[go: up one dir, main page]

JP2017089158A - Management method of secondary slime treatment - Google Patents

Management method of secondary slime treatment Download PDF

Info

Publication number
JP2017089158A
JP2017089158A JP2015217677A JP2015217677A JP2017089158A JP 2017089158 A JP2017089158 A JP 2017089158A JP 2015217677 A JP2015217677 A JP 2015217677A JP 2015217677 A JP2015217677 A JP 2015217677A JP 2017089158 A JP2017089158 A JP 2017089158A
Authority
JP
Japan
Prior art keywords
hole
slime treatment
stabilizing liquid
sand content
slime
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015217677A
Other languages
Japanese (ja)
Other versions
JP6693090B2 (en
Inventor
直之 喜多
Naoyuki Kita
直之 喜多
真 荒川
Makoto Arakawa
真 荒川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2015217677A priority Critical patent/JP6693090B2/en
Publication of JP2017089158A publication Critical patent/JP2017089158A/en
Application granted granted Critical
Publication of JP6693090B2 publication Critical patent/JP6693090B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

【課題】安定液を満たした掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を施工する方法において、2次スライム処理終了後の安定液を静置しても、孔底にスライムが堆積することのない、2次スライム処理の管理方法を提供する。【解決手段】安定液を満たした掘削孔にて1次スライム処理および2次スライム処理を実施し、掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を構築する方法における、2次スライム処理の管理方法であって、孔底近傍の安定液の砂分率の測定を、一定時間ごとに繰り返し行い、前記孔底近傍の安定液の砂分率が施工現場ごとに定められた管理基準値以下となることを確認する工程と、少なくとも孔口近傍の安定液の砂分率の測定を行い、同時刻に測定した孔底近傍の安定液の砂分率と同一もしくは近似する数値となることを確認する工程とを、2次スライム処理の実施中に行い、両工程の確認が終了するまで2次スライム処理を継続する。【選択図】図2PROBLEM TO BE SOLVED: To construct a cast-in-place concrete structure by placing concrete in an excavation hole filled with a stabilizer, even if the stabilizer after the completion of the secondary slime treatment is allowed to stand, slime is placed on the bottom of the hole. Provides a method of managing secondary slime treatment without depositing. SOLUTION: A secondary in a method of performing a primary slime treatment and a secondary slime treatment in a drilling hole filled with a stabilizing liquid and placing concrete in the drilling hole to construct a cast-in-place concrete structure. This is a slime treatment management method in which the measurement of the sand content of the stabilizing liquid near the bottom of the hole is repeated at regular intervals, and the sand content of the stabilizing liquid near the bottom of the hole is determined for each construction site. The step of confirming that the value is below the reference value and at least the sand content of the stabilizer near the hole mouth are measured, and the value is the same as or close to the sand content of the stabilizer near the bottom of the hole measured at the same time. The step of confirming the result is performed during the execution of the secondary slime treatment, and the secondary slime treatment is continued until the confirmation of both steps is completed. [Selection diagram] Fig. 2

Description

本発明は、安定液を満たした掘削孔にて1次スライム処理および2次スライム処理を実施する際の、2次スライム処理の管理方法に関する。   The present invention relates to a management method for secondary slime treatment when primary slime treatment and secondary slime treatment are performed in an excavation hole filled with a stabilizing liquid.

地盤中に現場打ちコンクリート杭や地中連続壁等のコンクリート構造物を構築するにあたり、安定液を供給しつつ地中を掘削して柱状もしくは溝状の掘削孔を形成する工法では、掘削完了後、掘削孔内の安定液を所要時間静置して安定液中に浮遊する土砂分を沈殿させ、孔底に堆積してスライムとなった土砂分を除去する1次スライム処理を行う。また、コンクリートの打設前には、1次スライム処理後に孔底に堆積してスライムとなった沈降速度の遅い砂分を、安定液と共に吸引除去する2次スライム処理を行う。   When constructing concrete structures such as cast-in-place concrete piles or continuous underground walls in the ground, a method of excavating the ground while supplying a stable liquid to form columnar or grooved drilling holes is necessary. Then, the stabilization liquid in the excavation hole is allowed to stand for a required time to precipitate sediments floating in the stabilization liquid, and a primary slime treatment is performed to remove sediments deposited on the bottom of the hole and becoming slime. In addition, before placing concrete, a secondary slime treatment is performed in which sand with a slow sedimentation rate deposited on the bottom of the hole after the primary slime treatment and formed into a slime is sucked and removed together with a stabilizing solution.

そして、例えば、特許文献1には、杭孔の底部に堆積したスライムを杭孔内の安定液とともに吸引し、杭孔外に排出するためのスライム除去装置が開示されている。   For example, Patent Document 1 discloses a slime removing device for sucking slime deposited on the bottom of a pile hole together with a stabilizing liquid in the pile hole and discharging it outside the pile hole.

このようなスライム除去装置を利用した2次スライム処理の管理方法は、一般に、スライム処理装置から排出される孔底近傍の安定液に対して砂分率の測定を行う、もしくは、孔底近傍の安定液を採取して砂分率の測定を行う、などして孔底近傍における安定液の砂分率が、所定の管理基準値以下になるまでスライムの除去処理を継続する、というものである。   The management method of the secondary slime treatment using such a slime removing device generally measures the sand fraction of the stable liquid near the hole bottom discharged from the slime treatment device, or the vicinity of the hole bottom. The removal of slime is continued until the sand content of the stable liquid near the bottom of the hole is equal to or lower than a predetermined control reference value by collecting the stable liquid and measuring the sand content. .

しかし、上記の2次スライム処理の管理方法では、杭孔中間部や杭孔口部近傍の安定液について状態把握を行っていないため、2次スライム処理終了後からコンクリートの打設作業前の間に不慮の時間を要した場合、浮遊していた砂分が沈降して孔底にスライムが堆積する可能性があり、構築後のコンクリート構造物に対して、スライムに起因する沈下や先端支持力の低下を招く恐れが生じる。   However, since the secondary slime treatment management method does not grasp the state of the stabilizing liquid in the middle part of the pile hole or in the vicinity of the mouth part of the pile hole, it does not occur until the concrete is placed after the secondary slime process. If it takes an unexpected amount of time, the suspended sand may settle and slime may accumulate on the bottom of the hole. There is a risk of lowering.

このような中、例えば、特許文献2には、杭孔の底部に注入袋体を配置した状態で上方にコンクリートを打設し、コンクリートの硬化後に注入袋体内に注入材を注入して杭先端から下方に向けて膨張させることで孔底地盤にプレロードを与え、孔底地盤をあらかじめ圧縮させて杭先端の強化を図る、場所打ちコンクリート杭工法が開示されている。   Under such circumstances, for example, in Patent Document 2, concrete is placed upward with an injection bag body arranged at the bottom of a pile hole, and an injection material is injected into the injection bag body after the concrete is hardened to A cast-in-place concrete pile construction method is disclosed in which preload is applied to the hole bottom ground by expanding downward from the bottom, and the hole bottom ground is pre-compressed to strengthen the pile tip.

特開2000−120067号公報JP 2000-120067 A 特許3688546号公報Japanese Patent No. 3688546

特許文献2に開示された方法によれば、注入袋体の膨張により、注入袋体の下方にスライムが存在していたとしてもこれを押出し排出することができ、また、杭先端地盤を圧縮させることにより、地盤の応力開放の改善を図ることができるため、場所打ちコンクリート杭の初期沈下を小さくすることが可能となる。   According to the method disclosed in Patent Document 2, due to the expansion of the infusion bag body, even if slime is present below the infusion bag body, it can be extruded and discharged, and the pile tip ground is compressed. As a result, the stress relief of the ground can be improved, so that the initial settlement of the cast-in-place concrete pile can be reduced.

しかし、特許文献2の方法では、杭先端地盤にプレロード圧を作用させる作業が煩雑であるとともに、プレロード圧の大きさや圧力保持時間の長さ等を設定する方法が確立されておらず、また、孔底に堆積したスライムを十分押し出し排出できたか否かについて確認することも容易ではない。   However, in the method of Patent Document 2, the work for applying the preload pressure to the pile tip ground is complicated, and the method for setting the size of the preload pressure or the length of the pressure holding time has not been established. It is not easy to confirm whether or not the slime deposited on the hole bottom has been sufficiently extruded and discharged.

本発明は、かかる課題に鑑みなされたものであって、その主な目的は、安定液を満たした掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を施工する方法において、2次スライム処理終了後の安定液を静置しても、孔底にスライムの堆積をほぼ生じない、2次スライム処理の管理方法を提供することである。   The present invention has been made in view of such a problem, and its main purpose is to provide a secondary in a method of placing a concrete in a drilling hole filled with a stabilizing liquid to construct a structure of cast-in-place concrete. It is to provide a management method for secondary slime treatment in which the slime is hardly deposited on the bottom of the hole even if the stabilizing liquid after the slime treatment is left standing.

かかる目的を達成するため、本発明の2次スライム処理の管理方法は、安定液を満たした掘削孔にて1次スライム処理および2次スライム処理を実施した後、前記掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を構築する方法における、2次スライム処理の管理方法であって、孔底近傍の安定液の砂分率の測定を、一定時間ごとに繰り返し行い、前記孔底近傍の安定液の砂分率が施工現場ごとに定められた管理基準値以下となることを確認する工程と、少なくとも孔口近傍の安定液の砂分率の測定を行い、同時刻に測定した孔底近傍の安定液の砂分率と同一もしくは近似する数値となることを確認する工程と、を備え、両工程の確認が終了するまで、前記2次スライム処理を継続することを特徴とする。   In order to achieve such an object, the secondary slime treatment management method of the present invention performs the primary slime treatment and the secondary slime treatment in the excavation hole filled with the stabilizing liquid, and then places concrete in the excavation hole. In the method of constructing a cast-in-place concrete structure, the secondary slime treatment management method, wherein the measurement of the sand content of the stabilizing liquid in the vicinity of the hole bottom is repeated at regular intervals, The process of confirming that the sand content of the nearby stable liquid is less than or equal to the control standard value set for each construction site, and at least measuring the sand content of the liquid near the hole and measuring at the same time A step of confirming that the sand content of the stabilizing liquid near the bottom of the hole is equal to or close to a numerical value, and the secondary slime treatment is continued until the confirmation of both steps is completed. .

上述する本発明の2次スライム処理の管理方法によれば、前記孔底近傍の安定液の砂分率が施工現場ごとに定められた管理基準値以下となることを確認するとともに、孔口近傍の安定液の砂分率を孔底近傍の安定液の砂分率と同一もしくは近似する数値とすることで、2次スライム処理終了後の掘削孔内全体の安定液について、砂分率を施工現場ごとに定められた管理基準値以下とし、時間の経過とともに沈降する可能性の高い砂分が大幅に低減された状態にすることができる。これにより、2次スライム処理後からコンクリート打設作業までに多大な時間を要した場合にも、コンクリートの打設直前時における掘削孔の孔底には、スライムの堆積をほぼ生じない。したがって、構築後の構造物に対して、スライムに起因する沈下および先端支持力の低下を抑制することが可能となる。   According to the management method of the secondary slime treatment of the present invention described above, it is confirmed that the sand fraction of the stabilizing liquid near the hole bottom is equal to or less than the management reference value determined for each construction site, and near the hole opening. By setting the sand fraction of the stable liquid of the same as or close to the sand percentage of the stable liquid near the bottom of the hole, the sand fraction is applied to the stable liquid in the entire borehole after the secondary slime treatment. It can be set below the control standard value determined for each site, and the sand content that is likely to sink with time can be greatly reduced. As a result, even when a great amount of time is required from the secondary slime treatment to the concrete placing operation, the slime is hardly deposited on the bottom of the excavation hole immediately before the concrete placement. Accordingly, it is possible to suppress settlement due to slime and a decrease in tip support force with respect to the structure after construction.

また、2次スライム処理終了後の安定液は、掘削孔内全域の砂分率が一様に管理された状態にあるため、コンクリート打設時の置換不良を生じることがなく、高品質の現場打ちコンクリート造の構造物を構築することが可能となる。   In addition, the stable liquid after the completion of the secondary slime treatment is in a state where the sand content rate in the entire excavation hole is uniformly controlled, so that there is no occurrence of replacement failure when placing concrete and a high quality site It becomes possible to construct a cast concrete structure.

本発明の2次スライム処理の管理方法は、安定液を満たした掘削孔にて1次スライム処理および2次スライム処理を実施した後、前記掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を構築する方法における、2次スライム処理の管理方法であって、孔底近傍の安定液の砂分率の測定を、一定時間ごとに繰り返し行い、前記孔底近傍の安定液の砂分率が施工現場ごとに定められた管理基準値以下となることを確認する工程と、少なくとも孔底近傍の安定液の比重と孔口近傍の安定液の比重の測定を行い、同時刻に測定した両者の比重が、施工現場ごとに定められた管理基準値の範囲内に収まることを確認する工程と、を備え、両工程の確認が終了するまで、前記2次スライム処理を継続することを特徴とする。   The management method of the secondary slime treatment of the present invention is the method of cast-in-place concrete construction in which after the primary slime treatment and the secondary slime treatment are carried out in the excavation hole filled with the stabilizing liquid, concrete is placed in the excavation hole. A secondary slime treatment management method in a method for constructing a structure, in which the measurement of the sand content of the stable liquid near the hole bottom is repeated at regular intervals, and the sand content of the stable liquid near the hole bottom is measured. The process to confirm that the rate is below the control standard value set for each construction site, and at least the specific gravity of the stable liquid near the hole bottom and the specific gravity of the stable liquid near the hole mouth were measured and measured at the same time A step of confirming that the specific gravity of both falls within the range of the control standard value determined for each construction site, and continuing the secondary slime treatment until the confirmation of both steps is completed. And

上述する本発明の2次スライム処理の管理方法によれば、比重と砂分率が相関関係にあることから、2次スライム処理の管理を砂分率のみで行う方法と同様に、スライムの堆積抑制効果やコンクリートとの良好な置換機能を保持効果が得られるとともに、2次スライム処理終了後の安定液が、掘削孔内全域の比重を一様に管理された状態にあるため、施工現場で地盤条件のことなる掘削孔ごとに、掘削孔内全体の安定液が良好な性状を有しているか否かの評価を行うことが可能となる。   According to the management method of the secondary slime treatment of the present invention described above, since the specific gravity and the sand content rate are correlated, the slime deposition is performed in the same manner as the method in which the secondary slime treatment is managed only by the sand content rate. In addition to providing a restraining effect and a good replacement function with concrete, the stabilizing liquid after the completion of the secondary slime treatment is in a state where the specific gravity of the entire borehole is uniformly controlled. For each excavation hole having different ground conditions, it is possible to evaluate whether or not the stable liquid in the entire excavation hole has good properties.

本発明によれば、2次スライム処理終了後の掘削孔内全体の安定液を、時間の経過とともに沈降する可能性の高い砂分が大幅に低減された状態にすることができる。これにより、2次スライム終了後からコンクリート打設作業までに多大な時間を要した場合にも、掘削孔の孔底にスライムの堆積をほぼ生じることなく、構築後の構造物に対して、スライムに起因する沈下および先端支持力の低下を抑制することが可能となる。   ADVANTAGE OF THE INVENTION According to this invention, the stable liquid of the whole excavation hole after the completion | finish of a secondary slime process can be made into the state by which the sand component with high possibility of settling with time progress was reduced significantly. As a result, even when a great amount of time is required from the completion of the secondary slime to the concrete placing operation, the slime is hardly deposited on the bottom of the excavation hole, and the slime can be applied to the constructed structure. It is possible to suppress the settlement due to the lowering and the decrease in the tip support force.

1次スライム処理終了後の掘削孔を示す図である。It is a figure which shows the excavation hole after completion | finish of a primary slime process. 掘削孔内の安定液の状態を示すグラフである。It is a graph which shows the state of the stable liquid in a digging hole. 2次スライム処理実施中の掘削孔を示す図である。It is a figure which shows the excavation hole under secondary slime process implementation.

本発明の2次スライム処理の管理方法は、地盤中に場所打ちコンクリート造の構造物を構築する工法であって、安定液が満たされた掘削孔にて1次スライム処理および2次スライム処理を実施する工程を含む工法に採用するものである。したがって、アースドリル工法、リバース工法、オールケーシング工法等の場所打ち杭工法や地中連続壁工法に採用可能であり、掘削孔の形状も、柱状もしくは溝状のいずれでもよく、構築される構造物も地中連続壁や基礎杭等いずれでもよい。   The management method of the secondary slime treatment of the present invention is a construction method for constructing a cast-in-place concrete structure in the ground, and the primary slime treatment and the secondary slime treatment are performed in the excavation hole filled with the stabilizing liquid. It is adopted for the construction method including the process to be carried out. Therefore, it can be applied to cast-in-place pile method such as earth drill method, reverse method, all-casing method and underground continuous wall method, and the shape of the drilling hole can be either columnar or grooved, Any of underground underground walls and foundation piles may be used.

また、掘削孔を満たす安定液は、ベントナイト安定液やポリマー安定液等いずれでもよく、地盤状況や打設しようとするコンクリートの性状等に応じて、孔壁の安定保持性、掘削土砂の分離性およびコンクリートの置換性を考慮し、適宜配合したものを採用すればよい。   The stabilizing liquid that fills the excavation hole may be either a bentonite stabilizing liquid or a polymer stabilizing liquid. Depending on the ground conditions and the properties of the concrete to be placed, the stability of the hole wall and the separability of the excavated soil In consideration of the substitutability of concrete and concrete, those appropriately blended may be adopted.

本実施の形態では、アースドリル工法にて場所打ちコンクリート杭を構築するべく、地中に柱状の掘削孔を形成し、その内方をベントナイト系の安定液で満たした場合を事例として、図1〜図3を参照しつつ以下に説明する。   In this embodiment, in order to construct a cast-in-place concrete pile by an earth drill method, a columnar excavation hole is formed in the ground, and the inside is filled with a bentonite-based stabilizing liquid as an example. Description will be given below with reference to FIG.

図1で示すように、掘削孔1は、対象地盤の表層7に対してケーシング3を建込んだ後、土質に適合した安定液2を注入しながら図示しないドリリングバケットを回転させて掘削されたもので、支持層8まで根入れ掘削されている。また、掘削作業の終了後には、一定時間静置して安定液2中に浮遊する土砂分を自然沈降させ、掘削孔1の孔底に堆積してスライムとなった土砂分を、底浚いバケット等にて地上に排出する1次スライム処理を行っている。   As shown in FIG. 1, the excavation hole 1 was excavated by rotating a drilling bucket (not shown) while injecting a stabilizing liquid 2 suitable for the soil after the casing 3 was built on the surface layer 7 of the target ground. It has been excavated to the support layer 8. In addition, after the excavation work is finished, the soil and sand floating in the stabilizing liquid 2 is allowed to stand for a certain period of time, and the sediment is deposited on the bottom of the excavation hole 1 to form a slime. Etc. The primary slime treatment discharged to the ground is performed.

掘削孔1の安定液2中には、図2(a)の深度と比重の関係を示すグラフからわかるように、1次スライム処理終了時(時点t1)に沈降しなかった沈降速度の遅い微細な砂分が浮遊しており、深度方向全体の比重が高い状態にある。そして、掘削孔1の安定液2を所定時間静置すると(時点t2)、安定液2中を浮遊していた微細な砂分が徐々に沈降するため、深度方向全体で比重も徐々に低下し、沈降した砂分がスライムとして孔底に堆積していく様子がわかる。   As can be seen from the graph showing the relationship between the depth and the specific gravity in FIG. 2 (a), the stable liquid 2 in the excavation hole 1 has a fine sedimentation rate that has not settled at the end of the primary slime treatment (time point t1). The sand is floating and the specific gravity in the depth direction is high. When the stabilizing liquid 2 in the excavation hole 1 is allowed to stand for a predetermined time (time point t2), the fine sand that has floated in the stabilizing liquid 2 gradually settles, so that the specific gravity gradually decreases in the entire depth direction. It can be seen that the sedimented sand accumulates on the bottom of the hole as slime.

このため、掘削孔1に対する2次スライム処理は、1次スライム処理後に安定液2を所定時間静置して浮遊していた沈降速度の遅い砂分の沈降が進んだところ(時点t2)で開始する。なお、2次スライム処理を開始する時刻(時点t2)の選定方法としては、例えば、図1で示すように、掘削孔1の孔口近傍における特定深度にサンプラー61を設置し、一定時間ごとに安定液2を採取して比重の定点測定を行う。そして、安定液2中に浮遊する砂分の沈降速度や安定液2の性状、現場状況等を考慮して、2次スライム処理を開始する基準となる比重を予め設定しておき、定点測定した比重が基準となる比重まで低減した時刻を、2次スライム処理を開始する時刻として選定する方法が採用できる。   For this reason, the secondary slime treatment for the excavation hole 1 starts when the sediment of the slow sedimentation speed that has floated by allowing the stabilizing liquid 2 to stand for a predetermined time after the primary slime treatment has progressed (time point t2). To do. In addition, as a selection method of the time (time t2) which starts a secondary slime process, as shown in FIG. Collect the Stabilizer 2 and measure the specific gravity at a fixed point. Then, taking into account the sedimentation speed of the sand floating in the stabilizing liquid 2, the properties of the stabilizing liquid 2, the on-site situation, etc., a specific gravity as a reference for starting the secondary slime treatment was set in advance and fixed point measurement was performed. A method of selecting the time at which the specific gravity is reduced to the reference specific gravity as the time at which the secondary slime process is started can be employed.

2次スライム処理は、図3で示すように、孔底に堆積したスライムを安定液2とともにスライム処理装置4にて吸引し、地上に排出する。このとき、孔底近傍に存在する安定液2の吸引と同時に、安定液供給管5を介して吸引した安定液2と同量の安定液2を追加供給し、掘削孔1内における安定液2の液面を常に一定に保持する。   In the secondary slime treatment, as shown in FIG. 3, the slime deposited on the bottom of the hole is sucked together with the stabilizing liquid 2 by the slime treatment device 4 and discharged to the ground. At this time, simultaneously with the suction of the stabilizing liquid 2 existing in the vicinity of the hole bottom, the same amount of the stabilizing liquid 2 as the stabilizing liquid 2 sucked through the stabilizing liquid supply pipe 5 is additionally supplied. The liquid level is always kept constant.

なお、追加供給する安定液2は、新たに安定液2として作液した新液、もしくは地上に排出したスライムを含んだ安定液2を、図示しない安定液プラントにて再生したリサイクル液のいずれを採用したものでもよい。また、スライム処理装置4は、一般に2次スライム処理に採用されているサンドポンプ方式、エアリフト方式、サクションポンプ方式等、掘削孔1の孔底に堆積したスライムを安定液2とともに吸引し、地上に排出できる装置であればいずれを採用してもよい。   The additionally supplied stabilizing liquid 2 is either a new liquid that has been newly produced as the stabilizing liquid 2 or a recycled liquid that has been regenerated at a stabilizing liquid plant (not shown) from the stabilizing liquid 2 containing slime discharged to the ground. It may be adopted. Further, the slime treatment device 4 sucks the slime deposited on the bottom of the excavation hole 1 together with the stabilizing liquid 2, such as a sand pump method, an air lift method, a suction pump method, etc., which are generally used for the secondary slime treatment, to the ground. Any device that can discharge can be used.

このような2次スライム処理の管理方法は、孔底近傍の安定液2に対して比重と相関関係にある砂分率の測定を一定時間ごとに繰り返し行い、この砂分率が施工現場ごとに定められた管理基準値以下となったところで、2次スライム処理を終了する、という方法である。なお、管理基準値とは、場所打ちコンクリート造の構造物を構築する場合に、施工現場ごとに立てられる施工計画に、安定液の管理方法として記載される数値である。しかし、上述の管理方法では、掘削孔1の孔口部や中間部の砂分率を確認していないため、孔底近傍の安定液2の砂分率が、掘削孔1中の安定液2全体の砂分率を反映しているか否かを評価することができない。   Such a management method for secondary slime treatment is to repeatedly measure the sand content ratio that is correlated with the specific gravity of the stabilizing liquid 2 near the bottom of the hole at regular intervals. This is a method in which the secondary slime process is terminated when the value becomes equal to or less than a predetermined management reference value. The management reference value is a numerical value described as a management method for the stable liquid in a construction plan established for each construction site when a cast-in-place concrete structure is constructed. However, in the above management method, since the sand content ratio of the hole portion and the intermediate portion of the excavation hole 1 is not confirmed, the sand content ratio of the stable liquid 2 near the bottom of the hole is equal to the stable liquid 2 in the excavation hole 1. It is not possible to evaluate whether the total sand content is reflected.

一方で、掘削孔1内の安定液2について発明者らは、管理基準値以下まで低減した孔底近傍の安定液2の砂分率と同一もしくは近似する数値まで、孔口近傍における安定液2の砂分率が低減すると、掘削孔1内の安定液2全体について、その砂分率を管理基準値以下とすることができ、これに伴って時間の経過とともに沈降する可能性の高い砂分を大幅に低減した状態とすることが可能となる、との知見を得ている。   On the other hand, regarding the stabilizing liquid 2 in the excavation hole 1, the inventors have determined that the stabilizing liquid 2 in the vicinity of the hole is up to a numerical value that is the same as or close to the sand fraction of the stabilizing liquid 2 in the vicinity of the hole bottom that has been reduced to the control standard value or less. If the sand content ratio of the slag is reduced, the sand content ratio of the entire stabilizing liquid 2 in the excavation hole 1 can be reduced to the control standard value or less. It has been found that it is possible to achieve a greatly reduced state.

そこで、本実施の形態では、孔底近傍の安定液2だけでなく掘削孔1内全体の安定液2中の砂分率を把握し、図2(b)の深度と砂分率の関係を示すグラフのように、2次スライム処理終了後(時点t3)の安定液2において、砂分率が深度方向に一様な状態となるよう、以下に示す2次スライム処理の管理方法を採用する。   Therefore, in this embodiment, not only the stabilizing liquid 2 in the vicinity of the hole bottom but also the sand content ratio in the stabilizing liquid 2 in the entire excavation hole 1 is grasped, and the relationship between the depth and the sand content ratio in FIG. As shown in the graph, the management method of the secondary slime treatment shown below is adopted so that the sand content rate is uniform in the depth direction in the stabilizing liquid 2 after the completion of the secondary slime treatment (time point t3). .

本実施の形態における2次スライム処理の管理方法は、2次スライム処理の管理として現在実施されている、孔底近傍の安定液2に対して砂分率の測定を一定時間ごとに繰り返し行い、この砂分率が施工現場ごとに定められた管理基準値以下となることを確認する工程(以下、従来工程という)を実施した上で、第1の実施の形態もしくは第2の実施の形態で示す工程を追加して行うものである。   The management method of the secondary slime treatment in the present embodiment is carried out as the management of the secondary slime treatment, repeatedly measuring the sand fraction for the stabilizing liquid 2 in the vicinity of the hole bottom at regular intervals, In the first embodiment or the second embodiment, after carrying out a process (hereinafter referred to as a conventional process) for confirming that the sand content rate is less than or equal to the management standard value determined for each construction site. The process shown is added.

〈第1の実施の形態〉
本実施の形態の2次スライム処理の管理方法では、孔底近傍の安定液2の砂分率を測定する従来工程に追加して、少なくとも孔口近傍の安定液2の砂分率の測定を行い、孔口近傍の安定液2の砂分率が同時刻に測定した孔底近傍の安定液2の砂分率と同一もしくは近似する数値となることを確認する工程を実施する。そして、孔底近傍の安定液2の砂分率が施工現場ごとに定められた管理基準値以下となることが確認され、かつ、孔口近傍の安定液2の砂分率が、同時刻に測定した孔底近傍の安定液2の砂分率と同一もしくは近似する数値となったことが確認されるまで、2次スライム処理を継続して行う。
<First Embodiment>
In the management method of the secondary slime treatment of the present embodiment, in addition to the conventional process for measuring the sand fraction of the stabilizing liquid 2 near the hole bottom, at least the sand fraction of the stabilizing liquid 2 near the hole mouth is measured. And performing a step of confirming that the sand fraction of the stabilizing liquid 2 near the hole mouth is a numerical value that is the same as or close to the sand percentage of the stabilizing liquid 2 near the hole bottom measured at the same time. And it is confirmed that the sand content rate of the stabilizing liquid 2 near the hole bottom is equal to or less than the control reference value determined for each construction site, and the sand content rate of the stabilizing liquid 2 near the hole mouth is the same time. The secondary slime treatment is continued until it is confirmed that the measured value is the same as or close to the sand fraction of the stabilizing liquid 2 in the vicinity of the hole bottom.

なお、砂分率の測定は、例えば図3で示すように、孔口近傍と孔底近傍にサンプラー61、62を設置し、一定時間ごとにサンプルを採取して地上にて測定する定点測定を行うとよい。孔口近傍に設置するサンプラー61は、先に述べた2次スライム処理を開始する時刻を選定するべく比重測定を行った特定深度と同一の深度に設定するとよい。また、孔底近傍に設置するサンプラー62は、従来工程にて砂分率を測定する際に、施工現場ごとで立てられる施工計画に安定液の管理方法として定められた深度に設定する。   For example, as shown in FIG. 3, the sand fraction is measured by fixed point measurement in which samplers 61 and 62 are installed in the vicinity of the hole mouth and the bottom of the hole, samples are taken at regular intervals and measured on the ground. It is good to do. The sampler 61 installed in the vicinity of the hole opening may be set to the same depth as the specific depth at which the specific gravity measurement was performed in order to select the time to start the secondary slime process described above. Moreover, the sampler 62 installed in the vicinity of the hole bottom is set to a depth determined as a management method of the stable liquid in a construction plan established for each construction site when measuring the sand content ratio in the conventional process.

こうすると、コンクリートの打設前に実施する、鉄筋かごを掘削孔1内に建込むとともにトレミー管を挿入するといった作業に手間を要した場合や、不慮の事態によりコンクリートの打設前に大幅な時間を要した場合にも、コンクリートの打設直前時における掘削孔1の孔底に、スライムの堆積をほぼ生じない。これにより、安定液2を長時間静置した場合であっても、従来行われていた、孔底近傍における安定液2を撹拌しスライムを拡散させた上で、コンクリートを打設するといった煩雑な作業を行うことなく、構築後の場所打ちコンクリート杭に対して、スライムに起因する先端支持力の低下を抑制することが可能となる。   In this case, it takes a lot of work to construct the rebar cage in the excavation hole 1 and insert the tremely pipe before the concrete is placed. Even when time is required, slime is hardly deposited on the bottom of the excavation hole 1 immediately before the concrete is placed. Thereby, even when the stabilizing liquid 2 is left standing for a long time, it is a troublesome practice to place the concrete after stirring the stabilizing liquid 2 in the vicinity of the hole bottom and diffusing the slime. Without performing the work, it is possible to suppress a decrease in the tip support force due to the slime for the cast-in-place concrete pile after construction.

また、2次スライム処理終了後の安定液2は、掘削孔内全域の砂分率が一様に管理された状態にあるため、安定液が打設中のコンクリートの流動性を損なって巻き込まれるといったコンクリート打設時の置換不良を生じることがなく、高品質の現場打ちコンクリート杭を構築することが可能となる。   In addition, since the stabilizing liquid 2 after the completion of the secondary slime treatment is in a state where the sand content ratio in the entire excavation hole is uniformly controlled, the stabilizing liquid is entrained by impairing the fluidity of the concrete being placed. Therefore, it is possible to construct a high quality on-site cast-in-place concrete pile without causing a defective replacement at the time of placing the concrete.

なお、孔口近傍の安定液2の砂分率が、同時刻に測定した孔底近傍の安定液2の砂分率と近似する数値となったことの判定方法はいずれでもよいが、例えば、安定液2の配合や作液時の性状、地盤条件や施工条件等を考慮した上で許容範囲を設定する。そして、孔口近傍の安定液2の砂分率と同時刻に測定した孔底近傍の安定液2の砂分率との差が、設定した許容範囲内に収まるか否かで判定してもよい。   Any method may be used to determine that the sand fraction of the stabilizing liquid 2 near the hole mouth is a numerical value that approximates the sand fraction of the stabilizing liquid 2 near the hole bottom measured at the same time. The allowable range is set in consideration of the composition of the stabilizing liquid 2, the properties at the time of liquid preparation, the ground conditions and the construction conditions. Even if the difference between the sand content of the stabilizing liquid 2 near the hole mouth and the sand content of the stabilizing liquid 2 near the hole bottom measured at the same time falls within the set allowable range. Good.

〈第2の実施の形態〉
先にも述べたように、比重と砂分率は相関関係にあることから、第2の実施の形態では、図2(a)の深度と比重の関係を示すグラフのように、2次スライム処理終了後(時点t3)の安定液2において、比重が深度方向に一様な状態となるよう、2次スライム処理の管理方法に砂分率と比重を用いる。
<Second Embodiment>
As described above, since the specific gravity and the sand content rate are in a correlation, in the second embodiment, as shown in the graph showing the relationship between the depth and the specific gravity in FIG. In the stabilizing liquid 2 after the end of the treatment (time point t3), the sand fraction and the specific gravity are used in the management method of the secondary slime treatment so that the specific gravity becomes uniform in the depth direction.

具体的には、孔底近傍の安定液2の砂分率を測定する従来工程に追加して、孔底近傍の安定液2の比重と孔口近傍の安定液2の比重の測定を行い、同時刻に測定した両者の比重が、施工現場ごとで定められた管理基準値の範囲内に収まることを確認する工程を実施する。そして、孔底近傍の安定液2の砂分率が管理基準値以下になることが確認され、かつ、孔口近傍の安定液2の比重と同時刻に測定した孔底近傍の安定液2の比重がともに、管理基準値の範囲内に収まったことが確認されるまで、2次スライム処理を継続して行う。   Specifically, in addition to the conventional process of measuring the sand fraction of the stabilizing liquid 2 near the hole bottom, the specific gravity of the stabilizing liquid 2 near the hole bottom and the specific gravity of the stabilizing liquid 2 near the hole mouth are measured, A process is performed to confirm that the specific gravity of both measured at the same time falls within the range of the management standard value determined for each construction site. Then, it is confirmed that the sand fraction of the stabilizing liquid 2 near the hole bottom is less than the control reference value, and the stability liquid 2 near the hole bottom measured at the same time as the specific gravity of the stabilizing liquid 2 near the hole mouth. The secondary slime process is continued until it is confirmed that both specific gravity values are within the control standard value range.

なお、比重の測定は第1の実施の形態と同様な深度位置で、孔口近傍と孔底近傍にサンプラー61、62を設置し、一定時間ごとにサンプルを採取して地上にて測定する定点測定を行うとよい。   The specific gravity is measured at the same depth position as in the first embodiment, samplers 61 and 62 are installed near the hole mouth and near the hole bottom, samples are taken at regular intervals and measured on the ground. It is good to make measurements.

こうすると、第1の実施の形態で示した管理方法と同様に、2次スライム処理の終了後からコンクリートの打設直前までに多大な時間を要した場合にも、掘削孔1の孔底にスライムの堆積をほぼ生じることがなく、コンクリート打設時の置換不良を生じることもない。また、掘削孔内全域の比重が一様に管理された状態にあるため、コンクリートの打設直前時まで、孔壁の崩落を安定して抑制することが可能となる。   In this way, as in the management method shown in the first embodiment, even when a great amount of time is required from the end of the secondary slime treatment to just before the concrete is placed, Slime does not almost accumulate, and there is no substitution failure when placing concrete. In addition, since the specific gravity of the entire area of the excavation hole is uniformly controlled, it is possible to stably suppress the collapse of the hole wall until just before the concrete is placed.

さらに、2次スライム処理の管理方法は、砂分率だけでなく比重を取り入れることから、施工現場で地盤条件のことなる掘削孔1ごとで、掘削孔1内全体の安定液2が良好な性状を有しているか否かの判定を行うことが可能となる。したがって、例えば、孔底近傍および孔口近傍の安定液2の両者の比重が、あらかじめ設定した時刻を経過しても、管理基準値の範囲内に収まらない場合には、掘削孔1内の安定液2を全量入れ替えるというように、良液置換の必要性を判断する指標とすることも可能となる。   Furthermore, since the secondary slime treatment management method incorporates not only the sand fraction but also the specific gravity, the stable liquid 2 in the entire excavation hole 1 is in good condition for each excavation hole 1 that has different ground conditions at the construction site. It is possible to determine whether or not Therefore, for example, if the specific gravity of the stabilizing liquid 2 in the vicinity of the hole bottom and in the vicinity of the hole does not fall within the control reference value range even after the preset time has elapsed, It can be used as an index for determining the necessity of good liquid replacement, such as replacing the entire amount of the liquid 2.

本発明における2次スライム処理の管理方法は、上記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲で種々の変更が可能である。   The management method of the secondary slime process in the present invention is not limited to the above embodiment, and various modifications can be made without departing from the spirit of the present invention.

例えば、本実施の形態では、孔底近傍および孔口近傍の2地点にて砂分率および比重を測定したが、これらに追加して掘削孔1の深度方向に異なる位置に複数の測定点を設けてもよい。   For example, in the present embodiment, the sand fraction and specific gravity were measured at two points near the bottom of the hole and near the hole mouth, but in addition to these, a plurality of measurement points were set at different positions in the depth direction of the borehole 1. It may be provided.

また、砂分率の測定方法は、電気比抵抗センサを用いる方法や砂分測定器を用いる方法等いずれを採用してもよく、同様に、比重の測定方法も、マッドバランスを用いる方法や浮き子式比重計を用いる方法等いずれを採用してもよい。このように、掘削孔1の深度方向に異なる位置に複数の設置された測定点の安定液2について、同時刻の砂分率および比重を測定できる方法であれば、原位置にて測定する方法もしくはサンプルを採取して地上にて測定する方法のいずれの測定方法を用いてもよい。   In addition, the sand percentage measurement method may employ either a method using an electrical resistivity sensor or a method using a sand content meter. Similarly, the specific gravity measurement method may be a method using mud balance or a float. Any method such as a method using a child type hydrometer may be adopted. Thus, if it is a method which can measure the sand fraction and specific gravity of the same time about the stabilizing liquid 2 of the several measurement point installed in the position which is different in the depth direction of the excavation hole 1, the method of measuring in the original position Alternatively, any measurement method of collecting a sample and measuring on the ground may be used.

さらに、サンプルを採取するにあたり、孔底近傍の安定液2については、サンプラーを用いて採取する方法、スライム処理装置4から排出される安定液2を採取する方法のいずれを採用してもよい。   Furthermore, when collecting the sample, either the method of collecting using the sampler or the method of collecting the stabilizing solution 2 discharged from the slime treatment device 4 may be adopted for the stabilizing solution 2 near the hole bottom.

また、本実施の形態では、2次スライム処理の終了後に鉄筋かごの建込みを行う方法を示したが、鉄筋かごの建込みを行った後、2次スライム処理を実施する工法に、2次スライム処理の管理方法を採用してもよい。   Moreover, in this Embodiment, although the method of erection of a reinforcing steel basket was shown after completion | finish of a secondary slime process, after constructing a reinforcement car, it is secondary to the construction method which implements a secondary slime process. You may employ | adopt the management method of a slime process.

1 掘削孔
2 安定液
3 ケーシング
4 スライム処理装置
5 安定液供給管
61 サンプラー
62 サンプラー
7 表層
8 支持層
DESCRIPTION OF SYMBOLS 1 Drilling hole 2 Stabilizing liquid 3 Casing 4 Slime processing apparatus 5 Stabilizing liquid supply pipe 61 Sampler 62 Sampler 7 Surface layer 8 Support layer

Claims (2)

安定液を満たした掘削孔にて1次スライム処理および2次スライム処理を実施した後、前記掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を構築する方法における、2次スライム処理の管理方法であって、
孔底近傍の安定液の砂分率の測定を、一定時間ごとに繰り返し行い、前記孔底近傍の安定液の砂分率が施工現場ごとに定められた管理基準値以下となることを確認する工程と、
少なくとも孔口近傍の安定液の砂分率の測定を行い、同時刻に測定した孔底近傍の安定液の砂分率と同一もしくは近似する数値となることを確認する工程と、を備え、
両工程の確認が終了するまで、前記2次スライム処理を継続することを特徴とする2次スライム処理の管理方法。
Secondary slime treatment in a method of constructing a cast-in-place concrete structure by placing concrete in the excavation hole after performing primary slime treatment and secondary slime treatment in the excavation hole filled with the stabilizing liquid Management method,
Repeat the measurement of the sand content of the stable liquid near the bottom of the hole at regular intervals to confirm that the sand content of the stable liquid near the bottom of the hole is below the control standard value set for each construction site. Process,
Measuring at least the sand content of the stabilizing liquid near the hole mouth, and confirming that the sand content of the stabilizing liquid near the hole bottom measured at the same time is the same or approximate numerical value,
The secondary slime treatment management method, characterized in that the secondary slime treatment is continued until confirmation of both steps is completed.
安定液を満たした掘削孔にて1次スライム処理および2次スライム処理を実施した後、前記掘削孔にコンクリートを打設して場所打ちコンクリート造の構造物を構築する方法における、2次スライム処理の管理方法であって、
孔底近傍の安定液の砂分率の測定を、一定時間ごとに繰り返し行い、前記孔底近傍の安定液の砂分率が施工現場ごとに定められた管理基準値以下となることを確認する工程と、
少なくとも孔底近傍の安定液の比重と孔口近傍の安定液の比重の測定を行い、同時刻に測定した両者の比重が、施工現場ごとに定められた管理基準値の範囲内に収まることを確認する工程と、を備え、
両工程の確認が終了するまで、前記2次スライム処理を継続することを特徴とする2次スライム処理の管理方法。
Secondary slime treatment in a method of constructing a cast-in-place concrete structure by placing concrete in the excavation hole after performing primary slime treatment and secondary slime treatment in the excavation hole filled with the stabilizing liquid Management method,
Repeat the measurement of the sand content of the stable liquid near the bottom of the hole at regular intervals to confirm that the sand content of the stable liquid near the bottom of the hole is below the control standard value set for each construction site. Process,
At least measure the specific gravity of the stabilizer near the bottom of the hole and the specific gravity of the stabilizer near the hole, and the specific gravity of both measured at the same time should be within the range of the control standard value set for each construction site. A step of confirming,
The secondary slime treatment management method, characterized in that the secondary slime treatment is continued until confirmation of both steps is completed.
JP2015217677A 2015-11-05 2015-11-05 Management method for secondary slime treatment Active JP6693090B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015217677A JP6693090B2 (en) 2015-11-05 2015-11-05 Management method for secondary slime treatment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015217677A JP6693090B2 (en) 2015-11-05 2015-11-05 Management method for secondary slime treatment

Publications (2)

Publication Number Publication Date
JP2017089158A true JP2017089158A (en) 2017-05-25
JP6693090B2 JP6693090B2 (en) 2020-05-13

Family

ID=58769236

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015217677A Active JP6693090B2 (en) 2015-11-05 2015-11-05 Management method for secondary slime treatment

Country Status (1)

Country Link
JP (1) JP6693090B2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4180350A (en) * 1978-03-30 1979-12-25 Early California Industries, Inc. Method for forming foundation piers
JPS58202809A (en) * 1982-05-22 1983-11-26 Shimizu Constr Co Ltd Casting pipe with slurry launch height and density measuring device
JPH0416620A (en) * 1990-05-10 1992-01-21 Taisei Corp Method and device for determining slime and concrete in muddy water
JPH06316929A (en) * 1993-05-10 1994-11-15 Daiyou Kiko Kogyo Kk Method and device for disposal of slime in cast-in-place pile method
JP2012154821A (en) * 2011-01-27 2012-08-16 Taiyu Kk Physical property measuring device for solid-liquid two phase fluid and physical property measuring method therefor
CN103031848A (en) * 2012-12-19 2013-04-10 广东省基础工程公司 Concrete grouting construction method and device for implementing same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4180350A (en) * 1978-03-30 1979-12-25 Early California Industries, Inc. Method for forming foundation piers
JPS58202809A (en) * 1982-05-22 1983-11-26 Shimizu Constr Co Ltd Casting pipe with slurry launch height and density measuring device
JPH0416620A (en) * 1990-05-10 1992-01-21 Taisei Corp Method and device for determining slime and concrete in muddy water
JPH06316929A (en) * 1993-05-10 1994-11-15 Daiyou Kiko Kogyo Kk Method and device for disposal of slime in cast-in-place pile method
JP2012154821A (en) * 2011-01-27 2012-08-16 Taiyu Kk Physical property measuring device for solid-liquid two phase fluid and physical property measuring method therefor
CN103031848A (en) * 2012-12-19 2013-04-10 广东省基础工程公司 Concrete grouting construction method and device for implementing same

Also Published As

Publication number Publication date
JP6693090B2 (en) 2020-05-13

Similar Documents

Publication Publication Date Title
CN104153352B (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN106284313A (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN115045270A (en) Method for constructing cast-in-situ bored pile
CN115030142A (en) Pile foundation engineering construction method
CN107246007B (en) A kind of CFG of construction method
JP4327638B2 (en) Construction method of cast-in-place concrete pile
JP2021080789A (en) Ground backfilling method, and stirring blade
CN100402759C (en) Pile forming method of threaded cast-in-situ pile
CN106545020A (en) A kind of construction method of deep foundation pit support
CN117188443A (en) A construction method for rotary digging cast-in-place piles
JP5268070B2 (en) Slime property management method and automatic slime processing equipment
CN109113051A (en) The method of bored pile construction work efficiency is improved under the conditions of karsts developing area
JP5543628B2 (en) Cement milk solidification strength judgment method, foundation pile construction method, cement milk column construction method, sampling device
JP6645098B2 (en) Removal method of existing pile
JP6693090B2 (en) Management method for secondary slime treatment
JP4327639B2 (en) Construction method of cast-in-place concrete pile
CN113404042A (en) Bridge pile position construction method
JP6409196B2 (en) Hydraulic solidifying material liquid replacement column building method and column building apparatus used for the building method
JP6907611B2 (en) Quality control method for stabilizers
CN116180732A (en) Bored pile construction method
CN110258653A (en) Connecting device and construction method for pile foundation construction in basement
CN211735404U (en) Anti-over-irrigation system for long spiral bored pile
CN116145645A (en) A Construction Method for Verticality Control and Deviation Correction of Grooving in Ultra-deep Connecting Wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20181019

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190722

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190730

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190927

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20191126

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200121

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200317

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200330

R150 Certificate of patent or registration of utility model

Ref document number: 6693090

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150