US20050155307A1 - Hanger for insulated concrete system and method of installation thereof and method of installing a retrofit hanger in an insulated concrete - Google Patents
Hanger for insulated concrete system and method of installation thereof and method of installing a retrofit hanger in an insulated concrete Download PDFInfo
- Publication number
- US20050155307A1 US20050155307A1 US11/037,354 US3735405A US2005155307A1 US 20050155307 A1 US20050155307 A1 US 20050155307A1 US 3735405 A US3735405 A US 3735405A US 2005155307 A1 US2005155307 A1 US 2005155307A1
- Authority
- US
- United States
- Prior art keywords
- hanger
- plate
- hanging
- wall
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000009434 installation Methods 0.000 title description 3
- 239000006260 foam Substances 0.000 claims abstract description 33
- 239000002131 composite material Substances 0.000 claims abstract description 28
- 230000014759 maintenance of location Effects 0.000 claims abstract description 7
- 230000003014 reinforcing effect Effects 0.000 claims description 16
- 239000002184 metal Substances 0.000 claims description 9
- 238000005520 cutting process Methods 0.000 claims description 4
- 238000005192 partition Methods 0.000 description 9
- 229910001335 Galvanized steel Inorganic materials 0.000 description 6
- 239000008397 galvanized steel Substances 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 239000004793 Polystyrene Substances 0.000 description 3
- 229920002223 polystyrene Polymers 0.000 description 3
- 230000003466 anti-cipated effect Effects 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000004698 Polyethylene Substances 0.000 description 1
- 229920005830 Polyurethane Foam Polymers 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 235000013351 cheese Nutrition 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000007373 indentation Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- ISWSIDIOOBJBQZ-UHFFFAOYSA-N phenol group Chemical group C1(=CC=CC=C1)O ISWSIDIOOBJBQZ-UHFFFAOYSA-N 0.000 description 1
- -1 polyethylene Polymers 0.000 description 1
- 229920000573 polyethylene Polymers 0.000 description 1
- 229920006327 polystyrene foam Polymers 0.000 description 1
- 239000011496 polyurethane foam Substances 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B1/2612—Joist hangers
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/388—Separate connecting elements
- E04B2001/389—Brackets
Definitions
- the present invention relates to a hanger for an insulated concrete system. In another of its aspect, the present invention relates to a method of installing a hanger in an insulated concrete system. In yet another of its aspects, the present invention relates to a method of installing a retrofit hanger in an insulated concrete system.
- Hangers are known for insulated concrete systems formed of composite walls having exterior foam panels and an interior cement core.
- U.S. Pat. No. 5,228,261 [Watkins] teaches a joist hanger having a U-shaped body. A plurality of nailing apertures are formed in the forward end of this U-shaped joist hanger for receiving nails to secure a joist thereto. A pair of support apertures are formed in the rearward end of the U-shaped joist hanger through which conventional reinforcing bars are journalled in horizontal orientation. A slot extending forwardly from the rearward edge of the base of the U-shaped hanger receives a vertical reinforcing bar.
- the joist hanger taught in Watkins is installed by cutting a U-shaped slot into an exterior foam panel at a pre-determined position. Rods are loosely installed through locating apertures between the front and rearward edge of the U-shaped bracket; these rods limit the extent of insertion of the bracket into the U-shaped slot. Reinforcing bars are then positioned between the foam panel walls and journalled through support apertures. Concrete is then poured between the foam panel walls and allowed to cure, thereby fixing the reinforcing bars and the rearward end of the hanger in position within the wall. The rods are then removed from the locating apertures. The joist is then rested within the projecting forward end of the bracket and nails or other fasteners are installed through the nailing apertures.
- the U-shape of the bracket requires that, for proper installation, U-shaped slots of a pre-determined size must be cut in the foam wall at predetermined positions.
- retaining the U-shaped bracket requires that reinforcing bars be journalled through apertures in the rear end of the bracket, which thereby constrains the arrangement of reinforcing bars.
- U.S. Pat. No. 4,889,310 issued to Boeshart (“Boeshart”) teaches ties for a concrete form system having opposed polystyrene panels that form a pair of parallel, spaced apart walls. At least one of the polystyrene walls has a smooth inner face to allow the panel to be removed after formation of the concrete wall.
- the ties are used to interlock the two vertical panels in order to form the concrete wall.
- Each tie has a pair of spaced apart paddle members which retain the thickness of the panel therebetween. Once the concrete wall has been formed, the outer paddle is removed by applying a blow thereto.
- the tie uses an enlarged outer paddle disposed outwardly of the outward face of the panels.
- This enlarged paddle may have fastener apertures and may be connected to vertical whalers.
- the tie taught by Boeshart is designed for holding two polystyrene panels together to permit forming and does not provide sufficient support to hang objects from a face of the wall once formed.
- the present invention provides a hanger for hanging an object from a composite wall, the composite wall having a concrete core, a foam outer wall and a second outer wall, the hanger comprising:
- a first plate having an embedded portion for retention within the concrete core and a hanging portion extending from the foam outer wall for connection to the object;
- the embedded portion having an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate.
- the present invention provides a method for installing a hanger on a composite wall formed from a foam wall and a second wall defining a cavity fillable with concrete, the hanger including a first plate having an embedded portion and a hanging portion, wherein the embedded portion comprises an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate, the method comprising the steps of:
- the present invention provides a method of hanging a hanger from a foam wall of a composite wall having a cured concrete core and at least one foam outer wall, the hanger comprising a substantially L-shaped bracket having a retaining portion and a hanging portion for connection to an object to be hung, the hanging portion disposed at substantially a 90 degree angle to the retaining portion, the method comprising the steps of:
- FIG. 1 illustrates a perspective view of a partially assembled embodiment of the present hanger.
- FIG. 2 illustrates a side cross-section view of a partially assembled embodiment of the present hanger.
- FIG. 3 illustrates a perspective view of a partially assembled embodiment of the present hanger.
- FIG. 4 illustrates a perspective view of an assembled embodiment of the present hanger.
- FIG. 5 illustrates a side cross-section view of an embodiment of the present hanger.
- FIG. 6 illustrates a side view of an embodiment of a plate of the present hanger.
- FIG. 7 illustrates a perspective view of an embodiment of a plate of the present hanger.
- FIG. 8 illustrates a perspective view of an embodiment of a partially assembled retrofit bracket of the present invention.
- FIG. 9 illustrates a side cross-section view of an installed plate of an embodiment of a retrofit bracket of the present invention.
- Insulated concrete form system 105 includes a composite wall 110 .
- Composite wall 110 is formed using a pair of outer walls 115 a and 115 b, at least one of which, and preferably both of which, are formed of rigid foam.
- the type of foam is not particularly restricted and is within the purview of a person skilled in the art.
- the rigid foam may be a polyurethane foam, a phenolic foam, or a polyethylene foam.
- the rigid foam is polystyrene foam.
- Foam wall 115 may be an integral structure or may be formed from foam panels.
- Composite wall 110 Prior to forming of composite wall 110 , outer walls 115 a and 115 b form a cavity 120 fillable with concrete.
- Composite wall 110 may also comprise reinforcing bars 125 a, 125 b, 125 c, 125 d and 125 e.
- the reinforcing bars may be vertical or horizontal and are installed in cavity 120 prior to pouring of the concrete.
- reinforcing bars 125 a, 125 b, 125 c, 125 d and 125 e are formed from steel.
- the number and arrangement of reinforcing bars is not particularly restricted and is within the purview of a person skilled in the art. It should be clearly noted that, in the illustrated arrangement, reinforcing bar 125 a is optional.
- Hanger 100 consists of a plate 130 .
- hanger 100 consists of a pair of plates 130 a and 130 b.
- Plates 130 a and 130 b may be attached by one or more members (not shown).
- Plates 130 a and 130 b are preferably formed of metal and, more preferably, are formed of stamped metal sheet.
- the metal is steel such as galvanized steel (preferably 22 gauge) or another cold rolled metal.
- Plates 130 a and 130 b are inserted into slits 135 a and 135 b cut into an outer wall 115 b. Slits 135 a and 135 b are cut to approximately the height at which the installer wishes to hang an object 138 .
- hanger 100 is particularly suitable for the hanging of joists and, in particular, floor joists for an interior floor.
- Hanger 100 is also suitable for other purposes including hurricane truss tie down anchorage, anchorage or fastening an exterior or interior applied framed partition wall to a composite wall, hanging an exterior or interior applied roof truss to a composite wall, and mounting exterior floor joists for, for example, an exterior deck application.
- the uses of hanger 100 are not particularly restricted and are within the purview of a person skilled in the art.
- Hanger 100 is particularly suitable for hanging weight bearing structural members.
- the ultimate load capacity of a single concrete insert plate is at least about 2000 lbs, more preferably at least about 3000 lbs, even more preferably at least about 4000 lbs.
- the most preferred ultimate load capacity is about 5,000 lbs.
- the entire assembly is expected to attain a factored rated load capacity (in total) substantially same, respectively, as the ultimate load capacity referred to above. This specification will vary for each required bearing condition, depending on the load anticipated and may be readily determend
- plates 130 a and 130 b have an embedded portion 140 , which extends into the cavity 120 for retention therein upon pouring and curing of concrete core 150 .
- Plate 130 further has a hanging portion 160 for connection to object 138 .
- Hanging portion 160 extends out from composite wall 110 .
- the plate axis extending from embedded portion 140 to hanging portion 160 will be referred to herein as the longitudinal axis, although this label is not intended to limit the size or shape of plate 130 .
- Embedded portion 140 has an edge transverse to the longitudinal axis. This edge is in addition to the distal (or most embedded) edge of embedded portion 140 . This edge helps retain embedded portion 140 in concrete core 150 .
- the edge may form part of slots or cut-outs, such as slots 155 a, 155 b, 155 c and 155 d about the periphery of plate 130 .
- embedded portion 140 forms part of an aperture 145 therein which improves retention of embedded portion 140 within concrete core 150 .
- slots 155 a, 155 b, 155 c, and 155 d are shaped and sized to accommodate horizontal reinforcing bars, such as reinforcing bar 125 e.
- the number of slots 155 a, 155 b, 155 c, and 155 d is not particularly restricted and is within the purview of a person skilled in the art.
- Hanger 100 further comprises a support 165 .
- Support 165 is preferably a U-shaped bracket.
- support 165 if formed of metal. More preferably, support 165 is formed of stamped metal sheet.
- the metal is steel such as galvanized steel (preferably 22 gauge) or another cold rolled metal.
- Support 165 is sized to hold at least a part of object 138 , such as an end portion of a joist. The size of support 165 is not particularly restricted and is within the purview of a person skilled in the art.
- Support 165 is securable to hanging portion 160 of plate 130 .
- Preferably support 165 is inserted between and secured to hanging portions 160 a and 160 b of plates 130 a and 130 b.
- hanging portion 160 comprises a plurality of apertures 170 and support 165 comprises a plurality of corresponding apertures 175 .
- Securing means 180 are inserted through apertures 170 and corresponding apertures 175 once support 165 is in position between hanging portions 160 a and 160 b.
- the plurality of apertures 170 and corresponding apertures 175 permit the hanging height of object 138 to be adjusted post-insertion of plates 130 a and 130 b and the pouring and curing of concrete core 150 .
- apertures 170 and corresponding apertures 175 permit the installer to accommodate moderate discrepancies in the heights of plates 130 a and 130 b after setting of concrete core 150 .
- apertures 170 and corresponding apertures 175 are not particularly restricted and is within the purview of a person skilled in the art.
- the arrangement of apertures 170 and corresponding apertures 175 may be such that support 165 may be secured so as to hang object 138 on an angle.
- plate 130 further comprises an outer projection 185 .
- Outer projection 185 extends at substantially a 90 degree angle from plate 130 and when plate 130 is in a hanging position, abuts an exterior surface of outer wall 115 a. Outer projection 185 may project from either face of plate 130 .
- plate 130 may comprise a plurality of similarly structured outer projections.
- plate 130 may contain one or more inner projections 190 .
- Inner projection 190 extends at substantially a 90 degree angle from plate 130 and when plate 130 is inserted in a hanging position, abuts an interior surface of outer wall 115 a, and concrete core 150 .
- inner projection 190 comprises an edge transverse to the longitudinal axis and present in addition to the distal edge of the embedded portion. Inner projection 190 may project from either face of plate 130 .
- the number of outer projections 185 and inner projections 190 is not particularly restricted and is within the purview of a worker skilled in the art.
- outer projections 185 and inner projections 190 are formed by punching out portions of plate 130 .
- plate 130 comprises an outer projection.
- hanger 100 is installed by first cutting slits 135 a and 135 b through foam wall 115 b to a desired hanging position, prior to pouring of concrete core 150 . Plates 130 a and 130 b are then slid into slits 135 a and 135 b to a desired hanging position. Reinforcing bars 125 may then be positioned between outer walls 115 a and 115 b. Concrete core 150 is then poured and allowed to cure.
- Object 138 is then positioned within support 165 .
- Support 165 is positioned between hanging portions 160 a and 160 b of plates 130 a and 130 b so that one or more of apertures 170 align with one or more corresponding apertures 175 .
- Securing means 180 are inserted through these aligned apertures to secure plate 130 to support 165 .
- securing means 180 are further forced into object 138 thereby securing plate 130 , support 165 and object 138 to each other.
- the number and type of securing means 180 used is not particularly restricted and is within the purview of a person skilled in the art, though, in some applications, suitable securing means should include screws only to provide adequate compression of the elements together, thereby effectively reducing the shear forces on parts 180 .
- object 138 can translated such that the bottom thereof is below the bottom edge of securing plate 130 (i.e., this can be seen, for example in FIG. 4 ).
- plates 130 a and 130 b are wet set into concrete core 150 at the top of a finished poured composite wall 110 parallel to truss or rafter placement. Once concrete core 150 is cured, the truss or rafter is secured in position between plates 130 a and 130 b. Support 165 may then be used as a tie down element by being slid downward upside down over the top of the truss or rafter member. Securing means 180 may then be used to secure plate 130 to support 165 and the truss or rafter.
- one or more of plates 130 can be used.
- the number of plates necessary for a partition anchorage application is within the purview of a person skilled in the art.
- a series of two or three plates 130 or pairs of plates 130 a and 130 b are required for a standard 8 or 9 foot high partition.
- slits are made into foam wall 115 b on one or both sides of where the partition will be installed. Plates 130 are then inserted through these slits.
- partition members such as wood and steel partition members, can be secured to the hanging portion(s) 160 of insert plate(s) 130 through apertures 170 .
- the partition can be pre-assembled and tilted up into place against plates 130 . Drywall finishes can then be installed as per normal installation practices directly over the insert plates.
- a series of opposing pairs of plates 130 a and 130 b are used in a partition anchorage application.
- FIGS. 8 and 9 there is illustrated a retrofit bracket 195 of another embodiment of the present invention for use in insulated concrete form system 205 .
- parts identified in the first embodiment are here numbered in the two-hundreds, however, when the same numbers appear as second and third digits, they denote a part corresponding to the part having the same digits in the first embodiment.
- Retrofit bracket 195 comprises a retrofit plate 230 .
- retrofit bracket 195 comprises two retrofit plates 230 a and 230 b.
- Retrofit plate 230 has a retaining portion 203 , which comprises one or more retaining apertures 207 a and 207 b to accommodate concrete securing means 209 a and 209 b.
- these securing means are concrete fasteners.
- concrete fasteners 209 a and 209 b are expansion (e.g., lag-type) anchors. Suitable screws are Tap-ConTM screws.
- Retrofit bracket 195 further comprises hanging portion 260 .
- Hanging portion 260 comprises a plurality of apertures 270 .
- Retrofit bracket 195 further comprises a support 265 .
- Support 265 is preferably a U-shaped bracket.
- Support 265 is sized to accommodate an object 238
- Support 265 has a plurality of corresponding apertures 275 .
- Support 265 is securable to hanging portion 260 of retrofit plate 230 .
- Preferably, support 265 is inserted between and secured to both hanging portions 260 a and 260 b.
- Apertures 270 and corresponding apertures 275 permit the height of object 238 to be adjusted post fastening of retrofit plates 230 a and 230 b to composite wall 210 .
- apertures 270 and corresponding apertures 275 permit an installer to accommodate moderate discrepancies in the heights of retrofit plates 230 a and 230 b after they are fastened to composite wall 210 .
- a portion of foam wall 215 b sized and shaped to accommodate retaining portion 203 is cut away at a desired hanging position.
- Retaining portion 203 is then fastened to concrete core 250 .
- fastening of retaining portion 203 to concrete core 250 will require that holes be drilled in concrete core 250 corresponding to retaining apertures 207 a and 207 b.
- Retaining portion 203 is then positioned adjacent concrete core 250 so that retaining apertures 207 a and 207 b align with the drilled holes.
- Concrete securing means 209 a and 209 b are then forced through retaining apertures 207 a and 207 b to secure retaining portion 203 to concrete core 250 .
- Support 265 is positioned between hanging ends 260 a and 260 b of retrofit plates 230 a and 230 b so that one or more of apertures 270 align with one or more of corresponding apertures 275 .
- Object 238 is positioned within support 265 . Either before or after it is positioned between retrofit plates 230 a and 230 b.
- support 265 may be secured to a single plate 230 .
- Securing means 280 are inserted through these aligned apertures to secure retrofit plate 230 to support 265 .
- securing means 280 are further forced into object 238 thereby securing retrofit plate 230 , support 265 and object 238 to each other.
- the number and type of securing means 280 used is not particularly restricted and is within the purview of a person skilled in the art. Suitable securing means 280 include screws and nails.
- supports 165 , 265 and the objects 138 , 238 to be hung have been shown as separate elements, those skilled in the art will recognize that the support could be inherent or integral with the object to be hung.
- connection is not particularly restricted, and is within the purview of a person skilled in the art.
- the connection may be by way of securing means such as screws, by friction fit or by gravity.
- this component is fed, stamped and bent in a two-stage operation which involves galvanized steel plate being supplied in a coil at the precise cut width of the component.
- the component is first fed forward into the manufacturing from when it is stamped to create the holes and outer notches and is cur from the coil.
- the second stage of the process involves another part of the die fitting to the component to break press the protruding tab to its final position about 90° to the plane of the plate.
- the component is then ejected from the die to start the next component.
- bearing Bracket (or support 165 ):
- this component can vary in width to suit a variety of different objects, as described in the specification.
- the manufacturing process is similar to above in two stages.
- galvanized steel coil is supplied in the width of the component. It is first fed from the coil and is stamped to the required size from galvanized steel coil sheet. At the same time as being stamped, the material is also slightly perforated in a designated grid pattern that is designed to line up with the pre-stamped holes of the concrete form insert plate.
- the perforations are such that, rather than being stamped as clear holes, the material is in fact only deformed to a point of piercing and left in place within the part (similar to a cheese grater)—this facilitates creation of a friction fit with the joist or other member being hung.
- the stamped component is then break-formed to a U shape with opposing 90° bends such that the side to which the perforations are pointing towards are now facing each other ready to contact the object they are designed to be fastened to. This forming is all completed within another component of the same forming die. The component is then ejected from the machine ready to form the next component.
- Retrofit Bracket or plate 230 Contrary to the other two components, it is preferred to manufacture this component from heavier gauge galvanized steel sheet which is stamped and break formed to required shape in a single step. The includes not only the 90° angle of the component but also the reinforcing “crimps” down the axis of the angle in three locations with arrow shaped indentations to providing the required increased resistance to loading.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
There is described a hanger for hanging an object from a composite wall. The composite wall has a concrete core, a foam outer wall and a second outer wall. The hanger comprises: a first plate having an embedded portion for retention within the concrete core and a hanging portion extending from the foam outer wall for connection to the object. The embedded portion having an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate. A method for installing the hanger is also described. The hanger is particularly well suited for hang a joist.
Description
- 1. Field of the Invention
- In one of its aspects, the present invention relates to a hanger for an insulated concrete system. In another of its aspect, the present invention relates to a method of installing a hanger in an insulated concrete system. In yet another of its aspects, the present invention relates to a method of installing a retrofit hanger in an insulated concrete system.
- 2. Description of the Prior Art
- Hangers are known for insulated concrete systems formed of composite walls having exterior foam panels and an interior cement core.
- For example, U.S. Pat. No. 5,228,261 [Watkins] teaches a joist hanger having a U-shaped body. A plurality of nailing apertures are formed in the forward end of this U-shaped joist hanger for receiving nails to secure a joist thereto. A pair of support apertures are formed in the rearward end of the U-shaped joist hanger through which conventional reinforcing bars are journalled in horizontal orientation. A slot extending forwardly from the rearward edge of the base of the U-shaped hanger receives a vertical reinforcing bar.
- The joist hanger taught in Watkins is installed by cutting a U-shaped slot into an exterior foam panel at a pre-determined position. Rods are loosely installed through locating apertures between the front and rearward edge of the U-shaped bracket; these rods limit the extent of insertion of the bracket into the U-shaped slot. Reinforcing bars are then positioned between the foam panel walls and journalled through support apertures. Concrete is then poured between the foam panel walls and allowed to cure, thereby fixing the reinforcing bars and the rearward end of the hanger in position within the wall. The rods are then removed from the locating apertures. The joist is then rested within the projecting forward end of the bracket and nails or other fasteners are installed through the nailing apertures.
- Disadvantages exist with regard to the above-described system. The U-shape of the bracket requires that, for proper installation, U-shaped slots of a pre-determined size must be cut in the foam wall at predetermined positions. In addition, retaining the U-shaped bracket requires that reinforcing bars be journalled through apertures in the rear end of the bracket, which thereby constrains the arrangement of reinforcing bars.
- U.S. Pat. No. 4,889,310 issued to Boeshart (“Boeshart”) teaches ties for a concrete form system having opposed polystyrene panels that form a pair of parallel, spaced apart walls. At least one of the polystyrene walls has a smooth inner face to allow the panel to be removed after formation of the concrete wall. The ties are used to interlock the two vertical panels in order to form the concrete wall. Each tie has a pair of spaced apart paddle members which retain the thickness of the panel therebetween. Once the concrete wall has been formed, the outer paddle is removed by applying a blow thereto. In one embodiment, the tie uses an enlarged outer paddle disposed outwardly of the outward face of the panels. This enlarged paddle may have fastener apertures and may be connected to vertical whalers. The tie taught by Boeshart is designed for holding two polystyrene panels together to permit forming and does not provide sufficient support to hang objects from a face of the wall once formed.
- Accordingly, it would be desirable to have a hanger system which overcomes the above-mentioned disadvantages of the prior art. It would be further desirable to have a retrofit hanger system useful in an insulated concrete system.
- It is an object of the present invention to provide a novel hanger system, particularly for hanging a joist) that obviates or mitigates at least one of the above-mentioned disadvantages of the prior art.
- Accordingly, in one of its aspects, the present invention provides a hanger for hanging an object from a composite wall, the composite wall having a concrete core, a foam outer wall and a second outer wall, the hanger comprising:
- a first plate having an embedded portion for retention within the concrete core and a hanging portion extending from the foam outer wall for connection to the object;
- the embedded portion having an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate.
- Accordingly, in another of its aspects, the present invention provides a method for installing a hanger on a composite wall formed from a foam wall and a second wall defining a cavity fillable with concrete, the hanger including a first plate having an embedded portion and a hanging portion, wherein the embedded portion comprises an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate, the method comprising the steps of:
- (a) cutting a slit through the foam wall so that the slit extends to a hanging position;
- (b) sliding the first plate in the slit to the hanging position, wherein the embedded portion of the first plate extends into the cavity and the hanging portion extends from the composite wall;
- (c) pouring concrete into the cavity and allowing it to cure to form the composite wall.
- In yet another of its aspects, the present invention provides a method of hanging a hanger from a foam wall of a composite wall having a cured concrete core and at least one foam outer wall, the hanger comprising a substantially L-shaped bracket having a retaining portion and a hanging portion for connection to an object to be hung, the hanging portion disposed at substantially a 90 degree angle to the retaining portion, the method comprising the steps of:
- (a) forming a cavity at a hanging position in the foam wall to accommodate the retaining portion;
- (b) securing the retaining portion to the concrete core.
- Embodiments of the present invention will be described with reference to the accompanying drawings, wherein like reference numerals denote like parts, and in which:
-
FIG. 1 illustrates a perspective view of a partially assembled embodiment of the present hanger. -
FIG. 2 illustrates a side cross-section view of a partially assembled embodiment of the present hanger. -
FIG. 3 illustrates a perspective view of a partially assembled embodiment of the present hanger. -
FIG. 4 illustrates a perspective view of an assembled embodiment of the present hanger. -
FIG. 5 illustrates a side cross-section view of an embodiment of the present hanger. -
FIG. 6 illustrates a side view of an embodiment of a plate of the present hanger. -
FIG. 7 illustrates a perspective view of an embodiment of a plate of the present hanger. -
FIG. 8 illustrates a perspective view of an embodiment of a partially assembled retrofit bracket of the present invention. -
FIG. 9 illustrates a side cross-section view of an installed plate of an embodiment of a retrofit bracket of the present invention. - With reference to
FIGS. 1 through 5 , there is illustrated ahanger 100 of an embodiment of the present invention for use in an insulatedconcrete form system 105. Insulatedconcrete form system 105 includes acomposite wall 110.Composite wall 110 is formed using a pair of 115 a and 115 b, at least one of which, and preferably both of which, are formed of rigid foam. The type of foam is not particularly restricted and is within the purview of a person skilled in the art. The rigid foam may be a polyurethane foam, a phenolic foam, or a polyethylene foam. Preferably, the rigid foam is polystyrene foam. Foam wall 115 may be an integral structure or may be formed from foam panels.outer walls - Prior to forming of
composite wall 110, 115 a and 115 b form aouter walls cavity 120 fillable with concrete.Composite wall 110 may also comprise reinforcing 125 a, 125 b, 125 c, 125 d and 125 e. The reinforcing bars may be vertical or horizontal and are installed inbars cavity 120 prior to pouring of the concrete. Preferably, reinforcing 125 a, 125 b, 125 c, 125 d and 125 e are formed from steel. The number and arrangement of reinforcing bars is not particularly restricted and is within the purview of a person skilled in the art. It should be clearly noted that, in the illustrated arrangement, reinforcingbars bar 125 a is optional. -
Hanger 100 consists of aplate 130. In a preferred embodiment,hanger 100 consists of a pair ofplates 130 a and 130 b.Plates 130 a and 130 b may be attached by one or more members (not shown).Plates 130 a and 130 b are preferably formed of metal and, more preferably, are formed of stamped metal sheet. Preferably, the metal is steel such as galvanized steel (preferably 22 gauge) or another cold rolled metal.Plates 130 a and 130 b are inserted into 135 a and 135 b cut into anslits outer wall 115 b. 135 a and 135 b are cut to approximately the height at which the installer wishes to hang anSlits object 138. - The objects for which
hanger 100 is suitable are not particularly restricted and are within the purview of a person skilled in the art.Hanger 100 is particularly suitable for the hanging of joists and, in particular, floor joists for an interior floor.Hanger 100 is also suitable for other purposes including hurricane truss tie down anchorage, anchorage or fastening an exterior or interior applied framed partition wall to a composite wall, hanging an exterior or interior applied roof truss to a composite wall, and mounting exterior floor joists for, for example, an exterior deck application. The uses ofhanger 100 are not particularly restricted and are within the purview of a person skilled in the art.Hanger 100 is particularly suitable for hanging weight bearing structural members. - Preferably, the ultimate load capacity of a single concrete insert plate (130 a or 130 b) is at least about 2000 lbs, more preferably at least about 3000 lbs, even more preferably at least about 4000 lbs. The most preferred ultimate load capacity is about 5,000 lbs. When combined in pairs and applying anticipated shear load to the assembly with the bearing bracket attached as described below, the entire assembly is expected to attain a factored rated load capacity (in total) substantially same, respectively, as the ultimate load capacity referred to above. This specification will vary for each required bearing condition, depending on the load anticipated and may be readily determend
- With reference to
FIGS. 1 through 7 ,plates 130 a and 130 b have an embeddedportion 140, which extends into thecavity 120 for retention therein upon pouring and curing ofconcrete core 150.Plate 130 further has a hangingportion 160 for connection to object 138. Hangingportion 160 extends out fromcomposite wall 110. The plate axis extending from embeddedportion 140 to hangingportion 160 will be referred to herein as the longitudinal axis, although this label is not intended to limit the size or shape ofplate 130. Embeddedportion 140 has an edge transverse to the longitudinal axis. This edge is in addition to the distal (or most embedded) edge of embeddedportion 140. This edge helps retain embeddedportion 140 inconcrete core 150. The edge may form part of slots or cut-outs, such as 155 a, 155 b, 155 c and 155 d about the periphery ofslots plate 130. In a preferred embodiment, embeddedportion 140 forms part of anaperture 145 therein which improves retention of embeddedportion 140 withinconcrete core 150. - In a preferred embodiment,
155 a, 155 b, 155 c, and 155 d are shaped and sized to accommodate horizontal reinforcing bars, such as reinforcingslots bar 125 e. The number of 155 a, 155 b, 155 c, and 155 d is not particularly restricted and is within the purview of a person skilled in the art.slots -
Hanger 100 further comprises asupport 165.Support 165 is preferably a U-shaped bracket. Preferably,support 165 if formed of metal. More preferably,support 165 is formed of stamped metal sheet. Preferably, the metal is steel such as galvanized steel (preferably 22 gauge) or another cold rolled metal.Support 165 is sized to hold at least a part ofobject 138, such as an end portion of a joist. The size ofsupport 165 is not particularly restricted and is within the purview of a person skilled in the art.Support 165 is securable to hangingportion 160 ofplate 130. Preferablysupport 165 is inserted between and secured to hanging 160 a and 160 b ofportions plates 130 a and 130 b. - In a preferred embodiment, hanging
portion 160 comprises a plurality ofapertures 170 andsupport 165 comprises a plurality ofcorresponding apertures 175. Securing means 180 are inserted throughapertures 170 andcorresponding apertures 175 oncesupport 165 is in position between hanging 160 a and 160 b. The plurality ofportions apertures 170 andcorresponding apertures 175 permit the hanging height ofobject 138 to be adjusted post-insertion ofplates 130 a and 130 b and the pouring and curing ofconcrete core 150. Further,apertures 170 andcorresponding apertures 175 permit the installer to accommodate moderate discrepancies in the heights ofplates 130 a and 130 b after setting ofconcrete core 150. The specific number and arrangement ofapertures 170 andcorresponding apertures 175 is not particularly restricted and is within the purview of a person skilled in the art. The arrangement ofapertures 170 andcorresponding apertures 175 may be such thatsupport 165 may be secured so as to hangobject 138 on an angle. - In a preferred embodiment,
plate 130 further comprises anouter projection 185.Outer projection 185 extends at substantially a 90 degree angle fromplate 130 and whenplate 130 is in a hanging position, abuts an exterior surface ofouter wall 115 a.Outer projection 185 may project from either face ofplate 130. In another embodiment,plate 130 may comprise a plurality of similarly structured outer projections. In another embodiment, in addition or in the alternative toouter projection 185,plate 130 may contain one or moreinner projections 190.Inner projection 190 extends at substantially a 90 degree angle fromplate 130 and whenplate 130 is inserted in a hanging position, abuts an interior surface ofouter wall 115 a, andconcrete core 150. As will be evident to a person skilled in the art,inner projection 190 comprises an edge transverse to the longitudinal axis and present in addition to the distal edge of the embedded portion.Inner projection 190 may project from either face ofplate 130. The number ofouter projections 185 andinner projections 190 is not particularly restricted and is within the purview of a worker skilled in the art. In a preferred embodiment,outer projections 185 andinner projections 190 are formed by punching out portions ofplate 130. Preferably,plate 130 comprises an outer projection. Preferably, when a pair ofplates 130 a are used they include outer projections offset relative to each other. - In a preferred embodiment,
hanger 100 is installed by first cutting slits 135 a and 135 b throughfoam wall 115 b to a desired hanging position, prior to pouring ofconcrete core 150.Plates 130 a and 130 b are then slid into 135 a and 135 b to a desired hanging position. Reinforcing bars 125 may then be positioned betweenslits 115 a and 115 b.outer walls Concrete core 150 is then poured and allowed to cure. -
Object 138 is then positioned withinsupport 165.Support 165 is positioned between hanging 160 a and 160 b ofportions plates 130 a and 130 b so that one or more ofapertures 170 align with one or morecorresponding apertures 175. Securing means 180 are inserted through these aligned apertures to secureplate 130 to support 165. Preferably, securing means 180 are further forced intoobject 138 thereby securingplate 130,support 165 and object 138 to each other. The number and type of securing means 180 used is not particularly restricted and is within the purview of a person skilled in the art, though, in some applications, suitable securing means should include screws only to provide adequate compression of the elements together, thereby effectively reducing the shear forces on parts 180. - With reference to
FIG. 5 , it should be noted thatobject 138 can translated such that the bottom thereof is below the bottom edge of securing plate 130 (i.e., this can be seen, for example inFIG. 4 ). - When
hanger 100 is used in a hurricane tie application,plates 130 a and 130 b are wet set intoconcrete core 150 at the top of a finished pouredcomposite wall 110 parallel to truss or rafter placement. Onceconcrete core 150 is cured, the truss or rafter is secured in position betweenplates 130 a and 130 b.Support 165 may then be used as a tie down element by being slid downward upside down over the top of the truss or rafter member. Securing means 180 may then be used to secureplate 130 to support 165 and the truss or rafter. - When
hanger 100 is used in a partition anchorage application, one or more ofplates 130 can be used. The number of plates necessary for a partition anchorage application is within the purview of a person skilled in the art. Generally, a series of two or threeplates 130 or pairs ofplates 130 a and 130 b are required for a standard 8 or 9 foot high partition. Prior to pouring ofconcrete core 150, slits are made intofoam wall 115 b on one or both sides of where the partition will be installed.Plates 130 are then inserted through these slits. Once the concrete is poured and cured, partition members, such as wood and steel partition members, can be secured to the hanging portion(s) 160 of insert plate(s) 130 throughapertures 170. If a single series ofplates 130 are used, the partition can be pre-assembled and tilted up into place againstplates 130. Drywall finishes can then be installed as per normal installation practices directly over the insert plates. Preferably, a series of opposing pairs ofplates 130 a and 130 b are used in a partition anchorage application. - With reference to
FIGS. 8 and 9 , there is illustrated aretrofit bracket 195 of another embodiment of the present invention for use in insulated concrete form system 205. In this embodiment, parts identified in the first embodiment are here numbered in the two-hundreds, however, when the same numbers appear as second and third digits, they denote a part corresponding to the part having the same digits in the first embodiment. -
Retrofit bracket 195 comprises aretrofit plate 230. In a preferred embodiment,retrofit bracket 195 comprises two 230 a and 230 b.retrofit plates Retrofit plate 230 has a retainingportion 203, which comprises one or 207 a and 207 b to accommodate concrete securing means 209 a and 209 b. Preferably these securing means are concrete fasteners. In a preferred embodiment,more retaining apertures 209 a and 209 b are expansion (e.g., lag-type) anchors. Suitable screws are Tap-Con™ screws.concrete fasteners Retrofit bracket 195 further comprises hanging portion 260. Hanging portion 260 comprises a plurality ofapertures 270. -
Retrofit bracket 195 further comprises asupport 265.Support 265 is preferably a U-shaped bracket.Support 265 is sized to accommodate anobject 238Support 265 has a plurality ofcorresponding apertures 275.Support 265 is securable to hanging portion 260 ofretrofit plate 230. Preferably,support 265 is inserted between and secured to both hanging 260 a and 260 b.portions Apertures 270 andcorresponding apertures 275 permit the height ofobject 238 to be adjusted post fastening of 230 a and 230 b to composite wall 210. Further,retrofit plates apertures 270 andcorresponding apertures 275 permit an installer to accommodate moderate discrepancies in the heights of 230 a and 230 b after they are fastened to composite wall 210.retrofit plates - To install
retrofit bracket 195, a portion offoam wall 215 b sized and shaped to accommodate retainingportion 203 is cut away at a desired hanging position. Retainingportion 203 is then fastened toconcrete core 250. Generally, fastening of retainingportion 203 toconcrete core 250 will require that holes be drilled inconcrete core 250 corresponding to retaining 207 a and 207 b. Retainingapertures portion 203 is then positioned adjacentconcrete core 250 so that retaining 207 a and 207 b align with the drilled holes. Concrete securing means 209 a and 209 b are then forced through retainingapertures 207 a and 207 b to secure retainingapertures portion 203 toconcrete core 250. -
Support 265 is positioned between hanging ends 260 a and 260 b of 230 a and 230 b so that one or more ofretrofit plates apertures 270 align with one or more ofcorresponding apertures 275.Object 238 is positioned withinsupport 265. Either before or after it is positioned between 230 a and 230 b. In an alternate embodiment,retrofit plates support 265 may be secured to asingle plate 230. Securing means 280 are inserted through these aligned apertures to secureretrofit plate 230 to support 265. Preferably, securing means 280 are further forced intoobject 238 thereby securingretrofit plate 230,support 265 and object 238 to each other. The number and type of securing means 280 used is not particularly restricted and is within the purview of a person skilled in the art. Suitable securing means 280 include screws and nails. - While
165, 265 and thesupports 138, 238 to be hung have been shown as separate elements, those skilled in the art will recognize that the support could be inherent or integral with the object to be hung.objects - While hanging
portions 160, 260 connect to 138, 238 the form of connection is not particularly restricted, and is within the purview of a person skilled in the art. For example, the connection may be by way of securing means such as screws, by friction fit or by gravity.objects - The manufacture of various elements of the present system will now be discussed.
- Concrete Form Insert Plate (130): Preferably, this component is fed, stamped and bent in a two-stage operation which involves galvanized steel plate being supplied in a coil at the precise cut width of the component. The component is first fed forward into the manufacturing from when it is stamped to create the holes and outer notches and is cur from the coil. The second stage of the process involves another part of the die fitting to the component to break press the protruding tab to its final position about 90° to the plane of the plate. The component is then ejected from the die to start the next component.
- Bearing Bracket (or support 165): Preferably, this component can vary in width to suit a variety of different objects, as described in the specification. The manufacturing process is similar to above in two stages. Preferably, galvanized steel coil is supplied in the width of the component. It is first fed from the coil and is stamped to the required size from galvanized steel coil sheet. At the same time as being stamped, the material is also slightly perforated in a designated grid pattern that is designed to line up with the pre-stamped holes of the concrete form insert plate. The perforations are such that, rather than being stamped as clear holes, the material is in fact only deformed to a point of piercing and left in place within the part (similar to a cheese grater)—this facilitates creation of a friction fit with the joist or other member being hung. The stamped component is then break-formed to a U shape with opposing 90° bends such that the side to which the perforations are pointing towards are now facing each other ready to contact the object they are designed to be fastened to. This forming is all completed within another component of the same forming die. The component is then ejected from the machine ready to form the next component.
- Retrofit Bracket or plate 230: Contrary to the other two components, it is preferred to manufacture this component from heavier gauge galvanized steel sheet which is stamped and break formed to required shape in a single step. The includes not only the 90° angle of the component but also the reinforcing “crimps” down the axis of the angle in three locations with arrow shaped indentations to providing the required increased resistance to loading.
- While this invention has been described with reference to illustrative embodiments, the description is not intended to be construed in a limiting sense. Thus, various modifications of the illustrative embodiments, as well as other embodiments of the invention, will be apparent to persons skilled in the art upon reference to this description. It is therefore contemplated that the appended claims will cover any such modifications or embodiments.
Claims (26)
1. A hanger for hanging an object from a composite wall, the composite wall having a concrete core, a foam outer wall and a second outer wall, the hanger comprising:
a first plate having an embedded portion for retention within the concrete core and a hanging portion extending from the foam outer wall for connection to the object;
the embedded portion having an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate.
2. The hanger defined in claim 1 , further comprising securing means for securing the hanging portion to the object.
3. The hanger defined in claim 1 , further comprising a support configured to receive the object, the support being securable to the hanging portion.
4. The hanger defined in claim 3 , further comprising securing means for securing the hanging portion to the support.
5. The hanger defined in claim 4 , wherein the support has an aperture formed therein for receiving the securing means.
6. The hanger defined in claim 3 , wherein the support is a U-shaped bracket.
7. The hanger defined in claim 2 , wherein the hanging portion has an aperture for receiving the securing means.
8. The hanger defined in claim 3 , wherein the securing means secures the hanging portion, the support and the object together.
9. The hanger defined in claim 3 , wherein the support and the hanging portion each have a plurality of apertures therein for receiving the securing means, the apertures arranged such that the support can be secured at a number of angles.
10. The hanger defined in claim 1 , wherein the embedded portion has an aperture therein for improved retention in the concrete core.
11. The hanger defined in claim 1 , wherein the embedded portion has slots about its periphery.
12. The hanger defined in claim 11 , wherein the slots are sized to fit reinforcing bars.
13. The hanger defined in claim 1 , wherein the first plate has a projection extending therefrom substantially parallel to the composite wall.
14. The hanger defined in claim 13 , wherein the projection is adjacent the exterior of the foam wall.
15. The hanger defined in claim 13 , wherein the projection is adjacent the concrete core.
16. The hanger defined in claim 1 , wherein the hanger is formed of metal.
17. The hanger defined in any one of claims 1-16, wherein the hanger further comprises a second plate having an embedded portion for retention within the concrete core and a hanging portion extending from the composite wall, the object being connectable to both plates.
18. The hanger defined in claim 17 wherein the first plate and second plate are the same.
19. The hanger defined in claim 17 wherein the first plate and second plate are different.
20. The hanger defined in claim 17 , further comprising a member connecting the first plate and second plate.
21. A method for installing a hanger on a composite wall formed from a foam wall and a second wall defining a cavity fillable with concrete, the hanger including a first plate having an embedded portion and a hanging portion, wherein the embedded portion comprises an edge in addition to its distal edge, the edge being substantially transverse to the longitudinal axis of the first plate, the method comprising the steps of:
(a) cutting a slit through the foam wall so that the slit extends to a hanging position;
(b) sliding the first plate in the slit to the hanging position, wherein the embedded portion of the first plate extends into the cavity and the hanging portion extends from the composite wall;
(c) pouring concrete into the cavity and allowing it to cure to form the composite wall.
22. The method defined in claim 21 , further comprising the step of securing a support for receiving an object to be hung to the hanging portion.
23. The method defined in claim 21 , further comprising the step of (d) sliding a second plate into a second slit before step (c) and positioning it substantially opposite the first plate, wherein an embedded portion of the second plate extends into the cavity and a hanging portion of the second plate extends from the composite wall.
24. The method defined in claim 23 , further comprising the step of (e) positioning the support between the hanging portions of the first and second plates and securing the support to the hanging portions of the first and second plates.
25. A method of hanging a hanger from a foam wall of a composite wall having a cured concrete core and at least one foam outer wall, the hanger comprising a substantially L-shaped bracket having a retaining portion and a hanging portion for connection to an object to be hung, the hanging portion disposed at substantially a 90 degree angle to the retaining portion, the method comprising the steps of:
(a) forming a cavity at a hanging position in the foam wall to accommodate the retaining portion;
(b) securing the retaining portion to the concrete core.
26. The method defined in claim 25 further comprising the step of securing a support for receiving the object to the hanging portion.
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CA2455376 | 2004-01-19 | ||
| CA002455376A CA2455376A1 (en) | 2004-01-19 | 2004-01-19 | Hanger for insulated concrete system and method of installation thereof and method of installing a retrofit hanger in an insulated concrete system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20050155307A1 true US20050155307A1 (en) | 2005-07-21 |
Family
ID=34744408
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US11/037,354 Abandoned US20050155307A1 (en) | 2004-01-19 | 2005-01-19 | Hanger for insulated concrete system and method of installation thereof and method of installing a retrofit hanger in an insulated concrete |
Country Status (2)
| Country | Link |
|---|---|
| US (1) | US20050155307A1 (en) |
| CA (1) | CA2455376A1 (en) |
Cited By (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20050161564A1 (en) * | 2003-06-03 | 2005-07-28 | Ganske Roger H. | Support bracket to suspend sheet material for a wall |
| US20070114347A1 (en) * | 2004-05-27 | 2007-05-24 | Ganske Roger H | Support bracket to suspend sheet material for a wall |
| GB2443483A (en) * | 2006-11-02 | 2008-05-07 | Victor Joseph Wigley | Joist Hanger with facility for damp-proofing |
| US20080202059A1 (en) * | 2007-02-27 | 2008-08-28 | Mccollough Daniel D | Floor joist hanger |
| GB2459935A (en) * | 2008-05-16 | 2009-11-18 | Victor Joseph Wigley | Joist end sleeve and joist collar for protecting joists within external masonry |
| US20100064626A1 (en) * | 2008-07-23 | 2010-03-18 | Lavern Kittlitz | Joist hanger for icf wall systems |
| US20110099932A1 (en) * | 2008-07-11 | 2011-05-05 | Roger Saulce | Panel interlocking system |
| US20130232758A1 (en) * | 2012-03-06 | 2013-09-12 | Inter-Med, Inc. | Bracket Assembly and Systems |
| US9663938B2 (en) * | 2015-08-21 | 2017-05-30 | Columbia Insurance Company | Hanger for bracing panel |
| US10316510B2 (en) * | 2013-12-31 | 2019-06-11 | Columbia Insurance Company | Hanger for fire separation wall |
| USRE48789E1 (en) * | 2013-12-14 | 2021-10-26 | Simpson Strong-Tie Company Inc. | Drywall joist hanger |
| US11225787B2 (en) | 2018-06-06 | 2022-01-18 | Simpson Strong-Tie Company, Inc. | Drywall spacing joist hanger |
| WO2022150931A1 (en) * | 2021-01-15 | 2022-07-21 | P & W Construction Materials and Consulting Ltd. | Brackets for insulated concrete forms and methods of manufacturing and installation thereof |
| US20250333956A1 (en) * | 2024-04-30 | 2025-10-30 | Simpson Strong-Tie Company Inc. | Insulated Concrete Form Connector |
| US12546106B2 (en) | 2021-09-01 | 2026-02-10 | Simpson Strong-Tie Company Inc. | Drywall hanger |
Citations (26)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US533659A (en) * | 1895-02-05 | Ceiling-supporter | ||
| US1728981A (en) * | 1927-04-30 | 1929-09-24 | Franklin N Ropp | Joist hanger for concrete buildings |
| US1785791A (en) * | 1928-12-17 | 1930-12-23 | Franklin N Ropp | Combination joist hanger and tie |
| US1785790A (en) * | 1928-08-14 | 1930-12-23 | Franklin N Ropp | Combination joist hanger and tie |
| US2013101A (en) * | 1934-03-30 | 1935-09-03 | Inglee Lewis | Furring clip |
| US2106084A (en) * | 1936-11-09 | 1938-01-18 | Reynolds Corp | Joist suspension |
| US2176450A (en) * | 1938-06-21 | 1939-10-17 | George F Barnett | Joist anchor and support |
| US2947119A (en) * | 1956-09-18 | 1960-08-02 | Jr Lawrence P Puckett | Anchored tie-down device for rafters |
| US3000145A (en) * | 1957-10-22 | 1961-09-19 | Advance Metal Products Inc | Truss anchor |
| US3267624A (en) * | 1963-05-31 | 1966-08-23 | Fenestra Inc | Composite panel with concrete backer and hanging members |
| US3338520A (en) * | 1965-08-16 | 1967-08-29 | Charles C Dinger | Rail anchor |
| US3423898A (en) * | 1966-07-28 | 1969-01-28 | Intern Enterprises Inc | Roof framing system |
| US3481635A (en) * | 1968-04-03 | 1969-12-02 | Intern Enterprises Inc | Universal roof bracket |
| US4124962A (en) * | 1977-07-15 | 1978-11-14 | Brown Company | Joist hanger |
| US4148164A (en) * | 1977-10-17 | 1979-04-10 | Humphrey Gerald A | Fascia board support |
| US4192623A (en) * | 1975-09-29 | 1980-03-11 | Borg Carl W | Adjustable joist hanger |
| US4223866A (en) * | 1977-05-10 | 1980-09-23 | Brown Company | Adjustable bracket |
| US4422279A (en) * | 1981-09-04 | 1983-12-27 | Powell John M | Method for constructing a reinforced foundation |
| US5092096A (en) * | 1990-12-13 | 1992-03-03 | Cornell James C | Temporary bridge joist support bracket |
| US5228261A (en) * | 1991-10-15 | 1993-07-20 | Watkins Robert P | Floor joist hanger |
| US5442887A (en) * | 1993-11-09 | 1995-08-22 | Welsh; Holden A. | Seat and anchor assembly for a roof truss and wooden joist |
| US5611189A (en) * | 1995-01-20 | 1997-03-18 | Fleck; Randy J. | Apparatus for hanging fascia board |
| US6131358A (en) * | 1997-08-29 | 2000-10-17 | Wise; Michael A. | Joist hanger and installation method |
| US20020134042A1 (en) * | 1999-07-23 | 2002-09-26 | Michael Bourque | Deck attachment bracket and method of attaching a deck to a building |
| US20050011157A1 (en) * | 2003-07-16 | 2005-01-20 | Lutz Robert W. | Truss anchor |
| US20060059846A1 (en) * | 1999-10-19 | 2006-03-23 | John Rice | Bracket for concrete forms |
-
2004
- 2004-01-19 CA CA002455376A patent/CA2455376A1/en not_active Abandoned
-
2005
- 2005-01-19 US US11/037,354 patent/US20050155307A1/en not_active Abandoned
Patent Citations (26)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US533659A (en) * | 1895-02-05 | Ceiling-supporter | ||
| US1728981A (en) * | 1927-04-30 | 1929-09-24 | Franklin N Ropp | Joist hanger for concrete buildings |
| US1785790A (en) * | 1928-08-14 | 1930-12-23 | Franklin N Ropp | Combination joist hanger and tie |
| US1785791A (en) * | 1928-12-17 | 1930-12-23 | Franklin N Ropp | Combination joist hanger and tie |
| US2013101A (en) * | 1934-03-30 | 1935-09-03 | Inglee Lewis | Furring clip |
| US2106084A (en) * | 1936-11-09 | 1938-01-18 | Reynolds Corp | Joist suspension |
| US2176450A (en) * | 1938-06-21 | 1939-10-17 | George F Barnett | Joist anchor and support |
| US2947119A (en) * | 1956-09-18 | 1960-08-02 | Jr Lawrence P Puckett | Anchored tie-down device for rafters |
| US3000145A (en) * | 1957-10-22 | 1961-09-19 | Advance Metal Products Inc | Truss anchor |
| US3267624A (en) * | 1963-05-31 | 1966-08-23 | Fenestra Inc | Composite panel with concrete backer and hanging members |
| US3338520A (en) * | 1965-08-16 | 1967-08-29 | Charles C Dinger | Rail anchor |
| US3423898A (en) * | 1966-07-28 | 1969-01-28 | Intern Enterprises Inc | Roof framing system |
| US3481635A (en) * | 1968-04-03 | 1969-12-02 | Intern Enterprises Inc | Universal roof bracket |
| US4192623A (en) * | 1975-09-29 | 1980-03-11 | Borg Carl W | Adjustable joist hanger |
| US4223866A (en) * | 1977-05-10 | 1980-09-23 | Brown Company | Adjustable bracket |
| US4124962A (en) * | 1977-07-15 | 1978-11-14 | Brown Company | Joist hanger |
| US4148164A (en) * | 1977-10-17 | 1979-04-10 | Humphrey Gerald A | Fascia board support |
| US4422279A (en) * | 1981-09-04 | 1983-12-27 | Powell John M | Method for constructing a reinforced foundation |
| US5092096A (en) * | 1990-12-13 | 1992-03-03 | Cornell James C | Temporary bridge joist support bracket |
| US5228261A (en) * | 1991-10-15 | 1993-07-20 | Watkins Robert P | Floor joist hanger |
| US5442887A (en) * | 1993-11-09 | 1995-08-22 | Welsh; Holden A. | Seat and anchor assembly for a roof truss and wooden joist |
| US5611189A (en) * | 1995-01-20 | 1997-03-18 | Fleck; Randy J. | Apparatus for hanging fascia board |
| US6131358A (en) * | 1997-08-29 | 2000-10-17 | Wise; Michael A. | Joist hanger and installation method |
| US20020134042A1 (en) * | 1999-07-23 | 2002-09-26 | Michael Bourque | Deck attachment bracket and method of attaching a deck to a building |
| US20060059846A1 (en) * | 1999-10-19 | 2006-03-23 | John Rice | Bracket for concrete forms |
| US20050011157A1 (en) * | 2003-07-16 | 2005-01-20 | Lutz Robert W. | Truss anchor |
Cited By (25)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20050161564A1 (en) * | 2003-06-03 | 2005-07-28 | Ganske Roger H. | Support bracket to suspend sheet material for a wall |
| US20070114347A1 (en) * | 2004-05-27 | 2007-05-24 | Ganske Roger H | Support bracket to suspend sheet material for a wall |
| US7578101B2 (en) | 2004-05-27 | 2009-08-25 | Roger Howard Ganske | Support bracket to suspend sheet material for a wall |
| GB2443483A (en) * | 2006-11-02 | 2008-05-07 | Victor Joseph Wigley | Joist Hanger with facility for damp-proofing |
| GB2443483B (en) * | 2006-11-02 | 2011-09-21 | Victor Joseph Wigley | Improvements relating to timber support and restraint in buildings |
| US20080202059A1 (en) * | 2007-02-27 | 2008-08-28 | Mccollough Daniel D | Floor joist hanger |
| GB2459935A (en) * | 2008-05-16 | 2009-11-18 | Victor Joseph Wigley | Joist end sleeve and joist collar for protecting joists within external masonry |
| US20110099932A1 (en) * | 2008-07-11 | 2011-05-05 | Roger Saulce | Panel interlocking system |
| US20100064626A1 (en) * | 2008-07-23 | 2010-03-18 | Lavern Kittlitz | Joist hanger for icf wall systems |
| US8051620B2 (en) * | 2008-07-23 | 2011-11-08 | Lavann ICF Hangers Inc. | Joist hanger for ICF wall systems |
| US9765805B2 (en) * | 2012-03-06 | 2017-09-19 | Gary J. Pond | Bracket assembly and systems |
| US20130232758A1 (en) * | 2012-03-06 | 2013-09-12 | Inter-Med, Inc. | Bracket Assembly and Systems |
| USRE48789E1 (en) * | 2013-12-14 | 2021-10-26 | Simpson Strong-Tie Company Inc. | Drywall joist hanger |
| US11920339B2 (en) | 2013-12-31 | 2024-03-05 | Columbia Insurance Company | Method of constructing a fire-resistive wall assembly |
| US20190284794A1 (en) * | 2013-12-31 | 2019-09-19 | Columbia Insurance Company | Hanger for fire separation wall |
| US11021867B2 (en) * | 2013-12-31 | 2021-06-01 | Columbia Insurance Company | Hanger for fire separation wall |
| US10316510B2 (en) * | 2013-12-31 | 2019-06-11 | Columbia Insurance Company | Hanger for fire separation wall |
| US11649626B2 (en) | 2013-12-31 | 2023-05-16 | Columbia Insurance Company | Hanger for fire separation wall |
| US9663938B2 (en) * | 2015-08-21 | 2017-05-30 | Columbia Insurance Company | Hanger for bracing panel |
| US11225787B2 (en) | 2018-06-06 | 2022-01-18 | Simpson Strong-Tie Company, Inc. | Drywall spacing joist hanger |
| US12534903B2 (en) | 2018-06-06 | 2026-01-27 | Simpson Strong-Tie Co. Inc. | Drywall spacing joist hanger |
| WO2022150931A1 (en) * | 2021-01-15 | 2022-07-21 | P & W Construction Materials and Consulting Ltd. | Brackets for insulated concrete forms and methods of manufacturing and installation thereof |
| US20240076866A1 (en) * | 2021-01-15 | 2024-03-07 | P & W Construction Materials and Consulting Ltd. | Brackets for insulated concrete forms and methods of manufacturing and installation thereof |
| US12546106B2 (en) | 2021-09-01 | 2026-02-10 | Simpson Strong-Tie Company Inc. | Drywall hanger |
| US20250333956A1 (en) * | 2024-04-30 | 2025-10-30 | Simpson Strong-Tie Company Inc. | Insulated Concrete Form Connector |
Also Published As
| Publication number | Publication date |
|---|---|
| CA2455376A1 (en) | 2005-07-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US20050155307A1 (en) | Hanger for insulated concrete system and method of installation thereof and method of installing a retrofit hanger in an insulated concrete | |
| US6199336B1 (en) | Metal wall framework and clip | |
| US5642597A (en) | Drywall mounting bracket | |
| US9038338B2 (en) | Insulated concrete form wall having a bracket attaching a rim joist thereto | |
| US7254919B2 (en) | Truss anchor | |
| US5519977A (en) | Joist reinforcing bracket | |
| US7178305B2 (en) | Hanger bracket | |
| US6625947B1 (en) | Insulated concrete wall system and method of making same | |
| US5692356A (en) | Insulated concrete wall tie system | |
| US5732524A (en) | Truss anchor | |
| US20030106280A1 (en) | Stud spacer | |
| US5228261A (en) | Floor joist hanger | |
| US20030029097A1 (en) | Siding and overhang attachment system | |
| MX2012006871A (en) | Seismic clip. | |
| MX2012003347A (en) | Bracket useful with sloped suspended ceiling systems. | |
| US20100064626A1 (en) | Joist hanger for icf wall systems | |
| US6668502B2 (en) | Ledger mould for building a ledger | |
| HU227931B1 (en) | Building acoustic structure | |
| US8276335B2 (en) | Attachment profile | |
| US6845594B2 (en) | Pre-manufactured joist and beam support for concrete walls | |
| EP1352133A1 (en) | A joist hanger | |
| GB2156398A (en) | Two-part joist-hanger | |
| US20060059846A1 (en) | Bracket for concrete forms | |
| CA3238064A1 (en) | Drywall spacing joist hanger | |
| WO2000043610A1 (en) | Building block retainer apparatus |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AS | Assignment |
Owner name: 1599717 ONTARIO LTD., ONTARIO Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:1391038 ONTARIO LTD.;REEL/FRAME:016198/0333 Effective date: 20040503 Owner name: 1391038 ONTARIO LTD., ONTARIO Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:TIMONY, PATRICK;REEL/FRAME:016198/0278 Effective date: 20040503 |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |