔLc以上になったら、運搬機械10の走行方向を反転させる。このようにして、管理装置3は、積荷距離Lfを抑制する。
管理装置3が、各ドリフトDRb、DReに設置された積込機械30b、30eをランダムに配車すると、運搬機械10の走行方向を反転させる必要があるか否かの判定の頻度が多くなり、鉱山Mの生産性の低下を招く可能性がある。鉱山の管理システム1は、坑内中心部部CPに対して対象となる位置に積込機械30e、30bを配置し、前者を一方のドローポイントDPa側から他方のドローポイントDPb側に向かって移動させ、後者を他方のドローポイントDPb側から一方のドローポイントDPa側に向かって移動させる。すなわち、複数のドリフトDRの両方の端部側に設けられた一対のオアパスOPa、OPbを結ぶ直線LLに対して両側のドリフトDRにそれぞれ積込機械30b、30eが配置され、かつ直線LLを基準とした一方側と他方側とでそれぞれの積込機械30b、30eの移動方向は反対になる。直線LLは、ドリフトDRに平行である。このようにすることで、鉱山の管理システム1は、積荷距離Lf及び空荷距離Leとの増減傾向が明瞭に発生しやすくして、運搬機械10の走行方向を反転させる頻度を抑制し、かつ積荷距離Lfを短くすることができる。
積込機械30b、30eを、例えば隣接するドローポイントDPに移動させるタイミング又は頻度は、運搬機械10の配車の状態及び積込機械30b、30eのフィーダー又は回転ローラーの速度が調整されることにより、ある程度調整が可能である。管理装置3は、前述した調整を実行することにより、積込機械30b、30eを、隣接するドローポイントDPに移動させるタイミングを揃えて、坑内中心部CPに対して対象となる位置に積込機械30e、30bを配置された積込機械30b、30eを、滑車の両側に吊した一対の錘が移動するように移動させる。
なお、前述の実施形態においては、積込機械30の掘削装置として回転ローラー33が使用される例について説明した。積込機械30は、刃先を有するバケットを用いて掘削を行ってもよいし、積込を行ってもよい。
以上、実施形態を説明したが、前述した内容により実施形態が限定されるものではない。また、前述した構成要素には、当業者が容易に想定できるもの、実質的に同一のもの、いわゆる均等の範囲のものが含まれる。さらに、前述した構成要素は適宜組み合わせることが可能である。さらに、実施形態の要旨を逸脱しない範囲で構成要素の種々の省略、置換及び変更のうち少なくとも1つを行うことができる。
1 鉱山の管理システム
3 管理装置
3C 処理装置
3M 記憶装置
5 給電ケーブル
10 運搬機械
10B 車体
11 ベッセル
12A、12B 車輪
14 蓄電器
24 駆動制御装置
30 積込機械
30B 車体
31 フィーダー
32 支持機構
33 回転ローラー
34 走行装置
35 貫入部材
36 回転体
40、41 情報収集装置
48 駆動制御装置
70、75 制御装置
71、76 処理装置
72、77 記憶装置
80 切替機構
90 蓄電器保持装置
CR、CRa、CRb、CRc、CRd、CRe クロスカット(第2坑道)
CD、CDa、CDb 周回路
CDI 第1周回路
CDE 第2周回路
DP、DPa、DPb、DPc、DPe ドローポイント(採掘場所)
DR、DRa、DRb、DRc、DRd、DRe、DRf ドリフト(第1坑道)
EX 蓄電器取扱装置
OP、OPa、OPb オアパス(排土場所)
RM 地山
TR、TRa、TRb 外周路(第3坑道)
3 管理装置
3C 処理装置
3M 記憶装置
5 給電ケーブル
10 運搬機械
10B 車体
11 ベッセル
12A、12B 車輪
14 蓄電器
24 駆動制御装置
30 積込機械
30B 車体
31 フィーダー
32 支持機構
33 回転ローラー
34 走行装置
35 貫入部材
36 回転体
40、41 情報収集装置
48 駆動制御装置
70、75 制御装置
71、76 処理装置
72、77 記憶装置
80 切替機構
90 蓄電器保持装置
CR、CRa、CRb、CRc、CRd、CRe クロスカット(第2坑道)
CD、CDa、CDb 周回路
CDI 第1周回路
CDE 第2周回路
DP、DPa、DPb、DPc、DPe ドローポイント(採掘場所)
DR、DRa、DRb、DRc、DRd、DRe、DRf ドリフト(第1坑道)
EX 蓄電器取扱装置
OP、OPa、OPb オアパス(排土場所)
RM 地山
TR、TRa、TRb 外周路(第3坑道)
Claims (9)
- 鉱体の内部又は下方に設置された採掘場所と、
前記鉱体の内部又は下方に設置された排土場所と、
前記鉱体の内部又は下方に設置された複数の第1坑道、前記採掘場所と前記第1坑道とを接続する第2坑道及び複数の前記第1坑道と接続される第3坑道と、を含み、
前記第3坑道と前記第1坑道とで周回路が形成される鉱山で前記鉱体から鉱石を採掘するにあたり、
前記周回路を一方向に走行し、かつ前記採掘場所で採掘された前記鉱石を積載して前記排土場所まで運搬してから排出する運搬機械と、
前記採掘場所で前記鉱石を掘削し、掘削した前記鉱石を前記運搬機械に積み込む積込機械と、
前記積込機械が異なる採掘場所へ移動することが決定した場合、前記周回路で稼働しているすべての前記運搬機械について、前記鉱石を積み込まれた位置から前記排土場所まで移動する第1距離の総和と、前記排土場所から前記鉱石が積み込まれる位置まで移動する第2距離の総和とを求め、前記第1距離の総和と前記第2距離の総和との差分が予め定められた規定値以上である場合には、前記運搬機械の走行方向を反転させる管理装置と、
を含む、鉱山の管理システム。 - 前記管理装置は、
前記積込機械が前記異なる採掘場所に到着した時点以降に、複数の前記運搬機械に対して、走行方向を反転させる指令を送信する、請求項1に記載の鉱山の管理システム。 - 複数の前記運搬機械は、
前記走行方向を反転させる指令を受信した後に、現在の状態に応じて定められた処理を実行し、前記運搬機械が前記処理を実行した後に、
それぞれの走行方向を反転して走行を開始する、請求項1又は請求項2に記載の鉱山の管理システム。 - 複数の前記運搬機械は、
前記走行方向を反転させる指令を受信した後に、それぞれの走行方向を反転して走行を開始する、請求項1から請求項3のいずれか1項に記載の鉱山の管理システム。 - 前記鉱山は、
前記排土場所を複数備える、請求項1から請求項4のいずれか1項に記載の鉱山の管理システム。 - 複数の前記第1坑道は、
一方向に向かって延在し、かつ並んで配列され、
前記積込機械は、それぞれの前記第1坑道に対して1台ずつ、かつ複数の前記第1坑道、前記第2坑道及び前記第3坑道を上方から見たときの中心部に対して点対称となる領域に設置される、請求項5に記載の鉱山の管理システム。 - 点対称となるように設置された一方の前記積込機械は、前記第1坑道の一方の端部側の採掘場所から他方側の端部側の採掘場所に向かって移動し、他方の前記積込機械は、前記第1坑道の他方の端部側の採掘場所から一方の端部側の採掘場所に向かって移動する、請求項6に記載の鉱山の管理システム。
- 一対の前記排土場所が、複数の前記第1坑道の両方の端部側に設けられ、
一対の前記排土場所を結ぶ直線に対して両側の前記第1坑道にそれぞれ前記積込機械が配置され、かつ前記直線を基準とした一方側と他方側とでそれぞれの前記積込機械の移動方向が反対になる、請求項1から請求項5のいずれか1鋼に記載の鉱山の管理システム。 - 鉱体の内部又は下方に設置された採掘場所と、
前記鉱体の内部又は下方に設置された複数の排土場所と、
前記鉱体の内部又は下方に設置された複数の第1坑道、前記採掘場所と前記第1坑道とを接続する第2坑道及び複数の前記第1坑道と接続される第3坑道と、を含み、
前記第3坑道と前記第1坑道とで周回路が形成される鉱山で前記鉱体から鉱石を採掘するにあたり、
前記周回路を一方向に走行し、かつ前記採掘場所で採掘された前記鉱石を積載して前記排土場所まで運搬してから排出する運搬機械と、
前記第2坑道に留まって、前記採掘場所で前記鉱石を掘削し、掘削した前記鉱石を前記採掘場所から離れる方向に搬送して、前記運搬機械に積み込む積込機械と、
前記積込機械が異なる採掘場所へ移動することが決定した場合、前記周回路で稼働しているすべての前記運搬機械について、前記鉱石を積み込まれた位置から前記排土場所まで移動する第1距離の総和と、前記排土場所から前記鉱石が積み込まれる位置まで移動する第2距離の総和とを求め、前記第1距離の総和と前記第2距離の総和との差分が予め定められた規定値以上である場合には、前記積込機械が前記異なる採掘場所に到着した時点以降に、複数の前記運搬機械に対して、走行方向を反転させる指令を送信する管理装置と、を含み、
複数の前記運搬機械は、前記走行方向を反転させる指令を受信した以降に、それぞれの走行方向を反転して走行を開始する、鉱山の管理システム。
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2014-074560 | 2014-03-31 | ||
| JP2014074560 | 2014-03-31 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2015151734A1 true WO2015151734A1 (ja) | 2015-10-08 |
Family
ID=54240067
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP2015/056872 Ceased WO2015151734A1 (ja) | 2014-03-31 | 2015-03-09 | 鉱山の管理システム |
Country Status (1)
| Country | Link |
|---|---|
| WO (1) | WO2015151734A1 (ja) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021038607A (ja) * | 2019-09-05 | 2021-03-11 | 株式会社小松製作所 | 計測システム及び計測方法 |
| CN119981900A (zh) * | 2025-03-03 | 2025-05-13 | 辽宁鑫丰矿业(集团)有限公司 | 露天矿开采系统 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2005061984A (ja) * | 2003-08-12 | 2005-03-10 | Hitachi Constr Mach Co Ltd | 建設機械の荷重計測装置 |
| JP2005139000A (ja) * | 2003-10-14 | 2005-06-02 | Toyota Industries Corp | 産業車両の稼働状況を管理するシステムおよび方法 |
| US20070027612A1 (en) * | 2005-07-26 | 2007-02-01 | Barfoot Timothy D | Traffic management system for a passageway environment |
| US20070170771A1 (en) * | 2006-01-25 | 2007-07-26 | Peabody Energy Corporation | Underground Mine and Method of Mining |
-
2015
- 2015-03-09 WO PCT/JP2015/056872 patent/WO2015151734A1/ja not_active Ceased
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2005061984A (ja) * | 2003-08-12 | 2005-03-10 | Hitachi Constr Mach Co Ltd | 建設機械の荷重計測装置 |
| JP2005139000A (ja) * | 2003-10-14 | 2005-06-02 | Toyota Industries Corp | 産業車両の稼働状況を管理するシステムおよび方法 |
| US20070027612A1 (en) * | 2005-07-26 | 2007-02-01 | Barfoot Timothy D | Traffic management system for a passageway environment |
| US20070170771A1 (en) * | 2006-01-25 | 2007-07-26 | Peabody Energy Corporation | Underground Mine and Method of Mining |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2021038607A (ja) * | 2019-09-05 | 2021-03-11 | 株式会社小松製作所 | 計測システム及び計測方法 |
| WO2021044914A1 (ja) * | 2019-09-05 | 2021-03-11 | 株式会社小松製作所 | 計測システム及び計測方法 |
| JP7357489B2 (ja) | 2019-09-05 | 2023-10-06 | 株式会社小松製作所 | 計測システム及び計測方法 |
| US12345159B2 (en) | 2019-09-05 | 2025-07-01 | Komatsu Ltd. | Measurement system and measurement method |
| CN119981900A (zh) * | 2025-03-03 | 2025-05-13 | 辽宁鑫丰矿业(集团)有限公司 | 露天矿开采系统 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6416882B2 (ja) | 鉱山の管理システム | |
| JP6321935B2 (ja) | 鉱山の採掘システム | |
| JP6193075B2 (ja) | 運搬機械 | |
| JP6243687B2 (ja) | 運搬機械 | |
| WO2015046598A1 (ja) | 運搬機械 | |
| JP6297807B2 (ja) | 鉱山の管理システム | |
| JP6359817B2 (ja) | 鉱山の管理システム | |
| WO2015151734A1 (ja) | 鉱山の管理システム | |
| WO2015046610A1 (ja) | 運搬機械 | |
| JP2015068142A (ja) | 積込機械 | |
| WO2015046612A1 (ja) | 積込機械 | |
| WO2015046590A1 (ja) | 積込機械 | |
| WO2015046597A1 (ja) | 積込機械 | |
| JP2015067245A (ja) | 運搬機械 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 15773758 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| NENP | Non-entry into the national phase |
Ref country code: JP |
|
| 122 | Ep: pct application non-entry in european phase |