RU123824U1 - GAS WELL DESIGN - Google Patents

GAS WELL DESIGN Download PDF

Info

Publication number
RU123824U1
RU123824U1 RU2012129796/03U RU2012129796U RU123824U1 RU 123824 U1 RU123824 U1 RU 123824U1 RU 2012129796/03 U RU2012129796/03 U RU 2012129796/03U RU 2012129796 U RU2012129796 U RU 2012129796U RU 123824 U1 RU123824 U1 RU 123824U1
Authority
RU
Russia
Prior art keywords
pipeline
automatic control
crosspiece
gas
design
Prior art date
Application number
RU2012129796/03U
Other languages
Russian (ru)
Inventor
Алексей Владимирович Немков
Александр Васильевич Кустышев
Игорь Владимирович Шулятиков
Антон Сергеевич Епрынцев
Дмитрий Александрович Кряквин
Виктор Владимирович Моисеев
Original Assignee
Общество с ограниченной ответственностью "ТюменНИИгипрогаз"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Общество с ограниченной ответственностью "ТюменНИИгипрогаз" filed Critical Общество с ограниченной ответственностью "ТюменНИИгипрогаз"
Priority to RU2012129796/03U priority Critical patent/RU123824U1/en
Application granted granted Critical
Publication of RU123824U1 publication Critical patent/RU123824U1/en

Links

Images

Landscapes

  • Flow Control (AREA)
  • Earth Drilling (AREA)

Abstract

Конструкция газовой скважины, включающая кондуктор, эксплуатационную, основную и центральную лифтовые колонны, подвешенные соответственно в колонной головке, переводной катушке трубной головки и переводнике нижней крестовины, коренную и надкоренную задвижки, верхнюю крестовину, при этом верхняя и нижняя крестовины соединены между собой посредством трубопроводов, объединенных в единый трубопровод, на трубопроводе от верхней крестовины и на общем трубопроводе размещены расходомеры, а на трубопроводе от нижней крестовины размещен автоматический регулирующий клапан, возле устья скважины размещен автоматический управляющий комплекс, связанный с расходомерами и автоматическим регулирующим клапаном.The design of a gas well, including a conductor, production, main and central lift columns, suspended respectively in the column head, the transfer coil of the pipe head and the sub of the lower cross, the root and root valves, the upper cross, the upper and lower crosses are interconnected via pipelines, united in a single pipeline, flow meters are placed on the pipeline from the upper crosspiece and on the common pipeline, and cars are placed on the pipeline from the lower crosspiece mathematical control valve, near the wellhead there is an automatic control complex associated with flowmeters and an automatic control valve.

Description

Устройство относится к нефтегазодобывающей промышленности, а именно к конструкции самозадавливающихся газовых скважин для эксплуатации на завершающей стадии разработки газовых месторождений, в частности к эксплуатации, так называемых, самозадавливающихся газовых скважин, то есть скважин, в которых скорости газового потока недостаточны для выноса жидкости с забоя.The device relates to the oil and gas industry, in particular to the design of self-priming gas wells for operation at the final stage of development of gas fields, in particular to the operation of so-called self-priming gas wells, that is, wells in which the gas flow rate is insufficient to remove the liquid from the bottom.

Газовые месторождения разрабатываются скважинами, конструкция которых содержит ряд обсадных колонн со спущенной во внутреннюю эксплуатационную колонну лифтовой колонны. Устье газовых скважин оборудовано колонной головкой и фонтанной арматурой, состоящей из трубной головки с боковыми отводами и фонтанной елки с коренной и надкоренной задвижками и крестовиной с рабочей и резервной струнами. Рабочие струны крестовины фонтанной елки соединены с боковыми отводами трубной головки трубопроводами, соединяющиеся в единый трубопровод.Gas fields are developed by wells, the design of which contains a number of casing strings with an elevator string lowered into the inner production string. The mouth of gas wells is equipped with a column head and fountain fittings, consisting of a pipe head with lateral branches and a fountain tree with root and root valves and a cross with a working and reserve strings. The working strings of the spider of the fountain tree are connected to the lateral branches of the pipe head by pipelines, connected to a single pipeline.

На завершающей стадии разработки газовых месторождений в связи со снижением пластовой энергии на забое скважины образовывается жидкостная пробка за счет поступления на забой из пласта пластовой воды или выпадения из добываемого газа и осаждения на забое конденсационной воды. Под воздействием все увеличивающего объема этой жидкости скважины останавливаются, так как энергии пласта и соответственно скорости восходящего потока газа не достаточно для выноса жидкости на поверхность. При достижении определенной высоты столба этой жидкости на забое газ из пласта не может преодолеть жидкостный барьер и скважина самозадавливается, то есть глушится [Кустышев А.В. Сложные ремонты газовых скважин на месторождениях Западной Сибири.- М.: ООО «Газпром экспо», 2010. - 212 с.].At the final stage of development of gas fields, due to a decrease in the reservoir energy, a liquid plug is formed at the bottom of the well due to the arrival of produced water from the reservoir or loss of produced gas and deposition of condensation water on the bottom. Under the influence of an ever-increasing volume of this fluid, the wells stop, since the reservoir energy and, accordingly, the velocity of the upward gas flow are not enough to carry the fluid to the surface. When a certain column height of this fluid is reached at the bottom, gas from the formation cannot overcome the fluid barrier and the well self-pressures, that is, it shuts off [A. Kustyshev Complicated repairs of gas wells in the fields of Western Siberia .- M .: OOO Gazprom Expo, 2010. - 212 p.].

Для предотвращения этого явления и обеспечения выноса жидкости на поверхность применяют различные способы и устройства: технологические отработки скважины на факел, закачивание в скважину поверхностно-активных веществ; уменьшение диаметра лифтовой колонны; применение плунжерного лифта.To prevent this phenomenon and ensure the removal of fluid to the surface, various methods and devices are used: technological development of a well on a torch, injection of surfactants into a well; reducing the diameter of the elevator column; the use of a plunger lift.

В последние годы начинает использоваться технология одновременной добычи газа по трубному и затрубному пространствам скважины [А.С. 345266 СССР. E21B 43/00. 1972. Бюл. №22]. Технология заключается в ограничении отбора газа из затрубного пространства путем дросселирования и обеспечения выноса скопившейся на забое жидкости на поверхность через лифтовую колонну.In recent years, technology has begun to be used for the simultaneous production of gas through the pipe and annular spaces of the well [A.S. 345266 USSR. E21B 43/00. 1972. Bull. No. 22]. The technology consists in limiting the extraction of gas from the annulus by throttling and ensuring the removal of fluid accumulated at the bottom to the surface through the elevator column.

Недостатком этой конструкции является недостаточная эффективность удаления жидкости с забоя, приводящая к ее скапливанию на забое и «самозадавливанию», не контролируемому глушению, скважины, а также низкая надежность скважины по причине абразивного и коррозионного износа эксплуатационной колонны при отборе газа по затрубному пространству, что запрещено правилами безопасности в нефтяной и газовой промышленности.The disadvantage of this design is the insufficient efficiency of liquid removal from the bottom, leading to its accumulation at the bottom and "self-squeezing", uncontrolled killing of the well, as well as low reliability of the well due to abrasive and corrosive wear of the production string during gas extraction through the annulus, which is prohibited safety rules in the oil and gas industry.

Задача создания полезной модели заключается в повышении надежности конструкции самозадавливающейся газовой скважины.The task of creating a utility model is to increase the reliability of the design of a self-filling gas well.

Достигаемый технический результат, который получается в результате создания полезной модели, состоит в устранении причин самозадавливания газовой скважины за счет автоматического выноса жидкости с забоя и в ликвидации абразивного и коррозионного износа эксплуатационной колонны за счет недопущения добычи газа через затрубное пространство.The achieved technical result, which is obtained as a result of creating a utility model, is to eliminate the causes of self-jamming of a gas well due to automatic removal of fluid from the bottom and to eliminate abrasive and corrosive wear of the production string due to the prevention of gas production through the annulus.

Технический результат достигается тем, что конструкция самозадавливающейся газовой скважины включает кондуктор, эксплуатационную, основную и центральную лифтовые колонны, подвешенные соответственно в колонной головке, переводной катушке трубной головки и переводнике нижней крестовины, коренную и надкоренную задвижки, верхнюю крестовину, при этом верхняя и нижняя крестовины соединены между собой посредством трубопроводов, объединяющиеся в единый трубопровод, на трубопроводе от верхней крестовины и на общем трубопроводе размещены расходомеры, а на трубопроводе от нижней крестовины размещен автоматический регулирующий клапан, возле устья скважины размещен автоматический управляющий комплекс, связанный с расходомерами и автоматическим регулирующим клапаном.The technical result is achieved by the fact that the design of a self-priming gas well includes a conductor, production, main and central lift columns suspended respectively in the column head, the transfer coil of the pipe head and the sub of the lower cross, the root and root valves, the upper cross, the upper and lower crosses interconnected by pipelines, combined into a single pipeline, on the pipeline from the upper cross and placed on a common pipeline skhodomery, and the pipeline is placed on the lower crosspiece automatic control valve at the wellhead is placed automatic control complex associated with flow and automatic control valve.

На фиг. изображена заявляемая конструкция самозадавливающейся газовой скважины.In FIG. depicted the claimed design of a self-priming gas well.

Конструкция самозадавливающейся газовой скважины включает кондуктор 1, концентрично установленную в нем эксплуатационную колонну 2, подвешенную в колонной головке 3. Внутри эксплуатационной колонны 2 размещена основная лифтовая колонна (ОЛК) 4, подвешенная в переводной катушке 5 трубной головки 6, которая установлена на верхнем фланце колонной головки 3. На верхнем фланце переводной катушки 5 размещена нижняя крестовина 7. Внутри ОЛК 4 размещена центральная лифтовая колонна (ЦЛК) 8, смонтированная из труб меньшего диаметра и подвешенная в переводнике 9, который установлен на нижней крестовины 7. Между основной 4 и центральной 8 лифтовыми колоннами образовано кольцевое пространство (КП) 10. На верхнем фланце переводника 9 установлены коренная 11 и надкоренная 12 задвижки и верхняя крестовина 13.The design of a self-priming gas well includes a conductor 1, a production casing 2 concentrically mounted in it, suspended in a casing head 3. Inside the production casing 2 there is a main lift casing (OLK) 4 suspended in a transfer coil 5 of the pipe head 6, which is mounted on the upper flange of the casing heads 3. On the upper flange of the transfer coil 5 there is a lower crosspiece 7. Inside the OLK 4 there is a central lift column (CLK) 8 mounted from pipes of smaller diameter and suspended in a evodnik 9, which is installed on the lower crosspiece 7. Between the main 4 and the central 8 lift columns, an annular space (CP) 10 is formed. 10. On the upper flange of the sub 9 there are installed a root 11 and an over-root 12 valve and an upper cross 13.

Верхняя крестовина 13 соединена с нижней крестовиной 7 трубопроводами 14 и 15, образуя после соединения единый трубопровод 16. На трубопроводе 14 и едином трубопроводе 16 размещены расходомеры (Р) 17 и 18, например, типа «трубы Вентури», сигналы от которых поступают на автоматический управляющий комплекс (АУК) 19, размещенный возле устья скважины. На трубопроводе 15 от нижней крестовины 7 размещен автоматический регулирующий клапан (РК) 20, управляемый посредством сигнала, передаваемого от автоматического управляющего комплекса 19.The upper crosspiece 13 is connected to the lower crosspiece 7 by pipelines 14 and 15, forming a single pipeline 16 after the connection. Flow meters (P) 17 and 18, for example, of the “Venturi pipe” type, are placed on the pipeline 14 and the single pipeline 16, the signals from which are sent to the automatic control complex (AUK) 19, located near the wellhead. On the pipeline 15 from the lower crosspiece 7 is placed an automatic control valve (PK) 20, controlled by a signal transmitted from the automatic control complex 19.

Скважина заявляемой конструкции работает следующим образом.The well of the claimed design works as follows.

После спуска во внутреннюю полость основной лифтовой колонны (ОЛК) 4 центральной лифтовой колонны (ЦЛК) 8, подвески ее в переводнике 9 и завершения монтажа на верхнем фланце переводника 9 коренной 11 и надкоренной 12 задвижек и верхней крестовины 13 с трубопроводом 14 и монтажа единого трубопровода 6, соединяющего трубопровод 14 с трубопроводом 15 от нижней крестовины 7, проводится вызов притока из пласта и отработка скважины на факел.After descent into the inner cavity of the main lift column (OLK) 4 of the central lift column (CLK) 8, suspend it in the sub 9 and complete the installation on the upper flange of the sub 9 of the root 11 and 12 root valves and the upper cross 13 with the pipe 14 and the installation of a single pipeline 6, connecting the pipeline 14 to the pipeline 15 from the lower crosspiece 7, the inflow from the reservoir is called and the well is flared.

Скважина вводится в эксплуатацию с одновременным отбором газа по центральной лифтовой колонне 8, размещенной во внутренней полости основной лифтовой колонны 4 и по кольцевому пространству (КП) 10, образованному основной 4 и центральной 8 лифтовыми колоннами.The well is put into operation with the simultaneous extraction of gas through the central lift column 8 located in the inner cavity of the main lift column 4 and along the annular space (KP) 10 formed by the main 4 and central 8 lift columns.

В процессе эксплуатации на забое 21 скважины образовывается жидкостная пробка за счет поступления на забой 21 пластовой воды или выпадения из газа и осаждения на забое 21 конденсационной воды. При определенных скоростях, например, выше 5 м/с, жидкость с забоя 21 вместе с газовым потоком выносится на устье скважины, при меньшей скорости жидкость перестает выноситься и остается на забое 21 в виде жидкостной пробки. Расходомеры 17 и 18, установленные на трубопроводе 14 от верхней крестовины 13 и едином трубопроводе 16 подают сигналы о величинах рабочих дебитов на автоматический управляющий комплекс (АУК) 19. Автоматический управляющий комплекс (АУК) 19 автоматически осуществляет обработку поступившей информации и на автоматический регулирующий клапан (РК) 20 поступает сигнал об изменении проходного сечения клапана, а значит об изменении дебитов в кольцевом пространстве (КП) 10 и в центральной лифтовой колонне (ЦЛК) 8.During operation, a liquid plug is formed at the bottom of 21 wells due to the arrival of produced water at the bottom of 21 or loss of gas from the gas and deposition of condensation water at the bottom of 21. At certain speeds, for example, above 5 m / s, the liquid from the bottom 21 along with the gas stream is discharged to the wellhead, at a lower speed, the liquid ceases to be discharged and remains at the bottom 21 in the form of a liquid plug. Flow meters 17 and 18 installed on the pipe 14 from the upper crosspiece 13 and the single pipe 16 give signals about the values of the working flow rates to the automatic control complex (AUC) 19. The automatic control complex (AUC) 19 automatically processes the received information and to the automatic control valve ( RK) 20, a signal is received about a change in the flow area of the valve, and therefore about a change in flow rates in the annular space (KP) 10 and in the central lift column (TsLK) 8.

Предлагаемая конструкция позволяет эксплуатировать самозадавливающуюся газовую скважину без проведения ее капитального ремонта, что на порядок снижает затраты на эксплуатацию скважины.The proposed design allows the operation of a self-squeezing gas well without major repairs, which reduces the cost of operating the well by an order of magnitude.

Пример №1 реализации конструкции самозадавливающейся газовой скважины. Конструкция самозадавливающейся газовой скважины включает кондуктор, смонтированный из обсадных труб диаметром 324 мм, эксплуатационную колонну, смонтированную из обсадных труб диаметром 219 мм, подвешенную в колонной головке ОКК1-210-324×219. Внутри эксплуатационной колонны размещена основная лифтовая колонна из лифтовых труб диаметром 168 мм, подвешенная в переводной катушке трубной головки фонтанной арматуры АФ6-150/100×210, которая установлена на верхнем фланце колонной головки. Внутри основной лифтовой колонны размещена центральная лифтовая колонна из насосно-компрессорных труб диаметром 89 мм, подвешенная в переводнике, который установлен на нижней крестовине. Между основной лифтовой колонной диаметром 168 мм и центральной лифтовой колонной образовано кольцевое пространство. На верхнем фланце переводника установлена верхняя крестовина с трубопроводом проходным сечением 80 мм, который соединен с трубопроводом от нижней крестовины, образуя после соединения единый трубопровод. На трубопроводе от верхней крестовины и единого трубопровода размещены расходомеры типа «трубы Вентури», сигналы от которых поступают на автоматический управляющий комплекс, размещенный возле устья скважины. На трубопроводе от нижней крестовины размещен автоматический регулирующий клапан РК-100×21, управляемый посредством сигнала, передаваемого от автоматического управляющего комплекса.Example No. 1 of the implementation of the design of a self-priming gas well. The design of a self-filling gas well includes a conductor mounted from casing pipes with a diameter of 324 mm, a production casing mounted from casing pipes with a diameter of 219 mm, suspended in a casing head OKK1-210-324 × 219. Inside the production casing, the main lift casing of lift pipes with a diameter of 168 mm is placed, suspended in the transfer coil of the tube head of the fountain fittings AF6-150 / 100 × 210, which is mounted on the upper flange of the column head. Inside the main lift column there is a central lift column of tubing with a diameter of 89 mm suspended in a sub that is mounted on the lower crosspiece. An annular space is formed between the main lift column with a diameter of 168 mm and the central lift column. An upper crosspiece is installed on the upper flange of the sub with a pipe with a flow-through section of 80 mm, which is connected to the pipeline from the lower crosspiece, forming a single pipeline after connection. On the pipeline from the upper crosspiece and a single pipeline, flow meters of the "Venturi pipe" type are placed, the signals from which are fed to an automatic control complex located near the wellhead. An automatic control valve RK-100 × 21, controlled by a signal transmitted from an automatic control complex, is located on the pipeline from the lower crosspiece.

Пример №2 реализации конструкции самозадавливающейся газовой скважины. Конструкция самозадавливающейся газовой скважины включает кондуктор, смонтированный из обсадных труб диаметром 245 мм, эксплуатационную колонну, смонтированную из обсадных труб диаметром 168 мм, подвешенную в колонной головке ОКК1-210-245×168. Внутри эксплуатационной колонны размещена основная лифтовая колонна из лифтовых труб диаметром 114 мм, подвешенная в переводной катушке трубной головки фонтанной арматуры АФ6-100/100×210, которая установлена на верхнем фланце колонной головки. Внутри основной лифтовой колонны размещена центральная лифтовая колонна из насосно-компрессорных труб диаметром 73 мм, подвешенная в переводнике, который установлен на нижней крестовине. Между основной лифтовой колонной диаметром 114 мм и центральной лифтовой колонной образовано кольцевое пространство. На верхнем фланце переводника установлена верхняя крестовина с трубопроводом проходным сечением 65 мм. Верхняя крестовина соединена с нижней крестовиной, образуя после соединения единый трубопровод. На трубопроводе от верхней крестовины и едином трубопроводе размещены расходомеры типа «трубы Вентури», сигналы от которых поступают на автоматический управляющий комплекс, размещенный возле устья скважины. На трубопроводе от нижней крестовины размещен автоматический регулирующий клапан РК-80×21, управляемый посредством сигнала, передаваемого от автоматического управляющего комплекса.Example No. 2 of the implementation of the design of a self-priming gas well. The design of a self-filling gas well includes a conductor mounted from casing pipes with a diameter of 245 mm, a production casing mounted from casing pipes with a diameter of 168 mm, suspended in a casing head OKK1-210-245 × 168. Inside the production casing, the main lift casing of elevator pipes with a diameter of 114 mm is located, suspended in the transfer coil of the tube head of the fountain fittings AF6-100 / 100 × 210, which is mounted on the upper flange of the column head. Inside the main lift column there is a central lift column of tubing 73 mm in diameter, suspended in a sub that is mounted on the lower crosspiece. An annular space is formed between the main lift column with a diameter of 114 mm and the central lift column. An upper crosspiece is installed on the upper flange of the sub with a 65 mm cross-section pipe. The upper crosspiece is connected to the lower crosspiece, forming a single pipeline after connection. On the pipeline from the upper cross and a single pipeline there are placed venturi-type flow meters, the signals from which are fed to an automatic control complex located near the wellhead. An automatic control valve RK-80 × 21, controlled by a signal transmitted from an automatic control complex, is located on the pipeline from the lower crosspiece.

Пример №3 реализации конструкции самозадавливающейся газовой скважины. Конструкция самозадавливающейся газовой скважины включает кондуктор, смонтированный из обсадных труб диаметром 245 мм, эксплуатационную колонну, смонтированную из обсадных труб диаметром 168 мм, подвешенную в колонной головке ОКК1-210-245×168. Внутри эксплуатационной колонны размещена основная лифтовая колонна из лифтовых труб диаметром 114 мм, подвешенная в переводной катушке трубной головки фонтанной арматуры АФ6-100/100×210, которая установлена на верхнем фланце колонной головки. Внутри основной лифтовой колонны размещена центральная лифтовая колонна из насосно-компрессорных труб диаметром 60 мм, подвешенная в переводнике, который установлен на нижней крестовине. Между основной лифтовой колонной диаметром 114 мм и центральной лифтовой колонной диаметром 60 мм образовано кольцевое пространство. На верхнем фланце переводника установлена верхняя крестовина с трубопроводом проходным сечением 60 мм. Верхняя крестовина соединена с нижней крестовиной, образуя после соединения единый трубопровод. На трубопроводе от верхней крестовины и едином трубопроводе размещены расходомеры типа «трубы Вентури», сигналы от которых поступают на автоматический управляющий комплекс, размещенный возле устья скважины. На трубопроводе от нижней крестовины размещен автоматический регулирующий клапан РК-80×21, управляемый посредством сигнала, передаваемого от автоматического управляющего комплекса.Example No. 3 of the implementation of the design of a self-priming gas well. The design of a self-filling gas well includes a conductor mounted from casing pipes with a diameter of 245 mm, a production casing mounted from casing pipes with a diameter of 168 mm, suspended in a casing head OKK1-210-245 × 168. Inside the production casing, the main lift casing of elevator pipes with a diameter of 114 mm is located, suspended in the transfer coil of the tube head of the fountain fittings AF6-100 / 100 × 210, which is mounted on the upper flange of the column head. Inside the main lift column there is a central lift column of tubing 60 mm in diameter, suspended in a sub that is mounted on the lower crosspiece. An annular space is formed between the main lift column with a diameter of 114 mm and the central lift column with a diameter of 60 mm. An upper crosspiece is installed on the upper flange of the sub with a pipe with a bore of 60 mm. The upper crosspiece is connected to the lower crosspiece, forming a single pipeline after connection. On the pipeline from the upper cross and a single pipeline there are placed venturi-type flow meters, the signals from which are fed to an automatic control complex located near the wellhead. An automatic control valve RK-80 × 21, controlled by a signal transmitted from an automatic control complex, is located on the pipeline from the lower crosspiece.

Claims (1)

Конструкция газовой скважины, включающая кондуктор, эксплуатационную, основную и центральную лифтовые колонны, подвешенные соответственно в колонной головке, переводной катушке трубной головки и переводнике нижней крестовины, коренную и надкоренную задвижки, верхнюю крестовину, при этом верхняя и нижняя крестовины соединены между собой посредством трубопроводов, объединенных в единый трубопровод, на трубопроводе от верхней крестовины и на общем трубопроводе размещены расходомеры, а на трубопроводе от нижней крестовины размещен автоматический регулирующий клапан, возле устья скважины размещен автоматический управляющий комплекс, связанный с расходомерами и автоматическим регулирующим клапаном.
Figure 00000001
The design of a gas well, including a conductor, production, main and central lift columns, suspended respectively in the column head, the transfer coil of the pipe head and the sub of the lower cross, the root and root valves, the upper cross, the upper and lower crosses are interconnected via pipelines, united in a single pipeline, flow meters are placed on the pipeline from the upper crosspiece and on the common pipeline, and cars are placed on the pipeline from the lower crosspiece mathematical control valve, near the wellhead there is an automatic control complex associated with flowmeters and an automatic control valve.
Figure 00000001
RU2012129796/03U 2012-07-13 2012-07-13 GAS WELL DESIGN RU123824U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2012129796/03U RU123824U1 (en) 2012-07-13 2012-07-13 GAS WELL DESIGN

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2012129796/03U RU123824U1 (en) 2012-07-13 2012-07-13 GAS WELL DESIGN

Publications (1)

Publication Number Publication Date
RU123824U1 true RU123824U1 (en) 2013-01-10

Family

ID=48807381

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2012129796/03U RU123824U1 (en) 2012-07-13 2012-07-13 GAS WELL DESIGN

Country Status (1)

Country Link
RU (1) RU123824U1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2524787C1 (en) * 2013-03-12 2014-08-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Тюменский государственный нефтегазовый университет" (ТюмГНГУ) Re-equipment of self-squeezing gas well head
RU2651740C1 (en) * 2017-05-17 2018-04-23 Общество с ограниченной ответственностью Финансово-промышленная компания "Космос-Нефть-Газ" Gas well operating method
RU2735593C1 (en) * 2016-12-09 2020-11-05 Дзе Юниверсити Оф Квинсленд Method for dehydration and operation of wells for production of gas from coal beds

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2524787C1 (en) * 2013-03-12 2014-08-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Тюменский государственный нефтегазовый университет" (ТюмГНГУ) Re-equipment of self-squeezing gas well head
RU2735593C1 (en) * 2016-12-09 2020-11-05 Дзе Юниверсити Оф Квинсленд Method for dehydration and operation of wells for production of gas from coal beds
RU2651740C1 (en) * 2017-05-17 2018-04-23 Общество с ограниченной ответственностью Финансово-промышленная компания "Космос-Нефть-Газ" Gas well operating method

Similar Documents

Publication Publication Date Title
CN103233923B (en) A kind of lead-jetting device getting rid of pit shaft hydrops
CN201843590U (en) Gas well underground vortex drainage gas production tool
CN208310748U (en) The complete well control water installations of horizontal well with bottom water reservoir AICD
CA2933886A1 (en) Pad plunger
RU2513942C2 (en) Gas well operation method
CN104514522B (en) Low pressure gas well vortex plunger drainage gas recovery device
RU123824U1 (en) GAS WELL DESIGN
CN105089608A (en) Injection tool and application method for drainage and gas production in cooperation with downhole vortex tool
CN105089607A (en) A Downhole Self-operated Ejector Drainage and Gas Production Tool
CN205036348U (en) Instrument of vortex water pumping gas production in pit
RU133188U1 (en) GAS WELL DESIGN
CN203515495U (en) Low pressure gas well vortex plunger drainage gas recovery device
CN106639984A (en) Gas production tubular column, gas production method and vortex device
CN204804812U (en) Drainage gas production tool for underground self-operated ejector
CN104929560A (en) Sand-prevention blanking plug
CN208950557U (en) A kind of oil well reverse-filling tubing string
CN204457576U (en) Mechanical plugging string
CN202832453U (en) A SAGD production well single tubing pumping process string
RU158968U1 (en) DEVICE FOR NIZA OF A STEEL POLYMER-FREE COUPLING FLEXIBLE PIPE FOR OPERATION OF A WELL WITHOUT MUCHING
CN206753560U (en) A system capable of realizing hydraulic jet continuous sand filling layered fracturing
CN205673300U (en) Well head oil can washing apparatus
CN105672964B (en) U-shaped pipe gas-lift liquid extraction and drainage device
RU2425959C1 (en) Well head equipment for simultaneous separate fluid injection
CN203362098U (en) Ultrahigh-pressure coiled tubing fracture wellhead device
CN104234133B (en) Intelligent groundwater mining and backflow device

Legal Events

Date Code Title Description
PC92 Official registration of non-contracted transfer of exclusive right of a utility model

Effective date: 20180716