JPH06153405A - Customer power source islanding prevention device or islanding prevention method - Google Patents
Customer power source islanding prevention device or islanding prevention methodInfo
- Publication number
- JPH06153405A JPH06153405A JP4297502A JP29750292A JPH06153405A JP H06153405 A JPH06153405 A JP H06153405A JP 4297502 A JP4297502 A JP 4297502A JP 29750292 A JP29750292 A JP 29750292A JP H06153405 A JPH06153405 A JP H06153405A
- Authority
- JP
- Japan
- Prior art keywords
- power
- distribution system
- ground fault
- voltage
- consumer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
(57)【要約】
【目的】変電所が電力を供給する電力需要家に設置され
ている需要家電源が単独運転となるのを防止することに
ある。
【構成】変電所から電力需要家へ電力を送出する送出遮
断器が開路しているにもかかわらず、この送出遮断器の
負荷側に電圧が存在していれば需要家電源が単独運転し
ているものと判断し、この送出遮断器の負荷側で人工的
な地絡事故を発生させる。この地絡事故は需要家電源側
で検出されて当該需要家電源は配電系統から切り離され
て単独運転を防止する。ここで人工的な地絡事故は1線
地絡,3線地絡,又はこの両者の組合せとし、送出遮断
器の負荷側電圧が零になるまで(即ち需要家電源が配電
系統から切り離されるまで)地絡事故を繰り返し発生さ
せるものとする。
(57) [Summary] [Purpose] It is to prevent the customer power supply installed in the power customer who supplies power from the substation from operating independently. [Structure] Even if the transmission breaker that sends electric power from the substation to the electric power consumer is open, if the voltage exists on the load side of this transmission breaker, the consumer power supply operates independently. Therefore, an artificial ground fault accident occurs on the load side of this transmission breaker. This ground fault is detected by the customer power supply side, and the customer power supply is disconnected from the power distribution system to prevent islanding. Here, the artificial ground fault is a one-wire ground fault, a three-wire ground fault, or a combination of both, until the load-side voltage of the output circuit breaker becomes zero (that is, until the customer power supply is disconnected from the distribution system). ) Repeated ground faults will occur.
Description
【0001】[0001]
【産業上の利用分野】この発明は、配電系統と需要家電
源とが並列運転中に変電所がこの配電系統を遮断して
も、前記需要家電源が単独運転となる危険を回避出来る
需要家電源の単独運転防止装置又は単独運転防止方法に
関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a customer who can avoid the risk of the customer power supply operating independently even if the substation cuts off the power distribution system while the distribution system and the customer power supply are operating in parallel. The present invention relates to an islanding prevention device or an islanding prevention method for a power source.
【0002】[0002]
【従来の技術】百万キロワット級の火力発電所であって
もその発電効率は40%を少し上回る程度であって、残
りの60%弱のエネルギーは熱として大気中や冷却水中
に廃棄されてしまっている。これよりも小容量の発電設
備、例えば千キロワット級エンジン発電設備の発電効率
は更に小さく一般に30%以下であって、70%のエネ
ルギーは使用されることなく廃棄されるので、極めて不
経済である。よって都市部ではこの程度の出力の発電設
備は非常用として設置することが多く、連続運転するこ
とは殆どなかった。しかしながら発電の際に発生して従
来は捨てていた熱も同時に利用すれば、総合した熱効率
は70乃至80%の高い値となる。そこで電力と共に大
量の熱も消費するオフィスビルやデパート等の需要家で
は電力のみを購入するよりもエネルギーコストが低下す
るので、このような設備を導入することが多くなってき
た。このように電力と共に発生した熱も同時に利用する
設備を一般にコジェネレーション設備と称している。2. Description of the Related Art Even a thermal power plant of a million kilowatt class has a power generation efficiency of slightly over 40%, and the remaining 60% or less of energy is discarded as heat into the atmosphere or cooling water. It's closed. The power generation efficiency of a power generation facility with a smaller capacity than this, for example, a 1,000 kilowatt class engine power generation facility is even smaller, generally 30% or less, and 70% of energy is discarded without being used, which is extremely uneconomical. . Therefore, in urban areas, power generation facilities with this level of output are often installed for emergency use, and there was almost no continuous operation. However, if the heat generated during power generation and wasted in the past is also used at the same time, the total thermal efficiency will be as high as 70 to 80%. Therefore, consumers such as office buildings and department stores that consume a large amount of heat together with electric power have a lower energy cost than purchasing only electric power, and thus such equipment has been introduced more often. Such equipment that also uses heat generated together with electric power at the same time is generally called cogeneration equipment.
【0003】図12は需要家電源を備えている電力需要
家へ変電所から電力を供給する配電系統の従来例を示し
た単線回路図である。この図12において、変電所10
へ入力する電力は受電用遮断器2を介して変圧器3で変
圧され、母線4に設けた送出遮断器としての第1遮断器
11,第2遮断器21,及び第3遮断器31を介してそ
れぞれの電力需要家へ電力を供給する。即ち、第1遮断
器11からは配電系統12を経て電力需要家としての第
1需要家13へ、第2遮断器21からは配電系統22を
経て電力需要家としての第2需要家23へ、第3遮断器
31からは配電系統32を経て電力需要家としての第3
需要家33へ電力が送られている。FIG. 12 is a single-line circuit diagram showing a conventional example of a power distribution system for supplying electric power from a substation to an electric power consumer equipped with a consumer power source. In FIG. 12, the substation 10
The electric power input to the transformer 3 is transformed by the transformer 3 via the power receiving circuit breaker 2 and passes through the first circuit breaker 11, the second circuit breaker 21, and the third circuit breaker 31 provided as the transmission circuit breakers on the bus bar 4. Power to each power consumer. That is, from the first circuit breaker 11 to the first customer 13 as a power consumer via the power distribution system 12, from the second circuit breaker 21 to the second customer 23 as a power consumer via the power distribution system 22, From the third circuit breaker 31 through the power distribution system 32 to the third
Electric power is being sent to the customer 33.
【0004】第1需要家13は図示のように入力遮断器
14と第1負荷15と第1電源16とで構成している。
第1需要家13に前述したようなコジェネレーション設
備を設ければ、そのエネルギーコストを低下させること
が出来るので、コジェネレーション設備としての第1電
源16を設けてこの第1電源16を配電系統12と並列
運転させておく。第1負荷15は第1電源16から電力
の供給を受けるが、これでも不足する電力のみを変電所
10から受電する。尚、第1電源16は前述したように
コジェネレーション設備であるが、熱部分は本発明とは
無関係であるので図示は省略し、発電機部分のみを図示
している。尚エンジン発電設備の代わりに燃料電池を使
用すると、電力の発生(直流電力であるがインバータで
交流電力に変換する)と共に熱湯を生じるのでコジェネ
レーション設備となる。The first customer 13 is composed of an input circuit breaker 14, a first load 15 and a first power source 16 as shown in the figure.
If the first customer 13 is provided with the cogeneration equipment as described above, the energy cost can be reduced. Therefore, the first power supply 16 as the cogeneration equipment is provided and the first power supply 16 is used as the power distribution system 12. And run in parallel. The first load 15 is supplied with electric power from the first power supply 16, but only the electric power that is still insufficient is received from the substation 10. The first power source 16 is a cogeneration facility as described above, but the heating portion is not related to the present invention, so the illustration is omitted and only the generator portion is shown. If a fuel cell is used instead of the engine power generation facility, hot water is generated together with the generation of electric power (DC power is converted into AC power by an inverter), so that it becomes a cogeneration facility.
【0005】第2需要家23も同様に入力遮断器24と
第2負荷25と第2電源26とで構成していて、第2電
源26がコジェネレーション設備である。しかし第3需
要家33は需要家電源を備えておらず、入力遮断器34
と第3負荷35のみで構成している。需要家電源を備え
ている電力需要家、即ち図12の従来例回路では第1需
要家13と第2需要家23では第1電源16と第2電源
26がそれぞれの配電系統と並列運転しているので、例
えば第1電源16に異常を生じた場合には直ちに配電系
統から解列しないと、配電系統に擾乱を与えて変電所1
0を停止させ、異常とは無関係の第2需要家23や第3
需要家33まで停電させてしまう恐れがある。そこで需
要家電源には例えば過電流保護、過電圧保護、逆電流保
護、地絡保護等の保護リレーを設けることが義務付けら
れており、需要家電源に異常を生じれば素早く配電系統
から切離すことが出来るようになっている。Similarly, the second consumer 23 also comprises an input circuit breaker 24, a second load 25 and a second power source 26, and the second power source 26 is a cogeneration facility. However, the third customer 33 does not have a customer power supply, and the input circuit breaker 34
And the third load 35 only. In the conventional example circuit of FIG. 12, the first power source 16 and the second power source 26 in the first consumer 13 and the second consumer 23 operate in parallel with their respective distribution systems. Therefore, for example, when an abnormality occurs in the first power supply 16, unless the power is immediately disconnected from the distribution system, the distribution system is disturbed and the substation 1
0, and the second consumer 23 and the third consumer irrelevant to the abnormality are
There is a risk that the customer 33 will be cut off. Therefore, it is obligatory to install protection relays for overcurrent protection, overvoltage protection, reverse current protection, ground fault protection, etc. in the customer power supply.If an abnormality occurs in the customer power supply, disconnect it from the power distribution system promptly. You can do it.
【0006】[0006]
【発明が解決しようとする課題】変電所10が各需要家
へ電力を供給中に、例えば変圧器3が故障するような所
内事故が発生すると受電用遮断器2がトリップし、これ
に引き続いて第1遮断器11,第2遮断器21,及び第
3遮断器31もトリップするので、配電系統12と配電
系統22及び配電系統32の電圧は零になるはずであ
る。ところがこの所内事故発生時に第1需要家13では
第1電源16が運転中であって、この第1電源16の発
生電力と第1負荷15の消費電力とがほぼ均衡している
ような場合には、第1遮断器11がトリップしても入力
遮断器14が閉路した状態のままで第1電源16が第1
負荷15へ電力を供給し続けることがあり、このとき配
電系統12は充電状態になっている。While the substation 10 is supplying electric power to each customer, for example, if an internal accident such as a failure of the transformer 3 occurs, the power receiving circuit breaker 2 trips. Since the first circuit breaker 11, the second circuit breaker 21, and the third circuit breaker 31 also trip, the voltage of the power distribution system 12, the power distribution system 22, and the power distribution system 32 should be zero. However, in the case where the first customer 13 is operating the first power supply 16 at the time of the in-house accident and the power generated by the first power supply 16 and the power consumption of the first load 15 are substantially balanced, Means that even if the first circuit breaker 11 trips, the first power source 16 keeps the first circuit
Power may be continuously supplied to the load 15, and at this time, the distribution system 12 is in a charged state.
【0007】このように変電所10から配電系統12へ
の電力は遮断されていても、需要家電源である第1電源
16が運転を継続して配電系統12を充電してしまう現
象を単独運転と称するが、第1電源16の単独運転によ
り第1遮断器11が開路しているにもかかわらずその負
荷側は充電しているので、感電の危険がある。それ故コ
ジェネレーション設備のような需要家電源には、単独運
転を防止する装置を設置することが系統連係技術要件と
して義務付けられている。しかしながら前述したよう
に、系統条件によっては従来の単独運転防止装置が作動
しない恐れがあった。As described above, even if the electric power from the substation 10 to the distribution system 12 is cut off, the phenomenon that the first power supply 16 as a consumer power supply continues to operate and charges the distribution system 12 is operated independently. However, there is a risk of electric shock because the load side of the first circuit breaker 11 is charged even though the first circuit breaker 11 is opened by the independent operation of the first power supply 16. Therefore, it is required as a system linkage technical requirement to install a device for preventing an independent operation in a power source for a customer such as a cogeneration facility. However, as described above, the conventional islanding prevention device may not operate depending on the system conditions.
【0008】そこでこの発明の目的は、変電所が電力を
供給する電力需要家に設置されている需要家電源が単独
運転となるのを防止することにある。Therefore, an object of the present invention is to prevent a customer power supply installed in a power customer who supplies power from a substation from operating independently.
【0009】[0009]
【課題を解決するための手段】上記の目的を達成するた
めにこの発明の需要家電源の単独運転防止装置又は単独
運転防止方法は、負荷と需要家電源との並列接続で構成
している電力需要家へ、変電所から電力を送出する送出
遮断器と配電系統とを介して電力を供給する構成の電力
系統において、前記送出遮断器の負荷側に前記配電系統
の電圧の有無を検出する電圧検出手段と、前記配電系統
に1線地絡状態を一定時間発生させる1線地絡手段と、
前記送出遮断器がオフしているときに前記配電系統に電
圧が存在すれば、前記1線地絡手段に作動指令を与える
作動指令手段とで構成した第1単独運転防止装置を前記
送出遮断器の負荷側に備えるか、又は前記配電系統の電
圧の有無を検出する電圧検出手段と、前記配電系統に3
線地絡状態を一定時間発生させる3線地絡手段と、前記
送出遮断器がオフしているときに前記配電系統に電圧が
存在すれば、前記3線地絡手段に作動指令を与える作動
指令手段とで構成した第2単独運転防止装置を備える
か、又は前記配電系統の電圧の有無を検出する電圧検出
手段と、前記配電系統に1線地絡状態を一定時間発生さ
せる1線地絡手段と、前記配電系統に3線地絡状態を一
定時間発生させる3線地絡手段と、前記送出遮断器がオ
フしているときに前記配電系統に電圧が存在すれば前記
1線地絡手段に作動指令を与え、この時点で当該配電系
統に電圧が存在すれば前記3線地絡手段に作動指令を与
える作動指令手段とで構成した第3単独運転防止装置を
備えるか、又はこれら第1単独運転防止装置又は第2単
独運転防止装置又は第3単独運転防止装置を配電系統電
圧が零になるまで繰り返し動作させるものとする。In order to achieve the above-mentioned object, a consumer power supply islanding prevention device or an islanding prevention method according to the present invention is an electric power configured by connecting a load and a customer power source in parallel. In a power system configured to supply power to a consumer via a transmission breaker that transmits power from a substation and a distribution system, a voltage that detects the presence or absence of the voltage of the distribution system on the load side of the transmission breaker. A detection unit and a one-line ground fault unit for generating a one-line ground fault condition in the distribution system for a certain period of time;
If a voltage exists in the power distribution system when the delivery breaker is off, the first islanding prevention device configured by the operation command means for giving an operation command to the one-line ground fault means is the delivery breaker. Or a voltage detecting means for detecting the presence or absence of voltage in the distribution system,
If there is a voltage in the three-wire ground fault means for generating a wire-ground fault condition for a certain period of time and the distribution system when the delivery breaker is off, an operation command for giving an operation command to the three-wire ground fault means. Or a voltage detection means for detecting the presence or absence of voltage in the distribution system, and a one-line ground fault means for generating a one-line ground fault condition in the distribution system for a certain period of time. A three-wire ground fault means for generating a three-wire ground fault condition in the power distribution system for a certain period of time; and a one-wire ground fault device if a voltage exists in the power distribution system when the delivery breaker is off. It is provided with a third islanding operation preventing device configured to give an operation command and an operation command means for giving an operation command to the three-wire ground fault means if a voltage exists in the distribution system at this point, or these first independent operation prevention devices are provided. Driving prevention device or second islanding prevention device or 3 alone driving preventing device power distribution system voltage is assumed to repeatedly operate until zero.
【0010】[0010]
【作用】この発明は、地絡を検出すれば需要家電源を配
電系統から切り離して系統に擾乱を与えないようにする
地絡検出リレーが必ず需要家電源に備えられていること
に着目したものであって、変電所から電力需要家へ電力
を送出する送出遮断器が開路しているにもかかわらず、
この送出遮断器の負荷側に電圧が存在していれば需要家
電源が単独運転しているものと判断し、この送出遮断器
の負荷側で人工的な地絡事故を発生させる。この地絡事
故は需要家電源側で検出されて当該需要家電源は配電系
統から切り離すので、単独運転は防止される。ここで人
工的な地絡事故は1線地絡,3線地絡,又はこの両者の
組合せとし、送出遮断器の負荷側電圧が零になるまで
(即ち需要家電源が配電系統から切り離されるまで)地
絡事故を繰り返し発生させるものとする。The present invention focuses on the fact that the customer power supply is always provided with a ground fault detection relay that disconnects the customer power supply from the power distribution system to prevent the system from being disturbed if a ground fault is detected. However, despite the fact that the transmission circuit breaker that transmits electric power from the substation to the electric power consumer is open,
If a voltage exists on the load side of the delivery breaker, it is determined that the consumer power supply is operating independently, and an artificial ground fault occurs on the load side of the delivery breaker. This ground fault is detected on the customer power supply side and the customer power supply is disconnected from the power distribution system, so islanding is prevented. Here, the artificial ground fault is a one-wire ground fault, a three-wire ground fault, or a combination of both, until the load-side voltage of the output circuit breaker becomes zero (that is, until the customer power supply is disconnected from the distribution system). ) Repeated ground faults will occur.
【0011】[0011]
【実施例】図1は本発明の基本となる実施例を表した単
線回路図であるが、この図1に図示の受電用遮断器2、
変圧器3、母線4、送出遮断器としての第1遮断器1
1、配電系統12、電力需要家としての第1需要家1
3、入力遮断器14、第1負荷15、第1電源16、送
出遮断器としての第2遮断器21、配電系統22、電力
需要家としての第2需要家23、入力遮断器24、第2
負荷25、第2電源26、送出遮断器としての第3遮断
器31、配電系統32、電力需要家としての第3需要家
33、入力遮断器34、及び第3負荷35の名称・用途
・機能は図12で既述の従来例回路のものと同じである
から、これらの説明は省略する。FIG. 1 is a single-line circuit diagram showing a basic embodiment of the present invention. The power receiving circuit breaker 2 shown in FIG.
Transformer 3, bus bar 4, first circuit breaker 1 as a transmission circuit breaker
1, distribution system 12, first consumer 1 as a power consumer
3, input circuit breaker 14, first load 15, first power supply 16, second circuit breaker 21 as a delivery circuit breaker, distribution system 22, second consumer 23 as a power consumer, input circuit breaker 24, second
Names, uses, and functions of the load 25, the second power supply 26, the third circuit breaker 31 as a delivery circuit breaker, the power distribution system 32, the third customer 33 as an electric power consumer, the input circuit breaker 34, and the third load 35. 12 is the same as that of the conventional circuit described above with reference to FIG.
【0012】本発明においては、需要家電源を備えてい
る電力需要家へ電力を送出する送出遮断器、即ち第1遮
断器11と第2遮断器21のそれぞれの負荷側に単独運
転防止装置41と単独運転防止装置42を別個に接続し
て、これら単独運転防止装置41又は42により配電系
統に地絡事故を発生させて、変電所40が停電した場合
に第1電源16又は第2電源26が単独運転状態になる
のを防止する。以下では第1需要家13が備えている第
1電源16が単独運転するのを防止する単独運転防止装
置41について説明するものとし、単独運転防止装置4
2はこれと同じ構成なのでその説明は省略する。According to the present invention, the islanding prevention device 41 is provided on each of the load breakers of the first breaker 11 and the second breaker 21 for sending electric power to the electric power consumer equipped with the consumer power supply. And the islanding prevention device 42 are separately connected, and when the islanding fault occurs in the power distribution system by the islanding prevention device 41 or 42, and the substation 40 has a power failure, the first power source 16 or the second power source 26. To prevent it from operating independently. In the following, the islanding prevention device 41 for preventing the first power source 16 provided in the first consumer 13 from operating alone will be described.
Since 2 has the same configuration as this, its description is omitted.
【0013】尚、単独運転防止装置41は以下に説明す
るように第1単独運転防止装置50、又は第2単独運転
防止装置60、又は第3単独運転防止装置70のいずれ
かで構成するものとする。単独運転防止装置42も同様
に第1単独運転防止装置50、又は第2単独運転防止装
置60、又は第3単独運転防止装置70のいずれかで構
成する。It should be noted that the islanding prevention device 41 is constituted by either the first islanding operation preventing device 50, the second islanding operation preventing device 60, or the third islanding operation preventing device 70, as will be described below. To do. Similarly, the islanding prevention device 42 is also configured by either the first islanding prevention device 50, the second islanding prevention device 60, or the third islanding prevention device 70.
【0014】図2は本発明の第1実施例である第1単独
運転防止装置の構成を表した外観図であって、図1の基
本実施例回路に図示の単独運転防止装置41に対応する
ものである。この図2の第1実施例は請求項1に対応し
ていて、図示の第1単独運転防止装置50は配電系統1
2の電圧の有無を測定する系統電圧測定器51と、人為
的にこの配電系統12に1線地絡状態を一定時間発生さ
せる1線地絡装置52と、系統電圧測定器51と1線地
絡装置52とへ動作指令を与える第1作動指令回路53
とで構成している。FIG. 2 is an external view showing the configuration of a first islanding prevention device which is the first embodiment of the present invention, and corresponds to the islanding prevention device 41 shown in the basic circuit of FIG. It is a thing. The first embodiment of FIG. 2 corresponds to claim 1, and the first islanding prevention device 50 shown in the drawing is the distribution system 1
2 system voltage measuring device 51 for measuring the presence or absence of voltage, 1-line ground fault device 52 for artificially generating a 1-line ground fault condition in this distribution system 12 for a certain period of time, system voltage measuring device 51 and 1-line ground First operation command circuit 53 for giving an operation command to the relay device 52
It consists of and.
【0015】図3は図2に図示の第1実施例の動作を表
した第1フローチャートであって、同じく請求項1に対
応する。この第1フローチャートでは、第1遮断器11
がオフしているかそれともオンしているかを判断81で
判断し、オフであるならば処理91により配電系統12
の電圧を計測し、判断82が電圧の有無を判断する。第
1遮断器11がオフしている際に入力遮断器14もオフ
していれば、第1電源16が運転中でも配電系統12に
電圧は印加されずに零であるが、第1電源16が運転中
で且つ入力遮断器14がオンならば配電系統12は充電
されるので、電圧有りを検出することになる。よって判
断82が電圧有りと判断すれば処理92により1線地絡
装置52を作動させるので、人為的な1線地絡状態が一
定時間継続する。この人為的な1線地絡状態により、第
1電源16が装備している地絡検出リレーが動作してこ
の第1電源16を配電系統12から切り離す操作、即ち
入力遮断器14をオフにする操作がなされるので、第1
電源16の単独運転は回避出来る。FIG. 3 is a first flow chart showing the operation of the first embodiment shown in FIG. 2, and also corresponds to claim 1. In this first flow chart, the first circuit breaker 11
Is determined to be off or on by determination 81, and if it is off, processing 91 determines power distribution system 12
The voltage is measured, and the judgment 82 judges the presence or absence of the voltage. If the input circuit breaker 14 is also off when the first circuit breaker 11 is off, the voltage is not applied to the distribution system 12 even when the first power supply 16 is operating, and the voltage is zero. If the circuit breaker 14 is turned on during operation and the power distribution system 12 is charged, the presence of voltage is detected. Therefore, if the determination 82 determines that there is a voltage, the one-line ground fault device 52 is activated by the process 92, so that the artificial one-line ground fault state continues for a certain period of time. Due to this artificial 1-line ground fault condition, the ground fault detection relay equipped in the first power source 16 operates to disconnect the first power source 16 from the power distribution system 12, that is, the input circuit breaker 14 is turned off. Because the operation is done, the first
The independent operation of the power supply 16 can be avoided.
【0016】図4は図2に図示の第1単独運転防止装置
を使用した場合の動作を示す本発明の第2実施例を表し
た第2フローチャートであって、請求項2に対応する。
この第2フローチャートに図示の判断81と82,及び
処理91と92の機能は図2で既述の第1フローチャー
トの場合と同じであるから、これらの説明は省略する。
この第2フローチャートでは、処理92で1線地絡装置
52を動作させた後の配電系統12の電圧を処理93で
計測し、判断83が電圧有りと判断すれば、配電系統1
2の電圧が零になるまで1線地絡装置52の動作と系統
電圧測定器51による電圧検出とを繰り返させる。FIG. 4 is a second flow chart showing a second embodiment of the present invention showing the operation when the first islanding prevention device shown in FIG. 2 is used, and corresponds to claim 2.
The functions of the judgments 81 and 82 and the processes 91 and 92 shown in the second flow chart are the same as those in the case of the first flow chart described above with reference to FIG.
In this second flowchart, the voltage of the power distribution system 12 after the one-line ground fault device 52 is operated in the process 92 is measured in the process 93, and if the judgment 83 judges that there is a voltage, the power distribution system 1
The operation of the one-wire ground fault device 52 and the voltage detection by the system voltage measuring device 51 are repeated until the voltage of 2 becomes zero.
【0017】図5は本発明の第3実施例である第2単独
運転防止装置の構成を表した外観図であって、図1の基
本実施例回路に図示の単独運転防止装置41に対応する
ものである。この図5の第3実施例は請求項3に対応し
ていて、図示の第2単独運転防止装置60は、配電系統
12の電圧の有無を測定する系統電圧測定器51と、人
為的に配電系統12に3線地絡状態を一定時間発生させ
る3線地絡装置62と、これら系統電圧測定器51と3
線地絡装置62とに動作指令を与える第2作動指令回路
63とで構成している。FIG. 5 is an external view showing the configuration of a second islanding prevention device which is a third embodiment of the present invention, and corresponds to the islanding prevention device 41 shown in the basic circuit of FIG. It is a thing. The third embodiment of FIG. 5 corresponds to claim 3, and the illustrated second islanding prevention device 60 includes a system voltage measuring device 51 for measuring the presence or absence of voltage in the distribution system 12, and artificial distribution. A three-wire ground fault device 62 for generating a three-wire ground fault condition in the system 12 for a certain period of time, and these system voltage measuring devices 51 and 3
The line-to-ground fault device 62 and the second operation command circuit 63 that gives an operation command.
【0018】図6は図5に図示の第3実施例の動作を表
した第3フローチャートであって、同じく請求項3に対
応する。この第3フローチャートでは、判断82が電圧
有りと判断すれば処理94により3線地絡装置62を動
作させるところが図3で既述の第1フローチャートとは
異なる点であるが、それ以外の判断81と82、及び処
理91の機能は第1フローチャートの場合と同じである
から、これらの説明は省略する。FIG. 6 is a third flow chart showing the operation of the third embodiment shown in FIG. 5, and also corresponds to claim 3. In this third flowchart, if the judgment 82 judges that there is a voltage, the process 94 operates the three-wire ground fault device 62, which is a point different from the first flowchart described above in FIG. And 82 and the function of the process 91 are the same as in the case of the first flow chart, and therefore their explanation is omitted.
【0019】図7は図5に図示の第2単独運転防止装置
を使用した場合の動作を示す本発明の第4実施例を表し
た第4フローチャートであって、請求項4に対応する。
この第4フローチャートは、図6で既述の第3フローチ
ャートに処理95と判断84とを付加した構成になって
いて、処理94で3線地絡装置62を動作させた後に処
理95で配電系統12の電圧を計測し、判断84が電圧
有りと判断すればこの電圧が零になるまで3線地絡装置
62の動作と系統電圧測定器51による電圧検出とを繰
り返させる。FIG. 7 is a fourth flowchart showing a fourth embodiment of the present invention showing the operation when the second islanding prevention device shown in FIG. 5 is used, and corresponds to claim 4.
This fourth flow chart has a configuration in which the processing 95 and the determination 84 are added to the third flow chart described in FIG. 6, and the three-wire ground fault device 62 is operated in the processing 94 and then the power distribution system is processed in the processing 95. The voltage of 12 is measured, and if the determination 84 determines that there is a voltage, the operation of the three-wire ground fault device 62 and the voltage detection by the system voltage measuring device 51 are repeated until this voltage becomes zero.
【0020】図8は本発明の第5実施例である第3単独
運転防止装置の構成を表した外観図であって、図1の基
本実施例回路に図示の単独運転防止装置41に対応する
ものである。この図8の第5実施例は請求項5に対応し
ていて、第3単独運転防止装置60は、配電系統12の
電圧の有無を測定する系統電圧測定器51と、人為的に
この配電系統12に1線地絡状態を一定時間発生させる
1線地絡装置52と、同じく人為的に配電系統12に3
線地絡状態を一定時間発生させる3線地絡装置62と、
これら系統電圧測定器51と1線地絡装置52及び3線
地絡装置62へ動作指令を与える第3作動指令回路73
とで構成している。FIG. 8 is an external view showing the configuration of the third islanding prevention device which is the fifth embodiment of the present invention, and corresponds to the islanding prevention device 41 shown in the basic circuit of FIG. It is a thing. The fifth embodiment of FIG. 8 corresponds to claim 5, and the third islanding prevention device 60 includes a system voltage measuring device 51 for measuring the presence or absence of voltage in the distribution system 12, and this distribution system artificially. A 1-line ground fault device 52 for generating a 1-line ground fault condition for 12 hours for a certain period of time, as well as artificially
A three-wire ground fault device 62 for generating a linear ground fault condition for a certain period of time,
A third operation command circuit 73 that gives an operation command to the system voltage measuring device 51, the one-line ground fault device 52, and the three-line ground fault device 62.
It consists of and.
【0021】図9は図8に図示の第5実施例の動作を表
した第5フローチャートであって、同じく請求項5に対
応する。この第5フローチャートは図3で既述の第1フ
ローチャートと図6で既述の第3フローチャートとを組
み合わせた構成になっていて、第1遮断器11がオフで
あることと配電系統12に電圧が有ることを判断81と
82とが判断すれば、先ず処理91で1線地絡装置52
を動作させるが、それでも判断83が電圧有りと判断す
れば処理94で3線地絡装置62を動作させるものであ
る。FIG. 9 is a fifth flowchart showing the operation of the fifth embodiment shown in FIG. 8, and also corresponds to claim 5. This fifth flow chart has a configuration in which the first flow chart described above with reference to FIG. 3 and the third flow chart described above with reference to FIG. If the determinations 81 and 82 determine that there is a fault, first, in a process 91, the 1-line ground fault device 52
However, if the determination 83 still determines that there is voltage, the three-wire ground fault device 62 is operated in step 94.
【0022】図10は図8に図示の第3単独運転防止装
置を使用した場合の動作を示す本発明の第6実施例を表
した第6フローチャートであって、請求項6に対応す
る。この第6フローチャートは図9で既述の第5フロー
チャートに処理95と判断84とを付加した構成になっ
ていて、処理94で3線地絡装置62を動作させた後に
処理95で配電系統12の電圧を計測し、判断84が電
圧有りと判断すればこの電圧が零になるまで3線地絡装
置62の動作と系統電圧測定器51による電圧検出とを
繰り返させる。FIG. 10 is a sixth flow chart showing a sixth embodiment of the present invention showing the operation when the third islanding prevention device shown in FIG. 8 is used, and corresponds to claim 6. The sixth flowchart has a configuration in which the process 95 and the determination 84 are added to the fifth flowchart described above in FIG. 9, and the three-wire ground fault device 62 is operated in the process 94 and then the power distribution system 12 is processed in the process 95. If the determination 84 determines that there is a voltage, the operation of the three-wire ground fault device 62 and the voltage detection by the system voltage measuring device 51 are repeated until the voltage becomes zero.
【0023】図11は図8に図示の第3単独運転防止装
置を使用した場合の動作を示した本発明の第7実施例を
表す第7フローチャートであって、請求項7に対応す
る。この第7フローチャートの構成は図10で既述の第
6フローチャートと同じ構成であるが、処理94で3線
地絡装置62を動作させた後に処理95で配電系統12
の電圧を計測し、判断84が電圧有りと判断すれば、こ
の電圧が零になるまで先ず1線地絡装置52を動作させ
て系統電圧測定器51による電圧検出を行い、次いで3
線地絡装置62の動作させて系統電圧測定器51による
電圧検出を、繰り返し行わせるものである。FIG. 11 is a seventh flow chart showing a seventh embodiment of the present invention showing an operation when the third islanding prevention device shown in FIG. 8 is used, and corresponds to claim 7. Although the configuration of the seventh flowchart is the same as the configuration of the sixth flowchart described above with reference to FIG. 10, the three-wire ground fault device 62 is operated in process 94 and then the power distribution system 12 is processed in process 95.
If the determination 84 determines that there is a voltage, the 1-line ground fault device 52 is first operated to detect the voltage by the system voltage measuring device 51 until the voltage becomes zero, and then 3
The line-to-ground fault device 62 is operated to repeatedly perform voltage detection by the system voltage measuring device 51.
【0024】[0024]
【発明の効果】変電所から配電系統を介して需要家電源
を備えている電力需要家へ電力を供給する場合に、変電
所の故障などにより配電系統へ電力を送出する送出遮断
器を遮断しても、需要家電源が単独運転状態にあると送
出遮断器の負荷側は充電したままのために感電の恐れが
あり極めて危険であるが、従来はこのような単独運転状
態を確実には回避することは困難であった。しかし本発
明では変電所の送出遮断器の負荷側、即ち配電系統に単
独運転防止装置を設置し、送出遮断器がオフであるにも
かかわらず配電系統に電圧が存在していれば、これは需
要家電源が単独運転状態にあると判断し、この配電系統
に人為的に1線地絡状態又は3線地絡状態を発生させ
る。需要家電源は必ず地絡検出リレーを設置しなければ
ならないので、この人為的な地絡を検出して需要家電源
を配電系統から切り離すので、単独運転を確実に回避す
ることが出来る。更にこの人為的な1線地絡又は3線地
絡は、需要家電源の地絡検出リレーの誤動作に対処出来
るように配電系統の電圧が零になるまで繰り返し行わせ
るので、需要家電源の単独運転をより確実に回避するこ
とが出来る。[Effects of the Invention] When power is supplied from a substation to a power consumer equipped with a customer power supply through a distribution system, the transmission breaker for sending power to the distribution system is shut off due to a failure of the substation or the like. However, if the customer power supply is in the isolated operation state, the load side of the output circuit breaker remains charged and there is a danger of electric shock, which is extremely dangerous in the past. It was difficult to do. However, in the present invention, if the islanding prevention device is installed on the load side of the transmission circuit breaker of the substation, that is, on the distribution system, and if the voltage exists in the distribution system despite the fact that the transmission circuit breaker is off, this will occur. It is determined that the consumer power supply is in the independent operation state, and this power distribution system artificially causes the one-line ground fault state or the three-line ground fault state. Since the customer power supply must always have the ground fault detection relay installed, the artificial power supply is detected and the customer power supply is disconnected from the power distribution system, so that the isolated operation can be reliably avoided. Furthermore, this artificial 1-wire ground fault or 3-wire ground fault is repeatedly performed until the voltage of the distribution system becomes zero so that the malfunction of the ground fault detection relay of the customer power supply can be dealt with. Driving can be avoided more reliably.
【図1】本発明の基本となる実施例を表した単線回路図FIG. 1 is a single-line circuit diagram showing a basic embodiment of the present invention.
【図2】本発明の第1実施例である第1単独運転防止装
置の構成を表した外観図FIG. 2 is an external view showing the configuration of a first islanding prevention device that is a first embodiment of the present invention.
【図3】図2に図示の第1実施例の動作を表した第1フ
ローチャートFIG. 3 is a first flowchart showing the operation of the first embodiment shown in FIG.
【図4】図2に図示の第1単独運転防止装置を使用した
場合の動作を示す本発明の第2実施例を表した第2フロ
ーチャートFIG. 4 is a second flowchart showing a second embodiment of the present invention, which shows the operation when the first islanding prevention device shown in FIG. 2 is used.
【図5】本発明の第3実施例である第2単独運転防止装
置の構成を表した外観図FIG. 5 is an external view showing the configuration of a second islanding prevention device which is a third embodiment of the present invention.
【図6】図5に図示の第3実施例の動作を表した第3フ
ローチャート6 is a third flowchart showing the operation of the third embodiment shown in FIG.
【図7】図5に図示の第2単独運転防止装置を使用した
場合の動作を示す本発明の第4実施例を表した第4フロ
ーチャートFIG. 7 is a fourth flow chart showing a fourth embodiment of the present invention, which shows the operation when the second islanding prevention device shown in FIG. 5 is used.
【図8】本発明の第5実施例である第3単独運転防止装
置の構成を表した外観図FIG. 8 is an external view showing the configuration of a third islanding prevention device which is a fifth embodiment of the present invention.
【図9】図8に図示の第5実施例の動作を表した第5フ
ローチャートFIG. 9 is a fifth flowchart showing the operation of the fifth embodiment shown in FIG.
【図10】図8に図示の第3単独運転防止装置を使用し
た場合の動作を示す本発明の第6実施例を表した第6フ
ローチャートFIG. 10 is a sixth flow chart showing a sixth embodiment of the present invention showing the operation when the third islanding prevention device shown in FIG. 8 is used.
【図11】図8に図示の第3単独運転防止装置を使用し
た場合の動作を示す本発明の第7実施例を表した第7フ
ローチャートFIG. 11 is a seventh flow chart showing a seventh embodiment of the present invention, showing the operation when the third islanding prevention device shown in FIG. 8 is used.
【図12】需要家電源を備えている電力需要家へ変電所
から電力を供給する配電系統の従来例を示した単線回路
図FIG. 12 is a single-line circuit diagram showing a conventional example of a distribution system that supplies electric power from a substation to an electric power customer equipped with a customer power supply.
2 受電用遮断器 3 変圧器 4 母線 10 変電所 11 送出遮断器としての第1遮断器 12 配電系統 13 電力需要家としての第1需要家 14 入力遮断器 15 第1負荷 16 第1電源 40 変電所 41 単独運転防止装置 50 第1単独運転防止装置 51 系統電圧測定器 52 1線地絡装置 53 第1作動指令回路 60 第2単独運転防止装置 62 3線地絡装置 63 第2作動指令回路 70 第3単独運転防止装置 73 第3作動指令回路 81 判断 82 判断 83 判断 84 判断 91 処理 92 処理 93 処理 94 処理 95 処理 2 Power receiving circuit breaker 3 Transformer 4 Bus 10 Substation 11 First circuit breaker as a transmission circuit breaker 12 Distribution system 13 First customer as a power consumer 14 Input circuit breaker 15 First load 16 First power supply 40 Transformer 41 41 islanding prevention device 50 1st islanding prevention device 51 system voltage measuring device 52 1-line ground fault device 53 1st operation command circuit 60 2nd islanding prevention device 62 3 wire ground fault device 63 2nd operation command circuit 70 Third islanding prevention device 73 Third operation command circuit 81 Judgment 82 Judgment 83 Judgment 84 Judgment 91 Processing 92 Processing 93 Processing 94 Processing 95 Processing
Claims (7)
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 前記配電系統の電圧の有無を検出する電圧検出手段と、
前記配電系統に1線地絡状態を一定時間発生させる1線
地絡手段と、前記送出遮断器がオフしているときに前記
配電系統に電圧が存在すれば前記1線地絡手段に作動指
令を与える第1作動指令手段とで構成した第1単独運転
防止装置を、前記送出遮断器の負荷側に備えることを特
徴とする需要家電源の単独運転防止装置。1. A power system configured to supply power to a power consumer configured by connecting a load and a power source in parallel to a power consumer via a transmission breaker for transmitting power from a substation and a power distribution system. A voltage detecting means for detecting the presence or absence of voltage in the distribution system,
1-line ground fault means for generating a 1-line ground fault condition in the power distribution system for a certain period of time, and an operation command to the 1-line ground fault device if a voltage exists in the power distribution system when the delivery breaker is off. A first isolated operation preventing device configured with a first operation commanding means for providing a power supply to a consumer side, the isolated operation preventing device for a consumer power supply.
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 請求項1に記載の前記第1単独運転防止装置で1線地絡
状態を一定時間発生させた後の前記配電系統に電圧が存
在すれば、この電圧が消滅するまで前記第1単独運転防
止装置を繰り返して作動させることを特徴とする需要家
電源の単独運転防止方法。2. A power system configured to supply power to a power consumer configured by connecting a load and a power source in parallel to a power consumer via a transmission breaker for transmitting power from a substation and a power distribution system. If a voltage exists in the distribution system after the 1-line ground fault condition is generated for a certain period of time by the first islanding prevention device according to claim 1, the first islanding prevention is performed until the voltage disappears. A method for preventing an isolated operation of a customer power supply, which comprises repeatedly operating the device.
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 前記配電系統の電圧の有無を検出する電圧検出手段と、
前記配電系統に3線地絡状態を一定時間発生させる3線
地絡手段と、前記送出遮断器がオフしているときに前記
配電系統に電圧が存在すれば前記3線地絡手段に作動指
令を与える第2作動指令手段とで構成した第2単独運転
防止装置を、前記送出遮断器の負荷側に備えることを特
徴とする需要家電源の単独運転防止装置。3. A power system configured to supply power to a power consumer, which is configured by connecting a load and a power source in parallel, to a power consumer via a transmission breaker for transmitting power from a substation and a power distribution system. A voltage detecting means for detecting the presence or absence of voltage in the distribution system,
3-wire ground fault means for generating a 3-wire ground fault condition in the power distribution system for a certain period of time, and an operation command to the 3-wire ground fault device if voltage exists in the power distribution system when the delivery breaker is off. A second islanding operation preventing device configured to provide a second operation commanding means for providing a power source to a consumer power source.
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 請求項3に記載の前記第2単独運転防止装置で3線地絡
状態を一定時間発生させた後の前記配電系統に電圧が存
在すれば、この電圧が消滅するまで前記第2単独運転防
止装置を繰り返して作動させることを特徴とする需要家
電源の単独運転防止方法。4. A power system configured to supply power to a power consumer configured by connecting a load and a power source in parallel to each other via a transmission breaker for transmitting power from a substation and a power distribution system. If a voltage exists in the distribution system after the three-wire ground fault condition is generated for a certain period of time by the second islanding prevention device according to claim 3, the second islanding prevention is performed until the voltage disappears. A method for preventing an isolated operation of a customer power supply, which comprises repeatedly operating the device.
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 前記配電系統の電圧の有無を検出する電圧検出手段と、
前記配電系統に1線地絡状態を一定時間発生させる1線
地絡手段と、前記配電系統に3線地絡状態を一定時間発
生させる3線地絡手段と、前記送出遮断器がオフしてい
るときに前記配電系統に電圧が存在すれば前記1線地絡
手段に作動指令を与え、この時点で当該配電系統に電圧
が存在すれば前記3線地絡手段に作動指令を与える第3
作動指令手段とで構成した第3単独運転防止装置を、前
記送出遮断器の負荷側に備えることを特徴とする需要家
電源の単独運転防止装置。5. A power system configured to supply power to a power consumer configured by a load and a power source connected in parallel to a power consumer via a transmission breaker for transmitting power from a substation and a power distribution system. A voltage detecting means for detecting the presence or absence of voltage in the distribution system,
A one-line ground fault means for generating a one-line ground fault condition in the power distribution system for a certain period of time, a three-wire ground fault device for generating a three-line ground fault condition in the power distribution system for a certain period of time, and the delivery breaker being turned off. If there is a voltage in the distribution system during the operation, an operation command is given to the one-line ground fault means, and if there is a voltage in the distribution system at this point, an operation command is given to the three-wire ground fault means.
An independent operation prevention device for a consumer power supply, comprising a third isolated operation prevention device configured with operation command means on the load side of the delivery breaker.
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 請求項5に記載の前記第3単独運転防止装置で3線地絡
状態を一定時間発生させた後の前記配電系統に電圧が存
在すれば、この電圧が消滅するまでこの第3単独運転防
止装置の3線地絡手段を繰り返して作動させることを特
徴とする需要家電源の単独運転防止方法。6. A power system configured to supply power to a power consumer configured by a load and a power source connected in parallel to a power consumer via a transmission breaker for transmitting power from a substation and a power distribution system. If a voltage exists in the distribution system after the three-wire ground fault condition is generated for a certain period of time by the third islanding prevention device according to claim 5, the third islanding prevention is performed until the voltage disappears. A method for preventing isolated operation of a customer power supply, characterized in that a three-wire ground fault means of the device is repeatedly operated.
いる電力需要家へ、変電所から電力を送出する送出遮断
器と配電系統とを介して電力を供給する構成の電力系統
において、 請求項5に記載の前記第3単独運転防止装置で3線地絡
状態を一定時間発生させた後の前記配電系統に電圧が存
在すれば、この電圧が消滅するまで、この第3単独運転
防止装置は先ず前記1線地絡手段を作動させ、次いで前
記3線地絡手段を作動させる動作を繰り返させることを
特徴とする需要家電源の単独運転防止方法。7. A power system configured to supply power to a power consumer configured by connecting a load and a power source in parallel to a power consumer via a transmission breaker for transmitting power from a substation and a power distribution system. If a voltage exists in the distribution system after the three-wire ground fault condition is generated for a certain period of time by the third islanding prevention device according to claim 5, the third islanding operation is performed until the voltage disappears. The preventive device first activates the one-line ground fault means, and then repeats the operation of operating the three-line ground fault means.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4297502A JPH06153405A (en) | 1992-11-09 | 1992-11-09 | Customer power source islanding prevention device or islanding prevention method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4297502A JPH06153405A (en) | 1992-11-09 | 1992-11-09 | Customer power source islanding prevention device or islanding prevention method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH06153405A true JPH06153405A (en) | 1994-05-31 |
Family
ID=17847348
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4297502A Pending JPH06153405A (en) | 1992-11-09 | 1992-11-09 | Customer power source islanding prevention device or islanding prevention method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH06153405A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2015039287A (en) * | 2010-04-12 | 2015-02-26 | 株式会社日立製作所 | Power management system |
-
1992
- 1992-11-09 JP JP4297502A patent/JPH06153405A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2015039287A (en) * | 2010-04-12 | 2015-02-26 | 株式会社日立製作所 | Power management system |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH08126210A (en) | Off-line control device for private generator connected to commercial power source | |
| JP2728398B2 (en) | Spot network power receiving substation protection device | |
| JPH0919066A (en) | Distributed power supply | |
| Salman | Detection of embedded generator islanding condition using elliptical trajectory technique | |
| US20040070281A1 (en) | Method and apparatus for isolating a cogeneration system from a utility source | |
| JPH06153405A (en) | Customer power source islanding prevention device or islanding prevention method | |
| CN100438248C (en) | Protective relay | |
| JP2620916B2 (en) | Grid connection protection device | |
| Moshoeshoe et al. | Adaptive overcurrent protection scheme with zonal approach for a stand-alone renewable-based microgrid | |
| JPH06343231A (en) | System-interconnection protecting apparatus | |
| JP2507338B2 (en) | Protection equipment for power receiving and transforming equipment | |
| JP6797073B2 (en) | Operation control device and power generation equipment | |
| Brewis et al. | Theory and practical performance of interlocked overcurrent busbar zone protection in distribution substations | |
| JP2684317B2 (en) | Grid connection protection device | |
| JPH01114332A (en) | Protective device for power receiving substation facility | |
| Rosolowski et al. | A new method for islanding detection in distributed generation | |
| JPH06343230A (en) | System-interconnection protecting apparatus | |
| JP2691692B2 (en) | Grid connection protection device | |
| JP2558585B2 (en) | Grid interconnection protection detector | |
| Baier et al. | Connection of a distributed resource to 2-transformer spot network | |
| JPH05328609A (en) | Distributed type power supply system | |
| JPH0467729A (en) | Reverse charge preventing system for distributed power supply | |
| JPH07322509A (en) | In-house protection device | |
| JPH0345127A (en) | System interconnection | |
| JPH0360334A (en) | Reverse-tidal-current-proof device in cogeneration equipment |