RU2010119568A - METAL COOLING METHOD FOR CONTINUOUS CASTING - Google Patents

METAL COOLING METHOD FOR CONTINUOUS CASTING Download PDF

Info

Publication number
RU2010119568A
RU2010119568A RU2010119568/02A RU2010119568A RU2010119568A RU 2010119568 A RU2010119568 A RU 2010119568A RU 2010119568/02 A RU2010119568/02 A RU 2010119568/02A RU 2010119568 A RU2010119568 A RU 2010119568A RU 2010119568 A RU2010119568 A RU 2010119568A
Authority
RU
Russia
Prior art keywords
cooler
cooling
supply
ingot
sections
Prior art date
Application number
RU2010119568/02A
Other languages
Russian (ru)
Other versions
RU2446913C2 (en
Inventor
Юрий Моисеевич Айзин (RU)
Юрий Моисеевич Айзин
Александр Валентинович Куклев (RU)
Александр Валентинович Куклев
Григорий Валерьевич Сгибнев (RU)
Григорий Валерьевич Сгибнев
Александр Михайлович Логинов (RU)
Александр Михайлович Логинов
Original Assignee
Закрытое акционерное общество "Корад" (RU)
Закрытое акционерное общество "КОРАД"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Закрытое акционерное общество "Корад" (RU), Закрытое акционерное общество "КОРАД" filed Critical Закрытое акционерное общество "Корад" (RU)
Priority to RU2010119568/02A priority Critical patent/RU2446913C2/en
Publication of RU2010119568A publication Critical patent/RU2010119568A/en
Application granted granted Critical
Publication of RU2446913C2 publication Critical patent/RU2446913C2/en

Links

Landscapes

  • Continuous Casting (AREA)

Abstract

1. Способ охлаждения металла при непрерывной разливке, включающий заливку его в кристаллизатор, вытягивание слитка из кристаллизатора с переменной скоростью, поддержание и направление слитка, охлаждение его водой или водовоздушной смесью, распыляемой в виде факелов форсунками, изменение удельных расходов охладителя вдоль зоны вторичного охлаждения в зависимости от скорости вытягивания от максимального значения под кристаллизатором до минимального в конце зоны, регулирование интенсивности охлаждения и циклическим законом подачи охладителя, отличающийся тем, что зону вторичного охлаждения вдоль широких граней слитка разделяют на три участка, центральный и два периферийных, с раздельным регулированием подачи охладителя, при этом производят чередование по времени циклов подачи или отключения охладителя центрального и периферийных участков слитка, а период циклов Т устанавливается равным ! Т=τ1+τ2, где ! τ1=(L·K1)/(V·100), ! τ2=(L·K2)/(V·100), ! τ1 - цикл отключения подачи охладителя на периферийные участки, мин; ! τ2 - цикл отключения подачи охладителя на центральный участок, мин; ! L - длина жидкой фазы = (H2·V)/4·K3 2, м; ! Н - толщина разливаемой заготовки мм, ! V - скорость разливки металла, м/мин; ! K1 - коэффициент учитывающий марочный сортамент разливаемой стали, устанавливается в пределах от 1 до 8; ! K2 - коэффициент учитывающий время отключения периферийных участков, устанавливается в пределах от 1 до 8, в зависимости от марочного сортамента разливаемой стали; ! K3 - коэффициент затвердевания стали, мм·мин-0,5. ! 2. Способ по п.1, отличающийся тем, что циклы подачи или отключения охладителя на центральный и периферийные участки охлаж 1. A method of cooling the metal during continuous casting, including pouring it into the mold, pulling the ingot from the mold at a variable speed, maintaining and directing the ingot, cooling it with water or a water-air mixture sprayed in the form of flares by nozzles, changing the specific flow rates of the cooler along the secondary cooling zone to depending on the drawing speed from the maximum value under the mold to the minimum at the end of the zone, regulation of the cooling intensity and the cyclic law of cooling supply A distinction, characterized in that the secondary cooling zone along the wide faces of the ingot is divided into three sections, the central and two peripheral, with separate control of the supply of the cooler, while alternating in time the supply or shutdown cycles of the cooler of the central and peripheral sections of the ingot, and the cycle period T set equal! T = τ1 + τ2, where! τ1 = (L · K1) / (V · 100),! τ2 = (L · K2) / (V · 100),! τ1 - shutdown cycle of the cooler supply to peripheral sections, min; ! τ2 — cycle of shutting off the supply of cooler to the central section, min; ! L is the length of the liquid phase = (H2 · V) / 4 · K3 2, m; ! N is the thickness of the cast billet mm,! V - metal casting speed, m / min; ! K1 - coefficient taking into account the grade range of cast steel, is set in the range from 1 to 8; ! K2 - coefficient taking into account the shutdown time of peripheral sections, is set in the range from 1 to 8, depending on the grade of steel being cast; ! K3 - coefficient of solidification of steel, mm · min-0.5. ! 2. The method according to claim 1, characterized in that the supply or shutdown cycles of the cooler to the central and peripheral cooling sections

Claims (3)

1. Способ охлаждения металла при непрерывной разливке, включающий заливку его в кристаллизатор, вытягивание слитка из кристаллизатора с переменной скоростью, поддержание и направление слитка, охлаждение его водой или водовоздушной смесью, распыляемой в виде факелов форсунками, изменение удельных расходов охладителя вдоль зоны вторичного охлаждения в зависимости от скорости вытягивания от максимального значения под кристаллизатором до минимального в конце зоны, регулирование интенсивности охлаждения и циклическим законом подачи охладителя, отличающийся тем, что зону вторичного охлаждения вдоль широких граней слитка разделяют на три участка, центральный и два периферийных, с раздельным регулированием подачи охладителя, при этом производят чередование по времени циклов подачи или отключения охладителя центрального и периферийных участков слитка, а период циклов Т устанавливается равным1. A method of cooling the metal during continuous casting, including pouring it into the mold, pulling the ingot from the mold at a variable speed, maintaining and directing the ingot, cooling it with water or a water-air mixture sprayed in the form of flares by nozzles, changing the specific flow rates of the cooler along the secondary cooling zone to depending on the drawing speed from the maximum value under the mold to the minimum at the end of the zone, regulation of the cooling intensity and the cyclic law of cooling supply A distinction, characterized in that the secondary cooling zone along the wide faces of the ingot is divided into three sections, the central and two peripheral, with separate control of the supply of the cooler, while alternating in time the supply or shutdown cycles of the cooler of the central and peripheral sections of the ingot, and the cycle period T set equal Т=τ12, гдеT = τ 1 + τ 2 , where τ1=(L·K1)/(V·100),τ 1 = (L · K 1 ) / (V · 100), τ2=(L·K2)/(V·100),τ 2 = (L · K 2 ) / (V · 100), τ1 - цикл отключения подачи охладителя на периферийные участки, мин;τ 1 - shutdown cycle of the supply of cooler to the peripheral sections, min; τ2 - цикл отключения подачи охладителя на центральный участок, мин;τ 2 - shutdown cycle of the cooler supply to the central section, min; L - длина жидкой фазы = (H2·V)/4·K32, м;L is the length of the liquid phase = (H 2 · V) / 4 · K 3 2 , m; Н - толщина разливаемой заготовки мм,N is the thickness of the cast billet mm, V - скорость разливки металла, м/мин;V - metal casting speed, m / min; K1 - коэффициент учитывающий марочный сортамент разливаемой стали, устанавливается в пределах от 1 до 8;K 1 - coefficient taking into account the grade range of cast steel, is set in the range from 1 to 8; K2 - коэффициент учитывающий время отключения периферийных участков, устанавливается в пределах от 1 до 8, в зависимости от марочного сортамента разливаемой стали;K 2 - coefficient taking into account the shutdown time of the peripheral sections, is set in the range from 1 to 8, depending on the grade of steel being cast; K3 - коэффициент затвердевания стали, мм·мин-0,5.K 3 - coefficient of solidification of steel, mm · min -0.5 . 2. Способ по п.1, отличающийся тем, что циклы подачи или отключения охладителя на центральный и периферийные участки охлаждения производят с перекрытием во времени где τ31/5, а период циклов Т устанавливается равным2. A method according to claim 1, characterized in that the feed cycles or off to the central cooling and peripheral cooling sections is carried out with a time overlap where τ 3 = τ 1/5, and the period of cycle T is set equal to Т=τ423, гдеT = τ 4 + τ 2 + τ 3 , where τ413=(1-1/5)·(L·K1)/(V·100),τ 4 = τ 13 = (1-1 / 5) · (L · K 1 ) / (V · 100), τ2=(L·K2)/(V·100),τ 2 = (L · K 2 ) / (V · 100), τ31/5,τ 3 = τ 1/5, τ4 - цикл отключения подачи охладителя на периферийные участки, мин;τ 4 - shutdown cycle of the cooler supply to peripheral sections, min; τ3 - цикл перекрытия, мин.τ 3 - overlap cycle, min. 3. Способ по любому из пп.1 или 2, отличающийся тем, что охлаждение центрального и периферийных участков слитка производят чередованием циклов подачи и снижения расхода охладителя с рабочего до минимального. 3. The method according to any one of claims 1 or 2, characterized in that the cooling of the central and peripheral sections of the ingot is carried out by alternating supply cycles and reducing the flow rate of the cooler from the working to the minimum.
RU2010119568/02A 2010-05-18 2010-05-18 Method of metal cooling in continuous casting RU2446913C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2010119568/02A RU2446913C2 (en) 2010-05-18 2010-05-18 Method of metal cooling in continuous casting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2010119568/02A RU2446913C2 (en) 2010-05-18 2010-05-18 Method of metal cooling in continuous casting

Publications (2)

Publication Number Publication Date
RU2010119568A true RU2010119568A (en) 2011-11-27
RU2446913C2 RU2446913C2 (en) 2012-04-10

Family

ID=45317462

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2010119568/02A RU2446913C2 (en) 2010-05-18 2010-05-18 Method of metal cooling in continuous casting

Country Status (1)

Country Link
RU (1) RU2446913C2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BR102015009492B1 (en) 2015-01-30 2021-05-04 Jfe Steel Corporation continuous steel casting method

Also Published As

Publication number Publication date
RU2446913C2 (en) 2012-04-10

Similar Documents

Publication Publication Date Title
MX2018011649A (en) Liquid metal jet optimization in direct chill casting.
MX2015011501A (en) Centrifugal casting method and apparatus.
UA122515C2 (en) SPRAYER AND METAL WIRE COOLING METHOD IN CONTINUOUS CASTING MACHINE
RU2010119568A (en) METAL COOLING METHOD FOR CONTINUOUS CASTING
CN102527960A (en) Novel crystallizer for horizontal continuous casting
MX2013006750A (en) Coolant control and wiper system for a continuous casting molten metal mold.
EP4052815A4 (en) METHOD AND DEVICE FOR AUXILIARY COOLING FOR CONTINUOUS CAST SLAB
MY190292A (en) Continuous casting method
RU2017127077A (en) METHOD FOR CONTINUOUS CASTING OF STEEL
CN103537642A (en) Novel method for controlling casting blank pull rate of round continuous casting machine
CN103128238A (en) Method utilizing slab crystallizer to continuously pour square billets
CN202984612U (en) Water cooling device of horizontal continuous casting machine
MX2020007903A (en) Submerged entry nozzle for continuous casting.
CN103212680B (en) A kind of crystallization wheel wall temperature adjusting device
CN102950264A (en) Gas-water spraying device for continuous casting
CN103752782B (en) Opposite roller type small-size ingot casting horizontal continuous casting system
CN103212685B (en) Pouring pot liquid level constant device
EA201491829A1 (en) CRYSTALIZER FOR CONTINUOUS CASTING INGOT FROM TITANIUM OR TITANIUM ALLOY AND UNIT WITH A DEVICE FOR CONTINUOUS CASTING
RU2015135384A (en) METHOD FOR CONTINUOUS CASTING OF SLAB FROM TITANIUM OR TITANIUM ALLOY
CN201960097U (en) Step-shaped copper pipe of crystallizer
RU2015133468A (en) CONTINUOUS CASTING METHOD FOR INGOT MADE FROM TITANIUM OR TITANIUM ALLOY
EA201101485A1 (en) METHOD OF CONTINUOUS STEEL CASTING AND SUBMERSIBLE GLASS FOR CONTINUOUS STEEL CASTING
CN204276894U (en) A kind of waveform submersed nozzle
RU2007113580A (en) METHOD FOR CONTINUOUS INJECTION CASTING
CN203281872U (en) Pouring pot adjustment device

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20130519