[go: up one dir, main page]

KR200300029Y1 - Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon - Google Patents

Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon Download PDF

Info

Publication number
KR200300029Y1
KR200300029Y1 KR20-2002-0029196U KR20020029196U KR200300029Y1 KR 200300029 Y1 KR200300029 Y1 KR 200300029Y1 KR 20020029196 U KR20020029196 U KR 20020029196U KR 200300029 Y1 KR200300029 Y1 KR 200300029Y1
Authority
KR
South Korea
Prior art keywords
concrete
strand
steel
lower flange
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
KR20-2002-0029196U
Other languages
Korean (ko)
Inventor
권오근
김원근
윤숙현
이무일
Original Assignee
동양종합건업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 동양종합건업 주식회사 filed Critical 동양종합건업 주식회사
Priority to KR20-2002-0029196U priority Critical patent/KR200300029Y1/en
Application granted granted Critical
Publication of KR200300029Y1 publication Critical patent/KR200300029Y1/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

본 고안은, 스틸 I형 거더와 하부플랜지를 감싸는 콘크리트 및 피.씨. 강연선을 조합하여 하부플랜지 콘크리트 상면에서 밖으로 일단 또는 양단이 미리 인출된 피.씨. 강연선을 조립하여 슬래브콘크리트와 복부콘크리트를 타설 양생한 후에 인장 정착시킬 수 있도록 한 합성빔으로서, 인출된 상기 피.씨. 강연선을 견고하게 정착할 수 있는 새로운 정착구조를 구비하여 빔의 연속성이 더욱 개선된 다경간 연속 프리플렉스 합성빔에 관한 것이다.The present invention is concrete and P. C. wrapping steel I-girder and lower flange. Combining the strands, P.C. with one end or both ends pre-drawn from the upper surface of the lower flange concrete. A composite beam for assembling a strand to allow tensile fixation after slab concrete and abdominal concrete are cast, wherein the drawn beam is drawn. The present invention relates to a multi-span continuous preplex composite beam having a new anchoring structure capable of firmly fixing the stranded wire, thereby further improving the continuity of the beam.

본 고안에서는, 스틸 I형 거더(2)와 하부플랜지 콘크리트(3)를 조합하여 각각의 프리플렉스 빔(1)을 지상에서 독립적으로 제작한 후 다수의 각 경간에 걸쳐 교각(6) 위에 각각의 빔(1)을 설치한 후 슬래브콘크리트(10)와 복부콘크리트(11)를 완성하여 일체로 연결하는 다수 경간의 프리플렉스 합성빔으로서, 내측지점의 각 교각(6) 위의 부모멘트 구간에서 종방향으로 인접한 2개 빔(1)의 스틸 I형 거더(2)의 상부플랜지(2a)와 복부(2b)를 상부이음판(7a)과 복부이음판(7b)에 의하여 연속 결합되고; 상기 스틸 I형 거더(2)의 하부플랜지(2c) 아래의 하부플랜지 콘크리트(3)의 내에는 피.씨. 강연선(4)이 배치되고, 상기 하부플랜지(2c)에는 관통공(14)이 형성되어 상기 피.씨. 강연선(4)의 단부가 상기 내측지점의 부모멘트 구간의 시작부에서 상기 관통공(14)을 통하여 하부플랜지 콘크리트(3) 외부로 인출되고; 상기 상부플랜지(2a)에는 관통공(14)이 형성되어 있어, 상기 하부플랜지 콘크리트(3) 외부로 인출된 상기 피.씨. 강연선(4)이 상기 관통공(14)을 통하여 상부플랜지(2a) 위로 인출되며; 상기 상부플랜지(2a)의 상기 관통공(14) 뒤쪽으로는 강선 정착구(8)가 각각 형성되어 있어, 상기 상부플랜지(2a) 위로 인출된 피.씨. 강연선(4)이 상기 부모멘트 구간의 상부이음판(7a) 위에서 서로 겹치도록 교차되어 그 단부가 상대편 스틸 I형 거더(2)의 상기 강선 정착구(8)에 관통하여 위치되도록 하며; 슬래브콘크리트(10)와 복부콘크리트(11)를 다수의 경간에 걸쳐 연속하여 타설 양생한 상태에서 상기 강선 정착구(8)에 관통하여 위치한 상기 피.씨. 강연선(4)을 긴장하여 강선 정착구(8)에 정착한 것을 특징으로 하는 다경간 연속 프리플렉스 합성빔이 제공된다.In the present invention, each preflex beam 1 is fabricated independently from the ground by combining the steel type I girder 2 and the lower flange concrete 3, and then each of the above-mentioned pier 6 over a plurality of spans. It is a multi-span preflex composite beam that completes and connects the slab concrete 10 and the abdominal concrete 11 after the beam 1 is installed. The upper flange 2a and the abdomen 2b of the steel I-type girder 2 of the two beams 1 adjacent in the direction are successively joined by the upper joint plate 7a and the abdominal joint plate 7b; In the lower flange concrete (3) below the lower flange (2c) of the steel I-type girder (2). The strand 4 is disposed, and a through hole 14 is formed in the lower flange 2c to form the P. An end of the strand 4 is drawn out of the lower flange concrete 3 through the through hole 14 at the beginning of the parent section of the inner point; The through flange 14 is formed in the upper flange (2a), the P. C. drawn out to the lower flange concrete (3). The strand 4 is drawn out through the through hole 14 onto the upper flange 2a; Steel wire fixing holes 8 are formed at the rear of the through hole 14 of the upper flange 2a, respectively, and are drawn out onto the upper flange 2a. A strand 4 intersects so as to overlap each other on the upper joint plate 7a of the parent section so that its end is positioned through the line anchorage 8 of the opposite steel I-girder 2; The slab concrete (10) and the abdominal concrete (11) is placed through the steel wire anchorage (8) in a state in which the casting cured successively over a plurality of spans. A multi-span continuous preplex composite beam is provided, which is characterized in that the strand 4 is tensioned and fixed to the wire anchorage 8.

본 고안에서는 상부플랜지(2a) 상면으로 노출된 피.씨. 강연선(4)이 연결부에서 바로 정착되는 것이 아니라, 연결부를 지나 소정 길이만큼 서로 교차한 상태에서 정착되므로, 연결부에서는 피.씨. 강연선(4)이 소정 길이로 겹쳐져 있게 되어 연결부의 강도가 증가되며, 피.씨. 강연선(4)의 긴장, 정착에 의하여 슬래브 콘크리트(10)에 작용하는 압축응력이 배가되어 빔의 연속성이 더욱 우수하게 된다.In the present invention, P. C. exposed to the upper surface of the upper flange (2a). The strand 4 is not directly settled at the connecting portion, but is settled in a state where they cross each other by a predetermined length past the connecting portion, so that the connecting portion P. The strand 4 is overlapped to a predetermined length to increase the strength of the connecting portion, P. The compressive stress acting on the slab concrete 10 is doubled by the tension and fixation of the strand 4, so that the continuity of the beam becomes more excellent.

Description

강선 정착구를 구비한 다경간 연속 프리플렉스 합성빔{Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon}Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon

본 고안은 다경간 연속 프리플렉스 합성빔에 관한 것으로서 더욱 상세히 설명하면, 스틸 I형 거더와 하부플랜지를 감싸는 콘크리트 및 피.씨. 강연선을 조합하여 하부플랜지 콘크리트 상면에서 밖으로 일단 또는 양단이 미리 인출된 피.씨. 강연선을 조립하여 슬래브콘크리트와 복부콘크리트를 타설 양생한 후에 인장 정착시킬 수 있도록 한 합성빔으로서, 인출된 상기 피.씨. 강연선을 견고하게 정착할 수 있는 새로운 정착구조를 구비하여 빔의 연속성이 더욱 개선된 다경간 연속 프리플렉스 합성빔에 관한 것이다.The present invention is directed to a multi-span continuous preplex composite beam, which will be described in more detail. The concrete and P. C. surrounding the steel I-girder and the lower flange. Combining the strands, P.C. with one end or both ends pre-drawn from the upper surface of the lower flange concrete. A composite beam for assembling a strand to allow tensile fixation after slab concrete and abdominal concrete are cast, wherein the drawn beam is drawn. The present invention relates to a multi-span continuous preplex composite beam having a new anchoring structure capable of firmly fixing the stranded wire, thereby further improving the continuity of the beam.

도 1a 내지 도 1d는 종래의 스틸 I형 거더(2)와 철근콘크리트를 조합하여 하부플랜지 콘크리트에 프리스트레스 압축응력을 도입하는 방법을 순차적으로 나타낸 측면도 및 정면도가 도시되어 있는데, 스틸 I형 거더(2)를 이용한 프리플렉스 합성빔이나 리프리스트레스트 프리플렉스 합성빔(1)의 개략적인 제작공정은 다음과 같다.1A to 1D show side and front views sequentially illustrating a method of introducing prestressed compressive stress to a lower flange concrete by combining conventional steel I type girder 2 and reinforced concrete. The schematic manufacturing process of the preplex composite beam or leafrestrest preplex composite beam 1 using the following is as follows.

먼저 수평방향의 상부플랜지(2a), 하부플랜지(2c) 및 수직방향의 복부(WEB)(2b)를 구비한 스틸 I형 거더(2)는 도 1a에 도시된 것처럼 위로 만곡된 상태로 제작된다. 이와 같이 만곡된 상태의 스틸 I형 거더 (2)에 하중(Pf)을 가하여 도 1b에 표현된 바와 같이 아래로 만곡된 처짐 변형을 유발시킨 상태에서, 도 1c와 같이 스틸 I형 거더(2)의 하부플랜지(2c)를 감싸는 형태의 하부플랜지콘크리트(3)를 타설하여 양생(경화)한 후, 스틸 I형 거더(2)에 가해진 하중(Pf)을 제거한다. 그에 따라 아래로 만곡되어 있던 처짐 변형이 원상태로 복귀하게 되고, 이때, 스틸 I형 거더(2)의 하부플랜지(2c)를 감싸고 있는 하부플랜지콘크리트(3) 스틸 I형 거더(2)와 함께 거동하여 하부플랜지콘크리트(3)에 프리스트레스 압축응력을 도입된다. 이러한 방법에 의하여 제작되는 것이 프리플렉스 합성빔(1)이다.First, a steel I-type girder 2 having a horizontal upper flange 2a, a lower flange 2c and a vertical abdomen (WEB) 2b is manufactured to be curved upward as shown in FIG. 1A. . In this state of applying a load Pf to the steel I-girder 2 in the curved state to induce a deflection deformation bent downward as shown in FIG. 1B, the steel I-girder 2 as shown in FIG. 1C. After pouring the lower flange concrete (3) of the shape surrounding the lower flange (2c) of the curing (curing), remove the load (Pf) applied to the steel I-type girder (2). As a result, the deflection deformation, which was curved downward, is returned to its original state, and at this time, the lower flange concrete 3 surrounding the lower flange 2c of the steel I-type girder 2 moves together with the steel I-type girder 2. Thus, the prestressed compressive stress is introduced into the lower flange concrete 3. Prefabricated composite beam 1 is produced by this method.

한편, 프리플렉스 합성빔(1)의 하부플랜지콘크리트(3)의 단면 내에 미리 피.씨. 강연선(4)을 배치한 후, 상기와 같은 프리플렉스 합성빔(1)의 제작과정에 의하여 일단 하부플랜지콘크리트(3)에 프리스트레스 압축응력을 도입한 후에 피.씨. 강연선(4)을 인장 정착함으로써, 추가로 프리스트레스 압축응력을 도입시켜 제작할 수 있는데, 이러한 방법에 의하여 제작되는 것을 리프리스트레스트 프리플렉스 합성빔(1)이라고 칭한다.On the other hand, P. C. in advance in the cross section of the lower flange concrete (3) of the preplex composite beam (1). After arranging the strand 4, the pre-stressed compressive stress was first introduced into the lower flange concrete 3 by the manufacturing process of the preflex composite beam 1 as described above. By tension-fixing the strand 4, a prestressed compressive stress can be further introduced and manufactured, and what is produced by this method is called the leafrest preplex composite beam 1.

다경간교량에 있어서 교각 또는 교대 위에 상기와 같은 프리플렉스 합성빔(1)을 설치하는 경우에 종방향으로 인접한 각 경간의 빔(1)은 연속되지 않은 상태로서 단순구조계가 각 경간에 걸쳐 반복되며 이때 각 경간의 경계인 지점부에는 필연적으로 교량의 신축 이음 장치를 설치하여야 하는바 이로 인하여 차량의 주행성이 저하될 뿐만 아니라 신축 이음 장치의 지속적인 유지 보수에 많은 노력과 비용이 소요된다.In the case of installing the above-described preflex composite beam 1 on a bridge or alternating bridge in a multi-span bridge, the beam 1 of each longitudinally adjacent beam is not continuous and the simple structure system is repeated over each span. At this point, it is inevitably required to install the expansion joint of the bridge at the point which is the boundary of each span, which not only decreases the driving performance of the vehicle but also requires a lot of effort and cost for the continuous maintenance of the expansion joint.

따라서, 상기와 같은 프리플렉스 합성빔(1)이 완전히 일체로 연결될 수 있도록 하는 것이 필요하다.Therefore, it is necessary to allow the above-described preplex composite beam 1 to be completely integrally connected.

본 고안은 상술한 바와 같은 종래의 프리플렉스 합성빔에 있어서 절실히 요구되었던 사항을 해소하게 위하여 개발된 것으로서, 본 고안의 목적은 합성빔에 배치된 피. 씨. 강연선을 연속화시켜 견고하게 정착할 수 있는 정착구조를 구비하여 합성빔의 연속성을 더욱 개선시킨 다경간 연속 프리플렉스 합성빔을 제공하는 것이다.The present invention was developed to solve the desperately required matters of the conventional preplex composite beam as described above. Seed. The present invention is to provide a multi-span continuous preplex composite beam having a fixing structure capable of continually fixing the strands to further fix the continuity of the composite beam.

도 1a 내지 도 1d는 종래의 스틸 I형 거더와 철근콘크리트를 조합하여 하부플랜지 콘크리트에 프리스트레스 압축응력을 도입하는 방법을 순차적으로 나타낸 측면도 및 정면도이고,1A to 1D are side and front views sequentially illustrating a method of introducing prestressed compressive stress into lower flange concrete by combining conventional steel I-girder and reinforced concrete;

도 2는 본 고안에 의한 3경간 연속 프리플렉스 합성빔에 의한 교량의 측단면도이고,Figure 2 is a side cross-sectional view of the bridge by the three-span continuous preplex composite beam according to the present invention,

도 3은 도 2의 중간지점 교각 위에서 종방향으로 인접한 2개 빔의 연결부 측단면 확대도이고,3 is an enlarged side cross-sectional view of two beams longitudinally adjacent above the mid-point pier of FIG.

도 4a 내지 도 4c는 각각 도 3의 A-A선, B-B선, C-C선에 따른 단면도로서 피.씨. 강연선의 배치형태를 보여주는 단면도이고,4A to 4C are cross-sectional views taken along line A-A, line B-B, and line C-C of FIG. 3, respectively. Is a cross-sectional view showing the arrangement of the strands,

도 5는 본 고안에 따른 합성빔으로서 외측경간인 제1경간과 마지막 경간에 사용되는 합성빔의 일부절개사시도이며,5 is a partially cutaway perspective view of a composite beam used for the first span and the last span, which are outer spans, as a composite beam according to the present invention;

도 6은 본 고안에 따른 내측경간에 사용되는 합성빔의 일부절개사시도이고,6 is a partially cutaway perspective view of the composite beam used in the inner span according to the present invention,

도 7은 도 2의 내측지점 교각 위에서 종방향으로 인접한 2개 빔의 연결부 확대 사시도이고,FIG. 7 is an enlarged perspective view of a connection portion of two beams longitudinally adjacent to the inner point pier of FIG. 2;

도 8은 도 2의 중간지점 교각 위에서 종방향으로 인접한 2개 빔의 스틸 I형거더의 상부플랜지와 복부를 이음판으로서 연결한 종단면도이다.FIG. 8 is a longitudinal sectional view of the upper flange and the abdomen of the two beams of steel I-girder longitudinally adjacent over the mid-point pier of FIG.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

1 - 프리플렉스합성빔, 1a - 외측경간의 빔,1-preflex composite beam, 1a-outer span beam,

1b - 외측경간의 빔, 2 - 스틸 I형 거더,1b-beam outside girth, 2-steel I-girder,

2a - 상부플랜지, 2b - 복부,2a-upper flange, 2b-abdomen,

2c - 하부플랜지, 3 - 하부플랜지 콘크리트,2c-lower flange, 3-lower flange concrete,

4 - 피.씨. 강연선(P.C. 강연선) 5 - 교대,4-Mr. P. Strand (P.C. strand) 5-shift,

6 - 교각, 7a - 상부플랜지이음판,6-pier, 7a-upper flanged joint plate,

7b - 복부이음판, 8 - 강선 정착구,7b-abdominal joint, 8-liner anchorage,

9 - 고정정착판, 10 - 슬래브콘크리트,9-fixed mounting plate, 10-slab concrete,

11 - 복부콘크리트, 12 - 슬래브콘크리트의 긴장개구부,11-abdominal concrete, 12-tension opening of slab concrete,

13 - 보울트, 14 - 스틸 I형 거더의 관통공,13-bolt, 14-through hole for steel I-girder,

15 - 강선 정착구의 관통공.15-through-holes of steel wire anchorage.

상술한 바와 같은 기술적 목적을 실현시키기 위한 본 고안에 따른 다경간 연속 프리플렉스 합성빔은, 스틸 I형 거더와 하부플랜지 콘크리트를 조합하여 각각의 프리플렉스 빔을 지상에서 독립적으로 제작한 후 다수의 각 경간에 걸쳐 교각 위에서 각각의 빔을 설치하고 슬래브콘크리트와 복부콘크리트를 완성하여 연결하는 다수경간의 프리플렉스 합성빔에 있어서, 내측지점의 각 교각 위의 부모멘트 구간에서 종방향으로 인접한 2개 빔의 스틸 I형 거더의 상부플랜지와 복부를 상부이음판과 복부이음판에 의하여 연속 결합되고; 상기 스틸 I형 거더의 하부플랜지 아래의 하부플랜지 콘크리트의 내에는 피.씨. 강연선(4)이 배치되고, 상기 하부플랜지에는 관통공이 형성되어 상기 피.씨. 강연선의 단부가 상기 내측지점의 부모멘트 구간의 시작부에서 상기 관통공을 통하여 하부플랜지 콘크리트 외부로 인출되고; 상기 상부플랜지에는 관통공이 형성되어 있어, 상기 하부플랜지 콘크리트 외부로 인출된 상기 피.씨. 강연선이 상기 관통공을 통하여 상부플랜지 위로 인출되며; 상기 상부플랜지의 상기 관통공 뒤쪽으로는 강선 정착구가 각각 형성되어 있어, 상기 상부플랜지 위로 인출된 피.씨. 강연선이 상기 부모멘트 구간의 상부이음판 위에서 서로 겹치도록 교차되어 그 단부가 상대편 스틸 I형 거더의 상기 강선 정착구에 관통하여 위치되도록 하며; 슬래브콘크리트와 복부콘크리트를 다수의 경간에 걸쳐 연속하여 타설 양생한 상태에서 상기 강선 정착구에 관통하여 위치한 상기 피.씨. 강연선을 긴장하여 강선 정착구에 정착한 것을 특징으로 한다.The multi-span continuous preplex composite beam according to the present invention for realizing the technical purpose as described above is a combination of the steel I-girder and the lower flange concrete to manufacture each preflex beam independently on the ground In a multi-span preflex composite beam that installs each beam over a bridge over a span and completes and connects slab concrete and abdominal concrete, the two longitudinally adjacent beams in the parent section over each pier at the inner point. The upper flange and the abdomen of the steel type I girder are continuously joined by the upper joint plate and the abdominal joint plate; P. C. in the lower flange concrete under the lower flange of the steel I-girder. The strand 4 is disposed, and a through hole is formed in the lower flange to form the p. An end of the strand is drawn out of the lower flange concrete through the through hole at the beginning of the parent section of the inner point; Through holes are formed in the upper flange, the P. C. drawn out to the lower flange concrete. The strand is drawn out onto the upper flange through the through hole; Steel wire anchorages are formed behind the through-holes of the upper flange, respectively, and are drawn out to the upper flange. Strands are crossed so that they overlap each other on the upper joint plate of the parent section so that their ends are positioned through the steel anchorage of the opposite steel I-girder; The P. C. positioned through the wire anchorage in a state in which slab concrete and abdominal concrete are continuously cast and cured over a plurality of spans. It is characterized by being settled in the steel wire anchorage by tensioning the strand.

본 고안을 첨부된 예시도면과 함께 상세히 설명하면 다음과 같다.The present invention will be described in detail with reference to the accompanying drawings.

본 고안에 따른 합성빔(1)에서는, 스틸 I형 거더(2)와 하부플랜지 콘크리트(3)를 조합함에 있어서, 상기 스틸 I형 거더(2)의 하부플랜지(2c) 아래측의 상기 하부플랜지 콘크리트(3)에 다수의 피.씨. 강연선(4)을 배치하고, 상기 하부플랜지(2c)에는 관통공(14)을 형성하여 상기 피.씨. 강연선(4)의 일단 또는 양단을 상기 관통공(14)을 통하여 하부콘크리트(3) 상면에서 밖으로 인출되도록 한 상태에서 종래의 프리플렉스 빔(1)의 제작과정에서 유발되는 스틸 I형 거더(2)의 변위로서 하부콘크리트(3)에 1차 프리스트레스 압축응력을 도입시킨다.In the combined beam 1 according to the present invention, in combining the steel I-girder 2 and the lower flange concrete 3, the lower flange below the lower flange 2c of the steel I-girder 2 Many P. seeds in concrete (3). The strand 4 is disposed, and a through hole 14 is formed in the lower flange 2c to form the P. One or both ends of the strand 4 are pulled out from the upper surface of the lower concrete 3 through the through hole 14, and the steel type I girder 2 caused in the manufacturing process of the conventional preflex beam 1 is carried out. The primary prestress compressive stress is introduced into the lower concrete 3 as a displacement of.

후속하여 도 2와 같이 각 경간의 교대(5) 또는 교각(6) 위에 각각의 빔(1)을 독립적으로 가설하되, 도 5와 같이 제 1 경간 마지막 경간인 외측 경간의 빔(1a)과 도 과 같은 중앙내측경간의 빔(1b)으로 구분하여 제작한다.Subsequently, each beam 1 is independently hypothesized on the alternation 5 or the pier 6 of each span as shown in FIG. 2, but the beam 1a of the outer span, which is the last span of the first span, as shown in FIG. 5 and FIG. Produced by dividing the beam (1b) between the center inner diameter as shown.

다음으로 각 경간의 경계인 지점부의 각 교각(6) 위에서 종방향으로 인접한 2개 빔(1)의 스틸 I형 거더(2)가 연속되도록 하기 위하여 도 7 및 도 8 과 같이 스틸 I형 거더(2)의 상부플랜지(2a)와 복부(2b)에 2겹의 복부이음판(7b)과 상부이음판(7a)을 설치하여 용접 또는 보울트(13)이음으로서 종방향으로 인접한 2개의 빔(1)의 스틸 I형 거더(2)의 복부(2b)와 상부플랜지(2a)가 완전하게 연속 결합되도록 한다. 이때 복부이음판 (7b)에는 지점부의 수직하중을 스틸 I형 거더(2)에서 교좌장치로 직접 전달하기 위하여 수직 보강재를 설치할 수도 있다.Next, the steel I type girders 2 as shown in FIGS. 7 and 8 are arranged so that the longitudinally adjacent two beams 1 of the two beams 1 are continuous on each of the piers 6 at the boundary points of the respective spans. Two beams (1) longitudinally adjacent by welding or bolting (13) by installing two layers of abdominal joint plate (7b) and upper joint plate (7a) on the upper flange (2a) and the abdomen (2b) of the The abdomen 2b and the upper flange 2a of the steel I-type girder 2 are completely continuous. At this time, the abdominal joint plate (7b) may be provided with a vertical reinforcement in order to directly transfer the vertical load of the point portion from the steel I-girder (2).

상기와 같이 스틸 I형 거더(2)의 연속결합이 완료되면, 도 3, 도 4, 및 도 7과 같이 종방향으로 인접한 2개 빔(1)의 하부콘크리트(3) 상면에서 밖으로 노출된 피.씨. 강연선(4)의 각 일단이 스틸 I형 거더(2)의 상부플랜지(2a)를 관통하여 상부플랜지(2a) 상면에서 서로 교차되어 연속되도록 조립한다. 이를 위하여 상부플랜지(2a)와 하부플랜지(2c)에 각각 피.씨. 강연선(4)을 관통시킬 수 있는관통공(14)을 미리 천공하여야 한다.When the continuous coupling of the steel I-type girder 2 as described above is completed, the blood exposed outside from the upper surface of the lower concrete (3) of the two longitudinally adjacent beams as shown in Figs. 3, 4 and 7 .Seed. Each end of the strand 4 passes through the upper flange 2a of the steel I-type girder 2, and is assembled so as to cross each other on the upper surface of the upper flange 2a. To this end, each of the upper and lower flanges (2a) and the lower flange (2c). A through hole 14 that can penetrate the strand 4 should be drilled in advance.

위와 같이 상부플랜지(2a) 상면으로 인출된 피.씨. 강연선(4)은 상부이음판(7a) 위를 지나 서로 교차되어 추후 상대편 거더의 상부플랜지(2a)에서 각각 그 단부가 정착된다.P. C. withdrawn to the upper surface of the upper flange (2a) as above. The strands 4 cross each other over the upper joint plate 7a, and then end portions thereof are respectively fixed at the upper flanges 2a of the opposite girder.

이를 위하여 거더의 상부플랜지(2a) 상면에는 상기 상부플랜지(2a) 상의 관통공(14) 후방으로 강선 정착구(8)가 형성되어 있는데, 상기 강선 정착구(7)에는 피.씨. 강연선(4)이 관통하게 되는 다수개의 관통공(15)이 형성되어 있다.To this end, a steel wire anchorage 8 is formed on the upper surface of the upper flange 2a of the girder to the rear of the through hole 14 on the upper flange 2a. A plurality of through holes 15 through which the strand 4 is formed are formed.

상부플랜지(2a) 상면으로 인출된 후 상부이음판(7a) 위를 지나 서로 교차한 피.씨. 강연선(4)은 상기 강선 정착구(8)의 관통공(15)에 삽입 관통된 후 상기 강선 정착구(8)의 외부로 노출된다.P. C. was drawn to the upper surface of the upper flange (2a) and then crossed over the upper joint plate (7a). The strand 4 is inserted into the through hole 15 of the wire anchorage 8 and then exposed to the outside of the wire anchorage 8.

상술한 바와 같이 교각(6) 위의 각 지점에서 인접한 2개 빔(1)의 스틸 I형 거더(2)와 피.씨. 강연선(4)의 연속 조립이 완료되면 복부 및 슬래브 콘크리트(10)(11)를 각 경간에 걸쳐 일체구조가 되도록 연속하여 타설한다. 이 때, 강선 정착구(8) 설치 위치까지의 거더(2)의 상부에는 슬래브 콘크리트(10)를 타설하지 아니한 긴장개구부(12)를 형성한다. 이는 후술하는 바와 같이, 피.씨. 강연선(4)을 긴장, 정착하기 위함이다.Steel I-girder 2 and P. C. of two adjacent beams 1 at each point on the pier 6 as described above. When the continuous assembly of the strand 4 is completed, the abdomen and the slab concrete (10) (11) is poured continuously to form an integral structure over each span. At this time, in the upper part of the girder 2 to the installation position of the steel wire anchorage 8, a tension opening 12 is not provided in which the slab concrete 10 is not poured. This will be described later. This is to tension and settle the strand 4.

복부 및 슬래브 콘크리트(10)(11)가 소정 강도 이상으로 양생되면, 상부이음판(7a) 위에서 서로 교차되어 그 단부가 상기 강선 정착구(8)의 관통공(15) 외부로 노출된 피.씨. 강연선(4)을 순차적으로 긴장한 후 상기 강선 정착구(8)에 정착한다.When the abdomen and the slab concrete (10) (11) is cured to a predetermined strength or more, the P. C cross each other on the upper joint plate (7a) and its ends exposed outside the through hole 15 of the steel wire anchorage (8). . The strand 4 is sequentially tensioned and then fixed to the liner anchorage 8.

이와 같이, 본 고안에서는 상부플랜지(2a) 상면으로 노출된 피.씨. 강연선(4)이 연결부에서 바로 정착되는 것이 아니라, 연결부를 지나 소정 길이만큼 서로 교차한 상태에서 정착되므로, 연결부에서는 피.씨. 강연선(4)이 소정 길이로 겹쳐져 있게 되어 연결부의 강도가 증가되며, 특히 피.씨. 강연선(4)의 긴장, 정착에 의하여 슬래브 콘크리트(10)에 작용하는 압축응력이 배가되어 빔의 연속성이 더욱 우수하게 된다.As such, in the present invention, P. C. exposed to the upper surface of the upper flange 2a. The strand 4 is not directly settled at the connecting portion, but is settled in a state where they cross each other by a predetermined length past the connecting portion, so that the connecting portion P. The strand 4 is overlapped to a predetermined length to increase the strength of the connecting portion, in particular P. The compressive stress acting on the slab concrete 10 is doubled by the tension and fixation of the strand 4, so that the continuity of the beam becomes more excellent.

피.씨. 강연선(4)의 긴장, 정착이 완료된 후 긴장개구부(12)에는 콘크리트 또는 시멘트몰탈 등을 채워서 마감될 수 있도록 한다.Mr. P. After the tension and fixation of the strand 4 is completed, the tension opening 12 may be filled with concrete or cement mortar to be finished.

지금까지는 내측 지점에 해당되는 각 교각(6) 위에서 인접한 2개 빔(1)의 스틸 I형 거더(2)와 피.씨. 강연선(4)의 연속결합과 긴장정착을 상술한 것인바, 외측지점인 교대측(5)으로 인출된 피.씨. 강연선(4)의 각 일단은 도 5와 같이 상부플랜지(2a)의 상면까지 인출시키지 않고, 교대(5) 위 지점에서 스틸 I형 거더 (2)의 복부(2b) 중간부분에 설치된 별도의 고정정착판(9)에 의하여 고정되어 복부 콘크리트(11) 속에 매립될 수 있도록 한다.So far, steel I type girders 2 and P. C. of two adjacent beams 1 on each pier 6 corresponding to the inner point. Continuous coupling and tension settling of the strand 4 is described above, P. C. withdrawn to the alternating side 5, which is an outer point. Each end of the strand 4 is not fixed to the upper surface of the upper flange (2a) as shown in Figure 5, a separate fixing provided in the middle of the abdomen (2b) of the steel I-type girder (2) at the point above the shift (5) It is fixed by the fixing plate 9 to be embedded in the abdominal concrete (11).

본 고안에 따르면, 스틸 I형 거더(2)와, 철근콘크리트(3)(10)(11) 및 피.씨. 강연선(4)을 적절히 조합하여 도 2 와 같이 다수의 각 경간에 걸쳐 콘크리트 (3) (10)(11) 내부의 스틸 I형 거더(2)가 완전하게 연속 결합함과 동시에 피.씨. 강연선(4)에 의한 프리스트레스 압축응력을 지간 중앙부 정모멘트 구간과 지점부 부모멘트 구간을 자연스럽게 교차하여 저항할 수 있도록 다수의 각 경간에 걸쳐 연속적으로 도입시키므로, 종래의 프리플렉스 빔(1)과 같은 제작과정에서 유발되는 스틸 I형 거더(2)의 변위로서 빔(1)의 하부플랜지 콘크리트(3)에 먼저 1차 압축프리스트레스 응력을 도입시켜 빔(1)의 자중과 복부 및 슬래브 콘크리트(10)(11)의 사하중에 저항하고, 각 경간의 경계인 지점부에서 복부 및 슬래브 콘크리트(10)(11) 타설시 스틸 I형 거더(2)에서 발생되는 부모멘트는 스틸 I형 거더(2)의 지점 연결부가 효과적으로 저항하고 활하중에 의한 지간중앙부의 정모멘트와 지점 슬래브 콘크리트(10)의 부모멘트에는 피.씨. 강연선(4)의 인장정착에 의한 2차 프리스트레스 압축응력으로서 효과적으로 대응하여 교량의 신축 이음 장치를 사용치 않게 되고 또한 종래와 같은 단순 구조계의 프리플렉스 합성형교에 비하여 지간장을 더욱 길게 할 수 있으면서도 더욱 경제적이고 안전한 연속구조계의 다경간 연속프리플렉스 합성빔을 건설할 수 있는 효과가 있다.According to the present invention, steel I-girder 2, reinforced concrete (3) (10) (11) and P. C. By properly combining the strand 4, as shown in FIG. 2, the steel I-girder 2 inside the concrete (3) (10) and (11) is completely continuously coupled to each other as shown in FIG. Since the prestressed compressive stress caused by the strand 4 is continuously introduced over a plurality of spans so as to naturally cross and resist the center positive moment section and the point parent moment section, the same as in the conventional preflex beam 1 As the displacement of the steel type I girder (2) caused during the manufacturing process, the first compression prestress stress is first introduced into the lower flange concrete (3) of the beam (1), so that the weight of the beam (1) and the abdominal and slab concrete (10) Resisting the dead weight of (11), and at the point of the boundary of each span, the parent moment generated in the steel I-girder (2) when placing the abdomen and slab concrete (10) (11) is the point of the steel I-girder (2) The connection part effectively resists the positive moment of the middle part of the earth due to the live load and the parent moment of the point slab concrete (10). It effectively responds to the secondary prestressed compressive stress due to the tension settling of the strand 4, thereby eliminating the use of the expansion joint of the bridge, and further increasing the length of the ground length as compared to the conventional preflex composite bridge. It is effective to construct multi-span continuous preplex composite beam of continuous and safe continuous system.

특히, 본 고안에서는 상부플랜지(2a) 상면으로 노출된 피.씨. 강연선(4)이 연결부에서 바로 정착되는 것이 아니라, 연결부를 지나 소정 길이만큼 서로 교차한 상태에서 정착되므로, 연결부에서는 피.씨. 강연선(4)이 소정 길이로 겹쳐져 있게 되어 연결부의 강도가 증가되며, 피.씨. 강연선(4)의 긴장, 정착에 의하여 슬래브 콘크리트(10)에 작용하는 압축응력이 배가되어 빔의 연속성이 더욱 우수하게 된다.In particular, in the present invention, P. C. exposed to the upper surface of the upper flange (2a). The strand 4 is not directly settled at the connecting portion, but is settled in a state where they cross each other by a predetermined length past the connecting portion, so that the connecting portion P. The strand 4 is overlapped to a predetermined length to increase the strength of the connecting portion, P. The compressive stress acting on the slab concrete 10 is doubled by the tension and fixation of the strand 4, so that the continuity of the beam becomes more excellent.

Claims (1)

스틸 I형 거더(2)와 하부플랜지 콘크리트(3)를 조합하여 각각의 프리플렉스 빔(1)을 지상에서 독립적으로 제작한 후 다수의 각 경간에 걸쳐 교각(6) 위에 각각의 빔(1)을 설치한 후 슬래브콘크리트(10)와 복부콘크리트(11)를 완성하여 일체로 연결하는 다수경간의 프리플렉스 합성빔으로서,Combined steel I-girder (2) and lower flange concrete (3) to make each preplex beam (1) independently from the ground and then to each beam (1) over the piers (6) over multiple spans As a multi-span preflex composite beam for connecting the slab concrete 10 and the abdominal concrete 11 after the installation and integrally connected, 내측지점의 각 교각(6) 위의 부모멘트 구간에서 종방향으로 인접한 2개 빔(1)의 스틸 I형 거더(2)의 상부플랜지(2a)와 복부(2b)를 상부이음판(7a)과 복부이음판(7b)에 의하여 연속 결합되고;The upper flange 2a and the abdomen 2b of the steel I-type girder 2 of two beams 1 longitudinally adjacent in the parent section section on each pier 6 of the inner point are connected to the upper joint plate 7a. And are continuously joined by the abdominal joint plate 7b; 상기 스틸 I형 거더(2)의 하부플랜지(2c) 아래의 하부플랜지 콘크리트(3)의 내에는 피.씨. 강연선(4)이 배치되고, 상기 하부플랜지(2c)에는 관통공(14)이 형성되어 상기 피.씨. 강연선(4)의 단부가 상기 내측지점의 부모멘트 구간의 시작부에서 상기 관통공(14)을 통하여 하부플랜지 콘크리트(3) 외부로 인출되고;In the lower flange concrete (3) below the lower flange (2c) of the steel I-type girder (2). The strand 4 is disposed, and a through hole 14 is formed in the lower flange 2c to form the P. An end of the strand 4 is drawn out of the lower flange concrete 3 through the through hole 14 at the beginning of the parent section of the inner point; 상기 상부플랜지(2a)에는 관통공(14)이 형성되어 있어, 상기 하부플랜지 콘크리트(3) 외부로 인출된 상기 피.씨. 강연선(4)이 상기 관통공(14)을 통하여 상부플랜지(2a) 위로 인출되며;The through flange 14 is formed in the upper flange (2a), the P. C. drawn out to the lower flange concrete (3). The strand 4 is drawn out through the through hole 14 onto the upper flange 2a; 상기 상부플랜지(2a)의 상기 관통공(14) 뒤쪽으로는 강선 정착구(8)가 각각 형성되어 있어, 상기 상부플랜지(2a) 위로 인출된 피.씨. 강연선(4)이 상기 부모멘트 구간의 상부이음판(7a) 위에서 서로 겹치도록 교차되어 그 단부가 상대편 스틸 I형 거더(2)의 상기 강선 정착구(8)에 관통하여 위치되도록 하며;Steel wire fixing holes 8 are formed at the rear of the through hole 14 of the upper flange 2a, respectively, and are drawn out onto the upper flange 2a. A strand 4 intersects so as to overlap each other on the upper joint plate 7a of the parent section so that its end is positioned through the line anchorage 8 of the opposite steel I-girder 2; 슬래브콘크리트(10)와 복부콘크리트(11)를 다수의 경간에 걸쳐 연속하여 타설 양생한 상태에서 상기 강선 정착구(8)에 관통하여 위치한 상기 피.씨. 강연선(4)을 긴장하여 강선 정착구(8)에 정착한 것을 특징으로 하는 다경간 연속 프리플렉스 합성빔.The slab concrete (10) and the abdominal concrete (11) is placed through the steel wire anchorage (8) in a state in which the casting cured successively over a plurality of spans. A multi-span continuous preplex composite beam, characterized in that the strand 4 is tensioned and fixed to the steel anchorage 8.
KR20-2002-0029196U 2002-09-30 2002-09-30 Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon Expired - Fee Related KR200300029Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2002-0029196U KR200300029Y1 (en) 2002-09-30 2002-09-30 Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2002-0029196U KR200300029Y1 (en) 2002-09-30 2002-09-30 Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon

Publications (1)

Publication Number Publication Date
KR200300029Y1 true KR200300029Y1 (en) 2003-01-06

Family

ID=49398166

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2002-0029196U Expired - Fee Related KR200300029Y1 (en) 2002-09-30 2002-09-30 Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon

Country Status (1)

Country Link
KR (1) KR200300029Y1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101208231B1 (en) 2010-08-23 2012-12-04 권오근 Method for constructing continuous supporting structure of corrugated steel web PSC beam
KR20150054034A (en) * 2013-11-08 2015-05-20 주식회사 티아이에스 Apparatus for reinforcing a girder section force for bridge and method manufacturing the same
CN115162510A (en) * 2022-07-11 2022-10-11 中国矿业大学 Pretensioned prestressed concrete frame beam and prefabricating method thereof
CN117516610A (en) * 2023-10-10 2024-02-06 山东建筑大学 Differential transformer type displacement sensor measuring head supporting device and construction and use methods thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101208231B1 (en) 2010-08-23 2012-12-04 권오근 Method for constructing continuous supporting structure of corrugated steel web PSC beam
KR20150054034A (en) * 2013-11-08 2015-05-20 주식회사 티아이에스 Apparatus for reinforcing a girder section force for bridge and method manufacturing the same
KR101641583B1 (en) * 2013-11-08 2016-07-22 주식회사 티아이에스 Apparatus for reinforcing a girder section force for bridge and method manufacturing the same
CN115162510A (en) * 2022-07-11 2022-10-11 中国矿业大学 Pretensioned prestressed concrete frame beam and prefabricating method thereof
CN117516610A (en) * 2023-10-10 2024-02-06 山东建筑大学 Differential transformer type displacement sensor measuring head supporting device and construction and use methods thereof

Similar Documents

Publication Publication Date Title
KR101283535B1 (en) Fully-precast prestressed concrete girder bridges and construction method of such bridges
US5457839A (en) Bridge deck system
KR100881921B1 (en) Opening Type Composite Shear Girder Construction Method
KR100885663B1 (en) Continuous construction method of PS composite girder using cross beam as fixing unit and its structure
KR20040098995A (en) Construction Method for PSC Girder Bridges
KR101582599B1 (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR101043239B1 (en) Segmented prestressed concrete beam for bridges with long spans and its manufacturing method
KR100823448B1 (en) Structure and Method of Continuous Construction of Prestressed Concrete Composite Beam Bridges with Improved Sheen
KR20100025161A (en) Girder bridge connected to abutment and the construction method thereof
KR100554408B1 (en) Composite girder for bridge and construction method using same
KR200300029Y1 (en) Multi-span Continuous Preflex Composite Beam Having Part for Fixing Tendon
JP2003138523A (en) Construction method for tension string girder bridge
KR100583671B1 (en) Prestressed concrete beams made of steel anchors installed at various locations and reinforcement materials installed on upper and lower flanges and bridge construction methods using them
KR200279224Y1 (en) Multi-span continuous Preflex Composite Beam Type Bridge
KR200342287Y1 (en) A structure of prestressed preflex steel composite beam prestressed by each construction steps
KR100547485B1 (en) Multi-span continuum bridge and its construction method using unit bridge girder fabricated to reduce surplus bending moment size through bridge continuity
KR20060017949A (en) Field prefabricated prestressing girder with reinforced load capacity due to increased eccentric distance and continuous bridge construction method using the same
KR20140125754A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR20040091350A (en) Prestressed steel girder
KR100403988B1 (en) Method for forming continuous p.s.c beams with steel plate girder splice and apparatus thereof
KR102077385B1 (en) Prestressed Steel-Concrete Composite Girder
KR100480471B1 (en) Connecting Structure and Connecting Method of Honeycomb Type Composite Beam Stiffened with Prestressed Concrete Panel
KR100662814B1 (en) Prestressed Concrete Euger with Hollow Tube and Its Continuous Method
KR20140139703A (en) Steel Connector Between Precast Segments and Connection Method
KR100580223B1 (en) Prestressed steel reinforced concrete beam using various types of steel plate on upper and lower flanges and bridge installation method using the same

Legal Events

Date Code Title Description
UA0108 Application for utility model registration

St.27 status event code: A-0-1-A10-A12-nap-UA0108

UR1002 Payment of registration fee

St.27 status event code: A-2-2-U10-U11-oth-UR1002

Fee payment year number: 1

REGI Registration of establishment
UR0701 Registration of establishment

St.27 status event code: A-2-4-F10-F11-exm-UR0701

UG1601 Publication of registration

St.27 status event code: A-4-4-Q10-Q13-nap-UG1601

R18-X000 Changes to party contact information recorded

St.27 status event code: A-5-5-R10-R18-oth-X000

UR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-UR1001

Fee payment year number: 2

UN2301 Change of applicant

St.27 status event code: A-5-5-R10-R13-asn-UN2301

St.27 status event code: A-5-5-R10-R11-asn-UN2301

UR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-UR1001

Fee payment year number: 4

R17-X000 Change to representative recorded

St.27 status event code: A-5-5-R10-R17-oth-X000

UR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-UR1001

Fee payment year number: 5

UR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-UR1001

Fee payment year number: 6

FPAY Annual fee payment

Payment date: 20081224

Year of fee payment: 7

UR1001 Payment of annual fee

St.27 status event code: A-4-4-U10-U11-oth-UR1001

Fee payment year number: 7

LAPS Lapse due to unpaid annual fee
UC1903 Unpaid annual fee

St.27 status event code: A-4-4-U10-U13-oth-UC1903

Not in force date: 20091224

Payment event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

UC1903 Unpaid annual fee

St.27 status event code: N-4-6-H10-H13-oth-UC1903

Ip right cessation event data comment text: Termination Category : DEFAULT_OF_REGISTRATION_FEE

Not in force date: 20091224

P22-X000 Classification modified

St.27 status event code: A-4-4-P10-P22-nap-X000