[go: up one dir, main page]

US20130105176A1 - Method of controlling pressure in a well - Google Patents

Method of controlling pressure in a well Download PDF

Info

Publication number
US20130105176A1
US20130105176A1 US13/667,554 US201213667554A US2013105176A1 US 20130105176 A1 US20130105176 A1 US 20130105176A1 US 201213667554 A US201213667554 A US 201213667554A US 2013105176 A1 US2013105176 A1 US 2013105176A1
Authority
US
United States
Prior art keywords
well
pressure
tubular element
venting means
outside
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/667,554
Inventor
John Robert Gradishar
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shell USA Inc
Original Assignee
Shell Oil Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shell Oil Co filed Critical Shell Oil Co
Priority to US13/667,554 priority Critical patent/US20130105176A1/en
Assigned to SHELL OIL COMPANY reassignment SHELL OIL COMPANY ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: GRADISHAR, JOHN ROBERT
Publication of US20130105176A1 publication Critical patent/US20130105176A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • E21B21/08Controlling or monitoring pressure or flow of drilling fluid, e.g. automatic filling of boreholes, automatic control of bottom pressure

Definitions

  • the invention relates to a system and method for controlling the pressure in a well, especially when the well is outside of normal operation, for example, during a blowout, or when regaining control of a blowout well by a cap and shutting in.
  • Drilling liners are tubulars used to extend casings with, among other purposes, the purpose of achieving an increase in the fracture gradient to allow an increase in mud weight to be used during the drilling of high pressure oil or gas wells.
  • thin wall tubular are used for drilling liners to permit a larger inside diameter and thus the use of a larger hole size during well construction.
  • the thin wall drilling liners have a lower collapse rating. Collapse loads during normal drilling operations are low and so the low collapse rating of the liner is not normally a problem.
  • the collapse load can be very high as a result of the low internal pressure due to the flowing produced fluid pressure and high pressure external to the liner as a result of thermal expansion of the fluid behind the tubular.
  • U.S. Pat. No. 6,457,528 describes a method for preventing critical annular pressure buildup in an offshore well using a burst disk assembly.
  • the burst disk ruptures at a predetermined pressure to protect the thin walled tubular during production from a well. Once the burst disk ruptures, it is open and there is no way to close it.
  • the invention provides a well venting system for controlling the external to internal pressure differential also known as the collapse load of a tubular element comprising a tubular element having an inner and outer surface forming a wall; and venting means to provide a path for fluid communication between the outside of the outer surface and the inside of the inner surface when the collapse rating of the tubular is approached.
  • the invention also provides a method to re-establish internal well integrity or the internal to external pressure differential also known as burst load of the tubular element by closing the venting system thus preventing fluid communication from the inside of the inner surface to the outside of the outer surface.
  • FIG. 1 depicts an embodiment of a system for controlling the pressure in a well.
  • the invention provides a system and method for controlling the pressure in a tubular element, typically a casing or liner, to prevent it from collapsing during a blowout. If a blowout occurs in a well, then the collapse load increases greatly and can damage the liner as described below. This could result in the inability to control the flow of hydrocarbons through the well and subsequent release to the environment. This can also make it difficult or impossible to cap and shut-in a well.
  • the buildup of pressure during a blowout is similar to the problems of annular pressure buildup that are described in U.S. Pat. No. 6,457,528.
  • a drill is used to bore through subterranean formations.
  • a drilling fluid known as a “mud” is pumped into the borehole and circulated through the hole and back to the surface.
  • the mud is used to help lubricate and cool the drill bit, to remove cuttings and to provide sufficient hydrostatic pressure to prevent a blowout.
  • a blowout can occur when the pressure in the formation exceeds the hydrostatic pressure of the mud because higher pressure gas and oil overcome the hydrostatic pressure of the mud and flow upward, typically exiting the well.
  • U.S. Pat. No. 6,457,528 teaches the use of rupture disks that protect the tubular element, but at the loss of containment. Once the tubular disk ruptures, it cannot be replaced.
  • burst integrity of the tubular elements may be compromised if the collapse rating of the element is exceeded during the period of the unrestricted flow also known as a blowout prior to capping the well.
  • FIG. 1 depicts a well drilled into a formation 10 that contains oil and gas. After a section of the well is drilled, a casing 12 is put into place and cemented with cement 14 . A liner 18 hangs from liner hanger 16 and extends downward into the well. A portion of the liner is cemented with cement 20 . Venting means 22 is located on the wall of the liner 18 and provides the ability to allow fluid communication between the inside of the liner 30 to the annulus 32 .
  • the venting means 22 is activated or opened to allow fluid communication between the inside of the liner 30 and the annulus 32 , thus equalizing the pressure of the annulus with the pressure in the well and the collapse load is reduced.
  • the venting means may comprise any suitable venting means known to one of ordinary skill in the art, for example, valves, closeable vents, and any opening that can be opened and closed.
  • the well To stop the blowout, the well must be first capped and shut-in so that control can be regained.
  • the pressure in the well increases and the venting means closes.
  • the liner has a sufficient burst rating to withstand the hydrocarbon pressure in the well and flow is stopped.
  • venting means This prevents the release of any hydrocarbon to the environment as all of the hydrocarbon is contained within the well or the reservoir. It is preferred for the venting means to be able to remain closed during normal well construction operations, open when collapse loads pressures are high and then close as needed so that the tubular element can withstand the burst load pressure, and the well can maintain integrity.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

A well venting system for controlling the pressure in a tubular element comprising a tubular element having an inner and outer surface forming a wall; and venting means to provide fluid communication between the inside of the inner surface and the outside of the outer surface.

Description

  • The present application claims the benefit of U.S. Patent Application No. 61/554,648, filed Nov. 2, 2011, the entire disclosure of which is hereby incorporated by reference.
  • FIELD OF THE INVENTION
  • The invention relates to a system and method for controlling the pressure in a well, especially when the well is outside of normal operation, for example, during a blowout, or when regaining control of a blowout well by a cap and shutting in.
  • BACKGROUND
  • Drilling liners are tubulars used to extend casings with, among other purposes, the purpose of achieving an increase in the fracture gradient to allow an increase in mud weight to be used during the drilling of high pressure oil or gas wells. Sometimes thin wall tubular are used for drilling liners to permit a larger inside diameter and thus the use of a larger hole size during well construction. However the thin wall drilling liners have a lower collapse rating. Collapse loads during normal drilling operations are low and so the low collapse rating of the liner is not normally a problem. However when a well blows out the collapse load can be very high as a result of the low internal pressure due to the flowing produced fluid pressure and high pressure external to the liner as a result of thermal expansion of the fluid behind the tubular.
  • U.S. Pat. No. 6,457,528 describes a method for preventing critical annular pressure buildup in an offshore well using a burst disk assembly. The burst disk ruptures at a predetermined pressure to protect the thin walled tubular during production from a well. Once the burst disk ruptures, it is open and there is no way to close it.
  • SUMMARY OF THE INVENTION
  • The invention provides a well venting system for controlling the external to internal pressure differential also known as the collapse load of a tubular element comprising a tubular element having an inner and outer surface forming a wall; and venting means to provide a path for fluid communication between the outside of the outer surface and the inside of the inner surface when the collapse rating of the tubular is approached.
  • The invention also provides a method to re-establish internal well integrity or the internal to external pressure differential also known as burst load of the tubular element by closing the venting system thus preventing fluid communication from the inside of the inner surface to the outside of the outer surface.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • FIG. 1 depicts an embodiment of a system for controlling the pressure in a well.
  • DETAILED DESCRIPTION
  • The invention provides a system and method for controlling the pressure in a tubular element, typically a casing or liner, to prevent it from collapsing during a blowout. If a blowout occurs in a well, then the collapse load increases greatly and can damage the liner as described below. This could result in the inability to control the flow of hydrocarbons through the well and subsequent release to the environment. This can also make it difficult or impossible to cap and shut-in a well.
  • The buildup of pressure during a blowout is similar to the problems of annular pressure buildup that are described in U.S. Pat. No. 6,457,528. During the drilling of hydrocarbon production wells, a drill is used to bore through subterranean formations. As the drill bores into the formation, a drilling fluid known as a “mud” is pumped into the borehole and circulated through the hole and back to the surface. The mud is used to help lubricate and cool the drill bit, to remove cuttings and to provide sufficient hydrostatic pressure to prevent a blowout. A blowout can occur when the pressure in the formation exceeds the hydrostatic pressure of the mud because higher pressure gas and oil overcome the hydrostatic pressure of the mud and flow upward, typically exiting the well.
  • Different mud weights are used at different depths because the pressure in the formation increases as you drill deeper. As heavier mud weights are used, these tend to penetrate the shallower portions of the subterranean formation, so casing strings, and sometimes liners, are run into the borehole to provide a boundary between the borehole and the formation. In addition, the casing string is typically cemented into place by placing cement between the walls of the borehole and the casing string. As the well is drilled, different casing strings are used as a barrier between the formation and the well. These regions at the intersection of different casing strings have a region of casing that is typically exposed directly to the formation. Annular pressure buildup typically occurs as the result of producing hydrocarbons from the well, which heats the mud or fluid contained in the annular region. If the pressure exceeds the collapse load of the casing string or liner then the well integrity may be compromised thus putting the well at risk of being breached. U.S. Pat. No. 6,457,528 teaches the use of rupture disks that protect the tubular element, but at the loss of containment. Once the tubular disk ruptures, it cannot be replaced.
  • During a blowout, it is critical to protect burst integrity of the tubular elements that keep the hydrocarbon in the well which preserves the ability to cap and shut in the well. The burst integrity of the tubular elements may be compromised if the collapse rating of the element is exceeded during the period of the unrestricted flow also known as a blowout prior to capping the well.
  • The invention will be further described in relation to FIG. 1. FIG. 1 depicts a well drilled into a formation 10 that contains oil and gas. After a section of the well is drilled, a casing 12 is put into place and cemented with cement 14. A liner 18 hangs from liner hanger 16 and extends downward into the well. A portion of the liner is cemented with cement 20. Venting means 22 is located on the wall of the liner 18 and provides the ability to allow fluid communication between the inside of the liner 30 to the annulus 32.
  • During a blowout, hydrocarbons flow up the well uncontrollably to the surface or mud line. The resulting increase in well temperature causes the mud behind the liner to expand. The mud expansion causes the annulus pressure to increase towards the collapse rating of the liner.
  • The venting means 22 is activated or opened to allow fluid communication between the inside of the liner 30 and the annulus 32, thus equalizing the pressure of the annulus with the pressure in the well and the collapse load is reduced. The venting means may comprise any suitable venting means known to one of ordinary skill in the art, for example, valves, closeable vents, and any opening that can be opened and closed.
  • To stop the blowout, the well must be first capped and shut-in so that control can be regained. When the well is shut-in, the pressure in the well increases and the venting means closes. The liner has a sufficient burst rating to withstand the hydrocarbon pressure in the well and flow is stopped.
  • This prevents the release of any hydrocarbon to the environment as all of the hydrocarbon is contained within the well or the reservoir. It is preferred for the venting means to be able to remain closed during normal well construction operations, open when collapse loads pressures are high and then close as needed so that the tubular element can withstand the burst load pressure, and the well can maintain integrity.

Claims (8)

What is claimed is:
1. A well venting system for controlling the pressure in a tubular element comprising a tubular element having an inner and outer surface forming a wall; and venting means to provide fluid communication between the inside of the inner surface and the outside of the outer surface.
2. The system of claim 1 wherein the tubular element is a drilling liner or casing located in a well.
3. The system of claim 1 wherein the venting means may be closed to prevent fluid communication between the inside of the inner surface and the outside of the outer surface.
4. The system of claim 1 wherein the venting means may be opened to allow fluid communication between the inside of the inner surface and the outside of the outer surface when the pressure differential across the tubular element wall approaches the collapse rating of the tubular element wall.
5. A method of controlling the pressure in a tubular element comprising providing a tubular element having an inner and outer surface and venting means that can provide fluid communication from inside the inner surface to outside the outer surface; and activating the venting means to equalize the pressure inside the inner surface with the pressure outside the outer surface.
6. The method of claim 5 wherein the tubular element is a drilling liner or casing located in a well.
7. The method of claim 5 wherein the venting means is activated when the pressure differential between the outside of the outer surface and the inside of the inner surface approaches the collapse rating of the tubular element.
8. The method of claim 5 wherein the venting means is closed when the pressure differential is at a safe pressure for the tubular element.
US13/667,554 2011-11-02 2012-11-02 Method of controlling pressure in a well Abandoned US20130105176A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US13/667,554 US20130105176A1 (en) 2011-11-02 2012-11-02 Method of controlling pressure in a well

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US201161554648P 2011-11-02 2011-11-02
US13/667,554 US20130105176A1 (en) 2011-11-02 2012-11-02 Method of controlling pressure in a well

Publications (1)

Publication Number Publication Date
US20130105176A1 true US20130105176A1 (en) 2013-05-02

Family

ID=48171236

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/667,554 Abandoned US20130105176A1 (en) 2011-11-02 2012-11-02 Method of controlling pressure in a well

Country Status (1)

Country Link
US (1) US20130105176A1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050189107A1 (en) * 2004-02-27 2005-09-01 Mcvay Chester S. Annular pressure relief collar
US20060027377A1 (en) * 2004-08-04 2006-02-09 Schlumberger Technology Corporation Well Fluid Control
US20110168389A1 (en) * 2010-01-08 2011-07-14 Meijs Raymund J Surface Controlled Downhole Shut-In Valve
US20120325475A1 (en) * 2011-06-21 2012-12-27 Fike Corporation Cementing tool

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050189107A1 (en) * 2004-02-27 2005-09-01 Mcvay Chester S. Annular pressure relief collar
US20060027377A1 (en) * 2004-08-04 2006-02-09 Schlumberger Technology Corporation Well Fluid Control
US20110168389A1 (en) * 2010-01-08 2011-07-14 Meijs Raymund J Surface Controlled Downhole Shut-In Valve
US20120325475A1 (en) * 2011-06-21 2012-12-27 Fike Corporation Cementing tool

Similar Documents

Publication Publication Date Title
US10208564B2 (en) Tubular airlock assembly
CA2780762C (en) Setting tool for expandable liner hanger and associated methods
US11035188B2 (en) Anchor module for anchoring to a casing, a casing plug assembly and a method for setting two casing plugs in one run
US10519741B2 (en) Annular barrier and downhole system for low pressure zone
US20110155377A1 (en) Joint or coupling device incorporating a mechanically-induced weak point and method of use
US20150330186A1 (en) Closure device for a surge pressure reduction tool
NO20190237A1 (en) Ball valve with dissolvable ball
CA2840326C (en) Gas injection for managed pressure drilling
GB2495839A (en) A well tool with a sliding sleeve which opens or closes a bypass passage
Schnitzler et al. Completion Considerations for MPD Deepwater Offshore Wells
US20130105176A1 (en) Method of controlling pressure in a well
CA2847780A1 (en) Method and apparatus for installing a liner and bridge plug
EP3199747A1 (en) Annular barrier and downhole system for low pressure zone
NO20210901A1 (en) Hydraulic landing nipple
AU2005311155B2 (en) Diverter tool
Fernandes et al. Perforating Using MPD Techniques: Design and Execution
Agustinus et al. Managed pressure drilling application to deploy lower completion safely and efficiently in static-underbalanced well
NO20210929A1 (en) A well barrier and release device for use in drilling operations
CA2917844C (en) Casing joint assembly for producing an annulus gas cap
Hajiyeva et al. Managing Total Circulation Losses with Pressurized Mud Cap Drilling (PMCD) During Completion: Case History of Practical Solution
US20150041140A1 (en) Casing Joint Assembly for Producing an Annulus Gas Cap
BR112020021317B1 (en) RECOVERABLE SAFETY VALVE FOR FAIL-SAFE AND PRESSURE-INSENSITIVE PROFILING OF PIPELINE AND METHOD FOR OPERATING A RECOVERABLE SAFETY VALVE FOR FAIL-SAFE AND PRESSURE-INSENSITIVE PROFILING OF PIPELINE

Legal Events

Date Code Title Description
AS Assignment

Owner name: SHELL OIL COMPANY, TEXAS

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:GRADISHAR, JOHN ROBERT;REEL/FRAME:029588/0712

Effective date: 20121106

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION