[go: up one dir, main page]

WO2015023010A1 - 건설기계용 유량 제어밸브 - Google Patents

건설기계용 유량 제어밸브 Download PDF

Info

Publication number
WO2015023010A1
WO2015023010A1 PCT/KR2013/007270 KR2013007270W WO2015023010A1 WO 2015023010 A1 WO2015023010 A1 WO 2015023010A1 KR 2013007270 W KR2013007270 W KR 2013007270W WO 2015023010 A1 WO2015023010 A1 WO 2015023010A1
Authority
WO
WIPO (PCT)
Prior art keywords
valve
orifice
passage
valve body
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/KR2013/007270
Other languages
English (en)
French (fr)
Inventor
전만석
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Volvo Construction Equipment AB
Original Assignee
Volvo Construction Equipment AB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Volvo Construction Equipment AB filed Critical Volvo Construction Equipment AB
Priority to EP13891462.7A priority Critical patent/EP3034705A4/en
Priority to KR1020167003724A priority patent/KR20160040581A/ko
Priority to US14/911,843 priority patent/US20160201297A1/en
Priority to PCT/KR2013/007270 priority patent/WO2015023010A1/ko
Priority to CN201380080199.7A priority patent/CN105637153A/zh
Publication of WO2015023010A1 publication Critical patent/WO2015023010A1/ko
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F15FLUID-PRESSURE ACTUATORS; HYDRAULICS OR PNEUMATICS IN GENERAL
    • F15BSYSTEMS ACTING BY MEANS OF FLUIDS IN GENERAL; FLUID-PRESSURE ACTUATORS, e.g. SERVOMOTORS; DETAILS OF FLUID-PRESSURE SYSTEMS, NOT OTHERWISE PROVIDED FOR
    • F15B13/00Details of servomotor systems ; Valves for servomotor systems
    • F15B13/02Fluid distribution or supply devices characterised by their adaptation to the control of servomotors
    • F15B13/04Fluid distribution or supply devices characterised by their adaptation to the control of servomotors for use with a single servomotor
    • F15B13/0416Fluid distribution or supply devices characterised by their adaptation to the control of servomotors for use with a single servomotor with means or adapted for load sensing
    • F15B13/0417Load sensing elements; Internal fluid connections therefor; Anti-saturation or pressure-compensation valves
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2264Arrangements or adaptations of elements for hydraulic drives
    • E02F9/2267Valves or distributors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2278Hydraulic circuits
    • E02F9/2282Systems using center bypass type changeover valves
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2278Hydraulic circuits
    • E02F9/2285Pilot-operated systems
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2278Hydraulic circuits
    • E02F9/2292Systems with two or more pumps
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2278Hydraulic circuits
    • E02F9/2296Systems with a variable displacement pump
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16KVALVES; TAPS; COCKS; ACTUATING-FLOATS; DEVICES FOR VENTING OR AERATING
    • F16K11/00Multiple-way valves, e.g. mixing valves; Pipe fittings incorporating such valves
    • F16K11/02Multiple-way valves, e.g. mixing valves; Pipe fittings incorporating such valves with all movable sealing faces moving as one unit
    • F16K11/06Multiple-way valves, e.g. mixing valves; Pipe fittings incorporating such valves with all movable sealing faces moving as one unit comprising only sliding valves, i.e. sliding closure elements
    • F16K11/065Multiple-way valves, e.g. mixing valves; Pipe fittings incorporating such valves with all movable sealing faces moving as one unit comprising only sliding valves, i.e. sliding closure elements with linearly sliding closure members
    • F16K11/07Multiple-way valves, e.g. mixing valves; Pipe fittings incorporating such valves with all movable sealing faces moving as one unit comprising only sliding valves, i.e. sliding closure elements with linearly sliding closure members with cylindrical slides

Definitions

  • the present invention relates to a flow control valve for a construction machine, and more specifically, to a flow control valve for a construction machine to operate the work and the working device smoothly when the composite work by operating the work device while driving. .
  • variable displacement first and second hydraulic pumps 1 and 2 (hereinafter referred to as “hydraulic pumps”);
  • a left traveling motor 3 and a first working device (referring to a working device such as an arm not shown) driven by the hydraulic oil supplied from the first hydraulic pump 1;
  • a switching valve is installed in the flow path 4 of the first hydraulic pump 1 and controls the hydraulic oil supplied to the left traveling motor 3 and the first working device when switching by application of pilot pressures a1 and b1. (5,6);
  • a right traveling motor 7 and a second working device (referring to a working device such as a boom not shown) driven by the hydraulic oil supplied from the second hydraulic pump 2;
  • a switching valve installed in the flow path 8 of the second hydraulic pump 2 and controlling the hydraulic oil supplied to the right traveling motor 7 and the second working device at the time of switching by applying pilot pressures a2 and b2; 9,10);
  • It is installed in the flow path (8) and supplies hydraulic oil from the first hydraulic pump (1) to the left and right traveling motors (3, 7) at the time of switching by application of the pilot pressure (a3), and the second hydraulic pump ( A part of the hydraulic oil from 2) is supplied to the switching valve 6 for the first working device through the flow path 11, and a part of the hydraulic oil from the second hydraulic pump 2 is supplied to the second working device through the flow path 12. It is provided with a traveling straight valve 13 which is respectively supplied to the switching valve 10 for.
  • the pilot pressure a3 is applied to the traveling straight valve 13 (the pilot pressure a3 only when the left and right switching valves 5 and 9 are switched and the pilot pressure b1 or b2 for the work device is simultaneously applied.
  • the inner spool is switched to the right in the drawing.
  • the pilot pressure b1 is applied to the switching valve 6 for the first work device to switch the internal spool to the left in the drawing, and the pilot pressure c1 is applied to the first center bypass valve 14.
  • the inner spool is switched to the left in the drawing.
  • a part of the hydraulic oil from the first hydraulic pump 1 is supplied to the left traveling motor 3 via the flow path 4 and the switching valve 5, and a part of the hydraulic oil of the first hydraulic pump 1 is flow path. 15 is supplied to the right traveling motor 7 via the traveling straight valve 13 and the switching valve 9 in this order.
  • the hydraulic oil from the first hydraulic pump 1 is supplied to the left traveling motor 3 and the right traveling motor 7 to drive them.
  • the hydraulic oil discharged from the second hydraulic pump 2 is supplied to the switching valve 6 for the first working device via the flow path 8, the traveling straight valve 13, the flow path 11, and the like. Can operate the work tool.
  • the hydraulic oil discharged from the second hydraulic pump 2 is supplied to the switching valve 10 for the second working device via the oil passage 12, and a part of the hydraulic oil of the second hydraulic pump 2 is the oil passage 16. Then, it is supplied to the right traveling motor 7 via the switching valve 9.
  • the working oil of the second hydraulic pump 2 is the check valve 17 of the flow path 12, the branch flow path (16) )
  • the first working device or the second working device can be operated when a load is generated through the orifice 18. That is, when the load generation amount is increased in the first working device or the second working device, the opening amount of the orifice 18 must be made smaller so that the hydraulic fluid can be smoothed from the second hydraulic pump 2 to the switching valve 6.
  • the first working device can be operated.
  • the parallel passage 26 and the actuator port communicate with each other when switching by the pilot pressure application, the hydraulic oil from the hydraulic pump through the one-side actuator port 21 to the hydraulic actuator And a spool 23 for supplying hydraulic oil discharged from the hydraulic actuator to the tank passage 22 through the other actuator port 24.
  • An orifice 18 for supplying hydraulic oil from the passage 12 to the parallel passage 26 is formed in an annular gap.
  • the orifice 18 is formed as an annular gap between the outer surface of the poppet 19 and the inner periphery of the corresponding valve body 20.
  • the outer diameter D2 of the poppet 19 corresponding to the inner diameter D1 of the valve body 20 is formed to be as large as possible within the tolerance range.
  • the outer diameter D2 of the poppet 19 corresponding to the inner diameter D1 of the valve body 20 is formed to a predetermined dimension so that a load is generated in the hydraulic oil passing through the orifice 18. In this case, the opening amount of the orifice 18 can be reduced to operate the work device.
  • the inner surface of the valve body 20 and the outer surface of the corresponding poppet 19 collide with each other upon contact. This causes a lot of noise when operating the work device while driving.
  • variable displacement first and second hydraulic pumps 1 and 2 (hereinafter referred to as “hydraulic pumps”);
  • a left traveling motor 3 and a first working device (referring to a working device such as an arm not shown) driven by the hydraulic oil supplied from the first hydraulic pump 1;
  • a switching valve is installed in the flow path 4 of the first hydraulic pump 1 and controls the hydraulic oil supplied to the left traveling motor 3 and the first working device when switching by application of pilot pressures a1 and b1. (5,6);
  • a right traveling motor 7 and a second working device (referring to a working device such as a boom not shown) driven by the hydraulic oil supplied from the second hydraulic pump 2;
  • a switching valve installed in the flow path 8 of the second hydraulic pump 2 and controlling the hydraulic oil supplied to the right traveling motor 7 and the second working device at the time of switching by applying pilot pressures a2 and b2; 9,10);
  • An inlet is branched to a predetermined position of the passage 12 and a branch passage 16 is connected to an outlet at a predetermined position of the passage 8 downstream of the traveling straight valve 13 to operate a work device while driving.
  • pilot pressure a4 to shut off the branch flow path 16
  • the hydraulic oil from the second hydraulic pump 2 is supplied to the left traveling motor 3 or the right traveling motor 7. It is provided with a control valve 24 to block the operation.
  • the present invention is to solve the above-described problems, and when the work device is operated while driving, the work device (for example, boom up or arm out operation) is prevented from operating or slowing down. It is an object of the present invention to provide a flow control valve for construction machinery that can prevent the occurrence of noise.
  • a valve body in which a parallel passage communicating with a hydraulic oil supply passage from a hydraulic pump and an actuator port connected to the hydraulic actuator;
  • the parallel passage and the actuator port in communication with the switch, to supply the hydraulic oil from the hydraulic pump to the hydraulic actuator through one actuator port, the hydraulic oil discharged from the hydraulic actuator to the other actuator port A spool to return to the tank passage through;
  • a first valve disposed in a passage between the passage and the parallel passage, the first valve having a first orifice in communication with the parallel passage and a second orifice for supplying hydraulic oil passing through the first orifice to the supply passage;
  • a second valve installed inside the first valve to open and close the first orifice
  • An elastic member configured to press the second valve to support the first orifice in a closed state
  • a third orifice which is formed at a predetermined position of the second valve so as to communicate with the second orifice, and prevents back pressure from being generated inside the first valve when the first orifice is opened.
  • the first valve The first valve
  • a valve body having a first chamber formed therein
  • a coupling part formed under the outer side of the valve body and having an outer diameter corresponding to the inner diameter of the valve body forming the passage;
  • a first orifice formed in communication with the first chamber on the bottom surface of the valve body
  • a second orifice formed in communication with the first orifice at a predetermined position on an outer surface of the valve body.
  • a valve body having a second chamber communicating with the first chamber of the first valve
  • a coupling part formed at a lower side of the outer side of the valve body to open and close the first orifice
  • a latching jaw in which one end of an elastic member elastically supporting the second valve by pressing the second valve is seated;
  • a third orifice formed in communication with the second chamber and the second orifice at a predetermined position on an outer surface of the valve body.
  • FIG. 1 is a hydraulic circuit diagram for a construction machine according to the prior art.
  • FIG. 2 is a schematic view of a flow control valve for a construction machine according to the prior art.
  • FIG. 3 is another hydraulic circuit diagram for a construction machine according to the prior art.
  • Figure 4 is a schematic diagram of a flow control valve for a construction machine according to an embodiment of the present invention.
  • FIG. 5 is a schematic view of a flow control valve for a construction machine according to another embodiment of the present invention.
  • Figure 6 (a, b) is an enlarged cross-sectional view of the first control valve and the second control valve in the construction machine flow control valve according to an embodiment of the present invention.
  • Figure 4 is a schematic diagram of a construction machinery flow control valve according to an embodiment of the present invention
  • Figure 5 is a schematic diagram of a construction machinery flow control valve according to another embodiment of the present invention
  • Figure 6 (a, b) is In a flow control valve for a construction machine according to an embodiment of the present invention, an enlarged cross-sectional view of a first control valve and a second control valve.
  • the flow control valve for a construction machine according to an embodiment of the present invention, the parallel passage communicating with the oil passage 12 is supplied with hydraulic oil from the hydraulic pump ( 26 and a valve body 20 in which actuator ports 21 and 24 connected to the hydraulic actuator are formed;
  • the hydraulic actuator (not shown) is installed in the valve body 20 and communicates the parallel passage 26 and the actuator port at the time of switching, so that the hydraulic oil from the hydraulic pump 2 is transferred through one side of the actuator port 21.
  • the parallel passage 26 is provided in the passage between the passage 12 and the parallel passage 26, and the hydraulic fluid passing through the first orifice 25 and the first orifice 25 communicated with the passage 12.
  • a second valve 29 installed inside the first valve 28 to open and close the first orifice 25;
  • An elastic member 30 (compression coil spring is used) for pressing the second valve 29 to support the first orifice 25 in a closed state
  • a first seal 32 may be provided to prevent leakage through the gap between the valve body 20 and the cover 31 in close contact with the valve body 20.
  • a second seal 33 may be provided to prevent leakage through a gap between an outer surface of the first valve 28 installed in the passage and an inner circumference of the valve body 20 corresponding thereto (FIG. Shown in 5).
  • the third orifice 34 may be provided.
  • the first valve 28 is the first valve 28,
  • An engaging portion 28c formed below the outer surface of the valve body 28b and formed to have an outer diameter D2 corresponding to an inner diameter D1 of the valve body 20 forming the passage;
  • a second orifice 27 formed in communication with the first orifice 25 may be provided at a predetermined position on the outer surface of the valve body 28b.
  • a valve body 29b having a second chamber 29a communicating with the first chamber 28a of the first valve 28;
  • a third orifice 34 may be provided at a predetermined position on the outer surface of the valve body 29b to communicate with the second chamber 29a and the second orifice 27.
  • reference numeral 35 is a fastening member for fixing the cover 31 to the valve body 20.
  • the first valve is installed in the passage between the passage 12 and the parallel passage 26 ( 28, between the second valve 29 supported by the elastic member 30 in the first valve 28, the cover 31, the valve body 20, and the cover 31. Except for the first seal 32 for preventing leakage through the gap and the second seal 33 for preventing leakage through the gap of the passage, the configuration of the flow control valve for construction machinery shown in FIG. Since the configuration is duplicated, detailed description of these configurations will be omitted.
  • the hydraulic oil discharged from the second hydraulic pump 2 is moved to the flow path 12, and then passes through the first orifice 25 of the first valve 28 to the first valve ( 28)
  • the second valve 29 therein is lifted upward.
  • the hydraulic fluid passing through the first orifice 25 is moved to the parallel passage 26 via the second orifice 27 formed in communication with the first orifice 25.
  • the spool 23 built into the valve body 20 is switched in the left or right direction on the drawing by the application of the pilot pressure Pi.
  • the hydraulic fluid moved to the parallel passage 26 is a hydraulic actuator (an example) through the actuator port 21 in communication with the parallel passage 26.
  • the right driving motor As the right driving motor).
  • the gap between the inner diameter (D1) of the can be eliminated.
  • one end of the first valve 28 is supported by the cover 31 so that the first valve 28 cannot move upward and downward as the first valve 28 is restricted. This can prevent the hydraulic oil leakage through the passage.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Fluid-Pressure Circuits (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

주행중 작업장치를 작동시켜 복합작업할 경우 주행 및 작업장치를 원활하게 작동시킬 수 있는 건설기계용 유량 제어밸브를 개시한다. 본 발명에 따른 건설기계용 유량 제어밸브에 있어서, 유압펌프로부터 작동유가 공급되는 유로에 연통되는 병렬통로와, 유압 액츄에이터에 연결되는 액츄에이터포트가 형성되는 밸브바디; 상기 밸브바디에 내설되며, 절환시 상기 병렬통로와 액츄에이터포트를 연통시켜, 상기 유압펌프로부터의 작동유를 일측 액츄에이터포트를 통해 상기 유압 액츄에이터에 공급하고, 상기 유압 액츄에이터로부터 배출되는 작동유를 타측 액츄에이터포트를 통해 탱크통로로 리턴시키는 스풀; 상기 유로와 병렬통로 사이의 통로에 설치되고, 상기 유로와 연통되는 제1오리피스, 상기 제1오리피스를 통과하는 작동유를 상기 병렬통로에 공급하는 제2오리피스를 구비하는 제1밸브; 상기 제1밸브의 내부에 설치되어 상기 제1오리피스를 개폐하는 제2밸브; 상기 제2밸브를 가압하여 상기 제1오리피스를 닫힌상태로 지지하는 탄성부재; 상기 제1밸브 및 탄성부재의 일단을 지지하여 상기 제1밸브 및 제2밸브의 스트로크를 제한하는 커버;를 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브를 제공한다.

Description

건설기계용 유량 제어밸브
본 발명은 건설기계용 유량 제어밸브에 관한 것으로, 보다 구체적으로 설명하면, 주행중 작업장치를 작동시켜 복합작업할 경우 주행 및 작업장치를 원활하게 작동시킬 수 있도록 한 건설기계용 유량 제어밸브에 관한 것이다.
도 1에 도시된 종래 기술에 의한 건설기계용 유압회로도는,
가변용량형 제1,2유압펌프(1,2)(이하 "유압펌프" 라고 함);
상기 제1유압펌프(1)로부터 공급되는 작동유에 의해 구동하는 좌측 주행모터(3) 및 제1작업장치(미도시된 아암 등의 작업장치를 말함);
상기 제1유압펌프(1)의 유로(4)에 설치되고, 파일럿압력(a1,b1) 인가에 의해 절환시 상기 좌측 주행모터(3) 및 제1작업장치에 공급되는 작동유를 제어하는 절환밸브(5,6);
상기 제2유압펌프(2)로부터 공급되는 작동유에 의해 구동하는 우측 주행모터(7) 및 제2작업장치(미도시된 붐 등의 작업장치를 말함);
상기 제2유압펌프(2)의 유로(8)에 설치되고, 파일럿압력(a2,b2) 인가에 의해 절환시 우측 주행모터(7) 및 제2작업장치에 공급되는 작동유를 제어하는 절환밸브(9,10);
상기 유로(8)에 설치되고, 파일럿압력(a3) 인가에 의해 절환시 제1유압펌프(1)로부터의 작동유를 좌측 및 우측 주행모터(3,7)에 각각 공급하고, 제2유압펌프(2)로부터의 작동유 일부를 유로(11)를 통하여 제1작업장치용 절환밸브(6)에 공급하며, 상기 제2유압펌프(2)로부터의 작동유 일부를 유로(12)를 통하여 제2작업장치용 절환밸브(10)에 각각 공급하는 주행직진밸브(13)를 구비한다.
가) 주행을 단독으로 조작하는 경우를 설명한다.
상기 좌측 주행모터(3)용 절환밸브(5)의 스풀이 파일럿압력(a1)의 인가에 의해 도면상, 좌측방향으로 절환되는 경우, 상기 제1유압펌프(1)로부터 토출되는 작동유는 유로(4)와 절환밸브(5)를 경유하여 좌측 주행모터(3)에 공급된다.
한편, 상기 우측 주행모터(7)용 절환밸브(9)의 스풀이 파일럿압력(a2)의 인가에 의해 도면상, 우측방향으로 절환되는 경우, 상기 제2유압펌프(2)로부터 토출되는 작동유는 유로(8), 주행직진밸브(13) 및 절환밸브(9)를 경유하거나 유로(12,16)를 경유하여 우측 주행모터(7)에 공급된다.
전술한 바와 같이 상기 좌측 주행모터(3)와 우측 주행모터(7)를 단독으로 조작하는 경우, 상기 제1유압펌프(1)로부터 토출되는 작동유는 좌측 주행모터(3)에 공급되고, 상기 제2유압펌프(2)로부터 토출되는 작동유는 우측 주행모터(7)에 공급된다.
나) 주행중 작업장치를 작동시켜 복합작업하는 경우를 설명한다.
상기 주행직진밸브(13)에 파일럿압력(a3)이 인가되어(좌측 및 우측 절환밸브(5,9)가 절환되면서 작업장치용 파일럿압력(b1 또는 b2)이 동시에 인가될 경우에만 파일럿압력(a3)이 인가된다) 내부 스풀을 도면상, 우측방향으로 절환시킨다. 이때 제1작업장치용 절환밸브(6)에 파일럿압력(b1)이 인가되어 내부 스풀을 도면상, 좌측방향으로 절환시키며, 제1센터바이패스밸브(14)에 파일럿압력(c1)이 인가되어 내부 스풀을 도면상, 좌측방향으로 절환시킨다.
따라서 상기 제1유압펌프(1)로부터의 작동유 일부는 유로(4)와 절환밸브(5)를 경유하여 좌측 주행모터(3)에 공급되고, 또한 제1유압펌프(1)의 작동유 일부는 유로(15), 주행직진밸브(13), 절환밸브(9)를 차례로 경유하여 우측 주행모터(7)에 공급된다.
전술한 바와 같이 상기 제1유압펌프(1)로부터의 작동유는 좌측 주행모터(3)와 우측 주행모터(7)에 공급되어 이들을 구동시키게 된다.
이때, 상기 제2유압펌프(2)로부터 토출되는 작동유는 유로(8), 주행직진밸브(13), 유로(11)를 경유하여 제1작업장치용 절환밸브(6)에 공급되므로, 아암 등의 작업장치를 작동시킬 수 있다. 또한 상기 제2유압펌프(2)로부터 토출되는 작동유는 유로(12)를 경유하여 제2작업장치용 절환밸브(10)에 공급되고, 제2유압펌프(2)의 작동유 일부는 유로(16), 절환밸브(9)를 경유하여 우측 주행모터(7)에 공급된다.
한편, 상기 작업장치를 작동시키는 상태에서 주행하는 경우 또는 주행하면서 작업장치 등을 작동시키는 경우, 상기 제2유압펌프(2)의 작동유가 유로(12), 분기유로(16)의 체크밸브(17)와 오리피스(18)를 경유할 때 부하가 발생될 경우, 상기 제1작업장치 또는 제2작업장치가 작동할 수 있게 된다. 즉 상기 제1작업장치 또는 제2작업장치에 부하 발생량이 증가되는 경우, 상기 오리피스(18)의 개구량을 더욱 작게 형성시켜야 제2유압펌프(2)로부터 상기 절환밸브(6)에 작동유가 원활하게 공급되어 제1작업장치를 작동시킬 수 있게 된다.
도 2에 도시된 종래 기술에 의한 건설기계용 유량 제어밸브는,
유압펌프(2)로부터 작동유가 공급되는 유로(12)에 연통되는 병렬통로(26)와, 유압 액츄에이터(미 도시됨)에 연결되는 액츄에이터포트(21,24)가 형성되는 밸브바디(20);
상기 밸브바디(20)에 내설되며, 파일럿압력 인가에 의해 절환시 상기 병렬통로(26)와 액츄에이터포트를 연통시켜, 상기 유압펌프로부터의 작동유를 일측 액츄에이터포트(21)를 통해 상기 유압 액츄에이터(미도시됨)에 공급하고, 상기 유압 액츄에이터로부터 배출되는 작동유를 타측 액츄에이터포트(24)를 통해 탱크통로(22)로 리턴시키는 스풀(23);을 구비한다.
상기 유로(12)에서 병렬통로(26)로 작동유를 공급하는 오리피스(18)는 환형 틈새로 형성된다. 즉 오리피스(18)가 포펫(19)의 외측면과 이와 대응되는 밸브바디(20)의 내주연 사이의 환형 틈새로 형성된다. 이때 상기 밸브바디(20)의 내경(D1)은 고정 치수이므로 밸브바디(20)의 내경(D1)과 대응되는 포펫(19)의 외경(D2)을 공차 범위 내에서 최대한 크게 형성하게 된다.
전술한 바와 같이 상기 오리피스(18)를 통과하는 작동유에 설정값만큼 부하가 발생되도록, 밸브바디(20)의 내경(D1)에 대응하는 포펫(19)의 외경(D2)을 소정치수로 형성할 경우, 오리피스(18)의 개구량이 줄어들어 작업장치를 작동시킬 수 있게 된다. 반면에 상기 밸브바디(20) 및 포펫(19)의 누적 공차 및 형상 공차 등에 의해 밸브바디(20)의 내측면에 이와 대응하는 포펫(19)의 외측면이 접촉시 충돌하게 된다. 이로 인해 주행중 작업장치를 작동시킬 경우 소음이 심하게 발생하게 된다.
이와 같은 문제점을 개선하고자 고안된 도 3에 도시된 종래 기술에 의한 건설기계용 다른 유압회로도는,
가변용량형 제1,2유압펌프(1,2)(이하 "유압펌프" 라고 함);
상기 제1유압펌프(1)로부터 공급되는 작동유에 의해 구동하는 좌측 주행모터(3) 및 제1작업장치(미도시된 아암 등의 작업장치를 말함);
상기 제1유압펌프(1)의 유로(4)에 설치되고, 파일럿압력(a1,b1) 인가에 의해 절환시 상기 좌측 주행모터(3) 및 제1작업장치에 공급되는 작동유를 제어하는 절환밸브(5,6);
상기 제2유압펌프(2)로부터 공급되는 작동유에 의해 구동하는 우측 주행모터(7) 및 제2작업장치(미도시된 붐 등의 작업장치를 말함);
상기 제2유압펌프(2)의 유로(8)에 설치되고, 파일럿압력(a2,b2) 인가에 의해 절환시 우측 주행모터(7) 및 제2작업장치에 공급되는 작동유를 제어하는 절환밸브(9,10);
상기 유로(8)에 설치되고, 파일럿압력(a3) 인가에 의해 절환시 제1유압펌프(1)로부터의 작동유를 좌측 및 우측 주행모터(3,7)에 각각 공급하고, 제2유압펌프(2)로부터의 작동유 일부를 유로(11)를 통하여 제1작업장치용 절환밸브(6)에 공급하며, 상기 제2유압펌프(2)로부터의 작동유 일부를 유로(12)를 통하여 제2작업장치용 절환밸브(10)에 각각 공급하는 주행직진밸브(13);
상기 유로(12) 소정위치에 입구가 분기접속되고 상기 주행직진밸브(13) 하류측의 유로(8) 소정위치에 출구가 분기접속되는 분기유로(16)에 설치되며, 주행중 작업장치를 작동시키는 복합작업시 파일럿압력(a4) 인가에 의해 절환되어 상기 분기유로(16)를 차단함에 따라, 제2유압펌프(2)로부터의 작동유가 좌측 주행모터(3) 또는 우측 주행모터(7)에 공급되는 것을 차단하는 제어밸브(24)를 구비한다.
전술한 바와 같이 상기 분기유로(16)에 설치되어 복합작업시 파일럿압력(a4) 인가에 의해 절환되는 제어밸브(24)에 의해, 상기 제2유압펌프(2)로부터 토출되어 우측 주행모터(7)에 공급되는 작동유를 차단시키거나 일부를 통과시킬 경우, 도 1에 도시된 문제점이 개선이 되지만, 해당 부품이 추가되어 원가비용 상승을 초래할 수 있는 문제점을 갖는다.
따라서, 본 발명은 전술한 문제점을 해결하고자 하는 것으로, 주행중 작업장치를 작동시켜 복합작업할 경우, 작업장치(일 예로서 붐 업 또는 아암 아웃 동작을 말함)가 작동되지않거나 느리게 작동되는 것을 방지하고, 소음 발생을 방지할 수 있는 건설기계용 유량 제어밸브를 제공하는 것을 목적으로 한다.
상기 및 기타 본 발명의 목적을 달성하기 위하여 본 발명의 일 실시예에 따르면, 유압펌프로부터 작동유가 공급되는 유로에 연통되는 병렬통로와, 유압 액츄에이터에 연결되는 액츄에이터포트가 형성되는 밸브바디;
상기 밸브바디에 내설되며, 절환시 상기 병렬통로와 액츄에이터포트를 연통시켜, 상기 유압펌프로부터의 작동유를 일측 액츄에이터포트를 통해 상기 유압 액츄에이터에 공급하고, 상기 유압 액츄에이터로부터 배출되는 작동유를 타측 액츄에이터포트를 통해 탱크통로로 리턴시키는 스풀;
상기 유로와 병렬통로 사이의 통로에 설치되고, 상기 병렬통로와 연통되는 제1오리피스, 상기 제1오리피스를 통과하는 작동유를 상기 공급통로에 공급하는 제2오리피스를 구비하는 제1밸브;
상기 제1밸브의 내부에 설치되어 상기 제1오리피스를 개폐하는 제2밸브;
상기 제2밸브를 가압하여 상기 제1오리피스를 닫힌상태로 지지하는 탄성부재; 및
상기 제1밸브 및 탄성부재의 일단을 지지하여 상기 제1밸브 및 제2밸브의 스트로크를 제한하는 커버;를 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브를 제공한다.
상기 밸브바디와 이와 밀착되는 상기 커버 사이의 틈새를 통해 누유되는 것을 방지하는 제1씰을 구비하는 것을 특징으로 한다.
상기 통로에 설치되는 제1밸브의 외측면과 이와 대응되는 상기 밸브바디의 내주연 사이의 틈새를 통해 누유되는 것을 방지하는 제2씰을 구비하는 것을 특징으로 한다.
상기 제2오리피스와 연통되게 상기 제2밸브의 소정위치에 형성되고, 상기 제1오리피스를 개방시 상기 제1밸브의 내부에 배압이 생성되는 것을 방지하는 제3오리피스를 구비하는 것을 특징으로 한다.
상기 제1밸브는,
내부에 제1챔버가 형성되는 밸브몸체와,
상기 밸브몸체의 외측면 하부에 형성되고, 상기 통로를 형성하는 상기 밸브바디의 내경에 대응되는 외경 크기로 형성되는 결합부와,
상기 밸브몸체의 바닥면에 상기 제1챔버와 연통되게 형성되는 제1오리피스와,
상기 밸브몸체의 외측면 소정위치에 상기 제1오리피스와 연통되게 형성되는 제2오리피스를 구비하여 이루어지는 것을 특징으로 한다.
상기 제2밸브는,
상기 제1밸브의 제1챔버와 연통되는 제2챔버가 형성되는 밸브몸체와,
상기 밸브몸체의 외측면 하부에 형성되어 상기 제1오리피스를 개폐하는 결합부와,
상기 제1밸브에 대해 상기 제2밸브를 가압하여 탄성지지하는 탄성부재의 일단이 안착되는 걸림턱과,
상기 밸브몸체의 외측면 소정위치에 상기 제2챔버 및 제2오리피스와 연통되게 형성되는 제3오리피스를 구비하는 것을 특징으로 한다.
전술한 구성을 갖는 본 발명에 따르면, 주행중 작업장치를 작동시켜 복합작업할 경우, 붐 업 또는 아암 아웃동작이 실행되지않거나 느리게 작동되는 것을 방지함에 따라 에너지 손실을 최소화하고, 소음 발생을 방지할 수 있는 효과가 있다.
도 1은 종래 기술에 의한 건설기계용 유압회로도.
도 2는 종래 기술에 의한 건설기계용 유량 제어밸브의 개략도.
도 3은 종래 기술에 의한 건설기계용 다른 유압회로도.
도 4는 본 발명의 일 실시예에 의한 건설기계용 유량 제어밸브의 개략도.
도 5는 본 발명의 다른 실시예에 의한 건설기계용 유량 제어밸브의 개략도.
도 6(a,b)는 본 발명의 일 실시예에 의한 건설기계용 유량 제어밸브에서, 제1제어밸브 및 제2제어밸브의 확대단면도이다.
〈도면의 주요 부분에 대한 참조 부호의 설명〉
20; 밸브바디
21; 액츄에이터포트
22; 탱크통로
23; 스풀
24; 액츄에이터포트
25; 제1오리피스
26; 병렬통로
27; 제2오리피스
28; 제1밸브
29; 제2밸브
30; 탄성부재
31; 커버
32; 제1씰
33; 제2씰
34; 제3오리피스
이하, 첨부도면을 참조하여 본 발명의 바람직한 실시예에 따른 건설기계용 유량 제어밸브를 상세히 설명하기로 한다.
도 4는 본 발명의 일 실시예에 의한 건설기계용 유량 제어밸브의 개략도이고, 도 5는 본 발명의 다른 실시예에 의한 건설기계용 유량 제어밸브의 개략도이며, 도 6(a,b)는 본 발명의 일 실시예에 의한 건설기계용 유량 제어밸브에서, 제1제어밸브 및 제2제어밸브의 확대단면도이다.
도 4 및 도 6(a,b)를 참조하면, 본 발명의 일 실시예에 따른 건설기계용 유량 제어밸브는, 유압펌프(2)로부터 작동유가 공급되는 유로(12)에 연통되는 병렬통로(26)와, 유압 액츄에이터에 연결되는 액츄에이터포트(21,24)가 형성되는 밸브바디(20);
상기 밸브바디(20)에 내설되며, 절환시 상기 병렬통로(26)와 액츄에이터포트를 연통시켜, 상기 유압펌프(2)로부터의 작동유를 일측 액츄에이터포트(21)를 통해 상기 유압 액츄에이터(미도시됨)에 공급하고, 상기 유압 액츄에이터로부터 배출되는 작동유를 타측 액츄에이터포트(24)를 통해 탱크통로(22)로 리턴시키는 스풀(23);
상기 유로(12)와 병렬통로(26) 사이의 통로에 설치되고, 상기 유로(12)와 연통되는 제1오리피스(25), 상기 제1오리피스(25)를 통과하는 작동유를 상기 병렬통로(26)에 공급하는 제2오리피스(27)를 구비하는 제1밸브(28);
상기 제1밸브(28)의 내부에 설치되어 상기 제1오리피스(25)를 개폐하는 제2밸브(29);
상기 제2밸브(29)를 가압하여 상기 제1오리피스(25)를 닫힌상태로 지지하는 탄성부재(30)(압축코일스프링이 사용됨); 및
상기 제1밸브(28) 및 탄성부재(30)의 일단을 지지하여 상기 제1밸브(28) 및 제2밸브(29)의 스트로크를 제한하는 커버(31);를 구비한다.
상기 밸브바디(20)와 이와 밀착되는 상기 커버(31) 사이의 틈새를 통해 누유되는 것을 방지하는 제1씰(32)(seal)을 구비할 수 있다.
상기 통로에 설치되는 제1밸브(28)의 외측면과 이와 대응되는 상기 밸브바디(20)의 내주연 사이의 틈새를 통해 누유되는 것을 방지하는 제2씰(33)을 구비할 수 있다(도 5에 도시됨).
상기 제2오리피스(27)와 연통되게 상기 제2밸브(29)의 소정위치에 형성되고, 상기 제1오리피스(25)를 개방시 상기 제1밸브(28)의 내부에 배압이 생성되는 것을 방지하는 제3오리피스(34)를 구비할 수 있다.
상기 제1밸브(28)는,
내부에 제1챔버(28a)가 형성되는 밸브몸체(28b)와,
상기 밸브몸체(28b)의 외측면 하부에 형성되고, 상기 통로를 형성하는 상기 밸브바디(20)의 내경(D1)에 대응되는 외경(D2) 크기로 형성되는 결합부(28c)와,
상기 밸브몸체(28b)의 바닥면에 상기 제1챔버(28a)와 연통되게 형성되는 제1오리피스(25)와,
상기 밸브몸체(28b)의 외측면 소정위치에 상기 제1오리피스(25)와 연통되게 형성되는 제2오리피스(27)를 구비할 수 있다.
상기 제2밸브(29)는,
상기 제1밸브(28)의 제1챔버(28a)와 연통되는 제2챔버(29a)가 형성되는 밸브몸체(29b)와,
상기 밸브몸체(29b)의 외측면 하부에 형성되어 상기 제1오리피스(25)를 개폐하는 결합부(29c)와,
상기 제1밸브(28)에 대해 상기 제2밸브(29)를 가압하여 탄성지지하는 탄성부재(30)의 일단이 안착되는 걸림턱(29d)과,
상기 밸브몸체(29b)의 외측면 소정위치에 상기 제2챔버(29a) 및 제2오리피스(27)와 연통되게 형성되는 제3오리피스(34)를 구비할 수 있다.
도면중 미 설명부호 35는 상기 밸브바디(20)에 커버(31)를 고정시키는 체결부재이다.
도 4 및 도 6(a,b)에 도시된 본 발명의 일 실시예에 의한 건설기계용 유량 제어밸브에서, 상기 유로(12)와 병렬통로(26) 사이의 통로에 설치되는 제1밸브(28)와, 상기 제1밸브(28) 내부에 탄성부재(30)에 의해 지지되는 제2밸브(29)와, 상기 커버(31)와, 상기 밸브바디(20)와 커버(31) 사이의 틈새를 통해 누유되는 것을 방지하는 제1씰(32)과, 상기 통로의 틈새를 통해 누유되는 것을 방지하는 제2씰(33)을 제외한 구성은, 도 2에 도시된 건설기계용 유량 제어밸브의 구성과 중복되므로 이들 구성의 상세한 설명은 생략한다.
전술한 구성을 따르면, 상기 제2유압펌프(2)로부터 토출되는 작동유는 상기 유로(12)에 이동된 후, 상기 제1밸브(28)의 제1오리피스(25)를 통과하여 제1밸브(28) 내부의 제2밸브(29)를 상방향으로 들어올리게 된다. 상기 제1오리피스(25)를 통과한 작동유는 제1오리피스(25)와 연통되게 형성된 제2오리피스(27)를 경유하여 병렬통로(26)로 이동된다.
상기 밸브바디(20)에 내설되는 스풀(23)은 파일럿압력(Pi)의 인가에 의해 도면상, 좌측 또는 우측방향으로 절환된다. 일 예로서 상기 스풀(23)이 도면상, 좌측방향으로 절환되는 경우, 상기 병렬통로(26)에 이동된 작동유는 병렬통로(26)와 연통되는 액츄에이터포트(21)를 통하여 유압 액츄에이터(일 예로서 우측 주행모터를 말함)에 공급된다.
이때, 상기 통로에 설치되는 상기 제1밸브(28)의 외측면에 장착된 제2씰(33)에 의해, 상기 제1밸브(28)의 외경(D2)과 이와 대응되는 밸브바디(20)의 내경(D1)사이의 틈새를 제거할 수 있다. 또한 상기 제1밸브(28)는 상기 커버(31)에 의해 제1밸브(28)의 일단이 지지되어 스트로크를 제한함에 따라 상하 방향으로 이동할 수 없게 된다. 이로 인해 상기 통로를 통하여 작동유 누유되는 것을 방지할 수 있다.
따라서, 상기 제2유압펌프(2)로부터 상기 유로(12)에 공급된 작동유는 상기 제1밸브(28)의 제1오리피스(25) 및 제2오리피스(27)를 통해서만 병렬통로(26)에 공급될 수 있다.
전술한 바와 같이 도 4 및 도 6(a,b)에 도시된 본 발명의 일 실시예에 의한 건설기계용 유량 제어밸브는, 종래의 도 2에 도시된 건설기계용 유량 제어밸브에서 발생되는 문제점(통로의 틈새를 통해 누유가 발생됨)과, 종래의 도 3에 도시된 건설기계용 유압회로도에서 발생되는 문제점(해당 부품이 추가되어 원가비용 상승을 초래함)을 해소할 수 있게 된다.
여기에서, 상술한 본 발명에서는 바람직한 실시예를 참조하여 설명하였지만, 해당 기술분야에서 숙련된 당업자는 하기의 특허청구범위에 기재된 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변경할 수 있음을 이해할 수 있을 것이다.
전술한 구성을 갖는 본 발명에 따르면, 주행중 작업장치를 작동시켜 복합작업할 경우, 붐 업 또는 아암 아웃동작이 실행되지않거나 느리게 작동되는 것을 방지하여 에너지 손실을 최소화하고, 소음 발생을 방지할 수 있는 효과가 있다.

Claims (6)

  1. 유압펌프로부터 작동유가 공급되는 유로에 연통되는 병렬통로와, 유압 액츄에이터에 연결되는 액츄에이터포트가 형성되는 밸브바디;
    상기 밸브바디에 내설되며, 절환시 상기 병렬통로와 액츄에이터포트를 연통시켜, 상기 유압펌프로부터의 작동유를 일측 액츄에이터포트를 통해 상기 유압 액츄에이터에 공급하고, 상기 유압 액츄에이터로부터 배출되는 작동유를 타측 액츄에이터포트를 통해 탱크통로로 리턴시키는 스풀;
    상기 유로와 상기 병렬통로 사이의 통로에 설치되고, 상기 유로와 연통되는 제1오리피스, 상기 제1오리피스를 통과하는 작동유를 상기 병렬통로에 공급하는 제2오리피스를 구비하는 제1밸브;
    상기 제1밸브의 내부에 설치되어 상기 제1오리피스를 개폐하는 제2밸브;
    상기 제2밸브를 가압하여 상기 제1오리피스를 닫힌상태로 지지하는 탄성부재; 및
    상기 제1밸브 및 탄성부재의 일단을 지지하여 상기 제1밸브 및 제2밸브의 스트로크를 제한하는 커버;를 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브.
  2. 제1항에 있어서, 상기 밸브바디와 이와 밀착되는 상기 커버 사이의 틈새를 통해 누유되는 것을 방지하는 제1씰을 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브.
  3. 제1항에 있어서, 상기 통로에 설치되는 제1밸브의 외측면과 이와 대응되는 상기 밸브바디의 내주연 사이의 틈새를 통해 누유되는 것을 방지하는 제2씰을 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브.
  4. 제1항에 있어서, 상기 제2오리피스와 연통되게 상기 제2밸브의 소정위치에 형성되고, 상기 제1오리피스를 개방시 상기 제1밸브의 내부에 배압이 생성되는 것을 방지하는 제3오리피스를 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브.
  5. 제1항에 있어서, 상기 제1밸브는,
    내부에 제1챔버가 형성되는 밸브몸체와,
    상기 밸브몸체의 외측면 하부에 형성되고, 상기 통로를 형성하는 상기 밸브바디의 내경에 대응되는 외경 크기로 형성되는 결합부와,
    상기 밸브몸체의 바닥면에 상기 제1챔버와 연통되게 형성되는 제1오리피스와,
    상기 밸브몸체의 외측면 소정위치에 상기 제1오리피스와 연통되게 형성되는 제2오리피스를 구비하여 이루어지는 것을 특징으로 하는 건설기계용 유량 제어밸브.
  6. 제5항에 있어서, 상기 제2밸브는,
    상기 제1밸브의 제1챔버와 연통되는 제2챔버가 형성되는 밸브몸체와,
    상기 밸브몸체의 외측면 하부에 형성되어 상기 제1오리피스를 개폐하는 결합부와,
    상기 제1밸브에 대해 상기 제2밸브를 가압하여 탄성지지하는 탄성부재의 일단이 안착되는 걸림턱과,
    상기 밸브몸체의 외측면 소정위치에 상기 제2챔버 및 제2오리피스와 연통되게 형성되는 제3오리피스를 구비하는 것을 특징으로 하는 건설기계용 유량 제어밸브.
PCT/KR2013/007270 2013-08-13 2013-08-13 건설기계용 유량 제어밸브 Ceased WO2015023010A1 (ko)

Priority Applications (5)

Application Number Priority Date Filing Date Title
EP13891462.7A EP3034705A4 (en) 2013-08-13 2013-08-13 Flow control valve for construction equipment
KR1020167003724A KR20160040581A (ko) 2013-08-13 2013-08-13 건설기계용 유량 제어밸브
US14/911,843 US20160201297A1 (en) 2013-08-13 2013-08-13 Flow control valve for construction equipment
PCT/KR2013/007270 WO2015023010A1 (ko) 2013-08-13 2013-08-13 건설기계용 유량 제어밸브
CN201380080199.7A CN105637153A (zh) 2013-08-13 2013-08-13 用于工程机械的流量控制阀

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/KR2013/007270 WO2015023010A1 (ko) 2013-08-13 2013-08-13 건설기계용 유량 제어밸브

Publications (1)

Publication Number Publication Date
WO2015023010A1 true WO2015023010A1 (ko) 2015-02-19

Family

ID=52468390

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2013/007270 Ceased WO2015023010A1 (ko) 2013-08-13 2013-08-13 건설기계용 유량 제어밸브

Country Status (5)

Country Link
US (1) US20160201297A1 (ko)
EP (1) EP3034705A4 (ko)
KR (1) KR20160040581A (ko)
CN (1) CN105637153A (ko)
WO (1) WO2015023010A1 (ko)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173015A (zh) * 2019-05-28 2019-08-27 江苏徐工工程机械研究院有限公司 直线行走阀、工程机械液压控制系统和工程机械

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10047769B2 (en) 2014-04-29 2018-08-14 Volvo Construction Equipment Ab Flow control valve for construction equipment
WO2016054047A2 (en) * 2014-09-29 2016-04-07 Parker-Hannifin Corporation Directional control valve
JP6440451B2 (ja) * 2014-10-27 2018-12-19 Kyb株式会社 ロードセンシングバルブ装置
JP6717541B2 (ja) * 2016-07-28 2020-07-01 キャタピラー エス エー アール エル 弁装置およびこれを備えた流体圧システム
EP3707389B1 (en) * 2017-11-08 2024-04-24 Volvo Construction Equipment AB Hydraulic circuit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5873561A (en) * 1993-07-16 1999-02-23 Hydrolux S.A.R.L. Two-port cartridge seat valve
KR19990037212A (ko) * 1997-10-23 1999-05-25 제임스 피. 게논 비-셔틀식 압력 보상기를 갖는 유압 제어밸브시스템
KR100348128B1 (ko) * 1994-09-30 2002-11-22 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 가변우선기능을갖는콘트롤밸브
KR20030052716A (ko) * 2001-12-21 2003-06-27 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 건설중장비용 유량 가변제어장치
KR20060033265A (ko) * 2004-10-14 2006-04-19 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 재생기능을 구비한 유압제어밸브

Family Cites Families (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1033109A (en) * 1963-07-19 1966-06-15 Dowty Hydraulic Units Ltd Control valves for fluid-pressure-operated mechanisms
US3501673A (en) * 1968-04-29 1970-03-17 Stromberg Datagraphix Inc Variable magnification cathode ray tube
US3534774A (en) * 1968-11-14 1970-10-20 Koehring Co Pressure compensated control valve
US3901264A (en) * 1972-03-06 1975-08-26 Gresen Manufacturing Co Adjustable flow control for hydraulic valves having high pressure main supply and controls fluid flow to cylinder and exhaust ports
US3774635A (en) * 1972-04-18 1973-11-27 Sperry Rand Corp Power transmission
FR2194891B1 (ko) * 1972-08-03 1976-01-23 Poclain Fr
US3985153A (en) * 1974-08-28 1976-10-12 Tomco, Inc. Pressure compensating valve spool assembly for a hydraulic control valve
US4574839A (en) * 1984-04-19 1986-03-11 J. I. Case Company Directional control valve with integral flow control valve
DE3619927A1 (de) * 1986-06-13 1987-12-23 Rexroth Mannesmann Gmbh 2-wege-einbauventil
JPH0786361B2 (ja) * 1988-11-10 1995-09-20 株式会社ゼクセル 油圧制御弁
DE4005967C2 (de) * 1990-02-26 1996-05-09 Rexroth Mannesmann Gmbh Steueranordnung für mehrere hydraulische Verbraucher
JPH0758082B2 (ja) * 1990-06-22 1995-06-21 株式会社ゼクセル 油圧制御弁装置
WO1994010456A1 (fr) * 1992-10-29 1994-05-11 Hitachi Construction Machinery Co., Ltd. Dispositif a soupapes de regulation hydraulique et dispositif a entrainement hydraulique
JPH07279906A (ja) * 1994-03-31 1995-10-27 Kayaba Ind Co Ltd 油圧制御装置
KR100208732B1 (ko) * 1996-05-21 1999-07-15 토니헬샴 가변 재생기능이 구비된 중장비용 콘트롤밸브
US5791142A (en) * 1997-03-27 1998-08-11 Husco International, Inc. Hydraulic control valve system with split pressure compensator
JP3536243B2 (ja) * 1998-03-16 2004-06-07 油研工業株式会社 油圧供給装置
US6745564B2 (en) * 2001-12-21 2004-06-08 Volvo Construction Equipment Holding Sweden Ab Hydraulic variable control apparatus for heavy construction equipment
US6868672B2 (en) * 2003-05-13 2005-03-22 Sauer-Danfoss, Inc. Method of controlling a swinging boom and apparatus for controlling the same
KR100518767B1 (ko) * 2003-05-28 2005-10-06 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 건설중장비용 액츄에이터 유량 가변제어장치
US7549241B2 (en) * 2005-07-07 2009-06-23 Nabtesco Corporation Hydraulic control device for loader
KR100753990B1 (ko) * 2006-08-29 2007-08-31 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 주행직진용 유압회로
JP4782711B2 (ja) * 2007-02-21 2011-09-28 日立建機株式会社 方向制御弁装置およびこの方向制御弁装置を複数備えた方向制御弁装置ブロック
US7621211B2 (en) * 2007-05-31 2009-11-24 Caterpillar Inc. Force feedback poppet valve having an integrated pressure compensator
WO2011096001A1 (en) * 2010-02-02 2011-08-11 Bucher Hydraulics S.P.A. Hydraulic section for load sensing applications and multiple hydraulic distributor

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5873561A (en) * 1993-07-16 1999-02-23 Hydrolux S.A.R.L. Two-port cartridge seat valve
KR100348128B1 (ko) * 1994-09-30 2002-11-22 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 가변우선기능을갖는콘트롤밸브
KR19990037212A (ko) * 1997-10-23 1999-05-25 제임스 피. 게논 비-셔틀식 압력 보상기를 갖는 유압 제어밸브시스템
KR20030052716A (ko) * 2001-12-21 2003-06-27 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 건설중장비용 유량 가변제어장치
KR20060033265A (ko) * 2004-10-14 2006-04-19 볼보 컨스트럭션 이키프먼트 홀딩 스웨덴 에이비 재생기능을 구비한 유압제어밸브

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173015A (zh) * 2019-05-28 2019-08-27 江苏徐工工程机械研究院有限公司 直线行走阀、工程机械液压控制系统和工程机械
CN110173015B (zh) * 2019-05-28 2021-07-30 江苏徐工工程机械研究院有限公司 直线行走阀、工程机械液压控制系统和工程机械

Also Published As

Publication number Publication date
EP3034705A1 (en) 2016-06-22
EP3034705A4 (en) 2017-04-05
KR20160040581A (ko) 2016-04-14
US20160201297A1 (en) 2016-07-14
CN105637153A (zh) 2016-06-01

Similar Documents

Publication Publication Date Title
WO2015023010A1 (ko) 건설기계용 유량 제어밸브
WO2013002429A1 (ko) 건설기계용 유압제어밸브
WO2014014146A1 (ko) 건설기계용 유량 컨트롤밸브
WO2012091182A1 (ko) 건설기계의 유압시스템
WO2011145759A1 (ko) 건설기계용 더블 체크밸브
WO2012121427A1 (ko) 파이프 레이어용 유압회로
WO2014112668A1 (ko) 건설기계의 유량 제어장치 및 제어방법
WO2011145754A1 (ko) 건설기계용 유압제어밸브
WO2011145755A1 (ko) 건설기계의 유압제어밸브
WO2013015467A1 (ko) 건설기계용 유압시스템
WO2017094986A1 (ko) 건설기계의 유압 시스템 및 유압 제어 방법
WO2014123251A1 (ko) 건설기계의 압력 제어밸브
WO2013022131A1 (ko) 건설기계의 유압 제어시스템
WO2016114556A1 (ko) 건설기계의 제어 시스템
WO2013176298A1 (ko) 건설기계용 유압시스템
WO2015064785A1 (ko) 플로팅기능이 구비된 건설기계용 유량제어밸브
WO2015099353A1 (ko) 붐 에너지 회생 제어 회로 및 제어 방법
WO2020045706A1 (en) Hydraulic circuit for construction equipment
WO2016175352A1 (ko) 건설기계의 유량 제어장치 및 제어방법
WO2015012423A1 (ko) 건설기계용 유압회로
WO2016108300A1 (ko) 건설기계용 제어밸브
WO2013089295A1 (ko) 건설기계의 주행 제어시스템
WO2014208796A1 (ko) 건설기계용 유압제어장치
WO2011087190A1 (ko) 도어밸브
WO2014034969A1 (ko) 건설기계용 유압시스템

Legal Events

Date Code Title Description
ENP Entry into the national phase

Ref document number: 20167003724

Country of ref document: KR

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: 14911843

Country of ref document: US

Ref document number: 2013891462

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: DE

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13891462

Country of ref document: EP

Kind code of ref document: A1