DE1301852B - Fusible wire in ribbon form for sluggish fusible links - Google Patents

Fusible wire in ribbon form for sluggish fusible links

Info

Publication number
DE1301852B
DE1301852B DE1965S0097152 DES0097152A DE1301852B DE 1301852 B DE1301852 B DE 1301852B DE 1965S0097152 DE1965S0097152 DE 1965S0097152 DE S0097152 A DES0097152 A DE S0097152A DE 1301852 B DE1301852 B DE 1301852B
Authority
DE
Germany
Prior art keywords
fusible
oxide layer
fusible conductor
ribbon
active substance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE1965S0097152
Other languages
German (de)
Inventor
Bobrowski Hans
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens Corp
Original Assignee
Siemens Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens Corp filed Critical Siemens Corp
Priority to DE1965S0097152 priority Critical patent/DE1301852B/en
Publication of DE1301852B publication Critical patent/DE1301852B/en
Withdrawn legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01HELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES
    • H01H69/00Apparatus or processes for the manufacture of emergency protective devices
    • H01H69/02Manufacture of fuses

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Fuses (AREA)

Description

In der Patentanmeldung P 12 97 206.4-32 ist ein Verfahren zum Herstellen von Schmelzleitern in Bandform für träge Schmelzeinsätze, bei denen das Schmelzleiterband an einer Stelle mit einem mechanisch befestigten Werkstoffkörper versehen ist, angegeben, das die Möglichkeit gibt, die Mechanisierung der Fertigung des Schmelzleiters besonders rationell durchzuführen. Dieses Verfahren besteht darin, daß aus einem Schmelzleiterband ein Durchzug hergestellt wird, danach quer zum Schmelzleiterband ein aus dem Wirkstoff bestehendes Flachband zugeführt wird, darauf das Schmelzleiterband lind das Wirkstoff-Flachband miteinander derart verpreßt werden, daß der Durchzug in das Wirkstoff-Flachband eindringt, und schließlich das an dem Schmelzleiterband befestigte Ende des Wirkstoff-Flachbandes von dem übrigen Wirkstoff-Flachband abgetrennt wird. Dieses Verfahren hat den Vorzug, daß die Herstellung des trägen Schmelzleiters vollständig in der gleichen Stanzmaschine durchgeführt werden kann, die sowieso erforderlich ist, um die an sich bekannten Löcher im Schmelzleiterband, die den Abschmelzvorgang festlegen, herzustellen und das Schmelzleiterband von dem in Rollenform herangeführten Halbfabrikat abzutrennen.In the patent application P 12 97 206.4-32 is a method for producing of fusible conductors in tape form for slow fuse inserts where the fusible tape is provided with a mechanically fastened material body at one point, that gives the possibility, the mechanization of the manufacture of the fuse element in particular to be carried out efficiently. This method consists in that from a fusible conductor strip a passage is made, then transversely to the fusible link from the active ingredient existing ribbon is fed, then the fusible tape and the active ingredient ribbon are pressed together in such a way that the passage into the active ingredient flat band penetrates, and finally the end of the active substance ribbon attached to the fusible conductor band is separated from the rest of the active ingredient ribbon. This procedure has the advantage that the production of the inert fusible conductor completely in the same punching machine can be carried out, which is required anyway to the known per se Holes in the fusible link, which determine the melting process, to produce and to separate the fusible tape from the semi-finished product brought in in roll form.

Um auszuschließen, daß gegebenenfalls auftretende Oxydschichten an dem Schmelzleiter den Angriff des Wirkstoffes auf den Schmelzleiter beim Ansprechen des Schmelzeinsatzes beeinträchtigen, ist erfindunggemäß an dem nach der Patentanmeldung P 12 97 206.4-32 hergestellten Schmelzleiter zwischen dem Wirkstoff-Flachband und dem Schmelzleiterband ein bereits vor dem Verpressen aufgebrachtes Mittel vorgesehen, das das Entstehen einer Oxydschicht an dem Schmelzleiterband verhindert oder eine entstandene Oxydschicht zerstört. Das Mittel kann von einem Flußmittel (z. B. Spiritus-Kolophonium-Lösung) gebildet sein, die das Entstehen der Oxydschicht verhindert oder eine entstandene Oxydschicht zerstört. Als Mittel kann auch eine auf das Schmelzleiterband aufgetragene Zinnschicht dienen, die das Entstehen einer Oxydschicht verhindert. Durch die Erfindung ist eine .stets sich gleichbleibende Abschmelzcharakteristik der nach der Patentanmeldung P 12 97 206.4-32 hergestellten Schmelzeinsätze gewährleistet, auf die auch eine lange Lagerhaltung vor dem Gebrauch der Schmelzeinsätze keinen Einfluß hat.In order to rule out any oxide layers that may occur the fusible link the attack of the active substance on the fusible link when responding the fusible link is affected according to the invention on the one after the patent application P 12 97 206.4-32 manufactured fusible link between the active ingredient ribbon and the fusible strip is provided with an agent that has already been applied before pressing, that prevents the formation of an oxide layer on the fusible link or a The resulting oxide layer is destroyed. The agent can be from a flux (e.g. alcohol-rosin solution) be formed that prevents the formation of the oxide layer or one that has arisen Oxide layer destroyed. An agent applied to the fusible conductor tape can also be used as a means Tin layer, which prevents the formation of an oxide layer. Through the invention is a constant melting characteristic according to the patent application P 12 97 206.4-32 produced fusible links guaranteed to the one Long storage before using the fusible link has no effect.

Bei Schmelzleitern für träge Schmelzeinsätze ist es an sich bekannt, zur Förderung der Legierungsbildung zwischen dem aus Kupfer bzw. Silber bestehenden Schmelzleiter und einem aus Zinn bestehenden Wirkstoffkörper ein Löt- oder Flußmittel z. B. Kolophonium zu verwenden. Man hat es bei den bekannten Schmelzleitern im Inneren des Wirkstoffkörpers untergebracht. Hat der Schmelzleiter bei einer überlastung der Sicherung eine Temperatur erreicht, bei der der Wirkstoffkörper in den Schmelzzustand übergeführt wird, so hat das eingeschlossene Löt- oder i Flußmittel infolge der erhöhten Temperatur eine Druckerhöhung erfahren, wodurch der nach und nach erweichende und den Fließpunkt erreichende Wirkstoffkörper gesprengt und mindestens ein Teil davon mit einem Teil des Löt- oder Flußmittels gegen den Schmelzleiter geschleudert wird. Am Schmelzleiter findet nunmehr die Legierungsbildung unmittelbar statt. In der Zeichnung ist ein Ausführungsbeispiel der Erfindung dargestellt.In the case of fusible conductors for slow fuse inserts, it is known per se to promote the formation of an alloy between the one made of copper or silver Fusible conductor and an active substance body made of tin, a solder or flux z. B. to use rosin. You have it with the well-known fusible conductors inside housed the active ingredient body. Has the fusible link in the event of an overload the fuse reaches a temperature at which the active substance body in the melting state is transferred, so has the enclosed solder or flux as a result of the increased temperature experience an increase in pressure, whereby the gradually softening and the active substance body reaching the pour point burst and at least a part with part of the soldering or flux being thrown against the fusible link will. Alloy formation now takes place directly on the fusible link. In the drawing shows an embodiment of the invention.

F i g.1 und 2 geben einen Vorgang bei der Fertigung des Schmelzleiters wieder; F i g. 3 und 4 zeigen den Schmelzleiter im fertiggestellten Zustand.F i g.1 and 2 show a process in the manufacture of the fusible conductor again; F i g. 3 and 4 show the fusible conductor in the completed state.

Der erfindungsgemäße Schmelzleiter, der eine Bandform hat, ist für träge Schmelzeinsätze bestimmt. Die trägen Schmelzeinsätze nehmen das Schmelzleiterband in einer Höhlung eines Patronenkörpers auf, die mit Sand gefüllt und mit Kontaktkappen abgeschlossen ist. Das nach dem Verfahren gemäß der Patentanmeldung P 12 97 206.4-32 hergestellte Schmelzleiterband ist in den F i g. 3 und 4 dargestellt. Das Schmelzleiterband 1 hat außer den Löchern 2, die zur Festlegung des Abschmelzvorganges dienen, noch einen metallischen Wirkstoffkörper 3, z. B. aus Zinn. Dieser Wirkstoffkörper ist mit dem Schmelzleiterband 1 mechanisch verbunden.The fusible conductor according to the invention, which has a ribbon shape, is for sluggish fuse links determined. The sluggish fuse links take the fuse strip in a cavity of a cartridge body, which is filled with sand and with contact caps is completed. The according to the method according to the patent application P 12 97 206.4-32 The fusible conductor strip produced is shown in FIGS. 3 and 4 shown. The fusible link In addition to the holes 2, which are used to define the melting process, 1 still has a metallic active ingredient body 3, e.g. B. made of tin. This drug body is mechanically connected to the fusible link 1.

Die Herstellung des Schmelzleiterbandes wurde wie folgt durchgeführt: In der gleichen Stanzmaschine, in der die Löcher 2 ausgestanzt werden, wird aus dem Schmelzleiterband ein Durchzug 4 hergestellt, und zwar an der Stelle, an der der Wirkstoffkörper angebracht werden soll. Quer zur Längsachse des Schmelzleiterbandes wird der Wirkstoff in Form eines Flachbandes 3 zugeführt und unter den Durchzug 4 des Schmeizleiterbandes gelegt. Danach werden Schmelzleiterband 1 und Wirkstoff-Flachband 3 miteinander derart verquetscht, daß der Durchzug mit seinem Kragen in den Wirkstoff des Flachbandes eindringt. Dabei füllt sich die Öffnung des Durchzuges durch das eindringende Wirkstoffmaterial völlig aus. Schließlich wird das an dem Schmelzleiterband befestigte Ende des Wirkstoff-Flachbandes von dem übrigen Wirkstoff-Flachband abgetrennt. Der an dem Schmelzleiterband verbleibende Wirkstoffkörper 3 befindet sich in einer völlig ausreichenden mechanischen Verbindung mit dem Schmelzleiterband.The production of the fusible link was carried out as follows: In the same punching machine in which the holes 2 are punched out, the fusible conductor band made a passage 4, at the point where the active ingredient body is to be attached. Transversely to the longitudinal axis of the fusible strip the active ingredient is supplied in the form of a flat belt 3 and under the passage 4 of the Schmeizleiterbandes placed. This is followed by the fusible conductor strip 1 and the active ingredient flat strip 3 squeezed together in such a way that the draft with its collar into the active ingredient of the ribbon penetrates. The opening of the draft fills through the penetrating active ingredient material completely. Eventually this will be done on the fusible link attached end of the active ingredient flat band separated from the rest of the active ingredient flat band. The active substance body 3 remaining on the fusible conductor strip is located in a completely sufficient mechanical connection with the fusible link.

Nach der Erfindung ist an dem Schmelzleiter 1 zwischen dem Wirkstoff-Flachband 3 und dem Schmelzleiterband 1 ein bereits vor dem Verpressen aufgebrachtes Mittel 5 vorgesehen, das das Entstehen einer Oxydschicht an dem Schmelzleiterband verhindert oder eine entstandene Oxydschicht zerstört. Auf diese Weise kann der Wirkstoff beim Ansprechen des Schmelzeinsatzes an dem Schmelzleiterband voll zur Wirkung gelangen. Das Mittel 5 kann von einem Flußmittel, z. B. einer Spiritus-Kolophonium-Lösung, gebildet sein, die das Entstehen einer Oxydschicht verhindert oder eine bereits vorhandene Oxydschicht zerstört. Das Flußmittel ist vor dem Verpressen entweder auf dem Wirkstoff-Flachband oder auf dem Schmelzleiterband aufgetragen. Es bleibt nach dem Verpressen als Zwischenschicht zwischen dem Wirkstoff-Flachband und dem Schmelzleiterband bestehen. Auch nach wiederholtem Aufheizen des Schmelzleiters sowie auch über lange Lagerzeiten des Schmelzeinsatzes ist das Flußmittel voll wirksam. In jedem Fall führt es zu einem wirksamen Angriff des Wirkstoffes auf den Schmelzleiter. Das Mittel 5 kann aber auch von einer auf das Schmelzleiterband aufgetragenen Zinnschicht gebildet sein, die das Entstehen einer Oxydschicht verhindert. Die Zinnschicht kann nur an der Verbindungsstelle zwischen Wirkstoffkörper und Schmelzleiter oder an der ganzen Oberfläche des Schmelzleiters angebracht sein. Auch die Zinnschicht läßt den Wirkstoff beim Ansprechen des Schmelzeinsatzes wirksam den Schmelzleiter angreifen. Durch die Zinnschicht erübrigt sich das Aufbringen eines Flußmittels an dem Schmelzleiter. Besonders zweckmäßig ist es, daß das an dem Schmelzleiterband 1 befestigte Ende des Wirkstoff-Flachbandes 3 die Breite des Schmelzleiters einnimmt. Auf diese Weise ist die Möglichkeit eines breitflächigen Angriffes des Wirkstoffes auf den Schmelzleiter gegeben.According to the invention, a means 5 is provided on the fusible conductor 1 between the active substance ribbon 3 and the fusible conductor strip 1, which means 5 is applied before pressing and prevents the formation of an oxide layer on the fusible conductor strip or destroys an oxide layer that has formed. In this way, the active substance can take full effect when the fuse link on the fusible conductor strip responds. The means 5 can be of a flux, e.g. B. a spirit-rosin solution, which prevents the formation of an oxide layer or destroys an existing oxide layer. Before pressing, the flux is applied either to the active ingredient flat strip or to the fusible conductor strip. After pressing, it remains as an intermediate layer between the active ingredient flat strip and the fusible conductor strip. The flux is fully effective even after repeated heating of the fusible conductor and even after long periods of storage of the fusible link. In any case, it leads to an effective attack of the active substance on the fuse element. The means 5 can, however, also be formed by a tin layer applied to the fusible conductor strip, which prevents the formation of an oxide layer. The tin layer can only be applied at the connection point between the active substance body and the fusible conductor or on the entire surface of the fusible conductor. The tin layer also allows the active substance to attack the fuse element effectively when the fuse link responds. The tin layer eliminates the need to apply a flux to the fusible conductor. It is particularly expedient that the end of the active substance ribbon 3 attached to the fusible conductor strip 1 takes up the width of the fusible conductor. In this way, there is the possibility of the active substance attacking the fusible conductor over a wide area.

Claims (4)

Patentansprüche: 1. Schmelzleiter in Bandform für träge Schmelzeinsätze, der nach dem Verfahren gemäß Patentanmeldung P 12 97 206.4-32 hergestellt ist, bei dem ein Schmelzleiterband mit einem aus einem Wirkstoff bestehenden Flachband unter Verwendung eines am Schmelzleiterband sitzenden in das Wirkstoff-Flachband eindringenden Durchzuges miteinander verpreßt wird, wobei nach dem Verpressen das an dem Schmelzleiterband befestigte Ende des Wirkstoffbandes von dem übrigen Wirkstoffband abgetrennt wird, d a -durch gekennzeichnet, daß zwischen dem Wirkstoff-Flachband (3) und dem Schmelzleiterband (1) ein bereits vor dem Verpressen aufgebrachtes Mittel (5) vorgesehen ist, das das Entstehen einer Oxydschicht an dem Schmelzleiterband verhindert oder eine entstandene Oxydschicht zerstört. Claims: 1. Fusible link in ribbon form for slow fuse inserts, which is produced by the method according to patent application P 12 97 206.4-32, at which is a fusible link with a ribbon consisting of an active ingredient Use of one that is located on the fusible conductor strip and penetrates into the active substance ribbon Passage is pressed together, after which the pressing on the fusible strip the attached end of the active substance tape is separated from the rest of the active substance tape, d a - characterized in that between the active ingredient ribbon (3) and the fusible link (1) a means (5) applied before pressing is provided, which or prevents the formation of an oxide layer on the fusible conductor strip Oxide layer destroyed. 2. Schmelzleiter nach Anspruch 1, dadurch gekennzeichnet, daß das Mittel (5) von einem Flußmittel (z. B. Spiritus-Kolophonium-Lösung) gebildet ist, das das Entstehen einer Oxydschicht verhindert oder eine entstandene Oxydschicht zerstört. 2. Fusible conductor according to claim 1, characterized in that that the agent (5) is formed by a flux (e.g. alcohol-rosin solution) that prevents the formation of an oxide layer or an oxide layer that has formed destroyed. 3. Schmelzleiter nach Anspruch 1, dadurch gekennzeichnet, daß das Mittel (5) von einer auf das Schmelzleiterband (1) aufgebrachten Zinnschicht gebildet ist, die das Entstehen einer Oxydschicht verhindert. 3. Fusible conductor according to claim 1, characterized in that the means (5) is formed by a tin layer applied to the fusible conductor strip (1), which prevents the formation of an oxide layer. 4. Schmelzleiter nach Anspruch 1, 2 oder 3, dadurch gekennzeichnet, daß das an dem Schmelzleiterband (1) befestigte Ende des Wirkstoff-Flachbandes (3) die Breite des Schmelzleiterbandes hat.4. fusible link according to claim 1, 2 or 3, characterized in that the attached to the fusible tape (1) The end of the active substance flat band (3) has the width of the fusible conductor band.
DE1965S0097152 1965-05-18 1965-05-18 Fusible wire in ribbon form for sluggish fusible links Withdrawn DE1301852B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE1965S0097152 DE1301852B (en) 1965-05-18 1965-05-18 Fusible wire in ribbon form for sluggish fusible links

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE1965S0097152 DE1301852B (en) 1965-05-18 1965-05-18 Fusible wire in ribbon form for sluggish fusible links

Publications (1)

Publication Number Publication Date
DE1301852B true DE1301852B (en) 1969-08-28

Family

ID=7520537

Family Applications (1)

Application Number Title Priority Date Filing Date
DE1965S0097152 Withdrawn DE1301852B (en) 1965-05-18 1965-05-18 Fusible wire in ribbon form for sluggish fusible links

Country Status (1)

Country Link
DE (1) DE1301852B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3909302A1 (en) * 1988-03-23 1989-10-12 Yazaki Corp FUSE PROTECTION AND METHOD FOR PRODUCING THE SAME

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE901921C (en) * 1950-03-01 1954-01-18 Licentia Gmbh Overcurrent carrier fuse

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE901921C (en) * 1950-03-01 1954-01-18 Licentia Gmbh Overcurrent carrier fuse

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3909302A1 (en) * 1988-03-23 1989-10-12 Yazaki Corp FUSE PROTECTION AND METHOD FOR PRODUCING THE SAME
DE3909302C2 (en) * 1988-03-23 1993-07-22 Yazaki Corp., Tokio/Tokyo, Jp

Similar Documents

Publication Publication Date Title
DE2228703A1 (en) PROCESS FOR MANUFACTURING A SPECIFIED SOLDER THICKNESS IN THE MANUFACTURING OF SEMI-CONDUCTOR COMPONENTS
DE1015152B (en) Method and device for manufacturing semiconductor devices
DE2920028A1 (en) ELECTRICAL CONTACT FOR A SWITCH AND PROCEDURE FOR MAKING SUCH CONTACT
DE2326614A1 (en) METHOD FOR HERMETICALLY SEALING A CONTAINER, IN PARTICULAR THE HOUSING OF A SEMICONDUCTOR, BY APPLYING A COVER PLATE AND METHOD FOR MANUFACTURING SUCH A COVER PLATE
DE2844888A1 (en) PRE-MATERIAL FOR ELECTRICAL CONTACTS
DE1627762A1 (en) Method for manufacturing semiconductor components
DE1902320A1 (en) Method and device for anchoring and connecting feeder wires to electrical components
DE19620087B4 (en) Method for producing a building block-like, secured capacitor with solid electrolyte
DE3012950C2 (en)
DE1301852B (en) Fusible wire in ribbon form for sluggish fusible links
DE3239051C2 (en) Fencing blade
DE3508806A1 (en) METHOD FOR PRODUCING ELECTRICAL CONTACTS
DE1233477B (en) Traeger fuse link with twisted fuse conductors
DE1788020C3 (en) Round wire fusible link for fusible links
EP0570662B1 (en) Billet for the production of electrical contacts, as well as fabrication and use of the billet
DE1297206B (en) Process for the production of fusible conductors in the form of strips for sluggish fusible links
CH656953A5 (en) DEVICE FOR THE IGNITION OF BLASTING BODIES.
DE2248570A1 (en) ELECTRIC FUSE
Habs Über chemische und biologische Veränderungen der Muskulatur nach öfters wiederholter faradischer Reizung. 2. Mitteilung.
DE959568C (en) Overcurrent carrier fuse link
DE948265C (en) Fusible link with coating mass for electrical fuses
DE742908C (en) Process for the production of anchoring pins for artificial teeth, consisting of a core made of base metal and one or more coatings made of noble metal or noble metal alloy
DE1915213A1 (en) Process for the production of an armature commutator unit with an armature winding of very small diameter
DE2121303B2 (en) Electric fuse filled with sand
DE495558C (en) Process for the production of electrical capacitors, the assignments of which are soldered to the ends protruding from the end faces with plates made of tin or other solder metal

Legal Events

Date Code Title Description
E77 Valid patent as to the heymanns-index 1977
EHJ Ceased/non-payment of the annual fee