JP2004123347A - Container import / export control device - Google Patents
Container import / export control device Download PDFInfo
- Publication number
- JP2004123347A JP2004123347A JP2002292335A JP2002292335A JP2004123347A JP 2004123347 A JP2004123347 A JP 2004123347A JP 2002292335 A JP2002292335 A JP 2002292335A JP 2002292335 A JP2002292335 A JP 2002292335A JP 2004123347 A JP2004123347 A JP 2004123347A
- Authority
- JP
- Japan
- Prior art keywords
- work
- data
- container
- import
- export
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
【課題】コンテナ輸出入の作業のスケジュールを管理し、効率的な作業を行うことを容易にするコンテナ輸出入管理装置を提供する。
【解決手段】過去の輸出入作業の実績データを記録している記録部11と、荷主から1個又は複数のコンテナ毎に輸出入作業に関する作業情報の入力を受け付ける受け付け部12と、記録された実績データから、受け付けられた情報に含まれる荷物の種類に対応する実績データを抽出し、抽出した実績データに基づいて予定作業日程を生成する作業日程生成部13、スケジュール表作成部17と、スケジュール表を各端末に提示させる提示部18とを備え、受け付け部12は、さらに、各端末により、荷主、海貨業者、コンテナヤードオペレータ及び船会社のそれぞれから輸出入作業の進捗状況の入力を受け付け、提示部18は、さらに、スケジュール表と共に進捗状況を提示させる。
【選択図】 図1An object of the present invention is to provide a container import / export management device that manages a schedule of container import / export operations and facilitates efficient operations.
A recording unit for recording actual data of past import / export operations, a receiving unit for accepting input of operation information relating to import / export operations for each container or containers from a shipper, A work schedule generator 13 for extracting actual data corresponding to the type of package included in the received information from the actual data and generating a scheduled work schedule based on the extracted actual data; And a presentation unit 18 for presenting a table to each terminal. The reception unit 12 further receives, from each terminal, an input of the progress of import / export work from each of the shipper, a sea freighter, a container yard operator, and a shipping company. The presentation unit 18 further presents the progress status together with the schedule table.
[Selection diagram] Fig. 1
Description
【0001】
【発明の属する技術分野】
本発明は、港湾運輸におけるコンテナ輸出入の作業を効率的に管理するコンテナ輸出入管理装置、プログラム及び方法に関する。
【0002】
【従来の技術】
現在、電化製品、電気機器、機械等の海外貿易においては、定期船によるコンテナ輸出入が大半を占めている。
コンテナ輸出入の作業には、荷主、海貨業者、陸運業者、船会社等の複数の業者が携わっており、各業者間において、各種書類のやり取りにより作業が連動して行われている。
【0003】
以下に、コンテナ輸出の手順について簡単に説明する。
まず各荷主が、荷物の明細等を記載した送り状にあたるインボイス(Invoice:略記「I/V」)、荷姿等を記載したパッキングリスト(Packing List:略記「P/L」)及び各種運送情報等を記載したシッピングインストラクション(Shipping Instruction:略記「S/I」)を、1個又は複数のコンテナ毎に作成し、海貨業者に送付する。
【0004】
次に、海貨業者が各荷主から荷と共にI/V、P/L及びS/Lを受け取り、これらの書類に基づいて、船単位の各種運送情報等を記載したドックレシート(Dock Receipt:略記「D/R」)を作成し、コンテナと共に船会社に送付する。
次に、船会社が海貨業者から荷と共にD/Rを受け取り、この書類に基づいて、有価証券であるビル オブ レィディング(Bill of Lading:略記「B/L」)、又は、有価証券ではないがB/Lに準ずるウェイビル(Way Bill:略記「W/B」)等の受取証を、1個又は複数のコンテナ毎に作成して荷主に送付し、コンテナの方は船積みして最終的に受取人の元へ届ける。
【0005】
受取人は、荷主からB/L又はW/Bを、金銭を支払う等と引き替えに入手し、海外においてこの書類により受取人であることの正当性を示して、コンテナを受け取る。
コンテナ輸入の場合には、船会社が発行するアライバル ノーティス(Arrival Notice:略記「A/N」)により入港日が確定し、輸入側荷主はB/LとA/Nとを基本情報とし、海貨業者が、船会社への運賃支払い、通関指示、コンテナ搬出、コンテナ輸送を行い、空コンテナを返却する。
【0006】
このように、コンテナ輸出入では、各業者において前工程の業者から受け取った書類に基づいて自工程の書類を作成してこの書類に基づいて作業している。
【0007】
【発明が解決しようとする課題】
しかしながら、上述したような書類ベースによる逐次処理では、前工程の業者の処理が完結し書類を受け取るまでは他業者の進捗状況が得られず、前もってスケジュールを調整したり、前工程のスケジュール変更に対応して自工程のスケジュールを変更することが容易にはできないので、効率的な作業を行うことが難かしい。
【0008】
また、各業者において作業の進捗状況を確認する場合、業者毎に作業を管理する単位が異なるので、たとえ他業者の進捗状況を得られたとしても、求める単位で全体の進捗状況を確認するためには、他業者が作成した書類と自ら作成した書類とを照合して管理する単位の読み替えを行わなければならず、敏速に全体の進捗状況を得ることは難しい。
【0009】
例えば、荷主においては荷物単位で進捗状況を確認する必要があるが、各荷主が自らの全I/VについてI/V単位で作業の進捗状況を管理し、各海貨業者と各陸運業者とが自社扱いの全コンテナについてコンテナ単位で進捗状況を管理し、各船会社が自社の全船について船単位で進捗状況を管理しているので、ある荷主が敏速に目的とする荷物の全体の進捗状況を得ることは非常に難しい。
【0010】
本発明は、各業者において、前工程の業者の処理が完結しなくても、他業者の進捗状況が得られ、前もってスケジュールを調整したり、前工程のスケジュール変更に対応して自工程のスケジュールを変更することができ、効率的な作業を行うことを容易にするコンテナ輸出入管理装置、プログラム及び方法を提供することを目的とする。
【0011】
【課題を解決するための手段】
上記目的を達成するために、本発明に係るコンテナ輸出入管理装置は、港湾運輸におけるコンテナ輸出入の作業を管理するコンテナ輸出入管理装置であって、過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段と、荷主から1個又は複数のコンテナ毎に荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、記録手段により記録された実績データから受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し抽出した実績データに基づいて予定作業日程表を生成する作業日程表生成手段と、荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に生成された予定作業日程表を提示させるべく当該予定作業日程表のデータを送信する提示手段とを備え、前記受け付け手段は、さらに、前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから輸出入作業の進捗状況のデータ入力を受け付け、前記提示手段は、さらに、前記各端末に予定作業日程表のデータを送信する際に進捗状況を予定作業日程表と共に提示させるべく当該進捗状況のデータを予定作業日程表のデータと関連付けて送付することを特徴とする。
【0012】
上記目的を達成するために、港湾運輸におけるコンテナ輸出入の作業を管理するコンピュータを用いて構築されたコンテナ輸出入管理装置において、前記コンテナ輸出入管理装置は過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、本発明に係るコンテナ輸出入管理プログラムは、前記コンピュータを、荷主から1個又は複数のコンテナ毎に荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、記録手段により記録された実績データから受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し抽出した実績データに基づいて予定作業日程表を生成する作業日程表生成手段と、荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に生成された予定作業日程表を提示させるべく当該予定作業日程表のデータを送信する提示手段として機能させ、前記受け付け手段は、さらに、前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから輸出入作業の進捗状況のデータ入力を受け付け、前記提示手段は、さらに、前記各端末に予定作業日程表のデータを送信する際に進捗状況を予定作業日程表と共に提示させるべく当該進捗状況のデータを予定作業日程表のデータと関連付けて送付することを特徴とする。
【0013】
上記目的を達成するために、本発明に係るコンテナ輸出入管理方法は、港湾運輸におけるコンテナ輸出入の作業を管理するコンテナ輸出入管理装置におけるコンテナ輸出入管理方法であって、前記コンテナ輸出入管理装置は、過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、当該コンテナ輸出入管理方法は、荷主から1個又は複数のコンテナ毎に荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、記録手段により記録された実績データから受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し抽出した実績データに基づいて予定作業日程表を生成する作業日程表生成手段と、荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に生成された予定作業日程表を提示させるべく当該予定作業日程表のデータを送信する提示手段とを含み、前記受け付け手段は、さらに、前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから輸出入作業の進捗状況のデータ入力を受け付け、前記提示手段は、さらに、前記各端末に予定作業日程表のデータを送信する際に進捗状況を予定作業日程表と共に提示させるべく当該進捗状況のデータを予定作業日程表のデータと関連付けて送付することを特徴とする。
【0014】
これらによって、荷主、海貨業者、及び、船会社のそれぞれが、作業開始直後から、それぞれの元に設置された端末を用いて予定作業日程表を参照することができ、また、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれが進捗状況を入力することにより、予定作業日程表と共に進捗状況を参照することができる。
【0015】
従って、各業者において、前工程の業者の処理が完結しなくても、他業者の進捗状況が得られ、前もってスケジュールを調整したり、前工程のスケジュール変更に対応して自工程のスケジュールを変更することができ、効率的な作業を行うことが容易となる。
【0016】
【発明の実施の形態】
<概要>
本発明の実施の形態に係るコンテナ輸出入管理システムは、過去の輸出入作業の実績データを記録し、荷主から輸出入作業に関する情報の入力を受け付けて実績データを元に予定作業日程表(以下「スケジュール表」)を生成し、荷主、海貨業者、コンテナヤードオペレータ(CYO)、船会社のそれぞれにスケジュール表を提示する。
【0017】
さらに、このコンテナ輸出入管理システムは、荷主、海貨業者、CYO、船会社のそれぞれから輸出入作業の進捗状況や詳細情報の入力を受け付け、それぞれに進捗状況や詳細情報を提示し、作業現場から必要な情報の入力を受け付けて荷主からの情報と合わせて受取証を自動作成し、また、受け付けた作業の進捗状況や詳細情報等に応じてスケジュール表を変更する。
【0018】
<構成>
図1は、本発明の実施の形態に係るコンテナ輸出入管理システムの概略を示す図である。
図1に示すように、コンテナ輸出入管理システムは、共有装置10、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、船会社用端末60、携帯入力端末70、及び、通信回線80からなる。
【0019】
共有装置10は、例えばハードディスクを備えるWEBサーバ及びメールサーバであり、記録部11、受け付け部12、作業日程生成部13、作業日程変更部14、登録部15、B/L作成部16、スケジュール表作成部17、提示部18、及び、スケジュール表変更部19からなる。
記録部11は、例えばハードディスクであり過去の輸出入作業の荷物の概略品名、実績作業日程、荷物の数量を含む実績データ、過去のスケジュール表のデータ、及び、船会社から送られてくる最新の配船スケジュールを記録している。
【0020】
図2は、記録部11に記録されている実績データの一例を示す図である。
ここで図2に示す各作業項目の先頭の記号は、左側から順に、数字が作業順位を表し、ローマ字が同時並列処理が可能であることを表している。
例えば、「作業順位(2)」の作業項目は「作業順位(1)」の作業項目を処理した後でないと処理できないことを表し(作業順位(1)〜(5)同様)、「作業順位(6A1)」及び「作業順位(6B1)」の作業項目は「作業順位(5)」の作業項目の処理以降に同時並列処理が可能であることを表し、「作業順位(6A2)」の作業項目は「作業順位(6A1)」を処理した後でないと処理できないことを表し(作業順位(6B1)〜(6B5)同様)、「作業順位(6B6A1)」及び「作業順位(6B6B1)」の作業項目は「作業順位(6B5)」の作業項目の処理以降に同時並列処理が可能であることを表し、「作業順位(6B6A2)」の作業項目は「作業順位(6B6A1)」の作業項目を処理した後でないと処理できないことを表し、「作業順位(6A3/B6B2A)」、「作業順位(6A3/B6B2B)」、及び「作業順位(6A3/B6B2C)」の作業項目は「作業順位(6A2)」と「作業順位(6B6B1)」の両方の作業項目の処理以降に同時並列処理が可能であることを表している(以下同様)。
【0021】
受け付け部12は、通信回線80を介して、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、船会社用端末60、及び、携帯入力端末70から各種情報の入力を受け付ける。
例えば、受け付け部12は、荷主用端末20から通信回線80を介して、輸出作業の場合には、従来のI/VとP/Lの記載内容と同等な、1個又は複数のコンテナ毎に荷物の概略品名及び数量を含むインボイス&パッキングリストデータ(I/V&P/Lデータ)、及び、従来のS/Iの記載内容と同等なシッピングインストラクションデータ(S/Iデータ)の入力を受け付け、輸入作業の場合には、従来のB/LとA/Nの記載内容と同等な、ビル オブ レィディング&アライバル ノーティスデータ(B/L&A/Nデータ)の入力を受を受け付ける。
【0022】
図3は、受け付け部12が受け付けるインボイス&パッキングリストデータの一例を示す図である。
図4は、受け付け部12が受け付けるシッピングインストラクションデータの一例を示す図である。
また受け付け部12は、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、及び、船会社用端末60から、スケジュール表のデータの送信要求、輸出入作業の進捗状況や詳細情報の入力、予定作業日程の変更指示、及び、スケジュール表の変更指示等を受け付ける。
【0023】
また受け付け部12は、携帯入力端末70から、コンテナ番号とシール番号の入力を受け付け、船会社用端末60からB/L作成の指示を受け付ける。
作業日程生成部13は、記録部11に記録された実績データから、受け付け部12により受け付けられたインボイス&パッキングリストデータ、又は、ビル オブ レィディング&アライバル ノーティスデータに含まれる荷物の概略品名に対応する実績データを抽出し、抽出した実績データの実績作業日程に、配船スケジュールと受け付けられたインボイス&パッキングリストデータ、又は、ビルオブ レィディング&アライバル ノーティスデータに含まれる数量とによる補正を施して、予定作業日程を生成し、記録部11に記録する。
【0024】
例えば、図3に示すようなインボイス&パッキングリストデータ201に含まれる荷物の概略品名「洗濯機」に対応する図2に示す実績データ101を抽出し、実績データ101の示す数が1000個、インボイス&パッキングリストデータ201に含まれる数が2倍の2000個なので、実績データ101の実績作業日程の実作業に関する部分の経過日数を2倍にし、その他の部分は実績データと同じ経過日数を用いて予定作業日程を生成する。
【0025】
ここで経過日数とは、作業項目毎に、自身の作業項目の実績日から直前の作業項目の実績日を差し引いた日数である。また、直前の作業項目が複数ある場合には一番遅い実績日を用いて計算する。また、対応する実績データが記録部11に存在しない場合には、予め記録部11に初期設定値を記録しておきこれを用いるか、あるいは、使用者に入力を促して初期設定値を入力させる。
【0026】
また、ここで実作業に関する部分とは、例えば図2中の「(6B5)空コンテナ着(CY→荷主)」、「(6B6A2)バン積め終了(荷主)」、「(8)実コンテナ着(荷主→CY)」、及び、「(15)コンテナ積込み終了(CY)」であり、「(6B5)空コンテナ着(CY→荷主)」の経過日数が2日から4日に、「(6B6A2)バン積め終了(荷主)」の経過日数が3日から6日に、「(8)実コンテナ着(荷主→CY)」の経過日数が2日から4日になる。
【0027】
作業日程変更部14は、受け付け部12が、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、及び、船会社用端末60から予定作業日程の変更指示を受け付けると、この変更指示に従って、記録部11に記録された予定作業日程を変更する。
また作業日程変更部14は、一部の作業項目が人為的に変更されたり、受け付けられた進捗状況が予定と異なっていた場合には、それ以降の作業日程を生成した時と同様の手順で修正する。
【0028】
登録部15は、受け付け部12が、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、及び、船会社用端末60から、シッピングインストラクションデータ、又は、進捗状況や詳細情報等の各種のデータや情報の入力を受け付けると、記録部11に記録された予定作業日程に関連付けて、受け付けた各種のデータや情報を登録する。
【0029】
図5は、作業日程生成部13により生成され、登録部15により進捗状況が登録された予定作業日程の一例を示す図である。
図5に示す予定作業日程は、処理開始の時期が図2に示す実績データ101と較べて丁度1ヶ月遅れであり、以降の予定は、実作業に関する部分の経過日数が2倍になっている事により数日のズレが生じている他は、おおよそ1ヶ月遅れである。
【0030】
B/L作成部16は、受け付け部12が船会社用端末60からB/L作成の指示を受けると、受け付け部12が携帯入力端末70から受け付けたコンテナ番号、及び、シール番号と、受け付け部12が荷主用端末20から受け付けたインボイス&パッキングリストデータ、及び、シッピングインストラクションデータとに基づいて、これらのデータが記載されたB/Lを作成し、B/Lを船会社用端末60へ出力し、B/Lの写しを荷主用端末20へ出力する。船会社用端末60へ出力されたB/Lは、船会社の社印が押される等によりその効力を得て、現物が荷主へ届けられる。
【0031】
図6は、B/L作成部16により生成されるB/Lの記載事項を示す図である。
スケジュール表作成部17は、記録部11に記録された過去のスケジュール表のデータの予定日及び実績日を、記録部11に記録された予定作業日程中の予定日及び実績日と入れ替えることにより、スケジュール表を生成してそのデータを記録部11に記録する。
【0032】
提示部18は、受け付け部12が、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、及び、船会社用端末60からスケジュール表のデータの送信要求を受け付けると、提示要求を出力した端末に、スケジュール表作成部17により生成されたスケジュール表のデータを送信して、当該端末にスケジュール表を提示させる。
【0033】
スケジュール表変更部19は、作業日程変更部14により予定作業日程が変更及び修正された場合や、登録部15により予定作業日程に各種のデータや情報が登録された場合に、記録部11に記録されたスケジュール表のデータを、生成した時と同様の手順で修正する。
また、スケジュール表変更部19は、受け付け部12が、荷主用端末20、海貨業者用端末30、CYO用端末40、運送業者用端末50、及び、船会社用端末60からスケジュール表の変更指示を受け付けると、受け付けた変更指示に従ってスケジュール表を変更する。
【0034】
例えば、スケジュール表変更部19は、提示部18により端末に提示させたスケジュール表の任意の場所に要注意マーク「※」や文字が記入されたり、記入内容が変更されたスケジュール表のデータを変更指示として受信し、記録部11に記録されたスケジュール表のデータと入れ替えることにより、スケジュール表を変更する。
【0035】
荷主用端末20は、例えばWEBブラウザであり、荷主の元に設置され通信回線80を介して共有装置10と接続されるものであり、荷主からインボイス&パッキングリストデータとシッピングインストラクションデータの入力、ビル オブ レィディング&アライバル ノーティスデータの入力、予定作業日程の変更指示、及び、スケジュール表の変更指示等を受けて共有装置10へ送信し、また、荷主からこの荷主のスケジュール表の提示要求を受けて、共有装置10へ所定I/Vに関係するスケジュール表のデータの送信要求を送信してこのデータを受信し、スケジュール表を荷主に提示する。
【0036】
図7は、荷主用端末20に提示される輸出作業のスケジュール表の一例を示す図である。
図7に示すスケジュール表には、図5に示した予定作業日程の記載順に各作業項目が並べられ、各作業項目毎に予定日及び実績日が記載されており、次に処理すべき作業項目にチェックポイントマーク301が付され、また、要注意マーク302、303と共に要注意事項が記入されている。
【0037】
また図8は、荷主用端末20に提示される輸入作業のスケジュール表の一例を示す図である。
なお、各作業項目毎にそれぞれの処理に関する詳細データを記録しておき、スケジュール表上の各理項目の位置に、その処理に関する詳細データを表示する画面を開くリンクを張っておいてもよい。
【0038】
このようにすれば、閲覧者がスケジュール表上の所望の作業項目の記載位置をマウスでクリックする等して作業項目の1つを選択すると、その処理に関する詳細データを表示する画面が開き、閲覧者は容易に所望の作業項目の詳細データを閲覧することができる。
また、荷主が、マークを付けた作業項目の情報だけをリストアップしたり、次に処理すべき作業項目や予定日を過ぎても実施されていない作業項目の情報だけをリストアップしてもよい。
【0039】
このようにすれば、荷主毎に複数のスケジュール表中の次に処理すべき作業項目の情報や実施が遅れている作業項目がリストアップされるので、各荷主が作業順序を容易に把握することができる。
海貨業者用端末30は、例えばWEBブラウザであり、海貨業者や海貨・通関業者の元に設置され通信回線80を介して共有装置10と接続されるものであり、海貨業者から予定作業日程の変更指示、及び、スケジュール表の変更指示等を受けて共有装置10へ送信し、また、海貨業者や海貨・通関業者から自社扱いの作業(発注単位)に関係するスケジュール表の提示要求を受けて、共有装置10へスケジュール表のデータの送信要求を送信してこれを受信し、スケジュール表を海貨業者や海貨・通関業者に提示する。
【0040】
なお、海貨業者や海貨・通関業者が、自社扱いの全作業の中から、マークを付けた作業項目の情報だけをリストアップしたり、次に処理すべき作業項目や予定日を過ぎても実施されていない作業項目の情報だけをリストアップしてもよい。このようにすれば、海貨業者や海貨・通関業者毎に複数のスケジュール表中の次に処理すべき作業項目の情報や実施が遅れている作業項目がリストアップされるので、各海貨業者や海貨・通関業者が作業順序を容易に把握することができる。
【0041】
CYO用端末40は、例えばWEBブラウザであり、コンテナヤードオペレータの元に設置され通信回線80を介して共有装置10と接続されるものであり、コンテナヤードオペレータから予定作業日程の変更指示、及び、スケジュール表の変更指示等を受けて、共有装置10へ送信し、またコンテナヤードオペレータから自社扱いの作業(発注単位)に関係するスケジュール表の提示要求を受けて共有装置10へスケジュール表のデータの送信要求を送信してこれを受信し、スケジュール表をコンテナヤードオペレータに提示する。
【0042】
なお、コンテナヤードオペレータが、自社扱いの全作業の中から、マークを付けた作業項目の情報だけをリストアップしたり、次に処理すべき作業項目や予定日を過ぎても実施されていない作業項目の情報だけをリストアップしてもよい。このようにすれば、コンテナヤードオペレータ毎に複数のスケジュール表中の次に処理すべき作業項目の情報や実施が遅れている作業項目がリストアップされるので、各コンテナヤードオペレータが作業順序を容易に把握することができる。
【0043】
運送業者用端末50は、例えばWEBブラウザであり、運送業者の元に設置され通信回線80を介して共有装置10と接続されるものであり、運送業者から予定作業日程の変更指示、及び、スケジュール表の提示要求を受けて共有装置10へスケジュール表のデータの送信要求を送信してこれを受信し、スケジュール表を運送業者に提示する。
【0044】
なお、運送業者が、自社扱いの全作業の中から、マークを付けた作業項目の情報だけをリストアップしたり、次に処理すべき作業項目や予定日を過ぎても実施されていない作業項目の情報だけをリストアップしてもよい。
このようにすれば、運送業者毎に複数のスケジュール表中の次に処理すべき作業項目の情報や実施が遅れている作業項目がリストアップされるので、各運送業者が作業順序を容易に把握することができる。
【0045】
また、運送業者用端末50は、例えば情報通信機能を備えた携帯電話であり、その表示画面に、コンテナヤードへの立ち入り許可の為の情報を示す2次元バーコードを表示する機能を備え、これをトラック運転手が携帯し、CYO用端末40は、この2次元バーコードを照合する機能を備えてもよい。
現在、トラック運転手が、輸入作業において空コンテナをコンテナヤードから搬出する時や実入りコンテナをコンテナヤードへ搬入する時、及び、輸入作業において実入りコンテナをコンテナヤードから搬出する時には、事前に海貨業者や運送業者が準備した書面を現場でCYOへ提示又は提出することによって、コンテナヤードへの立ち入りが許可されている。その為に、事前に海貨業者や運送業者とCYOとの間で書類のやり取りを行い書面を準備する手間や、トラック運転手が海貨業者や運送業者の元へ書面を取りに行く手間がかかり、また、CYOでは現場でトラック運転手から提示された書面をその場で目視検査しているので、作業が繁雑であり、正確さにも欠けるという問題点がある。
【0046】
そこで、事前に海貨業者や運送業者とCYOとの間で行うやり取りを、本発明の実施の形態に係るコンテナ輸出入管理システムにおいて行い、トラック運転手が携帯する端末に、コンテナヤードへの立ち入り許可の為の情報を送信してこの情報を示す2次元バーコードを表示し、CYO用端末40がこの2次元バーコードをコンテナヤードの出入口に設置した2次元バーコードリーダで読み取って照合することにより、上記の問題点を解決することができる。
【0047】
なお、ここでコンテナヤードへの立ち入り許可の為の情報を、トラック運転手が携帯する運送業者用端末50からCYO用端末40へ伝送する為に、2次元バーコードを用いる例を説明したが、例えば、ブルートゥース等の近距離無線通信や、赤外線通信、超音波通信等の他の非接触伝送を用いてもよいし、USB接続等による接触伝送を用いてもよいし、メモリカード等の記録媒体を用いてもよい。
【0048】
船会社用端末60は、例えばWEBブラウザであり、船会社の元に設置され通信回線80を介して共有装置10と接続されるものであり、船会社や船会社毎に決まっているコンテナ荷役会社から予定作業日程の変更指示、及び、スケジュール表の変更指示等を受けて共有装置10へ送信し、また、船会社やコンテナ荷役会社からこの船会社の船に関係するスケジュール表の提示要求を受けて共有装置10へスケジュール表のデータの送信要求を送信してこれを受信し、スケジュール表を船会社やコンテナ荷役会社に提示する。
【0049】
なお、船会社が、自社の船に関係する全作業の中から、マークを付けた作業項目の情報だけをリストアップしたり、次に処理すべき作業項目や予定日を過ぎても実施されていない作業項目の情報だけをリストアップしてもよい。
このようにすれば、船会社毎に複数のスケジュール表中の次に処理すべき作業項目の情報や実施が遅れている作業項目がリストアップされるので、各船会社が作業順序を容易に把握することができる。
【0050】
携帯入力端末70は、入力機能付きの携帯電話やバーコードリーダを備える専用の携帯通信機器等であり、コンテナのバン積め場所又はコンテナ運送において、コンテナ荷役会社、又は、運送業者の現場作業者により、入力対象のコンテナに記載されたコンテナ番号とシール番号の入力が行なわれる。例えば、現場作業者は携帯入力端末70の備えるバーコードリーダで、コンテナに貼付されたバーコードを読み取ることによってコンテナ番号とシール番号の入力を行う。
【0051】
なお、携帯入力端末70は、一般の携帯電話や通信機能付きPDA等を用いてもよいが、このような場合には、コンテナ番号とシール番号を送信する際に、暗号化したり情報に冗長性を持たせてチェックする等により、情報の機密性及び正当性を確保する手段を備える事が望ましい。
また、携帯入力端末70の代わりに、通常のWEBブラウザのような通常の端末を用いてよい。
【0052】
通信回線80は、専用電話回線、イントラネット、インターネット等の通信用の回線である。
なお、各端末において、各業者毎に関係するスケジュール表だけを参照させるためには、例えば、受け付け部12が、荷主用端末20から、インボイス&パッキングリストデータとシッピングインストラクションデータの入力、又は、ビルオブ レィディング&アライバル ノーティスデータの入力を受け付ける際に、荷主に対応する荷主識別子、荷主が指定する海貨業者に対応する海貨業者識別子、及び、荷主が指定する船会社に対応する船会社識別子を受け付け、作業日程生成部13が、生成した予定作業日程毎に、受け付け部12により受け付けられた荷主識別子、海貨業者識別子、及び、船会社識別子を添付し、また、受け付け部12が、海貨業者用端末30から、海貨業者が指定する運送会社に対応する運送会社識別子の入力を受け付け、作業日程生成部13が、さらに予定作業日程毎に、運送会社識別子を添付し、また、受け付け部12が、船会社用端末60から、船会社が指定するコンテナヤードオペレータに対応するコンテナヤードオペレータ識別子の入力を受け付け、作業日程生成部13が、さらに予定作業日程毎に、コンテナヤードオペレータ識別子を添付し、提示部18が、荷主毎に当該荷主に対応する荷主識別子が添付されたスケジュール表のデータのみを送信し、海貨業者毎に当該海貨業者に対応する海貨業者識別子が添付されたスケジュール表予定作業日程表のデータのみを送信し、運送会社毎に当該運送会社に対応する運送会社が添付されたスケジュール表のデータのみを送信し、コンテナヤードオペレータ毎に当該コンテナヤードオペレータに対応するコンテナヤードオペレータ識別子が添付されたスケジュール表のデータのみを送信し、船会社毎に当該船会社に対応する船会社識別子が添付されたスケジュール表のデータのみを送信する。
【0053】
<動作>
図9は、本発明の実施の形態に係るコンテナ輸出入管理システムにおける共有装置10の輸出動作の手順を示す図である。
以下に、共有装置10の輸出動作の手順について説明する。
(1)受け付け部12が、各端末からの入力を待つ(ステップS1)。
【0054】
(2)各端末から入力があったら、インボイス&パッキングリストデータの入力であるか否かを判断する(ステップS2)。
(3)インボイス&パッキングリストデータの入力である場合には、作業日程生成部13が、記録部11に記録された実績データから、当該インボイス&パッキングリストデータに含まれる荷物の概略品名に対応する実績データを抽出する(ステップS3)。
【0055】
(4)作業日程生成部13が、抽出した実績データの実績作業日程に、当該インボイス&パッキングリストデータに含まれる数量による補正を施して予定作業日程を生成し、続いてスケジュール表作成部17が、記録部11に記録された過去のスケジュール表のデータの予定日及び実績日を予定作業日程中の予定日及び実績日と入れ替えることによりスケジュール表を生成する(ステップS4)。
【0056】
(5)インボイス&パッキングリストデータの入力でない場合には、スケジュール表のデータの送信要求であるか否かを判断する(ステップS5)。
(6)スケジュール表のデータの送信要求である場合には、提示部18が、スケジュール表作成部17により生成されたスケジュール表、又は、スケジュール表変更部19により修正されたスケジュール表のデータを返送して送信要求を出力した端末にスケジュール表を提示させる(ステップS6)。
【0057】
(7)スケジュール表のデータの送信要求でない場合には、シッピングインストラクションデータ、作業の進捗状況や詳細情報の入力、及び、コンテナ番号とシール番号の入力であるか否かを判断する(ステップS7)。
(8)シッピングインストラクションデータ、作業の進捗状況や詳細情報の入力、及び、コンテナ番号とシール番号の入力である場合には、登録部15が、記録部11に記録された予定作業日程に関連付けて、受け付けたデータや情報を登録し、スケジュール表変更部19が、この登録に基づいてスケジュール表のデータを修正する(ステップS8)。
【0058】
(9)シッピングインストラクションデータ、作業の進捗状況や詳細情報の入力、コンテナ番号とシール番号の入力でない場合には、予定作業日程の変更指示であるか否かを判断する(ステップS9)。
(10)予定作業日程の変更指示である場合には、作業日程変更部14が、この変更指示に従って予定作業日程を変更し、スケジュール表変更部19が、予定作業日程を変更にともないスケジュール表のデータを修正する(ステップS10)。
【0059】
(11)予定作業日程の変更指示でない場合には、スケジュール表の変更指示であるか否かを判断する(ステップS11)。
(12)スケジュール表の変更指示である場合には、スケジュール表変更部19が、受け付けた変更指示に従ってスケジュール表を変更する(ステップS12)。
【0060】
(13)スケジュール表の変更指示でない場合には、B/L作成の指示であるか否かを判断する(ステップS13)。
(14)B/L作成の指示である場合には、B/L作成部16が、インボイス&パッキングリストデータ、シッピングインストラクションデータ、コンテナ番号、及び、シール番号に基づいて、これらのデータが記載されたB/Lを作成する(ステップS14)。
【0061】
(15)以上の何れの入力でもない場合、及び、それぞれの処理を済ませた場合には、各端末からの入力待ちに戻る。
図10は、本発明の実施の形態に係るコンテナ輸出入管理システムにおける共有装置10の輸入動作の手順を示す図である。
以下に、共有装置10の輸入動作の手順について説明する。
【0062】
なお、以下の輸入動作の手順の説明において、図9に示した輸出動作の手順と同様のステップには同一番号を付し、その説明を省略する。
(1)輸出動作の手順(1)と同じ(ステップS1)。
(2)各端末から入力があったら、B/L&A/Nの入力であるか否かを判断する(ステップS21)。
【0063】
(3)B/L&A/Nの入力である場合には、輸出動作の手順(3)と同じ(ステップS3)。
(4)輸出動作の手順(4)と同じ(ステップS4)。
(5)B/L&A/Nの入力でない場合には、輸出動作の手順(5)と同じ(ステップS5)。
【0064】
(6)輸出動作の手順(6)と同じ(ステップS6)。
(7)スケジュール表のデータの送信要求でない場合には、作業の進捗状況や詳細情報の入力であるか否かを判断する(ステップS22)。
(8)進捗状況や詳細情報の入力である場合には、輸出動作の手順(8)と同じ(ステップS8)。
【0065】
(9)作業の進捗状況や詳細情報の入力でない場合には、輸出動作の手順(9)と同じ(ステップS9)。
(10)輸出動作の手順(10)と同じ(ステップS10)。
(11)輸出動作の手順(11)と同じ(ステップS11)。
(12)輸出動作の手順(12)と同じ(ステップS12)。
【0066】
(13)以上の何れの入力でもない場合、及び、それぞれの処理を済ませた場合には、各端末からの入力待ちに戻る。
以上のように、本発明の実施の形態によれば、各業者において、前工程の業者の処理が完結しなくても、他業者の進捗状況や詳細情報が得られ、前もってスケジュールを調整したり、前工程のスケジュール変更に対応して自工程のスケジュールを変更することができ、効率的な作業を行うことが容易である。
【0067】
なお、コンピュータに本実施の形態のような動作を実行させることができるプログラムがコンピュータ読み取り可能な記録媒体に記録され、この記録媒体が流通し取り引きの対象となりうる。また、当該プログラムは、例えばネットワーク等を介して流通し、取り引きの対象となりうる。
ここでコンピュータ読み取り可能な記録媒体とは、例えば、フレキシブルディスク、CD、MO、DVD、メモリカード等の着脱可能な記録媒体、及び、ハードディスク、半導体メモリ等の固定記録媒体等であり、特に限定されるものではない。
【0068】
【発明の効果】
本発明に係るコンテナ輸出入管理装置は、港湾運輸におけるコンテナ輸出入の作業を管理するコンテナ輸出入管理装置におけるコンテナ輸出入管理方法であって、前記コンテナ輸出入管理装置は、過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、当該コンテナ輸出入管理方法は、荷主から1個又は複数のコンテナ毎に荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、記録手段により記録された実績データから受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し抽出した実績データに基づいて予定作業日程表を生成する作業日程表生成手段と、荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に生成された予定作業日程表を提示させるべく当該予定作業日程表のデータを送信する提示手段とを含み、前記受け付け手段は、さらに、前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから輸出入作業の進捗状況のデータ入力を受け付け、前記提示手段は、さらに、前記各端末に予定作業日程表のデータを送信する際に進捗状況を予定作業日程表と共に提示させるべく当該進捗状況のデータを予定作業日程表のデータと関連付けて送付することを特徴とする。
【0069】
また、港湾運輸におけるコンテナ輸出入の作業を管理するコンピュータを用いて構築されたコンテナ輸出入管理装置において、前記コンテナ輸出入管理装置は過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、本発明に係るコンテナ輸出入管理プログラムは、前記コンピュータを、荷主から1個又は複数のコンテナ毎に荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、記録手段により記録された実績データから受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し抽出した実績データに基づいて予定作業日程表を生成する作業日程表生成手段と、荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に生成された予定作業日程表を提示させるべく当該予定作業日程表のデータを送信する提示手段として機能させ、前記受け付け手段は、さらに、前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから輸出入作業の進捗状況のデータ入力を受け付け、前記提示手段は、さらに、前記各端末に予定作業日程表のデータを送信する際に進捗状況を予定作業日程表と共に提示させるべく当該進捗状況のデータを予定作業日程表のデータと関連付けて送付することを特徴とする。
【0070】
また、本発明に係るコンテナ輸出入管理方法は、港湾運輸におけるコンテナ輸出入の作業を管理するコンテナ輸出入管理装置におけるコンテナ輸出入管理方法であって、前記コンテナ輸出入管理装置は、過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、当該コンテナ輸出入管理方法は、荷主から1個又は複数のコンテナ毎に荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、記録手段により記録された実績データから受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し抽出した実績データに基づいて予定作業日程表を生成する作業日程表生成手段と、荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に生成された予定作業日程表を提示させるべく当該予定作業日程表のデータを送信する提示手段とを含み、前記受け付け手段は、さらに、前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから輸出入作業の進捗状況のデータ入力を受け付け、前記提示手段は、さらに、前記各端末に予定作業日程表のデータを送信する際に進捗状況を予定作業日程表と共に提示させるべく当該進捗状況のデータを予定作業日程表のデータと関連付けて送付することを特徴とする。
【0071】
これらによって、荷主、海貨業者、及び、船会社のそれぞれが、作業開始直後から、それぞれの元に設置された端末を用いて予定作業日程表を参照することができ、また、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれが進捗状況を入力することにより、予定作業日程表と共に進捗状況を参照することができる。
【0072】
従って、各業者において、前工程の業者の処理が完結しなくても、他業者の進捗状況が得られ、前もってスケジュールを調整したり、前工程のスケジュール変更に対応して自工程のスケジュールを変更することができ、効率的な作業を行うことが容易となる。
また、コンテナ輸出入管理装置において、前記受け付け手段が入力を受け付ける作業情報は、荷主に対応する荷主識別子、荷主が指定する海貨業者に対応する海貨業者識別子、及び、荷主が指定する船会社に対応する船会社識別子を含み、前記作業日程表生成手段は生成した予定作業日程表毎に、受け付け手段により受け付けられた作業情報に含まれる荷主識別子、海貨業者識別子、及び、船会社識別子を添付し、前記提示手段は、荷主毎に当該荷主に対応する荷主識別子が添付された予定作業日程表のデータのみを送信し、海貨業者毎に当該海貨業者に対応する海貨業者識別子が添付された予定作業日程表のデータのみを送信し、船会社毎に当該船会社に対応する船会社識別子が添付された予定作業日程表のデータのみを送信することを特徴とすることもできる。
【0073】
これによって、各端末において、荷主、海貨業者、及び、船会社毎に、それぞれに関係するスケジュール表だけを参照させることができる。
また、コンテナ輸出入管理装置において、前記受け付け手段は、さらに、海貨業者から海貨業者が指定する運送会社に対応する運送会社識別子の入力を受け付け、前記作業日程表生成手段は生成した予定作業日程表毎に受け付け手段により受け付けられた運送会社識別子を添付し、前記提示手段は、さらに、運送会社の元に設置された端末に生成された予定作業日程表を提示させるべく運送会社毎に当該運送会社に対応する運送会社が添付された予定作業日程表のデータのみを送信し、前記受け付け手段は、さらに、前記運送会社の元に設置された端末により運送会社から輸出入作業における運送作業の進捗状況のデータ入力を受け付けることを特徴とすることもできる。
【0074】
これによって、さらに、運送会社の元に設置された端末において、運送会社毎に、それぞれに関係するスケジュール表だけを参照させることができる。
また、コンテナ輸出入管理装置において、前記記録手段が記録している実績データは荷物の数量を含み、前記受け付け手段が入力を受け付ける作業情報は荷物の数量を含み、前記作業日程表生成手段は抽出した実績データの実績作業日程に受け付けられた作業情報に含まれる数量による補正を施して予定作業日程表を生成することを特徴とすることもできる。
【0075】
これによって、数量による補正を施して予定作業日程表を生成することができる。
従って、より正確に予定作業日程表を生成することができる。
また、コンテナ輸出入管理装置において、前記受け付け手段は、さらに、前記各端末から前記予定作業日程を変更する変更指示を受け付け、前記コンテナ輸出入管理装置は、さらに、受け付けられた変更指示に従って前記予定作業日程を変更する作業日程変更手段を備えることを特徴とすることもできる。
【0076】
これによって、荷主、海貨業者、及び、船会社のそれぞれが、それぞれの元に設置された端末を用いて予定作業日程を変更することができる。
従って、各業者において、前工程の業者の処理が完結しなくても、他業者の進捗状況や自己都合に応じて、前もって自工程のスケジュールを変更することができ、効率的な作業を行うことが容易となる。
【0077】
また、コンテナ輸出入管理装置において、前記実績データは、複数の作業項目、作業項目毎の実績日、及び、作業項目毎の処理の作業順位を含み、前記受け付け手段が受け付ける変更指示は、所定の作業項目の予定日を変更するか、又は、所定の作業項目において予定日と異なる日付の実績日を登録するものであり、前記作業日程変更手段は、変更指示がなされた所定の作業項目よりも作業順位が低い作業項目の全ての予定日を作業順位が高い順に変更指示による変更日数分だけ変更することを特徴とすることもできる。
【0078】
これによって、予定日の変更、又は、予定通り実績されなかった場合に、以後の予定日を変更日数分だけ変更することができる。
従って、敏速にスケジュールを変更することができ、効率的な作業を行うことが容易となる。
また、コンテナ輸出入管理装置において、前記受け付け手段は、さらに、入力端末からの、コンテナ番号の入力、及び、シール番号の入力、及び、コンテナへのバン積め日時情報を受け付け、前記コンテナ輸出入管理装置は、さらに、受け付けられた作業情報、コンテナ番号、シール番号、及び、コンテナへのバン積め日時情報に基づいてこれらの情報を記載に含むコンテナ受取証を作成する受取証作成手段を備え、前記提示手段は、さらに、コンテナ番号、シール番号、及び、コンテナへのバン積め日時情報を予定作業日程表のデータと関連付けて送付することを特徴とすることもできる。
【0079】
これによって、携帯入力端末から、コンテナ番号、及び、シール番号の入力を受け付けることができ、これらに基づいて、コンテナ受取証を自動作成することができる。
従って、コンテナ受取証を容易に作成できる。
また、コンテナ輸出入管理装置において、前記記録手段は、さらに、作業項目毎にそれぞれの処理に関する詳細データを記録し、前記受け付け手段は、さらに、前記各端末のいずれかから作業項目の指定を受け付け、前記提示手段は、さらに、指定された作業項目の詳細データを前記記録手段から読み出して返信することを特徴とすることもできる。
【0080】
これによって、指定された作業項目の詳細データを返信することができる。
従って、荷主、海貨業者、及び、船会社のそれぞれが、それぞれの元に設置された端末を用いて、作業項目の詳細データを閲覧することができる。
また、前記コンテナ輸出入管理装置は、さらに、マークを付けられた作業項目、次に処理すべき作業項目、又は、予定日を過ぎても実施日が入力されていない作業項目のリストを生成するリスト生成手段を備え、前記提示手段は、さらに、前記各端末へリスト生成手段により生成されたリストをへ提示させるべく当該リストのデータを送信することを特徴とすることもできる。
【0081】
これによって、マークを付けられた作業項目、次に処理すべき作業項目、又は、予定日を過ぎても実施日が入力されていない作業項目のリストを生成して、そのデータを送信することができる。
従って、荷主、海貨業者、及び、船会社のそれぞれが、それぞれの元に設置された端末を用いて、注意を要する作業項目のリストを閲覧することができる。
【図面の簡単な説明】
【図1】本発明の実施の形態に係るコンテナ輸出入管理システムの概略を示す図である。
【図2】記録部11に記録されている実績データの一例を示す図である。
【図3】受け付け部12が受け付けるインボイス&パッキングリストデータの一例を示す図である。
【図4】受け付け部12が受け付けるシッピングインストラクションデータの一例を示す図である。
【図5】作業日程生成部13により生成され、登録部15により進捗状況が登録された予定作業日程の一例を示す図である。
【図6】B/L作成部16により生成されるB/Lの一例を示す図である。
【図7】荷主用端末20に提示されるスケジュール表を示す図である。
【図8】荷主用端末20に提示される輸入作業のスケジュール表の一例を示す図である。
【図9】本発明の実施の形態に係るコンテナ輸出入管理システムにおける共有装置10の輸出動作の手順を示す図である。
【図10】本発明の実施の形態に係るコンテナ輸出入管理システムにおける共有装置10の輸入動作の手順を示す図である。
【符号の説明】
10 共有装置
11 実績データ記録部
12 受け付け部
13 作業日程生成部
14 作業日程変更部
15 登録部
16 B/L作成部
17 スケジュール表作成部
18 提示部
19 スケジュール表変更部
20 荷主用端末
30 海貨業者用端末
40 CYO用端末
50 運送業者用端末
60 船会社用端末
70 携帯入力端末
80 通信回線[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a container import / export management device, a program, and a method for efficiently managing container import / export operations in port transportation.
[0002]
[Prior art]
At present, the majority of overseas trade in electrical appliances, electrical equipment and machinery is import / export of containers by liner.
A plurality of traders, such as a shipper, a sea freight trader, a land transport trader, and a shipping company, are involved in the work of importing and exporting containers, and the work is carried out by exchanging various documents between the traders.
[0003]
The following briefly describes the procedure for exporting containers.
First, each shipper has an invoice (Invoice: abbreviated “I / V”) corresponding to a bill of lading describing the details of the package, a packing list (Packing List: abbreviated “P / L”) describing the packing style, and various kinds of transportation information. A shipping instruction (Shipping Instruction: abbreviated as “S / I”) describing the above is prepared for each container or a plurality of containers, and is sent to a shipping company.
[0004]
Next, the forwarder receives the I / V, P / L, and S / L together with the cargo from each shipper, and, based on these documents, a dock receipt (Dock Receipt: abbreviation) describing various types of transportation information for each ship. "D / R") and send it to the shipping company along with the container.
Next, the shipping company receives the D / R together with the cargo from the forwarding agent and, based on this document, bills of billing (Bill of Lading: abbreviated “B / L”) or non-securities. Creates a receipt such as a Way Bill (abbreviated as “W / B”) per B / L for each container or containers and sends it to the shipper. To the recipient.
[0005]
The recipient obtains the B / L or W / B from the shipper in exchange for paying money, etc., and shows the legitimacy of the recipient by this document overseas and receives the container.
In the case of container import, the arrival date is determined by Arrival Notice (abbreviation "A / N") issued by the shipping company, and the importing shipper uses B / L and A / N as basic information, The freight company pays the fare to the shipping company, instructs customs clearance, unloads the container, transports the container, and returns the empty container.
[0006]
As described above, in the container import / export, each contractor prepares the document of the own process based on the document received from the contractor in the previous process and works based on this document.
[0007]
[Problems to be solved by the invention]
However, in the above-described sequential processing based on the document, the progress of another company cannot be obtained until the processing of the previous process is completed and the documents are received, so that the schedule can be adjusted in advance or the schedule of the previous process can be changed. Since it is not easy to change the schedule of the own process correspondingly, it is difficult to perform efficient work.
[0008]
Also, when checking the progress of work at each contractor, since the unit of work management is different for each contractor, even if the progress of other contractors is obtained, it is necessary to check the overall progress of the requested unit In this case, it is necessary to replace the unit managed by collating the document created by another company with the document created by itself, and it is difficult to quickly obtain the overall progress.
[0009]
For example, it is necessary for the shipper to check the progress of each luggage, but each shipper manages the progress of the work in I / V units for all its own I / Vs, and each shipper and each land carrier Manages the progress status of all containers handled by its own company on a container basis, and each shipping company manages the progress status of all its own ships on a ship basis. It is very difficult to get the situation.
[0010]
According to the present invention, the progress of another company can be obtained even if the process of the previous process is not completed in each company, the schedule can be adjusted in advance, or the schedule of the own process can be adjusted in response to the schedule change of the previous process. It is an object of the present invention to provide a container import / export management apparatus, a program, and a method, which can change the information and facilitate efficient work.
[0011]
[Means for Solving the Problems]
In order to achieve the above object, a container import / export management device according to the present invention is a container import / export management device that manages container import / export operations in port transportation, and includes types of past import / export luggage, and Recording means for recording actual data including actual work schedules, accepting means for accepting input of work information relating to import / export work including the type of package for each of one or more containers from a shipper, and recording means for recording A work schedule table generating means for extracting actual data corresponding to the type of package included in the work information received by the receiving means from the obtained actual data and generating a scheduled work schedule based on the extracted actual data; The date of the scheduled work schedule is presented so that the generated scheduled work schedule can be presented on the terminal installed at each of the forwarding agent and the shipping company. And a receiving unit for receiving the data input of the progress status of the import / export work from each of the shipper, the sea freight forwarder, the container yard operator, and the shipping company, The presenting means further transmits the data of the progress status in association with the data of the scheduled work schedule so as to present the progress together with the scheduled work schedule when transmitting the data of the scheduled work schedule to each terminal. It is characterized by the following.
[0012]
In order to achieve the above object, in a container import / export management device constructed using a computer that manages container import / export work in port transportation, the container import / export management device is a type of baggage of past import / export work, The container import / export management program according to the present invention includes a recording unit that records actual data including an actual work schedule. The computer exports and exports the computer including a type of package for each of one or more containers from the shipper. Receiving means for receiving input of work information relating to the incoming work, and extracting and outputting the result data corresponding to the type of package included in the work information received by the receiving means from the result data recorded by the recording means, based on the extracted result data A work schedule table generating means for generating a scheduled work schedule table, and each of a shipper, a forwarder, and a shipping company. Function as presentation means for transmitting the data of the scheduled work schedule to the terminal installed under the terminal, and the receiving means further includes a shipper, a sea, A cargo trader, a container yard operator, and a shipping company receive data input on the progress of import / export work, and the presenting unit further transmits the data on the scheduled work schedule to each terminal. The data of the progress is transmitted in association with the data of the scheduled work schedule so as to be presented together with the scheduled work schedule.
[0013]
In order to achieve the above object, a container import / export management method according to the present invention is a container import / export management method in a container import / export management device that manages container import / export operations in port transportation, The apparatus is provided with a recording means for recording the actual data including the type of the package in the past import / export work and the actual work schedule, and the container import / export management method is performed by the shipper for each of one or more containers. Receiving means for receiving input of work information relating to import / export work including the type of baggage, and extracting actual data corresponding to the type of baggage included in the work information received by the receiving means from the actual data recorded by the recording means; A work schedule table generating means for generating a scheduled work schedule table based on the extracted actual data, and a shipper, a sea forwarder, and a shipping company. Presenting means for transmitting data of the scheduled work schedule to cause the terminal installed at each of the terminals to present the generated scheduled work schedule, and the receiving means further comprises: The presenter receives the data input of the progress status of the import / export work from each of the shipper, the sea freight trader, the container yard operator, and the shipping company, and the presenting means further transmits the data of the scheduled work schedule to each of the terminals. In order to present the progress status together with the scheduled work schedule, the data of the progress is transmitted in association with the data of the scheduled work schedule.
[0014]
By these means, each of the shipper, sea freight forwarder and shipping company can refer to the scheduled work schedule using the terminal installed at the start of work immediately after the start of work, When each of the contractor, the container yard operator, and the shipping company inputs the progress status, the progress status can be referred to together with the scheduled work schedule.
[0015]
Therefore, even if the processing of the previous process is not completed, each company can obtain the progress status of the other company, adjust the schedule in advance, or change the schedule of the own process in response to the schedule change of the previous process And efficient work can be easily performed.
[0016]
BEST MODE FOR CARRYING OUT THE INVENTION
<Overview>
A container import / export management system according to an embodiment of the present invention records past import / export work data, receives input of information on import / export work from a shipper, and based on the actual data, a scheduled work schedule (hereinafter, referred to as a schedule table). A "schedule table") is generated, and the schedule table is presented to each of the shipper, the forwarder, the container yard operator (CYO), and the shipping company.
[0017]
In addition, the container import / export management system accepts progress and detailed information on import / export work from shippers, shipping agents, CYOs, and shipping companies, presents the progress and detailed information to each, And automatically creates a receipt together with the information from the shipper, and changes the schedule according to the progress of the received work and detailed information.
[0018]
<Structure>
FIG. 1 is a diagram schematically showing a container import / export management system according to an embodiment of the present invention.
As shown in FIG. 1, the container import / export management system includes a
[0019]
The
The
[0020]
FIG. 2 is a diagram illustrating an example of the result data recorded in the
Here, the symbols at the head of each work item shown in FIG. 2 indicate the work order in order from the left, and the Roman characters indicate that simultaneous parallel processing is possible.
For example, a work item of “work order (2)” indicates that it cannot be processed without processing the work item of “work order (1)” (similar to work orders (1) to (5)). The work items of “(6A1)” and “work order (6B1)” indicate that simultaneous parallel processing is possible after the processing of the work item of “work order (5)”, and the work of “work order (6A2)” The item indicates that processing can only be performed after processing “work order (6A1)” (similar to work order (6B1) to (6B5)), and work of “work order (6B6A1)” and “work order (6B6B1)” The item indicates that simultaneous parallel processing is possible after the processing of the work item of “work order (6B5)”, and the work item of “work order (6B6A2)” processes the work item of “work order (6B6A1)”. Can't be processed until after The work items of “work order (6A3 / B6B2A)”, “work order (6A3 / B6B2B)”, and “work order (6A3 / B6B2C)” are “work order (6A2)” and “work order (6A2)”. 6B6B1)), the simultaneous parallel processing is possible after the processing of both work items (the same applies hereinafter).
[0021]
The
For example, in the case of an export operation from the terminal 20 for a shipper via the
[0022]
FIG. 3 is a diagram illustrating an example of the invoice & packing list data received by the receiving
FIG. 4 is a diagram illustrating an example of shipping instruction data received by the receiving
The accepting
[0023]
In addition, the receiving
The work
[0024]
For example, the actual data 101 shown in FIG. 2 corresponding to the schematic item name “washing machine” of the luggage included in the invoice & packing list data 201 as shown in FIG. 3 is extracted, and the number of the actual data 101 is 1000, Since the number included in the invoice & packing list data 201 is doubled to 2000, the elapsed days of the part related to the actual work in the actual work schedule of the actual data 101 are doubled, and the other parts are the same elapsed days as the actual data. To generate a scheduled work schedule.
[0025]
Here, the number of elapsed days is the number of days obtained by subtracting the actual date of the immediately preceding work item from the actual date of the work item for each work item. When there are a plurality of immediately preceding work items, the calculation is performed using the latest actual date. If the corresponding performance data does not exist in the
[0026]
The parts related to actual work here are, for example, “(6B5) Empty container arrival (CY → shipper)”, “(6B6A2) Van loading end (shipper)”, “(8) Actual container arrival ( Shipper → CY) ”and“ (15) Container loading end (CY) ”, and the elapsed days of“ (6B5) Empty container arrival (CY → Shipper) ”are 2 to 4 days and“ (6B6A2) The elapsed days of "van loading end (shipper)" are from 3 to 6 days, and the elapsed days of "(8) Actual container arrival (shipper → CY)" are from 2 days to 4 days.
[0027]
The work
In addition, when some work items are artificially changed or the received progress status is different from the schedule, the work
[0028]
The
[0029]
FIG. 5 is a diagram illustrating an example of the scheduled work schedule generated by the
In the scheduled work schedule shown in FIG. 5, the processing start time is just one month later than the actual data 101 shown in FIG. 2, and in the subsequent schedules, the elapsed days of the part related to the actual work are doubled. It is about one month late, except for a few days shift.
[0030]
When the receiving
[0031]
FIG. 6 is a diagram illustrating the description items of the B / L generated by the B /
The schedule table creating unit 17 replaces the scheduled date and the actual date of the data of the past schedule table recorded in the
[0032]
In the presenting
[0033]
The schedule
In addition, the schedule
[0034]
For example, the schedule
[0035]
The
[0036]
FIG. 7 is a diagram illustrating an example of an export work schedule table presented to the
In the schedule table shown in FIG. 7, each work item is arranged in the order of description of the planned work schedule shown in FIG. 5, and the planned date and the actual date are described for each work item. , A
[0037]
FIG. 8 is a diagram showing an example of an import work schedule table presented to the
Note that detailed data on each process may be recorded for each work item, and a link for opening a screen for displaying detailed data on the process may be provided at the position of each process item on the schedule table.
[0038]
In this way, when the viewer selects one of the work items by, for example, clicking on the description position of the desired work item on the schedule table with a mouse, a screen for displaying detailed data on the processing is opened and the browsing is performed. The user can easily browse the detailed data of the desired work item.
In addition, the shipper may list only the information of the work items marked, or may list only the information of the work items to be processed next or the work items that have not been performed even after the scheduled date. .
[0039]
In this way, information on work items to be processed next and work items whose execution is delayed in a plurality of schedule tables are listed for each shipper, so that each shipper can easily grasp the work order. Can be.
The terminal 30 for a sea forwarder is, for example, a WEB browser, is installed at a forwarder of a forwarder or a forwarder / customs broker, and is connected to the shared
[0040]
In addition, the forwarding agent or marine forwarding / customs broker may list only the information of the marked work items from all the work handled by the company, or may list the work items to be processed next or the scheduled date. Alternatively, only information on work items that have not been implemented may be listed. In this way, information on work items to be processed next and work items whose execution is delayed in a plurality of schedule tables are listed for each sea freight forwarder or sea freight / customs broker. It is possible for traders, sea freight and customs brokers to easily grasp the work order.
[0041]
The
[0042]
In addition, the container yard operator lists only the information of the marked work items from all the works handled by the company, or the work items to be processed next and the work that has not been performed even after the scheduled date. Only the item information may be listed. In this way, information on work items to be processed next and work items whose execution is delayed in a plurality of schedule tables are listed for each container yard operator, so that each container yard operator can easily perform a work order. Can be grasped.
[0043]
The
[0044]
In addition, the carrier may list only the information of the marked work items from among all the works handled by the company, or the work items to be processed next or the work items that have not been implemented even after the scheduled date May be listed.
In this way, information on work items to be processed next and work items whose execution is delayed in a plurality of schedule tables are listed for each carrier, so that each carrier can easily grasp the work order. can do.
[0045]
Further, the
At present, truck operators need to check in advance when importing empty containers from the container yard, importing empty containers to the container yard, and importing empty containers from the container yard. By submitting or submitting a document prepared by the carrier or the carrier to the CYO on site, entry to the container yard is permitted. For this purpose, the time required to exchange documents between the forwarding agent or carrier and CYO in advance and prepare a document, and the time for the truck driver to get the document to the forwarding agent or carrier are reduced. In addition, CYO has a problem that the work presented by the truck driver is visually inspected on the spot at the site, and the work is complicated and lacks accuracy.
[0046]
Therefore, the exchange performed in advance between the CYO and the forwarding agent or the forwarder is performed in the container import / export management system according to the embodiment of the present invention, and the terminal carried by the truck driver enters the container yard. The information for permission is transmitted, a two-dimensional barcode indicating this information is displayed, and the
[0047]
Here, an example in which a two-dimensional barcode is used to transmit information for permitting entry to the container yard from the
[0048]
The
[0049]
In addition, the shipping company may list only the information of the marked work items from among all the work related to its own ship, or it may be carried out even after the next work item to be processed or the scheduled date. Only the information of the work items that do not exist may be listed.
In this way, information on work items to be processed next and work items whose execution is delayed are listed in a plurality of schedule tables for each shipping company, so that each shipping company can easily grasp the work order. can do.
[0050]
The
[0051]
The
Instead of the
[0052]
The
In addition, in order for each terminal to refer only to the schedule table related to each trader, for example, the receiving
[0053]
<Operation>
FIG. 9 is a diagram showing a procedure of an export operation of the
Hereinafter, a procedure of the export operation of the shared
(1) The receiving
[0054]
(2) If there is an input from each terminal, it is determined whether the input is invoice and packing list data (step S2).
(3) In the case of inputting the invoice and packing list data, the work
[0055]
(4) The work
[0056]
(5) If it is not input of invoice & packing list data, it is determined whether it is a request for transmission of schedule table data (step S5).
(6) In the case of a request to transmit schedule table data, the
[0057]
(7) If the request is not a request to transmit data in the schedule table, it is determined whether the input is shipping instruction data, work progress and detailed information, and a container number and a seal number (step S7). .
(8) In the case of inputting shipping instruction data, work progress and detailed information, and inputting a container number and a seal number, the
[0058]
(9) If it is not an input of shipping instruction data, work progress or detailed information, or an input of a container number and a seal number, it is determined whether or not it is an instruction to change the scheduled work schedule (step S9).
(10) When the instruction is a change instruction of the scheduled work schedule, the work
[0059]
(11) If the instruction is not the instruction to change the scheduled work schedule, it is determined whether the instruction is to change the schedule table (step S11).
(12) If the instruction is a schedule table change instruction, the schedule
[0060]
(13) If the instruction is not a schedule table change instruction, it is determined whether the instruction is a B / L creation instruction (step S13).
(14) In the case of a B / L creation instruction, the B /
[0061]
(15) If none of the above inputs are made, and if each processing is completed, the process returns to waiting for input from each terminal.
FIG. 10 is a diagram showing a procedure of an import operation of the
Hereinafter, a procedure of the import operation of the shared
[0062]
In the following description of the procedure of the import operation, the same steps as those in the procedure of the export operation shown in FIG. 9 are denoted by the same reference numerals, and description thereof will be omitted.
(1) Same as the export operation procedure (1) (step S1).
(2) When there is an input from each terminal, it is determined whether or not the input is B / L & A / N (step S21).
[0063]
(3) If the input is B / L & A / N, the procedure is the same as the export operation procedure (3) (step S3).
(4) Same as the export operation procedure (4) (step S4).
(5) If the input is not B / L & A / N, it is the same as the export operation procedure (5) (step S5).
[0064]
(6) Same as the export operation procedure (6) (step S6).
(7) If the request is not a request to transmit the data of the schedule table, it is determined whether or not the progress of the work and the input of detailed information are input (step S22).
(8) If the input is a progress status or detailed information, it is the same as the export operation procedure (8) (step S8).
[0065]
(9) When the progress of the work or the detailed information is not input, the procedure is the same as the procedure (9) of the export operation (step S9).
(10) Same as the export operation procedure (10) (step S10).
(11) Same as the export operation procedure (11) (step S11).
(12) Same as the export operation procedure (12) (step S12).
[0066]
(13) If none of the above inputs have been made, and if each process has been completed, the process returns to waiting for input from each terminal.
As described above, according to the embodiment of the present invention, the progress status and detailed information of other vendors can be obtained in each vendor even if the processing of the vendor in the previous process is not completed, and the schedule can be adjusted in advance. In addition, the schedule of the own process can be changed in response to the schedule change of the previous process, and it is easy to perform efficient work.
[0067]
Note that a program that allows a computer to execute an operation as in the present embodiment is recorded on a computer-readable recording medium, and this recording medium can be distributed and traded. Further, the program can be distributed through, for example, a network or the like, and can be a target of a transaction.
Here, the computer-readable recording medium includes, for example, a removable recording medium such as a flexible disk, a CD, an MO, a DVD, and a memory card, and a fixed recording medium such as a hard disk and a semiconductor memory. Not something.
[0068]
【The invention's effect】
A container import / export management device according to the present invention is a container import / export management method in a container import / export management device that manages container import / export operations in port transportation, wherein the container import / export management device performs past import / export operations. Storage means for recording actual data including the type of package and the actual work schedule, and the container import / export management method uses import / export work including the type of package for each container or containers. Receiving means for receiving input of work information related to the work information, and extracting actual data corresponding to the type of package included in the work information received by the receiving means from the actual data recorded by the recording means, and scheduling based on the extracted actual data. A work schedule table generating means for generating a work schedule table, and terminals installed at shippers, sea forwarders, and shipping companies. Presenting means for transmitting data of the scheduled work schedule to cause the generated scheduled work schedule to be presented, and the receiving means further includes a shipper, a sea freight agent, a container yard operator, And accepting data input of the progress status of the import / export work from each of the shipping companies, and the presenting means further presents the progress status together with the planned work schedule when transmitting the data of the planned work schedule to each of the terminals. In this case, the data on the progress is transmitted in association with the data on the scheduled work schedule.
[0069]
Further, in a container import / export management device constructed using a computer that manages container import / export work in port transportation, the container import / export management device determines the types of baggage in past import / export work and the actual work schedule. The import / export management program according to the present invention includes a recording means for recording the result data including the actual data including the type of the import / export operation including the type of the luggage for each one or a plurality of containers from the shipper. Receiving means for receiving the input; extracting actual data corresponding to the type of baggage included in the work information received by the receiving means from the actual data recorded by the recording means; and preparing a scheduled work schedule based on the extracted actual data. The work schedule table generation means to be generated and the terminals installed at each of the shipper, sea forwarder, and shipping company In order to present the generated scheduled work schedule table to be generated, it is made to function as a presentation means for transmitting data of the scheduled work schedule table, and the receiving means further includes, by the terminals, a shipper, a sea freight agent, a container yard operator, And accepting data input of the progress status of the import / export work from each of the shipping companies, and the presenting means further presents the progress status together with the planned work schedule when transmitting the data of the planned work schedule to each of the terminals. In this case, the data on the progress is transmitted in association with the data on the scheduled work schedule.
[0070]
Further, the container import / export management method according to the present invention is a container import / export management method in a container import / export management device that manages container import / export work in port transportation, wherein the container import / export management device includes a past export The container import / export management method is provided with a recording means for recording the actual data including the type of baggage of the incoming work and the actual work schedule. Receiving means for receiving input of work information relating to the incoming work, and extracting and outputting the result data corresponding to the type of package included in the work information received by the receiving means from the result data recorded by the recording means, based on the extracted result data A work schedule table generating means for generating a scheduled work schedule table, and installed at each of the shipper, sea forwarder and shipping company. Presenting means for transmitting the data of the scheduled work schedule to the terminal that has generated the scheduled work schedule, and the receiving means further includes a shipper, a sea freight trader, a container yard, An operator and a shipping company receive data input on the progress of import / export work from each of the shipping companies, and the presenting means further displays the progress on the scheduled work schedule when transmitting the data of the scheduled work schedule to the terminals. The data of the progress is transmitted in association with the data of the scheduled work schedule to be presented together with the data.
[0071]
By these means, each of the shipper, sea freight forwarder and shipping company can refer to the scheduled work schedule using the terminal installed at the start of work immediately after the start of work, When each of the contractor, the container yard operator, and the shipping company inputs the progress status, the progress status can be referred to together with the scheduled work schedule.
[0072]
Therefore, even if the processing of the previous process is not completed, each company can obtain the progress status of the other company, adjust the schedule in advance, or change the schedule of the own process in response to the schedule change of the previous process And efficient work can be easily performed.
Further, in the container import / export management apparatus, the work information that the accepting means receives the input is a shipper identifier corresponding to the shipper, a sea forwarder identifier corresponding to the sea forwarder specified by the shipper, and a shipping company specified by the shipper. The work schedule table generating means includes, for each generated scheduled work schedule table, a shipper identifier, a shipping agent identifier, and a shipping company identifier included in the work information received by the receiving means. Attachment, the presenting means transmits only the data of the scheduled work schedule to which the shipper identifier corresponding to the shipper is attached for each shipper, and the forwarder identifier corresponding to the forwarder is provided for each forwarder. Only the data of the attached scheduled work schedule is transmitted, and only the data of the scheduled work schedule to which the shipping company identifier corresponding to the shipping company is attached is transmitted for each shipping company. It can also be a.
[0073]
Thus, each terminal can refer only to the schedule table related to each of the shipper, the sea freight forwarder, and the shipping company.
Further, in the container import / export management apparatus, the receiving unit further receives an input of a shipping company identifier corresponding to a shipping company designated by the shipping company from a shipping company, and the work schedule table generating unit generates the scheduled work. Attaching the shipping company identifier accepted by the accepting means for each schedule, the presenting means further includes, for each shipping company, the generated scheduled work schedule to be presented on a terminal installed under the shipping company. Only the data of the scheduled work itinerary to which the shipping company corresponding to the shipping company is attached is transmitted, and the accepting unit further performs a transport operation in the import / export operation from the shipping company by a terminal installed under the shipping company. It may be characterized in that the input of the progress data is received.
[0074]
This allows the terminal installed at the transportation company to refer only to the schedule table related to each transportation company.
In the container import / export management apparatus, the performance data recorded by the recording unit includes the number of packages, the work information received by the receiving unit includes the number of packages, and the work schedule table generating unit extracts The scheduled work schedule table may be generated by performing a correction based on the quantity included in the work information received in the actual work schedule of the actual work data obtained.
[0075]
As a result, the scheduled work schedule table can be generated by performing the correction based on the quantity.
Therefore, the scheduled work schedule can be generated more accurately.
Further, in the container import / export management device, the receiving unit further receives a change instruction for changing the scheduled work schedule from each of the terminals, and the container import / export management device further performs the schedule according to the received change instruction. It is also possible to provide a work schedule changing means for changing the work schedule.
[0076]
As a result, each of the shipper, the sea freight forwarder, and the shipping company can change the scheduled work schedule using the terminals installed at the respective locations.
Therefore, even if the processing of the supplier in the previous process is not completed, the schedule of the own process can be changed in advance according to the progress of the other supplier and the own convenience, and efficient work can be performed by each supplier. Becomes easier.
[0077]
In the container import / export management apparatus, the performance data includes a plurality of work items, a performance date for each work item, and a work order of processing for each work item, and the change instruction received by the receiving unit is a predetermined instruction. Changing the scheduled date of the work item, or registering an actual date different from the scheduled date in the predetermined work item, wherein the work schedule changing means is more than the predetermined work item instructed to change. It may be characterized in that all the planned dates of the work items with the lower work order are changed in the order of the higher work order by the number of change days according to the change instruction.
[0078]
As a result, if the scheduled date is changed or the result is not as scheduled, the subsequent scheduled date can be changed by the number of changed days.
Therefore, the schedule can be changed promptly, and efficient work can be easily performed.
Further, in the container import / export management device, the accepting unit further accepts input of a container number, an input of a seal number, and a date and time of loading a van into the container from the input terminal, and The apparatus further includes a receipt creating means for creating a container receipt including these information based on the received work information, the container number, the seal number, and the date and time of loading the van on the container, The presenting means may further be characterized in that the container number, the seal number, and the date and time of loading the van on the container are transmitted in association with the data of the scheduled work schedule.
[0079]
Thereby, the input of the container number and the seal number can be received from the portable input terminal, and the container receipt can be automatically created based on these.
Therefore, a container receipt can be easily created.
Further, in the container import / export management apparatus, the recording unit further records detailed data on each process for each work item, and the receiving unit further receives a designation of the work item from any of the terminals. The presenting means may be further characterized in that the detailed data of the designated work item is read out from the recording means and returned.
[0080]
As a result, the detailed data of the designated work item can be returned.
Therefore, each of the shipper, the sea freighter, and the shipping company can browse the detailed data of the work item by using the terminals installed at the respective locations.
The container import / export management device further generates a list of the marked work items, the work items to be processed next, or the work items for which the execution date has not been input even after the scheduled date. The information processing apparatus may further include a list generation unit, and the presentation unit may further transmit the data of the list to each terminal so as to present the list generated by the list generation unit to the terminal.
[0081]
This makes it possible to generate a list of marked work items, work items to be processed next, or work items for which the execution date has not been entered even after the scheduled date, and to transmit the data. it can.
Therefore, each of the shipper, the sea freighter, and the shipping company can browse the list of work items requiring attention using the terminals installed at the respective locations.
[Brief description of the drawings]
FIG. 1 is a diagram schematically showing a container import / export management system according to an embodiment of the present invention.
FIG. 2 is a diagram showing an example of performance data recorded in a
FIG. 3 is a diagram illustrating an example of invoice & packing list data received by a receiving
FIG. 4 is a diagram illustrating an example of shipping instruction data received by a receiving
FIG. 5 is a diagram showing an example of a scheduled work schedule generated by the
FIG. 6 is a diagram illustrating an example of a B / L generated by a B /
7 is a diagram showing a schedule table presented to the
8 is a diagram showing an example of an import work schedule table presented to the
FIG. 9 is a diagram showing a procedure of an export operation of the
FIG. 10 is a diagram showing a procedure of an import operation of the
[Explanation of symbols]
10 Shared device
11 Result data recording section
12 Reception desk
13 Work schedule generator
14 Work schedule change section
15 Registration Department
16 B / L creation unit
17 Schedule table creation section
18 Presentation part
19 Schedule table change section
20 Shipper terminals
30 Terminals for forwarding agents
Terminal for 40 CYO
50 Carrier terminals
60 Shipping company terminal
70 Mobile input terminal
80 Communication line
Claims (11)
過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段と、
荷主から、1個又は複数のコンテナ毎に、荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、
記録手段により記録された実績データから、受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し、抽出した実績データに基づいて、予定作業日程表を生成する作業日程表生成手段と、
荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に、生成された予定作業日程表を提示させるべく、当該予定作業日程表のデータを送信する提示手段とを備え、
前記受け付け手段は、さらに、
前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから、輸出入作業の進捗状況のデータ入力を受け付け、
前記提示手段は、さらに、
前記各端末に予定作業日程表のデータを送信する際に、進捗状況を予定作業日程表と共に提示させるべく、当該進捗状況のデータを予定作業日程表のデータと関連付けて送付すること
を特徴とするコンテナ輸出入管理装置。A container import / export control device for managing container import / export operations in port transportation,
Recording means for recording the actual data including the type of baggage of past import / export work and the actual work schedule;
Accepting means for accepting, from the shipper, input of work information relating to import / export work including the type of package for each of one or more containers;
A work schedule for extracting actual data corresponding to the type of package included in the work information received by the receiving unit from the actual data recorded by the recording unit, and generating a scheduled work schedule table based on the extracted actual data. Table generation means;
A shipper, a forwarding agent, and a terminal installed at each of the shipping companies, in order to present the generated scheduled work schedule, to provide a presentation means for transmitting data of the scheduled work schedule,
The receiving means further includes:
From each of the terminals, a shipper, a forwarder, a container yard operator, and, from each of the shipping companies, accept data input of the progress of import / export work,
The presenting means further comprises:
When transmitting the data of the scheduled work schedule to each of the terminals, the progress data is transmitted in association with the data of the scheduled work schedule so that the progress is presented together with the scheduled work schedule. Container import / export control device.
前記作業日程表生成手段は、生成した予定作業日程表毎に、受け付け手段により受け付けられた作業情報に含まれる荷主識別子、海貨業者識別子、及び、船会社識別子を添付し、
前記提示手段は、
荷主毎に、当該荷主に対応する荷主識別子が添付された予定作業日程表のデータのみを送信し、
海貨業者毎に、当該海貨業者に対応する海貨業者識別子が添付された予定作業日程表のデータのみを送信し、
船会社毎に、当該船会社に対応する船会社識別子が添付された予定作業日程表のデータのみを送信すること
を特徴とする請求項1に記載のコンテナ輸出入管理装置。The work information that the accepting unit accepts the input includes a shipper identifier corresponding to the shipper, a shipping agent identifier corresponding to the shipper specified by the shipper, and a shipping company identifier corresponding to the shipping company specified by the shipper,
The work schedule table generating means, for each of the generated scheduled work schedule table, attached a shipper identifier, a sea freight agent identifier, and a shipping company identifier included in the work information received by the receiving means,
The presenting means,
For each shipper, send only the data of the scheduled work schedule to which the shipper identifier corresponding to the shipper is attached,
For each forwarding agent, transmit only the data of the scheduled work schedule to which the forwarding agent identifier corresponding to the forwarding agent is attached,
2. The container import / export management device according to claim 1, wherein only the data of the scheduled work schedule to which the shipping company identifier corresponding to the shipping company is attached is transmitted for each shipping company.
海貨業者から、海貨業者が指定する運送会社に対応する運送会社識別子の入力を受け付け、
前記作業日程表生成手段は、生成した予定作業日程表毎に、受け付け手段により受け付けられた運送会社識別子を添付し、
前記提示手段は、さらに、
運送会社の元に設置された端末に、生成された予定作業日程表を提示させるべく、運送会社毎に、当該運送会社に対応する運送会社が添付された予定作業日程表のデータのみを送信し、
前記受け付け手段は、さらに、
前記運送会社の元に設置された端末により、運送会社から、輸出入作業における運送作業の進捗状況のデータ入力を受け付けること
を特徴とする請求項2に記載のコンテナ輸出入管理装置。The receiving means further includes:
Accepting the input of the shipping company identifier corresponding to the shipping company specified by the shipping company from the forwarding agent,
The work schedule table generating means, for each of the generated scheduled work schedule table, attach the shipping company identifier received by the receiving means,
The presenting means further comprises:
In order to present the generated scheduled work schedule to the terminal installed under the carrier, only the data of the scheduled work schedule attached to the carrier corresponding to the respective carrier is transmitted for each carrier. ,
The receiving means further includes:
The container import / export management device according to claim 2, wherein the terminal installed at the transportation company receives data input of the progress of the transportation work in the import / export operation from the transportation company.
前記受け付け手段が入力を受け付ける作業情報は、荷物の数量を含み、
前記作業日程表生成手段は、抽出した実績データの実績作業日程に、受け付けられた作業情報に含まれる数量による補正を施して、予定作業日程表を生成すること
を特徴とする請求項1に記載のコンテナ輸出入管理装置。The performance data recorded by the recording means includes the number of packages,
The work information that the accepting unit accepts the input includes the number of packages,
2. The scheduled work schedule table according to claim 1, wherein the work schedule table generation unit corrects the actual work schedule of the extracted actual data based on the quantity included in the received work information, and generates a scheduled work schedule table. 3. Container import and export control equipment.
前記各端末から、前記予定作業日程を変更する変更指示を受け付け、
前記コンテナ輸出入管理装置は、さらに、
受け付けられた変更指示に従って、前記予定作業日程を変更する作業日程変更手段を備えること
を特徴とする請求項1に記載のコンテナ輸出入管理装置。The receiving means further includes:
A change instruction for changing the scheduled work schedule is received from each of the terminals,
The container import / export management device further comprises:
2. The container import / export management apparatus according to claim 1, further comprising a work schedule changing unit configured to change the scheduled work schedule in accordance with the received change instruction.
複数の作業項目、作業項目毎の実績日、及び、作業項目毎の処理の作業順位を含み、
前記受け付け手段が受け付ける変更指示は、
所定の作業項目の予定日を変更するか、又は、所定の作業項目において予定日と異なる日付の実績日を登録するものであり、
前記作業日程変更手段は、
変更指示がなされた所定の作業項目よりも作業順位が低い作業項目の全ての予定日を、作業順位が高い順に、変更指示による変更日数分だけ変更すること
を特徴とする請求項5に記載のコンテナ輸出入管理装置。The performance data is
Includes multiple work items, actual dates for each work item, and work order for processing for each work item,
The change instruction received by the receiving unit is:
Either change the scheduled date of the predetermined work item, or register an actual date different from the scheduled date in the predetermined work item,
The work schedule changing means,
6. The method according to claim 5, wherein all the scheduled dates of the work items whose work order is lower than the predetermined work item for which the change instruction is given are changed in the order of the work order by the number of change days according to the change order. Container import / export control device.
入力端末からの、コンテナ番号の入力、及び、シール番号の入力、及び、コンテナへのバン積め日時情報を受け付け、
前記コンテナ輸出入管理装置は、さらに、
受け付けられた作業情報、コンテナ番号、シール番号、及び、コンテナへのバン積め日時情報に基づいて、これらの情報を記載に含むコンテナ受取証を作成する受取証作成手段を備え、
前記提示手段は、さらに、
コンテナ番号、シール番号、及び、コンテナへのバン積め日時情報を、予定作業日程表のデータと関連付けて送付すること
を特徴とする請求項1に記載のコンテナ輸出入管理装置。The receiving means further includes:
From the input terminal, the input of the container number, the input of the seal number, and the date and time of loading the van to the container,
The container import / export management device further comprises:
Based on the received work information, the container number, the seal number, and the information on the date and time of loading the van on the container, there is provided a receipt creating means for creating a container receipt including these information in the description,
The presenting means further comprises:
The container import / export management device according to claim 1, wherein the container number, the seal number, and the date and time of loading the van on the container are transmitted in association with data of the scheduled work schedule.
作業項目毎にそれぞれの処理に関する詳細データを記録し、
前記受け付け手段は、さらに、
前記各端末のいずれかから、作業項目の指定を受け付け、
前記提示手段は、さらに、
指定された作業項目の詳細データを、前記記録手段から読み出して返信すること
を特徴とする請求項1に記載のコンテナ輸出入管理装置。The recording means further comprises:
Record detailed data on each process for each work item,
The receiving means further includes:
Accepting the designation of a work item from any of the terminals,
The presenting means further comprises:
2. The container import / export management apparatus according to claim 1, wherein the detailed data of the designated work item is read out from the recording unit and returned.
マークを付けられた作業項目、次に処理すべき作業項目、又は、予定日を過ぎても実施日が入力されていない作業項目のリストを生成するリスト生成手段を備え、
前記提示手段は、さらに、
前記各端末へ、リスト生成手段により生成されたリストをへ提示させるべく、当該リストのデータを送信すること
を特徴とする請求項1に記載のコンテナ輸出入管理装置。The container import / export management device further comprises:
A list generating means for generating a list of marked work items, work items to be processed next, or work items for which the execution date has not been input even after the scheduled date;
The presenting means further comprises:
2. The container import / export management device according to claim 1, wherein data of the list is transmitted to each terminal so as to present the list generated by the list generation unit to the terminal. 3.
前記コンテナ輸出入管理装置は、
過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、
前記コンピュータを、
荷主から、1個又は複数のコンテナ毎に、荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、
記録手段により記録された実績データから、受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し、抽出した実績データに基づいて、予定作業日程表を生成する作業日程表生成手段と、
荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に、生成された予定作業日程表を提示させるべく、当該予定作業日程表のデータを送信する提示手段として機能させ、
前記受け付け手段は、さらに、
前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから、輸出入作業の進捗状況のデータ入力を受け付け、
前記提示手段は、さらに、
前記各端末に予定作業日程表のデータを送信する際に、進捗状況を予定作業日程表と共に提示させるべく、当該進捗状況のデータを予定作業日程表のデータと関連付けて送付すること
を特徴とするコンテナ輸出入管理プログラム。In a container import / export management device constructed using a computer that manages container import / export work in port transportation,
The container import / export management device,
Equipped with recording means for recording the actual data including the type of baggage of past import / export work and the actual work schedule,
Said computer,
Accepting means for accepting, from the shipper, input of work information relating to import / export work including the type of package for each of one or more containers;
A work schedule for extracting actual data corresponding to the type of package included in the work information received by the receiving unit from the actual data recorded by the recording unit, and generating a scheduled work schedule table based on the extracted actual data. Table generation means;
The shipper, the forwarding agent, and a terminal installed at each of the shipping companies, in order to present the generated scheduled work schedule, to function as a presentation means for transmitting the data of the scheduled work schedule,
The receiving means further includes:
From each of the terminals, a shipper, a forwarder, a container yard operator, and, from each of the shipping companies, accept data input of the progress of import / export work,
The presenting means further comprises:
When transmitting the data of the scheduled work schedule to each of the terminals, the progress data is transmitted in association with the data of the scheduled work schedule so that the progress is presented together with the scheduled work schedule. Container import / export management program.
前記コンテナ輸出入管理装置は、
過去の輸出入作業の荷物の種類、及び、実績作業日程を含む実績データを記録している記録手段を備え、
当該コンテナ輸出入管理方法は、
荷主から、1個又は複数のコンテナ毎に、荷物の種類を含む輸出入作業に関する作業情報の入力を受け付ける受け付け手段と、
記録手段により記録された実績データから、受け付け手段により受け付けられた作業情報に含まれる荷物の種類に対応する実績データを抽出し、抽出した実績データに基づいて、予定作業日程表を生成する作業日程表生成手段と、
荷主、海貨業者、及び、船会社のそれぞれの元に設置された端末に、生成された予定作業日程表を提示させるべく、当該予定作業日程表のデータを送信する提示手段とを含み、
前記受け付け手段は、さらに、
前記各端末により、荷主、海貨業者、コンテナヤードオペレータ、及び、船会社のそれぞれから、輸出入作業の進捗状況のデータ入力を受け付け、
前記提示手段は、さらに、
前記各端末に予定作業日程表のデータを送信する際に、進捗状況を予定作業日程表と共に提示させるべく、当該進捗状況のデータを予定作業日程表のデータと関連付けて送付すること
を特徴とするコンテナ輸出入管理方法。A container import / export control method in a container import / export control device for managing container import / export operations in port transportation,
The container import / export management device,
Equipped with recording means for recording the actual data including the type of baggage of past import / export work and the actual work schedule,
The container import / export management method is
Accepting means for accepting, from the shipper, input of work information relating to import / export work including the type of package for each of one or more containers;
A work schedule for extracting actual data corresponding to the type of package included in the work information received by the receiving unit from the actual data recorded by the recording unit, and generating a scheduled work schedule table based on the extracted actual data. Table generation means;
A shipper, a forwarding agent, and a terminal installed at each of the shipping companies, including a presentation means for transmitting data of the scheduled work schedule in order to present the generated scheduled work schedule,
The receiving means further includes:
From each of the terminals, a shipper, a forwarder, a container yard operator, and, from each of the shipping companies, accept data input of the progress of import / export work,
The presenting means further comprises:
When transmitting the data of the scheduled work schedule to each of the terminals, the progress data is transmitted in association with the data of the scheduled work schedule so that the progress is presented together with the scheduled work schedule. Container import / export management method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002292335A JP2004123347A (en) | 2002-10-04 | 2002-10-04 | Container import / export control device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002292335A JP2004123347A (en) | 2002-10-04 | 2002-10-04 | Container import / export control device |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004123347A true JP2004123347A (en) | 2004-04-22 |
Family
ID=32283620
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002292335A Pending JP2004123347A (en) | 2002-10-04 | 2002-10-04 | Container import / export control device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004123347A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006154934A (en) * | 2004-11-25 | 2006-06-15 | Toshiba Plant Systems & Services Corp | Plant construction work information management system |
JP2022131477A (en) * | 2021-02-26 | 2022-09-07 | 株式会社オービック | LOGISTICS MANAGEMENT DEVICE, LOGISTICS MANAGEMENT METHOD, AND LOGISTICS MANAGEMENT PROGRAM |
-
2002
- 2002-10-04 JP JP2002292335A patent/JP2004123347A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006154934A (en) * | 2004-11-25 | 2006-06-15 | Toshiba Plant Systems & Services Corp | Plant construction work information management system |
JP2022131477A (en) * | 2021-02-26 | 2022-09-07 | 株式会社オービック | LOGISTICS MANAGEMENT DEVICE, LOGISTICS MANAGEMENT METHOD, AND LOGISTICS MANAGEMENT PROGRAM |
JP7590215B2 (en) | 2021-02-26 | 2024-11-26 | 株式会社オービック | Logistics management device, logistics management method, and logistics management program |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6718980B2 (en) | Systems, methods and programs for trade transactions | |
AU2006254632B2 (en) | Management and analysis of cargo shipments | |
US20050119926A1 (en) | Method and system for managing multi-national integrated trade and logistics and processes for efficient, timely, and compliant movement of goods across international borders | |
KR20050084684A (en) | Systems and methods for producing ducumentry credit and conforming shipping documents | |
US7487119B2 (en) | Physical distribution business management method, physical distribution business management system, and storage medium | |
MXPA06009103A (en) | Systems and methods to support approval to settle an international trade from a credit facility, such as a line of credit or a demand deposit account. | |
US6970825B1 (en) | Planning engine for a parcel shipping system | |
US12387165B2 (en) | System and method to deliver goods with precise handling requirements | |
JP2004302723A (en) | Physical distribution control information processing system and method | |
US20050071247A1 (en) | Integrated transportation method and system | |
KR20010095347A (en) | Method for managing the information of imported and exported goods using computer network and its system | |
KR102035209B1 (en) | Distribution information management apparatus of shiplping company/ delivery company for import and export | |
JP5443703B2 (en) | Export business support system and method for supporting export business using the system | |
WO1998058303A2 (en) | Partially user-defined computer transportation system | |
KR102054251B1 (en) | Distribution information management apparatus for import and export | |
JP6247914B2 (en) | Trade business support equipment | |
KR20010098236A (en) | A performance method of import and export by internet | |
JP2004123347A (en) | Container import / export control device | |
JP2006244196A (en) | Support system for managing international transportation risk | |
US20040068426A1 (en) | Shipment management system and method | |
KR20240014782A (en) | Freight information of cargo transportation means and system for providing cargo delivery | |
JP2004126663A (en) | Trade support system | |
JP7686286B2 (en) | Information Processing System | |
US20240303597A1 (en) | Automated logistics transshipment management system | |
KR20230085827A (en) | System and method for cloud-based logistic management |