[go: up one dir, main page]

JPH0613770B2 - Method of constructing mountain retaining wall with parent pile - Google Patents

Method of constructing mountain retaining wall with parent pile

Info

Publication number
JPH0613770B2
JPH0613770B2 JP58175511A JP17551183A JPH0613770B2 JP H0613770 B2 JPH0613770 B2 JP H0613770B2 JP 58175511 A JP58175511 A JP 58175511A JP 17551183 A JP17551183 A JP 17551183A JP H0613770 B2 JPH0613770 B2 JP H0613770B2
Authority
JP
Japan
Prior art keywords
wall
underground wall
ground
retaining wall
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58175511A
Other languages
Japanese (ja)
Other versions
JPS6065825A (en
Inventor
光弘 國藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ask Kenkyusho KK
Original Assignee
Ask Kenkyusho KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ask Kenkyusho KK filed Critical Ask Kenkyusho KK
Priority to JP58175511A priority Critical patent/JPH0613770B2/en
Publication of JPS6065825A publication Critical patent/JPS6065825A/en
Publication of JPH0613770B2 publication Critical patent/JPH0613770B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〔技術分野〕 本発明は、地盤から下方を掘削するに際して周囲の土砂
が崩壊しないようにするための親杭を有する山止め壁の
製造方法に関する。
Description: TECHNICAL FIELD The present invention relates to a method of manufacturing a retaining wall having a main pile to prevent surrounding sediment from collapsing when excavating downward from the ground.

〔背景技術〕[Background technology]

従来から、地盤(1)から下方を掘削するに際して土砂が
崩壊しないようにH鋼材よりなる親杭(3)′を適当間隔
で必要な深さまで建込み、親杭(3)′と親杭(3)′との間
に掘削底面の深さまで木製又はコンクリート製等の横矢
板を順次積み重ねていくものが知られている。しかしな
がらこの従来例にあつては、掘削が進行するに従つて横
矢板(6)を親杭(3)′と親杭との間に嵌めていくものであ
り、その際に横矢板(6)の背面の土を乱し、周囲の地盤
沈下の原因となつており、また掘削の進行と同時に横矢
板(6)の嵌め込み作業を必要とするので、作業が煩雑と
なる問題があつた。また従来にあつては横矢板(6)と横
矢板(6)との継ぎ目から山止め背面にある水が漏水して
漏水と共に土砂を掘削面に流出させて山止め背面の地盤
の沈下を生ぜしめるという問題があつた。
Conventionally, parent piles (3) 'made of H steel have been installed at appropriate intervals to the required depth to prevent the soil from collapsing when excavating downward from the ground (1). It is known that wooden or concrete horizontal sheet piles are sequentially stacked up to the depth of the excavated bottom between 3) '. However, in this conventional example, as the excavation proceeds, the horizontal sheet pile (6) is fitted between the main pile (3) 'and the main pile, at which time the horizontal sheet pile (6) is inserted. It disturbs the soil on the back side of the ground and causes ground subsidence in the surrounding area. Moreover, since the work of inserting the horizontal sheet pile (6) is required at the same time as the excavation proceeds, there is a problem that the work becomes complicated. Also, in the past, the water on the back surface of the mountain stop leaks from the joint between the horizontal sheet pile (6) and the horizontal sheet pile (6), causing the sediment to flow to the excavation surface together with the leakage, causing the subsidence of the ground behind the mountain stop. There was a problem of tightening.

〔発明の目的〕[Object of the Invention]

本発明の目的とするところは、掘削開始以前に地中壁の
造成と親杭の建て込みとができて周囲の地盤をゆるめる
ことがなく、また止水効果にすぐれて背面の地盤沈下を
防止し、且つ土砂の崩壊を確実に防止できる親杭を有す
る山止め壁の造成方法を提供するにある。
The object of the present invention is to prevent the ground subsidence on the back side without damaging the surrounding ground because the underground wall can be constructed and the main piles can be built before excavation is started and the water blocking effect is excellent. In addition, the present invention provides a method of constructing a mountain retaining wall having a main pile that can surely prevent the collapse of earth and sand.

〔発明の開示〕[Disclosure of Invention]

本発明の親杭を有する山止め壁の造成方法は、地盤(1)
から下方を掘削するに際して周囲の土砂が崩壊しないよ
うに山止め壁を造成するに当つて、ほぼ予定される掘削
底面までソイルセメント壁の地中壁(2)を地中壁(2)の各
部分の下端部分の深さをほぼ等しく形成し、該地中壁
(2)の中に任意の間隔をあけて地中壁(2)よりも深く地盤
(1)の支持層までH鋼材のような親杭(3)を建て込むもの
であつて、このような方法を採用することで上記した本
発明の目的を達成したものである。
The method for creating a mountain retaining wall having a parent pile of the present invention is the ground (1)
When constructing a retaining wall to prevent the surrounding sediment from collapsing when excavating downward from the ground, the soil cement wall underground wall (2) up to the almost planned excavation bottom The lower end of the part is formed to have almost the same depth,
The ground is deeper than the underground wall (2) with arbitrary spacing in (2).
A parent pile (3) such as H steel is built up to the support layer of (1), and the object of the present invention described above is achieved by adopting such a method.

以下本発明を実施例により詳述する。本発明にあつて
は、まずほぼ予定される掘削底面までソイルセメント壁
の地中壁(2)を形成する。ここでソイルセメント壁の地
中壁(2)を形成するにあたつては、例えば掘削機にて円
穴を削孔すると共に円孔内で掘削土砂とセメントミルク
のような固結材とを混合撹拌したソイルセメント柱(4)
を形成し、このソイルセメント柱(4)を次々と一部ラツ
プさせながら形成することで柱列壁を形成し、この柱列
壁を地中壁(2)としたり、あるいは掘削軸を複数本有す
る多軸掘削機によつて複数個の円穴が数殊つなぎ状に連
続した長方形状穴を形成すると共に長方形状穴内で掘削
土砂とセメントミルクのような固結材とを混合したソイ
ルセメント壁(5)を形成し、このソイルセメント壁(5)を
端部同士が一部重複するように次々と形成することで連
続壁を形成し、この連続壁を地中壁(2)としたりするも
のである。ここで地中壁(2)の各部分の下端部の深さは
第2図に示すようにほぼ等しい深さとなっている。上記
のようにして地中壁(2)を形成した後、地中壁(2)の中に
任意の間隔をあけてH鋼材のような親杭(3)を建込む。
ここで親杭(3)は下部が地中壁(2)の下端よりも必要長だ
け下方に位置するように地中壁(2)よりも深く建込むも
のである。上記のようにして親杭を有する山止め壁を造
成した後に山止め壁に囲まれた部分の地盤(1)を下方に
掘削していくのであるが、この場合地中壁(2)は掘削時
に周辺地盤より水がもれるのを防止する役目をしている
ものであり、このため地中壁(2)の深さは止水をするの
に最低限必要な深さ(つまり予定される掘削底面)であ
れば十分であるが、一方親杭(3)は予定される掘削底面
まで掘削した状態においても背面の土圧や水圧によつて
土砂が崩壊するのを防止しうるように予定される掘削底
面よりも更に必要長だけ深く建込む必要があるのであ
る。
Hereinafter, the present invention will be described in detail with reference to Examples. In the present invention, first, the underground wall (2) of soil cement wall is formed up to almost the planned excavation bottom surface. Here, in forming the underground wall (2) of the soil cement wall, for example, a circular hole is drilled with an excavator and the excavated soil and a solid material such as cement milk are formed in the circular hole. Mixed and stirred soil cement columns (4)
The soil cement columns (4) are formed by partially lapping them one after another to form a column wall, which can be used as the underground wall (2), or multiple excavation shafts can be used. With a multi-axis excavator having a plurality of circular holes, a rectangular cemented hole is formed in the shape of a continuous bridge, and the soil cement wall is formed by mixing drilled earth and sand and a cementitious material such as cement milk in the rectangular hole. (5) is formed and a continuous wall is formed by forming the soil cement wall (5) one after another so that the ends partially overlap each other, and this continuous wall is used as the underground wall (2). It is a thing. Here, the depth of the lower end of each part of the underground wall (2) is almost equal as shown in FIG. After forming the underground wall (2) as described above, a main pile (3) such as H steel is built in the underground wall (2) at arbitrary intervals.
Here, the main pile (3) is built deeper than the underground wall (2) so that its lower portion is located below the lower end of the underground wall (2) by a required length. After constructing the retaining wall with parent piles as described above, the ground (1) surrounded by the retaining wall is excavated downward.In this case, the underground wall (2) is excavated. Sometimes it serves to prevent water from leaking from the surrounding ground, so the depth of the underground wall (2) is the minimum required to stop the water (that is, the planned depth). The excavation bottom) is sufficient, while the main pile (3) is planned to prevent the soil from collapsing due to the earth pressure or water pressure on the back side even when the excavation bottom is excavated. It is necessary to build it deeper than the excavated bottom surface by the required length.

〔発明の効果〕〔The invention's effect〕

本発明にあつては、叙述のようにほぼ予定される掘削底
面までソイルセメント壁の地中壁を地中壁の各部分の下
端部分の深さをほぼ等しく形成し、地中壁の中に任意の
間隔をあけて地中壁よりも深く地盤(1)の支持層まで親
杭を建込むので、掘削が始まる前に地中壁及び親杭の施
工ができ、掘削中に横矢板を建込むといつた煩雑な作業
を必要としないのみならず、従来のように掘削中に横矢
板を建込むといつたとかがないので、横矢板の建込みに
よつて背面の土を乱し、周囲の地盤沈下が生じたりしな
いものである。しかもソイルセメント壁の地中壁がほぼ
予定される掘削底面まで形成するので、ソイルセメント
壁の地中壁によつて確実に止水されて山止め壁の背面の
地盤の沈下を防止できるものであり、更に地中壁の中に
地中壁よりも深く親杭を建込むので、所定地盤まで掘削
しても親杭がそれよりも深く建込んであるので、親杭に
よつて水圧、水圧に耐え土砂の崩壊を防止できるもので
あり、更にここで地中壁は各部の下端部の深さを等しく
してあり、H鋼材のような親杭のみを地中壁よりも深く
建て込んであるので、止水性を必要としない部分に(つ
まり地中壁の下方の部分)にソイルセメント柱のような
ものを設けることなく、止水性は地中壁で確保し、地中
壁の崩壊をH鋼材のような親杭で確保し、無駄な構成が
なく、コストを下げることができる。またH鋼材のよう
な親杭を建て込む場合、地中壁部分はソイルセメントが
硬化する前に入れることで、地中壁の下端までは殆ど打
撃力を要することなく入れることができ、その後、地中
壁から下方の部分のみを打ち込むので、打ち込みが簡単
にできるのである。
In the present invention, the underground wall of the soil cement wall is formed to almost the same depth as the lower end portion of each part of the underground wall to the excavated bottom surface almost as described above, and Since the main pile is built deeper than the underground wall to the support layer of the ground (1) at arbitrary intervals, the underground wall and the main pile can be constructed before excavation starts, and a horizontal sheet pile is constructed during excavation. Not only does it require complicated work when it is installed, but since it does not take a while to install the horizontal sheet pile during excavation as in the past, the construction of the horizontal sheet pile disturbs the soil on the back, The surrounding ground subsidence does not occur. Moreover, since the underground wall of the soil cement wall is formed up to almost the planned excavation bottom surface, water can be reliably stopped by the underground wall of the soil cement wall and it is possible to prevent the subsidence of the ground on the back side of the earth retaining wall. Yes, and because the main pile is built in the underground wall deeper than the underground wall, the main pile is still deeper than that even if it is excavated to the specified ground. The bottom wall of each part has the same depth at the lower end, and only the main piles such as H steel are built deeper than the bottom wall. Therefore, without providing something like a soil cement column in the part that does not require water stoppage (that is, the part below the underground wall), the water stoppage is secured by the underground wall to prevent collapse of the underground wall. Secure with parent piles such as H steel, there is no wasteful configuration and cost can be reduced. Also, when building a main pile such as H steel, by inserting the underground wall before the soil cement hardens, it is possible to insert it to the lower end of the underground wall with almost no impact force, and then Since only the portion below the underground wall is driven in, the driving can be done easily.

【図面の簡単な説明】[Brief description of drawings]

第1図は従来例の斜視図、第2図は本発明の斜視図、第
3図は本発明で形成する地中壁の1例の断面図、第4図
は同上の他の地中壁の断面図であつて、(1)は地盤、(2)
は地中壁、(3)は親杭である。
FIG. 1 is a perspective view of a conventional example, FIG. 2 is a perspective view of the present invention, FIG. 3 is a sectional view of an example of an underground wall formed by the present invention, and FIG. 4 is another underground wall of the same. (1) is the ground, (2)
Is the underground wall and (3) is the main pile.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】地盤から下方に掘削するに際して周囲の土
砂が崩壊しないように山止め壁を造成するに当たって、
ほぼ予定される掘削底面までソイルセメント壁の地中壁
を地中壁の各部分の下端部分の深さをほぼ等しく形成
し、該地中壁の中に任意の間隔をあけて地中壁よりも深
く地盤の支持層までH鋼材のような親杭を建て込むこと
を特徴とする親杭を有する山止め壁の造成方法。
1. When constructing a retaining wall to prevent the surrounding soil from collapsing when excavating downward from the ground,
The soil cement wall underground wall is formed to almost the expected bottom of the excavation, and the depths of the lower end portions of each portion of the underground wall are formed to be approximately equal to each other. A method of constructing a retaining wall having a parent pile, characterized in that a parent pile such as an H steel material is built deeply into the support layer of the ground.
JP58175511A 1983-09-22 1983-09-22 Method of constructing mountain retaining wall with parent pile Expired - Lifetime JPH0613770B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58175511A JPH0613770B2 (en) 1983-09-22 1983-09-22 Method of constructing mountain retaining wall with parent pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58175511A JPH0613770B2 (en) 1983-09-22 1983-09-22 Method of constructing mountain retaining wall with parent pile

Publications (2)

Publication Number Publication Date
JPS6065825A JPS6065825A (en) 1985-04-15
JPH0613770B2 true JPH0613770B2 (en) 1994-02-23

Family

ID=15997324

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58175511A Expired - Lifetime JPH0613770B2 (en) 1983-09-22 1983-09-22 Method of constructing mountain retaining wall with parent pile

Country Status (1)

Country Link
JP (1) JPH0613770B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2895378B2 (en) * 1993-12-28 1999-05-24 株式会社テノックス Steep slope construction method
BE1019993A3 (en) * 2011-05-26 2013-03-05 Ekolplast Nv POLE INTENDED TO BE PARTIALLY DRIVEN IN A SUBSTRATE.
JP6142538B2 (en) * 2013-01-15 2017-06-07 大成建設株式会社 Mountain retaining wall
JP5762511B2 (en) * 2013-11-11 2015-08-12 藤井 俊彦 Ground improvement wall construction method
CN106703013A (en) * 2017-01-25 2017-05-24 山西大学 Water-proof curtain for treating built loess roadbed subsidence damages
JP7280602B2 (en) * 2019-04-26 2023-05-24 株式会社アストリード Concrete wall forming method for earth retaining

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58189414A (en) * 1982-04-10 1983-11-05 Masato Ohori Construction of sheathing wall

Also Published As

Publication number Publication date
JPS6065825A (en) 1985-04-15

Similar Documents

Publication Publication Date Title
EP3521514B1 (en) Permanent prefabricated braced wall
JPH0768705B2 (en) Soil retaining method and its retaining pile
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
JPH0613770B2 (en) Method of constructing mountain retaining wall with parent pile
JP7509679B2 (en) Structure and method for preventing subsidence of adjacent buildings
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
JPS582294B2 (en) Continuous basement wall construction method
JP2607966B2 (en) Expanded connecting wall construction method
KR100401330B1 (en) A method of construction for earth-protection walls of building
JP2761531B2 (en) Construction method of guide for underground diaphragm wall
JP2565452B2 (en) Construction method of self-supporting retaining wall
KR100669530B1 (en) Construction method
JPS5944431A (en) How to build a basement
JP2005113672A (en) Pile extracting construction method and heterogeneous coating material of pile
JP2988516B2 (en) Construction method of shield excavation wall
JPH0133610B2 (en)
JPS6145021B2 (en)
JP2003027885A (en) Underground tunnel method and underground tunnel
JPH05125723A (en) Simple construction method of underground structure
JPS5826124A (en) Construction of retaining wall for basement
JPS584021A (en) Underground wall construction work
JPS62211418A (en) Construction of continuous wall
JPH0137529B2 (en)
JPS63125725A (en) Construction of underground continuous wall
JPS63156124A (en) Construction of basement