[go: up one dir, main page]

TWI851524B - Precasting structure and construction method thereof - Google Patents

Precasting structure and construction method thereof Download PDF

Info

Publication number
TWI851524B
TWI851524B TW113110684A TW113110684A TWI851524B TW I851524 B TWI851524 B TW I851524B TW 113110684 A TW113110684 A TW 113110684A TW 113110684 A TW113110684 A TW 113110684A TW I851524 B TWI851524 B TW I851524B
Authority
TW
Taiwan
Prior art keywords
precast
section
precast beam
column
steel bar
Prior art date
Application number
TW113110684A
Other languages
Chinese (zh)
Other versions
TW202538129A (en
Inventor
尹衍樑
曹昌盛
Original Assignee
潤弘精密工程事業股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 潤弘精密工程事業股份有限公司 filed Critical 潤弘精密工程事業股份有限公司
Priority to TW113110684A priority Critical patent/TWI851524B/en
Priority to US18/790,797 priority patent/US20250297470A1/en
Application granted granted Critical
Publication of TWI851524B publication Critical patent/TWI851524B/en
Publication of TW202538129A publication Critical patent/TW202538129A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present disclosure relates to a precasting structure and a construction method thereof. The precasting structure includes a first precasting beam and a second precasting beam. The first precasting beam includes a first section, a second section and a first rebar. The second section is separate from the first section and a gap is formed therebetween. The first rebar penetrates through and connects the first section and the second section along a length direction. The second precasting beam aligns with the first precasting beam and being adjacent to the second section of the first precasting beam. The second precasting beam is coupled to the first rebar of the first precasting beam.

Description

預鑄結構及其施工方法 Precast structure and its construction method

本揭露係關於一種建築結構及其施工方法,尤其是關於一種預鑄結構及其施工方法。 This disclosure relates to a building structure and a construction method thereof, and in particular to a precast structure and a construction method thereof.

傳統現場澆置的鋼筋混凝土(RC)建築物構築方式需等待建築物每一層混凝土的強度到達預定強度後方能逐層向上施工,耗費時間,不僅如此,由於需有大量工人於施工現場捆紮、組模及灌漿等流程,因此施工品質掌控不易,易受到工人素質及天候影響。相較之下,鋼骨鋼筋混凝土(SRC)建築物構築方式可大幅減少工程時間,然而,若全部結構梁與結構柱皆採用鋼骨鋼筋混泥土結構,將耗費大量鋼材,提高建置成本。為解決上述問題,預鑄工法應運而生。 The traditional on-site poured reinforced concrete (RC) building construction method requires waiting for the strength of each layer of concrete in the building to reach the predetermined strength before construction can be carried out layer by layer, which is time-consuming. In addition, since a large number of workers are required to tie, assemble molds and pour grout at the construction site, it is difficult to control the construction quality, which is easily affected by the quality of workers and weather. In contrast, the steel frame reinforced concrete (SRC) building construction method can greatly reduce the construction time. However, if all structural beams and columns are made of steel frame reinforced concrete structure, a large amount of steel will be consumed, increasing the construction cost. To solve the above problems, the precast method came into being.

預鑄工法係指一種在工廠中生產,將混凝土澆築到可重複使用的模具中,在受控環境下凝固硬化,並運送到建築工地安裝之工法。工廠生產具有環境穩定,不受天候影響且技術工需求小以及作業標準化之優點。在工地現場部分,則利用機械化設備進行組立吊裝工作,且免搭外部鷹架,外牆與裝修同步進行,有效縮短工期。由於工程現場不使用傳統本模板,有助於森林資源保存且環保並且可保持工地現場整齊乾淨。預鑄 工法經常使用於預鑄柱或預鑄梁等承受負載的較重要建築物結構。 Precasting refers to a method of pouring concrete into reusable molds in a factory, solidifying and hardening it in a controlled environment, and transporting it to the construction site for installation. Factory production has the advantages of a stable environment, not being affected by weather, requiring less skilled workers, and standardized operations. On-site, mechanized equipment is used for assembly and hoisting, and external scaffolding is not required. The exterior wall and decoration are carried out simultaneously, effectively shortening the construction period. Since traditional formwork is not used on the construction site, it helps preserve forest resources and is environmentally friendly, and can keep the construction site neat and clean. Precasting is often used for more important building structures that bear loads, such as precast columns or precast beams.

此外,一般習知之建築物之結構構築方式,通常係在建築現場按照建築物預定之占地面積及預訂樓層數或高度,由低層向高層依照逐層完成建構預定占地面積之單層結構之方式構築建築物。此一習知之建構方式之缺點在於,由於一次必須完成整個預定占地面積之一層樓層結構(包括完成所有梁、柱及樓層板等結構),因此在建築現場的作業動線安排(包含吊裝結構、運送物料及人員進出等工作)必定較為複雜,且隨著建築結構體樓層開始往上逐層施工,在高度逐漸增加的狀況下,更不利於現場作業人員、吊車、運載車輛、物料運送等等的順暢動線安排。因此,囿於此種習知建築物建構方式,無法有效縮短完成一建築物的工期。 In addition, the commonly known method of building structure construction is usually to construct the building on the construction site according to the planned floor area and the planned number of floors or height of the building, and to construct a single-story structure with a planned floor area layer by layer from the low floor to the high floor. The disadvantage of this conventional construction method is that since the entire floor structure of a predetermined area must be completed at one time (including the completion of all beams, columns and floor slabs, etc.), the work flow arrangement on the construction site (including hoisting structures, transporting materials and personnel entry and exit, etc.) must be more complicated. Moreover, as the building structure begins to be constructed layer by layer, the height gradually increases, which is more detrimental to the smooth flow arrangement of on-site workers, cranes, transport vehicles, material transportation, etc. Therefore, due to this conventional building construction method, it is impossible to effectively shorten the construction period of a building.

特別是關於高科技廠房的建造,由於投資金額龐大且高科技產品替代週期快速,因此在建構新廠房時,均要求能快速完成廠房以期能盡速開始完成內部無塵室或潔淨室的建構,從而機器設備能快速進駐安裝,以儘早開始生產例如晶片等高科技產品。以預鑄式建築為例,在工程現場,施工者採用塔吊的方式或用吊車將預鑄柱及預鑄梁放置其預定設置位置。然而,由於無論是塔吊或吊車都有其承載限制或是運載距離限制,針對重量較大的預鑄柱及預鑄梁,吊裝的成本和困難度大幅增高。因此,上述之習知建築物構建方式顯然不能滿足快速施工、縮短工期的要求。 Especially in the construction of high-tech factories, due to the huge investment amount and the fast replacement cycle of high-tech products, when building a new factory, it is required to complete the factory quickly so that the construction of the internal clean room or clean room can be completed as soon as possible, so that the machinery and equipment can be quickly installed to start the production of high-tech products such as chips as soon as possible. Taking precast buildings as an example, at the construction site, the construction workers use tower cranes or cranes to place precast columns and precast beams in their predetermined locations. However, since both tower cranes and cranes have their load-bearing limitations or transportation distance limitations, the cost and difficulty of hoisting heavier precast columns and precast beams are greatly increased. Therefore, the above-mentioned conventional building construction method obviously cannot meet the requirements of rapid construction and shortened construction period.

有鑑於上述習知技術之缺點,如何能夠改變習知的建築物施工方式,以期能夠有效縮短工期完成高科技廠房之建置,實為產業界所長久企盼。 In view of the shortcomings of the above-mentioned known technologies, how to change the known building construction methods in order to effectively shorten the construction period to complete the construction of high-tech factories has long been expected by the industry.

緣是,為達上述目的,本揭露之一項態樣係關於一種預鑄 結構施工方法,包括:提供依序間隔排列之一第一預鑄柱、一第二預鑄柱及一第三預鑄柱;提供一第一預鑄梁,第一預鑄梁包括一第一區段、與第一區段間隔設置的一第二區段、及貫穿第一區段與第二區段的一第一鋼筋;吊裝第一預鑄梁,以使得第一預鑄梁跨越設置於第一預鑄柱及第二預鑄柱上,其中,第一區段的兩端部分別設置於第一預鑄柱及第二預鑄柱彼此相鄰的一第一端及一第二端上,第二區段設置於第二預鑄柱的與第二端相對的一第三端上;提供一第二預鑄梁,第二預鑄梁包括一第一端部以及相對於第一端部之一第二端部;吊裝第二預鑄梁,以使得第二預鑄梁的第一端部設置於一臨時支撐架上,並使得第二預鑄梁的第二端部設置於第三預鑄柱的一第四端上;及移動第二預鑄梁,以使得第二預鑄梁的第一端部與第一預鑄梁中之第一鋼筋之伸出第一預鑄梁中之第二區段的一銜接端耦接。 Therefore, in order to achieve the above-mentioned purpose, one aspect of the present disclosure is related to a precast structure construction method, including: providing a first precast column, a second precast column and a third precast column arranged in sequence; providing a first precast beam, the first precast beam including a first section, a second section arranged at intervals from the first section, and a first steel bar penetrating the first section and the second section; hoisting the first precast beam so that the first precast beam is arranged across the first precast column and the second precast column, wherein the two ends of the first section are respectively arranged at a position adjacent to the first precast column and the second precast column. A first end and a second end are provided, and the second section is provided on a third end of the second precast column opposite to the second end; a second precast beam is provided, and the second precast beam includes a first end and a second end opposite to the first end; the second precast beam is hoisted so that the first end of the second precast beam is provided on a temporary support frame, and the second end of the second precast beam is provided on a fourth end of the third precast column; and the second precast beam is moved so that the first end of the second precast beam is coupled with a connecting end of the first steel bar in the first precast beam extending out of the second section in the first precast beam.

本揭露之另一項態樣係關於一種預鑄結構,其包括一第一預鑄梁及一第二預鑄梁。第一預鑄梁包括一第一區段、一第二區段及一第一鋼筋。第二區段與第一區段間隔分離以形成一間隙於第一區段以及第二區段之間。第一鋼筋沿預鑄結構之長度方向,連接並貫穿第一區段及第二區段。第二預鑄梁與第一預鑄梁沿其長度方向大致對齊,並鄰近第一預鑄梁之第二區段,第二預鑄梁與第一預鑄梁之第一鋼筋耦合。 Another aspect of the present disclosure is related to a precast structure, which includes a first precast beam and a second precast beam. The first precast beam includes a first section, a second section and a first steel bar. The second section is separated from the first section to form a gap between the first section and the second section. The first steel bar connects and penetrates the first section and the second section along the length direction of the precast structure. The second precast beam is roughly aligned with the first precast beam along its length direction and is adjacent to the second section of the first precast beam. The second precast beam is coupled with the first steel bar of the first precast beam.

100:第一預鑄梁 100: The first pre-cast beam

110:第一區段 110: Section 1

111:第一端部 111: First end

112:第二端部 112: Second end

114:箍筋彎勾 114: Stirrup bend hook

120:第二區段 120: Second section

130:第一鋼筋 130: First steel bar

132:銜接端 132:Connection terminal

134:自由端 134: Free end

200:第二預鑄梁 200: Second pre-cast beam

210:本體 210:Entity

211:第一端部 211: First end

212:第二端部 212: Second end

214:貫穿槽 214:Through slot

216:箍筋彎勾 216: Stirrup bend hook

230:第二鋼筋 230: Second steel bar

231:第一端 231: First end

232:第二端 232: Second end

240:第一續接器 240: First connector

300:第三預鑄梁 300: The third pre-cast beam

310:一端 310: One end

400:纜繩 400: Cable

600:第一預鑄柱 600: First pre-cast column

610:第一本體 610: The first entity

615:頂面 615: Top

620:第一組鋼筋 620: The first set of steel bars

630:第一端 630: First end

700:第二預鑄柱 700: Second pre-cast column

710:第二本體 710: Second body

715:頂面 715: Top

720:第二組鋼筋 720: The second set of steel bars

730:第二端 730: Second end

740:第三端 740: The third end

750:第六端 750: The sixth end

760:角托 760: Corner bracket

770:第七端 770: The seventh end

790:角托 790: Corner bracket

795:頂面 795: Top

800:第三預鑄柱 800: The third pre-cast column

810:第三本體 810: The third entity

815:頂面 815: Top

820:第二續接器 820: Second connector

830:第三組鋼筋 830: The third set of steel bars

840:第四端 840: The fourth end

850:第五端 850: The fifth end

860:第一主筋 860: First main reinforcement

870:第二主筋 870: Second main reinforcement

880:後接柱鋼筋 880: Rear column reinforcement

900:臨時支撐架 900: Temporary support frame

910:頂部表面 910: Top surface

920:臨時支撐架 920: Temporary support frame

G:間隙 G: Gap

X:軸向 X: Axial direction

Y:軸向 Y: Axis

Z:軸向 Z: Axial direction

a,a',b,b':預鑄梁 a,a',b,b': pre-cast beams

以下附圖之描述僅是出於例示性目的,並非欲以任何方式限制本揭露之範疇。 The following descriptions of the attached figures are for illustrative purposes only and are not intended to limit the scope of this disclosure in any way.

圖1為根據本揭露一實施的施工流程示意圖一。 Figure 1 is a schematic diagram of the construction process implemented according to the present disclosure.

圖2為根據本揭露上述實施例的施工流程示意圖二。 Figure 2 is a schematic diagram of the construction process according to the above embodiment of the present disclosure.

圖3為根據本揭露上述實施例的施工流程示意圖三。 Figure 3 is a schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure.

圖4為根據本揭露上述實施例的施工流程示意圖四。 Figure 4 is a schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure.

圖5為根據本揭露上述實施例的施工流程示意圖五。 Figure 5 is a schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure.

圖6為根據本揭露上述實施例的施工流程示意圖六。 Figure 6 is a schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure.

圖7為根據本揭露上述實施例的施工流程示意圖七。 Figure 7 is a schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure.

圖8為圖7之線段8-8之右側視圖。 Figure 8 is a right side view of line segment 8-8 in Figure 7.

圖9A為習知採階梯式退吊步驟的示意圖。 Figure 9A is a schematic diagram of the known step-by-step lifting and retraction steps.

圖9B為根據本揭露上述實施例採垂直退吊步驟的示意圖。 FIG. 9B is a schematic diagram of the vertical retraction step according to the above-mentioned embodiment of the present disclosure.

下文將參照圖式詳細描述本揭露的實施方式,其包含多種實施例。應注意的是,本案實施方式的內容僅用於例示本揭露的一種具體態樣,並非限制本案所請揭露的範圍。圖式中各元件的尺寸大小及相對比例僅用以示意。除非明確界定元件的尺寸及比例關係,則非用以限定本案之範疇。 The following will describe the implementation of the present disclosure in detail with reference to the drawings, which includes multiple implementation examples. It should be noted that the content of the implementation of this case is only used to illustrate a specific aspect of the present disclosure, and does not limit the scope of the present disclosure. The size and relative proportion of each component in the figure are only for illustration. Unless the size and proportion relationship of the component are clearly defined, it is not used to limit the scope of the present case.

圖1為根據本揭露一實施例的施工流程示意圖一。首先,提供沿著X軸向依序間隔排列之一第一預鑄柱600、一第二預鑄柱700及一第三預鑄柱800。 FIG. 1 is a schematic diagram of the construction process according to an embodiment of the present disclosure. First, a first pre-cast column 600, a second pre-cast column 700 and a third pre-cast column 800 are provided, which are arranged in sequence and spaced along the X-axis.

第一預鑄柱600包含一第一本體610及一第一組鋼筋620。第一本體610由混凝土包覆箍筋等所構成。第一組鋼筋620,係垂直設置之柱鋼筋組,其依設計間隔設置於第一本體610內,並自第一本體610的一頂面615向上(Y軸向)延伸。在本實施例中,第一組鋼筋620僅以兩條鋼筋為示例,在本揭露一些實施例中,第一組鋼筋620的數目為多個,例 如十二條或更多。此外,第一預鑄柱600具有一第一端630,其面向第二預鑄柱700。 The first precast column 600 includes a first body 610 and a first set of steel bars 620. The first body 610 is composed of concrete-wrapped stirrups and the like. The first set of steel bars 620 is a vertically arranged column steel bar group, which is arranged in the first body 610 according to the designed interval and extends upward (in the Y-axis direction) from a top surface 615 of the first body 610. In this embodiment, the first set of steel bars 620 is only exemplified by two steel bars. In some embodiments disclosed in the present invention, the number of the first set of steel bars 620 is multiple, for example, twelve or more. In addition, the first precast column 600 has a first end 630, which faces the second precast column 700.

第二預鑄柱700包含一第二本體710及一第二組鋼筋720。第二本體710由混凝土包覆箍筋等所構成。第二組鋼筋720,係垂直設置之柱鋼筋組,其依設計間隔設置於第二本體710內,並自第二本體710的頂面715向上(Y軸向)延伸。在本實施例中,第二組鋼筋720僅以兩條鋼筋為示例,在其他實施例中,第二組鋼筋720的數目為多個,例如十二條或更多。第二預鑄柱700具有沿X軸向彼此相對的一第二端730及一第三端740。第二預鑄柱700之第二端730面向於第一預鑄柱600的第一端630,第二預鑄柱700之第三端740面向第三預鑄柱800。在本實施例之施工方法包括設置一角托790(或稱角隅托架)於第二預鑄柱700的第三端740的外側並朝向第三預鑄柱800,並使得角托790之一頂面795與第二預鑄柱700的第二本體710的頂面715大致齊平。在本實施例中,複數個三角形的角托790沿著Z軸向平行排列並設置於第二預鑄柱700的第三端740的側面上。 The second precast column 700 includes a second body 710 and a second set of steel bars 720. The second body 710 is composed of concrete-wrapped stirrups and the like. The second set of steel bars 720 is a vertically arranged column steel bar group, which is arranged in the second body 710 according to the designed interval and extends upward (in the Y-axis direction) from the top surface 715 of the second body 710. In this embodiment, the second set of steel bars 720 is only exemplified by two steel bars. In other embodiments, the number of the second set of steel bars 720 is multiple, for example, twelve or more. The second precast column 700 has a second end 730 and a third end 740 opposite to each other along the X-axis. The second end 730 of the second precast column 700 faces the first end 630 of the first precast column 600, and the third end 740 of the second precast column 700 faces the third precast column 800. The construction method in this embodiment includes setting an angle bracket 790 (or corner bracket) on the outer side of the third end 740 of the second precast column 700 and facing the third precast column 800, and making a top surface 795 of the angle bracket 790 roughly flush with the top surface 715 of the second body 710 of the second precast column 700. In this embodiment, a plurality of triangular angle brackets 790 are arranged in parallel along the Z axis and are set on the side surface of the third end 740 of the second precast column 700.

第三預鑄柱800包含一第三本體810及一第三組鋼筋830。類似地,第三本體810由混凝土包覆箍筋等所構成。第三預鑄柱800具有沿X軸向彼此相對的一第四端840及一第五端850。第三預鑄柱800的第四端840面向第二預鑄柱700的第三端740。第三組鋼筋830,係垂直設置之柱鋼筋組,其依設計設置於間隔設置於第三本體810中,並包括一第一主筋860與一第二主筋870。在本實施例中,第三預鑄柱800中的第一主筋860鄰近第三預鑄柱800之第五端850,並延伸出第三預鑄柱800的第三本體810的一頂面815。第三預鑄柱800中的第二主筋870鄰近第三預鑄柱800之第四端840,並且其頂端被完全埋設於第三預鑄柱800中。在本實施例 中,第三預鑄柱800鄰近第四端840的第二主筋870的頂端更進一步設有暴露於頂面815外的一第二續接器820。在本實施例之圖式中,第一主筋860與第二主筋870僅分別以一條為示例。在其他實施例中,第一主筋860與第二主筋870的數目可為為多個,例如各為六條或更多。 The third precast column 800 includes a third body 810 and a third set of steel bars 830. Similarly, the third body 810 is composed of concrete-wrapped stirrups. The third precast column 800 has a fourth end 840 and a fifth end 850 that are opposite to each other along the X-axis. The fourth end 840 of the third precast column 800 faces the third end 740 of the second precast column 700. The third set of steel bars 830 is a vertically arranged column steel bar group, which is arranged at intervals in the third body 810 according to the design, and includes a first main bar 860 and a second main bar 870. In this embodiment, the first main rib 860 in the third precast column 800 is adjacent to the fifth end 850 of the third precast column 800 and extends out of a top surface 815 of the third body 810 of the third precast column 800. The second main rib 870 in the third precast column 800 is adjacent to the fourth end 840 of the third precast column 800 and its top end is completely buried in the third precast column 800. In this embodiment, the top end of the second main rib 870 adjacent to the fourth end 840 of the third precast column 800 is further provided with a second connector 820 exposed outside the top surface 815. In the drawings of this embodiment, only one of the first main rib 860 and the second main rib 870 is used as an example. In other embodiments, the number of the first main ribs 860 and the second main ribs 870 may be multiple, for example, six or more each.

圖2為根據本揭露上述實施例的施工流程示意圖二。如圖2所示,第一預鑄梁100包括一第一區段110、一第二區段120及一第一鋼筋130。第一區段110與第二區段120以一間隙G間隔分離設置。第一鋼筋130沿第一預鑄梁100結構之長度方向(即圖2之X軸向)貫穿並同時連接第一區段110及第二區段120。第一鋼筋130遠離於第二預鑄柱700的一自由端134穿出第一區段110並於第一預鑄柱600一側邊之上方向上延伸(Y軸向)。第一鋼筋130相對於該自由端134的一銜接端132,自第一預鑄梁100中之第二區段120之一端面向外伸出。本實施例的圖式僅以一條第一鋼筋130作為示例,在實際操作上,第一鋼筋130一般為沿Z軸向延伸排列的複數條鋼筋。 FIG. 2 is a second schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure. As shown in FIG. 2 , the first pre-cast beam 100 includes a first section 110, a second section 120 and a first steel bar 130. The first section 110 and the second section 120 are separated and arranged with a gap G. The first steel bar 130 penetrates and simultaneously connects the first section 110 and the second section 120 along the length direction of the first pre-cast beam 100 structure (i.e., the X-axis direction of FIG. 2 ). A free end 134 of the first steel bar 130 far from the second pre-cast column 700 passes through the first section 110 and extends in a direction above a side of the first pre-cast column 600 (Y-axis direction). A connecting end 132 of the first steel bar 130, which is opposite to the free end 134, extends outward from an end surface of the second section 120 in the first pre-cast beam 100. The figure of this embodiment only takes one first steel bar 130 as an example. In actual operation, the first steel bar 130 is generally a plurality of steel bars arranged and extending along the Z axis.

在本實施例中,以一吊車(未繪示)吊裝第一預鑄梁100,以使得第一預鑄梁100跨越並以其兩端(即第一端部111與第二端部112)設置於第一預鑄柱600及第二預鑄柱700上。在本實施例中,吊車的纜繩400係綑綁於自第一預鑄梁100之第一區段110伸出的箍筋彎勾114,以吊起第一預鑄梁100。在其他實施例中,吊車的纜繩400亦可直接環繞第一區段110的下方並經固定後而直接吊起第一預鑄梁100。第一區段110的相對兩端部(即第一端部111與第二端部112)分別設置於第一預鑄柱600及第二預鑄柱700彼此相鄰的第一端630及第二端730上。第二區段120設置於第二預鑄柱700的與第二端730相對的第三端740上。間隙G此時位 於第二預鑄柱700的第二本體710上方,並可容納第二預鑄柱700之第二組鋼筋720而不會彼此干涉。在本實施例中,吊裝第一預鑄梁100之步驟更進一步包含使第一預鑄梁100的第二區段120的至少一部分位於固定在第二預鑄柱700的側邊之角托790的頂面795上。換句話說,第一預鑄梁100的第二區段120的一部分設置在第二本體710上,而其另一部分設置在角托790上。藉由角托790的設置,可增加第二區段120設置於第二預鑄柱700上的面積,提升穩固性。在其他實施例中,亦可於第一預鑄柱600的第一端630及第二預鑄柱700的第二端730分別設置其他角托(未繪示)。 In this embodiment, a crane (not shown) is used to hoist the first pre-cast beam 100, so that the first pre-cast beam 100 spans and is disposed at its two ends (i.e., the first end 111 and the second end 112) on the first pre-cast column 600 and the second pre-cast column 700. In this embodiment, the cable 400 of the crane is tied to the stirrup hook 114 extending from the first section 110 of the first pre-cast beam 100 to hoist the first pre-cast beam 100. In other embodiments, the cable 400 of the crane can also be directly wrapped around the bottom of the first section 110 and fixed to directly hoist the first pre-cast beam 100. The opposite ends of the first section 110 (i.e., the first end 111 and the second end 112) are respectively disposed on the first end 630 and the second end 730 of the first precast column 600 and the second precast column 700, which are adjacent to each other. The second section 120 is disposed on the third end 740 of the second precast column 700, which is opposite to the second end 730. The gap G is now located above the second body 710 of the second precast column 700, and can accommodate the second set of steel bars 720 of the second precast column 700 without interfering with each other. In this embodiment, the step of suspending the first precast beam 100 further includes positioning at least a portion of the second section 120 of the first precast beam 100 on the top surface 795 of the angle bracket 790 fixed to the side of the second precast column 700. In other words, a portion of the second section 120 of the first pre-cast beam 100 is disposed on the second body 710, and another portion thereof is disposed on the angle bracket 790. By disposing the angle bracket 790, the area of the second section 120 disposed on the second pre-cast column 700 can be increased, thereby improving stability. In other embodiments, other angle brackets (not shown) can also be disposed on the first end 630 of the first pre-cast column 600 and the second end 730 of the second pre-cast column 700, respectively.

圖3為根據本揭露上述實施的施工流程示意圖三。在本實施例中,提供一臨時支撐架900於第二預鑄柱700及第三預鑄柱800之間的地面上,且臨時支撐架900的頂部表面910大致上與第二預鑄柱700的頂面715以及角托790的頂面795齊平。 FIG3 is a third schematic diagram of the construction process according to the above implementation of the present disclosure. In this embodiment, a temporary support frame 900 is provided on the ground between the second precast column 700 and the third precast column 800, and the top surface 910 of the temporary support frame 900 is substantially flush with the top surface 715 of the second precast column 700 and the top surface 795 of the angle bracket 790.

圖4為根據本揭露上述實施例的施工流程示意圖四。本實施例提供一第二預鑄梁200,其包括一本體210、一第二鋼筋230及一第一續接器240。第二預鑄梁200之本體210具有沿第二預鑄梁200之長度方向(即圖中所示之X軸向)延伸的預先設置之一貫穿槽214,並包括彼此相對的一第一端部211以及一第二端部212。在本實施例中,第一續接器240埋入於第一端部211內的貫穿槽214中。第二鋼筋230自該第二端部212伸入第二端部212中,使其第一端231伸入於本體210之貫穿槽214中,以與第一續接器240固接。第二鋼筋230的相對第二端232朝向遠離第一預鑄梁100的方向延伸出本體210外一段距離後,向上(Y軸向)折彎。 FIG4 is a fourth schematic diagram of the construction process according to the above-mentioned embodiment of the present disclosure. The present embodiment provides a second pre-cast beam 200, which includes a body 210, a second steel bar 230 and a first connector 240. The body 210 of the second pre-cast beam 200 has a pre-set through-slot 214 extending along the length direction of the second pre-cast beam 200 (i.e., the X-axis direction shown in the figure), and includes a first end 211 and a second end 212 opposite to each other. In the present embodiment, the first connector 240 is embedded in the through-slot 214 in the first end 211. The second steel bar 230 extends from the second end 212 into the second end 212, so that its first end 231 extends into the through-slot 214 of the body 210 to be fixedly connected to the first connector 240. The second end 232 of the second steel bar 230 extends a distance away from the first pre-cast beam 100 outside the main body 210 and then bends upward (in the Y-axis direction).

本實施例經由吊裝第二預鑄梁200,以使得第二預鑄梁200的第一端部211設置於臨時支撐架900的頂部表面910上,並使得第二預鑄 梁200的第二端部212設置於第三預鑄柱800的第四端840上以及第三預鑄柱800中的第二主筋870頂端之上方。此時,第二預鑄梁200與第一預鑄梁100沿其長度方向(X軸向)大致對齊,並且第二預鑄梁200之第一端部211鄰近第一預鑄梁100之第二區段120。本實施例係透過吊車的纜繩400係綑綁於自第二預鑄梁200之本體210上方伸出的箍筋彎勾216,以吊起第二預鑄梁200。需要注意的是,雖然第二預鑄梁200的第二端部212位於第三預鑄柱800的第四端840上以及第三預鑄柱800中的第二主筋870頂端之上方,但由於第二主筋870及第二續接器820係埋設於第三本體810內,因此第二預鑄梁200之吊裝不會與第三預鑄柱800干涉。 In this embodiment, the second precast beam 200 is hoisted so that the first end 211 of the second precast beam 200 is disposed on the top surface 910 of the temporary support frame 900, and the second end 212 of the second precast beam 200 is disposed on the fourth end 840 of the third precast column 800 and above the top end of the second main reinforcement 870 in the third precast column 800. At this time, the second precast beam 200 is roughly aligned with the first precast beam 100 along the length direction (X axis), and the first end 211 of the second precast beam 200 is adjacent to the second section 120 of the first precast beam 100. In this embodiment, the second precast beam 200 is hoisted by tying the cable 400 of the crane to the stirrup hook 216 extending from the upper body 210 of the second precast beam 200. It should be noted that although the second end 212 of the second precast beam 200 is located on the fourth end 840 of the third precast column 800 and above the top of the second main reinforcement 870 in the third precast column 800, the second main reinforcement 870 and the second connector 820 are buried in the third body 810, so the hoisting of the second precast beam 200 will not interfere with the third precast column 800.

圖5為根據本揭露上述實施例的施工流程示意圖五。根據本實施例的施工流程,接著上述步驟,操作者沿著X軸向,向左方移動第二預鑄梁200,以使得第二預鑄梁200的第一端部211內的第一續接器240與第一預鑄梁100中之第一鋼筋130之伸出第一預鑄梁100中之第二區段120的銜接端132耦接,藉此第二預鑄梁200透過第一續接器240以使第二鋼筋230與第一預鑄梁100的第一鋼筋130耦合。此時,由於第二預鑄梁200已被吊離,第二續接器820外露於第三預鑄柱800之頂面815。更詳細來說,本步驟係使得第二預鑄梁200與第一預鑄梁100沿其各自長度方向(即圖5所示之X軸向)對齊,並將第二預鑄梁200朝向第一預鑄梁100向圖式中之左側水平移動,並使得第二預鑄梁200的第一端部211設置於角托790的頂面795上,且第二預鑄梁200的第二端部212仍位於第三預鑄柱800的第三本體810的頂面815上,進而使第二預鑄梁200中的第一續接器240與第一預鑄梁100中之第一鋼筋130之伸出第一預鑄梁100中之第二區段120的銜接端132耦接。在一實施例中,第一預鑄梁100與第二預鑄梁 200可保留一間隙,並待之後在該間隙之間澆築混凝土或砂漿而使第一預鑄梁100與第二預鑄梁200彼此連接。在其他實施例中,第一預鑄梁100與第二預鑄梁200可彼此貼合。 FIG5 is a fifth schematic diagram of the construction process according to the above embodiment of the present disclosure. According to the construction process of the present embodiment, following the above steps, the operator moves the second pre-cast beam 200 to the left along the X-axis so that the first connector 240 in the first end 211 of the second pre-cast beam 200 is coupled with the connecting end 132 of the first steel bar 130 in the first pre-cast beam 100 extending out of the second section 120 in the first pre-cast beam 100, thereby the second pre-cast beam 200 is coupled with the first steel bar 130 of the first pre-cast beam 100 through the first connector 240. At this time, since the second pre-cast beam 200 has been lifted off, the second connector 820 is exposed on the top surface 815 of the third pre-cast column 800. In more detail, this step is to align the second pre-cast beam 200 and the first pre-cast beam 100 along their respective length directions (i.e., the X-axis direction shown in FIG. 5 ), and to horizontally move the second pre-cast beam 200 toward the first pre-cast beam 100 to the left side in the figure, and to place the first end 211 of the second pre-cast beam 200 on the top surface 795 of the angle bracket 790, and the second end 212 of the second pre-cast beam 200 is still located on the top surface 815 of the third body 810 of the third pre-cast column 800, thereby coupling the first connector 240 in the second pre-cast beam 200 with the connecting end 132 of the first steel bar 130 in the first pre-cast beam 100 extending out of the second section 120 in the first pre-cast beam 100. In one embodiment, a gap may be reserved between the first precast beam 100 and the second precast beam 200, and concrete or mortar may be poured between the gap to connect the first precast beam 100 and the second precast beam 200. In other embodiments, the first precast beam 100 and the second precast beam 200 may be bonded to each other.

圖6為根據本揭露上述實施例的施工流程示意圖六。根據本實施例的施工流程,接著上述步驟,操作者進一步包含將一後接柱鋼筋880之一端固定至第三預鑄柱800中之第二續接器820中,使後接柱鋼筋880延Y軸向,豎立於第三預鑄柱800。需要注意的是,後接柱鋼筋880及第一主筋860在Z軸方向上經設計,避開第二鋼筋230之位置而避免彼此干涉。 FIG6 is a schematic diagram of the construction process according to the above embodiment of the present disclosure. According to the construction process of this embodiment, following the above steps, the operator further includes fixing one end of a rear column steel bar 880 to the second connector 820 in the third pre-cast column 800, so that the rear column steel bar 880 is vertically connected to the third pre-cast column 800 along the Y axis. It should be noted that the rear column steel bar 880 and the first main bar 860 are designed in the Z axis direction to avoid the position of the second steel bar 230 to avoid interference with each other.

圖7為根據本揭露上述實施例的施工流程示意圖七。圖8為圖7之線段8-8之右側視圖。請同時參閱圖7及8,根據本實施例的施工流程,接著上述步驟,操作者進一步提供一第三預鑄梁300,並吊裝第三預鑄梁300以使得第三預鑄梁300的一端310設置於第一預鑄梁100的第一區段110與第二區段120之間的間隙G中,其中第三預鑄梁300的長度方向係沿Z軸向而與第一預鑄梁100或第二預鑄梁200的長度方向(X軸向)大致垂直。第一區段110及第二區段120之間的間隙G經構形以供大致垂直於第一預鑄梁100與第二預鑄梁200之一第三預鑄梁300之一端310配合收納於間隙G中。更詳細來說,第三預鑄梁300的一端310設置於第二預鑄柱700的頂面715上介於第二預鑄柱700之第二端730及第三端740之間一側的第六端750(如圖8所示)上。另一方面,如圖8所示,第二預鑄柱700亦可設置另一角托760及臨時支撐架920,以承載第三預鑄梁300的其他部分。之後,可澆築混凝土於第一預鑄梁100的第一區段110、第二區段120與第三預鑄梁300之間,以形成彼此之間的接頭。 FIG7 is a schematic diagram of the construction process according to the above embodiment of the present disclosure. FIG8 is a right side view of the line segment 8-8 of FIG7. Please refer to FIG7 and 8 at the same time. According to the construction process of this embodiment, after the above steps, the operator further provides a third pre-cast beam 300, and hoists the third pre-cast beam 300 so that one end 310 of the third pre-cast beam 300 is disposed in the gap G between the first section 110 and the second section 120 of the first pre-cast beam 100, wherein the length direction of the third pre-cast beam 300 is along the Z axis and is substantially perpendicular to the length direction (X axis) of the first pre-cast beam 100 or the second pre-cast beam 200. The gap G between the first section 110 and the second section 120 is configured so that one end 310 of a third pre-cast beam 300 substantially perpendicular to the first pre-cast beam 100 and the second pre-cast beam 200 can be accommodated in the gap G. In more detail, one end 310 of the third pre-cast beam 300 is disposed on the sixth end 750 (as shown in FIG. 8 ) on one side between the second end 730 and the third end 740 of the second pre-cast column 700 on the top surface 715 of the second pre-cast column 700. On the other hand, as shown in FIG. 8 , the second pre-cast column 700 can also be provided with another angle bracket 760 and a temporary support frame 920 to support other parts of the third pre-cast beam 300. Afterwards, concrete can be poured between the first section 110 of the first precast beam 100, the second section 120 and the third precast beam 300 to form joints therebetween.

在其他實施例中,第三預鑄梁300可包括間隔設置的兩區段(未顯示),並由至少一鋼筋連接兩區段,第三預鑄梁300的上述兩區段可分別設置於第二預鑄柱700的頂面715上相對的第六端750及第七端770上。 In other embodiments, the third pre-cast beam 300 may include two interval-arranged sections (not shown) connected by at least one steel bar. The two sections of the third pre-cast beam 300 may be respectively arranged on the sixth end 750 and the seventh end 770 opposite to each other on the top surface 715 of the second pre-cast column 700.

綜合上述,本申請所揭露之預鑄結構及其施工方法,透過具有透過第一鋼筋而間隔設置的第一區段與第二區段之第一預鑄梁與第二預鑄梁彼此銜接,重量較輕,且可快速組裝預鑄柱上,如此的結構設計和施工方式可大幅提升預鑄梁之組合效率及縮短工期之功效。詳而言之,經由本申請所揭露之預鑄結構及其施工方法,在吊裝預鑄梁時由於可節省相當之空間,無須如圖9A所示,採階梯式退吊步驟(上下層之對應預鑄梁(a、b需呈現階梯狀吊裝順序),而可採如圖9B所示之垂直退吊步驟(上下層之對應預鑄梁a'、b'可呈現上下重疊之吊裝順序),以節省吊裝空間並增加吊裝效率。 In summary, the precast structure and construction method disclosed in the present application are characterized by that the first precast beam and the second precast beam, which have a first section and a second section spaced apart by a first steel bar, are connected to each other, and are light in weight and can be quickly assembled on the precast column. Such a structural design and construction method can greatly improve the assembly efficiency of the precast beams and shorten the construction period. In detail, the precast structure and construction method disclosed in this application can save considerable space when hoisting precast beams. It is not necessary to adopt a step-by-step hoisting procedure as shown in FIG. 9A (the corresponding precast beams a and b on the upper and lower layers need to be hoisted in a step-by-step manner), but a vertical hoisting procedure as shown in FIG. 9B (the corresponding precast beams a' and b' on the upper and lower layers can be hoisted in an overlapping order) to save hoisting space and increase hoisting efficiency.

本文中的用語「一」或「一種」係用以敘述本揭露的元件及成分。此術語僅為了敘述方便及給予本揭露的基本觀念。此敘述應被理解為包括一種或至少一種,且除非明顯地另有所指,表示單數時亦包括複數。於申請專利範圍中和「包含」一詞一起使用時,該用語「一」可意謂一個或超過一個。此外,本文中的用語「或」其意同「及/或」。 The term "a" or "an" herein is used to describe the elements and components of the present disclosure. This term is only for the convenience of description and to give the basic concept of the present disclosure. This description should be understood to include one or at least one, and unless otherwise clearly indicated, the singular also includes the plural. When used with the word "including" in the scope of the patent application, the term "a" can mean one or more than one. In addition, the term "or" herein means the same as "and/or".

除非另外規定,否則諸如「上方」、「下方」、「向上」、「左邊」、「右邊」、「向下」、「本體」、「基座」、「垂直」、「水平」、「側」、「較高」、「下部」、「上部」、「上方」、「下面」等空間描述係關於圖中所展示的方向加以指示。應理解,本文中所使用的空間描述僅出於說明的目的,且本文中所描述的結構的實際實施 可以任何相對方向在空間上配置,此限制條件不會改變本揭露實施例的優點。舉例來說,在一些實施例的描述中,提供「在」另一元件「上」的一元件可涵蓋前一元件直接在後一元件上(例如,與後一元件實體接觸)的狀況以及一或複數個介入元件位於前一元件與後一元件之間的狀況。 Unless otherwise specified, spatial descriptions such as "above", "below", "upward", "left", "right", "downward", "body", "base", "vertical", "horizontal", "side", "higher", "lower", "upper", "above", "below" and the like are indicated with respect to the directions shown in the figures. It should be understood that the spatial descriptions used herein are for illustrative purposes only, and that the actual implementation of the structures described herein can be spatially arranged in any relative direction, and this limitation does not change the advantages of the disclosed embodiments. For example, in the description of some embodiments, providing an element "on" another element may cover the situation where the former element is directly on the latter element (e.g., in physical contact with the latter element) and the situation where one or more intervening elements are located between the former element and the latter element.

如本文中所使用,術語「大致」、「實質上」、「大略」及「約」用以描述及考慮微小的變化。當與事件或情形結合使用時,該等術語可意指事件或情形明確發生的情況以及事件或情形極近似於發生的情況。 As used herein, the terms "substantially", "substantially", "roughly" and "approximately" are used to describe and take into account minor variations. When used in conjunction with an event or circumstance, these terms may refer to both situations where the event or circumstance definitely occurred and situations where the event or circumstance closely approximates to occurring.

本揭露並不限於本文中所揭示的特定結構或設置,本揭露所屬技術領域具有通常知識者當可理解,在本揭露的精神下,本文中所揭示的此等結構及設置在一定程度上可經改變或置換。亦應瞭解本文所使用的術語及描述方向或相對位置的用語僅為描述特定實施方式及便於說明與理解而使用,並不意欲限制本揭露的範圍。 The present disclosure is not limited to the specific structures or settings disclosed herein. A person with ordinary knowledge in the art to which the present disclosure belongs should understand that within the spirit of the present disclosure, the structures and settings disclosed herein can be changed or replaced to a certain extent. It should also be understood that the terms and terms describing directions or relative positions used herein are only used to describe specific implementations and facilitate explanation and understanding, and are not intended to limit the scope of the present disclosure.

110:第一區段 110: Section 1

111:第一端部 111: First end

112:第二端部 112: Second end

114:箍筋彎勾 114: Stirrup bend hook

120:第二區段 120: Second section

130:第一鋼筋 130: First steel bar

132:銜接端 132:Connection terminal

134:自由端 134: Free end

200:第二預鑄梁 200: Second pre-cast beam

210:本體 210:Entity

211:第一端部 211: First end

212:第二端部 212: Second end

214:貫穿槽 214:Through slot

230:第二鋼筋 230: Second steel bar

231:第一端 231: First end

232:第二端 232: Second end

240:第一續接器 240: First connector

600:第一預鑄柱 600: First pre-cast column

610:第一本體 610: The first entity

615:頂面 615: Top

620:第一組鋼筋 620: The first set of steel bars

630:第一端 630: First end

700:第二預鑄柱 700: Second pre-cast column

710:第二本體 710: Second body

715:頂面 715: Top

720:第二組鋼筋 720: The second set of steel bars

730:第二端 730: Second end

740:第三端 740: The third end

790:角托 790: Corner bracket

795:頂面 795: Top

800:第三預鑄柱 800: The third pre-cast column

810:第三本體 810: The third entity

815:頂面 815: Top

820:第二續接器 820: Second connector

830:第三組鋼筋 830: The third set of steel bars

840:第四端 840: The fourth end

850:第五端 850: The fifth end

860:第一主筋 860: First main reinforcement

870:第二主筋 870: Second main reinforcement

880:後接柱鋼筋 880: Rear column reinforcement

900:臨時支撐架 900: Temporary support frame

910:頂部表面 910: Top surface

G:間隙 G: Gap

X:軸向 X: axial direction

Y:軸向 Y: Axis

Z:軸向 Z: Axial direction

Claims (10)

一種預鑄結構施工方法,包括:提供依序間隔排列之一第一預鑄柱、一第二預鑄柱及一第三預鑄柱;提供一第一預鑄梁,該第一預鑄梁包括一第一區段、與該第一區段間隔設置的一第二區段、及貫穿該第一區段與該第二區段的一第一鋼筋;吊裝該第一預鑄梁,以使得該第一預鑄梁跨越設置於該第一預鑄柱及該第二預鑄柱上,其中,該第一區段的兩端部分別設置於該第一預鑄柱及該第二預鑄柱彼此相鄰的一第一端及一第二端上,該第二區段設置於該第二預鑄柱的與該第二端相對的一第三端上;提供一第二預鑄梁,該第二預鑄梁包括一第一端部以及相對於該第一端部之一第二端部;吊裝該第二預鑄梁,以使得該第二預鑄梁的該第一端部設置於一臨時支撐架上,並使得該第二預鑄梁的該第二端部設置於該第三預鑄柱的一第四端上;以及移動該第二預鑄梁,以使得該第二預鑄梁的該第一端部與該第一預鑄梁中之該第一鋼筋之伸出該第一預鑄梁中之該第二區段的一銜接端耦接。 A precast structure construction method comprises: providing a first precast column, a second precast column and a third precast column arranged in sequence and spaced apart; providing a first precast beam, the first precast beam comprising a first section, a second section spaced apart from the first section, and a first steel bar penetrating the first section and the second section; hoisting the first precast beam so that the first precast beam is arranged across the first precast column and the second precast column, wherein two ends of the first section are respectively arranged on a first end and a second end of the first precast column and the second precast column adjacent to each other, and the second section The method comprises the steps of: providing a second precast beam, the second precast beam comprising a first end and a second end opposite to the first end; hoisting the second precast beam so that the first end of the second precast beam is disposed on a temporary support frame, and the second end of the second precast beam is disposed on a fourth end of the third precast column; and moving the second precast beam so that the first end of the second precast beam is coupled with a connecting end of the first steel bar in the first precast beam extending out of the second section of the first precast beam. 如請求項1之預鑄結構施工方法,其中該第二預鑄梁之該第一端部包含一第一續接器於其中,且進一步包含一第二鋼筋,伸入該第二端部中,並且其一端與該第一續接器固接,其中移動該第二預鑄梁的步驟包括: 使得該第二預鑄梁與該第一預鑄梁沿其各自長度方向對齊;以及將該第二預鑄梁朝向該第一預鑄梁水平移動,使得該第二預鑄梁中的該第一續接器與該第一預鑄梁中之該第一鋼筋之伸出該第一預鑄梁中之該第二區段的該銜接端耦接。 The precast structure construction method of claim 1, wherein the first end of the second precast beam includes a first connector therein, and further includes a second steel bar extending into the second end and having one end fixedly connected to the first connector, wherein the step of moving the second precast beam includes: Aligning the second precast beam and the first precast beam along their respective length directions; and horizontally moving the second precast beam toward the first precast beam so that the first connector in the second precast beam is coupled to the connecting end of the first steel bar in the first precast beam extending out of the second section of the first precast beam. 如請求項2之預鑄結構施工方法,更進一步包含:提供一第三預鑄梁;以及吊裝該第三預鑄梁以使得該第三預鑄梁的一端設置於該第一預鑄梁的該第一區段與該第二區段之間,其中該第三預鑄梁的一長度方向與該第一預鑄梁或該第二預鑄梁的長度方向大致垂直。 The precast structure construction method of claim 2 further comprises: providing a third precast beam; and hoisting the third precast beam so that one end of the third precast beam is disposed between the first section and the second section of the first precast beam, wherein a length direction of the third precast beam is substantially perpendicular to the length direction of the first precast beam or the second precast beam. 如請求項1之預鑄結構施工方法,更進一步包括:設置一角托於該第二預鑄柱的該第三端的外側並朝向該第三預鑄柱,並使得該角托之一頂面與該第二預鑄柱的頂面齊平;其中吊裝該第一預鑄梁之步驟包含使得該第一預鑄梁的該第二區段的至少一部分位於該角托上。 The precast structure construction method of claim 1 further includes: setting an angle bracket on the outer side of the third end of the second precast column and facing the third precast column, and making a top surface of the angle bracket flush with the top surface of the second precast column; wherein the step of hoisting the first precast beam includes making at least a portion of the second section of the first precast beam be located on the angle bracket. 如請求項2之預鑄結構施工方法,其中該第三預鑄柱包含一第一主筋以及一第二主筋於其中,其中該第一主筋鄰近該第三預鑄柱之與該第四端相對之一第五端,並伸出該第三預鑄柱之一頂面,該第二主筋鄰近該第三預鑄柱之該第四端,並且完全埋設於該第三預鑄柱中,其中吊裝該第二預鑄梁之步驟包括:使得該第二預鑄梁的該第二端部設置於該第三預鑄柱的該第四端上以及該第二主筋之上方。 As in claim 2, the precast structure construction method, wherein the third precast column includes a first main reinforcement and a second main reinforcement therein, wherein the first main reinforcement is adjacent to a fifth end of the third precast column opposite to the fourth end and extends out of a top surface of the third precast column, and the second main reinforcement is adjacent to the fourth end of the third precast column and is completely buried in the third precast column, wherein the step of hoisting the second precast beam includes: placing the second end of the second precast beam on the fourth end of the third precast column and above the second main reinforcement. 如請求項5之預鑄結構施工方法,其中該第二主筋的頂端設有一第二續接器,該方法進一步包括:在該第二預鑄梁中的該第二續接器與該第一預鑄梁中之該第一鋼筋之伸出該第一預鑄梁中之該第二區段的該銜接端耦接,且該第二續接器曝露於該第三預鑄柱之該頂面後,將一後接柱鋼筋之一端固定至該第三預鑄柱中之該第二續接器。 The precast structure construction method of claim 5, wherein the top end of the second main reinforcement is provided with a second connector, and the method further comprises: coupling the second connector in the second precast beam with the connecting end of the first reinforcement in the first precast beam extending out of the second section in the first precast beam, and after the second connector is exposed to the top surface of the third precast column, fixing one end of a post-column reinforcement to the second connector in the third precast column. 一種預鑄結構,其包括:一第一預鑄梁,其包括:一第一區段;一第二區段,其與該第一區段間隔分離以形成一間隙於該第一區段以及該第二區段之間;及一第一鋼筋,其沿該預鑄結構之長度方向,連接並貫穿該第一區段及該第二區段;及一第二預鑄梁,其與該第一預鑄梁沿其長度方向大致對齊,並鄰近該第一預鑄梁之該第二區段,該第二預鑄梁與該第一預鑄梁之該第一鋼筋耦合。 A precast structure, comprising: a first precast beam, comprising: a first section; a second section, which is spaced apart from the first section to form a gap between the first section and the second section; and a first steel bar, which connects and penetrates the first section and the second section along the length direction of the precast structure; and a second precast beam, which is roughly aligned with the first precast beam along its length direction and is adjacent to the second section of the first precast beam, and the second precast beam is coupled with the first steel bar of the first precast beam. 如請求項7之預鑄結構,其進一步包含一第一預鑄柱、一第二預鑄柱及一第三預鑄柱,其中該第一預鑄梁跨越設置於該第一預鑄柱及該第二預鑄柱上,該第一區段的兩端部分別設置於該第一預鑄柱及該第二預鑄柱彼此相鄰的一第一端及一第二端上,該第二區段設置於該第二預鑄柱的與該 第二端相對的一第三端上,且其中該第二預鑄梁的一第二端部設置於該第三預鑄柱的一第四端上。 The precast structure of claim 7 further comprises a first precast column, a second precast column and a third precast column, wherein the first precast beam is arranged across the first precast column and the second precast column, the two ends of the first section are respectively arranged on a first end and a second end of the first precast column and the second precast column adjacent to each other, the second section is arranged on a third end of the second precast column opposite to the second end, and a second end of the second precast beam is arranged on a fourth end of the third precast column. 如請求項7之預鑄結構,其中該第二預鑄梁包括:一本體,其具有沿該第二預鑄梁之長度方向延伸的一貫穿槽,並包括一第一端部以及相對於該第一端部之一第二端部,其中該第一端部鄰近該第一預鑄梁之該第二區段;一第二鋼筋,其一端伸入於該本體之該貫穿槽中,其相對另一端朝向遠離該第一預鑄梁的方向延伸並向上折彎;及一續接器,包含於該第二預鑄梁之該第一端部中,其中該續接器與該第一預鑄梁中之該第一鋼筋之伸出該第一預鑄梁中之該第二區段的一銜接端耦接,藉此該第一鋼筋與該第二鋼筋透過該續接器耦合。 The precast structure of claim 7, wherein the second precast beam comprises: a body having a through slot extending along the length direction of the second precast beam, and comprising a first end and a second end opposite to the first end, wherein the first end is adjacent to the second section of the first precast beam; a second steel bar, one end of which extends into the through slot of the body, and the other end of which extends away from the first precast beam and bends upward; and a connector included in the first end of the second precast beam, wherein the connector is coupled to a connecting end of the first steel bar in the first precast beam extending out of the second section of the first precast beam, whereby the first steel bar and the second steel bar are coupled through the connector. 如請求項7之預鑄結構,其中該第一區段及該第二區段之間的該間隙經構形以供大致垂直於該第一預鑄梁與該第二預鑄梁之一第三預鑄梁之一端配合收納於該間隙中。 The precast structure of claim 7, wherein the gap between the first section and the second section is configured so that one end of a third precast beam substantially perpendicular to the first precast beam and the second precast beam can be accommodated in the gap.
TW113110684A 2024-03-22 2024-03-22 Precasting structure and construction method thereof TWI851524B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
TW113110684A TWI851524B (en) 2024-03-22 2024-03-22 Precasting structure and construction method thereof
US18/790,797 US20250297470A1 (en) 2024-03-22 2024-07-31 Precast structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW113110684A TWI851524B (en) 2024-03-22 2024-03-22 Precasting structure and construction method thereof

Publications (2)

Publication Number Publication Date
TWI851524B true TWI851524B (en) 2024-08-01
TW202538129A TW202538129A (en) 2025-10-01

Family

ID=93283877

Family Applications (1)

Application Number Title Priority Date Filing Date
TW113110684A TWI851524B (en) 2024-03-22 2024-03-22 Precasting structure and construction method thereof

Country Status (2)

Country Link
US (1) US20250297470A1 (en)
TW (1) TWI851524B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM288896U (en) * 2005-09-23 2006-03-21 Runhorn Pretech Eng Co Ltd Thin-shell beam frame structure
CN205530682U (en) * 2016-04-01 2016-08-31 上海城建建设实业集团新型建筑材料有限公司 Precast prestressed frame construction
US9765521B1 (en) * 2016-10-18 2017-09-19 King Saud University Precast reinforced concrete construction elements with pre-stressing connectors
TW201912901A (en) * 2017-09-11 2019-04-01 潤弘精密工程事業股份有限公司 Method for forming a plurality of beams connected in series

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM288896U (en) * 2005-09-23 2006-03-21 Runhorn Pretech Eng Co Ltd Thin-shell beam frame structure
CN205530682U (en) * 2016-04-01 2016-08-31 上海城建建设实业集团新型建筑材料有限公司 Precast prestressed frame construction
US9765521B1 (en) * 2016-10-18 2017-09-19 King Saud University Precast reinforced concrete construction elements with pre-stressing connectors
TW201912901A (en) * 2017-09-11 2019-04-01 潤弘精密工程事業股份有限公司 Method for forming a plurality of beams connected in series

Also Published As

Publication number Publication date
US20250297470A1 (en) 2025-09-25
TW202538129A (en) 2025-10-01

Similar Documents

Publication Publication Date Title
CN105507470B (en) A kind of periphery overlapping overall assembled floor and its construction method
CN111576619B (en) Production method of high-strength concrete post-cast assembled frame system
CN110439137A (en) Prefabricated wall panel, wall and prefabricated wall panel production method, prefabricated wall construction method
CN116240987A (en) A post-cast prefabricated protective wall and its construction method
CN118273462B (en) Concrete module integrated with prefabricated shear wall and assembly method
KR102440832B1 (en) Precat girder-column structure with large depth truss and construction method for the same
CN113047417A (en) 3D printing assembly type box structure and connecting method thereof
TWI851524B (en) Precasting structure and construction method thereof
CN216475803U (en) A Novel Prefabricated Floor Structure Applied to Shear Wall System
CN212656384U (en) High-strength concrete connecting piece, high-strength concrete post-cast assembled frame system and support frame
CN108978854A (en) One kind being bolted Precast Concrete Frame
TWI818840B (en) Method for fabricating architecture structure
CN111364642A (en) A prefabricated energy-consuming shear wall system and its construction method
CN213204438U (en) Semi-prefabricated and semi-cast-in-place building component
JPH09279742A (en) Work execution method for floor
CN116145875A (en) A new type of reinforced truss concrete laminated hollow floor and its implementation method
TWI803430B (en) Precasting column and method of manufacturing the same
KR102244658B1 (en) Method for constructing flat slab structure with drop panel
TWI701373B (en) Method for constructing construction structure of multi-floor building
KR100685147B1 (en) Construction method of high-rise building structure with reinforced concrete structure
TW202413779A (en) Construction structure
KR101866559B1 (en) Construction technique of concrete structures through the Precast Concrete
KR102811776B1 (en) Coupling structure for pre-assembled rebar
CN205502340U (en) Peripheral coincide unit -installment floor
CN219710661U (en) Steel joint concrete precast shear wall