JPH0114400B2 - - Google Patents
Info
- Publication number
- JPH0114400B2 JPH0114400B2 JP56028580A JP2858081A JPH0114400B2 JP H0114400 B2 JPH0114400 B2 JP H0114400B2 JP 56028580 A JP56028580 A JP 56028580A JP 2858081 A JP2858081 A JP 2858081A JP H0114400 B2 JPH0114400 B2 JP H0114400B2
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pipe sheet
- ground
- tunnel
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【発明の詳細な説明】
この発明は、既存の鉄道、道路等の構造物下の
地盤内に、上部構造物の使用に何等支障をもたら
すことなく、長スパンにわたつてトンネルを構築
しうる水平鋼管矢板支保工を用いるトンネルの構
築方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention provides a horizontal tunnel that can be constructed over a long span in the ground under existing structures such as railways and roads without causing any hindrance to the use of superstructures. This relates to a method of constructing a tunnel using steel pipe sheet pile shoring.
従来、水平鋼管矢板支保工を使用して既存の構
造物下の地盤を掘削して、その掘削坑内にコンク
リートボツクスを場所打ちしてトンネルを構築す
るパイプビーム工法があるが、中間に支保工を設
けないので掘削構築可能なトンネルのスパン長は
高々20m程度までである。また、同様地盤へのト
ンネル構築法として地盤改良を施し、地盤内にパ
イプルーフによる防護工を施した後、発進基地に
設けたプレキヤストのコンクリートボツクス躯体
を、到着基地に設けたフロンテジヤツキにより
PC鋼材を介して引き込み、躯体内部に入つてく
る土砂を掘削してトンネルを構築するフロンテジ
ヤツキング工法があるが、発進基地に広い作業面
積を必要とし、躯体のブロツク先端地盤を掘削し
ながら引き入れるため、周辺地盤の改良を広範囲
に行なう必要があり、さらに重量の大きい躯体ブ
ロツクを地盤中で牽引するため経険と高度の技術
が要求される。 Conventionally, there is a pipe beam construction method in which a tunnel is constructed by excavating the ground under an existing structure using horizontal steel pipe sheet pile shoring, and then pouring concrete boxes into place in the excavated hole. Since there are no tunnels installed, the span length of tunnels that can be constructed by excavation is approximately 20 meters at most. In addition, as a similar method for constructing tunnels in the ground, after improving the ground and providing protection with a pipe roof in the ground, the precast concrete box frame installed at the departure base was installed using a frontage jack installed at the arrival base.
There is a frontage construction method in which a tunnel is constructed by drawing soil through prestressing steel and excavating the soil that enters the structure, but this method requires a large work area at the starting base, and while excavating the ground at the tip of the structure block, In order to pull it in, it is necessary to extensively improve the surrounding ground, and furthermore, towing the heavy frame block through the ground requires cost and advanced technology.
この発明は前記事情に鑑み開発されたもので、
トンネルスパン長を大幅に増加させ、かつ施工を
容易ならしめたものである。以下、その詳細を図
示した実施例によつて説明する。 This invention was developed in view of the above circumstances,
This greatly increased the tunnel span length and made construction easier. The details will be explained below with reference to illustrated embodiments.
実施例は軌道Aの路盤にトンネルを施工する場
合を示したもので、先ず掘削区間の両端に架台フ
レーム1を支柱と梁とによつて構築する(第1
図、第5図)。次いで、その架台フレーム1に沿
つて鋼管矢板2を、その継手部3で相互に連結し
ながら地盤中に押込み、前記両端架台フレーム1
間に架渡す(第2図、第6図)。なお、押込みに
際しては鋼管矢板2内にオーガーを挿入して掘削
を併用することができる。また、地盤が軟弱な場
合には底部にも鋼管矢板2を押し込み四周を囲む
ようにする。また、必要により地盤硬化剤を掘削
区間およびその周辺に注入する。 The example shows a case where a tunnel is constructed on the roadbed of track A. First, a trestle frame 1 is constructed using supports and beams at both ends of the excavated section (the first
(Fig. 5). Next, the steel pipe sheet piles 2 are pushed into the ground along the trestle frame 1 while being connected to each other at the joints 3, and the trestle frames 1 at both ends are pushed into the ground.
(Fig. 2, Fig. 6). In addition, when pushing, an auger can be inserted into the steel pipe sheet pile 2 and excavation can also be used. In addition, if the ground is soft, the steel pipe sheet piles 2 are also pushed into the bottom so as to surround the four peripheries. Also, if necessary, soil hardening agent will be injected into the excavated section and its surroundings.
押し込んだ鋼管矢板2の継手部3内にモルタル
を充填し、また鋼管矢板2と架台フレーム1との
間隙にも支点部固定のためのコンクリート4を充
填し(第7図、第8図)、さらに中間支点等で鋼
管矢板2が局部座屈を生ずる恐れのある場合は、
その鋼管内にコンクリートを充填する。 Fill the joint 3 of the pushed steel pipe sheet pile 2 with mortar, and also fill the gap between the steel pipe sheet pile 2 and the pedestal frame 1 with concrete 4 for fixing the fulcrum part (Figures 7 and 8). Furthermore, if there is a risk that the steel pipe sheet pile 2 may locally buckle at an intermediate fulcrum, etc.
Fill the steel pipe with concrete.
次いで、掘削全スパンを数区間に分け、片方あ
るいは両側から鋼管矢板2で囲まれる地盤を掘削
する。このとき、鋼管矢板2は一方を架台フレー
ム、他方は未掘削地盤8で支承する(第3図)。
未掘削地盤8の耐力を補足するため掘削された所
要区間ごとに仮設支柱5を順次設置しておくもの
とする。つぎに、掘削坑内において現場打ちコン
クリートによつて、トンネル覆工となるコンクリ
ートボツクス6を製作する。そして、コンクリー
トボツクス6と鋼管矢板2との間隙には無収縮性
モルタルまたは発泡モルタル7を充填する(第4
図)続いて完成したコンクリートボツクス6を一
方の支点、未掘削地盤を他方の支点とし、その中
間は仮設支柱5を支点として鋼管矢板2を支承し
ながら順次掘削を行ない、同様の手順施工を繰返
して全区間のトンネルを完成する。 Next, the entire excavation span is divided into several sections, and the ground surrounded by the steel pipe sheet piles 2 from one or both sides is excavated. At this time, the steel pipe sheet pile 2 is supported on one side by the frame frame and on the other side by the unexcavated ground 8 (FIG. 3).
In order to supplement the bearing capacity of the unexcavated ground 8, temporary supports 5 are sequentially installed in each required excavated section. Next, a concrete box 6, which will serve as the tunnel lining, is manufactured using on-site concrete in the excavation pit. Then, the gap between the concrete box 6 and the steel pipe sheet pile 2 is filled with non-shrinkable mortar or foam mortar 7 (fourth
Figure) Next, using the completed concrete box 6 as one fulcrum and the unexcavated ground as the other fulcrum, excavation is carried out in sequence while supporting the steel pipe sheet pile 2 with the temporary support 5 as the fulcrum in the middle, and the same procedure is repeated. The entire tunnel section will be completed.
この発明は以上の構成からなり、掘削に先立つ
て両端の架台フレーム間に、継手部で連結された
鋼管矢板を架渡し、坑道の掘作に伴つてその鋼管
矢板の一方を未掘削地盤および仮設支柱を用いて
支承し、他方を現場施工による硬化したコンクリ
ートボツクスによつて支承しながら順次コンクリ
ートを打設していくから上部構造の使用に支障な
く、100m程度までのトンネルを迅速かつ容易に
構築できる。 This invention has the above-mentioned configuration. Prior to excavation, steel pipe sheet piles connected at joints are installed between the frame frames at both ends, and as the tunnel is excavated, one of the steel pipe sheet piles is placed in the unexcavated ground and temporarily installed. The tunnel is supported by pillars, and the other is supported by hardened concrete boxes constructed on site, and concrete is poured in sequence, so there is no problem in using the superstructure, and tunnels up to about 100 meters can be constructed quickly and easily. can.
第1図、第2図、第3図、第4図は施工順序に
示した縦断面図、第5図、第第6図は第1図、第
2図の側面図、第7図、第8図は要部の断面図で
ある。
A……軌道。1……架台フレーム、2……鋼管
矢板、3……継手部、4……コンクリート、5…
…仮設支柱、6……コンクリートボツクス、7…
…モルタル、8……未掘削地盤。
Figures 1, 2, 3, and 4 are longitudinal sectional views shown in the construction order; Figures 5 and 6 are side views of Figures 1 and 2; Figure 8 is a sectional view of the main part. A... Orbit. 1... Frame, 2... Steel pipe sheet pile, 3... Joint part, 4... Concrete, 5...
...Temporary support, 6...Concrete box, 7...
...Mortar, 8...Unexcavated ground.
Claims (1)
の架台に沿つて鋼管矢板を、その継手部で相互に
連結しながら地盤中に押込み、前記両架台間に架
渡し、次いで前記鋼管矢板で囲まれる地盤を部分
区間掘削するとともに、所要間隔ごとに順次仮設
支柱を設置し、その掘削坑内に現場打ちコンクリ
ートによつてトンネル覆工となるコンクリートボ
ツクスを製作して前記架台フレーム間に順次現場
打ちコンクリートによつてコンクリートボツクス
を製作し、トンネルを構築することを特徴とする
水平鋼管矢板支保工を用いるトンネルの構築方
法。1. Construct a trestle frame at both ends of the excavation section, push the steel pipe sheet piles into the ground along the trestles while interconnecting them at their joints, bridge them between the two trestles, and then surround them with the steel pipe sheet piles. Partial sections of the ground are excavated, temporary supports are sequentially installed at required intervals, a concrete box is made to serve as the tunnel lining with cast-in-place concrete inside the excavation, and cast-in-place concrete is sequentially placed between the pedestal frames. A method for constructing a tunnel using horizontal steel pipe sheet pile shoring, which is characterized by manufacturing a concrete box and constructing a tunnel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2858081A JPS57143091A (en) | 1981-02-28 | 1981-02-28 | Construction of tunnel using horizontal steel pipe sheet pipe support |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2858081A JPS57143091A (en) | 1981-02-28 | 1981-02-28 | Construction of tunnel using horizontal steel pipe sheet pipe support |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS57143091A JPS57143091A (en) | 1982-09-04 |
| JPH0114400B2 true JPH0114400B2 (en) | 1989-03-10 |
Family
ID=12252531
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2858081A Granted JPS57143091A (en) | 1981-02-28 | 1981-02-28 | Construction of tunnel using horizontal steel pipe sheet pipe support |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS57143091A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6016698A (en) * | 1983-07-05 | 1985-01-28 | 日本国有鉄道 | Pipe parallelly arranging method |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5264132A (en) * | 1975-11-21 | 1977-05-27 | Sakaguchi Manabu | Method of tunnel excavation |
-
1981
- 1981-02-28 JP JP2858081A patent/JPS57143091A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS57143091A (en) | 1982-09-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110499779B (en) | Construction method of air duct structure sharing side wall with subway station | |
| JP4317322B2 (en) | Arch support structure | |
| KR100510092B1 (en) | A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it | |
| JPH0114400B2 (en) | ||
| JPS584094A (en) | Method of constructing low road cross | |
| JP3146333B2 (en) | Tunnel construction method | |
| JP2536376B2 (en) | Foundation structure of shed for road protection | |
| JPH03199528A (en) | Steel frame foundation of construction | |
| JPH0584773B2 (en) | ||
| JP5073960B2 (en) | Construction method of underground structure and underground structure | |
| JP3406370B2 (en) | Horizontal shaft construction method | |
| JP2587029B2 (en) | Viaduct construction method | |
| JPS6361475B2 (en) | ||
| JPS6286242A (en) | Reverse construction method | |
| JPH0238627A (en) | Rebuilding of existing building | |
| JP4399062B2 (en) | Construction method of viaduct underground beam | |
| JP3380302B2 (en) | Viaduct construction method | |
| JP2572680B2 (en) | Underground structure by reverse strike method | |
| JPH04238919A (en) | Construction of underground beam | |
| JPH02266016A (en) | Structural process of underground concrete body of building | |
| JPH0466965B2 (en) | ||
| JPH06220872A (en) | Underground beam construction method | |
| JPS61211497A (en) | Support construction method of existing underground structure | |
| JPS6178927A (en) | Construction of retaining wall | |
| JPH0776508B2 (en) | Existing tunnel protection method |