US20130074758A1 US13/200,585 US201113200585A US2013074758A1 US 20130074758 A1 US20130074758 A1 US 20130074758A1 US 201113200585 A US201113200585 A US 201113200585A US 2013074758 A1 US2013074758 A1 US 2013074758A1
Authority
US
United States
Prior art keywords
anchoring
enclosure
anchor
scouring
wec
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/200,585
Inventor
William Blaine Powers
Wei Ming Chi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ocean Power Technologies Inc
Original Assignee
Ocean Power Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ocean Power Technologies Inc filed Critical Ocean Power Technologies Inc
Priority to US13/200,585 priority Critical patent/US20130074758A1/en
Assigned to OCEAN POWER TECHNOLOGIES, INC reassignment OCEAN POWER TECHNOLOGIES, INC ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: CHI, WEI MING, POWERS, WILLIAM BLAINE
Priority to PCT/US2012/056784 priority patent/WO2013048915A1/en
Publication of US20130074758A1 publication Critical patent/US20130074758A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B13/00Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates
    • F03B13/12Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy
    • F03B13/14Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy using wave energy
    • F03B13/16Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates characterised by using wave or tide energy using wave energy using the relative movement between a wave-operated member, i.e. a "wom" and another member, i.e. a reaction member or "rem"
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/97Mounting on supporting structures or systems on a submerged structure
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2270/00Control
    • F05B2270/10Purpose of the control system
    • F05B2270/18Purpose of the control system to control buoyancy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/30Energy from the sea, e.g. using wave energy or salinity gradient

Definitions

  • This invention relates to anchoring apparatus and, in particular, to anchoring apparatus suitable for mooring wave energy converter devices (WECs) and holding them in place at offshore sites.
  • WECs wave energy converter devices
  • anchors for mooring devices in the ocean are known, and each of these anchors has its own set of design features aimed at particular end use requirements.
  • WEC wave energy converter
  • anchors must be: (a) very large with high holding power, (b) cost effective both in their manufacture and also their deployment, (c) have low environmental impact, (d) able to function in a variety of sea-bed soil conditions, (e) provide anchoring to multiple wave energy converters in a matrix arrangement, and (f) able to be raised from the sea-bed to the water surface in a controlled and inexpensive manner for maintenance, relocation, and or final project site remediation if necessary.
  • an anchor to perform the desired holding function to hold a WEC(s) in place may, for example, have to weigh in the neighborhood of 300 to 500 tons, or more, and be 5-15 meters in diameter and 5-15 meters in height.
  • the deployment of such structures requires very large barges, cranes and ships to transport the structures out to a deep sea site.
  • An anchor which can achieve the holding power requirement, provide anchoring to multiple WECS, and significantly reduce the size and cost of the installation equipment.
  • an anchor embodying the invention includes an anchoring enclosure, having at least one chamber, whose buoyancy can be controlled by pumping a gas (e.g., air) or a liquid (e.g., sea water) into the chamber.
  • a gas e.g., air
  • a liquid e.g., sea water
  • the anchoring enclosure is made less buoyant.
  • the anchoring enclosure can then be rendered less buoyant so as to sink, or be lowered in a controlled manner, to the bottom of the body of water.
  • the anchoring enclosure includes a bottom extension extending around the underside of the anchoring enclosure for embedding the anchoring enclosure into the bottom of the body of water.
  • the anchoring enclosure also includes an anti-scouring skirt extending about the perimeter of the lower portion of the structure and extending about the anchoring enclosure for resting along the bottom of the body of water and preventing water movement from disturbing the embedded bottom extension.
  • the anchoring enclosure also includes mooring attachment points for enabling the connection of the anchoring enclosure to one, or more, wave energy converters (WECs) generally disposed along the surface of the body of water.
  • WECs wave energy converters
  • Embodiments of the invention may include more than one chamber to provide greater control for the lowering and raising of the anchoring enclosure.
  • Each chamber includes piping and/or tubing means for pumping a gas or a liquid into, or out of, each chamber.
  • the anchoring enclosure when submerged is of sufficient mass to enable multiple WECs to be connected to the enclosure and maintain the WECs in position.
  • Anchors embodying the invention provide a solution to the cost problem of deployment of anchors while providing a mooring structure which can prevent the drifting of devices such as WECs.
  • FIG. 1 is a simplified cross-sectional diagram of an anchor embodying the invention riding along the surface of a body of water;
  • FIG. 2 is a simplified cross-sectional diagram of the anchor of FIG. 1 , lying along the sea bed;
  • FIGS. 3A and 3B are isometric drawings of anchors embodying the invention.
  • FIGS. 4A and 4B are top views of anchors embodying the invention.
  • FIG. 5 is an idealized drawing of vessels for towing an anchor out to a deep water site and providing the means for lowering or raising an anchor embodying the invention to, or from, the ocean floor;
  • FIG. 6 is an idealized diagram illustrating the connection of a WEC to a mooring buoy connected to an anchor, in accordance with the invention.
  • the cross section of an anchor 10 embodying the invention is shown in FIGS. 1 and 2 .
  • the anchor may have any suitable shape as shown, for example, in FIGS. 3A , 3 B, 4 A and 4 B. That is, the anchor 10 may be square shaped, rectangular, cylindrical, domed or be an “n” faceted polygon or any like structure, as shown in the figures.
  • the anchor may be formed of any suitable material (e.g., concrete, steel). The choice of concrete may be dictated by the economics (concrete is generally very cheap and is also well suited from environmental conditions and other factors). The dimensions and weight of the anchors may vary over a wide range depending on the size of the WEC(s) to be held in place and the forces which need to be counteracted.
  • the length “L” and width “W” may range from less than 1 meter to more than 10 meters and the height “H” may also range from less than 1 meter to more than 10 meters.
  • the diameter “D” may range from less than 1 meter to more than 10 meters and the height “H” may also range from less than 1 meter to more than 10 meters.
  • the weight of the anchor may vary over a wide range from, for example, less than 1000 tons to more than 500,000 tons.
  • the anchor 10 is shown to have a basic box-like or cylindrical frame 110 with outer vertical wall sections 112 and 114 and an outer upper horizontal section 116 and an outer lower horizontal section 118 .
  • Horizontal section 116 is the top most section and horizontal section 118 is the bottom most section.
  • three (3) tanks/chambers (T 1 , T 2 , T 3 ) are formed within the box/block separated by wall 120 and 122 .
  • the chambers may be filled with a fluid (e.g., a gas such as air or a liquid such as water) to vary the weight (and buoyancy) of the anchor.
  • each tank may be controlled or determined by means of pipes which extend from a point external to the tank to a point within the tank.
  • tank T 1 has a pipe P 1 a and a pipe P 1 b
  • tank T 2 has a pipe P 2 a and a pipe P 2 b
  • Tank T 3 has a pipe P 3 a and a pipe P 3 b .
  • the Pipes P 1 a , P 2 a , and P 3 a may be coupled via tubing (see FIG. 5 ) to a source of liquid (which could be sea-water or any other suitable liquid) to selectively fill the tanks with the liquid (e.g., water).
  • a source of liquid which could be sea-water or any other suitable liquid
  • the pipes P 1 b , P 2 b , and P 3 b may be coupled via tubing (see FIG. 5 ) to a source of fluid (which could be air or any suitable gas) to selectively push the water out of the tanks and fill them with the fluid to render the structure more buoyant.
  • a source of fluid which could be air or any suitable gas
  • the pipes shown and/or any a number of different or additional pipes may extend from a surface of the anchor and be available to access one or more chambers formed within the anchor.
  • Anchors 10 include an extension 130 a , 130 b , extending from vertical sections 112 and 114 (outer wall of anchor 10 ).
  • the extension 130 a , 130 b is intended to dig into the sea bed and provide additional grabbing into the sea bed.
  • pipes P 10 and P 11 extend from above the anchor to a point below the lowest horizontal member 118 .
  • Pipes P 10 and P 11 may also be coupled via tubing (see FIG. 5 ) to a source of air or water which can be blown underneath horizontal member 118 of the anchor 10 to aid the anchor to rise above the sea bed (when so desired).
  • Anchor 10 includes an “anti-scouring” skirt 132 a , 132 b which functions to ensure that the anchor 10 remains in place by preventing the seabed material/sediment from being pulled or washed away from extension 130 a , 130 b and the base region of the anchor.
  • the anti-scouring skirt prevents scouring by hugging and overlying the sea bed area extending around 130 a , 130 b and preventing the soil/sediment at the anchor's base from being washed away.
  • the anti-scouring skirt is an important feature of anchor's embodying the invention. Water motion about the base of an anchor resting on the ocean floor may eat away at the soil/sand surrounding the anchor base. If sufficient soil/sand is removed, the anchor may topple over. To overcome this problem, anchors embodying the invention include an anti-scouring skirt which extends from the base of the anchor and rests on the ocean floor to prevent soil/sand from being removed or lost from around the base of the anchor. As shown in FIGS. 1 , 3 A, 3 B, 4 A and 4 B, the anti-scouring skirt may take several different forms and be of several different materials. For example, a layer of concrete or cement surrounding the anchor base and extending outwardly from there may be used to protect the sea bed sediment structure around the anchor base and prevent scouring.
  • the size and dimensions and shape of the anti-scouring skirt 132 depends on the amount of water motion and the type of sediment at the anchor site.
  • the anchor base will face varying amounts of scouring action. As a general rule, the greater the propensity to scour out, the more the need for protection and a larger area is preferred.
  • the scouring skirt is indicated to be 5 meters greater than the length “L” of the anchor. However, this is by way of illustration only and the scouring skirt may be less than 5 meters and significantly greater than that value.
  • the anti-scouring skirt may be formed of steel or concrete or any other suitable material. It may be formed as part of the anchor when the anchor is originally constructed. Alternatively, the anti-scouring skirt may be formed as sub assemblies added on to the anchor after fabrication of the anchor.
  • the anti-scouring skirt may be:
  • Two mooring line attachment points 140 are shown extending from the outer walls of the anchor. It should be appreciated that many more mooring posts can be formed and attached to the outer walls of the anchor 10 .
  • an anchor 10 In practice, to tow an anchor 10 to a site, it would be made sufficiently buoyant by pumping a required amount of gas in the chambers to allow the unit to float. The assembled anchor 10 would be sufficiently buoyant to float on the surface of the water. It would then be towed out to a site and subsequently lowered to the sea bed (ocean floor). The towing operation and the lowering of the anchor to the sea bed would be as accomplished follows.
  • the “buoyant” anchor can be towed out via a relatively small vessel (e.g., 89 or 90 in FIG. 5 , or an auxiliary vessel) and positioned at a site to be lowered into the water.
  • tubes may be connected between each one of the pipes and a corresponding source of fluid (e.g., 92 , 94 ) mounted on a vessel 90 .
  • the sources of fluid e.g., 92 , 94
  • the sources of fluid can pump air or water into or out or the anchor chambers.
  • the amount and type of fluid blown into or out of the tanks/chambers of the anchor determine its buoyancy.
  • To float the anchor some, or all, of its chambers would be filled with a gas (e.g., air).
  • a gas e.g., air
  • one of the chambers e.g., T 2
  • the rate of descent may be controlled by the use of a crane 87 on a vessel 89 . Since the anchor is initially buoyant, the crane and the vessel may be relatively “small”. The buoyancy characteristic of the anchor during the lowering process is controlled by adjusting the amount of liquid pumped into chamber T 2 , or any of the other chambers. The controlled lowering of the anchor is desirable to prevent any breakage and to control the positioning of the anchor.
  • the other chambers e.g., T 1 , T 3
  • the tubing may be disconnected from the anchor and retracted to the surface attending vessel.
  • the tubing(s) may be left attached at their bottom ends to the anchor 10 with their top ends left floating along the water surface to have the tubing available if, and when, there is a need to raise or move the anchor for additional positioning.
  • the tubing(s) may be left attached at their bottom ends to the anchor 10 , and the surface ends can be lowered into containment bins located on top of the anchor.
  • anti-scouring skirt ( 132 a , 132 b ) lies along the surface of the sea bed preventing soil erosion about the base of the anchor and its extension 130 a , 130 b.
  • FIGS. 1 , 2 and 5 note that tubing is shown attached between the anchor 10 and sources of fluid, such as air compressor 92 and water pump 94 mounted on vessel 90 . Air can be blown through pipes P 10 , P 11 to provide break suction and lift to the anchor by pushing up on horizontal member 118 . Then, air can be pushed into selected ones (or all) of the chambers T 1 , T 2 and/or T 3 causing water to be evacuated from the chambers and for the anchor to start rising. The amount of air pushed in can be controlled to assure a smooth and continuous ascent.
  • sources of fluid such as air compressor 92 and water pump 94 mounted on vessel 90 . Air can be blown through pipes P 10 , P 11 to provide break suction and lift to the anchor by pushing up on horizontal member 118 . Then, air can be pushed into selected ones (or all) of the chambers T 1 , T 2 and/or T 3 causing water to be evacuated from the chambers and for the anchor to start rising. The amount of air pushed
  • FIG. 6 there is shown a WEC 20 which includes a spar 22 and a float 24 .
  • the submerged end of the spar is connected to heave plate 26 which adds mass to the spar and keeps it generally in place and stabilized.
  • the float and spar move relative to each other and their relative motion is converted into electrical energy via power take off device (not shown).
  • An anchor 10 is connected via a line 52 to a mooring buoy 54 which is connected via line 56 and bridles 58 , 60 to the spar 22 of a WEC 20 .
  • the mooring buoy 54 provides damping action for the forces tending to push the WEC away from the anchor.
  • An anchor embodying the invention may be used to hold more than one WEC in place.
  • a multiplicity of WECs may be interconnected via mooring buoys to their respective anchors.
  • a multiplicity (farm) of WECs can be interconnected and share anchors to minimize the number of anchors needed to hold the multiplicity of WECs in place.
  • the anchors of the invention are highly suited to enable a multiplicity of WECs to be held in place.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)

Abstract

An anchoring enclosure embodying the invention includes a chamber whose buoyancy can be controlled by pumping a gas (e.g., air) or a liquid (e.g., sea water) into the chamber. The anchoring enclosure includes a bottom extension for embedding the anchoring enclosure into the seabed and an anti-scouring skirt extending about the perimeter of the lower portion of the structure and outward from the anchoring enclosure for resting along the seabed and preventing water movement from disturbing the embedded bottom extension. The anchoring enclosure may be rendered sufficiently buoyant to be easily towed to a selected site of a body of water without the need for large and expensive equipment and to then be rendered less buoyant so as to sink, in a controlled manner, to the seabed.

Description

    BACKGROUND OF THE INVENTION
  • This invention relates to anchoring apparatus and, in particular, to anchoring apparatus suitable for mooring wave energy converter devices (WECs) and holding them in place at offshore sites.
  • A variety of anchors for mooring devices in the ocean are known, and each of these anchors has its own set of design features aimed at particular end use requirements. However, there are significant problems in meeting the anchoring needs for large wave energy converter (WEC) structures in the ocean. To meet some key requirements of the wave energy converter business, anchors must be: (a) very large with high holding power, (b) cost effective both in their manufacture and also their deployment, (c) have low environmental impact, (d) able to function in a variety of sea-bed soil conditions, (e) provide anchoring to multiple wave energy converters in a matrix arrangement, and (f) able to be raised from the sea-bed to the water surface in a controlled and inexpensive manner for maintenance, relocation, and or final project site remediation if necessary.
  • The problem may be better appreciated when it is noted that an anchor to perform the desired holding function to hold a WEC(s) in place may, for example, have to weigh in the neighborhood of 300 to 500 tons, or more, and be 5-15 meters in diameter and 5-15 meters in height. The deployment of such structures requires very large barges, cranes and ships to transport the structures out to a deep sea site.
  • The costs of the anchoring system alone can become a sizable portion of the cost of the total WEC system. Building and deploying such structures to hold a WEC(s) in place can present significant economic challenges.
  • Offshore vessels and equipment used to install large anchoring systems need to be very large and are very expensive. An anchor is needed which can achieve the holding power requirement, provide anchoring to multiple WECS, and significantly reduce the size and cost of the installation equipment.
  • Employing larger and larger equipment for the deployment of such anchors results in reduced number of available days to work offshore to complete equipment installation due to the tight window of workable marine conditions for such lifts. Project delays based on unsuitable marine conditions can cost projects large amounts of money.
  • Given the significant cost associated with the building and deployment of the anchors for the WECs, it is also important, where numerous WECs are to be deployed in a given area, to minimize the number of anchors per WEC by having WECs share anchors.
  • SUMMARY OF THE INVENTION
  • In accordance with the invention, an anchor embodying the invention includes an anchoring enclosure, having at least one chamber, whose buoyancy can be controlled by pumping a gas (e.g., air) or a liquid (e.g., sea water) into the chamber. When a gas (e.g., air) is pumped (or blown) into the chamber the anchoring enclosure is made more buoyant. When a liquid (e.g., sea water) is pumped into the chamber the anchoring enclosure is made less buoyant. By controlling the amount of gas or liquid pumped into the chamber of the anchoring enclosure it may be rendered sufficiently buoyant to be easily towed to a selected site of a body of water and to be deployed at the selected site without the need for large and expensive offshore equipment. The anchoring enclosure can then be rendered less buoyant so as to sink, or be lowered in a controlled manner, to the bottom of the body of water. The anchoring enclosure includes a bottom extension extending around the underside of the anchoring enclosure for embedding the anchoring enclosure into the bottom of the body of water. The anchoring enclosure also includes an anti-scouring skirt extending about the perimeter of the lower portion of the structure and extending about the anchoring enclosure for resting along the bottom of the body of water and preventing water movement from disturbing the embedded bottom extension. The anchoring enclosure also includes mooring attachment points for enabling the connection of the anchoring enclosure to one, or more, wave energy converters (WECs) generally disposed along the surface of the body of water.
  • Embodiments of the invention may include more than one chamber to provide greater control for the lowering and raising of the anchoring enclosure. Each chamber includes piping and/or tubing means for pumping a gas or a liquid into, or out of, each chamber.
  • The anchoring enclosure when submerged is of sufficient mass to enable multiple WECs to be connected to the enclosure and maintain the WECs in position.
  • Anchors embodying the invention provide a solution to the cost problem of deployment of anchors while providing a mooring structure which can prevent the drifting of devices such as WECs.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • In the accompanying, which are not necessarily drawn to scale, like reference characters denote like components; and
  • FIG. 1 is a simplified cross-sectional diagram of an anchor embodying the invention riding along the surface of a body of water;
  • FIG. 2 is a simplified cross-sectional diagram of the anchor of FIG. 1, lying along the sea bed;
  • FIGS. 3A and 3B are isometric drawings of anchors embodying the invention;
  • FIGS. 4A and 4B are top views of anchors embodying the invention;
  • FIG. 5 is an idealized drawing of vessels for towing an anchor out to a deep water site and providing the means for lowering or raising an anchor embodying the invention to, or from, the ocean floor; and
  • FIG. 6 is an idealized diagram illustrating the connection of a WEC to a mooring buoy connected to an anchor, in accordance with the invention.
  • DETAILED DESCRIPTION OF THE DRAWINGS
  • The cross section of an anchor 10 embodying the invention is shown in FIGS. 1 and 2. The anchor may have any suitable shape as shown, for example, in FIGS. 3A, 3B, 4A and 4B. That is, the anchor 10 may be square shaped, rectangular, cylindrical, domed or be an “n” faceted polygon or any like structure, as shown in the figures. The anchor may be formed of any suitable material (e.g., concrete, steel). The choice of concrete may be dictated by the economics (concrete is generally very cheap and is also well suited from environmental conditions and other factors). The dimensions and weight of the anchors may vary over a wide range depending on the size of the WEC(s) to be held in place and the forces which need to be counteracted. By way of example, referring to FIGS. 3A and 4A the length “L” and width “W” may range from less than 1 meter to more than 10 meters and the height “H” may also range from less than 1 meter to more than 10 meters. In a similar manner referring to FIGS. 3B and 4B, the diameter “D” may range from less than 1 meter to more than 10 meters and the height “H” may also range from less than 1 meter to more than 10 meters. And, as already noted, the weight of the anchor may vary over a wide range from, for example, less than 1000 tons to more than 500,000 tons.
  • In FIG. 1, the anchor 10 is shown to have a basic box-like or cylindrical frame 110 with outer vertical wall sections 112 and 114 and an outer upper horizontal section 116 and an outer lower horizontal section 118. Horizontal section 116 is the top most section and horizontal section 118 is the bottom most section. In FIGS. 1 and 2, three (3) tanks/chambers (T1, T2, T3) are formed within the box/block separated by wall 120 and 122. In practice, more, or less, chambers/tanks can be formed. The chambers may be filled with a fluid (e.g., a gas such as air or a liquid such as water) to vary the weight (and buoyancy) of the anchor. The contents of each tank may be controlled or determined by means of pipes which extend from a point external to the tank to a point within the tank. Thus, it is shown that tank T1 has a pipe P1 a and a pipe P1 b, tank T2 has a pipe P2 a and a pipe P2 b and Tank T3 has a pipe P3 a and a pipe P3 b. The Pipes P1 a, P2 a, and P3 a may be coupled via tubing (see FIG. 5) to a source of liquid (which could be sea-water or any other suitable liquid) to selectively fill the tanks with the liquid (e.g., water). Likewise, the pipes P1 b, P2 b, and P3 b may be coupled via tubing (see FIG. 5) to a source of fluid (which could be air or any suitable gas) to selectively push the water out of the tanks and fill them with the fluid to render the structure more buoyant. As illustrated in the figures, the pipes shown and/or any a number of different or additional pipes (Pia, Pib) may extend from a surface of the anchor and be available to access one or more chambers formed within the anchor.
  • Anchors 10 include an extension 130 a, 130 b, extending from vertical sections 112 and 114 (outer wall of anchor 10). The extension 130 a, 130 b, is intended to dig into the sea bed and provide additional grabbing into the sea bed. Note pipes P10 and P11 extend from above the anchor to a point below the lowest horizontal member 118. Pipes P10 and P11 may also be coupled via tubing (see FIG. 5) to a source of air or water which can be blown underneath horizontal member 118 of the anchor 10 to aid the anchor to rise above the sea bed (when so desired).
  • Anchor 10, as shown in the figures, includes an “anti-scouring” skirt 132 a, 132 b which functions to ensure that the anchor 10 remains in place by preventing the seabed material/sediment from being pulled or washed away from extension 130 a, 130 b and the base region of the anchor. The anti-scouring skirt prevents scouring by hugging and overlying the sea bed area extending around 130 a, 130 b and preventing the soil/sediment at the anchor's base from being washed away.
  • The anti-scouring skirt is an important feature of anchor's embodying the invention. Water motion about the base of an anchor resting on the ocean floor may eat away at the soil/sand surrounding the anchor base. If sufficient soil/sand is removed, the anchor may topple over. To overcome this problem, anchors embodying the invention include an anti-scouring skirt which extends from the base of the anchor and rests on the ocean floor to prevent soil/sand from being removed or lost from around the base of the anchor. As shown in FIGS. 1, 3A, 3B, 4A and 4B, the anti-scouring skirt may take several different forms and be of several different materials. For example, a layer of concrete or cement surrounding the anchor base and extending outwardly from there may be used to protect the sea bed sediment structure around the anchor base and prevent scouring.
  • The size and dimensions and shape of the anti-scouring skirt 132 (a, b) depends on the amount of water motion and the type of sediment at the anchor site. The anchor base will face varying amounts of scouring action. As a general rule, the greater the propensity to scour out, the more the need for protection and a larger area is preferred. In FIG. 3A, the scouring skirt is indicated to be 5 meters greater than the length “L” of the anchor. However, this is by way of illustration only and the scouring skirt may be less than 5 meters and significantly greater than that value.
  • The anti-scouring skirt may be formed of steel or concrete or any other suitable material. It may be formed as part of the anchor when the anchor is originally constructed. Alternatively, the anti-scouring skirt may be formed as sub assemblies added on to the anchor after fabrication of the anchor.
  • The anti-scouring skirt may be:
      • i. Pre-fabricated mats consisting of reinforced loosely woven heavy duty fabric with concrete blocks pre-attached that can be cut away or rolled up or pulled out from the anchor; or
      • ii. Articulated concrete slabs held together with ropes or wire that can be cut away or rolled or pulled out away from the anchor; or
      • iii. A concrete form(s) that can unfold from the anchor sides and fold down like ramps extending from the sides of the anchor's outer walls.
  • Two mooring line attachment points 140 are shown extending from the outer walls of the anchor. It should be appreciated that many more mooring posts can be formed and attached to the outer walls of the anchor 10.
  • In practice, to tow an anchor 10 to a site, it would be made sufficiently buoyant by pumping a required amount of gas in the chambers to allow the unit to float. The assembled anchor 10 would be sufficiently buoyant to float on the surface of the water. It would then be towed out to a site and subsequently lowered to the sea bed (ocean floor). The towing operation and the lowering of the anchor to the sea bed would be as accomplished follows. The “buoyant” anchor can be towed out via a relatively small vessel (e.g., 89 or 90 in FIG. 5, or an auxiliary vessel) and positioned at a site to be lowered into the water.
  • As shown in FIG. 5, tubes may be connected between each one of the pipes and a corresponding source of fluid (e.g., 92, 94) mounted on a vessel 90. The sources of fluid (e.g., 92, 94) can pump air or water into or out or the anchor chambers. The amount and type of fluid blown into or out of the tanks/chambers of the anchor determine its buoyancy. To float the anchor some, or all, of its chambers would be filled with a gas (e.g., air). To lower the anchor, one of the chambers (e.g., T2) would be filled with water to cause the anchor to reach a state so it is slightly negatively buoyant and the anchor would start sinking. The rate of descent may be controlled by the use of a crane 87 on a vessel 89. Since the anchor is initially buoyant, the crane and the vessel may be relatively “small”. The buoyancy characteristic of the anchor during the lowering process is controlled by adjusting the amount of liquid pumped into chamber T2, or any of the other chambers. The controlled lowering of the anchor is desirable to prevent any breakage and to control the positioning of the anchor. Once the anchor is lowered to the seabed and placed in its desired location, the other chambers (e.g., T1, T3) are filled with water and this extra mass increases the anchor holding power to its specified value. Once the anchor is along the sea bed bottom the tubing may be disconnected from the anchor and retracted to the surface attending vessel.
  • Alternatively, the tubing(s) may be left attached at their bottom ends to the anchor 10 with their top ends left floating along the water surface to have the tubing available if, and when, there is a need to raise or move the anchor for additional positioning. Also the tubing(s) may be left attached at their bottom ends to the anchor 10, and the surface ends can be lowered into containment bins located on top of the anchor.
  • The final positioning of an anchor on the sea bed is shown in FIGS. 2, 5 and 6. Note that anti-scouring skirt (132 a, 132 b) lies along the surface of the sea bed preventing soil erosion about the base of the anchor and its extension 130 a, 130 b.
  • There are many occasions where it is desirable to raise the anchor. For example it may need maintenance, it may be desirable to move it to another location or upon a project completion and the anchor may need to be removed for site remediation. Referring to FIGS. 1, 2 and 5, note that tubing is shown attached between the anchor 10 and sources of fluid, such as air compressor 92 and water pump 94 mounted on vessel 90. Air can be blown through pipes P10, P11 to provide break suction and lift to the anchor by pushing up on horizontal member 118. Then, air can be pushed into selected ones (or all) of the chambers T1, T2 and/or T3 causing water to be evacuated from the chambers and for the anchor to start rising. The amount of air pushed in can be controlled to assure a smooth and continuous ascent.
  • Another significant aspect of the invention pertains to the use of the anchors to hold wave energy converters (WECs) in place. Referring to FIG. 6, there is shown a WEC 20 which includes a spar 22 and a float 24. The submerged end of the spar is connected to heave plate 26 which adds mass to the spar and keeps it generally in place and stabilized. The float and spar move relative to each other and their relative motion is converted into electrical energy via power take off device (not shown). An anchor 10 is connected via a line 52 to a mooring buoy 54 which is connected via line 56 and bridles 58, 60 to the spar 22 of a WEC 20. The mooring buoy 54 provides damping action for the forces tending to push the WEC away from the anchor.
  • An anchor embodying the invention may be used to hold more than one WEC in place. A multiplicity of WECs may be interconnected via mooring buoys to their respective anchors. In addition, a multiplicity (farm) of WECs can be interconnected and share anchors to minimize the number of anchors needed to hold the multiplicity of WECs in place. The anchors of the invention are highly suited to enable a multiplicity of WECs to be held in place.

Claims (15)

What is claimed is:
1. An anchoring system comprising:
an anchoring enclosure, having at least one chamber, whose buoyancy can be controlled;
piping apparatus connected to the chamber for enabling a gas or a liquid to be pumped into or out of the chamber; when a gas is pumped into the chamber the anchoring enclosure is made more buoyant, when a fluid is pumped into a chamber the anchoring enclosure is made less buoyant; said anchoring enclosure being rendered sufficiently buoyant to be towed to a selected site of a body of water and to be deployed at the selected site and said anchoring enclosure being selectively rendered less buoyant so as to sink or be lowered, in a controlled manner, to the bottom of the body of water;
said anchoring enclosure including a bottom extension extending around the underside of the anchoring enclosure for embedding the anchoring enclosure into the bottom of the body of water; and
an anti-scouring skirt extending about the perimeter of the lower portion of the anchoring enclosure and extending about the anchoring enclosure for resting along the bottom of the body of water and preventing water movement from disturbing the embedded bottom extension.
2. An anchoring system as claimed in claim 1 further including mooring attachment points formed along the anchoring enclosure for enabling the connecting of the anchoring enclosure to a wave energy converter (WEC).
3. An anchoring system as claimed in claim 2, wherein said anchoring enclosure is designed to be positioned on and to hug the ocean floor and the WEC is designed to be lie generally about the surface of the ocean to respond to the ocean waves and the anchoring enclosure prevents the WEC from drifting from a selected site.
4. An anchoring system as claimed in claim 1, wherein said anchoring enclosure includes more than one chamber.
5. An anchoring system as claimed in claim 1, wherein the anchoring enclosure has sufficient mass, when submerged, to be connected to a multiplicity of WECs and hold the WECs in their designated space.
6. An anchoring system as claimed in claim 3, wherein each WEC has at least one mooring buoy and wherein the anchoring enclosure is connected to the WEC's mooring buoy.
7. An anchoring system as claimed in claim 6, wherein the WEC is connected to its mooring buoy via a bridle line.
8. An anchoring system as claimed in claim 3, wherein the anchoring enclosure is connected to a WEC having a float and a spar which move relative to each other in response to the waves.
9. An anchoring system as claimed in claim 2, wherein said anchoring enclosure is of cylindrical shape, having a diameter D and a height H, and wherein each of D and H may range from less than 1 meter to more than 10 meters.
10. An anchoring system as claimed in claim 2, wherein said anchoring enclosure is of a generally rectangular shape, having a length “L”, a width “W” and a height “H”, and wherein each of L, W and H may range from less than 1 meter to more than 10 meters.
11. An anchoring system as claimed in claim 1 wherein said anti-scouring skirt extends from less than 1 meter to more than 5 meters from the side of the anchoring enclosure.
12. An anchoring system as claimed in claim 1 wherein said anti-scouring skirt is formed of metal, or concrete.
13. An anchoring system as claimed in claim 1 wherein said anti-scouring skirt is formed of pre-fabricated mats consisting of reinforced loosely woven heavy duty fabric with concrete blocks pre-attached to the anchor and arranged so they can be cut away or rolled up or pulled out from the anchor.
14. An anchoring system as claimed in claim 1 wherein said anti-scouring skirt is formed of articulated concrete slabs attached to the anchor, the concrete slabs being held together with ropes or wire that can be cut away or rolled or pulled out away from the anchor.
15. An anchoring system as claimed in claim 1 wherein said anti-scouring skirt is formed of a concrete form that can unfold from the anchor sides and fold down like ramps extending from the anchor's external walls.
US13/200,585 2011-09-26 2011-09-26 Anchoring apparatus for wave energy converters Abandoned US20130074758A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US13/200,585 US20130074758A1 (en) 2011-09-26 2011-09-26 Anchoring apparatus for wave energy converters
PCT/US2012/056784 WO2013048915A1 (en) 2011-09-26 2012-09-23 Anchoring apparatus for wave energy converters

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US13/200,585 US20130074758A1 (en) 2011-09-26 2011-09-26 Anchoring apparatus for wave energy converters

Publications (1)

Publication Number Publication Date
US20130074758A1 true US20130074758A1 (en) 2013-03-28

Family

ID=47909824

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/200,585 Abandoned US20130074758A1 (en) 2011-09-26 2011-09-26 Anchoring apparatus for wave energy converters

Country Status (2)

Country Link
US (1) US20130074758A1 (en)
WO (1) WO2013048915A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140265339A1 (en) * 2013-03-15 2014-09-18 James G.P. Dehlsen Wave energy converter system
US20150211551A1 (en) * 2014-01-29 2015-07-30 Curtis VanWalleghem Energy accumulation apparatus
US20200232440A1 (en) * 2016-02-18 2020-07-23 Ingine, Inc. Block type wave power generation apparatus and installation method therefor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4296706A (en) * 1978-07-13 1981-10-27 The British Petroleum Company Limited Anchor
US4761096A (en) * 1987-02-24 1988-08-02 Lin Sheng S Universal footing with jetting system
US20070214780A1 (en) * 2004-05-07 2007-09-20 Walters William D Submersible power plant
US20100117366A1 (en) * 2007-03-02 2010-05-13 Kenneth Rhinefrank Methods and apparatus for power generation
US20110215650A1 (en) * 2010-03-08 2011-09-08 Massachusetts Institute Of Technology Offshore energy harvesting, storage, and power generation system

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0420344D0 (en) 2004-09-14 2004-10-13 Amersham Plc Diagnostic compounds
US8247534B2 (en) * 2006-12-13 2012-08-21 Ge Healthcare As Synthesis of radiofluorinated peptide using microwave activation technology
WO2011044422A2 (en) * 2009-10-08 2011-04-14 Ge Healthcare Limited Solid phase extraction purification method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4296706A (en) * 1978-07-13 1981-10-27 The British Petroleum Company Limited Anchor
US4761096A (en) * 1987-02-24 1988-08-02 Lin Sheng S Universal footing with jetting system
US20070214780A1 (en) * 2004-05-07 2007-09-20 Walters William D Submersible power plant
US20100117366A1 (en) * 2007-03-02 2010-05-13 Kenneth Rhinefrank Methods and apparatus for power generation
US20110215650A1 (en) * 2010-03-08 2011-09-08 Massachusetts Institute Of Technology Offshore energy harvesting, storage, and power generation system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140265339A1 (en) * 2013-03-15 2014-09-18 James G.P. Dehlsen Wave energy converter system
US9074577B2 (en) * 2013-03-15 2015-07-07 Dehlsen Associates, Llc Wave energy converter system
US20150211551A1 (en) * 2014-01-29 2015-07-30 Curtis VanWalleghem Energy accumulation apparatus
US9416796B2 (en) * 2014-01-29 2016-08-16 Hydrostor Inc. Energy accumulation apparatus
US20200232440A1 (en) * 2016-02-18 2020-07-23 Ingine, Inc. Block type wave power generation apparatus and installation method therefor

Also Published As

Publication number Publication date
WO2013048915A1 (en) 2013-04-04

Similar Documents

Publication Publication Date Title
CN1240940C (en) Method and system for installing and transporting a landwind power plant at sea
US8037838B2 (en) Mooring system
EP3436640B1 (en) Seabed base structure and method for installation of same
CN111559469A (en) Floating structure and installation method thereof
CN110382344B (en) Autonomous floatable gravity base for connection to an offshore facility
KR20200084041A (en) Buoys and installation methods for the buoys
MXPA04008784A (en) Marine buoy for offshore support.
JP2022167735A (en) Floating island on sea
US10352010B2 (en) Self-installing offshore platform
US20130074758A1 (en) Anchoring apparatus for wave energy converters
AU2010250147B2 (en) Method for installing a topside module on an offshore support structure
JP2019534401A (en) Port plant and method for mooring a floating body in a port plant
DK2860314T3 (en) Gravity fundering
AU2021202442B2 (en) Gravity-Based Structure For Off-Shore Structures
GB2241011A (en) Offshore platform system
KR102192138B1 (en) Water level control system of floating marine structure
JP2005193730A (en) Artificial floating island
HK40011237B (en) Autonomously buoyant heavyweight foundation for connection to an offshore plant
HK40011237A (en) Autonomously buoyant heavyweight foundation for connection to an offshore plant
WO2013179003A2 (en) Apparatus and method
HK40004343B (en) Seabed base structure and method for installation of same
HK40004343A (en) Seabed base structure and method for installation of same
NO20150926A1 (en) Sub-fixed floating platform
JPS58110723A (en) Offshore building-up of caisson

Legal Events

Date Code Title Description
AS Assignment

Owner name: OCEAN POWER TECHNOLOGIES, INC, NEW JERSEY

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:CHI, WEI MING;POWERS, WILLIAM BLAINE;REEL/FRAME:027097/0271

Effective date: 20110923

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION