JP2008215031A - Scaffolding construction method - Google Patents
Scaffolding construction method Download PDFInfo
- Publication number
- JP2008215031A JP2008215031A JP2007057249A JP2007057249A JP2008215031A JP 2008215031 A JP2008215031 A JP 2008215031A JP 2007057249 A JP2007057249 A JP 2007057249A JP 2007057249 A JP2007057249 A JP 2007057249A JP 2008215031 A JP2008215031 A JP 2008215031A
- Authority
- JP
- Japan
- Prior art keywords
- scaffold
- construction method
- piles
- row
- scaffolding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 229910000831 Steel Inorganic materials 0.000 abstract description 18
- 239000010959 steel Substances 0.000 abstract description 18
- 239000002184 metal Substances 0.000 abstract description 7
- 239000000725 suspension Substances 0.000 description 14
- 239000000463 material Substances 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000010422 painting Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
- Revetment (AREA)
Abstract
Description
本発明は、複数列の杭に支持される床版の直下に施工する足場の施工方法に関する。 The present invention relates to a scaffold construction method for construction directly under a floor slab supported by a plurality of rows of piles.
従来より、複数列の杭に床版が支持された橋梁や桟橋等の構造物の下面を対象とした点検や塗装や補修等を行う場合、その床版の直下に足場を一時的に設置し、作業足場として使用している。 Conventionally, when inspecting, painting, or repairing the lower surface of a structure such as a bridge or pier where the slab is supported by multiple rows of piles, a scaffold is temporarily installed directly under the slab. It is used as a working scaffold.
このような足場は一般に、地表面から組み上げられているが、例えば桟橋のように、地表面から足場を組み上げることが不可能な場合には、吊り足場が採用されている。 Such a scaffold is generally assembled from the ground surface, but a suspended scaffold is employed when it is impossible to assemble the scaffold from the ground surface, such as a pier.
この吊り足場は、床版の下面にアンカー材を打ち込み、そのアンカー材から吊りチェーンで鋼管を吊り、その鋼管上に足場板を敷き並べて足場床とするものである(例えば、特許文献1参照。)。
しかしながら、上述した吊り足場は、多数のアンカー材を床版の下面に打ち込む必要があるため、組み立てや解体に多大な時間や労力を要する。また、多数の吊りチェーンが吊り足場上に存在することとなるため、その吊りチェーンが点検や塗装や補修等の作業の妨げとなるおそれがあり、作業性が悪いといった問題がある。さらに、その吊りチェーンが作業時における危険要素となるおそれもある。 However, the suspension scaffold described above requires a great amount of time and labor for assembly and disassembly because a large number of anchor materials need to be driven into the lower surface of the floor slab. In addition, since a large number of suspension chains exist on the suspension scaffold, there is a possibility that the suspension chains may hinder operations such as inspection, painting, and repair, resulting in poor workability. Furthermore, there is a possibility that the suspension chain may become a dangerous factor during work.
本発明は、上記事情に鑑み、組み立てや解体が容易であり、床版の直下における作業性や安全性に優れた足場の施工方法を提供することを目的とするものである。 In view of the above circumstances, an object of the present invention is to provide a method for constructing a scaffold that is easy to assemble and dismantle and is excellent in workability and safety directly under a floor slab.
上記目的を達成する本発明の足場の施工方法は、複数列の杭に支持される床版の直下に足場を施工するに当たり、各列の杭の両側面の足場架設レベルにPCケーブルを支承する支承部材を取り付け、PCケーブルを上記支承部材に支承させて各列の杭の周囲に配設し、そのPCケーブルを緊張して定着し、そのPCケーブル上に作業床を施工することを特徴とする。 The construction method of the scaffold of the present invention that achieves the above object is to support the PC cable at the scaffold construction level on both sides of the piles in each row when constructing the scaffold directly under the floor slab supported by the rows of piles. It is characterized in that a support member is attached, a PC cable is supported on the support member and arranged around the piles in each row, the PC cable is tensioned and fixed, and a work floor is constructed on the PC cable. To do.
本発明の足場の施工方法は、各列の杭の両側面の足場架設レベルに取り付けられた支承部材にPCケーブルを支承させて各列の杭の周囲に配設し、そのPCケーブルを緊張して定着し、そのPCケーブル上に作業床を施工する方法である。従って、本発明の足場の施工方法によれば、従来の吊り足場に比して、組み立てや解体が容易であるため、足場工の施工日数を短縮することができ、施工費が抑制される。また、本発明の足場の施工方法によれば、足場上に作業の妨げとなる吊りチェーン等が存在しないこととなるため、床版の直下における作業性や安全性に優れる。 In the scaffold construction method of the present invention, a PC cable is supported on a support member attached to a scaffolding construction level on both sides of each row of piles and arranged around each pile, and the PC cable is tensioned. The work floor is constructed on the PC cable. Therefore, according to the scaffold construction method of the present invention, assembly and disassembly are easier than conventional suspension scaffolds, so that the number of construction days for the scaffolding can be shortened and construction costs are suppressed. In addition, according to the scaffold construction method of the present invention, there is no suspension chain or the like that hinders work on the scaffold, so that the workability and safety directly under the floor slab are excellent.
本発明の足場の施工方法によれば、従来の吊り足場に比して、組み立てや解体が容易であり、床版の直下における作業性や安全性に優れる。 According to the scaffold construction method of the present invention, it is easy to assemble and disassemble as compared with a conventional suspended scaffold, and is excellent in workability and safety directly under the floor slab.
以下、図面を参照して本発明の実施の形態を説明する。 Embodiments of the present invention will be described below with reference to the drawings.
図1は、本発明の足場の施工方法についての一実施形態を説明するもので、足場100および足場100が施工された桟橋200の縦断面図である。また、図2は、図1に示す足場100の施工方法における第1の工程を示す平面図である。また、図3は、図2に示すA部の拡大図である。また、図4は、図3に示すB矢視図であり、図5は、図3に示すC矢視図であり、図6は、図3に示すD矢視図であり、図7は、図3に示すE矢視図である。
FIG. 1 is a longitudinal sectional view of a
図1には、5列の杭210に床版220が支持された桟橋200が示されている。また、この図1には、桟橋200の床版の直下に施工された足場100も示されている。
FIG. 1 shows a
以下、この図1に示す足場100の施工方法を説明する。
Hereinafter, a construction method of the
まず、図2〜図7に示すように、各列の杭210の両側面の足場架設レベルにPC鋼より線120を支承する吊り金具111,112をボルト114を用いて取り付け、各列の一方の端部の杭210にPC鋼より線120の端部を定着する定着金具113をボルトを用いて取り付ける。このPC鋼より線120は、本発明にいうPCケーブルの実施例である。
First, as shown in FIG. 2 to FIG. 7, hanging
次に、PC鋼より線120を吊り金具111,112に支承させて各列の杭210の周囲に配設し、PC鋼より線120を、図示しないジャッキを用いて緊張し、定着金具113に定着する。
Next, the PC steel stranded
ここで、図3〜図5に示す、各列の一方の端部の杭210に取り付けられた吊り金具111は、取り付け状態において上部が解放されるコの字型形状の、本発明にいう支承部材の第1実施例であって、PC鋼より線120を上方から差し入れて支承させる。
Here, the suspension fitting 111 attached to the
また、図3,図6,図7に示す、上記一方の端部を除く各列の杭210に取り付けられた吊り金具112は、取り付け状態において両側部が解放される箱型形状の、本発明にいう支承部材の第2実施例であって、PC鋼より線120を側方から挿入して配設する。
Moreover, the
尚、ここでは、本発明にいう支承部材の実施例として、上述した2種類の吊り金具の例を挙げて説明したが、本発明にいう支承部材はこれに限られるものではなく、PCケーブルを支承するものであればいかなる形状のものであってもよい。 In addition, here, as an example of the support member according to the present invention, the above-described two types of suspension fittings have been described. However, the support member according to the present invention is not limited to this, and a PC cable is used. Any shape may be used as long as it is supported.
図8は、図1に示す足場100の施工方法における第2の工程を示す平面図である。
FIG. 8 is a plan view showing a second step in the construction method of the
図8に示すように、各列の杭210の周囲に配設して定着したPC鋼より線120上に鋼管130を敷き並べる。
As shown in FIG. 8, the
最後に、敷き並べられた鋼管130上に、作業床としてのエキスパンドメタル140を敷き並べる。
Finally, the expanded
図9は、本発明の他の実施形態を説明する平面図である。 FIG. 9 is a plan view for explaining another embodiment of the present invention.
図9に示すように、各列の両端部の杭210にPC鋼より線121,122の端部を定着する定着金具113を取り付け、各列の杭210のうちの中央の杭211を境に分割した各杭列の周囲にぞれぞれのPC鋼より線121,122を配設してジャッキを用いて緊張し、定着金具113に定着してもよい。
As shown in FIG. 9,
以上説明したように、本実施形態の足場の施工方法によれば、従来の吊り足場に比して、組み立てや解体が容易であるため、足場工の施工日数を短縮することができ、施工費が抑制される。また、本実施形態の足場の施工方法によれば、足場100上に作業の妨げとなる吊りチェーン等が存在しないこととなるため、床版220の直下における作業性や安全性に優れる。
As described above, according to the scaffold construction method of the present embodiment, since it is easier to assemble and dismantle than conventional suspension scaffolds, the number of construction days for the scaffolding can be shortened, and the construction cost is reduced. Is suppressed. Further, according to the scaffold construction method of the present embodiment, there is no suspension chain or the like that hinders work on the
尚、上述した実施形態では、本発明の足場の施工方法が、桟橋の床版の直下に施工する足場の施工方法である例を挙げて説明したが、本発明の足場の施工方法はこれに限られるものではなく、複数列の杭に支持される床版の直下に施工する足場の施工方法に適用することができる。 In the above-described embodiment, the scaffold construction method of the present invention has been described with reference to an example of the scaffold construction method constructed immediately below the floor slab of the pier. However, the scaffold construction method of the present invention is described here. It is not limited, and can be applied to a construction method for a scaffold that is constructed immediately below a floor slab supported by a plurality of rows of piles.
100 足場
111,112 吊り金具
113 定着金具
114 ボルト
120,121,122 PC鋼より線
130 鋼管
140 エキスパンドメタル
200 桟橋
210,211 杭
220 床版
100 Scaffold 111,112
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2007057249A JP2008215031A (en) | 2007-03-07 | 2007-03-07 | Scaffolding construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2007057249A JP2008215031A (en) | 2007-03-07 | 2007-03-07 | Scaffolding construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JP2008215031A true JP2008215031A (en) | 2008-09-18 |
Family
ID=39835413
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2007057249A Pending JP2008215031A (en) | 2007-03-07 | 2007-03-07 | Scaffolding construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2008215031A (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103669214A (en) * | 2013-11-19 | 2014-03-26 | 中建三局建设工程股份有限公司 | Superlong prestress strand combing, binding and strand pulling integrated device |
| WO2014189962A1 (en) * | 2013-05-21 | 2014-11-27 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| WO2014189498A1 (en) * | 2013-05-21 | 2014-11-27 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| US9410333B2 (en) | 2013-05-21 | 2016-08-09 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| CN105908739A (en) * | 2016-04-15 | 2016-08-31 | 中交四航局第二工程有限公司 | Rigid-soft combined pile clamp structure and method |
| US9976264B2 (en) | 2013-05-21 | 2018-05-22 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| CN111691307A (en) * | 2020-06-24 | 2020-09-22 | 中交第二航务工程局有限公司 | Front support leg supporting and limiting device of bridge girder erection machine and mounting method |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11107219A (en) * | 1997-10-06 | 1999-04-20 | Ps:Kk | Wire scaffold and construction thereof |
-
2007
- 2007-03-07 JP JP2007057249A patent/JP2008215031A/en active Pending
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11107219A (en) * | 1997-10-06 | 1999-04-20 | Ps:Kk | Wire scaffold and construction thereof |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2014189962A1 (en) * | 2013-05-21 | 2014-11-27 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| WO2014189498A1 (en) * | 2013-05-21 | 2014-11-27 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| US9388589B2 (en) | 2013-05-21 | 2016-07-12 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| US9410333B2 (en) | 2013-05-21 | 2016-08-09 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| JP2016524666A (en) * | 2013-05-21 | 2016-08-18 | サーフウエイ サービシーズ, エルエルシー | Work platform system including suspended panel and method of mounting work platform system |
| US9976264B2 (en) | 2013-05-21 | 2018-05-22 | Safway Services, Llc | Work platform system including suspended paneled portion and method of implementing same |
| CN103669214A (en) * | 2013-11-19 | 2014-03-26 | 中建三局建设工程股份有限公司 | Superlong prestress strand combing, binding and strand pulling integrated device |
| CN105908739A (en) * | 2016-04-15 | 2016-08-31 | 中交四航局第二工程有限公司 | Rigid-soft combined pile clamp structure and method |
| CN105908739B (en) * | 2016-04-15 | 2018-05-15 | 中交四航局第二工程有限公司 | The clip pile structure and method of a kind of rigid flexible system |
| CN111691307A (en) * | 2020-06-24 | 2020-09-22 | 中交第二航务工程局有限公司 | Front support leg supporting and limiting device of bridge girder erection machine and mounting method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2008215031A (en) | Scaffolding construction method | |
| US8375676B2 (en) | Half precast slab and method for structuring half precast slab | |
| JP2014074304A (en) | Hanger device, top end positioning tool for reinforcement cage, hanging method for reinforcement cage, and erecting method for reinforcement cage | |
| JP5937898B2 (en) | Construction method of box girder bridge | |
| JP6889743B2 (en) | Manufacturing method of erected concrete structure in water area | |
| KR102080492B1 (en) | Construction method for cantilever in steel composite girder bridge | |
| JP2014190116A (en) | Construction method of concrete slab | |
| JP5553702B2 (en) | Connection method and connection structure of precast slab with loop joint | |
| JP5444203B2 (en) | Bridge closure construction method | |
| CN103993738A (en) | Floor penetrating and anchoring type overhanging unloading steel platform | |
| JP3144708U (en) | Reinforcing bar temporary fixing device | |
| JP5693869B2 (en) | Bridge girder construction method | |
| KR20130021178A (en) | Head reforcement apparatus of pipe piles for foundation work | |
| JP5075392B2 (en) | Rope type repair scaffold | |
| KR101106799B1 (en) | Construction method of top down concrete slab | |
| JP4421421B2 (en) | Columnar structure construction method and suspension jig | |
| JP3172161U (en) | scaffold | |
| JP5075398B2 (en) | Construction method of tower-like PC structure and tension system device | |
| JP6562544B2 (en) | Cylindrical caisson scaffolding | |
| JP2024000683A (en) | Reinforcement structure and reinforcement method | |
| WO2011132894A2 (en) | Pile head reinforcement assembly of steel pipe pile | |
| JP7037996B2 (en) | How to assemble slab rebar | |
| JP7093714B2 (en) | Pit structure and how to build it | |
| CN115506244B (en) | A pre-tensioning installation construction method for the horizontal steel-concrete combined section of a special-shaped landscape bridge | |
| JPH11107219A (en) | Wire scaffold and construction thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20091214 |
|
| A977 | Report on retrieval |
Effective date: 20110427 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
| A131 | Notification of reasons for refusal |
Effective date: 20110510 Free format text: JAPANESE INTERMEDIATE CODE: A131 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20110913 |