[go: up one dir, main page]

JP2018031159A - Construction method of underground structure - Google Patents

Construction method of underground structure Download PDF

Info

Publication number
JP2018031159A
JP2018031159A JP2016163339A JP2016163339A JP2018031159A JP 2018031159 A JP2018031159 A JP 2018031159A JP 2016163339 A JP2016163339 A JP 2016163339A JP 2016163339 A JP2016163339 A JP 2016163339A JP 2018031159 A JP2018031159 A JP 2018031159A
Authority
JP
Japan
Prior art keywords
underground structure
existing
hollow
earth
buoyancy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2016163339A
Other languages
Japanese (ja)
Inventor
植村 誠
Makoto Uemura
誠 植村
賢治郎 植村
Kenjiro Uemura
賢治郎 植村
丸田 新市
Shinichi Maruta
新市 丸田
智哉 中村
Tomoya Nakamura
智哉 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2016163339A priority Critical patent/JP2018031159A/en
Publication of JP2018031159A publication Critical patent/JP2018031159A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

【課題】既設のトンネル等の中空地下構造物の上方で前記中空地下構造物と直交する方向の近接位置に地下構造物を構築する地下構造物の構築方法において、中空地下構造物が浮力により浮上することを防止でき、コンクリート函体内(トンネル内)ではなく切羽前方の地上から掘削機等での切羽掘削であり、トンネル作業が地上作業となるので施工性も良好で、掘削作業の施工環境が良好となり、施工環境が良いため、工期が短縮され、工期短縮により、浮力発生期間が短くなり、浮力防止効果も向上する。【解決手段】既設の地下構造物上方に残された土砂を土砂の掘削は切羽前方の地上から掘削機20で切羽掘削する。【選択図】図1A method for constructing an underground structure in which an underground structure is constructed near a hollow underground structure, such as an existing tunnel, in a direction orthogonal to the hollow underground structure, and the hollow underground structure is lifted by buoyancy. It is a face excavation with excavator etc. from the ground in front of the face instead of the concrete box (in the tunnel), and the tunnel work becomes the ground work, so the workability is good and the construction environment of the excavation work is Since the construction environment is good and the construction environment is good, the construction period is shortened, and the shortening of the construction period shortens the buoyancy generation period and improves the buoyancy prevention effect. The earth and sand left above the existing underground structure is excavated by the excavator 20 from the ground in front of the face. [Selection] Figure 1

Description

本発明は、地中に埋設されている既設の中空地下構造物の上方に新設の地下構造物を構築する方法に関するものである。   The present invention relates to a method for constructing a new underground structure above an existing hollow underground structure buried in the ground.

下記特許文献は、既設トンネルなどの中空の地下構造物またはその他の地下構造物の上方近接位置に新設の地下構造物を構築する場合、補助対策を必要とせず、低コストで既設の地下構造物が浮上がることを防止できる地下構造物の構築方法を提案し、特許を取得した。
特許第4113187号公報
The following patent documents show that when a new underground structure is built near a hollow underground structure such as an existing tunnel or other underground structure, an auxiliary measure is not required and the existing underground structure is low-cost. Proposed a method for constructing underground structures that can prevent buoys from rising, and obtained a patent.
Japanese Patent No. 4131187

これは図3に示すように、既設のトンネル等の中空地下構造物の上方で前記中空地下構造物と直交する方向の近接位置に地下構造物を構築する地下構造物の構築方法において、既設の中空地下構造物の側部両側に発進立坑と到達立坑とを築造し、既設の中空地下構造物上方には、少なくともこの中空地下構造物が浮力により浮上することを防止できるだけの高さの土砂を残して土砂を掘削し、新設する地下構造物を、発進立坑から到達立坑に向けて水平に移動しながら、当該箇所の残された土砂を徐々に取除き、既設の中空地下構造物には必要な荷重が絶えず作用するよう、この土砂と置換させながら新設の地下構造物を既設の中空地下構造物の上方に設置することで、前記既設の中空地下構造物上方に残された土砂による既設の中空地下構造物への浮力による浮上防止に必要な荷重を新設する地下構造物に徐々に置き換えて行くものである。   As shown in FIG. 3, this is a method for constructing an underground structure in which an underground structure is constructed at a position close to a direction perpendicular to the hollow underground structure above a hollow underground structure such as an existing tunnel. A start shaft and a reach shaft are built on both sides of the hollow underground structure, and at least above the existing hollow underground structure is at least high enough to prevent the hollow underground structure from rising due to buoyancy. Necessary for the existing hollow underground structure by excavating the earth and sand, moving the newly constructed underground structure horizontally from the start shaft to the arrival shaft, and gradually removing the remaining sediment at the location. By installing this new underground structure above the existing hollow underground structure while substituting it with the earth and sand so that a continuous load acts continuously, the existing sand and sand left above the existing hollow underground structure is installed. Hollow basement Is intended to go gradually replaced the underground structure that established the load required for the anti-surfacing by the buoyancy of the thing.

地下には、トンネル、地下道、共同溝などの中空地下構造物が埋設されているが、例えば既設の中空地下構造物である既設トンネルの上側で近接位置に道路を横断する形態でコンクリート函体による地下構造物を新規に構築する場合や、既設トンネルの上側で近接位置に鉄道を横断する形態でコンクリート函体による地下構造物を新規に構築する場合に、開削工法により掘削し、開削した部分にコンクリート函体を地表の開口から新規のコンクリート函体を吊り降ろして設置していたのでは、開削されて既設トンネルにかかる上方からの荷重が減少するため、例えば地下水を有する地域などでは既設トンネルに対して大きな浮力が作用し、既設トンネルが浮き上がり、周辺地盤も隆起するなどの問題が発生する。   In the basement, hollow underground structures such as tunnels, underground passages, and common grooves are buried, but for example, with a concrete box in a form that crosses the road to the adjacent position above the existing tunnel that is an existing hollow underground structure When constructing a new underground structure, or when constructing a new underground structure with a concrete box in the form of crossing the railway near the upper side of the existing tunnel, excavation by the open-cut method will be performed on the excavated part. If a new concrete box was hung from the opening on the surface of the ground and installed, the load from the upper side of the existing tunnel is reduced and the existing tunnel is reduced. On the other hand, large buoyancy acts, causing problems such as the existing tunnel floating and the surrounding ground rising.

そこで、既設トンネル1などの既設の中空地下構造物が浮き上がらないようにするためには、既設の中空地下構造物を一時期、取り壊すか、撤去すれば問題は解消されるが、このようにした場合、その間の既設中空構造物の使用停止などの多大な影響が生じるだけでなく、用地を別途確保する必要があり、そのためのコストも要する。   Therefore, in order to prevent the existing hollow underground structure such as the existing tunnel 1 from rising, the problem can be solved by demolishing or removing the existing hollow underground structure for a period of time. In addition, a great influence such as the suspension of use of the existing hollow structure in the meantime occurs, and it is necessary to secure a site separately, and the cost is also required.

前記特許文献1はかかる問題を解決するものとして、開削工法で掘削しないから、補助対策を講じる必要がなく、新設の地下構造物が設置される直前まで、既設の地下構造物の上方の土砂は掘削されず、土砂と置換されて新設の地下構造物が設置されるから、新設の地下構造物が設置されるまでの間に既設の地下構造物が浮力により浮上がることはないものである。   Since the said patent document 1 solves such a problem, since it does not excavate by an open-cut method, it is not necessary to take an auxiliary measure, and immediately before a newly installed underground structure is installed, the sediment above the existing underground structure is Since the new underground structure is installed without excavation and replaced with earth and sand, the existing underground structure is not lifted by buoyancy until the new underground structure is installed.

また、発進立坑と到達立坑とは既設の地下構造物の両側に築造されるから、これらの立坑が既設の中空地下構造物に影響を及ぼして該構造物に浮力を生じさせるおそれはない。   Moreover, since the start shaft and the reaching shaft are built on both sides of the existing underground structure, there is no possibility that these shafts will affect the existing hollow underground structure and cause buoyancy in the structure.

前記特許文献1を含めて一般にトンネル掘削は、トンネル内で行われている。特許文献1の場合も、コンクリート函体2を発進立坑9から到達立坑10に向けて推進するのにこの函体推進工はコンクリート函体2内から切羽を掘削しながらコンクリート函体2を既設トンネル1の上方近接位置を推進させるものである。   In general, the tunnel excavation including Patent Document 1 is performed in a tunnel. In the case of Patent Document 1 as well, in order to propel the concrete box 2 from the start shaft 9 toward the arrival shaft 10, the box propulsion works by excavating the face from the concrete box 2 to construct the concrete box 2 in the existing tunnel. 1 is advanced.

このため、通常切羽の安定を図り、掘削・土砂排土・土留等を行う施工とするため、相当の時間を要すことになる。   For this reason, it takes a considerable amount of time to stabilize the face normally and to perform excavation, earth and sand removal, and earth retaining.

本発明の目的は前記従来例の不都合を解消し、トンネル内切羽掘削は、必ずしもトンネル内ではなく、切羽前方の地上から掘削機での切羽掘削を行うので、掘削作業の施工環境が良好となり、その結果として工期も短縮できる地下構造物の構築方法を提供することにある。   The object of the present invention is to eliminate the inconvenience of the conventional example, and the face excavation in the tunnel is not necessarily in the tunnel, but the face excavation is performed with the excavator from the ground in front of the face, so that the construction environment of the excavation work is improved. As a result, an object of the present invention is to provide an underground structure construction method that can shorten the construction period.

前記目的を達成するため請求項1記載の本発明は、既設のトンネル等の中空地下構造物の上方で前記中空地下構造物と直交する方向の近接位置に地下構造物を構築する地下構造物の構築方法において、既設の中空地下構造物の側部両側に発進立坑と到達立坑とを築造し、既設の中空地下構造物上方には、少なくともこの中空地下構造物が浮力により浮上することを防止できるだけの高さの土砂を残して土砂を掘削し、新設する地下構造物を、発進立坑から到達立坑に向けて水平に移動しながら、当該箇所の残された土砂を徐々に取除き、既設の中空地下構造物には浮力防止に必要な荷重が絶えず作用するよう、この土砂と置換させながら新設の地下構造物を既設の中空地下構造物の上方に設置することで、前記既設の中空地下構造物上方に残された土砂による既設の中空地下構造物への浮力による浮上防止に必要な荷重を新設する地下構造物に徐々に置き換えて行く地下構造物の構築方法において、既設の地下構造物上方に残された土砂を土砂の掘削は切羽前方の地上から掘削機で切羽掘削することを要旨とするものである。   In order to achieve the above object, the present invention according to claim 1 is directed to an underground structure for constructing an underground structure in a proximity position in a direction orthogonal to the hollow underground structure above a hollow underground structure such as an existing tunnel. In the construction method, a start shaft and a reach shaft are built on both sides of the existing hollow underground structure, and at least the hollow underground structure can be prevented from rising due to buoyancy above the existing hollow underground structure. Excavation of the earth leaving the earth and sand, and moving the newly constructed underground structure horizontally from the starting shaft to the arrival shaft, gradually removing the remaining earth and sand at the location, By replacing this earth and sand with the newly installed underground structure above the existing hollow underground structure so that the load necessary to prevent buoyancy acts constantly on the underground structure, the existing hollow underground structure Left above In the construction method of the underground structure that gradually replaces the load necessary to prevent levitation due to buoyancy to the existing hollow underground structure with the earth and sand that was newly installed, it was left above the existing underground structure The excavation of earth and sand is to excavate the face with an excavator from the ground in front of the face.

請求項1記載の本発明によれば、開削工法で掘削しないから、新設の地下構造物が設置される直前まで、既設の地下構造物の上方の土砂は掘削されず、土砂と置換されて新設の地下構造物が設置されるから、新設の地下構造物が設置されるまでの間に既設の地下構造物が浮力により浮上がることはない。   According to the first aspect of the present invention, since excavation is not performed by the open-cut method, the earth and sand above the existing underground structure is not excavated and replaced with earth and sand until just before the newly installed underground structure is installed. The existing underground structure will not be lifted by buoyancy until the newly installed underground structure is installed.

また、発進立坑と到達立坑とは既設の地下構造物の両側に築造されるから、これらの立坑が既設の中空地下構造物に影響を及ぼして該構造物に浮力を生じさせるおそれはない。   Moreover, since the start shaft and the reaching shaft are built on both sides of the existing underground structure, there is no possibility that these shafts will affect the existing hollow underground structure and cause buoyancy in the structure.

さらに、コンクリート函体内(トンネル内)ではなく切羽前方の地上から掘削機等での切羽掘削であり、トンネル作業が地上作業となるので施工性も良好で、掘削作業の施工環境が良好となる。   Furthermore, it is a face excavation by an excavator or the like from the ground in front of the face rather than the concrete box (inside the tunnel), and the tunnel work becomes the ground work, so the workability is good and the construction environment of the excavation work is good.

施工環境が良いため、工期が短縮され、工期短縮により、浮力発生期間が短くなり、浮力防止効果も向上する。   Because the construction environment is good, the construction period is shortened, and shortening the construction period shortens the buoyancy generation period and improves the buoyancy prevention effect.

請求項2記載の本発明は、新設する構造物の天端は、浅い土被りや地上面より高いものとすることを要旨とするものである。   The gist of the present invention described in claim 2 is that the top end of the newly constructed structure is higher than the shallow earth covering or the ground surface.

請求項2記載の本発明によれば、新設する構造物の天端は、浅い土被りや地上面より高いものとすることにより、切羽前方の地上から掘削機等での切羽掘削をより容易に行うことができる。   According to the second aspect of the present invention, the top end of the newly constructed structure is higher than the shallow earth covering or the ground surface, thereby facilitating face excavation with an excavator or the like from the ground in front of the face. It can be carried out.

以上述べたように本発明の地下構造物の構築方法は、既設トンネルなどの中空の地下構造物またはその他の地下構造物の上方近接位置に新設の地下構造物を構築する場合、開削工法を用いず、既設の地下構造物上方に土砂を残し、この土砂を掘削して、この土砂と置換させながら発進立坑から到達立坑に向けて新設の地下構造物を移動させて既設の地下構造物の上方に新設の地下構造物を設置するようにしたから、補助対策を必要とせず、低コストで既設の地下構造物が浮上がることを防止でき、施工期間が長引くこともなく、しかも、安全に施工できる。   As described above, the construction method of the underground structure according to the present invention uses the open-cut method when constructing a newly installed underground structure near a hollow underground structure such as an existing tunnel or other underground structure. First, leave the earth and sand above the existing underground structure, excavate this earth and sand, replace the earth and sand, move the new underground structure from the start shaft to the destination shaft, and move above the existing underground structure. Since a new underground structure is installed in the building, no auxiliary measures are required, it is possible to prevent the existing underground structure from rising at a low cost, the construction period is not prolonged, and construction can be performed safely. it can.

しかも、コンクリート函体内(トンネル内)ではなく切羽前方の地上から掘削機等での切羽掘削であり、トンネル作業が地上作業となるので施工性も良好で、掘削作業の施工環境が良好となり、施工環境が良いため、工期が短縮され、工期短縮により、浮力発生期間が短くなり、浮力防止効果も向上する。   In addition, it is face excavation by excavator etc. from the ground ahead of the face rather than the concrete box (inside the tunnel), and the tunnel work becomes ground work, so the workability is also good and the excavation work environment is good, Since the environment is good, the construction period is shortened, and shortening the construction period shortens the buoyancy generation period and improves the buoyancy prevention effect.

以下、図面について本発明の実施形態を詳細に説明する。図1は本発明の地下構造物の構築方法の1実施形態を示す縦断側面図であるが、先に本発明の構築方法で施工する地下構造物について説明すると、図4に示すように既設の中空地下構造物としての例えば既設トンネル1の上方で近接位置に新設の地下構造物であるコンクリート函体2を設置する場合であり、道路16の地下地盤の中に既設トンネル1が埋設されている。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a longitudinal side view showing an embodiment of a construction method for an underground structure of the present invention. However, an underground structure constructed by the construction method of the present invention will be described first. As shown in FIG. For example, a concrete box 2 that is a newly installed underground structure is installed near the upper position of the existing tunnel 1 as a hollow underground structure, and the existing tunnel 1 is embedded in the underground ground of the road 16. .

既設トンネル1の上方に高さh分の土砂が残るようにして道路16の路面から深さh1だけ掘削するもので、前記高さhは既設トンネル1が浮力より浮上がることが防止されるだけの荷重を有する土砂量である。   Excavation is carried out by a depth h1 from the road surface of the road 16 so that earth and sand for a height h remain above the existing tunnel 1, and the height h only prevents the existing tunnel 1 from being lifted by buoyancy. The amount of earth and sand with a load of.

図2に示すように、既設トンネル1に浮力が作用しないような位置で既設トンネル1の側部両側に仮土留杭4を間隔をおいて打設し、仮土留杭4、4の間を二次掘削して発進立坑9と到達抵抗10とを築造する。   As shown in FIG. 2, temporary earth retaining piles 4 are driven on both sides of the existing tunnel 1 at a position where buoyancy does not act on the existing tunnel 1, and two spaces between the temporary earth retaining piles 4, 4 are provided. Next, the start shaft 9 and the arrival resistance 10 are constructed by excavation.

このとき、既設トンネル1の上方には高さh分の土砂が依然として残されており、回りに発進立坑9と到達立坑10とが築造されても既設トンネル1が浮力により浮きあがることはない。そして、発進立坑9内に発進台11を築造する。   At this time, the earth and sand for the height h are still left above the existing tunnel 1, and the existing tunnel 1 will not be lifted by buoyancy even if the starting shaft 9 and the reaching shaft 10 are built around. And the start stand 11 is built in the start shaft 9.

発進立坑9内に反力設備としての支圧壁12を設置し、新規の地下構造物となるコンクリート函体2を配設し、またはこの発進立坑9内でコンクリート函体2を築造し、このコンクリート函体2の前部に刃口13を組み立てる。   A bearing wall 12 as a reaction force facility is installed in the start shaft 9, and a concrete box 2 as a new underground structure is arranged, or the concrete box 2 is built in the start shaft 9, The blade edge 13 is assembled at the front of the concrete box 2.

刃口13は鋼板によるもので、コンクリート函体2の前端から前に突き出るように取付けられ、本実施形態では底板と側板のコ字形であり、水平棚が無い形状とする。なお、側板は上下段に段階的に突出長さを変化させた。   The blade edge 13 is made of a steel plate and is attached so as to protrude forward from the front end of the concrete box 2. In this embodiment, the shape is a U-shape of a bottom plate and a side plate, and there is no horizontal shelf. In addition, the protrusion length of the side plate was changed stepwise up and down.

そして、コンクリート函体2の後部と支圧壁12との間に元押しジャッキ14などによる推進設備を設置する。   Then, propulsion equipment such as a push jack 14 is installed between the rear portion of the concrete box 2 and the bearing wall 12.

このようにしてコンクリート函体2を発進立坑9から到達立坑10に向けて推進する。   In this way, the concrete box 2 is propelled from the starting shaft 9 toward the reaching shaft 10.

本実施形態の施工は、鉄道又は道路横断等では無く、フラットな地盤での施工であり、コンクリート函体2の天端は浅い土被りの場合や地上路面より高い場合である。   The construction of this embodiment is not a railroad or a road crossing but a construction on a flat ground, and the top of the concrete box 2 is a shallow earth cover or a case where it is higher than the ground road surface.

なお、地上の路面を事前に掘削して、あらかじめ低くしておくように一次掘削を行い、盤下げするようにしてもよい。   The ground road surface may be excavated in advance, and primary excavation may be performed so as to be lowered in advance, and the board may be lowered.

コンクリート函体2を発進立坑9から到達立坑10に向けて推進する。この函体推進工は切羽掘削は切羽前方の地上から掘削機20で切羽掘削する。掘削機20としてはバックホータイプのシャベル系掘削機が最適であり、アーム20aの先端の掘削用バケット20bで掘削するものである。   The concrete box 2 is propelled from the starting shaft 9 toward the reaching shaft 10. In this box propulsion work, the face is excavated by the excavator 20 from the ground in front of the face. As the excavator 20, a backhoe type shovel excavator is optimal, and excavates with the excavation bucket 20b at the tip of the arm 20a.

そして、掘削した分コンクリート函体2を推進させるが、掘削機20はコンクリート函体2の推進と共に移動して行くことができる。   Then, although the excavated concrete box 2 is propelled, the excavator 20 can move along with the propulsion of the concrete box 2.

このようにして先頭のコンクリート函体2の後方に発進立坑9内で後続のコンクリート函体2を製作し、接続して先頭のコンクリート函体2及び後続のコンクリート函体2を切羽を掘削しながらさらに推進する。   In this way, the succeeding concrete box 2 is manufactured in the start shaft 9 behind the leading concrete box 2, and connected to the leading concrete box 2 and the succeeding concrete box 2 while excavating the face. Further promote.

本発明の函体推進工は切羽を掘削しながらコンクリート函体2を既設トンネル1の上方近接位置を推進させるもので、土砂とコンクリート函体2とを置換させることで既設トンネル1の上部にかかる荷重が軽減しないようにする。   The box body propelling work of the present invention is to push the concrete box 2 to the upper adjacent position of the existing tunnel 1 while excavating the face. By replacing the earth and sand with the concrete box 2, the upper part of the existing tunnel 1 is applied. Do not reduce the load.

これにより、既設トンネル1には上方から一定の荷重が常時加わることになり、既設トンネル1の上方を掘削しても浮力により既設トンネル1が浮上がることはない。   As a result, a constant load is always applied to the existing tunnel 1 from above, and the existing tunnel 1 will not be lifted by buoyancy even when excavating above the existing tunnel 1.

そしてコンクリート函体2の先頭の刃口13が到達立坑10に達したならば、コンクリート函体2の推進が完了し、既設トンネル1の上方近接位置に新設のコンクリート函体2が設置される。   When the leading edge 13 of the concrete box 2 reaches the reach shaft 10, the concrete box 2 is completely propelled, and the new concrete box 2 is installed at a position close to the upper side of the existing tunnel 1.

なお、前記実施形態では新設のコンクリート函体2の前進手段として発進立坑9側に設置の元押しジャッキを使用してコンクリート函体2を押し出して推進したが、これに限定されるものではなく、コンクリート函体2を水平移動できる機構であれば、到達立坑10側に設置の牽引設備を使用して到達立坑10側から新規のコンクリート函体2を牽引して前進させることもできる。   In the above-described embodiment, the concrete box 2 is pushed and propelled by using a main push jack installed on the start shaft 9 side as a forward means of the new concrete box 2, but the invention is not limited to this. If it is a mechanism which can move the concrete box 2 horizontally, the new concrete box 2 can also be pulled and advanced from the reach shaft 10 side using the pulling equipment installed in the reach shaft 10 side.

以上、既設の地下構造物として既設トンネルなどの中空の地下構造物の場合を示したが建物やそのその他の中空井でない地下構造物の場合の本発明は同様に適用できるものである。   In the above, the case of a hollow underground structure such as an existing tunnel has been shown as the existing underground structure, but the present invention in the case of a building or other underground structure other than a hollow well can be similarly applied.

本発明の地下構造物の構築方法の1実施形態を示す縦断側面図である。It is a vertical side view which shows one Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の構築方法の1実施形態を示す前工程の縦断側面図である。It is a vertical side view of the front process which shows one Embodiment of the construction method of the underground structure of this invention. 従来例を示す縦断側面図である。It is a vertical side view which shows a prior art example. 既設の中空地下構造物の上方に新設の地下構造物を構築する場合の想定図である。It is an assumption figure in the case of constructing a new underground structure above an existing hollow underground structure.

1…既設トンネル 2…コンクリート函体
3…工事桁 4…仮土留杭
5…グランドアンカー 6…浮上がり防止材
7…立坑 8…基礎杭
9…発進立坑 10…到達立坑
11…発進台 12…支圧壁
13…刃口 14…元押しジャッキ
15…ストラット 16…道路
20…掘削機 20a…アーム
20b…掘削用バケット
DESCRIPTION OF SYMBOLS 1 ... Existing tunnel 2 ... Concrete box 3 ... Construction girder 4 ... Temporary earth retaining pile 5 ... Ground anchor 6 ... Lifting prevention material 7 ... Vertical shaft 8 ... Foundation pile 9 ... Starting shaft 10 ... Reaching shaft 11 ... Start stand 12 ... Support Pressure wall 13 ... Blade 14 ... Presser jack 15 ... Strut 16 ... Road 20 ... Excavator 20a ... Arm 20b ... Drilling bucket

Claims (2)

既設のトンネル等の中空地下構造物の上方で前記中空地下構造物と直交する方向の近接位置に地下構造物を構築する地下構造物の構築方法において、既設の中空地下構造物の側部両側に発進立坑と到達立坑とを築造し、既設の中空地下構造物上方には、少なくともこの中空地下構造物が浮力により浮上することを防止できるだけの高さの土砂を残して土砂を掘削し、新設する地下構造物を、発進立坑から到達立坑に向けて水平に移動しながら、当該箇所の残された土砂を徐々に取除き、既設の中空地下構造物には浮力防止に必要な荷重が絶えず作用するよう、この土砂と置換させながら新設の地下構造物を既設の中空地下構造物の上方に設置することで、前記既設の中空地下構造物上方に残された土砂による既設の中空地下構造物への浮力による浮上防止に必要な荷重を新設する地下構造物に徐々に置き換えて行く地下構造物の構築方法において、既設の地下構造物上方に残された土砂を土砂の掘削は切羽前方の地上から掘削機で切羽掘削することを特徴とした地下構造物の構築方法。   In the construction method of an underground structure in which an underground structure is constructed near a hollow underground structure, such as an existing tunnel, in a direction perpendicular to the hollow underground structure, on both sides of the existing hollow underground structure, A start shaft and a reaching shaft will be constructed, and at the upper part of the existing hollow underground structure, at least this hollow underground structure will be excavated with a sufficient height to prevent the hollow underground structure from rising due to buoyancy. While moving the underground structure horizontally from the start shaft to the arrival shaft, the remaining earth and sand is gradually removed, and the load necessary to prevent buoyancy is constantly acting on the existing hollow underground structure. Thus, by replacing this earth and sand with the newly installed underground structure above the existing hollow underground structure, the existing hollow underground structure with the earth and sand left above the existing hollow underground structure is installed. Buoyancy In the construction method of the underground structure that gradually replaces the load necessary to prevent levitation with the newly installed underground structure, the earth and sand left above the existing underground structure is excavated from the ground in front of the face. Construction method of underground structure characterized by excavating face at 新設する構造物の天端は、浅い土被りや地上面より高いものとする請求項1記載の地下構造物の構築方法。   The method for constructing an underground structure according to claim 1, wherein the top end of the newly constructed structure is higher than the shallow earth covering or the ground surface.
JP2016163339A 2016-08-24 2016-08-24 Construction method of underground structure Pending JP2018031159A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016163339A JP2018031159A (en) 2016-08-24 2016-08-24 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016163339A JP2018031159A (en) 2016-08-24 2016-08-24 Construction method of underground structure

Publications (1)

Publication Number Publication Date
JP2018031159A true JP2018031159A (en) 2018-03-01

Family

ID=61302843

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016163339A Pending JP2018031159A (en) 2016-08-24 2016-08-24 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JP2018031159A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424398A (en) * 2019-07-03 2019-11-08 中铁一局集团厦门建设工程有限公司 Across existing shield section open-cut engineering method in zero distance
CN115680022A (en) * 2022-11-14 2023-02-03 中建二局第二建筑工程有限公司 Construction Method of Underground Structure across Existing Tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5289215A (en) * 1976-01-21 1977-07-26 Ishikawajima Kenzai Kogyo Kk Tunnel construction method and selfftravelling system earth and sand breaking stopping machine used for this method
US4072021A (en) * 1976-11-02 1978-02-07 Tekken Construction Co. Ltd. Method of driving and forming a tunnel with hydraulic boring machine
JP2007154448A (en) * 2005-12-01 2007-06-21 Uemura Giken Kogyo Kk Construction method for underground structures
JP4113187B2 (en) * 2005-02-02 2008-07-09 誠 植村 Construction method of underground structure
JP2010065498A (en) * 2008-09-12 2010-03-25 Kajima Corp Box body construction method
JP2016020569A (en) * 2014-07-14 2016-02-04 植村 誠 Concrete box body used for open shield method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5289215A (en) * 1976-01-21 1977-07-26 Ishikawajima Kenzai Kogyo Kk Tunnel construction method and selfftravelling system earth and sand breaking stopping machine used for this method
US4072021A (en) * 1976-11-02 1978-02-07 Tekken Construction Co. Ltd. Method of driving and forming a tunnel with hydraulic boring machine
JP4113187B2 (en) * 2005-02-02 2008-07-09 誠 植村 Construction method of underground structure
JP2007154448A (en) * 2005-12-01 2007-06-21 Uemura Giken Kogyo Kk Construction method for underground structures
JP2010065498A (en) * 2008-09-12 2010-03-25 Kajima Corp Box body construction method
JP2016020569A (en) * 2014-07-14 2016-02-04 植村 誠 Concrete box body used for open shield method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424398A (en) * 2019-07-03 2019-11-08 中铁一局集团厦门建设工程有限公司 Across existing shield section open-cut engineering method in zero distance
CN115680022A (en) * 2022-11-14 2023-02-03 中建二局第二建筑工程有限公司 Construction Method of Underground Structure across Existing Tunnel

Similar Documents

Publication Publication Date Title
JP4184400B2 (en) Construction method of underground structure
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
JP5584542B2 (en) Ground deformation prevention method and underground structure construction method using the same
CN106930321B (en) A construction method for building underground structures with large diameter pipe jacking combined with hole piles
CN103882881A (en) Underwater construction method for bearing platform deeply embedded in rock
JP4309219B2 (en) Tunnel construction method
JP2015048659A (en) Start reaction device for open shield machine
JP2018031159A (en) Construction method of underground structure
JP7177233B2 (en) Start Reaction Force Structure and Method for Concrete Box or Open Shield Machine
JP5204063B2 (en) Box foundation construction method in open shield method
JP4113187B2 (en) Construction method of underground structure
JP6826820B2 (en) Insertion pile type retaining wall
CN108457303A (en) A method of increasing underground parking newly under existing building
CN100593052C (en) Open cut foundation pit supporting and protecting method
JP7671124B2 (en) How to build a tunnel
JP5639213B2 (en) Open shield method
JP6276300B2 (en) Open shield method
KR102608601B1 (en) Sheet non excavation method for drilling a tunnel having a file reinforcing structure
JP4279818B2 (en) Open shield method
JP4349570B2 (en) Construction method of division box and underground level crossing
JP7597777B2 (en) Method of entering the vertical shaft of an open shield machine in the open shield construction method
JP3766423B2 (en) Retaining wall construction method
JP5960786B2 (en) Shield machine collection method in open shield method
CN110005420A (en) A kind of underground structure and construction method of underground excavation and reverse construction of arch cover
JP4272228B2 (en) Construction method of underground structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180403

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181114

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20181218

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190215

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20190402