[go: up one dir, main page]

EP3223221A1 - Construction management - Google Patents

Construction management Download PDF

Info

Publication number
EP3223221A1
EP3223221A1 EP16161760.0A EP16161760A EP3223221A1 EP 3223221 A1 EP3223221 A1 EP 3223221A1 EP 16161760 A EP16161760 A EP 16161760A EP 3223221 A1 EP3223221 A1 EP 3223221A1
Authority
EP
European Patent Office
Prior art keywords
data
information
message
dimensional model
event
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP16161760.0A
Other languages
German (de)
French (fr)
Inventor
Bo Pettersson
Håkan ANDERSSON
Jonas WEDIN
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hexagon Technology Center GmbH
Original Assignee
Hexagon Technology Center GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hexagon Technology Center GmbH filed Critical Hexagon Technology Center GmbH
Priority to EP16161760.0A priority Critical patent/EP3223221A1/en
Priority to US15/466,701 priority patent/US10664781B2/en
Priority to CN201710172788.8A priority patent/CN107220398B/en
Publication of EP3223221A1 publication Critical patent/EP3223221A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T19/00Manipulating 3D models or images for computer graphics
    • G06T19/006Mixed reality
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2219/00Indexing scheme for manipulating 3D models or images for computer graphics
    • G06T2219/004Annotating, labelling

Definitions

  • the present invention pertains to a construction management system for a building site of a structure, and to a method for linking data to a three-dimensional model of the building site or of the structure.
  • the data comprises information about an event occurring at the building site.
  • said three-dimensional model is a part of or comprises a building information model (BIM).
  • Paper based orders might be outdated by the time they are issued to the executing entity;
  • An immediate response to and purposeful handling of the unexpected is required, wherein all the consequences to a desired schedule have to be considered to minimize impact.
  • Detecting, handling and documenting of the done work has to be established, deviations from a planed schedule have to be documented, determined and handled.
  • the existing dependencies are often too complex to immediately cope with, in particular for an on-site executing entity.
  • At least one of these objects is achieved by the construction management system according to claim 1, the method according to claim 7 and/or the dependent claims of the present invention.
  • a first aspect of the present invention relates to a construction management system for the construction of a structure, e. g. a building or piece of infrastructure.
  • the construction management system comprises a plurality of sensor means adapted to detect events at a building site of the structure and a central computing unit, e. g. a server computer, providing a building information model comprising at least a three-dimensional model of the building site or of the structure, a construction plan comprising a target state of the construction of the structure, information about a current construction state of the structure, and information about participants in the construction of the structure, e. g. building companies and handicraft businesses.
  • the system comprises at least one displaying device, e. g. a personal computer or Smartphone, that is adapted to display the three-dimensional model to a user, e. g. a site manager.
  • the plurality of sensor means is adapted for generating data comprising information about a detected event
  • the system comprises a plurality of communication units adapted to transmit a message comprising the data and a location information to the central computing unit.
  • the system is adapted to assign coordinates in the three-dimensional model according to the location information
  • the central computing unit has an evaluation algorithm adapted to evaluate options for reacting on the event by analyzing the data, thereby considering information from the building information model, and the system is adapted to assign evaluated options to the data.
  • the at least one displaying device is adapted to display a note which is related to the data and to evaluated options to the user in real-time, wherein the note is displayed at the assigned coordinates in the three-dimensional model.
  • the sensor means are adapted to generate the data automatically.
  • the communication units are adapted to generate the message automatically.
  • each of the plurality of sensor means comprises one of the plurality of communication units.
  • the sensor means are adapted as or comprise cameras, distance meters, motion detectors, smoke detectors, thermometers, hygrometers, and/or input means that are adapted to allow an input by an operator, the input means particularly comprising a keypad for inputting a code or text or a microphone for inputting a voice message.
  • the sensor means are adapted to generate the location information, particularly automatically, the location information comprising information about a location of the event, or of the sensor means detecting the event.
  • the location information comprises either coordinates in a global or local coordinate system, particularly in a coordinate system of the building site, or a designator or code identifying a pre-defined position or area in the structure or at the building site, particularly a room of a building.
  • the central computing unit comprises at least one server computer.
  • the central computing unit comprises a cluster of server computers working as a cloud system.
  • the communication units are adapted to transmit the message to the central computing unit by means of an internet or intranet connection, and/or the at least one displaying device is adapted to receive the data from the central computing unit by means of an internet or intranet connection.
  • the construction management system comprises a plurality of displaying devices, each of which being adapted to display the three-dimensional model with the note to a user in real-time, each user having a role in the construction of the structure.
  • the evaluation algorithm is adapted to evaluate, based on said roles, on which of the displaying devices a note is to be displayed, and/or the system is adapted to assign evaluated options to the data for each displaying device individually.
  • displaying the three-dimensional model with the note comprises focussing on those notes which are of particular relevance for the role of the user to which the model is displayed. Said focussing may comprise e. g. a highlighting of the notes, a zooming to the note in the model, or an alignment of the view on the model so that the note is centred.
  • a second aspect of the present invention relates to a method for linking data to a building information model, particularly by means of a construction management system according to the first aspect.
  • the data comprises information about an event occurring at a building site of a structure
  • the building information model comprises at least a three-dimensional model of the building site or of the structure, a construction plan for the construction of the structure comprising a target state of the construction of the structure, information about a current construction state of the structure, and information about participants in the construction of the structure.
  • the method comprises
  • the data is generated automatically by sensor means detecting the event, particularly wherein the message is generated automatically by a communication unit of the sensor means, and the options are evaluated automatically by an evaluation algorithm of the central computing unit.
  • the location information comprises information about a location of the event, of a sensor means detecting the event, or of a communication unit generating the message.
  • the location information particularly comprises coordinates in a global or local coordinate system, particularly in a coordinate system of the building site, or a designator or code identifying a pre-defined position or area in the structure or at the building site, particularly a room.
  • the message comprises information about a time of the event or of the detection of the event, wherein for evaluating options for reacting also the information about the time are considered, and/or the note is based also on the information about the time.
  • the three-dimensional model is displayed simultaneously to a plurality of users on a plurality of displaying devices, each user having a role in the construction of the structure, wherein each of the displaying devices receives the data from the central computing unit, particularly by means of an internet or intranet connection, the central computing unit comprising at least one server computer, particularly a cluster of server computers working as a cloud system.
  • the method comprises evaluating, based on the roles, on which of the displaying devices a note is to be displayed, and/or assigning evaluated options to the data for each displaying device individually.
  • displaying the three-dimensional model with the note comprises focusing on those notes which are of particular relevance for the role of the user to which the model is displayed.
  • displaying the note in the three-dimensional model comprises presenting the data and evaluated options to the user.
  • displaying the note in the three-dimensional model comprises visualizing an icon at the assigned coordinates in real-time, wherein the icon is user-selectable, and upon a user-selection of the icon a notice is visualized based on the message.
  • a third aspect of the invention relates to a computer programme product comprising programme code which is stored on a machine-readable medium, or being embodied by an electromagnetic wave comprising a programme code segment, and having computer-executable instructions for performing, in particular when run on calculation means of a construction management system according to the first aspect of the invention, at least the following steps of the method according to the second aspect:
  • FIG. 1 an exemplary embodiment of a construction management system 1 according to the invention is depicted.
  • the system comprises a computer system 2 comprising one or more display units 20 and a server computer 25 that are connected by means of an internet connection 26.
  • the display unit 20 is a laptop comprising a display 21 (output means) and a mouse 22 (input means).
  • GUI graphical user interface
  • a three-dimensional model 35 of a building 30 is visualized.
  • a user (not shown) of the laptop is enabled to change the view on the model 35 by moving the cursor 23 on one of the GUI buttons 24a-c and clicking on a button of the mouse 22 (e. g. rotate the model, zoom in or out).
  • the system furthermore comprises at least one sensor unit (not shown) that is located at a building site 3 of the building 30 that is represented by the three-dimensional model 35.
  • the sensor unit can be installed in the building 30 to work autonomously or be operated by an operator 4 at the building site.
  • the user of the display unit 20 has a certain role with respect to the construction, for instance is a site manager of the building site 3.
  • the construction can of course also be or comprise infrastructure such as roads or railways.
  • infrastructure such as roads or railways.
  • server computer 25 instead of a single server computer 25, a cluster of servers, a cloud or similar means can be used.
  • Figure 2 is a flow chart illustrating a method 100 according to the invention for linking data comprising information about an event taking place at the building site to the three-dimensional model.
  • the dotted line represents a virtual border between those method steps on the left of the line which take place at the building site 3 and those on the right taking place in the computer system 2 (see Figure 1 ).
  • the method 100 begins with detection 110 of an event.
  • the event is detected by some kind of sensor unit at the building site.
  • the sensor units may comprise thermometers and hygrometers for detecting a temperature and wetness in a certain room of the construction, highly precise distance meters for detecting unwanted movement of the construction, motion detectors and cameras for detecting work progress or unauthorized persons, or smoke detectors for detecting fire.
  • the sensor units can also comprise input means to allow input by an operator of the units. E. g. these comprise a keypad for inputting a code or text, a microphone for recording a voice message or a camera for recording a video message. This user input is then the event detected by the unit.
  • step 120 data is generated, particularly automatically by the sensor unit.
  • this data may comprise measured values, the information that a pre-defined threshold has been reached, video data, or the user input.
  • a location is determined.
  • this location can either be that of the sensor unit itself or that of the determined event.
  • an operator can input the exact location of the event.
  • the location can be either a set of coordinates or a code for a certain room or area.
  • a message is generated in step 140.
  • This message comprises at least the data from step 120 and the location information of step 130. Also, a time information can be added automatically.
  • the message is transmitted via an internet or intranet connection to a computer, e. g. a remote server computer, having memory on which a model of the building site or structure is stored.
  • a computer e. g. a remote server computer
  • the sensor units can comprise or be connected to a suitable communication means which sends the message by cable or wireless, e. g. by means of Blutooth, WiFi, or a mobile communications network.
  • the data can be encoded or compressed.
  • the message is received by the remote server computer (right side of the flow chart). If necessary, the data is decoded or decompressed.
  • step 160 the data received with the message is analyzed by an algorithm of the computer with respect to whether a reaction to the event is necessary.
  • the algorithm takes into account available data from the BIM database, i.e. a construction plan, comprising a target state of the construction of the structure at the building site, information about a current construction state of the structure (as-built) and information about participating parties in the construction of the structure. Based on this information, it is evaluated whether the event has an impact on the construction and to what extent. If necessary, options for reacting on the event are evaluated by the algorithm, and, if applicable, recommended options for reacting on the event are selected and assigned to the data.
  • step 170 the location information is read out, and the message (or its data, respectively) is assigned a corresponding set of coordinates in the three-dimensional model.
  • the data is send to a display unit, on which the three-dimensional model is displayed.
  • a notice is displayed in the model at the location of the event, comprising the data from the message. Due to the visualization of the notice at the position of the model that corresponds to the location of the event and due to the enclosed automatically generated recommendations, a user is enabled to grasp the context of the presented data and to decide how to react more quickly.
  • Figure 3 illustrates the detection of an event at the building site 3 and the transmission of a message comprising data about the event to a remote server computer 25.
  • an operator 4 of a mobile device 41 is situated in a room 31 of the structure.
  • the mobile device 41 comprises input means, such as a keypad or a touchscreen.
  • This text or other data may e. g. be related to his work progress, to measuring results, to missing parts, or other observations related to this room 31.
  • the mobile device 41 is equipped with means for determining its position on the building site 3 and with means for determining a time.
  • the device 41 generates a message 50 comprising the text or other data, a location information, e. g. a set of coordinates, and a time information.
  • the mobile device 41 furthermore comprises communication means adapted to transmit the message to a remote server computer 25 by means of a wireless data connection 27.
  • a direct data connection 27 is shown here, the connection to the server 25 can of course also be indirect, e. g. via the internet 26 or a mobile communications network.
  • the message 50 then for instance could be send as an email or SMS text.
  • the server 25 can be connected to one or more display units (not shown here) via the internet 26.
  • Figures 4a-d a visualization of the data of Figure 3 in a three-dimensional model 35 is illustrated.
  • Figure 4a shows the laptop 20 of Figure 1 having a display 21 and a mouse 22. Shown is the GUI with the three-dimensional model 35 before the transmission of the message containing the data.
  • the transmitted data which has been assigned a set of coordinates in the three-dimensional model 35 according to the location information with respect to the building site is received by the laptop 20.
  • the icon 6 is automatically displayed at the correct position in the model 35. In this case it pops up at the position of the room of Figure 3 where the message was generated.
  • a notification signal 61 can sound, to let the user know that a new message has arrived.
  • the user has moved the mouse cursor 23 onto the icon 6 and clicks the button of the mouse 22 to select the message.
  • the recommendations section can comprise shortcut links.
  • the icon 6 e. g. can be a miniature version of the notice 60 or a symbol coloured according to a kind of event or priority of reaction.
  • the icon 6 can be visualized as a two- or three-dimensional object in the three-dimensional model 35.
  • the icon 6 and or the notice 60 can be displayed semi-transparent in order not to hide the model 35.
  • the following Figures each show examples of sensor units at the building site, the sensor units generating and transmitting messages that can be visualized in a three-dimensional model of the building site.
  • a hygrometer unit 43 is positioned in a room 31 of the building 30.
  • a dehydrator 33 has been placed in this room to reduce the humidity in this room.
  • the hygrometer unit 43 is thus programmed to send a message as soon as a pre-defined humidity level is reached.
  • the generated message 51 that the room is dry enough to continue work is sent together with the location information (e. g. a room number) to the central computer unit (not shown here).
  • a geodetic measuring device 44 is positioned in the room 31 and continuously measures a distance to a distant wall with high precision in order to determine a stability of the structure 30. In pre-determined intervals, a message 52 is generated and transmitted automatically, the message 52 comprising one or more measured values, the exact time and the coordinates of the device 44 in a local coordinate system.
  • an operator 4 operates a hand-held laser-based distance measuring device 45 for measuring distances between points in the room 31, e. g. between corner points. After the measurements, the operator 4 initiates a generation and transmission of a message 52 by the device 45, the message comprising the relevant results and either coordinates determined by the device or a room number entered by the operator 4.
  • a multitude of camera units 46a, 46b, 46c is positioned on the building site 3, each of which comprising a motion sensor and a surveillance camera.
  • camera unit 46a detects a motion and starts recording a video.
  • a message 53 is generated comprising a file 56 with the video data and transmitted to the server.
  • an icon can be visualized in the three-dimensional model of the building site 3 at model coordinates corresponding to the real-world position of the camera unit 46a at the building site 3.
  • the video is replayed on the display.
  • each camera unit 46a, 46b, 46c can generate and transmit a message in pre-defined intervals, comprising an image taken by the surveillance camera.
  • the images can be visualized in real-time in the three-dimensional model at model coordinates corresponding to the real-world positions of the respective camera unit 46a, 46b, 46c at the building site 3.
  • an operator 4 operates a hand-held sensor unit 47 comprising a microphone, which is adapted to record and transmit voice messages to the server computer.
  • the operator 4 being situated at a room 31 of the building 30, speaks his observation or report into the microphone. For instance, the operator could report occurring problems such as lack of or defective material, bad preparatory work, or other unexpected conditions. In this example, the operator 4 simply reports that his task in the room 31 has been accomplished.
  • the sensor unit 47 generates a message 54 comprising an audio file 57 and transmits this message 54 to the remote computer.
  • the spoken words of the audio file can be translated into a text which is transmitted to the remote computer, or the translation is performed at the remote computer.
  • Figure 10 illustrates the output of the recorded message of Figure 9 to the user.
  • the three-dimensional model 35 of the structure is displayed on the display 21 of the laptop 20.
  • An icon 6 pops up at the correct position in the three-dimensional model 35.
  • the audio file with the recorded voice message 67 is played by a speaker system of the laptop 20.
  • a smoke detector 48 is located in a room 31 of the building 30 to be constructed on the building site 3. If this smoke detector 48 detects smoke 38, a message 58 is generated and transmitted to a remote server computer. In Figure 12 the output to the user is illustrated. As in the analysis of the event data the message has been evaluated to be urgent, together with the visualization of the icon 6 in the model 35 at the location of the smoke detector, a fire alert signal 68 is sounded without the user having to click the icon 6.
  • Figure 13 shows a computer system 2 of another exemplary embodiment of the construction management system, the computer system 2 comprising a server computer 25 on which a building information model (BIM) is provided.
  • the computer system 2 comprises a plurality of display devices 20, 20', 20". These are connected to the server computer 25 via the internet 26.
  • On the display 21 a three-dimensional model 35 of a building to be constructed is presented, wherein a plurality of icons 6 are displayed at model coordinates corresponding to the locations of events occurred at a construction site of the building.
  • One of the icons has been selected by the user by clicking on it with the mouse cursor, so that a notice 60 comprising information about the event is displayed.
  • the notice optionally also comprises recommended options for reacting to the event.
  • the three-dimensional model 35 of the structure can be displayed on a plurality of devices 20, 20', 20" simultaneously.
  • These devices comprise desktop computers, laptops and hand-held devices such as tablet computers or Smart-phones. All these devices are connected to a central server computer 25, for instance by means of the internet.
  • Each user can have a certain role assigned.
  • the users of the BIM can be site managers of the building site, architects of the building, the owner of the building, building project organisers, sub-contractors, site foremen and official construction inspectors.
  • the evaluation algorithm of the central server computer 25 is preferably adapted to evaluate which user, user group or role needs to know about which event, and thus to which of the devices 20, 20', 20" the data is provided. Furthermore, the evaluation algorithm can be adapted to evaluate options for reacting on the event for each user, user group or role individually, so that data about the same event can be provided with different assigned options to each of the devices 20, 20', 20".
  • the system can be setup to work offline and only be synchronized on the devices 20, 20', 20" when these are online. This applies particularly to mobile devices.
  • new notices can also be sent as push-up notices to mobile devices.
  • all detected events and generated messages can be logged and stored on a server or in a cloud until the end of the construction project or even longer, e. g. for conservation of evidence.

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Geometry (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Computer Hardware Design (AREA)
  • General Engineering & Computer Science (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Evolutionary Computation (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Development Economics (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Computational Mathematics (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Architecture (AREA)
  • Data Mining & Analysis (AREA)
  • Computer Graphics (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention pertains to a construction management system (1) for the construction of a structure (30), comprising a plurality of sensor means adapted to detect events at a building site (3) of the structure, a central computing unit (25) providing a building information model comprising a three-dimensional model (35) of the building site or of the structure, and at least one displaying device (20) that is adapted to display the three-dimensional model to a user, characterized in that the plurality of sensor means is adapted for generating data comprising information about a detected event, the system comprises a plurality of communication units adapted to transmit a message comprising the data and a location information to the central computing unit, the system is adapted to assign coordinates in the three-dimensional model according to the location information, the central computing unit has an evaluation algorithm adapted to evaluate options for reacting on the event by analyzing the data, thereby considering information from the building information model, the system is adapted to assign evaluated options to the data, and the at least one displaying device is adapted to display a note which is related to the data and to evaluated options to the user in real-time, wherein the note is displayed at the assigned coordinates in the three-dimensional model.

Description

  • The present invention pertains to a construction management system for a building site of a structure, and to a method for linking data to a three-dimensional model of the building site or of the structure. The data comprises information about an event occurring at the building site. Particularly, said three-dimensional model is a part of or comprises a building information model (BIM).
  • In the art of general construction work such as building construction and civil engineering, planning, progress observation, documentation, appropriate accounting are important key factors. In many instances, those aspects are getting more and more complex and dynamic, in particular due to the many parties involved, fluctuating human and/or objective resources, increased complexity of the end results, tighter schedules, increased costs of human resources, etc. Work that was formerly planed and overseen by a single manager is nowadays too complex for a single person and a splitting between multiple people often miscarries at the thereby uprising interfaces.
  • Therefore, it has been tried to expand automation and computerization in this technical field. For example, in the art of building construction EP 2 629 210 , JP 5489310 , CN 103886139 , US 2014/268064 or US 2014/192159 are giving examples of so called BIM-System approaches.
  • The technical problems therewith are multifarious. For example: Paper based orders might be outdated by the time they are issued to the executing entity; An immediate response to and purposeful handling of the unexpected is required, wherein all the consequences to a desired schedule have to be considered to minimize impact. Detecting, handling and documenting of the done work has to be established, deviations from a planed schedule have to be documented, determined and handled. Therein, the existing dependencies are often too complex to immediately cope with, in particular for an on-site executing entity.
  • In particular, in view of the desired flexible and efficient usage of executing entities, in view of the demand for increased efficiency and tight schedules, or often practiced real time replacement and spare management of structural and human resources, improvements going further than the standard human usage of computer and mobile phones are demanded. Also, the documentation demands are increased, e. g. by the project owner or principal, by the contractors or suppliers for proving flawlessness, by insurances, by government bodies, for settlement of damages, for handling compensation claims, to enforce due contractual penalties, for commissioning, etc.
  • It is therefore an object of the present invention to provide an improved construction management system for a building site of a structure. It is another object to provide an improved method for linking data to a building information model.
  • It is a particular object to provide such a system and method that allow a user to decide a proper reaction on an event more quickly.
  • At least one of these objects is achieved by the construction management system according to claim 1, the method according to claim 7 and/or the dependent claims of the present invention.
  • A first aspect of the present invention relates to a construction management system for the construction of a structure, e. g. a building or piece of infrastructure. The construction management system comprises a plurality of sensor means adapted to detect events at a building site of the structure and a central computing unit, e. g. a server computer, providing a building information model comprising at least a three-dimensional model of the building site or of the structure, a construction plan comprising a target state of the construction of the structure, information about a current construction state of the structure, and information about participants in the construction of the structure, e. g. building companies and handicraft businesses. Furthermore the system comprises at least one displaying device, e. g. a personal computer or Smartphone, that is adapted to display the three-dimensional model to a user, e. g. a site manager.
  • According to this aspect of the invention, the plurality of sensor means is adapted for generating data comprising information about a detected event, and the system comprises a plurality of communication units adapted to transmit a message comprising the data and a location information to the central computing unit. Furthermore, the system is adapted to assign coordinates in the three-dimensional model according to the location information, the central computing unit has an evaluation algorithm adapted to evaluate options for reacting on the event by analyzing the data, thereby considering information from the building information model, and the system is adapted to assign evaluated options to the data. Moreover, for presenting the data, the at least one displaying device is adapted to display a note which is related to the data and to evaluated options to the user in real-time, wherein the note is displayed at the assigned coordinates in the three-dimensional model.
  • In one embodiment of the construction management system, the sensor means are adapted to generate the data automatically. In another embodiment, the communication units are adapted to generate the message automatically. Particularly, each of the plurality of sensor means comprises one of the plurality of communication units.
  • In a further embodiment of the construction management system, the sensor means are adapted as or comprise cameras, distance meters, motion detectors, smoke detectors, thermometers, hygrometers, and/or input means that are adapted to allow an input by an operator, the input means particularly comprising a keypad for inputting a code or text or a microphone for inputting a voice message.
  • According to another embodiment, the sensor means are adapted to generate the location information, particularly automatically, the location information comprising information about a location of the event, or of the sensor means detecting the event. In particular, the location information comprises either coordinates in a global or local coordinate system, particularly in a coordinate system of the building site, or a designator or code identifying a pre-defined position or area in the structure or at the building site, particularly a room of a building.
  • According to yet another embodiment, the central computing unit comprises at least one server computer. Particularly, the central computing unit comprises a cluster of server computers working as a cloud system. In this embodiment, the communication units are adapted to transmit the message to the central computing unit by means of an internet or intranet connection, and/or the at least one displaying device is adapted to receive the data from the central computing unit by means of an internet or intranet connection.
  • In one embodiment, the construction management system comprises a plurality of displaying devices, each of which being adapted to display the three-dimensional model with the note to a user in real-time, each user having a role in the construction of the structure. In this embodiment, the evaluation algorithm is adapted to evaluate, based on said roles, on which of the displaying devices a note is to be displayed, and/or the system is adapted to assign evaluated options to the data for each displaying device individually. In particular, displaying the three-dimensional model with the note comprises focussing on those notes which are of particular relevance for the role of the user to which the model is displayed. Said focussing may comprise e. g. a highlighting of the notes, a zooming to the note in the model, or an alignment of the view on the model so that the note is centred.
  • A second aspect of the present invention relates to a method for linking data to a building information model, particularly by means of a construction management system according to the first aspect. The data comprises information about an event occurring at a building site of a structure, and the building information model comprises at least a three-dimensional model of the building site or of the structure, a construction plan for the construction of the structure comprising a target state of the construction of the structure, information about a current construction state of the structure, and information about participants in the construction of the structure. The method comprises
    • generating a message comprising the data and a location information;
    • transmitting the message to a central computing unit;
    • evaluating options for reacting on the event by analyzing the data, thereby considering information from the building information model, and assigning evaluated options to the data;
    • assigning coordinates in the three-dimensional model to the data according to the location information; and
    • displaying the three-dimensional model to at least one user, wherein a note which is related to the data and to the assigned options is displayed in the three-dimensional model at the assigned coordinates in real-time.
  • According to one embodiment of the method, the data is generated automatically by sensor means detecting the event, particularly wherein the message is generated automatically by a communication unit of the sensor means, and the options are evaluated automatically by an evaluation algorithm of the central computing unit.
  • According to another embodiment, the location information comprises information about a location of the event, of a sensor means detecting the event, or of a communication unit generating the message. The location information particularly comprises coordinates in a global or local coordinate system, particularly in a coordinate system of the building site, or a designator or code identifying a pre-defined position or area in the structure or at the building site, particularly a room.
  • In one embodiment, the message comprises information about a time of the event or of the detection of the event, wherein for evaluating options for reacting also the information about the time are considered, and/or the note is based also on the information about the time.
  • According to a further embodiment, the three-dimensional model is displayed simultaneously to a plurality of users on a plurality of displaying devices, each user having a role in the construction of the structure, wherein each of the displaying devices receives the data from the central computing unit, particularly by means of an internet or intranet connection, the central computing unit comprising at least one server computer, particularly a cluster of server computers working as a cloud system. In this embodiment, the method comprises evaluating, based on the roles, on which of the displaying devices a note is to be displayed, and/or assigning evaluated options to the data for each displaying device individually. In particular, displaying the three-dimensional model with the note comprises focusing on those notes which are of particular relevance for the role of the user to which the model is displayed.
  • In one embodiment of the method, displaying the note in the three-dimensional model comprises presenting the data and evaluated options to the user.
  • In another embodiment, displaying the note in the three-dimensional model comprises visualizing an icon at the assigned coordinates in real-time, wherein the icon is user-selectable, and upon a user-selection of the icon a notice is visualized based on the message. In particular,
    • together with visualizing the icon, a notification sound signal is played, the sound signal depending on a kind of the data, particularly on the kind of detected event;
    • the icon is assigned a design according to a kind of the data or of the message and visualized with the assigned design;
    • the user-selection of the icon comprises pointing a mouse cursor on the icon, or touching a touchpad;
    • evaluating options for reacting on the event comprises selecting recommended options for reacting on the event, and the visualizing the notice comprises presenting at least one recommended option to the user; and/or
    • the notice is visualized at the assigned coordinates. According to one embodiment, the data comprises picture data and/or audio data, particularly wherein
    • displaying the note comprises displaying an image based on the picture data;
    • the data comprises video data, and a video based on the video data is displayed upon user-selection of the respective note; and/or
    • generating the message comprises recording a voice message or a video message by an operator, the voice or video message being replayed by the display unit upon user-selection of the respective note.
  • A third aspect of the invention relates to a computer programme product comprising programme code which is stored on a machine-readable medium, or being embodied by an electromagnetic wave comprising a programme code segment, and having computer-executable instructions for performing, in particular when run on calculation means of a construction management system according to the first aspect of the invention, at least the following steps of the method according to the second aspect:
    • evaluating options for reacting on the event by analyzing the data, thereby considering information from the building information model, and assigning evaluated options to the data;
    • assigning coordinates in the three-dimensional model to the data according to the location information; and
    • displaying the three-dimensional model, wherein a note which is related to the data and to the assigned options is displayed in the three-dimensional model at the assigned coordinates in real-time.
  • The invention in the following will be described in detail by referring to exemplary embodiments that are accompanied by figures, in which:
  • Fig. 1
    shows the components of an exemplary embodiment of a construction management system according to the invention;
    Fig. 2
    illustrates an exemplary embodiment of a method for linking data comprising information about an event to a three-dimensional model;
    Fig. 3
    illustrates a first exemplary event detection and the sending of a message comprising event data to a server computer;
    Figs. 4a-d
    illustrate the visualization of the data in the three-dimensional model;
    Fig. 5
    shows a second exemplary event detection by means of hygrometer;
    Fig. 6
    shows a third exemplary event detection by means of an autonomous distance meter;
    Fig. 7
    shows a fourth exemplary event detection by means of a hand-held distance meter;
    Fig. 8
    shows a fifth exemplary event detection by means of cameras and motion sensors;
    Fig. 9
    shows a sixth exemplary event detection by means of a user input device having a microphone for recording a voice message;
    Fig. 10
    illustrates the visualization and replay of a voice message;
    Fig. 11
    shows a seventh exemplary event detection by means of a smoke detector;
    Fig. 12
    illustrates the visualization of a fire alert; and
    Fig. 13
    illustrates an exemplary embodiment of a construction management system having a plurality of display units.
  • In Figure 1 an exemplary embodiment of a construction management system 1 according to the invention is depicted.
  • The system comprises a computer system 2 comprising one or more display units 20 and a server computer 25 that are connected by means of an internet connection 26. In the shown example, the display unit 20 is a laptop comprising a display 21 (output means) and a mouse 22 (input means). On the display 21 a graphical user interface (GUI) is displayed with a mouse cursor 23 and several buttons 24a-c. In the GUI, a three-dimensional model 35 of a building 30 is visualized. A user (not shown) of the laptop is enabled to change the view on the model 35 by moving the cursor 23 on one of the GUI buttons 24a-c and clicking on a button of the mouse 22 (e. g. rotate the model, zoom in or out).
  • The system furthermore comprises at least one sensor unit (not shown) that is located at a building site 3 of the building 30 that is represented by the three-dimensional model 35. The sensor unit can be installed in the building 30 to work autonomously or be operated by an operator 4 at the building site.
  • The user of the display unit 20 has a certain role with respect to the construction, for instance is a site manager of the building site 3.
  • Instead of a building, the construction can of course also be or comprise infrastructure such as roads or railways. Further, instead of a single server computer 25, a cluster of servers, a cloud or similar means can be used.
  • Figure 2 is a flow chart illustrating a method 100 according to the invention for linking data comprising information about an event taking place at the building site to the three-dimensional model. The dotted line represents a virtual border between those method steps on the left of the line which take place at the building site 3 and those on the right taking place in the computer system 2 (see Figure 1).
  • The method 100 begins with detection 110 of an event. The event is detected by some kind of sensor unit at the building site. A multitude of sensor means and detectable events that occur on a building site are thinkable. For instance, the sensor units may comprise thermometers and hygrometers for detecting a temperature and wetness in a certain room of the construction, highly precise distance meters for detecting unwanted movement of the construction, motion detectors and cameras for detecting work progress or unauthorized persons, or smoke detectors for detecting fire. The sensor units can also comprise input means to allow input by an operator of the units. E. g. these comprise a keypad for inputting a code or text, a microphone for recording a voice message or a camera for recording a video message. This user input is then the event detected by the unit.
  • When the event is detected, in step 120 data is generated, particularly automatically by the sensor unit. For example, this data may comprise measured values, the information that a pre-defined threshold has been reached, video data, or the user input.
  • Furthermore, in step 130 a location is determined. Depending on the kind of sensor, this location can either be that of the sensor unit itself or that of the determined event. Alternatively, an operator can input the exact location of the event. The location can be either a set of coordinates or a code for a certain room or area.
  • Next, a message is generated in step 140. This message comprises at least the data from step 120 and the location information of step 130. Also, a time information can be added automatically.
  • In step 150, the message is transmitted via an internet or intranet connection to a computer, e. g. a remote server computer, having memory on which a model of the building site or structure is stored. To do so, the sensor units can comprise or be connected to a suitable communication means which sends the message by cable or wireless, e. g. by means of Blutooth, WiFi, or a mobile communications network. Optionally, before transmitting the message, the data can be encoded or compressed.
  • The message is received by the remote server computer (right side of the flow chart). If necessary, the data is decoded or decompressed.
  • In step 160, the data received with the message is analyzed by an algorithm of the computer with respect to whether a reaction to the event is necessary. The algorithm takes into account available data from the BIM database, i.e. a construction plan, comprising a target state of the construction of the structure at the building site, information about a current construction state of the structure (as-built) and information about participating parties in the construction of the structure. Based on this information, it is evaluated whether the event has an impact on the construction and to what extent. If necessary, options for reacting on the event are evaluated by the algorithm, and, if applicable, recommended options for reacting on the event are selected and assigned to the data.
  • In step 170, the location information is read out, and the message (or its data, respectively) is assigned a corresponding set of coordinates in the three-dimensional model.
  • The data is send to a display unit, on which the three-dimensional model is displayed. According to the assigned coordinates, in step 170 a notice is displayed in the model at the location of the event, comprising the data from the message. Due to the visualization of the notice at the position of the model that corresponds to the location of the event and due to the enclosed automatically generated recommendations, a user is enabled to grasp the context of the presented data and to decide how to react more quickly.
  • Figure 3 illustrates the detection of an event at the building site 3 and the transmission of a message comprising data about the event to a remote server computer 25.
  • In the building site 3 of the structure 30 an operator 4 of a mobile device 41 is situated in a room 31 of the structure. The mobile device 41 comprises input means, such as a keypad or a touchscreen. The operator 4, e. g. a construction worker or a craftsman, using the input means of the mobile device 41, writes a text or enters other data. This text or other data may e. g. be related to his work progress, to measuring results, to missing parts, or other observations related to this room 31.
  • The mobile device 41 is equipped with means for determining its position on the building site 3 and with means for determining a time. The device 41 generates a message 50 comprising the text or other data, a location information, e. g. a set of coordinates, and a time information.
  • The mobile device 41 furthermore comprises communication means adapted to transmit the message to a remote server computer 25 by means of a wireless data connection 27. Although a direct data connection 27 is shown here, the connection to the server 25 can of course also be indirect, e. g. via the internet 26 or a mobile communications network. The message 50 then for instance could be send as an email or SMS text. The server 25 can be connected to one or more display units (not shown here) via the internet 26.
  • In Figures 4a-d, a visualization of the data of Figure 3 in a three-dimensional model 35 is illustrated. Figure 4a shows the laptop 20 of Figure 1 having a display 21 and a mouse 22. Shown is the GUI with the three-dimensional model 35 before the transmission of the message containing the data.
  • In Figure 4b, the transmitted data which has been assigned a set of coordinates in the three-dimensional model 35 according to the location information with respect to the building site is received by the laptop 20. This results in the visualization of an icon 6 on the display 21. According to the invention, the icon 6 is automatically displayed at the correct position in the model 35. In this case it pops up at the position of the room of Figure 3 where the message was generated. Together with the visualization of the icon 6, a notification signal 61 can sound, to let the user know that a new message has arrived.
  • In Figure 4c, the user has moved the mouse cursor 23 onto the icon 6 and clicks the button of the mouse 22 to select the message. As shown in Figure 4d, this opens a notice window 60 comprising the data of the message and recommendations for proceeding. Optionally, the recommendations section can comprise shortcut links.
  • The icon 6 e. g. can be a miniature version of the notice 60 or a symbol coloured according to a kind of event or priority of reaction. The icon 6 can be visualized as a two- or three-dimensional object in the three-dimensional model 35. Optionally, the icon 6 and or the notice 60 can be displayed semi-transparent in order not to hide the model 35.
  • The following Figures each show examples of sensor units at the building site, the sensor units generating and transmitting messages that can be visualized in a three-dimensional model of the building site.
  • In Figure 5, a hygrometer unit 43 is positioned in a room 31 of the building 30. A dehydrator 33 has been placed in this room to reduce the humidity in this room. As soon as the room is dry enough, i.e. the humidity falls below a certain threshold, work can continue. The hygrometer unit 43 is thus programmed to send a message as soon as a pre-defined humidity level is reached. The generated message 51 that the room is dry enough to continue work is sent together with the location information (e. g. a room number) to the central computer unit (not shown here).
  • In the example of Figure 6, a geodetic measuring device 44 is positioned in the room 31 and continuously measures a distance to a distant wall with high precision in order to determine a stability of the structure 30. In pre-determined intervals, a message 52 is generated and transmitted automatically, the message 52 comprising one or more measured values, the exact time and the coordinates of the device 44 in a local coordinate system.
  • In the example of Figure 7, an operator 4 operates a hand-held laser-based distance measuring device 45 for measuring distances between points in the room 31, e. g. between corner points. After the measurements, the operator 4 initiates a generation and transmission of a message 52 by the device 45, the message comprising the relevant results and either coordinates determined by the device or a room number entered by the operator 4.
  • In the example of Figure 8, a multitude of camera units 46a, 46b, 46c is positioned on the building site 3, each of which comprising a motion sensor and a surveillance camera.
  • Here, camera unit 46a detects a motion and starts recording a video. A message 53 is generated comprising a file 56 with the video data and transmitted to the server. Then, as shown in Figure 4b, on a display an icon can be visualized in the three-dimensional model of the building site 3 at model coordinates corresponding to the real-world position of the camera unit 46a at the building site 3. When the icon is selected by the user, the video is replayed on the display.
  • Alternatively or additionally, each camera unit 46a, 46b, 46c can generate and transmit a message in pre-defined intervals, comprising an image taken by the surveillance camera. The images can be visualized in real-time in the three-dimensional model at model coordinates corresponding to the real-world positions of the respective camera unit 46a, 46b, 46c at the building site 3.
  • In the example of Figure 9, an operator 4 operates a hand-held sensor unit 47 comprising a microphone, which is adapted to record and transmit voice messages to the server computer. The operator 4, being situated at a room 31 of the building 30, speaks his observation or report into the microphone. For instance, the operator could report occurring problems such as lack of or defective material, bad preparatory work, or other unexpected conditions. In this example, the operator 4 simply reports that his task in the room 31 has been accomplished. The sensor unit 47 generates a message 54 comprising an audio file 57 and transmits this message 54 to the remote computer.
  • Alternatively, the spoken words of the audio file can be translated into a text which is transmitted to the remote computer, or the translation is performed at the remote computer.
  • Figure 10 illustrates the output of the recorded message of Figure 9 to the user. The three-dimensional model 35 of the structure is displayed on the display 21 of the laptop 20. An icon 6 pops up at the correct position in the three-dimensional model 35. By clicking on the icon 6 with the mouse cursor 23, the audio file with the recorded voice message 67 is played by a speaker system of the laptop 20.
  • Optionally, e. g. if the task has been accomplished earlier as expected, also a window with recommendations could open on the display 21 (as shown with respect to Figure 4d), e. g. suggesting advancing other works at that room.
  • In the example of Figure 11, a smoke detector 48 is located in a room 31 of the building 30 to be constructed on the building site 3. If this smoke detector 48 detects smoke 38, a message 58 is generated and transmitted to a remote server computer. In Figure 12 the output to the user is illustrated. As in the analysis of the event data the message has been evaluated to be urgent, together with the visualization of the icon 6 in the model 35 at the location of the smoke detector, a fire alert signal 68 is sounded without the user having to click the icon 6.
  • Figure 13 shows a computer system 2 of another exemplary embodiment of the construction management system, the computer system 2 comprising a server computer 25 on which a building information model (BIM) is provided. In this embodiment, the computer system 2 comprises a plurality of display devices 20, 20', 20". These are connected to the server computer 25 via the internet 26. On the display 21 a three-dimensional model 35 of a building to be constructed is presented, wherein a plurality of icons 6 are displayed at model coordinates corresponding to the locations of events occurred at a construction site of the building. One of the icons has been selected by the user by clicking on it with the mouse cursor, so that a notice 60 comprising information about the event is displayed. The notice optionally also comprises recommended options for reacting to the event.
  • As a multitude of persons can have access to the BIM, the three-dimensional model 35 of the structure can be displayed on a plurality of devices 20, 20', 20" simultaneously. These devices comprise desktop computers, laptops and hand-held devices such as tablet computers or Smart-phones. All these devices are connected to a central server computer 25, for instance by means of the internet.
  • Each user can have a certain role assigned. For instance, the users of the BIM can be site managers of the building site, architects of the building, the owner of the building, building project organisers, sub-contractors, site foremen and official construction inspectors.
  • The evaluation algorithm of the central server computer 25 is preferably adapted to evaluate which user, user group or role needs to know about which event, and thus to which of the devices 20, 20', 20" the data is provided. Furthermore, the evaluation algorithm can be adapted to evaluate options for reacting on the event for each user, user group or role individually, so that data about the same event can be provided with different assigned options to each of the devices 20, 20', 20".
  • The system can be setup to work offline and only be synchronized on the devices 20, 20', 20" when these are online. This applies particularly to mobile devices. Optionally, new notices can also be sent as push-up notices to mobile devices.
  • Optionally, all detected events and generated messages can be logged and stored on a server or in a cloud until the end of the construction project or even longer, e. g. for conservation of evidence.
  • Although the invention is illustrated above, partly with reference to some preferred embodiments, it must be understood that numerous modifications and combinations of different features of the embodiments can be made. All of these modifications lie within the scope of the appended claims.

Claims (15)

  1. Construction management system (1) for the construction of a structure (30), comprising
    - a plurality of sensor means adapted to detect events at a building site (3) of the structure (30);
    - a central computing unit (25) providing a building information model comprising at least
    ▪ a three-dimensional model (35) of the building site (3) or of the structure (30),
    ▪ a construction plan comprising a target state of the construction of the structure (30),
    ▪ information about a current construction state of the structure (30), and
    ▪ information about participants in the construction of the structure (30); and
    - at least one displaying device (20) that is adapted to display the three-dimensional model (35) to a user,
    characterized in that
    - the plurality of sensor means (41-48) is adapted for generating data comprising information about a detected event;
    - the system comprises a plurality of communication units adapted to transmit a message (50-54, 58) comprising the data and a location information to the central computing unit (25);
    - the system is adapted to assign coordinates in the three-dimensional model (35) according to the location information;
    - the central computing unit (25) has an evaluation algorithm adapted to evaluate options for reacting on the event by analyzing the data, thereby considering information from the building information model;
    - the system is adapted to assign evaluated options to the data; and
    - the at least one displaying device (20) is adapted to display a note (6, 60) which is related to the data and to evaluated options to the user in real-time, wherein the note (6, 60) is displayed at the assigned coordinates in the three-dimensional model (35).
  2. Construction management system (1) according to claim 1,
    characterized in that
    - the sensor means (41-48) are adapted to generate the data automatically, and/or
    - the communication units are adapted to generate the message automatically,
    particularly wherein each of the plurality of sensor means (41-48) comprises one of the plurality of communication units.
  3. Construction management system (1) according to claim 1 or claim 2,
    characterized in that
    the sensor means (41-48) are adapted as or comprise
    - cameras (46a-c),
    - distance meters (44, 45),
    - motion detectors,
    - smoke detectors (48),
    - thermometers,
    - hygrometers (43), and/or
    - input means (41, 47) that are adapted to allow an input by an operator (4), the input means (41, 47) particularly comprising a keypad for inputting a code or text (50) or a microphone for inputting a voice message (54).
  4. Construction management system (1) according to any one of the preceding claims,
    characterized in that
    the sensor means (41-48) are adapted to generate the location information, particularly automatically, the location information comprising information about a location of the event, or of the sensor means (41-48) detecting the event, particularly wherein the location information comprises
    - coordinates in a global or local coordinate system, particularly in a coordinate system of the building site (3); or
    - a designator or code identifying a pre-defined position or area in the structure (30) or at the building site (3), particularly a room (31).
  5. Construction management system (1) according to any one of the preceding claims,
    characterized in that
    the central computing unit (25) comprises at least one server computer, particularly a cluster of server computers working as a cloud system, wherein
    - the communication units are adapted to transmit the message (50-54, 58) to the central computing unit (25) by means of an internet (26) or intranet connection; and/or
    - the at least one displaying device (20) is adapted to receive the data from the central computing unit (25) by means of an internet (26) or intranet connection.
  6. Construction management system (1) according to any one of the preceding claims,
    characterized by
    a plurality of displaying devices (20, 20', 20"), each of which being adapted to display the three-dimensional model (35) with the note (6, 60) to a user in real-time, each user having a role in the construction of the structure (30), wherein
    - the evaluation algorithm is adapted to evaluate, based on the roles, on which of the displaying devices (20, 20', 20") a note (6, 60) is to be displayed, and/or
    - the system is adapted to assign evaluated options to the data for each displaying device (20, 20', 20") individually,
    particularly wherein displaying the three-dimensional model (35) with the note (6, 60) comprises focusing on those notes (6, 60) which are of particular relevance for the role of the user to which the model (35) is displayed.
  7. Method (100) for linking data to a building information model, particularly by means of a construction management system (1) according to any one of the preceding claims, wherein
    - the data comprises information about an event occurring at a building site (3) of a structure (30); and
    - the building information model comprises at least
    ▪ a three-dimensional model (35) of the building site (3) or of the structure (30),
    ▪ a construction plan for the construction of the structure (30) comprising a target state of the construction of the structure (30),
    ▪ information about a current construction state of the structure (30), and
    ▪ information about participants in the construction of the structure (30),
    the method (100) comprising
    - generating (140) a message (50-54, 58) comprising the data and a location information;
    - transmitting (150) the message (50-54, 58) to a central computing unit (25);
    - evaluating (160) options for reacting on the event by analyzing the data, thereby considering information from the building information model, and assigning evaluated options to the data;
    - assigning (170) coordinates in the three-dimensional model (35) to the data according to the location information; and
    - displaying (180) the three-dimensional model (35) to at least one user, wherein a note (6, 60) which is related to the data and to the assigned options is displayed in the three-dimensional model (35) at the assigned coordinates in real-time.
  8. Method (100) according to claim 7,
    characterized in that
    - the data is generated automatically by sensor means (41-48) detecting the event, particularly wherein the message (50-54, 58) is generated automatically by a communication unit of the sensor means (41-48); and
    - the options are evaluated automatically by an evaluation algorithm of the central computing unit (25).
  9. Method (100) according to claim 7 or claim 8,
    characterized in that
    the location information comprises information about a location of the event, a sensor means (41-48) detecting the event, or a communication unit generating the message (50-54, 58), particularly wherein the location information comprises
    - coordinates in a global or local coordinate system, particularly in a coordinate system of the building site (3); or
    - a designator or code identifying a pre-defined position or area in the structure (30) or at the building site (3), particularly a room (31).
  10. Method (100) according to any one of claims 7 to 9,
    characterized in that
    the message (50-54, 58) comprises information about a time of the event or of the detection of the event, wherein
    - for evaluating options for reacting also the information about the time are considered; and/or
    - the note (6, 60) is based also on the information about the time.
  11. Method (100) according to any one of claims 7 to 10,
    characterized in that
    the three-dimensional model (35) is displayed simultaneously to a plurality of users on a plurality of displaying devices (20, 20', 20"), each user having a role in the construction of the structure (30), wherein each of the displaying devices (20) receives the data from the central computing unit (25), particularly by means of an internet (26) or intranet connection, the central computing unit (25) comprising at least one server computer, particularly a cluster of server computers working as a cloud system, wherein
    - the method (100) comprises evaluating, based on the roles, on which of the displaying devices (20, 20', 20") a note (6, 60) is to be displayed, and/or
    - options for reacting are assigned to the data for each displaying device (20, 20', 20") individually,
    particularly wherein displaying the three-dimensional model (35) with the note (6, 60) comprises focusing on those notes (6, 60) which are of particular relevance for the role of the user to which the model (35) is displayed.
  12. Method (100) according to any one of claims 7 to 11,
    characterized in that
    displaying the note (6, 60) in the three-dimensional model (35) comprises presenting the data and evaluated options to the user.
  13. Method (100) according to any one of the preceding claims,
    characterized in that
    displaying the note (6, 60) in the three-dimensional model (35) comprises visualizing an icon (6) at the assigned coordinates in real-time, wherein the icon (6) is user-selectable, and upon a user-selection of the icon (6) a notice (60) is visualized based on the message (50-54, 58), particularly wherein
    - together with visualizing the icon (6), a notification sound signal (61, 68) is played, the sound signal (61, 68) depending on a kind of the data, particularly on the kind of detected event;
    - the icon (6) is assigned a design according to a kind of the data or of the message (50-54, 58) and visualized with the assigned design;
    - the user-selection of the icon (6) comprises pointing a mouse cursor (23) on the icon (6), or touching a touchpad;
    - evaluating options for reacting on the event comprises selecting recommended options for reacting on the event, and the visualizing the notice (60) comprises presenting at least one recommended option to the user; and/or
    - the notice (60) is visualized at the assigned coordinates.
  14. Method (100) according to any one of the preceding claims,
    characterized in that
    the data comprises picture data and/or audio data (57), particularly wherein
    - displaying the note (6, 60) comprises displaying an image based on the picture data;
    - the data comprises video data (56), and a video based on the video data is displayed upon user-selection of the respective note (6, 60); and/or
    - generating the message comprises recording a voice message (54) or a video message (53) by an operator (4), the voice or video message being replayed by the display unit (20) upon user-selection of the respective note (6, 60) or automatically being transferred into a text message which is presented upon user-selection of the respective note (6, 60).
  15. Computer programme product comprising programme code which is stored on a machine-readable medium, or being embodied by an electromagnetic wave comprising a programme code segment, and having computer-executable instructions for performing, in particular when run on calculation means of a construction management system (1) according to any one of claims 1 to 6, at least the following steps of the method according to one of the claims 7 to 14:
    - evaluating (160) options for reacting on the event by analyzing the data, thereby considering information from the building information model, and assigning evaluated options to the data;
    - assigning (170) coordinates in the three-dimensional model (35) to the data according to the location information; and
    - displaying (180) the three-dimensional model (35), wherein a note (6, 60) which is related to the data and to the assigned options is displayed in the three-dimensional model (35) at the assigned coordinates in real-time.
EP16161760.0A 2016-03-22 2016-03-22 Construction management Withdrawn EP3223221A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
EP16161760.0A EP3223221A1 (en) 2016-03-22 2016-03-22 Construction management
US15/466,701 US10664781B2 (en) 2016-03-22 2017-03-22 Construction management system and method for linking data to a building information model
CN201710172788.8A CN107220398B (en) 2016-03-22 2017-03-22 Construction management system and method for linking data to building information model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP16161760.0A EP3223221A1 (en) 2016-03-22 2016-03-22 Construction management

Publications (1)

Publication Number Publication Date
EP3223221A1 true EP3223221A1 (en) 2017-09-27

Family

ID=55589724

Family Applications (1)

Application Number Title Priority Date Filing Date
EP16161760.0A Withdrawn EP3223221A1 (en) 2016-03-22 2016-03-22 Construction management

Country Status (3)

Country Link
US (1) US10664781B2 (en)
EP (1) EP3223221A1 (en)
CN (1) CN107220398B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102018200226A1 (en) * 2018-01-09 2019-07-11 Robert Bosch Gmbh Method for the management and detection of building material, in particular in the construction of buildings
CN111080491A (en) * 2019-12-12 2020-04-28 成都阳帆网络科技有限公司 Construction site inspection system and method based on video identification
CN111401581A (en) * 2020-03-11 2020-07-10 中煤航测遥感集团有限公司 Building operation and maintenance management method, system, equipment and storage medium
CN113159475A (en) * 2020-12-04 2021-07-23 中国国家铁路集团有限公司 Infrastructure life cycle monitoring platform and method

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11244412B1 (en) 2017-05-12 2022-02-08 Zillow, Inc. Interface for uncompleted homes planning
CN107909287A (en) * 2017-12-01 2018-04-13 南京智行信息科技有限公司 A kind of method of the infrastructure management based on BIM
CN110895723B (en) 2018-09-13 2024-12-10 开利公司 Fire detection system - intelligent fire signal transmission for fire equipment
CN110895864B (en) * 2018-09-13 2024-02-09 开利公司 Fire detection system tool for constraint-consistent placement of fire equipment
CN109559087B (en) * 2018-09-20 2021-06-04 中建科技有限公司深圳分公司 Building visualization system and method
CN109670899B (en) * 2018-11-05 2022-04-19 陈树铭 BIM-based (building information modeling-based) integrated big data analysis system and method for house property sale, loading and management
CN110232731A (en) * 2019-04-16 2019-09-13 广东康云科技有限公司 A kind of smart city system and its implementation
WO2021025616A1 (en) * 2019-08-02 2021-02-11 Global Engineers Investment Singapore Pte. Ltd. Method and system for managing a crane and/or construction site
CN110599113A (en) * 2019-08-12 2019-12-20 新疆交通建设集团股份有限公司 BIM technology-based highway construction real-time management and control system and work flow thereof
CN111461487B (en) * 2020-03-02 2021-05-18 广州高新工程顾问有限公司 Indoor decoration engineering wisdom management system based on BIM
CN111833016A (en) * 2020-07-08 2020-10-27 惠州市筑成工程管理有限公司 Infrastructure building supervision method based on BIM
CN112182692B (en) * 2020-09-03 2023-04-07 同济大学建筑设计研究院(集团)有限公司 Building project file processing method and device, computer equipment and storage medium
CN112456575A (en) * 2020-11-17 2021-03-09 北控水务建设发展有限公司 Application method of building information system in water treatment
CN112583906A (en) * 2020-12-04 2021-03-30 久瓴(江苏)数字智能科技有限公司 Information processing method and device based on BIM (building information modeling), storage medium and electronic equipment
CN112697191A (en) * 2020-12-31 2021-04-23 龙岩烟草工业有限责任公司 Sensor working state display method and device and storage medium
CN112950773A (en) * 2021-04-07 2021-06-11 万翼科技有限公司 Data processing method and device based on building information model and processing server
CN114139243A (en) * 2021-09-14 2022-03-04 江苏中云筑智慧运维研究院有限公司 BIM-based bridge fire emergency rescue method, terminal and storage medium
CN114626133B (en) * 2022-03-28 2024-07-26 北京商询科技有限公司 Model display method, device and equipment
WO2023224031A1 (en) * 2022-05-17 2023-11-23 パナソニック インテレクチュアル プロパティ コーポレーション オブ アメリカ Information processing method, information processing device, and information processing program
CN117592749B (en) * 2023-12-07 2025-02-28 深圳市丰怡国际建筑设计有限公司 Intelligent scheduling method and system for prefabricated building components using BIM technology

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1990001763A1 (en) * 1988-07-29 1990-02-22 Lionel James Barden Personnel guidance system
JPH11311023A (en) * 1998-04-30 1999-11-09 Sekisui House Ltd Computer processing system for building construction work
JP2005173698A (en) * 2003-12-08 2005-06-30 Toda Constr Co Ltd Construction inspection system
US20050171790A1 (en) * 2004-01-30 2005-08-04 Theodore Thomas Blackmon Construction project management system and method
US20090210277A1 (en) * 2008-02-14 2009-08-20 Hardin H Wesley System and method for managing a geographically-expansive construction project
GB2461647A (en) * 2008-10-10 2010-01-13 Ilm Legal Services Ltd A system for surveying buildings and evaluation of building properties
JP2010266202A (en) * 2009-04-13 2010-11-25 Itt:Kk Image processing apparatus for photo measurement, field recording system using the same, package recording system, and laser processing system
WO2012171138A1 (en) * 2011-06-14 2012-12-20 Metrologic Instruments, Inc. Camera registration and video integration in 3-d geometry model
WO2013056395A1 (en) * 2011-10-19 2013-04-25 Honeywell International Inc. Model-based generation of information and evacuation messages
EP2629210A1 (en) 2012-02-20 2013-08-21 Solideo Systems Co., Ltd. Method of providing data included in building information modeling data file, computer readable medium therefor, system using the method, and method of providing data using building information modeling server
KR101354688B1 (en) * 2013-07-05 2014-01-27 한국건설기술연구원 System and method for supervision of construction site
US20140095119A1 (en) * 2011-06-13 2014-04-03 Industry-Academic Cooperation Foundation, Yonsei University System and method for location-based construction project management
JP5489310B1 (en) 2012-12-20 2014-05-14 東芝エレベータ株式会社 BIM system and method
CN103886139A (en) 2014-02-27 2014-06-25 上海蓝色星球科技有限公司 Event interaction method based on building information model (BIM)
KR20140108465A (en) * 2013-02-28 2014-09-11 한국남부발전 주식회사 System for construction information creation and method for construction information creation using the same
US20140268064A1 (en) 2013-03-13 2014-09-18 Trimble Navigation Limited Method and apparatus for projection of bim information
US20140316837A1 (en) * 2013-04-19 2014-10-23 Trimble Navigation Limited Method and system of construction project management
CN104765905A (en) * 2015-02-13 2015-07-08 上海同筑信息科技有限公司 (Building Information Modeling) BIM based plan graph and first view-angle split-screen synchronous display method and system
CN104794331A (en) * 2015-04-07 2015-07-22 上海大学 Deep foundation pit heath monitoring and management system and management method thereof

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6144375A (en) * 1998-08-14 2000-11-07 Praja Inc. Multi-perspective viewer for content-based interactivity
US7865285B2 (en) * 2006-12-27 2011-01-04 Caterpillar Inc Machine control system and method
US20090089018A1 (en) * 2007-09-28 2009-04-02 Harris Corporation Geospatial modeling system providing building generation based upon user input on 3d model and related methods
CA2754225A1 (en) * 2011-08-29 2013-02-28 Clover Point Cartographics Ltd. Geographic asset management system and method
US9070216B2 (en) * 2011-12-14 2015-06-30 The Board Of Trustees Of The University Of Illinois Four-dimensional augmented reality models for interactive visualization and automated construction progress monitoring
KR20160002688A (en) * 2013-02-13 2016-01-08 오피40 홀딩스, 인코포레이티드 Distributed cloud services and uses thereof
US10296665B2 (en) * 2013-03-15 2019-05-21 On Center Software, Inc. Image management in construction project software programs
US20150234377A1 (en) * 2014-02-18 2015-08-20 ResiWeb Limited Construction management system
US9852238B2 (en) * 2014-04-24 2017-12-26 The Board Of Trustees Of The University Of Illinois 4D vizualization of building design and construction modeling with photographs
CN105240051B (en) * 2015-10-10 2018-03-23 成都金自天正智能控制有限公司 A kind of fieldbus mine TT&C system
CN105389931A (en) 2015-11-18 2016-03-09 西安天璇智能系统科技有限公司 Intelligent monitoring and warning system for forest fire prevention

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1990001763A1 (en) * 1988-07-29 1990-02-22 Lionel James Barden Personnel guidance system
JPH11311023A (en) * 1998-04-30 1999-11-09 Sekisui House Ltd Computer processing system for building construction work
JP2005173698A (en) * 2003-12-08 2005-06-30 Toda Constr Co Ltd Construction inspection system
US20050171790A1 (en) * 2004-01-30 2005-08-04 Theodore Thomas Blackmon Construction project management system and method
US20090210277A1 (en) * 2008-02-14 2009-08-20 Hardin H Wesley System and method for managing a geographically-expansive construction project
GB2461647A (en) * 2008-10-10 2010-01-13 Ilm Legal Services Ltd A system for surveying buildings and evaluation of building properties
JP2010266202A (en) * 2009-04-13 2010-11-25 Itt:Kk Image processing apparatus for photo measurement, field recording system using the same, package recording system, and laser processing system
US20140095119A1 (en) * 2011-06-13 2014-04-03 Industry-Academic Cooperation Foundation, Yonsei University System and method for location-based construction project management
WO2012171138A1 (en) * 2011-06-14 2012-12-20 Metrologic Instruments, Inc. Camera registration and video integration in 3-d geometry model
US20140192159A1 (en) 2011-06-14 2014-07-10 Metrologic Instruments, Inc. Camera registration and video integration in 3d geometry model
WO2013056395A1 (en) * 2011-10-19 2013-04-25 Honeywell International Inc. Model-based generation of information and evacuation messages
EP2629210A1 (en) 2012-02-20 2013-08-21 Solideo Systems Co., Ltd. Method of providing data included in building information modeling data file, computer readable medium therefor, system using the method, and method of providing data using building information modeling server
JP5489310B1 (en) 2012-12-20 2014-05-14 東芝エレベータ株式会社 BIM system and method
KR20140108465A (en) * 2013-02-28 2014-09-11 한국남부발전 주식회사 System for construction information creation and method for construction information creation using the same
US20140268064A1 (en) 2013-03-13 2014-09-18 Trimble Navigation Limited Method and apparatus for projection of bim information
US20140316837A1 (en) * 2013-04-19 2014-10-23 Trimble Navigation Limited Method and system of construction project management
KR101354688B1 (en) * 2013-07-05 2014-01-27 한국건설기술연구원 System and method for supervision of construction site
CN103886139A (en) 2014-02-27 2014-06-25 上海蓝色星球科技有限公司 Event interaction method based on building information model (BIM)
CN104765905A (en) * 2015-02-13 2015-07-08 上海同筑信息科技有限公司 (Building Information Modeling) BIM based plan graph and first view-angle split-screen synchronous display method and system
CN104794331A (en) * 2015-04-07 2015-07-22 上海大学 Deep foundation pit heath monitoring and management system and management method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102018200226A1 (en) * 2018-01-09 2019-07-11 Robert Bosch Gmbh Method for the management and detection of building material, in particular in the construction of buildings
CN111080491A (en) * 2019-12-12 2020-04-28 成都阳帆网络科技有限公司 Construction site inspection system and method based on video identification
CN111401581A (en) * 2020-03-11 2020-07-10 中煤航测遥感集团有限公司 Building operation and maintenance management method, system, equipment and storage medium
CN113159475A (en) * 2020-12-04 2021-07-23 中国国家铁路集团有限公司 Infrastructure life cycle monitoring platform and method
CN113159475B (en) * 2020-12-04 2024-03-15 中国国家铁路集团有限公司 Infrastructure full life cycle monitoring platform and method

Also Published As

Publication number Publication date
CN107220398B (en) 2021-08-27
US10664781B2 (en) 2020-05-26
CN107220398A (en) 2017-09-29
US20170278037A1 (en) 2017-09-28

Similar Documents

Publication Publication Date Title
US10664781B2 (en) Construction management system and method for linking data to a building information model
US20220092234A1 (en) Detection of defects within physical infrastructure by leveraging ai
US20210097475A1 (en) Networked activity management with media collection and selectable activity insertion
US20180129193A1 (en) Patrol check system, patrol check device, patrol check method, and storage medium
Chong et al. Improving quality and performance of facility management using building information modelling
Sandanayake et al. Residential building defects investigation and mitigation–a comparative review in Victoria, Australia, for understanding the way forward
US12373613B2 (en) Construction knowledge graph
Zhao et al. Using real-time indoor resource positioning to track the progress of tasks in construction sites
Omar et al. Using BIM to automate construction site activities
Abdelalim et al. Dynamic labor tracking system in construction project using BIM technology
Ani et al. Building information modeling (BIM)-based building condition assessment: A survey of water ponding defect on a flat roof
JP7554889B2 (en) CONCRETE STRUCTURE MANAGEMENT DEVICE, INFORMATION PROCESSING SYSTEM, CONCRETE STRUCTURE MANAGEMENT METHOD, AND PROGRAM
JP7312581B2 (en) Concrete structure management device, information processing system, concrete structure management method, and program
WO2022149071A1 (en) Capturing and analysis of construction site images
CN107219825B (en) Method for providing inspection instruction, job site management system, and storage medium
Görsch et al. Unlocking productivity: revealing waste and hidden disturbances impacting MEP workers
Zenker et al. Design and implementation of a collaborative smartwatch application supporting employees in industrial workflows
US11790519B2 (en) Systems and methods for menu directed inspection
WO2020075061A1 (en) Asset management
Omar et al. Automated data collection for progress tracking purposes: a review of related techniques
Hou et al. An integration framework of advanced technologies for productivity improvement for LNG mega-projects
CN118096440A (en) Water system management method and device, storage medium and electronic equipment
US20250258485A1 (en) Plant management device, plant management method, and storage medium
WO2022266757A1 (en) System for management of facility construction and maintenance
JP2016001442A (en) Map data processing of environment location evaluation and output system thereof, computer program product and method of the same

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

17P Request for examination filed

Effective date: 20180327

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

17Q First examination report despatched

Effective date: 20180430

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20180911