JPH01244015A - Anchor casting for foundation pile - Google Patents
Anchor casting for foundation pileInfo
- Publication number
- JPH01244015A JPH01244015A JP25422988A JP25422988A JPH01244015A JP H01244015 A JPH01244015 A JP H01244015A JP 25422988 A JP25422988 A JP 25422988A JP 25422988 A JP25422988 A JP 25422988A JP H01244015 A JPH01244015 A JP H01244015A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- ground
- reamer
- hole
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005266 casting Methods 0.000 title claims description 17
- 238000000034 method Methods 0.000 claims description 49
- 239000012530 fluid Substances 0.000 claims description 8
- 239000002689 soil Substances 0.000 abstract description 50
- 239000004568 cement Substances 0.000 abstract description 47
- 238000009412 basement excavation Methods 0.000 abstract description 24
- 239000008267 milk Substances 0.000 abstract description 11
- 210000004080 milk Anatomy 0.000 abstract description 11
- 235000013336 milk Nutrition 0.000 abstract description 11
- 229910000897 Babbitt (metal) Inorganic materials 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 70
- 239000004567 concrete Substances 0.000 description 50
- 230000008093 supporting effect Effects 0.000 description 41
- 239000010410 layer Substances 0.000 description 40
- 230000003014 reinforcing effect Effects 0.000 description 33
- 229910000831 Steel Inorganic materials 0.000 description 26
- 239000010959 steel Substances 0.000 description 26
- 239000004576 sand Substances 0.000 description 25
- 238000005242 forging Methods 0.000 description 20
- 238000005520 cutting process Methods 0.000 description 16
- 238000005553 drilling Methods 0.000 description 13
- 239000011295 pitch Substances 0.000 description 12
- 238000003756 stirring Methods 0.000 description 12
- 239000000853 adhesive Substances 0.000 description 10
- 230000001070 adhesive effect Effects 0.000 description 10
- 238000013461 design Methods 0.000 description 7
- 239000002131 composite material Substances 0.000 description 6
- 238000010586 diagram Methods 0.000 description 6
- 230000002093 peripheral effect Effects 0.000 description 6
- 238000009434 installation Methods 0.000 description 5
- 125000006850 spacer group Chemical group 0.000 description 5
- 238000007796 conventional method Methods 0.000 description 4
- 239000002184 metal Substances 0.000 description 4
- 238000003825 pressing Methods 0.000 description 4
- 238000004458 analytical method Methods 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 239000002245 particle Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000011049 filling Methods 0.000 description 2
- 239000011372 high-strength concrete Substances 0.000 description 2
- 238000011068 loading method Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 230000002441 reversible effect Effects 0.000 description 2
- 238000009987 spinning Methods 0.000 description 2
- 239000002344 surface layer Substances 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 230000009974 thixotropic effect Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 229910000278 bentonite Inorganic materials 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000000052 comparative effect Effects 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000002156 mixing Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000009527 percussion Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000010079 rubber tapping Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Earth Drilling (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は基礎徐の施工法に関し,その目的は基礎柱体の
外面に,杭の周りの原地盤内に張り出した所要の凸条を
突設し,原地盤に杭を定着させ,杭の軸圧耐力及び杭の
引抜き耐力を増大させることにある。[Detailed Description of the Invention] The present invention relates to a method of constructing a foundation, and its purpose is to provide a necessary protrusion on the outer surface of the foundation column that extends into the original ground around the pile, and to attach the pile to the original ground. The objective is to increase the axial pressure capacity and pull-out capacity of the pile.
従来の杭の施工法を通観するに,場所打杭の造成施工時
及び既成杭の設置施工時とも,設置位置の原地盤を掘削
して杭を内蔵する地下孔を設ける施工法では,地下孔の
先端に拡底根または球根を造成して杭の先端支持力を増
大させる手段を講ずる方法が慣用されている。本来,杭
の支持力は,杭の先端に対する支持層の支持力と,杭の
周面に対する中間原地盤の支持力との合成された複合力
からなる。特に支持層が深く,且つ中間に硬質地盤があ
る施工地では,杭の周面支持力が,杭の先端支持力を超
えて大きくなる場合がある。A general view of the conventional pile construction method shows that both when creating cast-in-place piles and when installing prefabricated piles, the construction method of excavating the original ground at the installation location and creating an underground hole to house the pile, A commonly used method is to create an enlarged root or bulb at the tip of the hole to increase the support force at the tip of the pile. Originally, the bearing capacity of a pile consists of the combined force of the bearing capacity of the bearing layer against the tip of the pile and the bearing capacity of the intermediate ground against the surrounding surface of the pile. Particularly in construction sites where the bearing layer is deep and there is hard ground in the middle, the peripheral surface bearing capacity of the pile may exceed the pile tip bearing capacity.
しかしながら,この突状にかかわらず,杭の周面支持力
を強化させる良好な手段は,現行の施工法では現在に至
るまでまだ開発されていない。杭本体に一定間隔をおい
て多段の大径のフシを突設しておき,このフシ杭を地中
に打込む際,フシとフシとの間の杭本体と,周りの原地
盤との隙間に土砂を詰め込む作業を順次繰り返してフシ
杭を地中に設置する施工法は,杭の周面を支持力を増大
させる目的の施工法ではあるが,土砂詰め込みの繰り返
し作業が繁雑であり点,長尺の杭では杭の打込み抵抗が
次第に強大となって打込み不能となることから,おおむ
ね10メートル内外の短かい特殊摩擦杭として適用され
,一般的施工法としては適用し難い。However, despite this protrusion, no good means to strengthen the circumferential bearing capacity of piles has yet been developed using current construction methods. Multi-tiered large-diameter fences are protruded from the pile body at regular intervals, and when driving these stake piles into the ground, the gaps between the pile body and the surrounding ground between the stakes are removed. The construction method in which the piles are installed underground by repeatedly filling the pile with earth and sand is a construction method that aims to increase the supporting capacity of the surrounding surface of the pile, but the repeated work of filling with earth and sand is complicated. With long piles, the driving resistance of the pile gradually increases and it becomes impossible to drive, so it is applied as short special friction piles of about 10 meters or less, and is difficult to apply as a general construction method.
また鋼管杭の光端部に数段のスパイラル翼を固定連結し
,この鋼管杭を原地盤内にねじ込み,この鋼管杭を支持
層に到達させ,前記スパイラル翼を支持層に定着させよ
うとする試みもあるが,実際の施工上鋼管杭の中空部先
端を閉じれば鋼管杭のねじ込みが渋滞し,鋼管杭の中空
部先端を開けば鋼管杭の先端支持力が大幅に低下し,実
用に供し難い。上記に引用した2束は,既成杭を対象と
した特殊施工例であるが,ベノト工法,リバースサーキ
ュレイション工法及びアースドリル工法などで代表され
る場所打コンクリート杭の施工法には,地中のコンクリ
ート柱体に対する原地盤の周面支持力を特に強化させよ
うとする特殊施工例さえ見いだすことはできない。すな
わち,現行の場所打杭の施工法には,杭を内蔵する地下
孔の孔壁の原地盤に対する一切の働らきかけは全くなく
,孔壁の原地盤の表層は,掘削によって組織破壊されて
ゆるんだままの状態に放置され,この状態の地下孔にコ
ンクリートが打設されるのである。従って,コンクリー
ト柱体の周面に作用する原地盤の土砂の摩擦力及び粘着
力は,ゆるんだ状態の表層原地盤の内部摩擦力及び粘着
力を超えることはできない。In addition, several stages of spiral blades are fixedly connected to the light end of a steel pipe pile, and this steel pipe pile is screwed into the original ground, and this steel pipe pile is made to reach the support layer, and the spiral blades are fixed to the support layer. Although some attempts have been made, in actual construction, closing the hollow end of the steel pipe pile will cause problems when screwing in the steel pipe pile, and opening the hollow end of the steel pipe pile will significantly reduce the supporting capacity of the end of the steel pipe pile, making it impractical for practical use. hard. The two bundles cited above are special construction examples for pre-fabricated piles, but cast-in-place concrete pile construction methods, such as the Benoto method, reverse circulation method, and earth drill method, include underground construction. It is not possible to find any examples of special construction in which the circumferential bearing capacity of the original ground for concrete columns is particularly strengthened. In other words, in the current construction method of cast-in-place piles, there is no action on the original ground of the hole wall of the underground hole in which the pile is built, and the surface layer of the original ground of the hole wall is tissue-destroyed by the excavation. The concrete was left in a loose state, and concrete was poured into the underground hole in this state. Therefore, the frictional force and adhesive force of the earth and sand in the original ground acting on the circumferential surface of the concrete column cannot exceed the internal frictional force and adhesive force of the surface original soil in a loose state.
以下に本発明の杭の定着鋳造法を,図面に示す実施例1
に従って説明する。地上の操作クレーン及び上部動力装
置などは,当業界の分野に属する通常の知識を有する技
術者には自明の構造で,これらは省略し,杭の設置位置
の地盤を掘削する掘進装置を第1図に示す。Example 1 of the fixed casting method for piles of the present invention is shown in the drawings below.
Explain according to the following. The ground operating crane and upper power unit are structures that are obvious to engineers with ordinary knowledge in the field of this industry, so these are omitted and the excavation equipment that excavates the ground at the location of the pile is the first one. As shown in the figure.
回転軸1の先端には掘削装置Kが固定連結される。第2
図に示す掘削装置Kは,中央円筒2の周面に板厚の厚い
4枚の反り面ビット3が一体に突設され,反り面ビット
3は矢印の回転方向Pに対して後方に反り返り,反転部
4が構成される。反り面ビット3の下面にはチップ5が
装備され,また中央円筒2の下半部には先端ビット6が
突設される。また回転軸1には多段の撹拌翼7が突設さ
れ,その先端には加圧丸棒8が連結され,この加圧丸棒
8は孔壁Tを順次押圧する構造とする。なお,支持層に
至るまでの中間層の地盤掘進時には,水セメント比率0
%内外の中濃度セメントミルクを回転軸1の先端の射出
口9から射出するのであるが,このセメントミルクと掘
削土砂とは,反り面ビット3及び多段の撹拌翼7の繰り
返し操作を受け,充分に練りまぜられたソイルセメント
となる。An excavation device K is fixedly connected to the tip of the rotating shaft 1. Second
The drilling equipment K shown in the figure has four thick warped bits 3 integrally protruding from the circumferential surface of a central cylinder 2. A reversing section 4 is configured. A tip 5 is provided on the lower surface of the warped bit 3, and a tip bit 6 is provided protruding from the lower half of the central cylinder 2. Further, multi-stage stirring blades 7 are protruded from the rotary shaft 1, and a pressurizing rod 8 is connected to the tip thereof, and the pressurizing rod 8 is structured to press the hole wall T in sequence. Note that when excavating the ground in the intermediate layer up to the supporting layer, the water-cement ratio is 0.
Cement milk with a medium concentration of around 10% is injected from the injection port 9 at the tip of the rotary shaft 1, and this cement milk and excavated soil are repeatedly operated by the warped bit 3 and the multi-stage stirring blades 7, and are thoroughly mixed. It is mixed into soil cement.
以上のようにして,地下孔M内にソイルセメント層を造
成しながら掘進するのであるが掘削装置Kの主動体とな
る反り面ビット3には,孔壁Tを圧縮する特性がある。As described above, excavation is carried out while creating a soil cement layer inside the underground hole M. The warped bit 3, which is the main moving body of the drilling equipment K, has the characteristic of compressing the hole wall T.
すなわち,チップ5で堀り上げた掘削土砂は,反り面ビ
ット3の湾曲面に沿って外側に集合し,反り面ビット3
の外縁部湾曲面の回転運動を受けて孔壁Tに向う強力な
圧力を受け,軟弱地盤では掘削土砂の一部又は相当量が
周りの原地盤内に圧入される。圧縮性の乏しい硬質地盤
では土砂の原地盤内への圧入量は減少するものの,孔壁
Tには反り面ビット3の湾曲面の強力な圧力が作用し,
チップ5ぶゆるめられた孔壁Tは,たちまち反り面ビッ
ト3の曲面構成によって強力に締め固められた状態に変
成される。従って,以上の掘削装置Kで穿孔された地下
孔Hの孔壁Tは,本来の組織より締め固められて密実な
組織となり,更に多段に突設した撹拌翼の加圧丸棒8の
繰り返し押圧作用を受けてその密実度が高められる。In other words, the excavated earth and sand excavated by the tip 5 gathers outward along the curved surface of the curved bit 3, and
Due to the rotational movement of the outer curved surface of the hole, strong pressure is applied toward the hole wall T, and in soft ground, a portion or a considerable amount of the excavated soil is forced into the surrounding original ground. Although the amount of earth and sand injected into the original ground is reduced in hard ground with poor compressibility, strong pressure from the curved surface of the warped bit 3 acts on the hole wall T.
The hole wall T, which has been loosened by the tip 5, is immediately transformed into a strongly compacted state due to the curved surface configuration of the warped surface bit 3. Therefore, the hole wall T of the underground hole H drilled by the above-mentioned drilling device K is compacted and becomes a denser structure than the original structure, and the pressurizing round bar 8 of the stirring blade protruding in multiple stages is repeated. The density is increased by the pressure action.
支持層の硬質地盤に掘削装置Kが到達すると,反り面ビ
ット3の外縁湾曲面に対する掘削土砂の回転抵抗力が急
増するので,回転動力の電力消費量が激増し,支持層へ
の到達が確認できる。このときは水セメント比50%内
外の高濃度セメントミルクを射出し,地下孔Hの孔底部
にセメント量の多い根固めソイルセメント層を造成する
。When the drilling equipment K reaches the hard ground of the supporting layer, the rotational resistance of the excavated soil against the outer curved surface of the warped bit 3 increases rapidly, so the power consumption of rotational power increases sharply, confirming that it has reached the supporting layer. can. At this time, high-concentration cement milk with a water-to-cement ratio of about 50% is injected to create a hardening soil cement layer with a large amount of cement at the bottom of the underground hole H.
以上に述べた地下孔造成の穿孔工程は,実は以下に述べ
る本発明の定着鋳造法の予備工程である。The drilling process for creating an underground hole described above is actually a preliminary process of the fixed casting method of the present invention described below.
すなわち,以上の穿孔工程によって杭の設置位置には,
反り面ビット3及び加圧丸棒8によって締め固められた
孔壁Tをもつ地下孔Hが造成され,この地下孔H内には
,まだ固まらない半流動状の生のソイルセメントが蓄わ
えられる。In other words, through the above drilling process, the pile installation position is
An underground hole H with a hole wall T compacted by the warped bit 3 and the pressurized round rod 8 is created, and semi-fluid raw soil cement that has not hardened yet is stored in the underground hole H. It will be done.
一方,前記した4個の反り面ビットのうち,正対する1
対の反り面ビット3,3は,孔壁Tに溝を刻むリーマを
取りつけるリーマ基体となる。リーマ基体となる反り面
ビット3の外縁湾曲部と,反転部4からなるU形鋼内に
,5cmないし6cmの間隔をおいて上下2枚の軸受金
具10を固定連結し,この軸受金具10に差し通した軸
11に,一定の角度回転できるリーマ12を取り付ける
。On the other hand, among the four warped bits mentioned above, the one facing directly
The pair of warped bits 3, 3 serve as a reamer base to which a reamer for carving a groove in the hole wall T is attached. Two upper and lower bearing fittings 10 are fixedly connected at a distance of 5 cm to 6 cm in a U-shaped steel consisting of the outer edge curved part of the warped bit 3 that serves as the reamer base and the inverted part 4. A reamer 12 that can be rotated by a certain angle is attached to the inserted shaft 11.
このリーマ12は,第3図の実線で示すように矢印のP
方向に回転軸1が回る穿孔工程では,その刃先13の突
端が孔壁Tを圧接しながら横倒れの状態にあって作動せ
ず,リーマ12の頭15が反り面ビット3の内壁にあた
り,リーマ12は実線の位置に保持される。第1図では
横倒れ状態のリーマの正面を示す。This reamer 12 is connected to the arrow P as shown by the solid line in FIG.
In the drilling process in which the rotating shaft 1 rotates in the direction, the tip of the cutting edge 13 is in pressure contact with the hole wall T and falls sideways and does not operate, and the head 15 of the reamer 12 hits the inner wall of the warped bit 3, causing the reamer to 12 is held at the position indicated by the solid line. FIG. 1 shows the front of the reamer in a sideways state.
掘削装置Kが支持地盤の所定深度に達し,地下孔Hの孔
底部領域の根固めソイルセメントの練り返し作業が完了
した時点で,今度は回転軸1をQ方向に逆転させる。す
ると,後方が次第に分厚くなる第5図に示すリーマの刃
先斜面14にソイルセメントの圧力が作用するとともに
,孔壁Tに圧接した刃先13のとがった突端が,Q方向
に回る運動によって孔壁Tに突き刺さると,原地盤の土
圧がリーマ12に急激に作用し,リーマ12は軸11の
周りを回って1点鎖線で示す位置に回転し,リーマの背
面が反り面ビット3の切き欠き曲面16の基部にあたっ
てリーマ12は1点鎖線で示す位置に保持される。ちな
みに,リーマ12の取付け付近の反り面ビットの湾曲部
は局部的に切り欠いてある。すなわち,このときリーマ
12は第3図の1点鎖線で示す状態に立ち上がり,溝の
圧造態勢にはいる。この工程では回転軸1はQ方向に回
転するので,リーマ12の刃先13も矢印のQ方向に運
動する。刃先13の進行前面は薄く鋭利で原地盤に割り
込み易く構成され,刃先斜面14は次第に分厚くなって
刃先三面体を構成するので,リーマの進行途上の堀り切
り土砂は,両面の刃先斜面14の進行圧力を受けるとと
もに,リーマの角柱端面17及び反り面ビット3の湾曲
部外面の押圧力を受け,地下孔H内への逃げ場を失ない
,三軸圧線状態となる,上下の孔壁地盤を刃先斜面14
でむりやり押し広げて,ここに圧造溝gが刻まれ,孔壁
Tは更に押し固められる。When the drilling device K reaches a predetermined depth in the supporting ground and the work of remixing the hardening soil cement in the bottom area of the underground hole H is completed, the rotating shaft 1 is then reversed in the Q direction. Then, the pressure of the soil cement acts on the slope 14 of the cutting edge of the reamer as shown in FIG. When it penetrates into the reamer, the earth pressure of the original ground acts suddenly on the reamer 12, and the reamer 12 rotates around the shaft 11 to the position shown by the dashed line, causing the back surface of the reamer to warp into the notch of the bit 3. The reamer 12 is held at the base of the curved surface 16 at the position indicated by the dashed line. Incidentally, the curved part of the warped bit near the attachment of the reamer 12 is locally cut out. That is, at this time, the reamer 12 rises to the state shown by the one-dot chain line in FIG. 3, and enters the groove heading state. In this step, since the rotating shaft 1 rotates in the Q direction, the cutting edge 13 of the reamer 12 also moves in the Q direction of the arrow. The advancing front surface of the cutting edge 13 is thin and sharp and is configured to easily cut into the original ground, and the cutting edge slope 14 gradually becomes thicker to form a cutting edge trihedron. The upper and lower hole wall ground is subjected to the advancing pressure and the pressing force of the prismatic end face 17 of the reamer and the outer surface of the curved part of the warped bit 3, so that there is no escape into the underground hole H and the ground is in a triaxial pressure line state. The cutting edge slope 14
The forging grooves G are carved here, and the hole walls T are further compacted.
実施例1では油圧モーターによって回転軸1を作動させ
,穿孔時1分間あたりの回転数を18回とし,溝gの圧
造工程では小容量の油圧ポンプに切り換え,1分間あた
りの回転軸1の回転数を6回に減速した。また,多重滑
車を使用してワイヤロープによる回転軸1の上昇速度を
1分間あたり3メートルに制限した。従った1個のリー
マ12で刻まれる圧造溝gの造成ピッチは50cmとな
るが,他の1個のリーマ12で刻まれる圧造溝gが半回
転おくれて造成されるので,圧造溝gの個個の間隔は2
5cmとなる。第4図は以上の地下孔Hの断面模形図で
孔壁Tには等間隔に整然とした圧造溝gが刻まれ,且つ
溝gに挾まれた孔壁原地盤の組織は特に密実となる。In Example 1, the rotary shaft 1 is operated by a hydraulic motor, and the number of revolutions per minute is set to 18 times during drilling, and in the forging process of the groove g, a small-capacity hydraulic pump is used, and the number of revolutions of the rotary shaft 1 per minute is set to 18. The number was reduced to six. In addition, multiple pulleys were used to limit the rate of rise of the rotating shaft 1 by the wire rope to 3 meters per minute. Accordingly, the pitch of the heading grooves g carved by one reamer 12 is 50 cm, but the pitch of the heading grooves g carved by the other reamer 12 is delayed by half a turn, so the pitch of the heading grooves g is 50 cm. The interval between the pieces is 2
It will be 5cm. FIG. 4 is a schematic cross-sectional view of the above-mentioned underground hole H, in which the hole wall T has regularly spaced forging grooves g, and the texture of the original ground of the hole wall sandwiched by the grooves g is particularly dense.
なお,後続の圧造溝gの造成時,先行の溝gが崩れ易い
と危惧された砂質地盤の孔壁でも,圧造溝gは崩れるこ
とがなく,この溝gにすかさず流入するソイルセメント
が溝の壁面を支え,そのままの形状でこのソイルセメン
トが硬化することが,杭の掘り起こし実験によって実証
された。この地下孔H内のソイルセメントが硬化すると
,ソイルセメント柱体の外面には,孔壁Tの原地盤内に
深く食い込んだラセン状の凸条Dが突設される。外径φ
600までの中形杭を設置する地下孔Hに刻む溝gの深
さは少なくとも50mm以上とする。In addition, when creating the subsequent heading groove g, the heading groove g does not collapse even on the hole wall in sandy ground where it was feared that the preceding groove g would easily collapse, and the soil cement that quickly flows into this groove g will not collapse. Pile excavation experiments have demonstrated that this soil cement can harden while supporting the wall surface of a pile. When the soil cement in the underground hole H hardens, a helical protrusion D that digs deeply into the original ground of the hole wall T protrudes from the outer surface of the soil cement column. Outer diameter φ
The depth of the groove g cut into the underground hole H in which medium-sized piles up to 600 mm will be installed shall be at least 50 mm or more.
また,リーマ12を取付ける軸11の軸心C1は,第1
図に示すように回転軸1の軸心に対して平行せず,わず
かに斜行し,リーマ12の末端は,基部(図面の右側)
より尻上がりに構成するので,刃先13の進行先端も多
少上向きとなり,孔壁Tに刻まれる溝gの軌跡は設計ど
おりのラセン状となる。Moreover, the axis C1 of the shaft 11 to which the reamer 12 is attached is the first
As shown in the figure, it is not parallel to the axis of the rotating shaft 1, but slightly obliquely, and the end of the reamer 12 is located at the base (on the right side of the figure).
Since the tip is configured to be more upward, the leading edge of the cutting edge 13 also points upwards to some extent, and the locus of the groove g carved in the hole wall T becomes a helical shape as designed.
以上のように回転軸1を徐徐に回しながら,定められた
低速度で回転軸1を引上げると,地下孔Hの孔壁Tには
,計画どおり2条の圧造溝gが構成される。When the rotating shaft 1 is pulled up at a predetermined low speed while being rotated gradually as described above, two forging grooves g are formed in the hole wall T of the underground hole H as planned.
この施工法では,杭の周面支持力及び先端支持力を増大
させることを主目的とするので,地下孔Hに沈設するP
HC杭の設置作業は次のとおり実施する。In this construction method, the main purpose is to increase the circumferential bearing capacity and tip bearing capacity of the pile, so the P
The HC pile installation work will be carried out as follows.
最下段の下杭には必ずフシ杭αを用いる。フシ杭αには
1定間隔に多段のフシ17が突設され,上端部の外径は
各フシ17間の軸部外径(公称外径)と同一で,補強バ
ンド18を連結した定着板19は,上既杭βの定着板1
9と溶接連結される。Be sure to use a stick pile α for the bottom pile at the bottom. A multi-stage bracket 17 is protruded from the bracket pile α at regular intervals, and the outer diameter of the upper end is the same as the outer diameter (nominal outer diameter) of the shaft between each bracket 17. 19 is the anchoring plate 1 of the upper pile β
9 is welded and connected.
上段杭βの補強バンド18の外面には数片の弧状スペー
サ20が取付けてあって,このスペーサ20のガイド作
用によって杭は地下孔Hの中心に誘導される。フシ柱α
の下端部にはフシ17の外径と同一の外径とした拡大部
γが構成され,この拡大部γに装着した補強バンド18
には弧状スペーサ20が装備され,拡大部γは地下孔H
の中心に誘導される。杭の中空部に通貫させた軽量の回
転軸1’の先端は,閉鎖板21の上面に突設したネジ棒
22とネジ連結され,杭より多少先行させた閉鎖板21
の下面に連結した鋼翼23を回転させて,地下孔H内の
ソイルエメントをかきまぜるので,杭の下方のソイルセ
メントは常に流動化し,杭が地下孔Hの中間位置で高上
がりすることがない。符号24は,回転軸1’を杭の中
空部の中心に案内するガイド片である。Several pieces of arcuate spacers 20 are attached to the outer surface of the reinforcing band 18 of the upper pile β, and the pile is guided to the center of the underground hole H by the guiding action of the spacers 20. Fushi pillar α
An enlarged part γ having the same outer diameter as the outer diameter of the clasp 17 is formed at the lower end, and a reinforcing band 18 attached to this enlarged part γ is formed.
is equipped with an arc spacer 20, and the enlarged part γ is connected to the underground hole H.
guided to the center of The tip of the lightweight rotating shaft 1' passed through the hollow part of the pile is screwed to a threaded rod 22 protruding from the upper surface of the closing plate 21, and the closing plate 21 is placed slightly ahead of the pile.
The steel blades 23 connected to the lower surface of the underground hole H are rotated to stir the soil cement in the underground hole H, so the soil cement below the pile is always fluidized, and the pile does not rise high at the intermediate position of the underground hole H. Reference numeral 24 is a guide piece that guides the rotating shaft 1' to the center of the hollow part of the pile.
最終的にフシ杭αの拡大部γは閉鎖板21上に乗り,そ
の中空部は閉鎖板21で閉じられ,鋼翼23は孔底の原
地盤に圧入され,杭の拡大部γの下部端面は支持層の孔
底面に接地する。第6図に示した特殊フシ杭αは,軸部
外径より13ンク大径の杭の型枠内に,軸部簡易内型を
取付ければ,簡単にフシ杭αを製作できることは,当業
界の技術者には説明を要せず理解されるであろう。従っ
て,例えば,PHC徐の上段の杭βはφ400の杭であ
るが,フシ杭αの拡大部γの接地面積はφ450,場合
によってはφ500の杭の接地面積に広がり,しかも杭
の先端は全閉状態となるので,杭の先端支持力が,通常
の先端開放の杭の場合より格別に増大することは当然の
結果である。Finally, the enlarged part γ of the pile α rides on the closing plate 21, its hollow part is closed by the closing plate 21, the steel wing 23 is press-fitted into the original ground at the bottom of the hole, and the lower end surface of the enlarged part γ of the pile is is grounded to the bottom of the hole in the support layer. The special fixed pile α shown in Figure 6 can be easily manufactured by installing a simple inner mold for the shaft inside the formwork of a pile with a diameter 13 inc larger than the outer diameter of the shaft. It will be understood by industry engineers without any need for explanation. Therefore, for example, the pile β in the upper stage of PHC is a φ400 pile, but the ground contact area of the enlarged part γ of the fence pile α is φ450, and in some cases it expands to the ground contact area of a φ500 pile, and the tip of the pile is completely covered. Since the pile is in a closed state, it is a natural result that the bearing capacity at the end of the pile is much greater than that of a normal pile with an open end.
ともあれ,本定着鋳造法による杭の支持性能が,従来の
施工法による杭の支持性能と著しい差異を示す点は,一
般的地盤(周面支持力が多少とも期待される地盤)を対
象とした場合,載荷試験時の杭の上半部の軸力負荷量が
,杭の下半部の軸力負担量に対して極めて大きい点にあ
る。上半部の杭の軸力負担量は上半部の杭の周りの原地
盤の杭に対する周面支持力が大きいほど大きく,この優
先する軸力負担量をL1とすると,載荷試験時の軸力は
一定値Lなので,下半部の杭の軸力負担量は必然的に前
記両者の差(L−L1)となり,これを超えることはで
きない。以上のことから上半部の中間層に硬質地盤があ
り,この地盤による杭の周面支持力が特に大きい場合は
,いかに下杭の支持能力が大きくても,下杭にはその能
力に比例する軸力が作用しない場合が生ずる。仮りに載
荷試験時の軸力Lを,PHC杭の抗材のもつ最大許容軸
力(長期)の4倍にしたときの下杭の軸力負担量が過少
となる場合は,下杭は実際上省略し得る。このことを換
言すると,新しい周面支持構造からなる本定着鋳造法に
よって設置された杭は,周面に対する地盤の摩擦及び剪
断支持力が特に大きいので,必ずしも杭先端を支持層ま
で到達させる必要はないという結論に達する。いわゆる
PHC杭にとって過大となる支持力は,必ずしも必要で
はないという本工法独項の考か方が発生する。従って次
の特長が得られる。In any case, the point that the support performance of piles produced by this anchored casting method is significantly different from that of piles produced by conventional construction methods is that the support performance of piles produced by this anchored casting method is significantly different from that of piles produced by conventional construction methods. In this case, the axial load on the upper half of the pile during the loading test is extremely large compared to the axial load on the lower half of the pile. The amount of axial load on the upper half of the pile increases as the circumferential bearing capacity of the ground around the pile increases, and if this priority axial load is L1, then Since the force is a constant value L, the axial force burden on the lower half pile is inevitably the difference between the two (L-L1), which cannot be exceeded. From the above, if there is hard ground in the middle layer of the upper half, and the circumferential bearing capacity of the pile due to this ground is particularly large, no matter how large the bearing capacity of the lower pile is, the lower pile will still be used in proportion to its capacity. There may be cases where the axial force applied does not act. If the axial force L during the loading test is made four times the maximum allowable axial force (long-term) of the PHC pile reinforcement, if the axial force burden on the lower pile becomes too small, the lower pile will actually The above can be omitted. In other words, for piles installed using this anchored casting method, which has a new peripheral support structure, the friction and shear bearing capacity of the ground against the peripheral surface are particularly large, so it is not always necessary for the pile tip to reach the support layer. I come to the conclusion that no. This construction method is unique in that it is not necessarily necessary to have excessive bearing capacity for so-called PHC piles. Therefore, the following features are obtained.
(1)本施工法は,支持力の大きい摩擦杭の設置工法と
して最良であって,経済的設計が可能となる。(1) This construction method is the best method for installing friction piles with large bearing capacity, and enables economical design.
この摩擦杭(正確には剪断摩擦杭)が,他の工法による
摩擦杭と比較し,支持能力が格別に大きいことは,両者
における地盤の支持構造の差異から生ずるものであるこ
とは誠に明白である。但し,この摩擦杭,または摩擦杭
の下杭にはフシ杭αを用いて,ソイルセメント柱体と,
PHC杭との一体化を図る。It is very clear that the fact that this friction pile (more precisely, shear friction pile) has an exceptionally large bearing capacity compared to friction piles made by other construction methods is due to the difference in the ground support structure between the two. be. However, for this friction pile or the lower pile of the friction pile, a stick pile α is used to connect the soil cement column and
Aim to integrate with PHC pile.
以上とは逆に,PHC杭を必ず支持部まで到達させなけ
ればならない地盤を次に列挙し,特に問題視されている
地盤における本地工法の特長を明らかにする。Contrary to the above, the following is a list of the ground in which the PHC pile must reach the supporting part, and the features of this method on ground that are considered to be particularly problematic are clarified.
(A)深層の支持層まで軟弱地盤が続く場合支持層まで
に至る地盤が,N値0〜3の砂質地盤,又はこれに相当
する粘性地盤では,杭を支持層中に設置する。(A) When soft ground continues up to the deep supporting layer If the ground up to the supporting layer is sandy ground with an N value of 0 to 3, or equivalent viscous ground, install piles in the supporting layer.
(B)液状化が予測される地盤
支持層に至るまでに,N値30内外の砂質地盤があって
も,地震時液状化が予測される施工地では,杭先端を支
持層中に設置する。(B) Even if there is sandy ground with an N value of around 30 before reaching the ground support layer where liquefaction is expected, in construction sites where liquefaction is predicted to occur during an earthquake, the pile tips are installed in the support layer. do.
(C)地盤沈下が予測される地盤
地盤沈下地帯では,上層部の地盤の周面支持力をすべて
無視し,杭先端を支持層中に設置する。(C) Ground where ground subsidence is expected In areas where ground subsidence is expected, the pile tips are installed in the supporting layer, ignoring all circumferential bearing capacity of the upper ground.
上記の地盤では,必ず杭先端を支持層中に設置するが,
このとき下杭となるフジ杭αと,根固のソイルセメント
柱体及び硬質支持地盤とは,相互の凹凸構造(フシ17
,凸条D)によって一体の合成体となるので,他の施工
法で設置された同一外径の杭に比較して,その軸圧耐力
及び引条耐力が格別に大きいことは,杭に対する両工法
の地盤の支持構造の差異から生ずる当然の華果であるこ
とは,当業界の分野に属する技術者には,自明のことと
して理解されるであろう。従って,本施工法では下記の
第2及び第3の特長が得られる。In the above ground, the tip of the pile must be installed in the bearing layer, but
At this time, Fuji Pile α, which will be the lower pile, and the soil cement column and hard supporting ground have a mutual uneven structure (Fuji Pile 17).
, ridges D) to form a single composite body, the fact that its axial pressure resistance and tensile resistance are exceptionally large compared to piles with the same outer diameter installed using other construction methods is due to the fact that It will be obvious to engineers in the field that this is a natural result of differences in the ground support structures of the construction methods. Therefore, this construction method provides the following second and third features.
(2)本工法は地震時液状化する恐れのある地盤の杭の
施工法として最適である。(2) This method is most suitable for constructing piles in ground that is likely to liquefy during an earthquake.
(3)本工法は地盤沈下地帯における杭の施工法として
最適である。(3) This construction method is optimal as a pile construction method in areas with ground subsidence.
また上記の地盤では,必要とみられる深度から下方の孔
壁に圧造溝gを造り,根固めソイルセメント柱体に凸条
Dを設ければよく,上層の孔壁には圧造溝gは造らない
。In addition, in the above-mentioned ground, it is sufficient to create a heading groove g on the hole wall below the required depth and provide a convex groove D on the foot protection soil cement column, but do not create a heading groove g on the hole wall in the upper layer. .
実施例1ではプレボーリングする2工程施工法を説明し
たが,上記特殊地盤の施工時には,上層部の孔壁Tには
圧造溝を造らないので,1工程で杭を設置する簡易鋳造
法を実施できる。第7図,第8図及び第9図は,この簡
易鋳造法の実施例2を示すもので,図示の下杭の下半部
は,杭本体(図面の都合上省略してある。)より約10
cm大径にし,長さ5メートル内外の拡大フシ徐α1に
構成する。杭の中空部には回転軸1が通貫され,回転軸
1の先端には閉鎖板21が装着される。閉鎖板21の下
面には掘削翼25を装備する。掘進工程時には,回転軸
1の先端に突設した主動金具26が閉鎖板21の上面に
突設した受動金具27を押して閉鎖板を矢印のP方向に
回し,掘削翼25で原地盤を掘削しながら掘進し,拡大
フシ杭α1を後続させる。回転軸1の下端部には射出口
(図面では省略してある。)を設け,掘進工程では低濃
度のセメントミルク又はベントナイト泥水を射出する。In Example 1, a two-step construction method using pre-boring was explained, but when constructing the above-mentioned special ground, a forging groove is not created in the upper hole wall T, so a simple casting method that installs piles in one step is implemented. can. Figures 7, 8 and 9 show Example 2 of this simple casting method, and the lower half of the lower pile shown is from the pile body (omitted for convenience of drawing) about 10
It has a large diameter of 1.5 cm, and is configured with an enlarged diameter of about 5 meters in length. A rotating shaft 1 passes through the hollow part of the pile, and a closing plate 21 is attached to the tip of the rotating shaft 1. A digging blade 25 is installed on the lower surface of the closing plate 21. During the excavation process, the active metal fitting 26 protruding from the tip of the rotary shaft 1 pushes the passive metal fitting 27 protruding from the upper surface of the closing plate 21 to turn the closing plate in the direction of arrow P, and the excavating blade 25 excavates the original ground. The excavation is carried out while enlarging the pile α1. An injection port (not shown in the drawing) is provided at the lower end of the rotating shaft 1, and low concentration cement milk or bentonite mud is injected during the excavation process.
掘削翼25を掘削した土砂は閉鎖板25の周りから上昇
し,粘性液体を給付され,この土砂は,P方向に回ると
き拡翼する拡大撹拌翼28の回転運動を受けて軟性泥土
となる。この泥土は徐の中空部及び拡大フシ杭α1と孔
壁Tとの間の外周ルートRを経て杭の貫入に従って上昇
するが,狭い中空部に進入した泥土は,回転軸1に多段
に突設した固定翼29の回転運動を受けて流動状態とな
り栓ずまりすることがない。The earth and sand excavated by the excavation blade 25 rises from around the closing plate 25 and is supplied with viscous liquid, and this earth and sand becomes soft mud by the rotational movement of the enlarged stirring blade 28 which expands when rotating in the P direction. This mud rises as the pile penetrates through the hollow part of Xu and the outer circumferential route R between the enlarged pile α1 and the hole wall T, but the mud that has entered the narrow hollow part protrudes from the rotating shaft 1 in multiple stages. Due to the rotational movement of the fixed blades 29, it becomes fluid and does not become clogged.
掘進工程では,閉鎖板21を拡大フシ徐α1より約1メ
ートル内外先行させて,杭の下方に流動する軟性泥土を
造りながら掘進するので,杭は渋滞なく地中に沈降する
。In the excavation process, the closing plate 21 is advanced by about 1 meter in front of the expansion shaft α1, and the excavation is carried out while creating soft mud that flows below the pile, so the pile sinks into the ground without traffic jams.
以上に述べた掘進作業の基体となる閉鎖板21の下面に
は,第7図に示すとおり2本の軸30が対称位置に固定
突設される。この軸30には孔壁Tに溝を刻むリーマ1
2が回転可能に取付けてあり,このリーマ12が軸30
から外れないようにナット31を軸30の下部に装着す
る。閉鎖板21が矢印のP方向に回るときには,このリ
ーマ12は実線で示すように横倒れの状態となって,そ
の先端は孔壁Tに圧接するにすぎない。符号32はリー
マのストッパーであって,リーマ12は実線の位置から
内側には回らない。一方,閉鎖板21の外周の一部には
曲面状の押圧鋼板33を一体に下垂させ,この押圧鋼板
33の弧状外面は孔壁Tに接面しながら回転する。また
,この押圧鋼板33には,リーマ12を受入れる切り欠
き部34を設ける。As shown in FIG. 7, two shafts 30 are fixedly protruded at symmetrical positions on the lower surface of the closing plate 21, which is the basis of the excavation work described above. This shaft 30 has a reamer 1 for carving a groove in the hole wall T.
2 is rotatably mounted, and this reamer 12 is connected to the shaft 30.
A nut 31 is attached to the lower part of the shaft 30 so that it does not come off. When the closing plate 21 rotates in the direction of arrow P, the reamer 12 falls sideways as shown by the solid line, and its tip merely comes into pressure contact with the hole wall T. Reference numeral 32 is a reamer stopper, and the reamer 12 does not turn inward from the position indicated by the solid line. On the other hand, a curved pressing steel plate 33 is integrally hung from a part of the outer periphery of the closing plate 21, and the arcuate outer surface of the pressing steel plate 33 rotates while being in contact with the hole wall T. Further, this pressed steel plate 33 is provided with a notch portion 34 for receiving the reamer 12.
閉鎖板21は以上のように構成されているので,この閉
鎖板21を第7図に示す矢印のQ方向に回すと,リーマ
12のとがった先端が孔壁Tの原地盤に突込み,原地盤
の土圧を受けて回転し,押圧鋼板33の切り欠き部34
にはまり込んで第7図の一点鎖線で示す位置で停止し,
孔壁Tに圧造満gを刻む起立体勢となり,このまま閉鎖
板21をQ方向に回すと,このリーマ12によって孔壁
Tに圧造溝gが刻まれる。押圧鋼板33は,リーマで溝
gを刻むとき,土砂のはみ出しを抑え,孔壁Tに溝gを
圧造させる重要な働らきをなす。Since the closing plate 21 is constructed as described above, when the closing plate 21 is turned in the direction of the arrow Q shown in FIG. The notch 34 of the pressed steel plate 33 rotates under the earth pressure.
It got stuck and stopped at the position shown by the dashed line in Figure 7.
The hole wall T is in an upright position in which a heading groove g is carved, and when the closing plate 21 is turned in the Q direction, a heading groove g is carved in the hole wall T by the reamer 12. The pressed steel plate 33 plays an important role in suppressing the protrusion of earth and sand and forcing the groove g into the hole wall T when the groove g is carved with a reamer.
第8図は,回転軸1をP方向に回し,掘削翼25で原地
盤を掘削しながら支持層の所要の深度に閉鎖板21を到
達させた状態を示す。FIG. 8 shows a state in which the rotary shaft 1 is rotated in the P direction and the closing plate 21 has reached the required depth of the support layer while excavating the original ground with the excavating blades 25.
支持層では拡大フシ杭α1を所要位置に停止させておき
,剛強な回転軸1を6メートル内外先行させて支持層の
所定深度まで掘進させる。掘進工程では常に閉鎖板21
をP方向に回すので,リーマ12は横倒しの伏位にあっ
て無作動状態にある。In the support layer, the enlarged pile α1 is stopped at a predetermined position, and the strong rotary shaft 1 is advanced 6 meters inward and outward to excavate the support layer to a predetermined depth. During the excavation process, the closing plate 21 is always used.
Since the reamer 12 is turned in the P direction, the reamer 12 is in a prone position and is in an inoperative state.
以上の支持層では,高濃度の根固めセメントミルクを射
出する。第8図の体勢では,回転軸1をP方向に回しな
がら徐徐に引き上げると,受動金具27の上部カギ部3
5が,主動金具26の上面を抑えるので閉鎖板21も回
転軸1に従って上昇する。このようにして回転軸1から
セメントミルクを射出しながら図示の孔底部から,拡大
フシ杭α1の下方近くまでを数回往復させると,掘削土
砂とセメントミルクとは,掘削翼25及び拡大撹拌翼2
8の回転運動を受けて充分に練り返され,拡大フシ杭α
1の下方には高濃度の根固めソイルセメントが造成され
る。For the above support layer, high concentration cement milk is injected. In the posture shown in FIG.
5 suppresses the upper surface of the main drive fitting 26, so that the closing plate 21 also rises along the rotating shaft 1. In this way, by injecting cement milk from the rotary shaft 1 and reciprocating several times from the bottom of the hole shown in the figure to near the bottom of the enlarged pile α1, the excavated soil and cement milk are separated from the excavation blade 25 and the enlarged stirring blade. 2
It is sufficiently kneaded by the rotational movement of 8, and the expanded stick pile α
Highly concentrated soil cement will be created below No. 1.
このソイルセメント造成工程の終末時,拡大撹拌翼28
が拡大フシ杭α1に近傍した時点で回転軸1を逆転させ
,閉鎖板21をQ方向に回転させる。すると,たちまち
リーマ12は第8図に示す伏位の状態から,第9図に示
す起立位の状態に回転変位し,リーマ12の刃先13の
三角錐(第5図参照)は孔壁Tの原地盤内にえぐりこま
れる。また拡大撹拌翼28もQ方向の回転作用によって
回転軸1の周りに縮翼する。上記リーマ12による溝g
の圧造工程時には,実施例1と同様に回転軸1を低速回
転させ,且つ回転軸1の下降速度を所要の速度に制限(
油圧シリンダ機構などを用いる。)するが,これらの作
動はすべて上部の機械装量の作動によって操作する。At the end of this soil cement creation process, the enlarged stirring blade 28
When it approaches the enlarged stake α1, the rotating shaft 1 is reversed and the closing plate 21 is rotated in the Q direction. Immediately, the reamer 12 is rotationally displaced from the prone position shown in FIG. 8 to the upright position shown in FIG. Gouged into the original ground. Further, the enlarged stirring blades 28 are also contracted around the rotating shaft 1 by the rotational action in the Q direction. Groove g formed by the reamer 12
During the forging process, the rotary shaft 1 is rotated at a low speed as in Example 1, and the descending speed of the rotary shaft 1 is limited to the required speed (
Uses a hydraulic cylinder mechanism, etc. ), but all these operations are operated by the operation of the upper mechanical load.
従って,拡大フシ杭α1の下方の孔壁Tには約5メート
ルの高さまで所要の形状の溝gが所要のピッチ間隔でラ
セン状に造成させる。このようにして閉鎖板が孔底部に
到達したのち回転軸を引き上げると,主動金具26が閉
鎖板の受動金具27の短かいかぎ部の下部斜面を滑動し
て上昇し,回転軸1と閉鎖板21とは離脱する。またこ
のとき,拡大撹拌翼28は小さく縮翼しているので,回
転軸1は,杭の中空部を通路として容易に地上に回収さ
れる。こののち,杭を圧入して拡大フシ杭α1の先端を
閉鎖板21上に接面させ,杭を軽打又は圧入して少くと
も掘削翼25の寸法だけ原地盤内に押し込み,閉鎖板2
1を支持地盤に直接圧接させる。Therefore, in the hole wall T below the enlarged stake α1, grooves g of the desired shape are formed in a helical pattern up to a height of about 5 meters at the desired pitch intervals. When the rotating shaft is pulled up after the closing plate reaches the bottom of the hole in this way, the driving metal fitting 26 slides on the lower slope of the short hook part of the passive fitting 27 of the closing plate and rises, and the rotating shaft 1 and the closing plate I will leave 21. Further, at this time, since the enlarged stirring blades 28 are contracted to a small size, the rotating shaft 1 is easily recovered to the ground using the hollow part of the pile as a passage. After that, the pile is press-fitted so that the tip of the enlarged pile α1 comes into contact with the closure plate 21, and the pile is pushed into the original ground by at least the dimension of the excavation wing 25 by tapping or press-fitting, and the closure plate 2
1 is directly pressed against the supporting ground.
実施例2では,杭本体の外径を50cm,拡大フシ杭α
1の外径を60cm,地下孔Hの直径を70cm,溝g
の深さを片側5cmに設計施工したので,溝gの谷部の
直径は80cmとなる。In Example 2, the outer diameter of the pile body was 50 cm, and the enlarged pile α
The outer diameter of 1 is 60 cm, the diameter of underground hole H is 70 cm, and the groove g
Since the depth of groove g was designed and constructed to be 5 cm on each side, the diameter of the groove g is 80 cm.
従って,所定の支持地盤の深度から上方へ5メートルの
区間の孔壁Tの原地盤には,深さ5cmのラセン状圧造
溝gが造成され,この孔底部に拡大フシ杭α1が設置さ
れ,板固めソイルセメント外設柱体が硬化後そのラセン
状凸条Dの最大外径は80cmとなる。以上の拡大フシ
杭α1,根固めソイルセメント外殻柱体及び孔壁Tの硬
質支持地盤とは,互に相互の凹凸構造によって一体の合
成体を構成する。この三者の合成体の極限支持力の限界
を考えると,三者の凹凸部の噛み合せ部のフシ17及び
凸条Dが破壊しないと仮定(これらは形状及び構造上更
に強化できる。)すると,ラセン状凸条D間に挟まれた
原地盤の剪断破壊がその限界とならざるを得ない。以上
を換言すると,拡大フシ杭α1は,高さ5メートル,直
径70cmから80cmに至る原地盤の円環状部分の剪
断抵抗の全力で支持されるとともに,直径70cmの円
面積(ソイルセメント外殻柱体の底面積と,拡大フシ杭
α1の底面積との和)に作用する支持地盤の圧縮抵抗力
を受け,立体的広範囲の支持地盤によって支持されるこ
ととなる。このように立体的広範囲の支持地盤によって
支持される杭は,現在までの低公害工法によってはいま
だ得られないことは明らかであって,本工法の一工程の
簡易鋳造法によっても,打撃工法に劣らない強大な先端
支持力をもつ杭を地中に設置し得ることが明白となった
。実施例2では,リーマ12を閉鎖板21に装備したが
,このリーマ12は1対の拡大撹拌翼28の先端に装備
する構造に設計変更できるものである。このときは埋殺
し装置となる閉鎖板21の製造原価が低下する。Therefore, a helical forging groove g with a depth of 5 cm is created in the original ground of the hole wall T in a section 5 meters upward from the depth of the predetermined supporting ground, and an enlarged fence pile α1 is installed at the bottom of this hole. After the plate-hardening soil cement external column hardens, the maximum outer diameter of the helical protrusion D becomes 80 cm. The above-mentioned enlarged fence pile α1, foot protection soil cement outer shell column, and hard supporting ground of the hole wall T constitute an integral composite body due to their mutual uneven structure. Considering the limit of the ultimate support capacity of the composite body of these three, assuming that the flange 17 and the protrusion D at the interlocking part of the concavo-convex portion of the three do not break (they can be further strengthened in shape and structure), The shear failure of the original ground sandwiched between the spiral ridges D has to be its limit. In other words, the expansion pile α1 is supported by the full force of the shear resistance of the annular part of the original ground with a height of 5 meters and a diameter of 70 to 80 cm, and a circular area of 70 cm in diameter (soil cement outer shell column). It receives the compressive resistance force of the supporting ground acting on the base area of the body (the sum of the base area of the expanded pile α1), and is supported by the supporting ground over a three-dimensional wide area. It is clear that piles that are supported by a wide range of three-dimensional support ground cannot be obtained using current low-pollution construction methods. It has become clear that it is possible to install piles underground that have an equally strong tip bearing capacity. In the second embodiment, the reamer 12 is installed on the closing plate 21, but the design of the reamer 12 can be changed to be installed at the tip of the pair of enlarged stirring blades 28. In this case, the manufacturing cost of the closing plate 21 serving as the burial device is reduced.
また従来の施工法では,先端開放の杭を用いて支持層に
拡大球根を造るが,杭の中実性補償する手段として中空
部内にセメントミルクを射出するとともに,拡大球根の
上半部に杭の先端を浮かせ,杭に作用する軸力を,杭の
端面から球根の底面に向う広く拡散する特殊構造とする
ので,杭に引抜き力が作用すると,杭の先端部が容易に
球根から抜け上がる欠点がある。In addition, in the conventional construction method, an enlarged bulb is created in the support layer using open-ended piles, but as a means of compensating for the solidity of the pile, cement milk is injected into the hollow part, and a pile is placed in the upper half of the enlarged bulb. The special structure allows the tip of the pile to float and spreads the axial force acting on the pile widely from the end of the pile to the bottom of the bulb, so when a pull-out force is applied to the pile, the tip of the pile easily pulls up from the bulb. There are drawbacks.
以上に反し,支持層中に設置した本実施例2の杭は,そ
の拡大フシ杭α1の全長が,根固めソイルセメント内に
フシ17の突設によって一体に定着し,且つ根固めソイ
ルセメントは,そのラセン状突条の張り出し構成によっ
て,硬翼支持層内に深く定着するので,硬質支持地盤の
立体的剪断抵抗の全力が拡大フシ杭α1に作用し,杭の
引抜き抵抗力が特に強大となる。従って下記の第4の特
長が得られる。Contrary to the above, in the pile of Example 2 installed in the support layer, the entire length of the enlarged fence pile α1 is integrally fixed in the foot hardening soil cement by the protruding installation of the fence 17, and the foot hardening soil cement is Due to the overhanging configuration of the helical protrusions, it is deeply anchored in the hard wing support layer, so the full force of the three-dimensional shear resistance of the hard support ground acts on the expanded stick pile α1, and the pull-out resistance of the pile is particularly strong. Become. Therefore, the following fourth feature is obtained.
(4)本施工法によって支持層に設置された杭は,引き
抜き力が生じ易い特殊構造物の基礎杭として最良である
。(4) Piles installed in the support layer using this construction method are best used as foundation piles for special structures where pull-out forces are likely to occur.
従来の施工法では,打撃工法であれ,低工害施工法であ
れ,下杭には大きな引抜き力は作用しないものと考え,
下杭にはプレストレスの小さいA種のPHC杭を用いて
いたが,上記特殊な場合は,本工法ではB種又はC種の
PHC杭の下杭を用いるべきであることが明白となった
。In conventional construction methods, whether it is the impact method or the low-damage construction method, it is assumed that large pull-out forces do not act on the lower pile.
A type A PHC pile with low prestress was used as the lower pile, but in the special case mentioned above, it became clear that lower piles such as B or C type PHC piles should be used in this construction method. .
以上に述べた徐の定着鋳造法は,既成杭の周りに遅硬性
流動物たるソイルセメントを造成し,このソイルセメン
トを原地盤に鋳造定着させるとともに,このソイルセメ
ントと既成板との一体化を図ったもので,ソイルセメン
トは,杭と原地盤とを一体化させる重要な媒材の働らき
をする。Xu's fixed casting method described above creates soil cement, which is a slow-hardening fluid, around a pre-formed pile, casts and fixes this soil cement in the original ground, and integrates this soil cement with a pre-formed plate. Soil cement acts as an important medium to integrate the pile and the original soil.
以下に述べる実施例3は,媒材を必要とせず,杭の本体
となるコンクリート柱体と,原地盤とを一体の合成体と
する更に積極的且つ、単純な施工法である。実施例3は
,水を循環させるリバース工法に,本発明の定着鋳造法
を適用させたものである。第10図は支持地盤に掘削装
置K1を到達させたのち,この孔底部に拡大孔H1を造
成するときの装置の態様を示す。水と土砂を吸い上げる
サクション軸1。の先端には,軸部地下孔Hを掘削する
円錐状基体36の外面に4条のアングル37を溶接し,
このアングル37にチップ5(1個のアングルだけに図
示してある。)を取付け,円錐状基体36の中央を通貫
したサクション軸1。先端は開口し,その突端に先端ビ
ット6が固着される。掘削装置K。は,サクション軸1
。のQ方向回転によって地盤を掘進するものであるが,
この装置K。が支持層の所定深度に達した時点で,サク
ション軸1。をQ方向に回転させる。以下に述べる下段
拡大翼38及び上段拡大翼39の縮翼拡翼の開閉機構は
,既成杭の球根造成時の常用手段として公知に属するの
で明細は省略する。すなわち,サクション軸1。を孔底
部でP方向に回すと,下段拡大翼38及び上段拡大翼3
9は,サクション軸1。に連結した軸受金具40に差し
通したピン41の周りを回って第10図に示す最大拡翼
の状態に至り,孔壁Tの原地盤内に深く潜入し,その外
縁の斜辺42で原地盤を掘削する体勢となる。下段拡大
翼38と上段拡大翼39の斜辺42の勾配は同一にし,
上段拡大翼39で掘削した外側の孔壁地盤を引き続いて
下段拡大翼38が更に大きく掘削することとなる。Embodiment 3, which will be described below, is a more active and simple construction method that does not require any medium and uses a concrete column, which is the main body of the pile, and the original ground as a single composite body. In Example 3, the fixed casting method of the present invention is applied to a reverse construction method that circulates water. FIG. 10 shows the state of the excavating device K1 when it reaches the supporting ground and then creates an enlarged hole H1 at the bottom of the hole. Suction shaft 1 sucks up water and soil. At the tip of the shaft, four angles 37 are welded to the outer surface of the conical base 36 for excavating the shaft underground hole H.
A tip 5 (only one angle is shown) is attached to this angle 37, and a suction shaft 1 passes through the center of the conical base 36. The tip is open, and a tip bit 6 is fixed to the tip. Drilling rig K. is suction shaft 1
. It excavates the ground by rotating in the Q direction.
This device K. When the suction shaft 1 reaches a predetermined depth in the support layer. Rotate in the Q direction. The opening/closing mechanism of the contracting wing expansion blades of the lower stage expanding wings 38 and the upper stage expanding wings 39, which will be described below, is a well-known means commonly used when creating bulbs for existing piles, so the details thereof will be omitted. That is, suction shaft 1. When turned in the P direction at the bottom of the hole, the lower expansion blade 38 and the upper expansion blade 39 move toward the suction shaft 1. The pin 41 inserted into the bearing fitting 40 connected to the It is in a position to excavate. The slopes of the oblique sides 42 of the lower enlarged wing 38 and the upper enlarged wing 39 are made the same,
Continuing on from the outer hole wall ground excavated by the upper stage enlarging wing 39, the lower stage enlarging wing 38 excavates even more.
従って,この回転軸1。をP方向に回しながら徐徐に引
き上げると,この両拡大翼38,39の掘削軌跡として
拡大地下孔H。が造成され,この地下孔H。の上端は軸
部地下孔Hの直径と同一となり,軸部地下孔Hと段差な
くつながる。第10図は,支持層内に高さ約5メートル
の拡大地下孔H。を造成した状態を示す。頚部孔壁の斜
面は緩勾配にして土砂の崩落を予防するが,掘削時,原
地盤を斜め上方に押圧しながら掘削するので,孔壁斜面
の表層が押圧されて引き締まり,土砂の崩落が防止され
る。以上のようにして支持層に拡大地下孔H。を造成し
たのち,孔底部のスライムをさらいあげ,サクション軸
1。をQ方向に回転させながら上昇させて回収するので
あるが,このとき上下の拡大掘削翼38,39は小さく
縮翼して軸部地下孔H内を容易に通過し得る。以上の地
下孔H,H。の造成作業は,本発明の定着鋳造法を行う
予備工作である。Therefore, this rotating shaft 1. When it is gradually pulled up while turning in the P direction, the enlarged underground hole H is created as the excavation trajectory of both enlarged wings 38 and 39. was created, and this underground hole H. The upper end of the hole is the same as the diameter of the shaft underground hole H, and is connected to the shaft underground hole H without any difference in level. Figure 10 shows an enlarged underground hole H approximately 5 meters high in the supporting layer. Shows the state in which it has been created. The slope of the neck hole wall is made gentle to prevent the collapse of earth and sand, but during excavation, the original ground is pressed diagonally upwards, so the surface layer of the slope of the hole wall is pressed and tightened, preventing the collapse of earth and sand. be done. As described above, the underground hole H is expanded into the supporting layer. After creating the hole, scoop up the slime at the bottom of the hole and attach the suction shaft 1. The excavator is raised and recovered while being rotated in the Q direction. At this time, the upper and lower enlarged excavation blades 38 and 39 contract to a small size so that they can easily pass through the shaft underground hole H. Above underground holes H, H. The preparation work is a preliminary work for performing the fixed casting method of the present invention.
このようにして地下孔H,H。を造成したのち,上端に
コンクリートを受入れるホッパーを装着したケリーバを
公用のロータリテーブルに貫通させ,このケリーバに所
要数のトレミー管を接続して,トレミー管の先端を孔底
部まで到達させる。このトレミー管43の先端部の所要
位置には,第11図に示す軸受金具40に差し通したピ
ン41に大形リーマ12が装着され,この大形リーマ1
2。は軸部地下孔Hを通過するときは実線で示すように
小さく縮翼する。図面は片方のリーマ12。In this way underground holes H, H. After this, a public rotary table is passed through a Kerry bar with a hopper for receiving concrete at its upper end, and the required number of tremie pipes are connected to this Kerry bar, and the tips of the tremie pipes are made to reach the bottom of the hole. A large reamer 12 is attached to a pin 41 inserted into a bearing fitting 40 shown in FIG.
2. When passing through the shaft underground hole H, the blade shrinks to a small size as shown by the solid line. The drawing shows one reamer 12.
だけを示した構造略図で,他方の大形リーマは図示と全
く対称位置に同一形状をなしてトレミー管マ3に連結さ
れる。この大形リーマ12。の装着位置からすこし上方
のトレミー管43に,第1図に示す小形のリーマ12を
取付けた反り面ビット3(第1図参照)を一体に連結す
る。以上の2種のリーマを装備したトレミー管を地下孔
H,H。The other large reamer is connected to the tremie tube reamer 3 in a completely symmetrical position and in the same shape as shown in the diagram. This large reamer 12. A curved bit 3 (see FIG. 1) with a small reamer 12 attached thereto shown in FIG. 1 is integrally connected to the tremie tube 43 slightly above the installation position. The tremie tubes equipped with the above two types of reamers are installed in underground holes H and H.
内に挿入設置したのち,前記ホッパーにコンクリートを
受入れ,トレミー管43を通じ拡大地下孔H。内にコン
クリートを送入する。送入コンクリートの層厚がおよそ
4メートルを越えた時点で,まずトレミー管43の回転
速度を1分間あたり3回ないし4回の低速にして回すと
,
大形リーマ12。はコンクリートの回転抵抗を受けて開
きはじめ,リーマ12。の刃先13のとがった先端が,
拡大地下孔H。の孔壁Tに突きささり,原地盤内に刃先
13が潜入し,やがて大形リーマ12。は一点鎖線で示
す状態に最大拡翼し,この状態は軸受金具40に固着さ
せた係止金具45の支持作用によって保持される。刃先
13が孔壁Tに溝を刻むとき,その局部の土砂は拡大地
孔内にはみ出ようとするが,刃先13の基部に取付けた
孔壁Tを押圧する広面積の曲線ガード44が土砂のはみ
出しを抑止するので,この土砂は孔壁の原地盤を上下の
方向に押しわけて,ここに圧造溝gが造成される。なお
,このトレミー管43をP方向に回しながら,1分間あ
たりの引上げ速度を約3メートルに制限して引き上げる
と,拡大地下孔H。の孔壁にはピッチ間隔40cmない
し50cmのラセン状圧造溝gが造成される。拡大地下
孔H。の直径に従ってトレミー管43の回転速度は1〜
2回/minに低速させてよく,このときはトレミー管
43の引上げ速度も減速して所要のピッチのラセン状溝
が刻まれるように設計する。このようにトレミー管43
の回転子低速にするので,トレミー管の出力トルクが増
大し,圧造溝の深さは大形杭では10cm内外の深さに
造成し得る。After the concrete is inserted into the hopper, it is passed through the tremie pipe 43 to the enlarged underground hole H. Concrete will be delivered inside. When the layer thickness of the incoming concrete exceeds approximately 4 meters, first, the tremie pipe 43 is rotated at a low speed of 3 to 4 times per minute, and the large reamer 12 is rotated. Reamer 12 begins to open due to the rotational resistance of the concrete. The sharp tip of the cutting edge 13 is
Expanded underground hole H. The cutting edge 13 penetrates into the hole wall T, and eventually the large reamer 12 is formed. The blades are expanded to the maximum in the state shown by the dashed line, and this state is maintained by the supporting action of the locking fitting 45 fixed to the bearing fitting 40. When the cutting edge 13 carves a groove in the hole wall T, the local earth and sand tries to protrude into the enlarged hole, but the wide-area curved guard 44 attached to the base of the cutting edge 13 and pressing against the hole wall T prevents the earth and sand from moving. In order to prevent extrusion, this earth and sand pushes the original ground of the hole wall in the vertical direction, and a forging groove g is created here. If the tremie tube 43 is turned in the P direction and pulled up while limiting the pulling speed to about 3 meters per minute, the enlarged underground hole H will be reached. Spiral-shaped forging grooves g with a pitch interval of 40 cm to 50 cm are created on the hole wall. Expanded underground hole H. The rotational speed of the tremie tube 43 varies from 1 to
The pulling speed may be reduced to 2 times/min, and in this case, the pulling speed of the tremie tube 43 is also slowed down, and the design is such that a helical groove of a required pitch is carved. In this way, the tremie tube 43
Since the rotor speed is set to be low, the output torque of the tremie tube increases, and the depth of the forging groove can be made to a depth of about 10 cm for large piles.
コンクリートの継続送入と,トレミー管の操作によって
拡大地下孔H。の平行孔壁Tに圧造溝を造ったのち,ト
レミー管43をQ方向に回すと,大形リーマ12。は土
圧とコンクリート圧を受けて第11図の実線に示す状態
に縮翼し,軸部地下孔Hを容易に通過し得る大きさとな
る。Underground hole H is enlarged by continuous supply of concrete and operation of tremie pipe. After making a forging groove in the parallel hole wall T, when the tremie tube 43 is turned in the Q direction, the large reamer 12 is formed. Under the influence of earth pressure and concrete pressure, the blade shrinks to the state shown by the solid line in Figure 11, and becomes large enough to easily pass through the shaft underground hole H.
このようにしてトレミー管43に連結した反り面ビット
3を,軸部地下孔H内に移行させてトレミー管43をQ
方向に回転させると,小形のリーマ12が土圧を受けて
起立状態ととなり圧造溝を造る体勢となることはまえに
述べたとおりである。The warped bit 3 connected to the tremie tube 43 in this way is moved into the shaft underground hole H, and the tremie tube 43 is moved to the Q
As mentioned above, when rotated in the direction, the small reamer 12 receives earth pressure and becomes erect, and is in a position to create a forging groove.
この起立体勢になったのちの圧造溝の造成操作は実施例
1に詳述したので,ここでは説明を省略する。ただ,こ
の場合はトレミー管を通じてコンクリートを補給するの
で,軸部地下孔H内のコンクリート上端位置を常に点検
しながら,リーマ12の作動が常にコンクリート内で行
われるように制御しなければならない。以上の圧造構造
成の操作によって拡大地下孔H。及び軸部地下孔Hの双
方に計画どおりの圧造溝gが刻まれ,地下孔内にはコン
クリートが蓄わえられる。The operation for creating the forging grooves after this raised state was described in detail in Example 1, so the explanation will be omitted here. However, in this case, since concrete is supplied through the tremie pipe, it is necessary to control the reamer 12 so that the operation of the reamer 12 is always carried out within the concrete while constantly checking the position of the upper end of the concrete in the shaft underground hole H. The underground hole H is enlarged by the above heading structure operation. A forging groove G is carved as planned in both the shaft part underground hole H, and concrete is stored in the underground hole.
なお,不工法で使用するコンクリートには膨張性セメン
トを用い,コンクリートの硬化後,孔壁Tにコンクリー
ト柱体の圧力を作用させるように施工すると,本鋳造工
法の支持力増強の効果が高められるが,この詳細につい
ては後述する。In addition, the effect of increasing the bearing capacity of this casting method can be enhanced by using expandable cement for the concrete used in the non-casting method and applying the pressure of the concrete column to the hole wall T after the concrete has hardened. However, the details will be explained later.
ところで地下孔が10メートル内外の浅い場合は,地下
孔のコンクリート内に組立て鉄筋籠を差し込むと容易に
自沈して目的を達し得るが,地下孔が深くなり,コンク
リートの打設時点と,鉄筋籠の沈設時点との間に長時間
が経過すると,コンクリートのチクソトロビック性(静
止状態のコンクリートが流動性を失い,多少の外力では
動かなくなる性質)が高くなり,鉄筋籠の沈降設置がほ
とんど不可能となる。コンクリートのチクソトロビック
性を低下させるには,強大な圧力を加えるよりも,コン
クリートに軽度の振動力を作用させた方が効果的である
。鉄筋籠に振動力を作用させると,鉄筋籠が高速度運動
をおこすので,主筋と帯筋との溶接は入念に行う。鉄筋
籠配設の一例を示せば,主鉄筋の上端内側に高さ20c
m内外の鋼板リングを配設し,この鋼板リングの外面に
主鉄筋を溶接し,この鋼板リングの三等分点又は四等分
点を,振動機の分岐アームに設けたチャックで掴み,鋼
板リングを介して全鉄筋籠に振動力を伝達し,鉄筋籠を
コンクリート内に沈降させる。鉄筋籠を地下孔Hの中央
に誘導するには,鉄筋籠の所要位置に所要数のスペーサ
を取付けておく。下段の鉄筋籠に上段の鉄筋籠を接続す
るには,上段の全主筋の下端部を下段鉄筋籠の鋼板リン
グの外側に均等に配設し,この全主筋を鋼板リングに溶
接する。この上段の鉄筋籠の上端にも,前記鋼板リング
が一体に溶接された構造とする。従って上段鉄筋籠の鋼
板リングをチャックで掴み,振動機の振動力を加えると
,その振動力は上段及び下段の全鉄筋に伝達し,この鉄
筋籠の周りのコンクリートは振動力を受けて流動軟化し
,鉄筋籠は円滑にコンクリート内に沈降する。このよう
にして所要数の鉄筋籠を順次継ぎたしてゆくので,地下
孔の深さが50メートルを超えても鉄筋籠の沈降が渋滞
することはない。なお,上下の鉄筋籠を眞っすぐに接続
する手段としては,上段の鉄筋籠の主筋の下端部の適切
な位置の内側に,直角度を正確にしたフープ鉄筋を一体
に溶接しておくと,接続作業時,このフープ鉄筋が下段
の鋼板リング上に乗り,眞っすぐな鉄筋籠の継手作業が
容易に実施できる。By the way, if the underground hole is shallow (about 10 meters or less), inserting the prefabricated reinforcing bar cage into the concrete of the underground hole will easily scuttle and achieve the purpose, but the underground hole will become deeper and the time of concrete pouring and the reinforcing bar cage will be different. If a long period of time passes between the time of sinking and the time of settling, the thixotropic property of concrete (the property of concrete in a static state losing its fluidity and becoming immovable by some external force) becomes high, and it becomes almost impossible to set the reinforcing steel cage in a sinking position. It becomes possible. In order to reduce the thixotropic properties of concrete, it is more effective to apply a mild vibration force to the concrete than to apply enormous pressure. When a vibration force is applied to a reinforcing bar cage, the reinforcing bar cage will move at high speed, so welding between the main bars and stirrups must be done carefully. To give an example of reinforcing bar cage arrangement, a height of 20 cm is placed inside the upper end of the main reinforcing bar.
A steel plate ring inside and outside m is arranged, a main reinforcing bar is welded to the outer surface of this steel plate ring, the third or fourth dividing point of this steel plate ring is grasped with a chuck provided on the branch arm of the vibrator, and the steel plate is Vibration force is transmitted to the entire reinforcing bar cage through the ring, causing the reinforcing bar cage to sink into the concrete. In order to guide the reinforcing bar cage to the center of the underground hole H, a required number of spacers are attached to the required positions of the reinforcing bar cage. To connect the upper reinforcing bar cage to the lower reinforcing bar cage, the lower ends of all the upper reinforcing bars are placed evenly on the outside of the steel plate ring of the lower reinforcing bar cage, and all of these main bars are welded to the steel ring. The above-mentioned steel plate ring is also integrally welded to the upper end of this upper reinforcing bar cage. Therefore, when the steel plate ring of the upper reinforcing bar cage is grasped with a chuck and the vibration force of the vibrator is applied, the vibration force is transmitted to all the reinforcing bars in the upper and lower tiers, and the concrete around this reinforcing bar cage receives the vibration force and becomes fluid and soft. However, the reinforcing bar cage sinks smoothly into the concrete. In this way, the required number of reinforcing bar cages are successively connected, so even if the depth of the underground hole exceeds 50 meters, there will be no congestion due to the sinking of the reinforcing bar cages. In addition, as a means to connect the upper and lower reinforcing bar cages straight, it is possible to weld hoop reinforcing bars with accurate perpendicularity to the inside of the lower end of the main bar of the upper reinforcing bar cage at an appropriate position. During connection work, this hoop reinforcing bar rides on the lower steel plate ring, making it easy to connect straight reinforcing bar cages.
以上の鉄筋籠の配設によって場所打鉄筋コンクリート杭
の造成作業がすべて完了する。By placing the above-mentioned reinforcing bar cages, all the construction work for cast-in-place reinforced concrete piles will be completed.
従来の場所打杭と,本発明の定着鋳造法により造成され
る場所打杭とを比較すると,本場所杭最大特長としては
,軸部地下孔H及び拡大地下孔H。Comparing conventional cast-in-place piles and cast-in-place piles created by the fixed casting method of the present invention, the biggest features of this pile are the underground hole H in the shaft and the enlarged underground hole H.
の孔壁Tに圧造溝gが刻まれ,孔壁の原地盤が圧造溝g
の造成時圧縮力を受けて密実化し,この密実化した孔壁
の圧造溝gにコンクリートが流入し,コンクリートの硬
化後,コンクリートの外面には密実な原地盤に張り出し
た凸条Dが突設され,コンクリート柱体と原地盤とが一
体の合成体となることである。特に実施例3では,鉄筋
籠の沈設時,鉄筋籠を介して地下孔の全長のコンクリー
トに振動力を作用させるので,孔壁Tに造成した溝に流
入した局部コンクリートを密実にするとともに,振動す
るコンクリートの流動圧力によって,孔壁Tの原地盤を
更に締め固め得る。すなわち,孔壁Tに地下孔の深さに
相当する生コンクリートの高圧を作用させる。A forging groove g is carved in the hole wall T, and the original ground of the hole wall is the forging groove g.
The concrete becomes compact due to the compressive force during formation, and the concrete flows into the compacted heading groove g of the hole wall. After the concrete hardens, the outer surface of the concrete has a convex strip D that overhangs the compact original ground. This means that the concrete column and the original ground form a single composite body. In particular, in Embodiment 3, when the reinforcing bar cage is sunk, vibration force is applied to the concrete along the entire length of the underground hole through the reinforcing bar cage. The original ground of the hole wall T can be further compacted by the flow pressure of the concrete. That is, high pressure of fresh concrete corresponding to the depth of the underground hole is applied to the hole wall T.
ところで,この凸条Dを突設したコンクリート柱体と,
周りの原地盤からなる合成体の支持力の内容分析が,本
発明の最も重要な基本問題である。By the way, this concrete column with protruding stripes D and
The content analysis of the bearing capacity of the composite body consisting of the surrounding original soil is the most important basic problem of the present invention.
従来工法では,針勅盤の杭の周面に作用する支持力は,
杭の周面に接する原地盤の接触面,幾有学的に表現すれ
ば杭の周りの厚さのない第1円筒A(第4図参照)の周
面から,土砂の粘着力及び摩擦力が単一支持力として杭
の周面に作用する。この第1円筒Aの周面積をSと定め
る。In the conventional construction method, the supporting force acting on the peripheral surface of the pile of the needle plate is
The contact surface of the original ground in contact with the circumferential surface of the pile, expressed geometrically, from the circumferential surface of the first cylinder A (see Figure 4) with no thickness around the pile, the adhesive force and frictional force of the earth and sand. acts on the circumferential surface of the pile as a single supporting force. The circumferential area of this first cylinder A is defined as S.
一方,本鋳造法における支持力は,第1円筒Aの周面積
Sからラセン状凸条Dの基紡面積を差し引いた有効周面
積(およそ0.8Sとなる。)から土砂の粘着力及び摩
擦力が第1支持力として杭の周面に作用するだけでなく
,ラセン状凸条Dの山を結ぶ第2円筒B(第4図参照)
の周面に沿う地盤の剪断面の剪断面の剪断強さτが,第
2支持力として杭に一体に突設した凸条Dに作用する。On the other hand, the supporting force in this casting method is calculated from the effective circumferential area (approximately 0.8S) obtained by subtracting the basic spinning area of the spiral protrusions D from the circumferential area S of the first cylinder A, and the adhesion force and friction of the earth and sand. The force not only acts on the peripheral surface of the pile as the first supporting force, but also acts on the second cylinder B that connects the peaks of the spiral protrusions D (see Figure 4).
The shear strength τ of the shear plane of the ground along the circumferential surface of the pile acts on the ridge D integrally protruding from the pile as a second supporting force.
第2円筒Bの直径は,通常の設計では第1円筒Aの直径
1.1〜1.2倍に設計する。The diameter of the second cylinder B is usually designed to be 1.1 to 1.2 times the diameter of the first cylinder A.
一般的に剪断強さτ(kg/cm2)は下記の(1)式
で示される。Generally, shear strength τ (kg/cm2) is expressed by the following equation (1).
τ=Ptanφ+C……(1)
P:剪断面に直角に作用する圧力(kg/cm2φ:土
の内部摩擦角
tanφ:摩擦係数
C:粘着力(kg/cm2)
ここでまず砂質地盤について検討する。第1円筒A系の
摩擦力fの強さは,杭のコンクリート面と土砂との摩擦
係数μAと,第1円筒Aに対する外圧Pに関連して決定
される。摩擦係数μAの最大値は0.5とされる。また
第2円筒Bにおける剪断強さをきめる砂の内部摩擦角は
,砂の組織がゆるく均等な円形粒状砂の場合およそ28
°,従って摩擦係数μBは0.53となり,第1円筒の
μAとほとんど同等とみなされる。以上のことから,砂
質地盤がゆるんだ状態で,砂粒子がそろった円形をなす
最悪条件の場合に限り,第2円筒における剪断強さτは
,第1円筒Aの砂粒子のコンクリート周面に作用する摩
擦力fとほぼ同等となるが,剪断強さにはわずかながら
土砂の粘着力が加算されるので,剪断強さτは前記周面
摩擦力fより小さくなることはない。τ=Ptanφ+C……(1) P: Pressure acting perpendicularly to the shear plane (kg/cm2φ: Internal friction angle of soil tanφ: Coefficient of friction C: Adhesive force (kg/cm2) First, let us consider sandy ground. The strength of the frictional force f of the first cylinder A system is determined in relation to the friction coefficient μA between the concrete surface of the pile and the earth and sand, and the external pressure P against the first cylinder A. The maximum value of the friction coefficient μA is The internal friction angle of the sand, which determines the shear strength in the second cylinder B, is approximately 28 in the case of circular granular sand with a loose and uniform sand structure.
Therefore, the friction coefficient μB is 0.53, which is considered to be almost equal to μA of the first cylinder. From the above, only in the worst case where the sandy ground is loose and the sand particles form a uniform circle, the shear strength τ in the second cylinder is the same as the concrete circumference of the sand particles in the first cylinder A. However, since the adhesive force of the earth and sand is slightly added to the shear strength, the shear strength τ does not become smaller than the circumferential friction force f.
次に粘性土地盤について考える。粘性土の粘着力Cは,
圧力Pがゼロの場合の剪断強さにほぼ等しいとされるの
で,以上のことから粘性土の剪断強さの最小限度は粘着
力Cとなる。以上を総合すると,砂質地盤であれ,粘性
土地盤であれ,土質が最悪条件の場合に限り,第2円筒
系の地盤の剪断強さτは,第1円筒系の土砂のコンクリ
ート周面に作用する摩擦力f及び粘着力Cと同等となる
ことはあっても,これらより以下になることはない。Next, let's consider the sticky ground. The cohesive force C of clayey soil is
Since it is said that the shear strength is approximately equal to the shear strength when the pressure P is zero, from the above, the minimum shear strength of cohesive soil is the adhesive strength C. To summarize the above, only when the soil condition is the worst, whether it is sandy ground or clay ground, the shear strength τ of the ground of the second cylindrical system will be equal to the concrete surrounding surface of the earth and sand of the first cylindrical system. Although it may be equal to the applied frictional force f and adhesive force C, it will never be less than these.
以上のことから,局部の土砂が最悪条件の場合,下記の
2式が成立する。From the above, when the local soil is in the worst condition, the following two equations hold true.
τ≧C τ≧f
このように,それぞれの土質において剪断強さτ,周面
摩擦力f及び周面粘着力Cとが,それぞれ別個に等しく
なり得る場合,それぞれの支持力の大きさは,その作用
面積に比例する。τ≧C τ≧f In this way, if the shear strength τ, circumferential surface friction force f, and circumferential surface adhesive force C can be independently equal for each soil type, the magnitude of each supporting force is It is proportional to its area of action.
1.従来工法における支持力作用面積(第1円筒)SM
2
2.本工法の支持力作用面積 イ.(第1円筒の1部)
0.85M2
ロ.(第2円筒 1.15〜1.25M2計 1.95
〜2SM2
以上の結果,第2円筒Bの周面に沿う砂質土がゆるみ,
且つその摩擦係数が0.5内外の低係数であり,また第
2円筒Bに直角に作用する内圧Pが低く,粘性土の剪断
強さがその粘着力とほぼ同等となる,第2円筒系の剪断
強さにとって諸条件が最悪条件における本工法の杭の縦
支持力は,従来工法における杭の総支持力の1.9倍な
いし2倍となる。1. Supporting force action area (first cylinder) SM in conventional construction method
2 2. Bearing force action area of this method a. (Part of the first cylinder)
0.85M2 b. (Second cylinder 1.15-1.25M2 total 1.95
~2SM2 As a result of the above, the sandy soil along the circumference of the second cylinder B loosens,
In addition, the second cylindrical system has a low friction coefficient of around 0.5, the internal pressure P acting perpendicularly to the second cylinder B is low, and the shear strength of the cohesive soil is almost equal to its adhesive strength. The vertical bearing capacity of piles using this construction method under the worst-case conditions for shear strength is 1.9 to 2 times the total bearing capacity of piles using conventional construction methods.
これは驚異的支持力の増大であるが,支持力が多元の要
素からなり,且つこの多元の支持力を,杭の周面と,杭
の凸条Dの双方で受けるようにした本工法独特の支持力
構成上,むしろ当然の結果であって,しかもこの倍率は
最小比較倍率である。This is an amazing increase in bearing capacity, but this construction method is unique in that the bearing capacity consists of multiple elements, and this multiple bearing capacity is received by both the peripheral surface of the pile and the ridges D of the pile. This is rather a natural result given the structure of the bearing capacity, and moreover, this magnification is the minimum comparative magnification.
従って,第2円筒B領域の砂質土が密実化され,且つ砂
粒子が角ばり内部摩擦角が大きくなり,更に内圧Pを高
める手段を講ずれば,本工法における周面支持力は更に
巨大な支持力となることは明らかである。Therefore, if the sandy soil in the area B of the second cylinder becomes compact, the sand particles become angular and the internal friction angle becomes large, and if measures are taken to further increase the internal pressure P, the circumferential support force in this method will further increase. It is clear that it will have a huge supporting capacity.
以上の特長を端的に表現すれば,本工法で設置された直
径1メートルの場所打杭aは周面支持力は,最低の場合
でも,従来工法で設置された直径2メートルの場所打杭
bの周面支持力と同等となる。しかもa自体の重量は,
杭bの重量の約1/4に軽減され,総支持力から自重を
差引いた有効支持力が更に増大するとともに,地下孔の
造成諸費用,残土処理費,コンクリートの材料費その他
諸雑費が著しく低減する経済的効果が大きい。To express the above features simply, a cast-in-place pile a with a diameter of 1 meter installed using this construction method has the lowest circumferential bearing capacity than a cast-in-place pile with a diameter of 2 meters installed using the conventional construction method b. It is equivalent to the circumferential support force of . Moreover, the weight of a itself is
It is reduced to about 1/4 of the weight of pile b, and the effective bearing capacity (deducting its own weight from the total bearing capacity) is further increased, and the costs of creating underground holes, disposal of residual soil, concrete materials, and other miscellaneous costs are significantly reduced. The economic effect of reducing this is significant.
以上の分析は,本工法の特性を示す誠に注目すべき分析
であって,前述したPHC杭の施工法におけるソイルセ
メントと,原地盤との構成要件は,上記場所打杭のコン
クリート柱体と原地盤との構成要件と同一であって,圧
造溝造成不能のヘドロ状地盤を除いては,本工法で設置
されたPHC杭の周面支持力は,従来工法で設置された
PHC杭の周面支持力の2倍ないし2倍以上の大きさと
なる。従って本工法ではソイルセメントの強度を高める
ため高濃度セメントミルクを用いてソイルセメントの強
化を図ったのである。なお,PHC杭のプレボーリング
工法では,杭の沈設作業時,杭に振動力を作用させて沈
設作業を行い,凸条Dに流入したソイルセメントの密実
化を図ることが望ましい。なお,場所打杭であれ,PH
C杭であれ,鋼管杭であれ,本工法で設置された杭の支
持力は,従来工法で設置された杭の支持力をはるかに超
えるので,この強大な支持力に相応する杭の水平耐力の
増大を図らなければならないが,PHC杭の上部に軸部
外径より大径のSC杭を接続するなどの手段は,施工上
容易な方法である。また場所打杭の上方に,下端部周面
にアンカー鉄筋を溶接し,且つ中空部先端を閉じたSC
杭を場所打杭の上方に沈めると,SC杭はコンクリート
の浮力を受けて浮ぶので,土砂又はコンクリートをその
中空部に送入して平衡させると,SC杭に対する大掛か
りな位置保全装置を用いることなく,場所打杭の上方に
SC杭を容易に接続することができる。The above analysis is a truly noteworthy analysis showing the characteristics of this construction method, and the constituent requirements of the soil cement and the original ground in the PHC pile construction method described above are the same as those of the concrete column of the cast-in-place pile and the original ground. The circumferential surface bearing capacity of PHC piles installed using this method is the same as that of PHC piles installed using conventional methods, except for sludge-like ground where it is impossible to create heading grooves. It is twice or more than twice the supporting force. Therefore, in this construction method, we used high-concentration cement milk to strengthen the soil cement in order to increase its strength. In addition, in the pre-boring method for PHC piles, it is desirable to apply vibration force to the piles during the installation process to make the soil cement that has flowed into the ridges D denser. In addition, even if it is a cast-in-place pile, the PH
Whether it is C piles or steel pipe piles, the bearing capacity of piles installed using this construction method far exceeds the bearing capacity of piles installed using conventional construction methods, so the horizontal bearing capacity of piles that corresponds to this strong bearing capacity is However, an easy method for construction is to connect an SC pile with a diameter larger than the outside diameter of the shaft to the top of the PHC pile. In addition, if an anchor reinforcing bar is welded to the circumference of the lower end above the cast-in-place pile and an SC pile with the hollow tip closed is sunk above the cast-in-place pile, the SC pile will float due to the buoyancy of the concrete. When earth and sand or concrete is introduced into the hollow part and balanced, the SC pile can be easily connected above the cast-in-place pile without using a large-scale position maintenance device for the SC pile.
次に,本工法と従来工法で設置された杭の第2の相違点
は,先端支持力の差異である。従来工法では,支持層の
硬質地盤中に拡底根を造る。すなわち,先端が円錐状に
広がったベル形の拡底根である。従って支持地盤との接
地面積は広くなるが,円錐面に対する硬質地盤の周面支
持力は全く期待できない。これは従来工法では,硬質地
盤の支持層に第10図に示す平行部をもつ拡大地下孔H
。Next, the second difference between piles installed using this method and the conventional method is the difference in tip bearing capacity. In the conventional construction method, an expanded root is built in the hard ground of the supporting layer. In other words, it is a bell-shaped, expanded root with a conical tip. Therefore, although the contact area with the supporting ground becomes larger, the circumferential supporting force of the hard ground against the conical surface cannot be expected at all. In the conventional construction method, this is an enlarged underground hole H with a parallel part shown in Figure 10 in the supporting layer of hard ground.
.
を造っても,孔壁Tは掘削時ゆるみ,これを修復するて
だてがないことから,周面支持力を無視し,もっぱら先
端部の接地面積を広げることに専念したことにほかなら
ない。However, the hole wall T loosened during excavation, and there was no way to repair it, so they ignored the supporting force of the circumferential surface and focused solely on expanding the ground contact area at the tip.
一方,本工法では,先端面積をむやみに広げても,打撃
工法のごとくは支持地盤の接地面を締め固めることは不
可能で,むしろ拡大地下孔H。の平行部の周面積を広げ
,且つ拡大平行部の高さを高くして,この孔壁Tを圧造
溝の造成時特殊な手段で圧縮密実化し,この密実化した
孔壁Tに原地盤に張り出した多段の凸条Dを造り,硬質
支持地盤のもつ剪断強さτ,周面摩擦力f及び周面粘着
力Cを杭の拡大平行部の周面及び多段の凸条Dに作用さ
せるとともに,拡大接地面の圧縮抵抗力を杭の先端に作
用させる多面的先端支持力増大の手段を講じたものであ
る。On the other hand, with this construction method, even if the tip area is expanded unnecessarily, it is impossible to compact the contact surface of the supporting ground as in the percussion construction method, and rather, the underground hole H is enlarged. The circumferential area of the parallel part of the hole is expanded, and the height of the expanded parallel part is increased, and this hole wall T is compacted and solidified using a special method when forming the forging groove, and this solidified hole wall T is Create multi-stage ridges D that overhang the ground, and apply the shear strength τ, circumferential friction force f, and circumferential adhesive force C of the hard supporting ground to the circumferential surface of the enlarged parallel part of the pile and the multi-stage ridges D. At the same time, the compressive resistance force of the enlarged ground contact area is applied to the pile tip to increase the multifaceted tip bearing capacity.
ここで観点を変えて,両工法の杭の接地面横の比較につ
いて数値をまじえて説明する。Now, from a different perspective, we will explain the comparison of the lateral contact surfaces of the piles of the two construction methods, including numerical values.
(1)従来工法の先端構造を,現在の拡底根の例になら
って設計すると,
軸部直径を1.2Mと仮定すると,円錐底面の直径は
R=1.2M×1.5=1.8M
従って底面積Aは
A=0.92π≒2.54M2
(2)本鋳造法の先端部設計例
イ.軸部直径 1.2M
ロ.拡大地下孔直径 1.5M
ハ.拡大平行紡高さ 5.0M
ニ.凸条の張り出し高 0.1M
ホ.凸条ピッチ 0.5M
ヘ.凸条ピッチ数 9ピッチ
(1)上記設計条件から凸条1ピッチの接地面積は
1.6π×0.1=0.5M2
(2)全凸条の接地面積は
0.5×9=4.5M2
(3)拡大地下孔底面積は
0.752π=1.76M2
(4)総接地面積Bは
B=4.5+1.76=6.26M2
(3)接地面積の比較
本工法/従来工法=B/A=6.26/2.54=2.
46
上記の算定結果によれば,上部荷重による軸力は,本工
法では従来工法の接地面積の2.46倍の広面積に分散
して伝達される。しかも凸条Dの接地地盤は圧接溝の造
成時圧縮されている関係上耐荷能力が高い。逆に言えば
軸力に対する地盤の変形(沈下量)が微小となる。また
従来工法の接地面には,本工法の単位面積あたりの圧力
の2.46倍の圧力が作用し,且つこの接地面は組織が
ゆるんでいる関係上,特に初期沈下量が大きくなる公算
が高い。以上を勘案すると,本工法によれば従来工法の
先端支持力の少くとも2倍の耐荷能力を保有することと
なる。(1) If the tip structure of the conventional construction method is designed following the current example of an expanded root, assuming that the diameter of the shaft is 1.2M, the diameter of the conical base will be R = 1.2M x 1.5 = 1. 8M Therefore, the base area A is A=0.92π≒2.54M2 (2) Example of tip design of this casting method A. Shaft diameter 1.2M b. Expanded underground hole diameter 1.5M c. Expanded parallel spinning height 5.0M d. Projection height 0.1M E. Convex pitch 0.5M f. Number of ridge pitches: 9 pitches (1) From the above design conditions, the ground contact area of 1 pitch of ridges is 1.6π x 0.1 = 0.5M2 (2) The ground contact area of all ridges is 0.5 x 9 = 4. 5M2 (3) The bottom area of the expanded underground hole is 0.752π = 1.76M2 (4) The total ground contact area B is B = 4.5 + 1.76 = 6.26M2 (3) Comparison of ground contact area This method / conventional method = B /A=6.26/2.54=2.
46 According to the above calculation results, in this construction method, the axial force due to the upper load is distributed over a wide area that is 2.46 times the ground contact area of the conventional construction method. Moreover, the ground of the protrusion D has a high load-bearing capacity because it is compressed when the pressure groove is created. In other words, the deformation (amount of subsidence) of the ground due to the axial force is small. In addition, the pressure per unit area of the conventional construction method is 2.46 times the pressure per unit area of the present construction method, and the structure of this contact surface is loose, so the amount of initial settlement is likely to be particularly large. expensive. Taking the above into consideration, this construction method has a load-bearing capacity that is at least twice the tip support capacity of the conventional construction method.
なお,軸力の影響の特徴として,支持層に至るまでの周
面に作用する地盤の支持力が大きいほど,杭先端に作用
する軸力は減少する。Furthermore, a characteristic of the influence of axial force is that the greater the bearing capacity of the ground acting on the circumferential surface up to the support layer, the less the axial force acting on the pile tip.
従って,周面支持力の大きい本工法による杭では,先端
支持力の軸力負担量は,従来工法の杭の先端支持力の負
担量より大幅に軽減することとなり,中間層に硬質地盤
をもつ施工地では,本工法では拡大根の造成を省略して
も,支持能力には大きな差異はないものと期待される。Therefore, for piles manufactured by this method that have a large circumferential bearing capacity, the axial load burden of the tip bearing capacity is significantly reduced compared to the burden of the tip bearing capacity of piles of the conventional method. At the construction site, even if the creation of expanded roots is omitted with this construction method, it is expected that there will be no major difference in the bearing capacity.
従って,必ず拡大根の造成を要する場合とは,既成杭の
場合に説明したとおり下記の施工時である。Therefore, as explained in the case of prefabricated piles, the cases where it is absolutely necessary to create expanded roots are during the following construction.
(1)軟弱層が支持層まで続く施工地
(2)地盤沈下が予測させる施工地
(3)土砂の液状化が予測される施工地以上の施工時に
は,実施例3に示した拡大根造成の手段を用いる。(1) Construction sites where the soft layer continues up to the supporting layer (2) Construction sites where ground subsidence is expected (3) Construction sites where soil liquefaction is expected or higher use means.
以上に本工法を,実施例1,2及び3に従って説明した
が,各実施例で用いた装置及び操作手段は,他の実施例
に応用して実施し得る。また各実施例で用いた圧造溝は
,リーマを回転させると同時にリーマを上下の方向に移
行させるので,圧造溝は,連続するラセン状圧造溝とな
り,この溝に造成される凸条Dも連続するラセン状凸条
となるが,リーマの軸方向の移行を一定時間停止させて
リーマを回転させると,孔壁Tには1条の環状溝が造成
される。次にリーマの回転を停止してリーマを一定の寸
法だけ軸方向に移動させたのち,リーマを回転させる。Although the present construction method has been described above according to Examples 1, 2, and 3, the apparatus and operating means used in each example can be applied to other examples. In addition, the forging groove used in each example moves the reamer in the vertical direction at the same time as the reamer is rotated, so the forging groove becomes a continuous helical forging groove, and the protrusion D formed in this groove is also continuous. However, if the axial movement of the reamer is stopped for a certain period of time and the reamer is rotated, a single annular groove is created in the hole wall T. Next, the rotation of the reamer is stopped, the reamer is moved in the axial direction by a certain distance, and then the reamer is rotated.
以上の操作を繰返すと,孔壁Tには一定間隔をおいて多
段の環状溝が造成される。このときはリーマの刃先13
を四角錐にして左右及び上下の方向に土砂を押し分けて
進行し得る形状とする。本工法では,上記した多段の溝
,及び前記ラセン状通の双方を用い得る。By repeating the above operations, multi-stage annular grooves are created in the hole wall T at regular intervals. At this time, the cutting edge of the reamer is 13.
is shaped like a square pyramid so that it can move forward by pushing the earth and sand in the left and right and up and down directions. In this construction method, both the above-mentioned multi-stage groove and the above-mentioned spiral passage can be used.
なお,まえに詳細に分析したとおり,本工法で設置した
杭は,その周面支持力及び先端支持力が,従来工法によ
る杭より格別に大きく,小径の杭によって,よく従来の
大径の杭を代行して上部構造物を支持し得る。従って,
本工法で設置する杭のコンクリート量は,場所打杭の場
合,最大でも従来工法による杭のコンクリート使用量の
約1/3を見込めば設計上充分である。反面,使用する
コンクリートは精選されたコンクリートを用いなければ
ならない。このコンクリートは,必ず圧造溝に流入すべ
き必要条件から,骨材の最大寸法を,20mm以内に制
限するとともに,現在のコンクリートの配合技術の最高
レベルの配合によってなる高強度コンクリートを使用す
ることとする。また高強度コンクリートに替えて高強度
モルタルを使用することも有効な手段である。更に凸条
Dの形状寸法,及び凸条のピッチ,間隔など,実施例で
示した形状,寸法,ピッチなどに局限されることなく,
設計の改変を自由に行い得るものである。As previously analyzed in detail, the circumferential bearing capacity and tip bearing capacity of the piles installed using this method are significantly greater than those of conventional piles, and small-diameter piles often outperform conventional large-diameter piles. can support the superstructure on behalf of the superstructure. Therefore,
In the case of cast-in-place piles, the amount of concrete required for the piles installed using this construction method should be at most about 1/3 of the amount of concrete used for piles using the conventional construction method, which is sufficient for design purposes. On the other hand, the concrete used must be carefully selected. Due to the requirement that this concrete must flow into the heading groove, the maximum size of the aggregate must be limited to 20 mm or less, and high-strength concrete made with the highest level of current concrete mixing technology must be used. do. Another effective method is to use high-strength mortar instead of high-strength concrete. Furthermore, the shape and dimensions of the protrusions D and the pitch and interval of the protrusions are not limited to the shapes, dimensions, pitches, etc. shown in the examples.
The design can be freely modified.
図面は本発明の実施例を示すもので,第1図はプレボー
リング工法における掘進装置の先端部を示す地中の態様
図,第2図は反り面ビットの斜面図,第3図は反り面ビ
ットに取付けたリーマ付近の断面図,第4図は地中に造
成されたセメント製柱体の模形断面図,第5図はリーマ
の先端部の斜面図,第6図はプレボーリングした地下孔
に沈設するフシ杭の構造図,第7図はリーマを取付けた
閉鎖板の下面図,第8図は支持層における杭と,掘進装
置の先行作動を示す地中の態様図,第9図は支持層にお
ける杭と,リーマの作動状態を示す掘進装置の態様図,
第10図は場所打杭の先端に拡大地下孔を造成するとき
の拡大掘削装置の構造略図,第11図はトレミー管に取
付けた大形リーマの開閉機構図である。
図面中,符号H…地下孔,H。…拡大地下孔,T…孔壁
,K…掘削装置,g…孔壁に圧造した溝,D…原地盤に
張りだした凸条,a…フシ杭,1…回転軸,1。…サク
ション軸,3…反り面ビット,5…掘削チップ,6…光
端ビット,7…撹拌翼,8…孔壁を押圧する丸棒,9…
射出孔,10…軸受金具,11…軸,12…リーマ,1
3…リーマの刃先,14…刃先の三角錐面,17…PH
C杭のフシ,18…補強バンド,19…定着板,20…
スペーサ,21…閉鎖板,25…掘削ビット,28…開
閉自在な撹拌翼,33…孔壁を抑える押圧鋼板,38及
び39…拡大翼,40…ピン受金具,41…ピン,42
…孔壁を切る斜辺ビット,43…トレミー管,44…孔
壁を抑える壁面ガード,45…係止金具。The drawings show an embodiment of the present invention. Fig. 1 is an underground view showing the tip of the excavation device in the pre-boring method, Fig. 2 is a slope view of the warped bit, and Fig. 3 is a diagram showing the tip of the digging device in the pre-boring method. Figure 4 is a cross-sectional view of the vicinity of the reamer attached to the bit, Figure 4 is a cross-sectional view of a model of a cement column built underground, Figure 5 is a slope view of the tip of the reamer, and Figure 6 is a pre-bored underground view. Figure 7 is a bottom view of the closing plate with a reamer attached, Figure 8 is a diagram of the underground structure showing the pile in the supporting layer and the advance operation of the excavation device, Figure 9 is a diagram of the excavation equipment showing the operating status of the pile and reamer in the supporting layer;
Fig. 10 is a schematic diagram of the structure of an enlarged excavation device for creating an enlarged underground hole at the tip of a cast-in-place pile, and Fig. 11 is a diagram of the opening/closing mechanism of a large reamer attached to a tremie pipe. In the drawing, code H...underground hole, H. ...Enlarged underground hole, T...hole wall, K...drilling equipment, g...groove pressed into the hole wall, D...projection extending over the original ground, a...stick pile, 1...rotating shaft, 1. ... Suction shaft, 3... Warped surface bit, 5... Drilling tip, 6... Light end bit, 7... Stirring blade, 8... Round bar that presses the hole wall, 9...
Injection hole, 10...Bearing fitting, 11...Shaft, 12...Reamer, 1
3... Reamer cutting edge, 14... Triangular pyramidal surface of cutting edge, 17... PH
C pile frame, 18... Reinforcement band, 19... Fixing plate, 20...
Spacer, 21... Closing plate, 25... Drilling bit, 28... Stirring blade that can be opened and closed, 33... Pressed steel plate that suppresses the hole wall, 38 and 39... Expanding blade, 40... Pin holder, 41... Pin, 42
...Hytenuse bit for cutting the hole wall, 43...Tremy tube, 44...Wall guard for suppressing the hole wall, 45...Locking metal fitting.
Claims (1)
マを、地下孔内の遅硬性流動物のなかで回転させるとと
もに、この遅硬性流動物のなかで回転体の軸方向運動を
断続して行うか、又は連続して行い、地下孔の孔壁に、
回転軸に連動する前記リーマで所要の溝を刻み、この溝
に前記遅硬性流動物を自動流入させ、この遅硬性流動物
の硬化後、孔壁の原地盤内に張り出した所要の凸条を外
面に突設した硬化柱体を地下孔内に造成することを特徴
とする基礎杭の定着鋳造法。[Scope of Claims] A reamer of a rotary body, which has a reamer for creating a groove in the hole wall attached to a reamer base connected to the tip of the rotary body, is rotated in a slow-hardening fluid in an underground hole. At the same time, the axial movement of the rotating body is performed intermittently or continuously in this slow-hardening fluid, and the hole wall of the underground hole is
The reamer, which is linked to the rotating shaft, cuts a required groove, and the slow-hardening fluid is automatically flowed into the groove, and after the slow-hardening fluid has hardened, the required protruding stripes are formed in the original ground of the hole wall. A fixed casting method for foundation piles, which is characterized by creating hardened columns protruding from the outside in underground holes.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP25422988A JPH01244015A (en) | 1988-10-07 | 1988-10-07 | Anchor casting for foundation pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP25422988A JPH01244015A (en) | 1988-10-07 | 1988-10-07 | Anchor casting for foundation pile |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP6845988A Division JPH01244016A (en) | 1988-03-22 | 1988-03-22 | Reflux spiral foundation work |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH01244015A true JPH01244015A (en) | 1989-09-28 |
Family
ID=17262057
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP25422988A Pending JPH01244015A (en) | 1988-10-07 | 1988-10-07 | Anchor casting for foundation pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH01244015A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2016535187A (en) * | 2013-10-27 | 2016-11-10 | ペン・グイジャオ | Pile formation method for composite expanded pile and pile forming equipment for combined expanded pile |
| US10024020B2 (en) * | 2016-12-05 | 2018-07-17 | Andrew Corbin Fuller | Apparatus for constructing foundation pilings |
| US11851839B1 (en) | 2021-12-06 | 2023-12-26 | Andrew Corbin Fuller | Cased piles |
-
1988
- 1988-10-07 JP JP25422988A patent/JPH01244015A/en active Pending
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2016535187A (en) * | 2013-10-27 | 2016-11-10 | ペン・グイジャオ | Pile formation method for composite expanded pile and pile forming equipment for combined expanded pile |
| US10024020B2 (en) * | 2016-12-05 | 2018-07-17 | Andrew Corbin Fuller | Apparatus for constructing foundation pilings |
| US11851839B1 (en) | 2021-12-06 | 2023-12-26 | Andrew Corbin Fuller | Cased piles |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7112012B2 (en) | Piling apparatus and method of installation | |
| US5219246A (en) | Drills for piles and soil stabilization, and drilling method | |
| US7494299B1 (en) | Piling apparatus having rotary drive | |
| JP5265500B2 (en) | Pile digging method, foundation pile structure | |
| US3962879A (en) | Reinforced pile in earth situs and method of producing same | |
| US20070224001A1 (en) | Novel surface structures and methods thereof | |
| JPH01244015A (en) | Anchor casting for foundation pile | |
| JPH02289718A (en) | Drilling method of expanded head pile hole, constructing method of expanded head pile and pile hole drill | |
| JP4074198B2 (en) | How to remove existing piles | |
| JP2000008372A (en) | Underground wall construction method | |
| US11788249B2 (en) | Cutting tool adapter and method of underpinning structures using cutting tool adapter for soil mixing | |
| JP4645091B2 (en) | Expanded pile and construction method of the expanded pile | |
| JP4197074B2 (en) | Embedded pile construction equipment | |
| JP4566634B2 (en) | Ground improvement method | |
| JPH07197469A (en) | Structure of earth retaining wall and earth retaining method | |
| JP6336259B2 (en) | Steel pipe with blade for construction of cast-in-place concrete piles with knots | |
| JPS6221089B2 (en) | ||
| JPH06220841A (en) | Construction method of continuous underground wall using steel pipe pile | |
| JPH0442493B2 (en) | ||
| JPS6251332B2 (en) | ||
| JPS60123620A (en) | Method of sinking steel pipe concrete composite pile | |
| CA2544121A1 (en) | Piling apparatus and method of installation | |
| JPH076190B2 (en) | Pile construction method | |
| JPS62202118A (en) | Burying work of pile | |
| JPS6262209B2 (en) |