DE19834072A1 - Position correction method for permanent ways - Google Patents

Position correction method for permanent ways

Info

Publication number
DE19834072A1
DE19834072A1 DE19834072A DE19834072A DE19834072A1 DE 19834072 A1 DE19834072 A1 DE 19834072A1 DE 19834072 A DE19834072 A DE 19834072A DE 19834072 A DE19834072 A DE 19834072A DE 19834072 A1 DE19834072 A1 DE 19834072A1
Authority
DE
Germany
Prior art keywords
layers
layer
lifting
pillow
slab track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19834072A
Other languages
German (de)
Inventor
Stefan Kolb
Hermann Theil
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ed Zueblin AG
Original Assignee
Ed Zueblin AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ed Zueblin AG filed Critical Ed Zueblin AG
Priority to DE19834072A priority Critical patent/DE19834072A1/en
Priority to DE19848655A priority patent/DE19848655B4/en
Publication of DE19834072A1 publication Critical patent/DE19834072A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/04Lifting or levelling of tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B19/00Protection of permanent way against development of dust or against the effect of wind, sun, frost, or corrosion; Means to reduce development of noise
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/04Removing the ballast; Machines therefor, whether or not additionally adapted for taking-up ballast
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • E01C7/26Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders mixed with other materials, e.g. cement, rubber, leather, fibre
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/02Removing or re-contouring ballast
    • E01B2203/022Horizontal chain
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/04Cleaning or reconditioning ballast or ground beneath
    • E01B2203/047Adding material, e.g. tar, glue, protective layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/03Injecting, mixing or spraying additives into or onto ballast or underground

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)
  • Road Paving Structures (AREA)

Abstract

Before filler material is introduced into the permanent way, the individual layers or the material within the layers are cut by mechanical tools. This creates defined mainly level border surfaces, forming a space to be filled. During cutting, and pref. in the softer layer, a working space of pref. 5-100 mm height is formed without lifting the permanent way. The working space is cut by wedges, cutter bars, band saws, etc., milling cutters, and/or jet cutting.

Description

Technisches GebietTechnical field

Um den Schienenverkehr attraktiver zu machen, werden die Geschwindigkei­ ten der Züge ständig erhöht. Der klassische Schottergleisbau stößt dabei an seine Grenzen, denn bei der Auslegung auf Hochgeschwindigkeitszüge wer­ den die Wartungsintervalle aufgrund der hohen Belastungen auf den Schot­ ter und der geforderten genauen Lage der Gleise kurz. Seit einigen Jahr­ zehnten geht daher die Tendenz zu sogenannten schotterlosen Oberbauten, auch Feste Fahrbahnen genannt, die längere Wartungsintervalle aufweisen. Schwierigkeiten bereitet dabei aber immer noch die zwar seltene, aber doch erforderliche Sanierung der Festen Fahrbahnen bei Setzungen des Unter­ grundes.To make rail transport more attractive, the speed ten of the trains constantly increased. The classic ballast track construction triggers its limits, because when designing for high-speed trains who the maintenance intervals due to the high loads on the sheet ter and the exact location of the tracks required. For a few years tenth is therefore the tendency towards so-called ballastless superstructures, also called slab tracks that have longer maintenance intervals. Difficulties are still the rare, but still required refurbishment of the slab tracks when subsidence reason.

Die Erfindung betrifft nun Verfahren und Vorrichtungen zur Sanierung von Festen Fahrbahnen durch Einbringen ausgleichenden Materials unter oder in zu sanierenden Fahrbahnkörper.The invention now relates to methods and devices for the remediation of Solid roadways by introducing leveling material under or in road surface to be renovated.

Stand der TechnikState of the art

Es sind verschiedene Verfahren bekannt, Absenkungen Fester Fahrbahnen zu beseitigen und entstandene Hohlräume unter Festen Fahrbahnen wieder aufzufüllen.Various methods are known, lowering of slab tracks eliminate and create voids under slab tracks again replenish.

Allen diesen Verfahren ist dabei gemein, daß sie die Fahrbahn anheben und den dadurch entstehenden Spalt darunter verfüllen, oder daß sie unter die Fahrbahn Material einpressen und sie dadurch wieder anheben.All these methods have in common that they raise the road and fill the resulting gap underneath, or that they are under the Press material into the roadway and lift it up again.

So ist z. B. aus der DE 42 01 108 C2 ein Verfahren bekannt, welches es er­ laubt, eine endlose Betonfahrbahn aufgrund ihrer hinreichenden Elastizität in einem zu sanierenden Bereich anzuheben und dort zu unterfüllen. Für diesen Zweck weist die Betonfahrbahn entweder Aussparungskammern auf, in die hydraulische Pressen eingesetzt werden, oder die Anhebung erfolgt mittels Quertraversen.So z. B. from DE 42 01 108 C2 a method known, which he leaves an endless concrete pavement due to its sufficient elasticity in to raise and refill an area to be renovated. For this Purpose, the concrete pavement either has recess chambers into which hydraulic presses are used, or the lifting takes place by means of Crossbeams.

Eine vollständige direkte Verfüllung der unregelmäßigen, sich aus schmalen und verwundenen Kanälen zusammensetzenden Hohlräume unter der Fe­ sten Fahrbahn, wie sie beim Anheben oder Einpressen des Verfüllgutes ent­ stehen, ist nun aus physikalischen Gründen schwierig: So kann man für die Füllgeschwindigkeit V/t (Volumen pro Zeit) der schmalen Hohlräume in erster Näherung das Hagen-Poiseuille'sche Gesetz heranziehen:
It is now difficult for physical reasons to fill the irregular cavities under the solid roadway, which are made up of narrow and twisted channels, as they arise when the filling material is lifted or pressed in. It is now difficult for physical reasons: For the filling speed V / t (volume per time) of the narrow cavities in a first approximation use Hagen-Poiseuille's law:

Dabei ist V/t der Volumenfluß einer Flüssigkeit mit der Viskosität η pro Zeiteinheit (Stromstärke), und Δp der Druckabfall über die Länge l eines Roh­ res mit Radius R. Bei Abnahme des Radius auf 1/10 des Anfangswertes ver­ ringert sich somit die Fließgeschwindigkeit auf 1/10000!
Erschwerend für den Füllvorgang kommt noch hinzu, daß die meisten Ver­ füllgüter (z. B. Beton) thixotrop sind, d. h., ihre Viskosität hängt stark von der Fließgeschwindigkeit ab! Das bedeutet, daß bei enger werdendem Quer­ schnitt der zu verfüllenden Kanäle die abnehmende Fließgeschwindigkeit die Viskosität exponentiell emporschnellen läßt, sobald eine bestimmte Ge­ schwindigkeit unterschritten wird. Feinste Kanäle sind somit so gut wie nicht verfüllbar und wirken nur wie ein Sieb, in das noch Wasser eindringen kann, wohingegen die festen Bestandteile früh steckenbleiben. Diese feinen nicht verfüllten Räume bilden wiederum Schwachstellen für künftige Ausspülungen und Senkungen.
V / t is the volume flow of a liquid with the viscosity η per unit of time (current), and Δp the pressure drop over the length l of a pipe with radius R. When the radius is reduced to 1/10 of the initial value, the flow velocity is reduced to 1/10000!
To make matters more difficult for the filling process, most filling materials (e.g. concrete) are thixotropic, ie their viscosity depends strongly on the flow rate! This means that as the cross-section of the channels to be filled becomes narrower, the decreasing flow rate causes the viscosity to skyrocket as soon as the speed falls below a certain level. The finest channels are practically impossible to fill and only act like a sieve into which water can still penetrate, whereas the solid components get stuck early. These fine, unfilled spaces in turn form weak spots for future flushing and subsidence.

Eine Entfernung von sehr losem und leicht zugänglichem Material unterhalb der Gleise ist aus dem konventionellen Schotterbau bekannt. So sind z. B. von den Firmen Plasser & Theurer (Wien) oder J. Hubert (Nürnberg) auf den Gleisen verfahrbare Planumsverbesserer im Einsatz, die die Schienen samt Schwellen an neu zu unterfütternden Stellen anheben und den Schotter dort austauschen und auch ein neues Planum einfügen. A removal of very loose and easily accessible material below the track is known from conventional ballast construction. So z. B. from Plasser & Theurer (Vienna) or J. Hubert (Nuremberg) to the Traversable track reformers in use, which include the rails Raise sleepers at new points to be relined and the ballast there exchange and also insert a new formation.  

Aufgabe der ErfindungObject of the invention

Aufgabe der Erfindung ist es, die geschilderten Füllprobleme, die beim Ein­ bringen von Material unter die Feste Fahrbahn zum Zwecke der Sanierung auftreten, zu vermeiden und somit Ausgleichsschichten ohne Fehler und Schwachstellen schaffen zu können.The object of the invention is to solve the filling problems described above bring material under the slab track for the purpose of renovation occur, avoid and therefore compensation layers without errors and To be able to create weak points.

Darstellung der ErfindungPresentation of the invention

Die Aufgabe wird durch die im Kennzeichen des Hauptanspruchs angegebe­ nen Merkmale gelöst.The task is indicated by the in the indicator of the main claim Features resolved.

Die Erfindung sieht hierzu vor, zunächst die Schichten der Festen Fahrbahn mit mechanischen Mitteln dergestalt aufzutrennen, daß definierte Grenzflä­ chen gebildet werden, bzw. bei größerem Materialaustrag Räume, die später einfacher wieder verfüllt werden können. Die Fahrbahn muß dann nicht oder kaum über die Sollhöhe angehoben werden und es treten keine Probleme wegen der Verfüllung schmaler unregelmäßig geformter Kanäle auf.To this end, the invention provides for the layers of the slab track to separate by mechanical means such that defined boundary surface Chen are formed, or with larger material discharge rooms that later can be filled in more easily. The lane does not have to or can hardly be raised above the target height and there are no problems because of the filling of narrow, irregularly shaped channels.

In einem ersten möglichen Ausführungsbeispiel wird die Tragplatte an den betreffenden Stellen angehoben und dabei die Feste Fahrbahn vom Unter­ grund getrennt.In a first possible embodiment, the support plate is attached to the relevant areas raised and the slab track from the lower reason separated.

(Feste Fahrbahnen weisen einen schichtartigen Aufbau auf, z. B. den folgen­ den: auf Erdreich folgt eine kaum zusammenhängende Frostschutzschicht, dann eine sogenannte hydraulisch gebundene Tragschicht (HGT), darüber dann ein armiertes Betonband, die Tragplatte, auf dem sich Schwellen mit Schienen befinden können oder auf entsprechenden Auflagern direkt die Schienen. Gemeinhin wird der Begriff Feste Fahrbahn für die Gesamtheit der Schichten von der HGT ab aufwärts verwendet. Die Frostschutzschicht ist dann bereits ein Teil des Untergrundes. Das im folgenden zu beschreibende Verfahren ist nun am zweckmäßigsten zwischen der HGT und der Frost­ schutzschicht einsetzbar, obwohl es, wenn auch mit größerem Aufwand, auch zwischen armiertem Beton band und HGT einsetzbar wäre.)
Das Auftrennen der Schichten (bevorzugt also Betonfahrbahn und HGT) un­ ter Ausbildung definierter Grenzflächen kann z. B. durch Spalten mit einem Keil in Fortschrittsrichtung der Sanierung erfolgen, eventuell mit Unterstüt­ zung der Trennung oder auch ausschließlich durch Trennung mittels Räum­ ketten, Bandsägen, Stichsägen, Wasserstrahl oder ähnlichem. Alle diese Verfahren schaffen definierte Grenzflächen (im Gegensatz zu bisher ge­ bräuchlichen Sanierungsverfahren) und alle tragen mehr oder weniger auch Material ab. (Auch der Keil alleine trägt schon ab, denn es wird die obere fe­ stere Schicht von noch anhängenden Teilen der unteren Schicht befreit, wo­ durch eine glattere Fläche entsteht.)
Um nun ausreichend Arbeitsraum für spätere Schritte zu erhalten, wird dabei in einer bevorzugten Ausführungsform des Verfahrens eine der Schichten, bevorzugt die untere (weniger feste), verstärkt abgetragen. Es kann aber natürlich auch der Verbindungsbereich der beiden Schichten räumlich abge­ tragen werden.
(Solid carriageways have a layered structure, e.g. the following: the soil is followed by a hardly continuous frost protection layer, then a so-called hydraulically bound base layer (HGT), then a reinforced concrete belt, the base plate on which sleepers with rails The term slab track is generally used for the totality of the layers from the HGT downwards. The frost protection layer is then already part of the subsurface. The procedure to be described below is now most appropriate between the HGT and the frost protection layer can be used, although it could also be used between the reinforced concrete belt and the HGT, if with more effort.)
The separation of the layers (preferably concrete road and HGT) un development of defined interfaces can, for. B. by splitting with a wedge in the direction of progress of the refurbishment, possibly with the support of the separation or chains only by separation by means of clearing, band saws, jigsaws, water jet or the like. All of these processes create defined interfaces (in contrast to previously used renovation processes) and all more or less also remove material. (Even the wedge alone wears off, because it removes any remaining parts of the lower layer from the upper, more solid layer, which creates a smoother surface.)
In order to obtain sufficient working space for later steps, one of the layers, preferably the lower (less solid), is removed in a preferred embodiment of the method. Of course, the connection area of the two layers can also be spatially removed.

Dadurch, daß Material abgetragen und dadurch Arbeitsraum geschaffen wird, braucht man die obenliegende Feste Fahrbahn weniger anzuheben. Dies ist von großem Vorteil, da der angehobene Betonkörper nur eine eingeschränk­ te Elastizität aufweist. Herkömmliche Hebe- und Sanierverfahren erzeugen hingegen bei bruchfreier Anhebung nur winzige und chaotisch geformte Zwi­ schenräume, die schwer zu verfüllen sind. Das erfindungsgemäße Verfahren erlaubt daher auch, sehr kleinräumige Setzungen zu sanieren.By removing material and creating work space, you don't need to lift the slab surface above. This is of great advantage, since the raised concrete body is only limited te elasticity. Generate conventional lifting and renovation processes on the other hand, with break-free lifting only tiny and chaotically shaped twos spaces that are difficult to fill. The method according to the invention therefore also allows renovation of very small-scale settlements.

Bei Varianten des erfindungsgemäßen Verfahrens ist es sogar möglich, die Feste Fahrbahn überhaupt nicht, oder nur sehr geringfügig, über das spätere Sollmaß anzuheben, nämlich dann, wenn nachher mit einem setzungsfreien Material verfüllt wird, z. B. mit verdichtetem Beton, das plastisch selbstan­ schmiegend ist und daher keiner Oberflächenbearbeitung bedarf.In variants of the method according to the invention, it is even possible to use the Solid carriageway not at all, or only very slightly, over the later one To increase the target dimension, namely if afterwards with a settlement-free Material is filled, e.g. B. with compacted concrete, the plastically self is cuddly and therefore does not require any surface treatment.

Um das Auftrennen der entscheidenden Schichten einer Festen Fahrbahn im Falle einer späteren Sanierung zu verbessern, kann auch schon bei ihrer Herstellung eine Sollbruchstelle, z. B. eine Trennfolie oder eine nicht oder nur schwach gebundene Schicht (z. B. Sand), eingebaut werden. Eine Trenn­ schicht wiese dabei bevorzugt eine Schichtdicke von etwa 2 bis 5 Zentime­ tern auf.To separate the crucial layers of a slab track in the In the event of a later refurbishment, you can already improve it Manufacturing a predetermined breaking point, e.g. B. a release film or not or only weakly bound layer (e.g. sand). A separation Layer meadow preferably has a layer thickness of about 2 to 5 centimes tern on.

Das Anheben der oberen abgetrennten Schichten erfolgt im angeführten Ausführungsbeispiel durch Gleiten oder Rollen über eine schiefe Ebene. Es können hierzu Gleitmittel eingepreßtwerden, z. B. auch schon im spaltenden Keil. Ein Anheben an den Schienen ist ungünstig wegen des anhängenden großen Gewichtes der Festen Fahrbahn.The upper separated layers are lifted in the above Embodiment by sliding or rolling over an inclined plane. It Lubricants can be pressed in, e.g. B. already in the divisive Wedge. Lifting on the rails is unfavorable because of the attached heavy weight of the slab track.

In den entstandenen Arbeitsraum wird nun die berechnete Menge Verfüllma­ terial maßgenau z. B. durch Gurte, Schnecken, durch Blasen, Spülen, Sprü­ hen oder Leitbleche eingebracht. Das Verfüllmaterial kann ungebunden blei­ ben oder durch Zusatz von Bindemitteln (hydraulisch oder auf Kunststoffba­ sis) verfestigt werden. Die Verdichtung erfolgt z. B. durch Walzen und Rütteln, das Nivellieren mit Abziehbohle oder Hobel. Die Oberfläche kann dann mit Klebermaterial besprüht werden. Als Verfüllgut eigenen sich z. B. Sand, Kies. Splitt, Bitumen, oder aufbereitetes Material aus der Auftrennung. Nach der Herstellung der Ausgleichsschicht senkt man die Fahrbahn ab. Durch Rütteln der Fahrbahn, z. B. mit Außenrüttlern, kann nachverdichtet werden und eine bessere Verbindung der vereinigten Flächen erzielt werden. Der Setzungsausgleich wird kontrolliert.The calculated amount of backfill is now in the created work area dimensionally accurate z. B. by belts, snails, by blowing, rinsing, spray hen or baffles introduced. The backfill material can lead unbound ben or by adding binders (hydraulic or on plastic Ba sis) are solidified. The compression takes place z. B. by rolling and shaking, leveling with a screed or planer. The surface can then be used  Adhesive material to be sprayed. As backfill z. B. sand, gravel. Grit, bitumen, or processed material from the separation. After the leveling layer has been made, the roadway is lowered. By shaking the road, e.g. B. with external vibrators, can be densified and a better connection of the united areas can be achieved. The settlement settlement is checked.

Es kann auch ohne starkes Anheben über die Sollage und späteres Absen­ ken Material unter eine ungefähr in Sollage befindliche Feste Fahrbahn ein­ gebracht werden. Außenrüttler übernehmen dabei die Verdichtung des Mate­ rials während der Verfüllung. Besonders einfach ist dies bei aushärtenden Massen, z. B. Beton. Da die Last der Festen Fahrbahn allerdings noch nicht auf dem sanierten Untergrund aufliegt, ist es besser einen erfahrungsgemä­ ßen Wert von einigen Millimetern über die Sollhöhe anzuheben, der dann nach Entfernen der anhebenden Mittel durch das Gewicht der Festen Fahr­ bahn niedergedrückt wird.It can also be done without lifting the target position and then lowering it later Insert material under a slab track approximately in the desired position to be brought. External vibrators take over the compaction of the mate rials during backfill. This is particularly easy with hardening Masses, e.g. B. Concrete. Since the load of the slab track is not yet on the renovated surface, it is better to experience one a few millimeters above the target height, which then after removing the lifting means by the weight of the fixed driving path is depressed.

Im Gegensatz zu den herkömmlichen, diskontinuierlichen, Verfahren zur Sa­ nierung Fester Fahrbahnen handelt es sich in diesem beschriebenen Ausfüh­ rungsbeispiel um ein kontinuierliches Verfahren, bei dem ein zu sanierender Streckenabschnitt von einem Sanierungsgerät kontinuierlich überfahren wird. Das heißt natürlich nicht, daß das Sanierungsgerät nicht auch manchmal kei­ ne Fortbewegung ausführt. Wesentlich ist, daß für jeden Fahrbahnabschnitt, der am Anfang des Gerätes aufgetrennt und angehoben wird, am Ende des Sanierungsgerätes auch wieder ein Fahrbahnabschnitt auf die Unterfüllung abgesenkt bzw. nur unterfüllt wird, wenn nur auf Sollhöhe angehoben wird. (Interessanterweise ähnelt das Vorgehen der Maschine dabei einem Vorbild in der Natur, nämlich der Reparatur von DNA in den Körperzellen, bei denen ein Reparaturenzymkomplex an der verdrillten und verknäulten DNA kontinu­ ierlich entlanggleitet, sie dort entknäult und ihre Stränge trennt, repariert, und dann die alte Konfiguration wieder herstellt.)
Das Verfahren kann weitgehend automatisiert werden, z. B. ist folgender Ab­ lauf denkbar:
Ein Meßwagen fährt vor dem Ausgleich über die zu sanierende Strecke, ein in Fahrbahnnähe angebrachter Drucker druckt im Tintenstrahlverfahren in kurzen Abständen als Barcode verschlüsselt die Ist- und Sollhöhe an der be­ treffenden Position auf die Betonoberfläche der Festen Fahrbahn. Detekto­ ren an der Setzungsausgleichsmaschine können dann beliebig oft an jeder Stelle diese Werte ablesen. Diese können dann für den aktuellen Ausgleich, d. h. die Steuerung der Nivellier- bzw. Abzugsbohle in Zone III (siehe Fig. 1) und die Dosierung des Verfüllmaterials ausgewertet werden.
In contrast to the conventional, discontinuous, method for renovating slab tracks, this exemplary embodiment described is a continuous method in which a section of the route to be rehabilitated is continuously run over by a rehabilitation device. Of course, this does not mean that the renovation equipment does not sometimes also carry out locomotion. It is essential that for each section of roadway that is opened and lifted at the beginning of the device, at the end of the renovation device, a section of roadway is again lowered to the underfill or only underfilled if it is only raised to the desired height. (Interestingly, the process of the machine resembles a model in nature, namely the repair of DNA in the body's cells, in which a repair enzyme complex continuously glides along the twisted and tangled DNA, uncoils it there and separates its strands, repairs, and then that restores the old configuration.)
The process can be largely automated, e.g. B. the following is possible:
A measuring car drives over the line to be rehabilitated before compensation, a printer attached near the road prints in short intervals the ink and ink code as a barcode encodes the actual and target height at the relevant position on the concrete surface of the slab track. Detectors on the settlement compensation machine can then read these values at any point as often as required. These can then be evaluated for the current compensation, ie the control of the leveling or screed in zone III (see Fig. 1) and the metering of the backfill material.

Ein zweites Ausführungsbeispiel des erfindungsgemäßen Verfahrens sieht kein kontinuierliches Anheben und Unterfüttern vor, sondern zuerst ein ab­ schnittsweises Aufsägen der Schichten der Festen Fahrbahn, bevorzugt mittels einer Seilsäge (Seilsägen haben einen Durchmesser von etwa 1 Zen­ timeter). Dies kann vor dem Einjustieren der Sollage geschehen oder erst nach dem Anheben auf Sollage. Seilsägen haben den Vorteil, noch an den unzugänglichsten Stellen einsetzbar zu sein, auch um Ecken herum. Bevorzugt ist das Aufsägen vor dem Anheben, da sich die Schichten dann nur an der Schnittstelle und nicht chaotisch irgendwo im Untergrund auftren­ nen. Weiterhin sind keine externen Hebevorrichtungen nötig, wenn die Fahr­ bahn durch den Einpreßdruck des Verfüllmaterials, welches in den Spalt ein­ gepreßt wird, angehoben wird.A second embodiment of the inventive method sees no continuous lifting and relining before, but first off sawing the layers of the slab track in sections, preferred using a wire saw (wire saws have a diameter of about 1 Zen timeter). This can happen before the target position is adjusted or only after lifting to target position. Cable saws have the advantage of to be used in the most inaccessible places, even around corners. Sawing is preferred before lifting, since the layers then become only occur at the interface and not chaotically anywhere in the underground nen. Furthermore, no external lifting devices are necessary if the driving path through the injection pressure of the backfill material which is in the gap is pressed, is raised.

Das Anheben ist als iterativer Prozeß möglich, bei dem in mehreren Durch­ gängender bis zu mehreren hundert Metern lange Bereich nivelliert wird. Der große Vorteil dieser Ausführungsvariante ist die Sanierung unter rollendem Rad: Es treten keine Sperrpausen auf!
Das Auftrennen geschieht bevorzugt zwischen HGT und Frostschutzschicht, die fast ungebunden ist und daher sehr leicht entfernt wird, ohne großen Verschleiß an der teuren Seilsäge hervorzurufen.
Lifting is possible as an iterative process, in which leveling is carried out in several passages up to several hundred meters long. The great advantage of this design variant is the renovation under a rolling wheel: there are no blocking breaks!
The separation preferably takes place between the HGT and the frost protection layer, which is almost unbound and is therefore very easy to remove without causing excessive wear on the expensive wire saw.

Eine spezielle Ausführung des Verfahrens sieht dann vor, mittels Rahmen, oder zwischen zwei schützenden Blechen, die quer zur Trasse durch den entstehenden Schlitz geführt werden, kissenartige Objekte einzubringen, die nach Entfernen der Rahmen/Bleche in dem Schlitz verbleiben und dann mit Verfüllgut aufgefüllt werden. (Das Einbringen zwischen zwei Blechen verhin­ dert ein Aufreißen der Kissen. Zum Entfernen der Bleche werden die Bleche, die bevorzugt an ihrer Ziehkante verbunden/zusammengeklemmt sind, gezo­ gen, während das Kissen von hinten festgehalten wird.) Die Kissen, die z. B. aus einem starken Folienmaterial, aber auch einem Textil (Vlies oder Gewe­ be) oder hohlen Blechkörper bestehen können, haben den Vorteil, daß bei ih­ rer Verfüllung kein Verfüllmaterial in die Frostschutzschicht eindringen kann und dann deren Körnung verändert und Funktion beeinträchtigt. Dies wäre sonst nur dadurch zu verhindern, daß das gleiche, ein ähnliches oder ein gröberes Material als die Frostschutzschicht eingefüllt wird.A special execution of the method then provides, by means of frames, or between two protective sheets that run across the route through the resulting slot are guided to bring pillow-like objects that after removing the frames / sheets remain in the slot and then with Filled goods to be filled. (Prevent insertion between two sheets tearing the pillows. To remove the sheets, the sheets, which are preferably connected / clamped together at their pulling edge conditions, while the pillow is held from behind.) B. made of a strong film material, but also a textile (fleece or fabric be) or hollow sheet metal body can have the advantage that at ih No backfill material can penetrate the frost protection layer and then changed their grain size and impaired function. This would be otherwise only by preventing the same, a similar or a coarser material than the frost protection layer is filled.

Das Kissen weißt mindestens einen Einfüllstutzen auf, durch den das Mate­ rial eingepreßt oder eingespült wird. Es ist sinnvoll, zusätzlich auch noch ei­ nen Auslaufstutzen vorzusehen, durch den überschüssiges Verfüllmaterial oder auch ein Trägermaterial des Verfüllgutes (z. B. Wasser bei Einspülungen Sand) abfließen kann.The pillow has at least one filler neck through which the mate rial is pressed or flushed. It also makes sense to add egg  to provide a spout due to the excess filling material or a carrier material for the backfill material (e.g. water during induction Sand) can drain off.

Die Gefahr der Verunreinigung der Frostschutzschicht ist nicht vorhanden, wenn zwischen Tragplatte und HGT aufgetrennt und verfüllt wird. In diesem Falle kann auch mit feinkörnigen Materialien oder bevorzugt aushärtenden breiigen Massen ohne Kissen verfüllt werden. Nachteil ist aber der höhere Verschleiß an der Säge. Durch das Verfüllen mit aushärtenden Massen wird erneut ein Verbund zwischen HGT und Tragplatte hergestellt.There is no risk of contamination of the frost protection layer, if it is cut and filled between the support plate and the HGT. In this Trap can also with fine-grained materials or preferably curing mushy masses can be filled without pillows. The disadvantage is the higher one Wear on the saw. By filling with hardening masses another bond between HGT and support plate.

Das Aufsägen geschieht bevorzugt abschnittsweise, damit der Spalt nicht so ausgedehnt ist, daß die Fahrbahn durchhängt und ein Einfädeln der Kissen nicht mehr möglich ist. Ansonsten müßte mit externen Mitteln angehoben werden, bevor das Kissen eingeführt wird.The sawing is preferably done in sections, so that the gap is not so It is extended that the road sags and the cushions are threaded is no longer possible. Otherwise it would have to be raised with external funds before the pillow is inserted.

Um die Seilsäge unter die Fahrbahn zu bringen, wird zuerst ein Loch durch die entsprechende Schicht gebohrt, durch welches das Seil in geöffnetem Zustand gefädelt wird. Durch ein zweites Loch in definierter Entfernung wird das Seil dann auf die Ursprungsseite der Fahrbahn zurückgeführt und wieder zum Ring geschlossen. Es ist auch möglich, das Seil oberhalb der Tragplatte unter den Schienen zwischen den Schwellen hindurch zurückzuführen, ohne daß der Bahnverkehr beeinträchtigt wird.In order to bring the wire saw under the roadway, a hole is first made through the corresponding layer drilled through which the rope in the open Condition is threaded. Through a second hole at a defined distance the rope then returned to the origin side of the lane and again closed to the ring. It is also possible to place the rope above the support plate under the rails between the sleepers, without that rail traffic is affected.

Die Seilsäge läuft über Umlenkrollen, die bewegt werden und dabei den Schnitt erzeugen (s. Fig. 5a). Wenn die Umlenkrollen weit genug auseinan­ der liegen, so ist es möglich, mit dem gleichen Seil gleich zwei Schnitte her­ zustellen (s. schematische Fig. 5b), wobei zwischen den zwei Schnittflächen eine Stütze verbleibt, die erst weggesägt wird, wenn die Fahrbahn bereits mit Füllkissen unterfüttert wurde. Das Verfahren läuft dann in etwa folgenderma­ ßen ab:
The wire saw runs over deflection rollers which are moved and thereby produce the cut (see Fig. 5a). If the pulleys are far enough apart, it is possible to make two cuts with the same rope (see schematic Fig. 5b), with a support remaining between the two cut surfaces that is only sawn away when the roadway is already was padded with filling pillows. The process then proceeds as follows:

  • 1. Sägen der Abschnitte A1 und Ak (k ist eine ganze positive Zahl)1. Saw sections A 1 and A k (k is an integer positive number)
  • 2. Einbringen der Füllkissen in A1 und Ak 2. Insert the filling cushions in A 1 and A k
  • 3. Sägen der Abschnitte A2 und Ak+1 3. Saw sections A 2 and A k + 1
  • 4. Einbringen der Füllkissen in A2 und Ak+1 4. Insert the filling cushions in A 2 and A k + 1

(2k-3). Sägen der Abschnitte Ak-1 (2k-3). Sawing sections A k-1

und A2k-2
and A 2k-2

(2k-2). Einbringen der Füllkissen in Ak-1 (2k-2). Introducing the filling cushions in A k-1

und A2k-2 and A 2k-2

..

Damit ist der Streckenabschnitt beendet, alles aufgesägt und unterfüttert. (Fig. 5b zeigt als Beispiel den Fall für k = 3.) This concludes the section of the route, sawn up and relined everything. ( Fig. 5b shows the case for k = 3 as an example.)

Bei diesem Verfahren müssen nur anfangs zwei Löcher gebohrt werden, dann arbeitet sich die Säge sukzessive den Bahndamm entlang, bis der weiter zurück liegende Sägebereich den schon mit Kissen unterfütterten Be­ reich des Bahndammes erreicht. Sollen längere Strecken unterfüttert werden, so muß die Säge in den neuen Abschnitt umgesetzt werden.With this method, only two holes need to be drilled initially, then the saw works its way along the embankment until the saw area further back the Be already lined with pillows reached the embankment. If longer distances are to be relined, so the saw must be moved to the new section.

Die einzelnen Abschnitte Ak sind bevorzugt gleich groß. Eine sinnvolle Aus­ dehnung sind etwa 1 bis 2 Meter. Prinzipiell sind auch unterschiedlich große Abschnitte möglich, doch macht dies das Verfahren nicht einfacher! Es ist aber auch möglich, die Sägeschnitte nicht in einer Ebene, sondern in zwei nebeneinanderliegenden Abschnitten Ar und Ar+1 in zwei unterschiedli­ chen Höhen anzubringen, wobei sich die Abschnitte auch etwas überlappen können. Dann müssen allerdings für jeden Sägeschnitt neue Löcher gebohrt werden. Dieses Verfahren ist nur zwischen Tragplatte und HGT ausführbar, da die Frostschutzschicht nicht oder kaum gebunden ist.The individual sections A k are preferably of the same size. A reasonable extension is about 1 to 2 meters. In principle, sections of different sizes are also possible, but this does not make the process easier! However, it is also possible to make the saw cuts not in one plane, but in two adjacent sections A r and A r + 1 in two different heights, the sections also being able to overlap somewhat. Then, however, new holes have to be drilled for each saw cut. This procedure can only be carried out between the support plate and the HGT, since the frost protection layer is not or hardly bound.

Fig. 5c zeigt schematisch eine weitere Möglichkeiten der schlangenlinienarti­ gen Sägeseilführung, bei der noch mehr Sägeschnitte mit dem gleichen Seil zur gleichen Zeit durchführbar sind. Fig. 5c shows schematically a further possibilities of the schlangenlinienarti gene saw cable guide, in which even more saw cuts can be carried out with the same rope at the same time.

Es ist auch möglich, mit einer Seilsäge, aber auch mit einer anderen Säge, Fräse oder dergleichen, kontinuierlich die Fahrbahn aufzutrennen, so wie es im ersten Ausführungsbeispiel beschrieben wurde. Jedesmal, wenn ein Ab­ schnitt, der einer Kissenbreite entspricht, aufgetrennt wurde, wird dann ein solches Kissen eingezogen. Bevorzugt wird dabei gleich als Stütze für die Fahrbahn Verfüllmaterial in das Kissen eingebracht, so daß weiter gesägt werden kann.It is also possible with a wire saw, but also with another saw, Milling machine or the like to continuously cut the roadway like it was described in the first embodiment. Every time an Ab cut that corresponds to a pillow width, is then cut such a pillow. Is preferred as a support for the Roadway filling material introduced into the pillow, so that sawed further can be.

Anstatt nur ein Kissen einzuziehen ist es auch möglich zwei oder mehr Kis­ sen übereinanderliegend einzuziehen. Dies erlaubt, zu späteren Zeitpunkten erneut eine Nachjustierung der Fahrbahn vorzunehmen, ohne erneut aufsä­ gen zu müssen. Es wird dann einfach das noch leere Kissen verfüllt. Bei nichthärtenden Verfüllmassen ist es allerdings auch möglich, mit nur einer Kissenlage auszukommen, da die Kissenwand dann nicht mit dem Verfüllgut verklebt.Instead of just pulling in a pillow, it is also possible to have two or more kis to move in one above the other. This allows for later times readjust the road again without sowing again to have to. The empty pillow is then simply filled. At non-hardening filling compounds, however, it is also possible with only one Pillow layer get along, because the pillow wall then not with the backfill glued.

In Gegenden, in denen keine Frostschutzschicht eingebaut wird, weil der sandige Untergrund eine solche darstellt, dient die Seilsäge der Entfernung von Unrauhigkeiten an der Unterseite der HGT. Ist diese sehr sorgfältig und an ihrer Unterseite plan hergestellt, so erübrigt sich der Einsatz einer Seilsä­ ge und es kann auf billigere Weise eine definierte Schicht unter der HGT ausgeräumt werden (Ausspülen, Absaugen, Ausblasen, Ausschaben, "Auslöffeln, . . .").In areas where no frost protection layer is installed because of the The rope saw is used to remove the sandy subsoil of roughness on the underside of the HGT. This is very careful and Made flat on the underside, there is no need to use a wire saw ge and it can cheaper a defined layer under the HGT  be cleared out (rinsing, suction, blowing out, scraping, "Spoon out,...").

Das zweite Ausführungsbeispiel des erfindungsgemäßen Verfahrens weist den großen Vorteil auf, daß alle Arbeitsvorgänge von der Seite her erfolgen und die Schienen daher weiterhin, wenn auch mit geringerer Geschwindig­ keit, vom fahrplanmäßigen Verkehr befahren werden können.The second embodiment of the method according to the invention has the great advantage that all operations are done from the side and the rails therefore continue, albeit at a slower speed speed, can be driven by the scheduled traffic.

Durch die seitliche Arbeitsweise ist es auch möglich, jederzeit durch die Ein­ füllöffnungen der Kissen wieder nachzujustieren, ohne dabei den Zugverkehr unterbrechen zu müssen.Due to the side working, it is also possible at any time by the one Readjust the filling openings of the pillows without changing the train traffic to have to interrupt.

Die Fig. 1 zeigt schematisch die Vorgehensweise bei der Sanierung gemäß dem ersten Ausführungsbeispiel des erfindungsgemäßen Verfahrens. In der dargestellten Variante wird die Feste Fahrbahn über das spätere Sollniveau angehoben. Fig. 1 shows schematically the procedure for renovation according to the first embodiment of the method according to the invention. In the variant shown, the slab track is raised above the later target level.

Im Abschnitt I findet der Trennvorgang der Schichten voneinander statt. Da­ bei wird bevorzugt Material von mindestens einer der zu trennenden Schich­ ten abgetragen.In section I, the layers are separated from each other. There material from at least one of the layers to be separated is preferred removed.

Im Abschnitt II wird die Fahrbahn durch geeignete Mittel angehoben.In section II, the road surface is raised by suitable means.

Im Abschnitt III wird das Füllmaterial als Ausgleich eingebracht und bearbei­ tet.In section III, the filling material is introduced and processed as compensation tet.

In Abschnitt IV wird die angehobene Fahrbahn wieder abgesenkt und mit der Ausgleichsschicht verbunden.In section IV the raised roadway is lowered again and with the Compensation layer connected.

Fig. 2 zeigt beispielhaft als Mittel für die Schaffung zweier definierter Grenz­ flächen durch einfache Auftrennung ohne starken Materialabtrag von den zu trennenden Schichten ein keilförmiges Messer, das in Arbeitsrichtung vorge­ schoben wird. Fig. 2 shows an example of a means for creating two defined interfaces by simple separation without heavy material removal from the layers to be separated, a wedge-shaped knife that is pushed in the working direction.

Fig. 3 zeigt eine aufwendigere Ausführung eines solchen Messers, welches an seiner vordersten Kante unterstützende Hochdruckwasserstrahlen zum Aufschneiden erzeugt (selbstverständlich kann man dort auch eine Räumket­ te oder Seilsäge einbauen) und über Düsen Schmier- und Gleitmittel zwi­ schen Fahrbahn und Messer einleitet. An der Rückseite des Messerbalkens wird über Öffnungen Verfüllmaterial in den freigeräumten Raum eingebracht. Der in Arbeitsrichtung vorwärtsbewegte Messerbalken führt hier also sämtli­ che nötigen Funktionen der Zonen I bis IV aus. Dabei kann durch die Nei­ gung des Messerbalkens die Höhe des Setzungsausgleichs gesteuert wer­ den. Fig. 3 shows a more complex version of such a knife, which generates supporting high-pressure water jets for cutting at its foremost edge (of course you can also install a Räumket or wire saw there) and introduces lubricant and lubricant between the roadway and knife via nozzles. At the back of the cutter bar, filling material is introduced into the cleared space through openings. The knife bar moved forward in the working direction thus performs all the necessary functions of zones I to IV. The level of settlement compensation can be controlled by the inclination of the cutter bar.

Fig. 4 ist die schematische Darstellung einer Gesamtausführungsform, bei der mittels einer Fräse oder Spaltsäge Material der zu trennenden Schichten ab­ getragen wird (hier beispielhaft der unteren weicheren). Die Abstützung er­ folgt in diesem Beispiel nicht an weiter vorn und weiter hinten liegenden Stellen der Festen Fahrbahn, sondern neben der Festen Fahrbahn. Der Übersichtlichkeit halber sind nur zwei auf Raupen verfahrbare Stützen ge­ zeigt. Eine bessere Stützung ergibt sich bei Verwendung von Stützen im Be­ reich der höchsten Anhebung der Fahrbahn. Fig. 4 is a schematic representation of an overall embodiment in which material of the layers to be separated is removed by means of a milling cutter or a splitting saw (here, for example, the lower softer layer). In this example, the support does not follow at points on the slab track further ahead and further back, but next to the slab track. For the sake of clarity, only two supports that can be moved on caterpillars are shown. Better support results when using supports in the area of the highest elevation of the road.

Fig. 5a zeigt gemäß zweitem Ausführungsbeispiel des erfindungsgemäßen Verfahrens von oben betrachtet einen Längsschnitt in der Grenzschicht zwi­ schen HGT und Frostschutzschicht der Festen Fahrbahn, in der eine Seilsä­ ge einen definierten Schnitt erzeugt. Fig. 5a shows according to the second embodiment of the method according to the invention viewed from above, a longitudinal section in the boundary layer between HGT's and frost protection layer of the slab track, in which a wire saw generates a defined cut.

Fig. 5b zeigt die simultane Durchführung eines Doppelschnitts. Fig. 5b shows the simultaneous performance of a double-section.

Fig. 5c zeigt die Seilführung bei der simultanen Durchführung eines Mehr­ fachschnitts Fig. 5c shows the cable guide in the simultaneous implementation of a multi-section

Fig. 6 zeigt, wie ein auffüllbares Kissen zwischen zwei Blechen in den aufge­ sägten Spalt eingebracht wird. Die Bleche werden nachher alleine herausge­ zogen und das Kissen verbleibt vor Ort zur Verfüllung mit der benötigten Menge Füllmaterial. Fig. 6 shows how a refillable cushion is inserted between two sheets in the sawn-up gap. The sheets are then pulled out alone and the pillow remains on site for filling with the required amount of filler material.

BezugszeichenlisteReference list

11

Tragplatte
Support plate

22nd

Hydraulisch gebundene Tragschicht (HGT)
Hydraulically bound base layer (HGT)

33rd

Ausgleichsschicht
Leveling layer

44th

Fräse
Milling machine

55

Halteplatten
Holding plates

66

Schnecke
slug

77

Messer
knife

88th

Messerbalken
Knife bar

99

Düse (z. B. Wasserstrahldüse)
Nozzle (e.g. water jet nozzle)

1010th

Schmierleitung
Lubrication line

1111

Schnecke/Verpreßbohrung
Auger / grouting hole

1212th

Verfüllbohrung
Backfill hole

1313

Verdichter
compressor

1414

Abziehvorrichtung
Puller

1515

Frostschutzschicht
Frost protection layer

1616

Vorratssilo mit Verfüllmaterial
Storage silo with filling material

1717th

Steuerstand
Steering position

1818th

Abstützung, verfahrbar (z. B. Raupe)
Support, movable (e.g. caterpillar)

1919th

horizontaler Schnitt durch Grenzfläche zwischen HGT und Frostschutzschicht, bzw. zwischen Tragplatte und HGT, oder innerhalb einer dieser Schichten
horizontal section through the interface between the HGT and the frost protection layer, or between the support plate and the HGT, or within one of these layers

2020th

durch Seilsäge erzeugte definierte Grenzfläche, bzw. definier­ ter Zwischenraum
Defined interface or defined interspace created by wire saw

2121

Seilsäge
Wire saw

2222

Umlenkrolle
Pulley

2323

Antriebsrolle
Drive roller

2424th

Abschnittsgrenze
Section boundary

2525th

verfüllbares Kissen
fillable pillow

2626

Doppelblech zum Einziehen des Kissens Double sheet for pulling in the pillow

2525th

in den Zwischen­ raum in the meantime room

2020th

.
.

Claims (20)

1. Verfahren zur Korrektur der Lage von Festen Fahrbahnen durch Einbrin­ gen von Verfüllmaterial unter, zwischen oder in die Schichten einer Festen Fahrbahn, dadurch gekennzeichnet, daß vor dem Einbringen des Verfüllmaterials die Schichten der Festen Fahrbahn oder auch das Material innerhalb einer solchen Schicht mittels mechanischer Werkzeuge dergestalt aufgetrennt wird, daß definierte im wesentlichen ebene Grenzflächen entstehen, die einen zu verfüllenden Raum begrenzen.1. A method for correcting the position of slab tracks by introducing filler material beneath, between or in the layers of a slab track, characterized in that the layers of the slab track or the material within such a layer by means of mechanical before inserting the filler material Tools are separated in such a way that defined, essentially flat interfaces are created which limit a space to be filled. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß beim Auftrennen ein Materialaustrag, be­ vorzugt in der weicheren Schicht, stattfindet, der auch schon ohne Anhe­ ben der Festen Fahrbahn einen Arbeitsraum für das spätere Verfüllen bietet.2. The method according to claim 1, characterized in that when cutting a material discharge, be preferably in the softer layer, which also takes place without attachments beneath the slab track a work space for later backfilling offers. 3. Verfahren nach mindestens einem der Ansprüche 1 und 2, dadurch gekennzeichnet, daß der freigelegte Arbeitsraum bevorzugt etwa 5 bis 100 Millimeter hoch ist.3. The method according to at least one of claims 1 and 2, characterized in that the exposed work space preferably about Is 5 to 100 millimeters high. 4. Verfahren nach mindestens einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, daß die Schaffung der definierten Grenzflächen bzw. des Arbeitsraumes durch Keile, Messerbalken, Seilsägen, Bandsä­ gen, Stichsägen, Spaltsägen, Fräsen, Räumketten oder/und Schneidstrah­ len erfolgt.4. The method according to at least one of claims 1 to 3, characterized in that the creation of the defined interfaces or the work area with wedges, cutter bars, wire saws, band saws  jigsaws, rip saws, milling, clearing chains and / or cutting beam len takes place. 5. Verfahren nach mindestens einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, daß das Verfahren von einem an der Festen Fahrbahn sich entlangarbeitenden Gerät ausgeführt wird, und dabei die folgenden Arbeitsschritte aufweist:
  • a) Auftrennen von mindestens zwei, die Feste Fahrbahn aufbauenden Schichten, bevorzugt der hydraulisch gebundenen Tragschicht (HGT) und der darunterliegenden Frostschutzschicht,
  • b) Anheben der abgetrennten Fahrbahn von der unteren Schicht,
  • c) Einbringen der für die spätere Sollhöhe notwendigen Menge Aus­ gleichsmaterial zwischen die angehobene Fahrbahn und die untere abge­ trennte Schicht,
  • d) Absenken der Fahrbahn auf die eingebrachte Ausgleichsschicht,
  • e) wenn nötig: Nachbearbeitung des Komposits aus Feste Fahrbahn und Ausgleichsschicht,
    und daß für jeden Streckenabschnitt der Fahrbahn, der am Kopf des Ge­ rätes angehoben wird, ein Streckenabschnitt am Ende des Gerätes gleichzeitig abgesenkt bzw. unterfüllt wird.
5. The method according to at least one of claims 1 to 4, characterized in that the method is carried out by a device working along the slab track, and has the following steps:
  • a) separation of at least two layers that build up the slab track, preferably the hydraulically bound base layer (HGT) and the underlying frost protection layer,
  • b) lifting the separated road from the lower layer,
  • c) placing the amount of balancing material required for the later target height between the raised roadway and the lower separated layer,
  • d) lowering the carriageway onto the leveling layer introduced,
  • e) if necessary: reworking the composite from slab track and leveling layer,
    and that for each section of the roadway that is raised at the head of the device, a section of the track at the end of the device is simultaneously lowered or underfilled.
6. Verfahren nach mindestens einem der Ansprüche 1 bis 4, dadurch gekennzeichnet, daß zwischen die zwei definierten Grenzflächen und diese Grenzflächen im wesentlichen bedeckend mindestens ein auf­ füllbares Kissen, bevorzugt mehrere, die nebeneinanderliegen, einge­ bracht wird und dieses/diese Kissen mit so viel Verfüllmaterial verfüllt wird/werden, wie für die Aufrechterhaltung der Sollhöhe der darauf auflie­ genden Festen Fahrbahn erforderlich ist. 6. The method according to at least one of claims 1 to 4, characterized in that between the two defined interfaces and essentially covering these interfaces at least one fillable pillow, preferably several that are next to each other is brought and this / these pillows filled with so much filling material will / will, as for the maintenance of the target height Fixed carriageway is required.   7. Verfahren nach mindestens einem der Ansprüche 1 bis 6, dadurch gekennzeichnet, daß mindestens zwei übereinanderliegende Schichten aus auffüllbaren Kissen eingebracht werden, wobei die erste Schicht für die erste Nachjustierung, die weiteren Schichten für spätere Nachjustierungen bestimmt sind.7. The method according to at least one of claims 1 to 6, characterized in that at least two superimposed Layers of refillable pillows are introduced, the first Layer for the first readjustment, the other layers for later ones Readjustments are determined. 8. Verfahren nach mindestens einem der Ansprüche 1 bis 4 und 6 und 7, dadurch gekennzeichnet, daß das/die Kissen zwischen zwei Blechen oder innerhalb eines Rahmen liegend von der Seite durch den gesägten Schlitz eingezogen wird/werden und hernach die Bleche bzw. der Rahmen ohne Kissen wieder herausgezogen wird.8. The method according to at least one of claims 1 to 4 and 6 and 7, characterized in that the cushion (s) between two sheets or within a frame from the side through the sawn slot is / are drawn in and afterwards the sheets or the frame without Pillow is pulled out again. 9. Verfahren nach mindestens einem der Ansprüche 1 bis 5, dadurch gekennzeichnet, daß das Anheben der Fahrbahn gemäß Schritt 5b über die spätere Sollhöhe hinaus erfolgt (maximal so weit, wie es die elastische Verformbarkeit der Fahrbahn ohne Schaden zuläßt), wenn ein nicht aushärtendes Ausgleichsmaterial verwendet wird, welches an seiner Oberfläche nach bearbeitet werden soll, und daß das Anheben gemäß 5b nur bis zur Sollhöhe oder geringfügig (maximal etwa 5 Millimeter) darüber erfolgt, wenn im Schritt 5c ein Ausgleichsmaterial bereits verdichtet einge­ bracht wird.9. The method according to at least one of claims 1 to 5, characterized in that the lifting of the carriageway according to step 5 b takes place beyond the later desired height (at most as far as the elastic deformability of the carriageway permits without damage), if not curing compensating material is used, which is to be processed on its surface, and that the lifting according to 5b only up to the desired height or slightly (maximum about 5 millimeters) above if a compensating material is already compacted in step 5 c is introduced. 10. Verfahren nach mindestens einem der Ansprüche 1 bis 9, dadurch gekennzeichnet, daß als Ausgleichsmaterial verdichtbares Schüttgut, z. B. Sand, Kies, Splitt, aufgearbeitetes abgetragenes Material aus der Trennung gemäß Schritt 1a oder auch aushärtbares Material, z. B. Beton, Bitumen, verwendet wird. 10. The method according to at least one of claims 1 to 9, characterized in that compressible bulk material, for. B. sand, gravel, grit, worked away material from the separation according to step 1 a or curable material, eg. B. concrete, bitumen is used. 11. Verfahren nach mindestens einem der Ansprüche 5 und 9, dadurch gekennzeichnet, daß zumindestens die obere aufgetrennte Grenzfläche mit Schmier-/Gleitmittel behandelt wird.11. The method according to at least one of claims 5 and 9, characterized in that at least the upper separated Interface is treated with lubricant / lubricant. 12. Verfahren nach mindestens einem der Ansprüche 5 und 9 bis 11, dadurch gekennzeichnet, daß das Anheben gemäß Schritt 5b durch Glei­ ten oder Rollen über eine schiefe Ebene erfolgt oder über ein auf Rollen oder Gleitflächen gelagertes endloses Band.12. The method according to at least one of claims 5 and 9 to 11, characterized in that the lifting according to step 5 b takes place by sliding or rolling over an inclined plane or via an endless belt mounted on rollers or sliding surfaces. 13. Verfahren nach mindestens einem der Ansprüche 1 bis 5 und 9 bis 12, dadurch gekennzeichnet, daß das Ausgleichsmaterial durch Gurte, Schnecken, Blasen, Spülen, Sprühen oder durch Leitbleche unter die an­ gehobene Fahrbahn eingebracht wird, daß es, wenn dies durch das Ein­ bringen noch nicht der Fall, durch Walzen oder Rütteln verdichtet wird, und daß es, falls schlecht fließfähig, mit einer Abziehbohle oder Hobel ni­ velliert wird.13. The method according to at least one of claims 1 to 5 and 9 to 12, characterized in that the compensating material by straps, Snails, bubbles, rinsing, spraying or through baffles under the upscale roadway is introduced that if this by the one do not bring the case, is compacted by rolling or shaking, and that, if poorly flowable, with a screed or planer ni velliert. 14. Verfahren nach mindestens einem der Ansprüche 1 bis 13, dadurch gekennzeichnet, daß die Oberfläche der Ausgleichsschicht mit Kleber behandelt wird.14. The method according to at least one of claims 1 to 13, characterized in that the surface of the leveling layer with Adhesive is treated. 15. Vorrichtung zur Durchführung des Verfahrens nach Anspruch 1 bis 14, dadurch gekennzeichnet, daß sie mindestens die folgenden Bestandteile aufweist, wobei aber einzelnen Unteranteilen getrennt voneinander ein­ setzbar sein können und nicht miteinander verbunden sein müssen:
  • a) Trennvorrichtung für die Schichten
  • b) Hebevorrichtung für die aufgetrennte Fahrbahn
  • c) Eintragvorrichtung für Ausgleichsmaterial
15. Device for carrying out the method according to claim 1 to 14, characterized in that it has at least the following components, but individual sub-parts can be used separately from one another and need not be connected to one another:
  • a) Separating device for the layers
  • b) lifting device for the split roadway
  • c) Entry device for compensating material
16. Vorrichtung zur Durchführung des Verfahrens nach Anspruch 5 und 9 bis 14, dadurch gekennzeichnet, daß sie mindestens die folgenden Bestandteile aufweist, wobei aber einzelnen Unteranteilen getrennt voneinander ein­ setzbar sein können und nicht miteinander verbunden sein müssen:
  • a) Trennvorrichtung für die Schichten
  • b) kontinuierliche Hebevorrichtung und Absenkvorrichtung für die abge­ trennte Fahrbahn, z. B. schiefe Ebenen
  • c) Eintragvorrichtung für Ausgleichsmaterial
  • d) Verdichtungsvorrichtung für Ausgleichsmaterial
  • e) Fortbewegungsmittel zum kontinuierlichen Bewegen entlang der Fahr­ bahn.
16. Apparatus for carrying out the method according to claim 5 and 9 to 14, characterized in that it has at least the following components, but individual sub-components can be inserted separately from one another and do not have to be connected to one another:
  • a) Separating device for the layers
  • b) continuous lifting and lowering device for the separated road, z. B. inclined planes
  • c) Entry device for compensating material
  • d) Compaction device for compensating material
  • e) means of transportation for continuous movement along the road.
17. Vorrichtung zur Durchführung des Verfahrens nach mindestens einem der Ansprüche 6 bis 8, dadurch gekennzeichnet, daß sie mindestens die folgenden Bestandteile aufweist, wobei aber einzelnen Unteranteilen getrennt voneinander ein­ setzbar sein können und nicht miteinander verbunden sein müssen:
  • a) Seilsäge zum Trennen der Schichten
  • b) Verfüllbares Kissen
  • c) Eintragvorrichtung für Ausgleichsmaterial in das Kissen
17. Device for carrying out the method according to at least one of claims 6 to 8, characterized in that it has at least the following components, but individual sub-parts can be used separately from one another and need not be connected to one another:
  • a) Wire saw to separate the layers
  • b) Fillable pillow
  • c) Entry device for compensating material in the pillow
18. Vorrichtung nach Anspruch 17, dadurch gekennzeichnet, daß das Kissen mindestens einen Einfüllstutzen aufweist. 18. The apparatus according to claim 17, characterized in that the pillow has at least one filler neck having.   19. Vorrichtung nach mindestens einem der Ansprüche 17 und 18, dadurch gekennzeichnet, daß das Kissen mindestens einen Auslaßstut­ zen aufweist, oder aus einem für Wasser durchlässigen Material besteht.19. The device according to at least one of claims 17 and 18, characterized in that the pillow at least one outlet mare zen, or consists of a water-permeable material. 20. Vorrichtung nach mindestens einem der Ansprüche 17 bis 19, dadurch gekennzeichnet, daß sie zusätzlich eine Hebevorrichtung für die Feste Fahrbahn aufweist.20. The device according to at least one of claims 17 to 19, characterized in that it additionally includes a lifting device for the Has a solid carriageway.
DE19834072A 1998-05-12 1998-07-29 Position correction method for permanent ways Withdrawn DE19834072A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
DE19834072A DE19834072A1 (en) 1998-05-12 1998-07-29 Position correction method for permanent ways
DE19848655A DE19848655B4 (en) 1998-05-12 1998-10-22 Renovation of slab tracks

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE19821081 1998-05-12
DE19834072A DE19834072A1 (en) 1998-05-12 1998-07-29 Position correction method for permanent ways

Publications (1)

Publication Number Publication Date
DE19834072A1 true DE19834072A1 (en) 1999-02-25

Family

ID=7867420

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19834072A Withdrawn DE19834072A1 (en) 1998-05-12 1998-07-29 Position correction method for permanent ways

Country Status (1)

Country Link
DE (1) DE19834072A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006102866A1 (en) * 2005-03-26 2006-10-05 Rail.One Gmbh Method for correcting the height of a fixed railway track
RU2334839C1 (en) * 2007-03-27 2008-09-27 Государственное образовательное учреждение высшего профессионального образования Иркутский государственный университет путей сообщения (ИрГУПС) Method of tunnel railway base repair
EP3023545A1 (en) 2014-11-21 2016-05-25 Hartmut Sassowsky Joint renovation machine and method for its operation

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006102866A1 (en) * 2005-03-26 2006-10-05 Rail.One Gmbh Method for correcting the height of a fixed railway track
KR100788992B1 (en) 2005-03-26 2007-12-28 레일 원 게엠베하 Method of adjusting the height of a fixed rail carriageway
US7810741B2 (en) 2005-03-26 2010-10-12 Rail.One Gmbh Method of adjusting the height of a fixed rail carriageway
RU2334839C1 (en) * 2007-03-27 2008-09-27 Государственное образовательное учреждение высшего профессионального образования Иркутский государственный университет путей сообщения (ИрГУПС) Method of tunnel railway base repair
EP3023545A1 (en) 2014-11-21 2016-05-25 Hartmut Sassowsky Joint renovation machine and method for its operation
DE102014017539A1 (en) 2014-11-21 2016-05-25 Hartmut Sassowsky Joint renovation machine and method for its operation and its use
DE102014017539B4 (en) 2014-11-21 2019-01-17 Hartmut Sassowsky Joint renovation machine and method for its operation and its use

Similar Documents

Publication Publication Date Title
EP2920366B1 (en) Rail-mounted transport system for a track construction machine
DE3227725C2 (en)
EP0771909B1 (en) Machine for dismantling old and installing new railway tracks
DE20003403U1 (en) Scraper for a platform edge foundation
DE19848655B4 (en) Renovation of slab tracks
DE102009007226B4 (en) Method for creating a drainage device next to the track of a railway line
DE3106063A1 (en) TRACK CONSTRUCTION MACHINE WITH A GRAVEL BED ROOM AND PLANNER DEVICE
DE10133246A1 (en) Conversion of ballasted trackbed to solid roadbed starts by removing rails and ballast used for concrete aggregate once crushed to size for concrete plate laid on bearing layer to complete solid roadbed.
EP1169516B1 (en) Method for renewing railway lines
DE10358363B4 (en) Slipform paver for the production of surface coverings
EP0585657A1 (en) Device for replacing soil, especially next to roads and buildings
DE19834072A1 (en) Position correction method for permanent ways
DE102012009284B4 (en) Process for the rehabilitation of a solid road / solidified gravel railway
DD154226A5 (en) METHOD AND DEVICE FOR UNDERGROUND ARMING OF RAILWAY RAILS
EP2166152A1 (en) Method and device for improving or repairing track systems
DE102007038461B4 (en) Method for rehabilitating a rail track and associated rail track
CH598429A5 (en) Frame for applying concrete liner to excavated canal
WO2005038140A1 (en) Slip form paver for producing surfacings
DE4308072A1 (en) Method and device for working up a track substructure
DE19818338C1 (en) Platform construction for providing access to and from trains, trams etc.
EP0751259B1 (en) Method and device for making recesses in asphalt layers
DE102005019139B4 (en) Screed with upstream compaction unit
DE102015102268B4 (en) Method for creating predetermined breaking points in concrete layers of roads and paths, arrangement for introducing release agents into a concrete layer
EP1191145A1 (en) Process and apparatus for connection of a track comprising rails and discrete bearing blocks with a fixed substructure of the track
DE102021127502A1 (en) Track for track-guided rail vehicles and method for its construction

Legal Events

Date Code Title Description
OAV Applicant agreed to the publication of the unexamined application as to paragraph 31 lit. 2 z1
8143 Lapsed due to claiming internal priority