[go: up one dir, main page]

JP6566481B2 - Removal mechanism, temporary pillar, and removal method - Google Patents

Removal mechanism, temporary pillar, and removal method Download PDF

Info

Publication number
JP6566481B2
JP6566481B2 JP2016127125A JP2016127125A JP6566481B2 JP 6566481 B2 JP6566481 B2 JP 6566481B2 JP 2016127125 A JP2016127125 A JP 2016127125A JP 2016127125 A JP2016127125 A JP 2016127125A JP 6566481 B2 JP6566481 B2 JP 6566481B2
Authority
JP
Japan
Prior art keywords
flange
shim plate
temporary
column
removal mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016127125A
Other languages
Japanese (ja)
Other versions
JP2018003288A (en
Inventor
勝彦 辻田
勝彦 辻田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toray Engineering Co Ltd
Original Assignee
Toray Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toray Engineering Co Ltd filed Critical Toray Engineering Co Ltd
Priority to JP2016127125A priority Critical patent/JP6566481B2/en
Publication of JP2018003288A publication Critical patent/JP2018003288A/en
Application granted granted Critical
Publication of JP6566481B2 publication Critical patent/JP6566481B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

本発明は、モジュール型プラントにおける仮設柱の撤去機構、仮設柱、および撤去方法に関するものである。 The present invention relates to a temporary pillar removal mechanism, a temporary pillar, and a removal method in a modular plant.

プラントを製作工場から据付地に輸送する際に、完成したプラントを複数のモジュールに分解して輸送し、据付地にて再度各モジュールを組み立てることが行われている。このとき、複数のモジュールに分解したことにより、柱の数が不足する等構造的に弱い部分ができる。この構造的弱点を補強するために仮設柱を設けて輸送することが行われている。この場合、モジュール組立後にこの仮設柱を撤去することが必要となる。   When a plant is transported from a manufacturing factory to an installation site, the completed plant is disassembled into a plurality of modules and transported, and each module is assembled again at the installation site. At this time, by disassembling into a plurality of modules, a structurally weak portion such as the number of pillars is insufficient. In order to reinforce this structural weakness, a temporary pillar is provided and transported. In this case, it is necessary to remove the temporary pillar after assembling the module.

プラントには、複数の縦梁および横梁により支持された重量機械を内蔵しているため、モジュール組立後には仮設柱にそれらの荷重がかかる。したがって仮設柱撤去時には、その荷重を開放させて撤去しなければならず容易な作業ではない。従来は、クレーンでプラントを吊り下げて仮設柱にかかる荷重をなくした状態で仮設柱を撤去するか、強引に仮設柱を切断して撤去する方法が実施されている。しかしながら、このような方法は手間がかかるという問題があった。 Since the plant incorporates a heavy machine supported by a plurality of vertical beams and horizontal beams, these loads are applied to the temporary columns after module assembly. Therefore, when removing the temporary pillar, the load must be released and removed, which is not an easy task. Conventionally, a method of suspending a plant with a crane and removing the temporary pillar in a state where a load applied to the temporary pillar is eliminated, or forcibly cutting and removing the temporary pillar has been implemented. However, such a method has a problem that it takes time.

特許文献1には、完成したプラントを多数のモジュールに分割して輸送し、外国における所定位置において各モジュールを組み立てるプラント建設の構成が記載されている。 Patent Document 1 describes a configuration of plant construction in which a completed plant is divided into a large number of modules and transported, and each module is assembled at a predetermined position in a foreign country.

特許文献1:特開昭60−80628号公報 Patent Document 1: Japanese Patent Laid-Open No. 60-80628

しかしながら、特許文献1記載のものは、複数のモジュールに分割した後の構造的弱点を補強する仮設柱については記載がなく、仮設柱の要否や撤去方法については不明である。このため、現在まで、荷重がかかっている仮設柱の撤去を簡易に行うことが困難であるという問題があった。 However, the thing of patent document 1 does not describe about the temporary pillar which reinforces the structural weak point after dividing | segmenting into several modules, and the necessity of a temporary pillar and the removal method are unknown. For this reason, until now, there has been a problem that it is difficult to easily remove the temporary columns that are under load.

本発明は、上記問題点を解決して、仮設柱の撤去を簡易な作業で行えるようにすることを課題とする。 This invention makes it a subject to solve the said problem and to be able to remove a temporary pillar by simple operation | work.

上記課題を解決するために本発明は、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱を撤去するために、当該仮設柱にかかる荷重を開放する撤去機構であって、
フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする撤去機構を提供するものである。
In order to solve the above problems, the present invention releases the load applied to the temporary column in order to remove the temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant. A removal mechanism,
A flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
It is an object of the present invention to provide a removal mechanism characterized in that the load applied to the temporary column can be released by removing the shim plate from the load receiving portion .

この構成により、ジャッキアップ部でジャッキアップし、シムプレートを除去することにより荷重を開放することができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the load can be released by jacking up at the jackup portion and removing the shim plate, and the temporary pillar can be removed with a simple operation.

前記シムプレートは、前記接続ボルトの挿通位置に対応し、一端を開放した長穴を備えるように構成してもよい。 The shim plate may correspond to the insertion position of the connection bolt and may be configured to have an elongated hole with one end opened.

この構成より、シムプレートの挿入および除去を容易にし、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the shim plate can be easily inserted and removed, and the temporary pillar can be removed with a simple operation.

また、上記課題を解決するために本発明は、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱であって、
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする仮設柱を提供するものである。
In order to solve the above problems, the present invention is a temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
The present invention provides a temporary column, wherein the load applied to the temporary column can be released by removing the shim plate from the load receiving portion .

この構成により、ジャッキアップ部でジャッキアップし、シムプレートを除去することにより荷重を開放することができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the load can be released by jacking up at the jackup portion and removing the shim plate, and the temporary pillar can be removed with a simple operation.

上部柱と下部柱とを有し、前記上部柱と前記下部柱との間に前記撤去機構を備え、前記対向部材は前記下部柱の最上部における部材である構成としてもよい。 An upper column and a lower column may be provided, the removal mechanism may be provided between the upper column and the lower column, and the opposing member may be a member at the uppermost portion of the lower column.

この構成により、作業者が作業しやすい位置に撤去機構を設けることができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the removal mechanism can be provided at a position where the worker can easily work, and the temporary pillar can be removed with a simple work.

最上部に前記撤去機構を備え、前記対向部材は前記上部梁における部材である構成としてもよい。 The removal mechanism may be provided on the top, and the opposing member may be a member in the upper beam.

この構成により、仮設柱を上部柱と下部柱とに分ける必要がなくなるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, it is not necessary to divide the temporary column into an upper column and a lower column, and it is possible to remove the temporary column with a simple operation.

最下部に前記撤去機構を備え、前記対向部材は前記下部梁における部材である構成としてもよい。 It is good also as a structure which equips the lowest part with the said removal mechanism and the said opposing member is a member in the said lower beam.

この構成により、仮設柱を上部柱と下部柱とに分ける必要がなくなるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, it is not necessary to divide the temporary column into an upper column and a lower column, and it is possible to remove the temporary column with a simple operation.

さらに、上記課題を解決するために本発明は、モジュール型プラントにおける上部梁からの荷重を受けて下部梁との間に設けられてなる仮設柱を撤去する撤去方法であって、
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記接続ボルトを緩め、前記ジャッキボルトを螺嵌して前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧して、前記フランジと前記対向部材との間に前記シムプレートの厚さよりも大きいスペースを形成した後、前記シムプレートを除去し、前記仮設柱を撤去することを特徴とする撤去方法を提供するものである。
Furthermore, in order to solve the above-mentioned problem, the present invention is a removal method for removing a temporary column provided between a lower beam and receiving a load from an upper beam in a modular plant,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the opposing member can be pressed by the tip of the screw portion of the jack bolt,
A space larger than the thickness of the shim plate between the flange and the opposing member by loosening the connecting bolt, screwing the jack bolt, and pressing the opposing member with the tip of the screw portion of the jack bolt Then, the shim plate is removed and the temporary pillar is removed, thereby providing a removal method.

この構成により、ジャッキアップ部でジャッキアップし、シムプレートを除去することにより荷重を開放することができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the load can be released by jacking up at the jackup portion and removing the shim plate, and the temporary pillar can be removed with a simple operation.

本発明の撤去機構、仮設柱、および撤去方法により、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With the removal mechanism, the temporary pillar, and the removal method of the present invention, the temporary pillar can be removed with a simple operation.

本発明の実施例1における仮設柱撤去の概要を説明する図である。It is a figure explaining the outline | summary of the temporary pillar removal in Example 1 of this invention. 本発明の実施例1における撤去機構の例を説明する図である。It is a figure explaining the example of the removal mechanism in Example 1 of this invention. 本発明の実施例1における撤去方法の例を説明する図である。It is a figure explaining the example of the removal method in Example 1 of this invention. 本発明の実施例2における撤去機構が設けられた仮設柱の例を説明する図である。It is a figure explaining the example of the temporary pillar provided with the removal mechanism in Example 2 of this invention. 本発明の実施例3における撤去機構が設けられた仮設柱の例を説明する図である。It is a figure explaining the example of the temporary pillar provided with the removal mechanism in Example 3 of this invention.

本発明の実施例1について、図1〜図3を参照して説明する。図1は、本発明の実施例1における仮設柱撤去の概要を説明する図である。図2は、本発明の実施例1における撤去機構の例を説明する図である。図3は、本発明の実施例1における撤去方法の例を説明する図である。 A first embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a diagram for explaining the outline of temporary pillar removal in the first embodiment of the present invention. FIG. 2 is a diagram illustrating an example of a removal mechanism in the first embodiment of the present invention. FIG. 3 is a diagram for explaining an example of the removal method according to the first embodiment of the present invention.

モジュール型プラントにおける仮設柱は、組み立てた後に上部梁から荷重を受けるため、そのままでは簡易に撤去することが困難である。そこで、本発明においては、仮設柱の一部に撤去機構を設けることにより、仮設柱が受ける荷重を開放して、仮設柱の撤去を容易にしている。実施例1においては、作業者が作業しやすい位置である仮設柱の途中に撤去機構を設けている。ここで、本発明において、モジュール型プラントとは、分割されている各モジュールを組立てて完成させるプラントをいう。このとき、分割されたモジュールは柱の数が不足して構造的に弱い部分ができるため、それを補強するために仮設柱を設けており、この仮設柱はプラント組立後撤去される。   The temporary pillar in the modular plant receives a load from the upper beam after assembling, so it is difficult to remove it as it is. Therefore, in the present invention, by providing a removal mechanism in a part of the temporary pillar, the load received by the temporary pillar is released, and the temporary pillar is easily removed. In Example 1, the removal mechanism is provided in the middle of the temporary pillar which is a position where an operator can work easily. Here, in the present invention, the modular plant refers to a plant that assembles and completes the divided modules. At this time, since the divided module has a structurally weak portion due to insufficient number of columns, a temporary column is provided to reinforce this, and this temporary column is removed after assembly of the plant.

以下、本発明の実施例1における仮設柱撤去の概要について図1を参照して説明する。図1(a)は、組立後のモジュール型プラントにおける仮設柱100を示している。仮設柱100は、上部柱150、下部柱160、および撤去機構10を含んでいる。仮設柱100の上部は上部柱150が上部梁30にボルト等により固定されこの上部梁30から荷重を受けている。仮設柱100の下部は下部柱160が下部梁40にボルト等により固定されている。そして、撤去機構10は上部柱150と下部柱160との間に設けられている。上部柱150の長さおよび下部柱160の長さは任意であるが、作業者が作業しやすい位置に撤去機構10が位置するように上部柱150の長さおよび下部柱160の長さを設定することが望ましい。そして、上部柱150の長さと撤去機構10におけるシムプレート11、12の厚みと下部柱160の長さとの合計が、上部梁30の下端から下部梁40の上端までの長さになるように、上部柱150の長さと撤去機構10におけるシムプレート11、12の厚みと下部柱160の長さとを設定する。   Hereinafter, the outline of temporary pillar removal in Example 1 of this invention is demonstrated with reference to FIG. Fig.1 (a) has shown the temporary pillar 100 in the modular plant after an assembly. The temporary pillar 100 includes an upper pillar 150, a lower pillar 160, and a removal mechanism 10. An upper column 150 is fixed to the upper beam 30 with bolts or the like at the upper part of the temporary column 100 and receives a load from the upper beam 30. A lower column 160 is fixed to the lower beam 40 with a bolt or the like at the lower portion of the temporary column 100. The removal mechanism 10 is provided between the upper column 150 and the lower column 160. The length of the upper column 150 and the length of the lower column 160 are arbitrary, but the length of the upper column 150 and the length of the lower column 160 are set so that the removal mechanism 10 is located at a position where an operator can easily work. It is desirable to do. Then, the total of the length of the upper column 150 and the thickness of the shim plates 11 and 12 in the removal mechanism 10 and the length of the lower column 160 is the length from the lower end of the upper beam 30 to the upper end of the lower beam 40. The length of the upper column 150, the thickness of the shim plates 11 and 12 in the removal mechanism 10, and the length of the lower column 160 are set.

撤去機構10はシムプレート11およびシムプレート12に荷重をかける状態で備えており、このシムプレート11およびシムプレート12を除去する(図1(b))ことで撤去機構10にスペースができる。つまり、上部梁30の下端から下部梁40の上端までの距離の方が、上部柱150の長さと下部柱160の長さとの合計よりも長くなる。このために仮設柱100にかかっていた荷重が開放される(図1(c))。荷重が開放された仮設柱100は、上部柱150および下部柱160ともに固定されていたボルト等を除去することにより容易に撤去することができる。 The removal mechanism 10 is provided in a state in which a load is applied to the shim plate 11 and the shim plate 12, and a space is created in the removal mechanism 10 by removing the shim plate 11 and the shim plate 12 (FIG. 1B). That is, the distance from the lower end of the upper beam 30 to the upper end of the lower beam 40 is longer than the sum of the length of the upper column 150 and the length of the lower column 160. For this reason, the load applied to the temporary pillar 100 is released (FIG. 1C). The temporary pillar 100 with the load released can be easily removed by removing the bolts and the like that are fixed to the upper pillar 150 and the lower pillar 160 together.

次に、撤去機構10について図2を参照して詳しく説明する。図2(a)は、仮設柱100における撤去機構10を説明する図であり、図2(b)は、撤去機構10におけるシムプレートを説明するA−A矢視図である。なお、以下の説明において、フランジ21に対向する部材を「対向部材」と称す。撤去機構10は、仮設柱100の上部柱150の最下部に設けたフランジ21と、フランジ21と対向部材との間にシムプレート11およびシムプレート12を挿入してなる荷重受け部141と、フランジ21と対向部材との間に接続ボルト17、18、19、20を螺合してなるシムプレート固定部142と、ジャッキボルト13、14、15、16のねじ部分の先端が対向部材を向くようにフランジ21に備えた雌ねじ部13S、14S、15S、16Sにジャッキボルト13、14、15、16を螺合させてなるジャッキアップ部140と、を備え、ジャッキボルト13、14、15、16のねじ部分の長さはフランジ21の厚みとシムプレート11、12の厚みとの和より長く、ジャッキボルト13、14、15、16のねじ部分の先端により対向部材を押圧可能であるように構成している。ここで、ジャッキボルト13、14、15、16はボルトで構成されている。   Next, the removal mechanism 10 will be described in detail with reference to FIG. FIG. 2A is a diagram illustrating the removal mechanism 10 in the temporary column 100, and FIG. 2B is a view taken along the line AA illustrating the shim plate in the removal mechanism 10. FIG. In the following description, a member that faces the flange 21 is referred to as a “facing member”. The removal mechanism 10 includes a flange 21 provided at the lowermost portion of the upper column 150 of the temporary column 100, a load receiving unit 141 formed by inserting the shim plate 11 and the shim plate 12 between the flange 21 and the opposing member, Shim plate fixing part 142 formed by screwing connection bolts 17, 18, 19, 20 between 21 and the opposing member, and the tips of the screw portions of jack bolts 13, 14, 15, 16 face the opposing member And a jack-up portion 140 in which the jack bolts 13, 14, 15, 16 are screwed to the female screw portions 13S, 14S, 15S, 16S provided in the flange 21, and the jack bolts 13, 14, 15, 16 The length of the screw portion is longer than the sum of the thickness of the flange 21 and the thickness of the shim plates 11, 12, and the screw portions of the jack bolts 13, 14, 15, 16 are It is configured to be pressed facing member by the end. Here, the jack bolts 13, 14, 15, and 16 are made of bolts.

ここで、実施例1におけるフランジ21に対向する部材(対向部材)とは、下部柱の最上部にある対向部材22を言い、フランジ21と対向する面積を有している。そして、フランジ21、シムプレート11、12、対向部材22が鉛直方向に並んで配置されている。また、接続ボルト17、18、19、20は、ボルトからなり、フランジ21および対向部材22に備えた挿通孔に挿通させた上で、ナット17N、18N、19N、20Nに螺合させている。   Here, the member (facing member) facing the flange 21 in the first embodiment refers to the facing member 22 at the top of the lower column, and has an area facing the flange 21. And the flange 21, the shim plates 11 and 12, and the opposing member 22 are arrange | positioned along with the perpendicular direction. The connection bolts 17, 18, 19, and 20 are bolts that are inserted through the insertion holes provided in the flange 21 and the opposing member 22, and are screwed into the nuts 17N, 18N, 19N, and 20N.

図2(b)に示すように、シムプレート11は、接続ボルト17、18の挿通位置に対応し、一端を開放した長穴11Aおよび11Bを備えた板材であり、シムプレート12は、接続ボルト19、20の挿通位置に対応し、一端を開放した長穴12Aおよび12Bを備えた板材である。この長穴11A、11B、12A、12Bを備えることにより、シムプレート11およびシムプレート12が、接続ボルト17、18、19、20の締め付け力を充分伝達させる面積を有する形状であるとともに、荷重受け部141に挿入又は除去しやすくなっている。シムプレート11およびシムプレート12の材質は限定するものではなく、鉄、アルミ、ステンレス等の金属や強化プラスチックなどの柱を支えるための強度があり変形の少ない材質を使用することができる。シムプレート11およびシムプレート12は同じ厚さを有している。また、シムプレート11およびシムプレート12の厚さは仮設柱が受ける荷重により適宜選択できる。つまり、シムプレート11およびシムプレート12を除去した場合における上部柱150の撓み量より大きければよく、シムプレート11およびシムプレート12の除去後にフランジ21と対向部材22の間にクリアランスが形成されればよい。   As shown in FIG. 2 (b), the shim plate 11 corresponds to the insertion position of the connection bolts 17 and 18, and is a plate material provided with elongated holes 11A and 11B whose one ends are opened. The shim plate 12 is a connection bolt. It is a board | plate material provided with the long holes 12A and 12B which corresponded to the insertion position of 19 and 20 and opened one end. By providing the elongated holes 11A, 11B, 12A, and 12B, the shim plate 11 and the shim plate 12 have a shape having a sufficient area to transmit the tightening force of the connecting bolts 17, 18, 19, and 20, and load receivers. It is easy to insert or remove from the portion 141. The material of the shim plate 11 and the shim plate 12 is not limited, and a material that has strength to support a pillar such as a metal such as iron, aluminum, and stainless steel or a reinforced plastic and is less deformable can be used. The shim plate 11 and the shim plate 12 have the same thickness. Further, the thickness of the shim plate 11 and the shim plate 12 can be appropriately selected depending on the load received by the temporary pillar. That is, it is sufficient that the amount of deflection of the upper column 150 when the shim plate 11 and the shim plate 12 are removed, and if a clearance is formed between the flange 21 and the opposing member 22 after the shim plate 11 and the shim plate 12 are removed. Good.

なお、実施例1においては、荷重受け部141に挿入するシムプレートをシムプレート11および12の2枚構成としたが、これに限定されるものではない。例えば、シムプレート11の長穴11Aおよび11Bの長さを接続ボルト19、20の挿通位置に対応する位置まで含むように長くして、シムプレート12を省略しシムプレート11のみの1枚構成としてもよい。また、各シムプレートを一つの接続ボルトの挿通位置に対応するサイズにして4枚構成としてもよい。さらに、長穴を設けることなく四角形等のシムプレートとして細分化された構成としてもよい。   In the first embodiment, the two shim plates 11 and 12 are configured as the shim plates to be inserted into the load receiving portion 141. However, the present invention is not limited to this. For example, the length of the long holes 11A and 11B of the shim plate 11 is increased so as to include the position corresponding to the insertion position of the connection bolts 19 and 20, and the shim plate 12 is omitted, and only one shim plate 11 is configured. Also good. Further, each shim plate may have a size corresponding to the insertion position of one connection bolt and may be configured as four plates. Furthermore, it is good also as a structure subdivided as shim plates, such as a square, without providing a long hole.

また、実施例1においては、接続ボルト17、18、19、20は、フランジ21および対向部材22に備えたそれぞれの挿通孔に挿通させた上で、ナット17N、18N、19N、20Nに螺合させる構成としたが、これに限定されるものではなく、適宜その構成は変更が可能である。例えば、接続ボルト17、18、19、20を螺合させる方向をフランジ21から対向部材22に向ける方向としてもよいし、対向部材22からフランジ21に向ける方向としてもよい。また、フランジを下部柱160の最上部に設けて、上部柱150の最下部における対向部材に向けて下からジャッキアップする構成にしてもよい。   In the first embodiment, the connection bolts 17, 18, 19, and 20 are screwed into the nuts 17N, 18N, 19N, and 20N after being inserted through the insertion holes provided in the flange 21 and the opposing member 22, respectively. However, the present invention is not limited to this configuration, and the configuration can be changed as appropriate. For example, the direction in which the connection bolts 17, 18, 19, and 20 are screwed may be a direction from the flange 21 toward the facing member 22, or may be a direction from the facing member 22 toward the flange 21. Alternatively, a flange may be provided at the uppermost part of the lower column 160 and jacked up from below toward the opposing member at the lowermost part of the upper column 150.

また、実施例1における雌ねじ部13S、14S、15S、16Sは、図2(a)に示すようにフランジ21の下面にナットを溶接して設けている。しかし、これに限定するものではなく、適宜変更することが可能である。例えば、フランジ21の上面にナットを強度のある溶接をして設けてもよいし、フランジ21の孔に雌ねじを形成してもよい。   Further, the female screw portions 13S, 14S, 15S, and 16S in the first embodiment are provided by welding nuts to the lower surface of the flange 21 as shown in FIG. However, the present invention is not limited to this, and can be changed as appropriate. For example, a nut may be provided on the upper surface of the flange 21 with strong welding, or a female screw may be formed in the hole of the flange 21.

また、実施例1においては、接続ボルトの数を4本とし、ジャッキボルトの数を4本としたが、必ずしもこれに限定されるものではなく、荷重の大きさや撤去機構の都合により適宜変更できる。例えば、接続ボルトおよびジャッキボルトの数を2本としてもよいし、5本以上としてもよい。   In the first embodiment, the number of connection bolts is four and the number of jack bolts is four. However, the number of connection bolts is not necessarily limited to this, and can be appropriately changed depending on the size of the load and the convenience of the removal mechanism. . For example, the number of connection bolts and jack bolts may be two, or five or more.

次に、実施例1における仮設柱の撤去方法について、図3を参照して説明する。プラントのモジュールが組み立てられた状態では、上部柱150と下部柱160との間に撤去機構10が設けられ、接続ボルト17、18、19、20がナット17N、18N、19N、20Nに螺嵌されてシムプレート固定部142が形成されている(図3(a))。そして、上部梁30(図1参照)からの荷重を受け、シムプレート11、12(図2(b)参照)が荷重受け部141を形成している。   Next, the removal method of the temporary pillar in Example 1 is demonstrated with reference to FIG. In a state where the module of the plant is assembled, the removal mechanism 10 is provided between the upper column 150 and the lower column 160, and the connection bolts 17, 18, 19, and 20 are screwed into the nuts 17N, 18N, 19N, and 20N. Thus, a shim plate fixing portion 142 is formed (FIG. 3A). The shim plates 11 and 12 (see FIG. 2B) receive the load from the upper beam 30 (see FIG. 1) and form the load receiving portion 141.

まず、接続ボルト17、18、19、20(図2(a)、(b)参照)とナット17N、18N、19N、20N(図2(a)参照、但し、ナット19N、20Nは図示せず)との締め付けを緩めて、図3(b)に示すクリアランスAのような隙間をつくる。次に、ジャッキボルト13、14、15、16の螺合を締め付けて、そのねじ部分先端を対向部材22に対して押圧する。この押圧により、フランジ21とシムプレート11、12との間にクリアランスBを得る(図3(b))。これで、フランジ21と対向部材22との間にシムプレート11、12の厚さよりも大きいスペースが形成されて、シムプレート11、12にかかる荷重は開放され、シムプレート11、12は容易に除去可能の状態となる。   First, connection bolts 17, 18, 19, and 20 (see FIGS. 2A and 2B) and nuts 17N, 18N, 19N, and 20N (see FIG. 2A), but nuts 19N and 20N are not shown. ) Is loosened to create a clearance such as a clearance A shown in FIG. Next, the screwing of the jack bolts 13, 14, 15, 16 is tightened, and the tip of the screw portion is pressed against the opposing member 22. By this pressing, a clearance B is obtained between the flange 21 and the shim plates 11 and 12 (FIG. 3B). As a result, a space larger than the thickness of the shim plates 11 and 12 is formed between the flange 21 and the opposing member 22, the load applied to the shim plates 11 and 12 is released, and the shim plates 11 and 12 are easily removed. It becomes possible.

次に、シムプレート11、12を荷重受け部141から引き抜くことで除去する(図3(c))。次に、ナット17N、18N、19N、20Nをさらに緩めて、接続ボルト17、18、19、20を除去する。そうすると、上部柱150および下部柱160が容易に除去可能となるので、これらを除去して、仮設柱100の撤去を完了する。   Next, the shim plates 11 and 12 are removed by being pulled out from the load receiving portion 141 (FIG. 3C). Next, the nuts 17N, 18N, 19N, and 20N are further loosened, and the connecting bolts 17, 18, 19, and 20 are removed. As a result, the upper column 150 and the lower column 160 can be easily removed, so that these are removed and the removal of the temporary column 100 is completed.

なお、実施例1においては、シムプレート11、12を除去してから接続ボルト17、18、19、20を除去するようにしたが、必ずしもこれに限定されず、適宜変更が可能である。例えば、先に接続ボルト17、18、19、20を除去してからシムプレート11、12を除去してもよい。この場合は、シムプレート11、12に長穴11A、11B、12A、12Bがなくても除去でき、シンプルな形状のシムプレートとすることができる。   In the first embodiment, the connection bolts 17, 18, 19, and 20 are removed after the shim plates 11 and 12 are removed. However, the present invention is not necessarily limited to this, and can be changed as appropriate. For example, the shim plates 11 and 12 may be removed after the connection bolts 17, 18, 19 and 20 are removed first. In this case, the shim plates 11 and 12 can be removed without the long holes 11A, 11B, 12A, and 12B, and a shim plate having a simple shape can be obtained.

以上のように、本発明の実施例1においては、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱を撤去するために当該仮設柱に備えた撤去機構であって、
フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であることを特徴とする撤去機構により、仮設柱の撤去を簡易な作業で行えるようにすることができる。
As described above, in the first embodiment of the present invention, the removal provided for the temporary column in order to remove the temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant. Mechanism,
A flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the removing member is capable of pressing the opposing member by the tip of the screw portion of the jack bolt. Thus, the temporary pillar can be removed by a simple operation.

また、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱であって、
前記仮設柱は、撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であることを特徴とする仮設柱により、仮設柱の撤去を簡易な作業で行えるようにすることができる。
Also, a temporary pillar provided between the lower beam to support the load from the upper beam in the modular plant,
The temporary pillar has a removal mechanism,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the temporary column can press the opposing member by the tip of the screw portion of the jack bolt. Thus, the temporary pillar can be removed by a simple operation.

さらに、モジュール型プラントにおける上部梁からの荷重を受けて下部梁との間に設けられてなる仮設柱を撤去する撤去方法であって、
前記仮設柱は撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記接続ボルトを緩め、前記ジャッキボルトを螺嵌して前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧して、前記フランジと前記対向部材との間に前記シムプレートの厚さよりも大きいスペースを形成した後、前記シムプレートを除去し、前記仮設柱を撤去することを特徴とする撤去方法により、仮設柱の撤去を簡易な作業で行えるようにすることができる。
Furthermore, it is a removal method for removing a temporary pillar provided between the lower beam in response to a load from the upper beam in a modular plant,
The temporary pillar has a removal mechanism;
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the opposing member can be pressed by the tip of the screw portion of the jack bolt,
A space larger than the thickness of the shim plate between the flange and the opposing member by loosening the connecting bolt, screwing the jack bolt, and pressing the opposing member with the tip of the screw portion of the jack bolt After the formation, the temporary plate can be removed by a simple operation by a removal method characterized by removing the shim plate and removing the temporary column.

本発明の実施例2は、撤去機構を仮設柱の最上部に設けた点で、実施例1と異なっている。以下、図4を参照して実施例2について説明する。図4は、本発明の実施例2における撤去機構が設けられた仮設柱の例を説明する図である。   The second embodiment of the present invention is different from the first embodiment in that the removal mechanism is provided at the uppermost part of the temporary pillar. Hereinafter, Example 2 will be described with reference to FIG. FIG. 4 is a diagram illustrating an example of a temporary column provided with a removal mechanism according to the second embodiment of the present invention.

図4に示すように、撤去機構210が仮設柱200の最上部に設けられている。撤去機構210は、実施例1における撤去機構10と同様であるが、フランジに対向する部材(対向部材)は上部梁30における部材であり、ジャッキボルトが仮設柱最上部のフランジから上部梁30に向けた構成となっている。そして、上部梁30とジャッキボルトのねじ部分先端との間、および上部梁30とシムプレートとの間には上部梁30を保護する保護プレート220が設けられている。保護プレート220は板材からなり、その材質は任意であるが、鉄、アルミ、ステンレス等の金属や強化プラスチックなどの柱を支えるための強度があり変形の少ない材質を採用することができる。また、保護プレート220の大きさは、少なくともジャッキボルトのねじ部先端による押圧点全てとシムプレートとを含む大きさであればよく、厚さはジャッキボルトのねじ部先端が押圧されても上部梁30を傷つけず保護できる厚さであればよい。   As shown in FIG. 4, the removal mechanism 210 is provided on the uppermost part of the temporary pillar 200. The removal mechanism 210 is the same as the removal mechanism 10 in the first embodiment, but the member (opposing member) facing the flange is a member in the upper beam 30, and the jack bolt extends from the flange at the top of the temporary column to the upper beam 30. It is the composition for. A protective plate 220 that protects the upper beam 30 is provided between the upper beam 30 and the screw portion tip of the jack bolt and between the upper beam 30 and the shim plate. The protection plate 220 is made of a plate material, and the material thereof is arbitrary, but a material having strength and less deformation for supporting a pillar such as a metal such as iron, aluminum or stainless steel or reinforced plastic can be used. Further, the size of the protection plate 220 may be a size that includes at least all of the pressing points by the screw bolt tip and the shim plate, and the thickness of the protective plate 220 is not limited even if the screw bolt tip is pressed. Any thickness that can protect 30 without damaging it is acceptable.

実施例2においても、撤去に際しては、接続ボルトを緩め、ジャッキボルトを螺嵌してねじ部分の先端により上部梁30における部材を押圧し、フランジとフランジに対向する上部梁30における部材との間にシムプレートの厚さよりも大きいスペースを形成した後、シムプレートを除去し仮設柱200が荷重を受けないようにして、仮設柱200を撤去する。   Also in the second embodiment, when removing, the connection bolt is loosened, the jack bolt is screwed and the member in the upper beam 30 is pressed by the tip of the threaded portion, and the flange and the member in the upper beam 30 facing the flange are between. After the space larger than the thickness of the shim plate is formed, the shim plate is removed so that the temporary column 200 is not subjected to a load, and the temporary column 200 is removed.

以上のように、実施例2においては、撤去機構を最上部に設けた仮設柱とすることにより、上部柱および下部柱を不要にできるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。   As described above, in the second embodiment, the removal mechanism is a temporary column provided at the uppermost portion, so that the upper column and the lower column can be made unnecessary, and the temporary column can be removed by a simple operation. be able to.

本発明の実施例3は、撤去機構を仮設柱の最下部に設けた点で、実施例1と異なっている。以下、図5を参照して実施例3について説明する。図5は、本発明の実施例3における撤去機構が設けられた仮設柱の例を説明する図である。   The third embodiment of the present invention differs from the first embodiment in that a removal mechanism is provided at the lowermost part of the temporary column. Hereinafter, Example 3 will be described with reference to FIG. FIG. 5 is a diagram for explaining an example of a temporary column provided with a removal mechanism according to the third embodiment of the present invention.

図5に示すように、撤去機構310が仮設柱300の最下部に設けられている。撤去機構310は、実施例1における撤去機構10と同様であるが、フランジに対向する部材(対向部材)が下部梁40における部材であり、ジャッキボルトが仮設柱最下部のフランジから下部梁40に向けた構成となっている。そして、下部梁40とジャッキボルトのねじ部分先端との間、および下部梁40とシムプレートとの間には保護プレート320が設けられている。保護プレートは板材からなり、その材質は任意であるが、鉄、アルミ、ステンレス等の金属や強化プラスチックなどの柱を支えるための強度があり変形の少ない材質を採用することができる。また、保護プレートの大きさは、少なくともジャッキボルトのねじ部先端による押圧点全てとシムプレートとを含む大きさであればよく、厚さはジャッキボルトのねじ部先端が押圧されても下部梁40を傷つけず保護できる厚さであればよい。   As shown in FIG. 5, a removal mechanism 310 is provided at the lowermost part of the temporary pillar 300. The removal mechanism 310 is the same as the removal mechanism 10 in the first embodiment, but a member (opposing member) facing the flange is a member in the lower beam 40, and the jack bolt extends from the lowermost flange of the temporary column to the lower beam 40. It is the composition for. A protective plate 320 is provided between the lower beam 40 and the screw portion tip of the jack bolt and between the lower beam 40 and the shim plate. The protective plate is made of a plate material, and the material thereof is arbitrary. However, a material that has strength to support a pillar such as a metal such as iron, aluminum, and stainless steel or a reinforced plastic and that is less deformed can be used. Further, the size of the protective plate may be a size that includes at least all the pressing points by the screw bolt tip of the jack bolt and the shim plate, and the thickness is low even if the screw bolt tip of the jack bolt is pressed. Any thickness can be used as long as it can be protected without being damaged.

実施例3においても、撤去に際しては、接続ボルトを緩め、ジャッキボルトを螺嵌してねじ部分の先端により下部梁40における部材を押圧して、フランジとフランジに対向する下部梁40における部材との間にシムプレートの厚さよりも大きいスペースを形成した後、シムプレートを除去し仮設柱300が荷重を受けないようにして、仮設柱300を撤去する。   Also in the third embodiment, when removing, the connection bolt is loosened, the jack bolt is screwed and the member in the lower beam 40 is pressed by the tip of the screw portion, and the flange and the member in the lower beam 40 facing the flange are connected. After a space larger than the thickness of the shim plate is formed therebetween, the shim plate is removed so that the temporary column 300 does not receive a load, and the temporary column 300 is removed.

以上のように、実施例3においては、撤去機構を最下部に設けた仮設柱とすることにより、上部柱および下部柱を不要にできるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。   As described above, in the third embodiment, the removal mechanism is a temporary column provided at the lowermost portion, so that the upper column and the lower column can be made unnecessary and the temporary column can be removed by a simple operation. be able to.

本発明における撤去機構、仮設柱、および撤去方法は、モジュール型プラントの分野に広く用いることができる。 The removal mechanism, temporary column, and removal method in the present invention can be widely used in the field of modular plants.

10:撤去機構 11:シムプレート 12:シムプレート11A:長穴 11B:長穴 12A:長穴 12B:長穴13:ジャッキボルト 14:ジャッキボルト 15:ジャッキボルト 16:ジャッキボルト13S:雌ねじ部 14S:雌ねじ部 15S:雌ねじ部 16S:雌ねじ部17:接続ボルト 18:接続ボルト 19:接続ボルト 20:接続ボルト17N:ナット 18N:ナット 19N:ナット 20N:ナット21:フランジ 22:フランジに対向する部材(対向部材)30:上部梁 40:下部梁
100:仮設柱 140:ジャッキアップ部 141:荷重受け部
142:シムプレート固定部
150:上部柱 160:下部柱
200:仮設柱 210:撤去機構 220:保護プレート
300:仮設柱 310:撤去機構 320:保護プレート
10: Removal mechanism 11: Shim plate 12: Shim plate 11A: Slotted hole 11B: Slotted hole 12A: Slotted hole 12B: Slotted hole 13: Jack bolt 14: Jack bolt 15: Jack bolt 16: Jack bolt 13S: Female thread portion 14S: Female thread portion 15S: Female thread portion 16S: Female thread portion 17: Connection bolt 18: Connection bolt 19: Connection bolt 20: Connection bolt 17N: Nut 18N: Nut 19N: Nut 20N: Nut 21: Flange 22: Member facing the flange (opposite) 30) Upper beam 40: Lower beam 100: Temporary column 140: Jack-up portion 141: Load receiving portion 142: Shim plate fixing portion 150: Upper column 160: Lower column 200: Temporary column 210: Removal mechanism 220: Protection plate 300: Temporary pillar 310: Removal mechanism 320: Protection play

Claims (7)

モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱を撤去するために、当該仮設柱にかかる荷重を開放する撤去機構であって、
フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする撤去機構。
In order to remove the temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant, a removal mechanism that releases the load applied to the temporary column ,
A flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
The removal mechanism characterized in that the load applied to the temporary column can be released by removing the shim plate from the load receiving portion .
前記シムプレートは、前記接続ボルトの挿通位置に対応し、一端を開放した長穴を備えたことを特徴とする請求項1に記載の撤去機構。   2. The removal mechanism according to claim 1, wherein the shim plate includes an elongated hole corresponding to an insertion position of the connection bolt and having one end opened. モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱であって、
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする仮設柱。
A temporary pillar provided between the lower beam and supporting the load from the upper beam in the modular plant,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
The temporary pillar, wherein the load applied to the temporary pillar can be released by removing the shim plate from the load receiving portion .
上部柱と下部柱とを有し、前記上部柱と前記下部柱との間に前記撤去機構を備え、前記対向部材は前記下部柱の最上部における部材であることを特徴とする請求項3に記載の仮設柱。   The upper column and the lower column are provided, the removal mechanism is provided between the upper column and the lower column, and the opposing member is a member at the uppermost part of the lower column. Temporary pillar described. 最上部に前記撤去機構を備え、前記対向部材は前記上部梁における部材であることを特徴とする請求項3に記載の仮設柱。   The temporary column according to claim 3, wherein the removal mechanism is provided at an uppermost portion, and the facing member is a member in the upper beam. 最下部に前記撤去機構を備え、前記対向部材は前記下部梁における部材であることを特徴とする請求項3に記載の仮設柱。   The temporary column according to claim 3, wherein the removal mechanism is provided at a lowermost part, and the opposing member is a member in the lower beam. モジュール型プラントにおける上部梁からの荷重を受けて下部梁との間に設けられてなる仮設柱を撤去する撤去方法であって、
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記接続ボルトを緩め、前記ジャッキボルトを螺嵌して前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧して、前記フランジと前記対向部材との間に前記シムプレートの厚さよりも大きいスペースを形成した後、前記シムプレートを除去し、前記仮設柱を撤去することを特徴とする撤去方法。
A removal method for receiving a load from an upper beam in a modular plant and removing a temporary pillar provided between the lower beam,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the opposing member can be pressed by the tip of the screw portion of the jack bolt,
A space larger than the thickness of the shim plate between the flange and the opposing member by loosening the connecting bolt, screwing the jack bolt, and pressing the opposing member with the tip of the screw portion of the jack bolt The removal method is characterized by removing the shim plate and removing the temporary pillar after forming.
JP2016127125A 2016-06-28 2016-06-28 Removal mechanism, temporary pillar, and removal method Active JP6566481B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016127125A JP6566481B2 (en) 2016-06-28 2016-06-28 Removal mechanism, temporary pillar, and removal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016127125A JP6566481B2 (en) 2016-06-28 2016-06-28 Removal mechanism, temporary pillar, and removal method

Publications (2)

Publication Number Publication Date
JP2018003288A JP2018003288A (en) 2018-01-11
JP6566481B2 true JP6566481B2 (en) 2019-08-28

Family

ID=60945870

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016127125A Active JP6566481B2 (en) 2016-06-28 2016-06-28 Removal mechanism, temporary pillar, and removal method

Country Status (1)

Country Link
JP (1) JP6566481B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102417709B1 (en) * 2020-07-17 2022-07-05 김동산 Apparatus and method for construction of slab which concrete build using euroform

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0748890Y2 (en) * 1989-09-20 1995-11-08 岡部株式会社 Temporary columns for formwork support
JPH03113058U (en) * 1990-03-05 1991-11-19
US6425712B1 (en) * 2000-09-07 2002-07-30 Liftplate International Method and apparatus for providing lateral support to a post
JP2002276525A (en) * 2001-03-19 2002-09-25 Kansai Electric Power Co Inc:The Hydraulic machine and upper cover level adjustment method
JP2014084201A (en) * 2012-10-23 2014-05-12 Hitachi Building Systems Co Ltd Handrail structure of passenger conveyor and handrail installation method

Also Published As

Publication number Publication date
JP2018003288A (en) 2018-01-11

Similar Documents

Publication Publication Date Title
CN102333625A (en) Method for producing concrete trestle, concrete trestle, and connecting member
US12258938B2 (en) Transporting a wind turbine component
JP6818401B2 (en) Connection structure using box-shaped hardware
JP6566481B2 (en) Removal mechanism, temporary pillar, and removal method
CN204715225U (en) A kind of bridge jacking platform based on steel hoop
KR100949894B1 (en) Turn-over method using turn-over fixture of hopper block
KR101048570B1 (en) Sectional Configuration Method of Monorail Crane Girder
CN108914763B (en) Application method of bridge closure stiffness framework quick locking device
WO2021067615A1 (en) Rolling block restraint connector having an improved linkage assembly
JP2017014730A (en) Beam material load bearing structure and beam material repair method
JP7160575B2 (en) Structure and construction method of structure
JP7386515B2 (en) Scaffold construction set and method for constructing scaffolding
SE524073C2 (en) Beam connection system, comprises fastener plates secured to beams and joined together via fixing parts
DE102008045478B4 (en) Clamping block and system of clamping blocks
KR102147059B1 (en) Steel structure supporting assembly and breast wall construction method using thereof
KR200470260Y1 (en) Anchor Bolt System
KR100914717B1 (en) strengthening notch-plate.
JP2019007134A (en) Reinforcing existing footing
JP6696814B2 (en) Construction method of connection member for transportation and unit building
JP6792338B2 (en) Wood structural material reinforcement structure
KR102160937B1 (en) Coupling device and method for preformed bar arrangement using threaded reinforcing bars
JP6604650B2 (en) Retaining wall formwork fixed hardware
JP6467202B2 (en) Steel tower main column replacement method
CN217840352U (en) Threaded connection embedded part
JP4871654B2 (en) Connector

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180206

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20181228

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190206

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190725

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190725

R150 Certificate of patent or registration of utility model

Ref document number: 6566481

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250