JP6566481B2 - Removal mechanism, temporary pillar, and removal method - Google Patents
Removal mechanism, temporary pillar, and removal method Download PDFInfo
- Publication number
- JP6566481B2 JP6566481B2 JP2016127125A JP2016127125A JP6566481B2 JP 6566481 B2 JP6566481 B2 JP 6566481B2 JP 2016127125 A JP2016127125 A JP 2016127125A JP 2016127125 A JP2016127125 A JP 2016127125A JP 6566481 B2 JP6566481 B2 JP 6566481B2
- Authority
- JP
- Japan
- Prior art keywords
- flange
- shim plate
- temporary
- column
- removal mechanism
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
本発明は、モジュール型プラントにおける仮設柱の撤去機構、仮設柱、および撤去方法に関するものである。 The present invention relates to a temporary pillar removal mechanism, a temporary pillar, and a removal method in a modular plant.
プラントを製作工場から据付地に輸送する際に、完成したプラントを複数のモジュールに分解して輸送し、据付地にて再度各モジュールを組み立てることが行われている。このとき、複数のモジュールに分解したことにより、柱の数が不足する等構造的に弱い部分ができる。この構造的弱点を補強するために仮設柱を設けて輸送することが行われている。この場合、モジュール組立後にこの仮設柱を撤去することが必要となる。 When a plant is transported from a manufacturing factory to an installation site, the completed plant is disassembled into a plurality of modules and transported, and each module is assembled again at the installation site. At this time, by disassembling into a plurality of modules, a structurally weak portion such as the number of pillars is insufficient. In order to reinforce this structural weakness, a temporary pillar is provided and transported. In this case, it is necessary to remove the temporary pillar after assembling the module.
プラントには、複数の縦梁および横梁により支持された重量機械を内蔵しているため、モジュール組立後には仮設柱にそれらの荷重がかかる。したがって仮設柱撤去時には、その荷重を開放させて撤去しなければならず容易な作業ではない。従来は、クレーンでプラントを吊り下げて仮設柱にかかる荷重をなくした状態で仮設柱を撤去するか、強引に仮設柱を切断して撤去する方法が実施されている。しかしながら、このような方法は手間がかかるという問題があった。 Since the plant incorporates a heavy machine supported by a plurality of vertical beams and horizontal beams, these loads are applied to the temporary columns after module assembly. Therefore, when removing the temporary pillar, the load must be released and removed, which is not an easy task. Conventionally, a method of suspending a plant with a crane and removing the temporary pillar in a state where a load applied to the temporary pillar is eliminated, or forcibly cutting and removing the temporary pillar has been implemented. However, such a method has a problem that it takes time.
特許文献1には、完成したプラントを多数のモジュールに分割して輸送し、外国における所定位置において各モジュールを組み立てるプラント建設の構成が記載されている。 Patent Document 1 describes a configuration of plant construction in which a completed plant is divided into a large number of modules and transported, and each module is assembled at a predetermined position in a foreign country.
特許文献1:特開昭60−80628号公報 Patent Document 1: Japanese Patent Laid-Open No. 60-80628
しかしながら、特許文献1記載のものは、複数のモジュールに分割した後の構造的弱点を補強する仮設柱については記載がなく、仮設柱の要否や撤去方法については不明である。このため、現在まで、荷重がかかっている仮設柱の撤去を簡易に行うことが困難であるという問題があった。 However, the thing of patent document 1 does not describe about the temporary pillar which reinforces the structural weak point after dividing | segmenting into several modules, and the necessity of a temporary pillar and the removal method are unknown. For this reason, until now, there has been a problem that it is difficult to easily remove the temporary columns that are under load.
本発明は、上記問題点を解決して、仮設柱の撤去を簡易な作業で行えるようにすることを課題とする。 This invention makes it a subject to solve the said problem and to be able to remove a temporary pillar by simple operation | work.
上記課題を解決するために本発明は、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱を撤去するために、当該仮設柱にかかる荷重を開放する撤去機構であって、
フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする撤去機構を提供するものである。
In order to solve the above problems, the present invention releases the load applied to the temporary column in order to remove the temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant. A removal mechanism,
A flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
It is an object of the present invention to provide a removal mechanism characterized in that the load applied to the temporary column can be released by removing the shim plate from the load receiving portion .
この構成により、ジャッキアップ部でジャッキアップし、シムプレートを除去することにより荷重を開放することができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the load can be released by jacking up at the jackup portion and removing the shim plate, and the temporary pillar can be removed with a simple operation.
前記シムプレートは、前記接続ボルトの挿通位置に対応し、一端を開放した長穴を備えるように構成してもよい。 The shim plate may correspond to the insertion position of the connection bolt and may be configured to have an elongated hole with one end opened.
この構成より、シムプレートの挿入および除去を容易にし、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the shim plate can be easily inserted and removed, and the temporary pillar can be removed with a simple operation.
また、上記課題を解決するために本発明は、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱であって、
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする仮設柱を提供するものである。
In order to solve the above problems, the present invention is a temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
The present invention provides a temporary column, wherein the load applied to the temporary column can be released by removing the shim plate from the load receiving portion .
この構成により、ジャッキアップ部でジャッキアップし、シムプレートを除去することにより荷重を開放することができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the load can be released by jacking up at the jackup portion and removing the shim plate, and the temporary pillar can be removed with a simple operation.
上部柱と下部柱とを有し、前記上部柱と前記下部柱との間に前記撤去機構を備え、前記対向部材は前記下部柱の最上部における部材である構成としてもよい。 An upper column and a lower column may be provided, the removal mechanism may be provided between the upper column and the lower column, and the opposing member may be a member at the uppermost portion of the lower column.
この構成により、作業者が作業しやすい位置に撤去機構を設けることができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the removal mechanism can be provided at a position where the worker can easily work, and the temporary pillar can be removed with a simple work.
最上部に前記撤去機構を備え、前記対向部材は前記上部梁における部材である構成としてもよい。 The removal mechanism may be provided on the top, and the opposing member may be a member in the upper beam.
この構成により、仮設柱を上部柱と下部柱とに分ける必要がなくなるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, it is not necessary to divide the temporary column into an upper column and a lower column, and it is possible to remove the temporary column with a simple operation.
最下部に前記撤去機構を備え、前記対向部材は前記下部梁における部材である構成としてもよい。 It is good also as a structure which equips the lowest part with the said removal mechanism and the said opposing member is a member in the said lower beam.
この構成により、仮設柱を上部柱と下部柱とに分ける必要がなくなるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, it is not necessary to divide the temporary column into an upper column and a lower column, and it is possible to remove the temporary column with a simple operation.
さらに、上記課題を解決するために本発明は、モジュール型プラントにおける上部梁からの荷重を受けて下部梁との間に設けられてなる仮設柱を撤去する撤去方法であって、
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記接続ボルトを緩め、前記ジャッキボルトを螺嵌して前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧して、前記フランジと前記対向部材との間に前記シムプレートの厚さよりも大きいスペースを形成した後、前記シムプレートを除去し、前記仮設柱を撤去することを特徴とする撤去方法を提供するものである。
Furthermore, in order to solve the above-mentioned problem, the present invention is a removal method for removing a temporary column provided between a lower beam and receiving a load from an upper beam in a modular plant,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the opposing member can be pressed by the tip of the screw portion of the jack bolt,
A space larger than the thickness of the shim plate between the flange and the opposing member by loosening the connecting bolt, screwing the jack bolt, and pressing the opposing member with the tip of the screw portion of the jack bolt Then, the shim plate is removed and the temporary pillar is removed, thereby providing a removal method.
この構成により、ジャッキアップ部でジャッキアップし、シムプレートを除去することにより荷重を開放することができ、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With this configuration, the load can be released by jacking up at the jackup portion and removing the shim plate, and the temporary pillar can be removed with a simple operation.
本発明の撤去機構、仮設柱、および撤去方法により、仮設柱の撤去を簡易な作業で行えるようにすることができる。 With the removal mechanism, the temporary pillar, and the removal method of the present invention, the temporary pillar can be removed with a simple operation.
本発明の実施例1について、図1〜図3を参照して説明する。図1は、本発明の実施例1における仮設柱撤去の概要を説明する図である。図2は、本発明の実施例1における撤去機構の例を説明する図である。図3は、本発明の実施例1における撤去方法の例を説明する図である。 A first embodiment of the present invention will be described with reference to FIGS. FIG. 1 is a diagram for explaining the outline of temporary pillar removal in the first embodiment of the present invention. FIG. 2 is a diagram illustrating an example of a removal mechanism in the first embodiment of the present invention. FIG. 3 is a diagram for explaining an example of the removal method according to the first embodiment of the present invention.
モジュール型プラントにおける仮設柱は、組み立てた後に上部梁から荷重を受けるため、そのままでは簡易に撤去することが困難である。そこで、本発明においては、仮設柱の一部に撤去機構を設けることにより、仮設柱が受ける荷重を開放して、仮設柱の撤去を容易にしている。実施例1においては、作業者が作業しやすい位置である仮設柱の途中に撤去機構を設けている。ここで、本発明において、モジュール型プラントとは、分割されている各モジュールを組立てて完成させるプラントをいう。このとき、分割されたモジュールは柱の数が不足して構造的に弱い部分ができるため、それを補強するために仮設柱を設けており、この仮設柱はプラント組立後撤去される。 The temporary pillar in the modular plant receives a load from the upper beam after assembling, so it is difficult to remove it as it is. Therefore, in the present invention, by providing a removal mechanism in a part of the temporary pillar, the load received by the temporary pillar is released, and the temporary pillar is easily removed. In Example 1, the removal mechanism is provided in the middle of the temporary pillar which is a position where an operator can work easily. Here, in the present invention, the modular plant refers to a plant that assembles and completes the divided modules. At this time, since the divided module has a structurally weak portion due to insufficient number of columns, a temporary column is provided to reinforce this, and this temporary column is removed after assembly of the plant.
以下、本発明の実施例1における仮設柱撤去の概要について図1を参照して説明する。図1(a)は、組立後のモジュール型プラントにおける仮設柱100を示している。仮設柱100は、上部柱150、下部柱160、および撤去機構10を含んでいる。仮設柱100の上部は上部柱150が上部梁30にボルト等により固定されこの上部梁30から荷重を受けている。仮設柱100の下部は下部柱160が下部梁40にボルト等により固定されている。そして、撤去機構10は上部柱150と下部柱160との間に設けられている。上部柱150の長さおよび下部柱160の長さは任意であるが、作業者が作業しやすい位置に撤去機構10が位置するように上部柱150の長さおよび下部柱160の長さを設定することが望ましい。そして、上部柱150の長さと撤去機構10におけるシムプレート11、12の厚みと下部柱160の長さとの合計が、上部梁30の下端から下部梁40の上端までの長さになるように、上部柱150の長さと撤去機構10におけるシムプレート11、12の厚みと下部柱160の長さとを設定する。
Hereinafter, the outline of temporary pillar removal in Example 1 of this invention is demonstrated with reference to FIG. Fig.1 (a) has shown the
撤去機構10はシムプレート11およびシムプレート12に荷重をかける状態で備えており、このシムプレート11およびシムプレート12を除去する(図1(b))ことで撤去機構10にスペースができる。つまり、上部梁30の下端から下部梁40の上端までの距離の方が、上部柱150の長さと下部柱160の長さとの合計よりも長くなる。このために仮設柱100にかかっていた荷重が開放される(図1(c))。荷重が開放された仮設柱100は、上部柱150および下部柱160ともに固定されていたボルト等を除去することにより容易に撤去することができる。
The
次に、撤去機構10について図2を参照して詳しく説明する。図2(a)は、仮設柱100における撤去機構10を説明する図であり、図2(b)は、撤去機構10におけるシムプレートを説明するA−A矢視図である。なお、以下の説明において、フランジ21に対向する部材を「対向部材」と称す。撤去機構10は、仮設柱100の上部柱150の最下部に設けたフランジ21と、フランジ21と対向部材との間にシムプレート11およびシムプレート12を挿入してなる荷重受け部141と、フランジ21と対向部材との間に接続ボルト17、18、19、20を螺合してなるシムプレート固定部142と、ジャッキボルト13、14、15、16のねじ部分の先端が対向部材を向くようにフランジ21に備えた雌ねじ部13S、14S、15S、16Sにジャッキボルト13、14、15、16を螺合させてなるジャッキアップ部140と、を備え、ジャッキボルト13、14、15、16のねじ部分の長さはフランジ21の厚みとシムプレート11、12の厚みとの和より長く、ジャッキボルト13、14、15、16のねじ部分の先端により対向部材を押圧可能であるように構成している。ここで、ジャッキボルト13、14、15、16はボルトで構成されている。
Next, the
ここで、実施例1におけるフランジ21に対向する部材(対向部材)とは、下部柱の最上部にある対向部材22を言い、フランジ21と対向する面積を有している。そして、フランジ21、シムプレート11、12、対向部材22が鉛直方向に並んで配置されている。また、接続ボルト17、18、19、20は、ボルトからなり、フランジ21および対向部材22に備えた挿通孔に挿通させた上で、ナット17N、18N、19N、20Nに螺合させている。
Here, the member (facing member) facing the
図2(b)に示すように、シムプレート11は、接続ボルト17、18の挿通位置に対応し、一端を開放した長穴11Aおよび11Bを備えた板材であり、シムプレート12は、接続ボルト19、20の挿通位置に対応し、一端を開放した長穴12Aおよび12Bを備えた板材である。この長穴11A、11B、12A、12Bを備えることにより、シムプレート11およびシムプレート12が、接続ボルト17、18、19、20の締め付け力を充分伝達させる面積を有する形状であるとともに、荷重受け部141に挿入又は除去しやすくなっている。シムプレート11およびシムプレート12の材質は限定するものではなく、鉄、アルミ、ステンレス等の金属や強化プラスチックなどの柱を支えるための強度があり変形の少ない材質を使用することができる。シムプレート11およびシムプレート12は同じ厚さを有している。また、シムプレート11およびシムプレート12の厚さは仮設柱が受ける荷重により適宜選択できる。つまり、シムプレート11およびシムプレート12を除去した場合における上部柱150の撓み量より大きければよく、シムプレート11およびシムプレート12の除去後にフランジ21と対向部材22の間にクリアランスが形成されればよい。
As shown in FIG. 2 (b), the
なお、実施例1においては、荷重受け部141に挿入するシムプレートをシムプレート11および12の2枚構成としたが、これに限定されるものではない。例えば、シムプレート11の長穴11Aおよび11Bの長さを接続ボルト19、20の挿通位置に対応する位置まで含むように長くして、シムプレート12を省略しシムプレート11のみの1枚構成としてもよい。また、各シムプレートを一つの接続ボルトの挿通位置に対応するサイズにして4枚構成としてもよい。さらに、長穴を設けることなく四角形等のシムプレートとして細分化された構成としてもよい。
In the first embodiment, the two
また、実施例1においては、接続ボルト17、18、19、20は、フランジ21および対向部材22に備えたそれぞれの挿通孔に挿通させた上で、ナット17N、18N、19N、20Nに螺合させる構成としたが、これに限定されるものではなく、適宜その構成は変更が可能である。例えば、接続ボルト17、18、19、20を螺合させる方向をフランジ21から対向部材22に向ける方向としてもよいし、対向部材22からフランジ21に向ける方向としてもよい。また、フランジを下部柱160の最上部に設けて、上部柱150の最下部における対向部材に向けて下からジャッキアップする構成にしてもよい。
In the first embodiment, the
また、実施例1における雌ねじ部13S、14S、15S、16Sは、図2(a)に示すようにフランジ21の下面にナットを溶接して設けている。しかし、これに限定するものではなく、適宜変更することが可能である。例えば、フランジ21の上面にナットを強度のある溶接をして設けてもよいし、フランジ21の孔に雌ねじを形成してもよい。
Further, the
また、実施例1においては、接続ボルトの数を4本とし、ジャッキボルトの数を4本としたが、必ずしもこれに限定されるものではなく、荷重の大きさや撤去機構の都合により適宜変更できる。例えば、接続ボルトおよびジャッキボルトの数を2本としてもよいし、5本以上としてもよい。 In the first embodiment, the number of connection bolts is four and the number of jack bolts is four. However, the number of connection bolts is not necessarily limited to this, and can be appropriately changed depending on the size of the load and the convenience of the removal mechanism. . For example, the number of connection bolts and jack bolts may be two, or five or more.
次に、実施例1における仮設柱の撤去方法について、図3を参照して説明する。プラントのモジュールが組み立てられた状態では、上部柱150と下部柱160との間に撤去機構10が設けられ、接続ボルト17、18、19、20がナット17N、18N、19N、20Nに螺嵌されてシムプレート固定部142が形成されている(図3(a))。そして、上部梁30(図1参照)からの荷重を受け、シムプレート11、12(図2(b)参照)が荷重受け部141を形成している。
Next, the removal method of the temporary pillar in Example 1 is demonstrated with reference to FIG. In a state where the module of the plant is assembled, the
まず、接続ボルト17、18、19、20(図2(a)、(b)参照)とナット17N、18N、19N、20N(図2(a)参照、但し、ナット19N、20Nは図示せず)との締め付けを緩めて、図3(b)に示すクリアランスAのような隙間をつくる。次に、ジャッキボルト13、14、15、16の螺合を締め付けて、そのねじ部分先端を対向部材22に対して押圧する。この押圧により、フランジ21とシムプレート11、12との間にクリアランスBを得る(図3(b))。これで、フランジ21と対向部材22との間にシムプレート11、12の厚さよりも大きいスペースが形成されて、シムプレート11、12にかかる荷重は開放され、シムプレート11、12は容易に除去可能の状態となる。
First,
次に、シムプレート11、12を荷重受け部141から引き抜くことで除去する(図3(c))。次に、ナット17N、18N、19N、20Nをさらに緩めて、接続ボルト17、18、19、20を除去する。そうすると、上部柱150および下部柱160が容易に除去可能となるので、これらを除去して、仮設柱100の撤去を完了する。
Next, the
なお、実施例1においては、シムプレート11、12を除去してから接続ボルト17、18、19、20を除去するようにしたが、必ずしもこれに限定されず、適宜変更が可能である。例えば、先に接続ボルト17、18、19、20を除去してからシムプレート11、12を除去してもよい。この場合は、シムプレート11、12に長穴11A、11B、12A、12Bがなくても除去でき、シンプルな形状のシムプレートとすることができる。
In the first embodiment, the
以上のように、本発明の実施例1においては、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱を撤去するために当該仮設柱に備えた撤去機構であって、
フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であることを特徴とする撤去機構により、仮設柱の撤去を簡易な作業で行えるようにすることができる。
As described above, in the first embodiment of the present invention, the removal provided for the temporary column in order to remove the temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant. Mechanism,
A flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the removing member is capable of pressing the opposing member by the tip of the screw portion of the jack bolt. Thus, the temporary pillar can be removed by a simple operation.
また、モジュール型プラントにおける上部梁からの荷重を支えて下部梁との間に設けられてなる仮設柱であって、
前記仮設柱は、撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であることを特徴とする仮設柱により、仮設柱の撤去を簡易な作業で行えるようにすることができる。
Also, a temporary pillar provided between the lower beam to support the load from the upper beam in the modular plant,
The temporary pillar has a removal mechanism,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the temporary column can press the opposing member by the tip of the screw portion of the jack bolt. Thus, the temporary pillar can be removed by a simple operation.
さらに、モジュール型プラントにおける上部梁からの荷重を受けて下部梁との間に設けられてなる仮設柱を撤去する撤去方法であって、
前記仮設柱は撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記接続ボルトを緩め、前記ジャッキボルトを螺嵌して前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧して、前記フランジと前記対向部材との間に前記シムプレートの厚さよりも大きいスペースを形成した後、前記シムプレートを除去し、前記仮設柱を撤去することを特徴とする撤去方法により、仮設柱の撤去を簡易な作業で行えるようにすることができる。
Furthermore, it is a removal method for removing a temporary pillar provided between the lower beam in response to a load from the upper beam in a modular plant,
The temporary pillar has a removal mechanism;
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the opposing member can be pressed by the tip of the screw portion of the jack bolt,
A space larger than the thickness of the shim plate between the flange and the opposing member by loosening the connecting bolt, screwing the jack bolt, and pressing the opposing member with the tip of the screw portion of the jack bolt After the formation, the temporary plate can be removed by a simple operation by a removal method characterized by removing the shim plate and removing the temporary column.
本発明の実施例2は、撤去機構を仮設柱の最上部に設けた点で、実施例1と異なっている。以下、図4を参照して実施例2について説明する。図4は、本発明の実施例2における撤去機構が設けられた仮設柱の例を説明する図である。 The second embodiment of the present invention is different from the first embodiment in that the removal mechanism is provided at the uppermost part of the temporary pillar. Hereinafter, Example 2 will be described with reference to FIG. FIG. 4 is a diagram illustrating an example of a temporary column provided with a removal mechanism according to the second embodiment of the present invention.
図4に示すように、撤去機構210が仮設柱200の最上部に設けられている。撤去機構210は、実施例1における撤去機構10と同様であるが、フランジに対向する部材(対向部材)は上部梁30における部材であり、ジャッキボルトが仮設柱最上部のフランジから上部梁30に向けた構成となっている。そして、上部梁30とジャッキボルトのねじ部分先端との間、および上部梁30とシムプレートとの間には上部梁30を保護する保護プレート220が設けられている。保護プレート220は板材からなり、その材質は任意であるが、鉄、アルミ、ステンレス等の金属や強化プラスチックなどの柱を支えるための強度があり変形の少ない材質を採用することができる。また、保護プレート220の大きさは、少なくともジャッキボルトのねじ部先端による押圧点全てとシムプレートとを含む大きさであればよく、厚さはジャッキボルトのねじ部先端が押圧されても上部梁30を傷つけず保護できる厚さであればよい。
As shown in FIG. 4, the
実施例2においても、撤去に際しては、接続ボルトを緩め、ジャッキボルトを螺嵌してねじ部分の先端により上部梁30における部材を押圧し、フランジとフランジに対向する上部梁30における部材との間にシムプレートの厚さよりも大きいスペースを形成した後、シムプレートを除去し仮設柱200が荷重を受けないようにして、仮設柱200を撤去する。
Also in the second embodiment, when removing, the connection bolt is loosened, the jack bolt is screwed and the member in the
以上のように、実施例2においては、撤去機構を最上部に設けた仮設柱とすることにより、上部柱および下部柱を不要にできるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。 As described above, in the second embodiment, the removal mechanism is a temporary column provided at the uppermost portion, so that the upper column and the lower column can be made unnecessary, and the temporary column can be removed by a simple operation. be able to.
本発明の実施例3は、撤去機構を仮設柱の最下部に設けた点で、実施例1と異なっている。以下、図5を参照して実施例3について説明する。図5は、本発明の実施例3における撤去機構が設けられた仮設柱の例を説明する図である。 The third embodiment of the present invention differs from the first embodiment in that a removal mechanism is provided at the lowermost part of the temporary column. Hereinafter, Example 3 will be described with reference to FIG. FIG. 5 is a diagram for explaining an example of a temporary column provided with a removal mechanism according to the third embodiment of the present invention.
図5に示すように、撤去機構310が仮設柱300の最下部に設けられている。撤去機構310は、実施例1における撤去機構10と同様であるが、フランジに対向する部材(対向部材)が下部梁40における部材であり、ジャッキボルトが仮設柱最下部のフランジから下部梁40に向けた構成となっている。そして、下部梁40とジャッキボルトのねじ部分先端との間、および下部梁40とシムプレートとの間には保護プレート320が設けられている。保護プレートは板材からなり、その材質は任意であるが、鉄、アルミ、ステンレス等の金属や強化プラスチックなどの柱を支えるための強度があり変形の少ない材質を採用することができる。また、保護プレートの大きさは、少なくともジャッキボルトのねじ部先端による押圧点全てとシムプレートとを含む大きさであればよく、厚さはジャッキボルトのねじ部先端が押圧されても下部梁40を傷つけず保護できる厚さであればよい。
As shown in FIG. 5, a
実施例3においても、撤去に際しては、接続ボルトを緩め、ジャッキボルトを螺嵌してねじ部分の先端により下部梁40における部材を押圧して、フランジとフランジに対向する下部梁40における部材との間にシムプレートの厚さよりも大きいスペースを形成した後、シムプレートを除去し仮設柱300が荷重を受けないようにして、仮設柱300を撤去する。
Also in the third embodiment, when removing, the connection bolt is loosened, the jack bolt is screwed and the member in the
以上のように、実施例3においては、撤去機構を最下部に設けた仮設柱とすることにより、上部柱および下部柱を不要にできるとともに、仮設柱の撤去を簡易な作業で行えるようにすることができる。 As described above, in the third embodiment, the removal mechanism is a temporary column provided at the lowermost portion, so that the upper column and the lower column can be made unnecessary and the temporary column can be removed by a simple operation. be able to.
本発明における撤去機構、仮設柱、および撤去方法は、モジュール型プラントの分野に広く用いることができる。 The removal mechanism, temporary column, and removal method in the present invention can be widely used in the field of modular plants.
10:撤去機構 11:シムプレート 12:シムプレート11A:長穴 11B:長穴 12A:長穴 12B:長穴13:ジャッキボルト 14:ジャッキボルト 15:ジャッキボルト 16:ジャッキボルト13S:雌ねじ部 14S:雌ねじ部 15S:雌ねじ部 16S:雌ねじ部17:接続ボルト 18:接続ボルト 19:接続ボルト 20:接続ボルト17N:ナット 18N:ナット 19N:ナット 20N:ナット21:フランジ 22:フランジに対向する部材(対向部材)30:上部梁 40:下部梁
100:仮設柱 140:ジャッキアップ部 141:荷重受け部
142:シムプレート固定部
150:上部柱 160:下部柱
200:仮設柱 210:撤去機構 220:保護プレート
300:仮設柱 310:撤去機構 320:保護プレート
10: Removal mechanism 11: Shim plate 12:
Claims (7)
フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする撤去機構。 In order to remove the temporary column provided between the lower beam and supporting the load from the upper beam in the modular plant, a removal mechanism that releases the load applied to the temporary column ,
A flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
The removal mechanism characterized in that the load applied to the temporary column can be released by removing the shim plate from the load receiving portion .
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記シムプレートを前記荷重受け部から除去することにより前記仮設柱にかかる荷重を開放可能であることを特徴とする仮設柱。 A temporary pillar provided between the lower beam and supporting the load from the upper beam in the modular plant,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the threaded portion of the jack bolt is longer than the sum of the thickness of the shim plate and the thickness of the flange, Ri depressible der the opposing member by the tip of the screw portion of the jack bolt,
The temporary pillar, wherein the load applied to the temporary pillar can be released by removing the shim plate from the load receiving portion .
前記仮設柱は、当該仮設柱にかかる荷重を開放する撤去機構を有し、
前記撤去機構は、フランジと、
前記フランジと前記フランジに対向する部材である対向部材との間にシムプレートを挿入してなる荷重受け部と、
前記フランジと前記対向部材との間に接続ボルトを螺合してなるシムプレート固定部と、
ジャッキボルトのねじ部分の先端が前記対向部材を向くように前記フランジに備えた雌ねじ部に前記ジャッキボルトを螺合させてなるジャッキアップ部と、を備え、
前記ジャッキボルトのねじ部分の長さは前記フランジの厚みと前記シムプレートの厚みとの和より長く、前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧可能であり、
前記接続ボルトを緩め、前記ジャッキボルトを螺嵌して前記ジャッキボルトのねじ部分の先端により前記対向部材を押圧して、前記フランジと前記対向部材との間に前記シムプレートの厚さよりも大きいスペースを形成した後、前記シムプレートを除去し、前記仮設柱を撤去することを特徴とする撤去方法。 A removal method for receiving a load from an upper beam in a modular plant and removing a temporary pillar provided between the lower beam,
The temporary pillar has a removal mechanism that releases a load applied to the temporary pillar ,
The removal mechanism includes a flange,
A load receiving portion formed by inserting a shim plate between the flange and a facing member which is a member facing the flange;
A shim plate fixing portion formed by screwing a connection bolt between the flange and the facing member;
A jack-up portion formed by screwing the jack bolt into a female screw portion provided in the flange so that the tip of the screw portion of the jack bolt faces the opposing member;
The length of the screw portion of the jack bolt is longer than the sum of the thickness of the flange and the thickness of the shim plate, and the opposing member can be pressed by the tip of the screw portion of the jack bolt,
A space larger than the thickness of the shim plate between the flange and the opposing member by loosening the connecting bolt, screwing the jack bolt, and pressing the opposing member with the tip of the screw portion of the jack bolt The removal method is characterized by removing the shim plate and removing the temporary pillar after forming.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2016127125A JP6566481B2 (en) | 2016-06-28 | 2016-06-28 | Removal mechanism, temporary pillar, and removal method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2016127125A JP6566481B2 (en) | 2016-06-28 | 2016-06-28 | Removal mechanism, temporary pillar, and removal method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2018003288A JP2018003288A (en) | 2018-01-11 |
| JP6566481B2 true JP6566481B2 (en) | 2019-08-28 |
Family
ID=60945870
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2016127125A Active JP6566481B2 (en) | 2016-06-28 | 2016-06-28 | Removal mechanism, temporary pillar, and removal method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP6566481B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR102417709B1 (en) * | 2020-07-17 | 2022-07-05 | 김동산 | Apparatus and method for construction of slab which concrete build using euroform |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0748890Y2 (en) * | 1989-09-20 | 1995-11-08 | 岡部株式会社 | Temporary columns for formwork support |
| JPH03113058U (en) * | 1990-03-05 | 1991-11-19 | ||
| US6425712B1 (en) * | 2000-09-07 | 2002-07-30 | Liftplate International | Method and apparatus for providing lateral support to a post |
| JP2002276525A (en) * | 2001-03-19 | 2002-09-25 | Kansai Electric Power Co Inc:The | Hydraulic machine and upper cover level adjustment method |
| JP2014084201A (en) * | 2012-10-23 | 2014-05-12 | Hitachi Building Systems Co Ltd | Handrail structure of passenger conveyor and handrail installation method |
-
2016
- 2016-06-28 JP JP2016127125A patent/JP6566481B2/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| JP2018003288A (en) | 2018-01-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102333625A (en) | Method for producing concrete trestle, concrete trestle, and connecting member | |
| US12258938B2 (en) | Transporting a wind turbine component | |
| JP6818401B2 (en) | Connection structure using box-shaped hardware | |
| JP6566481B2 (en) | Removal mechanism, temporary pillar, and removal method | |
| CN204715225U (en) | A kind of bridge jacking platform based on steel hoop | |
| KR100949894B1 (en) | Turn-over method using turn-over fixture of hopper block | |
| KR101048570B1 (en) | Sectional Configuration Method of Monorail Crane Girder | |
| CN108914763B (en) | Application method of bridge closure stiffness framework quick locking device | |
| WO2021067615A1 (en) | Rolling block restraint connector having an improved linkage assembly | |
| JP2017014730A (en) | Beam material load bearing structure and beam material repair method | |
| JP7160575B2 (en) | Structure and construction method of structure | |
| JP7386515B2 (en) | Scaffold construction set and method for constructing scaffolding | |
| SE524073C2 (en) | Beam connection system, comprises fastener plates secured to beams and joined together via fixing parts | |
| DE102008045478B4 (en) | Clamping block and system of clamping blocks | |
| KR102147059B1 (en) | Steel structure supporting assembly and breast wall construction method using thereof | |
| KR200470260Y1 (en) | Anchor Bolt System | |
| KR100914717B1 (en) | strengthening notch-plate. | |
| JP2019007134A (en) | Reinforcing existing footing | |
| JP6696814B2 (en) | Construction method of connection member for transportation and unit building | |
| JP6792338B2 (en) | Wood structural material reinforcement structure | |
| KR102160937B1 (en) | Coupling device and method for preformed bar arrangement using threaded reinforcing bars | |
| JP6604650B2 (en) | Retaining wall formwork fixed hardware | |
| JP6467202B2 (en) | Steel tower main column replacement method | |
| CN217840352U (en) | Threaded connection embedded part | |
| JP4871654B2 (en) | Connector |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20180206 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20181119 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20181228 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20190206 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20190725 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20190725 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 6566481 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |