[go: up one dir, main page]

JPH0692719B2 - Lining construction method - Google Patents

Lining construction method

Info

Publication number
JPH0692719B2
JPH0692719B2 JP63287277A JP28727788A JPH0692719B2 JP H0692719 B2 JPH0692719 B2 JP H0692719B2 JP 63287277 A JP63287277 A JP 63287277A JP 28727788 A JP28727788 A JP 28727788A JP H0692719 B2 JPH0692719 B2 JP H0692719B2
Authority
JP
Japan
Prior art keywords
outer shell
lining
press ring
concrete
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63287277A
Other languages
Japanese (ja)
Other versions
JPH02132297A (en
Inventor
喜久雄 石田
敏夫 古田
光 竹内
Original Assignee
三井建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三井建設株式会社 filed Critical 三井建設株式会社
Priority to JP63287277A priority Critical patent/JPH0692719B2/en
Publication of JPH02132297A publication Critical patent/JPH02132297A/en
Publication of JPH0692719B2 publication Critical patent/JPH0692719B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 (a).産業上の利用分野 本発明は、プレスリングを用いたシールドによるトンネ
ルの掘削に際して、施工サイクルの短縮化が出来る覆工
構築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (a). BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a lining construction method capable of shortening a construction cycle when excavating a tunnel with a shield using a press ring.

(b).従来の技術 第13図は従来のシールド工法におけるコンクリート打設
の方法を示す図である。
(B). Prior Art FIG. 13 is a diagram showing a concrete placing method in a conventional shield construction method.

従来、現場打ちコンクリートを用いてシールド掘削機等
のシールドにより掘削したトンネルに覆工を構築する際
には、例えば特開昭62−0194399に開示されているよう
に、型枠13の1リング分のトンネル覆工20を構築した
後、次の1リング分のトンネル覆工20を構築するとき
に、第13図に示すように、掘進用ジャッキ6のラム6aを
ゲージリング11と共に矢印A方向に型枠13の1リング分
の長さだけ後退させ、型枠13Aとゲージリング11との間
に形成された空間31に補強部材12及び型枠13Bを組立て
設置する。次に、該空間31に、型枠13Bに接続されたコ
ンクリート供給管25からコンクリート21Aを打設した
後、プレスリング7を矢印A方向に移動させつつ、供給
ホース30からプレスリング7の吐出管10を介してコンク
リート21Cを打設することにより、コンクリート21A及び
コンクリート21Cからなるトンネル覆工20を構築してい
く。
Conventionally, when constructing a lining in a tunnel excavated by a shield such as a shield excavator using cast-in-place concrete, for example, as disclosed in JP-A-62-0194399, one ring of the formwork 13 is used. After constructing the tunnel lining 20 of the above, when constructing the tunnel lining 20 for the next one ring, as shown in FIG. 13, the ram 6a of the jack 6 for excavation is moved in the direction of the arrow A along with the gauge ring 11. The mold frame 13 is retracted by the length of one ring, and the reinforcing member 12 and the mold frame 13B are assembled and installed in the space 31 formed between the mold frame 13A and the gauge ring 11. Next, in the space 31, after concrete 21A is placed from the concrete supply pipe 25 connected to the formwork 13B, the press ring 7 is moved in the direction of arrow A, and the supply hose 30 discharges the press ring 7 from the discharge pipe. By placing concrete 21C through 10, a tunnel lining 20 made of concrete 21A and concrete 21C will be constructed.

(c).発明が解決しようとする問題点 しかし、この構築方法においては、ゲージリング11が型
枠13Aを離れてから空間31に補強部材12及び型枠13Bが組
立て設置され、更にコンクリートが該部分に打設される
までの間は、直前に打設された型枠13A部分のコンクリ
ート21Bに対するゲージリング11の押圧状態が解除され
る。すると、打設されたコンクリートの流動を阻止する
手段が何ら存在しなくなるので、コンクリートが未硬化
の状態では、地山19からの土圧、水圧などにより、当該
コンクリートが外部に噴出してしまう危険性が有り、そ
うした危険性を回避するために、該打設されたコンクリ
ート21Bを地山19からの土圧、水圧等の圧力に耐え得る
程度迄に硬化養生させた後に、ゲージリング11を型枠13
Aから離す必要がある。この養生時間は、特に大深度施
工等の高土圧、高水圧下での施工において必然的に長く
なり、従ってトンネル覆工20構築する際のシールド掘削
機のサイクルタイムが打設コンクリート21Bの硬化養生
時間に相当する分だけ長くなり、結果的に工期の長期化
が生じる危険性がある。
(C). Problems to be Solved by the Invention However, in this construction method, after the gauge ring 11 leaves the mold 13A, the reinforcing member 12 and the mold 13B are assembled and installed in the space 31, and further concrete is poured into the part. Until that time, the pressed state of the gauge ring 11 against the concrete 21B at the part of the formwork 13A placed immediately before is released. Then, there is no means to prevent the flow of the poured concrete, so if the concrete is in an unhardened state, there is a risk that the concrete will spout to the outside due to earth pressure or water pressure from the natural ground 19. In order to avoid such danger, the cast concrete 21B is cured and cured to an extent that it can withstand the pressure such as earth pressure and water pressure from the ground 19, and then the gauge ring 11 is molded. Frame 13
Must be separated from A. This curing time is inevitably long especially in construction under high soil pressure and high water pressure, such as when working at large depths, so the cycle time of the shield excavator when constructing the tunnel lining 20 hardens the concrete 21B that is poured. There is a risk that it will be lengthened by the amount corresponding to the curing time, resulting in a longer construction period.

また、型枠として、捨て型枠を使用し、該捨て型枠に妻
板を一体化した形で設け、該妻板により、ゲージリング
が型枠から離れた際に、打設されたコンクリートが崩壊
することを防止する方法も知られているが、型枠として
妻板が予め設けられた特殊な捨て型枠を使用しなければ
ならず、汎用性に欠ける不都合がある。また、ゲージリ
ングが妻板から離れる際には、ゲージリングからの押圧
力が消失するので、打設されたコンクリートが流動状態
では、地山からの土圧、水圧などでコンクリートがトン
ネル内部に噴出してしまうので、こうした方法を用いて
も、打設されたコンクリートがある程度凝固するまで、
コンクリートを養生する時間が必要であり、上記した問
題を根本的に解決することは出来なかった。
In addition, a discard form is used as the form, and the end plate is integrated with the end form. When the gauge ring is separated from the form by the end plate, the cast concrete collapses. Although a method of preventing this is also known, a special discarding formwork having a gable plate provided in advance must be used as the formwork, which is inconvenient in general versatility. In addition, when the gauge ring separates from the end plate, the pressing force from the gauge ring disappears, so when the placed concrete is in a fluid state, the concrete spouts inside the tunnel due to earth pressure and water pressure from the natural ground. Even if you use this method, until the cast concrete solidifies to some extent,
It took time to cure the concrete, and the above problems could not be solved fundamentally.

本発明は、上記の問題点を解消すべく、トンネル覆工の
構築に要するサイクルタイムを短縮することが出来る覆
工構築方法を提供することを目的とする。
An object of the present invention is to provide a lining construction method capable of shortening the cycle time required to construct a tunnel lining in order to solve the above problems.

(d).問題点を解決するための手段 即ち、本発明は、外殻(2)を有し、該外殻(2)の内
側にプレスリング(7)を前記外殻の掘進方向に移動駆
動自在に設け、該プレスリングの内側に型枠支持部材
(11)を前記外殻に対して移動駆動自在に設け、前記プ
レスリングの内周面に対型枠シール部材(5)を全周に
わたり設け、該型枠支持部材と前記外殻の間に掘進用ジ
ャッキ(6)を設けたシールドを用いて覆工(20)を構
築する際は、プレスリング(7)を外殻後方に突出させ
た状態で、型枠支持部材を外殻前方に移動させ、該型枠
支持部材と既に覆工構築部材(21)の打設が完了した型
枠(13A)との間に型枠(13B)を設置し、次いで、プレ
スリングを、該プレスリングが前記型枠(13A,13B)の
コンクリート接触面と前記対型枠シール部材(5)を介
して常時当接する形で外殻前方に移動させつつ、該プレ
スリングの移動に伴なって生じる覆工構築部材打設空間
(26)中に覆工構築部材を注入充填し、その後、シール
ド(1)による掘進を開始して、掘進用ジャッキ(6)
により外殻の前方への移動を開始すると共に、プレスリ
ングを、該プレスリングが前記型枠のコンクリート接触
面と前記対型枠シール部材を介して常時当接する形で後
方に突出させて、前記直前に充填された覆工構築部材を
加圧することにより、前記外殻の移動に伴なって生じる
テールボイド(27)中に該覆工構築部材を充填させて1
次覆工(35)を形成し、その後、前記1次覆工の覆工構
築部材の硬化した部分の型枠(13)を脱型して、該1次
覆工の内側に2次覆工(29)を構築するようにして構成
される。
(D). Means for Solving the Problems That is, according to the present invention, an outer shell (2) is provided, and a press ring (7) is provided inside the outer shell (2) so as to be movable in the excavation direction of the outer shell. A mold support member (11) is provided inside the press ring so as to be movable with respect to the outer shell, and a pair of mold seal members (5) is provided on the inner peripheral surface of the press ring over the entire circumference, When constructing a lining (20) using a shield having a jack (6) for excavation between the formwork support member and the outer shell, the press ring (7) is projected to the rear of the outer shell. , Move the formwork support member forward of the outer shell, and install the formwork (13B) between the formwork support member and the formwork (13A) on which the lining construction member (21) has already been placed. Then, a press ring is attached to the concrete contact surface of the formwork (13A, 13B) and the paired formwork seal member (5). Then, the lining construction member is injected and filled into the lining construction member placing space (26) generated by the movement of the press ring while being moved in such a manner that it is always in contact with the outer shell, and then the shield ( Start the excavation by 1), and jack for excavation (6)
The forward movement of the outer shell is started by the press ring, and the press ring is caused to project rearward in such a manner that the press ring is always in contact with the concrete contact surface of the mold via the anti-mold frame seal member, By pressurizing the lining construction member that has just been filled, the lining construction member is filled in the tail void (27) that accompanies the movement of the outer shell.
A secondary lining (35) is formed, and then the mold (13) of the hardened portion of the lining construction member of the primary lining is demolded, and a secondary lining is provided inside the primary lining. (29) is constructed to build.

なお、括弧内の番号等は、図面における対応する要素を
示す便宜的なものであり、従って、本記述は図面上の記
載に限定拘束されるものではない。以下の「(e).作
用」の欄についても同様である。
The numbers in parentheses are for convenience of showing the corresponding elements in the drawings, and therefore the present description is not limited to the description in the drawings. The same applies to the section "(e). Action" below.

(e).作用 上記した構成により、本発明は、地山(19)と型枠(1
3)の間に打設された覆工構築部材(21)は、プレスリ
ングと型枠(13A、13B)のコンクリート接触面が対型枠
シール部材(5)により常に閉塞された状態でプレスリ
ング(7)により常時加圧支持されるように作用する。
(E). Action With the above-mentioned configuration, the present invention provides the ground (19) and the form (1
The lining construction member (21) cast between 3) is the press ring with the concrete contact surfaces of the press ring and the molds (13A, 13B) being always closed by the paired mold seal member (5). By (7), it works so as to be constantly supported under pressure.

(f).実施例 以下、本発明の実施例を図面に基づき説明する。(F). Embodiment An embodiment of the present invention will be described below with reference to the drawings.

第1図は本発明による覆工構築方法が適用されるシール
ド掘削機等の一例を示す正断面図、 第2図は第1図のII−II線による断面図、 第3図は第1図のIII−III線による断面図、 第4図は第1図に示すシールド掘削機のジャッキ部分の
拡大図、 第5図は第4図のV−V線による断面図、 第6図乃至第12図は本発明による覆工構築方法の一例を
示す工程図である。
1 is a front sectional view showing an example of a shield excavator to which the lining construction method according to the present invention is applied, FIG. 2 is a sectional view taken along line II-II of FIG. 1, and FIG. 3 is FIG. 3 is a sectional view taken along line III-III of FIG. 4, FIG. 4 is an enlarged view of a jack portion of the shield excavator shown in FIG. 1, FIG. 5 is a sectional view taken along line VV of FIG. 4, and FIGS. The drawing is a process drawing showing an example of a lining construction method according to the present invention.

シールド掘削機1は、第1図に示すように、円筒状に形
成された外殻2を有しており、外殻2の前面、即ち第1
図左側面にはカッター3が回転自在に支持されている。
カッター3は、外殻2内部の空間を図中左右方向に遮断
する形で設けれた隔壁2aに設けられた駆動モーター3aと
接続しており、更に隔壁2aには掘進用ジャッキ6が複数
個、第1図及び第2図に示すように、外殻2に沿った形
で円環状に配列設置されている。掘進用ジャッキ6には
ラム6aが矢印A、B方向に突出後退自在に設けられてお
り、更に外殻2の内側には、円筒状に形成されたプレス
リング7が、外殻2内面と接する形で矢印A、B方向に
摺動自在に設けられている。プレスリング7の内周面に
は、第4図に示すように、ゴム等の可撓性材料からなる
シール材5が図中右側の側面7a付近にその全周に亙って
貼設されている。また、プレスリング7には、第2図に
示すように、所定の間隔でプレスリングジャッキ9が外
殻2に沿った形で円環状に複数個配置されており、更に
それ等プレスリングジャッキ9の間には、第2図及び第
5図に示すように、複数の吐出管10が先端の吐出口10a
をプレスリング7の側面7a、即ちシールド掘削機1の後
方に向けた形で設けられている。吐出管10には、吐出管
内清掃用のシリンダー10bがロッド10cを矢印A、B方向
に突出後退自在にした形で設けられており、更に吐出管
10には供給ホール30が接続されている。
As shown in FIG. 1, the shield excavator 1 has an outer shell 2 formed in a cylindrical shape, and the front surface of the outer shell 2, that is, the first outer shell 2.
A cutter 3 is rotatably supported on the left side surface of the drawing.
The cutter 3 is connected to a drive motor 3a provided on a partition wall 2a provided so as to block the space inside the outer shell 2 in the left-right direction in the figure, and the partition wall 2a is further provided with a plurality of jacks 6 for excavation. As shown in FIGS. 1 and 2, they are arranged in an annular shape along the outer shell 2. The jack 6 for excavation is provided with a ram 6a so as to project and retract in the directions of arrows A and B. Further, a press ring 7 formed in a cylindrical shape is in contact with the inner surface of the outer shell 2 inside the outer shell 2. The shape is slidable in the directions of arrows A and B. As shown in FIG. 4, a sealing material 5 made of a flexible material such as rubber is attached to the inner peripheral surface of the press ring 7 in the vicinity of the side surface 7a on the right side of the drawing over the entire circumference thereof. There is. As shown in FIG. 2, a plurality of press ring jacks 9 are annularly arranged along the outer shell 2 at predetermined intervals on the press ring 7, and these press ring jacks 9 are also arranged. In between, as shown in FIG. 2 and FIG.
Is provided so as to face the side surface 7a of the press ring 7, that is, the rear side of the shield excavator 1. The discharge pipe 10 is provided with a cylinder 10b for cleaning the inside of the discharge pipe in such a shape that a rod 10c can be projected and retracted in the directions of arrows A and B.
A supply hole 30 is connected to 10.

ところで、掘進用ジャッキ6のラム6aの先端には、第4
図に示すように、円環状に形成されたゲージリング11が
プレスリング7の内面と接する形で装着されており、ゲ
ージリング11には、第2図及び第3図に示すように、円
環状に組立てられた型枠13が第1図左右方向に接続され
た形で設けられている。
By the way, at the tip of the ram 6a of the jack 6 for excavation,
As shown in the figure, a ring-shaped gauge ring 11 is attached so as to be in contact with the inner surface of the press ring 7. The gauge ring 11 has an annular shape as shown in FIGS. 2 and 3. The assembled formwork 13 is provided so as to be connected in the left-right direction in FIG.

また、シールド掘削機1の後方には、第1図に示すよう
に、円環状のセントル17が該シールド掘削機1の掘進方
向、即ち矢印A、B方向に移動駆動自在に設置されてお
り、セントル17には図示しないコンクリート供給管が設
けられている。
Further, as shown in FIG. 1, an annular centle 17 is installed behind the shield excavator 1 so as to be movable and driven in the excavating direction of the shield excavator 1, that is, in the directions of arrows A and B. The center 17 is provided with a concrete supply pipe (not shown).

シールド掘削機1等は、以上のような構成を有するの
で、トンネル15の掘削に際しては、駆動モーター3aを駆
動してカッター3を回転させる共に、掘進用ジャッキ6
のラム6aを第1図矢印B方向に突出させて、隔壁2a及び
外殻2を介してカッター3を切羽16方向、即ち矢印A方
向に押圧する。すると、その押圧力により、切羽16と回
転するカッター3は所定の接触圧力で接し、切羽16はカ
ッター3により掘削されると同時に、外殻2は矢印A方
向に推進してトンネル15がシールド掘削機1の後方、即
ち図中右方に形成されていく。
Since the shield excavator 1 and the like have the above-described configuration, when excavating the tunnel 15, the drive motor 3a is driven to rotate the cutter 3 and the jack 6 for excavation.
1. The ram 6a of FIG. 1 is projected in the direction of arrow B in FIG. 1, and the cutter 3 is pressed through the partition wall 2a and the outer shell 2 in the direction of the cutting face 16, that is, in the direction of arrow A. Then, due to the pressing force, the cutting face 16 and the rotating cutter 3 come into contact with each other with a predetermined contact pressure, the cutting face 16 is excavated by the cutter 3, and at the same time, the outer shell 2 is propelled in the direction of arrow A and the tunnel 15 is shield excavated. It is formed behind the machine 1, that is, on the right side of the drawing.

こうして、トンネル15が形成されていくにつれ、掘削さ
れた地山19の崩壊を防止するためにトンネル覆工20を構
築する必要があるが、このトンネル覆工20の構築は以下
の手順で行なわれる。即ち、シールド掘削機1が、型枠
13の1リング分の長さL1だけ矢印A方向に掘進した状態
で、掘進用ジャッキ6のラム6aは、第6図に示すよう
に、矢印B方向に突出した状態となっており、またプレ
スリング7も矢印B方向に移動した状態となっている。
In this way, as the tunnel 15 is formed, it is necessary to construct the tunnel lining 20 to prevent the excavated ground 19 from collapsing. The construction of the tunnel lining 20 is performed by the following procedure. . That is, the shield excavator 1 is
As shown in FIG. 6, the ram 6a of the jack 6 for excavation is in a state of protruding in the direction of arrow B in a state in which the length L1 for one ring 13 is excavated in the direction of arrow A. The ring 7 is also moved in the direction of arrow B.

この状態で、第7図に示すように、掘進用ジャッキ6の
ラム6aを矢印A方向に距離L1だけ後退させる。すると、
直前にコンクリート21の打設された部分の型枠13Aから
ゲージリング11が離れて矢印A方向に移動し、型枠13A
とゲージリング11との間に距離11なる空間が形成され
る。
In this state, as shown in FIG. 7, the ram 6a of the excavation jack 6 is retracted in the direction of arrow A by the distance L1. Then,
Immediately before, the gauge ring 11 moves away from the formwork 13A of the part where the concrete 21 was placed and moves in the direction of arrow A,
A space having a distance 11 is formed between the gauge ring 11 and the gauge ring 11.

この際、プレスリング7と型枠13Aのコンクリート接触
面(第7図における上面)との間は、シール材5により
閉塞されているので、直前に打設されたプレスリング7
の側面7aの第7図右方のコンクリート21が凝固状態にな
く、いまだ流動性を保持していても、当該未硬化のコン
クリートがプレスリング7と型枠13Aとの間から漏出し
てしまうことは無い。
At this time, the space between the press ring 7 and the concrete contact surface of the mold 13A (the upper surface in FIG. 7) is closed by the sealing material 5, so that the press ring 7 placed immediately before is pressed.
Even if the concrete 21 on the right side of FIG. 7 on the side surface 7a of Fig. 7 is not in a solidified state and still retains fluidity, the uncured concrete leaks from between the press ring 7 and the form 13A. There is no.

そこで、該空間部分に、図中想像線で示すように、型枠
13Aに接する形で型枠13Bを円環状に組立て設置する。
Therefore, as shown by the imaginary line in the figure,
The form 13B is assembled and installed in an annular shape so as to be in contact with 13A.

こうして、型枠13Bが円環状に組立て設置されたところ
で、第8図に示すように、プレスリングジャッキ9を駆
動してプレスリング7を矢印A方向に徐々に後退させ
る。すると、プレスリング7の通過した後には、外殻2
と型枠13A、13Bとの間に円環状のコンクリート打設空間
26が形成される。そこで、プレスリング7の矢印A方向
への移動と共に、第9図に示すように、供給ホース30か
ら、コンクリート21を吐出管10を介してコンクリート打
設空間26中に注入し、該コンクリート打設空間26をコン
クリート21で充填する。この際、プレスリング7と型枠
13A、13Bの間に設けられたシール材5が、該プレスリン
グ7の移動中、常時型枠13A又は13Bに当接するように変
形するので、コンクリート打設空間26は、閉鎖された状
態を維持しつつコンクリート21で充填される。従って、
注入されたコンクリート21がプレスリング7と型枠13
A、13Bの間から漏出することはない。プレスリング7が
矢印A方向に移動して、第10図に示すように、側面7aが
ゲージリング11の型枠支持位置とほぼ一致したところ
で、第11図に示すように、掘進用ジャッキ6のラム6aを
矢印B方向に突出駆動させて型枠13から反力を取ると共
に、カッター3を回転させて掘削動作を開始する。
In this way, when the mold frame 13B is assembled and installed in an annular shape, as shown in FIG. 8, the press ring jack 9 is driven to gradually retract the press ring 7 in the arrow A direction. Then, after passing through the press ring 7, the outer shell 2
-Shaped concrete placing space between the mold and the formwork 13A, 13B
26 is formed. Then, along with the movement of the press ring 7 in the direction of arrow A, as shown in FIG. 9, concrete 21 is poured from the supply hose 30 into the concrete placing space 26 through the discharge pipe 10, and the concrete placing space 26 is poured. The space 26 is filled with concrete 21. At this time, press ring 7 and formwork
Since the sealing material 5 provided between 13A and 13B is deformed so as to constantly contact the formwork 13A or 13B during the movement of the press ring 7, the concrete placing space 26 remains closed. While being filled with concrete 21. Therefore,
The injected concrete 21 is press ring 7 and formwork 13
There is no leakage from between A and 13B. When the press ring 7 moves in the direction of the arrow A and the side surface 7a almost coincides with the frame supporting position of the gauge ring 11 as shown in FIG. 10, the jack 6 for excavation is moved as shown in FIG. The ram 6a is driven to project in the direction of the arrow B to take a reaction force from the form 13, and the cutter 3 is rotated to start the excavation operation.

すると、既に述べたように、外殻2が矢印A方向に移動
を開始し、外殻2が移動した後には、打設充填されたコ
ンクリート21と地山19との間にテールボイド27が形成さ
れる。そこで、外殻2が矢印A方向に移動するにつれて
プレスリングジャッキ9を駆動して、プレスリング7を
外殻2の移動に同期した形で矢印B方向に徐々に移動さ
せる。すると、先程打設されたコンクリート打設空間26
内の未硬化コンクリート21は、プレスリング7に押圧さ
れて、テールボイド27を充填する形で流動する。こうし
て、第12図に示すように、外殻2の矢印A方向への移動
につれて、プレスリング7を矢印B方向に移動させてい
くと、外殻2の移動の結果発生するテールボイド27は、
効果的に充填されていく。この際、プレスリング7は円
筒状に形成され、また、プレスリング7が型枠13のコン
クリート接触面とシール材5を介して常時当接している
ので、コンクリート21はリング全周に亙り均一に加圧さ
れ、従ってテールボイド27の充填動作は外殻2の全周に
亙り均一で良好な状態で行なわれる。このようにして、
外殻2が型枠13の1リング分の長さL1だけ推進すると、
プレスリング7は、第6図に示すように、その側面7aが
外殻2の後端部2bに一致した形となり、1リング分の1
次覆工35の構築が完了する。
Then, as described above, the outer shell 2 starts moving in the direction of the arrow A, and after the outer shell 2 moves, the tail void 27 is formed between the concrete 21 that has been poured and filled and the ground 19. It Therefore, as the outer shell 2 moves in the arrow A direction, the press ring jack 9 is driven to gradually move the press ring 7 in the arrow B direction in synchronization with the movement of the outer shell 2. Then, the concrete placing space 26 that was just placed
The uncured concrete 21 therein is pressed by the press ring 7 and flows so as to fill the tail void 27. Thus, as shown in FIG. 12, when the press ring 7 is moved in the arrow B direction as the outer shell 2 moves in the arrow A direction, the tail void 27 generated as a result of the movement of the outer shell 2 becomes
It will be filled effectively. At this time, since the press ring 7 is formed in a cylindrical shape and the press ring 7 is always in contact with the concrete contact surface of the formwork 13 via the seal material 5, the concrete 21 is evenly distributed over the entire circumference of the ring. It is pressurized and therefore the filling operation of the tail void 27 is carried out in a uniform and good condition over the entire circumference of the outer shell 2. In this way
When the outer shell 2 propels the length L1 of one ring of the formwork 13,
As shown in FIG. 6, the press ring 7 has a shape in which the side surface 7a thereof coincides with the rear end portion 2b of the outer shell 2 and is divided by one ring.
Construction of the next lining 35 is completed.

なお、1リング分の1次覆工35が構築されると、次の1
リング分の1次覆工35を構築するため、既に述べたよう
に、この状態で掘進用ジャッキ6のラム6aを、第7図に
示すように、矢印A方向に距離L1だけ後退させて、ゲー
ジリング11による型枠13への押圧状態を解除するが、こ
の際には、直前に打設されたコンクリート21の妻部21a
がプレスリング7により常時加圧支持され、しかも、プ
レスリング7と型枠13のコンクリート接触面はシール材
5により閉塞されているので、打設されたコンクリート
21が未だ未硬化な状態であっても、該妻部21aが土圧や
水圧等により崩壊することはなく、従って次の型枠13の
設置作業は円滑に行なわれる。
When the primary lining 35 for one ring is constructed, the following 1
In order to construct the primary lining 35 for the ring, as described above, in this state, the ram 6a of the jack 6 for retreat is moved backward in the direction of arrow A by the distance L1 as shown in FIG. The pressing state of the form ring 13 by the gauge ring 11 is released, but at this time, the gable portion 21a of the concrete 21 that was placed immediately before is released.
Is constantly supported under pressure by the press ring 7, and the concrete contact surfaces of the press ring 7 and the formwork 13 are closed by the sealing material 5, so that the concrete poured
Even when 21 is still in an uncured state, the end 21a does not collapse due to earth pressure, water pressure, etc. Therefore, the next work for installing the form 13 can be performed smoothly.

このようにして1次覆工35を構築していくと、注入打設
されたコンクリート21は、上述したように、シール材5
によりプレスリング7と型枠13のコンクリート接触面と
の間が常に閉塞された状態で、プレスリング7により常
時加圧支持されて、地山19の土圧や水圧等による応力の
解放を起こさないので、該コンクリート21の硬化具合に
無関係に次々とトンネル15の掘削作業及び1次覆工35の
構築作業を続けることが出来る。従って、第13図に示す
ような従来の構築方法と比べて、本発明による方法で
は、特に高土圧、高水圧下において長くなりがちなコン
クリート21の養生時間がシールドによるトンネル15の掘
削サイクルに全く影響を及ぼさず、シールドは打設され
たコンクリート21の強度発現状況とは無関係に、型枠13
から反力を取る形で掘進していくことが出来る。
When the primary lining 35 is constructed in this way, the concrete 21 poured and poured will have the sealing material 5 as described above.
The press ring 7 and the concrete contact surface of the formwork 13 are always closed by the press ring 7, and the press ring 7 constantly pressurizes and supports them so that the stress due to earth pressure or water pressure of the natural ground 19 does not occur. Therefore, the excavation work of the tunnel 15 and the construction work of the primary lining 35 can be continued one after another regardless of the degree of hardening of the concrete 21. Therefore, as compared with the conventional construction method as shown in FIG. 13, in the method according to the present invention, the curing time of the concrete 21 which tends to be long especially under high earth pressure and high water pressure is applied to the excavation cycle of the tunnel 15 by the shield. It has no effect, and the shield does not depend on the strength development status of the cast concrete 21.
You can continue to dig in the form of taking a reaction force.

以上のようにして1次覆工35が構築された後、該1次覆
工35の内側に、円環状のセントル17を用いて補強コンク
リート33からなる2次覆工29を構築していく。それに
は、第1図に示すように、まずコンクリート21が円筒状
に硬化し、1次覆工35の構築されたコンクリート21部分
の型枠13を順次脱型して、該コンクリート21の内側に妻
止め22Bを円環状に設置する。次に、妻止め22Bと直前に
打設形成された2次覆工29の間に、図中想像線で示すよ
うに、パンチプレートや鉄筋等からなる補強部材12を円
環状に設置する。その後、直前に打設された2次コンク
リート23を支持しているセントル17を、図中想像線で示
すように、該セントル17の1リング分の長さL2だけ矢印
A方向に移動させる。すると、セントル17が前記妻止め
23Bに当接し、該セントル17、妻止め22B、1次覆工35及
び直前に形成された2次覆工29の端面に囲まれた2次コ
ンクリート打設空間32が形成される。
After the primary lining 35 is constructed as described above, the secondary lining 29 made of the reinforced concrete 33 is constructed inside the primary lining 35 by using the annular center 17. To do this, as shown in FIG. 1, first, the concrete 21 hardens into a cylindrical shape, and the formwork 13 of the concrete 21 portion where the primary lining 35 has been constructed is sequentially demolded, and the inside of the concrete 21 is removed. The wife stopper 22B is installed in an annular shape. Next, as shown by an imaginary line in the drawing, a reinforcing member 12 made of a punch plate, a reinforcing bar, or the like is annularly installed between the gable stopper 22B and the secondary lining 29 formed immediately before. Thereafter, as shown by an imaginary line in the drawing, the centle 17 supporting the secondary concrete 23 cast immediately before is moved in the direction of the arrow A by a length L2 corresponding to one ring of the centle 17. Then, Centr 17 stops the wife.
A secondary concrete placing space 32 is formed which is in contact with 23B and is surrounded by the end faces of the center 17, the girder 22B, the primary lining 35 and the secondary lining 29 formed immediately before.

次に、該2次コンクリート打設空間32に、セントル17に
設けられた図示しないコンクリート供給管を介して2次
コンクリートを打設し、充填する。該打設された2次コ
ンクリートが硬化したところで、1リング分の2次覆工
29の構築が完了する。
Next, in the secondary concrete placing space 32, secondary concrete is placed and filled through a concrete supply pipe (not shown) provided in the center 17. When the cast secondary concrete has hardened, the secondary lining for one ring
29 builds complete.

1リング分の2次覆工29の構築が完了したら、同様の手
順で順次2次覆工29を1リング分ずつ構築していくこと
により、1次覆工35及び2次覆工29からなるトンネル覆
工20が構築されていく。
When the construction of the secondary lining 29 for one ring is completed, the secondary lining 29 is constructed one ring at a time by the same procedure, and the primary lining 35 and the secondary lining 29 are formed. The tunnel lining 20 is built.

なお、上述の実施例においては、2次覆工29の構築に際
して、セントル17を用いて2次コンクリート23を現場打
設して、補強部材12で補強することにより補強コンクリ
ート33を形成し、2次覆工29としたが、これ以外の方
法、例えばセグメントを用いる方法であっても、強度的
に十分な2次覆工29を構築することが可能である限り、
どのような方法を用いてもよい。
In the above-described embodiment, when constructing the secondary lining 29, the secondary concrete 23 is cast on site using the center 17 and reinforced with the reinforcing member 12 to form the reinforced concrete 33. Although the secondary lining 29 is used, as long as it is possible to construct the secondary lining 29 with sufficient strength even with a method other than this, for example, a method using a segment,
Any method may be used.

(g).発明の効果 以上、説明したように、本発明は、外殻2を有し、該外
殻2の内側にプレスリング7を前記外殻の掘進方向に移
動駆動自在に設け、該プレスリングの内側にゲージリン
グ11などの型枠支持部材を前記外殻2に対して移動駆動
自在に設け、前記プレスリングの内周面にシール材5な
どの対型枠シール部材を全周にわたり設け、該型枠支持
部材と前記外殻の間に掘進用ジャッキ6を設けたシール
ド掘削機1などのシールド(従って、カッター3等は必
ずしも必要ではない。)を用いてトンネル覆工20などの
覆工を構築する際は、プレスリング7を外殻後方に突出
させた状態で、型枠支持部材を外殻前方に移動させ、該
型枠支持部材と既にコンクリート21などの覆工構築部材
の打設が完了した型枠13Aとの間に型枠13Bを設置し、次
いで、プレスリングを、該プレスリングが前記型枠のコ
ンクリート接触面と前記対型枠シール部材を介して常時
当接する形で外殻前方に移動させつつ、該プレスリング
の移動に伴なって生じるコンクリート打設空間26などの
覆工構築部材打設空間中に覆工構築部材を注入充填し、
その後、シールドによる掘進を開始して、掘進用ジャッ
キにより外殻の前方への移動を開始すると共に、プレス
リングを、該プレスリングが前記型枠のコンクリート接
触面と前記対型枠シール部材を介して常時当接する形で
後方に突出させて、前記直前に充填された覆工構築部材
を加圧することにより、前記外殻の移動に伴なって生じ
るテールボイド27中に該覆工構築部材を充填させて1次
覆工35を形成し、その後、前記1次覆工の覆工構築部材
の硬化した部分の型枠13を脱型して、該1次覆工の内側
に2次覆工29を構築するようにして構成したので、対型
枠シール部材がプレスリングと型枠のコンクリート接触
面との間を常時閉塞した状態で、プレスリング7が、地
山19と型枠13の間に形成された覆工構築部材打設空間中
に打設充填された覆工構築部材を常時加圧支持すること
が可能となり、従って型枠13の設置作業を覆工構築部材
の硬化状況に無関係に行なうことが出来、シールドの掘
削サイクルタイムを大幅に短縮することが可能となる。
(G). EFFECTS OF THE INVENTION As described above, the present invention has the outer shell 2, and the press ring 7 is provided inside the outer shell 2 so as to be movable and movable in the excavating direction of the outer shell, and the inside of the press ring is provided. A mold frame supporting member such as a gauge ring 11 is movably driven with respect to the outer shell 2, and an anti-mold frame sealing member such as a sealing material 5 is provided on the inner peripheral surface of the press ring over the entire circumference. Constructing a lining such as a tunnel lining 20 using a shield such as a shield excavator 1 having a jack 6 for excavation provided between the frame support member and the outer shell (hence, the cutter 3 and the like are not always necessary). In doing so, with the press ring 7 protruding rearward of the outer shell, the formwork support member is moved forward of the outer shell, and the placing of the formwork support member and the lining construction member such as concrete 21 has already been completed. Install the formwork 13B between the formed formwork 13A and the While moving the sling forward of the outer shell in such a manner that the press ring constantly contacts the concrete contact surface of the mold via the anti-mold seal member, the concrete placing caused by the movement of the press ring Inject and fill the lining construction member into the lining construction member placing space such as the space 26,
After that, the excavation by the shield is started, the forward movement of the outer shell is started by the jack for excavation, and the press ring is inserted through the concrete contact surface of the mold and the paired mold seal member. By projecting to the rear in a form of always abutting and pressurizing the lining construction member that has just been filled, the lining construction member is filled in the tail void 27 that is generated with the movement of the outer shell. To form a primary lining 35, and thereafter, the mold 13 of the hardened portion of the lining construction member of the primary lining is demolded, and a secondary lining 29 is formed inside the primary lining. Since it is constructed as constructed, the press ring 7 is formed between the ground 19 and the mold 13 in a state where the pair of mold seal members always closes the space between the press ring and the concrete contact surface of the mold. The lining that was placed and filled in the space where the construction member was placed. Since it is possible to constantly support the building member under pressure, it is possible to perform the work of installing the formwork 13 regardless of the hardening condition of the lining building member, and it is possible to greatly reduce the excavation cycle time of the shield. Become.

また、コンクリートの噴出を防止するために、妻板と型
枠が一体化した捨て型枠等の特殊な型枠を使用する必要
が無いので、極めて汎用性に富む。
Further, since it is not necessary to use a special formwork such as a waste formwork in which the end plate and the formwork are integrated in order to prevent the spouting of concrete, it is extremely versatile.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明による覆工構築方法が適用されるシール
ド掘削機等の一例を示す正断面図、 第2図は第1図のII−II線による断面図、 第3図は第1図のIII−III線による断面図、 第4図は第1図に示すシールド掘削機のジャッキ部分の
拡大図、 第5図は第4図のV−V線による断面図、 第6図乃至第12図は本発明による覆工構築方法の一例を
示す工程図、 第13図は従来のシールド工法におけるコンクリート打設
の方法を示す図である。 1……シールド(シールド掘削機) 2……外殻 5……対型枠シール部材(シール材) 6……掘進用ジャッキ 7……プレスリング 11……型枠支持部材(ゲージリング) 13A、13B……型枠 20……覆工(トンネル覆工) 21……覆工構築部材(コンクリート) 26……覆工構築部材打設空間(コンクリート打設空間) 27……テールボイド 29……2次覆工 35……1次覆工
1 is a front sectional view showing an example of a shield excavator to which the lining construction method according to the present invention is applied, FIG. 2 is a sectional view taken along line II-II of FIG. 1, and FIG. 3 is FIG. 3 is a sectional view taken along line III-III of FIG. 4, FIG. 4 is an enlarged view of a jack portion of the shield excavator shown in FIG. 1, FIG. 5 is a sectional view taken along line VV of FIG. 4, and FIGS. The figure is a process diagram showing an example of a lining construction method according to the present invention, and FIG. 13 is a diagram showing a concrete pouring method in a conventional shield construction method. 1 ... Shield (shield excavator) 2 ... Outer shell 5 ... Counter formwork seal member (seal material) 6 ... Jack for excavation 7 ... Press ring 11 ... Formwork support member (gauge ring) 13A, 13B …… Formwork 20 …… Coating (tunnel lining) 21 …… Coating construction member (concrete) 26 …… Coating construction member placing space (concrete placing space) 27 …… Tail void 29 …… Secondary Lining 35 …… Primary lining

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】外殻を有し、 該外殻の内側にプレスリングを前記外殻の掘進方向に移
動駆動自在に設け、 該プレスリングの内側に型枠支持部材を前記外殻に対し
て移動駆動自在に設け、 前記プレスリングの内周面に対型枠シール部材を全周に
わたり設け、 該型枠支持部材と前記外殻の間に掘進用ジャッキを設け
たシールドを用いて覆工を構築する際は、 プレスリングを外殻後方に突出させた状態で、型枠支持
部材を外殻前方に移動させ、 該型枠支持部材と既に覆工構築部材の打設が完了した型
枠との間に型枠を設置し、 次いで、プレスリングを、該プレスリングが前記型枠の
コンクリート接触面と前記対型枠シール部材を介して常
時当接する形で外殻前方に移動させつつ、該プレスリン
グの移動に伴なって生じる覆工構築部材打設空間中に覆
工構築部材を注入充填し、 その後、シールドによる掘進を開始して、掘進用ジャッ
キにより外殻の前方への移動を開始すると共に、 プレスリングを、該プレスリングが前記型枠のコンクリ
ート接触面と前記対型枠シール部材を介して常時当接す
る形で後方に突出させて、前記直前に充填された覆工構
築部材を加圧することにより、前記外殻の移動に伴なっ
て生じるテールボイド中に該覆工構築部材を充填させて
1次覆工を形成し、 その後、前記1次覆工の覆工構築部材の硬化した部分の
型枠を脱型して、該1次覆工の内側に2次覆工を構築す
るようにして構成した覆工構築方法。
1. An outer shell, wherein a press ring is provided inside the outer shell so as to be movable in the excavation direction of the outer shell, and a frame support member is provided inside the press ring with respect to the outer shell. It is provided so as to be movable and movable, and an anti-framework seal member is provided on the inner peripheral surface of the press ring over the entire circumference, and lining is performed using a shield provided with a jack for excavation between the frame frame support member and the outer shell. At the time of construction, with the press ring projected to the rear of the outer shell, the form support member is moved to the front of the outer shell, and the form support member and the form that has already been cast into the lining construction member are And then moving the press ring forward of the outer shell in such a manner that the press ring is in constant contact with the concrete contact surface of the form via the pair of form seal members. In the space where the lining construction member is placed, which is generated as the press ring moves. Inject and fill the lining construction member, then start excavation by the shield and start the forward movement of the outer shell by the excavation jack, and at the same time, press the ring to the concrete contact surface of the mold. And by projecting to the rear in a form of always abutting through the pair form frame seal member, and pressurizing the lining construction member filled immediately before, in the tail void generated with the movement of the outer shell. The lining construction member is filled to form a primary lining, and then the mold of the hardened portion of the lining construction member of the primary lining is demolded to the inside of the primary lining. A lining construction method configured so as to construct a secondary lining.
JP63287277A 1988-11-14 1988-11-14 Lining construction method Expired - Lifetime JPH0692719B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63287277A JPH0692719B2 (en) 1988-11-14 1988-11-14 Lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63287277A JPH0692719B2 (en) 1988-11-14 1988-11-14 Lining construction method

Publications (2)

Publication Number Publication Date
JPH02132297A JPH02132297A (en) 1990-05-21
JPH0692719B2 true JPH0692719B2 (en) 1994-11-16

Family

ID=17715320

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63287277A Expired - Lifetime JPH0692719B2 (en) 1988-11-14 1988-11-14 Lining construction method

Country Status (1)

Country Link
JP (1) JPH0692719B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4829593B2 (en) * 2005-11-09 2011-12-07 淳 小泉 Shield machine and shield method using the same

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62202200A (en) * 1985-11-06 1987-09-05 鉄建建設株式会社 Method of lining shield tunnel
JPS62194399A (en) * 1986-02-20 1987-08-26 三井建設株式会社 Construction method for coating tunnel

Also Published As

Publication number Publication date
JPH02132297A (en) 1990-05-21

Similar Documents

Publication Publication Date Title
JPS62194399A (en) Construction method for coating tunnel
JPH0692719B2 (en) Lining construction method
JPH02132295A (en) Constructing method for tunnel lining work
JPH06248889A (en) Concrete casting device for tunnel lining
JP2634883B2 (en) Construction method of tunnel lining
JPH0519000B2 (en)
JP2704891B2 (en) Construction method of shield excavator and tunnel lining
JPH02178500A (en) Shield excavator and lining constructing method
JP2676691B2 (en) Construction method of shield and lining using shield
JPH0333398A (en) Lining work for tunnel
JPH0518999B2 (en)
JPS63103199A (en) shield excavator
JPH01312199A (en) Construction of tunnel linining work
JPH0642296A (en) Concrete placing device for tunnel lining
JPH02225799A (en) Lining construction
JPH0377000A (en) Reinforcing member for tunnel lining and constructing method of tunnel lining by using said reinforcing member
JPH0361000B2 (en)
JPH02183094A (en) Constructing method of lining
JP2691473B2 (en) Tunnel lining Concrete continuous pouring method
JPH02292497A (en) Shield excavator and lining constructing method using its shield excavator
JPS62206198A (en) Method of constructing tunnel lining
JPH02183095A (en) Constructing method of tunnel lining
JPH0493498A (en) Concrete placing device for covering tunnel
JPH02178493A (en) Shield excavator
JPH0747920B2 (en) Tunnel lining construction method