US20070028551A1 - Beam attachment system - Google Patents
Beam attachment system Download PDFInfo
- Publication number
- US20070028551A1 US20070028551A1 US10/562,733 US56273305A US2007028551A1 US 20070028551 A1 US20070028551 A1 US 20070028551A1 US 56273305 A US56273305 A US 56273305A US 2007028551 A1 US2007028551 A1 US 2007028551A1
- Authority
- US
- United States
- Prior art keywords
- tie
- attachment system
- posts
- post
- beams
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B2001/2466—Details of the elongated load-supporting parts
- E04B2001/2472—Elongated load-supporting part formed from a number of parallel profiles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B2001/2487—Portico type structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B2001/3583—Extraordinary methods of construction, e.g. lift-slab, jack-block using permanent tensioning means, e.g. cables or rods, to assemble or rigidify structures (not pre- or poststressing concrete), e.g. by tying them around the structure
Definitions
- the present invention relates to a beam attachment system, in particular, for long-span beams.
- Beams and, in particular, long-span beams have various uses, in particular in the field of large-span structures, for the construction of buildings and engineering structures. Examples of such structures are warehouses, hypermarkets, aircraft hangars, sports centres, buildings on piles or of great height, car parks, bridges and footbridges.
- FR 2 611 781 discloses a system ensuring the support and attachment of long-span beams.
- the attachment is carried on metal support posts, each post being provided with at least one buttress leg member articulated at its lower end on an articulation shaft integral with the corresponding post.
- the upper end of the buttress member is provided with a two-wing channel on which bears a corner strengthening member integral with the end of a long-span beam by means of contact members with which said corner strengthening member is provided. Thanks to this system, the vertical reaction to the weight of the beam is transferred into a buttress force on the shaft of the corresponding leg member. This force in turn creates a horizontal longitudinal stress force on the corresponding long-span beam, intended to support a structure.
- a subject of the invention is a beam attachment system comprising two posts, a beam and at least one beam tie, in which the posts are stressed by the beam pushing them apart and stressed by the beam tie pulling them together.
- the invention comprises one or more of the following characteristics:
- the beam is connected to the beam tie
- the beam and the beam tie are mounted sliding relative to each other according to a finite sliding portion
- the beam comprises at least two lateral parts between which a beam tie passage is formed;
- the beam is supported by the beam tie;
- the beam comprises several longitudinal segments
- each of the posts is connected to the beam by means of a connecting rod, the connecting rod being articulated on the one hand on the post that it connects to the beam and on the other hand on the beam;
- one of the posts is an edge post.
- FIG. 1 a diagrammatic illustration of the attachment system according to the invention
- FIG. 2 a front view and cross-section representing the upper part of a post connected to two beams by means of connecting rods;
- FIG. 3 a top view of the elements represented in FIG. 2 ;
- FIG. 4 a partial front view of a beam tie fixed at the head of a post and at the level of one end of a beam;
- FIG. 5 transversal cross-section of a beam, at the level of a central section of the beam
- FIG. 6 partial view and cross-section, along a longitudinal section of the beam, at the level of its central part;
- FIG. 7 a front view, representing a beam intended to be mounted in the attachment system
- the invention proposes a beam attachment system comprising two posts, a beam and at least one beam tie, in which the posts are stressed by the beam pushing them apart and stressed by the beam tie pulling them together.
- the beam tie compensates at least in part for the stress exerted by the beam on the post. This system makes it possible to lengthen the span of the beam and to retain the stability of the system.
- FIG. 1 is a diagrammatic illustration of the attachment system according to the invention.
- the figure shows an edge post 14 as well as several posts 5 a, 5 b, beams 3 a, 3 b, 3 c and beam ties 9 a, 9 b, 9 c.
- the posts 5 a, 5 b are embedded in the ground 4 (i.e. in the foundation) and form a metal frame intended for the attachment of the beams.
- the general reference number 3 designates a beam
- the number 9 designates a beam tie
- the number 5 designates a frame post other than an edge post.
- the additional reference letters a, b, c designate different sections of the frame.
- a beam is attached between two posts using support systems which are described below.
- the beam tie is an element of the system intended to resist traction.
- the beam attachment system 1 therefore comprises two posts 5 a, 5 b, a beam 3 b and at least one beam tie 9 b.
- the beam is placed under stress and the beam tie connects at least one of the posts 5 a , 5 b, so that the two posts 5 a, 5 b are stressed by the beam 3 b pushing them apart and stressed by the beam tie 9 b pulling them together.
- the stress exerted by the beam tie 9 b compensates at least partially for the moment exerted by a beam on the posts and moreover creates an increase in longitudinal stress in the beam.
- This system thus makes it possible, on the one hand, to lengthen the span of the beam and, on the other hand, to absorb part of the stress exerted on a post. It therefore also makes it possible to retain the stability of the system.
- FIG. 2 is a front view and cross-section representing the upper part of a post connected to two beams by means of connecting rods.
- the figure shows a post 5 a, two beams 3 a, 3 b, a vertical fastening 17 , two connecting rods 13 a, 13 b, two distribution plates 19 a, 19 b and two beam ties 9 a, 9 b.
- One element a of each pair of abovementioned elements a, b is situated to the left of the post 5 a, the other element being situated to the right of the post.
- the post 5 a is embedded in the ground 4 in this example and, more particularly, in the foundation. According to a variant it can be articulated on the foundation.
- the post 5 a is connected to the beams 3 a, 3 b by means of a connecting rod 13 a, 13 b articulated on the one hand on the post 5 a which it connects to a beam and on the other hand on a beam 3 a, 3 b.
- the articulation at the level of the post 5 a can be produced by means of a pivot connection 14 a, 14 b or, as a variant, by means of a shaft.
- the articulation at the level of the beam can be produced by means of a support angle 18 a, 18 b.
- a corner strengthening member can then be articulated in the support angle 18 a, 18 b so as to form a pivot connection.
- the corner strengthening member can be produced in the form of a distribution plate 19 a, 19 b.
- This plate fixed to a beam 3 a, 3 b makes it possible, on the one hand, to support this beam and, on the other hand, to distribute the reaction of the support in this beam 3 .
- Two beam ties 9 a, 9 b are fixed at the head of the post 5 a, to the left and to the right, respectively.
- only one beam tie is fixed at the head of the post 5 a.
- the same beam tie can then extend along a frame comprising several posts.
- Such a structure has the advantage of distributing the stresses, as well as the absorption of these stresses, along the frame. This results in a better cohesion of the frame.
- the beam ties are at least partially retracted into the beam, as described below.
- a fastening 17 of the two beams, at the head of the post 5 a, can moreover be ensured by two fastening elements, situated on both sides of the beams. This is better described with reference to FIG. 3 .
- FIG. 3 is a top view of the elements represented in FIG. 2 .
- Each of the beams 3 a, 3 b comprises two lateral parts, respectively referenced in FIG. 3 as 3 a G, 3 a D, 3 b G and 3 b D.
- the two lateral parts are assembled and connected by fixing elements 20 a, 20 b such as bolts.
- These fixing elements pass through a distribution plate 19 a, 19 b, as represented in FIG. 2 .
- These plates are however hidden by a beam tie 9 a, 9 b and are therefore not visible in FIG. 3 .
- the lateral parts 3 a G, 3 a D, 3 b G, 3 b D are clamped at their head by the two fastening elements 17 G, 17 D, which can thus prevent the lateral buckling of the beams.
- Other fixing elements 16 hold the fastening elements 17 clamping the head of the beams 3 a, 3 b.
- a passage 15 a, 15 b is formed between two lateral parts, allowing a beam tie 9 a, 9 b to engage therein.
- the section of the half-beams can be designed so that after the assembly of the two half-beams a passage 15 a, 15 b forms a channel allowing a beam tie 9 a, 9 b to engage therein.
- a beam tie 9 a, 9 b is thus at least partially retracted into a beam, which makes it possible to protect it, for example in case of fire.
- two beam ties 9 a, 9 b are fixed at the head of the post 5 a.
- FIG. 4 is a partial, front view of a beam tie fixed at the head of a post and at the level of one end of a beam.
- the figure shows a beam tie 9 b, the head of a post 5 a, a beam 3 b as well as a tensioning element 23 b of the beam tie 9 b.
- This element 23 b makes it possible to adjust the tension of the beam tie 9 b, for example after the mounting of the beam 3 b on the posts and of the beam tie with the beam.
- FIG. 5 is a transversal cross-section of a beam, at the level of a central section of the beam.
- This figure shows a beam 3 comprising two left and right lateral parts (or half-beams) 3 G, 3 D firmly connected by fixing elements 20 .
- the figure also shows part of a post 5 and a connecting rod 13 articulated on the post 5 via a pivot connection 14 and in contact with the beam 3 at the level of a distribution plate 19 of the beam.
- the fixing elements 20 pass through this plate 19 .
- the left 3 G and right 3 D lateral parts of the beam 3 form a passage 15 allowing a beam tie (not shown) to engage therein.
- the beam tie passage 15 means there is much less material in the beam. In addition it allows the beam tie to be engaged inside the beam in order to support it, the passage 15 releases material and therefore lightens the beam 3 . The beam 3 is thus less subject to the buckling caused by its own mass. Moreover, the retraction of the beam tie inside the passage 15 reduces the space requirement of the beam tie and makes it possible to protect the beam tie, for example, in case of fire. If needed, a fire-retardant film can be fixed in such a manner as to close the passage 15 , in order to further protect the beam tie in case of fire.
- the passage 15 is formed in such a manner that the beam tie supports the beam at the level of the beam's centre of gravity.
- a central distribution plate 41 of the beam rests on the beam tie 9 . This central plate 41 is passed through by fixing elements 40 firmly connecting the two lateral beam parts 3 G, 3 D via the central plate 41 .
- the beam tie passage 15 formed by the lateral parts 3 G, 3 D allows a relative sliding of the beam with respect to the beam tie.
- Such a characteristic allows the beam 3 to adjust naturally relative to the beam tie 9 .
- This last property of the attachment system proves to be particularly advantageous when the beam 3 is subjected to an asymmetrical load. This is for example the case when equipment such as air-conditioning or heating equipment are fixed supported on the beam at a point distant from the centre of the beam.
- the additional degree of freedom offered by the relative sliding of the beam 3 with respect to the beam tie 9 makes it possible to reduce the potential energy connected with the load stress. Such a property therefore makes it possible to further stabilize the attachment system.
- the beam 3 is supported by the beam tie 9 , the latter can also be connected to the beam tie according to various possible variants.
- the beam tie can support the beam by means of a ring or an equivalent connecting element allowing the beam 3 to slide along the beam tie.
- the beam tie is simply fixed to the beam, for example in the centre of the upper surface of the beam.
- This variant makes it possible to simplify the production of the attachment system 1 .
- an attachment system I is obtained in which the stressing of posts by a beam tie compensates at least partially for the moment exerted by the beam 3 on the posts and moreover creates an increase in longitudinal stress in the beam 3 .
- Such an attachment system benefits from great simplicity of assembly, makes it possible to lengthen the span of the beam and to absorb part of the stress force exerted on a post.
- the fact that the beam tie connects the beam 3 moreover makes it possible to stabilize the beam—posts assembly of the attachment system.
- the beam tie can be produced in two distinct beam-tie parts. One of these parts connects a post to the beam and the other one of these parts connects the beam to another post.
- An anchored-type beam tie—posts—beam structure is then obtained in which each of the two beam-tie parts compensates at least partially for the moment exerted by the beam on each of the posts.
- the additional degree of freedom offered by the relative sliding of the beam 3 with respect to the beam tie 9 made it possible to reduce the potential energy connected with the load stress and to further stabilize the attachment system.
- a sleeve 43 fixed onto the beam tie 9 limits the sliding of the beam with respect to the beam tie. This is better described with reference to FIG. 6 .
- FIG. 6 is a partial cross-section, along a longitudinal section of the beam, at the level of its central part.
- the figure shows the central part of a beam 3 comprising two lateral parts.
- the cross-section is made between these two lateral parts.
- the beam tie 9 is engaged in the beam-tie passage form by the lateral beam parts and allows a relative sliding of the beam 3 with respect to the beam tie 9 .
- the beam 3 and the beam tie 9 are mounted sliding relative to each other according to a finite sliding portion.
- the slipping portion is delimited by two sleeves 43 , 45 fixed onto the beam tie 9 .
- the two lateral beam parts are connected by a central distribution plate 41 , with several holes drilled in it allowing the fixing of the plate 41 onto the two lateral parts.
- the central distribution plate can thus slide along the beam tie 9 and between the sleeves. The difference between the finite sliding portion and the length of the distribution plate defines a sliding play, as illustrated in FIG. 6 .
- the distribution plates 19 , 41 are themselves subdivided into two plates. Each of these two plates can be pre-assembled on a lateral beam part 3 G, 3 D.
- the assembly phase of the beam 3 now requires no more than assembly directly by fixing the lateral beam parts, for example by means of bolts.
- the pre-assembly phase being a factory phase, it can be easily controlled. Any errors during the assembly of the beam are thus eliminated.
- the on-site assembly of the beam 3 is substantially simplified by this.
- the sliding play is typically comprised between 0.2/10,000 th and 5/10,000 th of the span of the beam. This play is chosen so as to be well below an instability threshold of the attachment system, i.e. a threshold beyond which the sliding of the beam 3 threatens the stability of the system.
- an instability threshold of the attachment system i.e. a threshold beyond which the sliding of the beam 3 threatens the stability of the system.
- Such a characteristic allows the beam 3 , articulated moreover on connecting rods, to be adjusted with respect to the beam tie 9 , inside a delimited sliding portion.
- the additional degree of freedom provided by the relative sliding of the beam 3 with respect to the beam tie makes it possible to reduce the potential energy connected to the load stress.
- Such a property makes it possible to stabilize the attachment system, as described above.
- the sliding takes place inside a finite sliding portion (delimited by sleeves), in order to prevent the beam from sliding beyond the instability threshold of the attachment system.
- FIG. 7 shows a front view, representing a beam intended to be mounted in the attachment system.
- the beam 3 is subdivided into three longitudinal segments 31 , 32 , 33 .
- the third segment 33 is similar to the first segment 31 but oriented symmetrically relative to the central transversal section of the beam 3 .
- Each of the segments ends in a stepped section at least one of its ends, as shown in the figure, so that the assembly of the segments is facilitated.
- the central segment 32 has a stepped section such that it rests on the other two segments 31 , 33 .
- Fixing plates 34 consolidate the beam 3 at the level of the stepped sections.
- these segments 31 , 32 , 33 are more manoeuvrable than a beam which is all in one piece, which considerably simplifies the logistics relating to the delivery of the attachment system to a site. Moreover, the use of segments makes it possible not to have to resort to exceptional transport means and therefore to reduce the production cost of an assembled beam.
- Such an attachment system design makes it possible to envisage the production of beams with lengths ranging from 5 to 120 m. It is, in fact, theoretically possible to produce beams with lengths greater than 120 m in an attachment system according to the invention, by adapting the general dimensions of the beams and posts.
- the lengths of beams typically envisaged in the attachment system according to the invention the following lengths can be mentioned: 18, 24, 30, 35, 40, 55 and 70 m.
- the material used for the beam is glued-laminated material.
- a welded reconstituted steel section can be used.
- the beam tie is made of steel or steel derivative and has a modulus of elasticity comprised between 190,000 and 230,000 MPa.
- the invention is not however limited to the variants described above but is capable of numerous other variations easily accessible to a person skilled in the art.
- An uneven number of segments makes it possible to envisage a beam which is symmetrical relative to its central transversal section, the beam comprising a central segment resting on the beam tie.
- the number of segments can then be optimized so as to reduce the overall cost of mounting the attachment system.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
- Rod-Shaped Construction Members (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Mutual Connection Of Rods And Tubes (AREA)
- Variable-Direction Aerials And Aerial Arrays (AREA)
- Braking Arrangements (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Led Device Packages (AREA)
- Flanged Joints, Insulating Joints, And Other Joints (AREA)
- Auxiliary Devices For And Details Of Packaging Control (AREA)
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| FR0308093A FR2857038B1 (fr) | 2003-07-03 | 2003-07-03 | Systeme d'accrochage de poutre |
| FR03/08093 | 2003-07-03 | ||
| PCT/FR2004/001722 WO2005012665A1 (fr) | 2003-07-03 | 2004-07-02 | Systeme d'accrochage de poutre |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20070028551A1 true US20070028551A1 (en) | 2007-02-08 |
Family
ID=33522714
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US10/562,733 Abandoned US20070028551A1 (en) | 2003-07-03 | 2004-07-02 | Beam attachment system |
Country Status (9)
| Country | Link |
|---|---|
| US (1) | US20070028551A1 (de) |
| EP (1) | EP1649116B1 (de) |
| CN (1) | CN100557153C (de) |
| AT (1) | ATE394553T1 (de) |
| CA (1) | CA2530559C (de) |
| DE (1) | DE602004013594D1 (de) |
| FR (1) | FR2857038B1 (de) |
| NO (1) | NO20060015L (de) |
| WO (1) | WO2005012665A1 (de) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2010128046A1 (en) * | 2009-05-04 | 2010-11-11 | Arcelormittal Investigación Y Desarrollo S.L. | Fire resistant steel structure |
| US20170353676A1 (en) * | 2016-06-01 | 2017-12-07 | Canon Kabushiki Kaisha | Image capturing apparatus, control method therefor, image sensor, and control method therefor |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2340337A1 (de) * | 2008-05-28 | 2011-07-06 | Marc Irigoyen | Trägerbefestigungssystem mit nockenförmigem aufnahmewinkel |
| FR3135472B1 (fr) | 2022-05-12 | 2024-04-19 | Sermeca Stephanoise | Dispositif d’augmentation des portées des poutrespour bâtiments industriels à vêture périmétrique mobile |
| FR3135473B1 (fr) | 2022-05-12 | 2024-04-26 | Sermeca Stephanoise | Dispositif de liaison d’angle pour bâtiments industriels à vêture périmétrique mobile dotés de poutres dotées d’un chemin de roulement |
| CN115182450B (zh) * | 2022-09-08 | 2023-01-13 | 中铁十九局集团第三工程有限公司 | 一种可重复利用且具有缓冲功能的钢材质支撑结构 |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2693195A (en) * | 1952-07-03 | 1954-11-02 | Frieder | Portable shelter |
| US4223495A (en) * | 1977-10-14 | 1980-09-23 | Emil Peter | Prestressed steel support structure and method of erecting the same |
| US4275537A (en) * | 1977-05-26 | 1981-06-30 | Tension Structures, Inc. | Tension members |
| US4353190A (en) * | 1979-03-02 | 1982-10-12 | Gleeson Maurice J | Stiffened elongate support member |
| US4393637A (en) * | 1980-10-10 | 1983-07-19 | Mosier Leo D | Wood roof truss construction |
| US4876836A (en) * | 1987-02-23 | 1989-10-31 | Irigoyen Marc E | Support and attachment system for long-span beams |
| US4890429A (en) * | 1986-03-13 | 1990-01-02 | Starch Industries, Pty. Ltd. | Building truss |
| US5337531A (en) * | 1992-10-15 | 1994-08-16 | Thompson Fabricating Company, Inc. | Adjustable camber truss |
| US6065257A (en) * | 1999-05-24 | 2000-05-23 | Hubbell, Roth & Clark, Inc. | Tendon alignment assembly and method for externally reinforcing a load bearing beam |
| US6647678B1 (en) * | 1999-10-12 | 2003-11-18 | Sergio Zambelli | Device for connecting prefabricated beams to pillars or similar load-bearing structural elements |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR1523827A (fr) * | 1967-05-22 | 1968-05-03 | Constructions à partir d'un assemblage d'éléments modulés | |
| FR2262167A1 (en) * | 1974-02-26 | 1975-09-19 | Savineau Pierre | Architectural supporting structure - has end gantries with ropes and arches between to support roof |
| FR2698897B1 (fr) * | 1992-12-08 | 1995-01-06 | Walter Ets Lucien | Structure pour construction telle que hall, chapiteau, tente ou analogue. |
-
2003
- 2003-07-03 FR FR0308093A patent/FR2857038B1/fr not_active Expired - Fee Related
-
2004
- 2004-07-02 WO PCT/FR2004/001722 patent/WO2005012665A1/fr not_active Ceased
- 2004-07-02 US US10/562,733 patent/US20070028551A1/en not_active Abandoned
- 2004-07-02 CN CNB2004800227880A patent/CN100557153C/zh not_active Expired - Fee Related
- 2004-07-02 AT AT04767562T patent/ATE394553T1/de not_active IP Right Cessation
- 2004-07-02 CA CA2530559A patent/CA2530559C/fr not_active Expired - Fee Related
- 2004-07-02 EP EP04767562A patent/EP1649116B1/de not_active Expired - Lifetime
- 2004-07-02 DE DE602004013594T patent/DE602004013594D1/de not_active Expired - Lifetime
-
2006
- 2006-01-03 NO NO20060015A patent/NO20060015L/no unknown
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US2693195A (en) * | 1952-07-03 | 1954-11-02 | Frieder | Portable shelter |
| US4275537A (en) * | 1977-05-26 | 1981-06-30 | Tension Structures, Inc. | Tension members |
| US4223495A (en) * | 1977-10-14 | 1980-09-23 | Emil Peter | Prestressed steel support structure and method of erecting the same |
| US4353190A (en) * | 1979-03-02 | 1982-10-12 | Gleeson Maurice J | Stiffened elongate support member |
| US4393637A (en) * | 1980-10-10 | 1983-07-19 | Mosier Leo D | Wood roof truss construction |
| US4890429A (en) * | 1986-03-13 | 1990-01-02 | Starch Industries, Pty. Ltd. | Building truss |
| US4876836A (en) * | 1987-02-23 | 1989-10-31 | Irigoyen Marc E | Support and attachment system for long-span beams |
| US5337531A (en) * | 1992-10-15 | 1994-08-16 | Thompson Fabricating Company, Inc. | Adjustable camber truss |
| US6065257A (en) * | 1999-05-24 | 2000-05-23 | Hubbell, Roth & Clark, Inc. | Tendon alignment assembly and method for externally reinforcing a load bearing beam |
| US6647678B1 (en) * | 1999-10-12 | 2003-11-18 | Sergio Zambelli | Device for connecting prefabricated beams to pillars or similar load-bearing structural elements |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2010128046A1 (en) * | 2009-05-04 | 2010-11-11 | Arcelormittal Investigación Y Desarrollo S.L. | Fire resistant steel structure |
| US20170353676A1 (en) * | 2016-06-01 | 2017-12-07 | Canon Kabushiki Kaisha | Image capturing apparatus, control method therefor, image sensor, and control method therefor |
Also Published As
| Publication number | Publication date |
|---|---|
| NO20060015L (no) | 2006-02-02 |
| FR2857038A1 (fr) | 2005-01-07 |
| CA2530559C (fr) | 2012-09-11 |
| WO2005012665A1 (fr) | 2005-02-10 |
| ATE394553T1 (de) | 2008-05-15 |
| DE602004013594D1 (de) | 2008-06-19 |
| CN1833079A (zh) | 2006-09-13 |
| FR2857038B1 (fr) | 2007-03-30 |
| EP1649116B1 (de) | 2008-05-07 |
| CA2530559A1 (fr) | 2005-02-10 |
| EP1649116A1 (de) | 2006-04-26 |
| CN100557153C (zh) | 2009-11-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101256130B1 (ko) | 프리캐스트 거더 및 이를 이용한 교량 구조물 | |
| KR100987061B1 (ko) | 교량 상부구조물 확장구조 및 방법 | |
| JP4993768B2 (ja) | 道路用柵 | |
| KR102216347B1 (ko) | 응력증대수단이 구비된 확장형 더블웹 켄틸레버 | |
| KR102487850B1 (ko) | 일체형 지지대를 포함하는 캔틸레버 프리캐스트 반단면 데크 및 이를 이용한 캔틸레버 구조체 시공 방법 | |
| US20070028551A1 (en) | Beam attachment system | |
| KR100648046B1 (ko) | 외적 포스트텐션 방법을 이용한 보 및 거더 보강장치 및 그를 이용한 보 및 거더의 보강방법 | |
| KR100699413B1 (ko) | 처짐 보정이 가능한 채널 브리지 시공방법 | |
| US20040123408A1 (en) | Building construction method using plane lattice typed cable structure | |
| US6018834A (en) | Method for building a bridge and bridge built according to said method | |
| KR20200013911A (ko) | 단면강성 증대용 새들이 장착된 가설교량 및 이의 시공 방법 | |
| CZ282647B6 (cs) | Kovové bezpečnostní svodidlo | |
| US20090065038A1 (en) | Demountable and reusable canopy | |
| KR100931318B1 (ko) | 트러스 구조의 지점부를 갖는 가설교량 및 그 시공방법 | |
| KR102163560B1 (ko) | 거더 및 이를 이용한 방음벽이 설치된 교량 | |
| KR101000269B1 (ko) | 트러스덱 바닥판을 tsc 보 측면에 부착한 띠쇠에 얹어 조성하는 합성보 | |
| JP2787422B2 (ja) | 雪崩等の防護柵 | |
| KR100916269B1 (ko) | 길이형 구조물의 받침대 | |
| KR102624294B1 (ko) | 공중 보행교 및 이의 시공방법 | |
| KR100436747B1 (ko) | 트러스 부재를 이용한 교량의 보수보강장치 및 방법 | |
| KR102173687B1 (ko) | 교량용 방음 터널 | |
| KR102132338B1 (ko) | 아치형보강재를 포함하는 강합성 psc 거더 | |
| RU2525895C2 (ru) | Основание забора и элемент забора | |
| JPH0693603A (ja) | 逆アーチ状弧部材及び斜張構造を用いた梁構築装置及び該梁構築装置に用いる逆アーチ状弧部材 | |
| KR102776479B1 (ko) | 구조물의 하중보강을 위한 강봉 포스트 텐션구조 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO PAY ISSUE FEE |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO PAY ISSUE FEE |