WO2012015160A1 - Procédé de distribution d'énergie sans interruption à l'aide d'un dispositif de modification de ligne électrique et d'un câble de dérivation - Google Patents
Procédé de distribution d'énergie sans interruption à l'aide d'un dispositif de modification de ligne électrique et d'un câble de dérivation Download PDFInfo
- Publication number
- WO2012015160A1 WO2012015160A1 PCT/KR2011/003996 KR2011003996W WO2012015160A1 WO 2012015160 A1 WO2012015160 A1 WO 2012015160A1 KR 2011003996 W KR2011003996 W KR 2011003996W WO 2012015160 A1 WO2012015160 A1 WO 2012015160A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- phase
- wire
- work
- cable
- bypass
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Definitions
- the present invention in the replacement and relocation of the distribution line connected to each pole and change of transition place, by installing the wire lead mechanism in each pole, the sequential electricity between the new and old wire by the bypass cable installed on the ground or pole It is possible to replace the electric wires, replace electric poles, move electric poles and change the transition site by uninterrupting by disconnecting and connecting them. Improved workability by allowing replacement and relocation by uninterruptible power, but by the applicant of the present invention, the patent application No.0407376, "Uninterrupted power distribution method using wire transfer mechanism in electric pole" and patent registration of pre-registered It is made by applying the "Uninterruptible power distribution method of single phase line using a processing temporary line" by the arc.
- Bopass cable method is a cable car and a work section necessary for a cable car and work section.
- the distribution line having a capacity of more than 5,000 KVA is less than 5,000 KVA at the time of applying the existing bypass cable method. Wastes a lot of time and labor costs when switching power loads to other distribution lines, and there is a serious problem in the system operation of an effective distribution line, and in particular, uninterrupted work on upper distribution lines of two or more lines is needed. There is a problem that construction is impossible with the current uninterrupted construction method.
- the inventor of the present invention uses a wire transfer mechanism and a wire twisted pair mechanism in Jeonju to secure a working space between the old and new wires and the relocation wire in Jeonju, as in 2001 Patent Application No. 32587.
- the uninterrupted operation of two or more upper distribution lines without switching power is provided by providing a method to replace and relocate new power lines with an uninterruptible uninterruptible power without using a separate bypass cable. It is possible to improve the power quality and also to use the mobile transformer car construction method except when replacing the transformer, which enables safe construction at low cost, and does not interfere with pedestrians' walking or passing through the vehicle even when it is under construction.
- Wire transfer mechanism in an electric pole and uninterrupted power using the same Bar has devised a major laws.
- the new wire can be replaced and relocated by separating the electric wire between the old and new wires while securing the working space between the old and new wires in Jeonju.
- This is a method of installing and removing wires and twisted wires for each wire to be replaced and relocated.However, by repeating the wire reworking process in the process of replacing and rewiring a large number of wires with one wire. There was a problem that a lot of time and manpower was consumed in the work.
- the applicant of the present invention in the uninterruptible power distribution method using a wire transfer mechanism in the electric pole that cuts electricity of the demolition wire without a power failure by a bypass by the connection of the installation wire and the demolition wire, Install the wires on only one side and transfer only one wire to the other side, and then replace the wires by the uninterrupted power distribution method in which the corresponding replacement wires are transferred, but the remaining replacement wires use the reverse wires as bypass cables without any separate wire process.
- the installation wire installation, the demolition wire removal process and the uninterrupted connection method by bypass it is necessary to install and wire the wire once and for the replacement and relocation of new and old wires.
- An uninterruptible power distribution method using a wire transfer mechanism in a pole was proposed.
- the uninterruptible power distribution method as described above has a problem that it is difficult to separate the side of the electric wires when a building, a street lamp, a signboard, a roadside tree, or a guard tree are adjacent to each other in order to separate the electric wires on one pole on the electric pole in a downtown area.
- the present invention is to solve the problems as described above, by using the "Uninterrupted power distribution method using electric wire transfer mechanism in the electric pole in accordance with the prior registration No. 10-0407376" sideways the one-phase wire on the electric pole in the metropolitan city area
- An uninterruptible power supply that completes three-phase work by sequential separation and connection of electricity one by one by using cable and wire that temporarily installs one of three phases of bypass cable and installs one phase among bypass cables.
- Development of "Uninterrupted Power Distribution Method Using Wire Transfer Mechanism and Bypass Cable” which enables wire replacement, Jeonju replacement and relocation work It aims to provide a more mature uninterrupted process according to the skills and preferences of workers in the field.
- one phase of the bypass cable is installed in the ground or the main phase by using the wire transfer mechanism to the ground or main phase by using a cable and wire to temporarily transmit the phase of electricity It is made by working with new technology developed to allow uninterrupted electric wire replacement, electric pole replacement and relocation work for jijangjeon pole that completes three phase work by separate connection.
- the present invention the uninterruptible power distribution method using the wire transfer mechanism in the downtown area of the metropolitan area when the wire to be moved to the side by installing the transfer mechanism in the Jeonju when the work distance is less than the distance from the building, signboard or streetlight, etc.
- the above-mentioned problems can be solved through the ground or air laying of the bypass cable according to such a case and necessary work conditions, and the selection and utilization of the uninterruptible method is widely available depending on the work proficiency and taste of the uninterruptible major. It is possible to improve safety by improving the scope of uninterruptible work and psychological stability of workers, and it is effective in reducing power outage and improving the power quality due to the expansion of work range.
- FIG. 3 is a state diagram in which the second phase of the three-phase line is removed from the power distribution method according to the present invention
- FIG. 5 is an exemplary view illustrating a construction in which a bypass cable is installed and installed in FIG. 4.
- FIG. 6 is a view illustrating a construction for a work section having a transformer column from the distribution method according to the present invention
- FIG. 7 is an exemplary view illustrating a construction in which a bypass cable is installed and installed in FIG. 6.
- FIG. 8 is an exemplary view showing the construction of a work section having a branch column from the distribution method according to the present invention
- FIG. 9 is an exemplary view illustrating a construction in which a bypass cable is installed and installed in FIG. 8.
- Phase 1 B Phase 2
- FIG. 1 is a state diagram in which the bypass cable is installed from the power distribution method according to the present invention
- Figure 2 is a state diagram in which the first phase of the three-phase line is removed from the power distribution method according to the present invention
- Figure 3 is from the power distribution method according to the present invention
- FIG. 4 is a state diagram in which the second phase of the three-phase line is removed.
- the present invention the uninterrupted power distribution method using the existing bypass cable method and wire unwired method and other uninterrupted method as an uninterrupted method in order to reduce the work outage for maintenance of new power distribution facilities, replacement of electric poles and relocation to the trouble pole. Is actively used and applied.
- Such the present invention is invented for the application of a wider and safer method according to the skill and field conditions of the operator in the field by using the existing bypass cable method and wire wire method.
- the first phase (A) jumper wire is compressed and the terminal cable of the installed cable is disconnected to complete the first phase (A) work, and in the second phase (B) work of the three phases, the already installed bypass After bypassing the cable 20 to the second phase B of the three phases on both sides of the work section, as shown in FIG. 3, the jumper wire of the second phase B is separated to make a diagonal line.
- the work of the second phase (B) is completed by compressing the jumper wire of the second phase (B) and disconnecting the terminal cable of the installed cable.
- the third phase C repeatedly performs the work process of the second phase B in the third phase C, and removes the installed bypass cable 30 to obtain a special high pressure 3. This is done by safely performing an uninterruptible operation.
- the bypass cable 20 is wired as shown in FIG. Jumper of the wire of the first phase (A) bypassed among the three high pressure phases after bypassing the first phase (A) of the three high pressure phases by installing it on the column near the neutral line through the two wire mechanism (10). Separate the wires and make the first phase (A) of the three phases oblique to secure the working space to complete wire stranded and long wire work.
- the first phase (A) jumper wire is compressed and the terminal cable of the installed cable is disconnected to complete the first phase (A) work, and in the second phase (B) work of the three phases, the already installed bypass After the cable 20 is bypassed to the second phase B of the three phases on both sides of the work section, the jumper wire of the second phase B is separated to make a diagonal line, and the wire stranding and the long wire work are performed.
- the jumper wire of (B) is compressed and the terminal cable of the installed cable is separated to complete the work of the second phase (B).
- the third phase (C) repeatedly performs the work process of the second phase (B) in the third phase (C), and safely removes the installed bypass cable 20 to perform the special high-pressure three-phase uninterrupted work. It is done by.
- the wire transfer mechanism 10 is installed on one side of the poles in the column, and then a separate bypass cable 20 is laid on the ground. If there is a transformer 30 in the work section after bypassing the first phase A of the phase, an uninterruptible transformer device is formed by branching a special high voltage by using a separate cable branch connecting member 40 in the middle of the bypass cable 20. The power supply of the transformer 30 is supplied to 50.
- the switchgear 70 for construction is operated to allow temporary transmission to the live state and the transformer line for the bypass cable 20.
- the jumper wire of the bypassed first phase (A) of the three phases of high pressure is separated to make the first phase (A) of the three phases oblique to secure a working space to complete the wire stranding and long wire work.
- the transformer is newly returned to the first phase A transmitted and the terminal cable of the bypass cable is disconnected to complete the first phase A work.
- the bypass cable 20 that is already installed is bypassed to the second phase (B) of the three phases on both sides of the work section, and then the second phase (B) ), If there is a transformer 30, the secondary power supply of the uninterruptible transformer device 50 already installed is connected to the second phase (B) transformer for transmission, and the jumper wire of the second phase (B) is removed to be in a diagonal state. Wire and long wire work, compress the jumper wire of the second phase (B), return the transformer to the newly established second (B) phase, and disconnect the terminal cable of the bypass cable to perform the work of the second phase (B). In the third phase (C), the second phase (B) work process is repeatedly performed in the third phase (C), and the installed bypass cable 20 is removed to perform the extra-high voltage three-phase uninterrupted work. It's safe to complete.
- the wire transfer mechanism 10 is installed on one side of the pole in the column, and then a separate bypass cable 20 is processed and installed near the neutral line. If there is a transformer 30 in the work section after bypassing the first phase A of the high-pressure three phases, an uninterruptible voltage may be generated by branching the special high voltage by using a separate cable branch connecting member 40 in the middle of the bypass cable 20. The power supply of the transformer 30 is supplied to the transformer device 50.
- the switchgear 70 for construction is operated to allow temporary transmission to the live state and the transformer line for the bypass cable 20.
- the jumper wire of the bypassed first phase (A) of the three phases of high pressure is separated to make the first phase (A) of the three phases oblique to secure a working space to complete the wire stranding and long wire work.
- the transformer is newly returned to the first phase (A) of the transmission and the terminal cable of the bypass cable is disconnected to complete the first phase (A) work.
- the bypass cable (20) already installed is bypassed to the second phase (B) of the three phases on both sides of the work section and then the second phase (B) in the work section.
- the secondary power supply of the uninterruptible transformer device 50 already installed is connected to the second phase (B) transformer for transmission, and the jumper wire of the second phase (B) is removed to be in a diagonal state.
- Wire and long wire work compress the jumper wire of the second phase (B), return the transformer to the newly established second (B) phase, and disconnect the terminal cable of the bypass cable to perform the work of the second phase (B).
- the second phase (B) work process is repeatedly performed in the third phase (C), and the installed bypass cable 20 is removed to perform the extra-high voltage three-phase uninterrupted work. It's safe to complete.
- the wire transfer mechanism 10 is installed on one side of the poles in the column, and then a separate bypass cable 20 is laid on the ground.
- the special high-pressure first phase (A) is used by utilizing the cable branch connection member 40 in the middle of the bypass cable 20.
- the jumper wire of the bypassed first phase A of the special high pressure three phases is separated and the first phase A of the three phases is separated.
- the bypass cable 20 as described above by installing the switchgear 70 for construction on each side end so that the twisted pair work between the bypass cable 20 and the branch line in the diagonal state can be made safely, the twisted pair work After this is completed by operating the construction switchgear 70 is to be made to temporarily transfer to the live state and branch line for the bypass cable (20).
- the already installed bypass cable 20 is bypassed to the second phase (B) of the third phase on both sides of the work section, and then the second phase in the work section.
- the cable branched from the branch connection member 40 already installed is connected to the branch line second phase (B), and temporarily transferred to the branch line, and then the jumper wire of the second phase (B) Disconnect the wires, make twisted wire and long wire work, compress the jumper wire of the second phase (B), return the branch line to the newly established second phase (B), and terminate the terminal cable of the bypass cable (20).
- the third phase (C) is repeatedly performed the work process of the second phase (B) in the third phase (C), the installed bypass cable (20) ), You can safely complete the special high-voltage three-phase uninterrupted work.
- a wire bypass mechanism 10 is installed on one side of the poles, and then a separate bypass cable 20 is processed near the neutral state.
- the special branch of the high pressure After installing and bypassing the first phase (A) of the special high pressure three phases, and if there is a branch column (60) in the work section, the special branch of the high pressure After the phase A is branched and connected temporarily to the branch line of the branch column 60 for the first phase, the jumper wire of the bypassed first phase A of the special high pressure three phases is separated and the first of three phases is separated.
- the bypass cable 20 as described above by installing the switchgear 70 for construction on each side end so that the twisted pair work between the bypass cable 20 and the branch line in the diagonal state can be made safely, the twisted pair work After this is completed by operating the construction switchgear 70 is to be made to temporarily transfer to the live state and branch line for the bypass cable (20).
- the already installed bypass cable 20 is bypassed to the second phase (B) of the third phase on both sides of the work section, and then the second phase in the work section.
- the cable branched from the branch connection member 40 already installed is connected to the branch line second phase (B), and temporarily transferred to the branch line, and then the jumper wire of the second phase (B) Disconnect the wires, make twisted wire and long wire work, compress the jumper wire of the second phase (B), return the branch line to the newly established second phase (B), and terminate the terminal cable of the bypass cable (20).
- the third phase (C) is repeatedly performed the work process of the second phase (B) in the third phase (C), the installed bypass cable (20) ), You can safely complete the special high-voltage three-phase uninterrupted work.
- the uninterruptible power distribution method allows the bypass cable allowable capacity to be applied from 5,000 kV to 10,000 kV, and is not connected in 50 m units and does not have connection points in the work section. , 200m, 300m cable is provided, the existing bypass cable method is not possible to install a three-phase bypass cable on the main street in the present invention by installing only one-phase bypass cable in the downtown area for road crossing and pedestrian safety The technology has been further improved to enable the installation of special high voltage cables without the need for laying them on the ground.
Landscapes
- Electric Cable Installation (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
La présente invention porte sur un procédé de distribution d'énergie sans interruption lors du remplacement d'une ligne électrique connectée à chacun des poteaux électriques et de la modification de l'installation de celle-ci, et pendant une construction pour le changement d'emplacement de passe-système. Plus particulièrement, un remplacement de câble triphasé ininterrompu est réalisé par l'intermédiaire d'une séparation d'électricité séquentielle et d'une connexion de chaque phase, par utilisation d'un dispositif de modification de ligne électrique qui étend l'une des trois phases d'un câble de dérivation sur le sol ou sur un poteau électrique, et les poteaux électriques peuvent être remplacés et d'une construction pour la modification de l'emplacement d'installation des poteaux électriques à l'aide du même procédé. En conséquence, une construction efficace et raisonnable pour une distribution d'énergie ininterrompue peut être obtenue dans des endroits, tels que des centres villes dans des villes métropolitaines, où la sécurité des piétons est menacée en raison d'une proximité étroite avec des poteaux électriques, et où différents obstacles, tels qu'un contact avec des bâtiments, existent. En outre, en fonction des compétences et des préférences de l'électricien spécialisé dans la distribution d'énergie ininterrompue, le procédé de distribution d'énergie ininterrompue pourrait être sélectionné parmi une large gamme et appliqué à une large gamme, permettant ainsi d'étendre la zone de travail de distribution d'énergie ininterrompue, d'améliorer la sécurité en favorisant une stabilité psychologique du travailleur, et de réduire efficacement les pannes d'électricité et d'améliorer la qualité énergétique pendant une construction par extension de la zone de construction.
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| KR1020100071855A KR101122499B1 (ko) | 2010-07-26 | 2010-07-26 | 전선이선기구 및 바이패스케이블을 이용한 무정전 배전공법 |
| KR10-2010-0071855 | 2010-07-26 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2012015160A1 true WO2012015160A1 (fr) | 2012-02-02 |
Family
ID=45530318
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/KR2011/003996 Ceased WO2012015160A1 (fr) | 2010-07-26 | 2011-06-01 | Procédé de distribution d'énergie sans interruption à l'aide d'un dispositif de modification de ligne électrique et d'un câble de dérivation |
Country Status (2)
| Country | Link |
|---|---|
| KR (1) | KR101122499B1 (fr) |
| WO (1) | WO2012015160A1 (fr) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102761076A (zh) * | 2012-07-05 | 2012-10-31 | 中国电力科学研究院 | 一种用于35kV线路配电化的设计方法 |
| US10367337B2 (en) | 2015-04-09 | 2019-07-30 | Quanta Associates, L.P. | Conductor as a tool |
Families Citing this family (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101394095B1 (ko) * | 2014-03-19 | 2014-05-14 | 운장전력 주식회사 | 특고압 중성선과 저압 중성선의 분리 설치 구조를 갖는 가공지선 겸용 특고압 중성선을 이용한 배전선로 공법 |
| KR101704613B1 (ko) * | 2016-03-30 | 2017-02-08 | 미래전기기술단(주) | 활선 상태에서의 배전선로 교체장치 |
| KR101736175B1 (ko) * | 2016-10-17 | 2017-05-29 | (주) 세양전기 | 절연스틱 및 공사용 개폐기를 이용한 사선작업 공간확보 무정전 공법 |
| KR101766162B1 (ko) | 2016-11-18 | 2017-08-08 | 대원전기 주식회사 | 단상 다분기 공사용개폐기를 이용한 바이패스케이블 중간접속개소가 없는 무정전 배전공법 |
| KR101754043B1 (ko) * | 2016-12-13 | 2017-07-06 | 대원전기 주식회사 | 개별 개폐형 단상 다분기 공사용개폐기를 이용한 바이패스케이블 중간접속개소가 없는 무정전 배전공법 |
| KR101777080B1 (ko) * | 2017-01-05 | 2017-09-12 | 대원전기 주식회사 | 절연활선장선기와 바이패스점퍼케이블을 이용하여 전주 경간내 전선을 분리하여 사선상태에서 구간내 작업을 하는 무정전 배전공법 |
| KR20240167209A (ko) | 2023-05-19 | 2024-11-26 | 한국전력공사 | 전력선로 공사용 개폐기의 전압 분기용 어댑터 |
| KR20240167208A (ko) | 2023-05-19 | 2024-11-26 | 한국전력공사 | 전력선로 공사용 개폐기의 전압 분기용 어댑터 |
| KR20240168500A (ko) | 2023-05-22 | 2024-12-02 | 한국전력공사 | 전력선로 공사용 개폐기의 안전성 확보 방법 및 그에 따른 전력선로 공사용 개폐기 |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0670468A (ja) * | 1992-08-13 | 1994-03-11 | Furukawa Electric Co Ltd:The | 無停電電流切替え方法および装置 |
| JPH06269128A (ja) * | 1993-03-11 | 1994-09-22 | Ngk Insulators Ltd | 三相配電線における給電回線切換装置 |
| KR200264163Y1 (ko) * | 2001-11-08 | 2002-02-19 | 한국전력공사 | 무정전공사용 바이패스라인의 분기케이블 고정 장치 |
| KR20030060615A (ko) * | 2002-01-10 | 2003-07-16 | 대원전기 주식회사 | 전주내 전선이선기구를 이용한 무정전 배전공법 |
| KR100479320B1 (ko) * | 2003-02-18 | 2005-03-25 | 우창전력(주) | 가공 임시선을 이용한 단상선로의 무정전 배전공법 |
| KR100864966B1 (ko) * | 2006-04-24 | 2008-10-22 | 에스엠 종합개발 주식회사 | 전선의 교체방법 |
| KR20100054948A (ko) * | 2008-11-17 | 2010-05-26 | (주) 진흥이엔지 | 단상변압기장치(이동용)를 이용한 주상변압기 (단상 또는 삼상) 무정전교체공법 |
-
2010
- 2010-07-26 KR KR1020100071855A patent/KR101122499B1/ko not_active Expired - Fee Related
-
2011
- 2011-06-01 WO PCT/KR2011/003996 patent/WO2012015160A1/fr not_active Ceased
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0670468A (ja) * | 1992-08-13 | 1994-03-11 | Furukawa Electric Co Ltd:The | 無停電電流切替え方法および装置 |
| JPH06269128A (ja) * | 1993-03-11 | 1994-09-22 | Ngk Insulators Ltd | 三相配電線における給電回線切換装置 |
| KR200264163Y1 (ko) * | 2001-11-08 | 2002-02-19 | 한국전력공사 | 무정전공사용 바이패스라인의 분기케이블 고정 장치 |
| KR20030060615A (ko) * | 2002-01-10 | 2003-07-16 | 대원전기 주식회사 | 전주내 전선이선기구를 이용한 무정전 배전공법 |
| KR100479320B1 (ko) * | 2003-02-18 | 2005-03-25 | 우창전력(주) | 가공 임시선을 이용한 단상선로의 무정전 배전공법 |
| KR100864966B1 (ko) * | 2006-04-24 | 2008-10-22 | 에스엠 종합개발 주식회사 | 전선의 교체방법 |
| KR20100054948A (ko) * | 2008-11-17 | 2010-05-26 | (주) 진흥이엔지 | 단상변압기장치(이동용)를 이용한 주상변압기 (단상 또는 삼상) 무정전교체공법 |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102761076A (zh) * | 2012-07-05 | 2012-10-31 | 中国电力科学研究院 | 一种用于35kV线路配电化的设计方法 |
| US10367337B2 (en) | 2015-04-09 | 2019-07-30 | Quanta Associates, L.P. | Conductor as a tool |
Also Published As
| Publication number | Publication date |
|---|---|
| KR20120010370A (ko) | 2012-02-03 |
| KR101122499B1 (ko) | 2012-03-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2012015160A1 (fr) | Procédé de distribution d'énergie sans interruption à l'aide d'un dispositif de modification de ligne électrique et d'un câble de dérivation | |
| KR100926445B1 (ko) | 분기접속기능을 갖는 익스텐션 엘보우를 이용한 지중배전선로의 무정전 바이패스 시공법 | |
| CN110168826B (zh) | 在死线状态下进行区间内作业的不断电配电方法 | |
| WO2012121457A1 (fr) | Procédé de construction d'un contournement ininterruptible de lignes de distribution d'énergie en utilisant des guides isolants pour maintenir la distance | |
| KR20100054948A (ko) | 단상변압기장치(이동용)를 이용한 주상변압기 (단상 또는 삼상) 무정전교체공법 | |
| WO2018097357A1 (fr) | Appareil à bras auxiliaire mobile destiné à être utilisé dans des travaux de distribution d'énergie sans coupure et procédé utilisant ledit appareil | |
| CN106451220A (zh) | 带电更换同杆多回路杆塔上设备的旁路设备及方法 | |
| KR101766162B1 (ko) | 단상 다분기 공사용개폐기를 이용한 바이패스케이블 중간접속개소가 없는 무정전 배전공법 | |
| CN110380340B (zh) | 一种变电站配电装置 | |
| KR101470868B1 (ko) | 지중 배전선로의 무정전 바이패스 공법이 적용된 시스템 | |
| WO2018110845A1 (fr) | Procédé de construction pour une distribution d'énergie sans coupure sans points de connexion intermédiaires de câble de dérivation à l'aide d'un appareillage de commutation à branchements multiples à phase unique pouvant être ouvert individuellement destiné à la construction | |
| KR100407376B1 (ko) | 전주내 전선이선기구를 이용한 무정전 배전공법 | |
| CN104466949A (zh) | 一种用于平原地区中小城市城区10kV主副线环网格布局的方法 | |
| KR100769583B1 (ko) | 무정전 공법에 의한 지중 배전선로의 지상 변압기 교체방법 | |
| KR20010084955A (ko) | 전주내 전선이선기구 및 이를 이용한 무정전 배전공법 | |
| KR20230124873A (ko) | 선로 작업 방법 | |
| CN206195248U (zh) | 带电更换同杆多回路杆塔上设备的旁路设备 | |
| KR20100036065A (ko) | 활선상태에서 배전선로의 교체시공방법 | |
| CA2946380C (fr) | Bus de transfert provisoire | |
| CN210779513U (zh) | 一种变电站配电装置 | |
| WO2009131322A2 (fr) | Poteau télégraphique pour câble sous-marin | |
| JP2005191727A (ja) | Opgwシステム | |
| JP7810093B2 (ja) | 変圧器取替工法 | |
| CN117895376A (zh) | 一种不间断供电下迁移杆线的作业方法 | |
| CN118971319A (zh) | 基于临时旁路开关的移动电源不间断供电架空方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11812691 Country of ref document: EP Kind code of ref document: A1 |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 11812691 Country of ref document: EP Kind code of ref document: A1 |