WO2011150941A1 - Device and method for testing a wind power plant component - Google Patents
Device and method for testing a wind power plant component Download PDFInfo
- Publication number
- WO2011150941A1 WO2011150941A1 PCT/DK2011/050194 DK2011050194W WO2011150941A1 WO 2011150941 A1 WO2011150941 A1 WO 2011150941A1 DK 2011050194 W DK2011050194 W DK 2011050194W WO 2011150941 A1 WO2011150941 A1 WO 2011150941A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- simulator
- power plant
- wind power
- wind
- grid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B23/00—Testing or monitoring of control systems or parts thereof
- G05B23/02—Electric testing or monitoring
- G05B23/0205—Electric testing or monitoring by means of a monitoring system capable of detecting and responding to faults
- G05B23/0208—Electric testing or monitoring by means of a monitoring system capable of detecting and responding to faults characterized by the configuration of the monitoring system
- G05B23/021—Electric testing or monitoring by means of a monitoring system capable of detecting and responding to faults characterized by the configuration of the monitoring system adopting a different treatment of each operating region or a different mode of the monitored system, e.g. transient modes; different operating configurations of monitored system
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D17/00—Monitoring or testing of wind motors, e.g. diagnostics
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D7/00—Controlling wind motors
- F03D7/02—Controlling wind motors the wind motors having rotation axis substantially parallel to the air flow entering the rotor
- F03D7/022—Adjusting aerodynamic properties of the blades
- F03D7/0224—Adjusting blade pitch
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D7/00—Controlling wind motors
- F03D7/02—Controlling wind motors the wind motors having rotation axis substantially parallel to the air flow entering the rotor
- F03D7/04—Automatic control; Regulation
- F03D7/042—Automatic control; Regulation by means of an electrical or electronic controller
- F03D7/047—Automatic control; Regulation by means of an electrical or electronic controller characterised by the controller architecture, e.g. multiple processors or data communications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B17/00—Systems involving the use of models or simulators of said systems
- G05B17/02—Systems involving the use of models or simulators of said systems electric
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2260/00—Function
- F05B2260/70—Adjusting of angle of incidence or attack of rotating blades
- F05B2260/74—Adjusting of angle of incidence or attack of rotating blades by turning around an axis perpendicular the rotor centre line
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2260/00—Function
- F05B2260/83—Testing, e.g. methods, components or tools therefor
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F05—INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
- F05B—INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- F05B2260/00—Function
- F05B2260/84—Modelling or simulation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
Definitions
- the present invention relates generally to wind power generation systems and, more specifically, to a device and method for testing a wind power plant component.
- a utility-scale wind energy system or wind power plant includes a group of wind turbines that operate collectively as a power plant to produce electrical energy without the consumption of fossil fuels.
- the electricity produced by the wind turbines is provided to the electrical grid, which distributes the generated electricity to power grid customers based on demand.
- the wind power plant thus reduces the amount of power which must be generated by traditional means by supplying a portion of the total power demand of the electrical grid.
- a typical wind turbine includes a rotor mounted to a nacelle disposed at the apex of a tower and housing a generator.
- the rotor typically includes a plurality of blades that capture wind currents to produce rotation of the wind turbine. The rotor thereby converts wind energy into rotational energy. This rotational energy is coupled to the generator, which converts the rotational energy into electricity.
- the rotor blades will typically have an adjustable pitch that is set by a wind turbine controller in response to wind conditions. The wind turbine controller monitors the speed of the rotor and adjusts the pitch of the rotor blades in response to existing wind conditions in order to maximize the output of the wind turbine and to maintain the speed and torque applied to the generator at or below rated levels.
- the power produced by the wind turbine is typically coupled to the grid through a power converter that converts the electrical output of the wind turbine generator into AC voltages suitable for use on the grid.
- the power converter operates under the control of a power controller, which adjusts the frequency, phase angle, and voltage of the power converter output as required to adjust the amount of real and reactive power transferred from the wind turbine generator to the grid.
- an energy storage system such as a battery, may be coupled to the power converter.
- the outputs of the wind turbine power converters are typically ganged together in parallel and connected to the grid at a single connection point. These connections will typically include circuit breakers to prevent damage to wind power plant and/or electrical grid components in the event of a power surge or other system disruption.
- the power controller function may be provided by a subsystem at each individual wind turbine, but may also be controlled, at least in part, by a centralized wind power plant controller.
- the centralized power plant control function monitors and controls individual wind turbine power converter outputs to provide power output levels that take into account both wind conditions at the individual wind turbine as well as system wide
- the power plant controller may also control the operation of a reactive compensator to adjust the reactive power supplied to the grid at the wind power plant level.
- a utility scale wind power plant thus includes multiple subsystems that control the operation of the various components of the power plant, such as electrical grid monitors, wind turbine controllers, power converter controllers, energy storage system controllers, circuit breaker controllers, and a power plant controller. These subsystems monitor wind power plant and grid conditions to provide control mechanisms that optimize the power output of the wind power plant.
- the wind power plant subsystems also include safety mechanisms that prevent wind turbines, power converters, and other plant systems from operating outside of their maximum allowable design parameters. To this end, the wind power plant subsystems monitor grid and wind power plant
- wind power plant subsystems interact in complex fashion so that changes in one subsystem can affect the overall performance of a wind power plant in unexpected ways.
- variable nature of both wind power availability and electrical grid demands further increase the potential for undesirable and unexpected results when wind power plant subsystems or components of the wind power plant are added, removed, or otherwise modified. Testing of new or modified power plant components and
- the method according to an embodiment of the invention is a method of testing a wind power plant controller.
- the controller is configured to receive signals from and transmit signals to wind turbines in a wind power plant.
- the testing method includes: (1 ) connecting the wind power plant controller to a test device.
- the test device includes one or more subsystem simulators. At least one subsystem simulator is arranged to simulate a certain wind power plant subsystem or conditions influencing wind turbines in a wind power plant; and (2) testing the wind power plant controller by performing a simulation via the subsystem simulators.
- Program instructions for performing the aforementioned method may be implemented in a computer program product.
- the program instructions are stored on a computer readable storage medium.
- the device according to an embodiment of the invention is a test device for testing a wind power plant component.
- the test device includes an interface for connecting a wind power plant controller to the test device and one or more subsystem simulators. Each of the one or more subsystem simulators is configured to simulate an associated wind power plant subsystem or condition.
- Figure 1 shows a schematic drawing of a wind power plant
- Figure 2 shows a schematic drawing of a test device for testing a wind power plant controller
- Figure 3 shows a schematic drawing similar to Figure 2 that further includes a test measurement simulator; and Figure 4 is a flow chart of a method according to the invention.
- a wind power plant 10 includes a wind power plant controller (WPP) 20, a plurality of wind turbines represented by wind turbines 30, 31 , 32, 33, and optional reactive power compensation equipment 40.
- the wind turbines 30-33 are connected via radials 36, 37, 38, 39 and switches 50, 51 to common connection points where the power output of the wind power plant 10 is coupled to one or more electric grids 60, 61 .
- the wind power plant 10 as illustrated also includes a switch 52 that connects a first group of wind turbines 30, 31 and a second group of wind turbines 32, 33 within the wind power plant 10.
- the first and second groups of wind turbines may be ganged together by closing the switch 52 so that the wind power plant 10 collectively provides a composite power output to the one or more electrical grids 60, 61 .
- the first and second groups of wind turbines may be electrically isolated from each other. This isolation allows the wind power plant 10 to provide power to the grids 60, 61 as two electrically separate wind power plants using only a subset of the available wind turbines 30-33 under the control of the wind power plant controller 20 to supply power to each grid 60, 61 .
- the switches 50-52 are typically not operated directly by the wind power plant controller 20. However, feedback signals relating to the status and/or position of the switches are typically provided to the wind power plant controller 20 to allow the controller 20 to factor in the state of the switches 50-52 as a parameter for controlling the operation of the wind power plant 10.
- the wind power plant controller 20 provides control signals to the wind turbines 30-33 in the form of power set points such as, but not limited to, the desired active and/or reactive power output to be supplied from the individual wind turbines 30-33. These set points and control signals may be used by the wind turbine power controller 20 to adjust the power output of the wind turbines 30- 33.
- the wind power system controller 20 may be operatively coupled to the optional compensation equipment 40, which may be configured to adjust the amount of reactive power provided to the grid using known methods.
- the wind power system controller 20 may thereby regulate the active and reactive power provided to the electrical grid 60, 61 by adjusting the individual power output levels of each wind turbine 30-33, and/or by adjusting the reactive power of the wind power plant 10 at a plant level.
- the wind power plant controller 20 may obtain measurements of the active and reactive power supplied to the electrical grid 60, 61 , as indicated by arrowed line 4. From these power measurements, the wind power plant controller 20 calculates new power set points and other control signals, as appropriate, to be supplied to the wind turbines 30-33 and other power control equipment, such as the compensation equipment 40 and the switches 50-52. The wind power plant controller 20 transmits these set points and other control signals to the appropriate components and subsystems of the wind power system 10 as indicated by arrowed line 5. In response to the control signals 5, the wind power plant components and subsystems may react by adjusting the power output of the wind turbines 30-33 and wind power system 10 as indicated by arrowed line 6.
- the wind power plant 10 may comprise a smaller or larger number of wind turbines 30-33.
- a large wind power plant 100 might include over 100 wind turbines 30-33.
- the wind power plant includes compensation equipment 40, in which case the wind power plant controller 20 may control the composite power output of the wind power plant 10 by controlling the power output of the wind turbine power converters.
- the test device 500 comprises a simulator system that includes subsystem simulators in the form of a wind turbine simulator 530, a reactive compensation equipment simulator 540, a circuit breaker simulator 550, a grid simulator 560, a wind simulator 570, a cabling system simulator 575 that simulates the cabling system within the wind power plant 10, an energy storage simulator 580, and/or a supervisory control and data acquisition (SCADA) system simulator 585.
- Figure 2 illustrates one embodiment in which a grid measurement subsystem 565 is shown outside the test device 500
- Figure 3 illustrates an alternative embodiment in which a grid measurement subsystem is
- the grid measurement subsystem as illustrated in Figure 3 is thereby implemented as a grid measurement simulator 566.
- the subsystem simulators may include data on real- world subsystem performance over a range of environmental conditions.
- the wind turbine simulator 530 may include the operation of one or more specific models of wind turbines over a range of operating conditions, including a range of wind speeds.
- the reactive compensation equipment simulator 540 may include simulation of reactive compensation equipment, such as a STATCOM or capacitor banks.
- the grid simulator 560 may include a range of possible grid operation conditions, including faults in the grid, low voltage ride through situations, frequency fluctuations, inclusion of large loads in the grid, etc.
- the wind simulator 570 may include simulation of a range of different wind conditions, e.g. wind speed, gusts, wind shear, turbulence, etc.
- the cabling system simulator 575 may include the electric properties of the cables within the wind power plant 10, such as the impedance of the cables.
- the energy storage simulator 580 may include properties of an energy storage system within or in conjunction to the wind power plant 10, including the charging state of the energy storage system.
- the simulated energy storage system might include a battery, a flywheel or other suitable power storage equipment.
- the test device 500 may include a control interface 590 that connects the wind power plant components to the associated subsystem simulators.
- the control interface 590 may thereby allow the subsystem simulators to exchange data with their associated wind power plant subsystems.
- the wind turbine simulator 530 may obtain operational data from the wind power plant controller 20 related to the operation of the wind turbines 30-33. This data may be used to modify the wind turbine simulator 530 so that it more accurately predicts the behavior of the wind turbines 30-33 as configured in the wind power plant 10.
- data generated by the wind turbine simulator 530 may be provided to the wind power plant controller 20 to improve, control, or otherwise modify the performance of the controller 20.
- the grid simulator 560 may exchange data with the grid measurement subsystem 565, whether implemented external to the test device 500 ( Figure 2) or, alternatively, within the test device 500 as a grid measurement simulator 566 ( Figure 3) to improve the performance of the grid simulator 560.
- the test device 500 provides the ability to conduct realistic simulations of wind power plant control strategies and control system under various scenarios which would be difficult, expensive, dangerous, and/or otherwise undesirable to create as a real-world test.
- the test device 500 thereby provides a virtual laboratory that renders it possible to perform realistic testing of the wind power plant control systems in various scenarios even before the wind power plant 10 is built.
- the test device 500 thus provides the ability to demonstrate wind power plant control system capabilities prior to implementation.
- the test device 500 facilitates testing of the wind power plant controller 20 in the case of fluctuations or faults on the electrical grid, e.g., a low voltage ride through (LVRT) or frequency deviations.
- LVRT low voltage ride through
- the output from the wind simulator 570 may be provided the wind turbine simulator 530 to generate wind turbine operational scenarios based on probable or extreme wind conditions at the wind power plant 10.
- signals may also be exchanged between the circuit breaker simulator 550, grid simulator 560, cabling system simulator 575, energy storage simulator 580, and wind turbine simulator 530 based on historical and/or expected behavior of related wind power plant components and the grid 60, 61 . Signals may also be
- the invention may be implemented in any suitable form including hardware, software, firmware or any combination of these.
- the invention or some features of the invention can be implemented as computer software running on one or more data processors and/or digital signal processors.
- the elements and components of embodiments of the invention may be physically, functionally and logically implemented in any suitable way. Indeed, the functionality may be implemented in a single unit, in a plurality of units or as part of other functional units. As such, the invention may be implemented in a single unit, or may be physically and functionally distributed between different units and processors.
- the simulator subsystems may be implemented as different computer software algorithms running on one or more data processors.
- the grid measurement subsystem 565 resides outside the test device 500.
- the grid measurement subsystem 565 may be a hardware grid meter connectable to the wind power plant controller 20 as well as to the test device 500 for testing the wind power plant controller 20.
- the grid measurement subsystem 565 may be implemented as a software algorithm within the test device 500 that provides a grid measurement simulator 566 as illustrated in Figure 3.
- the wind power plant controller 20 is configured to receive signals from and transmit signals to wind turbines 30-33 in the wind power plant 10.
- the wind power plant controller 20 is connected to the test device 500.
- the test device 500 may include a plurality of subsystem simulators that each represents a component or subsystem of the wind power plant 10. Each subsystem simulator is thereby arranged to simulate a certain wind power plant subsystem or conditions influencing the wind turbines 30-33 in the wind power plant 10.
- the wind power plant controller 20 is tested by performing a simulation via the subsystem simulators and by registering the performance of the wind power plant controller 20 as a function of the simulations.
- the results of the simulations from the test device 500 may be used to adjust parameters within the wind power plant controller 20 to optimize the performance of the wind power plant 10, to predict the effect of changes to subsystems within the wind power plant 10, or to control the wind power plant 10.
- Different configurations and environmental scenarios may thereby be tested with regard to the wind power plant 10 by modeling the wind power plant 10 in the test device (500).
- wind power plant is synonymous to “wind farm” and “wind park” and is meant to denote a plurality of wind turbines as well further units, equipment, or subsystems, as
- the methods described herein can be implemented by computer program instructions supplied to the processor of any type of computer to produce a machine with a processor that executes the instructions to implement the functions/acts specified herein.
- These computer program instructions may also be stored in a computer readable medium that can direct a computer to function in a particular manner. To that end, the computer program instructions may be loaded onto a computer to cause the performance of a series of operational steps and thereby produce a computer implemented process such that the executed instructions provide processes for implementing the functions/acts specified herein.
- Such computer program instructions may also be provided through a computer based network, e.g., the Internet.
- inventions of embodiments of the invention may be physically, functionally and logically implemented in any suitable way.
- functionality may be implemented in a single unit, in a plurality of units or as part of other functional units.
- the invention may be implemented in a single unit, or may be physically and functionally distributed between different units and processors.
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Physics & Mathematics (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Automation & Control Theory (AREA)
- Fluid Mechanics (AREA)
- Wind Motors (AREA)
Abstract
The invention relates to a test device (500) and method (100) of testing a wind power plant component, such as a wind power plant controller (20). The test device (500) includes one or more subsystem simulators (530, 540, 550, 560, 66, 570, 575, 580, 585)that cooperate to provide a system level simulation of a wind power plant (10). Each subsystem simulator (530, 540, 550, 560, 566, 70, 575, 580, 585) is configured to simulate a wind power plant subsystem or conditions influencing the wind power plant (10).The method(100) includes connecting (102) the wind power plant controller (20) to the test device (500), and testing (103) the wind power plant controller (20).
Description
DEVICE AND METHOD FOR TESTING A WIND POWER PLANT
COMPONENT FIELD OF THE INVENTION
The present invention relates generally to wind power generation systems and, more specifically, to a device and method for testing a wind power plant component.
BACKGROUND OF THE INVENTION
A utility-scale wind energy system or wind power plant includes a group of wind turbines that operate collectively as a power plant to produce electrical energy without the consumption of fossil fuels. The electricity produced by the wind turbines is provided to the electrical grid, which distributes the generated electricity to power grid customers based on demand. The wind power plant thus reduces the amount of power which must be generated by traditional means by supplying a portion of the total power demand of the electrical grid.
A typical wind turbine includes a rotor mounted to a nacelle disposed at the apex of a tower and housing a generator. The rotor typically includes a plurality of blades that capture wind currents to produce rotation of the wind turbine. The rotor thereby converts wind energy into rotational energy. This rotational energy is coupled to the generator, which converts the rotational energy into electricity. The rotor blades will typically have an adjustable pitch that is set by a wind turbine controller in response to wind conditions. The wind turbine controller monitors the speed of the rotor and adjusts the pitch of the rotor blades in response to existing wind conditions in order to maximize
the output of the wind turbine and to maintain the speed and torque applied to the generator at or below rated levels.
The power produced by the wind turbine is typically coupled to the grid through a power converter that converts the electrical output of the wind turbine generator into AC voltages suitable for use on the grid. The power converter operates under the control of a power controller, which adjusts the frequency, phase angle, and voltage of the power converter output as required to adjust the amount of real and reactive power transferred from the wind turbine generator to the grid. To store excess power production for release to the grid during times of low wind production, an energy storage system, such as a battery, may be coupled to the power converter.
The outputs of the wind turbine power converters are typically ganged together in parallel and connected to the grid at a single connection point. These connections will typically include circuit breakers to prevent damage to wind power plant and/or electrical grid components in the event of a power surge or other system disruption. The power controller function may be provided by a subsystem at each individual wind turbine, but may also be controlled, at least in part, by a centralized wind power plant controller. The centralized power plant control function monitors and controls individual wind turbine power converter outputs to provide power output levels that take into account both wind conditions at the individual wind turbine as well as system wide
conditions, such as electrical grid demands. The power plant controller may also control the operation of a reactive compensator to adjust the reactive power supplied to the grid at the wind power plant level.
A utility scale wind power plant thus includes multiple subsystems that control the operation of the various components of the power plant, such as electrical
grid monitors, wind turbine controllers, power converter controllers, energy storage system controllers, circuit breaker controllers, and a power plant controller. These subsystems monitor wind power plant and grid conditions to provide control mechanisms that optimize the power output of the wind power plant. The wind power plant subsystems also include safety mechanisms that prevent wind turbines, power converters, and other plant systems from operating outside of their maximum allowable design parameters. To this end, the wind power plant subsystems monitor grid and wind power plant
operational parameters, and condition the power generated by the wind turbines so that the power is safely provided to the electrical grid in
conformance with grid codes.
The aforementioned wind power plant subsystems interact in complex fashion so that changes in one subsystem can affect the overall performance of a wind power plant in unexpected ways. In addition, the variable nature of both wind power availability and electrical grid demands further increase the potential for undesirable and unexpected results when wind power plant subsystems or components of the wind power plant are added, removed, or otherwise modified. Testing of new or modified power plant components and
configurations by simply placing these components and configurations in service and observing the results thus introduces undesirable expenses and risks into the operation of the wind power plant.
Accordingly, there is a need for a device and a method which allow testing of power plant components and system modifications before they are
implemented avoid introducing undesirable components and modifications into wind power plants.
SUMMARY OF THE INVENTION
It is an object of the invention to improve the testing of wind power plant components.
The method according to an embodiment of the invention is a method of testing a wind power plant controller. The controller is configured to receive signals from and transmit signals to wind turbines in a wind power plant. The testing method includes: (1 ) connecting the wind power plant controller to a test device. The test device includes one or more subsystem simulators. At least one subsystem simulator is arranged to simulate a certain wind power plant subsystem or conditions influencing wind turbines in a wind power plant; and (2) testing the wind power plant controller by performing a simulation via the subsystem simulators.
Program instructions for performing the aforementioned method may be implemented in a computer program product. The program instructions are stored on a computer readable storage medium. The device according to an embodiment of the invention is a test device for testing a wind power plant component. The test device includes an interface for connecting a wind power plant controller to the test device and one or more subsystem simulators. Each of the one or more subsystem simulators is configured to simulate an associated wind power plant subsystem or condition.
When the wind power plant control system is connected to simulators which will simulate the behavior of the electrical grid and/or the turbines in the wind farm power plant, it becomes possible to execute real time control using the proper wind power plant controller prior to implementation thereof on a grid.
BRIEF DESCRIPTION OF THE FIGURES
The present invention will now be explained, by way of example only, with reference to the accompanying Figures, where
Figure 1 shows a schematic drawing of a wind power plant;
Figure 2 shows a schematic drawing of a test device for testing a wind power plant controller;
Figure 3 shows a schematic drawing similar to Figure 2 that further includes a test measurement simulator; and Figure 4 is a flow chart of a method according to the invention.
DETAILED DESCRIPTION
Referring now to Figure 1 , a wind power plant 10 includes a wind power plant controller (WPP) 20, a plurality of wind turbines represented by wind turbines 30, 31 , 32, 33, and optional reactive power compensation equipment 40. The wind turbines 30-33 are connected via radials 36, 37, 38, 39 and switches 50, 51 to common connection points where the power output of the wind power plant 10 is coupled to one or more electric grids 60, 61 . The wind power plant 10 as illustrated also includes a switch 52 that connects a first group of wind turbines 30, 31 and a second group of wind turbines 32, 33 within the wind power plant 10. The first and second groups of wind turbines may be ganged together by closing the switch 52 so that the wind power plant 10 collectively provides a composite power output to the one or more electrical grids 60, 61 .
By opening the switch 52, the first and second groups of wind turbines may be electrically isolated from each other. This isolation allows the wind power plant 10 to provide power to the grids 60, 61 as two electrically separate wind power plants using only a subset of the available wind turbines 30-33 under the control of the wind power plant controller 20 to supply power to each grid 60, 61 . The switches 50-52 are typically not operated directly by the wind power plant controller 20. However, feedback signals relating to the status and/or position of the switches are typically provided to the wind power plant controller 20 to allow the controller 20 to factor in the state of the switches 50-52 as a parameter for controlling the operation of the wind power plant 10.
The wind power plant controller 20 provides control signals to the wind turbines 30-33 in the form of power set points such as, but not limited to, the desired active and/or reactive power output to be supplied from the individual wind turbines 30-33. These set points and control signals may be used by the wind turbine power controller 20 to adjust the power output of the wind turbines 30- 33. To provide plant level control of the reactive power supplied to the grid 60, 61 , the wind power system controller 20 may be operatively coupled to the optional compensation equipment 40, which may be configured to adjust the amount of reactive power provided to the grid using known methods. The wind power system controller 20 may thereby regulate the active and reactive power provided to the electrical grid 60, 61 by adjusting the individual power output levels of each wind turbine 30-33, and/or by adjusting the reactive power of the wind power plant 10 at a plant level.
To this end, the wind power plant controller 20 may obtain measurements of the active and reactive power supplied to the electrical grid 60, 61 , as indicated by arrowed line 4. From these power measurements, the wind power plant controller 20 calculates new power set points and other control signals, as
appropriate, to be supplied to the wind turbines 30-33 and other power control equipment, such as the compensation equipment 40 and the switches 50-52. The wind power plant controller 20 transmits these set points and other control signals to the appropriate components and subsystems of the wind power system 10 as indicated by arrowed line 5. In response to the control signals 5, the wind power plant components and subsystems may react by adjusting the power output of the wind turbines 30-33 and wind power system 10 as indicated by arrowed line 6. Although only four wind turbines are shown in Figure 1 it should be understood that the wind power plant 10 may comprise a smaller or larger number of wind turbines 30-33. For example, a large wind power plant 100 might include over 100 wind turbines 30-33. Moreover, it is not mandatory that the wind power plant includes compensation equipment 40, in which case the wind power plant controller 20 may control the composite power output of the wind power plant 10 by controlling the power output of the wind turbine power converters.
Referring now to Figures 2 and 3, a schematic drawing illustrating a test device or system 500 for testing a wind power plant controller 20 is presented. The test device 500 comprises a simulator system that includes subsystem simulators in the form of a wind turbine simulator 530, a reactive compensation equipment simulator 540, a circuit breaker simulator 550, a grid simulator 560, a wind simulator 570, a cabling system simulator 575 that simulates the cabling system within the wind power plant 10, an energy storage simulator 580, and/or a supervisory control and data acquisition (SCADA) system simulator 585. Figure 2 illustrates one embodiment in which a grid measurement subsystem 565 is shown outside the test device 500, while Figure 3 illustrates an alternative embodiment in which a grid measurement subsystem is
implemented as a software algorithm within the test device 500. The grid
measurement subsystem as illustrated in Figure 3 is thereby implemented as a grid measurement simulator 566.
To provide the test device 500 with accurate models on which to base wind power plant simulations, the subsystem simulators may include data on real- world subsystem performance over a range of environmental conditions. For example, the wind turbine simulator 530 may include the operation of one or more specific models of wind turbines over a range of operating conditions, including a range of wind speeds. Similarly, the reactive compensation equipment simulator 540 may include simulation of reactive compensation equipment, such as a STATCOM or capacitor banks. The grid simulator 560 may include a range of possible grid operation conditions, including faults in the grid, low voltage ride through situations, frequency fluctuations, inclusion of large loads in the grid, etc. The wind simulator 570 may include simulation of a range of different wind conditions, e.g. wind speed, gusts, wind shear, turbulence, etc. The cabling system simulator 575 may include the electric properties of the cables within the wind power plant 10, such as the impedance of the cables. The energy storage simulator 580 may include properties of an energy storage system within or in conjunction to the wind power plant 10, including the charging state of the energy storage system. The simulated energy storage system might include a battery, a flywheel or other suitable power storage equipment.
The test device 500 may include a control interface 590 that connects the wind power plant components to the associated subsystem simulators. The control interface 590 may thereby allow the subsystem simulators to exchange data with their associated wind power plant subsystems. For example, the wind turbine simulator 530 may obtain operational data from the wind power plant controller 20 related to the operation of the wind turbines 30-33. This data may
be used to modify the wind turbine simulator 530 so that it more accurately predicts the behavior of the wind turbines 30-33 as configured in the wind power plant 10. Likewise, data generated by the wind turbine simulator 530 may be provided to the wind power plant controller 20 to improve, control, or otherwise modify the performance of the controller 20. The grid simulator 560 may exchange data with the grid measurement subsystem 565, whether implemented external to the test device 500 (Figure 2) or, alternatively, within the test device 500 as a grid measurement simulator 566 (Figure 3) to improve the performance of the grid simulator 560.
When the wind power plant controller 20 is connected to simulators that simulate the behavior of the electrical grid 60, 61 and/or the wind turbines 30- 33 comprising the wind power plant 10, it becomes possible to execute real time control using the proper wind power plant controller 20 prior to
implementation thereof on a grid. Advantageously, the test device 500 provides the ability to conduct realistic simulations of wind power plant control strategies and control system under various scenarios which would be difficult, expensive, dangerous, and/or otherwise undesirable to create as a real-world test. The test device 500 thereby provides a virtual laboratory that renders it possible to perform realistic testing of the wind power plant control systems in various scenarios even before the wind power plant 10 is built. The test device 500 thus provides the ability to demonstrate wind power plant control system capabilities prior to implementation. Moreover, the test device 500 facilitates testing of the wind power plant controller 20 in the case of fluctuations or faults on the electrical grid, e.g., a low voltage ride through (LVRT) or frequency deviations.
As an example of how the test device 500 might provide a wind power plant simulation using data provided by the subsystem simulators, the output from
the wind simulator 570 may be provided the wind turbine simulator 530 to generate wind turbine operational scenarios based on probable or extreme wind conditions at the wind power plant 10. Likewise, signals may also be exchanged between the circuit breaker simulator 550, grid simulator 560, cabling system simulator 575, energy storage simulator 580, and wind turbine simulator 530 based on historical and/or expected behavior of related wind power plant components and the grid 60, 61 . Signals may also be
exchanged between the grid simulator 560, the grid measurement subsystem 565 or grid measurement simulator 566, as well as between the grid simulator 560 and the circuit breaker simulator 550. Signals may also be exchanged between the grid measurement subsystem 565 and/or simulator 566, between grid measurement subsystem 565 and/or simulator 566 and the wind turbine simulator 530 as well as between the wind power plant controller 20 and the reactive compensation equipment simulator 540 and SCADA simulator 585.
The invention may be implemented in any suitable form including hardware, software, firmware or any combination of these. The invention or some features of the invention can be implemented as computer software running on one or more data processors and/or digital signal processors. The elements and components of embodiments of the invention may be physically, functionally and logically implemented in any suitable way. Indeed, the functionality may be implemented in a single unit, in a plurality of units or as part of other functional units. As such, the invention may be implemented in a single unit, or may be physically and functionally distributed between different units and processors.
Thus, the simulator subsystems may be implemented as different computer software algorithms running on one or more data processors. For example, as shown in Figure 2, the grid measurement subsystem 565 resides outside the
test device 500. The grid measurement subsystem 565 may be a hardware grid meter connectable to the wind power plant controller 20 as well as to the test device 500 for testing the wind power plant controller 20. In an alternative embodiment of the invention, the grid measurement subsystem 565 may be implemented as a software algorithm within the test device 500 that provides a grid measurement simulator 566 as illustrated in Figure 3.
Referring now to Figure 4, a flow chart of a method 100 of testing the wind power plant controller 20 according to an embodiment of the invention is presented. The wind power plant controller 20 is configured to receive signals from and transmit signals to wind turbines 30-33 in the wind power plant 10.
In block 102 the wind power plant controller 20 is connected to the test device 500. As described with respect to Figure 2, the test device 500 may include a plurality of subsystem simulators that each represents a component or subsystem of the wind power plant 10. Each subsystem simulator is thereby arranged to simulate a certain wind power plant subsystem or conditions influencing the wind turbines 30-33 in the wind power plant 10. Once the test device 500 has been configured to model the subsystems of the wind power plant 10, the method 100 proceeds to block 103.
In block 103, the wind power plant controller 20 is tested by performing a simulation via the subsystem simulators and by registering the performance of the wind power plant controller 20 as a function of the simulations. The results of the simulations from the test device 500 may be used to adjust parameters within the wind power plant controller 20 to optimize the performance of the wind power plant 10, to predict the effect of changes to subsystems within the wind power plant 10, or to control the wind power plant 10. Different configurations and environmental scenarios may thereby be tested with regard
to the wind power plant 10 by modeling the wind power plant 10 in the test device (500).
It should be noted that as used herein, the term "wind power plant" is synonymous to "wind farm" and "wind park" and is meant to denote a plurality of wind turbines as well further units, equipment, or subsystems, as
appropriate, such as a power plant controller and/or compensation equipment.
The methods described herein can be implemented by computer program instructions supplied to the processor of any type of computer to produce a machine with a processor that executes the instructions to implement the functions/acts specified herein. These computer program instructions may also be stored in a computer readable medium that can direct a computer to function in a particular manner. To that end, the computer program instructions may be loaded onto a computer to cause the performance of a series of operational steps and thereby produce a computer implemented process such that the executed instructions provide processes for implementing the functions/acts specified herein. Such computer program instructions may also be provided through a computer based network, e.g., the Internet.
The elements and components of embodiments of the invention may be physically, functionally and logically implemented in any suitable way. For example, the functionality may be implemented in a single unit, in a plurality of units or as part of other functional units. As such, the invention may be implemented in a single unit, or may be physically and functionally distributed between different units and processors.
Although the present invention has been described in connection with the specified embodiments, it is not intended to be limited to the specific form set
forth herein. Rather, the scope of the present invention is limited only by the accompanying claims. In the claims, the term "comprising" does not exclude the presence of other elements or steps. Additionally, although individual features may be included in different claims, these features may possibly be advantageously combined, and the inclusion in different claims does not imply that a combination of features is not feasible and/or advantageous. In addition, singular references do not exclude a plurality. Thus, references to "a", "an", "first", "second" etc. do not preclude a plurality. Furthermore, reference signs in the claims shall not be construed as limiting the scope of embodiments of the invention.
Claims
1 . A method (100) of testing a wind power plant component, comprising the steps of:
connecting (102) a wind power plant controller (20) to a test device
(500), the test device (500) comprising one or more subsystem simulators 530, 540, 550, 560, 566, 570, 575, 580, 585) configured to simulate associated wind power plant subsystems or conditions influencing wind turbines (30-33) in a wind power plant (20); and
testing (103) the wind power plant controller (20) by performing a simulation using the subsystem simulators.
2. A method (100) according to claim 1 , wherein the wind power plant component is a wind power plant controller (20) configured to receive signals from and transmit signals to the wind turbines (30-33).
3. A method (100) according to claim 1 , wherein the subsystem simulators of the test device (500) comprise one or more of a wind turbine simulator (530), a reactive compensation simulator (540), a circuit breaker simulator (550), a grid simulator (560), a grid measurement simulator (566), a wind simulator (570), a cabling system simulator (575), an energy storage simulator (580), and a SCADA simulator (585).
4. A method (100) according to claim 3, wherein the subsystem simulators comprise a wind turbine simulator (530) and a wind simulator (570).
5. A method (100) according to claim 4, the method further comprising:
transmitting an output signal from the wind simulator (570) to the wind turbine simulator (530).
6. A method according to any of the claims 1 to 5, the method further comprising:
obtaining grid data via a grid meter from a grid measurement subsystem (565); and
exchanging signals between the grid meter and the wind power plant controller (20).
7. A computer program product comprising:
a computer readable storage medium; and
program instructions for performing the method of claims 1 -6, wherein the program instructions are stored on the computer readable storage medium.
8. A test device (500) for testing a wind power plant component, the test device (500) comprising:
an interface for connecting a wind power plant controller (20) to the test device (500); and
one or more subsystem simulators (530, 540, 550, 560, 566, 570, 575, 580, 585), wherein each of the one or more subsystem simulators (530, 540, 550, 560, 566, 570, 575, 580, 585) is configured to simulate an
associated wind power plant subsystem or condition.
9. A test device (500) according to claim 8 wherein the wind power plant component is a wind power plant controller (20).
10. A test device (500) according to claim 9, wherein the one or more subsystem simulators (530, 540, 550, 560, 566, 570, 575, 580, 585) includes a grid simulator (560), and further comprising: a grid measurement subsystem (565) connectable to the wind power plant controller (20) and to the grid simulator (560).
1 1 . A test device (500) according to claim 8, wherein the subsystem simulators (530, 540, 550, 560, 566, 570, 575, 580, 585) comprise one or more of a wind turbine simulator (530), a reactive compensation simulator (540), a circuit breaker simulator (550), a grid simulator (560), a grid measurement simulator (566), a wind simulator (570), a cabling system simulator (575), an energy storage simulator (580), and a SCADA simulator (585).
12. A test device (500) according to claim 8, wherein the subsystem simulators comprise a wind turbine simulator (530) and a wind simulator (570).
Applications Claiming Priority (4)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US35137910P | 2010-06-04 | 2010-06-04 | |
| DKPA201000479 | 2010-06-04 | ||
| DKPA201000479 | 2010-06-04 | ||
| US61/351,379 | 2010-06-04 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2011150941A1 true WO2011150941A1 (en) | 2011-12-08 |
Family
ID=45066194
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/DK2011/050194 Ceased WO2011150941A1 (en) | 2010-06-04 | 2011-06-02 | Device and method for testing a wind power plant component |
Country Status (1)
| Country | Link |
|---|---|
| WO (1) | WO2011150941A1 (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2013156026A1 (en) * | 2012-04-16 | 2013-10-24 | Kk-Electronic A/S | A data acquisition system and a method of acquiring data from a wind turbine |
| CN103558771A (en) * | 2013-11-05 | 2014-02-05 | 济南轨道交通装备有限责任公司 | Wind power plant simulation testing platform and testing method thereof |
| EP2853731A1 (en) * | 2013-09-27 | 2015-04-01 | Korea Electric Power Corporation | Apparatus for simulating wind power farm |
| CN105760636A (en) * | 2016-04-14 | 2016-07-13 | 南方电网科学研究院有限责任公司 | A real-time simulation system and real-time simulation method for a power generation system |
| CN108121214A (en) * | 2016-11-28 | 2018-06-05 | 北京金风科创风电设备有限公司 | Yaw strategy simulation method and system for wind turbine generator |
| US10018185B2 (en) | 2013-12-30 | 2018-07-10 | General Electric Company | System and method for commissioning wind turbines |
| CN112983753A (en) * | 2021-03-03 | 2021-06-18 | 南京理工大学 | Draught fan mechanical dynamic simulation method and system based on speed-sensorless ground test bed |
| CN116880241A (en) * | 2023-08-04 | 2023-10-13 | 山东大学 | Multi-level control integrated system and method for offshore wind turbine ground test platform |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2170325A (en) * | 1985-01-24 | 1986-07-30 | Sojuzorgenergogaz Proizv Ob | Device for automatic testing of gas turbine automatic control system |
| EP1659287A2 (en) * | 2004-11-17 | 2006-05-24 | NORDEX ENERGY GmbH | Device and procedure for the functional test of a wind energy plant |
| DE102007052980A1 (en) * | 2007-11-07 | 2009-05-14 | Nordex Energy Gmbh | Method for representing operational behavior of wind energy plant, involves representing wind energy plant three-dimensionally by visualization unit, which selects computed operational data sequentially from simulation unit |
-
2011
- 2011-06-02 WO PCT/DK2011/050194 patent/WO2011150941A1/en not_active Ceased
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2170325A (en) * | 1985-01-24 | 1986-07-30 | Sojuzorgenergogaz Proizv Ob | Device for automatic testing of gas turbine automatic control system |
| EP1659287A2 (en) * | 2004-11-17 | 2006-05-24 | NORDEX ENERGY GmbH | Device and procedure for the functional test of a wind energy plant |
| DE102007052980A1 (en) * | 2007-11-07 | 2009-05-14 | Nordex Energy Gmbh | Method for representing operational behavior of wind energy plant, involves representing wind energy plant three-dimensionally by visualization unit, which selects computed operational data sequentially from simulation unit |
Non-Patent Citations (1)
| Title |
|---|
| HOOFT EN AL V: "Real time process simulation for evaluation of wind turbine control systems", INTERNET CITATION, 14 August 2008 (2008-08-14), pages 1 - 4, XP008095362, Retrieved from the Internet <URL:http://www.ecn.nl/docs/library/report/2003/rx03043.pdf> [retrieved on 20080814] * |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2013156026A1 (en) * | 2012-04-16 | 2013-10-24 | Kk-Electronic A/S | A data acquisition system and a method of acquiring data from a wind turbine |
| CN104380215A (en) * | 2012-04-16 | 2015-02-25 | Kk风能解决方案公司 | A data acquisition system and a method of acquiring data from a wind turbine |
| EP2853731A1 (en) * | 2013-09-27 | 2015-04-01 | Korea Electric Power Corporation | Apparatus for simulating wind power farm |
| US10180997B2 (en) | 2013-09-27 | 2019-01-15 | Korea Electric Power Corporation | Apparatus for simulating wind power farm |
| CN103558771A (en) * | 2013-11-05 | 2014-02-05 | 济南轨道交通装备有限责任公司 | Wind power plant simulation testing platform and testing method thereof |
| EP2869144A1 (en) * | 2013-11-05 | 2015-05-06 | Jinan Railway Vehicles Equipment Co., Ltd. | Simulation testing platform for wind power plant and testing method thereof |
| US10018185B2 (en) | 2013-12-30 | 2018-07-10 | General Electric Company | System and method for commissioning wind turbines |
| CN105760636A (en) * | 2016-04-14 | 2016-07-13 | 南方电网科学研究院有限责任公司 | A real-time simulation system and real-time simulation method for a power generation system |
| CN108121214A (en) * | 2016-11-28 | 2018-06-05 | 北京金风科创风电设备有限公司 | Yaw strategy simulation method and system for wind turbine generator |
| CN112983753A (en) * | 2021-03-03 | 2021-06-18 | 南京理工大学 | Draught fan mechanical dynamic simulation method and system based on speed-sensorless ground test bed |
| CN116880241A (en) * | 2023-08-04 | 2023-10-13 | 山东大学 | Multi-level control integrated system and method for offshore wind turbine ground test platform |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US9822765B2 (en) | Wind power plant control system | |
| Hansen et al. | Dynamic modelling of wind farm grid interaction | |
| WO2011150941A1 (en) | Device and method for testing a wind power plant component | |
| CN105205232A (en) | RTDS (real time digital simulator) based stability simulation testing platform for micro grid system | |
| CA2878335A1 (en) | Method and apparatus for feeding electric energy into an electric supply grid | |
| CN106527182A (en) | Power grid stability test system containing multiple types of high-penetration new energy based on RTDS and method thereof | |
| CN205823545U (en) | A kind of test system of wind generating set pitch control system | |
| CN102854463B (en) | Megawatt wind power simulation test system and test method | |
| CN104201716A (en) | Electro-mechanical transient simplified model building method based on controlled current source | |
| Wu et al. | Development of an equivalent wind farm model for frequency regulation | |
| CN102830692A (en) | Low-voltage ride through consistency testing system and method of main control system of wind turbine generator | |
| CN117707117A (en) | A wind turbine main control testing device and testing method | |
| Mahmoud et al. | Integrated optimal active and reactive power control scheme for grid connected permanent magnet synchronous generator wind turbines | |
| Abbes et al. | Participation of PMSG-based wind farms to the grid ancillary services | |
| Martinez et al. | Tools for analysis and design of distributed resources—Part IV: Future trends | |
| CN103076745A (en) | Simulation method for wind turbine generator model in conventional power system simulation software | |
| CN103207373A (en) | Test system and test method of backup power of pitch system of wind turbine generator set | |
| EP2620780A1 (en) | Grid performance test unit for wind turbines | |
| Wang et al. | Development of wind-energy modeling technology and standards | |
| Gevorgian et al. | Wgrid-49 GMLC project report: Understanding the role of short-term energy storage and large motor loads for active power controls by wind power | |
| CN113536532A (en) | A method and system for calculating short-circuit current provided by a double-fed fan | |
| Yang et al. | Aggregating wind farm with DFIG in power system online analysis | |
| Ofoli et al. | Real-time digital simulator testbed using eMEGASim® for wind power plants | |
| KR102328080B1 (en) | System for testing performance and reliability of distributed power source and method thereof | |
| CN117748589A (en) | Wind farm overall process active power control simulation system and method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11729891 Country of ref document: EP Kind code of ref document: A1 |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 11729891 Country of ref document: EP Kind code of ref document: A1 |