[go: up one dir, main page]

JP2010048060A - Construction method of structure - Google Patents

Construction method of structure Download PDF

Info

Publication number
JP2010048060A
JP2010048060A JP2008215871A JP2008215871A JP2010048060A JP 2010048060 A JP2010048060 A JP 2010048060A JP 2008215871 A JP2008215871 A JP 2008215871A JP 2008215871 A JP2008215871 A JP 2008215871A JP 2010048060 A JP2010048060 A JP 2010048060A
Authority
JP
Japan
Prior art keywords
work table
floor
scaffold
column
oblique
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2008215871A
Other languages
Japanese (ja)
Inventor
Yoshito Oba
義人 大場
Norikazu Moriya
紀和 守屋
Hideto Kobayashi
秀人 小林
Mitsuru Otani
満 大谷
Tatsuo Suzuki
辰雄 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Kawada Construction Co Ltd
JFE Civil Engineering and Construction Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Kawada Construction Co Ltd
JFE Civil Engineering and Construction Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp, Kawada Construction Co Ltd, JFE Civil Engineering and Construction Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2008215871A priority Critical patent/JP2010048060A/en
Publication of JP2010048060A publication Critical patent/JP2010048060A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

【課題】地表面に対して傾斜した構造物を構築する際の施工性を向上させることのできる構造物の構築方法を提供すること。
【解決手段】作業台40を施工対象階の外壁面に対応させて配置し、作業台40を用いて施工対象階の施工を行った後に、作業台40を外壁面に沿って次の施工対象階まで上昇させる工程を繰り返すことにより、地表面に対して傾斜した構造物を上層部まで順次構築する方法において、作業台40を、構造物の傾斜方向に移動させることによって次の施工対象階まで上昇させる。
【選択図】 図3
The present invention provides a method for constructing a structure capable of improving workability when constructing a structure inclined with respect to the ground surface.
SOLUTION: After a work table 40 is arranged corresponding to the outer wall surface of the floor to be constructed, and the work floor 40 is constructed using the work table 40, the work table 40 is moved to the next construction object along the outer wall surface. In the method of sequentially building the structure inclined with respect to the ground surface to the upper layer by repeating the process of raising to the floor, the work table 40 is moved to the next construction target floor by moving in the inclination direction of the structure. Raise.
[Selection] Figure 3

Description

本発明は、地表面に対して傾斜した構造物を構築する方法に関するものである。   The present invention relates to a method for constructing a structure inclined with respect to the ground surface.

従来、地表面に対して傾斜した構造物を構築する方法の一例として、特許文献1に示される斜柱の構築方法が知られている。この方法では、構築する斜柱の外壁面に沿って水平方向にレールを吊下げ支持し、このレール上にスライド可能に設置された作業台(足場)を用いて、鉄筋組立、型枠設置、コンクリート打設等の作業を行う。そして、これらの施工が完了した後、レールを鉛直方向に引き上げて、作業台を次の施工対象階まで上昇させる。上記の工程を繰り返し行うことによって斜柱を構築する。   Conventionally, as an example of a method of constructing a structure inclined with respect to the ground surface, a construction method of an oblique column shown in Patent Document 1 is known. In this method, a rail is suspended and supported along the outer wall surface of the oblique column to be constructed, and a work table (scaffold) slidably installed on the rail is used to assemble the rebar, formwork, Work such as placing concrete. And after these construction is completed, a rail is pulled up in the perpendicular direction and a work table is raised to the next construction object floor. The oblique column is constructed by repeating the above steps.

斜柱に対して作業台を鉛直方向に引き上げる場合、作業台が上昇するにつれて、斜柱の位置に対して作業台の位置がずれる。このため、作業台を引き上げた後にこの作業台を水平方向に移動させて、斜柱の位置に作業台を合わせるようにしている。作業台を水平方向に移動させる際には、作業台のつりあいをとる必要がある。   When the work table is pulled up in the vertical direction with respect to the oblique column, the position of the work table is shifted from the position of the oblique column as the work table is raised. For this reason, after raising the work table, the work table is moved in the horizontal direction so that the work table is aligned with the position of the oblique column. When moving the work table in the horizontal direction, it is necessary to balance the work table.

特開平10−339033号公報Japanese Patent Laid-Open No. 10-339033

上述した特許文献1の構築方法では、作業台をレールに対して水平方向に移動させるための機構が必須であり、その分装置が複雑になる。また、作業台を上階の設置位置に引き上げるたびに、作業台を水平方向に移動させ、作業台の位置を斜柱の位置に合わせる必要があるため、施工効率が悪いという問題がある。さらに、作業台を水平方向に移動させる際に、常に作業台のつりあいをとるように移動させることは困難である。   In the construction method of Patent Document 1 described above, a mechanism for moving the work table in the horizontal direction with respect to the rail is essential, and the apparatus is complicated accordingly. In addition, every time the work table is pulled up to the installation position on the upper floor, it is necessary to move the work table in the horizontal direction so that the position of the work table matches the position of the oblique column. Furthermore, when the work table is moved in the horizontal direction, it is difficult to move the work table so that the work table is always balanced.

本発明は、上記の点に鑑み、地表面に対して傾斜した構造物を構築する際の施工性を向上させることのできる方法を提供することを目的とする。   An object of this invention is to provide the method of improving the construction property at the time of constructing | assembling the structure inclined with respect to the ground surface in view of said point.

本発明の構造物の構築方法は、作業台を施工対象階の外壁面に対応させて配置し、前記作業台を用いて施工対象階の施工を行った後に、前記作業台を前記外壁面に沿って次の施工対象階まで上昇させる工程を繰り返すことにより、地表面に対して傾斜した構造物を上層部まで順次構築する方法において、前記作業台を、前記構造物の傾斜方向に移動させることによって次の施工対象階まで上昇させることを特徴とする。   In the construction method of the structure of the present invention, a work table is arranged corresponding to the outer wall surface of the floor to be constructed, and after the work floor is constructed using the work table, the work table is placed on the outer wall surface. In the method of sequentially constructing the structure inclined with respect to the ground surface up to the upper layer part by repeating the process of raising up to the next floor to be constructed, moving the work table in the inclination direction of the structure Is raised to the next construction target floor.

また、本発明の請求項2の構造物の構築方法は、上記請求項1において、前記外壁面にジャッキ支持部材を取付け、前記ジャッキ支持部材に支持させたジャッキで前記作業台を前記構造物の傾斜方向に押し上げることによって、前記作業台を次の施工対象階まで上昇させることを特徴とする。   According to a second aspect of the present invention, there is provided a structure construction method according to the first aspect, wherein a jack support member is attached to the outer wall surface, and the work table is attached to the structure by a jack supported by the jack support member. By pushing up in the inclination direction, the work table is raised to the next construction target floor.

また、本発明の請求項3の構造物の構築方法は、上記請求項1又は2において、前記作業台上に足場を設けるとともに、前記作業台の下部に吊足場を設けることを特徴とする。   According to a third aspect of the present invention, there is provided a method for constructing a structure according to the first or second aspect, wherein a scaffold is provided on the work table and a suspension scaffold is provided at a lower portion of the work table.

本発明の構造物の構築方法によれば、作業台を上階の設置位置まで上昇させる際に、傾斜した構造物の傾斜方向に作業台を移動させるようにしたことで、傾斜した構造物に対して鉛直方向に作業台を引き上げる従来の方法のように、作業台を上階の設置位置に引き上げるたびに構造物に対して作業台の位置がずれるといったことがなくなるため、施工性に優れる。   According to the construction method of the structure of the present invention, when the work table is raised to the installation position on the upper floor, the work table is moved in the inclination direction of the inclined structure. On the other hand, since the position of the work table is not shifted with respect to the structure every time the work table is lifted to the installation position on the upper floor as in the conventional method of lifting the work table in the vertical direction, the workability is excellent.

以下に、添付図面を参照して、本発明の構造物の構築方法における好適な実施の形態について詳細に説明する。なお、以下では、構造物として斜張橋の主塔を適用した例について説明する。   Hereinafter, preferred embodiments of a method for constructing a structure according to the present invention will be described in detail with reference to the accompanying drawings. In the following, an example in which the main tower of a cable-stayed bridge is applied as a structure will be described.

図1は斜張橋の側面図であり、図2は図1に示した斜張橋における主塔の正面図である。図1に例示される斜張橋1は、橋梁の中間2箇所に設けた主塔2,2より、斜めに張ったケーブル3で橋桁4を支持した構造を有する一般的な斜張橋である。   1 is a side view of the cable-stayed bridge, and FIG. 2 is a front view of the main tower of the cable-stayed bridge shown in FIG. A cable-stayed bridge 1 illustrated in FIG. 1 is a general cable-stayed bridge having a structure in which a bridge girder 4 is supported by a cable 3 that is slanted from main towers 2 and 2 provided at two intermediate positions of the bridge. .

主塔2は、図2に示すように、一対の斜柱5,5と頂部6とから構成される鉄筋コンクリート構造物である。一対の斜柱5,5は、橋脚7の両端部を基端とし、上方へいくにつれて相互の間隔が狭まる態様で地表面に対して傾斜した形状を有している。   As shown in FIG. 2, the main tower 2 is a reinforced concrete structure including a pair of oblique columns 5 and 5 and a top portion 6. The pair of slanted columns 5 and 5 have shapes that are inclined with respect to the ground surface in such a manner that the both ends of the pier 7 are the base ends and the distance between them is narrowed upward.

本実施の形態では、以下に説明するように、斜柱5の傾斜方向に移動可能な作業台ユニット10を斜柱5の施工対象階に設置し、作業台ユニット10に足場を設置し、この足場を用いて、鉄筋組立て作業、型枠組立て作業、型枠内へのコンクリート打設作業、硬化コンクリート仕上げ作業等の施工を行い、これらの施工完了後に、作業台ユニット10を斜柱5の傾斜方向に上昇させる工程を繰り返すことにより、斜柱5を構築する。なお本実施の形態では、作業台ユニット10を1階(約4m)ずつ上昇させる。また、一対の斜柱5,5に設置される各作業台ユニット10は同一のものである。   In the present embodiment, as will be described below, a workbench unit 10 movable in the inclination direction of the oblique column 5 is installed on the construction target floor of the oblique column 5, and a scaffold is installed on the workbench unit 10. Using the scaffolding, rebar assembly work, formwork assembly work, concrete placement work in the formwork, hardened concrete finishing work, etc., and after completion of the work, the workbench unit 10 is inclined to the inclined column 5 The oblique column 5 is constructed by repeating the step of raising in the direction. In the present embodiment, the workbench unit 10 is raised by the first floor (about 4 m). The work table units 10 installed on the pair of oblique columns 5 and 5 are the same.

図3は、作業台ユニット10を用いて斜柱5の構築を行っている状態を示す正面図であり、図4は、図3において右側に位置する斜柱5に設置された作業台ユニット10を拡大して示した図である。なお、図3では、右側の作業台ユニット10における吊足場52を省略している。また、図4では、作業台ユニット10上に設置される足場51と下方に吊設される吊足場52を省略するとともに、受梁30の一部を破断して示している。   FIG. 3 is a front view showing a state in which the oblique column 5 is constructed using the work table unit 10, and FIG. 4 is a work table unit 10 installed on the oblique column 5 located on the right side in FIG. It is the figure which expanded and showed. In FIG. 3, the suspension scaffold 52 in the right workbench unit 10 is omitted. In FIG. 4, the scaffold 51 installed on the workbench unit 10 and the suspended scaffold 52 suspended below are omitted, and a part of the receiving beam 30 is shown broken away.

図3及び図4に例示する作業台ユニット10は、斜柱5における正面の壁面及び背面の壁面にそれぞれ設置されるクライミング装置20と、クライミング装置20に支持される一対の受梁30,30と、一対の受梁30,30上に架設される作業台40とを備えて構成してある。   3 and 4 includes a climbing device 20 installed on the front wall surface and the rear wall surface of the oblique column 5, and a pair of receiving beams 30 and 30 supported by the climbing device 20. And a work table 40 installed on the pair of receiving beams 30, 30.

クライミング装置20は、作業台40を支持する機能と作業台40を斜柱5の傾斜方向に上昇させる機能とを兼ね備えたものであり、鋼板21、反力柱22、ジャッキ支持部材23、ジャッキ24、支持部材25とから構成されるものである。   The climbing device 20 has a function of supporting the work table 40 and a function of raising the work table 40 in the direction of inclination of the oblique column 5, and includes a steel plate 21, a reaction force column 22, a jack support member 23, and a jack 24. And the support member 25.

鋼板21は、後述する反力柱22を固定するためのものであり、斜柱5の外壁面、すなわち、コンクリートを打設した後所定期間養生させ、十分に強度が発現した状態の硬化コンクリート壁面8に、アンカーボルト26によって固定してある。   The steel plate 21 is for fixing a reaction force column 22 to be described later, and is an outer wall surface of the oblique column 5, that is, a hardened concrete wall surface in which the concrete is cured for a predetermined period after being placed and sufficiently strengthened. 8 is fixed by an anchor bolt 26.

反力柱22は、H形鋼等の長尺形状を成す鋼材からなるものであり、図4に示すように、斜柱5の傾斜方向に平行に配置され、ボルト等の締結手段(図示せず)によって鋼板21に対して固定してある。この反力柱22は、ジャッキ24で作業台40を押し上げる際の反力受けとしての機能を有すると同時に、支持部材25及びジャッキ24を上昇させる案内レールとしての機能を有したものである。   The reaction force column 22 is made of a steel material having a long shape such as H-shaped steel, and is arranged in parallel to the inclined direction of the oblique column 5 as shown in FIG. To the steel plate 21. The reaction force column 22 has a function as a reaction force receiver when the work table 40 is pushed up by the jack 24 and also has a function as a guide rail for raising the support member 25 and the jack 24.

ジャッキ支持部材23は、ジャッキ24の下端部と締結され、反力柱22に沿って移動可能に反力柱22に取付けられる鋼材である。作業者が作業台40で作業を行う際、及び、ジャッキ24を伸長させて作業台40を押し上げる際には、このジャッキ支持部材23をボルト等の締結手段(図示せず)によって反力柱22に対して固定する。一方、ジャッキ24を伸長させて作業台40を上階まで押し上げた後、クライミング装置20を上階に盛り替える際には、ジャッキ支持部材23と反力柱22とのボルト締結を解除することにより、ジャッキ支持部材23を反力柱22に沿って上昇させることができるようになっている。   The jack support member 23 is a steel material fastened to the lower end portion of the jack 24 and attached to the reaction force column 22 so as to be movable along the reaction force column 22. When an operator works on the work table 40 and when the work table 40 is pushed up by extending the jack 24, the jack support member 23 is attached to the reaction force column 22 by a fastening means (not shown) such as a bolt. Fixed against. On the other hand, after the jack 24 is extended and the work table 40 is pushed up to the upper floor, when the climbing apparatus 20 is replaced with the upper floor, the bolt fastening between the jack support member 23 and the reaction force column 22 is released. The jack support member 23 can be raised along the reaction force column 22.

ジャッキ24は、その下端部がジャッキ支持部材23に締結される一方、上端部が支持部材25に締結され、自身を伸長させて支持部材25及びジャッキ支持部材23を押すことにより、支持部材25上の受梁30及び作業台40を押し上げるものである。ジャッキ24は、図4に示すように、反力柱22に平行に、すなわち、斜柱5の傾斜方向に平行となるように配置される。ジャッキ24としては、油圧式ジャッキ等の一般的なものを適用することができる。   The lower end of the jack 24 is fastened to the jack support member 23, while the upper end is fastened to the support member 25, and the jack 24 extends to push the support member 25 and the jack support member 23. The receiving beam 30 and the work table 40 are pushed up. As shown in FIG. 4, the jack 24 is arranged so as to be parallel to the reaction force column 22, that is, to be parallel to the inclination direction of the oblique column 5. As the jack 24, a general one such as a hydraulic jack can be applied.

支持部材25は、図4に示すように、受梁30を支持する鋼材である。この支持部材25は、ジャッキ24の上端部と締結され、反力柱22に沿って移動可能に反力柱22に対して取付けてある。作業者が作業台40で作業を行う際、及び、クライミング装置20を上層部に盛り替える際には、この支持部材25をボルト等の締結手段(図示せず)によって反力柱22に対して固定する。一方、ジャッキ24を伸長させて作業台40を押し上げる際には、支持部材25と反力柱22との締結を解除することにより、支持部材25を反力柱22に沿って上昇させることができるようになっている。   As illustrated in FIG. 4, the support member 25 is a steel material that supports the receiving beam 30. The support member 25 is fastened to the upper end portion of the jack 24 and is attached to the reaction force column 22 so as to be movable along the reaction force column 22. When the operator performs work on the work table 40 and when the climbing apparatus 20 is replaced with the upper layer portion, the support member 25 is attached to the reaction force column 22 by fastening means (not shown) such as a bolt. Fix it. On the other hand, when the jack 24 is extended to push up the work table 40, the support member 25 can be raised along the reaction force column 22 by releasing the fastening between the support member 25 and the reaction force column 22. It is like that.

上記のように構成したクライミング装置20は、斜柱5における正面5aの壁面及び背面(図示せず)の壁面にそれぞれ一対ずつ、計4台配置される。   A total of four climbing apparatuses 20 configured as described above are arranged on the wall surface of the front surface 5a and the wall surface of the back surface (not shown) of the oblique column 5 in pairs.

受梁30は、上述したクライミング装置20に支持されるものであり、斜柱5の幅寸法よりも大きい長さ寸法を有している。本実施の形態では、受梁30として、図3及び図4に例示するようなトラス梁を適用している。この受梁30は、斜柱5の正面5a側と背面側(図示せず)にそれぞれ一本ずつ配置される。   The receiving beam 30 is supported by the climbing device 20 described above, and has a length dimension larger than the width dimension of the oblique column 5. In this embodiment, a truss beam as illustrated in FIGS. 3 and 4 is applied as the receiving beam 30. One receiving beam 30 is arranged on each of the front 5a side and the back side (not shown) of the oblique column 5.

作業台40は、上述した2本の受梁30,30間に架設される矩形状の台である。図には明示されていないが、この作業台40の中央部分には、斜柱5の周囲を取り囲む態様で開口部が形成してある。作業台40と受梁30との間には、図4に示すようにコロ装置41を介在させてあり、作業台40が受梁30に対してスライド可能となっている。   The work table 40 is a rectangular table constructed between the two receiving beams 30 and 30 described above. Although not clearly shown in the figure, an opening is formed in the central portion of the work table 40 so as to surround the oblique column 5. As shown in FIG. 4, a roller device 41 is interposed between the work table 40 and the receiving beam 30, so that the work table 40 can slide with respect to the receiving beam 30.

上記の作業台40には、図3に示すように、斜柱5の周りに足場51及び吊足場52が設置される。足場51は、作業台40上で建枠53を上下方向及び左右方向に所要数連結して設けた枠組足場である。吊足場52は、作業台40から複数の吊枠54を吊下げることによって設けた足場である。本実施の形態では、足場51を2階層分設置し、吊足場52を1階層分設置する。   As shown in FIG. 3, the work table 40 is provided with a scaffold 51 and a suspended scaffold 52 around the oblique column 5. The scaffold 51 is a frame scaffold provided by connecting a required number of building frames 53 in the vertical direction and the horizontal direction on the work table 40. The suspension scaffold 52 is a scaffold provided by suspending a plurality of suspension frames 54 from the work table 40. In the present embodiment, the scaffolds 51 are installed for two levels, and the suspended scaffolds 52 are installed for one level.

作業台40上に設置される足場に使用する建枠は圧縮材料から構成されており、吊足場に使用する吊枠と比べて重い。このため、本実施の形態のように、作業台40上に2階層の足場51を設け、作業台40の下方に1階層の吊足場52を吊設する場合、作業台40上に3階層の足場を設ける場合と比べて、作業台ユニット10の全体重量を減らすことができる。   The building frame used for the scaffold installed on the work table 40 is made of a compressed material, and is heavier than the suspension frame used for the suspension scaffold. For this reason, when the two-layer scaffold 51 is provided on the work table 40 and the one-layer suspension scaffold 52 is suspended below the work table 40 as in the present embodiment, the three-layer scaffold 51 is provided on the work table 40. Compared with the case where a scaffold is provided, the overall weight of the workbench unit 10 can be reduced.

作業台40の支点は、一対のクライミング装置20における支持部材25の中間付近にある。そして、足場51及び吊足場52が設置されていない状態では、作業台40は支点の回りでつりあっている。図5に示すように、斜柱5において作業台40より上の部分は、支点に対して左側にある。このため、作業台40上で斜柱5の周りに足場51を設けると、足場51の重心は支点より左になり、作業台40はつりあいがとれなくなる。そこで、作業台40のつりあいをとるために、図5に示すように、作業台ユニット10の操作を行う操作室55を作業台40の右側に設けることにより、これをカウンタウェイト代わりにしている。なお、図5では、図3において右側に位置する斜柱5を例示したが、図3において左側に位置する斜柱5の場合には、操作室55を作業台40の左側に設置するのはいうまでもない。   The fulcrum of the work table 40 is near the middle of the support member 25 in the pair of climbing apparatuses 20. In a state where the scaffold 51 and the suspended scaffold 52 are not installed, the work table 40 is balanced around the fulcrum. As shown in FIG. 5, the portion of the oblique column 5 above the work table 40 is on the left side with respect to the fulcrum. For this reason, when the scaffold 51 is provided around the oblique column 5 on the work table 40, the center of gravity of the scaffold 51 is to the left of the fulcrum, and the work table 40 cannot be balanced. Therefore, in order to balance the work table 40, an operation chamber 55 for operating the work table unit 10 is provided on the right side of the work table 40 as shown in FIG. In FIG. 5, the oblique column 5 located on the right side in FIG. 3 is illustrated, but in the case of the oblique column 5 located on the left side in FIG. 3, the operation chamber 55 is installed on the left side of the work table 40. Needless to say.

上記のように構成した作業台ユニット10では、図5に示すように、足場51の2階において鉄筋9の組立て・配置作業を行い、足場52の1階において型枠11の組立て及び型枠11内へのコンクリート打設作業を行う。また、吊足場52においては、所定期間養生させて十分な強度が発現した状態にある硬化コンクリートの壁面8の仕上げ作業を行う。   In the workbench unit 10 configured as described above, the rebar 9 is assembled and arranged on the second floor of the scaffold 51, and the mold 11 is assembled and formed on the first floor of the scaffold 52, as shown in FIG. 5. The concrete is placed inside. Moreover, in the suspended scaffold 52, the finishing operation | work of the wall surface 8 of the hardened concrete in the state which was made to age for a predetermined period and expressed sufficient intensity | strength is performed.

次に、図6−1〜図6−4を参照しながら、作業台ユニット10を用いて斜柱5を構築する手順について説明する。なお、本実施の形態では、一対の斜柱5,5にそれぞれ作業台ユニット10を設置して独立に施工を行うため、以下では一方の斜柱5の構築についてのみ説明する。   Next, a procedure for constructing the oblique column 5 using the work table unit 10 will be described with reference to FIGS. In the present embodiment, since the work table unit 10 is installed on each of the pair of oblique columns 5 and 5 and construction is performed independently, only the construction of one of the oblique columns 5 will be described below.

まず、図6−1に示すように斜柱5の1階の構築を行う際には、作業台ユニット10を用いず、橋脚7上に足場(図示せず)を設け、通常支保工で構築する。1階に打設したコンクリートを養生させて硬化させた後、以下のようにして、図6−2に示す位置に作業台ユニット10を設置する。斜柱5の1階の硬化コンクリート壁面8に鋼板21(図4を参照)を介して反力柱22を固定し、クライミング装置20を設置する。この際、クライミング装置20のジャッキ支持部材23及び支持部材25はともに反力柱22に対して固定しておく。次いで、クライミング装置20に受梁を介して作業台40を支持させた後、作業台40上に2階層の足場51を設けるとともに、作業台40の下部に1階層の吊足場52を設ける。以上のようにして、作業台ユニット10の設置が完了する。   First, when constructing the first floor of the oblique column 5 as shown in FIG. 6A, a scaffold (not shown) is provided on the pier 7 without using the workbench unit 10, and is constructed by normal support work. To do. After the concrete placed on the first floor is cured and hardened, the workbench unit 10 is installed at the position shown in FIG. 6-2 as follows. The reaction force column 22 is fixed to the hardened concrete wall surface 8 on the first floor of the oblique column 5 via a steel plate 21 (see FIG. 4), and the climbing device 20 is installed. At this time, both the jack support member 23 and the support member 25 of the climbing device 20 are fixed to the reaction force column 22. Next, after the work table 40 is supported by the climbing device 20 via the receiving beam, a two-level scaffold 51 is provided on the work table 40 and a one-level suspended scaffold 52 is provided below the work table 40. As described above, the installation of the workbench unit 10 is completed.

斜柱の2階以降は、作業台ユニット10を用いて構築する。図6−2に示すように、足場51の1階では、斜柱5の2階部分の鉄筋組立て、型枠11の設置、型枠11内へのコンクリート打設を行う。足場51の2階では、斜柱5の3階部分の鉄筋組立てを行う。また、吊足場52では、斜柱5の1階の硬化コンクリートの仕上げ作業を行う。以上の施工を同時進行で行う。   The second and subsequent floors of the oblique column are constructed using the work table unit 10. As shown in FIG. 6B, on the first floor of the scaffold 51, rebar assembly of the second floor portion of the oblique column 5, installation of the mold 11, and concrete placement into the mold 11 are performed. On the second floor of the scaffold 51, rebar assembly of the third floor portion of the oblique column 5 is performed. Moreover, in the suspended scaffolding 52, the finishing work of the hardened concrete on the first floor of the oblique column 5 is performed. The above construction is performed simultaneously.

斜柱5の1階〜3階までの施工が完了し、2階に打設したコンクリートが硬化した後、斜柱5の2階の硬化コンクリート壁面8に鋼板21(図4を参照)を介して反力柱22を固定し、クライミング装置20を設置する。この際、2階の反力柱22を、1階に設置した反力柱22に連続するように設置する。   After the construction from the first floor to the third floor of the oblique column 5 is completed and the concrete placed on the second floor is hardened, the hardened concrete wall surface 8 on the second floor of the oblique column 5 is passed through the steel plate 21 (see FIG. 4). Then, the reaction force column 22 is fixed and the climbing device 20 is installed. At this time, the reaction column 22 on the second floor is installed so as to be continuous with the reaction column 22 installed on the first floor.

次いで、以下のようにして、作業台ユニット10を上階の設置位置(図6−2の破線で示す位置)まで上昇させる。まず、クライミング装置20の支持部材25と反力柱22との締結を解除し、支持部材25を反力柱22に沿って移動可能な状態にする。次に、ジャッキ24を伸長させ、支持部材25を反力柱22に沿って上昇させることによって作業台40を押し上げる。これにより、作業台40は斜柱5の傾斜方向に上昇し、上階の設置位置に到達する。   Next, the workbench unit 10 is raised to the upper floor installation position (position indicated by the broken line in FIG. 6-2) as follows. First, the fastening between the support member 25 and the reaction force column 22 of the climbing apparatus 20 is released, and the support member 25 is moved along the reaction force column 22. Next, the work table 40 is pushed up by extending the jack 24 and raising the support member 25 along the reaction force column 22. As a result, the work table 40 rises in the inclination direction of the oblique column 5 and reaches the installation position on the upper floor.

作業台40を上階の設置位置まで上昇させた後、クライミング装置20の支持部材25を反力柱22に対して固定する。一方、ジャッキ支持部材23と反力柱22との締結を解除し、ジャッキ支持部材23を反力柱22に沿って移動可能な状態にする。そして、ジャッキ24を縮退させてジャッキ支持部材23を反力柱22に沿って上昇させた後、ジャッキ支持部材23を反力柱22に固定する。以上の手順により、図6−3に示すように作業台ユニット10の移動が完了する。   After raising the work table 40 to the installation position on the upper floor, the support member 25 of the climbing device 20 is fixed to the reaction force column 22. On the other hand, the fastening of the jack support member 23 and the reaction force column 22 is released, so that the jack support member 23 is movable along the reaction force column 22. Then, after the jack 24 is retracted and the jack support member 23 is raised along the reaction force column 22, the jack support member 23 is fixed to the reaction force column 22. By the above procedure, the movement of the workbench unit 10 is completed as shown in FIG. 6-3.

図6−2及び図6−3に示すように、上階の設置位置に移動した後の作業台40の斜柱5に対する位置は、移動する前の作業台40の斜柱5に対する位置と変わらない。すなわち、斜柱5に対して作業台40の位置がずれることはない。従って、作業台40を上階の設置位置に移動させた後、作業台40を水平方向に移動させたり、足場51及び吊足場52を移動させる必要がなく、速やかに各作業に取り掛かることができる。   As shown in FIGS. 6-2 and 6-3, the position of the work table 40 with respect to the oblique column 5 after moving to the installation position on the upper floor is different from the position of the work table 40 with respect to the oblique column 5 before moving. Absent. That is, the position of the work table 40 does not shift with respect to the oblique column 5. Therefore, it is not necessary to move the work table 40 in the horizontal direction or move the scaffold 51 and the suspended scaffold 52 after moving the work table 40 to the installation position on the upper floor, and can immediately start each work. .

作業台ユニット10が図6−3に示す位置にあるとき、足場51の1階では、斜柱5の3階部分の型枠11の設置及び型枠11内へのコンクリート打設を行い、足場51の2階では、斜柱の4階の鉄筋9の組立てを行い、吊足場52では、斜柱5の2階の硬化コンクリートの仕上げ作業を行う。   When the workbench unit 10 is in the position shown in FIG. 6-3, on the first floor of the scaffold 51, the formwork 11 on the third floor portion of the oblique column 5 is installed and the concrete is placed in the formwork 11, and the scaffold is placed. On the second floor of 51, the reinforcing bars 9 on the fourth floor of the oblique pillar are assembled, and on the suspension scaffold 52, the hardened concrete on the second floor of the oblique pillar 5 is finished.

上記の工程を繰り返すことによって斜柱5を斜め上方に向けて順次構築していく。他方の斜柱5についても同様の工程を繰り返して構築する。   By repeating the above-described steps, the oblique column 5 is constructed in an obliquely upward direction. The same process is repeated for the other oblique column 5 to build.

なお、一対の斜柱5,5の構築が進むのに伴い、一対の斜柱5,5間の距離は狭まる。このため、上層部の構築を行う際には、2台の作業台40,40が衝突するのを防止するために、図6−4に示すように、各作業台40を互いに離れる方向に受梁30に対してスライドさせる。   Note that the distance between the pair of oblique columns 5 and 5 decreases as the construction of the pair of oblique columns 5 and 5 progresses. For this reason, when constructing the upper layer portion, in order to prevent the two work tables 40, 40 from colliding with each other, as shown in FIG. Slide against beam 30.

以上説明したように、本実施の形態における構造物の構築方法によれば、作業台40を上階の設置位置に上昇させる際に、斜柱5の傾斜方向に作業台40を移動させるようにしたことで、斜柱5に対して鉛直方向に作業台40を引き上げる従来の方法のように、作業台40を上階の設置位置に引き上げるたびに斜柱5に対して作業台40の位置がずれるといったことがなくなるため、施工性に優れる。   As described above, according to the structure construction method in the present embodiment, when the work table 40 is raised to the installation position on the upper floor, the work table 40 is moved in the inclination direction of the oblique column 5. Thus, the position of the work table 40 with respect to the oblique column 5 is changed every time the work table 40 is pulled up to the installation position on the upper floor as in the conventional method of lifting the work table 40 in the vertical direction with respect to the oblique column 5. Since there is no slippage, it is excellent in workability.

また、本実施の形態における構造物の構築方法によれば、外壁面に反力柱22を介してジャッキ支持部材23を取付け、ジャッキ支持部材23に支持させたジャッキ24を用いて、作業台40を斜柱5の傾斜方向に押し上げるようにしたことで、簡易な構成で確実に作業台40を斜柱5の傾斜方向に移動させることができる。   Moreover, according to the construction method of the structure in the present embodiment, the work table 40 is attached to the outer wall surface via the reaction force column 22 and the jack 24 supported by the jack support member 23 is used. By pushing up in the inclination direction of the oblique column 5, the work table 40 can be reliably moved in the inclination direction of the oblique column 5 with a simple configuration.

また、本実施の形態における構造物の構築方法によれば、作業台40上に足場51を設けるとともに、作業台40の下方に吊足場52を吊設することで、作業台40上のみに足場を設ける場合と比べて、作業台ユニット10の全体重量を減らすことが可能である。すなわち、作業台40上に設置される足場51に使用する建枠は圧縮材料から構成されるものであるため、吊足場に使用する吊枠と比べて重い。このため、上記実施の形態のように、作業台40上に2階層の足場51を設け、作業台40の下方に1階層の吊足場52を吊設する場合、作業台40上に3階層の足場51を設ける場合と比べて、作業台ユニット10の全体重量を減らすことができる。   Further, according to the construction method of the structure in the present embodiment, the scaffold 51 is provided on the work table 40 and the scaffold 52 is suspended below the work table 40, so that the scaffold is provided only on the work table 40. It is possible to reduce the overall weight of the workbench unit 10 as compared to the case of providing the work table. That is, since the building frame used for the scaffold 51 installed on the work table 40 is composed of a compressed material, it is heavier than the suspension frame used for the suspension scaffold. Therefore, when the two-layer scaffold 51 is provided on the work table 40 and the one-layer suspension scaffold 52 is suspended below the work table 40 as in the above embodiment, the three-layer scaffold 51 is provided on the work table 40. Compared with the case where the scaffold 51 is provided, the overall weight of the workbench unit 10 can be reduced.

なお、上記実施の形態は、斜張橋の主塔を構築する場合について説明したが、適用対象はこれに限定されるものではなく、他の柱状の構造物を斜めに構築する場合にも適用することができる。また、上記実施の形態では、鉄筋コンクリート構造物を構築する場合について説明したが、鉄塔などの鉄筋コンクリート構造物以外の構造物にも適用することができる。   In the above embodiment, the case where the main tower of the cable-stayed bridge is constructed has been described. However, the application target is not limited to this, and the present invention is also applied to the case where other columnar structures are constructed obliquely. can do. Moreover, although the said embodiment demonstrated the case where a reinforced concrete structure was constructed | assembled, it is applicable also to structures other than reinforced concrete structures, such as a steel tower.

また、上記実施の形態では、2本の構造物を構築する場合について説明したが、1本の構造物に適用してもよいのはもちろんである。   Moreover, although the case where two structures were constructed | assembled was demonstrated in the said embodiment, of course, you may apply to one structure.

さらに、上記実施の形態では、一対の斜柱5,5に設置した各作業台ユニット10の作業台40が衝突するのを防止するために、受梁30に対して作業台40をスライド可能に構成したが、1本の構造物を構築する場合には、必ずしもスライド機構を設ける必要はない。   Furthermore, in the above embodiment, the work table 40 can be slid with respect to the receiving beam 30 in order to prevent the work tables 40 of the work table units 10 installed on the pair of oblique columns 5 and 5 from colliding with each other. Although constructed, when a single structure is constructed, it is not always necessary to provide a slide mechanism.

斜張橋の側面図である。It is a side view of a cable-stayed bridge. 図1に示す斜張橋における主塔の正面図である。It is a front view of the main tower in a cable-stayed bridge shown in FIG. 本発明の構築方法を適用して図2に示す主塔(斜柱)の構築を行っている状態を示す正面図である。It is a front view which shows the state which has constructed the main tower (slanted column) shown in FIG. 2 by applying the construction method of the present invention. 図3において、作業台ユニットを拡大して示した図である。In FIG. 3, it is the figure which expanded and showed the workbench unit. 作業台ユニットの足場の各階で行う施工内容を説明するための図である。It is a figure for demonstrating the construction content performed on each floor of the scaffold of a work bench unit. 作業台ユニットを用いて斜柱を構築する手順を説明する図である。It is a figure explaining the procedure which constructs an oblique pillar using a workbench unit. 作業台ユニットを用いて斜柱を構築する手順を説明する図である。It is a figure explaining the procedure which constructs an oblique pillar using a workbench unit. 作業台ユニットを用いて斜柱を構築する手順を説明する図である。It is a figure explaining the procedure which constructs an oblique pillar using a workbench unit. 作業台ユニットを用いて斜柱を構築する手順を説明する図である。It is a figure explaining the procedure which constructs an oblique pillar using a workbench unit.

符号の説明Explanation of symbols

1 斜張橋
2 主塔
3 ケーブル
4 橋桁
5 斜柱
6 頂部
7 橋脚
8 硬化コンクリート壁面
9 鉄筋
10 作業台ユニット
11 型枠
20 クライミング装置
21 鋼板
22 反力柱
23 ジャッキ支持部材
24 ジャッキ
25 支持部材
26 アンカーボルト
30 受梁
40 作業台
41 コロ装置
51 足場
52 吊足場
53 建枠
54 吊枠
55 操作室
DESCRIPTION OF SYMBOLS 1 Cable-stayed bridge 2 Main tower 3 Cable 4 Bridge girder 5 Oblique pillar 6 Top part 7 Pier pier 8 Hardened concrete wall 9 Reinforcement 10 Worktable unit 11 Formwork 20 Climbing device 21 Steel plate 22 Reaction force pillar 23 Jack support member 24 Jack 25 Support member 26 Anchor bolt 30 Receiving beam 40 Work table 41 Roller device 51 Scaffolding 52 Suspended scaffolding 53 Building frame 54 Hanging frame 55 Operation room

Claims (3)

作業台を施工対象階の外壁面に対応させて配置し、前記作業台を用いて施工対象階の施工を行った後に、前記作業台を前記外壁面に沿って次の施工対象階まで上昇させる工程を繰り返すことにより、地表面に対して傾斜した構造物を上層部まで順次構築する方法において、
前記作業台を、前記構造物の傾斜方向に移動させることによって次の施工対象階まで上昇させることを特徴とする構造物の構築方法。
A work table is arranged corresponding to the outer wall surface of the floor to be constructed, and after the work floor is constructed using the work table, the work table is raised along the outer wall surface to the next floor to be constructed. In the method of sequentially building the structure inclined to the ground surface up to the upper layer by repeating the process,
A construction method for a structure, wherein the work table is moved up to the next floor to be constructed by moving the work table in an inclination direction of the structure.
前記外壁面にジャッキ支持部材を取付け、前記ジャッキ支持部材に支持させたジャッキで前記作業台を前記構造物の傾斜方向に押し上げることによって、前記作業台を次の施工対象階まで上昇させることを特徴とする請求項1に記載の構造物の構築方法。   A jack support member is attached to the outer wall surface, and the work table is raised to the next floor to be constructed by pushing up the work table in a tilt direction of the structure with a jack supported by the jack support member. The method for constructing a structure according to claim 1. 前記作業台上に足場を設けるとともに、前記作業台の下部に吊足場を設けることを特徴とする請求項1又は2に記載の構造物の構築方法。   The structure construction method according to claim 1 or 2, wherein a scaffold is provided on the work table, and a suspended scaffold is provided at a lower part of the work table.
JP2008215871A 2008-08-25 2008-08-25 Construction method of structure Pending JP2010048060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008215871A JP2010048060A (en) 2008-08-25 2008-08-25 Construction method of structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008215871A JP2010048060A (en) 2008-08-25 2008-08-25 Construction method of structure

Publications (1)

Publication Number Publication Date
JP2010048060A true JP2010048060A (en) 2010-03-04

Family

ID=42065346

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008215871A Pending JP2010048060A (en) 2008-08-25 2008-08-25 Construction method of structure

Country Status (1)

Country Link
JP (1) JP2010048060A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251478A (en) * 2011-04-27 2011-11-23 中铁港航局集团第二工程有限公司 Control method for synchronous construction survey of pylons and beams of cable-stayed bridge
CN102277836A (en) * 2011-06-14 2011-12-14 中铁五局集团建筑工程有限责任公司 Construction method of tilting concrete tower base
RU2468144C1 (en) * 2011-06-10 2012-11-27 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Curb to form cable unit in reinforced concrete span
CN102926329A (en) * 2012-11-23 2013-02-13 江苏省交通工程集团有限公司 Device dedicated for lifting steel box beam of small and medium-sized long-span suspension bridge and lifting method
CN104343086A (en) * 2014-10-27 2015-02-11 中铁港航局集团有限公司 Small-spatial construction method for steel anchor beam anchoring zone of cable-stayed bridge upper pylon
CN105755959A (en) * 2016-03-11 2016-07-13 广东省长大公路工程有限公司 Auxiliary bracket system suitable for construction of cable towers with different sections and building method
CN106522104A (en) * 2016-12-21 2017-03-22 中铁四局集团有限公司 A construction method for a curved concrete tower
CN107386115A (en) * 2017-07-17 2017-11-24 中交路桥华南工程有限公司 Inclined pier pouring method
KR20180056155A (en) * 2016-11-18 2018-05-28 현대건설주식회사 Construction method of a long span bridge main tower
CN109989350A (en) * 2019-03-26 2019-07-09 中铁七局集团有限公司 A kind of bridge Sarasota construction method
CN114717950A (en) * 2022-03-17 2022-07-08 中交武汉港湾工程设计研究院有限公司 Intelligent pier making machine and construction method
CN116356696A (en) * 2023-03-21 2023-06-30 中铁二十局集团第六工程有限公司 Construction Method of Climbing Form for Inclined Variable Section Structure
CN116905352A (en) * 2023-08-15 2023-10-20 中铁大桥勘测设计院集团有限公司 An orthogonal steel-concrete composite structure inclined bridge tower
CN119824803A (en) * 2025-01-22 2025-04-15 中铁大桥局第九工程有限公司 Construction method for curve variable-section bridge tower reinforcement cage block prefabrication
CN119877380A (en) * 2025-01-26 2025-04-25 中铁大桥勘测设计院集团有限公司 An asymmetrically arranged steel structure cable tower anchoring system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49103154U (en) * 1972-12-27 1974-09-04
JPS5670362A (en) * 1979-11-12 1981-06-12 Tokyu Kensetsu Kk Form method of and apparatus for concrete
JPH01190877A (en) * 1988-01-25 1989-07-31 Kajima Corp Concrete column forming equipment
JPH0782883A (en) * 1993-09-10 1995-03-28 Taisei Corp Construction method of tower concrete structure
JPH09235707A (en) * 1996-03-04 1997-09-09 Kajima Corp Self-climbing device for lifting tower structures
JPH10219993A (en) * 1997-02-06 1998-08-18 Kajima Corp Work scaffold
JP2003328323A (en) * 2002-05-15 2003-11-19 Kajima Corp Construction method of tower structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49103154U (en) * 1972-12-27 1974-09-04
JPS5670362A (en) * 1979-11-12 1981-06-12 Tokyu Kensetsu Kk Form method of and apparatus for concrete
JPH01190877A (en) * 1988-01-25 1989-07-31 Kajima Corp Concrete column forming equipment
JPH0782883A (en) * 1993-09-10 1995-03-28 Taisei Corp Construction method of tower concrete structure
JPH09235707A (en) * 1996-03-04 1997-09-09 Kajima Corp Self-climbing device for lifting tower structures
JPH10219993A (en) * 1997-02-06 1998-08-18 Kajima Corp Work scaffold
JP2003328323A (en) * 2002-05-15 2003-11-19 Kajima Corp Construction method of tower structure

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251478B (en) * 2011-04-27 2013-05-08 中铁港航局集团第二工程有限公司 Control method for synchronous construction survey of pylons and beams of cable-stayed bridge
CN102251478A (en) * 2011-04-27 2011-11-23 中铁港航局集团第二工程有限公司 Control method for synchronous construction survey of pylons and beams of cable-stayed bridge
RU2468144C1 (en) * 2011-06-10 2012-11-27 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Curb to form cable unit in reinforced concrete span
CN102277836A (en) * 2011-06-14 2011-12-14 中铁五局集团建筑工程有限责任公司 Construction method of tilting concrete tower base
CN102926329A (en) * 2012-11-23 2013-02-13 江苏省交通工程集团有限公司 Device dedicated for lifting steel box beam of small and medium-sized long-span suspension bridge and lifting method
CN102926329B (en) * 2012-11-23 2015-01-21 江苏省交通工程集团有限公司 Device dedicated for lifting steel box beam of small and medium-sized long-span suspension bridge and lifting method
CN104343086A (en) * 2014-10-27 2015-02-11 中铁港航局集团有限公司 Small-spatial construction method for steel anchor beam anchoring zone of cable-stayed bridge upper pylon
CN105755959A (en) * 2016-03-11 2016-07-13 广东省长大公路工程有限公司 Auxiliary bracket system suitable for construction of cable towers with different sections and building method
CN105755959B (en) * 2016-03-11 2017-07-28 广东省长大公路工程有限公司 Suitable for the Sarasota construction auxiliary stand system and building method of different cross section
KR101889064B1 (en) * 2016-11-18 2018-08-16 현대건설 주식회사 Construction method of a long span bridge main tower
KR20180056155A (en) * 2016-11-18 2018-05-28 현대건설주식회사 Construction method of a long span bridge main tower
CN106522104A (en) * 2016-12-21 2017-03-22 中铁四局集团有限公司 A construction method for a curved concrete tower
CN107386115A (en) * 2017-07-17 2017-11-24 中交路桥华南工程有限公司 Inclined pier pouring method
CN109989350A (en) * 2019-03-26 2019-07-09 中铁七局集团有限公司 A kind of bridge Sarasota construction method
CN114717950A (en) * 2022-03-17 2022-07-08 中交武汉港湾工程设计研究院有限公司 Intelligent pier making machine and construction method
CN114717950B (en) * 2022-03-17 2024-04-12 中交武汉港湾工程设计研究院有限公司 Intelligent pier making machine and construction method
CN116356696A (en) * 2023-03-21 2023-06-30 中铁二十局集团第六工程有限公司 Construction Method of Climbing Form for Inclined Variable Section Structure
CN116905352A (en) * 2023-08-15 2023-10-20 中铁大桥勘测设计院集团有限公司 An orthogonal steel-concrete composite structure inclined bridge tower
CN119824803A (en) * 2025-01-22 2025-04-15 中铁大桥局第九工程有限公司 Construction method for curve variable-section bridge tower reinforcement cage block prefabrication
CN119877380A (en) * 2025-01-26 2025-04-25 中铁大桥勘测设计院集团有限公司 An asymmetrically arranged steel structure cable tower anchoring system

Similar Documents

Publication Publication Date Title
JP2010048060A (en) Construction method of structure
JP5280445B2 (en) Method for forming multiple horizontal structural members
JP4777922B2 (en) Mobile suspension support
CN210659200U (en) High-rise building elevator shaft operation platform
JP6474151B2 (en) Dismantling system and dismantling method
JP6752160B2 (en) Mobile work vehicle
KR101030053B1 (en) Mobile formwork installation and dismantling device for steel box bridge
JPH10339033A (en) Concrete multistory building construction device and construction method for concrete oblique post
JP2018059288A (en) Overhang construction method
US9683338B2 (en) Form traveller for the construction of engineering works
KR102534830B1 (en) PIT floor multi support system and PIT floor construction method using the same
KR20110105489A (en) High-rise building construction method using table form that rises through slab opening
KR20190041189A (en) Modular work platform of a long span bridge main tower rebar and construction method using the same
JP6449637B2 (en) Building construction method
JP5003253B2 (en) RC beam construction method
JP5645334B2 (en) Structure dismantling system
JP5448193B2 (en) Temporary roof support structure
JP6391135B2 (en) How to install temporary pillars
KR102585356B1 (en) A System Foam Device for High-Rise Elevators for Installation of Embed-Plates and Construction Method for Embed-Plates for High-Rise Elevators using the same
JP2016044470A (en) How to install temporary pillars
JP2009299346A (en) Construction method of building
JP7500408B2 (en) Pre-construction method for interior stairs of buildings
JP6508959B2 (en) Demolition system and demolition method
JP2009197537A (en) Structure and method for supporting floor slab
JP5972113B2 (en) Construction method of multistory parking lot

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110407

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120521

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120529

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20121002