SU149200A1 - The method of installation of precast reinforced concrete shells double curvature - Google Patents

The method of installation of precast reinforced concrete shells double curvature

Info

Publication number
SU149200A1
SU149200A1 SU652981A SU652981A SU149200A1 SU 149200 A1 SU149200 A1 SU 149200A1 SU 652981 A SU652981 A SU 652981A SU 652981 A SU652981 A SU 652981A SU 149200 A1 SU149200 A1 SU 149200A1
Authority
SU
USSR - Soviet Union
Prior art keywords
reinforced concrete
installation
precast reinforced
double curvature
concrete shells
Prior art date
Application number
SU652981A
Other languages
Russian (ru)
Inventor
М.С. Грутман
И.А. Скачков
С.А. Ривкин
Original Assignee
М.С. Грутман
И.А. Скачков
С.А. Ривкин
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by М.С. Грутман, И.А. Скачков, С.А. Ривкин filed Critical М.С. Грутман
Priority to SU652981A priority Critical patent/SU149200A1/en
Application granted granted Critical
Publication of SU149200A1 publication Critical patent/SU149200A1/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

Известны способы монтажа сборных железобетонных оболочек дво кой кривизны покрытий зданий и сооружений из трапецеидальных ребристых плит. Однако такие способы сложны.Methods of mounting precast reinforced concrete shells of the double curvature of coatings of buildings and structures of trapezoidal ribbed slabs are known. However, such methods are complex.

При применении описываемого способа дл  упрощени  изготовлени  элементов и возможности монтажа их без подмостей примен ют сборные плоские плиты, которые стыкуют в плане по сплошным кольцевым и меридиональным сечени м с помощью монтажных стоек с подвесками, устанавливаемых неподвижно на опорном кольце покрыти , и замоноличивают, образу  самонесущие кольцевые по са купола.When using the described method, prefabricated flat plates are used to simplify the fabrication of the elements and install them without scaffolding, which are joined in plan along continuous annular and meridional sections using mounting racks with suspensions mounted fixedly on the support ring of the coating and monolithic to form self-supporting annular sa dome.

На фиг. 1 изображена .схема монтируемой оболочки; на фиг. 2 - трапецеидальна  ребриста  плита.FIG. 1 shows a schematic of the mounted shell; in fig. 2 - trapezoidal ribbed plate.

Способ монтажа сборных железобетонных оболочек дво кой кривизны состоит в том, что к опорному кольцу / прикрепл ют монтажные стойки 2, фиксируемые расчалками 3. Плиту 4 поднимают за петли 5 с помощью бащенного крана б с наклоном, соответствующим ее проектному положению. При этом ее одним концом опирают на кольцо 1, а другим - на установочные винты 7 фермы-щаблона 8, вращающейс  относительно крана 6. Ферма-щаблон 8 опираетс  на кольцо 9, установленное на кране 6, и на кольцевой рельс 10. После отсоедингки  от плиты 4 строп 11 к ее петл м 5 прикрепл ют подвески jf2 и с помощью нат жных муфт 13 фиксируют плиту 4 в проектном положении . Затем ферму-щаблон 8, освобожденную от установленной плиты 4, перемещают к следующей плите 4, монтаж которой производ т таким же образом, как и первой. С опорным кольцом 1 и между собой плиты 4 соедин ют посредством сварки, образу  самонесущий кольцевой по с /4, меридиональные швы 15 которого заполн ют бетоном. После затвердевани  бетона по с 14 приобретает достаточную жесткость иThe method of mounting precast reinforced concrete shells of double curvature consists in mounting racks 2 fixed by braces 3 to the support ring / fixed by the braces 3. The plate 4 is lifted by the loops 5 with the help of a tilt b-shaped crane corresponding to its design position. At the same time, one end is supported on the ring 1, and the other on the set screws 7 of the truss-blade 8, which rotates relative to the crane 6. The truss-plate 8 rests on the ring 9, mounted on the crane 6, and on the ring rail 10. After detaching from the plates 4, the sling 11, attach the suspensions jf2 to its loops 5 and with the help of the tension sleeves 13 fix the plate 4 in the design position. Then the template farm 8, freed from the installed plate 4, is moved to the next plate 4, which is assembled in the same manner as the first one. With the support ring 1 and between each other, the plates 4 are joined by welding, forming a self-supporting annular c / 4, the meridional seams 15 of which are filled with concrete. After the concrete has hardened, c 14 gains sufficient rigidity and

№ 149200- 2 прочность дл  воспри ти  собственного веса и монтажных нагрузок. После монтажа второго по са 16 заделывают бетоном кольцевой шов 17 между ним и по сом 14. При замоноличивании швов /5 и /7 в случае необходимости перед укладкой бетона устанавливают арматурные каркасы. Весь последующий монтаж оболочки (купола ) 18 1ведут вышеописанным образом, причем нижние кра  монтируемых плит 4 опирают на накладки, привариваемые к закладным част м плит предыдущего по са, а подвески -12 переставл ют с нижних по сов на верхние. При устройстве покрытий над здани ми и сооружени ми больщих пролетов в состав оболочки включают промежуточные железобетонные кольца повыщенной жесткости, используемые дл  установки монтажных стоек, снимаемых с опорного кольца.No. 149200-2 strength for absorbing its own weight and mounting loads. After the second stage is installed, 16 is embedded in concrete with an annular joint 17 between it and som 14. When reinforcing seams / 5 and / 7, if necessary, reinforcing cages are installed before laying the concrete. The entire subsequent installation of the shell (dome) 18 will be introduced as described above, with the lower edges of the mounted plates 4 resting on the lining welded to the embedded parts of the plates of the previous strip, and the suspensions -12 are rearranged from the lower parts to the upper ones. When building coatings over buildings and structures of large spans, the shell includes intermediate reinforced concrete rings of increased rigidity used to install mounting racks removed from the support ring.

Описываемый способ монтажа поз1вол ет сократить сроки возведений зданий и сооружений, на пример цирков, крытых рынков резервуаров , отстойников и т. д., уменьшить их стоимость, экономить больщое количество леса, обычно используемого на леса и подмости, а также многократно использовать монтажные приспособлени .The described installation method makes it possible to reduce the time required for erecting buildings and structures, for example, circuses, covered markets for reservoirs, settlers, etc., to reduce their cost, to save a large amount of wood, which is usually used for scaffolding and scaffolding, and to reuse mounting tools.

Предмет изобретени Subject invention

Способ монтажа сборных железобетонных оболочек дво кой кривизны покрытий зданий и сооружений из трапецеидальных ребристых плит, отличающийс  тем, что, с целью упрощени  изготовлени  элементов и возможности монтажа их без подмостей, примен ют сборные плоские плиты, которые стыкуют в гглане по сплощным кольцевым и меридиональным сечени м с помощью монтажных стоек с подвескалги , устанавливаемых неподвижно на опорном кольце покрыти , и замоноличивают , образу  самонесущие кольцевые по са купола.The method of installation of precast reinforced concrete shells of double curvature of the coatings of buildings and structures of trapezoidal ribbed plates, characterized in that, in order to simplify the manufacture of elements and the possibility of installing them without scaffolding, prefabricated flat plates are used that join in the gglan along circular annular and meridional sections m using mounting racks with suspension mounted fixedly on the support ring of the coating, and monolithic, forming a self-supporting ring on the dome of the dome.

Фаг fPhage f

SU652981A 1960-02-01 1960-02-01 The method of installation of precast reinforced concrete shells double curvature SU149200A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU652981A SU149200A1 (en) 1960-02-01 1960-02-01 The method of installation of precast reinforced concrete shells double curvature

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU652981A SU149200A1 (en) 1960-02-01 1960-02-01 The method of installation of precast reinforced concrete shells double curvature

Related Child Applications (2)

Application Number Title Priority Date Filing Date
SU813353810A Addition SU1002048A2 (en) 1981-09-04 1981-09-04 Apparatus for separating material to fractions
SU833696682A Addition SU1162509A2 (en) 1983-11-03 1983-11-03 Apparatus for dividing material into fractions,preferably fodder granules

Publications (1)

Publication Number Publication Date
SU149200A1 true SU149200A1 (en) 1961-11-30

Family

ID=48304372

Family Applications (1)

Application Number Title Priority Date Filing Date
SU652981A SU149200A1 (en) 1960-02-01 1960-02-01 The method of installation of precast reinforced concrete shells double curvature

Country Status (1)

Country Link
SU (1) SU149200A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2357055C1 (en) * 2007-11-28 2009-05-27 Закрытое акционерное общество "Управляющая компания "ВЫСО" Device for performance of works inside domelike reservoirs and premises that have circular shape in plan (versions)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2357055C1 (en) * 2007-11-28 2009-05-27 Закрытое акционерное общество "Управляющая компания "ВЫСО" Device for performance of works inside domelike reservoirs and premises that have circular shape in plan (versions)

Similar Documents

Publication Publication Date Title
WO2020118563A1 (en) Design and rapid construction methods for flush assembly of prefabricated steel beams and floor
JP2750368B2 (en) Construction method of reactor containment top slab
SU149200A1 (en) The method of installation of precast reinforced concrete shells double curvature
CN109610707A (en) A design and rapid construction method for flush assembly of prefabricated steel beams and floor slabs
CN116856543B (en) Construction methods for tiered dome steel structures
RU2078884C1 (en) Method of monolithic building erection and movable framework for its realization
US3552080A (en) Method for erecting multistory buildings
RU96105130A (en) METHOD OF CONSTRUCTION OF MONOLITHIC BUILDINGS AND STRUCTURES
JP3212231B2 (en) Plant construction method and construction equipment
CN110805346A (en) Shallow round bin assembly type bin top cover and construction process thereof
JP7012486B2 (en) Bridge construction method
SU58722A1 (en) The method of construction of reinforced concrete structures
JPH05179707A (en) Truss manufacturing method and dome construction method using truss
CN215714679U (en) Steel purlin arched bridge side span unstressed construction equipment
JPH058305B2 (en)
JPH10237886A (en) Method for constructing underground tank
RU78835U1 (en) ASSEMBLY NUMBER OF COLUMN WITH LATCHES FOR PREMIUM MONOLITHIC BUILDINGS (STRUCTURES)
JP3376388B2 (en) Roof construction method using precast panels
JPS62165185A (en) Construction method of reactor containment vessel superstructure
JPH0960114A (en) Construction method of dome-like roof
JPH1181679A (en) Construction for building
JP3345537B2 (en) Diaphragm floor of reinforced concrete containment vessel
JPH03237391A (en) Storage container constructing method for nuclear power plant
SU1313986A1 (en) Apparatus for constructing a dome roof of a building round in plan view
JPH11125014A (en) Construction method of building