US20160060817A1 - Method and System for Pouring Consecutive Separating Sections of Concrete Structures - Google Patents
Method and System for Pouring Consecutive Separating Sections of Concrete Structures Download PDFInfo
- Publication number
- US20160060817A1 US20160060817A1 US14/471,826 US201414471826A US2016060817A1 US 20160060817 A1 US20160060817 A1 US 20160060817A1 US 201414471826 A US201414471826 A US 201414471826A US 2016060817 A1 US2016060817 A1 US 2016060817A1
- Authority
- US
- United States
- Prior art keywords
- concrete
- section
- barrier
- dowel
- pouring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims abstract description 38
- 230000004888 barrier function Effects 0.000 claims abstract description 74
- 239000000463 material Substances 0.000 claims description 6
- 239000002991 molded plastic Substances 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 239000000919 ceramic Substances 0.000 claims description 2
- 239000002131 composite material Substances 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 10
- 230000008602 contraction Effects 0.000 description 3
- 241000272470 Circus Species 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 238000000926 separation method Methods 0.000 description 2
- 238000013519 translation Methods 0.000 description 2
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 229910052782 aluminium Inorganic materials 0.000 description 1
- 230000001143 conditioned effect Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000009977 dual effect Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 239000007769 metal material Substances 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 238000011160 research Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C11/00—Details of pavings
- E01C11/02—Arrangement or construction of joints; Methods of making joints; Packing for joints
- E01C11/04—Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
- E01C11/14—Dowel assembly ; Design or construction of reinforcements in the area of joints
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C11/00—Details of pavings
- E01C11/02—Arrangement or construction of joints; Methods of making joints; Packing for joints
- E01C11/04—Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
- E01C11/06—Methods of making joints
Definitions
- This invention relates to the field of roadway construction. More specifically, the present invention comprises a device and method for separating sections of concrete fir multiple structures.
- Governing bodies such as the department of transportation for states and other territories, have rules and regulations which must be followed when erecting structures associated with walking paths and roadways. These restrictions pertain to roads, sidewalks, retaining, gravity and barrier walls, junction and/or moment slabs and other structures that are constructed using concrete. Although these restrictions are enforced with public safety and structural integrity in mind, the regulations create inefficiencies during construction.
- each structure must have concrete poured in separate sections of a specified length.
- the separate sections of concrete create joints along the length of the structure. These joints allow for expansion, contraction, bond breaks, and movement of each individual section of concrete, thereby decreasing the likelihood of cracking and other complications.
- sonic structures require an interlocking joint comprising a mortise and tenon wherein each concrete section is not bonded together.
- the expansion joint (also known as the “bond break” joint) is typically created using a piece of lumber with a relatively small thickness to create a temporary form.
- the current process used to create an array of junction and moment slabs requires the construction team to measure out each section of concrete to be poured.
- the sections are poured in an alternating fashion. Typically, a first section is poured, then a space which is equal to the length of a section is left vacant. Next, concrete is poured adjacent to the open space for a section, and so on down the line of junction/moment slabs.
- the vacant sections can be filled with concrete (this is typically done the day after the first concrete sections are poured).
- the adjacent concrete sections are prevented from bonding together, and the required expansion joint is formed between each section of concrete.
- dowel bars are inserted at regular intervals along the length of each piece of lumber. The hole for each dowel bar must be measured and drilled prior to pouring concrete.
- the present invention comprises a device and method for pouring consecutive concrete sections which are disjoint.
- the present invention includes the required bond breaks, which prevent the adjacent concrete slabs from bonding to each other.
- This joint is referred to throughout the following disclosure as an expansion joint or bond breaking joint, as it serves a dual purpose.
- the inventive device and method preferably include a barrier used to separate adjacent concrete slabs. This barrier is preferably erected in such a way that it allows a construction crew to continuously pour concrete in successive sections of a concrete structure, which prior to the current invention, could not be poured continuously. Previously, concrete sections were poured in an alternating fashion in order to create an expansion joint between each section of concrete. However, the current inventive method and device allows the crew to pour adjacent concrete sections while still creating an expansion joint between each concrete section.
- Each concrete section barrier includes an upright surface and dowel sleeves. Prior to pouring concrete into each designated gap, which have been measured and sectioned off, dowel bars are inserted into each dowel sleeve. Then, each gap is filled with concrete in a manner that allows a crew to pour adjacent gaps. This is an improvement on the previous method, wherein alternating gaps are filled on a first day, and then the remaining gaps are filled on a second day.
- FIG. 1 is a perspective view, showing the concrete section barrier of the present invention.
- FIG. 2 is a perspective view, showing a channel in which the concrete is to be poured.
- FIG. 3 is a perspective view, showing the concrete section harrier inserted between two form walls.
- FIG. 4 is a perspective view, showing the insertion of dowel bars into the concrete section barrier.
- FIG. 5 is a perspective view, showing the pouring of concrete.
- FIG. 6 is a perspective view, showing the concrete section barrier embedded in dried concrete sections.
- FIG. 7 is a perspective view, showing an alternate embodiment of the section barrier of the present invention.
- FIG. 1 shows a preferred embodiment of the present concrete section barrier 10 .
- the concrete section barrier 10 comprises upright surface 12 and dowel sleeves 14 .
- Concrete section barrier 10 serves two primary purposes. First, concrete section barrier 10 acts as a barrier between sections of concrete. As discussed in a previous section, many governing bodies require concrete structures to be poured in sections of concrete as opposed to a singular slab. Concrete section barrier 10 acts as the separator for those sections, whereby concrete can be poured on either side of concrete section barrier 10 . Second, concrete section barrier 10 preferably creates an expansion joint between each section of concrete. The expansion joint allows each section of concrete to expand, contract, and for slight movements while decreasing the likelihood of cracking or damaging the concrete sections.
- concrete section barrier 10 is fabricated using a molded plastic.
- a molded plastic material is capable of expansion and contraction.
- corrosion of molded plastic is less likely than with a metallic material such as steel or aluminum.
- molded plastic may be the preferred embodiment, there may be other suitable materials used for concrete section barrier 10 .
- suitable materials for barrier 10 are a composite, ceramic, coated steels, or another plastic material.
- FIG. 2 shows the channel 17 prior to insertion of concrete section barrier 10 .
- channel 17 is bounded by ground 16 and two form walls 18 .
- FIG. 3 shows a setup for a series of junction or moment slab sections with concrete section barrier 10 inserted at a specified location into channel 17 , which allows barrier 10 to act as a separator for each section.
- Concrete section barrier 10 preferably separates channel 17 into first gap 20 and second gap 22 , thereby allowing for full separation within the channel 17 .
- the reader will note that the setup illustrated in FIG. 3 is shown prior to the pouring of concrete. Once the ground 16 has been properly conditioned (leveled, packed, etc.), form walls 18 are fixed in place as illustrated, thereby creating channel 17 (as shown in FIG. 2 ).
- form walls 18 are positioned such that the walls are parallel to each other.
- the spacing between the two form walls 18 is preferably equal to the length of concrete section barrier 10 , thereby allowing concrete section barrier 10 to effectively separate the two sections of concrete to be poured.
- concrete section barrier 10 is held in place at the form wall-barrier junction 19 .
- the mechanism used to maintain barrier 10 in an upright position can be any technique known in the art. One such method used to maintain barrier 10 in an upright position is shown.
- Chamfer 21 is preferably attached to barrier 10 and form wall 18 at each form wall-barrier junction 19 in order to maintain the desired position of concrete section barrier 10 .
- FIG. 3 only shows a single concrete section harrier 10 . Therefore, the figure also only shows two gaps for concrete to be poured a first gap 20 and a second gap 22 . However, there are multiple gaps and barriers 10 along a specified stretch where junction slabs (or other concrete structures) are to be constructed.
- dowels 24 Prior to pouring concrete into first gap 20 and second gap 22 , dowels 24 are preferably inserted into dowel sleeves 14 . This is illustrated in FIG. 4 .
- Each dowel sleeve 14 includes an extruded cylinder (located within second gap 22 in the figure) and a dowel sleeve opening 26 (located on the first gap 20 side of concrete section barrier 10 ).
- dowels 24 are preferably inserted into dowel sleeve opening 26 .
- each dowel sleeve 14 is hollow in order to allow dowels 24 to be inserted.
- FIG. 4 demonstrates the expansion joint present while the present invention is in used.
- the concrete poured into first gap 20 adheres to dowels 24 .
- the concrete poured into second gap 22 adheres to dowel sleeves 14 not dowels 24 .
- contraction or expansion of the concrete in first gap 20 will result in dowels 24 translating along dowel sleeve centerlines 28 within dowel sleeve opening 26 .
- FIG. 5 shows concrete section barrier 10 inserted between form walls 18 , and with dowels 24 fully inserted into dowel sleeves 14 .
- concrete section barrier 10 is preferably covered with expansion paper.
- the concrete bonds to the expansion paper as opposed to barrier 10 .
- concrete 30 can now be poured.
- One preferred advantage of using concrete section barrier 10 in conjunction with dowel sleeves 14 and dowels 24 is that concrete 30 is poured successively (or even simultaneously if possible illustrated in the figure) along the sections of junction or moment slabs.
- FIG. 6 shows two concrete junction and/or moment slabs 32 which have been poured and dried.
- the reader will note that dashed hidden lines are made visible in order to illustrate features which would not ordinarily be seen in the current view.
- the figure includes a first concrete slab 34 and a second concrete slab 36 . Some preferred features of the invention are demonstrated in the figure.
- the concrete section barrier 10 located between first concrete slab 34 and second concrete slab 36 creates separation between the two slabs.
- the center barrier 10 between the first slab 34 and the second slab 36 remains in place after the concrete has dried. In fact, each concrete section barrier 10 remains in place for the lifetime of the array of junction or moment slabs.
- each junction or moment slab 32 includes a series of dowels 24 and dowel sleeves 14 which are embedded into the concrete of the slab.
- each barrier 10 is placed such that the dowel sleeves 14 are facing the upper right hand corner, as illustrated in the figure. This insures that each concrete slab 32 includes a series of dowels 24 and dowel sleeves 14 embedded into the slab 32 , rather than each end of the slab 32 containing only dowels 24 or only dowel sleeves 14 . Of course, the order could be reversed, whereby dowel sleeves 14 face the lower left hand side of the figure.
- the direction of the concrete section barriers 10 depends on the direction in which the concrete is poured.
- FIG. 7 shows an alternate embodiment of concrete barrier 10 including a keyway 38 which can be used in the present method.
- Keyway 38 creates a mortise 40 and a tenon 42 in each successive concrete section.
- the embodiment illustrated creates interlocking sections of concrete by means of the mortise 40 and tenon 42 joint.
- the interlocking sections increase the strength of each expansion joint, especially when coupled with the dowel sleeves 14 and dowel bars 24 (not shown in the current figure).
- the reader will note that the addition of keyway 38 still allows the concrete structure to be constructed using a continuous pouring of adjacent sections. This embodiment simply increases the strength of the expansion joint created between each concrete section.
- dowel sleeves 14 and dowels 24 act to maintain the alignment of junction/moment slabs 32 . While translation along axis of the dowels/dowel sleeves is allowed, the dowels 24 and dowel sleeves 14 inhibit lateral (radially in reference to the dowels/sleeves) and vertical translation. Thus, each concrete slab 32 is capable of expanding and contracting in the axial direction.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
A device and method for pouring consecutive concrete sections. The inventive device and method preferably include a barrier used to separate adjacent concrete slabs. This barrier is preferably erected in such a way that it allows a construction crew to continuously pour concrete in successive sections of a concrete structure, which prior to the current invention, could not be poured continuously. Previously, concrete sections were poured in an alternating fashion in order to create an expansion joint between each section of concrete which also acts to break the bond between each concrete section. However, the current inventive method and device allows the crew to pour adjacent concrete sections while still creating a joint between each concrete section. Each concrete section barrier preferably includes an upright surface and dowel sleeves. Prior to pouring concrete into each designated gap dowel bars are inserted into each dowel sleeve.
Description
- This non-provisional patent application is a continuation-in-part of U.S. application Ser. No. 14/016,412, filed on Sep. 3, 2013, which is a continuation-in-part of U.S. application Ser. No. 13/787,487. The original application was filed on Mar. 6, 2013. All applications list the same inventors.
- Not applicable
- Not Applicable
- 1. Field of the Invention
- This invention relates to the field of roadway construction. More specifically, the present invention comprises a device and method for separating sections of concrete fir multiple structures.
- 2. Description of the Related Art
- Governing bodies, such as the department of transportation for states and other territories, have rules and regulations which must be followed when erecting structures associated with walking paths and roadways. These restrictions pertain to roads, sidewalks, retaining, gravity and barrier walls, junction and/or moment slabs and other structures that are constructed using concrete. Although these restrictions are enforced with public safety and structural integrity in mind, the regulations create inefficiencies during construction.
- One of the main restrictions mandated by most governing bodies for construction of retaining walls, gravity walls, barrier walls, and junction slabs is that each structure must have concrete poured in separate sections of a specified length. The separate sections of concrete create joints along the length of the structure. These joints allow for expansion, contraction, bond breaks, and movement of each individual section of concrete, thereby decreasing the likelihood of cracking and other complications. In addition, sonic structures require an interlocking joint comprising a mortise and tenon wherein each concrete section is not bonded together.
- In the case of junction and moment slabs, the expansion joint (also known as the “bond break” joint) is typically created using a piece of lumber with a relatively small thickness to create a temporary form. The current process used to create an array of junction and moment slabs requires the construction team to measure out each section of concrete to be poured. However, due to the requirement of an expansion joint, whereby each section must not be bonded together, the sections are poured in an alternating fashion. Typically, a first section is poured, then a space which is equal to the length of a section is left vacant. Next, concrete is poured adjacent to the open space for a section, and so on down the line of junction/moment slabs. Once the first sections of concrete slabs have dried and cured, the vacant sections can be filled with concrete (this is typically done the day after the first concrete sections are poured). Thus, the adjacent concrete sections are prevented from bonding together, and the required expansion joint is formed between each section of concrete. In addition, dowel bars are inserted at regular intervals along the length of each piece of lumber. The hole for each dowel bar must be measured and drilled prior to pouring concrete.
- Therefore, what is needed is a device and method which allows a construction team to continuously pour isolated sections of concrete during the fabrication of an array of junction or moment slabs. The present invention achieves this objective, as well as others that are explained in the following description.
- The present invention comprises a device and method for pouring consecutive concrete sections which are disjoint. The present invention includes the required bond breaks, which prevent the adjacent concrete slabs from bonding to each other. This joint is referred to throughout the following disclosure as an expansion joint or bond breaking joint, as it serves a dual purpose. The inventive device and method preferably include a barrier used to separate adjacent concrete slabs. This barrier is preferably erected in such a way that it allows a construction crew to continuously pour concrete in successive sections of a concrete structure, which prior to the current invention, could not be poured continuously. Previously, concrete sections were poured in an alternating fashion in order to create an expansion joint between each section of concrete. However, the current inventive method and device allows the crew to pour adjacent concrete sections while still creating an expansion joint between each concrete section.
- Each concrete section barrier includes an upright surface and dowel sleeves. Prior to pouring concrete into each designated gap, which have been measured and sectioned off, dowel bars are inserted into each dowel sleeve. Then, each gap is filled with concrete in a manner that allows a crew to pour adjacent gaps. This is an improvement on the previous method, wherein alternating gaps are filled on a first day, and then the remaining gaps are filled on a second day.
-
FIG. 1 is a perspective view, showing the concrete section barrier of the present invention. -
FIG. 2 is a perspective view, showing a channel in which the concrete is to be poured. -
FIG. 3 is a perspective view, showing the concrete section harrier inserted between two form walls. -
FIG. 4 is a perspective view, showing the insertion of dowel bars into the concrete section barrier. -
FIG. 5 is a perspective view, showing the pouring of concrete. -
FIG. 6 is a perspective view, showing the concrete section barrier embedded in dried concrete sections. -
FIG. 7 is a perspective view, showing an alternate embodiment of the section barrier of the present invention. -
REFERENCE NUMERALS IN THE DRAWINGS 10 concrete section barrier 12 upright surface 14 dowel sleeve 16 ground 17 channel 18 form wall 19 form wall - barrier junction 20 first gap 21 chamfer 22 second gap 24 dowel bars 26 dowel sleeve opening 28 dowel sleeve centerline 30 concrete 32 junction or moment slab 34 first concrete slab 36 second concrete slab 38 keyway 40 mortise 42 tenon - The present invention provides a method and device for separating sections of concrete during construction of structures on or near a roadway.
FIG. 1 shows a preferred embodiment of the presentconcrete section barrier 10. Preferably, theconcrete section barrier 10 comprisesupright surface 12 anddowel sleeves 14.Concrete section barrier 10 serves two primary purposes. First,concrete section barrier 10 acts as a barrier between sections of concrete. As discussed in a previous section, many governing bodies require concrete structures to be poured in sections of concrete as opposed to a singular slab.Concrete section barrier 10 acts as the separator for those sections, whereby concrete can be poured on either side ofconcrete section barrier 10. Second,concrete section barrier 10 preferably creates an expansion joint between each section of concrete. The expansion joint allows each section of concrete to expand, contract, and for slight movements while decreasing the likelihood of cracking or damaging the concrete sections. - In one embodiment of the present invention,
concrete section barrier 10 is fabricated using a molded plastic. A molded plastic material is capable of expansion and contraction. In addition, corrosion of molded plastic is less likely than with a metallic material such as steel or aluminum. However, it should be noted that molded plastic may be the preferred embodiment, there may be other suitable materials used forconcrete section barrier 10. Some examples of suitable materials forbarrier 10 are a composite, ceramic, coated steels, or another plastic material. -
FIG. 2 shows thechannel 17 prior to insertion ofconcrete section barrier 10. Preferably,channel 17 is bounded byground 16 and twoform walls 18.FIG. 3 shows a setup for a series of junction or moment slab sections withconcrete section barrier 10 inserted at a specified location intochannel 17, which allowsbarrier 10 to act as a separator for each section.Concrete section barrier 10 preferably separateschannel 17 intofirst gap 20 andsecond gap 22, thereby allowing for full separation within thechannel 17. The reader will note that the setup illustrated inFIG. 3 is shown prior to the pouring of concrete. Once theground 16 has been properly conditioned (leveled, packed, etc.),form walls 18 are fixed in place as illustrated, thereby creating channel 17 (as shown inFIG. 2 ). Preferably,form walls 18 are positioned such that the walls are parallel to each other. In addition, the spacing between the twoform walls 18 is preferably equal to the length ofconcrete section barrier 10, thereby allowingconcrete section barrier 10 to effectively separate the two sections of concrete to be poured. Preferably,concrete section barrier 10 is held in place at the form wall-barrier junction 19. There are four form wall-barrier junctions 19 for eachbarrier 10 inserted (although only two are visible in the current view). The mechanism used to maintainbarrier 10 in an upright position (as illustrated) can be any technique known in the art. One such method used to maintainbarrier 10 in an upright position is shown.Chamfer 21 is preferably attached tobarrier 10 andform wall 18 at each form wall-barrier junction 19 in order to maintain the desired position ofconcrete section barrier 10. - The reader will note that
FIG. 3 only shows a singleconcrete section harrier 10. Therefore, the figure also only shows two gaps for concrete to be poured afirst gap 20 and asecond gap 22. However, there are multiple gaps andbarriers 10 along a specified stretch where junction slabs (or other concrete structures) are to be constructed. - Prior to pouring concrete into
first gap 20 andsecond gap 22, dowels 24 are preferably inserted intodowel sleeves 14. This is illustrated inFIG. 4 . Eachdowel sleeve 14 includes an extruded cylinder (located withinsecond gap 22 in the figure) and a dowel sleeve opening 26 (located on thefirst gap 20 side of concrete section barrier 10). As indicated by the arrows at the edge of each dowel and dowelsleeve center lines 28, dowels 24 are preferably inserted intodowel sleeve opening 26. In the preferred embodiment of the present invention, eachdowel sleeve 14 is hollow in order to allowdowels 24 to be inserted. - Those familiar with the art will realize that the configuration shown in
FIG. 4 demonstrates the expansion joint present while the present invention is in used. The concrete poured intofirst gap 20 adheres to dowels 24. Similarly, the concrete poured intosecond gap 22 adheres to dowelsleeves 14 not dowels 24. Thus, by maintaining the concrete infirst gap 20 andsecond gap 22 separate, contraction or expansion of the concrete infirst gap 20 will result indowels 24 translating alongdowel sleeve centerlines 28 withindowel sleeve opening 26. -
FIG. 5 showsconcrete section barrier 10 inserted betweenform walls 18, and withdowels 24 fully inserted intodowel sleeves 14. Once dowels 24 have been inserted intodowel sleeves 14,concrete section barrier 10 is preferably covered with expansion paper. As a result, the concrete bonds to the expansion paper as opposed tobarrier 10. As demonstrated by the arrows in the figure, concrete 30 can now be poured. One preferred advantage of usingconcrete section barrier 10 in conjunction withdowel sleeves 14 and dowels 24 is that concrete 30 is poured successively (or even simultaneously if possible illustrated in the figure) along the sections of junction or moment slabs. Those familiar with the art will realize that there is an enormous cost, labor, and time advantage of pouring continuously without the need for skipping pours on adjacent sections. By allowing adjacent sections to be poured consecutively, as opposed to pouring alternating sections that are required to dry overnight, an enormous amount of time is saved during construction a single concrete dispenser is only required to make a single pass along the construction site as opposed to two separate passes. In addition, the prior art method required removing parts used to form the first section of concrete and applying felt paper and dowel sleeves after the first section has dried. The present inventive method eliminates this step of the process. -
FIG. 6 shows two concrete junction and/ormoment slabs 32 which have been poured and dried. The reader will note that dashed hidden lines are made visible in order to illustrate features which would not ordinarily be seen in the current view. The figure includes a firstconcrete slab 34 and a secondconcrete slab 36. Some preferred features of the invention are demonstrated in the figure. First, theconcrete section barrier 10 located between firstconcrete slab 34 and secondconcrete slab 36 creates separation between the two slabs. Second, thecenter barrier 10 between thefirst slab 34 and thesecond slab 36 remains in place after the concrete has dried. In fact, eachconcrete section barrier 10 remains in place for the lifetime of the array of junction or moment slabs. Third, each junction ormoment slab 32 includes a series ofdowels 24 anddowel sleeves 14 which are embedded into the concrete of the slab. One way to achieve this is illustrated. Eachbarrier 10 is placed such that thedowel sleeves 14 are facing the upper right hand corner, as illustrated in the figure. This insures that eachconcrete slab 32 includes a series ofdowels 24 anddowel sleeves 14 embedded into theslab 32, rather than each end of theslab 32 containing only dowels 24 or only dowelsleeves 14. Of course, the order could be reversed, wherebydowel sleeves 14 face the lower left hand side of the figure. The direction of theconcrete section barriers 10 depends on the direction in which the concrete is poured. -
FIG. 7 shows an alternate embodiment ofconcrete barrier 10 including akeyway 38 which can be used in the present method.Keyway 38 creates amortise 40 and atenon 42 in each successive concrete section. The embodiment illustrated creates interlocking sections of concrete by means of themortise 40 andtenon 42 joint. The interlocking sections increase the strength of each expansion joint, especially when coupled with thedowel sleeves 14 and dowel bars 24 (not shown in the current figure). The reader will note that the addition ofkeyway 38 still allows the concrete structure to be constructed using a continuous pouring of adjacent sections. This embodiment simply increases the strength of the expansion joint created between each concrete section. - Those familiar with the art will realize that in addition to the previously mentioned applications,
dowel sleeves 14 and dowels 24 act to maintain the alignment of junction/moment slabs 32. While translation along axis of the dowels/dowel sleeves is allowed, thedowels 24 anddowel sleeves 14 inhibit lateral (radially in reference to the dowels/sleeves) and vertical translation. Thus, eachconcrete slab 32 is capable of expanding and contracting in the axial direction. - The preceding description contains significant detail regarding the hovel aspects of the present invention. It should not be construed, however, as limiting the scope of the invention but rather as providing illustrations of the preferred embodiments of the invention. Thus, the scope of the invention should be fixed by the following claims, rather than by the examples given.
Claims (20)
1. A method for pouring consecutive concrete slabs using concrete comprising:
a. providing a concrete section barrier having:
i. a surface; and
ii. at least one dowel sleeve;
b. providing at least two form walls;
c. fixing said at least two form walls in a position to form a channel;
d inserting said concrete section barrier such that said concrete section barrier is capable of separating said channel into at least two gaps;
e. maintaining said concrete section barrier in an upright position;
f. providing at least one dowel;
g. inserting said at least one dowel into said at least one dowel sleeve of said concrete section barrier; and
h. pouring said concrete in said at least two gaps consecutively.
2. The method of claim 1 , wherein said at least one dowel sleeve is further comprised of:
a. an extruded cylinder; and
b. a dowel sleeve opening.
3. The method of claim 1 , wherein said concrete barrier section is comprised of molded plastic.
4. The method of claim 1 , wherein said concrete barrier section is comprised of ceramic.
5. The method of claim 1 , wherein said concrete barrier section is comprised of a composite.
6. The method of claim 1 , wherein said concrete barrier section is comprised of coated steel or any other rigid material.
7. The method of claim 1 , wherein said form walls are fixed parallel to one another set apart a distance equal to the length of said concrete section barrier.
8. The method of claim 1 , further comprising allowing said concrete to adhere to said at least one dowel in a first gap and said at least one dowel sleeve in a second gap, such that said concrete in said first gap and said concrete in said second gap are not fixed together.
9. The method of claim 8 , wherein said at least one dowel is capable of translating within said at least one dowel sleeve upon said concrete expanding.
10. The method of claim 9 , wherein said at least one dowel is capable of translating within said at least one dowel sleeve upon said concrete contracting.
11. A method for pouring consecutive concrete slabs using concrete comprising:
a. providing at least one concrete section barrier having:
i. a surface; and
ii. a plurality of dowel sleeves;
b. providing at least two form walls;
c. fixing said at least two form walls in an upright position to form a channel;
d. inserting said at least one concrete section barrier such that said at least one concrete section barrier is capable of separating said channel into a plurality of gaps;
e. maintaining said at least one concrete section barrier in an upright position by providing a chamfer attached to said at least one concrete section barrier and said form wall;
f. providing a plurality of dowels;
g. inserting said plurality of dowels into said plurality of dowel sleeves of said at least one concrete section barrier; and
h. pouring said concrete in said at least two gaps prior to allowing said concrete to set.
12. The method of claim 11 , wherein said plurality of dowel sleeves are further comprised of:
a. a plurality of extruded cylinders; and
b. a plurality of dowel sleeve openings.
13. The method of claim 11 wherein said at east one concrete barrier section is comprised of a rigid material.
14. The method of claim 11 , further comprising covering said at least one concrete barrier section with a portion of expansion paper such that said concrete bonds to said portion of expansion paper when said concrete sets.
15. The method of claim 11 , wherein said at least one concrete barrier section further comprises a keyway having a mortise and a tenon.
16. The method of claim 15 , further comprising allowing said concrete to adhere to said keyway at said mortise and said tenon, thereby creating a mortise and tenon joint after said concrete sets.
17. The method of claim 10 , further comprising allowing said concrete to adhere to said at least one dowel in a first gap and said at least one dowel sleeve in a second gap, such that said concrete in said first gap and said concrete in said second gap are not fixed together.
18. The method of claim 16 , wherein said at least one dowel is capable of translating within said at least one dowel sleeve upon said concrete movement.
19. A method for pouring consecutive concrete slabs, using concrete, comprising:
a. providing a plurality of concrete section barriers having:
i. a surface; and
ii. a plurality of dowel sleeves;
b. providing at least two form walls;
c. fixing said at least two form walls in a position to form a channel;
d. inserting said plurality of concrete section barriers such that said plurality of concrete section barriers are capable of separating said channel into a plurality of consecutive gaps;
e. maintaining said plurality of concrete section barriers in an upright position by providing a plurality of chamfers attached to said plurality of concrete section barriers and said at least two form walls;
f. providing a plurality of dowels;
g. inserting said plurality of dowels into said plurality of dowel sleeves of said plurality of concrete section barriers; and
h. pouring said concrete in said plurality of consecutive gaps prior to allowing said concrete to set.
20. The method of claim 19 , wherein said step of pouring said concrete further comprises pouring said concrete simultaneously into said plurality of consecutive gaps.
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US14/471,826 US20160060817A1 (en) | 2013-09-03 | 2014-08-28 | Method and System for Pouring Consecutive Separating Sections of Concrete Structures |
| US14/859,773 US20170081866A1 (en) | 2013-09-03 | 2015-09-21 | Method and System for Pouring Consecutive Separating Sections of Concrete Structures |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US201314016412A | 2013-09-03 | 2013-09-03 | |
| US14/471,826 US20160060817A1 (en) | 2013-09-03 | 2014-08-28 | Method and System for Pouring Consecutive Separating Sections of Concrete Structures |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20160060817A1 true US20160060817A1 (en) | 2016-03-03 |
Family
ID=55401836
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US14/471,826 Abandoned US20160060817A1 (en) | 2013-09-03 | 2014-08-28 | Method and System for Pouring Consecutive Separating Sections of Concrete Structures |
| US14/859,773 Abandoned US20170081866A1 (en) | 2013-09-03 | 2015-09-21 | Method and System for Pouring Consecutive Separating Sections of Concrete Structures |
Family Applications After (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US14/859,773 Abandoned US20170081866A1 (en) | 2013-09-03 | 2015-09-21 | Method and System for Pouring Consecutive Separating Sections of Concrete Structures |
Country Status (1)
| Country | Link |
|---|---|
| US (2) | US20160060817A1 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109763642A (en) * | 2019-03-15 | 2019-05-17 | 中国五冶集团有限公司 | Construction structure and construction method of expansion joint wall of high-rise building |
| US11578491B2 (en) * | 2020-02-07 | 2023-02-14 | Shaw Craftsmen Concrete, Llc | Topping slab installation methodology |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3522618A (en) * | 1967-01-30 | 1970-08-04 | Hermann Stranzinger | Structural element and assembly |
| US5487249A (en) * | 1994-03-28 | 1996-01-30 | Shaw; Ronald D. | Dowel placement apparatus for monolithic concrete pour and method of use |
| US8221027B2 (en) * | 2008-01-30 | 2012-07-17 | Lura Enterprises, Inc. | Roller screed with dual-drive power unit |
| US20130161481A1 (en) * | 2011-12-22 | 2013-06-27 | Theodore L. Kegeris | Flexible composite structure for magnetic coupling |
| US8959862B1 (en) * | 2011-01-18 | 2015-02-24 | Kenneth Robert Kreizinger | Thixotropic concrete forming system |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2940152A (en) * | 1956-03-14 | 1960-06-14 | Superior Concrete Accessories | Concrete form and chamfer corner strip therefor |
| US6502359B1 (en) * | 2000-02-22 | 2003-01-07 | Bometals, Inc. | Dowel placement apparatus for concrete slabs |
| US20070134063A1 (en) * | 2005-12-14 | 2007-06-14 | Shaw And Sons, Inc. | Dowel device with closed end speed cover |
-
2014
- 2014-08-28 US US14/471,826 patent/US20160060817A1/en not_active Abandoned
-
2015
- 2015-09-21 US US14/859,773 patent/US20170081866A1/en not_active Abandoned
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3522618A (en) * | 1967-01-30 | 1970-08-04 | Hermann Stranzinger | Structural element and assembly |
| US5487249A (en) * | 1994-03-28 | 1996-01-30 | Shaw; Ronald D. | Dowel placement apparatus for monolithic concrete pour and method of use |
| US8221027B2 (en) * | 2008-01-30 | 2012-07-17 | Lura Enterprises, Inc. | Roller screed with dual-drive power unit |
| US8959862B1 (en) * | 2011-01-18 | 2015-02-24 | Kenneth Robert Kreizinger | Thixotropic concrete forming system |
| US20130161481A1 (en) * | 2011-12-22 | 2013-06-27 | Theodore L. Kegeris | Flexible composite structure for magnetic coupling |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109763642A (en) * | 2019-03-15 | 2019-05-17 | 中国五冶集团有限公司 | Construction structure and construction method of expansion joint wall of high-rise building |
| US11578491B2 (en) * | 2020-02-07 | 2023-02-14 | Shaw Craftsmen Concrete, Llc | Topping slab installation methodology |
| US12264475B2 (en) | 2020-02-07 | 2025-04-01 | Shaw Craftsmen Concrete, Llc | Topping slab installation methodology |
Also Published As
| Publication number | Publication date |
|---|---|
| US20170081866A1 (en) | 2017-03-23 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US9206597B2 (en) | Unitized post tension block system for masonry structures | |
| JP7710975B2 (en) | Deck installation structure and deck installation method | |
| US2645114A (en) | Hollow structure | |
| US1924801A (en) | Concrete building | |
| US20150078822A1 (en) | Apparatus and method for joining adjacent concrete panels | |
| RU2008149771A (en) | STRUCTURAL ELEMENTS AND WAYS OF THEIR APPLICATION | |
| US20160340898A1 (en) | Self-Aligning Interlocking Construction Blocks | |
| US3969872A (en) | Method of constructing modular buildings | |
| US20160060817A1 (en) | Method and System for Pouring Consecutive Separating Sections of Concrete Structures | |
| US1033106A (en) | Building construction. | |
| US20170145680A1 (en) | Arched building structure, modular building blocks, and method of constructing an arched building structure | |
| KR101502484B1 (en) | Bridge improved supporting force and aesthetic design and method for constructing the same | |
| US937142A (en) | Method of producing concrete structures. | |
| US2331083A (en) | Building and building construction | |
| US865336A (en) | Building structure. | |
| US2294890A (en) | Structural corrugated building unit and wall fabricated therefrom | |
| FR2880370A1 (en) | Antiseismic, anticyclonic and heat insulating wall mounting method for building, involves placing trellis, channel bar and lattice stanchion in space between two rows of panels and filling concrete in space until to height of rows | |
| US2042113A (en) | Wall and floor construction | |
| JP7342386B2 (en) | Construction method of column-beam frame, precast concrete members and column-beam frame | |
| JP6808585B2 (en) | Construction method of concrete floor slab | |
| AU2010201627A1 (en) | Construction block | |
| US1737526A (en) | Concrete building construction | |
| US2428562A (en) | Expansion joint structure | |
| US4695031A (en) | Gang form | |
| KR102516724B1 (en) | Fireproof mortar installed joint structure of wind duct slab segment and joint method of the same |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AS | Assignment |
Owner name: ROADWAY CONCRETE SPECIALTIES, LLC, FLORIDA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:ROADWAY CONCRETE HOLDINGS, LLC;REEL/FRAME:037998/0637 Effective date: 20160307 |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |