US1600081A - Wall construction - Google Patents
Wall construction Download PDFInfo
- Publication number
- US1600081A US1600081A US40859A US4085925A US1600081A US 1600081 A US1600081 A US 1600081A US 40859 A US40859 A US 40859A US 4085925 A US4085925 A US 4085925A US 1600081 A US1600081 A US 1600081A
- Authority
- US
- United States
- Prior art keywords
- ties
- beams
- wall
- cross
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title description 6
- 239000004567 concrete Substances 0.000 description 10
- 230000000284 resting effect Effects 0.000 description 4
- 239000000463 material Substances 0.000 description 2
- 239000011178 precast concrete Substances 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/06—Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
- E02B3/066—Quays
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0216—Cribbing walls
Definitions
- This invention relates to wall construction and has special reference to seawalls.
- the objects of the invention are to produce a wall which will have a wider base, per unit of material used, than'walls heretofore constructed thereby increasing the resistance to overturning forces, to reduce the form work employed, and to minimize the delays ordinarily due to storms and waves.
- One embodiment of the invention is illustrated in the accompanying drawings and will be hereinafter fully described, the novel features being particularly pointedout in the appended claims.
- Figure 1 is a plan view of a seawall showing different stages in the development
- Figure 2 is a front elevation of the same
- Figure 3 is a transverse vertical section
- Figure 4 is a detail perspective of a bottom cross tie
- Figure 5 is a similar view of an upper cross tie
- Figure 6 is a similar view of a longitudinal beam.
- a row of interlocking sheet piling 1 is driven along the line of the toe of the contemplated wall to a depth below the low water line and located where it will be likely to remain submerged in the sand.
- a capping wall 2 of concrete is then cast in place alon the top edge of the piling and embedding the same, as shown in Fig. 3.
- concrete footings 3 are cast to form the base supports for the back of the wall.
- the cross ties 6 are placed upon the beams in vertical alinement with the ties 5 and itwill be noted that the ties 6 are identical with the ties 5 in construction except that a recess 9 is formed in the underside of the tie 6 adjacent its rear end in order to engage over and lock with the rear beam. A second row of beams is then placed in position and this alternate arrangement of beams and ties is repeated until a crib of the desired height has been formed. It will be noted that the cross ties successively decrease in length upwardly and while the rear ends of the ties are in the same vertical plane, in any cross section of the crib, the front ends are in stepped relation, the structure thus far described presenting open spaces between the successive risers in the stepped front of the crib.
- a retaining wall comprising transverse crossties of precast concrete arranged in vertical series, precast concrete longitudinally extending beams resting on lower ties and supporting upper ties whereby both beams and ties will be spaced vertically, and
- a retaining Wall comprising vertical series of concrete cross ties having their front ends in stepped relation, concrete beams supported by lower cross ties near the ends of the ties and supporting upper cross ties, and bonding members uniting the front ends of the cross ties and the front beams in stepped form and closing the spaces between the front beams.
- a retaining Wall comprising a submerged line of sheet piling, a capping wall extending along and embedding the top of the piling, footings at the rear of the capping wall, concrete cross ties resting at their front ends upon the capping wall and at their rear ends upon the respective footings, longitudinal concrete beams resting upon the cross ties, series of alternating ties and beams of concrete superposed upon the firstmentioned beams, the ties regularly decreasing in length upwardly whereby their front ends and the front beams are disposed in stepped relation, and bonding members closing the spaces between the front ends :of the tics and the front beams and integrally connecting said beams and ties.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Revetment (AREA)
Description
R. B. TUFTS WAL'Z CONSTRUCTION Filed July 1..
Sept. 14 1926.-
Patented Sept. 14, 1926.
UNITED STATES ROBERT n. TUFTS, OF ATLANTA, GEORGIA.
WALL CONSTRUCTION.
Application filed July 1,
This invention relates to wall construction and has special reference to seawalls. The objects of the invention are to produce a wall which will have a wider base, per unit of material used, than'walls heretofore constructed thereby increasing the resistance to overturning forces, to reduce the form work employed, and to minimize the delays ordinarily due to storms and waves. One embodiment of the invention is illustrated in the accompanying drawings and will be hereinafter fully described, the novel features being particularly pointedout in the appended claims.
In the accompanying drawings, Figure 1 is a plan view of a seawall showing different stages in the development;
Figure 2 is a front elevation of the same;
Figure 3 is a transverse vertical section;
Figure 4 is a detail perspective of a bottom cross tie Figure 5 is a similar view of an upper cross tie;
Figure 6 is a similar view of a longitudinal beam.
In the practice of the invention, a row of interlocking sheet piling 1 is driven along the line of the toe of the contemplated wall to a depth below the low water line and located where it will be likely to remain submerged in the sand. A capping wall 2 of concrete is then cast in place alon the top edge of the piling and embedding the same, as shown in Fig. 3. At the proper distance back of the capping wall and at equal intervals along the length of the proposed wall or embankment, concrete footings 3 are cast to form the base supports for the back of the wall. Previous to or simultaneous with the described operations, beams, as shown at 5 and 6, of reenforced concrete are cast in molds so that by the time the capping Wall 2 and the footings 3 have set, the ties and beams will be thoroughly hardened and ready to be placed in position. The lowest tie, 5, is formed with a recess 7 in its under side at its front end whereby it is adapted to rest on the capping wall and abut the rear side thereof, and a tie is placed in position at each footing 3 with its rear end resting centrally upon the footing and its front supported by the capping wall, as shown in Figure 3, the proportions of the parts preferably being such that the topof the capping wall is below the mean low tide such as shown at 4, and cross ties, such 1925. Serial No. 40,859. I
level while tops of the cross tiesare above such level. In the upper side of the cross tie 1 overhanging the sides of the ties, it being economically advantageous to have the rear beams bridge only the alternate bays definedv V by the ties. After the beams 4 are in place,
the cross ties 6 are placed upon the beams in vertical alinement with the ties 5 and itwill be noted that the ties 6 are identical with the ties 5 in construction except that a recess 9 is formed in the underside of the tie 6 adjacent its rear end in order to engage over and lock with the rear beam. A second row of beams is then placed in position and this alternate arrangement of beams and ties is repeated until a crib of the desired height has been formed. It will be noted that the cross ties successively decrease in length upwardly and while the rear ends of the ties are in the same vertical plane, in any cross section of the crib, the front ends are in stepped relation, the structure thus far described presenting open spaces between the successive risers in the stepped front of the crib.
With a suflicient length of the crib or skeleton wall completed, forms of false work are placed in position at the front ends of the ties and concrete is poured into the same to form the intermediate steps 10 and the top pair of steps 11, earth being filled in back of the steps, after the poured steps have set, to cover from view all the back beams and all the cross ties except the stepped ends that project through the front. The poured steps automatically key themselves to and between the precast steps and completely close the spaces in the front of the wall between the beams and cross ties. Inasmuch as the successive sets of cross ties decrease in length by equal amounts, the front face of the finished wall has the effect of ordinary concrete steps.
It will be readily seen that this construction gives a wider base than is obtainable from the same amount of material with the Letters-Patent, is
1. A retaining wall comprising transverse crossties of precast concrete arranged in vertical series, precast concrete longitudinally extending beams resting on lower ties and supporting upper ties whereby both beams and ties will be spaced vertically, and
longitudinally extending beams poured between the first-mentioned beams adjacent the front ends of the ties whereby to close the spaces in the front of the Wall and intimately unite the beams and ties therein.
2. A retaining Wall comprising vertical series of concrete cross ties having their front ends in stepped relation, concrete beams supported by lower cross ties near the ends of the ties and supporting upper cross ties, and bonding members uniting the front ends of the cross ties and the front beams in stepped form and closing the spaces between the front beams.
3. A retaining Wall comprising a submerged line of sheet piling, a capping wall extending along and embedding the top of the piling, footings at the rear of the capping wall, concrete cross ties resting at their front ends upon the capping wall and at their rear ends upon the respective footings, longitudinal concrete beams resting upon the cross ties, series of alternating ties and beams of concrete superposed upon the firstmentioned beams, the ties regularly decreasing in length upwardly whereby their front ends and the front beams are disposed in stepped relation, and bonding members closing the spaces between the front ends :of the tics and the front beams and integrally connecting said beams and ties.
In testimony whereof, I have signed this specification.
ROBERT B, rUFT-sf
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US40859A US1600081A (en) | 1925-07-01 | 1925-07-01 | Wall construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US40859A US1600081A (en) | 1925-07-01 | 1925-07-01 | Wall construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US1600081A true US1600081A (en) | 1926-09-14 |
Family
ID=21913364
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US40859A Expired - Lifetime US1600081A (en) | 1925-07-01 | 1925-07-01 | Wall construction |
Country Status (1)
| Country | Link |
|---|---|
| US (1) | US1600081A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4384810A (en) * | 1980-05-23 | 1983-05-24 | Herwig Neumann | Locking beam to form a three-dimensional lattice in a construction system for plantable shoring walls |
-
1925
- 1925-07-01 US US40859A patent/US1600081A/en not_active Expired - Lifetime
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4384810A (en) * | 1980-05-23 | 1983-05-24 | Herwig Neumann | Locking beam to form a three-dimensional lattice in a construction system for plantable shoring walls |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US2313363A (en) | Retaining wall and block for the same | |
| US4269537A (en) | Revetment unit | |
| US3802204A (en) | Retaining wall and method for construction of the same | |
| DK148328B (en) | PROCEDURE FOR BUILDING A BUILDING CONSTRUCTION, BUILDING ELEMENT FOR USE BY THE PROCEDURE AND BUILDING CONSTRUCTION PROCEDURED BY THE PROCEDURE AND THE BUILDING ELEMENT | |
| US1933483A (en) | Wall construction | |
| US1746566A (en) | Sewer construction | |
| Young | The Gordion campaign of 1967 | |
| US1600081A (en) | Wall construction | |
| US3225548A (en) | Retaining wall and section thereof | |
| US2466343A (en) | Jetty | |
| US1083289A (en) | Method of building concrete dock-walls. | |
| US2159556A (en) | Cribbing construction | |
| US1693311A (en) | Sea wall and method of making same | |
| US1636114A (en) | Pavement | |
| CN211646245U (en) | High-pile wharf and breakwater structure | |
| US2439606A (en) | Retaining sea wall | |
| US1952380A (en) | Wall structure | |
| US1423884A (en) | Ocean pier | |
| US1983772A (en) | Concrete mat | |
| US1487098A (en) | Concrete floor construction | |
| US782557A (en) | Floatable concrete pier. | |
| US1633211A (en) | Roadway embankment | |
| US1637065A (en) | Retaining-wall construction | |
| US4096703A (en) | Concrete constructional members | |
| US1809636A (en) | Dam |