SU1408069A1 - Method of mining twin longwalls by longwall set of equipment - Google Patents
Method of mining twin longwalls by longwall set of equipment Download PDFInfo
- Publication number
- SU1408069A1 SU1408069A1 SU853948783A SU3948783A SU1408069A1 SU 1408069 A1 SU1408069 A1 SU 1408069A1 SU 853948783 A SU853948783 A SU 853948783A SU 3948783 A SU3948783 A SU 3948783A SU 1408069 A1 SU1408069 A1 SU 1408069A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- lava
- lagging
- mechanized
- lining
- lavas
- Prior art date
Links
- 238000005065 mining Methods 0.000 title claims abstract description 12
- 238000000034 method Methods 0.000 title claims description 4
- 230000021615 conjugation Effects 0.000 claims abstract description 3
- 229910052500 inorganic mineral Inorganic materials 0.000 claims abstract description 3
- 239000011707 mineral Substances 0.000 claims abstract description 3
- 238000009434 installation Methods 0.000 claims abstract 2
- 230000013011 mating Effects 0.000 claims description 7
- 238000006467 substitution reaction Methods 0.000 abstract description 3
- 239000003245 coal Substances 0.000 abstract description 2
- 238000012423 maintenance Methods 0.000 abstract description 2
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- PWWVAXIEGOYWEE-UHFFFAOYSA-N Isophenergan Chemical compound C1=CC=C2N(CC(C)N(C)C)C3=CC=CC=C3SC2=C1 PWWVAXIEGOYWEE-UHFFFAOYSA-N 0.000 abstract 1
- 238000005728 strengthening Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 3
- 230000008878 coupling Effects 0.000 description 3
- 238000010168 coupling process Methods 0.000 description 3
- 238000005859 coupling reaction Methods 0.000 description 3
- 101100328887 Caenorhabditis elegans col-34 gene Proteins 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000002028 premature Effects 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Landscapes
- Control Of Conveyors (AREA)
Abstract
Изобретение относитс к горной промети и м. б. использовано при подземной разработке пологих и наклонных угольных пластов . Цель изобретени - повышение произв- сти и безопасности добычных работ, обеспечение независимости работы лав (Л) при остановке одной из них. Ведут отработку отстаюшей левосторонней Л 1 и опережающей правосторонней Л 2 с механизированной крепью сопр жени (КС). Транспортировку полезного ископаемого из Л 1 и 2 производ т на конвейер 19 бортового конвейерного штрека (Ш) 4 или 5. Поддержание сопр жени Л 2 с обшим Ш 3 производ т с помощью КС 9. Завальными консол ми 10 КС 9 осуществл ют временное поддержание верхн ков 13 на таге передвижени КС 9. Усиление штрековой крепи Ш 3 на участке от Л 2 до Л 1 производ т путем установки под вер.хи ки 13 нитей вандрутов 14-16, 18 с подстановкой под них гидростоек 17, Сопр жение Л 1 с Ш 3 поддерживают линейными секци ми 8 крепи. Вслед за обработкой Л 1 и 2 производ т обрушение кровли и пога1пение Ш 3. При аварийной остановке Л 1 продолжают продвигать Л 2 с увеличением скорости ее продвигани до подхода секций 8 крепи вплотную к консол м 10 КС 9. Затем КС 9 отсоедин ют от секций 6 крепи Л 2 и подвигают вперед совместно с секци ми 8 до установки их в один р д с секци ми 6. Секции 8 на Ш 3 отсоедин ют от крепи Л 1 и соедин ют с крепью Л 2. При этом крепь Л 1 соедин ют с КС 9, после чего Л 1 отрабатывают с опережением . 3 ил. € (Л 4 О оо о О5 со 1риг.1The invention relates to mining promet and m. B. used in underground mining of flat and inclined coal seams. The purpose of the invention is to increase the production and safety of mining operations, to ensure the independence of the work of lavas (L) when one of them stops. The left-sided left-handed L 1 and the advancing right-handed L 2 with the mechanized support of the interface (CS) are working out. Transportation of minerals from L 1 and 2 is carried out on the conveyor 19 of the on-board conveyor road (W) 4 or 5. The maintenance of the mate L 2 with the general W 3 is carried out with the help of COP 9. The loading console 10 COP 9 temporarily maintain the upper 13 on the tag of movement KS 9. Strengthening the road lining Sh 3 in the area from L 2 to L 1 is made by installing under the upper wall 13 threads of vandruts 14-16, 18 with substitution of hydraulic rails for them 17, Conjugation L 1 s The W 3 is supported by 8 lining linear sections. Following the processing of L 1 and 2, the roof collapses and the W 3 is destroyed. At an emergency stop, L 1 continue to advance L 2 with an increase in the speed of its advance until sections 8 come up against the brackets 10 of COP 9. Then COP 9 is disconnected from the sections 6 supports L 2 and move forward together with sections 8 prior to their installation in one row with sections 6. Sections 8 on W 3 are disconnected from the supports L 1 and connected to the support L 2. At the same time the support L 1 connects with COP 9, after which L 1 is worked out ahead of time. 3 il. € (L 4 O o o O5 co 1g.1
Description
Изобретение относитс к горной промышленности и может быть использовано при подземной разработке пологих и наклонных угольных пластов.The invention relates to the mining industry and can be used in underground mining of flat and inclined coal seams.
Цель изобретени - повышение производительности и безопасности добычных работ, обеспечение независимости работы лав при остановке одной из них.The purpose of the invention is to increase the productivity and safety of mining operations, to ensure the independence of the work of lavas when one of them stops.
На фиг. 1 представлена схема, реализующа способ, правосторонн лава опережает левостороннюю лаву; на фиг. 2 - то же, левосторонн лава опережает остановленную лаву; на фиг. 3 - разрез А-А на фиг. 2.FIG. Figure 1 shows a scheme that implements the method, right-sided lava ahead of left-sided lava; in fig. 2 - the same, left-sided lava ahead of stopped lava; in fig. 3 shows section A-A in FIG. 2
Спаренные лавы, оборудованные механизированными комплексами, левосторонн отстающа 1 и правосторонн опережаю- ща 2 оконтурены трем выемочными штреками - общим штреком 3, левым бортовым конвейерным 4 и правым бортовым конвейерным 5 штреками. Механизированные комплексы обеих лав включают механизирован- ные крепи, состо щие из одинаковых по конструкции линейных секций 6, механизированной крепи, одинаковых по конструкции крепей 7 сопр жени левого бортового конвейерного штрека и правого бортового штрека . В качестве крепей сопр жени могут быть использованы серийно выпускаемые крепи Т-бк. Общий штрек на сопр жении с отстающей левосторонней лавой или правосторонней закреплен линейными секци ми 8 механизированной крепи, одинаковых по конструкции с линейными секци ми механизированной крепи. Общий штрек на сопр жении с опережаюшей правосторонней лавой или левосторонней лавой закреплен крепью 9 сопр жени , имеющей свободные проходы дл выхода на участок общего штрека между отстающей и опережающими лавами. В качестве крепи сопр жени может быть использована крепь сопр жени КСУ. Крепь 9 сопр жени общего штрека с одной из опережающих лав имеет выступающие в сторону отстающей лавы завальные консоли 10, выполненные, например, из двутавровых металлических балок, жестко закрепленных к перекрыти м 11 крепи сопр жени . Выемочные штреки, а также общий штрек закреплены, например, ра.мной щтрековой дерев нной крепью, состо щей из стоек 12 и верхн ков 13. Участок общего штрека между опережающей и отстающей лавами усилен со стороны отстающей лавы одной ниткой вандрутов 14, а со стороны опережающей лавы - двум нитками вандрутов 15 и 16с постановкой под них переносных гидростоек 17, например, типа 2 ГСК. Дополнительно со стороны опережающей лавы участок общего щтрека усилен ниткой вандрутов 18.Paired lavas equipped with mechanized complexes, left-sided 1 and right-sided 2, are left-sided contoured with three excavation drifts - common drift 3, left-side conveyor 4 and right-side conveyor 5 drifts. Mechanized complexes of both lavas include mechanized supports, consisting of identical in construction linear sections 6, mechanized supports, identical in construction of supports 7 for coupling the left onboard conveyor roadway and the right side roadway. Commercially available support T-bk can be used as mate supports. A common drift on the mate with a lagging left-sided lava or right-sided is fixed by linear sections 8 of mechanized support, the same in design with linear sections of mechanized support. The common drift on the interface with the leading right-sided lava or left-sided lava is fixed by the fixture 9 of the linkage, which has free passages for reaching the common drift section between the lagging and leading lavas. KSU lining can be used as a support mate. The support 9 of the common drift interface with one of the leading lavas has protruding consoles 10 facing the lagging lava, made, for example, of I-beam metal beams rigidly fixed to the ceilings 11 of the coupling support. Extraction drifts, as well as a common drift, are fixed, for example, with a white wooden support, consisting of racks 12 and upper 13. The section of the common drift between the advancing and lagging lavas is reinforced from the lava behind by one string of vandruts 14, and from leading lava - two strings of vandruts 15 and 16s by placing under them portable gidroeek 17, for example, type 2 GSK. In addition, from the side of the advanced lava, the section of the common shtrek is reinforced with a wandroot thread 18.
На левом и правом бортовых конвейерных штреках установлены одинаковые по конструкции конвейеры 19, а на обшем штреке имеютс рельсовые пути 20. Кроме того, в состав комплексов, которыми отрабатываютс спаренные лавы, вход т лавные конвейеры , комбайны, насосные станции, электро- и гидрооборудование и др.On the left and right side conveyor drifts, the same construction conveyors 19 are installed, and there are rail tracks 20 on the common drift. In addition, the composition of the complexes that work paired lava, includes lateral conveyors, combines, pumping stations, electrical and hydraulic equipment and others
Способ отработки заключаетс в следующем .The method of working out is as follows.
Отработку лав 1 и 2 ведут с небольшим опережением одной лавы другой, в пределах 3-5 м, которое определ етс , с одной стороны , минимальной длиной участка общего штрека, поддерживаемого между отстающей и опережающей лавами, а с другой - независимой работой обеих лав при остановке одной из них Б сл-учае непродолжительной аварии (до суток) с механизмами или осложнени ми горно-геологических условий в одной из лав, сдерживающей ее подвигание. Транспортировку добытого полезного ископаемого из каждой лавы 1 и 2 осуществл ют .на конвейер 19 соответствующего бортового конвейерного штрека 4 и 5. Доставку материалов и оборудовани в лавы 1 и 2 производ т по рельсовым пут м 20 общего штрека 3 до крепи 9 сопр жени , далее через свободные проходы в крепи 9 сопр жени в отстающую лаву 1 по участку общего штрека 3 между отстающей 1 и опережающей 2 лавами.The mining of lavas 1 and 2 is carried out with a slight advance of one lava of another, within 3-5 m, which is determined, on the one hand, by the minimum length of the section of the common drift supported between the lagging and advancing lavas, and on the other, by the independent operation of both lavas at stopping one of them, due to a brief accident (up to a day) with mechanisms or complications of mining and geological conditions in one of the lavas that restrain its movement. The mined minerals from each lava 1 and 2 are transported to a conveyor 19 of the corresponding on-board conveyor ram 4 and 5. The materials and equipment are delivered to lavas 1 and 2 along rail track 20 of the common ram 3 to lining 9 of the mating, further through free passages in the lining of 9 mates into the lagging lava 1 along the section of the common drift 3 between lagging 1 and the advancing 2 lavas.
Поддержание сопр жени опережающей лавы 2 с общим штреком 3 производ т с помощью крепи 9 сопр жени , завальнымиThe maintenance of the advancing lava mate 2 with the common drift 3 is made with the help of lining 9 matings
консол ми 10 которой осуществл ют также временное поддержание верхних элементов штрековой кр епи - верхн ков 13 на шаге передвижени крепи 9 сопр жени . Дл этого перед передвижкой крепи 9 сопр жени стойки 12 щтрековой крепи впереди крепи сопр жени удал ют, крепь 9 сопр же ПИЯ передвигают на шаг передвижки, подхватыва ею верхн ки 13, которые при передвижени х крепи 9 сопр жени сдвигаютс на выступающие в сторону отстающей лавыthe consoles 10 of which also provide temporary support for the upper elements of the drift liner - the upper plates 13 in the step of moving the support 9 of the conjugation. To do this, before moving the support 9 of the linkage, the support 12 of the support support in front of the support of the support is removed, the support 9 of the same PIA moves by a step of the movement, picking up the top 13, which when moving the support 9 of the coupling move to the side of the lagging lava
завальные консоли 10 и удерживаютс на них до восстановлени штрековой крепи общего штрека, которое осуществл ют подстановкой под верхн ки 13 стоек щтрековой крепи. Если щирина крепи 9 сопр жени менее ширины общего штрека 3, возможноthe dammed arms 10 and are held on them until the lining of the common drift is restored, which is carried out by substituting the lining of the lining support for the top 13 of the racks. If the width of the lining is 9 mates less than the width of the common drift 3, it is possible
сохранение с одной стороны общего штрека 3 стоек 12 штрековой крепи без удалени из- под верхн ков 13 и последующей подстановки .preservation on one side of the common drift 3 racks 12 drift supports without removing from under the upper 13 and subsequent substitution.
Усиление штрековой крепи общего щтрека 3 на участке от опережающей 2 до отстающей 1 лав производ т путем установки под верхн ки 13 нескольких нитей вандрутов 14, 15, 16 и 18 с подстановкой под них переносных гидростоек 17. Вначале, следом за передвижением крепи 9 сопр жени иThe reinforcement of common roof support shchrek 3 in the area from the leading 2 to the lagging 1 lavas is strengthened by installing under the top 13 several threads of vandruts 14, 15, 16 and 18 with the substitution of portable hydraulic posts 17 under them. First, following the movement of the lining 9 mates and
восстановлением стоек 12 устанавливают две нити вандрутов 15 и 16 со стороны онережающей лавы, а затем одну нить вандрутов 14 со стороны отстающей лавы. Поby restoring the posts 12, two threads of the Vandrut 15 and 16 are installed from the side of the lava-attenuating one, and then one thread of the Vandrut 14 from the side of the lava behind. By
33
мере увеличени длины поддерживаемого участка общего штрека 3 между отстающей 1 и опережающей 2 лавами, в случае усилени горного давлени , производ т дополнительное усиление щтрековой крепи постановкой дополнительной нити вандру- тов 18. Возможна установка еще 1-2 нитей вандрутов на этом участке общего щтрека 3 с целью еще больщего усилени щтрековой крепи при дальнейшем росте рассто ни между отстающей и опережающей лавами и последующем увеличении нагрузки на штрековую крепь.as the length of the maintained section of the common drift 3 between the lagging 1 and the advancing 2 lavas increases, in case of increasing mountain pressure, additional support is strengthened with additional support of the additional thread of vandruts 18. It is possible to install another 1-2 threads of vandruts on this section of the common shield 3 in order to further strengthen the roof support with a further increase in the distance between the lagging and advancing lavas and the subsequent increase in the load on the roof support.
Сопр жение отстаюшей лавы 1 с общим штреком 3 поддерживают линейными секци ми 8 механизированной крепи, аналогичными по конструкции линейным секци м б лавной механизированной крепи. По мере подвигани отстаюшей лавы 1 из-под нитей вандрутов 14, 15, 16 и 18 убирают переносные гидростойки 17 на шаге ее передвижени и вандруты перенос т, вновь устанавлива следом за подвиганием крепи 9 сопр жени , или складируют, в случае уменьшени длины участков общего штрека 3 между отстающей и опережающей лавами. Погащение общего щтрека 3 осуществл ют по мере передвижени линейных секций 8 механизированной крепи, наход щихс на общем штреке 3, обрушением кровли за ними.The mating of the lagging lava 1 with the common drift 3 is supported by linear sections 8 of mechanized supports, similar in design to the linear sections of b mechanized supports. As the lagging lava 1 is pushed, portable hydroracks 17 are removed from under the threads of the vandruts 14, 15, 16, and 18 at the movement step, and the vandruts are transferred, re-installed following the advancing of the support 9, or stored, drift 3 between lagging and advancing lavas. The deviation of the common shield 3 is carried out as the linear sections 8 of the mechanized support, which are located on the common drift 3, move, with the roof collapsing.
При аварийной остановке отстающей лавы 1 опережающую лаву 2 продолжают подвигать, увеличива скорость ее подвигани и нагрузку на нее. Такой же пор док работ сохран етс и при остановке опережающей лавы 2 до того, как отстающа лава 1 догонит ее. Наиболее веро тным такой вариант вл етс при длительной (более суток) остановке опережающей лавы. В этом случае возникает необходимость опередить отстающей лавой 1 остановленную опережающую лаву 2. Дл этого лаву 1 подвигают до тех пор, пока линейные секции крепи 8 подойдут вплотную к завальным консол м 10 крепи 9 сопр жени . После этого крепь 9 сопр жени отсоедин ют от линейных секций 6 механизированной крепи остановленной лавы 2 и подвигают вперед совместно с линейными секци ми 8 до тех пор, пока линейные секции 8 не станут в один р д с линейными секци ми 6 механизированной крепи комплекса правосторонней остановленной лавы 2, а крепь 9 сопр жени подвинетс вперед нее. После этого линейные секции 8 на общем штреке 3 отсоедин ют от механизированной крепи левосторонней лавы 1 и соедин ют с механизированной крепью правосторонней лавы 2. Левосторонн (бывша отстающа лава 1) продолжает работать и подвигатьс до тех пор, пока не станет в один р д с крепью 9 сопр жени , ранее отсоединенной от механизированной крепи правосторонней лавы 2 и подвинутой вперед нее. При этом механизированную крепь левосторонней лавы 1 со14In case of emergency stop of lagging lava 1, advancing lava 2 continues to move, increasing its speed and load on it. The same order of work is preserved when the advanced lava 2 stops, until the lagging lava 1 catches up with it. Such an option is most likely to occur when the advanced lava stops for a long time (more than a day). In this case, it is necessary to outrun premature lava 2, lagging behind lava 1. For this purpose, lava 1 is pushed until the line sections of the lining 8 come close to the dammed console 10 of the lining 9 of the mating. After that, the mating support 9 is disconnected from the linear sections 6 of the mechanized support of stopped lava 2 and pushed forward together with the linear sections 8 until the linear sections 8 are in one row with the linear sections 6 of the mechanized support of the right-handed complex. Lava 2, and lining 9 of the pair will move forward of it. After that, the linear sections 8 on the common drift 3 are disconnected from the mechanized lining of the left-sided lava 1 and connected to the mechanized lining of the right-sided lava 2. The left-sided (formerly lagging lava 1) continues to operate and move until lining 9 mating, previously detached from the mechanized lining of right-sided lava 2 and moved forward. At the same time, mechanized lining of left-sided lava 1 so14
14080691408069
00
5five
00
5five
00
5five
00
5five
00
5five
един ют с крепью 9 сопр жени и продолжают подвигать совместно с ней, теперь уже левосторонн лава 1 вл етс опережающей , а правосторонн лава 2 - отстающей . Пока правосторонн лава 2 стоит из-за аварии, левосторонн лава 1 работает по добыче до пуска лавы 2, обеспечива увеличение нагрузки в ней до уровн , достигающего нагрузку на обе лавы -при их совместной работе. В дальнейшем, при ликвидации аварии и пуске остановленной лавы 2, лавы 1 и 2 работают совместно, причем если лава 1 подвинулась далеко вперед лавы 2 и участок общего штрека 3 между лавами 2 поддерживать трудоемко, то подвига- ние лавы 1 искусственно снижают, а лавы 2 увеличивают, добива сь уменьшени до оптимального размера длины поддерживаемого участка общего штрека 3. Во врем работы спаренных лав возможна остановка любой из лав 1 и 2, тогда добыча с этих лав будет обеспечиватьс другой работающей лавой.they are united with the support of 9 mates and continue to move together with it, now the left-sided lava 1 is advanced, and the right-sided lava 2 is lagging. While right-sided lava 2 is due to an accident, left-sided lava 1 works on mining before the launch of lava 2, providing an increase in the load in it to a level reaching the load on both lavas when they work together. Later, in case of liquidation of the accident and the launch of stopped lava 2, lava 1 and 2 work together, and if lava 1 moved far ahead of lava 2 and the section of common drift 3 between lava 2 is laborious, then the movement of lava 1 is artificially reduced, and 2 is increased, until the length of the supported section of the common drift is reduced to the optimal size. During the operation of paired lavas, any of lavas 1 and 2 can be stopped, then production from these lavas will be provided by another working lava.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU853948783A SU1408069A1 (en) | 1985-09-02 | 1985-09-02 | Method of mining twin longwalls by longwall set of equipment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU853948783A SU1408069A1 (en) | 1985-09-02 | 1985-09-02 | Method of mining twin longwalls by longwall set of equipment |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| SU1408069A1 true SU1408069A1 (en) | 1988-07-07 |
Family
ID=21195756
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SU853948783A SU1408069A1 (en) | 1985-09-02 | 1985-09-02 | Method of mining twin longwalls by longwall set of equipment |
Country Status (1)
| Country | Link |
|---|---|
| SU (1) | SU1408069A1 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5769504A (en) * | 1996-03-11 | 1998-06-23 | Council Of Scientific & Industrial Research | Equipment for shortwall mining useful for extraction of pillars in underground coal mines |
| RU2344291C2 (en) * | 2002-12-09 | 2009-01-20 | Джоуи У. ХАРМАН | System of deposit development |
-
1985
- 1985-09-02 SU SU853948783A patent/SU1408069A1/en active
Non-Patent Citations (1)
| Title |
|---|
| Авторское свидетельство СССР № 626204, кл. Е 21 С 41/04, 1977. Адилов К. Н. Совершенствование те.хно- логии подземной разработки пластовых месторождений.-М.: Недра, 1979, с. 112-119. * |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5769504A (en) * | 1996-03-11 | 1998-06-23 | Council Of Scientific & Industrial Research | Equipment for shortwall mining useful for extraction of pillars in underground coal mines |
| RU2344291C2 (en) * | 2002-12-09 | 2009-01-20 | Джоуи У. ХАРМАН | System of deposit development |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2015281641A1 (en) | Method for removing hydraulic support for solid filling coal mining | |
| CN103195457A (en) | Supporting method for roadway fully-mechanized drivage operation without withdrawal of roadheader | |
| CN103174448A (en) | In-time supporting method for roadway fully-mechanized excavating operation | |
| CN105715272A (en) | Fully mechanized caving mining method of extra-thick hard coal with lower layers | |
| CN109252860B (en) | High-degree mechanical mining method for thin coal seam continuous mining machine | |
| US4799738A (en) | Mining method for working large-scale mineral deposits by the caving system | |
| CN108457652A (en) | A kind of blockette segmentation full blast pressure shortwall even adopts placement method | |
| CN111828005B (en) | Face mining method | |
| AU2009212092B2 (en) | A method and an apparatus for mining a material in an underground environment | |
| SU1408069A1 (en) | Method of mining twin longwalls by longwall set of equipment | |
| EP0795680B1 (en) | Shortwall mining equipment for extraction of pillars in underground coal mines | |
| GB1569172A (en) | Mining method and apparatus | |
| RU2000115735A (en) | METHOD FOR WORKING DEPOSITS OF THE CHAMBER AND POST SYSTEM DEVELOPMENT | |
| CN103982184A (en) | Falling ore directional slip control method adopting underground mine bottom-pillar-free caving mining method | |
| US6474745B2 (en) | Method of mining | |
| CN112360461B (en) | Circulating coal mining method and mining system thereof | |
| RU2069748C1 (en) | Method for rill cut mining of thick steeply dipping beds with filling | |
| RU2211332C1 (en) | Method of preparation of bedded deposits for room mining system with retreating | |
| RU2273733C1 (en) | Method for flat-laying coal seam development | |
| SU1682566A1 (en) | Method for working paired longwalls by mechanizes complexes | |
| US3473846A (en) | Shearer-loader supported against horizontally extending forces | |
| SU1164437A1 (en) | Set for excavating steep coal beds | |
| SU1789020A3 (en) | Method for mining gently dipping mineral beds | |
| CN113153301B (en) | Horizontal sectional mechanized caving coal mining method for steeply inclined coal seam | |
| US1684597A (en) | Long-wall mining shield |