RU2024691C1 - Method for protecting bridge pier against freezing swelling - Google Patents
Method for protecting bridge pier against freezing swellingInfo
- Publication number
- RU2024691C1 RU2024691C1 SU4931568A RU2024691C1 RU 2024691 C1 RU2024691 C1 RU 2024691C1 SU 4931568 A SU4931568 A SU 4931568A RU 2024691 C1 RU2024691 C1 RU 2024691C1
- Authority
- RU
- Russia
- Prior art keywords
- soil
- foundation
- pit
- freezing
- bridge pier
- Prior art date
Links
- 230000008014 freezing Effects 0.000 title claims abstract description 11
- 238000007710 freezing Methods 0.000 title claims abstract description 11
- 238000000034 method Methods 0.000 title claims description 8
- 230000008961 swelling Effects 0.000 title 1
- 239000002689 soil Substances 0.000 claims description 17
- 239000011152 fibreglass Substances 0.000 claims description 4
- 239000012212 insulator Substances 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 3
- 239000000126 substance Substances 0.000 abstract 1
- 239000011810 insulating material Substances 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 230000002209 hydrophobic effect Effects 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Изобретение относится к строительству, а именно к способам защиты фундаментов мостовых опор от выпучивания. The invention relates to construction, and in particular to methods of protecting the foundations of bridge supports from buckling.
Известен способ защиты свай от выпучивания, включающий разработку котлована вокруг сваи, засыпку гидрофобного грунта, установку конусного защитного элемента из досок и засыпку из мятой глины. A known method of protecting piles from buckling, including the development of a pit around the pile, backfilling of hydrophobic soil, installing a conical protective element from boards and backfilling from crushed clay.
Недостатком этого способа является высокая трудоемкость, связанная с многодельностью технологических операций. Кроме того, при наличии небольшого слоя воды у опоры и промерзания ее в котловане в зимний период воздействие силы морозного пучения не уменьшится, а увеличивается, так как находящаяся в котловане вода, смерзаясь с гидрофобным грунтом, превращает его в монолит, который выпучивается окружающим грунтом, а вместе с ним выпучивается и сама свая. The disadvantage of this method is the high complexity associated with the busyness of technological operations. In addition, if there is a small layer of water at the support and its freezing in the foundation pit during the winter period, the effect of frost heaving will not decrease, but will increase, since the water in the foundation pit, freezing with hydrophobic soil, turns it into a monolith, which bulges out with surrounding soil, and the pile itself bulges with it.
Цель - повышение надежности защиты фундаментов мостовых опор от воздействия морозного пучения. The goal is to increase the reliability of protecting the foundations of bridge supports from the effects of frost heaving.
Цель достигается тем, что в способе защиты, включающем разработку котлована вокруг фундамента на глубину промерзания грунта и размещение в котловане оболочки из несвязного грунта, котлован разрабатывают шириной, равной глубине промерзания грунта, а несвязный грунт заключают в многосекционную клеть, а в его качестве используют крупнообломочный грунт 5, снабженный в верхней части теплоизолирующим материалом, который покрывается стеклохолстом. The goal is achieved in that in the method of protection, including the development of a foundation pit around the foundation to the depth of freezing of the soil and placement of a shell from incoherent soil in the foundation pit, the foundation pit is developed with a width equal to the depth of freezing of the soil, and the incoherent soil is enclosed in a multi-section stand, and a large fragmentary one is used as its
В качестве теплоизолирующего материала можно применить, например, морозоустойчивый материал Дорнит-4. As a heat-insulating material, for example, frost-resistant material Dornit-4 can be used.
На фиг. 1 изображена разработка котлована; на фиг. 2 - установка клети в котлован; на фиг. 3 - готовая опора, поперечный разрез. In FIG. 1 shows the development of the pit; in FIG. 2 - installation of the stand in the pit; in FIG. 3 - ready support, cross section.
Способ осуществляют следующим образом. The method is as follows.
Производят разработку котлована, размеры которого соответствуют глубине промерзания грунта у опоры для данного грунта. A pit is being developed, the dimensions of which correspond to the depth of freezing of the soil at the support for this soil.
При наличии воды у опор мостов предварительно производят перед разработкой котлована, забивку шпунтового ограждения. If there is water at the bridge supports, the tongue and groove fencing is preliminarily performed before excavation.
После разработки котлована с помощью крана устанавливают клети, заполненные крупнообломочным грунтом, содержащие в верхней части теплоизолирующий и защитно-дренирующий материал. After development of the pit, using a crane, stands are installed, filled with coarse soil, containing heat-insulating and protective-draining material in the upper part.
В качестве теплоизолирующего материала может быть принят, например, Дорнит-4, который обладает тепломорозостойкими свойствами, а в качестве защитно-дренирующего материала может быть принят стеклохолст. По окончании процесса по установке клетей при необходимости производят извлечение шпунтового ограждения. As a heat insulating material, for example, Dornit-4, which has heat and frost resistant properties, can be adopted, and fiberglass can be adopted as a protective-draining material. At the end of the cage installation process, if necessary, the sheet piling is removed.
В некоторых случаях использования этого технического решения можно не применять и стеклохолст. Это имеет место, например, при возможности очистки клетей от заиливания или при наличии крупнообломочного грунта в русле реки, например, на горных водотоках. In some cases, the use of this technical solution may not apply fiberglass. This takes place, for example, if it is possible to clean silts from silting or in the presence of coarse soil in the river channel, for example, on mountain streams.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU4931568 RU2024691C1 (en) | 1991-04-26 | 1991-04-26 | Method for protecting bridge pier against freezing swelling |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SU4931568 RU2024691C1 (en) | 1991-04-26 | 1991-04-26 | Method for protecting bridge pier against freezing swelling |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| RU2024691C1 true RU2024691C1 (en) | 1994-12-15 |
Family
ID=21572003
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| SU4931568 RU2024691C1 (en) | 1991-04-26 | 1991-04-26 | Method for protecting bridge pier against freezing swelling |
Country Status (1)
| Country | Link |
|---|---|
| RU (1) | RU2024691C1 (en) |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2227194C1 (en) * | 2002-10-16 | 2004-04-20 | Лязгин Анатолий Леонидович | Method of foundation protection against frost heaves in soil |
| RU2227195C1 (en) * | 2002-10-16 | 2004-04-20 | Лязгин Анатолий Леонидович | Method of foundation protection against frost heaves in soil |
| RU2230854C1 (en) * | 2002-10-14 | 2004-06-20 | Лязгин Анатолий Леонидович | Method of pile foundation protection from freezing heaving |
| RU2318098C1 (en) * | 2006-04-10 | 2008-02-27 | Открытое Акционерное Общество "Проектно-изыскательский и научно-исследовательский институт по проектированию энергетических систем и электрических сетей" "Энергосетьпроект" | Seasonal freezing retarding method |
| RU2318097C1 (en) * | 2006-04-10 | 2008-02-27 | Открытое Акционерное Общество "Проектно-изыскательский и научно-исследовательский институт по проектированию энергетических систем и электрических сетей" "Энергосетьпроект" | Method to control normal heaving force acting in direction opposite to tangent heaving force action |
| RU2422589C1 (en) * | 2009-10-29 | 2011-06-27 | Институт криосферы Земли Сибирского отделения Российской Академии Наук | Method to increase strength of plastic frozen soils and foundation for method realisation |
| RU2574643C1 (en) * | 2015-01-23 | 2016-02-10 | Открытое Акционерное Общество "Российские Железные Дороги" | Method of protection of concrete foundation against forces of quelling of frozen soil |
| RU2602538C1 (en) * | 2015-09-03 | 2016-11-20 | Общество с ограниченной ответственностью "Газпром добыча Ямбург" | Method for reduction of action of forces of frost boil and increasing stability of pile foundations in permafrost zone |
| RU2769160C1 (en) * | 2021-07-29 | 2022-03-28 | Федеральное государственное казенное учреждение "12 Центральный научно-исследовательский институт" Министерства обороны Российской Федерации | Method for installation of supporting structural elements of technical means of object protection systems in seasonally freezing heaving soils |
| CN114703907A (en) * | 2021-11-19 | 2022-07-05 | 中国科学院西北生态环境资源研究院 | A kind of rectification structure and rectification method for freezing and pulling disease of pile during operation period |
-
1991
- 1991-04-26 RU SU4931568 patent/RU2024691C1/en active
Non-Patent Citations (1)
| Title |
|---|
| Паталеев А.В. Фундаменты в пучинистых грунтах, Хабаровское книжное издательство, 1955, с.85, рис.38. * |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2230854C1 (en) * | 2002-10-14 | 2004-06-20 | Лязгин Анатолий Леонидович | Method of pile foundation protection from freezing heaving |
| RU2227194C1 (en) * | 2002-10-16 | 2004-04-20 | Лязгин Анатолий Леонидович | Method of foundation protection against frost heaves in soil |
| RU2227195C1 (en) * | 2002-10-16 | 2004-04-20 | Лязгин Анатолий Леонидович | Method of foundation protection against frost heaves in soil |
| RU2318098C1 (en) * | 2006-04-10 | 2008-02-27 | Открытое Акционерное Общество "Проектно-изыскательский и научно-исследовательский институт по проектированию энергетических систем и электрических сетей" "Энергосетьпроект" | Seasonal freezing retarding method |
| RU2318097C1 (en) * | 2006-04-10 | 2008-02-27 | Открытое Акционерное Общество "Проектно-изыскательский и научно-исследовательский институт по проектированию энергетических систем и электрических сетей" "Энергосетьпроект" | Method to control normal heaving force acting in direction opposite to tangent heaving force action |
| RU2422589C1 (en) * | 2009-10-29 | 2011-06-27 | Институт криосферы Земли Сибирского отделения Российской Академии Наук | Method to increase strength of plastic frozen soils and foundation for method realisation |
| RU2574643C1 (en) * | 2015-01-23 | 2016-02-10 | Открытое Акционерное Общество "Российские Железные Дороги" | Method of protection of concrete foundation against forces of quelling of frozen soil |
| RU2602538C1 (en) * | 2015-09-03 | 2016-11-20 | Общество с ограниченной ответственностью "Газпром добыча Ямбург" | Method for reduction of action of forces of frost boil and increasing stability of pile foundations in permafrost zone |
| RU2769160C1 (en) * | 2021-07-29 | 2022-03-28 | Федеральное государственное казенное учреждение "12 Центральный научно-исследовательский институт" Министерства обороны Российской Федерации | Method for installation of supporting structural elements of technical means of object protection systems in seasonally freezing heaving soils |
| CN114703907A (en) * | 2021-11-19 | 2022-07-05 | 中国科学院西北生态环境资源研究院 | A kind of rectification structure and rectification method for freezing and pulling disease of pile during operation period |
| CN114703907B (en) * | 2021-11-19 | 2023-11-03 | 中国科学院西北生态环境资源研究院 | Pile column operation period freeze-pulling disease remediation structure and remediation method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| RU2024691C1 (en) | Method for protecting bridge pier against freezing swelling | |
| Rasmussen | Concrete immersed tunnels—Forty years of experience | |
| US4080797A (en) | Artificial ice pad for operating in a frigid environment | |
| JPS55122916A (en) | Method for building prestressed concrete-made pier foundation | |
| RU2064554C1 (en) | Method for running pipeline through sagging and swelling soils | |
| JP3075179B2 (en) | Bridge pier foundation structure and its construction method | |
| JPH06983B2 (en) | Protective method of underground structure in sand ground that is easily liquefied | |
| CN206591535U (en) | Combined type cofferdam | |
| JP2814898B2 (en) | Underground storage facility | |
| US20090252555A1 (en) | Protective wall, dyke and method of producing a dyke | |
| KR20040084126A (en) | Dry Construction Method of Underwater Structure Using Watertight Caisson | |
| Sonu et al. | Harry Seed, liquefaction and the gravel drain | |
| RU2193086C2 (en) | Coast-protecting structure | |
| RU2081246C1 (en) | Method for providing seismic insulation of building foundation | |
| SU977555A1 (en) | Retaining wall | |
| Charlwood et al. | A review of the performance of two large sub-stations and eight large dams during the Chi Chi Taiwan earthquake | |
| RU2791119C1 (en) | Method for construction of geotechnical structures in the water area of urban rivers and canals | |
| How | Stability and survival | |
| Ojha | Rehabilitation of sunkoshi small hydropower plant (2.6 mk), nepal after sequences of natural disaster | |
| SU1497338A1 (en) | Shore-protecting arrangement | |
| JPS56105023A (en) | Preventing method for frost heaving of pile | |
| SU642437A1 (en) | Arrangement for protecting beds and foundations of constructions built on ever-frozen soils from ground water | |
| JPS61155514A (en) | Mass concrete pouring method | |
| JPH086337B2 (en) | Foundation construction method and foundation pile | |
| RU2149947C1 (en) | Method for stabilization of washing-away banks of tundra rivers |