[go: up one dir, main page]

JP2010071950A - Method for verifying airtightness of framework under construction - Google Patents

Method for verifying airtightness of framework under construction Download PDF

Info

Publication number
JP2010071950A
JP2010071950A JP2008242904A JP2008242904A JP2010071950A JP 2010071950 A JP2010071950 A JP 2010071950A JP 2008242904 A JP2008242904 A JP 2008242904A JP 2008242904 A JP2008242904 A JP 2008242904A JP 2010071950 A JP2010071950 A JP 2010071950A
Authority
JP
Japan
Prior art keywords
construction
airtightness
housing
airtight
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008242904A
Other languages
Japanese (ja)
Other versions
JP5319221B2 (en
Inventor
Yousuke Chiba
陽輔 千葉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Homes Corp
Original Assignee
Asahi Kasei Homes Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Homes Corp filed Critical Asahi Kasei Homes Corp
Priority to JP2008242904A priority Critical patent/JP5319221B2/en
Publication of JP2010071950A publication Critical patent/JP2010071950A/en
Application granted granted Critical
Publication of JP5319221B2 publication Critical patent/JP5319221B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for measuring airtightness of a building under construction, capable of confirming airtightness of a framework after completion of airtightness construction with high simplification and desired precision. <P>SOLUTION: The method for verifying airtightness of a building under construction, capable of verifying airtightness of a framework by generating a pressure difference at an inside and an outside of the building under construction completed up to airtightness construction in which an airtightness layer is formed in a framework after completion of framework construction in which framework is formed by erecting an upper structure on a foundation structure and installing construction materials such as outer walls and roofs on the upper structure to form the framework, includes an airtightness verification process (S3) for generating a differential pressure inside and outside the framework by operating forced exhaust equipment installed on the framework with airtightness construction completed, thus verifying an airtightness state of the framework. As the forced exhaust equipment, there can be utilized a forced exhaust system installed to improve discharge of oil-contaminated water of the construction materials by introducing outside air into an internal space of the framework. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、高気密躯体等の躯体を建設する途上での気密性を検証する方法に関する。   The present invention relates to a method for verifying airtightness in the course of constructing a housing such as a highly airtight housing.

近年、住宅の空調効率を高める等の目的で、高気密躯体が建てられることが多くなっている。
この種の高気密躯体の施工においては、梁や柱等の骨組みからなる上部構造に外壁や屋根を設置して躯体を形成した後に、当該躯体に気密層を形成する気密施工を行い、その後当該躯体及び気密層に貫通孔等を設けて配管や配線を行う設備施工を行うことが一般的になされている。また、当該気密施工と設備施工とは、夫々異なる業者によってなされることが通常である。そうすると、設備施工を完了させて施工の最終段階に至った時点や建物完成後に当該建物の気密性に問題があると発覚した場合、それが気密施工を行った気密施工業者の施工に基づくものであるのか、或いは当該気密施工により形成された気密層に開口を形成した設備施工業者の施工に基づくものであるのか判断することが著しく困難となり、両者の間で無用の争いとなる虞がある。このため、建設途上の躯体においても簡易に気密性を計測する方法の提示が望まれている。
In recent years, highly airtight enclosures are often built for the purpose of increasing the air conditioning efficiency of houses.
In the construction of this type of highly airtight enclosure, after the outer wall and roof are installed on the upper structure consisting of frames such as beams and columns, the enclosure is formed, and then the airtight construction is performed to form an airtight layer on the enclosure. It is common practice to install facilities that provide piping and wiring by providing through holes and the like in the housing and hermetic layer. Further, the airtight construction and the equipment construction are usually performed by different contractors. Then, when it is found that there is a problem with the airtightness of the building after completing the equipment construction and reaching the final stage of construction or after the building is completed, it is based on the construction of the airtight construction contractor who performed the airtight construction. It is extremely difficult to determine whether it is based on the construction of a facility contractor who has an opening in the airtight layer formed by the airtight construction, and there is a risk that there will be a useless dispute between the two. For this reason, presentation of the method of measuring airtightness easily also in the frame in construction is desired.

これに対し、例えば特許文献1には、「躯体の内外に生じる圧力差から躯体の気密を測定する躯体の気密測定方法であって、前記躯体に予め備えられている給排気設備を用いて吸気または排気を行うことにより、前記躯体の内外に圧力差を生じさせて前記躯体の気密を測定する」こととした躯体の気密測定方法が開示されている。
しかしながら、特許文献1は、前述の設備施工が終了した後における気密測定方法を開示するものであって、設備施工前の施工途上躯体の気密検証については開示も示唆もしていない。
特開2001−91397号公報
On the other hand, for example, Patent Document 1 discloses a method of measuring the airtightness of a housing from a pressure difference generated inside and outside the housing, and uses an air supply / exhaust equipment provided in advance in the housing. Alternatively, a method for measuring the airtightness of the housing is disclosed in which a pressure difference is generated inside and outside the housing by exhausting to measure the airtightness of the housing.
However, Patent Document 1 discloses a method for measuring the airtightness after the above-described facility construction is completed, and does not disclose or suggest the airtightness verification of the in-process housing before the facility construction.
JP 2001-91397 A

本発明は、上記事情に鑑みてなされたもので、気密施工完了後の躯体の気密性を簡易且つ所望の精度で確認することができる施工途上の建物の気密測定方法を提供することにある。   This invention is made | formed in view of the said situation, and it is providing the airtight measuring method of the building in the middle of construction which can confirm the airtightness of the housing after completion of airtight construction simply and with desired precision.

上記課題解決のための具体的手段として、本願発明は、
(1)基礎構造上に上部構造を建ち上げると共に当該上部構造に外壁と屋根等の建材とを設置して躯体を形成する躯体施工を終えた後に、当該躯体に気密層を形成する気密施工までを完了した施工途上の建物の内外に圧力差を生じさせて当該躯体の気密性を検証する施工途上建物の気密検証方法であって、
前記気密施工が完了した躯体に設けられる強制排気設備を運転して当該躯体の排気を行うことにより、当該躯体の内外に差圧を生じさせ、該差圧に基づいて当該躯体の気密状態を確認する気密確認工程を備えていることを特徴としている。
このような構成によれば、気密施工が完了した段階で、躯体に設けられる強制排気設備を利用して躯体の気密性を検証することができ、きわめて簡便に躯体の現状での気密状態を確認することができる。ここで、強制排気設備は、建物の竣工後にそのまま利用される給排気設備を利用してもよいし、別途、一時的に強制排気装置を取外し可能に設置して利用しても構わない。但し、住宅等の建物にそのまま設置されたままとなる給排気ファン、台所レンジファン、換気扇、天井扇等の給排気設備を利用する場合は、当然ながら、気密検証を実施する際に、かかる設備が既に備えられていることが必要であり、設備施工がなされていない気密施工終了の段階では、かかる設備を利用できない場合がある。また建物全体の気密性の検証には比較的高出力の排気設備が必要となるので、備わっている設備が高出力の条件を満たさない場合は、気密性測定のための十分な気圧差を得ることができず、高精度の差圧計が必要になったり、測定に著しく手間がかかってしまったりする等のため、結局利用できない場合もある。
一方、強制排気設備を一時的に設置する場合は、気密検証に必要な十分な出力を備えた強制排気設置を設置しなければならないのは当然であるが、更に設置と撤去が容易な装置とされる必要がある。
従って、両者を比較すると、強制排気設備は、建物の竣工後にそのまま利用される給排気設備を利用してもよいが、一時的に強制排気装置を取外し可能に設置して利用する方が好ましい場合が多い。
As a specific means for solving the above problems, the present invention provides:
(1) After building the upper structure on the foundation structure and installing the outer wall and building materials such as a roof on the upper structure to form the housing, until the airtight construction to form an airtight layer on the housing Is a method for verifying the airtightness of a building under construction, in which a pressure difference is generated inside and outside the building under construction to verify the airtightness of the frame,
By operating a forced exhaust facility provided on the housing after the airtight construction is completed and exhausting the housing, a differential pressure is generated inside and outside the housing, and the airtight state of the housing is confirmed based on the differential pressure. It is characterized by having an airtight confirmation process.
According to such a configuration, when the hermetic construction is completed, the hermeticity of the chassis can be verified by using the forced exhaust equipment provided in the chassis, and the current hermetic state of the chassis can be checked very easily. can do. Here, the forced exhaust facility may be an air supply / exhaust facility that is used as it is after the completion of the building, or may be separately installed so that the forced exhaust device can be temporarily removed. However, when using air supply / exhaust equipment such as an air supply / exhaust fan, kitchen range fan, ventilation fan, ceiling fan, etc. that remain installed in a building such as a house, of course, such equipment is necessary when performing airtightness verification. Must already be provided, and such equipment may not be available at the stage of completion of hermetic construction where construction of equipment has not been performed. In addition, since a relatively high output exhaust system is required to verify the airtightness of the entire building, if the installed equipment does not meet the high output conditions, obtain a sufficient pressure difference for airtightness measurement. In some cases, a high-precision differential pressure gauge becomes necessary, and it takes a lot of time and effort to measure.
On the other hand, when installing forced exhaust equipment temporarily, it is natural that a forced exhaust installation with sufficient output necessary for airtightness verification must be installed. Need to be done.
Therefore, comparing the two, forced exhaust equipment may use the air supply and exhaust equipment that is used as it is after the building is completed, but it is preferable to temporarily install and use the forced exhaust equipment so that it can be removed There are many.

なお、躯体とは、基礎構造(コンクリート基礎や土台)より上部に構築される上部構造及び当該上部構造に支持される外壁を含むものを示している。躯体は、柱梁で構成される軸組の骨組に屋根・床スラブや外壁で覆われた躯体や壁式構造の躯体など特に限定されるものではない。
躯体の内部空間を形成する屋根・床スラブや外壁は、建物の設計の基準となるモジュール寸法に基づいた規格化された寸法を有する建材であり、例えばコンクリートパネルやサイディングパネルなどを用いて構成され、躯体が完成すれば(棟上げ工事段階)、外部から雨水等が流入しない一定の内部空間が構成されているが、窓や建材間の間隙等を通じて外気が導入されうる。
よって、躯体は、外部に対して換気の必要のないほど開放された構造ではないし、内部空間が外部に対して密閉された構造でもなく、外部との自然換気が可能となる開口面積等(隙間相当面積)を具備し、躯体を形成する建材の含有水分の放出に必要な換気量に相当する換気回数が確保される構造であり、換気の空気の流れ(内部空間の空気を強制換気扇により循環させて、内部の空気を外気に置換する)によって水分が運搬されるものである。
また、基礎構造は、躯体を含んだ建物の上部荷重を地盤に伝える基礎や土台で構成される下部構造であるが、その内部空間の換気のための換気口が外周基礎の立上り部の要所に適宜形成されているものである。
また、建材は、モルタルなどの水分を含有する建材と接触したり、雨水などにさらされることにより水分の吸収する建材を必須に含み、かかる吸水性の建材としては、工場成型される軽量気泡コンクリート(ALC)などのコンクリートパネル、サイディングパネルなどが特に例示される。
また、躯体施工完了とは、例えば、軸組構造の建物では、基礎や土台の上部に軸組である柱や梁が組立てられ、屋根パネルや床パネルが敷設され、外壁パネルの配設が完了した状態を指す。また、壁構造の建物においても同様に、基礎や土台の上部に屋根や床が敷設され、外壁パネルの配設が完了した状態である。
In addition, a frame has shown the thing containing the upper structure constructed | assembled above a foundation structure (concrete foundation and foundation), and the outer wall supported by the said upper structure. The frame is not particularly limited, such as a frame covered with a roof / floor slab or an outer wall, or a wall-type frame with a frame of a frame composed of column beams.
Roofs, floor slabs, and outer walls that form the interior space of the frame are building materials that have standardized dimensions based on the module dimensions that serve as building design standards, such as concrete panels and siding panels. When the housing is completed (in the building construction stage), a certain internal space is formed in which rainwater or the like does not flow from the outside, but outside air can be introduced through windows or gaps between building materials.
Therefore, the housing is not a structure that is not open to the outside so that ventilation is not necessary, and the internal space is not a structure that is sealed from the outside. Equivalent area), and is a structure that ensures the number of ventilations equivalent to the ventilation required to release the moisture contained in the building materials that form the enclosure, and the flow of ventilation air (circulates the air in the internal space by a forced ventilation fan) The water is transported by replacing the internal air with the outside air.
The foundation structure is a lower structure consisting of a foundation and foundation that transmits the upper load of the building including the frame to the ground, but the ventilation opening for the ventilation of the internal space is a key part of the rising part of the outer foundation Are appropriately formed.
In addition, building materials essentially include building materials that absorb moisture when exposed to building materials containing moisture, such as mortar, and are exposed to rainwater. Specific examples include concrete panels such as (ALC), siding panels, and the like.
In addition, for example, in a building with a frame structure, a frame or pillar is assembled on the upper part of the foundation or foundation, roof panels and floor panels are laid, and the installation of exterior wall panels is completed. Refers to the state. Similarly, in a building with a wall structure, a roof and a floor are laid on the upper part of the foundation and foundation, and the arrangement of the outer wall panel is completed.

(2)また、前記強制排気設備が、躯体の内部空間に外気を導入して前記建材の含有水分の放出を促進するために設置される強制排気装置であることが好ましい。
本願発明者らは、気密性計測に十分な出力を備えた一時的に設置する強制排気装置について鋭意検討したところ、気密施工後の躯体の気密性を計測するに際し、躯体の内部空間に外気を導入して上記建材の含有水分の放出を促進する強制排気装置を用いることが好ましいことを知見した。当該強制排気装置は、外気である乾燥空気を躯体の内部空間に導き、該乾燥空気を躯体内に循環させた後に排出するものであって、該強制排気装置により躯体の隙間や開口から該躯体の内部空間に導入される乾燥空気は、当該躯体を形成する建材等の水分を吸収して湿潤空気となった後に強制排気装置を通じて躯体の外方に排出されるものとなる。この様な強制空気流を躯体の内外で形成すべく、上記強制排気装置の換気量は、主に施工後の建物の日常生活上で必要とされる機械換気のために配備される各種の換気設備よりも著しく大きい。当該強制排気装置を利用することにより、躯体に気密層を形成した後であっても当該強制排気装置を起動すると、当該躯体(気密層)内外で10Pa程度の大きな差圧を発生させることが可能となることも本願発明者は確認している。これにより、当該差圧の測定が容易なものとなり、躯体に気密層を形成する気密施工直後の躯体の気密性を判断することが可能となるのである。
(2) Moreover, it is preferable that the said forced exhaust equipment is a forced exhaust apparatus installed in order to introduce | transduce outside air into the internal space of a housing and to accelerate | stimulate discharge | release of the moisture content of the said building material.
The inventors of the present application have made extensive studies on a temporarily installed forced exhaust device with sufficient output for airtightness measurement.When measuring the airtightness of the housing after the airtight construction, the outside air is discharged into the internal space of the housing. It has been found that it is preferable to use a forced exhaust device that is introduced to promote the release of moisture contained in the building material. The forced exhaust device exhausts the dry air, which is outside air, to the internal space of the housing and circulates the dry air in the housing, and then exhausts the dry air from the gap or opening of the housing by the forced exhaust device. The dry air introduced into the interior space is exhausted to the outside of the housing through a forced exhaust device after absorbing moisture of the building material and the like forming the housing to become wet air. In order to form such a forced air flow inside and outside the enclosure, the ventilation amount of the forced exhaust system is mainly the various ventilation provided for mechanical ventilation required in daily life of the building after construction. It is significantly larger than the equipment. By using the forced exhaust device, it is possible to generate a large differential pressure of about 10 Pa inside and outside the housing (airtight layer) when the forced exhaust device is activated even after an airtight layer is formed on the housing. The present inventor has also confirmed that As a result, the differential pressure can be easily measured, and it is possible to determine the airtightness of the housing immediately after the airtight construction for forming an airtight layer on the housing.

また、当該強制排気装置は、上記気密施工を行う以前から、躯体を形成する建材の水分を除去するために当該躯体に設置されているものであって、気密を測定するため目的のために設置されるものではなく、そうすると、建物の施工の過程において、躯体を形成する建材の水分を除去するという別の目的で設けられた換気装置を利用して躯体の気密をも確認することができ、気密確認のための装置設置の工程を著しく軽減又は省略することができ、施工の遅延化を回避しつつ気密の確認を行うことができる。   In addition, the forced exhaust device has been installed in the housing to remove moisture from the building materials forming the housing before the airtight construction, and is installed for the purpose of measuring airtightness. Then, in the construction process of the building, you can also check the airtightness of the enclosure using the ventilation device provided for another purpose of removing the moisture of the building material that forms the enclosure, The device installation process for airtightness confirmation can be significantly reduced or omitted, and airtightness confirmation can be performed while avoiding delays in construction.

(3)また、 前記気密施工後に、前記躯体の外壁及び気密層を貫通する通気孔などの貫通孔の形成を伴う施工を行う設備施工を備え、
前記気密確認工程は、
前記気密施工までを完了させた時点で、前記強制給排気装置により強制排気を行うことにより、前記躯体の内外に差圧を生じさせて気密性を確認する当初気密確認工程と、
前記設備施工までを完了させた時点で、前記強制給排気装置により強制排気を行うことにより、前記躯体の内外に差圧を生じさせて気密性を確認する設備施工後気密確認工程と、
を備えていることが好ましい。
これによれば、設備施工により生じる可能性がある気密欠損により躯体の気密性がどの程度低下したかを確認することができるものとなる。
(3) In addition, after the airtight construction, equipped with equipment construction to perform construction with the formation of through holes such as air holes penetrating the outer wall and the airtight layer of the housing,
The airtightness confirmation process includes
At the time of completing up to the airtight construction, by performing forced exhaustion by the forced air supply and exhaust device, an initial airtight confirmation step for confirming airtightness by generating a differential pressure inside and outside the housing,
After completing the facility construction, by performing forced exhaust by the forced air supply / exhaust device, an airtight confirmation step after facility construction for confirming airtightness by generating a differential pressure inside and outside the housing,
It is preferable to provide.
According to this, it becomes possible to confirm how much the airtightness of the housing has been reduced due to the airtight defect that may occur due to the facility construction.

(4)また、前記設備施工を複数回に亘って行い、
各設備施工を完了させる度に、前記強制排気装置による強制排気により生じる内外差圧に基づいて当該設備施工後の躯体の気密性を確認する設備施工後気密確認工程を行う、
ことが好ましい。
これによれば、各設備施工工程ごとにどれだけ躯体の気密性が低下したかを判断することができる。
(4) In addition, the facility construction is performed multiple times,
Every time each facility construction is completed, an after-construction airtightness confirmation process is performed to confirm the airtightness of the enclosure after the facility construction based on the internal / external differential pressure generated by forced exhaust by the forced exhaust device,
It is preferable.
According to this, it can be judged how much the airtightness of the housing has decreased for each facility construction process.

(5)また、上記計測を可能な強制排気装置としては、
前記躯体に形成されている開口部の開口縁部を形成する枠材に載置される支持部材と、
該支持部材に取り付けられ、前記躯体の内部空間の空気を吸引して躯体の外方に排気する換気扇本体と、
該換気扇本体よりも風上に配設されて換気扇本体を保護する保護部材と、
上記換気扇本体の風下に配設されて排気流れを変更させる風向変更部材と
を具備することが好ましい。
(5) Also, as a forced exhaust device capable of the above measurement,
A support member mounted on a frame material that forms an opening edge of the opening formed in the housing;
A ventilation fan body attached to the support member, for sucking air in the internal space of the housing and exhausting it outside the housing;
A protective member disposed on the windward side of the ventilation fan body to protect the ventilation fan body;
It is preferable to provide a wind direction changing member that is disposed leeward of the ventilation fan body and changes the exhaust flow.

(6)また、上記強制排気装置の位置は、強制排気装置の運転により、躯体の内部空間に導入せしめられた外気が、躯体の内部空間を循環して、再び外部に排出されるならば、何処であっても構わないが、前記強制排気装置が設置される開口部は、躯体施工により形成される基礎構造の上に構築された躯体の内部空間を基礎構造の内部空間に連通させるものであることが特に好ましい。
これによれば、強制排気装置からの排気により、躯体と基礎構造によって包囲される床下空間を加圧状態とすることができる。このため、躯体の内部空間と基礎構造の内部空間との差圧は、該躯体の内部空間と屋外空間との差圧よりも加圧分だけ大きなり、これによって、躯体の内部空間と基礎構造の内部空間とを連通する漏気路が存在する場合には、当該漏気路を通じての該基礎構造の内部空間から躯体の内部空間に向けての漏気を過大に評価することができ、ひいては当該漏気路の存在を厳しく評価することができる。即ち、内外差圧が著しく小さい場合等は、先ずかかる漏気路の存在を疑うことができるのである。冬季等の温度差による換気は、この様な躯体の下方に存在する漏気路によって大きくなりやすいため、当該漏気路の存在を可及的減じることが躯体の気密性能向上に有効であるが、上述の如く基礎構造の内部空間に向けて排気させることにより、当該漏気路の発見に有利に作用することとなるのである。
(6) In addition, the position of the forced exhaust device is determined so that the outside air introduced into the internal space of the housing by the operation of the forced exhaust device circulates in the internal space of the housing and is discharged to the outside again. The opening in which the forced exhaust device is installed may communicate with the internal space of the frame constructed on the foundation structure formed by the frame construction to the internal space of the foundation structure. It is particularly preferred.
According to this, the underfloor space surrounded by the housing and the foundation structure can be brought into a pressurized state by the exhaust from the forced exhaust device. For this reason, the differential pressure between the internal space of the enclosure and the internal space of the foundation structure is larger than the differential pressure between the internal space of the enclosure and the outdoor space by the amount of pressure, and thereby the internal space of the enclosure and the basic structure When there is an air leakage path that communicates with the internal space, it is possible to overestimate the leakage from the internal space of the foundation structure to the internal space of the enclosure through the air leakage path, The presence of the leak path can be strictly evaluated. That is, when the internal / external differential pressure is extremely small, the existence of such an air leakage path can be suspected first. Ventilation due to temperature differences in winter and the like is likely to increase due to the air leakage path that exists below the chassis, so reducing the presence of the air leakage path as much as possible is effective in improving the airtight performance of the chassis. As described above, exhausting toward the internal space of the foundation structure has an advantageous effect on the discovery of the leakage path.

本発明の建設途上の建物の気密測定方法によれば、上記気密施工を完了した直後の気密性能を簡易且つ所望の精度で測定することができる。   According to the method for measuring the airtightness of a building under construction according to the present invention, the airtightness performance immediately after the completion of the airtight construction can be easily measured with desired accuracy.

本発明は、図1に示す如く、躯体を基礎構造の上に構築する躯体施工(ステップS1)を完了させた後に、当該躯体に気密層を形成する気密施工(ステップS2)を施し、その後、当該施工途上の建物の気密性を確認する気密性確認作業(当初気密確認工程(ステップS3))を行い、その後、設備施工(ステップS4)を行った後にさらに気密性確認作業(設備施工後気密確認工程(ステップS5))を行うものである。
各気密性確認作業(ステップS3,S4)においては、躯体に用いられた建材の含有水分を放出すべく上記躯体施工の完了後に当該躯体に設置されたまま残置されている強制排気装置を運転させて躯体と外部空間との間に圧力差(以後、内外差圧又は単に差圧とも言う)を生じさせ、当該圧力差を計測することで当該建設途上の建物の当該計測時点での気密性を確認する。
In the present invention, as shown in FIG. 1, after completing the frame construction (step S1) for constructing the frame on the foundation structure, the airtight construction (step S2) for forming an airtight layer on the frame is performed, and then Airtightness confirmation work (initial airtightness confirmation process (step S3)) to confirm the airtightness of the building under construction is performed, and after the equipment construction (step S4) is performed, further airtightness confirmation work (airtightness after equipment construction) A confirmation step (step S5)) is performed.
In each of the airtightness confirmation operations (steps S3 and S4), the forced exhaust device that is left in the housing is operated after the construction of the housing is completed in order to release moisture contained in the building material used in the housing. The pressure difference (hereinafter also referred to as the internal / external differential pressure or simply the differential pressure) is generated between the housing and the external space, and the pressure difference of the building under construction is measured by measuring the pressure difference. Check.

躯体施工(ステップS1)は、図2に示す如き建物の基礎構造1を形成する基礎構築工程(ステップS1-1)と、該基礎構造1上に建物の躯体2を構築する躯体構築工程(ステップS1-2)と、当該躯体2の水分を除去する水分除去工程(ステップS1-3)とを備えている。
基礎構築工程(ステップS1-1)は、地盤に基礎を立ち上げる工程であって、本実施形態においては、躯体2を支持する基礎構造1として鉄筋コンクリート連続布基礎を採用している。当該基礎構造1の外周部を形成する立上り部には、後記する図3(b)に示されるように、複数の換気口3aが長手方向に沿って適宜間隔を開けて設けられている。内周部の基礎構造の立上り部にも基礎グリッド間を互いに連通させる複数の換気口3bが長手方向に沿って適宜間隔をあけて設けられており、これら換気口3a,3bを通じて基礎構造の内部空間の自然換気がなされる。該換気口3a,3bは、例えば概ね4mおきに約300cmの見付け面積(基礎立上り面に設ける)を有し、強制排気装置による排気に十分な開口面積を得ることができる。
The frame construction (step S1) includes a foundation construction process (step S1-1) for forming the foundation structure 1 of the building as shown in FIG. 2, and a frame construction process (step S1) for building the building frame 2 on the foundation structure 1. S1-2) and a moisture removing step (step S1-3) for removing moisture from the casing 2.
The foundation construction process (step S1-1) is a process of starting up the foundation on the ground. In this embodiment, a reinforced concrete continuous cloth foundation is adopted as the foundation structure 1 that supports the frame 2. As shown in FIG. 3B to be described later, a plurality of ventilation openings 3a are provided at appropriate intervals along the longitudinal direction at the rising portion that forms the outer peripheral portion of the foundation structure 1. A plurality of ventilation openings 3b communicating with each other between the foundation grids are also provided at appropriate intervals along the longitudinal direction at the rising portion of the foundation structure on the inner periphery, and the interior of the foundation structure is provided through these ventilation openings 3a and 3b. Natural ventilation of the space is made. The vents 3a and 3b have a finding area (provided on the basic rising surface) of about 300 cm 2 at intervals of about 4 m, for example, and can provide a sufficient opening area for exhaust by the forced exhaust device.

躯体構築工程(ステップS1-2)は、上記基礎構造に躯体2を構築する工程であって、本実施形態において、躯体は、基礎構造の上に構築される通常の一階建て、二階建て、三階建て等の梁4や柱からなる骨組み構造に工場成型されるコンクリートパネル等の建材により壁5、床6、屋根7が構築されたもので、躯体2を建ち上げた時点では、壁5、床6、屋根7等が組み上げられて一定の内部空間が形成され、雨水等が流入しないように屋根部等に防水工事が施される一方、窓サッシ、建材間の隙間等が密閉(シール)されていないか、外形的にはシールされていてもまだ不完全な状態であり、壁5等に一定の開口部、隙間等が存在し、躯体の内外である程度の空気の流出入を許容し得る状態のものである。すなわち、躯体施工を完了した躯体とは、各種部材及び部材間に隙間を有し、後記する必要な換気量に相当する換気回数が確保される構造である。
なお、上記基礎構造に躯体2を立ち上げることにより、躯体2の1階床スラブ6aの下方には、基礎構造及び1階床スラブ6aに包囲される床下空間Sが形成されることとなる。
The frame building step (step S1-2) is a step of building the frame 2 on the foundation structure, and in this embodiment, the frame is a normal one-story, two-story building constructed on the foundation structure, The wall 5, floor 6 and roof 7 are constructed of building materials such as concrete panels that are factory-molded into a three-storied beam 4 and pillar frame structure. When the frame 2 is erected, the wall 5 The floor 6 and the roof 7 are assembled to form a certain internal space, and the roof portion is waterproofed so that rainwater does not flow in, while the window sash and the gap between the building materials are sealed (seal ) Or is externally sealed but still incomplete, and there are certain openings, gaps, etc. in the wall 5 etc., allowing a certain amount of air in and out of the housing. It is in a state that can be. In other words, the frame that has completed the frame construction is a structure that has various members and gaps between the members, and the number of ventilations corresponding to the necessary ventilation amount to be described later is secured.
In addition, by raising the housing 2 to the foundation structure, an underfloor space S surrounded by the foundation structure and the first floor slab 6a is formed below the first floor slab 6a of the housing 2.

ところで、当該躯体施工までを完了させた躯体2においては、外壁や床スラブに用いられているコンクリートパネルやサイディングパネル等の建材の内部に工場での成型完了後も水分が残留しているばかりでなく、これらの建材は吸水性も有しているので、現場施工においてモルタル等の水分を含有する材料と接触すると、その水分を吸収して水分を含んだ状態となる。或いは、建材の現場搬入後、降雨等にさらされることによって吸水する場合もある。
上記のような理由から過剰な水分を含んでしまうこととなった建材をそのまま過水分状態で建物を完成させてしまうと、当該水分に起因して建物の内部に結露が生じたり、建物の居住者に高湿感をもたらす原因となるばかりでなく、建材の耐久性やひいては建物全体の耐久性にも悪影響を与える可能性もある。
By the way, in the case 2 that has been completed up to the case construction, moisture remains in the interior of building materials such as concrete panels and siding panels used for outer walls and floor slabs even after completion of molding at the factory. However, since these building materials also have water absorption properties, when they come into contact with a material containing water such as mortar in the construction on site, the water is absorbed and becomes in a state containing water. Alternatively, there are cases in which water is absorbed by exposure to rainfall after the building materials are carried on site.
If the building is completed with the building materials that contain excessive moisture for the above reasons in an excessively humid state, condensation will occur inside the building due to the moisture, In addition to causing a high humidity feeling to the person, it may also adversely affect the durability of the building material and thus the durability of the entire building.

そこで、本実施形態においては、上記躯体構築工程(ステップS1-2)の完了の後、建材内に残留する水分を可及的除去することを目的として水分除去工程(ステップS1-3)を設けている。
該水分除去工程(ステップS1-3)は、躯体内に強制換気流を形成し、当該換気流によって建材を内側から乾燥させるものである。上記強制換気流は、躯体に強制排気装置を取り付け、該強制排気装置を起動させることによって躯体内に発生させることが可能となる。
該強制排気装置は、躯体の内部空間に外気を導入できる位置であれば、何処に設置しても構わず、例えば窓等の開口部に設置することが可能である。とは云え、例えば窓の開口部に当該強制排気装置を設置すると、幾つかの問題が生じる場合がある。すなわち、窓に強制排気装置を設備すると、雨天時に雨水の吹込みがありうること、開口部周辺の施工に障害が多いこと、防犯上の問題があること、サッシを傷つける恐れがあること、排気や騒音が隣家に迷惑をかける恐れがあることなどの不具合がある。
Therefore, in the present embodiment, a water removal step (step S1-3) is provided for the purpose of removing as much as possible the water remaining in the building material after the completion of the above-mentioned frame construction step (step S1-2). ing.
In the water removal step (step S1-3), a forced ventilation flow is formed in the housing, and the building material is dried from the inside by the ventilation flow. The forced ventilation flow can be generated in the housing by attaching a forced exhaust device to the housing and starting the forced exhaust device.
The forced exhaust device may be installed anywhere as long as the outside air can be introduced into the internal space of the housing. For example, the forced exhaust device can be installed in an opening such as a window. However, for example, if the forced exhaust device is installed at the opening of a window, several problems may occur. In other words, if a forced exhaust system is installed in the window, rainwater can be blown in the rain, there are many obstacles in the construction around the opening, there are security problems, the sash may be damaged, exhaust There are problems such as noise and noise that may annoy neighbors.

そこで、本発明の好適な実施形態に係る方法では、これらの問題を回避するために、図3(b)に示すように、一階床スラブ6aに強制排気装置9を設置し、基礎構造の内部空間(以下、床下空間Sとも言う)を通じて外部に排気する。
空気を基礎構造の内部空間を通じて排出するには、強制排気装置9を、基礎構造の内部空間に連通する躯体2の開口部8に設置する。該開口部8は、建物完成後においても床下点検口として存在するものである。
Therefore, in the method according to the preferred embodiment of the present invention, in order to avoid these problems, as shown in FIG. 3B, a forced exhaust device 9 is installed on the first floor slab 6a, and the foundation structure The air is exhausted outside through an internal space (hereinafter also referred to as an underfloor space S).
In order to discharge air through the internal space of the foundation structure, the forced exhaust device 9 is installed in the opening 8 of the housing 2 that communicates with the internal space of the foundation structure. The opening 8 exists as an underfloor inspection port even after the building is completed.

上記強制排気装置により建材の含有水分の放出を行う場合に必要な換気量等について検討する。図3(a)は、基礎構造の上に二階建て家屋の躯体2が構築された状態を示しており、一階床の開口部(床下点検口)8に設置された強制排気装置9の運転により、躯体の開口部、隙間等から外気が一階、二階の室内に導入され、躯体2の壁5、床6、天井、屋根7を構成する吸水した建材の乾燥を行い、一階に導入された外気はそのまま一階の床下点検口8に設置した強制排気装置9を経由し、二階に導入された外気は吹き抜け等を経てやはり一階の床下点検口8に設置した強制排気装置9によって吸引されて床下空間Sに導かれ、基礎構造の換気口3a,3bから再び外部に排気される。なお、一般的に設計された住宅の場合、一階の床下空間Sである基礎構造1の内部空間の気積は、躯体2の内部空間の気積の約1/10程度以上で、換気回数としては躯体2の内部空間の約10倍以上に相当する。   Examine the ventilation volume required when the moisture content of building materials is released by the forced exhaust system. FIG. 3A shows a state in which a two-story house frame 2 is constructed on the foundation structure, and the operation of the forced exhaust device 9 installed in the opening (underfloor inspection port) 8 on the first floor. As a result, outside air is introduced into the first and second floor rooms from the openings and gaps of the housing, and the water-absorbing building materials constituting the wall 5, floor 6, ceiling, and roof 7 of the housing 2 are dried and introduced to the first floor. The outside air is passed through the forced exhaust device 9 installed in the lower floor inspection port 8 on the first floor, and the outside air introduced on the second floor is blown through the forced exhaust device 9 installed in the lower floor inspection port 8 on the first floor. The air is sucked and guided to the underfloor space S, and is exhausted to the outside again through the ventilation holes 3a and 3b of the foundation structure. In the case of a generally designed house, the volume of the internal space of the foundation structure 1 that is the underfloor space S on the first floor is about 1/10 or more of the volume of the internal space of the housing 2, and the ventilation frequency Corresponds to about 10 times or more the internal space of the housing 2.

一例として、躯体2を構成する建材が含んでいる水分重量のうち2tを強制換気により除去するための換気量は次のようにして試算される。
先ず、躯体2の内部空間に流入する外気が、例えば、東京の4月の月平均である気温が15.1℃、相対湿度が61%RHであると仮定する。そして、このときの躯体2の内部空間の相対湿度を100%RHとし、流入外気が躯体の内部空間を強制循環した後、床下の基礎構造1の内部空間に吸引されるときの相対湿度を、前記流入外気(61%RH)と躯体の内部空間(100%RH)の相対湿度値の中央値である80.5%RHと仮定する。ここで、簡易計算のため温度は変化しないものと仮定する。
この場合、建物に流入する前の外気は気温15.1℃、相対湿度61%RHの状態であるから、7.869g/mの水分を有していることになるが、躯体2の内部空間に入った新しい湿度の低い空気が余剰水分を含有する建材に接することにより平衡状態が崩れて、水分が建材から室内空気に移動する。そして、その空気が床下の基礎構造1の内部空間に吸引される際には、気温15.1℃、相対湿度80.5%RHであり、10.385g/mの水分を含有している状態となる。したがって、計算上、流入外気は、躯体の内部空間を対流して、基礎構造の内部空間を経て外部に戻る間に、10.385g/m−7.869g/m=2.51g/mの水分を移動させることができることになる。
ここで、強制排気を実施できる工事期間を40日間とする場合、躯体の内部空間を構成する建材から2tの水分を排出するには、
2,000,000g/(40日×24時間)/(2.5g/m)=833m/時
の換気量が必要となる。
そこで、1000m/時の換気能力を有する換気設備を使用すれば十分と考えられる。
ちなみに1000m/時の換気能力を有する換気設備を使用した場合の東京の月別の水分重量を試算すると、強制排気を実施できる工事期間40日で、1月は、1.8tの水分重量、4月は、2.4tの水分重量、7月は、2.4tの水分重量、10月は、3.0tの水分重量の排出が期待できる。
実際には、強制排気装置の設置初期は、躯体内が高湿度のため、排出量が大きく、乾燥が進むにつれて、躯体内の相対湿度は低下し、水分排出量は減少する。また、現場での作業のため、強制排気装置の運転時間が減少することはあり得るので、その点を見込む必要がある。
As an example, a ventilation amount for removing 2 t of moisture weight contained in the building material constituting the housing 2 by forced ventilation is calculated as follows.
First, it is assumed that the outside air flowing into the internal space of the housing 2 has, for example, a monthly average temperature of April in Tokyo of 15.1 ° C. and a relative humidity of 61% RH. And the relative humidity of the internal space of the housing 2 at this time is set to 100% RH, and the relative humidity when the inflowing outside air is forced to circulate through the internal space of the housing and then sucked into the internal space of the foundation structure 1 under the floor, Assume 80.5% RH, which is the median relative humidity value between the inflowing outside air (61% RH) and the internal space (100% RH) of the enclosure. Here, it is assumed that the temperature does not change for simple calculation.
In this case, since the outside air before flowing into the building is in a state where the temperature is 15.1 ° C. and the relative humidity is 61% RH, it has moisture of 7.869 g / m 3. The new low-humidity air that has entered the space comes into contact with the building material containing excess moisture, so that the equilibrium state is lost and moisture moves from the building material to room air. When the air is sucked into the internal space of the foundation structure 1 under the floor, the air temperature is 15.1 ° C., the relative humidity is 80.5% RH, and it contains 10.385 g / m 3 of water. It becomes a state. Therefore, in calculation, the inflowing outside air convects the internal space of the housing, returns to the outside through the internal space of the foundation structure, and 10.385 g / m 3 −7.869 g / m 3 = 2.51 g / m. 3 moisture can be moved.
Here, when the construction period during which forced exhaust can be carried out is 40 days, in order to discharge 2t of moisture from the building material constituting the internal space of the housing,
A ventilation volume of 2,000,000 g / (40 days × 24 hours) / (2.5 g / m 3 ) = 833 m 3 / hour is required.
Therefore, it is considered sufficient to use a ventilation facility having a ventilation capacity of 1000 m 3 / hour.
By the way, when calculating the monthly moisture weight in Tokyo when using a ventilation facility with a ventilation capacity of 1000 m 3 / hour, the construction period in which forced exhaust can be carried out is 40 days, and in January, a moisture weight of 1.8 t, 4 It is expected that a moisture content of 2.4 t will be emitted in the month, a moisture mass of 2.4 t in July, and a moisture content of 3.0 t in October.
Actually, at the initial stage of installation of the forced exhaust device, the amount of discharge is large because the inside of the case is high humidity, and the relative humidity inside the case is lowered and the amount of water discharged is reduced as drying progresses. Further, since the operation time of the forced exhaust system may be reduced due to the work at the site, it is necessary to allow for this point.

以上説明した1000m/時の換気量は、例えば延べ床面積が40坪の住宅(階数は2階でも3階でもよい)の換気回数としては3.3回/時に相当し、現場における躯体を構成する建材の含有水分の放出を行うためには、通常の換気を行う場合に比して多くの換気量が必要となる。その換気回数は、実居住環境での換気に比べて大きすぎるレベルである。
ちなみに、一般に、住宅内では、2003年の建築基準法改正により、室内空気質の観点から0.5回/時の換気設備の設置が義務づけられているが、居住する環境下、特に冬期において、換気量が多い場合、気流感により快適性が損なわれる場合があり、このため1.0回/時を超える場合が過換気とされる。なお、窓開けにより通風換気を行う場合の換気量は概ね30回/時以上である。
The ventilation volume of 1000 m 3 / hour explained above corresponds to 3.3 ventilation / hour as the ventilation frequency of a house with a total floor area of 40 tsubo (the floor may be 2nd floor or 3rd floor). In order to release the moisture content of the building materials to be configured, a large amount of ventilation is required as compared with the case of normal ventilation. The ventilation frequency is a level that is too large compared with ventilation in an actual living environment.
By the way, in general, it is obliged to install ventilation equipment 0.5 times / hour from the viewpoint of indoor air quality due to the revision of the Building Standards Act in 2003, but in the living environment, especially in winter, When the amount of ventilation is large, comfort may be impaired due to the feeling of airflow. For this reason, the case of exceeding 1.0 times / hour is regarded as overventilation. Note that the ventilation rate when ventilation is performed by opening a window is approximately 30 times / hour or more.

上記のように強制排気装置9は、風量が多いものが使用され、好適には2〜10回/時の換気回数を達成できるものが選択され、特に、内外差圧が大きくとも排気量が落ち難い有圧型換気扇が用いられる。
なお、建材の含有する水分、当該施工を行う季節、気候や天気、さらには建物の大きさ等によって換気期間や強制排気装置9の換気量は適宜異なるものの、換気期間としては少なくとも3〜4週間を設定し、強制排気装置9としては1000m/時以上の換気量のものを用いることが好ましい。
As described above, a forced exhaust device 9 having a large air volume is used, and preferably a device capable of achieving a ventilation rate of 2 to 10 times / hour is selected. In particular, even if the internal / external differential pressure is large, the exhaust amount decreases. Difficult pressured ventilation fan is used.
In addition, although the ventilation period and the amount of ventilation of the forced exhaust system 9 vary appropriately depending on the moisture contained in the building material, the season in which the construction is performed, the climate and weather, and the size of the building, the ventilation period is at least 3 to 4 weeks. It is preferable to use a forced exhaust device 9 having a ventilation amount of 1000 m 3 / hour or more.

次に本発明に係る強制排気装置9の設置構造について説明する。
図3(b)に示す如く、基礎構造1である連続布基礎は、外周部の立上り部と内周部の立上り部が一体化されて形成されており外周部には複数の換気口3aが長手方向に沿って適宜間隔を開けて設けられ、また内周部にも基礎グリッド間を互いに連通させる複数の換気口3bが長手方向に沿って適宜間隔をあけて設けられており、基礎構造内の換気が可能な構造とされている。この換気口3a,3bは、例えば概ね4mおきに配され、例えば約300cmの見付け面積を有しており、強制排気装置9による排気に十分な開口面積を得ることができる。また、躯体2は、基礎構造1の上に構築されており、6aaは床パネルの表面、6bはは二階床スラブ、10は一階と二階を連通させる吹き抜け部、11は窓等が設置されている開口部である。
Next, the installation structure of the forced exhaust device 9 according to the present invention will be described.
As shown in FIG. 3 (b), the continuous fabric foundation as the foundation structure 1 is formed by integrating the rising portion of the outer peripheral portion and the rising portion of the inner peripheral portion, and a plurality of ventilation ports 3a are formed on the outer peripheral portion. A plurality of ventilation openings 3b are provided at appropriate intervals along the longitudinal direction, and are provided at appropriate intervals along the longitudinal direction. It has a structure that allows for ventilation. The ventilation openings 3a and 3b are arranged, for example, at intervals of about 4 m, for example, and have an area of about 300 cm 2 , for example, and an opening area sufficient for exhausting by the forced exhaust device 9 can be obtained. The housing 2 is constructed on the foundation structure 1, 6aa is the surface of the floor panel, 6b is the second floor slab, 10 is the atrium that connects the first floor and the second floor, 11 is installed with windows and the like. It is an opening.

上記躯体2の一階床スラブ6aには、開口部としての床下点検口8が設けられており、この床下点検口8に、有圧型換気扇からなる強制排気装置9が、吸気側を一階居室側に、排気側を基礎構造3の内部空間に向けて取外し自在に設置される。
そして、この強制排気装置9を運転することにより、躯体2の開口部11や図示しない部材間の隙間等から外気が室内に導入され、強制排気装置9によって吸引されて、基礎構造1の内部空間に導かれ、換気口3a,3bから再び外部に排出されて換気がなされ、その間の空気の強制循環により、躯体2を構成する建材が乾燥せしめられ、また基礎構造1内の含有水分も放出されるようになっている。
The first floor slab 6a of the housing 2 is provided with an underfloor inspection port 8 as an opening, and a forced exhaust device 9 composed of a pressure type ventilation fan is connected to the underfloor inspection port 8 on the intake side on the first floor. On the side, the exhaust side is detachably installed toward the internal space of the foundation structure 3.
Then, by operating the forced exhaust device 9, outside air is introduced into the room through the opening 11 of the housing 2 or a gap between members (not shown) and the like, and is sucked by the forced exhaust device 9, and the internal space of the foundation structure 1. The air is exhausted from the ventilation openings 3a and 3b to the outside to be ventilated, and the building material constituting the housing 2 is dried by forced air circulation between them, and the moisture contained in the foundation structure 1 is also released. It has become so.

強制排気装置9は、図3(b)〜図5に示す如く、箱状の支持部材12に収納して支持部材12ごと床下点検口8から床下に落とし込まれ、支持部材12が床下点検口8において一階床面より下側に納められ突出することがない。また、強制排気装置9の上は、床下点検口8の周縁を利用して載置した格子状の保護部材13で保護する。すなわち、保護部材13は、床下点検口8周縁に沿って支持部材12のフランジ状縁部12b上に嵌め込まれ、その設置高さは、一階床面とほぼ同じレベルになっている。
図4に示す如く、床下点検口8は、一階床スラブ6aに形成された矩形の貫通口であり、貫通口は、該貫通口を設けるべき1枚の床パネル領域に断面視L字状の部材で構成された床敷設用鋼製枠部材14を敷設し、部分的に床パネルを敷設することにより形成される。
そして、貫通口の内周縁部には、その鋼製枠部材14に沿って床開口枠部材15が固定して取り付けられている。すなわち、該床開口枠部材15は、鋼製枠部材14の断面視L字状の立上り片に当接させ、一階床スラブ6a側の水平片に当接させて取り付けられている。
As shown in FIGS. 3B to 5, the forced exhaust device 9 is housed in a box-like support member 12 and dropped together with the support member 12 from the underfloor inspection port 8 to the underfloor inspection port. No. 8 is stored below the floor of the first floor and does not protrude. Further, the upper part of the forced exhaust device 9 is protected by a grid-like protective member 13 placed by using the peripheral edge of the underfloor inspection port 8. That is, the protection member 13 is fitted on the flange-like edge portion 12b of the support member 12 along the periphery of the underfloor inspection port 8, and its installation height is substantially the same level as the first floor surface.
As shown in FIG. 4, the underfloor inspection port 8 is a rectangular through-hole formed in the first-floor floor slab 6a, and the through-hole is L-shaped in cross-section in one floor panel region where the through-hole is to be provided. It is formed by laying a steel frame member 14 for floor laying composed of the above members and partially laying a floor panel.
A floor opening frame member 15 is fixedly attached to the inner peripheral edge of the through hole along the steel frame member 14. That is, the floor opening frame member 15 is attached to a steel frame member 14 in contact with a rising piece having an L-shape in sectional view and in contact with a horizontal piece on the first floor slab 6a side.

また該枠部材14の略水平な上面には、枠部材14と略同じ外周寸法であるが幅が枠部材14よりも小さい外枠部材16が固定して取り付けられ、これによって枠部材15の上面で外枠部材16の内側部分に受け座17が形成されている。この構造は、通常の工業化住宅において施工される床下点検口8の床開口部構造で、規格化された複数のコンクリートパネルを基礎、土台又は梁に設けた床スラブである。
強制排気装置9は、フレーム18と、駆動部19と羽根部材20とからなる換気扇本体とで構成され、支持部材12の矩形の開口部が形成された底部12aに載せられている。
フレーム18は、着座部がフランジ状に外方に広がった矩形のフレーム枠18a上に複数のタスキ状のアーム部18bが設けられ、駆動部19は、駆動軸19aがフレーム枠18aの略中心側を向く状態でアーム部18bに支持され、羽根部材20は、駆動軸19aに取り付けられてフレーム枠18aに囲まれた位置に配されて、支持部材12に取り付けられて支持部材12ごと、上記受け座17に載置されている。
Further, on the substantially horizontal upper surface of the frame member 14, an outer frame member 16 having substantially the same outer peripheral dimensions as the frame member 14 but smaller in width than the frame member 14 is fixedly attached. A receiving seat 17 is formed on the inner portion of the outer frame member 16. This structure is a floor opening structure of an underfloor inspection port 8 constructed in a normal industrialized house, and is a floor slab in which a plurality of standardized concrete panels are provided on the foundation, foundation or beam.
The forced exhaust device 9 includes a frame 18 and a ventilation fan body including a drive unit 19 and a blade member 20, and is placed on a bottom 12 a in which a rectangular opening of the support member 12 is formed.
The frame 18 is provided with a plurality of Tasuki-shaped arm portions 18b on a rectangular frame frame 18a in which a seating portion spreads outward in a flange shape, and the drive portion 19 has a drive shaft 19a on the substantially central side of the frame frame 18a. The blade member 20 is attached to the drive shaft 19a and is disposed at a position surrounded by the frame frame 18a, and is attached to the support member 12 together with the support member 12. It is mounted on the seat 17.

本発明では、床下点検口8に対する前記支持部材12や前記支持部材12に対する前記強制排気装置9の着脱が容易に可能となるように構成されているので、建物の工事中の任意に時期に、工程や職種にかかわらず、だれでも強制排気装置9の設置や撤去が可能である。また、この強制排気装置9は、建物の建設工事中に仮設で設置する換気扇装置であり、また換気装置装置9の着脱作業は、床スラブ面6aaの上側から行うワンサイド作業であるため、上下両側から作業しなければならないボルトなどによる固定を排除している。この場合、換気装置運転時に振動が発生することが問題となるが、これを抑制するべく床敷設用の鋼製枠部材14と支持部材12間のクリアランスを3〜5mm程度に設定し、支持部材12が横ずれしないように外枠部材16の内側部分の受け座17枠に嵌め込んだ形にしている。   In the present invention, the support member 12 with respect to the underfloor inspection port 8 and the forced exhaust device 9 with respect to the support member 12 are configured to be easily attached and detached, so at any time during construction of the building, Regardless of the process and job type, anyone can install or remove the forced exhaust device 9. The forced exhaust device 9 is a ventilation fan device that is temporarily installed during the construction work of the building, and the attachment / detachment work of the ventilation device 9 is a one-side operation performed from the upper side of the floor slab surface 6aa. Eliminates fixing with bolts that must be operated from both sides. In this case, there is a problem that vibration occurs during operation of the ventilator. In order to suppress this, the clearance between the steel frame member 14 for laying the floor and the support member 12 is set to about 3 to 5 mm, and the support member 12 is fitted into a receiving seat 17 frame on the inner portion of the outer frame member 16 so as not to be laterally displaced.

図5に示されるように、支持部材12は、矩形の開口部が形成されて底部12aが帯状とされた矩形の箱状枠体であり、強制排気装置9は、この底部12aにフレーム枠18aのフランジ状部分が着座せしめられてボルト・ナット等の締結手段21で締結され、支持部材12に取り付けられている。
また、支持部材12の上縁部は、外側方に折曲されてフランジ状に形成され、このフランジ状縁部12bが上記受け座17に着座されて、支持部材12が強制排気装置9ごと、上記枠部材15に載置されている。更に、支持部材12の床下側方向の長さ(深さ)は、強制排気装置9の頂部である駆動部19が、枠部材15の上面の高さよりも低い位置に位置せしめられるような深さが確保されている。
As shown in FIG. 5, the support member 12 is a rectangular box-like frame body in which a rectangular opening is formed and the bottom 12a is formed in a strip shape, and the forced exhaust device 9 has a frame frame 18a on the bottom 12a. The flange portion is seated and fastened by fastening means 21 such as bolts and nuts and attached to the support member 12.
Further, the upper edge portion of the support member 12 is bent outward and formed into a flange shape, the flange-like edge portion 12b is seated on the receiving seat 17, and the support member 12 is forced to the forced exhaust device 9 together. It is placed on the frame member 15. Further, the length (depth) of the support member 12 in the lower floor direction is such a depth that the drive unit 19 which is the top of the forced exhaust device 9 is positioned at a position lower than the height of the upper surface of the frame member 15. Is secured.

そして、図6に示すように、支持部材12の上には、矩形の周部材13aに複数の棒状の格子13bが設けられてなる矩形の保護部材13が、周部材13aを、上記枠部材15の受け座17に着座された支持部材12のフランジ状縁部12b上に当接させて載置され、この保護部材13の上面は、上記外枠部材16の上面とほぼ同一高さとされている。この保護部材13は、好ましくは、床面との段差が0〜30mmとなるように設置される。
また強制排気装置9は、設置状態で上方に当たる躯体側を吸気側とし、下方に当たる基礎構造1の内部空間側を排気側とするもので、有圧型であり、排気は軸方向下方に向けてなされる。よって、強制排気装置9には、風向変更手段が設けられている。すなわち、強制排気装置9が取り付けられた上記支持部材12には、風向変更手段を構成する邪魔板22が、強制排気装置9の羽根部材16から下方に一定間隔をおいて配され、複数のボルト・ナット等からなる連結手段23によって固定されており、軸方向下方に排気された空気の流れはこの邪魔板22に当たって水平方向に風向を変更して流れていく構成とされている。
As shown in FIG. 6, a rectangular protective member 13 in which a plurality of rod-like lattices 13 b are provided on a rectangular peripheral member 13 a is provided on the support member 12, and the peripheral member 13 a is replaced with the frame member 15. The support member 12 is placed on the flange-like edge portion 12b of the support member 12 that is seated on the receiving seat 17, and the upper surface of the protection member 13 is substantially the same height as the upper surface of the outer frame member 16. . This protective member 13 is preferably installed so that the level difference from the floor surface is 0 to 30 mm.
The forced exhaust device 9 is a pressure type in which the housing side that hits the upper side in the installed state is the intake side and the inner space side of the foundation structure 1 that hits the lower side is the exhaust side, and the exhaust is made downward in the axial direction. The Therefore, the forced exhaust device 9 is provided with wind direction changing means. That is, on the support member 12 to which the forced exhaust device 9 is attached, baffle plates 22 constituting wind direction changing means are arranged at regular intervals downward from the blade member 16 of the forced exhaust device 9, and a plurality of bolts -It is fixed by connecting means 23 made of nuts or the like, and the flow of the air exhausted downward in the axial direction hits the baffle plate 22 and changes the air direction in the horizontal direction and flows.

以上のような強制排気装置9は、箱状の支持部材12に収納して支持部材12ごと一階床面に設けられた床下点検口8から一階床下に落とし込むことにより、簡便に設置でき、また装置の自重があるため、設置状態も安定である。また、含有水分の放出作業が完了した段階では、支持部材12ごと床下点検口8から引き上げることによって容易に撤去することが可能となっている。
更に、支持部材12が床下点検口8において一階床面より下側に納められ突出することがないので、強制排気装置9の上は、床下点検口8の周縁を利用して載置した(嵌め込んだ)格子状の保護部材13で保護する。すなわち、保護部材13は、その設置高さは、一階床面とほぼ同じレベルにするようにしている。
強制排気装置9の上に床下点検口8の周縁を利用して載置した格子状の保護部材13で保護することができ、空気の流入を確保しながら強制排気装置9の上に工事資材等が落下することを未然に防止することができ、また保護部材13は、床下点検口8周縁に沿って支持部材12のフランジ状縁部12b上に嵌め込まれ、その設置高さを一階床面とほぼ同じレベルにするようにしたので、作業者は強制排気装置9の上を自由に歩行でき、荷物の移動時にも換気装置を引っ掛けたりすることはなく、現場での良好な作業性が担保される。
The forced exhaust device 9 as described above can be easily installed by being housed in a box-shaped support member 12 and dropping into the first floor under the floor inspection port 8 provided on the first floor with the support member 12. In addition, the installation state is stable due to the weight of the device. Further, at the stage where the operation of releasing the contained water is completed, the supporting member 12 can be easily removed by pulling it up from the underfloor inspection port 8.
Furthermore, since the support member 12 is stored below the floor of the first floor at the underfloor inspection port 8 and does not protrude, it is placed on the forced exhaust device 9 using the periphery of the underfloor inspection port 8 ( It is protected by a lattice-shaped protective member 13 (which is fitted). That is, the protective member 13 is set to have almost the same installation height as the first floor surface.
It can be protected by a grid-like protective member 13 placed on the forced exhaust device 9 by using the periphery of the underfloor inspection port 8, and construction materials etc. are placed on the forced exhaust device 9 while ensuring the inflow of air. Can be prevented in advance, and the protective member 13 is fitted on the flange-like edge 12b of the support member 12 along the periphery of the underfloor inspection port 8, and its installation height is set to the first floor surface. The operator can walk freely on the forced exhaust system 9, and does not catch the ventilator when moving the load, ensuring good workability on site. Is done.

上記のような構造の強制排気装置9は、有圧型であるので、空気の除湿に必要な多量の風量を一基で確保できる。上記強制排気装置9を運転すると、躯体2の内部空間は、減圧気味になり、ALC建材等の建材からの余剰水分の放出が促進される。
更に、床下点検口8への設置なので、窓に設置する場合のように、作業者が不在の夜間でも防犯上の問題を生じさせることはなく、また排気や騒音等で隣家に迷惑をかけることもない。
強制排気装置9を運転して、外気を躯体2の内部空間に導き、躯体2の内部空間において強制循環させて、基礎構造1の内部空間を経由してその換気口3aから再び外部に排出するが、その流通せしめられる外気が吸水している躯体2の建材周辺を通過して、建材の表面から水分を吸収し、これを乾燥させ、建設工事中において建材の含有水分の放出が促進される。強制排気装置9の運転は、各建材の含有水分の放出がある程度完了するまでの間実施され、作業者がいる日中のみならず、夜間でも継続的に実施される。
Since the forced exhaust device 9 having the above structure is a pressure type, a large amount of air necessary for dehumidifying the air can be secured by a single unit. When the forced exhaust device 9 is operated, the internal space of the housing 2 becomes a reduced-pressure atmosphere, and the release of excess moisture from building materials such as ALC building materials is promoted.
Furthermore, because it is installed at the inspection floor 8, it does not cause security problems even at night when there are no workers, and it causes trouble to the neighbors due to exhaust and noise. Nor.
By operating the forced exhaust device 9, the outside air is guided to the internal space of the housing 2, is forcedly circulated in the internal space of the housing 2, and is discharged to the outside again from the vent 3 a through the internal space of the foundation structure 1. However, it passes through the surroundings of the building material 2 of the housing 2 where the circulated outside air absorbs water, absorbs moisture from the surface of the building material, dries it, and promotes the release of moisture contained in the building material during construction work. . The operation of the forced exhaust device 9 is performed until the release of moisture contained in each building material is completed to some extent, and is continuously performed not only during the day when the worker is present but also at night.

そして、上述の如き水分除去工程(ステップS1-3)を所定期間(例えば3〜7日)行って躯体施工(ステップS1)を完了した建物について、図7(a)に示す如く、当該上部構造躯体2に気密層を形成する気密施工(ステップS2)を施すのである。
なお、上記水分除去工程(ステップS1-3)は躯体施工(ステップS1)に属するものの、建材の含有水分の放出具合に応じ、一方で気密施工(ステップS2)やその後の施工を行いつつ続行することも可能である。その場合であっても、水分除去工程は、作業開始から概ね2〜4週間程度、建物完成前まで完了する。上述の如く水分除去工程は強制換気装置9を運転しつづける工程であるため、他の工程作業を阻害することなく行うことが可能となっているのである。
気密施工(ステップS2)は、上記躯体施工(ステップS1)を行う業者とは異なる業者によってなされるものであって、外壁よりも内側に気密性断熱材25を配備する沿外壁気密工程(ステップS2-1)と、屋根スラブに沿って気密性断熱材25を設ける沿屋根気密施工(ステップS2-2)と、1階床スラブ上に気密性断熱材25を敷設する沿床気密工程(ステップS2-3)と、を備えている。
沿外壁気密施工(ステップS2-1)は、外壁の内側の面に沿って気密性断熱材25を配備する外壁断熱工程と、当該外壁を支持する梁や当該梁を支持する柱周りに気密性断熱材を配備する構造断熱工程とを備えている。構造断熱工程は、上記構造部材のうち、外壁等を支持すべく最外に位置する構造部材の内側の面又は外側の面の何れかに沿って気密性断熱材25を設ける工程であって、本実施形態においては、当該構造部材の内側の面に沿って気密性断熱材25を敷設する。
また、沿屋根気密施工(ステップS2-2)は、屋根スラブの上面又は下面に沿って気密性断熱材25を敷設するものであって、本実施形態においては、屋根スラブの上面に気密性断熱材25を敷設することとし、その後、当該気密性断熱材25上に防水層を形成することとしている。
また、沿床気密工程(ステップS2-3)は、上述の如く1階の床スラブ6a上に気密性断熱材25を敷設することとするが、当該気密性断熱材25を1階床スラブの下方に設ける構成も採用可能である。
Then, as shown in FIG. 7A, the upper structure of the building in which the moisture removal process (step S1-3) as described above is performed for a predetermined period (for example, 3 to 7 days) to complete the frame construction (step S1) is performed. An airtight construction (step S2) for forming an airtight layer on the housing 2 is performed.
In addition, although the said water removal process (step S1-3) belongs to a frame construction (step S1), according to the discharge | release condition of the moisture content of building materials, it continues on the other hand, performing airtight construction (step S2) and subsequent construction. It is also possible. Even in that case, the water removal process is completed for about 2 to 4 weeks from the start of work until before the building is completed. As described above, the water removal step is a step in which the forced ventilation device 9 is continuously operated, so that it can be performed without hindering other process operations.
The airtight construction (step S2) is performed by a contractor different from the contractor performing the above-mentioned frame construction (step S1), and the outside wall airtight process (step S2) in which the airtight heat insulating material 25 is arranged inside the outer wall. -1), along the roof slab, along the roof slab, along the roof slab (step S2-2), and along the first floor slab, along the floor slab, along the floor hermetic step (step S2). -3).
The exterior wall hermetic construction (step S2-1) includes an outer wall heat insulation process in which an airtight heat insulating material 25 is arranged along the inner surface of the outer wall, and a beam that supports the outer wall and a column that supports the beam. And a structural heat insulating step of disposing a heat insulating material. The structural heat insulating step is a step of providing an airtight heat insulating material 25 along either the inner surface or the outer surface of the structural member located on the outermost side to support the outer wall or the like among the structural members, In this embodiment, the airtight heat insulating material 25 is laid along the inner surface of the structural member.
Further, the airtight construction along the roof (step S2-2) is to lay the airtight heat insulating material 25 along the upper surface or the lower surface of the roof slab. In this embodiment, the airtight heat insulation is performed on the upper surface of the roof slab. The material 25 is laid, and then a waterproof layer is formed on the airtight heat insulating material 25.
In the floor-to-floor airtight process (step S2-3), the airtight heat insulating material 25 is laid on the floor slab 6a on the first floor as described above. A configuration provided below can also be employed.

なお、当該気密施工(ステップS2)により用いられる気密性断熱材25は、フェノール樹脂発泡体等の気密性と断熱性の両方を具備する硬質プラスチック系の板状の断熱パネルによって形成されており、これによって当該断熱パネルを通じての通気は著しく制限される。上記各断熱施工においては、複数の断熱パネルを互いに突きつけて連続させることによって断熱層が形成されている。
さらに、各断熱パネル間の継目はもちろん、各気密施工(ステップS2)によって形成される気密層間は、気密テープにより目張りされており、該気密テープによる目張りがなされることにより、当該気密性断熱材25と気密テープとによって躯体の内側に気密層(断熱気密層)が形成されることとなるのである。
In addition, the airtight heat insulating material 25 used by the said airtight construction (step S2) is formed by the hard plastic type plate-shaped heat insulation panel which has both airtightness and heat insulation, such as a phenol resin foam, This significantly restricts ventilation through the insulation panel. In each said heat insulation construction, the heat insulation layer is formed by mutually abutting a plurality of heat insulation panels.
Furthermore, the airtight layers formed by the respective airtight constructions (step S2) as well as the joints between the respective heat insulating panels are covered with an airtight tape, and the airtight heat insulating material is formed by being covered with the airtight tape. Thus, an airtight layer (heat insulating airtight layer) is formed inside the housing by 25 and the airtight tape.

なお、沿外壁気密施工(ステップS2-1)においては屋根スラブ上に気密性断熱材25が敷設されることとなるが、最上階での外壁断熱施工においては、当該屋根スラブを支持する梁を覆う気密性断熱材25の上端部を屋根スラブに当接させ、当該屋根スラブと気密性断熱材25との境界となる継目を気密テープ等で目張りすることによって気密性が確保されている。
上記施工により気密施工(ステップS2)を完了することにより、躯体2に断熱層が形成されると共に気密層が形成されることとなる。ここで、本実施形態においては、当該気密施工(ステップS2)により形成された気密層の気密性能を確認する目的で、上記気密施工の完了の後、気密確認作業(ステップS3)を行う。
In the exterior wall airtight construction (step S2-1), the airtight heat insulating material 25 is laid on the roof slab. However, in the outer wall heat insulation construction on the top floor, the beam that supports the roof slab is installed. The upper end of the airtight heat insulating material 25 to be covered is brought into contact with the roof slab, and the seam serving as a boundary between the roof slab and the airtight heat insulating material 25 is lined with an airtight tape or the like to ensure airtightness.
By completing the airtight construction (step S2) by the above construction, a heat insulating layer is formed on the housing 2 and an airtight layer is formed. Here, in this embodiment, for the purpose of confirming the airtight performance of the airtight layer formed by the airtight construction (step S2), the airtightness confirmation work (step S3) is performed after the completion of the airtight construction.

図7(b)に示す当該気密確認作業(ステップS3)は、躯体2の内外に亘って差圧計26を設けると共に開口部等を塞ぐ準備工程と、当該準備工程の後に上記強制排気装置9を起動させて建物の内外に差圧を発生させる差圧発生工程と、当該差圧工程の後に建物内外の差圧を測定するする測定工程とを備えている。
差圧計26は、U字管マノメータ、ブルドン管式差圧計、ダイヤフラム式微差圧計等の公知のものであって、本実施形態においては、管を湾曲形成してなるU字管部26aと、該U字管部の一端に連結される一方のチューブ26bと、他端に連結される他方のチューブ26cとを備えている。
当該準備工程は、躯体2内にあっては一方のチューブ26bの先端を強制排気装置9による送風の影響を受け難い場所に、屋外にあっては他方のチューブ26cの先端を外部風の影響を受け難い場所に設置する。また、躯体2の外壁には、上述の如く何れかの位置には、常時換気の通気口等、竣工後には通気孔となる貫通穴2aが形成されているので、気密層にも当該貫通穴2aに対向する位置に貫通穴25aを形成することとし、上記差圧計26を設置するには、何れか一方のチューブ26b,26cを貫通穴2a、25aを通じて躯体2の内外に亘って設け、その後、当該貫通穴2a、25aに充填材等の詰め物を充填して隙間を埋める。
In the airtightness confirmation operation (step S3) shown in FIG. 7B, a differential pressure gauge 26 is provided over the inside and outside of the housing 2 and an opening and the like are closed, and the forced exhaust device 9 is installed after the preparation step. It comprises a differential pressure generating step that is activated to generate a differential pressure inside and outside the building, and a measurement step that measures the differential pressure inside and outside the building after the differential pressure step.
The differential pressure gauge 26 is a known one such as a U-tube manometer, a Bourdon tube-type differential pressure meter, a diaphragm-type fine differential pressure meter, etc. In this embodiment, a U-shaped tube portion 26a formed by bending a tube, One tube 26b connected to one end of the U-shaped tube portion and the other tube 26c connected to the other end are provided.
In the preparatory step, the tip of one tube 26b is not easily affected by the air blow by the forced exhaust device 9 in the housing 2, and the tip of the other tube 26c is affected by external wind in the outdoors. Install in a place that is difficult to receive. Moreover, since the through-hole 2a used as a ventilation hole after completion is formed in the outer wall of the housing | casing 2 in any position as above-mentioned, such as a ventilation hole for normal ventilation, the said through-hole is also formed in an airtight layer. In order to form the through hole 25a at a position opposite to 2a and to install the differential pressure gauge 26, either one of the tubes 26b and 26c is provided over the inside and outside of the housing 2 through the through holes 2a and 25a. The through holes 2a and 25a are filled with a filling material such as a filler to fill the gap.

なお、3階建てのような高い建物や内外温度差が大きい場合の建物内の圧力差測定の高さ位置は、上下圧力分布の中性帯近傍が好ましい。また、測定の正確を期すためには、建物内の測定対象期間の圧力差の分布は内外圧力差の10%以内であることを確認することが好ましい。また、当該準備工程においては、差圧計26のゼロ点の確認をすべく、圧力差を測定する前に、チューブ26b,26cを外して圧力差測定器の差圧のゼロ点を確認しておく。
なお、測定工程を終えた測定終了後に、強制排気装置9を停止させて再びゼロ流量時の内外圧力差を測定し、測定前後に圧力差を生じていないことを確認することは好ましい。
また、上述の如く差圧計26を設置すると共に、窓等、通常の開口部や、上記気密施工の段階で形成されている貫通穴等を適宜隙間なく塞ぎ、これら開口部や貫通穴等を通じて躯体内外への空気の流出入を確実に防止する。
In addition, the height position of the pressure difference measurement in a high building such as a three-story building or a large internal / external temperature difference is preferably near the neutral zone of the vertical pressure distribution. In order to ensure the accuracy of the measurement, it is preferable to confirm that the pressure difference distribution in the measurement target period in the building is within 10% of the internal / external pressure difference. Moreover, in the said preparation process, before measuring a pressure difference, in order to confirm the zero point of the differential pressure gauge 26, the tubes 26b and 26c are removed and the zero point of the differential pressure | voltage of a pressure difference measuring device is confirmed. .
Note that it is preferable to stop the forced exhaust device 9 after the measurement process is completed and measure the internal / external pressure difference at zero flow rate again to confirm that no pressure difference occurs before and after the measurement.
In addition, the differential pressure gauge 26 is installed as described above, and a normal opening such as a window or a through hole formed at the stage of the airtight construction is appropriately closed without gaps, and the casing is formed through the opening and the through hole. Ensure that air flow in and out is prevented.

次に、差圧発生工程は、図7(c)に示す如く強制排気装置9を起動させて上部構造躯体内の空気を1階床スラブ下方の床下空間に向けて排出し、当該上部構造躯体内を減圧する。
ここで、強制排気装置9は上述の如く1000m/時の換気能力を有する有圧型の換気装置であって、当該強制排気装置は、台所レンジ等の局所換気を行うために完成後の建物に常設される通常の換気装置(400m/時〜600m/時程度の換気能力)よりも著しく大きな換気量で躯体内を減圧することが可能であると共に、当該躯体内が外気よりも減圧される場合であっても、換気量を著しく低下する虞はなく、所定の換気能力を発揮して躯体内を減圧するものとなる。
Next, in the differential pressure generating step, as shown in FIG. 7C, the forced exhaust device 9 is activated to discharge the air in the upper structural body toward the under-floor space below the first floor slab. The inside is depressurized.
Here, the forced exhaust device 9 is a pressure type ventilator having a ventilation capacity of 1000 m 3 / hour as described above, and the forced exhaust device is installed in a completed building in order to perform local ventilation such as a kitchen range. at a significantly greater ventilation than normal ventilator is permanent (400 meters 3 / hour ~600m 3 / h approximately ventilation capacity) with a skeleton body can be vacuum, the skeleton body is decompressed than the outside air Even if it is a case, there is no possibility that the amount of ventilation will fall remarkably, and the inside of a housing will be decompressed by exhibiting predetermined ventilation ability.

本実施形態においては、図8に示す静圧―風量特性を有する強制排気装置9を採用しており、本願発明者は、当該強制排気装置9を起動させることにより、100〜150m程度の床面積を有する2階建ての躯体の内外で少なくとも10Pa程度の差圧を生じさせることが可能であることを知見しており、この程度の差圧を確認することができれば、上記差圧計による差圧の測定には充分であることも確認している。
なお、上記静圧―風量特性を有する強制排気装置9は、上述の如き水分除去工程に用いられる強制排気装置としても充分な性能を有している。
また、当該強制排気装置9により、床下空間Sに排気を行うこととなるので、躯体2と基礎構造によって包囲される床下空間を加圧状態とすることができる。このため、躯体2の内部空間と基礎構造1の内部空間(床下空間S)との差圧は、該躯体2の内部空間と屋外空間との差圧よりも加圧分だけ大きなり、これによって、躯体2の内部空間と基礎構造1の内部空間とを連通する漏気路が存在する場合には、当該漏気路を通じての該基礎構造1の内部空間から躯体2の内部空間に向けての漏気を過大に評価することができ、ひいては当該漏気路の存在を厳しく評価することが可能となっている。即ち、内外差圧が著しく小さい場合等は、先ずかかる漏気路の存在を疑うことができるのである。冬季等の温度差による換気は、この様な躯体の下方に存在する漏気路によって大きくなりやすいため、当該漏気路の存在を可及的減じることが躯体の気密性能向上に有効であるが、上述の如く基礎構造1の内部空間に向けて排気させることにより、当該漏気路の発見に有利に作用することとなる。
In the present embodiment, the forced exhaust device 9 having the static pressure-air flow characteristic shown in FIG. 8 is adopted, and the inventor of the present application activates the forced exhaust device 9 to thereby have a floor of about 100 to 150 m 2. We know that it is possible to generate a differential pressure of at least about 10 Pa on the inside and outside of a two-story housing having an area, and if this level of differential pressure can be confirmed, the differential pressure by the differential pressure gauge It has also been confirmed that this is sufficient for the measurement.
The forced exhaust device 9 having the static pressure-air flow characteristics has sufficient performance as a forced exhaust device used in the moisture removal process as described above.
In addition, since exhaust is performed to the underfloor space S by the forced exhaust device 9, the underfloor space surrounded by the housing 2 and the foundation structure can be in a pressurized state. For this reason, the differential pressure between the internal space of the enclosure 2 and the internal space of the foundation structure 1 (underfloor space S) is larger than the differential pressure between the internal space of the enclosure 2 and the outdoor space, When there is an air leakage path that connects the internal space of the housing 2 and the internal space of the foundation structure 1, the internal space of the basic structure 1 through the air leakage path is directed toward the internal space of the housing 2. Leakage can be overestimated, and as a result, the existence of the leakage path can be strictly evaluated. That is, when the internal / external differential pressure is extremely small, the existence of such an air leakage path can be suspected first. Ventilation due to temperature differences in winter and the like is likely to increase due to the air leakage path that exists below the chassis, so reducing the presence of the air leakage path as much as possible is effective in improving the airtight performance of the chassis. As described above, exhausting air toward the internal space of the foundation structure 1 has an advantageous effect on the discovery of the leakage path.

そして、強制排気装置9を所定時間起動させて上部構造体内外に差圧を生じさせた後、当該差圧Paを差圧計により測定し、当該測定した差圧Paを対応表に対応させて、現計測時点での気密状態を確認する(測定工程)。その後、強制排気装置9を停止させ、気密性確認作業(ステップS3)を終了する。   Then, after starting the forced exhaust device 9 for a predetermined time to generate a differential pressure inside and outside the upper structure, the differential pressure Pa is measured with a differential pressure gauge, and the measured differential pressure Pa is made to correspond to the correspondence table, Check the airtight state at the time of the current measurement (measurement process). Thereafter, the forced exhaust device 9 is stopped, and the airtightness confirmation operation (step S3) is terminated.

上記対応表は、図9に示す如く、躯体の延べ床面積を横軸、内外差圧を縦軸として示されるグラフGであって、当該グラフGは、隙間特性値n=1.67とした場合に各延べ床面積に対し躯体の有効隙間面積C=3cm/mとなる内外差圧Pをプロットしたものであり、上記計測差圧Paの値がグラフGの下側に位置する場合(Pa<P)、気密性は充分に保たれている(C=3cm/m以下)ことが確認される一方、上記計測差圧Paの値がグラフGの上側に位置する場合(Pa>P)、気密性が確保されていない(C=3cm/m以上)であることが確認される。 As shown in FIG. 9, the above correspondence table is a graph G in which the total floor area of the frame is shown on the horizontal axis and the internal / external differential pressure is shown on the vertical axis, and the graph G has a gap characteristic value n = 1.67. In this case, the internal and external differential pressure P at which the effective gap area C of the frame is 3 cm 2 / m 2 is plotted against each total floor area, and the value of the measured differential pressure Pa is located below the graph G (Pa <P), while it is confirmed that the airtightness is sufficiently maintained (C = 3 cm 2 / m 2 or less), while the value of the measured differential pressure Pa is located on the upper side of the graph G (Pa > P), it is confirmed that hermeticity is not ensured (C = 3 cm 2 / m 2 or more).

ここで、隙間特性値とは、隙間の状態を示し、以下の式1で示される通気特性式を対数で表した場合の直線の傾きを示すものであって、1.0〜2.0の範囲で定められ、それぞれの隙間がきわめて狭い場合にはnは1.0に近づき、広くなるにつれてnは2.0に近づく。本願発明者は、実証試験等を繰り返すことで、住宅等の建物においては当該隙間特性値が1.5〜1.7の範囲内に納まることを確認しており、対応表の作成おいては、当該範囲内で適宜建物に合った数値を採用すればよい。

Figure 2010071950
但し、Q:通気量(m/h、送風機により建物内外に圧力差を生じさせたとき、建物外皮の隙間を通して外から内へ、もしくは内から外へ流れる空気の量。また、本願においては強制排気装置の換気量に相当)
a:通気率(m/h・Pa1/n、通気特性式の係数で、建物内外の圧力差が1Paのときの1時間当たりの通気量)
ΔP:内外圧力差(Pa、建物の内外圧力差)
n:隙間特性値
また、相当隙間面積とは、総相当隙間面積を建物外皮内の実質延べ面積で除したものであり、以下の式2で示される。実質延べ床面積は建物によって明らかになるものであるから、総相当隙間面積を仮定することにより、相当隙間面積を仮定することができる。
Figure 2010071950
但し、C:相当隙間面積(cm/m、総相当隙間面積を建物外皮内の実質延べ床面積で除したもの)
αA:総相当隙間面積(cm、建物内外の圧力差9.8Pa時の通気量から、隙間と等価の単純開口の有効面積を算出したもの)
S:実質延べ床面積(m、原則的に建物外皮内の換気にかかわる部分の延べ床面積) Here, the gap characteristic value indicates the state of the gap, and indicates the slope of a straight line when the airflow characteristic expression represented by the following expression 1 is expressed in logarithm, and is 1.0 to 2.0. If each gap is very narrow, n approaches 1.0, and as it becomes wider, n approaches 2.0. The inventor of the present application has confirmed that the gap characteristic value is within the range of 1.5 to 1.7 in a building such as a house by repeating a verification test and the like. Any numerical value suitable for the building within the range may be adopted.
Figure 2010071950
However, Q: Ventilation rate (m 3 / h, the amount of air flowing from outside to inside or from inside to outside through a gap in the building skin when a pressure difference is generated inside and outside the building by a blower. Equivalent to forced exhaust ventilation
a: Ventilation rate (m 3 / h · Pa 1 / n , coefficient of ventilation characteristic formula, ventilation rate per hour when the pressure difference inside and outside the building is 1 Pa)
ΔP: Pressure difference between inside and outside (Pa, pressure difference inside and outside the building)
n: Gap characteristic value The equivalent gap area is obtained by dividing the total equivalent gap area by the substantial total area in the outer skin of the building, and is expressed by Equation 2 below. Since the actual total floor area is determined by the building, the equivalent gap area can be assumed by assuming the total equivalent gap area.
Figure 2010071950
C: equivalent gap area (cm 2 / m 2 , total equivalent gap area divided by the total floor area in the building skin)
αA: Total equivalent clearance area (cm 2 , the effective area of a simple opening equivalent to the clearance calculated from the air flow rate when the pressure difference between inside and outside the building is 9.8 Pa)
S: Real total floor area (m 2 , in general, the total floor area of the part related to ventilation inside the building skin)

なお、該強制排気装置は、図8に示す如く、例えば内外差圧を10Pa程度の低静圧とする場合、当該内外差圧(静圧)に対する風量の低下が比較的小さいため、上記対応表を予め作成するにつき、内外差圧による風量低下に基づく補正等を行う必要はない。一方、例えば内外差圧を10Pa程度以上となる場合には、当該内外差圧に伴う風量の低下が生じてしまうため、上記対応表の作成においては、かかる風量の低下を見込んでグラフを作成しておく必要がある。
また、当該グラフは、建物の隙間特性値nや仮定すべき相当隙間面積Cの値によって傾きや形状を異にするものであるが、検証すべき建物によって適正なグラフを作成し、当該グラフを計測値の比較対象として採用することが望ましい。本実施形態においては、上述の如き対応表を採用しているが、対応表としては上記のものに限定されず、検証すべき建物の隙間特性や当該建物に要求される相当隙間面積に対しある程度の許容値や安全率を見込むことによって得られる当該建物の実情に合ったグラフを予め作成したものも含む。また、対応表としては、これら隙間特性と相当隙間面積の何れか一方又は両方を変更したグラフが複数用意されているものも含み、当該対応表においては、検証すべき建物に応じて用いるべきグラフを予め決定しておく等の対応と取ることが可能となり、これによって、検証のさらなる容易化が図られるのである。
さらには、グラフと得られた座標とを比較する場合においても、用いるグラフのある程度下方まで気密性が確保されている、又は用いるグラフのある程度上方まで気密性が確保されていない、と仮定する等、当該グラフを測定対象となる躯体2の実情等に応じた気密性判断の目安に用いることも可能である。
As shown in FIG. 8, when the internal / external differential pressure is set to a low static pressure of about 10 Pa, for example, the forced exhaust device has a relatively small decrease in the air volume with respect to the internal / external differential pressure (static pressure). , It is not necessary to perform correction based on a decrease in the air volume due to the internal / external differential pressure. On the other hand, for example, when the internal / external differential pressure is about 10 Pa or more, the air volume is reduced due to the internal / external differential pressure. Therefore, in the creation of the correspondence table, a graph is prepared in anticipation of such air volume reduction. It is necessary to keep.
Moreover, although the said graph changes inclination and a shape with the value of the gap characteristic value n of a building, and the value of the equivalent gap area C which should be assumed, an appropriate graph is produced according to the building to be verified, It is desirable to adopt as a comparison target of measured values. In the present embodiment, the correspondence table as described above is adopted, but the correspondence table is not limited to the above-mentioned one, and to some extent the gap characteristics of the building to be verified and the equivalent gap area required for the building. This includes a graph created in advance that fits the actual situation of the building, which is obtained by considering the allowable value and safety factor. In addition, the correspondence table includes a graph prepared by changing one or both of the gap characteristics and the equivalent gap area. In the correspondence table, the graph to be used according to the building to be verified. It is possible to take measures such as pre-determining the value, thereby further facilitating the verification.
Furthermore, even when comparing the graph and the obtained coordinates, it is assumed that airtightness is secured to some extent below the graph used, or airtightness is not secured to some extent above the graph used, etc. It is also possible to use the graph as a measure of airtightness judgment according to the actual situation of the casing 2 to be measured.

また、当該気密性確認作業(ステップS3)は、躯体2の内外で差圧を形成するための装置が既設の上記強制排気装置9を用いて行われ、また、差圧計26の設置も上記貫通孔を通じてなされることによりきわめて容易になされ、準備工程は、躯体2の開口部の目張り等に時間を要するとしても10数分程度で完了する。また、当該強制排気装置9の換気量(又は風量)を安定させて躯体内外の差圧をある程度定常状態にする差圧発生工程には1分程度を要するのみである。さらには、上記強制排気装置9によれば差圧を10Pa程度生じさせることが可能となっているので、上述の如き差圧計26であっても充分に目視可能な差圧が示されることとなり、これによって差圧の確認する差圧確認作業は数秒で済むこととなるので、当該気密性確認作業(ステップS3)は、差圧計26を取り外す作業を含めても全体でも1時間弱程度で完了し、きわめて短時間で且つ簡易になされることとなる。   In addition, the airtightness confirmation operation (step S3) is performed using the above-described forced exhaust device 9 for forming a differential pressure inside and outside the housing 2, and the differential pressure gauge 26 is also installed through the above-mentioned through-hole. The preparation process can be made very easily by being done through the hole, and the preparation process is completed in about 10 minutes even if it takes time to open the opening of the housing 2. In addition, the differential pressure generating step of stabilizing the ventilation amount (or air volume) of the forced exhaust device 9 and setting the differential pressure inside and outside the housing to a certain steady state only requires about 1 minute. Further, according to the forced exhaust device 9, it is possible to generate a differential pressure of about 10 Pa, so that even the differential pressure gauge 26 as described above shows a sufficiently visible differential pressure, As a result, the differential pressure confirmation work for confirming the differential pressure can be completed in a few seconds. Therefore, the airtightness confirmation work (step S3) can be completed in about an hour or less, including the work for removing the differential pressure gauge 26. This is done in a very short time and easily.

そして、上記対応表を参照することにより、当該差圧Paが当該躯体2に要求されるC値を維持するために必要とされる内外差圧Pよりも大きいと確認される場合には、図9に示す如く、上記気密施工(ステップS2)では躯体2に対し所望の気密性が確保されていないと判断され(ステップS3-1)、当該気密施工を行った業者は、気密性を確保すべく各箇所の点検・気密確保のための補修等を行う(ステップS2-1,S2-2,S2-3)。
また、当該差圧Paが当該躯体2に要求されるC値を維持するために必要とされる内外差圧Pよりも小さいと確認される場合には、上記気密施工により躯体の気密性が要求される気密性以上に確保されていると判断され(ステップS3-1)、気密施工を行った業者は当該気密施工を完了させると共に躯体2は次工程に移行する。
When it is confirmed by referring to the correspondence table that the differential pressure Pa is greater than the internal / external differential pressure P required to maintain the C value required for the housing 2, As shown in FIG. 9, it is judged that the desired airtightness is not secured for the housing 2 in the airtight construction (step S2) (step S3-1), and the contractor who performed the airtight construction secures the airtightness. Therefore, inspections and repairs for ensuring airtightness are performed (steps S2-1, S2-2, S2-3).
Moreover, when it is confirmed that the differential pressure Pa is smaller than the internal / external differential pressure P required to maintain the C value required for the housing 2, the airtightness of the housing is required by the airtight construction. It is judged that it is secured more than the airtightness to be performed (step S3-1), and the contractor who performed the airtight construction completes the airtight construction and the casing 2 moves to the next process.

次に、上記気密施工を行う業者とは異なる業者によって、図10(a)に示す設備施工(ステップS4)を行う。当該設備施工とは、躯体2の内外に亘って水道管や排水管等を配設する水道配管工程(ステップS4-1)や、躯体2の内外に亘って電気配線等を行う電気配線工程(ステップS4-3)等であって、これらの施工は同一の業者又は異なる業者によって行われる。
また、これらの設備施工は、気密層を事前に形成しているにも拘らず、躯体2の外壁及び気密層を貫通させる貫通孔を開設し、当該貫通孔内に配管や配線等(以下、配管等27という)を配設する施工を伴うものであって、当該配管等27を配設した後には当該貫通孔に充填材等を充填して隙間を塞ぐ。当該作業(気密回復工程(ステップS4-2,S4-4))は、孔を開設することにより一旦は気密性が劣化するものの、充填材の充填による隙間の封止により、気密性は一応回復されると考えられる。
Next, the facility construction (step S4) shown in FIG. 10A is performed by a contractor different from the contractor performing the airtight construction. The facility construction means a water pipe process (step S4-1) in which water pipes and drain pipes are arranged inside and outside the casing 2, and an electric wiring process in which electrical wiring is carried out inside and outside the casing 2 ( Step S4-3) and the like, and these constructions are performed by the same contractor or different contractors.
Moreover, although these facilities construction has formed the airtight layer in advance, the through-hole which penetrates the outer wall of the housing 2 and the airtight layer is opened, and piping, wiring, etc. (hereinafter, referred to as the following) This is accompanied by construction for arranging the pipes 27 and the like. After the pipes 27 are arranged, the through holes are filled with a filler or the like to close the gap. In this work (airtight recovery process (steps S4-2 and S4-4)), the airtightness is temporarily deteriorated by opening the hole, but the airtightness is temporarily recovered by sealing the gap by filling the filler. It is thought that it is done.

本実施形態は、上述の如き設備施工(ステップS4)による躯体2の気密性の変動を確認すべく、当該設備施工(ステップS4)の完了の後に、図10(b)に示す如く開設した貫通孔を閉塞した状態で上述の気密性確認作業を再び行い、躯体2の当該測定時点での差圧Pbを測定し、当該測定値がグラフGに対し上下いずれに位置するかを確認する(ステップS5)。
そして、当該差圧PbがグラフGよりも上側に位置する場合には、図9に示す如く上記設備施工によって躯体の気密性が要求される気密性よりも悪化したことと判断され(ステップS5-1)、設備施工を行った業者は、気密性を確保すべく加工した部分を中心に各箇所の点検・気密確保のための補修等を行う(ステップS4-2,S4-4)。
また、当該差圧PbがグラフGよりも下側に位置する場合には、上記設備施工を行ったにも拘らず躯体の気密性が要求される気密性以上に確保されていると判断され(ステップS5-1)、設備施工を行った業者は、施工を完了させると共に躯体2についての施工は内装施工、仕上げ施工等(ステップS6)を経て完成する。
In the present embodiment, in order to confirm the change in the airtightness of the housing 2 due to the equipment construction (step S4) as described above, the through-hole opened as shown in FIG. 10B after the equipment construction (step S4) is completed. The above-mentioned airtightness confirmation operation is performed again in a state where the hole is closed, the differential pressure Pb at the measurement time of the housing 2 is measured, and it is confirmed whether the measurement value is located above or below the graph G (step) S5).
When the differential pressure Pb is located above the graph G, it is determined that the airtightness of the housing is deteriorated from the required airtightness by the above-described facility construction as shown in FIG. 9 (step S5−). 1) The contractor who has installed the equipment performs inspections and repairs for ensuring airtightness around the parts processed to ensure airtightness (steps S4-2 and S4-4).
Moreover, when the said differential pressure Pb is located below the graph G, it is judged that the airtightness of a housing is ensured more than the airtightness requested | required in spite of having performed the said equipment construction ( In step S5-1), the contractor who performed the facility construction completes the construction and completes the construction of the frame 2 through interior construction, finishing construction, and the like (step S6).

本実施形態によれば、気密施工(ステップS2)が完了した段階で、躯体2に設けられる強制排気装置9を利用して躯体2の気密性を検証するので、気密施工(ステップS2)までの施工における気密性を検証することができ、自己の作業責任を達成できたことを確認することができることとなる。また、これにより、建物に対する気密性についての各工程完了時点での責任の所在をはっきりさせることができ、この結果、例えば気密施工業者と設備施工業者との間でいずれが気密性を損なう施工を行ってしまったのか、といった無用の争いが生じる虞はない。
また、強制排気装置9として、躯体の内部空間に外気を導入して上記建材の含有水分の放出を促進する装置を流用できるので、気密確認のためにだけ強制排気装置9を準備し設置する必要がなく、施工の遅延化を回避しつつ気密の確認を行うことができる。また、強制排気装置9より、所定の換気量を確保することにより、建物内外の差圧を確保することができ、測定の精度はそれほど高いものではないものの、簡便な差圧計26により、また予め作成した図9の如くの対応表を利用することにより、各施工段階に於ける気密の変動を十分な精度で検査することができる。また、強制排気装置9は、床下点検口8に設置するようにしたので、躯体2と基礎構造1によって包囲される床下空間Sを加圧状態とすることができ、躯体2の内部空間と床下空間Sとの差圧は、躯体2の内部空間と屋外空間との差圧よりも加圧分だけ大きなり、よって、躯体2の内部空間と基礎構造1の内部空間とを連通する漏気路の存在を厳しく評価することができる。また、強制排気装置9は、床下点検口8に落とし込むだけで容易に設置でき、撤去も極めて容易に行えるので作業性が良好である。更に、強制排気装置9等の設置や差圧の測定等が簡便であるため、施工の進捗に応じて適宜気密性を測定することができ、また外的条件(気温・湿度等)を除いて原則的に常に同一条件で計測することとなるので、施工の進捗に応じた測定結果の信頼性も比較的高い。
According to this embodiment, since the airtightness of the housing 2 is verified using the forced exhaust device 9 provided in the housing 2 at the stage where the airtight construction (step S2) is completed, the steps up to the airtight construction (step S2) are performed. Airtightness in construction can be verified, and it can be confirmed that one's own work responsibility has been achieved. In addition, this makes it possible to clarify the location of responsibility at the time of completion of each process for the airtightness of the building, and as a result, for example, between the airtight construction contractor and the equipment contractor, the construction that impairs the airtightness. There is no risk of unnecessary conflicts such as whether they have gone.
Further, as the forced exhaust device 9, a device that introduces outside air into the internal space of the housing and promotes the release of moisture contained in the building material can be diverted. Therefore, it is necessary to prepare and install the forced exhaust device 9 only for airtightness confirmation. No airtightness can be confirmed while avoiding delays in construction. Further, by ensuring a predetermined ventilation amount from the forced exhaust device 9, it is possible to ensure a differential pressure inside and outside the building, and although the accuracy of measurement is not so high, a simple differential pressure gauge 26 is used in advance. By using the created correspondence table as shown in FIG. 9, it is possible to inspect the airtight variation at each construction stage with sufficient accuracy. In addition, since the forced exhaust device 9 is installed in the underfloor inspection port 8, the underfloor space S surrounded by the casing 2 and the foundation structure 1 can be brought into a pressurized state, and the internal space of the casing 2 and the underfloor The differential pressure with the space S is larger than the differential pressure between the internal space of the housing 2 and the outdoor space by an amount of pressurization, and thus the air leakage path that connects the internal space of the housing 2 and the internal space of the foundation structure 1. Can be evaluated strictly. Further, the forced exhaust device 9 can be easily installed just by dropping it into the underfloor inspection port 8 and can be removed very easily, so that workability is good. Furthermore, since the installation of the forced exhaust system 9 and the measurement of the differential pressure, etc. are simple, the airtightness can be measured appropriately according to the progress of the construction, and excluding external conditions (temperature, humidity, etc.) In principle, measurements are always made under the same conditions, so the reliability of the measurement results according to the progress of construction is relatively high.

なお、参考として、「住宅の気密性能試験方法」(発行:財団法人 建築環境・省エネルギー機構、編集:気密測定技術普及委員会)に基づく住宅の気密性の試験方法によれば、試験装置として、温度計、送風機、流量測定器、流量測定装置及び圧力差測定器を必要とし、1試験を完了するには60〜120分程度を要し、試験を行うにはきわめて大掛かりでなく多大な時間を要するものとなってしまう。   For reference, according to the test method for airtightness of houses based on “House's airtightness performance testing method” (published by: Building Environment and Energy Conservation Organization, edited by: Airtightness Measurement Technology Promotion Committee) A thermometer, a blower, a flow rate measuring device, a flow rate measuring device, and a pressure difference measuring device are required, and it takes about 60 to 120 minutes to complete one test. It becomes necessary.

以上、本発明の施工途上の建物の気密性確認方法の実施形態について詳述したが、本発明は上記実施形態にのみ限定されるものではない。
例えば、上記気密施工後の気密性確認作業において、差圧のみを確認して当該気密施工完了直後の差圧を記録等しておき、その後、設備施工を完了直後の気密性確認作業において、再び差圧を確認しておき、これら2つの記録差圧の大小を比較する構成を採用することも可能であって、当該気密性確認方法によれば、差圧を比較するだけで当該設備施工により気密施工完了直後よりも気密性が悪化したか否か、悪化したとすればどの程度悪化したのか等を確認することができる。
また、設備施工は、配管設備施工、電気設備施工等の複数の施工を異なる業者によって順次行う態様をとることも可能であって、この種の設備施工においては、各施工を完了させる度に上記気密性確認作業を行い、各施工においてどの程度気密性が変動したのか明確にしつつ、或全体の施工を進めていく構成を採用することも可能であり、これによって、各業者単位で躯体の気密性に対する責任の所在を明確なものとすることができる。
As mentioned above, although embodiment of the airtightness confirmation method of the building under construction of this invention was explained in full detail, this invention is not limited only to the said embodiment.
For example, in the airtightness confirmation work after the above airtight construction, only the differential pressure is confirmed and the differential pressure immediately after completion of the airtight construction is recorded, and then the airtightness confirmation work immediately after completion of the equipment construction is performed again. It is also possible to confirm the differential pressure and adopt a configuration for comparing the magnitudes of these two recorded differential pressures. According to the airtightness confirmation method, it is only necessary to compare the differential pressure and to construct the equipment. It can be confirmed whether or not the airtightness has deteriorated more than immediately after the completion of the airtight construction, and to what extent the airtightness has deteriorated.
In addition, equipment construction can take a form in which a plurality of constructions such as piping equipment construction, electrical equipment construction, etc. are sequentially performed by different contractors, and in this kind of equipment construction, each time each construction is completed, It is possible to adopt a configuration in which airtightness confirmation work is performed and how the airtightness fluctuates in each construction is clarified, or a construction in which the entire construction is advanced can be adopted. The location of responsibility for gender can be clarified.

また、異なる業者間のみならず、同一の業者間であっても、各施工の完了ごとに上記気密性確認作業を行うことによって、いずれの時点で気密性を損なってしまったのかを確認することができ、これによって、各作業者間での気密性に対する責任の所在を明確なものとすることができるばかりでなく、気密性を損なった部位に早期特定にも繋がり、ひいては、気密性悪化に起因する施工全体の手戻りを最小限に抑えつつ、最終工程に至るまで躯体を気密性を確保することが可能となる。
また、各施工において、各工程は上述の順序を遵守する必要はなく、例えば、気密施工にて沿屋根断熱工程の後に沿外壁気密工程を行う等、各施工での工程の順序は適宜変更することが可能である。また、防水加工等、躯体を仕上げていく他の施工も、躯体施工の後であれば、気密施工や設備施工と同時期またはこれらの施工と前後して適宜行うことが可能である。
In addition, not only between different contractors, but also between the same contractors, confirming at which point the airtightness has been lost by performing the above airtightness confirmation work at the completion of each construction. As a result, it is possible not only to clarify the location of the responsibility for airtightness among the workers, but also to identify the site where the airtightness has been lost, leading to deterioration of the airtightness. It is possible to ensure the airtightness of the casing until the final process while minimizing the rework of the entire construction.
Moreover, in each construction, it is not necessary to observe the above-mentioned order in each construction. For example, the order of the processes in each construction is changed as appropriate, for example, the exterior wall airtight process is performed after the roof insulation process in the airtight construction. It is possible. In addition, other constructions such as waterproofing that finish the chassis can be appropriately performed after the chassis construction, at the same time as the airtight construction and facility construction, or before and after these constructions.

本発明に係る気密検証工程を含む建物の施工工程を示すフロー図である。It is a flowchart which shows the construction process of the building containing the airtight verification process which concerns on this invention. 本発明に係る気密検証方法が実施される建物の概略断面図である。It is a schematic sectional drawing of the building where the airtight verification method which concerns on this invention is implemented. (a)は、二階建て家屋の躯体において、強制排気装置により建材の含有水分の放出を行う場合に必要な換気量の検討に参照される躯体の概略断面図、(b)は強制排気装置を設置して運転している状態を示す概略断面図である。(A) is a schematic cross-sectional view of a housing that is referred to when examining the amount of ventilation necessary for releasing moisture contained in building materials in a housing of a two-story house, and (b) is a forced exhaust device. It is a schematic sectional drawing which shows the state which installs and drive | operates. 強制排気装置を建物の床下点検口に取り付けた状態を示す断面図である。It is sectional drawing which shows the state which attached the forced exhaust apparatus to the floor under inspection port of the building. 強制排気装置が取り付けられる支持部材の平面図である。It is a top view of the support member to which a forced exhaust apparatus is attached. 強制排気装置の上に配置される保護部材の平面図である。It is a top view of the protection member arrange | positioned on a forced exhaust apparatus. 気密施工工程後の気密検証方法を示す断面模式図で、気密施工が完了した時点の図である。It is a cross-sectional schematic diagram which shows the airtight verification method after an airtight construction process, and is a figure at the time of airtight construction being completed. 気密施工工程後の気密検証方法を示す断面模式図で、差圧計、強制排気装置を設置した状態を示す図である。It is a cross-sectional schematic diagram which shows the airtight verification method after an airtight construction process, and is a figure which shows the state which installed the differential pressure gauge and the forced exhaust apparatus. 気密施工工程後の気密検証方法を示す断面模式図で、気密性検証のために強制排気装置を運転している状態を示す図である。It is a cross-sectional schematic diagram which shows the airtight verification method after an airtight construction process, and is a figure which shows the state which is operating the forced exhaust apparatus for airtightness verification. 本発明の実施形態において用いられている強制排気装置の静圧―風量特性を示すグラフである。It is a graph which shows the static pressure-air volume characteristic of the forced exhaust apparatus used in embodiment of this invention. 上部構造体内外の差圧と気密状態の対応表である。It is a correspondence table | surface of the differential pressure | voltage inside and outside an upper structure, and an airtight state. 設備施工後の気密検証方法を示す図7(a)と同様の模式図で、設備施工が完了した時点の図である。FIG. 8 is a schematic diagram similar to FIG. 7A showing an airtight verification method after facility construction, and is a diagram at the time when facility construction is completed. 設備施工後の気密検証方法を示す図7(b)と同様の模式図で、差圧計、強制排気装置を設置した状態を示す図である。It is a schematic diagram similar to FIG. 7B showing the airtightness verification method after facility construction, and is a diagram showing a state in which a differential pressure gauge and a forced exhaust device are installed. 設備施工後の気密検証方法を示す図7(c)と同様の模式図で、気密性検証のために強制排気装置を運転している状態を示す図である。FIG. 8 is a schematic view similar to FIG. 7C showing the airtightness verification method after facility construction, and is a view showing a state in which a forced exhaust device is operated for airtightness verification.

符号の説明Explanation of symbols

1 基礎構造
2 躯体
3a、3b 換気口
4 梁
5 壁
6 床
6a 1階床スラブ
6aa 床パネルの表面
6b 2階床スラブ
7 屋根
8 点検口
9 強制排気装置(強制排気設備)
10 吹き抜け部
11 開口部
12 支持部材
13 保護部材
14 枠部材
15 開口枠部材
16 外枠部材
17 受け座
18 フレーム
18a フレーム枠
18b アーム部
19 駆動軸
20 羽根部材
21 締結手段
22 邪魔板
23 連結手段
25 気密性断熱材
26 差圧計
26a U字管部
26b 一方のチューブ
26b 他方のチューブ
27 配管等
S 床下空間
DESCRIPTION OF SYMBOLS 1 Basic structure 2 Housing 3a, 3b Ventilation port 4 Beam 5 Wall 6 Floor 6a First floor slab 6aa Floor panel surface 6b Second floor slab 7 Roof 8 Inspection port 9 Forced exhaust device (forced exhaust equipment)
DESCRIPTION OF SYMBOLS 10 Blow-off part 11 Opening part 12 Support member 13 Protection member 14 Frame member 15 Opening frame member 16 Outer frame member 17 Seat 18 Frame 18a Frame frame 18b Arm part 19 Drive shaft 20 Blade member 21 Fastening means 22 Baffle plate 23 Connection means 25 Airtight heat insulating material 26 Differential pressure gauge 26a U-shaped pipe part 26b One tube 26b The other tube 27 Piping etc. S Underfloor space

Claims (6)

基礎構造上に上部構造を建ち上げると共に当該上部構造に外壁と屋根等の建材とを設置して躯体を形成する躯体施工を終えた後に、当該躯体に気密層を形成する気密施工までを完了した施工途上の建物の内外に圧力差を生じさせて当該躯体の気密性を検証する施工途上建物の気密検証方法であって、
前記気密施工が完了した躯体に設けられる強制排気設備を運転して当該躯体の排気を行うことにより、当該躯体の内外に差圧を生じさせ、該差圧に基づいて当該躯体の気密状態を確認する気密確認工程を備えていることを特徴とする施工途上建物の気密検証方法。
After building the upper structure on the foundation structure and installing the outer wall and building materials such as the roof on the upper structure to form the housing, we completed the airtight construction to form an airtight layer on the housing An airtight verification method for a building under construction in which a pressure difference is generated inside and outside the building under construction to verify the airtightness of the building,
By operating a forced exhaust facility provided on the housing after the airtight construction is completed and exhausting the housing, a differential pressure is generated inside and outside the housing, and the airtight state of the housing is confirmed based on the differential pressure. An airtight verification method for a building under construction, characterized by comprising an airtight confirmation process.
前記強制排気設備が、躯体の内部空間に外気を導入して前記建材の含有水分の放出を促進するために設置される強制排気装置であることを特徴とする請求項1に記載の施工途上建物の気密検証方法。   2. The building under construction according to claim 1, wherein the forced exhaust facility is a forced exhaust device that is installed to introduce outside air into an internal space of a housing to promote release of moisture contained in the building material. Hermetic verification method. 前記気密施工後に、前記躯体の外壁及び気密層を貫通する通気孔などの貫通孔の形成を伴う施工を行う設備施工を備え、
前記気密確認工程は、
前記気密施工までを完了させた時点で、前記強制給排気装置により強制排気を行うことにより、前記躯体の内外に差圧を生じさせて気密性を確認する当初気密確認工程と、
前記設備施工までを完了させた時点で、前記強制給排気装置により強制排気を行うことにより、前記躯体の内外に差圧を生じさせて気密性を確認する設備施工後気密確認工程と、
を備えていることを特徴とする請求項2に記載の施工途上建物の気密検証方法。
After the airtight construction, equipped with facility construction to perform construction with the formation of through holes such as air holes penetrating the outer wall and airtight layer of the housing,
The airtightness confirmation process includes
At the time of completing up to the airtight construction, by performing forced exhaustion by the forced air supply and exhaust device, an initial airtight confirmation step for confirming airtightness by generating a differential pressure inside and outside the housing,
After completing the facility construction, by performing forced exhaust by the forced air supply / exhaust device, an airtight confirmation step after facility construction for confirming airtightness by generating a differential pressure inside and outside the housing,
The airtight verification method for a building under construction according to claim 2, comprising:
前記設備施工を複数回に亘って行い、
各設備施工を完了させる度に、前記強制排気装置による強制排気により生じる内外差圧に基づいて当該設備施工後の躯体の気密性を確認する設備施工後気密確認工程を行う、
ことを特徴とする請求項3に記載の施工途上建物の気密検証方法。
Perform the facility construction multiple times,
Every time each facility construction is completed, an after-construction airtightness confirmation process is performed to confirm the airtightness of the enclosure after the facility construction based on the internal / external differential pressure generated by forced exhaust by the forced exhaust device,
The airtight verification method for a building under construction according to claim 3.
前記強制排気装置は、
前記躯体に形成されている開口部の開口縁部を形成する枠材に載置される支持部材と、
該支持部材に取り付けられ、前記躯体の内部空間の空気を吸引して躯体の外方に排気する換気扇本体と、
該換気扇本体よりも風上に配設されて換気扇本体を保護する保護部材と、
上記換気扇本体の風下に配設されて排気流れを変更させる風向変更部材と
を具備することを特徴とする請求項1乃至請求項4のいずれかに記載の施工途上建物の気密検証方法。
The forced exhaust device is
A support member mounted on a frame material that forms an opening edge of the opening formed in the housing;
A ventilation fan body attached to the support member, for sucking air in the internal space of the housing and exhausting it outside the housing;
A protective member disposed on the windward side of the ventilation fan body to protect the ventilation fan body;
5. The method for verifying airtightness of a building under construction according to claim 1, further comprising: a wind direction changing member that is disposed leeward of the ventilation fan main body and changes an exhaust flow.
前記強制排気装置が設置される開口部は、躯体施工により形成される基礎構造の上に構築された躯体の内部空間を基礎構造の内部空間に連通させるものであることを特徴とする請求項5に記載の施工途上建物の気密検証方法。   6. The opening in which the forced exhaust device is installed communicates the internal space of the frame constructed on the foundation structure formed by the frame construction with the internal space of the foundation structure. The airtightness verification method for the building under construction described in 1.
JP2008242904A 2008-09-22 2008-09-22 Method for airtightness verification of building structures Active JP5319221B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008242904A JP5319221B2 (en) 2008-09-22 2008-09-22 Method for airtightness verification of building structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008242904A JP5319221B2 (en) 2008-09-22 2008-09-22 Method for airtightness verification of building structures

Publications (2)

Publication Number Publication Date
JP2010071950A true JP2010071950A (en) 2010-04-02
JP5319221B2 JP5319221B2 (en) 2013-10-16

Family

ID=42203866

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008242904A Active JP5319221B2 (en) 2008-09-22 2008-09-22 Method for airtightness verification of building structures

Country Status (1)

Country Link
JP (1) JP5319221B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010169425A (en) * 2009-01-20 2010-08-05 Japan Radio Co Ltd Fm-cw radar apparatus
JP2014500494A (en) * 2010-11-22 2014-01-09 サン−ゴバン・イソベール Device and method for measuring air permeability of buildings
JP5924512B1 (en) * 2014-12-24 2016-05-25 有限会社神田工務店 Airtight structure
WO2016083670A1 (en) * 2014-11-26 2016-06-02 Si-Tecno Oy Method for measuring pressure differences between different premises in a building
WO2020167133A1 (en) * 2019-02-14 2020-08-20 Airtight As Method and system for monitoring air leaks through a building envelope and controlling a ventilation system
CN114018487A (en) * 2021-10-29 2022-02-08 上海振华重工(集团)股份有限公司南通分公司 Improved tire crane portal frame air tightness test method
JP7666666B1 (en) 2024-01-16 2025-04-22 積水ハウス株式会社 How to measure airtightness of building parts

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04145339A (en) * 1990-10-06 1992-05-19 Deitsukusu Kk Air tightness measuring device for prefabricated building
JPH05296872A (en) * 1992-04-15 1993-11-12 Daiwa House Ind Co Ltd Simple air-tight performance measurement method of residence
JPH09145517A (en) * 1995-11-24 1997-06-06 Sekisui Chem Co Ltd How to measure the airtightness of a building
JPH10281922A (en) * 1997-04-02 1998-10-23 Shigeki Iwaoka Method for measuring airtightness of building
JP2001091397A (en) * 1999-09-24 2001-04-06 Misawa Homes Co Ltd Airtightness measurement method of building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04145339A (en) * 1990-10-06 1992-05-19 Deitsukusu Kk Air tightness measuring device for prefabricated building
JPH05296872A (en) * 1992-04-15 1993-11-12 Daiwa House Ind Co Ltd Simple air-tight performance measurement method of residence
JPH09145517A (en) * 1995-11-24 1997-06-06 Sekisui Chem Co Ltd How to measure the airtightness of a building
JPH10281922A (en) * 1997-04-02 1998-10-23 Shigeki Iwaoka Method for measuring airtightness of building
JP2001091397A (en) * 1999-09-24 2001-04-06 Misawa Homes Co Ltd Airtightness measurement method of building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JPN7013000114; '平塚市内にて気密測定を実施致しました。' 気密測定試験と気密住宅専門サイト , 20070417 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010169425A (en) * 2009-01-20 2010-08-05 Japan Radio Co Ltd Fm-cw radar apparatus
JP2014500494A (en) * 2010-11-22 2014-01-09 サン−ゴバン・イソベール Device and method for measuring air permeability of buildings
WO2016083670A1 (en) * 2014-11-26 2016-06-02 Si-Tecno Oy Method for measuring pressure differences between different premises in a building
US10481035B2 (en) 2014-11-26 2019-11-19 Si-Tecno Oy Method for measuring pressure differences between different premises in a building
JP5924512B1 (en) * 2014-12-24 2016-05-25 有限会社神田工務店 Airtight structure
WO2020167133A1 (en) * 2019-02-14 2020-08-20 Airtight As Method and system for monitoring air leaks through a building envelope and controlling a ventilation system
US12332146B2 (en) 2019-02-14 2025-06-17 Airthings Asa Method and system for monitoring air leaks through a building envelope and controlling a ventilation system
CN114018487A (en) * 2021-10-29 2022-02-08 上海振华重工(集团)股份有限公司南通分公司 Improved tire crane portal frame air tightness test method
CN114018487B (en) * 2021-10-29 2024-04-16 上海振华重工(集团)股份有限公司南通分公司 Improved air tightness test method for portal frame of tire crane
JP7666666B1 (en) 2024-01-16 2025-04-22 積水ハウス株式会社 How to measure airtightness of building parts

Also Published As

Publication number Publication date
JP5319221B2 (en) 2013-10-16

Similar Documents

Publication Publication Date Title
JP5319221B2 (en) Method for airtightness verification of building structures
KR20190122605A (en) Customized system for discharging radon gas in soil capable of preventing dew condensation and rain inflow
Lstiburek et al. Air pressure and building envelopes
CA2447389A1 (en) Moisture reduction and mold and moisture damage preventative system and method in construction
Finch et al. Building envelope performance monitoring and modeling of West Coast rainscreen enclosures
JP2012246622A (en) Construction method of foundation structure, and ventilation structure
JP5204419B2 (en) How to remove moisture from building materials
Turk et al. Effectiveness of radon control techniques in fifteen homes
Pol et al. Mitigation Techniques for Interior Radon in Refurbishment Work in High Radiation Areas of Galicia: An Experimental Model to Test Building Solutions
Hellerich et al. Overview Of Two Large-Scale Residential Sub-Slab Depressurization System Installation Programs
JP2001091397A (en) Airtightness measurement method of building
Fernández-Agüera et al. Influence of improvement of air-tightness on energy retrofit of social housing, a case study in a mediterranean climate
JP2015168920A (en) Ventilation structure for building
KR102403835B1 (en) System for discharging radon gas in soil layer and constructing method thereof
CN118704523B (en) A systematic approach to radon shielding construction in underground projects
Brennan et al. Measuring airtightness at ASHRAE headquarters
CN112324278B (en) Building external window structure and mounting method thereof
Andersson Swedish experience with airtight ductwork
Abadie et al. Development of a Natural Soil Depressurization System Sizing Tool
WORK Project Background
Finch et al. Hygrothermal performance and drying potential of wood frame rainscreen walls in Vancouver’s coastal climate
CN118602478A (en) Air conditioning construction method
Høegh et al. Development and test of a combined radon sub-slab suction and sub-slab drainage system
Dickson Guide to Closing and Conditioning Ventilated Crawlspaces
JP2023172803A (en) Specification method of water entry point into building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110801

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121220

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130115

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130311

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130709

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130711

R150 Certificate of patent or registration of utility model

Ref document number: 5319221

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350